Centrifugal Sprayed Concrete for Lining Horizontal Pipes and Culverts and Vertical Shafts
|
|
|
- Griffin Dorsey
- 10 years ago
- Views:
Transcription
1 Centrifugal Sprayed Concrete for Lining Horizontal Pipes and Culverts and Vertical Shafts D.R. (Rusty) Morgan AMEC Earth & Environmental, a division of AMEC Americas Limited Vancouver, British Columbia, Canada Kristian Loevlie Shotcrete Technologies Inc. Idaho Springs, Colorado, USA Nicholas Kwong New Gold Inc. New Afton, British Columbia, Canada ABSTRACT: Conventional dry-mix shotcrete (where water is added at the nozzle) or wet-mix shotcrete (where air is added at the nozzle) to pneumatically convey the material to the receiving surface has long been used for lining horizontal pipes and culverts and vertical shafts. This paper, however, describes a different technology for spraying concrete onto such surfaces; the use of wet-mix centrifugal sprayed concrete (CSC). Instead of adding water at the nozzle (as in dry-mix shotcrete), or air at the nozzle (as in wet-mix shotcrete), the concrete mix is pumped into a spinning head, which spins at between about 4000 to 5000 rpm. The concrete is then centrifugally sprayed onto the receiving surface at high impacting velocity. This paper describes the use of this CSC technology for lining horizontal pipes, culverts and other circular structures and vertical raise-bore shafts. The case history example described for the vertical raise-bore shaft at a mine in British Columbia, Canada, used a macro-synthetic fibre reinforced concrete. This is believed to be the first use of this technology in North America, if not the world. Productivity with the CSC was much greater than that previously achieved in using a conventional robotically supplied dry-mix, steel fibre reinforced shotcrete system to line similar vertical shafts at the mine. 1.0 INTRODUCTION Since 1991 Shotcrete Technologies Inc. provided remote controlled robotic equipment and know-how for wet-mix shotcrete lining of many horizontal pipes and culverts and vertical shafts in tunnels and mines. Some of these horizontal structures were over 1000 m long and some of the shafts were over 100 m deep. Pipe and culvert diameters ranged from as little as 450 mm to as much as 2.5 m. Shafts were typically in the 2.5 to 3.5 m diameter range. Plain and synthetic or steel fibre reinforced shotcrete mixes have been used in many such applications, depending on the engineer s requirements. Figure 1 shows a remote control robotic wet-mix shotcrete lining rig being winched through a culvert. Visual monitoring is provided by a television camera attached to the robotic rig. Figure 2 shows a similar wet-mix shotcrete robotic rig being used to line a raise-bore shaft at a mine. Figure 1: Robotic lining of culvert with conventional wetmix shotcrete Figure 2 : Robotic lining of raise bore shaft with conventional wet-mix shotcrete 1
2 While the preceding systems have generally worked well and provided high quality lining systems, they are not without their challenges. There are many moving parts in the robotic rig that need to be maintained and the shotcrete nozzle needs to be regularly cleaned to maintain an optimal spraying pattern. Recognizing this, Shotcrete Technologies Inc. embarked on development of an innovative new system for spraying concrete; the development of the centrifugal sprayed concrete (CSC) spinner head system. A list is provided in Table 3 of some of the projects where robotically applied CSC has been used for lining horizontal pipes, culverts and other structures. Most of this paper, however, concentrates on the CSC lining of a 3.5 m diameter 290 m deep raise-bore shaft at the New Gold Inc. mine at New Afton, British Columbia, Canada in June 2009, using a macro-synthetic fibre reinforced wet-mix CSC. This is believed to be the first use of this technology in North America, if not the world. 2.0 CENTRIFUGAL SPRAYED CONCRETE SYSTEM Figure 3 shows the spinning head used on the New Afton project. The red hose is the 25 mm diameter line connected to the coupling which feeds compressed air into the spinner head to rotate it at 4000 to 5000 rpm. The greater the volume of air provided, the faster the head spins. The concrete is pumped into the spinner head, which has a conical dispersion feature. As the head spins the pumped concrete is centrifugally sprayed at high impacting velocity onto the receiving surface (pipe, culvert or shaft). The ejected material dispersion and velocity is such that unlike conventional wet-mix shotcrete, where a dense shotcrete stream ejecting from the nozzle is clearly visible, the ejected material is barely visible. One simply sees material building up on the receiving surface. The rate at which the material builds up on the receiving surface depends on the diameter of the pipe, culvert or shaft and the rate at which the spinning head is pulled through the pipe or culvert. Figure 3 : Spinner head assembly connected to pump hose and compressed air line Figure 4 shows start-up of spraying of an ASTM C1550 round panel in an above ground test chamber at the New Afton project. Figure 5 shows the filled test panel prior to cutting back and trowelling to provide a flat surface. There is some rebound of sprayed concrete and fibre on the floor at the base of the test chamber. Systematic studies to quantify the amount and constitution of the rebound materials have not yet been conducted, but are planned prior to lining the next raise-bore shaft at the New Afton project. However, reports from the mining engineers at the New Afton project on completion of lining the approximately 290 m deep, 3.5 m diameter raise-bore shaft lined in June 2009 indicated that very little rebound material was found at the base of the shaft. Figure 4 : Start-up of centrifugal spraying of an ASTM C1550 round test panel in an above ground test chamber Page 2
