Case Study -Sandy Grove Middle School First Net Positive Energy P3 School In North Carolina
|
|
|
- Aron Porter
- 10 years ago
- Views:
Transcription
1 Case Study -Sandy Grove Middle School First Net Positive Energy P3 School In North Carolina
2 Public-Private Partnership (P3) Government - provides incentive(s): transfer of asset (land), one time grant, tax breaks / credits Developer obtains incentive(s), obtains financing, designs, builds, may maintain User(s) Leases facility and site, operates and utilizes facility, may be responsible for utility cost and some maintenance
3 Advantages of P3 Delivery Harness expertise and efficiency of private sector Off-balance sheet method of financing the delivery of public sector assets Speed of delivery Possible Tax Credits / Breaks Energy tax credits Potential New Market Tax Credit Eliminates Bid Day Risk Eliminates Construction Risk Reduces Risk of Rate Inflation
4 Public-Private Partnership (P3) Integrated Design, Build, Finance, Operate Solutions Design Build Finance Operate
5 SGMS -Organization / Roles
6 Sandy Grove Middle School Project Team Owner / Developer Design Architect M/E/P Engineers Commissioning Authority General Contractor / CM
7 Sandy Grove Middle School GYMNASIUM STEM School 74,000 SF, designed for 624 students CLASSROOMS SCIENCES High Performance Systems BAND ORCHESTRA ADMIN Ground Source Geothermal CHOIR High Output LED Lighting CLASSROOMS SCIENCES LAB MEDIA CENTER DINING Load Bearing Masonry Enhanced Building Automation and Resource Monitoring Systems ART KITCHEN Solar Photovoltaic (589 kw) CLASSROOMS KITCHEN SCIENCES
8 Other Sustainability Features Enhanced envelope with 6 inches of rigid insulation in roof and 3 inches of spray foam insulation in exterior walls High efficiency plumbing features reduce water consumption by 40% Three electric vehicle charging stations free to User powered by school s solar panels 75% of construction waste was diverted, 20% of construction materials contained recycled content and 30% was produced in the region Furniture is certified green
9 Sandy Grove Middle School Benefits of Leasing School Project delivered (school constructed) in 12 months Energy Positive: Generates 30% - 40% more electricity than it consumes Estimated it will save county approx. $35 million over next 40 years - ($16 million in energy) Designed to LEED Platinum Standards PV and New Market Tax Credits Reduce the total cost of ownership by approximately 70% o Construction, interest and energy
10 Sandy Grove Middle School Life Cycle Cost
11 Sandy Grove Middle School Leasing Energy Positive Schools Energy Positive vs. Traditional Schools
12 Solar Photovoltaic System Local utility is Lumbee River Electrical Cooperative 589 kw PV system is split between two metered systems 504 kw is grid connected and is sell all, electricity feeds the grid and the Owner receives a check from the utility company 85kW PV ties in on building side of second meter; offsetting what is purchased from the grid System oversized to eliminate power bill; since cost is $0.128/kWH and payment is $0.051/kWH
13 Solar Photovoltaic System Solar Panels by REC high performance 250 PE BLK panels 2,310 roof mounted panels can produce 751 MWh annually, 40% more than the school will need Design and installation by PowerSecure Inc. Modules connected in strings (typically eight (8) modules per string), which in turn are collected in combiner boxes for sub arrays. Small weather station on roof tied thru the data acquisition system to the BAS
14 Solar Photovoltaic System Checklists and measurements for Solar PV System Combiner box checks DC voltage, Amperage, Irradiance, ambient temperature DC Megger Test - Ground Inverter installation and start-up For inverters DC input voltage, AC line voltage, comparison between inverter panel readings and field measurements. System operation in kw, summary of PV system output
15 Solar Trees by Spotlight Solar Four trees each 20 ft. tall with 12 solar panels Contribute 12 kw of power Solar design combining clean energy with solar art
16 Stand-by Generator 600kW generator, currently enrolled in demand response program with local utility Automated tie-in under Utility company control to run during peaks 30 minutes to 2 hours Negotiating with utility to employ generator to feed into grid to help during peak demand periods Electrical peak occurs during summer when school is not in session and limited cooling load on the campus.
