An Introduction to IMP/IMS
|
|
|
- Ashley Robertson
- 9 years ago
- Views:
Transcription
1 An Introduction to IMP/IMS In 2003 the US Government revised its acquisition policies with a procurement strategy focused on process improvement and acquisition reform implemented by performance-based management. Glen B Alleman Niwot, Colorado1 Planning projects usually starts with tasks and milestones. The planner gathers this information from the participants customers, engineers, subject matter experts. This information is usually arranged in the form of activities and milestones. PMBOK defines project time management in this manner. The activities are then sequenced according to the projects needs and mandatory dependencies. The usual critical path methods are then used to determine the estimated completion date, risk areas of the project and other statistical planning data. What s missing from the concept of this task-oriented schedule is the realization that the plan is not the same as done. A description of done is usually not part of the plan in an explicit manner. Rather is usually found inside of a specification. It s there in implicit form after all the tasks are complete. In the US Department of Defense version of PMBOK Section 6 (Project Time Management) this task-oriented approach is replaced by IMP/IMS. Why was this done? The DoD version as well as the US Air Force IMP/IMS guides don t explicitly state the reason for replacing the traditional planning approach with IMP/IMS. 1
2 Program Management is a Full Contact Sport IMP/IMS 2 /54 2 We ve all had experiences in much the same as the carton charters shown here. Things are going along well, even the numbers all look good. Then the surprise happens. Sometimes out of the blue, sometimes with a clear vision of the train wreck happening before our eyes. Why does the happen? If there was a simple answer to this question all the efforts of program management, tools and processes would not be needed. The answer is we don t really know why projects fail in any detail that would allow us to avoid failure with certainty. There are many authors, professional organizations, and government agencies who profess to have a solution. But in the end its simply not possible to state assuredly how to avoid failure. Opportunities for improvement certainly exist. Obvious failure modes can be identified and avoided. Postmortems can easily identify the gaps that occurred with or without the knowledge of the project managers, customers, and engineers. 2
3 Booz Allen Hamilton s 16 Program Management Processes Program Management Framework Program Process Capabilities 1: Program Management Involvement in Proposal 2: Program Planning 3: Performance Management 4: Sub-Contract Management 5: Follow-On Business Development 7: Requirements Management 9: Financial Management 6: Earned Value Management 8: Schedule Management 10: Risk Management Program Enablers 11: Organization/IPD 12: Customer Partnership 13: Program Review Process 14: Configuration/ Data Management Business Enablers 15: PM Process Management 16: PM Development and Succession IMP/IMS 3 /54 3 Booz Allen Hamilton defined 16 processes for program management. These all appear obvious on the surface as any good idea does. The challenge is to put these practices into practice on real programs with real people and real customers. The Program Process Capabilities (1 10) are the core of the IMP/IMS outcomes. Planning, performance management, subcontract relations, cost, and earned value are critical operational activities for the success of any program. For these processes to be effective, there has to be a clearly defined statement of work, a cooperative customer, a skilled and qualified team, proper funding, and most importantly a feasible solution to the customer s needs. But even with all these pre-conditions, projects get in trouble. What s missing? The IMP/IMS approach would say what s missing is a way to assess the incremental progress of the program in a way that can be measured in unambiguous terms. By defining done in terms of events, accomplishments, and criteria, progress of the program can be measured. 3
4 Why IMP/IMS? Proposal Preparation Emphasize real integrated product development Provide flexibility in performing detailed planning Contract Award At post-award conference, provides a basis of mutual understanding Program Execution Identify and assess program progress based on done rather then passage of time or effort expended Assess program maturity through pre-defined accomplishments IMP/IMS 4 /54 4 There are no simple answers for the question why use IMP/IMS? As well there doesn t seem to be much in the way of documentation for the deployment of IMP/IMS. The fact is though that the world is littered with failed projects. Even after decades of professional development, bodies of knowledge, endless seminars and training processes and even Presidential commissions. There are an equal number of successful projects. The parameters of project success or project failure are elusive. But one thing is clear, without a concise definition of done, no process will help. 4
5 What is the Integrated Master Plan? The IMP is an event based plan, rather than a task based plan A hierarchy of program events defines the program flow Each event is supported by specific accomplishments Each accomplishment has specific criteria to be satisfied The IMP tracks the step-by-step completion of the required accomplishments for each event The IMP demonstrates the satisfactory completion criteria for each accomplishment IMP/IMS 5 /54 5 The Integrated Master Plan is a collection of milestones (IMP/IMS calls them events) that form the process architecture of the program. This means the sequence of events that will result in a deliverable product or service. Delivering products or services is relatively straight forward in many cases. List the tasks to be done, arrange them in the proper sequence, execute this plan. Several problems appear immediately: The description of done is many times missing for the intermediate activities. As products or services are delivered the maturity of the program is as critical as quality, functionality, and other program attributes. This maturity is an insurance policy against problems encountered in the program. Program partners, integration activities, subcontractors all have unknown or possibly unknowable impacts on the program Exposing done to and from the IPTs builds a shared version of done 5
6 What is the Integrated Master Plan? The IMP is NOT based on calendar dates, therefore it is not schedule oriented Each event is completed when its supporting accomplishments are completed This completion is evidenced by the satisfaction of the criteria supporting each of the accomplishments Many of the events in an IMP are fixed by customer milestones PDR, CDR, Production delivery Intermediate events are defined by the supplier Integration and test, Software releases, TRR IMP/IMS 6 /54 6 The critical attribute of the IMP is its focus on events. This is in comparison to effort or task focused planning. The event focus asks and answers the question what does done look like? Rather than what work has been done. Certainly work must be done to complete a task. But focusing on the work hides the more important metric of are we meeting our commitments? Meeting commitments is critical but the criteria for judging if the commitments are being met comes first. This is where Significant Accomplishments and their Accomplishment Criteria become important. It is important to meet commitments, but recognizing when the commitment has been met is even more important. 6
7 What is the Integrated Master Schedule? The IMS flows directly from the IMP, and is linked to: Work Breakdown Structure Statement of Work Earned Value Management System The IMS is used to manage the day-to-day execution of the program Tracking program technical and schedule status Managing and mitigating program risk Incrementally assessing the maturity of the program IMP/IMS 7 /54 7 The term Integrated Master Schedule sounds obvious on the surface. A project schedule that is integrated. But what does integrated really mean? Integrated at what level? Integrated with what components? The IMS integrates the Events with Tasks. The work efforts that produce accomplishments, assess these accomplishments through criteria and complete the Events are the basis of the IMP/IMS 7
8 The Importance of the IMP/IMS The IMP/IMS is the single most important document to a program s success It clearly demonstrates the providers understanding of the program requirements and the soundness of the approach a represented by the plan The program uses the IMP/IMS to provide: Up Front Planning and commitment from all participants A balanced design discipline with risk mitigation activities Integrated requirements including production and support Management with an incremental verification for informed program decisions IMP/IMS 8 /54 8 This may sound like hype, but without a clear and concise description of what is to be delivered, tied to the plan, with measurement criteria the program has no way of knowing how it is performing other than the passage of time The emphasis on maturity is seen in product development programs. In one off programs there is no cyclic process on which to base maturity of the product. But in these one off programs, progress of the program toward the goal can be seen a maturing. 8
