TEASER. Privatization of Turkey s Electricity Distribution Industry

Size: px
Start display at page:

Download "TEASER. Privatization of Turkey s Electricity Distribution Industry"

Transcription

1 TEASER Privatization of Turkey s Electricity Distribution Industry

2 Legal Disclaimer Regarding the Teaser Any estimates and projections contained in the present Teaser (the Teaser ) involve significant elements of subjective judgment and analysis, which may or may not be correct. None of the PA, TEDAS or any of its distribution companies, Lazard or any of their affiliates, their advisors or any of their direct or indirect shareholders or any of their respective members, public servants, employees or agents provides any guarantee or warranty (express or implied) or assumes any responsibility with respect to the authenticity, validity, accuracy or completeness of the information and data contained in the Teaser, or assumes any obligation for damages, losses or costs (including, without limitation, any direct or consequential losses) resulting from any errors, incompleteness or omissions contained in the Teaser. The economic valuations contained in the Teaser are necessarily based on the current market conditions, which may change significantly over a short period of time. Changes and events occurring after the date hereof may, therefore, affect the validity of the conclusions of the Teaser. None of the PA, TEDAS and its distribution companies or Lazard assumes no obligation to update and/or revise the Teaser or the information and data upon which it has been based. The Teaser does not constitute an offer or the solicitation of an offer for the sale or purchase of any assets or shares of TEDAS and its distribution companies. Neither this Teaser nor the information contained herein shall form the basis of, or constitute, any contract or binding offer. It is essential for the Participants to examine TEDAS and its distribution companies and the current condition of these companies prior to the final bidding date. Accordingly, it is accepted that the Participants had full knowledge about TEDAS and its distribution companies and the current actual condition of these companies during all phases of the tender and while signing the Share Sale Agreement and that they have placed their bid with such knowledge and signed the Share Sale Agreement. The Participants and, the Purchaser after the sale procedure, accept, declare and guarantee that acting as a prudent merchant, it has made/have somebody make all kinds of technical, legal, financial, tax related and other examinations and facility visits it deemed necessary regarding TEDAS and its distribution companies; and that the shares were taken over and received knowing the current and physical condition of these companies as of the Share Sale Agreement date; that it will not claim that the information declaration and /or explanations in the Teaser and/or other documents are not correct and/or erroneous or any similar claims, and that based on such it will not make any claims from the PA or any other public institution under the scope of warranty for defect provisions or other provisions within the legislation after the shares are transferred.

3 Contents 1. TEDAS PRIVATIZATION OVERVIEW 1 2. KEY ASPECTS OF THE INTENDED PRIVATIZATION 3 A. TSS MODEL 3 B. ELECTRICITY TARIFFS 3 C. ENERGY SALES AGREEMENTS 5 D. INVESTMENT OBLIGATIONS 6 3. INVESTMENT CONSIDERATIONS 8 4. TURKISH ELECTRICITY MARKET OVERVIEW APPENDIX 15

4 1. TEDAS PRIVATIZATION OVERVIEW Republic of Turkey Prime Ministry Privatization Administration ( PA ) has started the privatization of Turkey s electricity distribution utility, Turkiye Elektrik Dagitim Anonim Sirketi ( TEDAS ). Turkiye Elektrik Dagitim A.S. ( TEDAS ) and its distribution companies 1 are Turkish State-owned joint-stock companies engaged in the distribution and retail sale of electricity and provision of retail services to final customers. With approximately 28 million customers, 93 billion kwh of electricity sales and 98% market share in electricity distribution across Turkey in 2005, TEDAS and its distribution companies together form one of the largest organizations in the country. PA has decided to start the privatization process with the simultaneous tender of 3 companies, each operating in respective regions, namely: Region 9: Baskent Elektrik Dagitim A.S. ( BASKENT ) Region 14: Istanbul Anadolu Yakasi Elektrik Dagitim A.S. ( AYEDAS ) Region 15: Sakarya Elektrik Dagitim A.S. ( SEDAS ) Privatization of distribution companies will be executed using a Transfer of Operating Rights ( TOR ) backed Share Sale model ("TSS model"). According to this model, the investor will be the sole owner of the shares of the distribution company which will be the unique licensee for the distribution of electricity in the designated region but which will not have the ownership of distribution network assets and other items that are essential for the operation of distribution assets. The ownership of these distribution assets will remain with TEDAS. The investor, through its shares in the distribution company, however, will be granted the right to operate the distribution assets pursuant to a Transfer of Operating Rights Agreement ("TOR Agreement") with TEDAS. Under the envisaged market structure, privatized electricity distribution companies will operate as regional monopolies with distribution licenses granted by Energy Market Regulatory Authority ( EMRA ). As part of ongoing liberalization efforts in the energy sector, Turkey s distribution network was divided into 21 distribution regions based on geographical proximity, managerial structure, energy demand and other technical/financial factors. After the inclusion of TEDAS in the privatization programme, a separate distribution company was established by the PA in each one of the 20 distribution regions owned by TEDAS. The geographical coverage of the distribution regions are provided in the following map. The only distribution region operated by a partially private company is Kayseri (Region #18), whose operating rights were transferred to KCETAS in Turkey s electricity distribution network has been divided into 21 distribution regions as announced in the Strategy Paper. TEDAS, which owns 20 of the 21 regions, have been included in the privatization programme, and a separate distribution company has been established in each of these 20 regions. These distribution companies are currently owned by TEDAS. 1

5 TURKEY S ELECTRICITY DISTRIBUTION COMPANIES Private Çanakkale Kırklareli 13 Edirne Tekirdağ Balıkesir Manisa İzmir Aydın Muğla Bartın Boğaziçi. İstanbul And. Yk. Sinop Kastamonu Zonguldak Kocaeli Karabük Samsun Düzce Yalova Ordu Sakarya 21 Bolu Çankırı Amasya Tokat Bursa 9 Çorum Bilecik Ankara Kırıkkale Sivas Eskişehir Yozgat 6 Kütahya Kırşehir 17 Uşak Denizli Burdur Afyon Konya Isparta Antalya 10 8 Aksaray Mersin Nevşehir Kayseri Niğde Adana Şanlıurfa Karaman Osmaniye Gaziantep Kilis Hatay Giresun Erzincan Tunceli Malatya Elazığ K.Maraş Adıyaman Trabzon 4 Gümüşhane Bayburt 5 Rize Diyarbakır 1 Artvin Ardahan Erzurum 3 Bingöl Muş 58,04 Bitlis Siirt Batman Şırnak Mardin Kars Iğdır Ağrı 2 Van Hakkari Source: PA 1. Dicle Elektrik Dagitim A.S 2. Vangolu Elektrik Dagitim A.S 3. Aras Elektrik Dagitim A.S 4. Coruk Elektrik Dagitim A.S 5. Firat Elektrik Dagitim A.S 6. Camlibel Elektirk Dagitim A.S 7. Toroslar Elektric Dagitim A.S 8. Meram Elektrik Dagitim A.S 9. Baskent Elektrik Dagitim A.S 10. Akdeniz Elektrik Dagitim A.S 11. Gediz Elektrik A.S 12. Uludag Elektrik Dagitim A.S 13. Trakaya Elektrik Dagitim A.S 14. İstanbul Anadolu Yakasi Elektrik Dagitim A.S 15. Sakarya Elektrik Dagitim A.S 16. Osmangazi Elektrik Dagitim A.S 17. Bogazici Elektrik Dagitim A.S 18. Kayseri ve Civari Elektrik T.A.S 19. Menderes Elektrik Dagitim A.S 20. Goksu Elektrik Dagitim A.S 21. Yesilirmak Elektrik Dagitim A.S 2

