1 AUDIT AND ASSURANCE COMMITTEE Meeting date: 10 th June 2014 From: Corporate Director - Environment and Community Services CONNECTING CUMBRIA CONTRACT MANAGEMENT 1.0 EXECUTIVE SUMMARY 1.1 This report is an update on the corporate risks associated with the Connecting Cumbria Project and the systems operating in order to mitigate their impact. 2.0 POLICY POSITION, BUDGETARY AND EQUALITY IMPLICATIONS, AND LINKS TO COUNCIL PLAN 2.1 The key objectives of Connecting Cumbria are to ensure digital inclusion amongst our communities, encouraging economic growth through increasing the competitiveness of Cumbria businesses and delivering public sector efficiencies through the reengineering of ICT networks and services. Connecting Cumbria therefore supports all objectives in the Council Plan Challenging poverty in all its forms; Ensuring that the most vulnerable people in our communities receive the support they need; and Improving the chances in life of the most disadvantaged in Cumbria Deliver a Superfast Broadband service across the whole of Cumbria, stimulating inward investment to make this happen through 3 channels Encourage private sector investment Use public sector funding to support the commercial business case where there is no commercial market

2 Work with communities in the hardest to reach areas where the public sector investment is not achievable 3.0 RECOMMENDATION 3.1 That the content of the report be noted. 4.0 BACKGROUND 4.1 Following a protracted procurement process, with programme delays incurred securing European Commission approval for State Aids and Major project approval, early works started in earnest in April This was followed in September 2013 with design work and first deployments taking place. The overall aim of the programme is to deliver at least a 2mb/s service to all properties in Cumbria with 93% of properties being able to order and access a service of 24mb/s or above. State aid and Major Project Approval were finally approved in June The Connecting Cumbria programme has two elements. a) Infrastructure which is delivered through a contract with BT. This is the infrastructure build and absorbs the vast majority of the funding with it targeted primarily at delivering infrastructure for European Regional Development Fund(ERDF) eligible businesses. The delivery to community groups is added value and paid for through funding from Broadband Delivery UK (BDUK), Performance Reward Grant (PRG) and BT funds. b) Business Support which is through a contract with a local company Commendium. This provides support to eligible businesses and is coordinated so that it runs in parallel to the roll out of Superfast broadband Cabinets. 4.3 The main contract was awarded to BT in November 2012 for delivery of the infrastructure and was made up of funding mostly through grant: PRG - 6.9m ERDF m BDUK m In addition BT are spending 15m 4.4 This represents an investment in Broadband infrastructure in Cumbria of 52m overall for a Council outlay of 6.9m of PRG. As a result of this project and Commercial deployments of broadband by BT, at the end of May % of properties in Cumbria will have access to Super fast Broadband. 4.5 The Commendium Contract was awarded in February 2013 and is jointly funded through ERDF and PRG. This contract, of 2.39m, aims to support 1973 businesses and will be complete by April 2015.

3 4.6 Spend to date on the Commendium contract has been 831,994 AND 739 Businesses have been assisted 5.0 RISKS 5.1 The previous entry for Connecting Cumbria on the corporate risk register was: There is a risk that Cumbria County Council cannot deliver the Super-Fast Broad Band project to match the expectation of the public and to the agreed schedule. This is caused by failure to secure sufficient funding or State Aid, to procure an appropriate contract, to effectively communicate with the public, failure to manage expectations and delays as a result of legal or political challenges. This will result in damage to Cumbria County Council s reputation and an inability to deliver the programme objectives. 5.2 Since the project is now underway, this is no longer a risk and the following risk has been assessed and placed on the corporate risk register: Failure to complete delivery of SFBB to provide 100% coverage and 93% Superfast due to supplier non delivery, issues around grant funding, change in national policy, political or legal challenges. 5.3 Depending on the reason and extent of the shortfall, this may result in ongoing economic disadvantage to the people and enterprises of Cumbria as other Counties would be able to provide better infrastructure. It may also result in damage to the reputation of Cumbria County Council. As a consequence this risk has been assigned a rating of To protect the council and encourage BT to continue to deliver, the Council legal position has been formally stated through an exchange of letters via an external legal firm - Addleshaw Goddard. 5.5 The Council position is that any failure to meet the funding requirements would be the responsibility of BT and that in the situation of any underperformance they are still liable to deliver the full project on the reduced funds. This conversation continues but has already had the effect of BT responding positively to ensure the project continues to deliver. 5.6 This is a complex project and it is possible that loss of ERDF funds could be made up in several ways: a) Funds returned under the contract by BT if take up of super fast broadband exceeds 20% b) Savings in BT project management costs that we are anticipating as a result of working together with BDUK and other authorities to benchmark and challenge BT on some costs within the project. c) Contingency of 1.4 M has been set aside to cover any possible loss of ERDF funds 5.7 There is also an acknowledgement that an upside risk exists that this project may deliver more than 93% superfast broadband. This could occur

4 through either faster roll out of the Cabinets or any increased uptake beyond 20% which would result in further money being available to the programme. 6.0 CONCLUSION 6.1 Through an investment of 6.9m of PRG a total of 52m investment has been secured to deliver the infrastructure to support both businesses and communities and ensure the project is already a success story. 6.2 Connecting Cumbria has already supported 739 businesses and 21 jobs have been created within those companies as a result of the project. 6.3 The delivery on the ground of the BT contract is progressing ahead of schedule with more than 50 % of properties in Cumbria now able to get access to Superfast Broadband and shows every sign of exceeding the 93% delivery promised by December The contract requires and has received robust management to keep the contract on track and to ensure that maximum value is achieved. 6.5 Risks continue to be identified and managed through the project team working with the suppliers to mitigate the impact of such risks. David Morton Senior Programme Manager Connecting Cumbria 06/05/14 APPENDICES No appendices IMPLICATIONS Staffing: * Financial: * Property: * Electoral Division(s): * PREVIOUS RELEVANT COUNCIL OR EXECUTIVE DECISIONS [including Local Committees] No previous relevant decisions.

