Project Charter Client: IPS

Size: px
Start display at page:

Download "Project Charter Client: IPS"

Transcription

1 Project Summary Project* IPS Integration with Global Financials Client* Mercer IPS Primary Contact Chi Swain Engagement Manager* Project Manager* Tracking/Billing Code* Description* Irene Spyke Joy Wallace MFIN (MFS) IMISGL-001-Multiple Projects (IPS) Migration of the IMIS Financials and other disparate operating systems and applications being used by the IPS business in each region towards one global finance system (Global Single Instance) in order to improve global operations and reporting. Project Team Role Name Responsibilities Sponsor Chi Swain Provides guidance to Engagement Manager: maintains project vision; establishes priorities; builds organizational support; grants formal approval, as needed. Engagement Manager* Irene Spyke (IPS) Errol Viegas (MFS) Sets strategic direction; drives decisionmaking; facilitates project team communication; manages team dynamics; resolves risk and scope issues; builds buy-in with project stakeholders. Establish the processes and disciplines for large, high-risk / high-reward projects - eg ensure PM Lite documents are completed; team is correctly identified; regular meeting set-up; project properly scoped; stakeholders thoroughly identified; a communication strategy established and followed; acts as peer reviewer / quality assurer to monitor and assist in the process as needed etc. Mercer Human Resource Consulting ( ) Page 1 of 9

2 Project Manager* Joy Wallace (IPS) Guy Mantley (Admin) Owns Project Plan; manages delivery; tracks progress; coordinates day-to-day activity; facilitates peer review and quality assurance protocol; elevates risks and scope changes to Engagement Manager. The Project manager may assume the Engagement Manager role in a small to medium-sized project. Core Team - Business Analysts* Irene Spyke Joy Wallace Local IPS (separate team sheet) Vinay Mandava (MFS) Ashley McDougald Completes specific Assignments (based on project and team member skills); collaborates with the Project Manager to negotiate Project Plan (results, resources and time); clarifies expectations; executes assigned responsibilities. Advisory Team* Irene Spyke Nathan Moutoux Chi Swain Doug Rausch (MFS) Randy Sanders (MFS) Errol Viegas (MFS) Kathy Grossman (PMO) Larry Vangen Gives input to the Project Manager and Engagement Manager (as requested); raises issues and potential conflict. Advisory Meetings will be scheduled twice a month (15th & 30th where possible) to review the IMIS Financial Migration Project's status. Mercer Human Resource Consulting ( ) Page 2 of 9

3 Executive Steering Committee Team Steve Brink Larry Snyder Nathan Moutoux Chi Swain (Sponsor) Andy Goldbaum Larry Boyd Harry Van Drunen Nancy Stromp Larry Vangen Gerry Fazio Peter Beltrame Reviews Project Progress & Status and key decisions to offer feedback; shares project status with others (and other teams) to inform and identify potential conflict; champions project; helps secure resources. Steering Committee Meetings will be scheduled once a month. Key Stakeholders IPS Leadership Group IPS Operations Members IPS Finance Members MFS Leadership Group MFS Oracle Support Members MFS Production Support Members MFS Global One-Code Members Have interest in the successful delivery of the project and that the objectives identified have been addressed in a sufficient manner Standardization in processes, support, and administration is reduced or eliminated. Able to meet reporting needs of senior management more efficiently and accurately. Have interest in the successful delivery of the project and that the objectives identified have been addressed in a sufficient manner Have interest in the successful delivery of the project and that the objectives identified have been addressed in a sufficient manner Enhance their capabilities to support the IPS Finance business group as part of the Global Mercer system Enhance their capabilities to support the IPS Finance business group as part of the Global Mercer system Mercer Human Resource Consulting ( ) Page 3 of 9

4 Business Alignment Business Need* The new IMIS system will be part of the Mercer financial platforms consistent with the One Mercer initiative and as such enhance the leveraging of resources while eliminating critical dependencies, other risks and duplicative work of maintaining a separate parallel instances/systems. As a global system that is part of Mercer s global single instance, this will also broaden the knowledge of customers and prospects creating additional marketing opportunities across both Consulting and Products Services. Business Needs identified are: Client data globally Tracking of Relationship management Tracking of Survey Purchase and Participation history Ability to assess Client Profitability One-code client records Migrate IPS Customers to Mercer s Global Customer base Access to Customer Demographic data Product data globally Ability to assess Product Profitability Standardize pricing Standardize processes Bundling (ATO, PTO) (Business decision) Revenue recognition, sharing Disparate systems, support, processes reduced or eliminated. Administration reduced, centralized Support leveraged across more resources System enhancements Legacy systems no longer supported or have the flexibility to grow and transform along with the business. MAGIC and SURVEY Operations enhancements, linkages Survey participation Product access / fulfillment (on-line access to Surveys) Evidence of Need Lack of a Global Instance with common Customer and Item Database. Mercer Human Resource Consulting ( ) Page 4 of 9

