1 Clustering and scheduling maintenance tasks over time Per Kreuger SICS Technical Report T2008:09 Abstract We report results on a maintenance scheduling problem. The problem consists of allocating maintenance task instances to and scheduling the performances of a suitable number of maintenance packages. The number of maintenance packages is not xed, nor is, in general, the dates or durations of their performances. A constraint programming (CP) model and solver for the problem is presented together with preliminary computational results. Keywords Maintenance scheduling, resource allocation, task clustering This work was funded by the Butler project run at SICS ISSN ISRN: SICS-T2008/09-SE
2 1 Introduction This report describes a modelling experiment performed to investigate the feasibility of using constraint programming techniques to solve the problem of allocating maintenance task instances to and scheduling the performances of a suitable number of maintenance packages. The number of maintenance packages is not xed, nor is, in general, the dates or durations of their performances but we may want to avoid scheduling the performance of maintenance packages so that they overlap in time. This type of problem occurs in many industrial maintenance problems where individual components belonging to a piece of equipment has to be serviced at regular intervals and where the whole piece of equipment has to be taken out of normal service during maintenance occasions. We do not in this work address the problem of deciding the ideal separation between instances of the tasks but regard these as xed and furthermore restrict the problem as follows: Individual instances of tasks have a xed duration and are performed at more or less regular intervals. Several such tasks with varying characteristic intervals exist in general but tasks from several classes can and usually are allocated to the same maintenance package. We restrict our analysis to the case where individual task instances may be performed in parallel during a the performance of a maintenance package so that its duration can be assumed to have the same duration as the longest task instance allocated to it. The regularity of the instances particular task is not necessarily completely xed. An individual instances may e.g. be performed before the full separation interval is complete. The instance may also be delayed with respect to the ideal separation within its task but costs are associated with both of these cases, usually a higher cost for the second type of situation. Cost are also associated with each maintenance package, and there may be (typically yearly) periods when scheduling maintenance occasions are more (or less) costly. This means that for a particular allocation of task instances to maintenance packages and a particular schedule of package performances, there are costs associated with both the scheduled occasions and with each tasks in which the sequence of instances deviate more or less from an ideal (usually equally spaced) schedule. We assume that in general, each task instance has to be allocated to exactly one maintenance package and that the minimum number of task instances allocated to a package is one. This means that the number of packages may vary from one to up to the number of individual task instances. There is however, a trade-o between performing the instances of a task at ideal separation intervals which may require to many individual packages and of minimising the number of package performances. 2
3 2 Problem model and parametrisation Let the number of task instances be n and let each task be characterised by the duration of its instances and the ideal temporal separation between application of its instances. The instances themselves are explicitly represented and characterised by an unique index n and earliest and latest start date. To encode the allocation problem we associate with each instance, a package variable. When bound, this variable denotes the lowest index of any task instance allocated to the same package. To solve the problem, we post precedence constraints on instances of each task and constrain the package variable of each instance to be less than or equal to the index of the instance itself. Then, for each pair of instances, equate the equality of their package indexes with that of their start times. Identify each package start time with that of the instances allocated to it, let the duration of the task be their maximum and optionally post scheduling constraints on the packages. To model the cost of a task, sum over the individual costs of the deviation of the scheduled interval between two consecutive instances of the task and that of the ideal separation. Count furthermore the sum of the cost of scheduling each package by summing over each pair of instances allocated to it and count costs only for the instances who's index coincide with their package allocation which will be true for only one instance per package. A redundant condition that could possibly improve propagation and speed up search would be to associate an additional variable denoting a sequence within the package. These variables could be constrained to be pairwise dierent which is an other way to formulate the partitioning condition. 