5 CONSIDERATION BY OVERVIEW AND SCRUTINY Considered by Overview and Scrutiny BACKGROUND PAPERS No background papers. Contact: David Morton Senior Programme Manager Connecting Cumbria 06/05/14

REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 535 SESSION 2013-14 5 JULY 2013. Department for Culture, Media & Sport. The rural broadband programme

REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 535 SESSION 2013-14 5 JULY 2013. Department for Culture, Media & Sport. The rural broadband programme REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 535 SESSION 2013-14 5 JULY 2013 Department for Culture, Media & Sport The rural broadband programme 4 Key facts The rural broadband programme Key facts

More information

First Making Kent Quicker Broadband Services go live

First Making Kent Quicker Broadband Services go live Making Kent Quicker Update: December 2013 First Making Kent Quicker Broadband Services go live We are delighted to announce that the first high speed broadband services to be funded under the Making Kent

More information

The Making Kent Quicker Programme covers a range of projects that Kent County Council is leading to improve broadband infrastructure.

The Making Kent Quicker Programme covers a range of projects that Kent County Council is leading to improve broadband infrastructure. What is the Making Kent Quicker Programme? The Making Kent Quicker Programme covers a range of projects that Kent County Council is leading to improve broadband infrastructure. These include the Kent and

More information

HIGH-SPEED BROADBAND IN KESWICK DELIVERS BOOST FOR TOURISM; Technology will boost businesses, according to research;

HIGH-SPEED BROADBAND IN KESWICK DELIVERS BOOST FOR TOURISM; Technology will boost businesses, according to research; DC14-372 EMBARGOED FOR USE UNTIL 00.01 HOURS FRIDAY AUGUST 8, 2014 HIGH-SPEED BROADBAND IN KESWICK DELIVERS BOOST FOR TOURISM; Technology will boost businesses, according to research; Local broadband champion

More information

The Making Kent Quicker Programme covers a range of projects that Kent County Council is leading on to improve broadband infrastructure.

The Making Kent Quicker Programme covers a range of projects that Kent County Council is leading on to improve broadband infrastructure. What is the Making Kent Quicker Programme? The Making Kent Quicker Programme covers a range of projects that Kent County Council is leading on to improve broadband infrastructure. These include the Kent

More information

EMBARGOED UNTIL THURSDAY 2 OCTOBER 2014. Connecting Cumbria fibre broadband team celebrates first birthday

EMBARGOED UNTIL THURSDAY 2 OCTOBER 2014. Connecting Cumbria fibre broadband team celebrates first birthday DC14-465 EMBARGOED UNTIL THURSDAY 2 OCTOBER 2014 Connecting Cumbria fibre broadband team celebrates first birthday Landmark passed as 50,000 homes and businesses get fibre through 200 new cabinets Lake

More information

Corporate Director Environment & Community Services

Corporate Director Environment & Community Services CABINET Meeting date: 23 July 2015 From: Corporate Director Environment & Community Services DIGITAL STRATEGY 1.0 EXECUTIVE SUMMARY 1.1 This paper presents Cabinet with a draft Digital Strategy for approval.

More information

Working together to bring high-speed broadband providers to Herefordshire and Gloucestershire

Working together to bring high-speed broadband providers to Herefordshire and Gloucestershire Briefing Note No.5 April 2012 www.herefordshire.gov.uk/broadband www.glosfirst.co.uk/broadband Working together to bring high-speed broadband providers to Herefordshire and Gloucestershire click on highlighted

More information

Digital Inclusion Programme Started. BL2a

Digital Inclusion Programme Started. BL2a PROJECT BRIEF Project Name Digital Inclusion Programme Status: Started Release 18.05.2011 Reference Number: BL2a Purpose This document provides a firm foundation for a project and defines all major aspects

More information

Community Development Group. Update on Delivery of Rural Broadband in Rushcliffe

Community Development Group. Update on Delivery of Rural Broadband in Rushcliffe Community Development Group 29 October 2013 Update on Delivery of Rural Broadband in Rushcliffe 4 Report of the Executive Manager - Transformation Summary Over the past two years, Nottinghamshire County

More information

Broadband Leicestershire Stakeholder Briefing. 11 th February 2013 Leicestershire County Council, County Hall

Broadband Leicestershire Stakeholder Briefing. 11 th February 2013 Leicestershire County Council, County Hall Broadband Leicestershire Stakeholder Briefing 11 th February 2013 Leicestershire County Council, County Hall Programme Welcome Mrs Lesley Pendleton Next Generation Access from BT Paul Bimson Broadband

