1 Authors and background System overview Case: The Kamppi Center Future research

2 Research background: Use of Line-of-Balance began in Finland in 1980s (HUT) Wide adoption in Finland by 1985 Now used by almost every construction company Authors: Line-of-Balance based schedule planning and control system Professor Jouko Kankainen: Helsinki University of Technology Construction Economics and Management Olli Seppänen (Ph.D. student): Operations research background Technology manager / DSS Inc. Development background: Before DYNAProject, there was a Line-of-Balance software on market which allowed conversion of Gantt Chart into Line-of-Balance DYNAProject was developed to replace the previous scheduling software Four big Finnish construction companies participated in the development work (June 2001 August 2002) References: DYNAProject More than 200 new users in year 2003 All leading construction companies in Finland, many small ones too Previous scheduling software is being replaced

3 Place Order of completion Work flow (m²) Space buffer Time buffer Time

4 ! A comprehensive time management system for construction projects Schedule planning Risk analysis Monitoring and control Reuse of completion data

5 " #$% "&''( Site location: Helsinki, Finland Project management by SRV Viitoset Ltd. One of the largest single city center projects in Europe Cost estimate: 2.5 billion Schedule: DYNAProject is currently being used in schedule planning and control of the Kamppi Center 6th of June 2003

6 " #$% "&''( Street level: Retail offices and shops Underground: Connection to subway Kamppi Park square Bus station (city of Espoo) Department store Retail outlets Pedestrian walkways for hotel Walk ways to city centre Pedestrian street Central bus station Kamppi market square Lasipalatsi square

7 " #$% "&) Master schedule: Just foundations and framework tasks are shown for every floor Phase schedule enables closer analysis: Place A and the tasks under Framework 2A under closer look Framework 2A

8 " #$% "&" Control chart shows task status: Foundations task is running late in some floors Forecasts show the expected delay of Foundations Alarm symbols show places where control actions are needed

9 " #$% "&" The total effect of the deviation of the Foundation is shown: Framework will be delayed for up to 2½ months Before control action: Control action (more resources) Framework is late only 2-3 weeks After control action

10 Improved schedule planning Control of work groups Evaluation of low cost / risk alternatives Continuous tasks Schedule compression less overhead costs Integrated procurement schedule Less risk in the schedule Time and cost savings Effective project control Graphical control features Total effects of deviations shown Optimal control actions in case of deviations More effective project control Increased productivity Less hurried work or waiting hours Schedule can be implemented as planned Software benefits All the tools needed in planning and controlling the schedule Easy to use graphical features Designed by industry experts, tested and used by project personnel

11 * More than 200 new users during 2003! DYNAProject1.2 improves project control and thus increases productivity. The schedule situation of the project can be seen at a glance! Vesa Tähti, Vice President, Skanska Finland DYNAProject1.2 is an innovation, which benefits the whole construction industry. Better schedule planning and control enables substantial cost savings. Jukka Pekkanen, Technology manager, RT (Confederation of Finnish Construction industries)

12 +' Cost and schedule effects of disturbances Cost loading the schedule tying payment schedule into tasks and places cost / schedule risks cost effects of control actions Integrating with 3D modeling software (4D) greatest value from 4D can be achieved by combining 4D with the Line-of-Balance pilot in Finland during fall 2003 / spring 2004 Integrating with the Last Planner Some DYNAProject pilot companies have also piloted Last Planner and want to have both in the same system We feel that the systems have a lot to contribute to each other

13 Complete system demonstration during the conference on request Q & A

14 , ) Total control of work and workgroups Planning based on the graphical Line-of-Balance Bill of materials Tasks under construction at any time Location of tasks Effects of tasks on each other Task information Line-of-Balance schedule

15 *$) Risk analysis features ensure feasibility ensures that schedule can be implemented as planned illustrates the probability of achieving milestones Risk input sheet graphically shows places where more control is needed Probability of achieving milestones Risks in the Line-of-balance

16 * Risk analysis indicates places where more control is needed

17 ,'" The use of control charts makes monitoring and control easy and effective Forecasts in the line of balance graphically illustrate the total effects of deviation The control chart for completions input, also works as a status report prompt for corrective measures Alarm Forecast Actual

18 "" Completion based forecasts are shown in the Line-of-Balance. Task status shown in different colors in the control chart