9 Misconceptions of IMP/IMS Too big and burdensome for our small dollar program We ll spend gobs of B&P money maintaining a thick document It s a management tool not a technical tool I want IPTs without the burden of IPD or IMP/IMS IMP/IMS 9 /54 9 The first impulse to IMP/IMS is this is great on large weapons systems procurements. SBIRS for example. But for our small to moderate program it s a lot of work for not much benefit. The second misconception is IMP/IMS is part of the proposal and procurement process, used to assess contractors on their ability to manage the program. This is true. BUT if this assessment shows competence in the proposal phase, why not continue the processes during the execution phase. Test as you Fly, should be augmented with Execute as you Propose. 9
10 Product vs Functional Focus Product-Oriented Engineering Test Mfg Suppliers Contracting Legal Financial Mgt Logistics Design Space Segment SE Satellite Payload Ground Segment Satellite Cntl Data Fusion I&T Segment PM SE I&T Functional-Oriented Engineering Test Mfg Suppliers Contracting Legal Financial Mgt Logistics Design Space Segment SE Satellite Payload Ground Segment Satellite Cntl Data Fusion I&T Segment PM SE I&T IMP/IMS 10 /54 10 There is much discussion in the project management literature about the differences between product processes and project processes. This is probably a discussion between purist, having little to do with actual project management. In the case of IMP/IMS the project processes are defined around the product delivery processes. Without a product or service to delivery, there is little interest in in the project processes they are simply theoretical discussions The more important concept is the differences between product processes and functional processes. A critical aspect of IMP/IMS is to define activities around products and their delivery rather than around functions. 10
11 Attributes of the IMP Traceability Expands and complies with the SOO, Performance Requirements, CWBS and CSOW Based on the customers WBS Is the basis of the IMS, cost reports, and award fees Implements a measurable and trackable program Accomplishes integrated product development Integrates the functional activities of the program Incorporates functional, lower level and S/C IMPs Provides for evaluation of Program Maturity Provides insight into the overall effort Level of detail is consistent with risk and complexity per L Decomposes events into a logical series of accomplishments Measurable criteria demonstrate completion / quality of accomplishments IMP/IMS 11 /54 11 A good IMP has the following attributes. But most importantly a good IMP describes the logical flow of the program. Although this again seems obvious the construction of this program flow requires input from all participants to assure they understand their deliverables, the sequence of those deliverables. 11
12 Attributes of an IMS Integrated, networked, multi-layered schedule of efforts required to achieve each IMP accomplishment Detailed tasks and work to be completed Calendar schedule shows work completion dates Network schedule shows interrelationships and critical path Expanded granularity, frequency, and depth of risk areas Resource loading for critical risk areas Correlates IMS work with IMP events IMP/IMS 12 /54 12 Once the IMP is in place and started to be structured, the SA/AC/Task structure can begin. This is an iterative process and continues on a rolling wave cycle at the detailed level. There are there (3) levels of IMS in most major programs: Master Intermediate Detailed The master level mirrors the IMP The intermediate level is usually found in the proposal and contains all the end-toend activities, but at the macro level. The detailed IMS is usually a rolling wave planned at the week level. For typical NASA contracts major efforts have 20 day cycles for measuring progress, so this detailed IMS 12
13 Integrated Program Management Framework Technical Requirements User requirements decomposed from RFP PLACED ON CONTRACT Guidance usually in RFP WBS Tailored to contractor s program / products Provides single numbering system for entire program Contractor generated. Based on SOW Statement of Work (SOW) Guidance provided in RFP Event-driven plan for entire program Product and Process Sections Process Metrics IMS Expands IMP, Provides timing USED TO Process quality measures TRACK Technical Performance Measures PERFORMANCE USED TO REPORT PERFORMANCE Integrated Master Plan (IMP) Earned Value Management System (EVMS) CPARS Links cost to IMS thru WBS Determined by performance IMP/IMS 13 /54 13 The complete end to end process is described here. Requirements come from the customer through the Statement of Work and the Work Breakdown Structure. The Integrated Master Plan is built from these documents and of course a face to face conversation with the customer, usually in the project kick off meeting. The IMP represents the logical flow of project events, transition points or deliverables as defined in the SOW. From the IMP the IMS is developed along with the program performance metrics for each of the IMP components. These metrics include earned value, resource utilization, milestone performance (late starts late finishes) 13
14 Objectives Of All This Formality Objective Event Driven Plan versus Schedule Driven Plan is based on completion of tasks not passage of time Condensed, easy to read plan showing events rather than effort Pre-defined entry and exit conditions for major program events Objective measure of progress/ completion for each accomplishment Stable, contractual plan flexible enough to portray program status Capture essence of functional processes without mandating a particular process Implementation Separate the plan (IMP) from the schedule (IMS) but link elements with numbering system Indentured, outline format (not text) Significant accomplishments (SA) for each key event (submitted in proposal) Pre defined accomplishment criteria (AC) for each SA IMP is part of contract, IMS is data item Split IMP into Product and Process sections IMP/IMS 14 /54 14 All this seems like a lot for effort for simply keeping track of the planned work of a project. And as a stand alone process it probably is a lot of effort. But there is a critical aspect to IMP/IMS (as well as more traditional task scheduling). That critical aspect is the making of the schedule. In IMP/IMS the making of the IMP/IMS is a process were the events, significant accomplishments, accomplishment criteria and the supporting tasks are developed from the contract source documents. This discovery process is critical the success of the program in the following ways: The accomplishments and criteria for these accomplishments is defined up front. This what does done look like process reveals the true activities in place of just working. The sequence of events defines the maturity of the program over time. As specific events are accomplished, the program matures toward its completion. The test of maturity is defined by events, accomplishment, and criteria rather than the passage of time. Impacts from changes in the programs plan, requirements or resource can be immediately seen in how the events are impacted. 14
15 Definitions Used in IMP/IMS Event A major transition point in the program Significant Accomplishment Interim, critical or discrete activity required to complete prior to an event Accomplishment Criteria Measurable indicators of evidence that demonstrates the achievement of maturity or progress in an activity Tasks E/A/C A combination of events, accomplishments, and criteria Integrated Master Plan A contractual commitment that lays out the entire program in a single plan Integrated Master Schedule Provides an integrated and networked time phased schedule of all program and product tasks Work performed in support of accomplishments and their criteria IMP/IMS 15 /54 15 Here are the formal definitions used in IMP/IMS. These should be used as they are defined, rather than trying to adapt previous definitions to the IMP/IMS process. 15
16 IMP/IMS Action Verb Dictionary Available Obtained Installed Written Complete(d) Ordered Integrated Acquired Conducted Met Loaded Analyzed Defined Prepared Operational Approved Delivered Provided Reduced Awarded Documented Published Released Corrected Delivered Received Tested Drafted Demonstrated Refined Updated Established Established Reviewed Validated Generated Finalized Submitted Verified Identified Implemented Trained In-Place Initiated IMP/IMS 16 /54 16 IMP/IMS is an action oriented process. Verbs are used to describe activities. Past and present tense is used in specific ways. Past tense verbs for PE/SA/AC and present tense for tasks. It is important to adhere to this convention and not lapse into the task oriented description of work. The verbs above are many times placed in a dictionary of the program. If IMP/IMS elements have verbs NOT found on the list then they either need to be evaluated and added or the IMP/IMS element needs to be edited. The psychological aspects of these verbs is subtitle at first. By stating a past tense action the read (and IMP/IMS user) is motivated to see what work was accomplished to complete the event. 16