6 2. KEY ASPECTS OF THE INTENDED PRIVATIZATION A. TSS MODEL The aim of the TSS model is to handover a fully operating distribution company to the investor. Establishment of the distribution company as a separate legal entity, signing of the TOR Agreement, provision of distribution and retail sales licenses and signing of the Energy Sales Agreements have been defined as the necessary pre-requisites for the TSS model implementation. All of these steps have already been completed prior to the privatization tender announcement. In the TSS model, asset ownership of new as well as existing distribution assets belong to TEDAS, while the investor attains the right to operate the distribution network together with the obligation to undertake the necessary investments. In line with the privatization purposes and investor expectations: The ownership of the existing assets and the new assets arising from investments to be carried out by the investor rests with TEDAS. The legal obligations relating to the asset base before the signing of the TOR Agreement (for example, expropriation costs) have been assumed by TEDAS. The investor shall purchase the shares of a company which holds the operating rights of distribution assets and all related assets (e.g., buildings, vehicles, machine park), and the electricity distribution and retail licenses in a given region. All investments shall be realized by the investor and will be recovered through the tariffs. Except for cases of investor misconduct, the part of investments not yet recovered via the tariffs shall be paid by TEDAS to the investor upon the expiry or termination of the contract. B. ELECTRICITY TARIFFS According to the general principles as stated in the Electricity Market Strategy Paper 2, Turkish Electricity Market has gone through a process of vast restructuring in core activities ranging from generation to distribution. Accordingly, a new tariff structure has been developed inline with the new structural requirements in mind. The main purpose of the market liberalization is to achieve lower tariffs by increasing overall system efficiency. Accordingly, the tariffs are calculated as cost-reflective based on predetermined operating and loss/theft improvement targets. The first tariff implementation period (or transition period), set as five years from 2006 to 2010, will serve as the transitory period to a fully cost based tariff structure after EMRA has already approved the end user tariffs and revenue requirements of each 2 Decision of High Planning Council No. 2004/3 dated

7 distribution company for the transition period. Revenue requirements cover the projected expenses for providing distribution and retail services and provide an allowance for the target level of technical and non-technical losses. The end-user tariffs for the period after 2010 will be determined by the distribution companies in accordance with the Electricity Market Tariffs Communiqué and the related regulations and will be subject to the Regulator s approval. The first implementation period is designed to have a smooth and gradual transition from existing tariff structure to a lean and simple tariff structure. As of 2010, most customer groups will have cost based tariffs in place and the tariff groups will be simplified to five only, namely residential, industrial, commercial, agricultural irrigation and lightening. According to the Electricity Market Law, the Electricity Market Tariffs Communiqué and other related regulation, the four tariff components 3 ; (a) retail sales, (b) distribution, (c) retail services and (d) transmission; are governed in an unbundled fashion. Retail sales tariff has a price cap which is set as the basket price of the energy purchased by the distribution company. Distribution and retail services have revenue caps which cover operating expenses and investment requirements related to distribution and retail services. Transmission tariff is a complete pass-through of transmission costs as charged by the national transmission company. Customers Residential Commercial Industrial Agricultural irrigation Street lighenting Distribution system usage tariff DECOMPOSITION OF END-USER TARIFF Taxes and other deductions Transmission tariff Retail services tariff TEİAŞ Distribution OPEX component Investments amortization and cost of capital component TOR value component Distr ibution Other charges* Company Lost/theft component Operating margin Pass-through of transmission costs Retail tariff Reference Price (Energ y pric e) TETAŞ Pass-through of energy costs Total end-user electricity tariff * Dual-term tariffs: capacity charge, penalty for overload and reactive energy fee Source: TEDAS As stated in the Strategy Paper, the existing national tariff scheme will be maintained for the first tariff implementation period, rather than implementing regional tariffs so that sudden price fluctuations could be avoided (currently, regional cost based tariffs vary significantly due to wide variation of loss/theft levels and other parameters across the 3 Excluding taxes and other deductions component 4

8 regions). Implementation of national tariffs, however, will result in revenue imbalances since the distribution company revenues will differ from their envisaged revenue caps. In order to remove such imbalances, EMRA will put in place a tariff equalization scheme to transfer revenues across the regions. TRANSITION PERIOD NATIONAL TARIFFS * (Krs/KWh) Industrial - MV Industrial - LV Commercial Residential Agricultutal Irrigation Lightening * Mono term tariffs valid throughout the day. Excluding VAT and Municipality tax. Excludes any adjustments to be made throughout years (e.g. inflation adjustment) and assumes no change in today s wholesale energy costs Source: TEDAS While the overall tariffs are pre-determined and approved for , the tariff revision process has still not been finalized. The exact nature and details of the process are expected to be announced by the Regulator soon, however some key highlights of the revision process are expected to be as follows: Revenue Cap: The revenue caps are expected to be guaranteed regardless of the consumption levels in the region. Namely, if a distribution company underbills its revenue cap due to lower consumption, tariff adjustment is allowed for the subsequent period under the supervision of EMRA. In addition, the approved revenue caps for are expected to be revised due to inflation, based on the changes in the Electricity Market Index ( EMI ) as announced by EMRA. Retail Price Cap: The distribution company could reflect any changes in its energy wholesale reference costs to the price cap through a pass-through mechanism under the supervision of the EMRA. Other than the end-user tariffs, customers are also charged a distribution connection fee for the establishment of the initial connection to the distribution network and a disconnection/reconnection fee in case a disconnection or reconnection is required. The full details of the tariff levels and procedures are explained in the regional tariff, tariff methodology and tariff application guideline documents as approved by EMRA. C. ENERGY SALES AGREEMENTS It is stated in the Strategy Paper that during the transition period , distribution companies are to procure 85% of the regional energy demand consumed by non-eligible 4 4 As per the Electricity Market Law, non-eligible customers shall buy their electricity from the distribution company operating in their region, while eligible customers are already free to choose their suppliers. The eligibility threshold is currently fixed by EMRA at 6.0 GWh per annum. 5

9 customers from TETAS and the portfolio generation companies carved out of EUAS. Accordingly, each distribution company inherited Energy Sales Agreements with TETAS and EUAS portfolio companies, which largely secure the majority of distribution companies energy needs for the transition period. These Energy Sales Agreements have been established based on regulated prices for the transition period. After the transition period, the distribution company will freely source its wholesale energy needs from alternative sources, e.g., bilateral contracts, spot market, vertical integration. The market balancing and settlement mechanism under the national transmission company, which has become operational recently in 2006, will remove daily market imbalances. A certain portion of the guaranteed supply in the EUAS contract is optional, i.e. the distribution company has the option not to buy the optional amount. This flexibility will protect the distribution company from an unexpected drop in regional consumption level and furthermore will provide the distribution company with the option to alternatively source some portion of its energy from lower cost providers. D. INVESTMENT OBLIGATIONS One of the primary objectives of privatization is to finance required distribution system and network improvements and expansions through private sector investments, thereby removing the burden of such investments away from the State budget. Investments are of great importance in ensuring continuity and quality of service in electricity distribution. The annual expansion, replacement and improvement investments that are required in each of the 20 distribution regions during the first tariff implementation period ( ) have been determined during the preparation of the end-user tariffs. For TEDAS as a whole, the investment requirement for the transition period is a total of YTL 2,750 million, distributed equally to each year of the transition period. These investments have been embedded into the first implementation period tariffs approved by the Regulator; hence, they will be recouped by the distribution companies over time. Investment requirements could be updated by EMRA through the revision mechanisms. Investment expenditures consist of three components: Expansion investments and expropriation cost: Investment expenditures for increasing the capacity of the existing network and the associated expropriation and right of way costs Replacement investments: Investment expenditures for the replacement of the economic assets that have completed their economic lives in the existing network Continuing investments: Investment expenditures for the completion of the already contracted projects, most of which are still continuing After 2010, distribution companies will prepare annual investment plans each year by making projections on consumption growth, analyzing network expansion requirements and other technical parameters. They will then present these investment plans to EMRA for approval. 6

10 7 After receiving EMRA approval, distribution companies are obliged to implement the approved plans. Implementation of these investments (i.e. investment amount and form) will be monitored through investment control and quality measurement mechanisms set up by the Regulator in collaboration with the distribution companies.

