PROJECT MANAGEMENT PLAN Florida A&M University Financials Version 9.0 Upgrade and Redeployment

Size: px
Start display at page:

Download "PROJECT MANAGEMENT PLAN Florida A&M University Financials Version 9.0 Upgrade and Redeployment"

Transcription

1 PROJECT MANAGEMENT PLAN Florida A&M University Financials Version 9.0 Upgrade and Redeployment Author: Carl F. Paroby, Oracle Consulting Creation Date: October 24, 2007 Last Updated: Version: DRAFT 3A Approvals: Carl F. Paroby Oracle Consulting (OC) Veronica Stokes Florida A&M University (FAMU)

2 Document Control Change Record Date Author Version Change Reference 24-October November November Carl Paroby Draft 1a No Previous Document Carl Paroby Draft 2a Initial Comments from STG Process Review Carl Paroby Draft 3a Detailed review with OC team members Distribution Copy No. Name Location 1 Library Master Project Library 2 Veronica Stokes Project Director 3 Carl Paroby Project Director 4 Note to Holders: If you receive an electronic copy of this document and print it out, please write your name on the equivalent of the cover page, for document control purposes. If you receive a hard copy of this document, please write your name on the front cover, for document control purposes. Final Financial PMP Document Control Page ii of 61

3 Contents Document Control... ii Change Record... ii Distribution... ii Purpose of the Project Management Plan... 1 Important Terminology Used in this Document... 1 Scope... 3 Project Charter / Objectives... 3 Project Scope Statement... 4 Out of Scope Items... 6 Constraints and Assumptions... 6 Risks... 7 Relationship to Other Systems/Projects... 8 Project Phases, Deliverables and Milestones... 8 Change Control Process Financial Management Purpose Financial Management Approach Work Management Purpose Work Management Approach Work Plan Control Issue Management Purpose Definitions Issue Management Approach Procedure Risk Management Purpose Risk Management Approach Procedure Problem Management Purpose Problem Management Approach Procedure Organization and Staff Management Purpose Final Financial PMP Document Control Page iii of 61

4 Strategy The Project Team Project Roles and Responsibilities Education and Training Communications Management Purpose Communication Model Recurring Project Meetings Meeting Agendas, Attendees, Inputs, and Outputs Project Status Reports Quality Management Purpose Approach Procedure Configuration Management Purpose Configuration Definition Instance Management Patch Management Strategy Migration Utility Infrastructure Management Purpose Project Software/Tools Technical Infrastructure Team Work Environment Software Backup Procedures and System Administration Procurement Management Purpose Strategy Organizational Change Management Purpose Strategy Appendix A Project Plan Appendix B Control Documents Final Financial PMP Document Control Page iv of 61

5 Purpose of the Project Management Plan The purpose of this Project Management Plan (PMP) is to define the overall project management strategies and approaches that will be applied to the Financials Upgrade project for FAMU. The time and material contract - Ordering Document US OD-23-JULY and all associated Ordering Document Amendments between FAMU and OC defines the sum total of all legally binding obligations between OC and FAMU. This PMP attempts to further address the following key topics for the purpose of clarification and to help facilitate the effective management of the project: Project Charter / Objectives Project Scope Project Approach This PMP specifically defines the detailed Project Management standards and procedures that will be followed on the project, including but not limited to: Scope Management Work Management Issue Management Key Decision Management Risk Management Problem Management Organizational and Staff Management Communications Management Quality Management Configuration Management Infrastructure Management Responsibilities outlined in this plan will be applicable to both, OC and FAMU across the project, as specified in the document. Important Terminology Used in this Document Throughout this document, the term solution refers to and is interchangeable with approach or system. Solution is not intended to contractually bind OC to solve any issues or problems. It is intended to express the concept that an Final Financial PMP Document Control Page 1 of 61

6 approach to the upgrade project has been well thought out and is the result of the use of our products, methods and experience. Throughout this document, the term partner refers to and is interchangeable with ally or collaborator. Partner is not intended to contractually or legally bind OC to FAMU. Final Financial PMP Document Control Page 2 of 61

7 Scope A clear project scope definition will be one of the most important aspects of managing the implementation of FAMU Financials Upgrade as it clearly identifies boundaries of what is to be upgraded and implemented, and key deliverables to be produced. A good scope definition should be easy to understand, and clearly define what application modules, business processes, interfaces, enhancements, conversions and technical architecture needs to be implemented. Scope should also include the geographical boundaries and locations. The scope definition should also clearly define those things that are out of scope. Project Charter / Objectives FAMU is currently on the PeopleSoft Financial Suite version 8.4. FAMU understands that their 8.4 applications are out of support as of March 22, With this project, FAMU intends to upgrade the current 8.4 version of the PeopleSoft Financials to version 9. FAMU also wants to redeploy the Expenses, Accounts Receivable, and Billing modules during this time. Project Objectives Specifically, the objectives of the project are to: Upgrade the following PeopleSoft Release 8.4 modules currently in production at FAMU including all additional interfaces, custom reports, and extensions a. General Ledger b. Accounts Payable c. Asset Management d. Purchasing e. epro f. Contracts g. Grants h. Project Costing Evaluate during fit/gap for Upgrade and Redeployment of other PeopleSoft Applications including: a. Expenses Final Financial PMP Scope Page 3 of 61

8 b. Accounts Receivable c. Billing Critical Success Factors The critical success factors to meeting the goals stated in the mission statement are: Strong executive sponsorship and management support of the project mission and project team Adequate project staffing for the expected goals and timeline to be met Clear roles and responsibilities defined for the project in order to assure accountability, ownership, and quality A committed and well-informed project manager and project team having a thorough understanding of the project mission, goals, and milestones A comprehensive project work plan and Project Management Plan A defined and maintained project infrastructure throughout the project duration A thorough understanding of known project risks and assumptions throughout the executive committee and project team. An encouragement of team cohesion and timely communication A timely and quality resolution of existing logged issues (Service Requests) with the OC Support and Development organizations A timely and quality service and support from the OC Solution Lab Highly experienced and expert level consultants working on the upgrade project Active and strong participation from the campus and FAMU subject matter experts A timely and accurate response for infrastructure and other technical services from all third party service providers Project Scope Statement The project scope is defined completely and comprehensively by the ordering document and all associated ordering document amendments. The ordering document between FAMU and OC is the document of record when it comes to all questions of scope. Please Refer document US OD-23-JULY-2007 for more details on project scope. Applications PeopleSoft Application Module Upgrade Re-Deploy General Ledger Accounts Payable Final Financial PMP Scope Page 4 of 61

9 PeopleSoft Application Module Upgrade Re-Deploy Purchasing eprocurement Asset Management Accounts Receivable Billing Grants Contracts Project Costing Expenses Upgrade and Redeployment Activities Using Compass Methodology as a roadmap, OC will provide project planning and the structure to create a detailed project plan for the upgrade and redeployment. Provide assistance to FAMU with the following Upgrade Activities: a. Delta fit/gap analysis; b. Mentor the FAMU Subject Matter Experts (SMEs); c. Configuration review and adjustment of upgraded functionality; d. Configuration of new functionality; e. Evaluation of customizations, interfaces, and reports; f. Data mapping, conversion; g. OC will provide guidance to the FAMU Technical Team which includes, but is not limited to Customizations, Enhancements, Modifications, Localizations, and Interfaces (CEMLIS) h. Unit, System, and User Acceptance Testing (UAT). Assist FAMU implementation team to validate the Version 9 base table configuration (existing or new, where appropriate), to supplement the Version 9 base table configuration where allowed and appropriate; to design interfaces, reports and extensions, and to test FAMU configured Version 9 applications. Provide FAMU with assistance in revalidating security and streamlining PeopleSoft Roles and Permission Lists. Final Financial PMP Scope Page 5 of 61