3 typically produces compressive strengths of around 40 MPa at 28 days. For the New Afton project it was decided to evaluate the potential for use of a macro-synthetic fibre reinforced concrete for lining raise-bore shafts, using the centrifugal sprayed concrete process. Proof of Concept trials were conducted in Vancouver, British Columbia in December Two different sprayed concrete mixes were evaluated: Figure 5 : Sprayed ASTM C1550 Round panel prior to cutting back to flat surface In the New Afton project the specified sprayed concrete lining thickness was a minimum of 50 mm. In spraying the ASTM C1550 test panel in the above-ground test chamber the concrete was centrifugally sprayed to a thickness of 100 mm on the panel and test chamber walls, before cutting back the round test panel to the required 75 mm thickness. Even at 100 mm sprayed concrete thickness adherence to the test chamber walls was excellent and there was no sagging or sloughing of the sprayed concrete. This is for concrete which was discharged into the pump from the ready-mix concrete truck at about 170 mm slump. Note that no accelerator was used in this sprayed concrete. Special sprayed concrete mixture designs are required to enable this type of performance. Concrete mixture proportioning is discussed in the next section. 3.0 SPRAYED CONCRETE MIXTURE DESIGNS Since 2005 Shotcrete Technologies Inc. has been using a proprietary natural pozzolan modified concrete, which also contains a superplasticizer, Kelcrete rheology modifier and a low dosage of micro-synthetic fibre reinforcement for robotically lining horizontal pipes, culverts and other circular structures. Such centrifugal sprayed concrete has typically had a 5 mm maximum size aggregate, as lining thicknesses have mainly been in the 20 to 40 mm range. This mixture formulation has worked well in these horizontal lining applications, with almost no rebound and good adhesion and productivity. Review of cast concrete cylinder test results from concrete supplied to centrifugal sprayed concrete projects shows that this mixture design a) A natural pozzolan mix provided by Shotcrete Technologies Inc. b) A silica fume modified mix designed by AMEC. Both mixtures contained 6 kg/m 3 of Barchip Shogun macro-synthetic fibre reinforcement. The New Afton project requirements were as follows: Slump: 150 ± 20 mm Maximum Aggregate Size: 5 mm (Aggregate to meet ACI 506 grading No. 1 requirement) Maximum Water/Cementing Materials Ratio: 0.45 Minimum Compressive Strength: 30 MPa at 7 days 40 MPa at 28 days ASTM C642 at 28 days: Maximum absorption: 8% Maximum volume of permeable voids: 17% ASTM C1550 Round Panel Test: Target 320 J at 28 days The trials in Vancouver demonstrated that it was possible to spray both the natural pozzolan mix and the silica fume mix containing 6 kg/m 3 of macrosynthetic fibres, using the centrifugal sprayed concrete system. Mixture proportions for the silica fume mix are provided in Table 1, which follows. Table 1: Silica Fume Trial Mixture Design Material Mass (kg) Density (kg/m 3 ) Volume (m 3 ) Cement Type GU Silica Fume Fine Aggregate (SSD) Water Barchip Shogun Fibre Superplasticizer Air Content (as shot) (2.0%) Totals Page 3
4 Mixture proportions for the natural pozzolan mix are not provided in this paper, since for logistics and costs reasons, it was subsequently decided to not import the natural pozzolan from the USA to Canada for the New Afton project. The silica fume mix produced compressive strengths (on cores extracted from sprayed test panels) of 73 MPa at 8 days and a toughness at 7 days on a sprayed round ASTM C1550 test panel of 389 J. Clearly, the sprayed concrete was of very high quality. It was, however, observed that the silica fume mix was very sticky and consequently did not spray out as efficiently as the natural pozzolan mix (lower rate of productivity). In order to address this concern, a decision was made to trial a different, less sticky supplementary cementing material. The selected product was Whitemud Resources calcined metakaolin from Saskatchewan, Canada. Hand cast laboratory trials were conducted at the AMEC Vancouver laboratory and subsequently centrifugal sprayed concrete trials at the New Afton project site using a metakaolin mix. While some sprayed concrete incorporating both metakaolin and a reduced amount of silica fume was also used in the trials and in some shaft lining work most of the shaft lining was completed using the metakaolin mix detailed in Table 2, which follows. Table 2: Metakaolin Sprayed Concrete Mix Design Material Mass (kg) Density (kg/m 3 ) Volume (m 3 ) Cement Type GU Metakaolin (Whitemud Resources) Fine Aggregate (SSD) Water Barchip Shogun Fibre High Range Water Reducing Admixture (BASF Glenium 7101)*,L Hydration Controlling Admixture (Delvo), L Air Content (as shot),% Totals Yield = * High range water reducing admixtures adjusted as necessary to provided required slump. Note that in this mix design the synthetic macrofibre addition rate was reduced to 5 kg/m 3. This was done as a precautionary measure, to reduce the potential for blockages during pumping down a 290 m deep shaft. This mix design generally shot well, provided it was provided in the specified slump range of 150 ± 20 mm. A hydration controlling admixture was added to keep the pumped concrete live for an extended period of time, given that it had to be pumped through over 300 m of hose. Figure 6 shows the hose laid out at the raise-bore shaft site. The hydration controlling admixture dosge rate was varied, depending on the ambient and sprayed concrete temperatures and the depth at which the spinner head was spraying in the raise-bore shaft. Concrete was kept live for up to as much as 8 hours. Figure 6 : 300m of concrete hose laid out at raise bore shaft 4.0 HORIZONTAL PIPE AND CULVERT LINING As mentioned previously, Shotcrete Technologies has been using remote control, robotic centrifugal sprayed concrete for lining pipes, culverts and other structures since Table 3, which follows, provides a list of some of these projects. As can be seen, pipe diameters ranged from 457 mm (18 in) to 2438 mm (96 in). Lengths of the pipes ranged from 8.5 m (28 ft) to 762 m (2500 ft). One concrete sewer tunnel lined was 2744 m (9000 ft) long Figure 7 shows robotically applied CSC lining of a corrugated metal pipe culvert. The robot is winched through the culvert, with the rate of travel of the winch controlling the lining thickness. Obviously the robot travels more rapidly in smaller diameter pipes, to apply a given thickness of CSC lining. Page 4
5 A television camera is mounted on the robot to provide real time monitoring of the spray application. In areas with voids or cavities in the original structure the rate of winching can be slowed down to provide local void filling and a smooth CSC finish profile. Figure 7 : Robotically applied centrifugal sprayed concrete lining horizontal metal culvert Table 3: List of Pipes and Culverts Lined with Centrifugally Sprayed Concrete Date Project Location Type Dimensions Thickness Remarks, All Structural Repair 2005 Union Pacific Railroad Hotchkiss, Colorado CMP 2500 If x 42 ID ¾ Lined 400 lf/day for 7 days 2005 Mesa County, Colorado Grand Junction, Colorado CMP 110 If x 36 ID 1 Lined in one day 2005 Elbert County, Colorado Simla, Colorado CMP 85 If x 96 ID 1 2 Culverts at this dimension 2005 City of Glenwood Springs Glenwood Springs, CMP ½ Several culverts, multiple Colorado diameters 2005 Town of Castle Rock Castle Rock, Colorado CMP 450 If x 60 ID 1 Storm sewer 2007 Kiewit Western Rocky Mtn National Park CMP 96 If x 24 ID ¾ 45 degree grade in national park 2007 El Paso County El Paso, Texas CMP 60 If x 60 ID 1 2 Culverts at this dimension If x 36 ID 1 3 Culverts at this dimension 2008 City of Idaho Springs Idaho Springs, Colorado Brick Manhole 3 Manholes 2009 El Paso County El Paso, Texas CMP 60 If 36 ID 1 6 Oval culverts, structural repair 2008 Jeffco Road & Bridge Colorado CMP 38 If x 18 ID 1 3 Culverts on golf course Colorado CMP 42 If x 18 ID 1 Difficult access Colorado CMP 28 If x 24 ID Mt. Snow Resort Vermont CMP 450 If x 48 ID ¾ Reline culvert under parking lot 120 If x 72 ID 2 Dam outlet 2008 Kansas DOT Topeka, Kansas CMP 50 If x30 x50 ¾ Under I-70 Various Oval 55 If x 23 x36 ¾ Oval highway culvert 196 If x42 x32 ¾ Oval highway culvert 175 If x 44 ID ¾ Circular, stepped inclines 2009 BNSF Railroad (Aecom) LaJunta, Colorado Tile 550 LF x 5.5 ft 1 ½ Storm sewer diesel inflow 2006 MMWS Sewer District Milwaukee, Wisconsin Concrete 9000 If, 60 ID ¾ Sewer tunnel + various manholes 2009 Sequoia National Park CMP Various 1 9 Various lengths and diameters CO Dept of Transportation Colorado CMP Various Many culvert repairs under I-70 CMP = Corrugated Metal Pipe Culvert 5.0 CSC LINING OF RAISE BORE SHAFT AT NEW AFTON Figure 8 shows the elliptical so-called egg about to be lowered into the shaft at the New Afton Project. This elliptical egg was constructed from tubular steel and is designed to keep the spinner head centred in the shaft at all times during concrete spraying. (Interestingly it is not needed to keep the spinner head stable. During spinning the spinner head does not move around during centrifugal spraying; it remains stable in one position even if it is simply dangling freely from the suspended hose without connection to the egg). The egg has slightly smaller lateral dimensions than the raise-bore shaft, so that it can be raised and lowered, (even after lining spraying) without friction. 5