11 3. INVESTMENT CONSIDERATIONS EMRA approved tariffs do incorporate an allowed level of regulated return on the investments and services to be carried out as part of the electricity sales & distribution activities. In addition to this allowed level of return, the distribution company can create substantial value by beating the pre-approved loss/theft and operational efficiency targets. From the investor s perspective and for the overall development of the electricity sector, the benefits and opportunities of the envisaged system can been summarized as follows: The investor is allowed to retain excess value derived from outperforming the predetermined loss/theft targets approved by the Regulator. Accordingly, as a result of this policy, technical and non-technical losses, which have become an excessive financial burden in Turkey over the years, are expected to be reduced to single digit figures. The investor is allowed to retain the savings achieved if energy is sourced at a lower wholesale cost than the regulated reference price. This policy will pave the way for construction of low-cost electricity production facilities going forward. The investor is allowed to retain excess value derived from outperforming the predetermined operational improvement targets approved by the Regulator. This will trigger efficiency improvements in electricity distribution. Particularly after year 2010, distribution companies will be able to vertically integrate to produce electricity and sell excess production in an open market, thereby increasing their revenues. Vertical integration will be instrumental in the development of an open market in electricity. At each distribution company, substantial operational efficiency improvements are believed to be achievable through optimizing core business processes such as billing and collections, arranging and redesigning work flows, enabling effective coordination between divisions, improving information systems and infrastructure and optimizing personnel productivity. In a broader perspective, Turkey provides a strategic position in the European energy markets with a stable and high-growth electricity industry. Introduction of an effective regulation and a liberal market structure have further enhanced the industry growth prospects for the coming years and enabled value creation opportunities for private players. The Turkish electricity sector has been modeled on EU market structure and a transparent regulatory framework has been set by the independent authority, EMRA. In the following years, further opportunities will arise for the privatized distribution companies from privatization/liberalization in the broader energy sector particularly in the generation area. Today, Turkish economy offers more stable market conditions primarily driven by the wideranging structural reforms undertaken and also as a result of the ongoing EU integration. The GDP grew by 8.9% and by 7.4% in 2004 and 2005, respectively and the inflation rate has fallen to 7.7% in 2005, the lowest figure in the last 35 years. This improved outlook has encouraged international investors to take on more Turkey risk; also taking into account the 8

12 9 strengthening fiscal and debt positions (yielding a surplus in the central budget in May 2006 for the first time in the last 22 years). Provided that the economic reforms are implemented swiftly, Turkey can expect to benefit disproportionately from the international FDI pool over the next decade.

13 4. TURKISH ELECTRICITY MARKET OVERVIEW The electricity industry is a large, high-growth sector in the Turkish economy. The industry contributes significantly to the country s GDP and is a USD 12 billion industry at current end-user prices. The sector s share in the Turkish economy has been growing rapidly, given the 8% per annum growth in electricity demand over the past two decades. This rate of demand growth has been higher than the growth rates seen in other major Turkish industries and outstrips growth in the Turkish economy overall. In 2004, the Turkish electricity sector recorded approximately 151 billion kwh of gross consumption (161 billion kwh in 2005) and 121 billion kwh of net consumption (excluding loss/theft and internal consumption). The industrials customer group represent approximately 50% of the total demand, while residential customers consume slightly less than a quarter of the total. Commercials customer group, excluding public institutions, is placed third in terms of consumption with a 13% share. Distribution losses of the system, which amounted to 19.8 billion kwh in 2004, are high compared to international benchmarks. Accordingly, one of the primary objectives of the electricity sector reform has been defined as reducing the loss/theft ratio to OECD levels. Electricity generation, imports & exports, distribution losses and the net consumption of main customer groups in 2004 are summarized in the following chart. GENERATION & NET CONSUMPTION *, 2004 PRODUCTION TWh INTERNAL CONSUMPTION 5.6 TWh TOTAL TWh GRID LOSS 3.4 TWh DISTRIBUTION LOSS 19.8 TWh IMPORT 0.5 TWh EXPORT 1.1 TWh Industrial Residential Commercial Other CONSUMPTION 59.6 TWh 27.6 TWh 15.7 TWh 18.3 TWh TWh * Figures are in TWh; 1 TWh equals 1 billion kwh Source: TEDAS, TEIAS Electricity consumption growth has historically been less volatile than the overall economic growth in Turkey. Between 1980 and 2004, GDP growth displayed a wide variance with a standard deviation of 4.7% around an average growth rate of 4%. Consumption growth in the electricity sector during the same time period displayed a lower standard deviation of 10

14 3.2%, around a higher average growth rate of approximately 8%. As can be seen in the next chart, electricity consumption was negative only in a single year over the past 25 years. ELECTRICITY CONSUMPTION VS. GDP GROWTH, GDP growth (% ) Electricity consumption growth (% ) Average growth = 4.2% Average growth = 7.7% Standard deviation: 4.7% Standard deviation: 3.2% Source: TEDAS, SIS Despite increasing demand, Turkey s per capita gross consumption is still very low at 2,090 kwh compared to the EU average of 6,460 kwh. According to the Ministry of Energy and Natural Resources ( MENR ) projections that assume a continued cumulative annual growth rate of 7.7% in gross demand, per capita consumption is forecasted to reach 5,700 kwh by During the 1980s, average consumption growth was the same for all customer groups around 8%. After 1990s, however, consumption growth for residential and commercial customer groups outpaced that of industrial customer group. Nevertheless, the industrials segment still accounts for approximately 50% of electricity consumption in Turkey. The next chart illustrates consumption growth for each customer group over the past two and a half decades. 11

15 ELECTRICITY CONSUMPTION BY CUSTOMER GROUP, (TWh) TWh CAGR 7.7% 67.4 TWh 98.3 TWh 17% 10% 15% 13% 23% 20.4 TWh 6% 9% 22% 64% 29.7 TWh 5% 10% 19% 66% 46.8 TWh 13% 5% 20% 62% 16% 6% 22% 56% 24% 50% 49% Industrial/Autoproducers Residential Commercial Other* ESTIMATED INDUSTRY REVENUES (USD billion) * Electricity used by public institutions, lightening, agricultural irrigation and non profit organizations such as schools and hospitals Sources: TEDAS, TEIAS The forces that fuel growth in the sector are continued economic and industrial development, population growth and improving income levels. According to projections prepared by the national transmission company TEIAS on the growth of supply, there is sufficient generation capacity at least until year Required investments for more capacity are expected to be covered primarily by private sector investments. Should this not take place, the State will take necessary measures to provide additional capacity, including imports and rehabilitation of existing plants to provide supply assurance, as stated in the Strategy Paper. Turkish electricity sector was dominated by the State-owned vertically integrated company Turkiye Elektrik Kurunu ( TEK ) until the early 1990s. In 1993, in view of market liberalization and privatization, TEK was separated into TEAS (generation, transmission and wholesale) and TEDAS (distribution). Then, with the enactment of the Electricity Market Law in 2001, TEAS was further unbundled into EUAS (generation), TETAS (wholesale) and TEIAS (transmission), each being organized as a separate legal entity. In this context: EUAS was envisaged to take over the ownership and the operation of the State thermal power plants from TEAS and the hydroelectric power plants from the Devlet Su Isleri ( State Water Works ). EUAS was also empowered to build, lease and operate new generation facilities, if deemed necessary, in accordance with the EMRA approved generation capacity projections and taking into consideration the generation investments by the private sector. TETAS was created to conduct wholesale operations and take over the existing energy sale and purchase agreements from TEAS and TEDAS. TETAS was also held 12

