INSPECTION AND TESTING OF EMERGENCY GENERATORS
|
|
|
- Dwight Gibbs
- 9 years ago
- Views:
Transcription
1 INSPECTION AND TESTING OF EMERGENCY GENERATORS Certification requirements NFPA 101(00), Sec requires that emergency generators be installed, tested and maintained in accordance with NFPA 110, Standard for Emergency and Standby Power Systems. Chapter 2 of NFPA 101 references the 1999 edition of NFPA 110. Buildings that fall under Chapter 18 of NFPA 101(00) and are equipped with or in which patients require the use of life-support systems (e.g. hospitals, nursing homes with residents on ventilators) must also meet the maintenance and testing provisions of the 1999 edition of NFPA 99, Standard for Health Care Facilities [see NFPA 101(00), Sections , , and ]. Provisions dealing with maintenance and testing of emergency generators can be found in NFPA 99(99), Sec This section starts out by referencing NFPA 110, but also deals with such issues as: Testing intervals Test conditions Personnel qualifications Maintenance and testing of circuitry Maintenance of batteries Each facility should have a copy of these standards. They can be ordered from NFPA at or Generator classifications In order to follow the requirements in NFPA 99 and NFPA 110, you need to know the classification systems used by those standards: 1. Let s take a look at NFPA 99 first: a. NFPA 99 treats emergency generators as part of an essential electrical system (EES), which is defined as, A system comprised of alternate sources of power and all connected distribution systems and ancillary equipment, designed to ensure continuity of electrical power to designated areas and functions of a health care facility during disruption of normal power sources, and also to minimize disruption within the internal wiring system. [see NFPA 99(99), Chapter 2, Definitions]. b. NFPA 99 breaks essential electrical systems down into three categories Type 1, Type 2 and Type 3. Basically, the services provided by a facility determine the type of EES required as follows: NFPA 99(99), Sec requires essential electrical systems in hospitals to conform to Type 1 system requirements. NFPA 99(99), Sec requires essential electrical systems in nursing homes to conform to Type 2 system requirements. By exception, however, Type 3 systems are allowed in nursing homes that do not provide life support (e.g. ventilators). c. For a more detailed description of these three types of systems, see Chapter 3 of NFPA 99(99). If you re unsure about which type of system describes your generator, the vendor that installed and/or maintains your generator should be able to provide you with that information.
2 Page 2 of 7 2. NFPA 110, on the other hand, treats emergency generators as part of an emergency power supply system (EPSS). a. There are two important definitions to keep in mind [see NFPA 110(99), Chapter 2]: Emergency Power Supply (EPS): The source of electric power of the required capacity and quality for an emergency power supply system (EPSS), including all the related electrical and mechanical components of the proper size and/or capacity required for the generation of the required electrical power at the EPS output terminals. A further explanation can be found in the Appendix [see NFPA 110(99), Sec. A-2-1]: For rotary energy converters, components of an EPS include the following: prime mover, cooling system, generator, excitation system, starting system, control system, fuel system, and lube system, if required. Emergency Power Supply System (EPSS): A complete functioning system of an EPS coupled to a system that can consist of conductors, disconnecting means, and overcurrent protective devices, transfer switches, and all control, supervisory, and support devices up to and including the load terminals of the transfer equipment needed for the system to operate as a safe and reliable source of electrical power. b. NFPA 110 breaks emergency power supply systems down into two categories Level 1 and Level 2. Once you know the NFPA 99 classification of your emergency generator (i.e. Type 1, Type 2 or Type 3), that standard tells you where your generator fits into NFPA 110. NFPA 99(99), Sec specifies that: Type 1 and Type 2 essential electrical system power sources shall be classified as Level 1 generator sets per NFPA 110. Type 3 essential electrical system power sources shall be classified as Level 2 generator sets per NFPA 110. State licensure requirements MSFC(07), Sec requires that emergency generators be maintained in accordance with the 2002 edition of NFPA 110. Fortunately, the provisions in this edition of the standard applicable to inspection and testing are very similar to those found in the 1999 edition of the standard. Maintenance and testing Applicable standards Requirements for routine maintenance and operational testing of emergency generators can be found in: Chapter 6 of the 1999 edition of NFPA 110 Chapter 8 of the 2002 edition of NFPA 110 Sections 3-4.4, and of NFPA 99(99) Maintenance and testing General 1. Maintenance and testing is critical to the continued reliability of your emergency generator and must be performed in accordance with manufacturer s recommendations, instruction manuals, and the minimum requirements of NFPA 110 and the authority having jurisdiction (AHJ) [see: NFPA 110(99), Section 6-1.1; NFPA 110(02), Sec ].