More information

The Welsh Government's Broadfast Cymru Contract and Its Role in Network Infrastructure Development

The Welsh Government's Broadfast Cymru Contract and Its Role in Network Infrastructure Development 28 May 2015 Archwilydd Cyffredinol Cymru Auditor General for Wales Welsh Government investment in next generation broadband infrastructure I have prepared and published this report in accordance with

More information

Phase 1 Summary BDUK 90% SFBB 2015/16

Phase 1 Summary BDUK 90% SFBB 2015/16 Shared Information All information is for the use of the Parish Council and is shared in good faith with the sole purpose of full and open engagement All projected information remains open to change and

More information

Welcome. First Phase Deployment Briefing. Julian Cobley Project Director

Welcome. First Phase Deployment Briefing. Julian Cobley Project Director Welcome First Phase Deployment Briefing Julian Cobley Project Director Programme 1. Introduction: Connecting Cheshire Overview Julian Cobley 2. Infrastructure: BT s role in the Project Bill Murphy; BT

More information

Staffordshire Moorlands Service Delivery Overview & Scrutiny Panel Superfast Staffordshire Highlight Report

Staffordshire Moorlands Service Delivery Overview & Scrutiny Panel Superfast Staffordshire Highlight Report AGENDA ITEM 9 Staffordshire Moorlands Service Delivery Overview & Scrutiny Panel Superfast Staffordshire Highlight Report 2 nd July 2014 Executive Summary The Superfast Staffordshire project is now in

More information

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY VERSION 1.0 ISSUED JULY 2015 CONTENTS Page CONTENTS VERSION CONTROL FOREWORD i ii iii POLICY 1 Scope 1 Aim and Objectives 1 Methods and Standards 1

More information

Waddesdon Local Area Forum Broadband update. Waddesdon Primary School Wednesday 20 th November 2013

Waddesdon Local Area Forum Broadband update. Waddesdon Primary School Wednesday 20 th November 2013 Waddesdon Local Area Forum Broadband update Waddesdon Primary School Wednesday 20 th November 2013 Buckinghamshire Business First Strategic economic development organisation Provides wide variety of business

More information

Getting a Basic Broadband service A guide for those who may wish to apply to benefit from the scheme

Getting a Basic Broadband service A guide for those who may wish to apply to benefit from the scheme Getting a Basic Broadband service A guide for those who may wish to apply to benefit from the scheme If you currently experience poor broadband speeds, or you are unable to obtain an affordable broadband

More information

Openreach's UMSUG Application

Openreach's UMSUG Application Openreach's UMSUG Application 16 th April 2013 Phil Royal Openreach Purpose Application to obtain UMSUG approved charge codes for Openreach Superfast Broadband communication cabinets. About Openreach In

More information

REPORT TO: ECONOMIC DEVELOPMENT AND INFRASTRUCTURE SERVICES COMMITTEE ON 25 AUGUST 2015

REPORT TO: ECONOMIC DEVELOPMENT AND INFRASTRUCTURE SERVICES COMMITTEE ON 25 AUGUST 2015 PAGE: 1 REPORT TO: ECONOMIC DEVELOPMENT AND INFRASTRUCTURE SERVICES COMMITTEE ON 25 AUGUST 2015 SUBJECT: BY: BROADBAND INFRASTUCTURE COVERAGE CORPORATE DIRECTOR (ECONOMIC DEVELOPMENT, PLANNING & INFRASTRUCTURE)

More information

Superfast broadband for Scotland. A progress report

Superfast broadband for Scotland. A progress report Superfast broadband for Scotland A progress report Prepared by Audit Scotland February 2015 Auditor General for Scotland The Auditor General s role is to: appoint auditors to Scotland s central government

More information

Broadband Delivery UK. National Broadband Scheme for the UK: Supporting the local and community roll-out of superfast broadband

Broadband Delivery UK. National Broadband Scheme for the UK: Supporting the local and community roll-out of superfast broadband Please Note: This document is made available by BDUK to local bodies for guidance in respect of local broadband projects. It is not to be used for any other purpose. This document may contain certain high

More information

Superfast Northamptonshire Business Demand Registration Survey. Results and Analysis

Superfast Northamptonshire Business Demand Registration Survey. Results and Analysis Superfast Northamptonshire Business Demand Registration Survey Results and Analysis November 2013 1 Business Survey: Results and Analysis Contents Page 1.0 Context...3 2.0 Methodology...3 3.0 Summary of

More information

Document Purpose: Sets out the Local Broadband Strategy for the Connecting Shropshire Programme. The content is only current at the time of issue.

Document Purpose: Sets out the Local Broadband Strategy for the Connecting Shropshire Programme. The content is only current at the time of issue. Document Purpose: Sets out the Local Broadband Strategy for the Connecting Shropshire Programme. The content is only current at the time of issue. Version History Version Issue Date Brief Summary of Change

More information

Superfast Berkshire Project Update September 2015

Superfast Berkshire Project Update September 2015 Superfast Berkshire Project Update September 2015 We are pleased to provide an update to Digital Champions on the Superfast Berkshire project. We appreciate that these updates have not been as frequent

More information

FREE Business Support from Superfast Lancashire

FREE Business Support from Superfast Lancashire FREE Business Support from Superfast Lancashire Objective & Content To provide the answers to the following questions What is Superfast Lancashire? Why are we doing this? What can you get from the programme?