10 Out of Scope Items The following items are specifically excluded from the scope of the FAMU Financials Upgrade: Hardware selection Network testing Performance Testing of hardware, network. Database Tuning after implementation Capacity and Sizing Disaster Recovery Reengineering Business processes End User Training Organizational Change Management Development and Execution of Test Scripts Audit Compliance Training Constraints and Assumptions The following constraints have been identified: FAMU resource availability is expected to be limited during July, 2008 due to fiscal year end activities. A July Go-Live was selected because it is best practice during an implementation or an upgrade to Go-Live on a fiscal year end. This facilitates year end processing, while allowing FAMU to start the new fiscal year with a fresh of books. FAMU has experienced a lot of staff turnover and is still trying to fill key project positions. In some cases, staffs with predominantly technical backgrounds have been assigned very challenging functional roles on the project. This presents a degree of risk to the success of the project as the learning curve for these individuals is higher. The following assumptions have been made in defining the Project Management Plan: Consulting Services will be performed at FAMU Tallahassee, Florida location and remotely when acceptable to both OC and FAMU. The FAMU PeopleSoft Financials upgrade project is estimated to be completed within 10 months (including one month of production support). OC will use the PeopleSoft Compass Methodology and related collateral. OC will provide guidance on PeopleSoft version 9 business processes and best practices. FAMU will evaluate new functionality contained within version 9 for possible uptake and inclusion during this upgrade process. Existing Final Financial PMP Scope Page 6 of 61

11 functionality already in use at FAMU will be evaluated during fit/gap of the project for possible inclusion into the project plan for this upgrade. OC will provide a Project Director experienced with Version 9 to work with the FAMU Project Director to plan and guide the implementation. It will be critical to include FAMU? Project Management for the PeopleSoft 8.4 to version 9 upgrade to coordinate onsite consulting, OC Lab, and FAMU resources. FAMU is responsible for providing OC with full access to the relevant FAMU functional, technical and business resources with adequate skills sets, experience, and knowledge to support the performance of upgrade and redeployment services. FAMU will provide a project team that is knowledgeable and experienced in completing work products in areas specific to FAMU business processes, policies and procedures, and organizational structure. FAMU will determine if and when process reengineering is required. FAMU is responsible for reengineering business processes. FAMU agrees to promptly address issues and provide timely responses to functional and technical questions. FAMU project team members will complete the required training or possess equivalent PeopleSoft Financials technical or functional experience. FAMU will provide adequate facilities for OC consultants while onsite, including office space, administrative supplies, meeting space, access to hardware and software, including security rights and passwords where required. FAMU is responsible for the revision and delivery of End User Training. FAMU is responsible for Organizational Change Management. FAMU Technical Team will work in partnership with the OC Team to work on existing and future CEMLIS. Risks The following risks have been identified that may affect the project during its progression: Significant turnover in FAMU leadership and staff FAMU s contractual obligation to IBM for the hosting of the PeopleSoft Financials instances Potential lack of support of the Executive Sponsor Significant data clean up is required in most of the current modules These and any other risks identified later will be tracked through the Risk Management process defined later in the Project Management Plan. Final Financial PMP Scope Page 7 of 61

12 Relationship to Other Systems/Projects It is the responsibility of FAMU to inform the OC Project Director of other business initiatives that may impact the project. The upgrade schedule of the PeopleSoft Financials environment may be impacted by other known business initiatives: Implementation of PeopleSoft HCM Production issues with the Campus Solutions or HCM environments Audit Issues FAMU s accreditation as an independent institution is in jeopardy. Project Phases, Deliverables and Milestones OC s Compass methodology is the toolkit for migrating from one PeopleSoft Applications release to another. Using this methodology, OC and FAMU will facilitate and provide guidance on how to upgrade the aforementioned modules from 8.4 to version 9 through six well-defined phases: Phasing Phase 1 : Strategy Without a strategy, the project doesn t have a course. In this phase, OC will assess FAMU s corporate objectives and business drivers for the project, and develop our understanding of their impacts and measurements. OC will work with FAMU to understand FAMU s critical business processes, current infrastructure, and application portfolio. OC will look at FAMU s goals and business drivers, and how OC can enhance FAMU s competitive advantage. In doing so, OC can understand FAMU s needs and can recommend PeopleSoft upgraded applications to help. Phase 2 : Planning In the Planning phase, our objective is to build a project plan. The deliverables FAMU will have at the end of the Planning phase include: A Project Management Plan (PMP), explaining how the project will be conducted. A Project Plan A list of defined deliverables An Issues, Risk, and Problem Log template Phase 3 : Structure During the Structure phase, FAMU will establish the framework for the upgrade project as a part of the fit/gap process. From the information gathered in the Planning phase, OC will identify, analyze, and prioritize any affected business processes, and OC will assess the software fit within this context. OC will show FAMU how the new release will impact its business processes, enabling FAMU to make decisions for gap solutions. At the conclusion of the Structure phase, FAMU will have: Documented business needs and affected business processes(see the Fit/Gap Prototype Document). Assessment of the fit of the software solution and identified gap solutions. Final Financial PMP Scope Page 8 of 61

13 Defined the technical and functional specifications for reports, interfaces, customizations, etc.. Phase 4 : Construct OC and FAMU together will design, build, and configure the upgraded system. As part of this work, OC will conduct initial system tests, prepare critical plans, and write documentation. The deliverables for this phase include: Test plans A production support plan A go-live contingency plan A fully configured upgraded system into which historical and current data can be loaded Phase 5 : Transition Just prior to Go-Live, the team will update and finalize system configuration and setup of base tables, prepare the production environment, and conduct final user and system tests to verify that all data has been converted accurately thus ensuring a smooth transition to production. OC will also help FAMU determine a training approach for FAMU s end users, design training materials and a training environment, and conduct train-the- trainer sessions. When this phase is completed FAMU will have: A fully tested, production-ready system. A complete end user training approach ready for rollout. A tested cutover plan. Phase 6 : Deploy FAMU is live. As FAMU makes the transition, OC consultants will remain with FAMU in support roles, helping to troubleshoot, teaching FAMU how to maximize the value of the upgraded system that has been deployed, and identifying next step opportunities. At the end of this phase, FAMU will have: Gone Live on v.9 PeopleSoft Financials. Moved all project support activities to FAMU production support team. Trained end users. Carried out project Close-Out activities including Project Diary (Project Documentation, Sign-Off, and Close Out) FAMU will have received production support for the first month end or longer if FAMU chooses to avail of these services. Work Products This section defines the tasks and key deliverables as well as target milestone dates for each phase described above. Please refer to the FAMU Deliverables Tracking Document. Final Financial PMP Scope Page 9 of 61

14 Change Control Process Note: As changes to scope or other controlled project baseline items arise during project execution, it is important to follow a disciplined change management process so as to ensure agreement on the following: 1. Required adjustments to schedule and/or cost 2. Incremental resource requirements 3. Business/project impact 4. Adherence to contractual requirements Note: The scope change management process will include a Change Request Form (CRF) and a change control log (used for tracking the status of all change requests). The process will take into account the following information: Who is logging the request and why Detailed functional and/or technical description of the requested change Business impact / Priority Cost/Schedule impact adjustments to work plan and financial plan Resource impact adjustments to resource plan OC and FAMU approval/escalation process (e.g. who is responsible for approving/rejecting proposed project changes, roles and responsibilities, are any changes automatically approved without review; etc.) The process for updating the contract based on approved changes The process for updating other project plans (i.e. work plan, finance plan, etc.) based on approved change requests Scope Change Control Approach The Scope Change Control procedure is defined as any modification to or deviation from the agreed functionality, or changes to the time or costs agreed upon in the contract will be subject to the following procedure. OC or FAMU may initiate change requests whenever there is a perceived need for a change that will affect the contract of work, such as schedules, functionality, or cost. Agreement to a CRF signifies agreement to a change in overall costs, functionality, or schedules. Propose Changes A change can be identified to both OC and FAMU project managers by a resolved problem or issue, document, conversation, or other form of communication. Final Financial PMP Scope Page 10 of 61

