1 Motorist Modernization Project Phase One For Period: January March 2015
2 Quarter Ending: 3/31/2015 Agency Name: Department of Highway Safety & Motor Vehicles (HSMV) Project Name: Motorist Modernization Project Phase One Project Description: The intent of the Motorist Modernization Project is to re-engineer and re-develop HSMV s legacy motorist information systems and infrastructure to better serve and support its customers, mitigate risks, and provide improved functionality over time. The Motorist Modernization project is comprised of three phases. The current phase, Phase One, focuses on creating a customer-centric data model with controls to support data quality. This includes establishing data governance, developing a new Florida Driver License Information System (FDLIS), re-engineering the renewal notice process and developing applications to streamline this process, and re-engineering GoRenew.com. FY funds will be used for requirements gathering and documentation, project management, and Independent Verification and Validation (IV&V) activities. Project tasks completed between the project s November 1, 2013 start date and the February, 2015 onset of project execution work included development and analysis of a business case, initiation of project charter, an initial appropriation request, a feasibility study as directed, a follow-up analysis/response, and solicitations for support services and IV&V vendors. Section I: Executive Summary Executive Summary Scope: The project scope is within the acceptable variance range; scope is in line with the Motorist Modernization project s Schedule IV-B and other supporting documentation. Cost: The project costs exceed the acceptable variance range, and the project is under budget for the reporting period. This is primarily due to deliverable payments not yet made to Accenture for deliverables not yet received. Budgeted deliverable costs of $248, remain unpaid to Accenture for FY Quarter 3. All expected FY Quarter 3 EY expenditures have been realized. Schedule: The project exceeds the acceptable variance range for the reporting period in that 13 of 94 FY Quarter 3 project tasks are behind schedule as of March 31, Contract executions for the support services contractor (Accenture) and the IV&V contractor (Ernst & Young (EY)) were delayed. Three Accenture FY Quarter 3 deliverables were completed on schedule, and six Accenture deliverables are behind schedule. All EY FY Quarter 3 deliverables were completed on schedule. Risks and Issues: The project has identified risks and issues for the reporting period; however, they have remained stable. The program management office has insufficient resources for complete and timely management of this project, and deficiencies have been identified related to project governance, project management procedures and documents, and deliverable acceptance schedules. HSMV is proactively addressing risks and issues as they are identified. 5/19/2015 Page 2 Revision.08
3 Section II: Scope Scope Summary The project scope is within the acceptable variance range for the reporting period and is expected to remain in scope. Both Accenture and EY contracts include mutually-approved Scope of Work (SOW) documents that detail the contracted service planned deliverables and tasks for the Motorist Modernization Project for FY These scope descriptions are in line with the Motorist Modernization project s Schedule IV-B and other supporting documentation. The formal advisory board identified in the Program Management Plan for change management and other decisionmaking has not yet met but is expected to begin meeting in May of The requirements gathering and documentation required for the successful completion of this project are extensive and require significant attention to detail in order to mitigate (allowing for greater risk). Also, the impending departure of the Department s primary legacy system knowledge base and potentially incomplete system integration lists and business rules impose additional risk. This work is scheduled for completion by June 25, This project s success, and the success of future phases of work, will likely benefit from an extension of the requirements gathering process to ensure scope and quality are maintained. Accenture is currently submitting two weekly status reports; one report for the Support Services deliverable of the contract and one for the Driver License (DL) Issuance deliverable of the contract. Separate status reports may create inconsistent management and monitoring of scope and other elements by the program management office. The content within these status reports is minimal at best, with numerous sections displaying No Data Available ; status reports should include greater detail and should not include references to No Data Available. EY s weekly status reports are comprehensive. Scope Variance Discussion The project scope is within the acceptable variance range for the reporting period; scope is in line with the Motorist Modernization project s Schedule IV-B and other supporting documentation. 