Review of Muskrat Falls Project Cost and Schedule Management Processes and Controls
|
|
|
- Britton King
- 10 years ago
- Views:
Transcription
1 December 18, 2015 Ms. Julia Mullaley Clerk of the Executive Council Cabinet Secretariat Government of Newfoundland and Labrador Confederation Building St. John s, NL A1B 4J6 Dear Ms. Mullaley: Re: Review of Muskrat Falls Project Cost and Schedule Management Processes and Controls Lower Churchill Management Corporation (LCMC) has had an opportunity to review the recent Ernst and Young (E&Y) report commissioned by the Oversight Committee to review the cost and schedule management processes and controls implemented by LCMC for the construction of Muskrat Falls, the Labrador-Island Transmission Link, and the Labrador Transmission Assets. External reviews are a valuable mechanism to confirm that appropriate practices are being applied and to identify opportunities for further improvement. We look at this review in the same light as previous work commissioned internally by the project team and the feedback provided by the Independent Engineer (IE). We also believe it is important to provide context for such reports, as there is often information and background that provides some additional insight into the rationale for certain project decisions and processes. This letter, in response to the E&Y report, was written from that perspective. The major points outlined by E&Y have been addressed below; they are listed and addressed individually in tables of concordance attached to this letter. 1
2 As noted in the report, LCMC has implemented a suite of project control processes for project cost and schedule, a Project Execution Plan, and coordination procedures for administering, controlling, and managing contractors costs and schedules. Reporting is also issued to provide updates on cost and schedule for the project. The project management controls and processes were developed early in the project development for standard project management oversight within the company. At that time, Nalcor did not design for these materials to be used in a public oversight process. As you will see noted below, Nalcor recognizes the different requirements of internal oversight related to project leadership and decision making versus the requirements of the Oversight Committee and the company will adjust process controls and management to address the needs of the Oversight Committee; in particular, in providing cost and schedule risk reports at a time and level that allows the Committee to identify and quantify project cost and schedule risks. Contractor management is an important and strategic consideration for the project team, as progress must be monitored, while at the same time avoiding claims arising from directing their activities. We acknowledge that E&Y noted that cost and schedule risks are subject to active and formalized management and that the project team has been staffed with resources experienced in cost and schedule management. We concur with the key schedule management process and control issues highlighted by E&Y and have been actively working with our contractors to see them addressed. The baseline documents identified in issue number 1 (baseline schedules and control documents) are contractor deliverables. As contractors are engaged, our approach is to provide feedback and comments so that deficiencies in these documents can be rectified by the applicable contractor before this information is incorporated into the Integrated Project Schedule (IPS). All approved baseline contractor schedules have been incorporated into the schedule, and issues arising from unapproved schedules are being addressed directly by the project team. The noted documentation gaps in the IPS development and management processes have not precluded development and management of the schedule, and they will be closed by year-end
3 A decision to re-baseline project cost and schedule is made at the project leadership level and not by the Project Control team. Consequently, it is not in their mandate and therefore not in their process or procedure. However, it is part of the Project Control team processes and procedures to monitor and report cost and schedule performance and provide the necessary management information to project senior management to take necessary action including: contingency drawdown status, comprehensive trend identification, trend analysis, mitigation plans and actions, and potential cost, schedule and quality impacts when appropriate analysis is completed. Project senior management s decision to re-baseline cost or schedule and seek related Approval for Expenditure (AFE) is an internal project process based on an evaluation of trends in project performance and the underlying risks associated with project execution that remain after mitigation strategies have been implemented. In response to E&Ys finding that the Oversight Committee s understanding of such conditions and processes is an important foundation as it conducts its oversight activities, Nalcor will add a formal alert process to the regular monthly interface meeting agenda with the Oversight Committee. This will provide a summary of potential emerging vulnerabilities and opportunity trends, associated mitigation