15 The person who is functionally responsible (from OC) for the area of change will: o o o o o o Complete a CRF for the proposed changes and submit copies to the relevant parties (possibly including subcontractors, and technical input) for assessment. Record the CRF in the change control log. Investigate and evaluate the impact of the proposed change. Prepare a response to the proposed change. File the CRF original in the project library. Agree with FAMU on whether the change should be performed and obtain authorization sign-off of the CRF. If the change is not agreed to: The OC Project Manager will discuss and document the objection with the FAMU Project Manager The proposed change will be re-negotiated if possible, or withdrawn if it is agreed to be non-essential. In such a case, the reasons will be documented on the CRF. Monitor Changes Once the CRF has been signed then work may begin. The Project Manager will adjust project plans to incorporate agreed changes and present them at progress meetings for approval. Progress on the change controls will be reported at progress meetings. Both OC and FAMU project managers must sign the CRF once the change has been completed. The CRF is returned to the originator who will update the Change Request Log with the date completed. The Change Request Log will be reviewed at progress meetings to check on changes that have not been completed. Final Financial PMP Scope Page 11 of 61

16 Financial Management Purpose The purpose of the Financial Management Plan is to define all the processes needed to ensure that the project operates and completes within the approved budget. Financial Management Approach Financial Management for the implementation of FAMU Financials Upgrade will be managed on a T&M basis: OC will invoice FAMU for actual time spent performing the services, plus materials, taxes and expenses. Established an initial time & materials project budget Develop a project plan that correlates to the project scope and schedule Additional costs are documented in approved change requests and the budget will be updated Invoicing and payment structure are documented in the contract Final Financial PMP Financial Management Page 12 of 61

17 Work Management Purpose The purpose of the Work Management Plan is to establish procedures for defining, monitoring, and directing all work performed on the project. Work Management Approach The Work Management Plan should clearly state the procedures for defining, documenting, gaining agreement on, and communicating the project s work plan as well as the processes to be used for executing and controlling the work. The project work plan is the hub of project management as it denotes all activities that the team will be participating in within the project s scope, objectives, and approach and it provides a repository of data that the project manager can utilize to manage the project to plan. Processes that would be used for work plan execution and control would include the following: Developing the Baseline Project Work Plan Controlling the Work Plan through the life cycle of the project. Executing the Work Plan Managing Team Work Managing Team Time The project work plan will be updated from project staff timesheets on a weekly basis. At weekly intervals the latest status will be reported to FAMU and OC management as part of Status Monitoring and Reporting. Each week the project work plan and high level project timeline will be archived so that it is possible to trace project data back to previous versions of the work plan. Work Plan Control This procedure defines how the Project Work plan will be maintained throughout the project management life cycle. The procedures also detail the entry of actual and estimated dollars to complete and reporting work progress. The Work plan Control Procedure assumes the use of Microsoft Project and Excel. The procedures are as follows: Commence project with the baseline Project Work plan. The OC Project Director and the FAMU Project Director review and confirm the Project Work plan. 1. OC leads their actual and percentage to complete to the OC Project Director each Friday. Final Financial PMP Work Management Page 13 of 61

18 The OC Project Director updates the Project Work plan on a weekly basis by entering percentage completion for each started task. 2. The OC Project Director backs up the plan after updating. 3. The OC Project Director uploads the updated project plan to 'iprojects' and reports status at the weekly or monthly meetings. 4. The Team Leads will create and maintain the project issue logs on a weekly basis and update the status report. The content of Issue Logs will be discussed at the weekly status-reporting meeting. Issue Logs will be summarized and presented to the Steering Committee on monthly basis. FAMU may use the same process for status reporting for their assigned activities as they relate to the program. The Project Work plan will be updated from project staff timesheets on a weekly basis. At monthly intervals the latest status will be reported to FAMU and OC management as part of status monitoring and reporting. Each week the Project Work plan will be saved to a file with the week number coded in the filename, so that it is possible to trace project data back to previous versions of the Work plan. OC project manager will maintain the project work plan and report changes as soon as they re known. FAMU will have three days to respond to any and all plan changes. Final Financial PMP Work Management Page 14 of 61

19 Issue Management Purpose During the project, issues will occur which will be outside the ability of the project team to be able to resolve immediately. In addition, the project team will require a mechanism to capturing the decisions or resolutions made regarding these issues. Issue Management is a structured process for identifying, documenting, tracking and resolving issues as they occur throughout the lifecycle of a project. Definitions Issues are differentiated from Problems and Risks as follows: An Issue is a point or matter that is not settled and is under discussion (there may also be opposing views and/or disagreements). Some issues if not addressed, could adversely impact the success of a project. (From PMI PMBOK Third Edition) A Problem is a perceived variance between the expected and observed ability of an item to fulfill its defined purpose (e.g. software bug, consistent unexpected downtimes, a faulty design, TARs/SRs, etc.). (From PMI PMBOK 2000) A Risk is an uncertain event or condition, which if it occurs, has a positive or negative effect on a project s objectives. (From PMI PMBOK Third Edition) Issue Management Approach This strategy must include details for Identifying and logging issues Prioritizing issues, including establishing clear guidelines and definitions for discrete issue priorities (e.g. showstopper/executive, high, medium, low, etc.) Assigning issues to person(s) responsible for owning resolution and for performing impact analysis as required Tracking and reporting issues status (e.g. issue aging, open/closed status, resolution status, etc.) Escalating issues including how long does the issue stay at one level before it is escalated to the next level up to the executive committee The intended result is a minimal backlog of unresolved issues, thus providing the lowest practical impact to the project. Final Financial PMP Issue Management Page 15 of 61

20 Procedure Issues can be raised by any project stakeholder, including project team members, third-party integrators, or vendors. Complex issues will be recorded in detail on an Issue Form. If the issue also represents a risk, the risk will be logged as well. Issues should be entered on the Issue Log and categorized by type and priority, and an estimated closure date should be assigned. The Project Manager will investigate the issue and, if necessary, will update the Issue Log with background information to place the issue in perspective. At a minimum, the following information should be captured and tracked for all issues: ISSUE ID - each issue should have a unique ID SUBMITTED BY person and/or organization who raised the issue DATE SUBMITTED date the issue was recorded in the issues tracking system ESTIMATED ACTION DATE date that the next action is expected on this issue IMPACT impact to the project and/or business in terms of money, time, and/or quality APPLICATION/FLOW/MODULE if applicable, the name of the application, flow, or module to which the issue pertains TYPE type of issue (e.g. technical, process, organizational, etc.) TITLE short description of the issue (usually a few words or a sentence, helpful when reporting issues) DESCRIPTION complete description of the issue, the more details the better PRIORITY issue priority (typically values could be critical, high, medium, low ) ESCALATION current escalation level and anticipated date and level of next escalation TARGET DATE target date for resolution ASSIGNED TO who currently owns resolution of the issue STATUS current status of the issue (typical values are open or closed ) ACTION PLAN detailed description of actions (including dates and owners) required resolving the issue. Once the issue has been formally documented, it will be assigned to an owner who will be responsible for resolving the issue. Final Financial PMP Issue Management Page 16 of 61