17 IMP/IMS Components This is different than a task oriented schedule where effort is connected to milestones Event (System or Product) Significant Accomplishment Significant Accomplishment Accomplishment Criterion Accomplishment Criterion Detailed Task Detailed Task IMP/IMS 17 /54 17 A quick review of the IMP/IMS components and their hierarchy is in order before moving on to more details. This time starting from the bottom. Remember this is not how the IMP/IMS is built, but it is another way to look at the relationships Tasks define the actual work performed on the program. These tasks deliver product or process in support of the criteria for an accomplishment. The output of the tasks should have a metric embodied in the accomplishment criteria that is a measurable outcome of the effort performed during the period of performance. The accomplishment criteria describe the measurement to be assessed in performance of the work. The significant accomplishment defines the measurable outcome of the tasks and their criteria. This accomplishment is a tangible outcome that moves the program forward. It is an assessment of the maturity of the program as well as an incremental progress toward the goal of the program. In the spacecraft construction business the final goal is usually the launch of the vehicle into orbit or to a planet. 17
18 Preparing the IMP Charter the working group Program Management Team (PMT) System Engineering Integration Team (SEIT) Integrated Product Team (IPT) Certified Principle Engineer (CPE) Functional managers if they are organized along functional disciplines IMP/IMS 18 /54 18 The preparation of the IMP is a semi-formal process. For proposal work the proposal team bursts the RFP and lays out the WBS and SOW. For a post-award program the SOW, WBS and contract are the basis of the IMP. The key element of IMP development is to have the appropriate number of events while capturing program maturity and progress rather than just the passage of time. There will be standard government milestones (PDR, CDR, etc.) The remaining events must reflect maturity measurements, transition points, handoff points, join up points, and other times in the program where assessment and evaluation can take place. These points must be tied to the risk mitigation processes as well. At these points the entire team (contractor and customer) must have to opportunity to evaluate the program for compliance as well as risk assessment. Free and frank questions and answers need to performed at these points. 18
19 Preparing the IMP Inputs for the IMP Statement of Work (SOW) Work Breakdown Structure (WBS) WBS Dictionary Contract Line Item Numbers (CLIN) Contract Data Requirements List (CDRL) Data Item Descriptors (DID) Program Requirements List (PRL) Organizational Breakdown Structure (OBS) IMP/IMS 19 /54 19 The obvious inputs for the IMP come from the obvious places. In fact there aren t really any non-obvious places to find information for the IMP. But an exhaustive search is necessary since the IMP will not only be a contract document, it s quality will be the basis of success for the program. 19
20 Preparing the IMP Each IPT plans, tracks, and executes its own efforts in a fully integrated manner through the IMP The IMP seamlessly integrates elements of the management process using an event-based code and numbering scheme Using the IMP/IMS verb dictionary construct an indented structure of E/A/C/Tasks Use past tense verb for E/A/C at end of sentence Use present tense verb for tasks at beginning of sentence There is a powerful effect of stating the completion criteria instead of the level of effort needed to complete the task. This defines upfront - What does done mean? IMP/IMS 20 /54 20 The preparation of the IMP is a team effort. It is also iterative and incremental. It is iterative because the program requirements are usually complex and convoluted. Many passes through the requirements are needed to build a clear and concise event map. If the requirements are held in electronic form (DOORS) then mapping requirements to events can be done electronically as well. In the proposal there is usually a map between proposal subsections and the SOW as well. It is incremental because of the hierarchical nature of the IMP. Developing too much detail too soon commits the IMP/IMS too early as well. Incrementing the levels of detail provide numerous opportunities to re-direct the program architecture early in the IMP/IMS development process. A properly developed IMP/IMS should contain labor and cost spreads against the tasks. If the structure of these tasks is committed too soon, re-doing the labor spreads will be tedious at best and avoidable at worse. 20
21 Three Sections of the IMP 1 Overview summarized key elements of the product process narratives and methodology for developing the IMP 2 Product IMP Matrix PE, SA and AC structure for the program 3 IMP Process Narratives description of how to manage and perform the contract effort defined in the IMP Matrix IMP/IMS 21 /54 21 In a formal process there are three sections of the IMP. This is a proposal based approach, so ongoing programs will likely not find value here. This brings up the issue though of doing a good IMP/IMS during the proposal, so when award comes it will be an easy transition from the Basis of Estimate costing to the actual costing model. As well the decomposition work should follow a product structure rather than the traditional functional structure. In the product decomposition Events and Significant Accomplishments can be easily identified. In the functional structure Events and Significant Accomplishments are more difficult to identify, since the passage of time is the primary metric of functional organizations. Pseudo-product structures are a problem, since they look like product structures but are actually functional structures. Care must be taken to clearly identify Events and Accomplishments not matter the structure. IMP/IMS depends on this clarity and without it the business benefits of IMP/IMS is lost without the users actually knowing it. 21
22 Define / Derive Deliverables CLINs list customer deliverables Items needed to support the CLINs Assign every product to an IPT, then to a CPE with full authority to deliver Summarize each product life cycle in the IMP IMP/IMS 22 /54 22 More sources of Events can be found in the CLINs and IPT Statements of Work 22
23 Criteria for Defining Events Customer provided events Key decisions Risk mitigation events Mandatory corporate events Capability demonstrations Verification efforts IMP/IMS 23 /54 23 The customer provides other sources as well 23
24 Typical IMP Events ATP Authorization to Proceed IBR Initial Baseline Review IBR Integrated Baseline Review SRR Systems Requirement Review SDR System Design Review PDR Preliminary Design Review CDR Critical Design Review TRR Test Readiness Review PCA Physical Configuration Audit FCA Functional Configuration Audit IOC Initial Operating Capability FOC Final Operating Capability IMP/IMS 24 /54 24 External events are common in government procurement processes as well 24
25 IMP/IMS Numbering Scheme Coding system links key Events to responsible IPTs, SAs, ACs, and Tasks Event IPT Task A 01 B 01 a 1001 Significant Accomplishment Accomplishment Criteria CWBS IMP/IMS 25 /54 25 One attribute of IMP/IMS is a common numbering system. This approach is emphasized in many guides and training sessions. Its importance depends on the program structure. In a complex IPT structure common numbering is the glue between the IPTs. In many other programs this common numbering provides little value since there are other common numbering schemes in place. Charge Account numbers, CWBS, Work Packages are used in homogenous program teams to serve as IMP/IMS numbers. 25
26 Defining Accomplishments SAs are event related not just time coincidental The passage of time has little to do with real progress These events should not be anchored at a specific date, unless imposed by the customer The date of the event should be driven by the supporting work that must be accomplished Accomplishment characteristics A discrete step in the process of planned development A desired result at a specific event Interrelationships, interdependencies, or handoffs points IMP/IMS 26 /54 26 The use of Significant Accomplishments is the first departure from task-based planning. SA s ask what have you done that moves this project along? SA s of course are the meat and potatoes of the Events. They are the actionable outcomes that are the basis of the Event. The emphasis is on action, doing something that is evidence of accomplishment, not just the passage of time. The SA s must be discrete increments, wholly intact deliverables. In the philosophy of Earned Value, credit for accomplishments is 0% or 100%. No partial credit. This may not always be the case, but it should only be a special case where partial credit is taken for performance of the accomplishment. 26