5 Success Measures Desired Outcomes Migrate the current IMIS North American application into the Global Single Instance (GSI) Expand the GSI version of IMIS to all IPS Operations. Desired Results: - Common Customer and Item Database - Standard, Participation tracking, Order and Invoicing Processes (IMIS, GIS-LITE, Survey, Magic, TPS) - Global, Regional and Local Reporting capabilities (drill up/down) Measurement Successful Migration of IMIS into a Global Single Instance. At a minimum, current functionality must be kept in tact. Global expansion of the GSI Version to support regional IPS groups in Asia-Pac, Australia, Latin America, and Europe. Single Instance database Common Survey Business Processes in one global system Enhanced Reporting Capabilities to provide management with client and product revenue. - Enhanced Customer knowledge Ability to use Client demographic data to pursue other opportunities to increase revenue - Reduce critical dependencies and repetitive efforts Stream line the Ordering process, and eliminate duplicated efforts The above initiatives should be done in tandem to insure that all proposed objectives are achieved. Preliminary Scope Proposed SMART Solution* Complete Project Scoping efforts by mid-january (excluding all Global Requirements). Launch the IMIS Migration Project early to mid-january Project Driver* Results -- Resources -- Time -- Deliverable(s)* Result, Product or Service Description Global Business Requirements Project Charter Global business requirements for all IPS regional groups must be gathered to build a standard global platform. Definition of the scope, risks, success criteria, resources, costs, communications, and overall governance of the project. Mercer Human Resource Consulting ( ) Page 5 of 9

6 Detailed Project Plan GAP Analysis Communications Plan Work break-down structure of the detailed tasks required during the course of the project timeline To identify gaps in systems/processes, their relevance and priority to the success/failure of the project. How the progress and status of the project will be communicated to the various stakeholders, executive members, and project team members. Project Governance Document Risk Management & Contingency Plan System Documentation Project Close Checklist Rules on how the project will be governed escalation of issues, constraints, progress tracking, etc. Identification of project risks, the severity of each type and the impact each may have on the project. Each risk should have a contingency measures if permissible in order to mitigate the risk of failure. Configuration guides, Interface specifications, custom programs, etc should all be documented and approved as the project unfolds and should be version controlled for modifications throughout the project lifecycle. Project Closure Components Estimated Timing* Start Jan-2008 End TBD Milestones* Event Develop Project Charter Develop Detailed Project Plan Charter Approval Project Kick-Off Meeting Finalize Business Requirements Finalize Training Requirements Identify GAPS and FITS Finalize IPS Migration Plan (Regional Migrations) Development Set-up Completed Custom Development Completed Conference Room Pilot 1 Quality Assurance Phase Completed Conference Room Pilot 2 Target Date 23-Jan Jan Feb Feb Feb-2008 TBD 06-Mar Mar Apr Jun Jul Aug-2008 TBD Mercer Human Resource Consulting ( ) Page 6 of 9

7 Customer Data readiness (UAT) Data Migration Completed User Acceptance Phase Completed User Acceptance Testing Sign-Offs Production Setup Completed Production Data Migration Completed Production Migration Sign-Offs Project Close 15-Aug Aug Oct Oct Oct Oct Oct-2008 TBD Estimated People Resources* Estimated Financial Resources* Scope Inclusions and Exclusions See Team Worksheet Matrix See Budget Worksheet In Scope: 1. Oracle Modules to be implemented are: A. Receivables B. Order Management C. Inventory D. Telesales E. General Ledger F. Advanced Pricing 2. Vertex Tax Calculation Engine 3. Migration of custom objects that are required to build the current functionality of IMIS into Global Financials 4. Migration of IPS North America to Global Financials 5. Enable Asia-Pac GIS Lite countries with additional global functionality/processes. 6. Migration of Australia/New Zealand from Survey Application 7. Migration of IPS Europe from Magic Application 8. Data Migration of AR Open Items 9. Global One-Coding of IPS Customer data 10. New Interface from Global Financials to M-IDEAS for Global Revenue Reporting Out of Scope: 1. Automated integration with Pay Monitor, DSMS, GST 2. Migration of Latin American countries Mercer Human Resource Consulting ( ) Page 7 of 9