5/19/2015 Page 3 Revision.08
4 Section III: Cost Management Cost Management Summary The project costs exceed the acceptable variance range for the reporting period. The project is under budget for this reporting period. The project has a DHSMV approved FY Summary Spending Plan broken out by contracts, contract deliverables, spending plan months, and detailed descriptions. Contract management is structured with deliverable acceptance required prior to payment. The issues discussed in the Schedule Management Summary related to deliverables submissions and schedule delays are contributing to the project costs exceeding the acceptable variance range. Cost Variance Discussion The project costs exceed the acceptable variance range for the reporting period. The project is under budget primarily due to deliverable payments not yet made to Accenture for deliverables not yet received. Budgeted deliverable costs of $248, remain unpaid to Accenture for FY Quarter 3. All expected FY Quarter 3 EY expenditures have been realized. If this payment trend continues, it may result in the FY appropriated project budget not being expended in its entirety. 5/19/2015 Page 4 Revision.08
5 Section IV: Schedule Management Schedule Management Summary The project schedule exceeds the acceptable variance range for the reporting period. The project s HSMV-approved Master Schedule has been task and resource loaded, is cost loaded per deliverables, includes dependencies for this fiscal year, and includes additional tasks identified for upcoming fiscal years. The schedule is currently not set up to assess Earned Value; however, the program management office may benefit from incorporating costs at the resource level for this purpose. Additionally, the schedule does not currently include tasks/timeframes for deliverable reviews and acceptance. The program management office may benefit from including these additional data points. Additional tasks as identified by the contractors are currently being merged into the schedule for baseline approval. The program management office appears to be significantly understaffed potentially impacting the timeliness of deliverable reviews. The project s Program Management Plan includes limited reference to resource management and may benefit from a more formal Human Resources Management Plan in order to ensure the acquisition and management of all resources as needed for completion of the project. Contract executions for the support services contractor and IV&V contractor were delayed; deliverable deadlines were not re-adjusted at time of contract execution. Current deliverable deadlines for both vendor contracts are for submission of a deliverable and not for the approval or acceptance of that deliverable by HSMV. Significant schedule delays are already occurring in the project due to the extensive review and revision process following initial submissions. It may benefit the project to address mutuallyapproved language via contract change orders which stipulates that due dates/deadlines apply to HSMV program management office acceptance of each deliverable. This will also benefit cost management, as deliverable approvals and correlating spending would more likely occur within planned spending months. The requirements gathering and documentation required for the successful completion of this project is extensive and is currently scheduled for completion by June 25, The project s success, and the success of future phases of work, will likely benefit from an extension of the requirements gathering process to ensure a complete and accurate assessment of system requirements and specifications. Schedule Variance Discussion The project schedule exceeds the acceptable variance range for the reporting period. Thirteen (13) of 94 FY Quarter 3 project tasks (14%) are behind schedule. Three Accenture FY Quarter 3 deliverables were completed on schedule, and six Accenture deliverables are behind schedule. All EY FY Quarter 3 deliverables were completed on schedule. 5/19/2015 Page 5 Revision.08