3 Page 3 of 7 2. Your facility should have at least two sets of instruction manuals for all major generator components. One set should be kept in a secure, convenient location near the equipment. The other set should be kept in a different secure location [see: NFPA 110(99), Section 6-2.1; NFPA 110(02), Sec ]. These manuals must, at a minimum, contain the following: A detailed explanation of the operation of the emergency power supply system Instructions for routine maintenance Detailed repair instructions An illustrated parts list and part numbers Illustrated and schematic drawings of electrical wiring systems, including operating and safety devices, control panels, instrumentation and annunciators 3. Special tools and testing devices necessary for routine maintenance must be available for use when needed [see: NFPA 110(99), Section 6-2.3; NFPA 110(02), Sec ]. 4. Routine maintenance, inspection and operational testing of the emergency generator and associated components must be overseen by a properly trained person [see MSFC(07), Sec ; NFPA 99(99), Sec (b)3; NFPA 110(99), Sec ; NFPA 110(02), Sec ]. Evidence of such training should be kept in the designated employees personnel file. In the absence of a properly trained person on-site, an outside vendor may need to be contracted to oversee the performance of all or part of these services. 5. The standards do not establish a specific date and time of day for required testing. Those are to be determined by management and are typically scheduled so as to provide minimum disruption of facility operations. Weekly inspections To meet federal certification and state licensure requirements, healthcare facilities must inspect their emergency generators weekly [see NFPA 110(99), Sec ; NFPA 110(02), Sec ]. At a minimum, this weekly inspection should include a check of the following: 1. Fuel (check main and day tank fuel supply levels; day tank float switch; piping, hoses and connectors; operating fuel pressure; and for any obstructions to tank vents and overflow piping 2. Oil (check for proper oil level and oil operating pressure; lube oil heater) Engine oil level can be checked with the unit stopped or running on many engines; otherwise, it should be checked with the unit stopped Oil operating pressure should normally be above 40 psi 3. Cooling system (check coolant level, water pump(s), jacket water heater, belts, hoses, fan) 4. Exhaust system (check drain condensate trap and for possible leakage) 5. Battery system [look for possible corrosion; check specific gravity, electrolyte level (a level between 1250 and 1275 is acceptable) and battery charger] 6. Electrical (conduct a general inspection of wiring and connections; check circuit breakers/fuses) 7. Prime Mover/Generator (Check for debris, foreign objects, loose or broken fittings; check guards and components; look for any unusual condition of vibration, leakage, noise, temperature or deterioration NOTE: This is not an all-inclusive list. The equipment manufacturer may have additional maintenance requirements that will likely include monthly, quarterly, semi-annual and annual inspections and checks.
4 Page 4 of 7 Monthly testing 1. To meet federal certification and state licensure requirements, healthcare facilities must exercise their emergency generators under load at least monthly [see NFPA 110(99), Sec ; NFPA 110(02), Sec ]. There are a number of ways to comply with this requirement: a. The base requirement is that generators be exercised for a minimum of 30 minutes* using one of the following methods [see NFPA 110(99), Sec ; NFPA 110(02), Sec ]: i. Under operating temperature conditions and at not less than 30 percent of the generator s nameplate kw rating. A 100 kw generator, for example, would need to be exercised under a load of at least 30 kw to meet this requirement. Normal operating temperatures are set by the manufacturer. Something to consider when scheduling your monthly tests is that your particular generator may not reach operating temperature in 30 minutes* and that running the generator for short periods of time may be harmful to the engine. You also want to make sure that the generator runs long enough to ensure that all engine parts are properly lubricated. ii. Loading that maintains the minimum exhaust gas temperatures recommended by the manufacturer (it is unlikely that minimum exhaust gas temperatures will be reached if the generator isn t carrying a load equivalent to at least 30 percent of the generator s nameplate kw rating). *Note: Warm-up and cool-down times do not count toward the required 30 minutes. b. An alternate method is provided for diesel-powered generators that do not meet the testing requirements outlined in 1.a above. This could occur when, for example, a large generator in relation to the load is installed (e.g. either to account for the largest motor connected to the generator or to accommodate future expansion of the facility). Such generators can be exercised monthly with the available load and exercised annually with supplemental loads at 25 percent of nameplate rating for 30 minutes, followed by 50 percent of nameplate rating for 30 minutes, followed by 75 percent of nameplate rating for 60 minutes, for a total of 2 continuous hours [see NFPA 110(99), Sec ; NFPA 110(02), Sec ]. c. For gasoline-powered, natural gas-powered or propane-powered generators that do not meet the testing requirements outlined in 1.a above, it will likely be necessary to add more load to the generator or conduct a load bank test to comply with testing requirements (a load bank is, typically, a mobile piece of equipment that simulates the actual electrical load the generator is intended to power). Where equivalent loads are used for testing, it s important to note that such loads are required to be automatically replaced with the emergency loads in case of failure of the normal power [see NFPA 110(99), Sec ; NFPA 110(02), Sec ]. d. Where a generator set is used for peak load shaving or operated during a power outage, such use is allowed to be substituted for a routine monthly test, provided the generator is operated in accordance with the standards and the appropriate data are recorded. Another thing to keep in mind, however, is that NFPA 99(99), Sec (b)1 requires a minimum 20-day and maximum 40-day interval between tests [see also NFPA 99(99), Sections (b) and (b)].