17 LED Lighting Over 80% of indoor and exterior lighting is LED LEDs use 60% less energy than standard fluorescent fixtures and emit less heat Interior lighting, base specification 3-lamp 32W T8 troffers 90W Interior lighting, upgrading to LED 40W LED troffers Immediate reduction of 56% in energy use Lighting controls included occupancy sensors, schedules and daylighting
18 Geothermal Heat Pump System Geothermal well field with approx. 192 wells, 4½ in diameter, approx. 300 feet deep Primary / secondary pumping systems with VFDs
19 Zone Water Source Heat Pump (WSHP) Zones served by horizontal or vertical WSHP Some with dedicated OA ducts Most equipped with two (2) compressors
20 Water-to-Water Heat Pump for DHW Domestic hot water primary by a water to water heat pump Gas-fired boiler for back-up System equipped with 400 gallon storage tank and recirculating pumps
21 Dedicated Outdoor Air Systems DOAS units with energy recovery wheels and integral controls VFDs and CO 2 sensors control volume of ventilation First stage heating / cooling during low load or unoccupied periods
22 Geothermal Heat Pump System Common Issues Flow TAB contractor proportionally balanced the water for the WSHP and WWHP, but did not do a final balance with all valves open, because there was not a global command from Siemens for this purpose. WSHP had many compressor failures due to inadequate flow once all systems were online. Ground Water Temperature o Design sequences required the loop temperature be kept between 63 F-77 F, yet WSHP/DOAS schedules indicated cooling capacity based on 85 F EWT and heating on 50 F EWT Outside Air Temperature o Delicate balance, OAT may generate a call for cooling when the GWT is too cold for cooling, causing compressor failures
23 Zone Water Source Heat Pumps Common Issues WSHPs and the WWHP were approved as BACnet/IP. Siemens BAS was BACnet/IP as well. However, WSHPs & WWHP arrived on site with BACnet/MSTP. Limited points for Siemens to have dynamic graphics, and control of units. Reprogramming occurred. WSHP integral controls not sourced to BAS. This was preventing the units from going into unoccupied mode. When the WSHP did not go to unoccupied mode, it prevented the geothermal system from going into unoccupied mode. The heating CFM was too low for some WSHP with two compressors. Compressors were going out on high pressure alarm. WSHPs with factory CO 2 controls would not go into unoccupied mode if the CO 2 sensors were enabled by the BMS. The room thermostats provided came with a slider control that allowed +/-5 F from the heating and cooling setpoints. This control could not be overridden from the BMS, so the control setpoints of 74 /70 F became 79 /65 F.
24 Dedicated Outdoor Air Systems Common Issues DOAS units were not controlling temperature based on the demand from the WSHP, as per design. They controlled off their own internal DAT. TAB contractor set water parameters at each DOAS, similar to the WSHP & WWHP, the global command for all units was not performed. DOAS had integrated control system and Siemens was limited to the manufacturer s BAS points. o DOAS and WSHP were not giving BMS a signal to start from the unoccupied mode (CO 2, high humidity, high/low temperature), so they were starting but the geothermal system was not.
25 Lessons Learned Perform conductivity well / loop testing: to ensure the loop will produce the temperatures / tonnage required and that the loop will dissipate heat to the surrounding earth. Conduct a controls meeting prior to the controls submittal. Many interpretations were made by the CC that were incorrect requiring reprogramming. Also need to coordinate multiple subcontractors / suppliers with different automation logic / communication protocols: Modbus, LON, BACnet/IP, BACnet/MSTP Ensure lighting controls and CO 2 sensors are coordinated with the CC submittal. CO 2 ppm need to be monitored and set back when areas are unoccupied during normal hours. Owner / Engineer to ensure that continuous monitoring of BAS system after occupancy is part of the BAS specification. Owner / Engineer ensure the understanding of the building occupancy schedules (normal & holiday) for set back of systems and adherence to energy model.