19 " Optimal control actions are planned to achieve the original schedule if deviations occur Control actions Alarm: control action needed Plan Forecast: task is late due to delay in previous task

20 -

21 $ In the Finnish system there are three features with which the fulfillment of starting prerequisites are ensured schedule s sensitivity to disturbance procurement schedule task plan» cost objective» master schedule task exploded» quality objectives and checking of design» resources» safety By combining task plans, it is possible to do look-ahead planning with DYNAProject (for example all the task plans for the next 6 weeks)

22 $ Master schedule task Floor covering works exploded

23 Procurement events that have not been completed are shown with red color

IMPLEMENTATION OF LINE-OF-BALANCE BASED SCHEDULING AND PROJECT CONTROL SYSTEM IN A LARGE CONSTRUCTION COMPANY

IMPLEMENTATION OF LINE-OF-BALANCE BASED SCHEDULING AND PROJECT CONTROL SYSTEM IN A LARGE CONSTRUCTION COMPANY IMPLEMENTATION OF LINE-OF-BALANCE BASED SCHEDULING AND PROJECT CONTROL SYSTEM IN A LARGE CONSTRUCTION COMPANY Mika Soini\ Ilkka LeskeHi 2, Olli Seppanen 3 ABSTRACT Line-of-Balance has been successfully

More information

The Combination of Last Planner System and Location-Based Management System

The Combination of Last Planner System and Location-Based Management System Seppänen, Olli, Glenn Ballard & Sakari Pesonen (2010) The Combination of Last Planner System and Location- Based Management System Lean Construction Journal 1 2010 pp 43-54 Abstract The Combination of

More information

Masters of Business Administration MBA Semester 2 MB0044 Production & Operations Management Assignments

Masters of Business Administration MBA Semester 2 MB0044 Production & Operations Management Assignments Spring 2014 Exam July/Aug2014 Masters of Business Administration MBA Semester 2 MB0044 Production & Operations Management Assignments Q. No 1 Explain briefly elements of operations strategy? Ans.1 Operations

More information

Helsinki-Vantaa Airport. Kamppi

Helsinki-Vantaa Airport. Kamppi Helsinki-Vantaa Airport Kamppi Airport connections By bus Bus number 615. From the airport to Helsinki city center/ From Helsinki city center to the airport From the airport, the bus leaves from terminal

More information

Demonstrate and apply knowledge of project management in

Demonstrate and apply knowledge of project management in Demonstrate and apply knowledge of project management in mechanical engineering 22918 version 2 Page 1 of 5 Level 6 Credits 15 Purpose This unit standard is intended primarily for use in diploma courses

More information

Edge Gateway and virtualization for IoT connectivity

Edge Gateway and virtualization for IoT connectivity Edge Gateway and virtualization for IoT connectivity Jukka Mäkelä, Mikko Valta, Pekka Karhula, Helena Rivas VTT Technical Research Centre of Finland More information contact: [email protected] Scenario

More information

consulting group Increase Competitiveness Reduce Costs

consulting group Increase Competitiveness Reduce Costs Strengthen the Textile Supply Chain Through IT Increase Competitiveness Increase Efficiencies Reduce Costs The real Textile World The Garment Industry Retail The Chemical Fibre Industry The Chemical Industry

More information

PRACTICAL IMPLICATIONS OF LOCATION-BASED SCHEDULING

PRACTICAL IMPLICATIONS OF LOCATION-BASED SCHEDULING Downloaded from orbit.dtu.dk on: Feb 01, 2016 PRACTICAL IMPLICATIONS OF LOCATION-BASED SCHEDULING Andersson, Niclas; Christensen, Knud Published in: CME25:Construction Management and Economics: past, present

More information

Project management. Objectives. Topics covered. Organizing, planning and scheduling software projects DISCUSSION

Project management. Objectives. Topics covered. Organizing, planning and scheduling software projects DISCUSSION Project management 1 Objectives 2 Organizing, planning and scheduling software projects DISCUSSION Project Managers? To introduce software project management and to describe its distinctive characteristics

More information

Studia Generalia: Business in St. Petersburg experiences of SRV

Studia Generalia: Business in St. Petersburg experiences of SRV Studia Generalia: Business in St. Petersburg experiences of SRV Turku School of Economics 21.11.2013 Mikko Söderlund The Contents SRV Group plc - General Presentation Food for Thought: The Russian Economy