5 Page 5 of 7 2. Load tests must include complete cold starts [see NFPA 99(99), Sec (b)2; NFPA 110(99), Sec ; NFPA 110(02), Sec ]. 3. Time delays must be set as follows [see NFPA 110(99), Sec ; NFPA 110(02), Sec ]: a. Time delay on start: 1 second minimum.* Exception: Gas turbine cycle: 0.5 second minimum. *Note: NFPA 101(00), Sec requires that emergency loads be picked up within 10 seconds. b. Time delay on transfer to emergency: none. c. Time delay on restoration to normal power: 5 minutes minimum (to give the primary source sufficient time to stabilize before retransfer of the load, a delay of between 15 and 30 minutes is recommended). d. Time delay on shutdown: 5 minutes minimum. It s important to be prepared in case something goes wrong during testing. It is strongly recommended that your facility have a policy in place that makes provisions for a portable generator or other alternate power source for situations in which the emergency generator malfunctions or, worse yet, is out of service. Transfer switches 1. Transfer switches are required to be operated monthly [see MSFC(07), Sec ; NFPA 110(99), Sec ; NFPA 110(02), Sec ]. 2. This monthly test must consist of electrically operating the transfer switch from the normal/standard position to the alternate position and then a return to the normal/standard position [see MSFC(07), Sec ; NFPA 110(99), Sec ; NFPA 110(02), Sec ]. In many cases, a Transfer Test switch or button is provided and can be used to perform this test. Where this feature does not exist, it may be necessary to manually disconnect normal power in some fashion to the transfer switch (see some words of caution on testing below). 3. Transfer switches must also be inspected monthly to ensure that they are maintained free from accumulated dust and dirt and to check for deterioration of the transfer switch contacts [see MSFC(07), Sec ; NFPA 110(99), Sec ; NFPA 110(02), Sec ]. 4. Because they are such a key component in the successful operation of your emergency generator, it is recommended that you consider having infrared testing of your transfer switch(es) conducted annually to check for loose connections. Some words of caution on testing 1. Shutting off power, especially shutting off the main breaker, can expose a person to possible shock, electrocution and/or arc flash hazards. It is important, therefore, that anyone performing a test in this fashion be adequately trained and take proper safety precautions, including the wearing of proper personal protective equipment (PPE). To reduce the safety risks, it is strongly recommended that facilities not already so equipped consider adding a switch for testing of their transfer switches.
6 Page 6 of 7 2. The explanatory information in NFPA s 1999 Health Care Facilities Handbook to Sec (b)2, which addresses test conditions (including cold starts and appropriate automatic and manual transfer of essential electrical system loads), provides more food for thought: Testing procedures might range from manually disconnecting power to the power sensors on transfer switches to manually opening the main incoming feeder breakers. It is very important that each test method be fully understood by all staff through appropriate notification and that the consequences of each method (if something fails to function) be weighed carefully. A procedure for returning to the normal power source should also be established in the event a failure occurred during testing. There is a false assumption that disconnecting a facility s mains is the best method of testing the standby generator(s) and essential electrical system. One has to always consider the possibility that failure of the disconnecting means or some other unexpected contingency might make it difficult or impossible to restore normal power. It is probably better to initiate engine start by interrupting power just ahead of the transfer switch(es) on an alternating or rotating basis in order to make sure each transfer switch has an intact engine start circuit. DOCUMENT your inspections and tests NFPA 110(99), Sec requires the establishment of a written schedule for routine generator maintenance and testing [see also: MSFC(07), Sec ]. A sample schedule can be found in Appendix A of the standard [see Figure A-6-3.1(a)]** or may even be available from the equipment manufacturer [see also: NFPA 110(02), Sec and Figure A.8.3.1(a); 1999 Health Care Facilities Handbook Appendix C-3.2]. ** Because there is a lot riding on the successful operation of a facility s emergency generator, it is strongly recommended that the schedule for Level 1 emergency power supply systems be followed when establishing your maintenance schedule. A written record of generator inspections, tests, exercising, operation and repairs must be maintained on the premises and be available for review by the fire inspector on request. This record must, at a minimum, include: the date of the report, name(s) of the person(s) providing the service, identification of unsatisfactory conditions and corrective action taken (including parts replaced), and any testing of repairs recommended by the manufacturer [see MSFC(07), Sec ; NFPA 99(99), Sec ; NFPA 110(99), Sec ; NFPA 110(02), Sections and ]. A sample inspection log can be found in Appendix A of NFPA 110(99) [see Figure A-6-3.1(b)] or may even be available from the equipment manufacturer [see also: NFPA 110(02), Figure A.8.3.1(b)]. A sample testing log can be found in NFPA 110(02), Figure A.8.4.1(a) or may even be available from the equipment manufacturer. As an alternate, sample inspection and testing logs have been developed to serve as a guide that you can use in creating your own logs. Completed logs are provided to serve as examples of how the logs are expected to be filled out.
7 Page 7 of 7 It s important that at least two people in your facility know where your logs are kept to increase the likelihood that they can be readily provided if requested during an inspection. It is recommended that these logs be maintained for at least three years. Click Here for the Emergency Generator Weekly Inspection Checklist Click Here for the Emergency Generator Monthly Test Log
The State Fire Marshal's Office and the VDH/Office of Licensure and Certification. Generator Testing in Nursing Facilities
Generator Testing in Nursing Facilities Introduction Recent emergencies and natural disasters have emphasized the need to ensure that nursing facilities have an adequate EPSS in place should the loss of
Prime Power Services, Inc. Georgia, Carolinas 800 741 0128. NFPA 110 Standards for Emergency & Stand by Generators June 1, 2010
Prime Power Services, Inc. Georgia, Carolinas 800 741 0128 NFPA 110 Standards for Emergency & Stand by Generators June 1, 2010 NFPA Disclaimer The views and opinions expressed in this seminar are purely
INSPECTION, TESTING AND MAINTENANCE OF FIRE PROTECTION SYSTEMS AND EQUIPMENT
CITY OF SPRING LAKE PARK Code Enforcement Department 1301 81 st Avenue NE Spring Lake Park MN 55432 Business Phone 763-784-6491 Fax 763-792-7257 INSPECTION, TESTING AND MAINTENANCE OF FIRE PROTECTION SYSTEMS
Oil and Coolant Circulating Heating System. Model - OCSM
Oil and Coolant Circulating Heating System Model - OCSM Installation & Operation Manual 216280-000 REV 2 Identifying Your System The HOTSTART heating system is designed to heat fluids for use in marine
Fire Sprinkler System Maintenance and Testing Page 1 MAINTENANCE AND TESTING OF FIRE SPRINKLER SYSTEMS
Page 1 MAINTENANCE AND TESTING OF FIRE SPRINKLER SYSTEMS Introduction When properly installed and maintained, automatic fire sprinkler systems have proven to be the most effective means for protecting
ELECTRICAL EMERGENCY SYSTEM PLAN REVIEW OVERVIEW OF CODE REQUIREMENTS
ELECTRICAL EMERGENCY SYSTEM PLAN REVIEW What to Look for during Plan Review OVERVIEW OF CODE REQUIREMENTS First determine the type of emergency power system; is the system designed for Emergency or Legally
INSPECTION AND TESTING OF FIRE ALARM SYSTEMS
Page 1 January 2, 2009 INSPECTION AND TESTING OF FIRE ALARM SYSTEMS Introduction Early warning plays a key role in a healthcare facility s ability to safely evacuate its residents during a fire emergency.
