The 3 Must Dos for Maintenance Planning and Scheduling
|
|
|
- Julie Weaver
- 9 years ago
- Views:
Transcription
1 The 3 Must Dos for Maintenance Planning and Scheduling "Simple Ideas" Presented by: Mike Gehloff The Core Problem Challenge Most maintenance staff actually work 2-4 hours a day (Effective Hours) Effective Direct work is low Lack of effective Planning Lack of effective Scheduling Inadequate Coordination Across all Departments 70-80% of equipment failures are Human-Induced Not using a torque wrench Not knowing specifications Not having the right part at the right time Improperly handling and installing bearings No repeatable, effective PM, Corrective, Lube Procedures Do any of us have real faith in our proactive maintenance approach? Wrench Time Where did the time go? Copyright 2005 Services Group
2 Planning s Goal: The Proactive Approach Identifying the parts, tools, procedures, and standards/specifications required for effective maintenance work, to increase wrench time and optimize reliability. Planning is key to the success of Precision Maintenance Lean Towards Proactive Work TRANSITION Lean Towards Proactive Work Two Avenues of Improvement: Design of the Proactive Maintenance Plan Execution of the Proactive Maintenance Plan TRANSITION Copyright 2005 Services Group
3 Terminology Planning: Performing research and determining the requirements of a task to be performed in the future WHAT, HOW, WHERE, WHY, WHEN, WHO Scheduling: The act of aligning available resources to the work backlog and placing it on the calendar WHEN, WHO Coordination: Reacting to emergencies and making adjustments to the schedule in real time based on priorities Must Do #1 PLANNERS FOCUS ON THE FUTURE A Maintenance Planner Does Not Plan Emergency Work Expedite Parts Schedule Work Schedule Routine Activities Act as a Relief Supervisor Maintain a Storeroom Act as a Clerk Perform the Buyer Function Pick up the tools and fill in for emergencies Engineer (Design) Jobs Not the Plant Engineer or the Plant Engineer s Assistant Copyright 2005 Services Group
4 Work Management - Core Beliefs Work Management Core Beliefs 1. Planners remain focused on FUTURE WORK. 2. Planners do not chase parts for jobs in progress. 3. Supervisors and crew leads handle the current day s work and problems. 4. Faced with the choice, a line supervisor must concentrate on today s problems rather than work on future (even tomorrow s) activities. 5. There is no such thing as a perfectly planned job continuous improvement is a must. 6. All stakeholders must share the same priorities active communication on priorities is an absolute requirement. Planners Must Add Value Planners battle and eliminate losses and delays from maintenance and its related activities The planner s efforts are measured by: Feedback on the completed work orders (job plan quality) The size of the Waiting for Schedule backlog (measured in weeks 2 weeks minimum) Example Backlog Calculation Total Required Man-Hours (Ready Status) on all Work Orders in the System = 1000 hours 7 Mechanics 3 Electricians 1 Planner 1 Maintenance Supervisor 40 hours per week for each resource Total Available Man Hours = 400 hrs/week Total Backlog = 2.5 weeks Copyright 2005 Services Group
5 Must Do #2 THE ENTIRE ORGANIZATION MUST PARTICIPATE Roles and Responsibilities Maintenance Planner Develops new Job Plans maintains Job Plan Library Maintains accurate equipment specifications, info, and parts lists Communicates with: Production Operators Supervisors Manages the Ready Backlog keeps the pipeline full Provide a good craftsperson with enough information to reduce the incidence of delay due to craftspeople seeking information or instructions Scheduling Team Consider production requirements, work priorities, and budgets when establishing the work schedule Actively communicate priorities at the Scheduling Meeting develop common priorities based on needs Review the Backlog and publish a Weekly Schedule Schedule for 100% Usage of Available Resources when developing the schedule Actively