16 responsible for managing the stranded costs associated with the Build Operate ( BO ), Build Operate Transfer ( BOT ) and TOR generation contracts. TEIAS took over all transmission facilities owned by the State and was named responsible for transmission system operations and maintenance, developing transmission investment plans for new facilities and also for operating the market balancing and settlement center. HISTORICAL DEVELOPMENT OF MARKET STRUCTURE Pre 1993 TEK (generation, transmission & distribution) Between TEAS (generation & transmission) TEDAS (distribution) Today EUAS (generation) TEIAS (transmission) TETAS (wholesale) 21 COMPANIES (distribution) Source: PA Currently, State dominance is still very much prevalent across the electricity value chain. In 2004, EUAS and its subsidiaries held 59% of the total installed generation capacity in Turkey and generated 45% of electricity produced countrywide. In transmission and wholesale, TEIAS and TETAS operate as national monopolies, and at the lower end of the value chain, TEDAS and its distribution companies have 98% market share in distribution covering 20 of the 21 distribution regions and a 71% share in countrywide electricity retail sales. 13

17 ELECTRICITY SECTOR VALUE CHAIN VALUE CHAIN GENERATION TRANSMISSION DISTRIBUTION RETAIL SALES PUBLIC/PRIVATE OWNERSHIP Still State dominated with private players slowly increasing their share in the past 5 years Totally under State control Still controlled by State in 20 out of 21 distribution regions Eligible customers are able to source energy through channels other than TEDAS Private producers* 39% 16% EUAS and subsidiaries 45 TEIAS 100% KCETAS 2% 98% TEIAS customers and others Auto- 7% producers 21% 1% KCETAS TEDAS 71% Autoproducers TEDAS State-owned companies * Private produces include BO, BOT, TOR and mobile power plants Source: TEIAS, TEDAS 14

18 5. APPENDIX NUMBER OF CUSTOMERS ( 000), 2005 # REGIONS Residential Commercial Public Instutions Industrial Agricultural Irrigation Other TOTAL 1Dicle EDAŞ Vangölü EDAŞ Aras EDAŞ Çoruh EDAŞ Fırat EDAŞ Çamlıbel EDAŞ Toroslar EDAŞ 2, , Meram EDAŞ 1, , Başkent EDAŞ 2, , Akdeniz EDAŞ 1, , Gediz EDAŞ 1, , Uludağ EDAŞ 1, , Trakya EDAŞ AYEDAŞ 1, , Sakarya EDAŞ 1, , Osmangazi EDAŞ , Boğaziçi EDAŞ 2, , Menderes EDAŞ 1, , Göksu EDAŞ Yeşilırmak EDAŞ 1, ,364.4 TOTAL 23, , ,972.6 Source: TEDAS NET CONSUMPTION (GWh), 2005 # REGIONS Residential Commercial Public Instutions Industrial Agricultural Irrigation Other TOTAL 1Dicle EDAŞ 1, ,162 4,003 2Vangölü EDAŞ Aras EDAŞ ,326 4Çoruh EDAŞ ,664 5Fırat EDAŞ ,644 6Çamlıbel EDAŞ ,560 7 Toroslar EDAŞ 2,626 1, , ,151 10,034 8Meram EDAŞ 1, , ,320 9Başkent EDAŞ 2,989 1, , , Akdeniz EDAŞ 1,209 1, , Gediz EDAŞ 2,810 1, , ,078 9, Uludağ EDAŞ 1, , , Trakya EDAŞ , , AYEDAŞ 2,851 1, , , Sakarya EDAŞ 1, , , Osmangazi EDAŞ , , Boğaziçi EDAŞ 5,090 4, , , Menderes EDAŞ 1, , , Göksu EDAŞ , , Yeşilırmak EDAŞ 1, , ,994 TOTAL 29,690 16,431 4,623 28,839 3,189 10,423 93,196 Source: TEDAS 15

19 LOSS AND THEFT, 2005 # REGIONS Purchased Electricity (GWh) Sold Electricity (GWh) Loss and Theft (GWh) Loss and Theft (% ) 1Dicle EDAŞ 11,219 4,003 7, % 2Vangölü EDAŞ 1, , % 3Aras EDAŞ 1,942 1, % 4Çoruh EDAŞ 1,943 1, % 5Fırat EDAŞ 1,918 1, % 6Çamlıbel EDAŞ 1,738 1, % 7 Toroslar EDAŞ 11,547 10,034 1, % 8Meram EDAŞ 4,652 4, % 9Başkent EDAŞ 9,045 8,041 1, % 10 Akdeniz EDAŞ 4,447 4, % 11 Gediz EDAŞ 10,174 9, % 12 Uludağ EDAŞ 6,643 5, % 13 Trakya EDAŞ 3,375 3, % 14 AYEDAŞ 7,049 6, % 15 Sakarya EDAŞ 4,712 4, % 16 Osmangazi EDAŞ 3,670 3, % 17 Boğaziçi EDAŞ 16,804 14,074 2, % 19 Menderes EDAŞ 4,453 4, % 20 Göksu EDAŞ 2,653 2, % 21 Yeşilırmak EDAŞ 3,393 2, % TOTAL 113,376 93,196 20, % Source: TEDAS 16

TEB 31 December 2014

TEB 31 December 2014 TEB 3 December 04 Summary Balance Sheet Source: TEB BRSA Consolidated Financials Summary Income Statement 3 Source: TEB BRSA Consolidated Financials Strong balance sheet growth with continuing commitment

More information

Summary Balance Sheet. Source: TEB BRSA Consolidated Financials

Summary Balance Sheet. Source: TEB BRSA Consolidated Financials TEB 30 June 03 Summary Balance Sheet Source: TEB BRSA Consolidated Financials Summary Income Statement 3 Source: TEB BRSA Consolidated Financials Strong balance sheet growth, commitment to core banking

More information

Privatisation Agenda for Energy Assets

Privatisation Agenda for Energy Assets www.pwc.com.tr October 2012 Privatisation Agenda for Energy Assets Contents Introduction 3 Power distribution companies 4 Hamitabat and small hydro assets 6 Başkent Gaz 7 2 PwC Introduction Lower deal

More information

Fibabanka Overview September 2013

Fibabanka Overview September 2013 Fibabanka Overview September 2013 12 Countries 74 Companies >12,000 employees Fiba Group Sectors & Companies Fiba Holding Fina Holding Banking Other Financial Services Retail Real Estate & Asset Management

More information

NATURAL GAS MARKET TARIFFS REGULATION

NATURAL GAS MARKET TARIFFS REGULATION NATURAL GAS MARKET TARIFFS REGULATION 1 Presentation Outline NATURAL GAS MARKET TARIFFS Tariff Definition Process and Main Principles Type of Tariffs Connection Tariffs Tariffs Regarding Transmission and