More information

#superfaststaffordshire. Bill Murphy Managing Director, Next Generation Access BT Group

#superfaststaffordshire. Bill Murphy Managing Director, Next Generation Access BT Group #superfaststaffordshire Bill Murphy Managing Director, Next Generation Access BT Group Fibre broadband: the legacy for Staffordshire starts today Bill Murphy Managing Director, Next Generation Access BT

More information

SUPERFAST BROADBAND IS COMING TO CUMBRIA

SUPERFAST BROADBAND IS COMING TO CUMBRIA SUPERFAST BROADBAND IS COMING TO CUMBRIA WHAT S CONNECTING CUMBRIA ALL ABOUT? THE VISION FOR CUMBRIA That everyone in Cumbria every resident, business, organisation and visitor to the county has access

More information

Appendix A: ICT and Information Management Strategy

Appendix A: ICT and Information Management Strategy Appendix A: ICT and Information Management 2014 2019 Head of Information and Business Change Sarah Caulkin October 2014 1 Version Control: Date Version Author Comments 04/08/14 0.1 Jo Harley First draft

More information

EAST AYRSHIRE COUNCIL CABINET27 NOVEMBER 2013 STEP CHANGE 2015 PROJECT UPDATE. Report by the Acting Executive Director of Neighbourhood Services

EAST AYRSHIRE COUNCIL CABINET27 NOVEMBER 2013 STEP CHANGE 2015 PROJECT UPDATE. Report by the Acting Executive Director of Neighbourhood Services PURPOSE EAST AYRSHIRE COUNCIL CABINET27 NOVEMBER 2013 STEP CHANGE 2015 PROJECT UPDATE Report by the Acting Executive Director of Neighbourhood Services 1 The purpose of this report is to provide an update

More information

RECOMMENDATIONS FROM ENTERPRISE AND GROWTH SCRUTINY COMMITTEE - BROADBAND IN SHROPSHIRE

RECOMMENDATIONS FROM ENTERPRISE AND GROWTH SCRUTINY COMMITTEE - BROADBAND IN SHROPSHIRE Committee and Date Cabinet 15 February 2011 Item 6 12.30 pm Public RECOMMENDATIONS FROM ENTERPRISE AND GROWTH SCRUTINY COMMITTEE - BROADBAND IN SHROPSHIRE Scrutiny Committee: Enterprise and Growth Scrutiny

More information

Update on the SharePoint 2010 Programme and Projects Portal

Update on the SharePoint 2010 Programme and Projects Portal Wiltshire Council Overview and Scrutiny Management Committee 13 December 2012 Update on the SharePoint 2010 Programme and Projects Portal Purpose of report 1. This report is to update the committee on

More information

Cabinet Member for Corporate Relations

Cabinet Member for Corporate Relations Cabinet Member for Corporate Relations Proposal for new customer experience October 2015 Report by the Executive Director Residents Services and the Director of Customer Services Ref No: CR05(15/16) Key

More information

Broadband Development in South Kesteven?

Broadband Development in South Kesteven? Communities PDG Briefing Note Fibre Optic Broadband in South Kesteven Background The County and District Councils of Lincolnshire are currently working together in the development and delivery of the onlincolnshire

More information

Rolling out fibre the BT reality. Bill Murphy, Managing Director, NGA BT

Rolling out fibre the BT reality. Bill Murphy, Managing Director, NGA BT Rolling out fibre the BT reality Bill Murphy, Managing Director, NGA BT Good news from the Government By 2015 Our goal is simple: within this parliament we want Britain to have the best superfast broadband

More information

The Current South Yorkshire Council Risk Register Summary

The Current South Yorkshire Council Risk Register Summary ROTHERHAM BOROUGH COUNCIL REPORT TO AUDIT COMMITTEE 1. Meeting: Audit Committee 2. Date: 23 April 14 3. Title: Corporate Risk Register 4. Directorate: Environment & Development Services 5. Summary Attached

More information

The Superfast (Rural) Broadband Programme: update

The Superfast (Rural) Broadband Programme: update Memorandum for the House of Commons Committee of Public Accounts Department for Culture, Media & Sport The Superfast (Rural) Broadband Programme: update JANUARY 2015 Our vision is to help the nation spend

More information

Building a Broadband Future. Cllr Keith Barrow

Building a Broadband Future. Cllr Keith Barrow Building a Broadband Future Cllr Keith Barrow Agenda and Introductions 11.00 Welcome and introductions - Cllr Keith Barrow 11:05 Connecting Shropshire Programme - Cllr Keith Barrow /Andrew Evans (Connecting

More information

Superfast Cornwall Extension Programme To further extend coverage of Superfast Broadband across Cornwall

Superfast Cornwall Extension Programme To further extend coverage of Superfast Broadband across Cornwall 25 May 2016 Superfast Cornwall Extension Programme To further extend coverage of Superfast Broadband across Cornwall STATE AID PUBLIC CONSULTATION 1. Introduction The Superfast Cornwall Extension Programme

More information

Big investment, big challenges - the BT view. Bill Murphy, Managing Director NGA, BT

Big investment, big challenges - the BT view. Bill Murphy, Managing Director NGA, BT Big investment, big challenges - the BT view Bill Murphy, Managing Director NGA, BT What a difference a year makes Good news from the Government By 2015 Our goal is simple: within this parliament we want