26 3213.13 Diesel Engine Driven Generators Page 1 of 6
Last Update: December 8, 2014 A. Description of System Consultant s Handbook Page 1 of 6 1. Provide a diesel engine driven electric generating unit, factory assembled, tested and certified to operate at
LOAD BANK TESTING PROCEDURE
LOAD BANK TESTING PROCEDURE APPENDIX G SPS-G-1 of 9 I. General GENERATOR LOAD BANK TESTING AND ENGINE TESTING A. Provide all equipment, labor, materials and supervision necessary to test the stand-by diesel
TECHNICAL ADVISORY BULLETIN
RISK CONTROL AND CLAIM ADVOCACY PRACTICE TECHNICAL ADVISORY BULLETIN November 2014 www.willis.com FIRE PUMP TESTING Fire pumps are a critical part of a fire protection system, especially when they are
Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches
Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches Downtime Is Not An Option The industrial uninterruptible power supply (UPS) is the foundation of your
ELECTRIC/DIESEL FIRE PUMP CHECK LIST
BUILDING NAME: DESIGNER: SCO REPRESENTATIVE: PUMP MANUF.: LOCATION: INSTALLER: DATE: OWNER NAME: INSTALLATION Certificate for flushing and hydrostatic test furnished Piping been hydrostatically tested
FIRE SAFETY REGISTER. Premises Name: Premises Address: Fire Safety Manager: Contact No. Kerry County Fire Service www.kerrycoco.ie
FIRE SAFETY REGISTER Premises Name: Premises Address: Fire Safety Manager: Contact No. Kerry County Fire Service www.kerrycoco.ie 1 CONTENTS Section Title Page 1.0 Introduction 3 2.0 Guidance for the completion
Fire Alarm System Monitoring - CAN/ULC-S561-03
Fire Alarm System Monitoring - CAN/ULC-S561-03 Brian McBain ULC Regulatory Services May 4, 2011 Copyright 1995-2007 Underwriters' Laboratories of Canada. All rights reserved. No portion of this material
BERMAD Fire Protection
400E-2M/700E-2M IOM Bermad Electrically Controlled Deluge Valve with EasyLock Manual Reset Model: 400E-2M/700E-2M INSTALLATION OPERATION MAINTENANCE Application Engineering BERMAD 400E-2M/700E-2M Bermad
Model: 400E-2M. Bermad Electrically Controlled Deluge Valve with Easy Lock Manual Reset. Installation Operation Maintenance. Application Engineering
Model: 400E-2M Bermad Electrically Controlled Deluge Valve with Easy Lock Manual Reset Installation Operation Maintenance Application Engineering BERMAD 1. Safety First BERMAD believes that the safety
BERMAD Fire Protection
Model: 400E-2M BERMAD Electrically Controlled Deluge Valve with Easy Lock Manual Reset Installation Operation Maintenance Safety First BERMAD believes that the safety of personnel working with and around
Winnipeg Fire Department Fire Prevention Branch
Winnipeg Fire Department Fire Prevention Branch Manitoba Fire Code Life-Safety Equipment Maintenance Requirements The Fire Prevention Branch of the Winnipeg Fire Department has prepared this document of
Thermo Top - Troubleshooting Tree
Thermo Top - Troubleshooting Tree 07-15-2002 CAUTION Troubleshooting requires comprehensive knowledge about the structure and theory of operation of the Thermo Top heater. Troubleshooting and repairs may
National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook
National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook Trainee:... Training Provider:... Year:... Trainee Contact no:... Competency Based Skill Training Logbook Introduction
Planned, Limited Notice and Emergency Outage Guidelines
Applies to: All Facilities Management Employees GUIDELINES: Issued: April 22, 2014 Revised: February 24, 2015 Author: Communications Coordinator PURPOSE: The purpose of these guidelines is to define roles
INSTRUCTIONS FOR BUILDINGS WITH FIRE PROTECTION EQUIPMENT
INSTRUCTIONS FOR BUILDINGS WITH FIRE PROTECTION EQUIPMENT FIRE EXTINGUISHERS,SPRINKLER SYSTEMS AND FIRE ALARMS Attachment #1 Inspection of Fire Extinguishers Fire Extinguishers must be tested according
Backup Fuel Oil System Decommissioning & Restoration Plan
Backup Fuel Oil System Page 1 of 19 Overview of Physical Fuel Oil System and Decommissioning Steps The fuel oil system at Milford Power consists of a number of subsystems. These include the following:
ALBERTA FIRE CODE SAFETY EQUIPMENT MAINTENANCE REQUIREMENTS
ALBERTA FIRE CODE SAFETY EQUIPMENT MAINTENANCE REQUIREMENTS In this document are the fire safety equipment maintenance requirements that are found in Division B of the Alberta Fire Code (AFC 2006) for
Federal Wage System Job Grading Standards for Air Conditioning Equipment Operating, 5415. Table of Contents
Federal Wage System Job Grading Standards for Air Conditioning Equipment Operating, 5415 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 HELPER AND INTERMEDIATE JOBS...