8 Project Context Risk Identification* Assumptions, Constraints and Dependencies Event 1. Inadequate resources (human or financial) to achieve project s desired outcomes or target timing. 2. Project Team unable to agree on resolution of additional requirements, scope creep, or agreed upon FITS to identifiable GAPS during the testing stages of the project. 3. Customer data in the Global Financials is adequately and properly maintained 4. Customer Maintenance is immediate and users have a need to directly access the data. H M L M - H M - H H H Potential Mitigation Obtain commitment on resources in advance (e.g. from Project Team and Management) Ensure adequate consultation with business areas to ensure their needs are taken into account Allow IPS responsibilities to maintain data that is specific to their organization. Allow IPS responsibilities to maintain data that is specific to their organization. Potential Contingency Build additional time into target date or put on more resources, or increase the budget Final decisions to be made by members of the Steering Committee Incorporate a data clean-up exercise into the timeline as a requirement of the project. TBD 1. Resources identified are fully engaged on the project in order to meet deliverables according to the detailed work plan 2. Project Tracking and Change Management Procedures Status Reporting* Scope Change* Team Communication Mercer Human Resource Consulting ( ) Page 8 of 9

9 Version Information Author* Errol Viegas Date Dec-2007 Reviewer Irene Spyke / Joy Wallace Date Project Team Approver* Irene Spyke / Errol Viegas Date Client Approver* Chi Swain Date Attachments/ Related Documents* Proposal Y Engagement Letter -- Business Case -- Situational Analysis -- Gap Analysis -- Risk Management Plan RACI -- Resource Plan -- Budget Development Worksheet Stakeholder Analysis -- Team Selection Worksheet -- Organization Chart -- Other: -- Other: -- Other: Y Version This form is intended to help Mercer employees initiate and preliminarily define an internal project or external engagement. This document does not constitute a legal contract or agreement between parties. Please refer to the document use guidelines (available separately) to learn more about the Mercer Project Management process and use of the Mercer PM toolkit. Examples, additional tools and information are available through Mercer s global intranet. c:\documents and settings\marian-pallazola\my documents\project management initiative\tools\gate tools\charter\charter_template_ doc Mercer Human Resource Consulting ( ) Page 9 of 9

Advisory User Group Meeting. October 18, 2011

Advisory User Group Meeting. October 18, 2011 Advisory User Group Meeting October 18, 2011 1 Agenda 11:30 Welcome Christine Lavoie 11:35 Session Objectives Christine Lavoie 11:40 USC s Research Administration System Christine Lavoie 11:50 Project

More information

Module 2: The Project Initiation Stage

Module 2: The Project Initiation Stage Overview Initiation stage is highly instrumental in the life cycle of a project as it defines the boundaries of the project gives clarity to all participants about the objectives, scope, cost timescale

More information

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,

More information

Subject Area 1 Project Initiation and Management

Subject Area 1 Project Initiation and Management DRII/BCI Professional Practice Narrative: Establish the need for a Business Continuity Plan (BCP), including obtaining management support and organizing and managing the BCP project to completion. (This

More information

OE PROJECT CHARTER Business Process Management System Implementation

OE PROJECT CHARTER Business Process Management System Implementation PROJECT NAME: PREPARED BY: DATE (MM/DD/YYYY): Andrea Lambert, Senior Business Process Consultant, OE Program Office 09/15/2014 PROJECT CHARTER VERSION HISTORY VERSION DATE COMMENTS (DRAFT, SIGNED, REVISED

More information

PROJECT MANAGEMENT PLAN <PROJECT NAME>

PROJECT MANAGEMENT PLAN <PROJECT NAME> PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information

Systems Approach Workbook: Implementation Plan Template

Systems Approach Workbook: Implementation Plan Template Systems Approach Workbook: Implementation Plan Template Intended to support regional directors, managers or others who will be leading system change, the implementation plan template has been developed

More information

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010 Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning

More information

Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)

Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

How To Write A Project Management Plan

How To Write A Project Management Plan Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents

More information

Roles: Scrum Master & Project Manager

Roles: Scrum Master & Project Manager Roles: Scrum Master & Project Manager Scrum Master: Facilitate collaborative meetings Track team performance Remove impediments (Risk, Issue) Validate team alignment to Agile framework and scope Drive

More information

DPC - Strategy and Project Delivery Unit Project Management Methodology. Updated April 2010

DPC - Strategy and Project Delivery Unit Project Management Methodology. Updated April 2010 DPC - Strategy and Project Delivery Unit Project Management Methodology Updated April 2010 This project management methodology is designed to help SPDU staff to plan, manage and measure a successful project

More information

Crosswalk Between Current and New PMP Task Classifications

Crosswalk Between Current and New PMP Task Classifications Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the

More information

Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing

Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing STATE OF MICHIGAN SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing Executive Summary The State of Michigan has dedicated integrated team of resources for the