6 Figure 11 : Coupling used for connecting lengths of pump hose and connecting pump hose to crane hoist cable Figure 8 : Top of raise bore shaft prior to centrifugal sprayed concrete lining The shroud at the top of the egg protects TV cameras mounted on the central tubular pipe, from damage from any falling objects during spraying. Figure 9 shows a close-up view of the cameras mounted on the egg. Figure 10 shows the general rigging set-up for the CSC lining of the raise-bore shaft. A 20 ton crane was used for lowering and raising the spinner head, egg, concrete pump lines, compressed air line and TV cable. The crane had a 20 mm diameter hoist cable to which the pump line was attached. Every 15 m (50 ft) of pump hose was connected with a custom-built coupling. Figure 13 shows this coupling. The U-bracket welded to the coupling was used in the rigging to connect the pump hose to the crane hoist cable. Figure 9 : View of TV cameras mounted at top of "egg Figure 12 shows a wooden cable reel, suspended from straps mounted on the steel beam spanning between the concrete lock-blocks shown in Figure 10, over which the concrete and air hoses pass as the egg is lowered down the shaft. (On future projects it is planned to use a metal truck tire rim instead of the wooden cable reel, as the wood wears out). Figure 12 : Cable reel over which the pump and air hoses pass Figure 13 shows two miners connecting the concrete pump line to the crane hoist cable. This was done using a 1.2 m long steel rope lanyard, connected with toggle bolts to the coupling shown in Figure 11, and with two quick-cinch bolts connecting the lanyard to the cable hoist. In this way the weight of the concrete pump hose (full of concrete) was connected to the crane hoist rope every 15 m (50 ft). This had to be done for every 15 m (50 ft) of hose as the egg was lowered down the shaft. The air line and TV cable were strapped to the pump hose with duct tape. Figure 10 : General rigging set-up for CSC lining of raise bore shaft Page 6
7 days. This included time for orientation, rigging optimization and maintenance. The AMEC Kamloops laboratory carried out quality control testing on CSC. Cores extracted from test panels sprayed in a special above-ground test chamber produced 7 day compressive strengths averaging about 38 MPa and 35 day compressive strengths averaging about 70 MPa for the metakaolin modified mix detailed in Table 2; clearly a very high quality concrete. Figure 13 : Miners cinching bolts coupling wire rope lanyard to pump hose and crane hoist rope Then as the egg was raised up the shaft during CSC lining operations, the bolts and lanyard had to be disconnected every 15 m (50 ft) so that the hose could be winched back over the cable reel. Proper rigging was key to the successful completion of this project and ergonomics and efficiency increased as the work progressed. The miners wore full safety harnesses at all times while working on the platform over the raise-bore shaft. The logistics of lining the shaft varied somewhat, but the general concept was to pump the required length of 50 mm ID pump line for the day s production full with concrete before attaching the egg and spinner head. The pump and spinner head was started. When it was verified that the spinner head was operating correctly, the assemblage was then lowered down the shaft. The egg was lowered down fairly rapidly, spraying about 6 mm of CSC onto the rock face in the shaft as it went down. Once the spinner head reached the lowest point for the day s production, the egg was withdrawn slowly, so that the required full minimum 20 mm of thickness required for the shaft lining was produced. A materials balance count was used to control lining thickness. i.e. a known volume of concrete discharged from the ready mix concrete trucks, applied over a known depth of shaft with an allowance for some materials loss through rebound. A special spring loaded flow control device was installed on the pump hose 3 m above the spinner head to prevent free-fall of concrete onto the spinner head. A total of 198 m 3 of sprayed concrete were used to line the shaft. Towards the end of the project between 35 to 40 m 3 of CSC were applied to the shaft lining per working day. The work took 6 working days of actual shooting to line the shaft. Total time to complete the project was 10 Round panel test results to ASTM C1550 produced high results of 313 J; close to the target value of 320 J. Lower results were found in some companion test panels sprayed at the same time and on other days. Some of these lower test results were, however, attributed to the test panels being finished, cured and handled in a less than optimal manner. In a couple of cases the panels did not break with the classic Y yield line failure pattern (broke in two) and this resulted in lower toughness results. 