More information

YAPI KREDİ: A New Bank is Born. İstanbul, 2 October 2006

YAPI KREDİ: A New Bank is Born. İstanbul, 2 October 2006 YAPI KREDİ: A New Bank is Born İstanbul, 2 October 2006 AGENDA THE NEW BANK SHAREHOLDING AND ORGANIZATIONAL STRUCTURE VISION AND KEY TARGETS 2 YAPI KREDİ MERGER IS THE BIGGEST M&A PROJECT IN THE HISTORY

More information

Monitoring data and existing information Country Presentation from Turkey

Monitoring data and existing information Country Presentation from Turkey Workshop on DEVELOPING REGIONAL COOPERATION FOR SHARED KARST AQUIFER MANAGEMENT IN SEE 27-28 June 2008 Thessaloniki, Greece Monitoring data and existing information Country Presentation from Turkey Plan

More information

Analysis of variable-base heating and cooling degree-days for Turkey

Analysis of variable-base heating and cooling degree-days for Turkey Applied Energy 69 (2001) 269 283 www.elsevier.com/locate/apenergy Analysis of variable-base heating and cooling degree-days for Turkey Orhan Bu yu kalaca *, Hu samettin Bulut, Tuncay Yılmaz Department

More information

CATTLE SECTOR IN TURKEY

CATTLE SECTOR IN TURKEY CATTLE SECTOR IN TURKEY Çagla Yüksel Kaya Veterınarıan CATTLE BREEDERS ASSOCIATION OF TURKEY CATTLE SECTOR its value shared in 2004 In EU-25 nearly 23% of the total value of agricultural production and

More information

THE INNOVATION INDEX OF CITIES OF TURKEY: AN EMPIRICAL ANALYSIS FOR DETERMINING FACTORS OF INNOVATION

THE INNOVATION INDEX OF CITIES OF TURKEY: AN EMPIRICAL ANALYSIS FOR DETERMINING FACTORS OF INNOVATION Ekonometri ve İstatistik Sayı:22 2015 36-46 İSTANBUL ÜNİVERSİTESİ İKTİSAT FAKÜLTESİ EKONOMETRİ VE İSTATİSTİK DERGİSİ THE INNOVATION INDEX OF CITIES OF TURKEY: AN EMPIRICAL ANALYSIS FOR DETERMINING FACTORS

More information

TURKEY WHAT S HOT WHAT S NOT

TURKEY WHAT S HOT WHAT S NOT TURKEY WHAT S NOT TURKEY WHAT S NOT There is TURKEY TURKEY WHAT S NOT There is TURKEY and TURKEY WHAT S NOT There is TURKEY and There is İSTANBUL TURKEY Secondary and tertiary cities Limited/focused service,

More information

As of 31.12.2013. www.sekerbank.com.tr

As of 31.12.2013. www.sekerbank.com.tr As of 3.2.203 www.sekerbank.com.tr Contents Pages Background & Ownership 3-4 Ratings and Financial Performance 6-0 Risk Management 4-6 Business Strategies & Current Strengths 8-20 National Presence and

More information

RENEWABLE INTEGRATION IN TURKISH POWER SYSTEM

RENEWABLE INTEGRATION IN TURKISH POWER SYSTEM RENEWABLE INTEGRATION IN TURKISH POWER SYSTEM Nurhan OZAN Transmission Planning & Coordination Manager Research, Planning, Coordination Department TURKISH ELECTRICITY TRANSMISSION CORPORATION () www.teias.gov.tr

More information

Zeitschrift für die Welt der Türken Journal of World of Turks THE IMPACT OF ECONOMIC DEVELOPMENT ON REGIONAL MIGRATION IN TURKEY

Zeitschrift für die Welt der Türken Journal of World of Turks THE IMPACT OF ECONOMIC DEVELOPMENT ON REGIONAL MIGRATION IN TURKEY THE IMPACT OF ECONOMIC DEVELOPMENT ON REGIONAL MIGRATION IN TURKEY Mustafa METE Hakkı ÖZBAŞ Abstract: Since its inception, Turkey has experienced several migration movements. It is a transit country that

More information

Individual Pension System Progress Report

Individual Pension System Progress Report Individual Pension System Progress Report 29 Individual Pension System Progress Report 29 [email protected] Electronic version of this document and reference data of selected statistics are available

More information

Modeling Solar Energy Potential In Turkey

Modeling Solar Energy Potential In Turkey Modeling Solar Energy Potential In Turkey Serhat SENSOY, Yusuf ULUPINAR, Mesut DEMIRCAN, Ilker ALAN, Zuhal AKYUREK, Pinar A. BOSTAN Turkish State Meteorological Service, Ankara, Turkey Abstract Since the

More information

NEWSPAPER ADVERTISING RATES

NEWSPAPER ADVERTISING RATES NEWSPAPER ADVERTISING RATES Effective from April 2014 CONTENTS SABAH Page TAKVİM Page Turkey Edition 2 Turkey and Istanbul Adv. Edition 10 Istanbul Edition 3 Günaydın Advertising Edition 4 FOTOMAÇ Sabah

More information

INVESTOR PRESENTATION. BRSA Unconsolidated Financial Statements Highlights 30.06.2015 www.sekerbank.com.tr

INVESTOR PRESENTATION. BRSA Unconsolidated Financial Statements Highlights 30.06.2015 www.sekerbank.com.tr INVESTOR PRESENTATION BRSA Unconsolidated Financial Statements Highlights 30.06.205 www.sekerbank.com.tr CONTENTS About Şekerbank 3-7 Background / Milestones Strategy & Mission Ownership Ratings Geographical

More information

INVESTOR PRESENTATION. BRSA Unconsolidated Financial Statements Highlights 31.03.2015 www.sekerbank.com.tr

INVESTOR PRESENTATION. BRSA Unconsolidated Financial Statements Highlights 31.03.2015 www.sekerbank.com.tr INVESTOR PRESENTATION BRSA Unconsolidated Financial Statements Highlights 3.03.205 www.sekerbank.com.tr CONTENTS About Şekerbank 3-7 Background / Milestones Strategy & Mission Ownership Ratings Geographical

More information

VISITOR SURVEY EXECUTIVE SUMMARY

VISITOR SURVEY EXECUTIVE SUMMARY VISITOR SURVEY EXECUTIVE SUMMARY March 11 14, 2015 TÜYAP Fair Convention and Congress Center Istanbul / TURKEY CONTENTS PAGE 1. SUBJECT 3 1.1. KEY INFORMATION 3 1.2. PURPOSE 4 1.3. METHOD AND SAMPLING

More information

INVESTOR PRESENTATION. BRSA Unconsolidated Financial Statements Highlights 31.12.2015 www.sekerbank.com.tr

INVESTOR PRESENTATION. BRSA Unconsolidated Financial Statements Highlights 31.12.2015 www.sekerbank.com.tr INVESTOR PRESENTATION BRSA Unconsolidated Financial Statements Highlights 3.2.205 www.sekerbank.com.tr CONTENTS About Şekerbank 3-7 Background / Milestones Strategy & Mission Ownership Ratings Geographical

More information

DIMENSION OF WATER LOSS THROUGH DISTRIBUTION SYSTEM AND REDUCTION METHODS IN TURKEY

DIMENSION OF WATER LOSS THROUGH DISTRIBUTION SYSTEM AND REDUCTION METHODS IN TURKEY DIMENSION OF WATER LOSS THROUGH DISTRIBUTION SYSTEM AND REDUCTION METHODS IN TURKEY İzzet ÖZTÜRK Vedat UYAK Mehmet ÇAKMAKCI Lütfi AKÇA İstanbul Technical University, Faculty of Civil Engineering, Department