21 The impact on schedules and costs will be estimated for each solution and any recommendations made for a solution will be documented in the Issue Log. Recommendations will be reviewed at progress meetings and Change Request Forms created a scope change is required. Issues will be transferred to Problem Reports if changes to documentation or software are required as a result of issue resolution. If change control is required then the Issue Form will be submitted for background information as part of the Change Control process. If the issue can be resolved without impacting contractual obligations then the Project Manager will sign-off the Issue Log. If no action is taken this fact must be clearly indicated in the Risk and Issue Log. If an issue cannot be resolved, it must be escalated to senior management for resolution. NOTE: A best practice is to discuss open issues in project status meetings, including executive steering committee meeting, and to make an effort to put a hard closure on. Final Financial PMP Issue Management Page 17 of 61

22 Risk Management The risks to project success were evaluated during the proposal development and updated in the earlier scope section in this document. To manage the risks that arise during the project, a Risk Management Strategy will be implemented. Purpose Risk Management is a structured process for identifying, documenting, tracking and mitigating the negative impact and maximizing the positive impact of project risks throughout the lifecycle of the project. The goal of risk management is the reduction of probability and severity of risk on the project. A Risk is viewed in two dimensions: Risk Probability - the likelihood that a certain risk will negatively affect a project Risk Impact - the anticipated monetary cost of if the risk occurs Risk Management Approach This strategy must include details for Identifying and logging risks Prioritizing risks, including establishing clear guidelines and definitions for discrete risk priorities (e.g. showstopper/executive, high, medium, low, etc.) Assigning risks to person(s) responsible for performing impact analysis as required Tracking and reporting risks status (e.g. probability, impact, mitigation, planned response, symptoms, etc.) A structured management process including the following components: Risk identification Risk analysis Risk prioritization Risk mitigation Risk response Final Financial PMP Risk Management Page 18 of 61

23 Procedure Risks can be raised by any project stakeholder, including project team members, third-party integrators, or vendors. Complex Risks will be recorded in detail on a Risk and Issue Form. Risks will be entered into a Risk Management System and categorized by type and priority. A Risk response will be developed for the risk and a Risk owner will be assigned. The following information will be captured and tracked for all Risks: RISK ID - each risk should have a unique ID SUBMITTED BY person and/or organization who raised the risk DATE SUBMITTED date the risk was recorded in the risks tracking system IMPACT impact to the project and/or business in terms of money, time, and/or quality APPLICATION/FLOW/MODULE if applicable, the name of the application, flow, or module to which the risk pertains TYPE type of risk (e.g. technical, process, organizational, etc.) TITLE short description of the risk (usually a few words or a sentence, helpful when reporting risks) DESCRIPTION complete description of the risk, the more details the better PROBABILITY indicate the probability of the risk SEVERITY risk severity (typically values could be critical, high, medium, low ) ESCALATION current escalation level and anticipated date and level of next escalation TARGET DATE target date for closure review of this risk ASSIGNED TO who currently owns mitigation of the risk STATUS current status of the risk (typical values are open or closed ) RISK RESPONSE PLAN detailed description of actions (including dates and owners) required to respond to the risk s occurrence. ESTIMATED RESPONSE PLAN DATE date that a response plan for the risk is expected to be in place Once the Risk has been formally documented, it s assigned to an owner for monitoring the Risk. Control risks according to the documented response plan for each risk and closely monitor risks paying close attention to symptoms that may indicate risks are Final Financial PMP Risk Management Page 19 of 61

24 beginning to occur. As symptoms and/or risks occur, implement the agreed upon response plans. Conduct regular risk assessments that include these steps as needed: Revisit risks defined at Project Start and include new risks as appropriate Categorize, assess and analyze the probability and severity of each risk Determine symptoms that would indicate that risks may be occurring Prepare a mitigation and response plan for each risk If change control is required then the Risk Form will be submitted for background information as part of the Change Control process. Note: A best practice is to discuss Risks and the response plans in project status meetings, including executive steering committee meetings. Final Financial PMP Risk Management Page 20 of 61

25 Problem Management A problem will normally need to be tracked in order to monitor its status and whether or not it has been resolved or is still outstanding. This might include problems found with documentation, software or during testing. Problems are distinguished from issues in that they apply to real or perceived deficiencies in deliverables of this project. Once remedied, the problem needs to be monitored so as to ensure that it doesn t reoccur. Purpose Problem Management is a structured process for identifying, documenting, tracking and resolving problems as they occur throughout the lifecycle of a project. Problem Management Approach This strategy must include details for Identifying and logging problems Prioritizing problems by severity level, including establishing clear guidelines and definitions for discrete problem severity levels (e.g. showstopper/executive, high, medium, low, etc.) Assigning problems to person(s) responsible for owning the solution and for performing impact analysis as required Tracking and reporting problems status (e.g. problem aging, open/closed status, solution status, etc.) Escalating problems including how long does the problem stay at one level before it is escalated to the next level up to the executive committee The intended result is a minimal backlog of unresolved problems, thus providing the lowest practical impact to the project. Procedure Problems can be raised by any project stakeholder, including project team members, third-party integrators, or vendors. Complex problems will be recorded in detail on a Problem Report Form. Problems should be entered on the Problem Log and categorized by type and priority, and an estimated closure date should be assigned. The Project Manager will investigate the problem and, if necessary, will update the Problem Log with background information to place the problem in perspective. At a minimum, the following information should be captured and tracked for all problems: Final Financial PMP Problem Management Page 21 of 61

26 PROBLEM ID - each problem should have a unique ID SUBMITTED BY person and/or organization who raised the problem DATE SUBMITTED date the problem was recorded in the Problems tracking system ESTIMATED ACTION DATE date the next action is expected on this problem IMPACT impact to the project and/or business in terms of money, time, and/or quality APPLICATION/FLOW/MODULE if applicable, the name of the application, flow, or module to which the problem pertains TYPE type of problem (e.g. application, technical, process, organizational, etc.) TITLE short description of the problem (usually a few words or a sentence, helpful when reporting problems) DESCRIPTION complete description of the problem, the more details the better SEVERITY problem priority (typically values could be critical, high, medium, low ) ESCALATION current escalation level and anticipated date and level of next escalation TARGET DATE target date for resolution ASSIGNED TO who currently owns resolution of the problem STATUS current status of the problem (typical values are open or closed ) ACTION PLAN detailed description of actions (including dates and owners) required resolving the problem. Once the problem has been formally documented, it s assigned to an owner for resolving the problem. The impact on schedules and costs will be estimated for each solution and any recommendations made for a solution will be documented in the Problem Log. Recommendations will be reviewed at progress meetings and Change Request Forms created if FAMU authorization is required. If change control is required then the Problem Report Form will be submitted for background information as part of the Change Control process. If the problem can be resolved without impacting contractual obligations then the Project Manager will sign-off the Problem Log. Final Financial PMP Problem Management Page 22 of 61

27 If no action is taken this fact must be clearly indicated in the Problem Log. If a problem cannot be resolved, it must be escalated to senior management for resolution. NOTE: A best practice is to discuss open problems in project status meetings, including executive steering committee meeting, and to make an effort to put a hard closure on lingering problems. Final Financial PMP Problem Management Page 23 of 61