communicate the schedule to all affected resources Coordinator Assign resources and execute to the published schedule React to emergencies and make spot changes to the schedule Ensure feedback is provided to both the Planners and the Scheduling Team to maximize efficiency in the future Communicate changing priorities back to the Scheduling Team on a daily basis RACI Planning and Scheduling Roles and Responsibilities R = Responsible A = Accountable (only 1) C = Consult I = Inform Identify Work Document in CMMS Develop the Weekly Work Schedule Develop Job Plans Monitor Backlog and React Accordingly Communicate Current Schedule Assign Resources to Jobs Order Specialty Parts React to Daily Schedule Changes Plan Emergency Work Maintain Accurate Equipment Specifications and Parts List Maintain Performance KPIs Develop a Craft Skills Training Plan Ensure the Maximum Use of all Available Resources Visit Craftspeople on the Job and Give them Work Instructions Formally Report Findings from Work on Work Orders - Feedback Planner Craftsperson Maintenance Supervisor Operators Operations Supervisor Stores/Procurement Copyright 2005 Services Group
6 Emergency Work Protocol Emergencies are unavoidable with discipline, we can reduce the frequency and impact of these events We must not try to plan for emergencies, but rather allow the daily coordination function (front line supervision) to handle these events In order to prevent abuses, we must define a protocol for emergencies What qualifies? What does not? Who decides? Who responds? On major emergency jobs, a work order should still be completed in order to document history and parts Must #3 COMMUNICATE ACTIVELY NOT PASSIVELY Routine Schedule Development Activities to Develop Next Week s Schedule DAILY REVIEW and COORDINATION of THIS WEEK S SCHEDULE Copyright 2005 Services Group
7 Documenting the Outage Schedule BAD BETTER BEST Outage Plan: Outage Preparation Matrix The War Room Contact List Actual Status Update Key 28 Job Plan Gantt Charts Outage Preparation Status Matrix Copyright 2005 Services Group
8 Visual Management of Progress Recap Must #1: Planners Focus on the Future Must #2: The Entire Organization Must Participate Must #3: Communicate Actively Not Passively Questions? Mike Gehloff GP Copyright 2005 Services Group
Overview of EAM Services. A Fully Integrated Global EAM Service Provider
A Fully Integrated Global EAM Service Provider Table of Contents Strategy & Process Services Overview... p. 3 Asset Reliability Services Overview... p. 4 Systems & Technology Services Overview... p. 7
Increase Equipment Uptime Through Robust Enterprise Asset Management. For the Upstream, Midstream & Downstream Sectors of the Oil & Gas Industry
Increase Equipment Uptime Through Robust Enterprise Asset Management For the Upstream, Midstream & Downstream Sectors of the Oil & Gas Industry The Oil & Gas industry is challenged with effectively maximizing
Building a Foundation for Maintenance & Reliability "Best Practice" Work Processes in EAM
Building a Foundation for Maintenance & Reliability "Best Practice" Work Processes in EAM Author: Dave Abecunas, CMRP Presented as IPSED: Back to Basics at the 2008 Reliability and EAM Summit Table of
Work Execution Management Training and Coaching Services
Work Execution Management Training and Coaching Services www.gpallied.com The Need Now, more than ever, your maintenance team is expected to increase effectiveness and performance with fewer members. This
Determining the Optimum Staffing Levels for a Maintenance and Reliability Department
An Allied Group White Paper 4200 Faber Place Drive Charleston, SC 29405 843.414.5760 www.alliedreliabilitygroup.com Determining the Optimum Staffing Levels for a Maintenance and Department By: Kate Kerrigan,
Asset Management Best Practices
Asset Management Best Practices Summary of a Five-Part Series on Maintenance Best Practices A series of white papers dedicated to Asset Management Best Practices. Maximize Asset Performance. Improve Operating
COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEMS. Dr. Abdul-Mohsen Al-Hammad. I. Maintenance Management Systems
COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEMS By Dr. Abdul-Mohsen Al-Hammad Outline I. Maintenance Management Systems II. Computerized Maintenance Management System. 2 1 I. Maintenance Management Systems
A S S E T I N T E G R I T Y I N T E L L I G E N C E
ASSET INTEGRITY INTELLIGENCE Fe atured Article BEST PRACTICES OF MAINTENANCE PLANNING & SCHEDULING MATT MIDAS, GenesisSolutions, An ABS Group Company VOLUME 21, ISSUE 2 MARCH APRIL 2015 BEST PRACTICES
Lean Silver Certification Blueprint
The Lean Certification Blueprint provides additional useful information beyond the Body of Knowledge. The Body of Knowledge specifies the competencies, topics, and subtopics required by different types
Reliability Solutions
Reliability Solutions Developing a World-Class Approach to Lubrication Lubrication is the cornerstone of an effective reliability-driven asset management program. A major bearing manufacturer has indicated
QAD Enterprise Asset Management BI Metrics Demonstration Guide. May 2015 BI 3.11
QAD Enterprise Asset Management BI Metrics Demonstration Guide May 2015 BI 3.11 Overview This demonstration focuses on one aspect of QAD Enterprise Asset Management Business Intelligence Metrics and shows
IBM Maximo Adapter for Primavera
IBM Maximo Tivoli Lab Services IBM Maximo Adapter for Primavera April 2008 Primavera partnership history Tactical partnership with custom integrations as early as 2000 Formalized integrations supporting
The Leading Reward of Maintenance Management
Halting the Cycle of Break & Fix: The Leading Reward of Maintenance Management Eric Hancock Practice Leader for Operations & Asset Management Jacobs Engineering Group Inc. Best Maintenance Strategies t
Total Productive Maintenance. Implementing TPM in Baxter Aibonito
Total Productive Maintenance Implementing TPM in Baxter Aibonito Overview TPM definition, elements overview, tools & expectations Continuous TPM improvement metric OEE definition & calculation Example
Maximizing Our CMMS Effectiveness
Maximizing Our CMMS Effectiveness Why be here? Learn about software that is available for facilities condition assessment and capital budget development Learn about some CMMS speed bumps Learn about our
The Role of CMMS. A white paper on the selection and implementation of computerized maintenance management systems. Prepared by:
A white paper on the selection and implementation of computerized maintenance management systems Prepared by: Mike Crain Manager, Industrial Technologies Northern Digital, Inc. [email protected]
Maintenance Planning and Scheduling Handbook
Maintenance Planning and Scheduling Handbook Third Edition Doc Palmer Me Graw Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New Delhi San Juan Seoul Singapore Sydney Toronto
21ST CENTURY PROCESS MANAGEMENT USING SPC BASED MANUFACTURING ANALYTICS
WHITE PAPER 21ST CENTURY PROCESS MANAGEMENT USING SPC BASED MANUFACTURING ANALYTICS By Jeffrey L. Cawley, Vice President Market Development, Northwest Analytics Inc. Actively using SPC and Manufacturing
HOW TO ACHIEVE OPERATIONAL EXCELLENCE THROUGH ENTERPRISE ASSET MANAGEMENT
HOW TO ACHIEVE OPERATIONAL EXCELLENCE THROUGH ENTERPRISE ASSET MANAGEMENT Optimize Assets to Move from Reactive to Predictive 919-835-0810 www.prometheusgroup.com Operational Excellence has been defined
PEOPLESOFT MAINTENANCE MANAGEMENT
PEOPLESOFT MAINTENANCE MANAGEMENT KEY BENEFITS Streamline Maintenance Operations Manage Full Asset Lifecycle Lower Total Cost of Ownership Oracle s PeopleSoft Maintenance Management completes the Enterprise
CSI study. A white paper from the itsmf Finland Continual Service Improvement Special Interest Group
CSI study Continual Service Improvement (CSI) study to the members of itsmf Finland A white paper from the itsmf Finland Continual Service Improvement Special Interest Group Date: April 2014 Authors: Anne
Copyright 1980 by the Association for Supervision and Curriculum Development. All rights reserved.