CARING FOR YOUR WATER HEATER
http://waterheatertimer.org/troubleshoot-rheem-tankless-water-heater.html Water Heater Inspections CARING FOR YOUR WATER HEATER Venting System (Direct Vent Only) The venting system should be inspected
14. Troubleshooting Guide
14. Guide 14.1 Refrigeration Cycle System In order to diagnose malfunctions, ensure the air conditioner is free from electrical problems before inspecting the refrigeration cycle. Such problems include
Installation Instructions for Alarm Module Kit A043F059
Instruction Sheet 07-2013 Installation Instructions for Alarm Module Kit A043F059 1 Introduction The information contained within is based on information available at the time of going to print. In line
Competency Framework for Marine Engineer Class 6. Competency Framework for Marine Engineer Class 6
Table of Contents (MEC 6)... 1 Function: Operate Vessel Machinery and Systems... 1 Diesel engines.... 1 Operational procedures.... 3 Operate and monitor a vessel s engines and auxiliary equipment.... 4
Mike Holt s Illustrated Guide to. Rule 220.87, Articles 445, 700, 701, and 702. Based on the 2011 NEC
Mike Holt s Illustrated Guide to NEC Requirements for Generators and Standby Power Systems Rule 220.87, Articles 445, 700, 701, and 702 Based on the 2011 NEC Extracted from Mike Holt s Illustrated Guides
Air Conditioner Water Heater - A Product of HotSpot Energy LLC
Air Conditioner Water Heater - A Product of HotSpot Energy LLC PLEASE READ THIS BEFORE YOU INSTALL THE UNIT 1. This air conditioner must be installed and/or repaired by a qualified technician. If you perform
FACILITY FIRE PREVENTION AND EMERGENCY PREPAREDNESS INSPECTION CHECKLIST
FACILITY FIRE PREVENTION AND EMERGENCY PREPAREDNESS INSPECTION CHECKLIST Date of Inspection: Conducted by: Location: Reviewed by: Date of Review: Comments or additional corrective action taken as a result
Section 10: Emergency and Standby Power Systems
Section 10: Emergency and Standby Power Systems Bill Brown, P.E., Square D Engineering Services Introduction Emergency and standby power systems are designed to provide an alternate source of power if
Medical Air Systems: Scroll
GENERAL The Chemetron skid mount scroll medical air system is designed to provide medical breathing air for hospital and medical institutions. This system meets NFPA 99 requirements for Level 1 breathing
Attachment J-C18.1. HVAC Work Instructions
. RFP: Attachment J-C18.1 HVAC Work Instructions NNC13ZFD017J SOW Item No. Title Page C18-02 Control Air Systems Annual PM 2 C18-03 Split System AC Indoor Section Annual PM 3 C18-04 Condensing Unit Semi-Annual
SDX Submersible Depth Transmitter User Manual
SDX Submersible Depth Transmitter User Manual January 2011 USER INFORMATION Stevens makes no warranty as to the information furnished in these instructions and the reader assumes all risk in the use thereof.
Service manual. Website: www.andico.com.au CAUTION - BEFORE SERVICING THE UNIT, READ THE SAFETY - PRECAUTIONS IN THIS MANUAL.
Website: www.andico.com.au Service manual CAUTION - BEFORE SERVICING THE UNIT, READ THE SAFETY - PRECAUTIONS IN THIS MANUAL. - ONLY FOR AUTHORISED SERVICE PERSONNEL. MODELS: MPK1-09CR-QB8 MPK1-12ER-QB6
GNOME PELLET E.I. Pellet Heater Owner's Manual Installation and Operating Instructions. Please read this entire manual before installation.
Pellet Heater Owner's Manual Installation and Operating Instructions Please read this entire manual before installation. Save these instructions. SAFETY NOTICE HEATER MUST BE PROPERLY INSTALLED AND MAINTAINED
Evaluate, Clean, and Tune Guidance
Evaluate, Clean, and Tune Guidance The Evaluate, Clean and Tune (ECT) process serves three essential purposes in the Weatherization Assistance Program (WAP). The first is to evaluate the existing system
HERNANDO COUNTY FIRE ALARM GUIDELINES
HERNANDO COUNTY FIRE ALARM GUIDELINES To be used for all commercial building fire alarm system plan review. The procedures set forth in this document are the minimum requirements necessary to ensure a
INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23
INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23 GUIDELINES FOR WORKING WITH PORTABLE POWER DISTRIBUTION SYSTEMS AND OTHER ELECTRICAL EQUIPMENT "ADDENDUM C" WORKING WITH 480 VOLT SYSTEMS
Topics of the Presentation
Drill Rig Safety Topics of the Presentation Personnel safety and monitoring PPE Health (Drugs and Alcohol) Drill Rig operation Safe set up procedures Safe operation of machine Safety related accidents
SL280UHV SERIES GAS FURNACE WARNING
2010 Lennox Industries Inc. Dallas, Texas, USA 506677 01 11/2010 Supersedes 506409 01 SL280UHV SERIES GAS FURNACE Litho U.S.A. FIRE OR EXPLOSION HAZARD. Failure to follow safety warnings exactly could
POWERING THE WAY Rental Power Planner
POWERING THE WAY Rental Power Planner PLANNING FOR TEMPORARY POWER: A Critical Management Duty As a facility manager, you know better than anyone that electrical power is the lifeblood of business. Without
FPS4 APPENDIX A (INTERIM) SPECIFICATION FOR THE INSPECTION AND TESTING OF AUTOMATIC FIRE SPRINKLER SYSTEMS
FPS4 APPENDIX A (INTERIM) SPECIFICATION FOR THE INSPECTION AND TESTING OF AUTOMATIC FIRE SPRINKLER SYSTEMS To be used in conjunction with the Fire Protection Association Australia FPS4-2000: Agreement