More information

Memorandum to the Public Administration Select Committee

Memorandum to the Public Administration Select Committee Memorandum to the Public Administration Select Committee Government Response to the Public Administration Select Committee s report: Government and IT a recipe for rip-offs : time for a new approach: Further

More information

Centre for Rural Economy Policy and Practice BRIEFING PAPERS: Rural Broadband

Centre for Rural Economy Policy and Practice BRIEFING PAPERS: Rural Broadband Centre for Rural Economy Policy and Practice BRIEFING PAPERS: www.newcastle.ac.uk/cre Hilary Talbot, Centre for Rural Economy How are rural areas disadvantaged? Many rural parts of Britain have an inadequate

More information

Cabinet Meeting. Bill Murphy, Managing Director Next Generation Access

Cabinet Meeting. Bill Murphy, Managing Director Next Generation Access Lancashire County Council Cabinet Meeting Bill Murphy, Managing Director Next Generation Access BT s fibre broadband roll-out 2.5bn investment to bring superfast fibre broadband to around two-thirds of

More information

Understanding the benefits of Superfast Fibre Access (SFFA) for Small Businesses

Understanding the benefits of Superfast Fibre Access (SFFA) for Small Businesses Understanding the benefits of Superfast Fibre Access (SFFA) for Small Businesses Openreach Web Seminar In conjunction with Comms Dealer Nigel Sergent, Comms Dealer Editorial Director Gemma Thompson, Openreach

More information

Mobile and Broadband Communications Willoughby, Warwickshire.

Mobile and Broadband Communications Willoughby, Warwickshire. Mobile and Broadband Communications Willoughby, Warwickshire. Broadband Services The EU has set targets for everyone to have Superfast Broadband (24 mbs+) by 2020. The UK Government has setup BDUK (Broadband

More information

Broadband Fit for Rural Growth: CLA VISION FOR RURAL BROADBAND. Country Land & Business Association

Broadband Fit for Rural Growth: CLA VISION FOR RURAL BROADBAND. Country Land & Business Association Broadband Fit for Rural Growth: CLA VISION FOR RURAL BROADBAND Country Land & Business Association CONTACTS For more information on Broadband Fit for Rural Growth: CLA vision for rural broadband, published

More information

Superfast Fibre Broadband rollout is on the way to Argyll and Bute. February 2015

Superfast Fibre Broadband rollout is on the way to Argyll and Bute. February 2015 Superfast Fibre Broadband rollout is on the way to Argyll and Bute February 2015 Next Generation Broadband Rollout Objectives Scottish Government s target is for Scotland to be a world class digital nation

More information

Marketing Projects Manager (Business Birmingham) (Fixed term contract to run until 31 March 2015) This post is funded by the European Union.

Marketing Projects Manager (Business Birmingham) (Fixed term contract to run until 31 March 2015) This post is funded by the European Union. Job profile Title: Marketing Projects Manager (Business Birmingham) Salary: circa 30,000-35,000 (Fixed term contract to run until 31 March 2015) This post is funded by the European Union. Job Purpose:

More information

REPORT FOR INFORMATION

REPORT FOR INFORMATION REPORT FOR INFORMATION REPORT TO: REPORT NO: All Members HAED/30/12S DATE: 30 January 2013 LEAD OFFICER: Head of Assets and Economic Development CONTACT OFFICER: Peter Scott (ext 2405) Dave Coates (ext

More information

Superfast Essex Broadband Programme Phase 2

Superfast Essex Broadband Programme Phase 2 State Aid Public Consultation Superfast Essex Broadband Programme Phase 2 Area Impacted: All parishes in Essex, Southend and Thurrock Consultation period: Thursday 16 th October 2014 to Monday 17 th November

More information

Business Continuity Policy. Version 1.0

Business Continuity Policy. Version 1.0 Business Continuity Policy Version.0 January 206 Contents Contents Version control Foreword Policy. Scope.2 Aim and objectives.3 Methods and standards.4 Responsibilities.5 Governance.6 Training and exercises

More information

Revised Risk Management Policy and Framework. Report by Head of Finance

Revised Risk Management Policy and Framework. Report by Head of Finance Audit Committee 29 April 2010 Item No 7 Revised Risk Management Policy and Framework Report by Head of Finance Summary A substantial review of our current Risk Management Strategy has been carried out.

More information

Central Superfast Broadband Project Frequently Asked Questions

Central Superfast Broadband Project Frequently Asked Questions Central Superfast Broadband Project Frequently Asked Questions What is the Central Superfast Broadband Project? The Central Superfast Broadband Project is a partnership between Central Bedfordshire Council,

More information

Councillor David Chambers Date of Decision/Referral to O & S REPORT OF: STRATEGIC DIRECTOR (CORPORATE) SDC/08/37

Councillor David Chambers Date of Decision/Referral to O & S REPORT OF: STRATEGIC DIRECTOR (CORPORATE) SDC/08/37 REPORT TO INDIVIDUAL CABINET MEMBER FOR FINANCE, LEGAL AND ICT 20 MAY 2008 Key Decision YES Forward Plan Ref No Corporate Priority ALL Cabinet Portfolio Holder : Councillor David Chambers Date of Decision/Referral