More information

RATIO ESTIMATORS IN POST-STRATIFICATION

RATIO ESTIMATORS IN POST-STRATIFICATION Nüfusbilim Dergisi\Turkish Journal of Population Studies, 2012, 34, 3-15 3 RATIO ESTIMATORS IN POST-STRATIFICATION In this study, some ratio-type estimators are taken into consideration in literature and

More information

A. Sinan Türkyılmaz, Attila Hancıoğlu and İsmet Koç

A. Sinan Türkyılmaz, Attila Hancıoğlu and İsmet Koç SURVEY DESIGN APPENDIX B A. Sinan Türkyılmaz, Attila Hancıoğlu and İsmet Koç The major features of sample design and implementation for the Turkish Demographic and Health Survey, 2003 (TDHS-2003) are described

More information

Poverty and Social Stratification at the Regional Levels in Turkey

Poverty and Social Stratification at the Regional Levels in Turkey Poverty and Social Stratification at the Regional Levels in Turkey Ercan Dansuk * Mehmet Ozmen ** Güzin Erdogan *** Abstract This study presents a starting point in examining the issue of poverty in Turkey

More information

Meşrutiyet Cad. No. 98 D. 10 Beyoğlu, Istanbul / Turkey Tel: +90 212 251 15 00 Fax: +90 212 251 15 01 A REGULATORY UPDATE. New Electricity Market Law

Meşrutiyet Cad. No. 98 D. 10 Beyoğlu, Istanbul / Turkey Tel: +90 212 251 15 00 Fax: +90 212 251 15 01 A REGULATORY UPDATE. New Electricity Market Law Meşrutiyet Cad. No. 98 D. 10 Beyoğlu, Istanbul / Turkey Tel: +90 212 251 15 00 Fax: +90 212 251 15 01 http://boden-law.com A REGULATORY UPDATE New Electricity Market Law ELECTRICITY MARKET LAW PASSED BY

More information

REPUBLIC OF TURKEY MINISTRY OF ECONOMY NEW INVESTMENT INCENTIVES PROGRAM

REPUBLIC OF TURKEY MINISTRY OF ECONOMY NEW INVESTMENT INCENTIVES PROGRAM REPUBLIC OF TURKEY MINISTRY OF ECONOMY NEW INVESTMENT INCENTIVES PROGRAM April, 2012 1 The New Investment Incentives Program General Investment Incentive Scheme Regional Investment Incentive Scheme Large

More information

FMD SITUATION IN TURKEY. -Country Report- FMD SITUATION IN TURKEY. - Country Report- Dr Nihat Pakdil Deputy Secretary of M.A.R.A.

FMD SITUATION IN TURKEY. -Country Report- FMD SITUATION IN TURKEY. - Country Report- Dr Nihat Pakdil Deputy Secretary of M.A.R.A. Appendix 11 FMD SITUATION IN TURKEY -Country Report- FMD SITUATION IN TURKEY - Country Report- Dr Nihat Pakdil Deputy Secretary of M.A.R.A. of Turkey A.Naci BULUT Head of Diagnosis Department Sap Institute,

More information

Applied Energy 84 (2007) 477 491. Simple model for the generation of daily global solar-radiation data in Turkey

Applied Energy 84 (2007) 477 491. Simple model for the generation of daily global solar-radiation data in Turkey Applied Energy 84 (2007) 477 491 APPLIED ENERGY www.elsevier.com/locate/apenergy Simple model for the generation of daily global solar-radiation data in Turkey Hüsamettin Bulut a, *, Orhan Büyükalaca b

More information

RANKING OF TURKISH UNIVERSITIES BY ACADEMIC PERFORMANCE (JANUARY 2010)

RANKING OF TURKISH UNIVERSITIES BY ACADEMIC PERFORMANCE (JANUARY 2010) RANKING OF TURKISH UNIVERSITIES BY ACADEMIC PERFORMANCE (JANUARY 2010) Turkish Universities (114 of them) are ranked according to their academic performances based on national and international sources.

More information

www.pk ww. fhot els e. ls c. om

www.pk ww. fhot els e. ls c. om Turkey - overview Zonguldak Tekirdağ Istanbul Kocaeli Sakarya Bursa Ankara Balıkesir Eskişehir Çorum Samsun Tokat Sivas Ordu Trabzon Erzurum Ağrı Manisa Kütahya İzmir Afyonkarahisar Aydın Denizli Muğla

More information

TURKISH NUCLEAR POWER PROGRAMME NUCLEAR ENERGY PROJECT IMPLEMENTATION DEPARTMENT

TURKISH NUCLEAR POWER PROGRAMME NUCLEAR ENERGY PROJECT IMPLEMENTATION DEPARTMENT TURKISH NUCLEAR POWER PROGRAMME NUCLEAR ENERGY PROJECT IMPLEMENTATION DEPARTMENT 0 75 75 150 km Kocaeli (İzmit) BOSBORUS 0 İzmir Konya ANKARA 150 mi İçel (Mersin) REPUPLIC OF CYPRUS Iskenderun Adana SYRIA

More information

The World Bank. Public Disclosure Copy. Public Disclosure Copy

The World Bank. Public Disclosure Copy. Public Disclosure Copy Implementation Status & Results Turkey Electricity Distribution Rehabilitation Project (P096801) Operation Name: Electricity Distribution Rehabilitation Project (P096801) Project Stage: Implementation

More information

Relationship between GDP per Capita and Gender Parity in Primary Education: Evidence from Provinces of Turkey 1. Sedat Gümüş a2

Relationship between GDP per Capita and Gender Parity in Primary Education: Evidence from Provinces of Turkey 1. Sedat Gümüş a2 Çankırı Karatekin Üniversitesi Sosyal Bilimler Enstitüsü Dergisi 1(2010) 141 158 Relationship between GDP per Capita and Gender Parity in Primary Education: Evidence from Provinces of Turkey 1 a Michigan

More information

Renewable Energy Solutions

Renewable Energy Solutions Renewable Energy Solutions About Us Mission, Vision and Management Approach Business Segments Energy Solar Power Plants (SPP) Hydroelectric Power Plant (HPP) Wind Power Plant (WPP) EPC (Engineering, Procurement

More information

www.pwc.com.tr Privatisation Update

www.pwc.com.tr Privatisation Update www.pwc.com.tr Privatisation Update 12 October 2015 Electricity generation...3 Electricity and gas distribution...10 Looking ahead...11 2 Privatization Update Electricity generation In March 2010, Turkey

More information

TRADE EXHIBITION ISSUE REPORT

TRADE EXHIBITION ISSUE REPORT TRADE EXHIBITION ISSUE REPORT 23 rd Anfaş Hotel Equipment Trade Exhibition 2012 which is the leading event in hospitality industry held on 18-21 January, successfully gathered all sector professionals.

More information

Slide 1 UNECE-Committee on Sustainable Energy 20th Session of the Working Party on Gas 19-20 January 2010 BOTAŞ Projects at the Center of the Energy Arena Strategy and Busines Development Department 03.02

More information

Chart Alert !! URGENT!!