6 Section V: Risk Assessment Evaluation of Project Risks and Issues Risks and issues remain stable for the reporting period. The Program Management Plan includes a risk and issue management plan which specifies that risks and issues shall be monitored within the HSMV program management office Project Portfolio Management tool (PPM). HSMV has implemented the Software-as-a-Service tool Daptiv for this purpose, and status reporting for the project is pulled from the Daptiv tool. The risk and issue management plan does not specify inclusion of an assignee or owner of the risk nor does it specify inclusion of a status of the issue or mitigation status of the risk. Discussion of project risks and issues is occurring weekly between the program management office staff and each of the contractors in status meetings. Risks and issues for this project are being managed independently per contractor using weekly status reports. Further, Accenture is currently providing two weekly status reports, each with separate risk and issue logs, for each of its current work efforts. Effective management of project risks in two or more separate logs requires sufficient program management office resourcing, especially as work becomes more technical and involved. Sufficient program management office resourcing has been noted as a deficiency for this project. Accenture status report risk logs do not include an assignee or owner of the risk, nor do they include a status of the issue or mitigation status of the risk. The program management office may benefit from implementing these requirements into status reporting pulled from Daptiv. Both the Accenture support services status report and Accenture DL Issuance status report, dated March 25, 2015, identify no issues and five risks. The risks include potentially no funding beyond this fiscal year, completion of requirements gathering and documentation within the project schedule, and potentially incomplete historical knowledge or incomplete inventories. EY risk and issue logs do not include an assignee or owner of the risk. The program management office may benefit from implementing this requirement into its status reporting. Risk Management Discussion Risks and issues are being monitored for this project, and areas for improvement have been noted. The program management office has insufficient resources for complete and timely management of this project and its risks and issues as they arise. HSMV is proactively addressing risks and issues as they are identified. 5/19/2015 Page 6 Revision.08
7 Document Version Control Version Date Change(s).03 4/15/2015 Original Draft.04 4/30/2015 Revisions per HSMV comments.05 5/5/2015 Final Revisions for AST Executive Review.06 5/7/2015 Incorporation of AST Executive Review.07 5/18/2015 Incorporation of AST Executive Review.08 5/19/2015 Incorporation of AST Executive Review 5/19/2015 Page 7 Revision.08
Department of Highway Safety & Motor Vehicles Motorist Modernization Project Phase One
Motorist Modernization Project Phase One For Period: April - June 2015 Project Description Quarter Ending: 6/30/2015 Agency Name: Department of Highway Safety & Motor Vehicles (HSMV) Project Name: Motorist
DOC Electronic Timekeeping System Quarterly Project Oversight Report: Comprehensive Review For Period January March 2015
Department of Corrections Electronic Timekeeping System Project For Period: January March 2015 Quarter Ending: 3/31/2015 Agency Name: Department of Corrections (DOC) Project Name: Electronic Timekeeping
HB 3588 FEASIBILITY STUDY OF AN INTERFACE MOTOR VEHICLE FINANCIAL RESPONSIBILITY VERIFICATION SYSTEM
Texas Department of Public Safety Texas Department of Insurance HB 3588 FEASIBILITY STUDY OF AN INTERFACE MOTOR VEHICLE FINANCIAL RESPONSIBILITY VERIFICATION SYSTEM Contents SECTION 1: EXECUTIVE SUMMARY...
Palm Beach County Clerk & Comptroller s Office Contracting & Purchasing Review
Palm Beach County Clerk & Comptroller s Office Contracting & Purchasing Review SHARON R. BOCK Clerk & Comptroller Palm Beach County Audit Services Division September 18, 2008 Report 2008 03 September 18,
Audit of Veterans Health Administration Blood Bank Modernization Project