More information

Communities now connected

Communities now connected November 2014 The Better Broadband for Oxfordshire partnership between Oxfordshire County Council, BT and Broadband Delivery UK (BDUK) has now delivered fibre-enabled broadband to more than 16,000 homes

More information

DERBYSHIRE COUNTY COUNCIL CABINET MEMBER MEETING 14 OCTOBER 2008. Report of the Director of Transformation and Corporate IT Manager

DERBYSHIRE COUNTY COUNCIL CABINET MEMBER MEETING 14 OCTOBER 2008. Report of the Director of Transformation and Corporate IT Manager In preparing this report the relevance of the following factors has been considered; financial, legal, prevention of crime and disorder, equality of opportunity; and environmental, health, human resources,

More information

Response of Channel 5 Broadcasting Ltd to Ofcom s Consultation on Securing Long Term Benefits from Scarce Spectrum Resources

Response of Channel 5 Broadcasting Ltd to Ofcom s Consultation on Securing Long Term Benefits from Scarce Spectrum Resources Response of Channel 5 Broadcasting Ltd to Ofcom s Consultation on Securing Long Term Benefits from Scarce Spectrum Resources INTRODUCTION Channel 5 welcomes the opportunity to respond to this forward-thinking

More information

Business Support Service Development Manager

Business Support Service Development Manager Job Profile Job Title: Business Support Service Development Manager Date Completed: 17/12/2014 Job Reference Number: T5CS0021 Tier: Tier 5 Job Band: Band 6 Functional Area: Corporate Services Accountable

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS What is this project about? Who is behind it? Why was this area chosen? How much will the project cost? Who will get improved broadband? When will it all happen? FREQUENTLY ASKED QUESTIONS What will improved

More information

Next Generation Access: Enabling Transformation. Bill Murphy - Managing Director, NGA BT Group

Next Generation Access: Enabling Transformation. Bill Murphy - Managing Director, NGA BT Group Next Generation Access: Enabling Transformation Bill Murphy - Managing Director, NGA BT Group Good news from the Government Our goal is simple: within this By 2015 parliament we want Britain to have the

More information

Getting a Basic Broadband service. A guide for those who may wish to apply to benefit from the scheme

Getting a Basic Broadband service. A guide for those who may wish to apply to benefit from the scheme Getting a Basic Broadband service A guide for those who may wish to apply to benefit from the scheme If you currently experience poor broadband speeds, or you are unable to obtain an affordable broadband

More information

Strategic Alliance. Business Continuity Policy

Strategic Alliance. Business Continuity Policy Version 1.1 April 2016 Contents Contents Version control Foreword Policy Scope Aim and objectives Methods and standards Responsibilities Governance Training and exercises Page i ii 1 2 2 2 Version 1.1

More information

BORDERS BROADBAND - FREQUENTLY ASKED QUESTIONS

BORDERS BROADBAND - FREQUENTLY ASKED QUESTIONS BORDERS BROADBAND - FREQUENTLY ASKED QUESTIONS What is this project about? Who is behind it? Why was this area chosen? How much will the project cost? Who will get improved broadband? When will it all

More information

How to Procure a Payment Service Contract in Cambridge City

How to Procure a Payment Service Contract in Cambridge City Cambridge City Council Item To: Report by: Relevant scrutiny committee: Wards affected: Executive Councillor for Planning Policy and Transport: Councillor Kevin Blencowe Sean Cleary, Commercial Operations

More information

Cambridge City Council

Cambridge City Council Cambridge City Council Item To: Report by: Relevant scrutiny committee: Wards affected: Executive Councillor for Customer Services and Resources James Nightingale, Head of ICT Client Services Strategy

More information

[to be completed by Democratic Services] Council 27 February 2015

[to be completed by Democratic Services] Council 27 February 2015 Council Title of Report: Report No: Decisions plan reference: Report to and date/s: Portfolio holder: Lead officer: Purpose of report: Budget and Council Tax Setting: 2015/16 and Medium Term Financial

More information

Wolverhampton City Council

Wolverhampton City Council Agenda Item No: 11a Wolverhampton City Council OPEN INFORMATION ITEM Scrutiny Panel AUDIT COMMITTEE Date 24 SEPTEMBER 2012 Originating Service Group(s) DELIVERY Contact Officer(s)/ PAT MAIN PETER OAKESHOTT

More information

The national scheme will be available for applications until the end of 2017.

The national scheme will be available for applications until the end of 2017. Getting a basic broadband service Some frequently asked questions and answers If you currently experience download broadband speeds of less than 2Mbps, we will help to provide you with access to an alternative

More information

RISK MANAGEMENT REPORT (for the Financial Year Ended 31 March 2012)

RISK MANAGEMENT REPORT (for the Financial Year Ended 31 March 2012) RISK MANAGEMENT REPORT (for the Financial Year Ended 31 March 2012) Integrated Risk Management Framework The Group s Integrated Risk Management Framework (IRMF) sets the fundamental elements to manage

More information

Performance Management 2012/ 13: Quarter 4

Performance Management 2012/ 13: Quarter 4 Performance Management 2012/ 13: Quarter 4 Policy and Resources Committee Chief Executive Director of Finance and Corporate Resources Director of Social and Community Services Director of Technical Services