28 Organization and Staff Management Purpose The Organization and Staff Management Plan provides the project with the right level of staffing and skills and the right environments to support them. Strategy The Organization and Staff Management Plan needs to address the Human Resource component of the project for the entire organization not just the internal project team. (E.g. sponsors, key stakeholders, support personnel, etc.) The plan must include processes to: Evaluate the skills required to deliver the project (within the agreed upon scope) Develop a project plan translating those skills into project roles and mapping those roles to specific tasks in the plan Source, select, and schedule qualified individuals to fill the agreed upon project roles Organize the resources into a cohesive team with assigned roles and responsibilities, and given the tools and information required to perform their assigned tasks Conduct team member orientation Develop methods of effective team building Develop methods to smoothly transition project resources The Project Team Name Role FAMU Robert Seniors Teresa Hardee Veronica Stokes Matthew Gaines Isaac Robinson Stephany Fall Mark Hinchee Project Sponsor Project Director Project Coordinator & AR/BI Lead Technical Lead Payables/Expenses Lead Purchasing/ePro Lead Asset Management/Project Costing Final Financial PMP Organization and Staff Management Page 24 of 61

29 Palmyra Williams Sheila Wesley OC KC Bacher Carl Paroby Vickie Martin Suresh Pandurangam Chester Chu Lead General Ledger Lead Contracts/Grants (AR/BI) Lead Project Sponsor Project Director AR/BI/AP/PO/ePro/Exp/Contracts/ AM Lead GL/KK/PC Lead Grants Lead Project Roles and Responsibilities Executive Sponsor The Executive Sponsor is responsible for : Providing vision and strategic intent Driving executive education, decision-making, and is the highest level for issues escalation and resolution Ensuring support for change at executive level through senior management updates and board presentation Owning the project budget, develop the business case and validate the benefits. Driving the project to successful completion Championing the business case for change, including gaining the support of, or overcoming resistance from, the business partners. Ensuring project benefits are achieved Resolving major issues around scope, budget, timelines, and risks, and keep appropriate councils and business partners apprised. Ensuring monthly status reports accurately reflect project status, risks and open issues. Executive Sponsorship directives include: Assisting FAMU in providing leadership to the project by guiding decision-making and issue resolution. Attending and actively participate in Executive Steering Committee Project Committee, and Project Leadership meetings. Facilitating collaboration with the project leadership team and business partners Ensuring appropriate alignment and integration of technology, business process, organization and control. Identifying and managing all product-related training requirements for FAMU staff Final Financial PMP Organization and Staff Management Page 25 of 61

30 Representing FAMU in meetings with vendors and other representatives associated or involved with the implementation Providing the principal point of contact between FAMU and OC Preparing and delivering regular reports on the project progress and outstanding issues Encouraging the transfer of product knowledge and skills to the appropriate staff within the organization Project Director The FAMU and OC Project Director are responsible for: Developing project plans Assigning tasks to other project personnel Monitoring staff and project Managing risks and escalated issues from project teams Controlling budgets, scheduling resources, and recommending implementation approaches Assuming overall responsibility for the successful conclusion of the project Measuring project success against budget, original scope, business objectives FAMU and OC Project Management directives include: Assisting FAMU in the timely implementation of PeopleSoft Financials Applications Assuming responsibility for planning resource requirements and coordinating the daily tasks of all project team members in conjunction with contract resources Ensuring that all resources and their respective skills are optimally utilized Providing quality assurance of work undertaken by staff assigned to the project Identifying and managing all product-related training requirements for FAMU staff Representing FAMU in meetings with vendors and other representatives associated or involved with the implementation Providing the principal point of contact between FAMU and OC Preparing and delivering regular reports on the project progress and outstanding issues Encouraging the transfer of product knowledge and skills to the appropriate staff within the organization Ensuring project methodology and deliverables align with corporate standards. Final Financial PMP Organization and Staff Management Page 26 of 61

31 Overseeing project delivery, schedule, and quality. Taking responsibility for the overall project budget Developing project financial variance analysis and budget reporting Maintaining project plan using Microsoft Project Overseeing project plan weekly update cycle Coordinating project plan administration with FAMU Taking responsibility for the expense management process Team Leader / Application Product Specialist The FAMU and OC Team Leaders are responsible for: Managing tasks for a specific process, functional or application area Monitoring and reporting the progress Advising, guiding, and supporting the project team on the use, implementation, and maintenance of PeopleSoft Applications Ensuring that FAMU derives the maximum benefits from the application products Completing tasks and deliverables assigned by the project manager Keeping the project manager informed of progress and issues in a timely manner Advising and assisting in the development of a generic model Evaluating specific requirements and recommending how each can be incorporated in the generic model Identifying feasible alternative solutions that minimize the need for custom development Reviewing existing work practices in order to recommend modifications or enhancements that enable the company to derive maximum benefits from the products Identifying any external data requirements and defining phased data load and validation procedures Assisting with the specification of representative data sets and business scenarios for acceptance testing Transferring the appropriate business and technical skills to other project team members The individuals who fulfill this role are likely to have the following qualifications: Accounting Systems background Thorough understanding of the applications Experience in implementing application systems In general, the assigned persons will be responsible for tasks requiring specific skill sets. When FAMU resources change, the FAMU Project Director will ensure that these project team members transfer sufficient knowledge and ensure that coverage exists for any outstanding assignments. If resource changes occur within the OC Final Financial PMP Organization and Staff Management Page 27 of 61

32 staff, the Project Director will use the same approach to maintain continuity and avoid unnecessary delays in progress. Some tasks will require representation from various FAMU functional areas. FAMU will provide all necessary resources to support these tasks. Technical Team The FAMU Technical Team is responsible for: Integration Strategy Information Delivery (Reports) Strategy Technical Designs for Reports, Interfaces, and Extensions Updated Master Test Plan and Phase Test Plans Unit Tested Reports, Interfaces, and Extensions System Tested Reports, Interfaces, and Extensions Integration Tested Reports, Interfaces, and Extensions UAT Reports, Interfaces, and Extensions Installed production-ready software Functional Specification Reviews Infrastructure stabilization (testing and shakeout of multiple environments) Technical Team Lead has to: Ensure that all business requirement are supported by developed software Understand project vision, goals, and lead the software development activities Guide decision making and issue resolution - point of escalation for the project Development team Ensure proper developments methods and standards are defined and adhered to. Participate on the program leadership team by attending meetings and elevating / resolving issues Manage the Development team resources, providing overall leadership and motivating team members. Own the integrated work-plan and budget for development team activities. Partner with the Infrastructure, Architecture, Business Process/Application Delivery, and Change Management Leads to ensure smooth delivery Test Lead The Test Team is responsible for: Master Test Plan Final Financial PMP Organization and Staff Management Page 28 of 61

33 Create Phase Test Plans Test Data Management and Strategy Integration Application, Reports, Interfaces, and Extension components User Acceptance test of Application, Reports, Interfaces, and Extension components Regression Test Tracking Defects and Reporting Coordinate creation of Secured Integration and User Acceptance Test environments Coordinate test activities in System Test, Integration Test and User Acceptance Test environments Manage and schedule test planning and test execution activities for matrix resources Identify components of Test Cycles in System Test, Integration Test and User Acceptance Test Test Status updates to Leadership Team Recommend and implement best practice test solution and processes Adhere to IT Standard Test Process methodology Review and Approve of Test Process Scripts and Business Scenarios Ensure the product delivered is of absolute highest quality Understand project vision, goals, and lead the test activities Direct the test work effort, striving to optimize efficiency and costs Guide decision making and issue resolution point of escalation for the project Test team Ensure proper test methods and standards are defined and adhere to the IT Standard Test Process Participate on the program leadership team by attending meetings and elevating / resolving issues Manage the Test team resources, providing overall leadership and motivating team members Partner with the Infrastructure, Architecture, Business Process/Application Delivery, Change Management and Development Leads to ensure smooth delivery Applications Solution Center Team / FAMU DBAs, Unix Administrators (Platform Support) and Firewall Support The FAMU and IBM Infrastructure Teams are responsible for: Test and Production Environments Performance and Stress testing Physical Test and Production Instances Operational and Support Documentation Final Financial PMP Organization and Staff Management Page 29 of 61