activities and a range of potential cost, schedule and quality impacts, provided the necessary analysis has progressed to the point where such impacts can be quantified. In addition, Nalcor will provide the Oversight Committee with an outlook, if and when a re-baseline may occur, and the rationale for such a decision. In relation to E&Y s comments regarding contingency forecasting, a comprehensive contingency analysis was undertaken at Decision Gate 3 (DG3). Subsequent contingency forecasting is based on an outcome of multiple inputs including actual contractor bids, detailed oversight of the contractor and procurement performance, all summarized into a comprehensive trend analysis process. This process highlights issues and opportunities early, incorporates mitigation activities and assesses potential impacts in the future. The current approach to contingency is both deliberate and planned and intended to drive the project team to control costs within tight limits. We believe it prudent to avoid 3
4 excessive contingencies which are reflective of our desire to deliver the project at the lowest possible cost. E&Y noted that it did not review the project s DG3 documentation. The process used by LCMC to develop the DG3 cost estimate was, however, reviewed by the IE as part of its initial review. The IE noted in its November 2013 report that: The cost estimating methodology employed by Nalcor utilizes a deterministic approach to calculate the project's direct and indirect costs and a risk-adjusted analytical technique to develop a contingency allocation for defined tactile risks. Finally, a separate escalation analysis has been developed to calculate and fund anticipated changes in forward price levels via an allowance into the capital budget. The IE notes that Nalcor follows standard estimating practices as put forward by the Association for the Advancement of Cost Engineering International (AACEI), including 69R-12, 58R-10, 18R-97, and 17R-97. The approaches to contingency development contemplated by E&Y were undertaken at project sanction in December Our current approach, which we believe to be appropriate and prudent at this stage of project development, is to continue to engage in direct discussion on emerging risks and cost pressures and take management action when they have emerged. This discussion will be supported by the regular risk ranging and trend analysis documentation as previously noted. E&Y has suggested thresholds for variance management, reporting and escalation are not defined and they expect them to be in place to assist in giving a clear indication of the severity of issues and need to escalate to the Oversight Committee. Nalcor has set the threshold for variance on any work as zero. Authority to expend funds beyond the approved amount for any work package does not exist, and additional funds must be acquired through the change control process before additional expenditures can be authorized. That being said, as we noted above, we are adding a process to our Oversight Committee interface which will address this suggestion by clearly indicating the type and severity of issues to the Oversight Committee. 4
5 In relation to the note that fully quantified risks or trends may not be documented for certain challenges, we note that the internal project risk management framework captures such risks; however, quantification of risks is a function of many variables and detailed analysis needs to be completed prior to quantification. This obviously takes time and resources and can only be completed when the analysis is reasonably progressed. The trends are assessed on an ongoing basis by project leadership, as indicated by E&Y in their previous comments. In summary, we believe that continued focus on, and enhanced discussion of project risks that could materially impact cost and schedule, as well as their mitigation strategies, is a valuable and important oversight tool to ensure a rigorous focus on cost and schedule to project completion. While E&Y and the other external organizations that have reviewed LCMC s processes and practices have consistently concluded that appropriate controls for cost and schedule are in place, we appreciate and understand the unique needs of the Oversight Committee and the important role it plays in advising Cabinet and are adjusting our reporting and alert processes with the Oversight Committee as discussed above. Sincerely, Gilbert J. Bennett, P. Eng., FCAE Vice President cc. Mr. Ed Martin, CEO & President, Nalcor Energy 5
6 Table 1 - LCMC RESPONSE TO KEY FINDINGS AND OBSERVATIONS IDENTIFIED BY E&Y 1. Key project control processes have been developed, including: LCMC concurs with these observations. a. Core project management and control processes for cost and schedule, including the development of an Integrated Program Schedule (IPS) for the program, identification of baseline, committed and incurred costs as well as linkage of cost and schedule baselines to change management processes and controls; b. A Project Execution Plan defining the basis of the schedule and the estimate, and key assumptions supporting Project baseline cost and schedule; and c. Coordination procedures for administration, execution control and management of the contractors cost and schedule.