27 Sample Accomplishments Accomplishments are past tense. Activities that have been performed with measurable outcomes EVMS processes demonstrated System Requirements Allocations Completed Functional Interface Requirements Established Software Build Cycle 1 Released IMP/IMS 27 /54 27 Using the grammatical structure of past tense verb at the end of the activity, SA s include this phrases. The IMP/IMS style is narrative, with complete sentences (minus articles and smaller components). The reader should be able to grasp the concept by reading the activity. If the IMP/IMS task names (in Microsoft Project) were read top to bottom it would be a properly formed description of the work performed during the program. The approach avoids task names like: Build software, which are vague, do not describe the outcome, and contain not measurable activities. Such a statement contains a verb build but nothing that can be measured. The passage of time in build software would seem to deliver the software at the end of the task. But as well all this does not happen. The reason for this is more complex than IMP/IMS can address. But IMP/IMS is the first step in removing the vagueness from the schedule by stating measurable outcomes along the way to building the software. 27
28 Evidence of Accomplishment Accomplishment Criteria (AC) are definitive measures supporting successful completion of a significant accomplishment (SA) An AC must show objective evidence of work progress Seen, read, demonstrated, or quantified Measured in an independent means, not just a statement we re done Defining the accomplishment criteria before proceeding with the work is critical IMP/IMS 28 /54 28 Accomplishments are nice, they re even mandatory. But how are they judged to be compliant with the work. The Accomplishment Criteria provide the means test for the accomplishments. You say you did the work, how can I test that this work meets my needs? How would I recognize that the work is done properly? The objective evidence approach is the way accomplishments are measured. Something deliverable an actionable outcome is the starting point. Something that can be held, read, demonstrated, operated, installed, used or any other variety of actionable verbs. 28
29 Integrated Master Schedule IMS is a calendar oriented tool that integrates all criteria, accomplishments, and events described in the IMP. Represents relationships between tasks Duration and timing Scope of work IMP/IMS 29 /54 29 With the Events, Accomplishments, and Criteria in hand, the Integrated Master Schedule is the next step. This is an easy process actually what tasks must be performed in order to exit the Event with the accomplishments complete according to their measurement criteria? These activities are the tasks. The major effort here is sequencing the tasks, getting the task constraints properly assigned, resource loading these tasks. This is not a easy effort, but the guidance for recognizing done has been defined in the PE/SA/AC descriptions, so now here is little vagueness of what work needs to be done. 29
30 Integrated Master Schedule Depicts both planned (baselined) and forecast dates Measures impact and performance for each activity Communicates program content, workflow, and approach Identified problem areas Enables management to prioritize Is the basis for evaluating and communicating change IMP/IMS 30 /54 30 Assembling all these components (PE/SA/AC/Task) in one place completes the IMS. The IMS is an event based, accomplishment focused, criteria measured, task description of the work to be done in the program. Done is now fully articulated in one place. The IMS IS the integrated master plan, in a way no other planning process is. It defines done It defines the path to done It defines how done is recognized Using Kipling s poem, Elephant s Child I keep six honest serving men (They taught me all I knew); Their names are What and Why and When And How and Where and Who The IMP/IMS provides new meaning to integrated. 30
31 Three Levels of Schedule Master usually published with the proposal, but also the supporting basis for the IMP Intermediate resource loaded derivative of the Master Schedule Detailed 60 to 90 day rolling wave details at the execution level Sufficient detail to control the work Deliverables at the end of the wave support the accomplishments IMP/IMS 31 /54 31 A properly formed IMP/IMS is a layered approach. In most modern project management guidelines a rolling wave or spiral approach is used for planning. The agile community has other terms for this but most modern process are iterative and incremental. The Big Design Up Front (BDUF) approaches of the past have been shown to contain a fundamental flaw. Predicting the future without feedback from the current and past is very sporty business. The customer wants to know the total cost to some degree of accuracy. Wants to know the risks. Wants to know the schedule. But the degree of accuracy varies as a function of time. IMP/IMS addresses this issue with three (3) levels of schedule. The Master schedule is usually a series of milestones and task bars for the end-toend activities The intermediate schedule is usually a Tier 2 or Tier 3 WBS schedule The detailed schedule is a week to week plan of the work, resources, and deliverables. This detailed schedule is often a 60 to 90-day rolling wave schedule designed to directly control the work. 31
32 Master Schedule Attributes Key elements of contract work IMP/IMS All test articles Deliverable hardware, software and documentation Key milestones / events over the life of the contract IMP/IMS 32 /54 32 The IMS has several important attributes. These seem obvious when stated here. Without the focus on event and outcomes, it is easy to fall into the trap of describing effort in place of outcomes. 32
33 Intermediate Schedule Reports a monthly review of program progress against schedule milestones Identified reference milestones Represents program activities to the lowest WBS level Is the product teams master schedule IMP/IMS 33 /54 33 A monthly reporting rhythm is common these days. What have you done lately is the theme of these reporting cycles. A formal reporting document usually accompanies the meeting. For NASA it is the 533M. For DoD it is the monthly CPR. For a program of nearly any size some type of formal report and review of progress is needed just to keep every focused on progress. 33
34 Detailed Schedule Lowest tier baseline schedule Cost Account focused with authorized work divided into a logical sequence of time-phased tasks IMP/IMS 34 /54 34 The detailed schedule is where the heavy lifting gets done for the planner. This is a week to week and sometimes a day to day schedule of the work activities. Since the detailed schedule is done on a 60 to 90 rolling wave the hard work of planning is limited in time. Well almost. One guideline for rolling waves is to start the planning of the next rolling wave long before the completion of the current rolling wave. But the planning packages developed in the intermediate schedule lay the ground work for the detailed rolling wave plan. It s still hard work but it doesn t all get done in a single sitting. By layering the planning process, iterative and incremental behaviors are enforced. IMS detail tasks are statused on a weekly basis. Status includes accomplishments, forecasts (late or early), and schedule changes. Using the Schedule Activity Task Identifier he IMP/IMS number), weekly detail activity status in the IMS is used to determine the monthly control account work package status. The Critical Path network in the detailed schedule provides the schedule impact to the program in comparison to the baseline schedule. 34
35 IMP / IMS Assembled from the RFP Requirement WBS Element SOW Task System Specification 1000 Spacecraft 1100 Avionics Ground Link 1000 Spacecraft 1100 Avionics 1110 Ground Link. 11n0 Avionics 3.1 Structure (WBS1000) Design, develop, produce and verify a complete spacecraft containing avionics, propulsion and other installed equipment. Integrated Master Plan (IMP) Management Plan Events Accomplishment Criteria 1. a. Duty cycle defined 1. Preliminary Design Review PDR b. Preliminary analysis complete Integrated Master Schedule (IMS) Program Events 1. Preliminary Design Complete PDR 2006 CDR 2. Duty Cycle Defined IMP/IMS 35 /54 35 This is a very simple (notational) picture of the IMP/IMS assembled from the requirements. This is one of those pictures that is both obvious and subtle at the same time. It is obvious because there is no information not already known by the planner. It is subtle because the development of the hierarchy of Events, Significant Accomplishments, and Accomplishment Criteria is not actually described in this picture. This by the way is the problem with most IMP/IMS training. It shows all the parts but does not tell the reader how to assemble the parts into a viable IMP/IMS. But this is a starting point. We ll get to a real IMP/IMS later. 35
36 A Very Simple IMP/IMS (not very useful) Activity # Program Event (PE) Significant Accomplishment (SA) WBS E E01 E01a E01b E02 E02a E02b Accomplishment Criteria (AC) Event E GN&C Flight Units Complete Release 1 Flight Production Complete Release 1 Subassemblies Complete Release 1 Assembly/Integration/Test Release 1a Flight Production Complete Release 1a Subassembly complete Release 1a Asmbl/Test/Launch/Ops IMP/IMS 36 /54 36 Again this is a carton of on IMP/IMS. This gentle introduction is meant to familiarize you with format before content. The content is harder to come up with, so format is a natural starting place. 36