Chart Alert !! URGENT!! Chart Alert!! URGENT!! Date: 18 December 2009 Subject: Turkey (LT) New Minimum Visibility Values for Airports within Turkey With AIRAC AIP SUP 07/09, Turkey has implemented minimum visibility values for

More information

The World Bank. Key Dates. Project Development Objectives. Component(s) Overall Ratings. Public Disclosure Copy

The World Bank. Key Dates. Project Development Objectives. Component(s) Overall Ratings. Public Disclosure Copy Implementation Status & Results Turkey Electricity Distribution Rehabilitation Project (P096801) Operation Name: Electricity Distribution Rehabilitation Project (P096801) Project Stage: Implementation

More information

RESULT SUMMARY OF THE VISITOR SURVEY

RESULT SUMMARY OF THE VISITOR SURVEY November, 14 17, 2013 RESULT SUMMARY OF THE VISITOR SURVEY TÜYAP Fair, Convention and Congress Center Büyükçekmece İstanbul, Turkey 6 TABLE OF CONTENTS PAGE 1. SUBJECT OF THE SURVEY 3 1.1. INFORMATION

More information

Universal health coverage in Turkey: enhancement of equity

Universal health coverage in Turkey: enhancement of equity Universal health coverage in Turkey: enhancement of equity Rifat Atun, Sabahattin Aydın, Sarbani Chakraborty, Safir Sümer, Meltem Aran, Ipek Gürol, Serpil Nazlıoğlu, Şenay Özgülcü, Ülger Aydoğan, Banu

More information

Mediterranean region. Contents 18.02.2014 WATER FOOTPRINT OF TOURISM AND AGRICULTURAL PRODUCTION IN TURKEY

Mediterranean region. Contents 18.02.2014 WATER FOOTPRINT OF TOURISM AND AGRICULTURAL PRODUCTION IN TURKEY WATER FOOTPRINT OF TOURISM AND AGRICULTURAL PRODUCTION IN TURKEY Prof.Dr.Bülent Topkaya Akdeniz University Department of Environmental Engineering Mediterranean Region Water in Turkey Tourism activities

More information

ENERMET. Enerji Meteoroloji Mühendislik ve Müşavirlik Anonim Şirketi

ENERMET. Enerji Meteoroloji Mühendislik ve Müşavirlik Anonim Şirketi Table of Contents Table of Content 2 List of Tables.4 List of Figures 4 List of Abbreviations 5 1 Executive Summary..6 2 Turkey Wind Power Market 8 2.1Turkey s Strategic Location............8 2.2 Terrain

More information

FACTS & FIGURES: TEDU 2014-15 (as of May 31st, 2015)

FACTS & FIGURES: TEDU 2014-15 (as of May 31st, 2015) FACTS & FIGURES: TEDU 2014-15 (as of May 31st, 2015) TEDU STUDENTS a. Newly enrolled students in 2014: Placed (w. full ) : 37 Placed (w. 75% ) : 34 Placed (w. 50% ) : 203 Placed (w. 25% ) : 96 Placed (total)

More information

2016 DHMİ AIRPORT CHARGES

2016 DHMİ AIRPORT CHARGES REPUBLIC OF TURKEY GENERAL DIRECTORATE OF STATE AIRPORTS AUTHORITY (DHMI) 2016 DHMİ AIRPORT CHARGES Charges Page 1 International Landing and Parking Charges 1 2 Passenger Service Charges 5 3 Charges for

More information

Turkish Energy Market: An Investor's Guide

Turkish Energy Market: An Investor's Guide Turkish Energy Market: An Investor's Guide 2012 ENERGY MARKET REGULATORY AUTHORITY Muhsin Yazıcıoğlu Cad. No: 51/C 06530 Yüzüncüyıl - Ankara / TURKEY www.epdk.gov.tr www.epdk.org.tr Turkish Energy Market:

More information

Zeynep ÖZLER Melih ÖZSÖZ Economic Development Foundation - TURKEY. Visa Situation in Turkey

Zeynep ÖZLER Melih ÖZSÖZ Economic Development Foundation - TURKEY. Visa Situation in Turkey Zeynep ÖZLER Melih ÖZSÖZ Economic Development Foundation - TURKEY Visa Situation in Turkey Strengthening the triangle CSOs National Governments- European Commission-Reinforcing the Europe-wide civil society

More information

ENERGY MARKET REGULATORY AUTHORITY. Electricity Market Report

ENERGY MARKET REGULATORY AUTHORITY. Electricity Market Report ENERGY MARKET REGULATORY AUTHORITY Electricity Market Report 2010 The translation of the Electricity Market Report 2010 has been completed with the valuable contributions of Association of Energy Experts.

More information

TURKISH ECONOMIC ASSOCIATION. DISCUSSION PAPER 2011/4 http ://www.tek. org.tr PRIVATIZATION AND REGIONAL DISTRIBUTION OF MANUFACTURING IN TURKEY

TURKISH ECONOMIC ASSOCIATION. DISCUSSION PAPER 2011/4 http ://www.tek. org.tr PRIVATIZATION AND REGIONAL DISTRIBUTION OF MANUFACTURING IN TURKEY TURKISH ECONOMIC ASSOCIATION DISCUSSION PAPER 2011/4 http ://www.tek. org.tr PRIVATIZATION AND REGIONAL DISTRIBUTION OF MANUFACTURING IN TURKEY Fatma Doğruel and A.Suut Doğruel April, 2011 Privatization

More information

Financing Wind Energy in Turkey. Emre Hatem Head of Project & Acquisition Finance Garanti Bank

Financing Wind Energy in Turkey. Emre Hatem Head of Project & Acquisition Finance Garanti Bank Financing Wind Energy in Turkey Emre Hatem Head of Project & Acquisition Finance Garanti Bank DISCLAIMER This document has been drafted with an informative purpose, having the information contained herein

More information

The Impacts of Internal Migration on Urban and Work Life in Istanbul

The Impacts of Internal Migration on Urban and Work Life in Istanbul The Impacts of Internal Migration on Urban and Work Life in Istanbul Mustafa Öztürk Abstract: The main destinations of internal migration movements that originated in Turkey in the 1950s as a result of

More information

REFERENCES LİST VAN 500 BEDS STATE HOSPITAL

REFERENCES LİST VAN 500 BEDS STATE HOSPITAL REFERENCES LİST BURSA CEKIRGE 700 BEDS STATE SANLIURFA EYYUBIYE 533 BEDS STATE ISPARTA SULEYMAN DEMIREL UNIVERSITY 500 BEDS TRAINING AND RESEARCH VAN 500 BEDS STATE MUGLA 475 BEDS STATE ORDU UNYE 400 BEDS

More information

ELDER ELECTRICITY DISTRIBUTION SYSTEM OPERATORS OF TURKEY

ELDER ELECTRICITY DISTRIBUTION SYSTEM OPERATORS OF TURKEY ELDER ELECTRICITY DISTRIBUTION SYSTEM OPERATORS OF TURKEY PREAMBLE ELDER is one of the oldest NGO s in the electricity sector with its almost 15-year history. Since its establishment, it has aimed to

More information

Intangible Cultural Heritage Safeguarding Efforts

Intangible Cultural Heritage Safeguarding Efforts Field Survey Report Intangible Cultural Heritage Safeguarding Efforts in the Asia-Pacific 2013 International Information and Networking Centre for Intangible Cultural Heritage in the Asia-Pacific Region

More information

SHEEP AND GOAT MEAT Non-exhaustive list of issues and questions to facilitate preparations for bilateral meetings TURKEY

SHEEP AND GOAT MEAT Non-exhaustive list of issues and questions to facilitate preparations for bilateral meetings TURKEY 1. General situation of the sector SHEEP AND GOAT MEAT Non-exhaustive list of issues and questions to facilitate preparations for bilateral meetings TURKEY 2002 2003 2004 1 2005 (f) Production: Total size