Department of Veterans Affairs Office of Inspector General Audit of Veterans Health Administration Blood Bank Modernization Project Report No. 06-03424-70 February 8, 2008 VA Office of Inspector General
Analysis Item 65: Department of Revenue Property Valuation System
Analysis Item 65: Department of Revenue Property Valuation System Analysts: John Borden and Sean McSpaden Request: Allocate $1.5 million from the Emergency Fund for an increase to the Property Valuation
STATEMENT THOMAS P. MICHELLI CHIEF INFORMATION OFFICER U.S. IMMIGRATION AND CUSTOMS ENFORCEMENT DEPARTMENT OF HOMELAND SECURITY REGARDING A HEARING ON
STATEMENT OF THOMAS P. MICHELLI CHIEF INFORMATION OFFICER U.S. IMMIGRATION AND CUSTOMS ENFORCEMENT DEPARTMENT OF HOMELAND SECURITY REGARDING A HEARING ON EXAMINING CHALLENGES AND WASTED TAXPAYER DOLLARS
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Enterprise Project Management Initiative
Executive Summary Enterprise Project Management Initiative At a time when budgetary challenges became more and more aggressive, the Commonwealth of Kentucky determined in late 2000 it must develop a more
integrate 2: Business Process Redesign
Nevada System of Higher Education integrate 2: Business Process Redesign Executive Summary TABLE OF CONTENTS I. BACKGROUND AND OBJECTIVES 2 II. METHODOLOGY AND APPROACH 3 III. PROJECT OUTCOMES 5 IV. MAJOR
State of XXXXX. Project Name/Phase (Planning Development Implementation) Status Report. Date Ending: Mm/dd/yy
APPENDIX E SAMPLE STATUS REPORT ** This sample report is a suggested guideline, and models the Status Report Checklist found in Appendix D State of XXXXX Project Name/Phase (Planning Development Implementation)
MEMORANDUM FOR CHIEF FINANCIAL OFFICERS. Update on the Financial Management Line of Business and the Financial Systems Integration Office
EXECUTIVE OFFICE OF THE PRESIDENT OFFICE OF MANAGEMENT AND BUDGET WASHINGTON, D.C. 20503 December 16, 2005 MEMORANDUM FOR CHIEF FINANCIAL OFFICERS FROM: SUBJECT: Linda M. Combs, Controller Update on the
STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840
MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles
Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report
Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report The Enterprise Program Investment Council (EPIC) is responsible for governance
Oversight of Information Technology Projects. Information Technology Audit
O L A OFFICE OF THE LEGISLATIVE AUDITOR STATE OF MINNESOTA FINANCIAL AUDIT DIVISION REPORT Oversight of Information Technology Projects Information Technology Audit May 29, 2009 Report 09-19 FINANCIAL
The Florida Department of Highway Safety and Motor Vehicles Statement of Agency Organization and Operation
This statement of agency organization and operation has been prepared in accordance with the requirements of Section 28 101.001, Florida Administrative Code and is available to any person upon request.
Financial Services FINANCIAL SERVICES UTILITIES 57 FINANCIAL SERVICES AND UTILITIES 2016-2018 BUSINESS PLAN. CR_2215 Attachment 1
CR_2215 Attachment 1 Financial Services FINANCIAL SERVICES & UTILITIES 57 FINANCIAL SERVICES AND UTILITIES 2016-2018 BUSINESS PLAN Acting Branch Manager: Stacey Padbury Table of Contents INTRODUCTION Our
STORAGE NAME: h0035.tr DATE: January 6, 2000 HOUSE OF REPRESENTATIVES COMMITTEE ON TRANSPORTATION ANALYSIS. BILL #: House Bill 35
HOUSE OF REPRESENTATIVES COMMITTEE ON TRANSPORTATION ANALYSIS BILL #: House Bill 35 RELATING TO: SPONSOR(S): TIED BILL(S): Motor Vehicle Licenses/Decals Rep. Heyman and others None ORIGINATING COMMITTEE(S)/COMMITTEE(S)
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Mission Director, USAID/Macedonia, Dick Goldman. Report on the Risk Assessment of USAID/Macedonia (Report No. B-165-04-004-S)
September 27, 2004 MEMORANDUM FOR: FROM: SUBJECT: Mission Director, USAID/Macedonia, Dick Goldman Regional Inspector General/Budapest, Nancy J. Lawton /s/ Report on the Risk Assessment of USAID/Macedonia
Capital Projects and Construction: Building in Risk Management and Project Controls
Capital Projects and Construction: Building in Risk Management and Project Controls Making Every Dollar Count The global economic crisis sparked by the subprime mortgage debacle, the collapse of the securitized
With so many property management companies vying for your business, how do you make the right selection for your property?