37 A Fully Integrated Framework Statement of Work Requirements 2.0 OBJECTIVES The objectives of the RTIP development program are to: 2.1 Specify an operational RTIP system by means of cost-benefit trades, in which Cost As an Independent Variable and a warfighter perspective are used to establish system threshold and objective performance parameters; (Pre-EMD/EMD) 2.2 Define an architectural foundation for continuous evolution and growth in operational capability using a modular/scaleable design approach. This capability is to incrementally meet threshold, objective and P3I requirements for the minimum non-recurring and recurring cost throughout the life cycle of the system; (Pre-EMD/EMD) 2.3 Develop a cost effective design and sustainment strategy to continuously reduce cost of ownership throughout the life cycle of the system, while continuously improving operational availability; (Pre- EMD/EMD) 2.4 Prove threshold operational performance, and as a minimum, in a system of hardware, software, people, training, maintenance and other infrastructure that is certified to be operationally suitable and effective, as the basis for a production decision; (EMD) 2.5 Deliver for a production milestone decision a production-ready system, to include cost estimates and plans for production infrastructure including ground support systems, within the cost and schedule allocated to perform the RTIP development program; (EMD) 2.6 Plan for, and if directed, prepare a reprocurement data package for the RTIP radar subsystem; (Pre- EMD/EMD) 2.7 Deleted Prepare and submit, when necessary, Engineering Change Proposals (ECPs), Deviations, Waivers, and Contract Change Proposals (CCPs). (Pre-EMD/EMD) LEVEL - 4 LEVEL-6 WBS The link is established between the IMS The link is established between the IMS and the WBS at the task level and the WBS at the task level WBS Dictionary O&C IPT Management Operations and Control O&C Design - This O&C element Design includes all efforts necessary for Software to support the development of the system specifications such as Subsystem Specification and Computer Program Configuration Items Subsystem (O & C ) O & C Studies and Analysis Specifications, Functional Interface Documents/Interface Requirements Documents, Verification Cross- "A" Reference Matrices O&C and Risk Requirements Reduction Traceability Matrices for the O&C Subsystem. Develop the software architecture and O&C design Integration by performing preliminary and detailed design. Preliminary design consists of converting software O&C requirements Subsystem into Qualification high-level software Testin design to the task (execution unit) level. All preliminary design products are reviewed for product assurance Integrated Master Plan (IMP) MPE Significant Accomplishment IPT Accomplishment Criteria WBS L4 WBS L6 (A) SRDT A06 O&C Subsystem Preliminary Design Initiated EXPL A0601 O&C Prototype Plan Updated (A) SRDT A06 O&C Subsystem Preliminary Design Initiated EXPL A0602 O&C Prototype Software Preliminary Design Completed Integrated Master Schedule (IMS) Major Program Event Significant Accomplishment Accomplishment Criteria Tasks Plans The Task contains the entire Life Cycle of each IPT processes The Task that contains lead to the the entire IMS Products. Life Cycle Schedules of each IPT Will Be processes Linked to that Identify lead to Critical the IMS Path Products. and Slack, Schedules and to Will Form Be Linked the Basis to Identify for Schedule Critical Risk Path Analysis and Slack, and to Form the Basis for Schedule Risk Analysis IMP No. L4 WBS L6 WBS IPT Task Name Cat. Start Dur Finish IMP No. A L4 WBS L6 WBS IPT Task (A) Name SYSTEM Cat. 10/1/01 Start Dur 0d 10/1/01 Finish 4 REQUIREMENTS& DESIGNTIM 10/1 A (A) SYSTEM REQUIREMENTS& DESIGNTIM 10/1/01 0d 10/1/01 10/1 A06 EXPL O&C Subsystem Preliminary Design Initiated 11/1/99 185d 8/2/00 8/2 A06 EXPL O&C Subsystem Preliminary Design Initiated 11/1/99 185d 8/2/00 8/2 A0601 EXPL O&C Prototype Plan Updated 11/1/99 184d 8/1/00 A0601 EXPL O&C Prototype Plan Updated 11/1/99 184d 8/1/00 A EXPL DevelopDraft O&CPrototype PlanUpdates M 11/1/99 124d 5/1/00 A EXPL DevelopDraft O&CPrototype PlanUpdates 11/1/99 124d 5/1/00 M A EXPL Develop FinalO&CPrototype PlanUpdates 5/2/00 60d 8/1/00 M A EXPL Develop FinalO&CPrototype PlanUpdates 5/2/00 60d 8/1/00 M IMP/IMS Common Numbering IMP/IMS 37 /54 37 Now for the obligatory big picture. Here are all the components of an integrated framework using IMP/IMS. You ll see all the components presented in previous slides and there relationships. Without some key of automation, this is going to be a mess for any sizable program. But rushing to automation should also be avoided, since the value of IMP/IMS is in the making, rather than in the completion not that a completed IMP/IMS is not our ultimate goal. This slide is borrowed from another slide show, as is likely that slide show. So if you ve worked at other aerospace firms this may be recognizable. Note the traceability between requirements, the WBS and its dictionary, the IMP and the IMS. 37
38 Naming Events, Accomplishments and Criteria Events, Significant Accomplishments, and Accomplishment Criteria Declarative sentence ending with a past tense verb Version 1 Subassemblies Completed Tasks Declarative sentence starting with a present tense verb Receive Raw Materials Color code each E/A/C/T to indicate differences Use BOLD Underlined Italic fonts to show differences IMP/IMS 38 /54 38 Let s talk about style. There are several styles for IMP/IMS. Our style is driven by the capabilities of Microsoft Project. Project is a hierarchy oriented tool. This means that work s defined in an indented structure. Summary tasks are created by indenting subordinate tasks. The levels on indenture are nearly unlimited I ve never really tested the limit though. For IMP/IMS the obvious levels of indenture are four matching the four components of IMP/IMS. In order to keep things straight color can be used as well. This puts a burden on planning to have a color printed, preferably a double sided color printer. Using color, underling, italics and bold, the PE/SA/AC/Task components can easily be distinguished. The trick (and there is one is to use flags for each Microsoft Project task to identify the type of component. Then using filters isolate each component and format it according to its type. The convention for formatting is simple Event (red Bold) Significant Accomplishment (Blue Bold) Accomplishment Criteria (Black, Normal, Underlined, Italic) Task (Black Normal) 38
39 Building an Integrated Master Plan How hard can this be, we ve built plans before? Turns out there are some subtleties to a good IMP Some events are obvious PDR, CDR, TRR Most are more difficult IF approached from the functional work allocation point of view Product focused deliverables True assessment points beyond the obvious reviews Integration, verification, assembly, test completion, operational assessment and other visible, tangible, measurement points are possible candidates These seem obvious as well, and some likely are, but others are still hiding in the details of the WBS IMP/IMS 39 /54 39 So far so good. But now we need to start putting together a real IMP/IMS. First the list of events may already be defined in the contract. PDR, CDR other Rs are likely defined in the RFP and have been carried over to the contract and now in the award kick off meeting the customer wants to see them again in the IMP. But other events need to be defined as well. If the planning process is functional orientated then these events may be difficult. That s why product focused planning is easier, since products have tangible outcomes that can be used for events, significant accomplishment, and the accomplishment criteria. Using the guidelines stated here the components of the IMP can be captured. 39
40 Building the IMP/IMS from the WBS Developing the Significant Accomplishments from the WBS to build a traceability matrix WBS PE s SRR SDR PDR CDR TRR ATLO SDAI A01, A02 B01 C01, C02 D01 E01 F System Test A05 B03, B04 D02, D03 E02 F Radar Subsystem Software A03 B02 C03 E O&C Subsystem A06, A07 B05 C04 D04 E04 F03, F Platform Integration A08 C05 E05, E06 F Support Commodities A09 D05 E07 F06, F07 Major Interface/ Relationship IMP/IMS 40 /54 40 One very useful way to start is with the Work Breakdown Structure. This WBS needs to be a product focused WBS. Using the obvious set of events from the contract a map between the WBS major elements and the events can be created. It may be this map represented all the work. But more likely there will be gaps in the lines connecting the cells in this matrix. Those gaps can be filled with new events. 40
41 Program Management Levels Program Levels Tier 1 Program Manager Control package manager IPT manager Technical performance goals Tier 2 Cost Account Managers Product work plan Responsible organization elements Tier 3 Work package manager IMP/IMS Elements Major Program Events (PE) Significant Accomplishments (SA) Accomplishment Criteria (AC) Tasks (NA) Detailed plans CWBS Level 1 & 2 Links to CLINs Level 3 & 4 Control Packages Link to PBS Integrated EVMS Level 5 Cost Account Package Cost Collection Level Links to WBS by OBS Resource summaries Early warning EVMS analysis Work package Earned value calculations IMP/IMS 41 /54 41 Looking back at the three (3) levels of IMP/IMS and using the map between WBS and Events the level of detail at each tier can be defined. 41