More information

Rumeli Cement Group Plants Preliminary Information. September 2004

Rumeli Cement Group Plants Preliminary Information. September 2004 Rumeli Cement Group Plants Preliminary Information September 2004 The present document has been prepared by Rumeli Group, Ernst & Young and Garanti Securities in good faith for information purposes only,

More information

Investor Presentation December 31, 2014

Investor Presentation December 31, 2014 Investor Presentation December 31, 2014 Leasing Sector in Turkey 3 LEASING VAT is %1 for various types of machinery. New Leasing Law approved (13/12/2012,Law no:6361). Product differentiation; Operating

More information

Investor Presentation 31 MARCH 2015

Investor Presentation 31 MARCH 2015 Investor Presentation 31 MARCH 2015 Leasing Sector in Turkey 3 LEASING VAT is %1 for various types of machinery. New Leasing Law approved (13/12/2012,Law no:6361). Product differentiation; Operating Leases,

More information

DENİZBANK FINANCIAL SERVICES GROUP ANNUAL REPORT 2013

DENİZBANK FINANCIAL SERVICES GROUP ANNUAL REPORT 2013 DENİZBANK FINANCIAL SERVICES GROUP ANNUAL REPORT 2013 DenizBank is a member of Sberbank Group. SECTION I INTRODUCTION 1 DenizBank Financial Services Group (DFSG) 2 DenizBank s Mission and Vision 2 Dividend

More information

Gas transport tariffs calculation

Gas transport tariffs calculation Ad Hoc Expert Facility under the INOGATE project Support to Energy Market Integration and Sustainable Energy in the NIS (SEMISE) Gas transport tariffs calculation 1 TABLE OF CONTENTS 1. INTRODUCTION...

More information

How To Understand And Understand The Financial Sector In Turkish Finance Companies

How To Understand And Understand The Financial Sector In Turkish Finance Companies FEBRUARY 14, 2013 BANKING SECTOR COMMENT Turkish Finance Companies: New legislation on Financial Leasing, Factoring and Financing Institutions Is Credit Positive Table of Contents: SUMMARY OPINION 1 OVERVIEW

More information

Developments in Turkey in the Context of Participatory Approach Based on River Basin Management. Nermin ÇİÇEK, Özge Hande SAHTİYANCI

Developments in Turkey in the Context of Participatory Approach Based on River Basin Management. Nermin ÇİÇEK, Özge Hande SAHTİYANCI Developments in Turkey in the Context of Participatory Approach Based on River Basin Management Nermin ÇİÇEK, Özge Hande SAHTİYANCI The Ministry of Forestry and Water Affairs, General Directorate of Water

More information

Tipco Asphalt Public Company Limited (TASCO)

Tipco Asphalt Public Company Limited (TASCO) (TASCO) Q1/2015 Opportunity Day 4 th June 2015 1 Disclaimer This presentation material has been prepared solely for informational purposes only. TASCO is furnishing it solely for use by prospective investors

More information

A Spotlight on. Cem Ali ATILGAN Atılgan Energy Ltd. June 3-4, 2009 - Budapest

A Spotlight on. Cem Ali ATILGAN Atılgan Energy Ltd. June 3-4, 2009 - Budapest A Spotlight on Turkish Electricity market by Cem Ali ATILGAN Atılgan Energy Ltd. June 3-4, 2009 - Budapest Outline Section 1 : Brief Turkish Electricity Market Overview Turkey at a Glance Comparison of

More information

Financial Services AKBANK

Financial Services AKBANK sabanc hold ng 2007 annual report 32 Financial Services AKBANK As of the end of 2007, Akbank was Turkey's most valuable bank having the most profitable banking operations among privately owned banks in

More information

Electricity in Egypt

Electricity in Egypt T: (+20) 2 3760 4592 F: (+20) 2 3760 4593 A: 16 Hussein Wassef Street, Messaha Square Dokki, Giza, Egypt 12311 www.ide.com.eg Electricity in Egypt Policy and Regulatory Reform November 2015 Electricity

More information

Mother Child Education Foundation

Mother Child Education Foundation 2007 Annual Report Contents 1 Mother Child Education Foundation 2 President s Message 6 Board of Trustees and Board of Directors 7 Our Consultants 10 ACEV Programs and Activities 11 ACEV's Approach 12

More information

THE TURKISH RENEWABLE ENERGY LAW: STILL HUNGRY I. INTRODUCTION

THE TURKISH RENEWABLE ENERGY LAW: STILL HUNGRY I. INTRODUCTION THE TURKISH RENEWABLE ENERGY LAW: STILL HUNGRY By Mehtap Yildirim Öztürk and Çagdas Evrim Ergün ε Turkey has recently enacted its first renewable energy law, namely Law No. 5346 Concerning the Use of Renewable

More information

TURKEY. Energy Policies of IEA Countries. 2009 Review

TURKEY. Energy Policies of IEA Countries. 2009 Review Energy Policies of IEA Countries Please note that this PDF is subject to specific restrictions that limit its use and distribution. The terms and conditions are available online at www.iea.org/about/copyright.asp

More information

Emlak Konut REIT. Equity / Large Cap. / Real Estate Investment Trust. Bloomberg: EKGYO TI OUTPERFORM. Reuters: EKGYO IS.

Emlak Konut REIT. Equity / Large Cap. / Real Estate Investment Trust. Bloomberg: EKGYO TI OUTPERFORM. Reuters: EKGYO IS. Equity / Large Cap. / Real Estate Investment Trust Emlak Konut REIT Bloomberg: EKGYO TI Reuters: EKGYO IS 01/06/2012 Company Report OUTPERFORM Upside Potential* 42% Good entry point for the long term investors

More information

Rule change request. 18 September 2013

Rule change request. 18 September 2013 Reform of the distribution network pricing arrangements under the National Electricity Rules to provide better guidance for setting, and consulting on, cost-reflective distribution network pricing structures

More information

Renewable Electricity and Liberalised Markets REALM. JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN. By ICCS / NTUA K. Delkis

Renewable Electricity and Liberalised Markets REALM. JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN. By ICCS / NTUA K. Delkis Renewable Electricity and Liberalised Markets REALM JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN By ICCS / NTUA K. Delkis October 1999 INTRODUCTION AND BACKGROUND Background to Renewable Energy

More information

RECOMMENDATIONS ON BUSINESS PLAN PREPARATION

RECOMMENDATIONS ON BUSINESS PLAN PREPARATION RECOMMENDATIONS ON BUSINESS PLAN PREPARATION 1. General provisions Business plan must contain: name of the investment project, as well description of its essence and feasibility; substantiation of the

More information

Competitive Electricity Procurement

Competitive Electricity Procurement Competitive Electricity Procurement To assist Texas political subdivisions in identifying variables and qualifications needed to make an "apples to apples" comparison of bid responses, the Texas General

More information

How To Read The Unitholders Of The Kukon Island Power Station

How To Read The Unitholders Of The Kukon Island Power Station E.ON s UK Consolidated Segmental Report for the year ended 31 December 2012 Introduction In accordance with the Electricity Generation Licence Condition 16 - Financial Information Reporting, and the Electricity

More information

3 Classification of post items to the letters according to their size (Conv., art. 14; Regs., art. RL 121.2) No

3 Classification of post items to the letters according to their size (Conv., art. 14; Regs., art. RL 121.2) No Currency : TRL Basic services Mail classification system (Conv., art. 13.3; Regs., art. RL 120) 1 Based on speed of treatment of items (Regs., art. RL 120.2): 1.1 Priority and non-priority items may weigh

More information