7 Table 1 - LCMC RESPONSE TO KEY FINDINGS AND OBSERVATIONS IDENTIFIED BY E&Y 2. Project reporting summarizes key information on construction cost and schedule, including: LCMC concurs with these observations. a. Schedule forecast and progress leveraging the IPS, including critical path and float review; and b. Cost forecasting, including Estimate to Complete, Estimate at Complete, variances and trends, as well as basic contingency forecasting. 3. Nalcor s continued efforts to work with contractors on maintaining a disciplined approach to project management, control and reporting. 4. Proactive measures were being taken to manage potential claims. 5. Cost and schedule issues and risks arising during the Project were subject to active and formalized management. LCMC concurs with these observations. LCMC concurs with this observation. LCMC concurs with this observation.
8 Table 1 - LCMC RESPONSE TO KEY FINDINGS AND OBSERVATIONS IDENTIFIED BY E&Y 6. A matrix organizational structure had been established, responsible for managing the Project as a whole. Key roles in this organizational structure had been staffed with resources experienced in cost and schedule management. LCMC concurs with this observation.
9 Table 2 - LCMC RESPONSE TO KEY SCHEDULE MANAGEMENT PROCESS AND CONTROL RISKS AND ISSUES IDENTIFIED BY E&Y 1. Certain baseline documents defining The baseline documents identified (baseline schedules and control contractor schedules as well as the documents documents) are contractor deliverables. As contractors are engaged, our defining the control of project schedules were approach is to provide feedback and comments so that deficiencies in not yet complete. these documents can be rectified by the applicable contractor before this information is incorporated into the Integrated Project Schedule (IPS). All approved baseline contractor schedules have been incorporated into the schedule, and issues arising from unapproved schedules are being addressed directly by the project team. The noted documentation gaps in the IPS development and management processes have not precluded development and management of the schedule, and they will be closed by year-end Contractors schedule updates were not being systematically rolled up into the Nalcor Integrated Project Schedule (IPS) that forms the basis of the reporting to the Oversight Committee. 3. A completion date has not been established for finalizing an integrated baseline of contractor and IPS schedules to correct the issues noted in #1 and #2 above. 4. The IPS development and maintenance process is not fully documented. Please refer to the response to #1 above. Please refer to the responses to #1 and #2 above. The level of documentation is sufficient to maintain the IPS; however, any documentation gaps will be addressed by year-end 2015.
10 Table 3 - LCMC RESPONSE TO KEY COST MANAGEMENT PROCESS AND CONTROL RISKS AND ISSUES IDENTIFIED BY E&Y 1. The conditions and processes for re-baselining A decision to re-baseline project cost and schedule is made at the project cost and schedule are not defined in the Cost leadership level and not by the Project Control team. Consequently, it is Control processes and procedures. The OC not in the Project Control team s mandate and therefore not in their understanding of such conditions and processes process or procedure. However, it is part of the Project Control team s is an important foundation as it conducts its processes and procedures to monitor and report cost and schedule oversight activities. performance and provide the necessary management information to project senior management to take necessary action including: contingency draw down status, comprehensive trend identification, trend analysis, mitigation plans and actions, and potential cost, schedule and quality impacts when appropriate analysis is completed. Project senior management s decision to re-baseline cost or schedule and seek related Approval for Expenditure (AFE) is an internal project process based on an evaluation of trends in project performance and the underlying risks associated with project execution that remain after mitigation strategies have been implemented. These processes are designed for internal project utilization, and, in our experience, function well. In response to E&Y s finding that the Oversight Committee understanding of such conditions and processes is an important foundation as it conducts its oversight activities, Nalcor will add a formal alert process to the regular monthly interface meeting agenda with the Oversight Committee. This will include providing a summary of potential emerging vulnerabilities and opportunity trends, associated mitigation activities and a range of potential cost, schedule and quality impacts, provided the necessary analysis has progressed to the point where such impacts can be quantified. In addition, Nalcor will provide the Oversight Committee with an outlook, if and when a re-baseline may occur, and the rationale for such a decision.