3 Computational results 3.1 Problem instance The basic model outlined above was assessed by using it to encode an example problem consisting of 8 tasks with ideal separations between 4 and 52 weeks and enough instances to cover a total of 5 years. The total number of task instances considered were 193. The task duration was set to one week for tasks with separation less than 16 weeks and varying from 3 to 4 weeks for the those with longer instance separations. The start time window was set to be equal to two times the ideal separation. The eect of this type of formulation is to allow each task instance to start at the earliest at the ideal moment of its predecessor and at the latest at the ideal start of its successor. The cost function of performing an instances at non ideal separations was scaled so that delays was penalised three time more than making it early. The cost of the package assignment is rst of all determined by the number 3
4 of individual packages used and secondly by the package schedule using dierent weights of packages scheduled during certain times of the year. The units and relative weights of the dierent cost components is probably not that important at this stage of the work, but the task cost is given in weeks (counting one week delay as three) and the package cost either 10/package or 110/package depending on the time of year. Although this is a completely articial example it appears to correspond fairly well to some real instances we have also encountered in other projects. 3.2 Search heuristics A number of search heuristics were investigated of which only the one that appears to be most robust will be described here. To nd a feasible solution, rst enumerate the package variables of the task instances. This will x the assignment of task instances to packages and constrain the start times of task instances assigned to the same package to coincide. For each such partial solution, nd the the optimal assignment of the instance separations of each individual task. Finally decide an arbitrary assignment of any start times that have not already been xed. At this point, the cost was always determined for the particular case we considered, in more complex cases it may make sense to use an optimising search at this step as well. Several minor modications of this general scheme were evaluated, using e.g. step/bisect and or using only the task cost for optimising the instance separations. To optimise the total cost, do a branch and bound search over the alternative assignments of task instances to packages. We used two dierent timeouts for the two optimising steps in the search, one for the inner loop, minimising the instance separations and an other for the outer loop that searches over the assignments. Varying these parameters gave slightly dierent results, e.g allowing a maximum of 5 seconds for each gave a solution with 65 separate packages, a task cost of 395 and a package schedule cost of 5400, while allowing a maximum 20 seconds for each iteration of the inner loop and 60 for the outer produced the same number of packages but with a slightly less costly schedule (5300) but an increased task cost (443). 4 Summary and conclusion We have formulated a combined allocation and scheduling model for a typical industrial maintenance problem. The model has been implemented and evaluated on an articial but fairly representative example and a number of dierent search heuristics has been tried out and the most promising one presented. The solver seems to be rather robust w.r.t. the number maintenance packages chosen, which was rather surprising, given the very general formulation. This may however be an an artifact of the particular example chosen and the way task instance star time windows were set. 4
5 It seems reasonable to expect that the model could be adapted to more realistic cases even though the scalability of the approach may have to be reevaluated for other cost functions and larger cases. Restricting the number of packages could be an approach to better scalability. 5
Scheduling Shop Scheduling. Tim Nieberg
Scheduling Shop Scheduling Tim Nieberg Shop models: General Introduction Remark: Consider non preemptive problems with regular objectives Notation Shop Problems: m machines, n jobs 1,..., n operations
Abstract Title: Planned Preemption for Flexible Resource Constrained Project Scheduling
Abstract number: 015-0551 Abstract Title: Planned Preemption for Flexible Resource Constrained Project Scheduling Karuna Jain and Kanchan Joshi Shailesh J. Mehta School of Management, Indian Institute
A-1. Chapter 1. Project planning. Chapter 1. Festo Didactic Mechatronics
A-1 Project planning A-2 Mechatronics specialists are responsible for the complete service life of an industrial machine, from the initial planning phase through to its disassembly and disposal. This cycle
A hybrid approach for solving real-world nurse rostering problems
Presentation at CP 2011: A hybrid approach for solving real-world nurse rostering problems Martin Stølevik ([email protected]) Tomas Eric Nordlander ([email protected]) Atle Riise ([email protected])
Improve Net Present Value using cash flow weight
2011 2 nd International Conference on Construction and Project Management IPEDR vol.15 (2011) (2011) IACSIT Press, Singapore Improve Net Present Value using cash flow weight Vacharee Tantisuvanichkul 1
The Rolling Stock Recovery Problem. Literature review. Julie Jespersen Groth *α, Jesper Larsen β and Jens Clausen *γ
The Rolling Stock Recovery Problem Julie Jespersen Groth *α, Jesper Larsen β and Jens Clausen *γ DTU Management Engineering, The Technical University of Denmark, Produktionstorvet, DTU Building 424, 2800
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
Integrating Benders decomposition within Constraint Programming
Integrating Benders decomposition within Constraint Programming Hadrien Cambazard, Narendra Jussien email: {hcambaza,jussien}@emn.fr École des Mines de Nantes, LINA CNRS FRE 2729 4 rue Alfred Kastler BP
14TH INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN 19-21 AUGUST 2003
14TH INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN 19-21 AUGUST 2003 A CASE STUDY OF THE IMPACTS OF PRELIMINARY DESIGN DATA EXCHANGE ON NETWORKED PRODUCT DEVELOPMENT PROJECT CONTROLLABILITY Jukka Borgman,
A Constraint Programming based Column Generation Approach to Nurse Rostering Problems
Abstract A Constraint Programming based Column Generation Approach to Nurse Rostering Problems Fang He and Rong Qu The Automated Scheduling, Optimisation and Planning (ASAP) Group School of Computer Science,
A Constraint Programming Application for Rotating Workforce Scheduling
A Constraint Programming Application for Rotating Workforce Scheduling Markus Triska and Nysret Musliu Database and Artificial Intelligence Group Vienna University of Technology {triska,musliu}@dbai.tuwien.ac.at
A Computer Application for Scheduling in MS Project
Comput. Sci. Appl. Volume 1, Number 5, 2014, pp. 309-318 Received: July 18, 2014; Published: November 25, 2014 Computer Science and Applications www.ethanpublishing.com Anabela Tereso, André Guedes and
A hierarchical multicriteria routing model with traffic splitting for MPLS networks
A hierarchical multicriteria routing model with traffic splitting for MPLS networks João Clímaco, José Craveirinha, Marta Pascoal jclimaco@inesccpt, jcrav@deecucpt, marta@matucpt University of Coimbra
Scheduling Single Machine Scheduling. Tim Nieberg
Scheduling Single Machine Scheduling Tim Nieberg Single machine models Observation: for non-preemptive problems and regular objectives, a sequence in which the jobs are processed is sufficient to describe
A CP Scheduler for High-Performance Computers
A CP Scheduler for High-Performance Computers Thomas Bridi, Michele Lombardi, Andrea Bartolini, Luca Benini, and Michela Milano {thomas.bridi,michele.lombardi2,a.bartolini,luca.benini,michela.milano}@
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
Resources Management
Resources Management. Introduction s we have seen in network scheduling, the basic inputs to criticalpath analysis are the individual project activities, their durations, and their dependency relationships.
Real Time Scheduling Basic Concepts. Radek Pelánek
Real Time Scheduling Basic Concepts Radek Pelánek Basic Elements Model of RT System abstraction focus only on timing constraints idealization (e.g., zero switching time) Basic Elements Basic Notions task
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule
Optimal Scheduling for Dependent Details Processing Using MS Excel Solver
BULGARIAN ACADEMY OF SCIENCES CYBERNETICS AND INFORMATION TECHNOLOGIES Volume 8, No 2 Sofia 2008 Optimal Scheduling for Dependent Details Processing Using MS Excel Solver Daniela Borissova Institute of
Interactive Timetabling
Interactive Timetabling Tomáš Müller, Roman Barták * Charles University Department of Theoretical Computer Science Malostranské náměstí 2/25, Praha 1, Czech Republic [email protected] [email protected]
Chapter 3 Managing the Information Systems (IS) Project
Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project
8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
Single machine models: Maximum Lateness -12- Approximation ratio for EDD for problem 1 r j,d j < 0 L max. structure of a schedule Q...
Lecture 4 Scheduling 1 Single machine models: Maximum Lateness -12- Approximation ratio for EDD for problem 1 r j,d j < 0 L max structure of a schedule 0 Q 1100 11 00 11 000 111 0 0 1 1 00 11 00 11 00
Introduction. Real World Planning. Planning with Time. Time 15/11/2012. COMP219: Artificial Intelligence. COMP219: Artificial Intelligence
COMP219: Artificial Intelligence COMP219: Artificial Intelligence Dr. Annabel Latham Room 2.05 Ashton Building Department of Computer Science University of Liverpool Lecture 26: Real World Planning: Scheduling
R u t c o r Research R e p o r t. A Method to Schedule Both Transportation and Production at the Same Time in a Special FMS.
R u t c o r Research R e p o r t A Method to Schedule Both Transportation and Production at the Same Time in a Special FMS Navid Hashemian a Béla Vizvári b RRR 3-2011, February 21, 2011 RUTCOR Rutgers
Branch-and-Price Approach to the Vehicle Routing Problem with Time Windows
TECHNISCHE UNIVERSITEIT EINDHOVEN Branch-and-Price Approach to the Vehicle Routing Problem with Time Windows Lloyd A. Fasting May 2014 Supervisors: dr. M. Firat dr.ir. M.A.A. Boon J. van Twist MSc. Contents
Scenario: Optimization of Conference Schedule.
MINI PROJECT 1 Scenario: Optimization of Conference Schedule. A conference has n papers accepted. Our job is to organize them in a best possible schedule. The schedule has p parallel sessions at a given
An optimisation framework for determination of capacity in railway networks
CASPT 2015 An optimisation framework for determination of capacity in railway networks Lars Wittrup Jensen Abstract Within the railway industry, high quality estimates on railway capacity is crucial information,
4.2 Description of the Event operation Network (EON)
Integrated support system for planning and scheduling... 2003/4/24 page 39 #65 Chapter 4 The EON model 4. Overview The present thesis is focused in the development of a generic scheduling framework applicable
INTEGER PROGRAMMING. Integer Programming. Prototype example. BIP model. BIP models
Integer Programming INTEGER PROGRAMMING In many problems the decision variables must have integer values. Example: assign people, machines, and vehicles to activities in integer quantities. If this is
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
Nonlinear Optimization: Algorithms 3: Interior-point methods
Nonlinear Optimization: Algorithms 3: Interior-point methods INSEAD, Spring 2006 Jean-Philippe Vert Ecole des Mines de Paris [email protected] Nonlinear optimization c 2006 Jean-Philippe Vert,
Resource-constrained Scheduling of a Real Project from the Construction Industry: A Comparison of Software Packages for Project Management
Resource-constrained Scheduling of a Real Project from the Construction Industry: A Comparison of Software Packages for Project Management N. Trautmann, P. Baumann Department of Business Administration,
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Criticality of Schedule Constraints Classification and Identification Qui T. Nguyen 1 and David K. H. Chua 2
Criticality of Schedule Constraints Classification and Identification Qui T. Nguyen 1 and David K. H. Chua 2 Abstract In construction scheduling, constraints among activities are vital as they govern the
Single-Link Failure Detection in All-Optical Networks Using Monitoring Cycles and Paths
Single-Link Failure Detection in All-Optical Networks Using Monitoring Cycles and Paths Satyajeet S. Ahuja, Srinivasan Ramasubramanian, and Marwan Krunz Department of ECE, University of Arizona, Tucson,
Optimization of an Operating Room Surgical Schedule. Anastasia Romanyuk & Alexandra Silva
Optimization of an Operating Room Surgical Schedule Anastasia Romanyuk & Alexandra Silva Washington University in St. Louis Department of Electrical & Systems Engineering April 27, 2012 Abstract: Operating
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
Scheduling Resources and Costs
Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used
Project Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
Optimising Patient Transportation in Hospitals
Optimising Patient Transportation in Hospitals Thomas Hanne 1 Fraunhofer Institute for Industrial Mathematics (ITWM), Fraunhofer-Platz 1, 67663 Kaiserslautern, Germany, [email protected] 1 Introduction
A Tool for Generating Partition Schedules of Multiprocessor Systems
A Tool for Generating Partition Schedules of Multiprocessor Systems Hans-Joachim Goltz and Norbert Pieth Fraunhofer FIRST, Berlin, Germany {hans-joachim.goltz,nobert.pieth}@first.fraunhofer.de Abstract.
Dimensioning an inbound call center using constraint programming
Dimensioning an inbound call center using constraint programming Cyril Canon 1,2, Jean-Charles Billaut 2, and Jean-Louis Bouquard 2 1 Vitalicom, 643 avenue du grain d or, 41350 Vineuil, France [email protected]
Constraints Propagation Techniques in Batch Plants Planning and Scheduling
European Symposium on Computer Arded Aided Process Engineering 15 L. Puigjaner and A. Espuña (Editors) 2005 Elsevier Science B.V. All rights reserved. Constraints Propagation Techniques in Batch Plants
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
A Business Process Driven Approach for Generating Software Modules
A Business Process Driven Approach for Generating Software Modules Xulin Zhao, Ying Zou Dept. of Electrical and Computer Engineering, Queen s University, Kingston, ON, Canada SUMMARY Business processes
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: 1. Activity : It is a particular work of a project which consumes some resources (in ) & time. It is shown as & represented
A Shift Sequence for Nurse Scheduling Using Linear Programming Problem
IOSR Journal of Nursing and Health Science (IOSR-JNHS) e-issn: 2320 1959.p- ISSN: 2320 1940 Volume 3, Issue 6 Ver. I (Nov.-Dec. 2014), PP 24-28 A Shift Sequence for Nurse Scheduling Using Linear Programming
Soft-Computing Models for Building Applications - A Feasibility Study (EPSRC Ref: GR/L84513)
Soft-Computing Models for Building Applications - A Feasibility Study (EPSRC Ref: GR/L84513) G S Virk, D Azzi, K I Alkadhimi and B P Haynes Department of Electrical and Electronic Engineering, University
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
JUST-IN-TIME SCHEDULING WITH PERIODIC TIME SLOTS. Received December May 12, 2003; revised February 5, 2004
Scientiae Mathematicae Japonicae Online, Vol. 10, (2004), 431 437 431 JUST-IN-TIME SCHEDULING WITH PERIODIC TIME SLOTS Ondřej Čepeka and Shao Chin Sung b Received December May 12, 2003; revised February
Offline sorting buffers on Line
Offline sorting buffers on Line Rohit Khandekar 1 and Vinayaka Pandit 2 1 University of Waterloo, ON, Canada. email: [email protected] 2 IBM India Research Lab, New Delhi. email: [email protected]
Application of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education
OPEN ACCESS Engineering Leaders Conference 2014 Application of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education M.O. Daramola
Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
CHAPTER 1. Basic Concepts on Planning and Scheduling
CHAPTER 1 Basic Concepts on Planning and Scheduling Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the selection and ordering of activities as well as
SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 Related Documents A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
Integrated maintenance scheduling for semiconductor manufacturing
Integrated maintenance scheduling for semiconductor manufacturing Andrew Davenport [email protected] Department of Business Analytics and Mathematical Science, IBM T. J. Watson Research Center, P.O.
A genetic algorithm for resource allocation in construction projects
Creative Construction Conference 2015 A genetic algorithm for resource allocation in construction projects Sofia Kaiafa, Athanasios P. Chassiakos* Sofia Kaiafa, Dept. of Civil Engineering, University of
Integration of ACO in a Constraint Programming Language
Integration of ACO in a Constraint Programming Language Madjid Khichane 12, Patrick Albert 1, and Christine Solnon 2 1 ILOG 2 LIRIS, UMR 5205 CNRS / University of Lyon ANTS 08 Motivations Ant Colony Optimization
Chapter 3: Section 3-3 Solutions of Linear Programming Problems
Chapter 3: Section 3-3 Solutions of Linear Programming Problems D. S. Malik Creighton University, Omaha, NE D. S. Malik Creighton University, Omaha, NE Chapter () 3: Section 3-3 Solutions of Linear Programming
Time Management II. http://lbgeeks.com/gitc/pmtime.php. June 5, 2008. Copyright 2008, Jason Paul Kazarian. All rights reserved.
Time Management II http://lbgeeks.com/gitc/pmtime.php June 5, 2008 Copyright 2008, Jason Paul Kazarian. All rights reserved. Page 1 Outline Scheduling Methods Finding the Critical Path Scheduling Documentation
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
A Production Planning Problem
A Production Planning Problem Suppose a production manager is responsible for scheduling the monthly production levels of a certain product for a planning horizon of twelve months. For planning purposes,
A SIMULATION MODEL FOR RESOURCE CONSTRAINED SCHEDULING OF MULTIPLE PROJECTS
A SIMULATION MODEL FOR RESOURCE CONSTRAINED SCHEDULING OF MULTIPLE PROJECTS B. Kanagasabapathi 1 and K. Ananthanarayanan 2 Building Technology and Construction Management Division, Department of Civil
Deming s 14 Points for TQM
1 Deming s 14 Points for TQM 1. Constancy of purpose Create constancy of purpose for continual improvement of products and service to society, allocating resources to provide for long range needs rather
The Problem of Scheduling Technicians and Interventions in a Telecommunications Company
The Problem of Scheduling Technicians and Interventions in a Telecommunications Company Sérgio Garcia Panzo Dongala November 2008 Abstract In 2007 the challenge organized by the French Society of Operational
Euler: A System for Numerical Optimization of Programs
Euler: A System for Numerical Optimization of Programs Swarat Chaudhuri 1 and Armando Solar-Lezama 2 1 Rice University 2 MIT Abstract. We give a tutorial introduction to Euler, a system for solving difficult
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
CRASHING-RISK-MODELING SOFTWARE (CRMS)
International Journal of Science, Environment and Technology, Vol. 4, No 2, 2015, 501 508 ISSN 2278-3687 (O) 2277-663X (P) CRASHING-RISK-MODELING SOFTWARE (CRMS) Nabil Semaan 1, Najib Georges 2 and Joe
Scheduling Algorithm with Optimization of Employee Satisfaction
Washington University in St. Louis Scheduling Algorithm with Optimization of Employee Satisfaction by Philip I. Thomas Senior Design Project http : //students.cec.wustl.edu/ pit1/ Advised By Associate
Pearson Education Limited 2003
156 Activities Activity 9.1 (PP. 357 358) [Project planning exercise] You are required to construct a project plan for the following information system development project. Your objective is to schedule
Scheduling Breaks in Shift Plans for Call Centers
Scheduling Breaks in Shift Plans for Call Centers Andreas Beer Johannes Gärtner Nysret Musliu Werner Schafhauser Wolfgang Slany Abstract In this paper we consider a real-life break scheduling problem for
MIP-Based Approaches for Solving Scheduling Problems with Batch Processing Machines
The Eighth International Symposium on Operations Research and Its Applications (ISORA 09) Zhangjiajie, China, September 20 22, 2009 Copyright 2009 ORSC & APORC, pp. 132 139 MIP-Based Approaches for Solving
Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
Information Theory and Coding Prof. S. N. Merchant Department of Electrical Engineering Indian Institute of Technology, Bombay
Information Theory and Coding Prof. S. N. Merchant Department of Electrical Engineering Indian Institute of Technology, Bombay Lecture - 17 Shannon-Fano-Elias Coding and Introduction to Arithmetic Coding
Collaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
The work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
An Online Optimised Pump Scheduling System
An Online Optimised Pump Scheduling System Stephanie Pegg Systems Technology Beca Carter Hollings & Ferner Ltd Auckland, New Zealand [email protected] Abstract A common problem facing the suppliers of bulk
Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
The effectiveness of resource levelling tools for Resource Constraint Project Scheduling Problem
Available online at www.sciencedirect.com International Journal of Project Management 27 (2009) 493 500 www.elsevier.com/locate/ijproman The effectiveness of resource levelling tools for Resource Constraint
Workforce scheduling with logical constraints: theory and applications in call centers
Workforce scheduling with logical constraints: theory and applications in call centers Gábor Danó This thesis was supervised by Sandjai Bhulai and Ger Koole Department of Mathematics Vrije Universiteit
Load Balancing by MPLS in Differentiated Services Networks
Load Balancing by MPLS in Differentiated Services Networks Riikka Susitaival, Jorma Virtamo, and Samuli Aalto Networking Laboratory, Helsinki University of Technology P.O.Box 3000, FIN-02015 HUT, Finland
16.1 MAPREDUCE. For personal use only, not for distribution. 333
For personal use only, not for distribution. 333 16.1 MAPREDUCE Initially designed by the Google labs and used internally by Google, the MAPREDUCE distributed programming model is now promoted by several
Lecture Outline Overview of real-time scheduling algorithms Outline relative strengths, weaknesses
Overview of Real-Time Scheduling Embedded Real-Time Software Lecture 3 Lecture Outline Overview of real-time scheduling algorithms Clock-driven Weighted round-robin Priority-driven Dynamic vs. static Deadline
ANT COLONY OPTIMIZATION ALGORITHM FOR RESOURCE LEVELING PROBLEM OF CONSTRUCTION PROJECT
ANT COLONY OPTIMIZATION ALGORITHM FOR RESOURCE LEVELING PROBLEM OF CONSTRUCTION PROJECT Ying XIONG 1, Ya Ping KUANG 2 1. School of Economics and Management, Being Jiaotong Univ., Being, China. 2. College
Project Management DISCUSSION QUESTIONS
3 C H A P T E R Project Management DISCUSSION QUESTIONS. There are many possible answers. Project management is needed in large construction jobs, in implementing new information systems, in new product