26 Controls Integration Challenge Siemens Building Automation System - Apogee BAS system - Direct control Geothermal condenser water system - Interface with WSHP, DOAS, Solar PV, Resource Monitoring, Dashboard PV Data Acquisition System Affinity Automation, LLC - Resource monitoring measure and verify utilities - Utilitrend cloud-based energy tracking, trending & reporting tool - Works with meter and automation systems MODBUS, LonWorks and BACnet Lucid Dashboard - Web-based showing building performance and energy usage - Linked to a kiosk in the lobby and smart boards in the classrooms - Shows live performance, as well as historic utility data
27 Lucid Dashboard Tracks building system(s) or submeter(s) and display information (like weather), as frequently as once per minute Enables energy and water reduction competitions Showcases real time system performance and building green features Can be incorporated in interactive wall mounted panels and kiosks, or through the internet.
28 Sandy Grove Middle School 28
29 Awarded ENR Best Project 2013 (K-12 Education Project) Sandy Grove Middle School
30 Thank You!
Rules of Thumb Energy Efficiency in Buildings
Energy Efficiency in Buildings Energy Savings Cost Savings Increased Productivity Economic Development Other Standard lighting retrofits: $0.90-$1.20 per square foot. High-efficiency packaged and split
BPC Green Builders. Green building for new and existing homes. Health Comfort Energy
BPC Green Builders Green building for new and existing homes Health Comfort Energy Mechanical Systems Installed HVAC Systems Primary energy source large, roof mounted, solar thermal array (AET flat plate)
The ASHRAE HQ Building Can the energy efficiency of the different mechanical systems really be compared? RESIDENTIAL LIGHT COMMERCIAL COMMERCIAL
The ASHRAE HQ Building Can the energy efficiency of the different mechanical systems really be compared? RESIDENTIAL LIGHT COMMERCIAL COMMERCIAL Technical Article April 2013 The ASHRAE HQ Building Can
MECHANICAL PROJECT PROPOSAL
PSUAE MECHANICAL PROJECT PROPOSAL REDESIGN PROJECT Nicholas B Scheib 2010 M e c h a n i c a l O p t i o n - IP Table of Contents Executive Summary... 2 Project Summary... 3 Existing Mechanical System Summary...
Bring the fresh in. Dedicated Outside Air Systems
Bring the fresh in. Dedicated Outside Air Systems The inside story on outside air. On average, we breathe in 3,400 gallons of air each day. Ambient indoor air pollution is a major problem, affecting health
HVAC For Schools How to purchase an HVAC system that meets your school s unique requirements and stays within your budget
A PRIMER Educational HVAC For Schools How to purchase an HVAC system that meets your school s unique requirements and stays within your budget Contents: Introduction: The best HVAC system is durable, reliable
Solar Power at Vernier Software & Technology
Solar Power at Vernier Software & Technology Having an eco-friendly business is important to Vernier. Towards that end, we have recently completed a two-phase project to add solar panels to our building
2009 Seattle Energy Code Impacts: See below for a recap of Changes in Envelope performance from 2006 to 2009
2009 Seattle Energy Code Impacts: Building Envelope Impacts: Below is a Summary of Changes that impact building envelope construction planned for 624 Yale. There are several modifications are required
HVAC Processes. Lecture 7
HVAC Processes Lecture 7 Targets of Lecture General understanding about HVAC systems: Typical HVAC processes Air handling units, fan coil units, exhaust fans Typical plumbing systems Transfer pumps, sump
Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings
Advanced Energy Design Guide LEED Strategies for Schools and High Performance Buildings Today s Presenters Stephen Koontz, LEED AP Energy Services Leader Tampa Bay Trane Allen Irvine General Sales Manager
CGC s Hybrid System Loop Control
verview The CGC Group Hybrid Heat Pump System does NT operate with the same fluid loop temperatures as a conventional reversing Water Source Heat Pump system. The CGC system differs from a WSHP system
Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues
Design Guide Retrofitting Options For HVAC Systems In Live Performance Venues Heating, ventilation and air conditioning (HVAC) systems are major energy consumers in live performance venues. For this reason,
Collaborative Laboratory Commissioning and Sustaining the Optimal Building. By E. Lon Brightbill, P.E Facility Dynamics
Collaborative Laboratory Commissioning and Sustaining the Optimal Building By E. Lon Brightbill, P.E Facility Dynamics Overview DefineCommissioning (Cx) Put the Cx process in the Context of a State of
Condensing Boiler Efficiency
Condensing Boiler Efficiency Date: July 17, 2012 PRES E NT ED BY DO N L E O NA RDI LE O N A RD I I NC. HV AC T RAI N I N G & C ON SU LT IN G Concepts 1 The current state of evolution in boiler design 2
RENOVATION OF SCHOOL #171 SPORT COMPLEX
RENOVATION OF SCHOOL #171 SPORT COMPLEX ADDRESS: NUTSUBIDZE PLATO III M/R TBILISI GEORGIA LTD SAKPROEKTI DESIGNED BY P. SAKHANBERIDZE N. SACHALELI G. MANDARIA N SITUATION PLAN NUTSUBIDZE PLATO III M/R
Statement of Work. 3.0 Details of Service Pre Start-up. - 1 - Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary
Installation Service Statement of Work - 1 - Cooling Start-up Service Cooling Start-up Service Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details
NEW JERSEY CENTER OF EXCELLENCE
Overview NEW JERSEY Page 1 The Plant (CUP) provides electricity via a cogeneration system, chilled water for environmental cooling, steam for heating, and compressed air primarily for HVAC control Serves
ENERGY AUDITS AND RETRO- COMMISSIONING Local Law 87
ENERGY AUDITS AND RETRO- COMMISSIONING Local Law 87 Overview Although energy-efficiency retrofits generally result in major cost and energy savings, many buildings are not participating in the audits that
Each icon on this map represents the physical location of a station.
ABBOTSFORD SCHOOL DISTRICT: GREEN TOUR TOMORROW S SUSTAINABLE SOLUTIONS TODAY Welcome to the Abbotsford School District: Green Tour. Our goal is to create an interactive learning experience for visitors
Richardsville Elementary The First Net Zero Energy Public School in the U.S. Installations Conference
Richardsville Elementary The First Net Zero Energy Public School in the U.S. Presented to: ARMY Net Zero Energy Installations Conference Kenneth L. Seibert, PE, LEED AP Kenny Stanfield, AIA, LEED AP January
Technical Specifications for West Campus Data Center HVAC System
Technical Specifications for West Campus Data Center HVAC System I. Mechanical Systems Requirements A. HVAC Primary Data Centers, Automation HVAC is to be provided on a 24 hours per day, 365 days per year
Proof of Concept - Solar Energy DG Distribution Warehouse
Proof of Concept - Solar Energy DG Distribution Warehouse This is for a proof of concept for a high efficiency renewable energy lighting system at a Distribution Center in Rochester, NY. This LEED gold-rated
SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE
SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE for solar energy management LEATEC Delivering Solutions for Energy Management SOLAR ENERGY DATA CENTER BUILDING 4 to8 String Monitoring with 0.% Accuracy
Energy Conservation Audits for Six Performing Arts Facilities A Toronto s Green Theatres Project
Energy Conservation Audits for Six Performing Arts Facilities A Toronto s Green Theatres Project Anthony Marshall, P.Eng., CEM January 2012 For Creative Trust for Arts & Culture Table of Contents Introduction
A SOLAR GUIDE - EVERYTHING YOU NEED TO KNOW
WE BRING GREEN SOLUTIONS TO YOU A SOLAR GUIDE - EVERYTHING YOU NEED TO KNOW Provided by A COOLER PLANET A Cooler Planet 1 The Complete Solar Guide WHY GO SOLAR? TOP FIVE FACTORS TO CONSIDER FOR ADDING
Green Buildings Guidelines for Harvard
Green Buildings Guidelines for Harvard Presentation to the Administrative Deans. October 26th 2007 Leith Sharp, Director, Harvard Green Campus Initiative What is a Green Building? Average Savings of Green
Geothermal Heat Pumps: A Pathway to Zero Net Energy (ZNE) for Schools, Homes and Businesses
Lisa Meline, P.E. Meline Engineering Corp. [email protected] Office: 916.366.3458 Geothermal Heat Pumps: A Pathway to Zero Net Energy (ZNE) for Schools, Homes and Businesses Session C: Institutional Applications
Xcel Business Customers: Program and Rebate Summary