With so many property management companies vying for your business, how do you make the right selection for your property? At Metropolitan Pacific Properties, we believe the difference is our people. For
EXECUTIVE SUMMARY...5
Table of Contents EXECUTIVE SUMMARY...5 CONTEXT...5 AUDIT OBJECTIVE...5 AUDIT SCOPE...5 AUDIT CONCLUSION...6 KEY OBSERVATIONS AND RECOMMENDATIONS...6 1. INTRODUCTION...9 1.1 BACKGROUND...9 1.2 OBJECTIVES...9
Financial Management Oversight (FMO) Progress Report
Finance & Administration Committee Information Item IV-A October 8, 2015 Financial Management Oversight (FMO) Progress Report Page 52 of 97 Washington Metropolitan Area Transit Authority Board Action/Information
THOMAS G. DAY SENIOR VICE PRESIDENT, INTELLIGENT MAIL AND ADDRESS QUALITY PRITHA N. MEHRA VICE PRESIDENT, BUSINESS MAIL ENTRY AND PAYMENT TECHNOLOGIES
March 31, 2009 THOMAS G. DAY SENIOR VICE PRESIDENT, INTELLIGENT MAIL AND ADDRESS QUALITY PRITHA N. MEHRA VICE PRESIDENT, BUSINESS MAIL ENTRY AND PAYMENT TECHNOLOGIES GEORGE W. WRIGHT VICE PRESIDENT, INFORMATION
Project Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
Audit of Financial Management Governance. Audit Report
Audit of Financial Management Governance Audit Report March 2015 TABLE OF CONTENTS Executive Summary... 2 What we examined... 2 Why it is important... 2 What we found... 2 Background... 4 Objective...
Program Management Office Provided Adequate Oversight of Two Contracts Supporting the Defense Enterprise Accounting and Management System
Report No. DODIG-2014-006 I nspec tor Ge ne ral U.S. Department of Defense OCTOBER 25, 2013 Program Management Office Provided Adequate Oversight of Two Contracts Supporting the Defense Enterprise Accounting
HHS Buyers Club Strategy
HHS Buyers Club Strategy Executive Summary The HHS Buyers Club is a HHS IDEA Lab sponsored project focused on addressing a critical problem in government: modernizing federal acquisition of information
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL AUDIT SERVICES August 24, 2015 Control Number ED-OIG/A04N0004 James W. Runcie Chief Operating Officer U.S. Department of Education Federal
Crosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
Citywide Contract Compliance Audit Report
City of Berkeley Office of the City Auditor Ann-Marie Hogan, City Auditor Citywide Contract Compliance Audit Report Prepared by: Ann Marie Hogan, City Auditor, CIA, CGAP Teresa Berkeley-Simmons, Audit
LOUISIANA DEPARTMENT OF PUBLIC SAFETY OFFICE OF MOTOR VEHICLES Strategic Plan FY 2014-2015 through FY 2018-2019
LOUISIANA DEPARTMENT OF PUBLIC SAFETY OFFICE OF MOTOR VEHICLES Strategic Plan FY 2014-2015 through FY 2018-2019 Vision The Office of Motor Vehicles (OMV) will provide the highest quality service and protection
U.S. Department of the Treasury. Treasury IT Performance Measures Guide
U.S. Department of the Treasury Treasury IT Performance Measures Guide Office of the Chief Information Officer (OCIO) Enterprise Architecture Program June 2007 Revision History June 13, 2007 (Version 1.1)
Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit
Internal Audit Report Toll Operations Contract Management TxDOT Office of Internal Audit Objective To determine whether the Toll Operations Division (TOD) contract management structure is designed and
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
Audit of the Data Center Consolidation Initiative at NARA. OIG Draft Audit Report No. 12-09. May 10, 2012
Audit of the Data Center Consolidation Initiative at NARA OIG Draft Audit Report No. 12-09 May 10, 2012 Table of Contents Executive Summary... 3 Background... 4 Objectives, Scope, Methodology... 7 Audit
INFORMATION TECHNOLOGY PROJECT REQUESTS
INFORMATION TECHNOLOGY PROJECT REQUESTS Guidelines & Instructions for Maryland State Agencies Revised Two Step PPR/PIR Approval Process Fiscal Year 2013 Table of Contents Part 1: Overview... 2 1.1 Introduction...