6.0 CONCLUSIONS This paper demonstrates that centrifugal sprayed concrete (CSC) provides a viable alternative to conventional wet or dry-mix shotcrete for lining circular or slightly oval horizontal pipes and culverts and circular vertical shafts. It is further demonstrated that CSC technology can be used with macro-synthetic fibre reinforcement for providing enhanced toughness to the sprayed concrete lining. It is further demonstrated in this paper that CSC technology, with appropriate rigging, can be used to line 3.5 m diameter by 290 m deep raise-bore shafts with high rates of productivity. Certainly CSC linings in such shafts can be completed in considerably less time than that achievable with robotically applied dry-mix, steel fibre reinforced shotcrete (10 days versus about 6 weeks). This is very cost attractive to the Owner. Additionally, this paper demonstrates that with appropriate mixture designs and using conventional ready mix concrete batching, mixing and delivery, the CSC system is capable of producing a high compressive strength and adequate toughness for most applications. This paper presents a case history example of a North America first application of CSC with macro-synthetic fibre reinforcement for lining large diameter (3.5 m) and deep (290 m) raise-bore shaft. It is expected that as similar shafts are lined with CSC, further enhancements in rigging and spraying methodologies will evolve, with further improvements in CSC quality and productivity and the economics of such linings. Page 7
8 7.0 ACKNOWLEDGEMENTS The raise-bore shaft lining with centrifugally sprayed concrete at the New Gold Inc. gold/copper mine at New Afton, British Columbia, Canada was done as a Joint Venture between Shotcrete Technologies Inc. and New Gold Inc. Proof of concept spraying in Vancouver, British Columbia of macro-synthetic fibre reinforced CSC was provided by Bel Pacific Limited. AMEC Earth & Environmental, a division of AMEC Americas Limited, British Columbia provided CSC mixture designs and quality control testing during preconstruction trials and during shaft lining operations. Finally, the permission of New Gold Inc. to allow publication of this case history example of the New Afton raise-bore shaft lining with CSC is gratefully acknowledged. Page 8
Shotcrete Quality Control and Testing for an Underground Mine in Canada
Shotcrete Quality Control and Testing for an Underground Mine in Canada By Dudley R. (Rusty) Morgan and Mazin Ezzet AMEC Earth & Environmental, a division of AMEC Americas Limited SHOTCRETE FOR AFRICA
C. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
Rapid Chloride Permeability Testing
Rapid Chloride Permeability Testing A test that can be used for a wide range of applications and quality control purposes if the inherent limitations are understood By Prakash Joshi and Cesar Chan C orrosion
SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
Example Specification for Concrete using Current Building Code Requirements
Example Specification for Concrete using Current Building Code Requirements DISCLAIMER: This specification is an example that accompanies a seminar titled The P2P Initiative: Performance-based Specs for
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
SECTION 18 - CAST IN PLACE HIGH PERFORMANCE CONCRETE (HPC)
SECTION 18 - CAST IN PLACE HIGH PERFORMANCE CONCRETE (HPC) 1.0 DESCRIPTION This section details the requirements for materials and methods in the proportioning, mixing, transporting, placing, finishing
Guide Specification Precast Concrete Products
Guide Specification Precast Concrete Products This specificaton should be used only by qualified professionals who are competent to evaluate the significance and limiations of the specification and who
Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete
Tremie Concrete Underwater concrete plays an important role in the construction of offshore structures. It may be used to tie together various elements in composite action (i.e., to tie piling to the footing).
The entire document shall be read and understood before proceeding with a test. ISTA 3B 2013 - Page 1 of 35
Packaged-Products for Less-Than-Truckload (LTL) Shipment ISTA 3 Series General Simulation Performance Test PROCEDURE VERSION DATE Last TECHNICAL Change: NOVEMBER 2012 Last EDITORIAL Change: JANUARY 2013
Mass Concrete. Robert Moser CEE8813A Material Science of Concrete. Definitions & Standards, Thermal Cracking, and Temperature Rise
Mass Concrete Robert Moser CEE8813A Material Science of Concrete Lecture Overview General Overview Definitions & Standards, Thermal Cracking, and Temperature Rise Temperature & Stress Prediction Factors
Demonstration of an Innovative Large-Diameter Sewer Rehabilitation Technology in Houston, Texas
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper TA-T3-03 Demonstration of an Innovative Large-Diameter Sewer Rehabilitation Technology
SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water
Advancements in Permeable Pavements
Advancements in Permeable Pavements Engineers Workshop Saint Vincent College March 14 & 15 2013 Permeable Pavements There are several different words that are used to describe a pavement that water drains
Pavement Thickness. esign and RCC-Pave Software. Roller-Compacted Concrete Pavement: Design and Construction. October 24, 2006 Atlanta, Georgia
Roller-Compacted Concrete Pavement: Design and Construction Pavement Thickness esign and RCC-Pave Software Gregory E. Halsted, P.E. Pavements Engineer Portland Cement Association October 24, 2006 Atlanta,
Commonwealth of Pennsylvania PA Test Method No. 632 Department of Transportation October 2013 5 Pages LABORATORY TESTING SECTION. Method of Test for
Commonwealth of Pennsylvania PA Test Method No. 632 Department of Transportation 5 Pages LABORATORY TESTING SECTION Method of Test for TIME OF SETTING OF CONCRETE MIXTURES BY PENETRATION RESISTANCE 1.