42 Using Schedule Constraints It is desirable to have tasks start as soon as possible Start determined by the relationships with predecessor tasks Provides maximum flexibility to stay within constraints of the critical path Changes to critical path have the least disruption to the planned schedule There are times when other constraints may be needed The execution IMS should not use hard constraints These types of constraints do not support credible risk assessment using CPM or Monte Carlo risk tools IMP/IMS 42 /54 42 Once the tasks, accomplishment criteria, significant accomplishments, and events have been assembled in one place (inside a Microsoft Project schedule), the tasks need to be linked. Notice this is the last step not the first step. In a traditional approach the tasks and their linkage is the starting point. In IMP/IMS it is the ending point. With the tasks defined and their initial duration specified, constraints can be placed on some of them to control their delivery. As Soon As Possible, Fixed Duration, Not Effort Driven should be the default settings for the tasks. This will allow the planner to connect the tasks into a logic network without having to worry about resource assignments messing with the durations at least at this point. 42
43 Soft Constraints Start No Earlier Than (SNE) Tasks not control by the execution team, for which the team has been given projects dates Government deliverables Tasks which may have to be scheduled in conjunction with other program elements Finish No Earlier Than (FNE) Just in Time tasks Rationale needs to be provided for constraints other than As Soon as Possible This information should be placed in the notes field IMP/IMS 43 /54 43 The use of constraints is fraught with difficulty and risk. So let s look at the limited constraint types to go into a good IMMP/IMS. There are only two (2) besides As Soon As Possible. Start No Earlier Than (SNE) should be used for task that cannot be controlled by the team. This usually means external tasks, government deliverables, and tasks that have to be schedules with external relationship that are themselves fixed. Finish No Earlier Than (FNE) should be used for tasks that define a just in time work process. Many activities we encountered have a aging component. The arrival of materials, the integration sequence of materials has a time phased order. This order may not be defined in the task sequence. The materials may have been delivered in parallel. FNE is a way to control the sequence of events that are not physically dependent on each other. 43
44 Task Relationships For an integrated master schedule to reflect the program status, all interdependencies must be identified Finish to Start one task finished before another starts Write Test Procedure Conduct Test Start to Start one cannot start until another starts Finish to Finish completion is driven by another task SS+5d Conduct Test Gather Results FF+22d Conduct Wind Tunnel Test Design Air Vehicle Start to Finish administrative tasks driven by a review date Prepare Agenda Conduct Review SF -10d IMP/IMS 44 /54 44 Most project scheduling programs provide a variety of ways of linking tasks. Here are the four ways Microsoft Project does it. Finish to Start is the most common Start to Start can be used for parallel tasks Finish to Finish for parallel tasks as well Start to Finish although rare is found in many review tasks that have a preparation or a pre-delivery process 44
45 Milestones Deadline constraint is a powerful tool for controlling Complete prior Complete after FF-10d FF+10d Complete 10 days prior Milestone Date Complete 10 days after IMP/IMS 45 /54 45 Linking milestones should be done with a deadline constraint. Milestones that precede or follow should use a Finish to Finish constraint. 45
46 Sorting the IMS Using Microsoft Project the IMS components can be sorted Events / SA / AC / Tasks Work Break Down Structure CDRLs IPTs Using flag fields, filters and a Project Sort order are used to produce different presentation views of the IMS. The IMP/IMS number is used to sort the filtered components IMP/IMS 46 /54 46 Let s look at how to get all these components to come out in a nice neat picture, like the ones we see in the guidebooks. Each project task has flags (yes/no values) that are used to sort the IMP/IMS. These flags are usually Flag1 through Flag4. Names are attached to the flags PE, SA, AC, Task. Filters are used to arrange the project schedule according the flags and the IMP/IMS coding number. 46
47 Flag Fields for IMP/IMS Components IMP/IMS 47 /54 47 The Flags Field used to identify IMP/IMS components provide filtering for display. These flags represent the hierarchy of activities in the IMS just as they will when the project is displayed. Care needs to be taken to make sure duplicate flags are not set or that at least one flag is set. This can be done with others filters to confirm the flags are set properly. 47
48 A Filter for Events, SA s and AC s Using the Flags, filters are build to construct various views of the IMP/IMS IMP/IMS 48 /54 48 Here s a simple example of a filter the selects activities that are Events, Significant Accomplishments and Accomplishment Criteria. Defining filters is sometimes tedious, but a complete set will serve the planner well. The primary outcome is to be able to produce the IMP and the IMS from the same schedule in project. 48
49 Filtering a Project Schedule into an IMP/IMS The filtered and sorted results show a well formed IMP/IMS IMP/IMS 49 /54 49 Using the previous filter this is what the project looks like. 49
50 Using the IMS Post-Award Communication Convey to all participants the work to be done Program Tracking Directed Budget Cuts What If Exercises Reporting Contractor Performance Assessment Reports (CPAR) Award Fee Earned Value Management System Change Control Process IMP/IMS 50 /
51 Using the IMS for Communication Flow of information between IPTs Assures all interfaces are recognized and addressed Avoid team stove pipes Provides a basis of discussion Data exchange between government and contractor Electronic publishing of IMS Performance tracking based on the completion of events rather than the passage of time IMP/IMS 51 /
52 Program Tracking with the IMS Block updates scheduled in the program management process Reporting status across an accomplishment rather than an individual task. Regular program status updates Guided by the current events and the deliverables that proceed them. IMP/IMS 52 /
53 A Real IMS Sample IMP/IMS 53 /54 53 This is the presentation format of the IMP/IMS. Logos, footers and headers, and legends are added. A standard way to produce a package is: 1. Display the events only and print this in PDF 2. Display the Events and Significant Accomplishment and print this in PDF 3. Display the CDRLs (using a filter with the CDRL flag set to TRUE and the CDRL text field completed and save this as a PDF 4. Display the complete package (PE/SA/AC/Task) and save this. 5. Open the Events only PDF and using the PDF Distiller add the PE/SA, CDRL, and complete documents into a total document. This document can then be sent to the interested parties. 53
54 Resource Materials Air Force Materiel Command: Integrated Master Plan / Integrated Master Schedule (IMP/IMS) Guide, Version 1, November The Integrated Project Management Handbook, 8 February 2002 Dayton Aerospace, Scheduling Guide for Program Managers, October 2001, Defense Systems Management College, Fort Belvoir, VA Department of the Army Cost Analysis Manual, US Army Cost and Economics Analysis Center, May NASA Systems Engineering Handbook, SP-610S, June 1995 IMP/IMS 54 /54 54 The materials in this presentation are not original, but derived from the sources listed here as well as other publicly available presentations. Goggle of course is a place to start once these sources have been digested. This is an evolving topic so conferences and their proceedings are a good place as well. 54
Developing Work Breakdown Structures
Developing Work Breakdown Structures International Cost Estimating & Analysis Association June 2014 Neil F. Albert MCR, LLC [email protected] 703-506-4600 2014 MCR, LLC Distribution prohibited without express
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Appendix B: Work Breakdown Structure (WBS)
: Work Breakdown Structure (WBS) B.1. Introduction The WBS and WBS dictionary are effective management processes for planning, organizing, and administering NASA programs and projects. In accordance with
SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT
1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between
Scheduling Process Maturity Level Self Assessment Questionnaire
Scheduling Process Maturity Level Self Assessment Questionnaire Process improvement usually begins with an analysis of the current state. The purpose of this document is to provide a means to undertake
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN?
1 IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN? Presented at The Nexus of Agile Software Development and Earned Value Management, OSD-PARCA, February 19 20, 2015 Institute for Defense Analysis, Alexandria,
Appendix E Program Management Plan Template
Appendix E Program Management Plan Template Version 2 March 7, 2005 This page is intentionally left blank. Version 2 March 7, 2005 Title Page Document Control Panel Table of Contents List of Acronyms Definitions
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK
Office of Safety and Mission Assurance NASA-GB-9503 SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK AUGUST 1995 National Aeronautics and Space Administration Washington, D.C. 20546 PREFACE The growth in cost
Government Contracting and Earned Value Management (EVM)
Government Contracting and Earned Value Management (EVM) Ida Davis, EVP, PMP, MBA Earned Value Manager DynPort Vaccine Company LLC, A CSC Company Note: This presentation is the property of DynPort Vaccine
PROJECT SCOPE MANAGEMENT
5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
Program/Project Management Series Work Breakdown Structure Reference Guide
Program/Project Management Series Work Breakdown Structure Reference Guide National Aeronautics and Space Administration May 1994 2 Work Breakdown Structure Reference Guide May 1994 Table of Contents Chapter
Fundamentals of Measurements
Objective Software Project Measurements Slide 1 Fundamentals of Measurements Educational Objective: To review the fundamentals of software measurement, to illustrate that measurement plays a central role
How To Develop Software
Software Engineering Prof. N.L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture-4 Overview of Phases (Part - II) We studied the problem definition phase, with which
FOREWORD. Page 2 of 88
FOREWORD Earned Value Management (EVM) is one of the DoD s and industry's most powerful program management tools. Government and industry program managers use EVM to assess cost, schedule and technical
Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc.
INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. February 2013 1 Executive Summary Adnet is pleased to provide this white paper, describing our approach to performing
Requirements Management John Hrastar
Requirements Management John Hrastar NASA Project Management Conference March 30-31, 2004 University of Maryland Conference Center Introduction Three aspects of requirements management Requirements in
Chapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Project Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
Criteria for Flight Project Critical Milestone Reviews
Criteria for Flight Project Critical Milestone Reviews GSFC-STD-1001 Baseline Release February 2005 Approved By: Original signed by Date: 2/19/05 Richard M. Day Director, Independent Technical Authority
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
Glen B. Alleman Niwotridge Consulting
1 /42 ESTABLISHING THE PERFORMANCE MEASUREMENT BASELINE (PMB) Glen B. Alleman Niwotridge Consulting The Performance Measurement Baseline is a time phased schedule of all the work to be performed, the budgeted
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor
MGMT 4135 Project Management. Chapter-4. Defining the Project
MGMT 4135 Project Management Chapter-4 Where We Are Now Chapter-4 Steps for Chapter-4 Step-1 Scope Step-2 Establishing Project Priorities Step-3 Creating the Work Breakdown Structure Step-4 Integrating
The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into
The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material,
Measurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by
Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones
WORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
Appendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
IT Project: System Implementation Project Template Description
2929 Campus Drive Suite 250 IT Project: System Implementation Project Template Description Table of Contents Introduction... 2 Project Phases... 3 Initiation & Requirements Gathering Milestone... 3 Initiation
INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page.
What This Is INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page. First of a series of guidelines for project
<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
ENOVIA Aerospace and Defense Accelerator for Program Management
ENOVIA Aerospace and Defense Accelerator for Program Management Through project pipeline dashboards, ENOVIA Aerospace and Defense Accelerator for Program Management provides real-time visibility into a
VA ICJIS. Program Management Plan
VA ICJIS Program Management Plan 1 08/29/01 Program Management Plan VA Integrated Criminal Justice Information System (ICJIS) Program 1. Introduction. The Commonwealth of Virginia Integrated Criminal Justice
DEPARTMENT OF DEFENSE STANDARD PRACTICE
NOT MEASUREMENT SENSITIVE MIL-STD-881C 3 October 2011 SUPERSEDING MIL-HDBK-881A 30 July 2005 MIL-STD-881B 25 March 1993 DEPARTMENT OF DEFENSE STANDARD PRACTICE WORK BREAKDOWN STRUCTURES FOR DEFENSE MATERIEL
Earned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide May 4, 2011 Revision 1* National Defense Industrial Association (NDIA) 2111
Statement Of Objectives (SOO) Information Guide
Statement Of Objectives (SOO) Information Guide 20 Jun 03 Prepared by OC-ALC/AE (ACE) TABLE OF CONTENTS SECTION PARAGRAPH/TITLE 1. Introduction:... 1 2. Purpose:... 1 3. SOO Development Process:... 1 4.
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
System/Data Requirements Definition Analysis and Design
EXECUTIVE SUMMARY This document provides an overview of the Systems Development Life-Cycle (SDLC) process of the U.S. House of Representatives. The SDLC process consists of seven tailored phases that help
Training Seminars. Description. Core Courses: The core courses consist of the following:
Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals
NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE Head, Office of Project Support Services
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
The Software Development Life Cycle (SDLC)
Document ID: Version: 2.0 1 / 22 2 TABLE OF CONTENTS INTRODUCTION... 4 THE SDLC WATERFALL... 4 ALLOWED VARIATIONS... 5 OTHER SDLC MODELS... 6 REFERENCES... 7 GENERIC STAGE... 8 KICKOFF PROCESS... 8 INFORMAL
Software Project Management Plan (SPMP)
Software Project Management Plan (SPMP) The basic template to be used is derived from IEEE Std 1058-1998, IEEE Standard for Software Project Management Plans. The following is a template for the SPMP.