Report No. DoDIG-2012-081 April 27, 2012. Navy Organic Airborne and Surface Influence Sweep Program Needs Defense Contract Management Agency Support
Report No. DoDIG-2012-081 April 27, 2012 Navy Organic Airborne and Surface Influence Sweep Program Needs Defense Contract Management Agency Support Additional Copies To obtain additional copies of this
Program and Project Management Practices in the Federal Civilian Agencies
Progress through partnership National Defense Industry Association, Civilian Agencies Industry Working Group Program and Project Management Practices in the Federal Civilian Agencies White Paper Lawrence
Status of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior Recommendations
Report No. DODIG-2013-111 I nspec tor Ge ne ral Department of Defense AUGUST 1, 2013 Status of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior s I N T
House Appropriations Committee NCDOT Information Technology. David H. Ulmer April 2, 2015
House Appropriations Committee NCDOT Information Technology David H. Ulmer April, 015 Agenda 1. Starting point portfolio and internal capabilities. Current portfolio activities and status 3. Internal improvement
PROCEDURES MANUAL FOR IMPLEMENTATION OF THE FLORIDA MOTOR VEHICLE NO-FAULT LAW AND FINANCIAL RESPONSIBILITY LAW INITIAL/RELOAD REQUIREMENTS
PROCEDURES MANUAL FOR IMPLEMENTATION OF THE FLORIDA MOTOR VEHICLE NO-FAULT LAW AND FINANCIAL RESPONSIBILITY LAW INITIAL/RELOAD REQUIREMENTS STATE OF FLORIDA DEPARTMENT OF HIGHWAY SAFETY AND MOTOR VEHICLES
Performance Audit Concurrent Review: ERP Pre-Solicitation
Performance Audit Concurrent Review: ERP Pre-Solicitation April 2002 City Auditor s Office City of Kansas City, Missouri 24-2001 April 10, 2002 Honorable Mayor and Members of the City Council: We conducted
REQUEST FOR PROPOSALS. Business Continuity Planning Consultant Services APPENDIX C RFP STATEMENT OF WORK EXHIBITS 1-3
REQUEST FOR PROPOSALS Business Continuity Planning Consultant Services APPENDIX C RFP STATEMENT OF WORK EXHIBITS 1-3 EXHIBITS EXHIBIT 1 EXHIBIT 2 EXHIBIT 3 Glossary of Terms and Acronyms Contract Discrepancy
PWGSC YOUR SERVICE OUR SERVICES, STANDARDS AND RESULTS 2015 2016
PWGSC YOUR SERVICE OUR SERVICES, STANDARDS AND RESULTS 2015 2016 BUYING AND SELLING A. KEY SERVICES We provide departments and agencies with the expertise needed to acquire complex commercial goods and
Overview of Florida Information Technology Project Management and Oversight Standards. Jason M. Allison, Executive Director
Overview of Florida Information Technology Project Management and Oversight Standards Jason M. Allison, Executive Director AGENCY FOR STATE TECHNOLOGY Statutory duties and responsibilities of AST: Establish
Timor- Leste. United Nations Development Programme. Vacancy Announcement
United Nations Development Programme Timor- Leste Vacancy Announcement Project Title: Strengthening Capacities for Disaster Risk Management in Timor Leste Post Title: National Administration and Finance
The Fast Track Project Glossary is organized into four sections for ease of use:
The Fast Track Management Glossary provides a handy reference guide to the fast track management model, encompassing the concepts, steps and strategies used to manage successful projects even in the face
HHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC)
Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services HHS OCIO Policy for Information Technology (IT) Enterprise
Workers Compensation Commission
Audit Report Workers Compensation Commission March 2009 OFFICE OF LEGISLATIVE AUDITS DEPARTMENT OF LEGISLATIVE SERVICES MARYLAND GENERAL ASSEMBLY This report and any related follow-up correspondence are
EXECUTIVE OVERVIEW OF THE ACCOUNTABILITY AGREEMENT
EXECUTIVE OVERVIEW OF THE ACCOUNTABILITY AGREEMENT This document summarizes the key elements of the 07/08-09/10 Accountability Agreement and its Schedules. It is intended to provide the reader with an
TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION
TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION Management Oversight of the Small Business/Self-Employed Division s Fuel Compliance Fleet Card Program Should Be Strengthened September 27, 2011 Reference