34 System Cutover Manage the infrastructure resources and deliverables Own the work plan and budget for the infrastructure team activities Overseeing the deployment of the various systems environments Own the development of the instance/environment strategy Responsible for overseeing the deployment of the various systems environments Database Administration support for PeopleSoft instances Responsible for overseeing the deployment of the various systems environments Design, Build and Maintain project technical infrastructure Education and Training The staff members working on this project are all suitably qualified in terms of background, experience, and training in the tasks to be undertaken, with the following exceptions that will be catered to during the course of the project as defined below and monitored in the associated Staff Training Plan: FAMU Staff Training needs XML Publisher System Administration PeopleSoft Financials OC Staff Training needs None Final Financial PMP Organization and Staff Management Page 30 of 61

Template K Implementation Requirements Instructions for RFP Response RFP #

Template K Implementation Requirements Instructions for RFP Response RFP # Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship

More information

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

Request for Proposal for Application Development and Maintenance Services for XML Store platforms

Request for Proposal for Application Development and Maintenance Services for XML Store platforms Request for Proposal for Application Development and Maintenance s for ML Store platforms Annex 4: Application Development & Maintenance Requirements Description TABLE OF CONTENTS Page 1 1.0 s Overview...

More information

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

Project Management Guidelines

Project Management Guidelines Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.

More information

How To Write An Slcm Project Plan

How To Write An Slcm Project Plan SLCM 2003.1 Artifacts in a Nutshell ( as of 01/21/2005) Project Development Phases Pension Benefit Guaranty Corporation s (PBGC) System Life Cycle Methodology (SLCM) is comprised of five project development

More information

Colorado Department of Health Care Policy and Financing

Colorado Department of Health Care Policy and Financing Colorado Department of Health Care Policy and Financing Solicitation #: HCPFRFPCW14BIDM Business Intelligence and Data Management Services (BIDM) Appendix B BIDM Project Phases Tables The guidelines for

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

Crosswalk Between Current and New PMP Task Classifications

Crosswalk Between Current and New PMP Task Classifications Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the

More information

Assessing the Appropriate Level of Project, Program, and PMO Structure

Assessing the Appropriate Level of Project, Program, and PMO Structure PMI Virtual Library 2011 Daniel D. Magruder Assessing the Appropriate Level of Project, Program, and PMO Structure By Daniel D. Magruder, PMP Executive Summary Does your organization have in-flight projects

More information

Project Charter and Scope Statement

Project Charter and Scope Statement Prepared by: Mike Schmidt Version: 1.0 Last Revision Date: April 14, 2010 Create Date: May 6, 2010 EXECUTIVE SUMMARY... 3 1 INTRODUCTION... 4 2 PROJECT OBJECTIVES... 4 2.1 MISSION... 4 2.2 OBJECTIVES...

More information

Development, Acquisition, Implementation, and Maintenance of Application Systems

Development, Acquisition, Implementation, and Maintenance of Application Systems Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of

More information

Cisco Unified Communications and Collaboration technology is changing the way we go about the business of the University.

Cisco Unified Communications and Collaboration technology is changing the way we go about the business of the University. Data Sheet Cisco Optimization s Optimize Your Solution using Cisco Expertise and Leading Practices Optimizing Your Business Architecture Today, enabling business innovation and agility is about being able

More information

SAP ERP Upgrade Checklist Project Preparation

SAP ERP Upgrade Checklist Project Preparation A SAP ERP Upgrade Checklist Project Preparation Upgrade Project Phase Project Preparation Definition From the project perspective the project preparation phase includes: Learning about the new functionality

More information

Department of Administration Portfolio Management System 1.3 June 30, 2010

Department of Administration Portfolio Management System 1.3 June 30, 2010 E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2

More information

Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview

Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program

More information

PHASE 8: IMPLEMENTATION PHASE

PHASE 8: IMPLEMENTATION PHASE PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the

More information

Appeals Case Management System Project. Scope Management Plan. November 20, 2014

Appeals Case Management System Project. Scope Management Plan. November 20, 2014 Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF

More information

CDC UNIFIED PROCESS JOB AID

CDC UNIFIED PROCESS JOB AID CDC UNIFIED PROCESS JOB AID Independent Verification & Validation Activities Document Purpose This Job Aid is a brief document listing the items to be noted, checked, remembered, and delivered when completing

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam 44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION

More information

Oracle RAC Services Appendix

Oracle RAC Services Appendix 1 Overview Oracle RAC Services Appendix As usage of the Blackboard Academic Suite grows and the system reaches a mission critical level, customers must evaluate the overall effectiveness, stability and

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11

More information

Project Implementation Process (PIP)

Project Implementation Process (PIP) Vanderbilt University Medical Center Project Implementation Process (PIP).......... Project Implementation Process OVERVIEW...4 PROJECT PLANNING PHASE...5 PHASE PURPOSE... 5 TASK: TRANSITION FROM PEP TO

More information

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)?

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? Due to the often complex and risky nature of projects, many organizations experience pressure for consistency in strategy, communication,

More information

Project Knowledge Areas

Project Knowledge Areas From Houston S: The Project Manager s Guide to Health Information Technology Implementation. Chicago: HIMSS; 2011; pp 27 39. This book is available on the HIMSS online bookstore at www. himss.org/store.

More information

Project Management Guidelines

Project Management Guidelines Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of

More information

Oracle Fixed Scope Services Definitions Effective Date: October 14, 2011

Oracle Fixed Scope Services Definitions Effective Date: October 14, 2011 Oracle Fixed Scope Services Definitions Effective Date: October 14, 2011 "You" and "your" refers to the individual or entity that has ordered Advanced Customer Services from Oracle or an authorized distributor.

More information

How To Develop An Enterprise Architecture

How To Develop An Enterprise Architecture OSI Solution Architecture Framework Enterprise Service Center April 2008 California Health and Human Services Agency Revision History REVISION HISTORY REVISION/WORKSITE # DATE OF RELEASE OWNER SUMMARY

More information

Project Lifecycle Management (PLM)

Project Lifecycle Management (PLM) Project Lifecycle Management (PLM) Process or Tool? Why PLM? Project Definition Project Management NEW REQUEST/ INITIATIVES SUPPORT (Quick fixes) PROJECT (Start Finish) ONGOING WORK (Continuous) ENHANCEMENTS

More information

Information Technology Services Project Management Office Operations Guide

Information Technology Services Project Management Office Operations Guide Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...

More information

Understand why, when and how-to to formally close a project

Understand why, when and how-to to formally close a project Project Closure Purpose: Understand why, when and how-to to formally close a project Audience: Project managers, project sponsors, team members and other key stakeholders Learning Objectives: Describe

More information

IT Project: System Implementation Project Template Description

IT Project: System Implementation Project Template Description 2929 Campus Drive Suite 250 IT Project: System Implementation Project Template Description Table of Contents Introduction... 2 Project Phases... 3 Initiation & Requirements Gathering Milestone... 3 Initiation

More information

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010 Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning

More information

Project Management Methodology

Project Management Methodology Project Management Methodology 1/6/2015 PAGE 1 OF 28 Version 2.0 Contents INTRODUCTION... 4 1. Overview... 4 PHASE 1 PROJECT INITIATION... 5 1. Governance Model... 6 2. Project Prioritization Process...

More information

How To Write A Project Management Plan

How To Write A Project Management Plan Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents

More information

PHASE 6: DEVELOPMENT PHASE

PHASE 6: DEVELOPMENT PHASE PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

Appendix 2-A. Application and System Development Requirements

Appendix 2-A. Application and System Development Requirements Appendix 2-A. Application and System Development Requirements Introduction AHRQ has set up a Distributed Systems Engineering Lab (DSEL) to support all internal development efforts and provide a facility

More information

Introduction to the ITS Project Management Methodology

Introduction to the ITS Project Management Methodology Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer

More information

PHASE 6: DEVELOPMENT PHASE

PHASE 6: DEVELOPMENT PHASE PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product

More information

Business Continuity Position Description

Business Continuity Position Description Position Description February 9, 2015 Position Description February 9, 2015 Page i Table of Contents General Characteristics... 2 Career Path... 3 Explanation of Proficiency Level Definitions... 8 Summary

More information

ATTACHMENT II - WRITTEN PROPOSAL RESPONSE AND GUIDELINES

ATTACHMENT II - WRITTEN PROPOSAL RESPONSE AND GUIDELINES ATTACHMENT II - WRITTEN PROPOSAL RESPONSE AND GUIDELINES RFP#CON2014-18 Attachments I through VI from the Response Teams will be evaluated and scored (1000 points total) in accordance with the criteria

More information

Fixed Scope Offering for. Oracle Taleo EE Saas Implementation

Fixed Scope Offering for. Oracle Taleo EE Saas Implementation Fixed Scope Offering for Oracle Taleo EE Saas Implementation Agenda Company Profile Business Challenges Business Objectives Solution Proposal Scope Modules and Functionalities Implementation Approach Project

More information

INTRODUCTION. Page 1 of 16

INTRODUCTION. Page 1 of 16 INTRODUCTION CALIFORNIA STATE TEACHERS RETIREMENT SYSTEM REQUEST FOR QUOTE JAMA LICENSING AND SERVICES RFQ NUMBER 201204 Offer Due Date: July 23, 2013, 2:00 p.m. Pacific Time (PT) The California State

More information

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES 1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through

More information

Implementation of PeopleSoft 8.9

Implementation of PeopleSoft 8.9 Implementation of PeopleSoft 8.9 Implementation of any ERP product is a huge effort considering the generic nature of the product and specific customer requirements. In addition the industry specific and

More information

Systems Programmer/Analyst (12203) (31002632)

Systems Programmer/Analyst (12203) (31002632) GENERAL DESCRIPTION OF WORK Positions in this banded class perform specialized work in supporting information technology equipment and systems for the business, research, and instructional functions of

More information

Capacity Plan. Template. Version X.x October 11, 2012

Capacity Plan. Template. Version X.x October 11, 2012 Template Version X.x October 11, 2012 This is an integral part of infrastructure and deployment planning. It supports the goal of optimum provisioning of resources and services by aligning them to business

More information

LEXEVS OPERATIONS AND MAINTENCE SUPPORT PROJECT MANAGEMENT PLAN

LEXEVS OPERATIONS AND MAINTENCE SUPPORT PROJECT MANAGEMENT PLAN LEXEVS OPERATIONS AND MAINTENCE SUPPORT PROJECT MANAGEMENT PLAN Version Number: 1.0 Version Date: October 1, 2014 VERSION HISTORY Version Number Implemented By Revision Date Approved By Approval Date 1.0

More information

SCHEDULE 3. Milestones and Deliverables. Redacted Version

SCHEDULE 3. Milestones and Deliverables. Redacted Version SCHEDULE 3 Milestones and Deliverables Redacted Version This Schedule 3 sets out the Service Provider s obligations in respect of the milestones and deliverables relating to the implementation and operation

More information

Clinical Risk Management: Agile Development Implementation Guidance

Clinical Risk Management: Agile Development Implementation Guidance Document filename: Directorate / Programme Document Reference NPFIT-FNT-TO-TOCLNSA-1306.02 CRM Agile Development Implementation Guidance v1.0 Solution Design Standards and Assurance Project Clinical Risk

More information

InForm On Demand Single Trial Services Description

InForm On Demand Single Trial Services Description InForm On Demand Single Trial Services Description Version 7.0 Effective Date: 0 25-Sep-2014 This is the Services Description for Oracle InForm On Demand Single Trial ( Schedule ) to Your Study Order for

More information

An Oracle White Paper Updated July 2011. Best Practices for Upgrading Oracle E-E-E- E-Business Suite

An Oracle White Paper Updated July 2011. Best Practices for Upgrading Oracle E-E-E- E-Business Suite An Oracle White Paper Updated July 2011 Best Practices for Upgrading Oracle E-E-E- E-Business Suite Best Practices for Upgrading Oracle E-Business Suite Introduction... 3 Upgrade Overview... 4 The Upgrade

More information

Request for Proposal for implementation of SAP HANA ERP System at MCL, ZAMBIA

Request for Proposal for implementation of SAP HANA ERP System at MCL, ZAMBIA Request for Proposal for implementation of SAP HANA ERP System at MCL, ZAMBIA RFP No. MCL/ZM/IT/001 Date of Issue: 10 th September, 2015 Last date of submission: 17 th October, 2015 Place of Submission:

More information

Framework. 3/3/2011 By Karla Campbell Project Manager PMP Certificated UCOP

Framework. 3/3/2011 By Karla Campbell Project Manager PMP Certificated UCOP PROJECT MANAGEMENT Framework 3/3/2011 By Karla Campbell Project Manager PMP Certificated UCOP Topics 1. Benefits Of Project Management 2. Definitions 3. Roles 4. Project Process Groups 5. Best Practices

More information

Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:

Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute

More information

Fixed Scope Offering for Oracle Fusion HCM. Slide 1

Fixed Scope Offering for Oracle Fusion HCM. Slide 1 Fixed Scope Offering for Oracle Fusion HCM Slide 1 Today s Business Challenges Adopt leading Global HCM practices. Streamline the HCM processes and achieve measurable efficiencies. Achieve HR excellence

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

PHASE 9: OPERATIONS AND MAINTENANCE PHASE

PHASE 9: OPERATIONS AND MAINTENANCE PHASE PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

Project, Program & Portfolio Management Help Leading Firms Deliver Value

Project, Program & Portfolio Management Help Leading Firms Deliver Value in collaboration with Project, Program & Portfolio Help Leading Firms Deliver Value Managing Effectively & Efficiently Through an Enterprise PMO Program & Portfolio : Aligning IT Capabilities with Business

More information

Organization. Project Name. Project Overview Plan Version # Date

Organization. Project Name. Project Overview Plan Version # Date Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents

More information

Integrating Project Management and Service Management

Integrating Project Management and Service Management Integrating Project and Integrating Project and By Reg Lo with contributions from Michael Robinson. 1 Introduction Project has become a well recognized management discipline within IT. is also becoming

More information

Project Management Change Management Procedure

Project Management Change Management Procedure Change Management Procedure Procedure # Description: Overview Outlines the steps for a Project Manager to manage change in an organization Objective To ensure that organizational change is managed in a

More information

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1

More information

Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing

Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing STATE OF MICHIGAN SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing Executive Summary The State of Michigan has dedicated integrated team of resources for the

More information

PHASE 5: DESIGN PHASE

PHASE 5: DESIGN PHASE PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed

More information

Microsoft Dynamics Sure Step 2012 Supplementary Training Material Version 5.0

Microsoft Dynamics Sure Step 2012 Supplementary Training Material Version 5.0 Microsoft Dynamics Sure Step 2012 Supplementary Training Material Version 5.0 www.firebrandtraining.com Course content Module 0 Course Content and Plan... 7 Objectives... 7 Course Plan... 7 Course Modules...

More information

PROPOSAL XXX INFRASTRUCTURE MIGRATION PROJECT (RFP 20XX.XX.XX)

PROPOSAL XXX INFRASTRUCTURE MIGRATION PROJECT (RFP 20XX.XX.XX) PROPOSAL XXX INFRASTRUCTURE MIGRATION PROJECT (RFP 20XX.XX.XX) PREPARED FOR: CLIENT Address City, Province / State, Index Contact: Name, Title PREPARED BY: VIMEX TECHNOLOGIES 604-126 West 3 rd Street North

More information

PMP Examination Tasks Puzzle game

PMP Examination Tasks Puzzle game PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in

More information

Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions

Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions Today s Business Challenges Adopt leading CRM practices and stream line processes Take advantage

More information

A Systems Implementation Project Planning Guide. Solutions & Project Management Services for Systems & Operations Projects

A Systems Implementation Project Planning Guide. Solutions & Project Management Services for Systems & Operations Projects A Systems Implementation Project Planning Guide Solutions & Project Management Services for Systems & Operations Projects Business Requirements Analysis Overview Project Plan High-Level Detailed Design

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,

More information

VoteCal Statewide Voter Registration System Project. Master Project Management Plan. Version 1.2

VoteCal Statewide Voter Registration System Project. Master Project Management Plan. Version 1.2 VoteCal Statewide Voter Registration System Project Master Project Management Plan Version 1.2 October 2010 October 2010 i REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF CHANGES 0.1 3/12/2009

More information

Risk management and the transition of projects to business as usual

Risk management and the transition of projects to business as usual Advisory Risk management and the transition of projects to business as usual Financial Services kpmg.com 2 Risk Management and the Transition of Projects to Business as Usual Introduction Today s banks,

More information

PROJECT CHARTER GUIDE

PROJECT CHARTER GUIDE Treasury Board of Canada Secretariat Secrétariat du Conseil du Trésor du Canada Enhanced Management Framework for Information Technology PROJECT CHARTER GUIDE February 1999 Chief Information Officer Branch

More information

IT Project Management Methodology. Project Scope Management Support Guide

IT Project Management Methodology. Project Scope Management Support Guide NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald

More information

Driving Excellence in Implementation and Beyond The Underlying Quality Principles

Driving Excellence in Implementation and Beyond The Underlying Quality Principles SAP Thought Leadership Paper SAP Active Quality Management Driving Excellence in Implementation and Beyond The Underlying Quality Principles 2014 SAP AG or an SAP affiliate company. All rights reserved.

More information

How To Implement An Enterprise Resource Planning Program

How To Implement An Enterprise Resource Planning Program ERP Implementation Program Key phases of ERP implementation: Analysis of the company existing or designing new business process descriptions Inventory of the company s existing formal workflows or designing

More information

PROJECT CHARTER University of Tennessee

PROJECT CHARTER University of Tennessee PROJECT CHARTER University of Tennessee Table of Contents 1 Introduction 1.1 Overview 1.2 Statement of Work Conflicts 1.3 Project Objectives 1.4 Benefits 1.5 Project Assumptions and Constraints 2 Scope

More information

Program Management Professional (PgMP) Examination Content Outline

Program Management Professional (PgMP) Examination Content Outline Program Management Professional (PgMP) Examination Content Outline Project Management Institute Program Management Professional (PgMP ) Examination Content Outline April 2011 Published by: Project Management

More information

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 - ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and

More information

CUSTOMER GUIDE. Support Services

CUSTOMER GUIDE. Support Services CUSTOMER GUIDE Support Services Table of Contents Nexenta Support Overview... 4 Support Contract Levels... 4 Support terminology... 5 Support Services Provided... 6 Technical Account Manager (TAM)... 6

More information

COST/FUNDING SOURCE: $549,050/FY2014 and FY2015 Uniform Rate

COST/FUNDING SOURCE: $549,050/FY2014 and FY2015 Uniform Rate AGENDA ITEM C3 DATE: April 7, 2014 TO: FROM: SUBJECT: Matt Jordan, General Manager Charles H. Carden, Chief Operating Officer Computerized Maintenance Management System Implementation Services Award Contract

More information

Program and Budget Committee

Program and Budget Committee E WO/PBC/21/12 ORIGINAL: ENGLISH DATE: JULY 1, 2013 Program and Budget Committee Twenty-First Session Geneva, September 9 to 13, 2013 PROGRESS REPORT ON THE IMPLEMENTATION OF A COMPREHENSIVE INTEGRATED

More information

CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS

CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS Chapter 3: Managing Implementation Projects CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS Objectives Introduction The objectives are: Describe common problems that occur in implementation projects. Describe

More information

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO

More information

Earned Value Management for Enterprise Resource Planning Implementations

Earned Value Management for Enterprise Resource Planning Implementations Earned Value Management for Enterprise Resource Planning Implementations Venu Kotamraju Abstract ERP implementations are a special breed of projects. They are often characterized by aggressive timelines,

More information

Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit

Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit Internal Audit Report Toll Operations Contract Management TxDOT Office of Internal Audit Objective To determine whether the Toll Operations Division (TOD) contract management structure is designed and

More information

Table of Contents. Page 1 of 39

Table of Contents. Page 1 of 39 Oracle Health Sciences InForm Cloud Services Service Descriptions and Metrics June 18, 2015 Table of Contents Metric Definitions... 2 Customer... 2 Instance... 2 Patient... 2 Site... 2 Trial... 2 Service

More information

INFORMATION TECHNOLOGY PROJECT REQUESTS

INFORMATION TECHNOLOGY PROJECT REQUESTS INFORMATION TECHNOLOGY PROJECT REQUESTS Guidelines & Instructions for Maryland State Agencies Revised Two Step PPR/PIR Approval Process Fiscal Year 2013 Table of Contents Part 1: Overview... 2 1.1 Introduction...

More information

COMMUNICATION MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

COMMUNICATION MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: COMMUNICATION MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Document Information Document Title Amendment History Document Version Date Author/Reviewer Modifications 5/28/2014 Page i 2014 CSG

More information

Eastern Illinois University EISE Configuration Management Plan

Eastern Illinois University EISE Configuration Management Plan Eastern Illinois University EISE Configuration Management Prepared by: Bill Witsman Version: 10.0 Create Date: April 13, 2005 Approval Date: Last Revision Date: December 17, 2009 CM Analyst: Project Manager:

More information

Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt. Programme, Project & Service Management Analysis

Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt. Programme, Project & Service Management Analysis Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt Programme, Project & Service Management Analysis Table of Content 1 Executive Summary... 3 1.1 Scope of Work... 3 1.2 Methodology for

More information

1 Project Management Methodology

1 Project Management Methodology 1 Artech s is intended to promote the delivery of quality products that meet customers needs and results in projects that are completed on time and within budget The objective of the methodology is to

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

How To Build A New System For A College

How To Build A New System For A College Application Development Methodology The main objective of Enterprise Applications is to design, develop, and maintain quality software. This document out lines the requirements for requesting new systems,

More information

Construction Management System (CMS) Deliverable Review Process

Construction Management System (CMS) Deliverable Review Process Construction Management System (CMS) Deliverable Review Process State of California Department of Transportation Division of Construction December 21, 2009 Version 1.0 Approvals Name: Title: Mark Leja

More information