CONCREBOL 2015. 2.3 There is no restriction regarding the number of participants in each team.
12 nd CONTEST REGULATION 1/11 CONCREBOL 2015 1 OBJECTIVE 1.1 This contest intends to test the competitors ability in developing construction methods and the production of lightweight homogeneous concrete
Chapter. Restoration of Damaged Structures
5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.
Proper use of the Rebound Hammer Updated to reflect the changes to ASTM C805
CEMEX USA - Technical Bulletin 2.1 Proper use of the Rebound Hammer Updated to reflect the changes to ASTM C805 The Rebound Hammer has been around since the late 1940 s and today is a commonly used method
LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD
www.norcalpug.com LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD Bob Fisher and Lance Stracner Ameron Protective Lining J.R. Pipeline Co Inc. Abstract: The
SPR PE Steel Reinforced Liner
ENGINEERED SOLUTIONS SPR PE Steel Reinforced Liner Reline Done Right Contech is your single source for rehabilitation of sanitary & storm sewers, culverts and bridges. Contech Engineered Solutions has
CGA Standard Practices Series. Article 600 Standard for Pozzolan Enhanced Grouts Used in Annular Seals & Well Destruction
California Groundwater Association An NGWA Affiliate State PO Box 14369 Santa Rosa CA 95402 707-578-4408 fax: 707-546-4906 email: [email protected] website: www.groundh2o.org CGA Standard Practices Series
NorthEast Transportation Training and Certification Program (NETTCP) Course Registration Form
(NETTCP) Course Registration Form Interim Certification (Cost $300 members / $425 non-members) HMA Plant Technician* HMA Paving Inspector* Soils & Aggregate Inspector* Soils & Aggregate Lab Technician*
Shrinkage and Creep Properties of High-Strength Concrete Up To 120 MPa
Seventh International Congress on Advances in Civil Engineering, October11-13, 26 Yildiz TechnicalUniversity, Istanbul, Turkey Shrinkage and Creep Properties of High-Strength Concrete Up To 12 MPa H. C.
The New York Connecting Railroad is a rail
2010 Outstanding Repair & Rehabilitation Project Concrete Arch Bridge No. 6.45 over 31st Street, Queens, NY By Tommy Pirkle and Arden Morris Boddie The New York Connecting Railroad is a rail line in the
MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS
MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS May 29, 2013 Revision B Structural Guideline for Design and Installation Holes in Composite Floor Slab Terminal 3, Departure Level
GUIDE SPECIFICATIONS FOR PRECAST CONCRETE PRODUCTS
GUIDE SPECIFICATIONS FOR PRECAST CONCRETE PRODUCTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. This specification covers the materials for and manufacture of precast reinforced concrete units produced in
Construction. Pre-Bagged Structural Waterproofing System. Product Description. Product Data. Tests. Form
Construction Product Data Sheet Edition 15/07/2013 Identification no: 01 07 05 04 001 0 000001 Sika 1 Pre-Bagged Structural Waterproofing System Product Description Pre-Bagged Structural Waterproofing
CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
TS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING
TORONTO TRANSPORTATION January 2012 TS 813 GROUNDING AND BONDING TABLE OF CONTENTS 1. DRAWINGS TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET
SECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
DIVISION 4300 STORM DRAINAGE
DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
Wastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines
SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)
NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
METHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.
CI/SfB Tn6 L6813 September 2013 RIW CAVITY DRAIN R20 R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. Other systems are available for specific uses,
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and
PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY
PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY Cured-In-Place Pipe Pressure & Gravity Lines Pipe Splitting Trenchless Pipe Replacement EcoCast Advanced
Optimum Curing Cycles for Precast Concrete
Optimum Curing Cycles for Precast Concrete Dr Norwood Harrison, Technical Support Manager, Humes Mr Tom Howie, Manager Engineered Structures, Humes Prepared for the Concrete Pipe Association of Australasia,
SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS
SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located
UVDB empowered by Achilles
UVDB empowered by Achilles DISAB Centurion: High Performance Wet/Dry Materials Handling Unit DISAB Centurion: High performance vacuum tanker that will vacuum dry or wet material The DISAB can vacuum material
The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
Chapter 8 Design of Concrete Mixes
Chapter 8 Design of Concrete Mixes 1 The basic procedure for mix design is applicable to concrete for most purposes including pavements. Concrete mixes should meet; Workability (slump/vebe) Compressive
Effects of Temperature and Fly Ash on Compressive Strength and Permeability of High-Performance Concrete*
Center for By-Products Utilization Effects of Temperature and Fly Ash on Compressive Strength and Permeability of High-Performance Concrete* By Tarun R. Naik, William A. Olson, Jr., and Shiw S. Singh Report
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown
Detailing of Reinforcment in Concrete Structures
Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For
INMET Konstrukcje sp z o.o. Leading steel forms for prefabrication manufacturer in Poland
The INMET Konstrukcje company is a leading manufacturer of the steel forms in Poland. On the basis of individualised projects the company manufactures modern and complex steel forms for the prefabrication
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General
7 ADVANCED. EFFICIENT. RELIABLE.
7 ADVANCED. EFFICIENT. RELIABLE. GCP UNDERGROUND SOLUTIONS GCP UNDERGROUND SOLUTIONS 1 TYTRO SHOTCRETE SYSTEM 2 ADVANCED FULL SHOTCRETE SYSTEM 10 3 A GLOBAL TEAM Focused on providing our customers the
Cardok Sàrl CP37 CH-1295 Tannay Switzerland Phone: 0041 22 77 66 051 [email protected]
CARDOK CARLIFT Fast access to underground garages Fast, Silent, Discreet, Design, High-Tech Installation to replace an access ramp on private property Dimensions: (Built to measure, all dimensions can
Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS
TABLE OF CONTENTS 2.18 CONCRETE AND/OR CORRUGATED STEEL STORM SEWER... 1 2.18.1 GENERAL... 1 2.18.2 MATERIALS... 1 2.18.2.1 Storm Sewer Pipe... 1 2.18.2.2 Cement Mortar... 1 2.18.2.3 Granular Materials...
Fire-Damage or Freeze-Thaw of Strengthening Concrete Using Ultra High Performance Concrete
Fire-Damage or Freeze-Thaw of Strengthening Concrete Using Ultra High Performance Concrete Ming-Gin Lee 1,a, Yi-Shuo Huang 1,b 1 Department of Construction Engineering, Chaoyang University of Technology,Taichung
VIDEO INSPECTION AND LASER PROFILING IN FLORIDA. AASHTO SOC Conference Larry Ritchie, FDOT August 14, 2013
VIDEO INSPECTION AND LASER PROFILING IN FLORIDA AASHTO SOC Conference Larry Ritchie, FDOT August 14, 2013 PIPE INSPECTION Over the last 5 years, the Department has spent approximately 175 million dollars
Life-365 Service Life Prediction Model Version 2.0
Originally printed in Concrete International and posted with permission from the American Concrete Institute (www.concrete.org). Life-365 Service Life Prediction Model Version 2.0 Widely used software
HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS
BSW HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS BSW is a fully reinforced Pre-Applied system membrane designed for horizontal and vertical external blind-side
REPAIRS TO DAMAGED SEWERS
REPAIRS TO DAMAGED SEWERS A digout is the replacement of sewer or storm water pipes that are either broken or blocked due to tree roots, ground movement or ageing of pipes. When the use of high-pressure
PROPERTIES OF SPRAYED CONCRETE WITH RECYCLED TYRE POLYMER FIBRES
PROPERTIES OF SPRAYED CONCRETE WITH RECYCLED TYRE POLYMER FIBRES Ana Baricevic 1, Dubravka Bjegovic 1, Martina Pezer 1, Nina Štirmer 1 1 University of Zagreb, Faculty of Civil Engineering, Department of
Additional Information. Paint Application
Additional Information Paint Prepared by: International Paint Ltd. www.international-pc.com The information in this guideline is not intended to be exhaustive; any person using the product for any purpose
SECTION 724 PIPE CULVERTS
SECTION 724 PIPE CULVERTS 724.1 Description. This work shall consist of providing pipe or pipe arch of the diameter or shape designated, laid upon a firm bed and backfilled as specified. Where appropriate
Operating, Installation, and Maintenance Instructions
ELKHART BRASS MFG. CO., INC. 1302 WEST BEARDSLEY AVENUE P.O. BOX 1127 ELKHART IN 46515 (574) 295-8330 FAX (574) 293-9914 Operating, Installation, and Maintenance Instructions RAM Personal Portable Monitor
CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements
16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover
Evaluation of In-Place Strength of Concrete By The Break-Off Method. Tarun Naik Ziad Salameh Amr Hassaballah
Evaluation of In-Place Strength of Concrete By The Break-Off Method By Tarun Naik Ziad Salameh Amr Hassaballah Evaluation of In-Place Strength of Concrete By The Break-Off Method By Tarun R. Naik Associate
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene
Wildland Fire Remote Monitor
K A N S A S F O R E S T S E R V I C E KANSAS STATE UNIVERSITY Wildland Fire Remote Monitor For years, fire department administrators have struggled to find an alternative to having firefighters ride on
After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE
86 :: Certificate in Construction Supervision (CIVIL) 12 ROOF 12.1 INTRODUCTION The structure provided to cover the house surface (floor) is known as roof. For different situation and requirement, it is
HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS
HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS Shiwei William Guan, Ph.D. Vice President, R&D and International Business Madison Chemical Industries Inc. 490
CHAPTER 5. Storm Sewer
CHAPTER 5 Storm Sewer A. Introduction All proposed developments shall have a properly designed and constructed storm water conveyance system. This chapter deals only with the conveyance system. Storm water
LIFELINE PIPELINE RESTORATION AND SEISMIC MITIGATION
LIFELINE PIPELINE RESTORATION AND SEISMIC MITIGATION Le Val LUND 1 And P E M ASCE 2 SUMMARY A number of methods are discussed which can be used for lifeline pipeline rehabilitation and improving the seismic
725-R-599 PIPE LINING. (Revised 05-01-12) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE
PIPE LINING (Revised 05-01-12) The Standard Specifications are revised as follows: SECTION 725, DELETE LINES 1 THRU 317. SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING
1.5 Concrete (Part I)
1.5 Concrete (Part I) This section covers the following topics. Constituents of Concrete Properties of Hardened Concrete (Part I) 1.5.1 Constituents of Concrete Introduction Concrete is a composite material
Structural Testing of GeoPolymer Pipe/Culvert Lining
Structural Testing of GeoPolymer Pipe/Culvert Lining Joseph Royer, Ph.D. October 27 th, 2015 What is a GeoPolymer? Not a Plastic Not HDPE/PVC/Epoxy Looks and feels like cement Workability Material Properties
Waste Collection Systems
Waste Collection Systems System Maintenance and Repair Maintenance and Repair Training Objectives To gain an understanding of: System Maintenance and Repair vocabulary System Maintenance and Repair techniques
SECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE
NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE GENERAL a. These specifications may be used in whole or in part by any party without
Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections
Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built
GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
How to build a Pizza Oven in 4 days
How to build a Pizza Oven in 4 days Preparation day (slab) 1. Foundation 1500 deep x 1300 wide x 75mm deep Required 20 bags cement pre mix. If you already have a concrete base, you save this prep day DAY
March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS
March 2006 CW 2140 - SEWER AND MANHOLE CLEANING TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions... 1 3. CONSTRUCTION METHODS... 1 3.1 High
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet
Scuffing Measurement Methodology and Improved Film Coating Systems
OPADRY II Application Data High Performance Film Coating System Scuffing Measurement Methodology and Improved Film Coating Systems PURPOSE Scuffing is a term used to describe coated tablet defects consisting
SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL. 1.01 Testing - General
SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL 1.01 Testing - General Testing shall be of the type and frequency described in each section and summarized in Item 1 of this section. In addition to
STORM AND SANITARY SEWER PIPE REHABILITATION BY THE QUADEX STRUCTURAL LINING REHABILITATION SYSTEM
STORM AND SANITARY SEWER PIPE REHABILITATION BY THE QUADEX STRUCTURAL LINING REHABILITATION SYSTEM OUTLINE PART 1 GENERAL 1.1 Description of Work 1.2 Intent 1.3 Objective 1.4 Work and Components Included
Strength and Workability Characteristics of Concrete by Using Different Super Plasticizers
International Journal of Materials Engineering 12, 2(1): 7-11 DOI: 1.923/j.ijme.11.2 Strength and Workability Characteristics of Concrete by Using Different Super Plasticizers Venu Malagavelli *, Neelakanteswara
Section 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
GENERAL SPECIFICATION FOR CIVIL ENGINEERING WORKS SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS
GENERAL SPECIFICATION FOR CIVIL ENGINEERING WORKS SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS 13.1 13.2 2006 Edition SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS GENERAL
EMPLOYEE FALL PROTECTION
EMPLOYEE FALL PROTECTION You can fall from any height and be seriously injured or killed. In the construction industry, as well as any other industry, when falls from heights happen, they are usually very
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials
STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200
STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES PART 1 - GENERAL A. Description This section includes materials, testing, and installation of precast concrete
SafetyBuletin. Concrete101 Aguidetounderstandingthequalitiesofconcrete andhowtheyaffectpumping
SafetyBuletin Concrete101 Aguidetounderstandingthequalitiesofconcrete andhowtheyaffectpumping Copyright 2008 v1.01 ACPA All rights reserved Manufacturer s recommendations supersede any and all information
all VAC LIFT ALL-VAC-LIFT Phone + 1.832.615.9110 4621 Redstart Street www.vac-lift.com Fax + 1.832.201.9101
ergonomic FORKLIFT vacuum ATTACHMENTs FOR ALL MATERIALS HANDLING FOR LIFTING METAL, WOOD, PLASTIC, STONE, CONCRETE, PAPER, AND MORE In Warehousing, Order Picking, Palletizing, Loading, Conveying, Production.