More information

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History

More information

Essential Elements for Any Successful Project

Essential Elements for Any Successful Project In this chapter Learn what comprises a successful project Understand the common characteristics of troubled projects Review the common characteristics of successful projects Learn which tools are indispensable

More information

KMS Implementation Roadmap

KMS Implementation Roadmap KMS Implementation Roadmap Sample Excerpt Prepared by: The Knowledge Compass, Inc. TABLE OF CONTENTS 1. EXECUTIVE SUMMARY 5 1.1 Overview 5 1.2 Project Goals & Objectives 5 1.3 Implementation Approach 5

More information

Project Management for econnectivity

Project Management for econnectivity Project Management for econnectivity Marilyn Hunter - PMP November 10, 2015 2 Purpose of this session Provide information and understanding of how to lead connectivity projects within AgGateway or within

More information

Central Agency for Information Technology

Central Agency for Information Technology Central Agency for Information Technology Development of a National IT Governance Framework Project Management Agenda 1 What is project management? Why it is important? 2 Leading practices 3 Project management

More information

1550 Nipissing Court Tel: 905.837.0953; Cell: 289.200.0953 Pickering Ontario L1V 6T9

1550 Nipissing Court Tel: 905.837.0953; Cell: 289.200.0953 Pickering Ontario L1V 6T9 1550 Nipissing Court Tel: 905.837.0953; Cell: 289.200.0953 Pickering Ontario L1V 6T9 email: horace.lindsay@gmail.com PROJECT MANAGEMENT EXPERIENCE SUMMARY Acquired diverse Project Management experiences

More information

Company A Project Plan

Company A Project Plan Company A Project Plan Project Name: Close Optimization Project Example Prepared By: David Done - Project Manager Title: John Doe -Project Manager Date: March 17, 2011 Project Plan Approval Signatures

More information

To provide a procedure and associated guidelines to facilitate the management of project dependencies.

To provide a procedure and associated guidelines to facilitate the management of project dependencies. Management DEPENDENCY MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project dependencies. Overview Dependencies in this Phase are defined as actions,

More information

MNsure Assessment Summary

MNsure Assessment Summary MNsure Assessment Summary Contact Center Technical Program Management Software and Data January 17, 2014 Executive Summary Based on Optum s initial review, we are able to conclude that, while MNsure will

More information

Project Implementation Process (PIP)

Project Implementation Process (PIP) Vanderbilt University Medical Center Project Implementation Process (PIP).......... Project Implementation Process OVERVIEW...4 PROJECT PLANNING PHASE...5 PHASE PURPOSE... 5 TASK: TRANSITION FROM PEP TO

More information

Driving Excellence in Implementation and Beyond The Underlying Quality Principles

Driving Excellence in Implementation and Beyond The Underlying Quality Principles SAP Thought Leadership Paper SAP Active Quality Management Driving Excellence in Implementation and Beyond The Underlying Quality Principles 2014 SAP AG or an SAP affiliate company. All rights reserved.

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS

CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS Chapter 3: Managing Implementation Projects CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS Objectives Introduction The objectives are: Describe common problems that occur in implementation projects. Describe

More information

California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9 th Street, Room 141 Sacramento, CA 95814

California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9 th Street, Room 141 Sacramento, CA 95814 IT Project Status Report For an MHSA-Funded IT Project Please send the Signed Original to the following address: California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9

More information

Facilities Portfolio Management Tool

Facilities Portfolio Management Tool 2016 Facilities Portfolio Management Tool Project Charter Budget- Facilities Oversight Office of Financial Management 4/10/2016 CONTENTS Overview... 2 Purpose Statement... 2 Background... 2 Goals & Objectives...

More information

Enterprise Data Governance

Enterprise Data Governance DATA GOVERNANCE Enterprise Data Governance Strategies and Approaches for Implementing a Multi-Domain Data Governance Model Mark Allen Sr. Consultant, Enterprise Data Governance WellPoint, Inc. 1 Introduction:

More information

Analysis One Code Desc. Transaction Amount. Fiscal Period

Analysis One Code Desc. Transaction Amount. Fiscal Period Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00

More information

UCPath Project: Phase 1 Implementation Plan UC Santa Cruz

UCPath Project: Phase 1 Implementation Plan UC Santa Cruz UCPath Project: Phase 1 Implementation Plan UC Santa Cruz 06/12/2012 Version: Final Author: Laurie Eppler, David Turner Table of Contents 1 EXECUTIVE SUMMARY... 1 1.1 Introduction... 1 1.2 Context for