D. Infrared scanning reports with pictures printed in a final report with any deficiencies and actions taken to rectify.
SECTION 263354 STATIC UPS TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes 1. System start-up services. 2. Battery charging. 3. Load bank testing. 4. Battery load testing. 5.
Vehicle Fire Protection. An Ownerʼs Manual for ANSUL Fire Suppression/Detection Systems
Vehicle Fire Protection An Ownerʼs Manual for ANSUL Fire Suppression/Detection Systems 002792 Off-road vehicles do have fires Statistics show that off-road vehicles burn with alarming frequency. These
MAINTENANCE INSTRUCTIONS. Thermia Robust heat pump
MAINTENANCE INSTRUCTIONS Thermia Robust heat pump 9 6 8 0-5 4 7 4 5 0 0 1 R e v. 3 Table of contents 1 Important information.................. 2 1.1 Product description....................... 2 1.2 General................................
SPECIFICATION TECHNICAL AIR-CONDITIONING UNITS SINGLE AND SPLIT (DUCTED) (AIR COOLED PACKAGED UNIT)
SPECIFICATION TECHNICAL AIR-CONDITIONING UNITS SINGLE AND SPLIT (DUCTED) (AIR COOLED PACKAGED UNIT) MAINTENANCE TYPE: STATUTORY 1.0 SCOPE OF SERVICES The Contractor shall provide maintenance Services for
3620 W 11th Streetб Houston, TX 77008 Telephone: 713-635-6291 Email: [email protected] Website: www.kellogg-american.com
Unpackaging & Handling Be sure to carefully inspect the unit before accepting the shipment. If any damage has occurred document it with the trucking company immediately. Contact your Kellogg Distributor
Electric Water Heater
Electric Water Heater Operation and Installation Manual (LIMITED WARRANTY AND TANK REPLACEMENT POLICY) The following information should be noted at time of installation and retained for future reference.
Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents
Federal Wage System Job Grading Standards for Electric Power Controlling, 5407 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 SPECIAL ADDITIONAL RESPONSIBILITIES...
Recommended Product Specifications Fuel Day Tank System Tramont UTRS Fuel Day Tank
Recommended Product Specifications Fuel Day Tank System Tramont UTRS Fuel Day Tank This specification describes requirements for a Diesel Fuel Day Tank System consisting of one or more fuel tanks, an Electronic
USER INSTRUCTIONS FOR GET PORTABLE 12k BTU AIR CONDITIONER MODEL No. GPACU12HR
USER INSTRUCTIONS FOR GET PORTABLE 12k BTU AIR CONDITIONER MODEL No. GPACU12HR CONTENTS Introduction Safety Notes Identification of parts Installation instructions Operation instructions Maintenance Troubleshooting
How To Use A Power Supply Unit (Upu)
BRAVER UPS (Uninterruptible Power System) User s Manual Safety CAUTION! This UPS utilizes voltages that may be hazardous. Do not attempt to disassemble the unit. The unit contains no user replaceable parts.
Boiler and Burner Cleaning and Servicing Specifications
Boiler and Burner Cleaning and Servicing Specifications The Town of Groton of Public Works Department is requesting bids to provide manufacturers recommended maintenance, repairs and emergency service
SWIMMING POOL HEAT PUMP
SWIMMING POOL HEAT PUMP Installation & User Manual Model HP40B HP50B HP65B Hayward Pool Products Canada, Inc. T: 1-888-238-7665 www.haywardpool.ca CONTENT I. Application 4 II. Features 4 III. Technical
NFPA31FuelOilPiping 1 Revised 3-1-11
NFPA 31 Fuel Oil Piping, Installation and Testing Chapter 8 Fuel Piping Systems and Components 8.1 Scope. This chapter shall apply to piping systems and their components used to transfer fuel oil from
A Guide to Trouble-Free Cooling Towers
A Guide to Trouble-Free Cooling Towers A basic understanding of cooling tower operation and maintenance will help keep a cooling water system running in top condition, year after year By David M. Suptic
Environment of Care Utility Systems Management Plan 2014 Updated 4.18.2014
Environment of Care Utility Systems Management Plan 2014 Updated 4.18.2014 PURPOSE The objectives of the Utility Systems Management plan is to establish, maintain, and continually provide a reliable utility
PC1131 Electric Air Compressor
Senco Products Inc. 8485 Broadwell Road Cincinnati, Ohio 45244 PC1131 Electric Air Compressor Operating Instructions 2006 by Senco Products, Inc. Warnings for the safe use of this tool are included in
IMPORTANT SAFETY NOTICE
IMPORTANT SAFETY NOTICE To: Our Valued Customers User safety is a major focus in the design of our products. Following the precautions outlined in this manual will minimize your risk of injury. ITT Goulds
FT-100 Fire Training Fog Machine User Manual English
FT-100 Fire Training Fog Machine User Manual English 2015 Antari Lighting and Effects Ltd. User Manual - English Safety Information Please read the following safety information carefully before operating
Fire Protection Notice No. 9 ELECTRICAL SAFETY
Fire Protection Notice No. 9 ELECTRICAL SAFETY Because electricity is one of the most controllable forms of energy it can also be one of the safest. But, as industry and commerce draw ever more heavily
Crawford Inspection Services C.C.B. # 76914 www.crawfordinspections.com
Crawford Inspection Services C.C.B. # 76914 www.crawfordinspections.com Portland Area PO Box 665 West Linn, OR 97068 Ph: (503) 650-6957 Salem Area 5434 River Rd. N; #192 Keizer, OR 97303 Ph: (503) 362-5809
Diesel Generating Set
MODEL Standby Power(50Hz) Prime Power(50Hz) 44KW /55KVA 40KW /50KVA Standard Features General Features: Engine( DCEC Cummins 4BTA3.9 -G) Radiator 40 O C max,fans are driven by belt, with safety guard 24V
The following definitions apply with regard to requirements specified in this document:
GUIDELINES FOR INSTALLATION OF TEMPORARY AND PERMANENT ABOVEGROUND DIESEL FUEL TANKS FOR EMERGENCY AND STANDBY POWER SYSTEMS LOCATED OUTSIDE OF BUILDINGS For Use by Unidocs Member Agencies or where approved
ALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.147 THE CONTROL OF HAZARDOUS ENERGY (LOCKOUT / TAGOUT) SECTION: 2400
OSHA REGULATION: 29 CFR 90.7 THE CONTROL OF HAZARDOUS ENERGY (LOCKOUT / TAGOUT) DATE: 0/5/2008 DATE: /2/202 A. POLICY. This procedure follows requirements set forth in 29 CFR 90.7. 2. It is the policy
SECTION 263235 STANDBY GENERATOR TESTING AND COMMISSIONING
SECTION 263235 STANDBY GENERATOR TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Standby generators. 2. Automatic Transfer Switches (ATS). 3. System start-up services. 4.
Fire Safety Plan (Single-Stage Fire Alarm System) (Small Establishment):
Fire Safety Plan (Single-Stage Fire Alarm System) (Small Establishment): Fire Safety Plan Single-Stage Fire Alarm System for: (Business Name) (Business Address) Submission Date - Submitted by - Signature
Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva
Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva Issued: August 2009 SIZED UP TO 100 KVA TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Applicability... 1 1.2 Definitions...
Industrial Process Pump Safety Manual IMPORTANT SAFETY NOTICE
Industrial Process Pump Safety Manual IMPORTANT SAFETY NOTICE To: Our Valued Customers User safety is a major focus in the design of our products. Following the precautions outlined in this manual will
CONTINGENCY PLANNING FOR DISRUPTED ELECTRIC POWER: The Case for Partnering with a Strong Rental Power Supplier
CONTINGENCY PLANNING FOR DISRUPTED ELECTRIC POWER: The Case for Partnering with a Strong Rental Power Supplier CONTINGENCY PLANNING FOR DISRUPTED ELECTRIC POWER: The Case for Partnering with a Strong Rental
Element D Services Plumbing
PART 1 - GENERAL 1.01 OVERVIEW A. This section addresses domestic cold, hot and hot water return distribution systems within and to five feet beyond building perimeter. PART 2 - DESIGN CRITERIA 2.01 GENERAL
CDS TROUBLESHOOTING SECTION I. VACUUM. 1.0. Weak vacuum at wand. Gauge reads normal (10hg to 14hg)
CDS TROUBLESHOOTING SECTION I. VACUUM 1.0. Weak vacuum at wand. Gauge reads normal (10hg to 14hg) 1.1. Clogged hoses or wand tube. Disconnect hoses and carefully check for an obstruction. 1.2. Excessive
Planned and Emergency Utility Outage Guidelines
Revised: April 4, 2014 GUIDELINES: PURPOSE: The purpose of these guidelines is to define roles and responsibilities in requesting, coordinating scheduling, and executing utility outages and restoration
BUILDING OWNERS - SERVICE RELATED ISSUES FOR FIRE ALARM SYSTEMS
BUILDING OWNERS - SERVICE RELATED ISSUES FOR FIRE ALARM SYSTEMS Owners have numerous responsibilities as it pertains to the maintenance and operation of a building s fire safety equipment. The liabilities
Fire Safety Log Book
Fire Safety Log Book Company... Address........ Responsible Person. Competent Person. Date Started For Additional Information: Safety Management (UK) Ltd Holme Suite, Clawthorpe Hall Business Centre, Burton
32:(5#5$7,1* 4833#USP283#+] 4;33#USP293#+] 3ULPH 113 kva, 90 kw 124 kva, 99 kw 6WDQGE\ 114 kva, 91 kw 125 kva, 100 kw
,1'8675,$/#*(16(7 6HULHV#'9#448 32:(5#5$7,1* 4833#USP283#+] 4;33#USP293#+] 3ULPH 113 kva, 90 kw 124 kva, 99 kw 6WDQGE\ 114 kva, 91 kw 125 kva, 100 kw Generator set consisting of engine and alternator mounted
LOCKOUT/TAGOUT (LOTO) SAFETY PROGRAM
1 UNIVERSITY OF WEST FLORIDA LOCKOUT/TAGOUT (LOTO) SAFETY PROGRAM (EQUIPMENT HAZARD DE-ENERGIZING AND ISOLATION) DEPARTMENT OF ENVIRONMENTAL HEALTH AND SAFETY 11000University Parkway Pensacola, FL 32514
Fire Alarm and Protection Impairment Policy and Procedures
1.0 Policy Statement The University of New Haven has developed a Fire Alarm and Protection Impairment Plan in accordance with the National Fire Protection Associations (NFPA) codes. Specific codes referenced
May, 1977. ArACBMENT I. Review of. Diesel Generator Alan and Control Circuitry. Indian Point Units No. 2 and 3. Docket Nos.
ArACBMENT I Review of Diesel Generator Alan and Control Circuitry Indian Point Units No. 2 and 3 Docket Nos. 50-247 and 50-286 May, 1977 8111230361 770519 PDR ADOCK 05000247 P.. PDR) Question (a) Identify
AIR-CONDITIONER SPLIT TYPE
FILE NO. A08-016 SERVICE MANUAL AIR-CONDITIONER SPLIT TYPE RAS-M10PKVP-E, RAS-M13PKVP-E, RAS-M16PKVP-E, RAS-M18PKVP-E / RAS-M10PKVP-ND, RAS-M13PKVP-ND, RAS-M16PKVP-ND, RAS-M18PKVP-ND / RAS-3M26GAV-E1,
Fire Pump Plan Review March 2010
Fire Pump Plan Review March 2010 Date of Review: / / Permit Number: Business/Building Name: Address of Project: Designer Name: Designer s Phone: Contractor: Contractor s Phone: Occupancy Classification:
PC1130 Electric Air Compressor
Senco Products Inc. 8485 Broadwell Road Cincinnati, Ohio 45244 PC1130 Electric Air Compressor Operating Instructions 2006 by Senco Products, Inc. Warnings for the safe use of this tool are included in
AIR CONDITIONER INSTALLATION MANUAL
INSTALLATION MANUAL AIR CONDITIONER Please read this installation manual completely before installing the product. Installation work must be performed in accordance with the national wiring standards by
Fire Safety Plan (Single-Stage Fire Alarm System - Small Establishment)
1 Fire Safety Plan (Single-Stage Fire Alarm System - Small Establishment) Fire Safety Plan Single-Stage Fire Alarm System (small establishment) for: (Business Name) (Business Address) The reproduction
ENGINE COOLING SYSTEM
ENGINE COOLING SYSTEM 1988 Toyota Celica 1987-88 TOYOTA Engine Cooling Systems Celica DESCRIPTION The basic liquid cooling system consists of a radiator, water pump, thermostat, cooling fan, pressure cap,
IMPLEMENTING THE NEW ELECTRICAL SAFETY REQUIREMENTS
IMPLEMENTING THE NEW ELECTRICAL SAFETY REQUIREMENTS Paul A Zoubek, CSP, CIH Occupational Services, Inc. San Diego, CA 619-861 861-0612 [email protected] OCCUPATIONAL SERVICES, INC. BACKGROUND Update Update
Manual for Fire Suppression & Methane Detection System
Manual for Fire Suppression & Methane Detection System Fogmaker North America Post address: 150 Gordon Dr Exton, PA 19341 Delivery address: 150 Gordon Dr Exton, PA 19341 Tel: 610-265-3610 Fax: 610-265-8327
Dehumidifier Users manual. For Models: DH45S DH65S
Dehumidifier Users manual For Models: DH45S DH65S 950-0062-revD Jan. 9 2007 FORWARD The appearance of the units that you purchase might be slightly different from the ones described in the Manual, but
Equipment Breakdown. The extended property coverage you need for the equipment you rely on.
Equipment Breakdown The extended property coverage you need for the equipment you rely on. Equipment Breakdown When it comes to protecting the equipment and machinery you need to keep your business operating
FIRE ALARM AND DETECTION SYSTEMS SECTION 16721
PART 1 - GENERAL 1.01 WORK INCLUDED FIRE ALARM AND DETECTION SYSTEMS SECTION 16721 A. Provide a complete fully addressable, power limited, fire detection and evacuation system. The system shall be connected
SECTION 15750 PACKAGED ROOFTOP AIR CONDITIONING UNITS
SECTION 15750 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes requirements for roof mounted, self-contained units, with electric cooling, and electric or reverse refrigeration cycle (heat pump) heating
Preventative Maintenance Plan. Guide. The Simple, Smart Way To Properly Care For Home Systems And Appliances.
Preventative Maintenance Plan Guide The Simple, Smart Way To Properly Care For Home Systems And Appliances. Protect. Prevent. Preserve. Prolong. What AHS Preventative Maintenance Plans Can Do For Your
NewAir AC-14100E / AC-14100H Portable Air Conditioner Owner s Manual PLEASE READ AND SAVE THESE INSTRUCTIONS
NewAir AC-14100E / AC-14100H Portable Air Conditioner Owner s Manual PLEASE READ AND SAVE THESE INSTRUCTIONS PARTS LIST Front Back FIG.5 FIG.6 1. Control panel 2. Carrying handle 3. Water tank 4. Casters
Master Workplace Inspection Checklist for General Shop Safety. MASTER WORKPLACE INSPECTION CHECKLIST General Shop Safety
Integrated Risk Management Master Workplace Inspection Checklist for General Shop Safety Document Type: Form Control Number: UIRM- FM_012_50 File Code: UIRM-001 Last Reviewed: March 2014 Department/Unit:
Recommended Practice for Installation of Transit Vehicle Fire Protection Systems
Recommended Practice for Installation of Transit Vehicle Fire Protection Systems Approved October 25, 2007 APTA Fire Safety Working Group Approved May 3, 2008 APTA Bus Safety Committee Approved October