More information

1 PURPOSE AND SUMMARY 1.1 This report seeks approval to consult on the draft 2015/16 2019/20 Revenue Financial Plan.

1 PURPOSE AND SUMMARY 1.1 This report seeks approval to consult on the draft 2015/16 2019/20 Revenue Financial Plan. ITEM NO. 11(a) 2015/1 201/20 REVENUE FINANCIAL PLAN Report by the Chief Financial Officer SCOTTISH BORDERS COUNCIL 18 December 2014 1 PURPOSE AND SUMMARY 1.1 This report seeks approval to consult on the

More information

Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding

Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding Committee and Date Cabinet 14 th October 2015 Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding Responsible Officer

More information

Shropshire Broadband Grants 2011

Shropshire Broadband Grants 2011 Business and Enterprise Shropshire Council Shirehall Abbey Foregate Shrewsbury Shropshire SY2 6ND Tel: 01743 252271 Fax: 01743 252277 Email: external.funding@shropshire.gov.uk External Funding Update 72

More information

Broadband Delivery Programme: Delivery Model

Broadband Delivery Programme: Delivery Model Programme : Delivery Model Broadband Delivery UK September 2011 0 Our aim is to improve the quality of life for all through cultural and sporting activities, support the pursuit of excellence, and champion

More information

1. The transfer of the service vehicle fleet and pool car fleet management to the County Council from 1 July 2013.

1. The transfer of the service vehicle fleet and pool car fleet management to the County Council from 1 July 2013. Cabinet Member for Finance and Resources and Cabinet Member for Highways and Transport Ref No. HT11(12/13) Service Vehicles Procurement Strategy November 2012 Report by Director of Business Change Key

More information

Technology Review Feedback Vale of Glamorgan Council

Technology Review Feedback Vale of Glamorgan Council Technology Review Feedback Vale of Glamorgan Council Audit year: Annual Improvement Assessment 2011 Issued: October 2011 Document reference: 538A2011 Status of report The person who delivered the work

More information

PUBLIC CONSULTATION Better Broadband for Norfolk. Consultation start date Wednesday 29 February 2012

PUBLIC CONSULTATION Better Broadband for Norfolk. Consultation start date Wednesday 29 February 2012 PUBLIC CONSULTATION Better Broadband for Norfolk Consultation start date Wednesday 29 February 2012 Consultation end date Monday 2 April 2012 EXECUTIVE SUMMARY Access to fast and reliable broadband is

More information

LONDON BOROUGH OF WALTHAM FOREST

LONDON BOROUGH OF WALTHAM FOREST LONDON BOROUGH OF WALTHAM FOREST Meeting / Date Cabinet /December 2015 Report Title Cabinet Portfolio Report Author/ Contact details Wards affected Public Access Appendices ICT Data Centre & Infrastructure

More information

why fixed.plan? We only connect to Tier 1 partners, including Openreach, BT and Talk Talk Business, ensuring a robust and reliable service.

why fixed.plan? We only connect to Tier 1 partners, including Openreach, BT and Talk Talk Business, ensuring a robust and reliable service. fixed.plan Operating directly with tier 1 suppliers including Openreach, BT and TalkTalk Business plan com provides you with access to the biggest and most reliable telecommunications networks in the UK.

More information

Internal Audit - progress report 2015-16 and 2016-17 plan

Internal Audit - progress report 2015-16 and 2016-17 plan Audit Committee, 16 March 2016 Internal Audit - progress report 2015-16 and 2016-17 plan Executive summary and recommendations Introduction Grant Thornton have prepared the attached report which sets out

More information

Merrycon s Approach to Business Continuity Management

Merrycon s Approach to Business Continuity Management Merrycon s Approach to Business Continuity Management Business Continuity is a management discipline that provides a framework for an organisation to build resilience, providing the capability for an effective

More information

Strategy 2012 2015. Providing resources for staff and students in higher and further education in the UK and beyond

Strategy 2012 2015. Providing resources for staff and students in higher and further education in the UK and beyond Providing resources for staff and students in higher and further education in the UK and beyond Strategy 2012 2015 EDINA is a JISC National Datacentre Table of Contents Introduction... 1 Vision... 1 Mission

More information

Corporate Director Health and Care Services

Corporate Director Health and Care Services COUNTY COUNCIL Meeting date: 16 th January 2014 From: Corporate Director Health and Care Services CUMBRIA ALCOHOL STRATEGY 1.0 EXECUTIVE SUMMARY 1.1 In 2009 partners involved in tackling alcohol related

More information

Broadband in Herefordshire Strategy for Delivery - Fibre at the Core. February 2011

Broadband in Herefordshire Strategy for Delivery - Fibre at the Core. February 2011 Broadband in Herefordshire Strategy for Delivery - Fibre at the Core February 2011 Overview The broadband vision for Herefordshire is to enable a fast and affordable broadband service that contributes

More information

Update on Programme Management Controls & Risks

Update on Programme Management Controls & Risks Committee and Date Audit Committee 26/06/14 Update on Programme Management Controls & Risks Responsible Officer George Candler Director of Commissioning e-mail: George.Candler@shropshire.gov.uk Tel: 01743

More information

SUBJECT: FRAMEWORK AGREEMENT FOR THE PROVISION OF VIDEO CONFERENCING EQUIPMENT

SUBJECT: FRAMEWORK AGREEMENT FOR THE PROVISION OF VIDEO CONFERENCING EQUIPMENT REPORT TO INDIVIDUAL CABINET MEMBER FOR FINANCE, LEGAL AND ICT 29 FEBRUARY Key Decision YES Forward Plan Ref No Corporate Priority ALL Cabinet Portfolio Holder: Date of Decision/ Referral to O&S Cllr David

More information

why fixed.plan? We only connect to Tier 1 partners, including Openreach, BT and Talk Talk Business, ensuring a robust and reliable service.

why fixed.plan? We only connect to Tier 1 partners, including Openreach, BT and Talk Talk Business, ensuring a robust and reliable service. fixed.plan Operating directly with tier 1 suppliers including Openreach, BT and TalkTalk Business plan.com provides you with access to the biggest and most reliable telecommunications networks in the UK.

More information

The Yorkshire SME Internet Connectivity and Business Growth Survey 2015

The Yorkshire SME Internet Connectivity and Business Growth Survey 2015 The Yorkshire SME Internet Connectivity and Business Growth Survey 2015 Foreword by David Tindall This survey took place in May 2015, when Talk Straight joined forces with Yorkshire Business Insider to

More information

The benefits anticipated from the project can be summarised as follows:

The benefits anticipated from the project can be summarised as follows: UNO Benefits Realisation Plan Background The aim of the UNO project was to create an up to date ICT system to enable the Assembly to work independently of the Welsh Government, to improve business continuity

More information

NEXT GENERATION BROADBAND - CASE STUDIES

NEXT GENERATION BROADBAND - CASE STUDIES NEXT GENERATION BROADBAND - CASE STUDIES HEADLINE A pioneering project that succeeded in ensuring that 85% of businesses across Northern Ireland have access to a next generation broadband service of 2

More information

RAISING LONDON S HIGH SPEED CONNECTIVITY TO WORLD CLASS LEVELS

RAISING LONDON S HIGH SPEED CONNECTIVITY TO WORLD CLASS LEVELS RAISING LONDON S HIGH SPEED CONNECTIVITY TO WORLD CLASS LEVELS ACCESS ACROSS THE CITY PAGE 1 Broadband is now considered the fourth utility. The Government has stated that it wants 99% of the population

More information

Central Superfast Broadband Project Frequently Asked Questions

Central Superfast Broadband Project Frequently Asked Questions Central Superfast Broadband Project Frequently Asked Questions What is the Central Superfast Broadband Project? The Central Superfast Broadband Project is a partnership between Central Bedfordshire Council,

More information

EAST AYRSHIRE COUNCIL CABINET 3 JUNE 2015 MEMBERSHIP OF BUSINESS LOANS SCOTLAND LTD. Depute Chief Executive and Chief Financial Officer

EAST AYRSHIRE COUNCIL CABINET 3 JUNE 2015 MEMBERSHIP OF BUSINESS LOANS SCOTLAND LTD. Depute Chief Executive and Chief Financial Officer EAST AYRSHIRE COUNCIL CABINET 3 JUNE 2015 MEMBERSHIP OF BUSINESS LOANS SCOTLAND LTD Depute Chief Executive and Chief Financial Officer Economy and Skills PURPOSE 1. The purpose of this paper is to seek

More information

Customer Service Software System Business Case Lead Officer:

Customer Service Software System Business Case Lead Officer: Agenda item: 17 Committee: CABINET Date of meeting: 21 November 2012 Subject: Customer Service Software System Business Case Lead Officer: Head of ICT Portfolio Holder: Resources - Councillor T Oliver

More information

Case Study: The Maltings Power to the People

Case Study: The Maltings Power to the People Case Study: The Maltings Power to the People What they needed High speed affordable connectivity Reliable and rapid installation Flexibility and availability of service to all tenants What we delivered

More information

The BT Business Big Giveaway.

The BT Business Big Giveaway. BT Business The BT Business Big Giveaway. Set your business free with our best ever offer on calls, lines and broadband. There s never been a better time to sign up to BT. We understand how tough the climate

More information

Internal Audit Follow Up Review Final Report Strategic Finance Council Tax May 2015

Internal Audit Follow Up Review Final Report Strategic Finance Council Tax May 2015 Internal Audit Follow Up Review Final Report Strategic Finance Council Tax May 2015 Page 1 of 32 CONTENTS Page EXECUTIVE SUMMARY 3 4 Review Opinion 3 Scope & Detailed Opinion 3 Summary of Recommendations

More information

I N T E R C A I M O N D I A L E

I N T E R C A I M O N D I A L E I N T E R C A I M O N D I A L E INTERCAI MONDIALE WORKING FOR LOCAL AUTHORITIES IN BROADBAND Does your authority wish to promote broadband in your county or district? Are there community groups and possible

More information

Business Continuity Policy and Business Continuity Management System

Business Continuity Policy and Business Continuity Management System Business Continuity Policy and Business Continuity Management System Summary: This policy sets out the structure for ensuring that the PCT has effective Business Continuity Plans in place in order to maintain

More information

Overview and Scrutiny Forum Resources

Overview and Scrutiny Forum Resources Overview and Scrutiny Forum Resources Part 1 17 th December 2004 Item No 4 Subject Purpose Author Ward Summary Implementation of Oracle iprocurement Suite The purpose of this report is to update members

More information