More information

G R E E N G L O B A L R E S O U R C E S : C O N F I D E N T I A L A N D P R O P R I E T A R Y 1

G R E E N G L O B A L R E S O U R C E S : C O N F I D E N T I A L A N D P R O P R I E T A R Y 1 P R O P R I E T A R Y 1 INTRODUCTION TO CHANGE MANAGEMENT Definition The Change Process Change Management Approach Awareness to New Normal Change Management Approach Operating Principles List of Change

More information

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

Project Management. Sally Buck, MS. Chief Executive Officer July 2014

Project Management. Sally Buck, MS. Chief Executive Officer July 2014 600 East Superior Street, Suite 404 I Duluth, MN 55802 I Ph. 800.997.6685 or 218.727.9390 I www.ruralcenter.org Project Management Sally Buck, MS Chief Executive Officer July 2014 Purpose The National

More information

Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview

Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program

More information

Launching an Enterprise-Wide Solution My Government of Canada Human Resources (My GCHR)

Launching an Enterprise-Wide Solution My Government of Canada Human Resources (My GCHR) Tammy Labelle Public Works and Government Services Government of Canada Launching an Enterprise-Wide Solution My Government of Canada Human Resources (My GCHR) Copyright Notice The contents of this presentation

More information

State of California Department of Transportation. Transportation System Data Business Plan

State of California Department of Transportation. Transportation System Data Business Plan DRAFT Page i State of California Department of Transportation Transportation System Data Business Plan RFO# TSI DPA-0003 September 29, 2011 DRAFT Page ii Table of Contents Executive Summary... 4 Chapter

More information

Project Number: P344. Business Intelligence Tool Data Warehouse Implementation. Project Charter Version 1.2 1/12/2011

Project Number: P344. Business Intelligence Tool Data Warehouse Implementation. Project Charter Version 1.2 1/12/2011 Project Number: P344 Business Intelligence Tool Data Warehouse Implementation Project Charter Version 1.2 1/12/2011 Table of Contents I) P344 Business Intelligence Tool Data Warehouse Implementation...

More information

Business Systems Analyst Job Family

Business Systems Analyst Job Family Promotion Criteria Entry level requires several years of work experience, either in a business area, or programmer with involvement in business systems. Demonstrated ability to learn and apply technology.

More information

Project Team Roles Adapted for PAAMCO

Project Team Roles Adapted for PAAMCO Project Team Roles Adapted for PAAMCO Project Roles, Authority & Responsibilities Role a defined funciton assumed by or assigned to a person in the project Authority the right to apply project resources,

More information

Procurement Reporting - OBIEE

Procurement Reporting - OBIEE UC BERKELEY Procurement Reporting - OBIEE Project Charter Tracey Bolton 9/7/2011 0 P age Version 3 Project Name: Prepared by: EDW Procurement Reporting Project Tracey Bolton Date (MM/DD/YYYY): 08/4/2011

More information

PM Services. Portfolio Strategy, Design and Build

PM Services. Portfolio Strategy, Design and Build PM Services Portfolio Strategy, Design and Build Portfolio Strategy, Design and Build PM Services consultants will design an effective portfolio management system and works closely with client management

More information

SUMMARY PROFESSIONAL EXPERIENCE. IBM Canada, Senior Business Transformation Consultant

SUMMARY PROFESSIONAL EXPERIENCE. IBM Canada, Senior Business Transformation Consultant Doreen Funk, MA 191 Discovery Ridge Blvd SW, Calgary Cell: 587-434- 0811 E- mail: dorfunk@hotmail.com SUMMARY Senior management consultant with 20 years of experience in applying strategies and implementing

More information

POLICY AND PROCEDURES OFFICE OF STRATEGIC PROGRAMS. CDER Informatics Governance Process. Table of Contents

POLICY AND PROCEDURES OFFICE OF STRATEGIC PROGRAMS. CDER Informatics Governance Process. Table of Contents CENTER FOR DRUG EVALUATION AND RESEARCH MAPP 7600.8 Rev. 1 POLICY AND PROCEDURES OFFICE OF STRATEGIC PROGRAMS CDER Informatics Governance Process Table of Contents PURPOSE...1 BACKGROUND...1 POLICY...2

More information

The Fast Track Project Glossary is organized into four sections for ease of use:

The Fast Track Project Glossary is organized into four sections for ease of use: The Fast Track Management Glossary provides a handy reference guide to the fast track management model, encompassing the concepts, steps and strategies used to manage successful projects even in the face

More information

ID Task Name Time Pred

ID Task Name Time Pred 0 UC Modernization Project Plan 1115 d 1 1 Phase I - Business Case Development and Competitive Procurement 205 d 2 1.1 Complete Initial Feasibility Study 55 d 3 1.2 Prepare and Issue LBR 30 d 2 4 1.3 Competitive