More information

Sage 200 Manufacturing Datasheet

Sage 200 Manufacturing Datasheet Sage 200 Manufacturing Datasheet Sage 200 Manufacturing is a powerful manufacturing solution that enables you to manage your entire supply chain in detail, end to end, giving you the information needed

More information

BIM-based falling prevention planning

BIM-based falling prevention planning BIM-based falling prevention planning BIM Safety research project, Pilot 1 Kristiina Sulankivi & Markku Kiviniemi VTT Technical Research Centre of Finland 2 Guardrail components for Pilot 1 (modelling

More information

Project management. Organizing, planning and scheduling software projects. Objectives. Chapter 3. Chapter 3 Project Management. Learning Objective

Project management. Organizing, planning and scheduling software projects. Objectives. Chapter 3. Chapter 3 Project Management. Learning Objective Chapter 3 Chapter 3 Project Management Learning Objective...to give an appreciation for and to introduce project management and to place it into context and give some of the fundamentals to project management

More information

Case Marja-Vantaa: Introduction of a new housing area

Case Marja-Vantaa: Introduction of a new housing area Case Marja-Vantaa: Introduction of a new housing area Nordic Cleantech Solutions 12.9.2008 Reijo Sandberg Project Director Marja-Vantaa Project City of Vantaa Vantaa - Vanda The fourth biggest city in

More information

Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University.

Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University. Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University. This was one of four innovative practices was described by

More information

Business ByDesign. The SAP Business ByDesign solution helps you optimize project management

Business ByDesign. The SAP Business ByDesign solution helps you optimize project management SAP Functions in Detail SAP Solutions for Small Businesses and Midsize Companies Efficient Project Management Drive Project Success with SAP Business ByDesign The SAP Business ByDesign solution helps you

More information

City of Helsinki Culinary Culture Strategy

City of Helsinki Culinary Culture Strategy City of Helsinki City of Helsinki Culinary Culture Strategy 1. Introduction The Strategy Programme of Helsinki for 2009 2012 has set a goal that Helsinki will be developed as a centre for Finnish food

More information

Project Portfolio White Paper

Project Portfolio White Paper NEW! Timesheet - Resource Reporting Resource Planning Snapshots and Trend Report Milestones Project Portfolio White Paper Contents 2 Project portfolio A Tool for Strategic Management 3 Portfolio Management:

More information

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7?

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? This document contains introduction to P2ware Project Manager 7 views (P2ware Project Manager 7 walkthrough) and shows how to create high quality plans

More information

Foreword. Version 1.0 27.03.2012 Parties to the COBIM project

Foreword. Version 1.0 27.03.2012 Parties to the COBIM project Series 12 author Insinööritoimisto Olof Granlund Oy: Markku Jokela, Tuomas Laine, Reijo Hänninen Foreword The publication series Common BIM 2012 is the result of a broadbased development project entitled

More information

Module 5 The R+ Available Stock Calculation

Module 5 The R+ Available Stock Calculation Welcome to Demand Driven Technologies, the home of Replenishment plus and module 5 of our education tutorials Understanding the R+ Available Stock Calculation This module is intended to provide a basic

More information

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2

More information

The NEC Group: Optimizing the Visitor Experience with Analytics and Business Intelligence Solutions from SAP

The NEC Group: Optimizing the Visitor Experience with Analytics and Business Intelligence Solutions from SAP 2015 SAP SE or an SAP affiliate company. All rights reserved. The NEC Group: Optimizing the Visitor Experience with Analytics and Business Intelligence Solutions from SAP The NEC Group, one of the world

More information

COMPANY... 3 SYSTEM...