Xcel Business Customers: Program and Rebate Summary Rebates for New Energy-Efficient Equipment Xcel offers prescriptive rebates to its business customers. What s a prescriptive rebate? It simply means
Center for Energy Education Laboratory
Paper ID #7072 Center for Energy Education Laboratory Dr. Robert Gilbert, Sinclair Community College Robert B. Gilbert, Ph.D., LEED AP, BA, is an Associate Professor of Energy Management Technology, and
Hybrid heat pumps. saving energy and reducing carbon emissions
Hybrid heat pumps saving energy and reducing carbon emissions Bart Aspeslagh Product planning and new technology manager, Daikin Europe NV. [email protected] Stefanie Debaets Design engineer,
Solar and Wind Energy for Greenhouses. A.J. Both 1 and Tom Manning 2
Solar and Wind Energy for Greenhouses A.J. Both 1 and Tom Manning 2 1 Associate Extension Specialist 2 Project Engineer NJ Agricultural Experiment Station Rutgers University 20 Ag Extension Way New Brunswick,
ENHANCED LABORATORY HVAC SYSTEM
ENHANCED LABORATORY HVAC SYSTEM INTRODUCTION Since the early 1980's the attention to more energy efficient laboratory designs has been on the rise due to the increase in energy cost and the emergence of
J O U R N A L. Energy Performance for. Proper Specification of Air Terminal Units Future Climate Impacts on Building Design
Copyright 24, American Society of Heating, Refrigerating & Air-Conditioning Engineers, Inc., 79 Tullie Circle NE, Atlanta, GA. 3329. Reprinted by permission from the September 24 Issue of ASHRAE Journal
Heating & Cooling Efficiency
Heating & Cooling Efficiency Advantages of Geothermal HVAC Efficiency Keith Swilley Gulf Power Company Why Gulf Power Promotes Energy Efficiency? Customer Satisfaction Education Help Customers Make Smart
Integrated Solar Radiant Systems
Integrated Solar Radiant Systems William Shady PE President Topics Radiant heating Indoor air quality Radiant Cooling Project Photos Questions and answers The goal for our clients Healthy Comfort Why Radiant
Princeton University Microgrid
Princeton University Microgrid IDEA evolvingenergy Conference Toronto, Canada 28th 30th October 2014 Edward Ted Borer, PE [email protected] Overview Campus Energy Demands Energy Plant Equipment Combined
TOWER RENEWAL CASE STUDY
TOWER RENEWAL CASE STUDY Energy Monitoring and Management: A Case Study of Brentwood Towers, Toronto Executive Summary Through good management, and new technologies, O Shanter Development has achieved
Air Conditioning. The opportunity for energy efficiency. Low cost actions to reduce energy usage now
Fact Sheet #6 Air Conditioning In this fact sheet you will discover: The opportunity for energy efficiency How air conditioning works Low cost actions to reduce energy usage now Investments to reduce costs
Vitocaldens 222-F Compact Gas-Hybrid appliance
Vitocaldens 222-F Compact Gas-Hybrid appliance Heating systems Industrial systems Refrigeration systems 2/3 Vitocaldens 222-F: The future-proof energy-source mix in one appliance Choosing Vitocaldens
Tysons Sustainability Summit Evidence Based Urban Design. Roger E. Frechette III, PE, LEED-AP
Tysons Sustainability Summit Evidence Based Urban Design 2013 Autodesk Roger E. Frechette III, PE, LEED-AP Live in Harmony with Nature Transit Community Energy Waste Air Quality Water Yujiapu Financial
UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01
GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per
Help. Help Software Tutorial. Building a load sizing project with an ME Series Humidifier
Help Help Software Tutorial Building a load sizing project with an ME Series Humidifier 502-B 18 Aug 2015 Help Tutorials provide step-by-step examples of complete load sizing projects and browser projects
Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks
Presentation Outline Common Terms / Concepts HVAC Building Blocks Plant Level Building Blocks Description / Application Data Green opportunities Selection Criteria Air Distribution Building Blocks same
EarthCents (DSM) Program Summary
EarthCents (DSM) Program Summary Renewable Energy EarthCents Programs Solar Water Heating This program is available to residential customers for the installation of a qualifying solar thermal water heater.
Example Retrocommissioning Measure: Opening Throttled Discharge Valves
Opening Throttled Discharge Valves This 21-story building, constructed in 1997, is located in Oregon and contains 589,000 gross square feet of mostly office occupancy. The HVAC system includes six large
Metering for today s systems
Metering for today s systems The sub-meter gathers data on the building side of the utility company meter. This allows us to break out usage so data can be collected from individual circuits, a single
Achieving ENERGY EFFICIENCY with Standard Air-Conditioning Units. Mike West, PhD, PE Advantek Consulting, Inc
Achieving ENERGY EFFICIENCY with Standard Air-Conditioning Units Mike West, PhD, PE Advantek Consulting, Inc Standard Air Conditioning Unit Packaged Unit Split System DX (not chilled water) Air-cooled
Hybrid Geothermal / Solar Thermal HVAC System: Part1 Design (OU Human Health Building)
Integrating Large Scale, Innovative Solar Thermal Systems into the Built Environment June 26, 2013 11:00am 12:30PM Track: Renewable & Alternative Energy Sources Sponsor: 6.7 Solar Energy Utilization Hybrid
The ABC s of VRF: A Green HVAC Technology An Ideal Green School Solution. Presented by: Fujitsu General America, Inc.
The ABC s of VRF: A Green HVAC Technology An Ideal Green School Solution Presented by: Fujitsu General America, Inc. What to look for in a Green HVAC solution? What if your HVAC system could provide Individual
Energy Efficiency. Bars & RestauRants. www.energia.ie
Energy Efficiency Bars & RestauRants www.energia.ie 2 Your chance to reduce your business energy usage by as much as 20%! 20% is a significant figure and reducing your energy bill by this amount could
KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM
KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM AIR HANDLING UNITS... 1 CHILLERS... 2 COOLING TOWERS... 2 CLOSED LOOP COOLERS... 2 MISCELLANEOUS SUPPLY FANS...
Geothermal Heat Pump Systems
Geothermal Heat Pump Systems GeoExchange Technology Curtis J. Klaassen, P.E. Iowa Energy Center Energy Resource Station Geothermal Heat Pump Technology Introduction What is Geothermal Energy? Geothermal
How To Use A Water Source Heat Pump
Geothermal Energy Using Water-Source Heat Pumps By VIRSTAR Corporation Geothermal Expertise Since 1978 All information contained herein is the exclusive property of VIRSTAR Corporation, all rights reserved.
Introduction To VRF: System Overview, Applications, & Savings Opportunities
Introduction To VRF: System Overview, Applications, & Savings Opportunities System Overview What is VRF? Zoning System Two-Pipe / Three Pipe System Packaged DDC Control Operates as a Heat Pump Simultaneous
Green House, Hungary
Further information Skanska AB www.skanska.com Contact Noel Morrin, SVP Sustainability & Green Support [email protected] Green House, Hungary Case Study 109 Aspects of Sustainability This project
Energy Efficiency HOSPITALITY. www.energia.ie
Energy Efficiency HOSPITALITY www.energia.ie Your chance to reduce your business energy usage by as much as 20%! 20% is a significant figure and reducing your energy bill by this amount could make a real
Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY
SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. HVAC Commissioning description. 2. HVAC Commissioning responsibilities. 1.2 REFERENCES A. American Society
Photo Kirklees IS SOLAR ENERGY FOR ME? A guide to going solar
Photo Kirklees IS SOLAR ENERGY FOR ME? A guide to going solar WHY SOLAR? Economics Solar energy can reduce bills, earn you money and protect you from rising energy prices. Solar is a free source of energy
Industrial Green Building Retrofit 101 Opportunities and Challenges. Light Industrial Green Building Retrofits. Why Green Retrofit?
Industrial Green Building 101 Opportunities and Challenges Joanne Sawatzky Senior Project Manager, Light House Sustainability at Work Re-visioning a Sustainable False Creek Flats Light Industrial Green
Introduction to Building Automation Systems (BAS)
Introduction to Building Automation Systems (BAS) Ryan R. Hoger, LEED AP 708.670.6383 [email protected] Building Automation Systems Centralized controls Change scheduling for multiple HVAC units
A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.
DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly
City of Cornwall Social Housing Division Top 10 Energy & Water Saving Tips. in Multi-Unit Residential Buildings
City of Cornwall Social Housing Division Top 10 Energy & Water Saving Tips in Multi-Unit Residential Buildings Duncan Hill Canada Mortgage and Housing Corporation Andrew Pride Minto Developments Inc. Energy
Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES
SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work
Free electricity for your home, offices or factory with solar PV panels
Free electricity for your home, offices or factory with solar PV panels Who we are Easy Being Green helps customers reduce their household s energy consumption by using energy saving products. Easy Easy
E-Version SECTION 15318 - CHLORINATION SYSTEM PART 1 - GENERAL PART 2 - PRODUCT
SECTION 15318 - CHLORINATION SYSTEM PART 1 - GENERAL 1.1. SCOPE OF WORK A. Under this item the Contractor shall furnish and install a sodium hypochlorite solution metering system complete with all accessories
SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP
research journal 2013 / VOL 05.01 www.perkinswill.com SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP ARCHITECTURE AND ENGINEERING OF SUSTAINABLE BUILDINGS Current Trends in Low-Energy HVAC Design
BSD Technical Standard Division 23: HVAC
Division 23: HVAC I. PURPOSE This technical standard is a narrative describing Beaverton School District s (BSD s) Basis of Design for mechanical systems and heating, ventilation, and air conditioning
Mount Wachusett Community College. Energy Conservation & Conversion : A Cost Sharing Approach
Mount Wachusett Community College Energy Conservation & Conversion : A Cost Sharing Approach Critical Issues The rising and disproportionate costs of energy in the Northeast The Nation s continued dependence
Solar Energy. Airports Going Green Aimee Fenlon
Solar Energy Airports Going Green Aimee Fenlon 1 Renewable vs. Non-Renewable Electrical Generation Renewables: Source Advantages Disadvantages Solar PV No CO2; Needs no Fuel Intermittent no power at night,
Greenhouse Gas Implications of HVAC Upgrades in Multi-Unit Residential Buildings
Greenhouse Gas Implications of HVAC Upgrades in Multi-Unit Residential Buildings J A NUARY 2015 INTRODUCTION This Research Report explores best practices and approaches for reducing greenhouse gas (GHG)
Request for Proposal. Solar Power Purchase Agreement
Request for Proposal Solar Power Purchase Agreement Solicitation The Town of Carbondale, Colorado is soliciting proposals from a qualified Contractor/Vendor to design, fabricate, deliver, install, operate,
Tim Sisson - Trane HVAC OVERVIEW
Tim Sisson - Trane HVAC OVERVIEW HVAC Systems System Types Acoustics Controls Modernization more than one Down to the Studs Opportunity for new System Type Renovation Possible opportunity for new System
Request for Proposals for Photovoltaic System Installation
Request for Proposals for Photovoltaic System Installation Presented by: Prepared by: Location: Contact: Date: Capitol Hill Housing Foundation Bonneville Environmental Foundation, Renewable Energy Group
The main steam enters the building in the basement mechanical room; this is where the condensate line also leaves the building.
MSV: Square Footage: 24,844 No. of Floors: 1 Year Built: 1963 Type of Use: Lounge and dining area open all night for snacks Steam Water-cooled condenser, 50-Ton York unit with a 6 cylinder-reciprocating
HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY
HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY Benson Kwong, CVS, PE, CEM, LEED AP, CCE envergie consulting, LLC Biography Benson Kwong is an independent consultant providing
Energy Design Resources Commissioning Plan Outline Template
IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended
Liebert Hiross HPW The High Performance Wallmount Cooling Solutions for Telecom Mobile Remote Access Nodes
Precision Cooling for Business-Critical Continuity Liebert Hiross HPW The High Performance Wallmount Cooling Solutions for Telecom Mobile Remote Access Nodes We re Emerson Network Power, backed by Emerson,
Consumers Energy Business Solutions. Commercial and Industrial Energy Efficiency Program April 18, 2013
1 Consumers Energy Business Solutions Commercial and Industrial Energy Efficiency Program April 18, 2013 Ralph Huston Energy Advisor Consumers Energy Business Solutions 3965 Okemos Rd. Ste. A-1 Okemos,
Case Study: Opportunities to Improve Energy Efficiency in Three Federal Data Centers
Case Study: Opportunities to Improve Energy Efficiency in Three Federal Data Centers Prepared for the U.S. Department of Energy s Federal Energy Management Program Prepared By Lawrence Berkeley National
Smart Integration of Wireless Temperature Monitoring System with Building Automation System
Smart Integration of Wireless Temperature Monitoring System with Building Automation System Case Study Area of engagement Solution to integrate wireless temperature monitoring system with BMS (Building
SDG&E s - Sustainable Communities Program
SDG&E s - Sustainable Communities Program February 21, 2014 Pete Pavao 2013 San Diego Gas & Electric Company. All copyright and trademark rights reserved. Overview SDG&E Sustainable Communities Program
newsletter engineers energy-saving strategies for Water-Source Heat Pump Systems volume 36 2 providing insights for today s hvac system designer
engineers volume 36 2 newsletter providing insights for today s hvac system designer energy-saving strategies for Water-Source Heat Pump Systems from the editor... Water-source heat pump (WSHP) systems
Carnegie Mellon University School of Architecture, Department of Mechanical Engineering Center for Building Performance and Diagnostics
Carnegie Mellon University School of Architecture, Department of Mechanical Engineering Center for Building Performance and Diagnostics A Presentation of Work in Progress 4 October 2006 in the Intelligent
Gas Absorption Heat Pumps. Future proofing your heating and hot water
Gas Absorption Heat Pumps Future proofing your heating and hot water Gas Absorption Heat Pumps 1 Contents Gas Absorption Heat Pumps (GAHPs) The heating solution What is a Gas Absorption Heat Pump? How
POMONA COLLEGE Sustainability Integration Office Facilities and Campus Services
POMONA COLLEGE Sustainability Integration Office Facilities and Campus Services May 200 Table of Contents NEW CONSTRUCTION/MAJOR RENOVATION Process... Design... 3 MINOR RENOVATIONS/PROJECTS Process...
Using Time-of-Day Scheduling To Save Energy
The following article was published in ASHRAE Journal, May 29. Copyright 29 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. It is presented for educational purposes only.
Catalyst RTU Controller Study Report
Catalyst RTU Controller Study Report Sacramento Municipal Utility District December 15, 2014 Prepared by: Daniel J. Chapmand, ADM and Bruce Baccei, SMUD Project # ET13SMUD1037 The information in this report
Forty-one miles of submerged coils that heat and cool a high school of 2,400 students.
ACKNOWLEDGEMENTS Architects: Bray Associates Architects, Inc., Sheboygan, Wisconsin Energy consultant: CDH Energy Corporation, Evansville, Wisconsin Energy management system: J&H Controls, Inc., Fond du
Variable Air Volume - VAV
Mode Enable Sensor Options Variable Air Volume - VAV The temperature of this sensor will determine if the unit is in heating, cooling or vent mode during occupied operation. The following options are available:
Achieving Net Zero. Bradley Berneche, President Alouette Homes. National Marketing Committee Canadian Home Builders Association Ottawa, June 6, 2008
Achieving Net Zero Bradley Berneche, President Alouette Homes National Marketing Committee Canadian Home Builders Association Ottawa, June 6, 2008 Overview Who Is Alouette Homes? The EQuilibrium Initiative
TANKLESS WATER HEATER INSTALLATION DIAGRAMS
TANKLESS WATER HEATER INSTALLATION DIAGRAMS Installation Diagrams Tankless Installation / Optional Return Small 10-15 Gallon Point-of-Use Water Single and Optional Return : One single, small capacity water