Turnaround and Maintenance Services
Turnaround and Maintenance Services Reliably providing quality turnaround and maintenance services safely Matrix Safe a cultural mindset For us, safety is more than a core value. It s a way of life. We
PROJECT MANAGEMENT FOR NON-PROJECT MANAGERS
PROJECT MANAGEMENT FOR NON-PROJECT MANAGERS NADC PTAC 2929 3 rd Ave., N., Suite 300 Billings, MT 59101 P. (406) 259-3804 F. (406) 259-4569 ww.nadc-nabn.org HIGHLINER CONSULTING GROUP, LLC. 255 E. Fireweed
SAFER Patient Flow Bundle
SAFER Patient Flow Bundle The patient flow bundle is similar to a clinical care bundle. It is a combined set of simple rules for adult inpatient wards to improve patient flow and prevent unnecessary waiting
Outsourcing Maintenance: A Plan for Success
Outsourcing Maintenance: A Plan for Success By Advanced Technology Services Because maintenance is usually determined not to be a core competency, outsourcing allows management to focus its scarce resources
Agile Development Overview
Presented by Jennifer Bleen, PMP Project Services Practice of Cardinal Solutions Group, Inc. Contact: Agile Manifesto We are uncovering better ways of developing software by doing it and helping others
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft
Implementing an Information Governance Program CIGP Installment 2: Building Your IG Roadmap by Rick Wilson, Sherpa Software
Implementing an Information Governance Program CIGP Installment 2: Building Your IG Roadmap by Rick Wilson, Sherpa Software www.sherpasoftware.com 1.800.255.5155 @sherpasoftware [email protected]
Business Challenges. Customer retention and new customer acquisition (customer relationship management)
Align and Optimize Workflows with Lean Dan Marino Marino Associates, LLC Strategic and tactical planning Information systems integration Customer retention and new customer acquisition (customer relationship
Sample Maintenance Audit Report
Sample Maintenance Audit Report NOTES: 1.0 This sample maintenance audit report and contents is indicative of the coverage and approach taken by Lifetime Reliability Solutions Consultants when performing
Achieve greater efficiency in asset management by managing all your asset types on a single platform.
Asset solutions To support your business objectives Achieve greater efficiency in asset by managing all your asset types on a single platform. Obtain an entirely new level of asset awareness Every company
Configuring the Optimization Server
Scheduler 7.5.2 Optimization Sr. Design Architects - Lori Pilgrim and Brian Downey Optimization Engine in Scheduler What-If Analysis 2 1 Architecture Application Server Application Server Maximo ODME Scheduler
NE-50413B Mastering Microsoft Project 2010
NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need
How project management software can smooth the way
How project management software can smooth the way By Michael V. Brown New Standard Institute The most demanding call on maintenance resources comes when a plant or facility is shut down for an extended
Priori ty ... ... ...
.Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared
6 Reasons Why Outsourcing Equipment Maintenance Is Your Best Hedge In A Down Economy
6 Reasons Why Outsourcing Equipment Maintenance Is Your Best Hedge In A Down Economy The decision to outsource equipment maintenance during times of economic boom is based on the desire of a company to
Root Cause Analysis Concepts and Best Practices for IT Problem Managers
Root Cause Analysis Concepts and Best Practices for IT Problem Managers By Mark Hall, Apollo RCA Instructor & Investigator A version of this article was featured in the April 2010 issue of Industrial Engineer
Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time.
T47400A, page 1 Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time. DUTIES Serves as the planner/scheduler for the Utilities
Oracle Utilities Work and Asset Management
Oracle Utilities Work and Asset Management User Guide Release 2.1.0 E61870-01 May 2015 Oracle Utilities Work and Asset Management User Guide Release 2.1.0 E61870-01 May 2015 Documentation build: 4.30.2015
Achieve greater efficiency in asset management by managing all your asset types on a single platform.
Asset solutions To support your business objectives Achieve greater efficiency in asset by managing all your asset types on a single platform. Obtain an entirely new level of asset awareness Every company
Starting a new Oil Analysis Program Burden or Benefit?
Starting a new Oil Analysis Program Burden or Benefit? Introduction So someone in senior management has finally realized the drain on the bottom line of your company caused by reactive maintenance in the
Executive Summary. This procedure supports Priority #4 of the Board Improvement Plan which states:
Executive Summary Policy and Procedure #409.0, Licensed Child Care in Schools Procedure #409.1, Security for Licensed Child Care and Before and After Care Programs in Schools Application Policy and Procedure
It s Time for Maintenance 2.0
It s Time for Maintenance 2.0 NOVEMBER 2010 Table of Contents Executive Summary... 3 Why Current Systems Fall Short... 4 It s Time for Maintenance 2.0... 5 Advantages of Maintenance 2.0... 6 Synchronize
Essential Elements for Any Successful Project
In this chapter Learn what comprises a successful project Understand the common characteristics of troubled projects Review the common characteristics of successful projects Learn which tools are indispensable
Well Service Manager Planning, Scheduling and Evaluation Software
Well Service Manager Planning, Scheduling and Evaluation Software Efficiently gather and store well information for effectively managing all well activities, including planning versus actual cost management.
50 Questions before computerization
50 Questions before computerization Before computerization, as an organization, ask yourself: 1. Is there enough time, money and interest to involve all levels within the maintenance department and other
Useful Key Performance Indicators for Maintenance
PO BOX 2091, ROSSMOYNE, WA, 6148 AUSTRALIA Phone: Fax: Email: Website: +61 (0) 402 731 563 +61 (8) 9457 8642 [email protected] www.lifetime-reliability.com Abstract Useful Key Performance Indicators
The Art of the Possible Scheduling Options in SAP. Mark W. Scott Vesta Partners, LLC
The Art of the Possible Scheduling Options in SAP Mark W. Scott Vesta Partners, LLC The Tool and the Challenge The Parts The Options The Results Scheduling in SAP What I ll cover: The Parts The Options
Technique 9.16 Metrics and Key Performance Indicators Gunter Wagner
Technique 9.16 Metrics and Key Performance Indicators Gunter Wagner Cover this area with a picture related to your presentation. It can be humorous. Make sure you look at the Notes Pages for more information
Lean and Six Sigma Healthcare Fad or Reality. Vince D Mello President
Lean and Six Sigma Healthcare Fad or Reality Vince D Mello President TODAY S DISCUSSION About Lean Methodologies Application benefits and outcomes About Six Sigma Key learning's QUALITY FUNDAMENTALS Function
Digital Marketing Specialist
Digital Marketing Specialist Financial Controller Our Vision To be the best company our employees ever work for, the best bank our customers ever do business with and the best investment for our shareholder.
GE Healthcare. Transforming radiology with actionable intelligence. *Trademark of General Electric Company
GE Healthcare Transforming radiology with actionable intelligence *Trademark of General Electric Company A roadmap for optimized radiology workflows As radiology departments transform themselves in this
Agile Project Management and the Real World. Emily Lynema DLF Fall 2010 November 1, 2010
Agile Project Management and the Real World Emily Lynema DLF Fall 2010 November 1, 2010 Outline Why care about project management? Traditional vs. Agile What is Agile? What is Scrum? Agile case study:
4. Maintenance and Materials Management
The Superintendent of Operations has various oversight responsibilities that impair his ability to effectively manage maintenance activities within the Project Operations Section. This impairment manifests
Table II:8 Overview of the Management System of an Organization
Table II:8 Overview of the Management System of an Organization Inputs: people, money, equipment, facilities, supplies, people's ideas, people's time, etc. System Loop Major Functions Comments Planning
How To Increase Employee Productivity And Increase Wrench Time At An Oil Refinery
Employee Productivity Improvement Strategies In Oil Refinery Environments Automated Workforce Management Helps Reduce Maintenance Backlogs, Increase Safety Compliance and Improve Profitability CONTENTS
CREATING A THIRD EDITION DAVID MANN
CREATING A LEAN CULTURE Tools to Sustain Lean Conversions THIRD EDITION DAVID MANN CRC Press Taylor & Francis Croup Boca Raton London New York CRC Press is an imprint of the Taylor St Francis Group, an
Supporting Lean Maintenance
Supporting Lean Maintenance Combining Best Practices with Technology for Superior Results TECHNOLOGY MANAGEMENT SOLUTIONS 2010 An Industry White Paper from Technology Management Solutions Supporting Lean
Top 10 Mistakes in Data Center Operations: Operating Efficient and Effective Data Centers
Top 10 Mistakes in Data Center Operations: Operating Efficient and Effective Data White Paper 2 Revision 0 by Bob Woolley > Executive summary How can you avoid making major mistakes when operating and
Position Description
Position Description Wesley Disability Services Quality Risk & Compliance Specialist Agreement Signed Quality Risk and Compliance Specialist Signed Executive Manager, Wesley Disability Services Date Date
Mastering Microsoft Project 2013
Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals
Building Contractor Management Excellence
Building Contractor Management Excellence For several years, companies have been under relentless pressure to control costs. That is especially true of industrial and assetintensive companies, and in response,
Copyright 2013 wolfssl Inc. All rights reserved. 2
- - Copyright 2013 wolfssl Inc. All rights reserved. 2 Copyright 2013 wolfssl Inc. All rights reserved. 2 Copyright 2013 wolfssl Inc. All rights reserved. 3 Copyright 2013 wolfssl Inc. All rights reserved.