More information

Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre

Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre Proposal To change the opening hours of the Revenues & Benefits Call Centre to 9am until 5pm Monday to Friday with effect

More information

Test Plan (a Real Sample) SoftwareTestingHelp.com Live Project Training - OrangeHRM

Test Plan (a Real Sample) SoftwareTestingHelp.com Live Project Training - OrangeHRM www.softwaretestinghelp.com Test Plan (a Real Sample) SoftwareTestingHelp.com Live Project Training - OrangeHRM 2/1/2014 SoftwareTestingHelp.com Name of the tester Note: This is a sample test plan created

More information

Employee performance management in a global setting. Brenda Wilson

Employee performance management in a global setting. Brenda Wilson Employee performance management in a global setting Brenda Wilson Performance management overview What is performance management? Performance management is a CORE business process driven by business strategy,

More information

Conducting Effective Change Management for Your Oracle E-Business Suite Implementation. Robert E. Henry AST Corporation

Conducting Effective Change Management for Your Oracle E-Business Suite Implementation. Robert E. Henry AST Corporation Conducting Effective Change Management for Your Oracle E-Business Suite Implementation Robert E. Henry AST Corporation TOPICS The necessity of change management Change management methodology Successful

More information

Health and Safety in Action

Health and Safety in Action Health and Safety in Action Safe and Healthy Workplaces for BC s Health Care Workers Provincial Reporting and Data Management Initiative #1 Final Report Initiative Sponsor: Catherine Fast HSIA #1: Final

More information

PROJECT: DLS Website Redesign STATUS REPORT May-June 2015

PROJECT: DLS Website Redesign STATUS REPORT May-June 2015 PROJECT: DLS Website Redesign STATUS REPORT May-June 2015 Key Project Roles Project Sponsor: Karen Johnson Executive Director, DLS Project Advisor: Vanessa Salway Program Manager: Project Manager: Steve

More information

PROJECT MANAGEMENT PLAN Florida A&M University Financials Version 9.0 Upgrade and Redeployment

PROJECT MANAGEMENT PLAN Florida A&M University Financials Version 9.0 Upgrade and Redeployment PROJECT MANAGEMENT PLAN Florida A&M University Financials Version 9.0 Upgrade and Redeployment Author: Carl F. Paroby, Oracle Consulting Creation Date: October 24, 2007 Last Updated: Version: DRAFT 3A

More information

Stephen Doune HRIS Project Manager Plan International

Stephen Doune HRIS Project Manager Plan International Stephen Doune HRIS Project Manager Plan International Content 1. About Plan International 2. The Challenge 3. The Vision 4. About Assima 5. The Projects 6. The Timeline 7. Partner Selection 8. Key 1st

More information

IT Project Management Methodology. Project Execution Support Guide. Version 0.3

IT Project Management Methodology. Project Execution Support Guide. Version 0.3 NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Execution Support Guide Version 0.3 Table of Contents 1 INTRODUCTION... 4 1.1 When should Project Execution

More information

GTA Board of Directors September 4, 2014

GTA Board of Directors September 4, 2014 GTA Board of Directors September 4, 2014 Our Strategic Vision Our Mission A transparent, integrated enterprise where technology decisions are made with the citizen in mind To provide technology leadership

More information

PROJECT: Online Shop STATUS REPORT September 2015

PROJECT: Online Shop STATUS REPORT September 2015 PROJECT: Online Shop STATUS REPORT September Key Project Roles Project Sponsor: Paul Dowler Project Director: Program Manager: Project Manager: Ryan Giltrap Solution Coordinator: Ivan Saric Business Analyst:

More information

Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report

Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report The Enterprise Program Investment Council (EPIC) is responsible for governance

More information

BETTER RECORDS MANAGEMENT

BETTER RECORDS MANAGEMENT BETTER RECORDS MANAGEMENT THROUGH PROJECT MANAGEMENT Maura L. Dunn, CRM President April 8, 2015 What is the difference between program management and project management? Why does it matter? Programs Are

More information

On 11/19/2015, the GLWA Board was presented with Enterprise Resource Planning & Accounting system options for GLWA

On 11/19/2015, the GLWA Board was presented with Enterprise Resource Planning & Accounting system options for GLWA December 4, 2015 On 11/19/2015, the GLWA Board was presented with Enterprise Resource Planning & Accounting system options for GLWA The driver of a condensed timeline for assembling these options was the

More information

Academic Affairs Provost s Office Business Model Analysis Project

Academic Affairs Provost s Office Business Model Analysis Project Academic Affairs Provost s Office Business Model Analysis Management Plan P a g e 1 Contents Management Plan Purpose Scope Deliverables Governance Roles and Responsibilities Staffing Plan Decision Making

More information

Business Analyst Position Description

Business Analyst Position Description Analyst Position Description September 4, 2015 Analysis Position Description September 4, 2015 Page i Table of Contents General Characteristics... 1 Career Path... 2 Explanation of Proficiency Level Definitions...

More information

An Oracle White Paper March 2013. Project Management Office Starter Kit

An Oracle White Paper March 2013. Project Management Office Starter Kit An Oracle White Paper March 2013 Project Management Office Starter Kit Executive Overview... 1 Introduction... 1 Plan Phase... 2 Create Statement of Purpose and Goals... 2 Define Scope and Target Maturity...

More information

The ITS Project Management Framework

The ITS Project Management Framework The ITS Project Management Framework Information Technology Services Project Management Framework v1.0 1 Table of Contents Introduction 3 Why Create a Project Management Framework? 4 Projects versus Operational

More information

PMO Starter Kit. White Paper

PMO Starter Kit. White Paper PMO Starter Kit White Paper January 2011 TABLE OF CONTENTS 1. ABOUT THE PMO STARTER KIT...3 2. INTRODUCTION TO THE PMO STARTER KIT WHITE PAPER...3 3. PMO DEVELOPMENT ROADMAP...4 4. PLAN PHASE...5 4.1 CREATE

More information

Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions

Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions Today s Business Challenges Adopt leading CRM practices and stream line processes Take advantage

More information

NICE and Framework Overview

NICE and Framework Overview NICE and Framework Overview Bill Newhouse NIST NICE Leadership Team Computer Security Division Information Technology Lab National Institute of Standards and Technology TABLE OF CONTENTS Introduction to

More information

Oracle Cloud Been there, Done that!

Oracle Cloud Been there, Done that! Oracle Cloud Been there, Done that! What we have heard today Can we upgrade from 11i or R12 to Fusion? (sure lets call it Cloud) Oracle Cloud has many flavors Fusion (ERP, HCM etc), licensing (SaaS model),

More information

Enterprise Resource Planning (ERP) Program: Overview and Status Update

Enterprise Resource Planning (ERP) Program: Overview and Status Update Enterprise Resource Planning (ERP) Program: Overview and Status Update Human Resources (HR), Finance & Property Services (FPS), and Information Technology (IT) Departments For the Council Committee of

More information

Phase III Work Team Project Charter Email and Calendar Consolidation Implementation

Phase III Work Team Project Charter Email and Calendar Consolidation Implementation Charter approved August 24, 2012 Phase III Work Team Project Charter Email and Calendar Consolidation Implementation Team Name Email and Calendar Consolidation Implementation Team Objective Team objectives

More information

Project Processes. Media Snapshot. Project Management Process Groups

Project Processes. Media Snapshot. Project Management Process Groups Project Processes PROJECT LIFECYCLE A project normally requires a number of processes. A process is a series of actions directed toward a particular result Project management can be viewed as a number

More information

Project Management. Crossing the Finish Line. Sean Kukauskas Director of Ambulance Services Spaulding Rehabilitation Network

Project Management. Crossing the Finish Line. Sean Kukauskas Director of Ambulance Services Spaulding Rehabilitation Network Project Management Crossing the Finish Line Sean Kukauskas Director of Ambulance Services Spaulding Rehabilitation Network Objectives What is a project Project vs. Operations Why project management Overview

More information

Request for Project Approval

Request for Project Approval Date Issued: 04/13/2016 Page #: 1 of 5 1.0 POLICY OVERVIEW 1.1. This policy establishes uniform practices and procedures to be followed for authorizing ITD software projects. 1.2. LAUSD s Information Technology

More information

Planning for a Successful Information Governance Program. Kathy Downing, MA, RHIA CHPS,PMP AHIMA Senior Director IG

Planning for a Successful Information Governance Program. Kathy Downing, MA, RHIA CHPS,PMP AHIMA Senior Director IG Planning for a Successful Information Governance Program Kathy Downing, MA, RHIA CHPS,PMP AHIMA Senior Director IG Objectives Overview of Project Management Applying Project Management techniques to Information

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

Consulting Services for Enterprise Resource Planning Project Planning and RFP Development Government Finance Officers Association

Consulting Services for Enterprise Resource Planning Project Planning and RFP Development Government Finance Officers Association Volusia County Schools Consulting Services for Enterprise Resource Planning Project Planning and RFP Development Government Finance Officers Association May 12, 2016 Agenda o Introductions o Approach &

More information

Advisory Council member responsibilities include:

Advisory Council member responsibilities include: GOVERNANCE AND OVERSIGHT OF THE KUALI PROJECT: The following provides a chart of the Governance and Oversight Structure for the Kuali Project. In addition to the below, is a Functional Council that includes

More information

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007

More information

Project Management Planning

Project Management Planning The Project Plan Template The Project Plan The project plan forms the basis for all management efforts associated with the project. A project plan template is included in this document. The information

More information

How To Manage The Health Benefit Exchange At Mhix

How To Manage The Health Benefit Exchange At Mhix Minnesota Health Insurance Exchange (MNHIX) 1.1.2 Project Charter Date: 09/21/2012 11/9/2012 12:10 PM Page 1 of 18 T A B L E O F C O N T E N T S 1. MNHIX Introduction... 3 1.1 MNHIX Scope... 4 1.2 Critical

More information

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam 44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION

More information

SCOPE MANAGEMENT PLAN <PROJECT NAME>

SCOPE MANAGEMENT PLAN <PROJECT NAME> SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information

HKITPC Competency Definition

HKITPC Competency Definition HKITPC Competency Definition for the Certification copyright 2011 HKITPC HKITPC Competency Definition Document Number: HKCS-CD-L1L2 Version: 1.0 Date: June 2011 Prepared by Hong Kong IT Professional Certification

More information

Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases

Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases Ellucian Implementation Methodology Summary of Project Management and Solution Delivery Phases Rev. 5/10/2013 Table of Contents Overview 3 Project Management Initiation 4 Planning 5 Execution 6 Monitor

More information

RBC Insurance Fetes Online Auto/Home Insurance Growth

RBC Insurance Fetes Online Auto/Home Insurance Growth Case Studies, K. Harris Research Note 29 October 2002 RBC Insurance Fetes Online Auto/Home Insurance Growth RBC Insurance's e-business successes are generating greater than $3 million in premiums per month.

More information

Supplier Rating System

Supplier Rating System Supplier Rating System Supplier Manual Presented by Admiral Tool & Manufacturing Purchasing and Quality WI-PU-06-002 Rev. Lev. 003 Rev. Date 02/06/2003 1 Table of Contents Introduction 3 Scoring Criteria

More information

Project Charter Updated

Project Charter Updated Enterprise IT Service Management Pilot Proof of Concept Project Charter Updated Prepared By: M. Riley & J. Foster Date of Publication: March 13, 2006 Date Last Revised: April 25, 2007 PMO CH1, 8/01 Document

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : BearBuy Implementation PREPARED BY: Vanessa Wong and Jon Conhaim DATE (MM/DD/YYYY): 07/23/2011 PROJECT CHARTER VERSION HISTORY VERSION DATE COMMENTS (DRAFT, SIGNED, REVISED CURRENT STATUS) (MM/DD/YYYY)

More information

Microsoft Dynamics Sure Step 2012 Supplementary Training Material Version 5.0

Microsoft Dynamics Sure Step 2012 Supplementary Training Material Version 5.0 Microsoft Dynamics Sure Step 2012 Supplementary Training Material Version 5.0 www.firebrandtraining.com Course content Module 0 Course Content and Plan... 7 Objectives... 7 Course Plan... 7 Course Modules...

More information

Implementation of PeopleSoft 8.9

Implementation of PeopleSoft 8.9 Implementation of PeopleSoft 8.9 Implementation of any ERP product is a huge effort considering the generic nature of the product and specific customer requirements. In addition the industry specific and

More information

Performance Audit Concurrent Review: ERP Pre-Solicitation

Performance Audit Concurrent Review: ERP Pre-Solicitation Performance Audit Concurrent Review: ERP Pre-Solicitation April 2002 City Auditor s Office City of Kansas City, Missouri 24-2001 April 10, 2002 Honorable Mayor and Members of the City Council: We conducted

More information

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have

More information

SECTION I PROJECT SUMMARY (TRW)

SECTION I PROJECT SUMMARY (TRW) AS OF OCTOBER 11, 2010 SECTION I PROJECT SUMMARY (TRW) Table I Project Summary Agency/Department Information TRW Information Executive Sponsor: Cynthia Lorenzo Received Date: Project Director: Tom McCullion

More information

Sound Transit Internal Audit Report - No. 2014-3

Sound Transit Internal Audit Report - No. 2014-3 Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management

More information

How To Implement Itil V3

How To Implement Itil V3 2009 NMCI Conference: Implementing ITIL Session 1: ITSM Process ITSM COE Agenda Background ITSM Overview ITIL and Service Delivery Adopting ITIL to NGEN SE&I Activities 2 Background Develop Government

More information

Process Validation Workshops. Overview Session

Process Validation Workshops. Overview Session Process Validation Workshops Overview Session 2 Session Objectives: Prepare staff for participating in a Process Validation Workshop Clarify the Purpose of Process Validation Workshops Clarify Expected

More information