COMPANY... 3 SYSTEM... Wisetime Ltd is a Finnish software company that has longterm experience in developing industrial Enterprise Resource Planning (ERP) systems. Our comprehensive system is used by thousands of users in 14

More information

INDEPENDENT STUDY PAILIN UDOMSANTI

INDEPENDENT STUDY PAILIN UDOMSANTI 1 INDEPENDENT STUDY ERP Comparison : Production Planning and Control Module PAILIN UDOMSANTI An Independent Study submitted in Partial Fulfillment of the requirements For the Degree of Master of Engineering

More information

1.3 ERP System Evolution

1.3 ERP System Evolution 1.3 ERP System Evolution Learning Objectives State the purpose of enterprise resource planning (ERP) systems List the challenges facing the industry List the development stages of the manufacturing planning

More information

Project management. Organizing, planning and scheduling software projects

Project management. Organizing, planning and scheduling software projects Project management Organizing, planning and scheduling software projects Ian Sommerville 1995 Software Engineering, 5th edition. Chapter 3 Slide 1 Objectives To introduce software project management and

More information

Planning and Scheduling Your Project Using Microsoft Project 2003

Planning and Scheduling Your Project Using Microsoft Project 2003 Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering [email protected] Meeting Protocol Agenda Project File Project Calendar Creating

More information

SUPPLY CHAIN MODELING USING SIMULATION

SUPPLY CHAIN MODELING USING SIMULATION SUPPLY CHAIN MODELING USING SIMULATION 1 YOON CHANG AND 2 HARRIS MAKATSORIS 1 Institute for Manufacturing, University of Cambridge, Cambridge, CB2 1RX, UK 1 To whom correspondence should be addressed.

More information

Cash flow is the life line of a business. Many start-up

Cash flow is the life line of a business. Many start-up PM.02 ABC of Cash Flow Projections Mark T. Chen, PE CCE Cash flow is the life line of a business. Many start-up companies fail because of insufficient cash flow. From the perspectives of both owner and

More information

Road Asset Management Research Program In Finland

Road Asset Management Research Program In Finland Langfassung / long version Road Asset Management Research Program In Finland Abstract Mr. Vesa Männistö, M.Sc. (Statistics) Inframan Ltd Länsituulentie 10, 02100 Espoo, Finland Tel +358-9-8567 7715, fax

More information

Organizing, planning and scheduling software projects

Organizing, planning and scheduling software projects Project management Organizing, planning and scheduling software projects Ian Sommerville 1995 Modified by Spiros Mancoridis 1998 Software Engineering, 5th edition. Chapter 3 Slide 1 Objectives To introduce

More information

WorkStream Management Driving Early Project Delivery with Phoenix Project Manager

WorkStream Management Driving Early Project Delivery with Phoenix Project Manager Phoenix WorkStream Scheduling WorkStream Management Driving Early Project Delivery with Phoenix Project Manager Executive Summary As a team member on any project, you are focused on project delivery: meeting

More information

SPEND ANALYSIS and SUPPLY BASE RATIONALIZATION

SPEND ANALYSIS and SUPPLY BASE RATIONALIZATION SPEND ANALYSIS and SUPPLY BASE RATIONALIZATION Presented By: TABLE OF CONTENTS INTRODUCTION.............................. 1 SURVEY METHODOLOGY..................... 1 DEMOGRAPHICS OF RESPONDENTS...........

More information

MICROSOFT PROJECT 2013 INTRODUCTION

MICROSOFT PROJECT 2013 INTRODUCTION Phone:08092595489 / 08168510709 Email: [email protected] MICROSOFT PROJECT 2013 INTRODUCTION Generate a group quote today or register now for the next public course date COURSE LENGTH: 1.0 DAYS

More information

The work breakdown structure can be illustrated in a block diagram:

The work breakdown structure can be illustrated in a block diagram: 1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as

More information

CHAPTER 24 SOFTWARE PROJECT SCHEDULING. Overview

CHAPTER 24 SOFTWARE PROJECT SCHEDULING. Overview CHAPTER 24 SOFTWARE PROJECT SCHEDULING Overview The chapter describes the process of building and monitoring schedules for software development projects. To build complex software systems, many engineering

More information

Welcome to our exhibition

Welcome to our exhibition Welcome to our exhibition Welcome to this public exhibition for Cherry Park, Westfield, Stratford. This exhibition has been organised to update residents on Cherry Park, the next phase of development in

More information

Partner Relationship Management (PRM) for Enhanced Extended Enterprise Team Selling. a white paper

Partner Relationship Management (PRM) for Enhanced Extended Enterprise Team Selling. a white paper Partner Relationship Management (PRM) for Enhanced Extended Enterprise Team Selling a white paper page 2 Executive Summary Industry Trends in the Indirect Channel sales are increasing in the indirect channel

More information

STAFF REPORT. December 20, 2004. North District Community Council. Director of Community Planning - North

STAFF REPORT. December 20, 2004. North District Community Council. Director of Community Planning - North STAFF REPORT December 20, 2004 To: From: Subject: North District Community Council Director of Community Planning - North Preliminary Report Respecting Revised Application OPA & Rezoning Application 01

More information

Control 2008 User Guide

Control 2008 User Guide Control 2008 User Guide A Guideline for the Location Based Scheduling and Production control Copyright 2008 by Vico Software, all rights reserved. Reproduction, paraphrasing or translation without express

More information

Climate Impact Assessment in Urban Planning: the Ecocity Evaluator Method. Topi Tiihonen Eero Paloheimo Ecocity Ltd topi.tiihonen@ecocity.

Climate Impact Assessment in Urban Planning: the Ecocity Evaluator Method. Topi Tiihonen Eero Paloheimo Ecocity Ltd topi.tiihonen@ecocity. Climate Impact Assessment in Urban Planning: the Ecocity Evaluator Method Topi Tiihonen Eero Paloheimo Ecocity Ltd [email protected] Eero Paloheimo Ecocity Ltd Founded in 2009 on the basis of Professor

More information

Implementing LEAN Techniques in Quality Control Optimizing and Leveraging Improved Efficiency

Implementing LEAN Techniques in Quality Control Optimizing and Leveraging Improved Efficiency Implementing LEAN Techniques in Quality Control Optimizing and Leveraging Improved Efficiency 1 Implementation of LEAN Techniques in Baxter s QC Laboratory Applying LEAN techniques can result in improved

More information

AN ECO-EFFICIENT OFFICE BUILDING IN KEILANIEMI

AN ECO-EFFICIENT OFFICE BUILDING IN KEILANIEMI AN ECO-EFFICIENT OFFICE BUILDING IN KEILANIEMI www.keilaranta.fi The new, truly adaptable office complex at Keilaranta is the closest building to the new Keilaniemi metro station. Attractive premises for

More information

Helsinki Metropolitan Area (HMA) Office MarketView

Helsinki Metropolitan Area (HMA) Office MarketView Helsinki Metropolitan Area (HMA) Office MarketView Q3 2014 CBRE Global Research and Consulting GDP -0.6% (Y-o-Y) CPI 1,3% (Y-o-Y) UNEMPLOYMENT RATE 8,2% (Sep) HELSINKI OFFICE MARKET - SALES VOLUME IS IMPROVING

More information

Software Engineering. Project Management. Based on Software Engineering, 7 th Edition by Ian Sommerville

Software Engineering. Project Management. Based on Software Engineering, 7 th Edition by Ian Sommerville Software Engineering Project Management Based on Software Engineering, 7 th Edition by Ian Sommerville Objectives To explain the main tasks undertaken by project managers To introduce software project

More information

Excel 2010: Create your first spreadsheet

Excel 2010: Create your first spreadsheet Excel 2010: Create your first spreadsheet Goals: After completing this course you will be able to: Create a new spreadsheet. Add, subtract, multiply, and divide in a spreadsheet. Enter and format column

More information

The New Mobility: Using Big Data to Get Around Simply and Sustainably

The New Mobility: Using Big Data to Get Around Simply and Sustainably The New Mobility: Using Big Data to Get Around Simply and Sustainably The New Mobility: Using Big Data to Get Around Simply and Sustainably Without the movement of people and goods from point to point,

More information

General Comparison between 4D Software

General Comparison between 4D Software General Comparison between 4D Software (Navisworks, Synchro professional, Vico control, itwo and Navigator) Comparison between 4D Software 4D BIM is the next generation of project management, including

More information

1 Introduction. Kari I. Leväinen

1 Introduction. Kari I. Leväinen 1 Introduction Kari I. Leväinen Professor of Real Estate and Facilities Management, Helsinki University of Technology, Institute of Real Estate Studies, PL 1200, FIN-02015 TKK The municipal organisations

More information

NORTHUMBERLAND. FOR SALE Freehold Office Investment with Planning Consent for a 27,157 sq Ft (GIA) Student Housing Block

NORTHUMBERLAND. FOR SALE Freehold Office Investment with Planning Consent for a 27,157 sq Ft (GIA) Student Housing Block CGI of student housing Existing FOR SALE Freehold Office Investment with Planning Consent for a 27,157 sq Ft (GIA) Student Housing Block G U I D E P R I C E 4. 2 m i l l i o n m i l l i o n NORTHUMBERLAND

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information

July 29, 2008 at 9.00am. (Unaudited figures. Unless otherwise stated comparisons are made to the same period one year ago. The currency is euro.

July 29, 2008 at 9.00am. (Unaudited figures. Unless otherwise stated comparisons are made to the same period one year ago. The currency is euro. F-SECURE CORPORATION Stock Exchange Release July 29, 2008 at 9.00am F-Secure Group January 1 - June 30, 2008 Financial Results Solid overall growth, good profitability (Unaudited figures. Unless otherwise

More information

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06 SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable

More information

Explore architectural design and act as architects to create a floor plan of a redesigned classroom.

Explore architectural design and act as architects to create a floor plan of a redesigned classroom. ARCHITECTURAL DESIGN AT A GLANCE Explore architectural design and act as architects to create a floor plan of a redesigned classroom. OBJECTIVES: Students will: Use prior knowledge to discuss functions

More information

19-23 May 2014, Helsinki, Finland http://cf2014.egi.eu/ EXHIBITION GUIDE

19-23 May 2014, Helsinki, Finland http://cf2014.egi.eu/ EXHIBITION GUIDE 19-23 May 2014, Helsinki, Finland http://cf2014.egi.eu/ EXHIBITION GUIDE The EGI Community Forum 2014 is an excellent opportunity to find out who is who in this exciting field of worldwide distributed

More information

To reuse a template that you ve recently used, click Recent Templates, click the template that you want, and then click Create.

To reuse a template that you ve recently used, click Recent Templates, click the template that you want, and then click Create. What is Excel? Applies to: Excel 2010 Excel is a spreadsheet program in the Microsoft Office system. You can use Excel to create and format workbooks (a collection of spreadsheets) in order to analyze

More information

Scheduling. Anne Banks Pidduck Adapted from John Musser

Scheduling. Anne Banks Pidduck Adapted from John Musser Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart

More information

Dynamics of the Commercial Property Markets in Finland

Dynamics of the Commercial Property Markets in Finland Arhi KIVILAHTI and Kauko VIITANEN, Finland Key words: commercial property market, rent determination, regression analysis, retail market, office market, submarkets, SUMMARY The paper discusses the characteristics,

More information

Prime and Composite Numbers

Prime and Composite Numbers Prime and Composite Numbers Student Probe Is 27 a prime number or a composite number? Is 17 a prime number or a composite number? Answer: 27 is a composite number, because it has factors other than 1 and

More information

Enter Here --> Scheduler123 : Excel-based Production Scheduling System - Real User Experience > GET IT NOW <

Enter Here --> Scheduler123 : Excel-based Production Scheduling System - Real User Experience > GET IT NOW < Download production schedule template, production schedule template for making films, manufacturing production scheduling excel. Enter Here --> Scheduler123 : Excel-based Production Scheduling System -

More information

Medical Spa Plan Development & Implementation

Medical Spa Plan Development & Implementation Medical Spa Plan Development & Implementation 2007 An Acara Partners Company Acara MedSpas LLC 500 East Main Street, Suite 216 Branford, CT 06405 203.488.0028 [email protected] www.acaramedspas.com

More information

MSP How to guide session 2 (Resources & Cost)

MSP How to guide session 2 (Resources & Cost) MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or

More information

GENERAL GUIDELINES FOR DEVELOPING A BUSINESS PLAN

GENERAL GUIDELINES FOR DEVELOPING A BUSINESS PLAN GENERAL GUIDELINES FOR DEVELOPING A BUSINESS PLAN August 2012 Table of contents Introduction... 3 1. Executive Summary... 3 2. Business Summary... 3 2.1 Company Summary... 3 2.2 Management Summary... 3

More information

1 st year / 2014-2015/ Principles of Industrial Eng. Chapter -3 -/ Dr. May G. Kassir. Chapter Three

1 st year / 2014-2015/ Principles of Industrial Eng. Chapter -3 -/ Dr. May G. Kassir. Chapter Three Chapter Three Scheduling, Sequencing and Dispatching 3-1- SCHEDULING Scheduling can be defined as prescribing of when and where each operation necessary to manufacture the product is to be performed. It

More information

Development of a Concept for the Public Transport Interconnectivity for Savaria International Airport. Report

Development of a Concept for the Public Transport Interconnectivity for Savaria International Airport. Report Development of a Concept for the Public Transport Interconnectivity for Savaria International Airport Report CENTRAL EUROPE Programme Project CHAMPIONS February 2012 Development of a Concept for the Public

More information

Cylon energy Solution

Cylon energy Solution Cylon energy Solution REAL INFORMATION, REAL CONTROL, REAL SAVINGS ABOUT CYLON CONTROLS Cylon is a pioneer and a recognised international leader in the development of smart energy management systems for

More information

Explore commands on the ribbon Each ribbon has groups, and each group has a set of related commands.

Explore commands on the ribbon Each ribbon has groups, and each group has a set of related commands. Quick Start Guide Microsoft Project 2013 looks different from previous versions, so we created this guide to help you minimize the learning curve. Quick Access Toolbar Customize this area so your favorite

More information

Search help. More on Office.com: images templates. Here are some basic tasks that you can do in Microsoft Excel 2010.

Search help. More on Office.com: images templates. Here are some basic tasks that you can do in Microsoft Excel 2010. Page 1 of 8 Excel 2010 Home > Excel 2010 Help and How-to > Getting started with Excel Search help More on Office.com: images templates Basic tasks in Excel 2010 Here are some basic tasks that you can do

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose 1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing

More information

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

CenterPoint Energy Executes Emergency Operating Plan. Hurricane Ike Restoration

CenterPoint Energy Executes Emergency Operating Plan. Hurricane Ike Restoration CenterPoint Energy Executes Emergency Operating Plan Hurricane Ike Restoration Who is CenterPoint Energy Public company traded on the New York Stock Exchange (CNP) Headquartered in Houston, TX Operate

More information

Automated decision-making along the product life cycle saves OTTO millions

Automated decision-making along the product life cycle saves OTTO millions Customer Case Study RETAIL Automated decision-making along the product life cycle saves OTTO millions OTTO is a leader in Smart Data in German retail Overview Customer Online retailer for fashion and lifestyle

More information

Auto Telecom Australia www.hybrex.com.au

Auto Telecom Australia www.hybrex.com.au Hybrex Hospitality Solutions Auto Telecom Australia www.hybrex.com.au Auto Telecom Corporation Overview Auto Telecom Corporation manufactures and distributes the Hybrex and TransTel range through its own

More information

Best Practices in the Procure-to-Pay Cycle: Perspectives from Suppliers and Industry Experts

Best Practices in the Procure-to-Pay Cycle: Perspectives from Suppliers and Industry Experts Best Practices in the Procure-to-Pay Cycle: Perspectives from Suppliers and Industry Experts Rob Handfield, Bank of America University Distinguished Professor, North Carolina State University VOLUME 9

More information

Business Idea Development Product production Services. Development Project. Software project management

Business Idea Development Product production Services. Development Project. Software project management Page 1, 1/20/2003 Ivica Crnkovic Mälardalen University Department of Computer Engineering [email protected] Development Project Product Lifecycle Business Idea Development Product production Services

More information

Process Mapping Guidelines

Process Mapping Guidelines Process Mapping Guidelines FLOWCHART SYMBOLS The following are the primary symbols: SYMBOL NAME DESCRIPTION Activity/Processing Decision Document Direction of Flow Chart Connections Indicates that an activity

More information

A. Look at the Resource Sheet and Gantt Entry View Sheet to see what and where resources are over allocated.

A. Look at the Resource Sheet and Gantt Entry View Sheet to see what and where resources are over allocated. Microsoft Project Pro Steps to completing Project Pro Assignments PART B. (These instructions include all you need to know about adjusting your project in Microsoft Project Pro 2013 and may include instructions

More information

The Network Approach to Inventory Management

The Network Approach to Inventory Management The Network Approach to Inventory Management Getting Accurate Inventory Information Across the Entire Supply Chain Stream Creates Healthy Companies A GT Nexus White Paper The Inventory Challenge The problem

More information