The 3 Must Dos for Maintenance Planning and Scheduling

Size: px
Start display at page:

Download "The 3 Must Dos for Maintenance Planning and Scheduling"

Transcription

1 The 3 Must Dos for Maintenance Planning and Scheduling "Simple Ideas" Presented by: Mike Gehloff The Core Problem Challenge Most maintenance staff actually work 2-4 hours a day (Effective Hours) Effective Direct work is low Lack of effective Planning Lack of effective Scheduling Inadequate Coordination Across all Departments 70-80% of equipment failures are Human-Induced Not using a torque wrench Not knowing specifications Not having the right part at the right time Improperly handling and installing bearings No repeatable, effective PM, Corrective, Lube Procedures Do any of us have real faith in our proactive maintenance approach? Wrench Time Where did the time go? Copyright 2005 Services Group

2 Planning s Goal: The Proactive Approach Identifying the parts, tools, procedures, and standards/specifications required for effective maintenance work, to increase wrench time and optimize reliability. Planning is key to the success of Precision Maintenance Lean Towards Proactive Work TRANSITION Lean Towards Proactive Work Two Avenues of Improvement: Design of the Proactive Maintenance Plan Execution of the Proactive Maintenance Plan TRANSITION Copyright 2005 Services Group

3 Terminology Planning: Performing research and determining the requirements of a task to be performed in the future WHAT, HOW, WHERE, WHY, WHEN, WHO Scheduling: The act of aligning available resources to the work backlog and placing it on the calendar WHEN, WHO Coordination: Reacting to emergencies and making adjustments to the schedule in real time based on priorities Must Do #1 PLANNERS FOCUS ON THE FUTURE A Maintenance Planner Does Not Plan Emergency Work Expedite Parts Schedule Work Schedule Routine Activities Act as a Relief Supervisor Maintain a Storeroom Act as a Clerk Perform the Buyer Function Pick up the tools and fill in for emergencies Engineer (Design) Jobs Not the Plant Engineer or the Plant Engineer s Assistant Copyright 2005 Services Group

4 Work Management - Core Beliefs Work Management Core Beliefs 1. Planners remain focused on FUTURE WORK. 2. Planners do not chase parts for jobs in progress. 3. Supervisors and crew leads handle the current day s work and problems. 4. Faced with the choice, a line supervisor must concentrate on today s problems rather than work on future (even tomorrow s) activities. 5. There is no such thing as a perfectly planned job continuous improvement is a must. 6. All stakeholders must share the same priorities active communication on priorities is an absolute requirement. Planners Must Add Value Planners battle and eliminate losses and delays from maintenance and its related activities The planner s efforts are measured by: Feedback on the completed work orders (job plan quality) The size of the Waiting for Schedule backlog (measured in weeks 2 weeks minimum) Example Backlog Calculation Total Required Man-Hours (Ready Status) on all Work Orders in the System = 1000 hours 7 Mechanics 3 Electricians 1 Planner 1 Maintenance Supervisor 40 hours per week for each resource Total Available Man Hours = 400 hrs/week Total Backlog = 2.5 weeks Copyright 2005 Services Group

5 Must Do #2 THE ENTIRE ORGANIZATION MUST PARTICIPATE Roles and Responsibilities Maintenance Planner Develops new Job Plans maintains Job Plan Library Maintains accurate equipment specifications, info, and parts lists Communicates with: Production Operators Supervisors Manages the Ready Backlog keeps the pipeline full Provide a good craftsperson with enough information to reduce the incidence of delay due to craftspeople seeking information or instructions Scheduling Team Consider production requirements, work priorities, and budgets when establishing the work schedule Actively communicate priorities at the Scheduling Meeting develop common priorities based on needs Review the Backlog and publish a Weekly Schedule Schedule for 100% Usage of Available Resources when developing the schedule Actively communicate the schedule to all affected resources Coordinator Assign resources and execute to the published schedule React to emergencies and make spot changes to the schedule Ensure feedback is provided to both the Planners and the Scheduling Team to maximize efficiency in the future Communicate changing priorities back to the Scheduling Team on a daily basis RACI Planning and Scheduling Roles and Responsibilities R = Responsible A = Accountable (only 1) C = Consult I = Inform Identify Work Document in CMMS Develop the Weekly Work Schedule Develop Job Plans Monitor Backlog and React Accordingly Communicate Current Schedule Assign Resources to Jobs Order Specialty Parts React to Daily Schedule Changes Plan Emergency Work Maintain Accurate Equipment Specifications and Parts List Maintain Performance KPIs Develop a Craft Skills Training Plan Ensure the Maximum Use of all Available Resources Visit Craftspeople on the Job and Give them Work Instructions Formally Report Findings from Work on Work Orders - Feedback Planner Craftsperson Maintenance Supervisor Operators Operations Supervisor Stores/Procurement Copyright 2005 Services Group

6 Emergency Work Protocol Emergencies are unavoidable with discipline, we can reduce the frequency and impact of these events We must not try to plan for emergencies, but rather allow the daily coordination function (front line supervision) to handle these events In order to prevent abuses, we must define a protocol for emergencies What qualifies? What does not? Who decides? Who responds? On major emergency jobs, a work order should still be completed in order to document history and parts Must #3 COMMUNICATE ACTIVELY NOT PASSIVELY Routine Schedule Development Activities to Develop Next Week s Schedule DAILY REVIEW and COORDINATION of THIS WEEK S SCHEDULE Copyright 2005 Services Group

7 Documenting the Outage Schedule BAD BETTER BEST Outage Plan: Outage Preparation Matrix The War Room Contact List Actual Status Update Key 28 Job Plan Gantt Charts Outage Preparation Status Matrix Copyright 2005 Services Group

8 Visual Management of Progress Recap Must #1: Planners Focus on the Future Must #2: The Entire Organization Must Participate Must #3: Communicate Actively Not Passively Questions? Mike Gehloff GP Copyright 2005 Services Group

Overview of EAM Services. A Fully Integrated Global EAM Service Provider

Overview of EAM Services. A Fully Integrated Global EAM Service Provider A Fully Integrated Global EAM Service Provider Table of Contents Strategy & Process Services Overview... p. 3 Asset Reliability Services Overview... p. 4 Systems & Technology Services Overview... p. 7

More information

Increase Equipment Uptime Through Robust Enterprise Asset Management. For the Upstream, Midstream & Downstream Sectors of the Oil & Gas Industry

Increase Equipment Uptime Through Robust Enterprise Asset Management. For the Upstream, Midstream & Downstream Sectors of the Oil & Gas Industry Increase Equipment Uptime Through Robust Enterprise Asset Management For the Upstream, Midstream & Downstream Sectors of the Oil & Gas Industry The Oil & Gas industry is challenged with effectively maximizing

More information

Building a Foundation for Maintenance & Reliability "Best Practice" Work Processes in EAM

Building a Foundation for Maintenance & Reliability Best Practice Work Processes in EAM Building a Foundation for Maintenance & Reliability "Best Practice" Work Processes in EAM Author: Dave Abecunas, CMRP Presented as IPSED: Back to Basics at the 2008 Reliability and EAM Summit Table of

More information

Work Execution Management Training and Coaching Services

Work Execution Management Training and Coaching Services Work Execution Management Training and Coaching Services www.gpallied.com The Need Now, more than ever, your maintenance team is expected to increase effectiveness and performance with fewer members. This

More information

Determining the Optimum Staffing Levels for a Maintenance and Reliability Department

Determining the Optimum Staffing Levels for a Maintenance and Reliability Department An Allied Group White Paper 4200 Faber Place Drive Charleston, SC 29405 843.414.5760 www.alliedreliabilitygroup.com Determining the Optimum Staffing Levels for a Maintenance and Department By: Kate Kerrigan,

More information

Asset Management Best Practices

Asset Management Best Practices Asset Management Best Practices Summary of a Five-Part Series on Maintenance Best Practices A series of white papers dedicated to Asset Management Best Practices. Maximize Asset Performance. Improve Operating

More information

COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEMS. Dr. Abdul-Mohsen Al-Hammad. I. Maintenance Management Systems

COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEMS. Dr. Abdul-Mohsen Al-Hammad. I. Maintenance Management Systems COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEMS By Dr. Abdul-Mohsen Al-Hammad Outline I. Maintenance Management Systems II. Computerized Maintenance Management System. 2 1 I. Maintenance Management Systems

More information

A S S E T I N T E G R I T Y I N T E L L I G E N C E

A S S E T I N T E G R I T Y I N T E L L I G E N C E ASSET INTEGRITY INTELLIGENCE Fe atured Article BEST PRACTICES OF MAINTENANCE PLANNING & SCHEDULING MATT MIDAS, GenesisSolutions, An ABS Group Company VOLUME 21, ISSUE 2 MARCH APRIL 2015 BEST PRACTICES

More information

Lean Silver Certification Blueprint

Lean Silver Certification Blueprint The Lean Certification Blueprint provides additional useful information beyond the Body of Knowledge. The Body of Knowledge specifies the competencies, topics, and subtopics required by different types

More information

Reliability Solutions

Reliability Solutions Reliability Solutions Developing a World-Class Approach to Lubrication Lubrication is the cornerstone of an effective reliability-driven asset management program. A major bearing manufacturer has indicated

More information

QAD Enterprise Asset Management BI Metrics Demonstration Guide. May 2015 BI 3.11

QAD Enterprise Asset Management BI Metrics Demonstration Guide. May 2015 BI 3.11 QAD Enterprise Asset Management BI Metrics Demonstration Guide May 2015 BI 3.11 Overview This demonstration focuses on one aspect of QAD Enterprise Asset Management Business Intelligence Metrics and shows

More information

IBM Maximo Adapter for Primavera

IBM Maximo Adapter for Primavera IBM Maximo Tivoli Lab Services IBM Maximo Adapter for Primavera April 2008 Primavera partnership history Tactical partnership with custom integrations as early as 2000 Formalized integrations supporting

More information

The Leading Reward of Maintenance Management

The Leading Reward of Maintenance Management Halting the Cycle of Break & Fix: The Leading Reward of Maintenance Management Eric Hancock Practice Leader for Operations & Asset Management Jacobs Engineering Group Inc. Best Maintenance Strategies t

More information

Total Productive Maintenance. Implementing TPM in Baxter Aibonito

Total Productive Maintenance. Implementing TPM in Baxter Aibonito Total Productive Maintenance Implementing TPM in Baxter Aibonito Overview TPM definition, elements overview, tools & expectations Continuous TPM improvement metric OEE definition & calculation Example

More information

Maximizing Our CMMS Effectiveness

Maximizing Our CMMS Effectiveness Maximizing Our CMMS Effectiveness Why be here? Learn about software that is available for facilities condition assessment and capital budget development Learn about some CMMS speed bumps Learn about our

More information

The Role of CMMS. A white paper on the selection and implementation of computerized maintenance management systems. Prepared by:

The Role of CMMS. A white paper on the selection and implementation of computerized maintenance management systems. Prepared by: A white paper on the selection and implementation of computerized maintenance management systems Prepared by: Mike Crain Manager, Industrial Technologies Northern Digital, Inc. [email protected]

More information

Maintenance Planning and Scheduling Handbook

Maintenance Planning and Scheduling Handbook Maintenance Planning and Scheduling Handbook Third Edition Doc Palmer Me Graw Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New Delhi San Juan Seoul Singapore Sydney Toronto

More information

21ST CENTURY PROCESS MANAGEMENT USING SPC BASED MANUFACTURING ANALYTICS

21ST CENTURY PROCESS MANAGEMENT USING SPC BASED MANUFACTURING ANALYTICS WHITE PAPER 21ST CENTURY PROCESS MANAGEMENT USING SPC BASED MANUFACTURING ANALYTICS By Jeffrey L. Cawley, Vice President Market Development, Northwest Analytics Inc. Actively using SPC and Manufacturing

More information

HOW TO ACHIEVE OPERATIONAL EXCELLENCE THROUGH ENTERPRISE ASSET MANAGEMENT

HOW TO ACHIEVE OPERATIONAL EXCELLENCE THROUGH ENTERPRISE ASSET MANAGEMENT HOW TO ACHIEVE OPERATIONAL EXCELLENCE THROUGH ENTERPRISE ASSET MANAGEMENT Optimize Assets to Move from Reactive to Predictive 919-835-0810 www.prometheusgroup.com Operational Excellence has been defined

More information

PEOPLESOFT MAINTENANCE MANAGEMENT

PEOPLESOFT MAINTENANCE MANAGEMENT PEOPLESOFT MAINTENANCE MANAGEMENT KEY BENEFITS Streamline Maintenance Operations Manage Full Asset Lifecycle Lower Total Cost of Ownership Oracle s PeopleSoft Maintenance Management completes the Enterprise

More information

CSI study. A white paper from the itsmf Finland Continual Service Improvement Special Interest Group

CSI study. A white paper from the itsmf Finland Continual Service Improvement Special Interest Group CSI study Continual Service Improvement (CSI) study to the members of itsmf Finland A white paper from the itsmf Finland Continual Service Improvement Special Interest Group Date: April 2014 Authors: Anne

More information

Turnaround and Maintenance Services

Turnaround and Maintenance Services Turnaround and Maintenance Services Reliably providing quality turnaround and maintenance services safely Matrix Safe a cultural mindset For us, safety is more than a core value. It s a way of life. We

More information

PROJECT MANAGEMENT FOR NON-PROJECT MANAGERS

PROJECT MANAGEMENT FOR NON-PROJECT MANAGERS PROJECT MANAGEMENT FOR NON-PROJECT MANAGERS NADC PTAC 2929 3 rd Ave., N., Suite 300 Billings, MT 59101 P. (406) 259-3804 F. (406) 259-4569 ww.nadc-nabn.org HIGHLINER CONSULTING GROUP, LLC. 255 E. Fireweed

More information

SAFER Patient Flow Bundle

SAFER Patient Flow Bundle SAFER Patient Flow Bundle The patient flow bundle is similar to a clinical care bundle. It is a combined set of simple rules for adult inpatient wards to improve patient flow and prevent unnecessary waiting

More information

Outsourcing Maintenance: A Plan for Success

Outsourcing Maintenance: A Plan for Success Outsourcing Maintenance: A Plan for Success By Advanced Technology Services Because maintenance is usually determined not to be a core competency, outsourcing allows management to focus its scarce resources

More information

Agile Development Overview

Agile Development Overview Presented by Jennifer Bleen, PMP Project Services Practice of Cardinal Solutions Group, Inc. Contact: Agile Manifesto We are uncovering better ways of developing software by doing it and helping others

More information

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft

More information

Implementing an Information Governance Program CIGP Installment 2: Building Your IG Roadmap by Rick Wilson, Sherpa Software

Implementing an Information Governance Program CIGP Installment 2: Building Your IG Roadmap by Rick Wilson, Sherpa Software Implementing an Information Governance Program CIGP Installment 2: Building Your IG Roadmap by Rick Wilson, Sherpa Software www.sherpasoftware.com 1.800.255.5155 @sherpasoftware [email protected]

More information

Business Challenges. Customer retention and new customer acquisition (customer relationship management)

Business Challenges. Customer retention and new customer acquisition (customer relationship management) Align and Optimize Workflows with Lean Dan Marino Marino Associates, LLC Strategic and tactical planning Information systems integration Customer retention and new customer acquisition (customer relationship

More information

Sample Maintenance Audit Report

Sample Maintenance Audit Report Sample Maintenance Audit Report NOTES: 1.0 This sample maintenance audit report and contents is indicative of the coverage and approach taken by Lifetime Reliability Solutions Consultants when performing

More information

Achieve greater efficiency in asset management by managing all your asset types on a single platform.

Achieve greater efficiency in asset management by managing all your asset types on a single platform. Asset solutions To support your business objectives Achieve greater efficiency in asset by managing all your asset types on a single platform. Obtain an entirely new level of asset awareness Every company

More information

Configuring the Optimization Server

Configuring the Optimization Server Scheduler 7.5.2 Optimization Sr. Design Architects - Lori Pilgrim and Brian Downey Optimization Engine in Scheduler What-If Analysis 2 1 Architecture Application Server Application Server Maximo ODME Scheduler

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

How project management software can smooth the way

How project management software can smooth the way How project management software can smooth the way By Michael V. Brown New Standard Institute The most demanding call on maintenance resources comes when a plant or facility is shut down for an extended

More information

Priori ty ... ... ...

Priori ty ... ... ... .Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared

More information

6 Reasons Why Outsourcing Equipment Maintenance Is Your Best Hedge In A Down Economy

6 Reasons Why Outsourcing Equipment Maintenance Is Your Best Hedge In A Down Economy 6 Reasons Why Outsourcing Equipment Maintenance Is Your Best Hedge In A Down Economy The decision to outsource equipment maintenance during times of economic boom is based on the desire of a company to

More information

Root Cause Analysis Concepts and Best Practices for IT Problem Managers

Root Cause Analysis Concepts and Best Practices for IT Problem Managers Root Cause Analysis Concepts and Best Practices for IT Problem Managers By Mark Hall, Apollo RCA Instructor & Investigator A version of this article was featured in the April 2010 issue of Industrial Engineer

More information

Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time.

Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time. T47400A, page 1 Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time. DUTIES Serves as the planner/scheduler for the Utilities

More information

Oracle Utilities Work and Asset Management

Oracle Utilities Work and Asset Management Oracle Utilities Work and Asset Management User Guide Release 2.1.0 E61870-01 May 2015 Oracle Utilities Work and Asset Management User Guide Release 2.1.0 E61870-01 May 2015 Documentation build: 4.30.2015

More information

Achieve greater efficiency in asset management by managing all your asset types on a single platform.

Achieve greater efficiency in asset management by managing all your asset types on a single platform. Asset solutions To support your business objectives Achieve greater efficiency in asset by managing all your asset types on a single platform. Obtain an entirely new level of asset awareness Every company

More information

Starting a new Oil Analysis Program Burden or Benefit?

Starting a new Oil Analysis Program Burden or Benefit? Starting a new Oil Analysis Program Burden or Benefit? Introduction So someone in senior management has finally realized the drain on the bottom line of your company caused by reactive maintenance in the

More information

Executive Summary. This procedure supports Priority #4 of the Board Improvement Plan which states:

Executive Summary. This procedure supports Priority #4 of the Board Improvement Plan which states: Executive Summary Policy and Procedure #409.0, Licensed Child Care in Schools Procedure #409.1, Security for Licensed Child Care and Before and After Care Programs in Schools Application Policy and Procedure

More information

It s Time for Maintenance 2.0

It s Time for Maintenance 2.0 It s Time for Maintenance 2.0 NOVEMBER 2010 Table of Contents Executive Summary... 3 Why Current Systems Fall Short... 4 It s Time for Maintenance 2.0... 5 Advantages of Maintenance 2.0... 6 Synchronize

More information

Essential Elements for Any Successful Project

Essential Elements for Any Successful Project In this chapter Learn what comprises a successful project Understand the common characteristics of troubled projects Review the common characteristics of successful projects Learn which tools are indispensable

More information

Well Service Manager Planning, Scheduling and Evaluation Software

Well Service Manager Planning, Scheduling and Evaluation Software Well Service Manager Planning, Scheduling and Evaluation Software Efficiently gather and store well information for effectively managing all well activities, including planning versus actual cost management.

More information

50 Questions before computerization

50 Questions before computerization 50 Questions before computerization Before computerization, as an organization, ask yourself: 1. Is there enough time, money and interest to involve all levels within the maintenance department and other

More information

Useful Key Performance Indicators for Maintenance

Useful Key Performance Indicators for Maintenance PO BOX 2091, ROSSMOYNE, WA, 6148 AUSTRALIA Phone: Fax: Email: Website: +61 (0) 402 731 563 +61 (8) 9457 8642 [email protected] www.lifetime-reliability.com Abstract Useful Key Performance Indicators

More information

The Art of the Possible Scheduling Options in SAP. Mark W. Scott Vesta Partners, LLC

The Art of the Possible Scheduling Options in SAP. Mark W. Scott Vesta Partners, LLC The Art of the Possible Scheduling Options in SAP Mark W. Scott Vesta Partners, LLC The Tool and the Challenge The Parts The Options The Results Scheduling in SAP What I ll cover: The Parts The Options

More information

Technique 9.16 Metrics and Key Performance Indicators Gunter Wagner

Technique 9.16 Metrics and Key Performance Indicators Gunter Wagner Technique 9.16 Metrics and Key Performance Indicators Gunter Wagner Cover this area with a picture related to your presentation. It can be humorous. Make sure you look at the Notes Pages for more information

More information

Lean and Six Sigma Healthcare Fad or Reality. Vince D Mello President

Lean and Six Sigma Healthcare Fad or Reality. Vince D Mello President Lean and Six Sigma Healthcare Fad or Reality Vince D Mello President TODAY S DISCUSSION About Lean Methodologies Application benefits and outcomes About Six Sigma Key learning's QUALITY FUNDAMENTALS Function

More information

Digital Marketing Specialist

Digital Marketing Specialist Digital Marketing Specialist Financial Controller Our Vision To be the best company our employees ever work for, the best bank our customers ever do business with and the best investment for our shareholder.

More information

GE Healthcare. Transforming radiology with actionable intelligence. *Trademark of General Electric Company

GE Healthcare. Transforming radiology with actionable intelligence. *Trademark of General Electric Company GE Healthcare Transforming radiology with actionable intelligence *Trademark of General Electric Company A roadmap for optimized radiology workflows As radiology departments transform themselves in this

More information

Agile Project Management and the Real World. Emily Lynema DLF Fall 2010 November 1, 2010

Agile Project Management and the Real World. Emily Lynema DLF Fall 2010 November 1, 2010 Agile Project Management and the Real World Emily Lynema DLF Fall 2010 November 1, 2010 Outline Why care about project management? Traditional vs. Agile What is Agile? What is Scrum? Agile case study:

More information

4. Maintenance and Materials Management

4. Maintenance and Materials Management The Superintendent of Operations has various oversight responsibilities that impair his ability to effectively manage maintenance activities within the Project Operations Section. This impairment manifests

More information

Table II:8 Overview of the Management System of an Organization

Table II:8 Overview of the Management System of an Organization Table II:8 Overview of the Management System of an Organization Inputs: people, money, equipment, facilities, supplies, people's ideas, people's time, etc. System Loop Major Functions Comments Planning

More information

How To Increase Employee Productivity And Increase Wrench Time At An Oil Refinery

How To Increase Employee Productivity And Increase Wrench Time At An Oil Refinery Employee Productivity Improvement Strategies In Oil Refinery Environments Automated Workforce Management Helps Reduce Maintenance Backlogs, Increase Safety Compliance and Improve Profitability CONTENTS

More information

CREATING A THIRD EDITION DAVID MANN

CREATING A THIRD EDITION DAVID MANN CREATING A LEAN CULTURE Tools to Sustain Lean Conversions THIRD EDITION DAVID MANN CRC Press Taylor & Francis Croup Boca Raton London New York CRC Press is an imprint of the Taylor St Francis Group, an

More information

Supporting Lean Maintenance

Supporting Lean Maintenance Supporting Lean Maintenance Combining Best Practices with Technology for Superior Results TECHNOLOGY MANAGEMENT SOLUTIONS 2010 An Industry White Paper from Technology Management Solutions Supporting Lean

More information

Top 10 Mistakes in Data Center Operations: Operating Efficient and Effective Data Centers

Top 10 Mistakes in Data Center Operations: Operating Efficient and Effective Data Centers Top 10 Mistakes in Data Center Operations: Operating Efficient and Effective Data White Paper 2 Revision 0 by Bob Woolley > Executive summary How can you avoid making major mistakes when operating and

More information

Position Description

Position Description Position Description Wesley Disability Services Quality Risk & Compliance Specialist Agreement Signed Quality Risk and Compliance Specialist Signed Executive Manager, Wesley Disability Services Date Date

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals

More information

Building Contractor Management Excellence

Building Contractor Management Excellence Building Contractor Management Excellence For several years, companies have been under relentless pressure to control costs. That is especially true of industrial and assetintensive companies, and in response,

More information

Copyright 2013 wolfssl Inc. All rights reserved. 2

Copyright 2013 wolfssl Inc. All rights reserved. 2 - - Copyright 2013 wolfssl Inc. All rights reserved. 2 Copyright 2013 wolfssl Inc. All rights reserved. 2 Copyright 2013 wolfssl Inc. All rights reserved. 3 Copyright 2013 wolfssl Inc. All rights reserved.

More information

OPTIMIZING PRODUCTION

OPTIMIZING PRODUCTION REAL WORLD SCENARIOS Volume 2 Cases 7-12 OPTIMIZING PRODUCTION SQUEEZE MORE OUT OF PRODUCTION OPTIMIZING SCHEDULING PRODUCTION FLOW IMPROVEMENTS INTEGRATED MAINTENANCE PLANNING INTEGRATED PROJECT MANAGEMENT

More information

SAFETY and HEALTH MANAGEMENT STANDARDS

SAFETY and HEALTH MANAGEMENT STANDARDS SAFETY and HEALTH STANDARDS The Verve Energy Occupational Safety and Health Management Standards have been designed to: Meet the Recognised Industry Practices & Standards and AS/NZS 4801 Table of Contents

More information

08X540. School For Community Research and Learning 1980 Lafayette Avenue School Address: Bronx, NY 10473

08X540. School For Community Research and Learning 1980 Lafayette Avenue School Address: Bronx, NY 10473 NYSED/NYCDOE JOINT INTERVENTION TEAM REPORT AND RECOMMENDATIONS BEDS Code/DBN: 08X540 School Name: School For Community Research and Learning 1980 Lafayette Avenue School Address: Bronx, NY 10473 Principal:

More information

INFORMATION MANAGED. Project Management You Can Build On. Primavera Solutions for Engineering and Construction

INFORMATION MANAGED. Project Management You Can Build On. Primavera Solutions for Engineering and Construction INFORMATION MANAGED Project Management You Can Build On Primavera Solutions for Engineering and Construction Improve Project Performance, Profitability, and Your Bottom Line Demanding owners, ineffective

More information

Our vision is A POPULATION WITH ADEQUATE AND ACCESSIBLE QUALITY MEDICINES AND MEDICAL SUPPLIES

Our vision is A POPULATION WITH ADEQUATE AND ACCESSIBLE QUALITY MEDICINES AND MEDICAL SUPPLIES NATIONAL MEDICAL STORES Plot 4-12, Nsamizi Road P.O Box 16, ENTEBBE, UGANDA. JOB ADVERTISMENTS National Medical Stores is an autonomous Corporation that was established by an Act of Parliament 1993. Our

More information

IBM Tivoli Software. Maximo Business Intelligence Work Packs. Workorder, Asset Failure, Asset and Inventory Management

IBM Tivoli Software. Maximo Business Intelligence Work Packs. Workorder, Asset Failure, Asset and Inventory Management IBM Tivoli Software Maximo Asset Management Version 7.5 Releases Maximo Business Intelligence Work Packs Workorder, Asset Failure, Asset and Inventory Management Revision 4 Pam Denny Maximo Report Designer/Architect

More information

The management of the projects with MS Project

The management of the projects with MS Project The management of the projects with MS Project Author: AgimDerguti 1 What is Microsoft Project? Microsoft Project is a project management software program developed and sold by Microsoft Designed to assist

More information

The Automated Agent. www.agentbreakthrough.com. By Travis Olson

The Automated Agent. www.agentbreakthrough.com. By Travis Olson The Automated Agent www.agentbreakthrough.com By Travis Olson 1 Introduction: Do you want to make more money? Easy, sell more homes Selling more homes comes with more challenges. Let s face it; there is

More information

ISEB Practitioner Certificate in IT Service Management: Specialising in Availability Management

ISEB Practitioner Certificate in IT Service Management: Specialising in Availability Management Syllabus and Qualification Framework This qualification covers the Service Management discipline of Availability Management as described in the IT Infrastructure Library (ITIL) Service Delivery book. The

More information

Using Predictive Analytics to Detect Contract Fraud, Waste, and Abuse Case Study from U.S. Postal Service OIG

Using Predictive Analytics to Detect Contract Fraud, Waste, and Abuse Case Study from U.S. Postal Service OIG Using Predictive Analytics to Detect Contract Fraud, Waste, and Abuse Case Study from U.S. Postal Service OIG MACPA Government & Non Profit Conference April 26, 2013 Isaiah Goodall, Director of Business

More information