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane [email protected] Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
How To Plan An Agile Project
GAO Scheduling Best Practices Applied to an Agile Setting by Juana Collymore and Brian Bothwell April 15, 2015 Outline Why is scheduling important? GAO Schedule Assessment Guide Overview Status of the
Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved
Description of Program Management Processes (Initiating, Planning) Topics Covered Program Management Process Groups salient features Description of all processes in Initiating Process Group: Initiate Program
Head, Office of Project Management Oversight
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Management Oversight REVISION: 43 APPROVED BY: TITLE Head, Office of Project Management
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
300 Scheduling and Budgeting
Jefferson Science Associates, LLC 300 Scheduling and Budgeting Project Control System Manual Revision 7-16 - 300 Scheduling and Budgeting This chapter of the JSA Project Control System Manual describes
3. SCHEDULING THE MOST IMPORTANT PHASE PLANNING ACTIVITY. 3.1 Project Management Software Does it Really Do That?
3. SCHEDULING THE MOST IMPORTANT PHASE PLANNING ACTIVITY 3.1 Project Management Software Does it Really Do That? Not really it doesn t do any management that takes a talented human like you! A betternamed
Step by Step Project Planning
Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
PROJECT AUDIT METHODOLOGY
PROJECT AUDIT METHODOLOGY 1 "Your career as a project manager begins here!" Content Introduction... 3 1. Definition of the project audit... 3 2. Objectives of the project audit... 3 3. Benefit of the audit
Integrated Project and Process Management A Cornerstone for the CMMI
Integrated Project and Process Management A Cornerstone for the CMMI Dennis J. Frailey [email protected] Copyright 2005, Dennis J. Frailey IEEE Long Island Objective To discuss what integrated process
Earned Value Management Best Practices
WHITE PAPER Earned Value Management Best Practices Contents Best Practices for EVMS Use...1 Use an EVMS Description and Keep it Up to Date...1 Use EVMS on Every Project...2 When to Use EVMS on a Program...3
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Project Control System Manual. Jefferson Science Associates, LLC. 200 Organization. Project Control System Manual Revision 7 - 7 -
Jefferson Science Associates, LLC 200 Organization Project Control System Manual Revision 7-7 - 200 Organization This section of the JSA Project Control System Manual describes the organizational elements
Positive Train Control (PTC) Program Management Plan
Positive Train Control (PTC) Program Management Plan Proposed Framework This document is considered an uncontrolled copy unless it is viewed online in the organization s Program Management Information
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
Earned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide January 27, 2015 Revision 2 National Defense Industrial Association (NDIA)
Deciding the work to be Performed (Work Breakdown Structure)
Deciding the work to be Performed (Work Breakdown Structure) Goals of the Unit Understanding the transition from project goals to the project schedule Introducing the Work Breakdown Structure notation
This is the software system proposal document for the <name of the project> project sponsored by <name of sponsor>.
Guide to Preparing the SOFTWARE PROJECT MANAGEMENT PLAN R. Buckley CSc 190 Senior Project Department of Computer Science - College of Engineering and Computer Science California State University, Sacramento
Template K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
PROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
WORK BREAKDOWN STRUCTURE HANDBOOK
WORK BREAKDOWN STRUCTURE HANDBOOK U.S. Department of Energy Washington, D.C. 20585 August 16, 2012 AVAILABLE ONLINE AT: URL TBD INITIATED BY: Office of Management FOREWORD This handbook was developed by
Project Management Standards: A Review of Certifications/Certificates
Project Standards: A Review of Certifications/Certificates Standards for Project Supporting Certification and Certificates Certificate Certification The Project Body of Knowledge PMBOK Guide Projects in
THE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
THE WORK BREAKDOWN STRUCTURE IN AN ACQUISITION REFORM ENVIRONMENT. Prepared For: COST SCHEDULE PERFORMANCE MANAGEMENT CONFERENCE
THE WORK BREAKDOWN STRUCTURE IN AN ACQUISITION REFORM ENVIRONMENT Prepared For: COST SCHEDULE PERFORMANCE MANAGEMENT CONFERENCE Prepared By: Neil F. Albert 700 Technology Park Drive Billerica, MA 01821
Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102
Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102 Interneer, Inc. Updated on 2/22/2012 Created by Erika Keresztyen Fahey 2 Workflow - A102 - Basic HelpDesk Ticketing System
The Phios Whole Product Solution Methodology
Phios Corporation White Paper The Phios Whole Product Solution Methodology Norm Kashdan Phios Chief Technology Officer 2010 Phios Corporation Page 1 1 Introduction The senior staff at Phios has several
3SL. Requirements Definition and Management Using Cradle
3SL Requirements Definition and Management Using Cradle November 2014 1 1 Introduction This white paper describes Requirements Definition and Management activities for system/product development and modification
Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University
Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
PROJECT PLAN TEMPLATE
Treasury Board of Canada Secretariat Secrétariat du Conseil du Trésor du Canada Enhanced Management Framework for Information Management/Information Technology PROJECT PLAN TEMPLATE Document Revision Draft
Biometrics Enterprise Architecture Project Management Plan (BMEA PMP)
Biometrics Enterprise Architecture Project Management Plan (BMEA PMP) Version 1.0 Prepared by: Date: November 24, 2008 Revision History Purpose Revision Date Level 11/17/2009 First Draft 1.0 Responsible
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
DEPARTMENT OF THE AIR FORCE HEADQUARTERS AERONAUTICAL SYSTEMS CENTER (AFMC) WRIGHT-PATTERSON AIR FORCE BASE OHIO
DEPARTMENT OF THE AIR FORCE HEADQUARTERS AERONAUTICAL SYSTEMS CENTER (AFMC) WRIGHT-PATTERSON AIR FORCE BASE OHIO BULLETIN AWB 002A 17 May 2011 ((supersedes AWB-002) United States Air Force (USAF) Airworthiness
Assessment of NCTD Program Management Framework for Positive Train Control Program
Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation
Abstract. 1 Introduction
Amir Tomer Amir Tomer is the Director of Systems and Software Engineering Processes at RAFAEL Ltd., Israel,with whom he has been since 1982,holding a variety of systems and software engineering positions,both
SYSTEMS ANALYSIS AND DESIGN DO NOT COPY
Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
Expert Reference Series of White Papers. Intersecting Project Management and Business Analysis
Expert Reference Series of White Papers Intersecting Project Management and Business Analysis 1-800-COURSES www.globalknowledge.com Intersecting Project Management and Business Analysis Daniel Stober,
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
How To Write Ansi/Eia Evm System Acceptanceance Guide
National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC) ANSI/EIA 748 Earned Value Management System Acceptance Guide Working Release For User Comment January 23, 2006
Accounting System. Page 1 of 9
Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems
Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide
Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide Health Check Summary Reports Performance Trend Schedule Trace Schedule Compare Margin Tracker Health Check Indicators Missing Predecessors
Project Management. An Overview for IT. Author: Kevin Martin & Denise Reeser
Project Management An Overview for IT Author: Kevin Martin & Denise Reeser Agenda Best Practices (5 min) Preliminary Assessment (10 min) The Need for Project Management (15 min) Involvement of EPMO (10
Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman
Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government
Value to the Mission. FEA Practice Guidance. Federal Enterprise Architecture Program Management Office, OMB
Value to the Mission FEA Practice Guidance Federal Enterprise Program Management Office, OMB November 2007 FEA Practice Guidance Table of Contents Section 1: Overview...1-1 About the FEA Practice Guidance...
U.S. Dept. of Defense Systems Engineering & Implications for SE Implementation in Other Domains
U.S. Dept. of Defense Systems Engineering & Implications for SE Implementation in Other Domains Mary J. Simpson System Concepts 6400 32 nd Northwest, #9 Seattle, WA 98107 USA Joseph J. Simpson System Concepts
NASCIO EA Development Tool-Kit Solution Architecture. Version 3.0
NASCIO EA Development Tool-Kit Solution Architecture Version 3.0 October 2004 TABLE OF CONTENTS SOLUTION ARCHITECTURE...1 Introduction...1 Benefits...3 Link to Implementation Planning...4 Definitions...5
Information Technology Project Oversight Framework
i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11