11 Table 3 - LCMC RESPONSE TO KEY COST MANAGEMENT PROCESS AND CONTROL RISKS AND ISSUES IDENTIFIED BY E&Y 2. Nalcor uses a relatively basic approach to its A comprehensive contingency analysis was undertaken at DG3. Subsequent updating of forecasted contingency contingency forecasting is based on an outcome of multiple inputs including requirements, which in our experience is not actual contractor bids, detailed oversight of the contractor and consistent with the expected practices for a procurement performance, all summarized into a comprehensive trend project of this scale and complexity. Given this, analysis process. This process highlights issues and opportunities early, it is not clear whether the cost contingency as incorporates mitigation activities and assesses potential impacts in the forecasted in reports for the Project will be future. The current approach to contingency is both deliberate and adequate. planned and intended to drive the project team to control costs within tight limits. We believe it prudent to avoid excessive contingencies which are reflective of our desire to deliver the project at the lowest possible cost. 3. The Project does not define thresholds for variance management, reporting and escalation purposes. We would normally expect these to be in place as they assist in giving clear indications of the severity of issues and the need to escalate to key stakeholders, such as the OC. Nalcor has set the threshold for variance on any work as zero. Authority to expend funds beyond the approved amount for any work package does not exist, and additional funds must be acquired through the change control process before additional expenditures can be authorized. That being said, as we noted above, we are adding a process to our Oversight Committee interface which will address this suggestion by clearly indicating the type and severity of issues to the Oversight Committee.
12 Table 3 - LCMC RESPONSE TO KEY COST MANAGEMENT PROCESS AND CONTROL RISKS AND ISSUES IDENTIFIED BY E&Y 4. Fully quantified risks or trends have not been The internal project risk management framework captures such risks; documented for certain significant challenges however, quantification of risks is a function of many variables and detailed on the project. The scale of potential analysis needs to be completed prior to quantification. This takes time and challenges is also not quantified in the resources and can only be completed when the analysis is reasonably summary reporting made available to the progressed. The trends are assessed on an ongoing basis by project Oversight Committee. leadership, as indicated by E&Y in their previous comments. The scale of potential challenges will be addressed in the process we are adding to the Oversight Committee interface.
LCMC Management Response to EY Review of Muskrat Falls Project Cost, Schedule and Related Risk April Report
nalcor (111 _br energy LOWER CHURCHILL PROJECT Lower Churchill Management Corporation Corporate Office 500 Columbus Drive P.O. Box 12800 St. John's, NL Canada Al B 0C9 April 12, 2016 Ms. Julia Mullaley
Muskrat Falls Project Oversight Committee. Committee Report August 2015
Muskrat Falls Project Oversight Committee Committee Report August 2015 Table of Contents Introduction...2 Project Costs...4 I. Muskrat Falls Generation Facility...6 II. Labrador Island Transmission Link...8
THE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
Project Management Guidelines
Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of
Financial Services FINANCIAL SERVICES UTILITIES 57 FINANCIAL SERVICES AND UTILITIES 2016-2018 BUSINESS PLAN. CR_2215 Attachment 1
CR_2215 Attachment 1 Financial Services FINANCIAL SERVICES & UTILITIES 57 FINANCIAL SERVICES AND UTILITIES 2016-2018 BUSINESS PLAN Acting Branch Manager: Stacey Padbury Table of Contents INTRODUCTION Our
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006. 31-d Page 1 of 7
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006 Control Objectives Example Control Activities Audit Procedures 1. INTERNAL AUDITS Management should periodically
Project Management Office (PMO)
Contents I. Overview of Project Management...4 1. Project Management Guide (PMG)...4 1.1 Introduction...4 1.2 Scope...6 1.3 Project Types...6 2. Document Overview, Tailoring, and Guidance...7 3. The Project
Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3
/01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,
Capital Planning Guidelines
Capital Planning Guidelines Contents Capital Planning Guidelines... 1 1. INTRODUCTION... 3 2. CAPITAL PROJECTS EVALUATION PROCESS... 3 3. APPRAISAL PROCESS UNDERTAKEN BY DEPARTMENTS... 4 3.1 Extension
Biometrics Enterprise Architecture Project Management Plan (BMEA PMP)
Biometrics Enterprise Architecture Project Management Plan (BMEA PMP) Version 1.0 Prepared by: Date: November 24, 2008 Revision History Purpose Revision Date Level 11/17/2009 First Draft 1.0 Responsible
Initiating Forms COPYRIGHTED MATERIAL 1.0 INITIATING PROCESS GROUP
1 Initiating Forms 1.0 INITIATING PROCESS GROUP The purpose of the initiating process group is to authorize a project, provide a high-level definition of the project, and identify stakeholders. There are
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
Audit of Financial Management Governance. Audit Report
Audit of Financial Management Governance Audit Report March 2015 TABLE OF CONTENTS Executive Summary... 2 What we examined... 2 Why it is important... 2 What we found... 2 Background... 4 Objective...
Organization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
PHASE 8: IMPLEMENTATION PHASE
PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the
10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.
PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition
Guidance Note: Corporate Governance - Board of Directors. March 2015. Ce document est aussi disponible en français.
Guidance Note: Corporate Governance - Board of Directors March 2015 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance - Board of Directors (the Guidance
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Part B1: Business case developing the business case
Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
Assessment of NCTD Program Management Framework for Positive Train Control Program
Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation
How to successfully manage your mega-project
BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How
PROJECT COST MANAGEMENT
7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major
pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage
BRITISH COLUMBIA INSTITUTE OF TECHNOLOGY ( BCIT ) PROJECT BUSINESS PLAN PROPOSAL TEMPLATE
BRITISH COLUMBIA INSTITUTE OF TECHNOLOGY ( BCIT ) PROJECT BUSINESS PLAN PROPOSAL TEMPLATE 1 PROJECT PROPOSAL PREAMBLE To obtain project approval from BCIT each school/department must submit a Project Business
CALL FOR PROPOSALS FOR INSTITUTIONAL CAPACITY DEVELOPMENT 1. BACKGROUND Organizational Context: The National Federal Parliament (NFP) was inaugurated in August 2012, with the selection (by traditional
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
Project Management. An Overview for IT. Author: Kevin Martin & Denise Reeser
Project Management An Overview for IT Author: Kevin Martin & Denise Reeser Agenda Best Practices (5 min) Preliminary Assessment (10 min) The Need for Project Management (15 min) Involvement of EPMO (10
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Ronald J. Rider, M.B.A. Table of Contents 1. INTRODUCTION...
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
ISO 20000-1:2005 Requirements Summary
Contents 3. Requirements for a Management System... 3 3.1 Management Responsibility... 3 3.2 Documentation Requirements... 3 3.3 Competence, Awareness, and Training... 4 4. Planning and Implementing Service
ENTERPRISE RISK MANAGEMENT FRAMEWORK
ENTERPRISE RISK MANAGEMENT FRAMEWORK COVENANT HEALTH LEGAL & RISK MANAGEMENT CONTENTS 1.0 PURPOSE OF THE DOCUMENT... 3 2.0 INTRODUCTION AND OVERVIEW... 4 3.0 GOVERNANCE STRUCTURE AND ACCOUNTABILITY...
Business Continuity Position Description
Position Description February 9, 2015 Position Description February 9, 2015 Page i Table of Contents General Characteristics... 2 Career Path... 3 Explanation of Proficiency Level Definitions... 8 Summary
CalPERS Budget Policy
California Public Employees Retirement System Agenda Item 6a Attachment 2 Page 1 of 6 CalPERS Budget Policy Purpose This document sets forth the budget policy (Policy) to ensure CalPERS budgeting practices
FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
Project Execution, Monitoring and Control (IS PM 8. Lecture; 2012 Spring)
Project Execution, Monitoring and Control Topics of the lecture as follows: PDCA cycle Project execution processes by PMBOK Project monitoring and controlling processes by PMBOK Project monitoring and
EXECUTIVE SUMMARY...5
Table of Contents EXECUTIVE SUMMARY...5 CONTEXT...5 AUDIT OBJECTIVE...5 AUDIT SCOPE...5 AUDIT CONCLUSION...6 KEY OBSERVATIONS AND RECOMMENDATIONS...6 1. INTRODUCTION...9 1.1 BACKGROUND...9 1.2 OBJECTIVES...9
Data Communications Company (DCC) price control guidance: process and procedures
Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: [email protected] Overview: The Data and Communications Company (DCC) is required
Managing Risk at Bank of America Corporation. Overview
Managing Risk at Bank of America Corporation Overview Risk is inherent in every material business activity that we undertake. Our business exposes us to strategic, credit, market, liquidity, compliance,
Palisade Risk Conference, 2014
Advanced Risk Management to Improve Cost and Schedule Performance on EPC Projects Risk-Management Best Practices from Nuclear Experience Palisade Risk Conference, 2014 Sola Talabi PhD MBA MSc BSc RMP Project
Audit of the Management of Projects within Employment and Social Development Canada
Unclassified Internal Audit Services Branch Audit of the Management of Projects within Employment and Social Development Canada February 2014 SP-607-03-14E Internal Audit Services Branch (IASB) You can
Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
PROJECT PROCUREMENT MANAGEMENT
12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,
THOMAS G. DAY SENIOR VICE PRESIDENT, INTELLIGENT MAIL AND ADDRESS QUALITY PRITHA N. MEHRA VICE PRESIDENT, BUSINESS MAIL ENTRY AND PAYMENT TECHNOLOGIES
March 31, 2009 THOMAS G. DAY SENIOR VICE PRESIDENT, INTELLIGENT MAIL AND ADDRESS QUALITY PRITHA N. MEHRA VICE PRESIDENT, BUSINESS MAIL ENTRY AND PAYMENT TECHNOLOGIES GEORGE W. WRIGHT VICE PRESIDENT, INFORMATION
Request for Proposals
Request for Proposals Connected Responder: Public Safety and Emergency Response Community Connected Vehicle Interest, Context and Business Case Development RFP Schedule RFP Release Date: April 30, 2015
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
UPTIME MAGAZINE. june/july15 JUNE/JULY 2015. uptimemagazine.com
june/july15 UPTIME MAGAZINE JUNE/JULY 2015 uptimemagazine.com AM Developing Plans Creating Value From Physical Assets by Mark Ruby 46 june/july 15A sset management plans form the cornerstone of an effective
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management
Safety Management Program
Corrective Action Plan (CAP) Safety Management Program Submitted by TransCanada PipeLines Limited and its National Energy Board Regulated Subsidiaries to address non-compliant findings in the National
Project success depends on
Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we
Information Technology Project Management (ITPM)
FUNCTIONAL AREA 10 Project Management (ITPM) Incumbents in this functional area direct information technology system solution and/or improvement projects for cost, time, scope, risk, and quality. They
Contract and Vendor Management Guide
Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier
Role Description Project Manager - Capital Work Program Delivery
Role Description Project Manager - Capital Work Program Delivery Cluster/Agency Department/Agency Division/Branch/Unit Location Planning & Environment Sydney Living Museums Heritage & Collections Division/Heritage
Report to Parliament No. 4 for 2011 Information systems governance and security. Financial and Assurance audit. Enhancing public sector accountability
Financial and Assurance audit Report to Parliament No. 4 for 2011 Information systems governance and security ISSN 1834-1128 Enhancing public sector accountability RTP No. 4 cover.indd 1 15/06/2011 3:19:31
Organizational Issues of Implementing Intrusion Detection Systems (IDS) Shayne Pitcock, CISSP First Data Corporation
Organizational Issues of Implementing Intrusion Detection Systems (IDS) Shayne Pitcock, CISSP First Data Corporation Agenda Problem Description Issues for Consideration Mitigation of the Issues Options
Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:
Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute
Integrating Project Management and Service Management
Integrating Project and Integrating Project and By Reg Lo with contributions from Michael Robinson. 1 Introduction Project has become a well recognized management discipline within IT. is also becoming
Office of Inspector General Evaluation of the Consumer Financial Protection Bureau s Consumer Response Unit
Office of Inspector General Evaluation of the Consumer Financial Protection Bureau s Consumer Response Unit Consumer Financial Protection Bureau September 2012 September 28, 2012 MEMORANDUM TO: FROM: SUBJECT:
Office of the Auditor General AUDIT OF IT GOVERNANCE. Tabled at Audit Committee March 12, 2015
Office of the Auditor General AUDIT OF IT GOVERNANCE Tabled at Audit Committee March 12, 2015 This page has intentionally been left blank Table of Contents Executive Summary... 1 Introduction... 1 Background...
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL AUDIT SERVICES August 24, 2015 Control Number ED-OIG/A04N0004 James W. Runcie Chief Operating Officer U.S. Department of Education Federal
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM
Appendix 3: Project Management Substation Guidelines (General Process Flow Template)
365 Appendix 3: Project Management Substation Guidelines (General Process Flow Template) Checkpoint Methodology The schedule is issued prior to the go decision. It covers the duration of the project. It
Sweetwater Union High School District. Proposition O Bond Fund Performance Audit Report For the Fiscal Year Ended June 30, 2014.
Proposition O Bond Fund Performance Audit Report For the Fiscal Year Ended June 30, 2014 Prepared by: MOSS ADAMS LLP 9665 Granite Ridge Drive, Suite 600 Santa Diego, CA 92123 March 31, 2015 Board of Trustees
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
NFSA Project Management Guidelines
NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and
PHASE 9: OPERATIONS AND MAINTENANCE PHASE
PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.
How To Maintain An Effective System Of Internal Control Over Financial Reporting
Internal control over financial reporting Statement, assessment summary and action plan For the fiscal year ending March 31, 2012 Summary of the assessment of effectiveness of the system of internal control
Project Charter Guide
Project Charter Guide Feedback and Questions To help maintain the currency of this document, feedback and questions are welcomed. Please contact: IT Project Review and Oversight Chief Information Officer
STUDENT LOAN CORPORATION OF NEWFOUNDLAND AND LABRADOR ANNUAL REPORT 2006-07
STUDENT LOAN CORPORATION OF NEWFOUNDLAND AND LABRADOR ANNUAL REPORT 2006-07 TABLE OF CONTENTS CHAIRPERSON S MESSAGE... i 1.0 OVERVIEW... 1 1.1 MANDATE... 1 1.2 VISION... 1 1.3 MISSION... 2 1.4 LINES OF
National IT Project Management Methodology
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA National IT Project Management Methodology Project Reporting Support Guide Version 0.5 Project Reporting Support Guide version 0.5 Page 1 Document Version
Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)
Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial
Quick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
PROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
Administrative Guidelines on the Internal Control Framework and Internal Audit Standards
Administrative Guidelines on the Internal Control Framework and Internal Audit Standards GCF/B.09/18 18 February 2015 Meeting of the Board 24 26 March 2015 Songdo, Republic of Korea Agenda item 24 Page
BUSINESS MANAGEMENT FINANCIAL MANAGEMENT BM FM WSQ. A Singapore Workforce Skills Qualifications Programme PROSPECTUS
BM FM WSQ PROSPECTUS BUSINESS MANAGEMENT FINANCIAL MANAGEMENT A Singapore Workforce Skills Qualifications Programme Part of Kaplan Learning Institute Pte Ltd Analyse Financial Statements 2 Develop and
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
White Paper Operations Research Applications to Support Performance Improvement in Healthcare
White Paper Operations Research Applications to Support Performance Improvement in Healthcare Date: April, 2011 Provided by: Concurrent Technologies Corporation (CTC) 100 CTC Drive Johnstown, PA 15904-1935
Establish Collaborative Strategies to Better Manage a Global Vendor Network Devise a Proper Float Plan
Establish Collaborative Strategies to Better Manage a Global Vendor Network Devise a Proper Float Plan CBI s Biopharmaceutical Forum on Clinical and Commercial Global Supply Chain Excellence Sandy Onorato
Sample Examination Questions
Sample Examination Questions The following questions are examples of the type of questions that appear on the PMP Certification Examination. Disclaimer: These questions are intended for study purposes
Objectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources
Project Management for Small Business Moderator: Maria Mancha Frontline Systems, Inc. Objectives Project Management Overview Successful Project Fundamentals Additional Training Resources Project Management
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit
Internal Audit Report Toll Operations Contract Management TxDOT Office of Internal Audit Objective To determine whether the Toll Operations Division (TOD) contract management structure is designed and