OPTIMIZING PRODUCTION
REAL WORLD SCENARIOS Volume 2 Cases 7-12 OPTIMIZING PRODUCTION SQUEEZE MORE OUT OF PRODUCTION OPTIMIZING SCHEDULING PRODUCTION FLOW IMPROVEMENTS INTEGRATED MAINTENANCE PLANNING INTEGRATED PROJECT MANAGEMENT
SAFETY and HEALTH MANAGEMENT STANDARDS
SAFETY and HEALTH STANDARDS The Verve Energy Occupational Safety and Health Management Standards have been designed to: Meet the Recognised Industry Practices & Standards and AS/NZS 4801 Table of Contents
08X540. School For Community Research and Learning 1980 Lafayette Avenue School Address: Bronx, NY 10473
NYSED/NYCDOE JOINT INTERVENTION TEAM REPORT AND RECOMMENDATIONS BEDS Code/DBN: 08X540 School Name: School For Community Research and Learning 1980 Lafayette Avenue School Address: Bronx, NY 10473 Principal:
INFORMATION MANAGED. Project Management You Can Build On. Primavera Solutions for Engineering and Construction
INFORMATION MANAGED Project Management You Can Build On Primavera Solutions for Engineering and Construction Improve Project Performance, Profitability, and Your Bottom Line Demanding owners, ineffective
Our vision is A POPULATION WITH ADEQUATE AND ACCESSIBLE QUALITY MEDICINES AND MEDICAL SUPPLIES
NATIONAL MEDICAL STORES Plot 4-12, Nsamizi Road P.O Box 16, ENTEBBE, UGANDA. JOB ADVERTISMENTS National Medical Stores is an autonomous Corporation that was established by an Act of Parliament 1993. Our
IBM Tivoli Software. Maximo Business Intelligence Work Packs. Workorder, Asset Failure, Asset and Inventory Management
IBM Tivoli Software Maximo Asset Management Version 7.5 Releases Maximo Business Intelligence Work Packs Workorder, Asset Failure, Asset and Inventory Management Revision 4 Pam Denny Maximo Report Designer/Architect
The management of the projects with MS Project
The management of the projects with MS Project Author: AgimDerguti 1 What is Microsoft Project? Microsoft Project is a project management software program developed and sold by Microsoft Designed to assist
The Automated Agent. www.agentbreakthrough.com. By Travis Olson
The Automated Agent www.agentbreakthrough.com By Travis Olson 1 Introduction: Do you want to make more money? Easy, sell more homes Selling more homes comes with more challenges. Let s face it; there is
ISEB Practitioner Certificate in IT Service Management: Specialising in Availability Management
Syllabus and Qualification Framework This qualification covers the Service Management discipline of Availability Management as described in the IT Infrastructure Library (ITIL) Service Delivery book. The
Using Predictive Analytics to Detect Contract Fraud, Waste, and Abuse Case Study from U.S. Postal Service OIG
Using Predictive Analytics to Detect Contract Fraud, Waste, and Abuse Case Study from U.S. Postal Service OIG MACPA Government & Non Profit Conference April 26, 2013 Isaiah Goodall, Director of Business