November 2009 Report No. 10-016
John Keel, CPA State Auditor An Audit Report on The Financial Responsibility Verification Program (TexasSure) Report No. 10-016 An Audit Report on The Financial Responsibility Verification Program (TexasSure)
Concept of Operations for Line of Business Initiatives
Concept of Operations for Line of Business Initiatives Version 1.0 Office of E-Gov and IT, OMB March 2006 Table of Contents FOREWORD...2 1 OBJECTIVES OF THE LINES OF BUSINESS CONCEPT OF OPERATIONS...3
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
December 2014 Report No. 15-017. An Audit Report on The Telecommunications Managed Services Contract at the Health and Human Services Commission
John Keel, CPA State Auditor An Audit Report on The Telecommunications Managed Services Contract at the Health and Human Services Commission Report No. 15-017 An Audit Report on The Telecommunications
How To Pass A Bill To Help A Breast Cancer Foundation In Florida
HOUSE OF REPRESENTATIVES STAFF ANALYSIS BILL #: HB 7055 PCB HWSS 15-01 Highway Safety and Motor Vehicles SPONSOR(S): Highway & Waterway Safety Subcommittee, Steube TIED BILLS: IDEN./SIM. BILLS: REFERENCE
LEXEVS OPERATIONS AND MAINTENCE SUPPORT PROJECT MANAGEMENT PLAN
LEXEVS OPERATIONS AND MAINTENCE SUPPORT PROJECT MANAGEMENT PLAN Version Number: 1.0 Version Date: October 1, 2014 VERSION HISTORY Version Number Implemented By Revision Date Approved By Approval Date 1.0
1.1 Identification This is the Subcontractor Management Plan, document number XYZ035, for the SYSTEM Z project.
A Sample contractor Management Plan 1.0 INTRODUCTION 1.1 Identification This is the contractor Management Plan, document number YZ035, for the SYSTEM Z project. 1.2 Purpose The contractor Management Plan
Accenture Federal Services. Federal Solutions for Asset Lifecycle Management
Accenture Federal Services Federal Solutions for Asset Lifecycle Management Assessing Internal Controls 32 Material Weaknesses: identified in FY12 with deficiencies noted in the management of nearly 75%
Department of Human Resources
Workforce Services Workforce Policy and Planning Department Management/ Human Resource Information Systems Employee Relations Employment Compensation and Workforce Analysis Employee Benefits Organizational
AUDITOR GENERAL DAVID W. MARTIN, CPA
AUDITOR GENERAL DAVID W. MARTIN, CPA AGENCY FOR HEALTH CARE ADMINISTRATION MEDICAID THIRD-PARTY LIABILITY ADMINISTRATION Operational Audit SUMMARY The Agency for Health Care Administration (Agency) is
AUDIT REPORT. The Department of Energy's Management of Cloud Computing Activities
U.S. Department of Energy Office of Inspector General Office of Audits and Inspections AUDIT REPORT The Department of Energy's Management of Cloud Computing Activities DOE/IG-0918 September 2014 Department
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM
ILLINOIS SECRETARY OF STATE Approach to Legacy System Modernization Request For Information
OVERVIEW The Office of the Illinois Secretary of State (SOS) has approximately 120 drivers license facilities located throughout the state of Illinois and five mobile units that travel to other physical
GTA Board of Directors September 4, 2014
GTA Board of Directors September 4, 2014 Our Strategic Vision Our Mission A transparent, integrated enterprise where technology decisions are made with the citizen in mind To provide technology leadership
Implementing GASB Statement No. 54. Linda C. Davidson Financial Services Director City of Boca Raton, Florida
Implementing GASB Statement No. 54 Linda C. Davidson Financial Services Director City of Boca Raton, Florida The objective of this Statement is to enhance the usefulness of fund balance information by
CODE: E.003 Financial Services BUDGET AND BUSINESS PLANNING POLICY. 1.2 The essential activities covered by this policy include:
BUDGET AND BUSINESS PLANNING POLICY CONTENTS 1.1 Budget and business planning is undertaken to support strategic planning and decision-making and to serve accountability by enabling administration to plan
Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26
Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain