THE JOINT CODE OF PRACTICE FOR RISK MANAGEMENT OF TUNNEL WORKS IN THE UK
|
|
|
- Isabella Baker
- 10 years ago
- Views:
Transcription
1 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 1 Logo t/c Published by: The British Tunnelling Society THE JOINT CODE OF PRACTICE FOR RISK MANAGEMENT OF TUNNEL WORKS IN THE UK Prepared jointly by The Association of British Insurers The British Tunnelling Society First edition: September 2003
2 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 2 Contributors to this Code Association of British Insurers D Southcott (Joint-Chairman) A Adeyemo M Brown S Cross R Gallagher O Hautefeuille H Philips H Reiner M Spencer D Thomas T Wylie Engineering Manager, Allianz Global Risks Risk Engineer, Gerling UK Senior Underwriter, Swiss Re Senior Construction Risk Engineering Consultant, Zurich Engineering Underwriter, Allianz AG Construction Underwriting Manager, Scor Underwriting Manager, ERC Frankona Underwriting Manager, Munich Reinsurance Company Construction Underwriting Manager, Zurich Underwriting Manager, Royal & Sun Alliance Construction Underwriting Manager, Gerling UK British Tunnelling Society T Mellors (Joint-Chairman) D Court A Umney E Woods Principal, Mellors Associates Tunnelling Manager, Nuttall Director, FaberMaunsell Director, Arup Reviewed on behalf of the British Tunnelling Society by C Eddie W Grose Engineering Director, Morgan Tunnelling Director, Arup Published by the British Tunnelling Society COPIES OF THE CODE ARE AVAILABLE FROM: BRITISH TUNNELLING SOCIETY ATT: The Secretary The Institution of Civil Engineers 1 Great George Street Westminster London SW1P 3AA TEL: (+44) FAX: (+44) [email protected] PRICE: LXX +LX Post &Handling For on-line purchasing see the BTS website at and follow the hyperlinks to the on-line ordering form British Tunnelling Society 2003 First published in September 2003 ISBN xxxxxxxxx All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted, in any other form or by any other means, without the prior permission in writing of the publisher; or be circulated in any form of binding or cover other than that in which it is published and without a similar condition to this being improsed on any subsequent purchaser. The copyright holder, the British Tunnelling Society has made extensive efforts to check the accuracy of the information and advice contained in this Joint Code of Practice as at the date of publication but the code is not fully comprehensive. The copyright holder does not warrant the accuracy of any information or advice contained in this code and shall not be liable for any, damage or expense whatsoever suffered by any person who relies on or uses information or advice.
3 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 3 CONTENTS 1. OBJECTIVE OF THE CODE COMPLIANCE WITH THE CODE INTRODUCTION RISK ASSESSMENT AND MANAGEMENT CLIENT ROLE AND RESPONSIBILITIES PROJECT DEVELOPMENT STAGE CONSTRUCTION CONTRACT PROCUREMENT STAGE DESIGN STAGES CONSTRUCTION STAGE APPENDICES 1. Definitions and Terms used in this Code Schedule of Deliverables for use by Contract Insurers Model Endorsement Note on drafting: Where this Joint Code of Practice uses the words 'shall' and 'must', the procedure to which it applies is compulsory. Where the word 'should' is used then the procedure is recommended best practice.
4 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 4 1. OBJECTIVE OF THE CODE 1.1. The objective of this Code is to promote and secure best practice for the minimisation and management of risks associated with the design and construction of tunnels, caverns, shafts and associated underground structures including the renovation of existing underground structures, referred to hereafter as Tunnel Works. It sets out practice for the identification of risks, their allocation between the parties to a contract and Contract Insurers, and the management and control of risks through the use of Risk Assessments and Risk Registers. Terms identified in italics in this Code are defined/described in Appendix 1, p It is intended that this Code applies to Contractors All Risks Insurance and Third Party Liability Insurance for Tunnel Works The scope of this Code applies to the project development, design, contract procurement for construction and construction stages of Tunnel Works in the UK and their operation so far as any stipulated maintenance period and the impact of Tunnel Works construction on third parties including infrastructure The Code excludes the operational performance of tunnels and underground structures other than that included within any stipulated maintenance period under a construction contract The Code is intended to operate in parallel with and does not derogate from: a) the recommendations for, and guidance on, health and safety practices in British Standard BS 6164:2001 (Code of practice for safety in tunnelling in the construction industry) and any subsequent revision; b) the requirements of The Construction (Design and Management) Regulations (1994) (CDM) and any subsequent revision; c) statutory duties, responsibilities and requirements of The Health and Safety at Work etc Act (1974) and any subsequent revision; d) statutory duties, responsibilities and requirements of The Construction Health, Safety and Welfare Regulations (1996) and any subsequent revision; e) statutory duties, responsibilities and requirements of the Management of Health and Safety Regulations 1999; f) all other statutory duties, responsibilities and requirements relevant to a particular project; g) all other appropriate British and European Standards relevant to a particular project; h) minimum standards of material and workmanship indicated in the Specification for Tunnelling (2000) prepared by the British Tunnelling Society and the Institution of Civil Engineers and any subsequent revision. 1.6 Where the provisions of the Code are more extensive than any of the recommendations, requirements, duties, responsibilities or standards set out above, the requirements of the Code shall apply in addition. 1.7 Definitions and terms used in this Code are generally those given in British Standard BS6100: Sections 2.2.1(1992); (1999); and 2.2.3(1990) (and any subsequent revision). 1.8 A suggested 'Schedule of Deliverables' for use by Contract Insurers is given in Appendix 2 (p16). It should be acknowledged, however, that the schedule as presented cannot and shall not be seen as exhaustive. The 'deliverables' on any particular Tunnel Works project will be determined by the project requirements, as set out in Contract Documentation. 2. COMPLIANCE WITH THE CODE 2.1 Compliance with the Code as it applies to construction projects involving Tunnel Works, should minimise the risk of physical loss or damage and associated delays. It follows that Insurance contracts covering Tunnel Works should include provisions enabling Insurers to enforce the requirements of the Code, if necessary on pain of suspension or cancellation of the cover. A Model Endorsement to the Insurance contract to ensure compliance is set out in Appendix 3 (p18) to the Code. 2.2 Contract Insurers will require compliance with the Code on all projects where the value of Tunnel Works is 1.0 million or above. For projects where the Tunnel Works element is less than 1.0 million, but where there is significant identified risk to third parties, the Insured should bring this matter to the attention of the Contract Insurers during the agreement of the terms of Insurance cover. This stipulation should not be seen as reducing, qualifying or definitively defining the Insured's duties of disclosure under the Contract of Insurance. 2.3 Contract Insurers will reserve the right to enter and inspect any Tunnel Works insured under an Insurance Contract and/or related documents within a reasonable time once a request is made. The purpose of any inspection is to assess compliance with the Code. 2.4 In the event that the Contract Insurers become aware of what they consider to be a breach of the Code, whether through an inspection or by any other means, the Contract Insurers will make the Client and the Contractor and/or the Designer aware of the nature of the breach. The Contract Insurers may require Insurer s Remedial Measures to be taken and under such circumstances will specify the period within which these shall be completed. 2.5 Where the Contract Insurers consider the breach of the requirements of the Code significant, the Contract Insurers shall confirm the same by notice in writing to the Client and the Contractor and/or the Designer. 4
5 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page Under the terms of any such notice the Contract Insurers will reserve the right to suspend or cancel all cover under the Insurance Contract at a date named in the notice, the date being no earlier than the date named for completion of any remedial measures. If cover is suspended, it will be reinstated once the Contract Insurers are satisfied the required remedial measures have been complied with. 2.7 All Insured parties should pay particular attention to the Notes to the Model Endorsement in Appendix 3 to the Code and to the contents of any endorsement to the Policy seeking to ensure compliance with the Code and should always take advice from their Insurance advisers. 3. INTRODUCTION 3.1. Hazard identification and the management of risk to ensure their reduction to a level 'as low as reasonably practicable' (ALARP) shall be integral considerations in the planning, design, procurement and construction of Tunnel Works. So far as it is reasonably practicable, risk should be reduced through appropriate design and construction procedures Responsibility for risk management shall be explicitly allocated to relevant parties to a contract so that they are addressed adequately and appropriately in the planning and management of a project and that appropriate financial allowances can be made The use of a formalised Risk Management procedure shall be employed as a means of documenting formally the identification, evaluation and allocation of risks. 4. RISK ASSESSMENT AND MANAGEMENT 4.1. General Risk Management is the systematic process of: a) identifying hazards and associated risks, through Risk Assessments, that impact on a project's outcome in terms of costs and programme, including those to third parties; b) quantifying risks including their programme and cost implications; c) identifying pro-active actions planned to eliminate or mitigate the risks; d) identifying methods to be utilised for the control of risks; e) allocating risks to the various parties to the Contract For the purpose of this Code, 'Risk' is defined as the combination of the consequence (or severity) of a 'hazard' and its likelihood, that is: Risk = Consequence/severity of a hazard x Likelihood of occurrence of the hazard A 'hazard' is defined as an event that has the potential to impact on matters relating to a project which could give rise to consequences associated with: a) health and safety; b) the environment; c) the design; d) the programme for design; e) the costs for the design; f) the construction of the project; g) the programme for construction; h) the costs associated with construction; i) third parties and existing facilities including buildings, bridges, tunnels, roads, surface and subsurface railways, pavements, waterways, flood protection works, surface and subsurface utilities and all other structures/ infrastructure that shall be affected by the carrying out of the works Hazards shall be identified and evaluated on a project-specific basis and their consequent risks shall be identified and quantified by Risk Assessments through all stages of a project (Project Development Stage, Construction Contract Procurement Stage, Design Stages, Construction Stage and operational stage for any stipulated maintenance period) The nature of the hazards (and hence their consequent risks) will be dependent on the stage of a project under consideration Risk Assessment Risk Assessment is the formalised process of identifying hazards and evaluating their consequence and probability of occurrence together with strategies as appropriate for preventative and contingent actions Risk Assessments required at each stage of a project shall be summarised in appropriate Risk Registers. Risk Registers shall clearly indicate the party responsible for the control and hence management of an identified risk (respecting any Contract responsibilities and liabilities), as well as contingency measures available for the mitigation of the risk The parameters to be used in the assessment of risks, in terms of probability of occurrence of a hazard and its severity of impact/consequence on cost, programme, environment, third parties and existing facilities shall be both project specific and appropriate to the project stage under consideration Insurance should not be considered as a contingency or mitigation measure in risk assessments for Tunnel Works. 5
6 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page Risk Registers The processes of Risk Assessment and the subsequent preparation of Risk Registers are required to identify and clarify ownership of risks and shall detail clearly and concisely how the risks are to be allocated, controlled, mitigated and managed. The systems used to track risks shall enable the management and mitigation of risks through contingency measures and controls to be monitored through all stages of a project Risk Registers shall be 'live' documents that are continually reviewed and revised as appropriate and available for scrutiny at any time. They shall provide an auditable trail through the life of a project to demonstrate compliance with the Code. They shall identify hazards, consequent risks, mitigation and contingency measures, proposed actions, responsibilities, critical dates for completion of actions and when required actions have been closed out. 5. CLIENT ROLE AND RESPONSIBILITIES 5.1. The Client shall have demonstrable technical and contract management competence appropriate to the type, scope and extent of the project to be planned, designed and procured for construction in: a) Project Development Stage studies; b) Design Stages; c) Construction Contract Procurement Stage procedures including selection of a Form of Contract; d) Construction Stage and management Such competence shall be demonstrable and evaluated on the basis of: a) the Corporate Competence of the Client body in relation to the proposed project and/or; b) the competence of individual staff within the Client body including their availability for the project In the absence of appropriate experience for any part of the project, the Client shall appoint a Client's Representative. The appointment of a Client's Representative should be based on a structured selection exercise. The criteria for the selection and appointment of a Client's Representative should be similar to those with which the Client assesses his own capability at the outset and include consideration of the following: a) the Corporate Competence of the company including references from previous clients (which should be followed up); b) the competence of staff; c) named Key Personnel; d) an assessment of the project planning competence including the planning, procurement, execution and interpretation of site and ground investigations; e) design capability including competence in the type of Tunnel Works to be designed and associated construction techniques; f) management or procurement (in the case of design-construct arrangements) of design, Design Checking and review procedures, CDM and the preparation of Risk Assessments; g) presentation by Key Personnel proposed for the project and confirmation of their availability; h) financial stability of the company/organisation The Client shall take full responsibility for the information prepared by him (or by his Client's Representative) and issued to tenderers as 'works information' The Client shall take into account all other matters relating to his role and responsibilities referred to in subsequent sections of this Code. 6. PROJECT DEVELOPMENT STAGE 6.1. General For the purpose of this Code, the Project Development Stage includes: a) project feasibility studies; b) site and ground investigations; c) assessment and evaluation of project options and the identification of a preferred project option and Form of Contract for construction (for example design and construct or design-construct); d) project design studies appropriate to the Form of Contract for construction The scope of work required under the Project Development Stage shall not be constrained by programme considerations or the terms and conditions for the appointment of a Client's Representative. The Client shall ensure that sufficient time and budget are available to: a) investigate and subsequently demonstrate the technical viability of a project prior to proceeding to the Construction Contract Procurement Stage; b) prepare designs appropriate to the Form of Contract to be adopted Site and Ground Investigations The nature, scope and extent of site and ground investigations to be carried out shall be based on the nature, scope and extent of the project, its location and its geological/hydrogeological environments. Site and ground investigations shall be designed, planned and procured by suitably competent personnel*. *See, for example, Site Investigation in Construction - Document 2 - Planning, procurement and quality management prepared by the Site Investigation Steering Group, published by Thomas Telford Services Ltd,
7 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page Site investigations shall be carried out in accordance with British Standard BS5930 (Code of Practice for Site Investigations) and shall take cognisance of British Standard BS6164. The basis (including standard) on which site investigations are carried out should be clearly stated. Site/ground investigations carried out by or on behalf of the Client should be phased appropriate to the pertaining physical and geological environments and be so designed and planned to: a) identify, so far as reasonably practicable, artificial (man-made) and natural (geological/hydrogeological) hazards (including gases such as methane, radon) and hence enable consequent risks to be assessed (which influence the design and construction of the project, including those that affect third parties); b) provide sufficient information on pertaining site conditions, ground (including artificial and natural ground) and groundwater conditions, previous history of the project site including any constraints of an engineering significance relevant to the works to be carried out (such as mining/mineral extraction, contamination) in order to enable realistic and reliable assessments of different tunnelling methodologies (including temporary and permanent support/lining requirements and health and safety issues) to be made in terms of technical viability, cost, programme and impact to third parties; c) enable the financial and technical viability of the project to be confirmed from preliminary design studies; d) enable alignment options to be compared and the feasibility of the options in terms of cost, programme and Constructability to be evaluated Site and ground investigations shall be executed by competent organisations for such work and supervised by suitably competent personnel by (or on behalf of) the Client to ensure that the results of the investigations are reviewed contemporaneously and the scope of the investigations is amended or revised to suit the conditions being encountered in relation to the proposed nature and scope of the project The results of site and ground investigations, including laboratory and field testing, shall be recorded factually in accordance with recognised standards, for example, BS 5930: Code of Practice for Site Investigation, BS 1377: Methods of Test for Soil for Civil Engineering Purposes, International Society for Rock Mechanics' Suggested Methods for Rock Characterisation and Monitoring. The method of reporting should be stated clearly and unequivocally. Any departure whatsoever from any Standards, Codes or other practices referred to or acknowledged in the factual reports shall be identified and clarified so as to obviate any ambiguity in the reporting of factual data Assessment and Evaluation of Project Options Assessments and evaluations of project options should be carried out during the Project Development Stage by the Client (or on his behalf by the appointed Client's Representative). For a selected alignment or alignment options, such assessments and evaluations should take into account: a) the geology (including the potential for methane generation or other gases of a potentially harmful nature) and the hydrogeology (as characterised by site and ground investigations); b) tunnelling methodologies (and other methodologies as appropriate associated with works such as caverns, shafts, adits) appropriate to the nature of the ground and the environment (for example, open- and closedface tunnel boring machines, partial face tunnelling machines (roadheaders, excavators), drill and blast) for the selected alignment or the alignment options; c) temporary and permanent ground support systems (for example, sprayed concrete linings, rockbolts/dowels, pre-cast concrete segmental linings, cast-iron segmental linings, cast in-situ concrete linings); d) ground and groundwater treatment measures (for example, the use of compressed air, grouting, dewatering/depressurisation, ground freezing) and their impact on the environment and to Third Parties (for example, groundwater abstraction/depressurisation leading to settlements, noise, vibrations); e) ground movements and settlements at the ground surface and their impact on a Third Party or subsurface ground movements and their impact on buried structures such as utility services, adjacent tunnels and underground structures; f) environmental considerations including dust, noise, vibrations, traffic, plant movements; g) associated costs, health (including occupational health considerations), safety and programme implications; h) appropriate forms of contract; i) hazardous materials including gasses, chemicals, other pollutants or naturally occurring substances that could be injurious to health or affect durability; j) all other particular factors relevant to the proposed project location, geology and environment The assessments and evaluations of project options shall include the identification and evaluation of associated option-related hazards and consequent risks. These shall be presented in formalised Risk Assessments for each identified project option. The Risk Assessments shall be continually reviewed and revised as appropriate during the Project Development Stage to take into account the results of site and ground investigation results and further and better information that becomes available during this Stage For identified project options (in terms of, for example, alignment, tunnelling methodology, environmental/third Party considerations, etc), the Client should establish (or have established on his behalf) overall estimates of cost and time for each project option with costs assigned to programme activities. Furthermore, cost and programme 7
8 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 8 sensitivity tests should be undertaken to determine the projected out-turn costs and programme durations in relation to project-option related risks and appropriately assigned confidence levels, taking into account possible mitigation measures to obviate or minimise identified risks By such means, the Client shall determine (or have determined on his behalf) a technically viable preferred project option or options Project Development Design Studies The Client should prepare (or have prepared on his behalf) a preliminary scheme design or detailed scheme design appropriate to the Form of Contract to be adopted (see Section 8) for the preferred project option (or options). The preliminary scheme design or detailed scheme design shall take full cognisance of the requirements of The Construction (Design and Management) Regulations and BS 6164 (see Section 9) A Risk Assessment shall be carried out and a Risk Register shall be prepared for the preferred project option (or options). This Risk Register should include the perceived hazards and associated risks for the preferred project option (or options) and indicate potential mitigating measures with comprehensive explanations for their basis, based on the studies carried out during the Project Development Stage. This Risk Register shall be included within the information provided to tenderers during the Construction Contract Procurement Stage. 7. CONSTRUCTION CONTRACT PROCUREMENT STAGE 7.1. General For the purpose of the Code, the Construction Contract Procurement Stage includes: a) the preparation and issue of Contract Documentation for Tunnel Works for tendering purposes; b) the selection or Pre-qualification of contractors for tendering; c) tender assessment The Preparation of Contract Documentation for Tendering Purposes The preparation of Contract Documentation for tendering purposes shall take due regard of the type of contract to be awarded (for example, design and construct or design-construct) and the Form of Contract (for example standard forms of Contract published by the Institution of Civil Engineers, the Institution of Chemical Engineers or modifications to standard forms of Contract) The selection of a Form of Contract by the Client and the drafting of its detailed terms should take due regard of the allocation of risks to the parties to the Contract (under the proposed Contract) and consequently the liabilities to the parties to the Contract All Contract Documentation (as well as subcontract documentation for Tunnel Works as appropriate) shall clearly demonstrate how the parties to each contract are to comply with this Code. Consequently, such contract (and subcontract) documentation should clearly and explicitly set out the responsibilities and duties of the parties to each contract and the responsibility for meeting the cost of Insurer s Remedial Measures Contract Documentation (as well as sub-contact documentation for Tunnel Works as appropriate) shall include full disclosure of those hazards and associated risks identified at the Project Development Stage for the preferred project option (or options) in the form of a project Risk Assessment Contract Documentation (as well as subcontract documentation for Tunnel Works as appropriate) shall include Ground Reference Conditions or Geotechnical Baseline Conditions* prepared by the Client (or prepared on his behalf) or shall require each tenderer to submit with their tender their own assessment of Ground Reference Conditions or Geotechnical Baseline Conditions, the requirements of which shall be defined and fully described in the Contract Documentation When prepared by (or on behalf of) the Client, the Ground Reference Conditions or Geotechnical Baseline Conditions shall be issued to tenderers as integral and formative information on which tenders shall be based and the Client shall take responsibility for the information so issued When prepared by a tenderer, the Ground Reference Conditions or Geotechnical Baseline Conditions shall be used by the Client in the tender assessment process Ground Reference Conditions or Geotechnical Baseline Conditions prepared either by the Client or by a tenderer shall form part of the Contract and shall provide the basis for comparison with ground conditions encountered in relation to those assumed and allowed for at the tender stage by the Contractor. The Ground Reference Conditions or Geotechnical Baseline Conditions shall provide the baseline against which encountered conditions can be assessed and compared. The Ground Reference Conditions or Geotechnical Baseline Conditions shall also identify hazards appropriate to the site and ground conditions established from the investigations to permit associated risks to be identified and catered for at time of tender, consistent with the Contract Documentation requirements Contract Documentation (as well as subcontract documentation for Tunnel Works as appropriate) shall clearly identify key Method Statements to be submitted with a tender that the Client or his Representative considers critical for the construction of the works Notwithstanding the issue of a project Risk Register in the contract documentation, tenderers are required to prepare and submit their own project Risk Regsiter for submission with a tender as well as specific Risk Assessments *See Geotechnical Baseline Reports for Underground Construction Guidelines and Practices published by the America Society of Civil Engineers,
9 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 9 appropriate to the methods of working allowed for (described in Method Statements) with descriptions of risk mitigation/control/contingency measures Contract Documentation (as well as subcontract documentation for Tunnel Works) should clearly set out the information required for assessment of tenders together with the criteria and their weighting on which the evaluation of the tenders will be based Sufficient and adequate time and resources should be allocated for the preparation of Contract Documentation before release for tendering purposes for Tunnel Works without the need for subsequent supplementary documentation (including addenda, corrigenda) during the tendering period Selection or Pre-qualification of Contractors for Tendering Purposes This is a key activity and shall have dedicated time and resources allocated by the Client. The selection or Pre-qualification of contractors for tendering purposes shall require contractors to demonstrate relevant experience The requirements for selection or Pre-qualification shall be prescribed. Appropriate information to be sought should include: a) experience obtained in the last 10 years with a list of relevant projects and Clients. Previous Clients should be contacted for references (for example on matters relating to the contractor's performance, working relationships); b) performance details on previous relevant projects; c) financial status; d) any proposed 'joint venture' arrangements; e) key staff available with the required qualifications; f) current work load and available resources; g) proposed use of subcontractors and supply chain and details of any long term working relationships; h) a focused technical submission on the proposed project which demonstrates technical understanding of the requirements for the project Time for Tendering Provision shall be made by the Client for reasonable time for tendering to reflect the type of contract, the complexity of the project and the requirements of the contract documentation in terms of a tender submission Tender Risk Register For all contracts, the tenderer shall be required through the Contract Documentation, to provide the Tender Risk Register for the benefit of the Contract Insurers. This Tender Risk Register should demonstrate how the tender submission adequately and appropriately caters for risks identified and to be allocated to the Contractor including management and control procedures, proposed contingency measures and the cost and programme implications of the implementation of contingency measures. 8. DESIGN STAGES 8.1. General For the purpose of the Code, Design Stages include preliminary and detailed designs for permanent Tunnel Works and temporary works designs during the Construction Stage of a project The principles to be adopted during the Design Stages shall apply equally for the designs for permanent works and the designs for temporary works, howsoever defined in the Code Prospective Designers should be provided with a brief, be it from the Client or Contractor. The prospective Designers should review this brief and identify any deficiencies or omissions that could lead to a risk to the project. The Client or Contractor shall be required to address these issues and make adjustments to the terms and scope of engagement prior to awarding the design commission Transfer of Information Between Designers Where a design is transferred between Designers for different Design Stages of a Tunnel Works project, the Client shall ensure that all information developed and collated during the previous Design Stage is made available to the Designer of the following stage, including Risk Assessments and Risk Registers The Designer appointed and responsible for the following Design Stage shall be required to evaluate this information and make recommendations to the employing party (Client or Contractor) as appropriate for further investigations and/or studies for the subsequent Design Stage to fulfil the brief for appointment The Design Process The fundamental objective of the design process is that of achieving a robust design, that is a design where the risk of failure or damage to the Tunnel Works or to a Third Party from all reasonably foreseeable causes, and including health and safety considerations, is extremely remote during the construction and the design life of the Tunnel Works. High consequence but low frequency events that could affect the works or a Third Party shall also be considered The Designer shall prepare documentation which shall include but not necessarily be limited to: a) a description of the element to be designed; 9
10 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 10 b) the design requirements and criteria to be adopted; c) a geotechnical assessment that shall evaluate the geological and geotechnical information available (including methane/radon gas generation, ground and groundwater contamination) and ascribe design values for the pertaining assessed ground and groundwater conditions for the purpose of design with justification in the light of information provided (including Ground Reference Conditions and/or Geotechnical Baseline Conditions); d) a description of the method of design (including reference to any applicable Codes and/or Standards); e) a description of the method(s) of analysis to be used for the design and justification thereof; f) a Design Risk Assessment which shall consider the impact on the design and hence its implementation (not only on the Tunnel Works but also to a Third Party) of any realistic variation in the design criteria and/or design values adopted, based on the information available in relation to the anticipated/proposed method(s) of construction. The Design Risk Assessment shall take account of potential failure mechanisms and include mitigation/contingency measures appropriate to the anticipated/proposed method(s) of construction; g) the checking procedure to be implemented for the Design Calculations, analyses and assessments should also consider intermediate stages of construction The design process shall include, where appropriate, sensitivity studies to assess the impact of: a) construction tolerances; b) variation in geotechnical design values; c) variation in materials characteristics; d) variation in workmanship and geometry; e) methods of construction and the implementation of mitigation/contingency measures; f) natural Perils exposure in the region of the project such as flood, storm, seismic or tidal effects The design process shall include an assessment of the impact of construction on Third Party infrastructure. In this respect, the Designer shall assemble as far as reasonably practicable all available records of foundations and other structures/artificial obstructions which could affect and/or be affected by the Tunnel Works Design Checks All designs shall be subject to a design check to ensure that a robust design has been achieved The extent and scope of design checks shall be appropriate to: a) the complexity, degree of difficulty and type of construction of the Tunnel Works (including excavation/support sequencing for intermediate construction stages if applicable); b) the level of risk (to the Tunnel Works and/or a Third Party) assessed from the Design Risk Assessment; c) any statutory or other requirements by a Client or a Third Party Design programmes shall allow for sufficient time for the appropriate level of checking Constructability Issues The Designer shall ensure that adequate construction expertise is available to undertake formal reviews of the design to assess and confirm the appropriateness of the design in terms of Constructability, including health and safety considerations in relation to BS The Designer shall take account of the impact of staged or sequential excavations to ensure the feasibility of construction stages and hence the appropriateness of the design. Provision shall be made by the Client for ensuring that the Designer's intent/requirements are adhered to during construction The Designer shall ensure that the site investigation is planned and designed to obtain, inter alia, ground and groundwater information and geotechnical properties appropriate for the construction of the Tunnel Works, recognising the likely method(s) of tunnelling/excavation that may be employed Where appropriate, the design shall detail excavation/support sequences and identify appropriate monitoring measures during the works for the range of anticipated ground and groundwater conditions and shall also include for the provision of contingency measures. The Designer shall ensure the design is robust in terms of geotechnical variability, workmanship and construction tolerances Where an 'observational method' is to be used, there must be compliance with the requirements of CIRIA Report R Validation of Design During Construction Provision shall be made in a Contract for sufficient monitoring of Tunnel Works during the Construction Stage to ensure that the design being implemented remains valid at all times. Such monitoring shall include the monitoring of the performances of the ground and groundwater, the Tunnel Works' structures and adjacent structures potentially affected by the Tunnel Works as appropriate to the method(s) of working adopted during the Construction Stage. 9. CONSTRUCTION STAGE 9.1. General This section of the Code identifies the elements of current best practice that a Contractor is required to comply with as a minimum - in addition to any statutory requirements - prior to and during construction and should be read in conjunction with the remaining sections of the Code. 10
11 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page Pre-construction Activities Following Contract Award, but prior to commencing on site, time shall be allowed in the programme for pre-construction activities including: a) the preparation and submission of a Project Risk Management Plan incorporating a Construction Stage Project Risk Register; b) the preparation and submission of Health and Safety, Quality, and Environmental Plans; c) the preparation of a Management Plan; d) the identification, design (as necessary under the Contract) and procurement of items which involve long lead items (such as tunnel boring machines, for example); e) pre-construction Planning and Method Statements; f) obtaining all necessary statutory consents; g) Constructability reviews Risk Management Procedures The Project Risk Management Plan shall include the Construction Stage Project Risk Register which records all project-related risks identified for the Construction Stage of the project and includes the project-related risks brought forward from the Client's pre-contract Risk Register The Construction Stage Project Risk Register shall identify the owners of the risks, actions and measures required to mitigate the impact of the identified project-related risks on the Tunnel Works. The Construction Stage Project Risk Register may include the results of the health and safety risk assessments related to the construction works/ activities (in respect of statutory or legislation requirements such as CDM) The Project Risk Management Plan shall identify the means and methods for: a) regular monitoring and review of the Construction Stage Project Risk Register by risk owners appropriate to the construction programme and activities for the Tunnel Works; b) the means of identifying and formally recording hazards and associated risks which arise during the course of the Construction Stage; c) identifying progress in the reduction/mitigation of the overall impact and number of risks; d) updating of the Construction Stage Project Risk Register and hence identifying any changes to the Project Risk Profile during the Construction Stage of the Tunnel Works Contractors' Staff and Organisation Prior to commencing work on site and thereafter whenever there is a significant change, as required by the Contract, the Contractor shall submit an overall Site Organisation Chart. This Chart should identify the reporting structure and lines of communication of Key Personnel and those persons nominated for safety critical work and Self-Certification (where required under the Contract) The Site Organisation chart shall be in sufficient detail to enable the Client or the Client's Representative to identify how and with whom the Contractor intends to manage the works. The chart shall be submitted together with the names and Curriculum Vitae of all Key Personnel to demonstrate the competence of those persons who will be employed in the management of the Tunnel Works In addition to the names and Curriculum Vitae of all Key Personnel, the Contractor shall provide details of the roles and responsibilities of those personnel identified Within the period stipulated in the Contract, the Contractor shall provide for approval his policy on employment of skilled operatives. The policy should set out how the Contractor shall ensure that all operatives have the necessary competency to carry out the processes required for the construction of the works and shall include details of the Contractor's training policy Within the period stipulated in the Contract, the Contractor shall provide a training plan which shall indicate how he intends to ensure that all staff are and will remain adequately and suitably trained for the positions and responsibilities that they are to hold As part of the organisation structure, the Contractor shall develop and implement a procedure for the dissemination of information including the methods he shall employ to ensure that feedback from sections of the works are communicated to all parts of the project Constructability Throughout the duration of any Tunnel Works contract, the Contractor shall carry out Constructability reviews jointly with the Designer. The frequency of such reviews shall be consistent with the requirement of ensuring that the construction methods being employed and to be employed are suitable and appropriate in the light of the nature and scope of the works and the monitoring of the works Methods and Equipment Prior to commencement of any operation or process in connection with construction of the Tunnel Works, the Contractor shall provide the Client or the Client's Representative with fully detailed Method Statements, Inspection and Test Plans and Risk Assessments as required and defined under the Contract Method Statements shall clearly and unequivocally detail the methods and resources with which the Contractor 11
12 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 12 intends to construct the works and should cover all aspects of the works including specification, design, environment, health and safety and quality. Method Statements shall reflect and demonstrate compliance with accepted current best practice and standards for the operations intended to be carried out Inspection and Test Plans shall clearly and unequivocally detail how the Contractor intends to inspect, check and certify the works throughout the construction process and should detail 'hold' points requiring approval by others such as the Designer, Client or Client's Representative in accordance with the Contract requirements. Inspection and Test Plans should identify those sections of the specification which are being referred to and the tolerances permitted Risk Assessments shall deal with specific risks associated with the construction methods, plant, equipment and materials to be employed including fire related risks associated with the working environment, construction methods, specific plant, material and equipment to be used in the construction of the works, having due regard to BS 6164 on such matters. Risk Assessments shall demonstrate that the hazards and associated risks involved in the construction process have been fully identified and assessed. Risk Assessments shall demonstrate that the appropriate Method Statement has included all mitigation necessary to reduce the impact of the risk to acceptable levels The Method Statements and Inspection and Test Plans shall indicate what monitoring and checking shall be carried out, by whom and at what intervals. Quality records shall be produced and provided to satisfy compliance with the Contract requirements. Procedures for dealing with non-compliances shall be included A register of approved signatures shall be maintained together with authority levels for all staff employed in the checking and certifying of Inspection and Test Plans and quality records In the case of a Self-Certification Contract, the Contractor shall additionally demonstrate how he shall control and maintain the independent supervision of the construction checking process The Method Statements shall identify what equipment and/or method it is intended to be used for the works and the criteria for selection of that method or equipment, particularly with regard to the risks identified in the Risk Register Where project critical equipment or methods such as tunnel boring machines (TBMs) or sprayed concrete linings (SCL) are to be used, a separate statement shall be prepared setting out the basis of the selection of the equipment or method with regard to operation, ground conditions, safety systems, maintenance, environmental monitoring, access, settlement, emergency procedures Management Systems Following award and prior to commencement on site, the Contractor shall provide the Client or the Client's Representative with a copy of his Health and Safety Plan, Quality Plan and Environmental Plan together with an overall Management Plan In addition to the requirements of the Health and Safety, Quality and Environmental Plans, the overall Management Plan shall identify and demonstrate the systems the Contractor intends to use to manage and control the construction process with regard to the requirements of the Contract and also with regard to identifying that the Contractor is working to current accepted best practice This Management Plan should include as a minimum procedures for the management and control of the following: a) documents; b) design; c) Self-Certification (where required under the Contract); d) procurement of materials, equipment, and designs (either for temporary or permanent works, according to the requirements of the Contract); e) planning; f) training; g) emergency procedures; h) control and calibration of test and inspection equipment; j) survey. If any of the above are included in other project-specific Plans (such as the Quality Plan for example), the Management Plan should merely include a reference to the relevant sections of the other project-specific Plans to avoid duplication The Contractor shall provide the Client or the Client's Representative with an Audit Plan that demonstrates how he intends to audit the construction process with both internal and external audits The Contractor shall implement a regular management review of all systems and procedures to ensure continuing compliance with the requirements of the Contract and shall update all procedures as necessary Monitoring Monitoring of the construction processes shall be carried out by use of Inspection and Test Plans, audits and management reviews For any process, the Method Statements and Inspection and Test Plans shall ensure that the critical parameters are clearly identified and monitored in such a way as to be able to be confirmed by audit that they are in compliance 12
13 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 13 with the requirements of the Contract and/or Third Parties involved With particular regard to Tunnel Works in urban areas and where Third Party equipment or structures are at risk, Method Statements shall clearly identify 'trigger levels' at which contingency action shall be taken. The Method Statements shall clearly identify the reporting roles and responsibilities and what actions are to be taken and by whom at each trigger level Where risks are identified from the Risk Register that have a high severity rating but which have been mitigated by the construction methods to an acceptable level, the Contractor shall provide the Client or the Client's Representative with an outline Emergency and Contingency Plan for dealing with the risk in the event that it is realised Management of Change Any changes to the design and/or method of working which result in greater assessed risks to the project or a Third Party shall be notified to the Contract Insurers immediately All Value Engineering proposals submitted for approval to the Client or the Client's Representative shall include a statement setting out in full, technical benefits as a consequence of the proposals together with any variation in the Project Risk Assessments. Full specifications and drawings as appropriate shall be prepared and approved by the Client before implanting the change All design changes instructed by the Client or the Client's Representative, or design changes introduced by the Contractor on design-construct contracts, during the Contract shall be reviewed by the Contractor and revised Risk Assessments submitted as appropriate for approval prior to carrying out the works Any modifications to safety critical equipment and/or procedures shall be undertaken only by competent persons and be subject to review by the Designer and the Contractor Regular monitoring of ground conditions shall be undertaken and any significant changes from those envisaged at commencement of the Contract shall be reviewed with the Client or the Client's Representative. The significance and potential impact of such changes in ground conditions shall be evaluated in relation to Method Statements, Inspection and Test Plans and Risk Assessments. The overall Management Plan and Risk Register shall be revised as necessary All changes in the construction process or design from that envisaged at commencement of the Contract shall be identified, reviewed and the Risk Register revised accordingly. 13
14 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 14 APPENDIX 1: Definitions and Terms used in this Code ALARP - 'as low as reasonably practicable' A principle used for defining a level of risk that can be achieved and that is acceptable to all those that may be affected by the risk being realised. Client The final owner of the Tunnel Works and the purchaser of goods or services. The purchase is generally governed by a contract. Client Brief The performance specification created by the Client that details the requirements of the completed works. Within the brief there will be details of intended usage of the works, capacity requirements, and lifespan specification. Additionally there should be an indication of overall budget available and proposed time for delivery. Client's Representative An individual, or company, that has been retained by the Client to look after the interests of the Client. Code The Joint Code of Practice for Risk Management for Tunnel Works in the United Kingdom. Constructability An objective review of the Design by experienced individuals to assess the practicalities of constructing the designed works. Construction Contract Procurement Stage The stage of a Tunnel Works project which involves the preparation and issue of Contract Documentation for tendering purposes following the selection or pre-qualification of contractors for tendering and tender assessment. Construction Stage Project Risk Register A register that records all project-related risks identified for the Construction Stage of the project and includes and identifies the project-related risks brought forward from the Client's pre-contract Risk Register, the owners of the risks and actions and measures required to mitigate the impact of the identified project-related risks on the Tunnel Works. Construction Stage The stage of a Tunnel Works project that involves all aspects relating to the implementation of designs for completion of the works to the requirements of the Client or Client's Representative. Contract Award The award of a construction contract to a principal contractor by the Client. Contract Documentation Documentation that defines the scope of works, the nature, the Form and Conditions of Contract (including specifications for the works), and the apportionment of risk and payment mechanisms. Contract Insurers The collective nomenclature for the providers of the Contractors All Risk Insurance for a Tunnel Works project. The Contract Insurers may be a single company, or a number of insurers operating in a co-insurance arrangement. In the instance of co-insurance there is likely to be a nominated Lead Insurer who will be the main point of contact for the Insured. Contractor The organisation appointed by the Client for the implementation for the Tunnel Works, appropriate to the Form of Contract. Contractors All Risks Insurance Under Contractors All Risk Insurance (commonly referred to as 'CAR Insurance'), insurance cover is typically provided for physical loss or damage to the contract works and may include/allow for physical loss or damage to construction plant and equipment or machinery. In addition it may also include cover for removal of debris; architects, engineers or surveyors fees; and expediting expenses. A 'CAR' policy may be effected by the Client or by the Contractor engaged for the work and can include all subcontractors. The cover typically begins at the start of the work except for items of construction plant and the like which are generally only covered after they have been unloaded at the site. The cover terminates when the completed project is handed over or any completed part is taken over or put into service. In respect of construction plant and the like, cover terminates when such equipment is removed from the site. A maintenance period, usually 12 months, can be incorporated in addition to the period of construction. The maintenance cover is for physical loss or damage to the works occurring during the maintenance period stipulated in the provisions of the clauses in the contract relating to the works. Corporate Competence The competence of an organisation as a whole gained through precedent experience in relation to the nature, form and extent of Tunnel Works proposed and the services to be provided. Design Checking The management process for checking the robustness of the Design, including numerical accuracy of the calculations, the dimensional accuracy of the drawings and the constructability of the overall concept. Design Stage(s) The stage or stages of a Tunnel Works project which involve the preparation of preliminary and/or detailed designs for permanent Tunnel Works and temporary works designs during the Construction Stage. Design Statement A document that details the method(s) of design, the parameters to be used in the design, the standards to be adhered to when undertaking the design. Designer The individual/organisation chosen to undertake the design process. Different designers may be appointed for different stages of the design process. The designer is typically a firm of consulting engineers but may be the design unit of a contractor, or an individual. 14
15 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 15 Form of Contract The contractual arrangement between the purchaser of services/goods and the provider of the services/goods. There are standard Forms of Contract that cover all procurement routes. Geotechnical Baseline Conditions and/or Ground Reference Conditions Definitive statements about the nature, form, composition and structure of the ground (both artificial and natural) and groundwater together with geotechnical properties of the ground which serve as a basis for construction Contract tendering purposes and for the subsequent application of the contract with respect to the conditions actually encountered during Tunnel Works. The Geotechnical Baseline Conditions and/or Ground Reference Conditions represent a contractual definition of 'what is assumed will be encountered'. However, the provision of such Conditions in the Contract is not a warranty that the Conditions will be encountered. Inspection and Test Plan A description and definition of the methods and procedures to be used to maintain and check quality within the construction process. Insured The Insured is the collective nomenclature for the insured parties named in the Insurance Policy. This is likely to include the Client and the Principal Contractor, and may include subcontractors and design professionals (for their on-site activities). Insurer's Remedial Measures Those measures required by contract Insurers following identification of a breach of the Code to ensure subsequent compliance with the Code. Key Personnel Named staff identified by an organisation that are nominated to undertake important roles within the work scope required. Management Plan A plan, in addition to the requirements of Health and Safety, Quality, and Environmental Plans, that identifies and demonstrates the systems and procedures the Contractor will use to manage and control the construction process. The Management Plan should include, as a minimum, procedures for the management and control of Documents, Design (where required), Self-Certification (where required), Procurement, Planning, Training, Survey and Control and Calibration of Test and Inspection Equipment. Method Statement A document prepared in advance of undertaking design or construction work that details the methods to be utilised, the people required to undertake the work, the equipment required to undertake the work, and any supporting documentation necessary to undertake the work. In addition the Method Statement will contain an assessment of the hazards that may be encountered when undertaking the work, and any mitigation measures that are to be taken during the work to reduce the probability of occurrence of a hazard to ALARP. Pre-qualification A process used by employers to assess prospective suppliers against pre-determined criteria. Project Development Stage The stage of a Tunnel Works project which includes project feasibility studies, site and ground investigations, and the assessment and evaluation of project options including identification of a preferred project option (or options) and Form of Contract for construction. Project Risk Profile An assessment of the residual risks at any point in time during Tunnel Works which potentially impact on the outcome of the project. Risk Assessment The formalised process of identifying hazards and associated risks, of evaluating their consequence and probability of occurrence, and of preparing strategies as appropriate for preventative and contingent actions. Risk Management The overall systematic process of Risk Assessment and providing for risk mitigation and control. Project Risk Management Plan A document identifying the means and methods for the regular monitoring and review of the Construction Stage Project Risk Register, of formally recording hazards and associated risks which arise during the course of the Construction Stage; of recording progress in the reduction/mitigation of the overall impact/number of risks; and of updating of the Construction Phase Project Risk Register and hence any changes to the Project Risk Profile during the Construction Stage of the Tunnel Works. Risk Register A formalised record of risks identified from the Risk Assessment process including full descriptive details of mitigation and control measures, risk owners and with appropriate cross-references. The Risk Register is the primary means of recording and monitoring the Risk Management process. Self-Certification A Quality Assurance process whereby the Contractor self-inspects and certifies that the Works are compliant with the Design and Contract requirements. Tender Documentation Documentation prepared and issued by a Client when requiring the services or goods of a supplier that detail the services or goods required and issued. Third Party A party that is affected by the actions of two other parties that are in a contractual relationship. Third Party Liability Insurance Insurance purchased to cover the financial consequences of damage to third party property or bodily injury to third parties arising from the performance of the Contract. Tunnel Works Tunnels, caverns, shafts and associated underground structures howsoever constructed and including the renovation of existing underground structures. Value Engineering The process of adding value to a project by for example reducing cost and/or time during the design and construction process. 15
16 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 16 APPENDIX 2: Schedule of Deliverables for use by Contract Insurers Clause Deliverable Prepared by Scope and intent PROJECT DEVELOPMENT STAGE Site Investigation - Factual Reports Client To assess ground conditions and obtain an understanding of the level of investigations carried out Risk Assessments of Project Options Client To demonstrate that risks associated with project options have been assessed at an early stage CONSTRUCTION PROCUREMENT STAGE Contract Documentation Client To assess level of information supplied to tenders including disclosure of hazards and associated risk identified during the Project Development Stage and Ground Reference Conditions/ Client or Tenderers To assess identified site and ground conditions hazards established from investigations Geotechnical Baseline Conditions Key Method Statements Tenderers To assess construction methods, materials and plant identified by tenderers Risk Assessment Tenderers To assess tenderers' perceptions and attitude to risk Tender Risk Register Tenderers To demonstrates how the tender submission adequately and appropriately caters for risks identified and to be allocated to the Contractor. DESIGN STAGES Design Brief Client/Contractor To confirm that scope of works has been identified appropriately Schedule of Third Party Infrastructure Designer To demonstrate that Third Party exposure and an assessed level of damage have been carried out Constructability Reviews Designer To demonstrate that appropriate assessments of the constructability of the design have been carried out, such assessments including health and safety considerations. CONSTRUCTION STAGE Project Risk Management Plan Contractor To demonstrates the means and methods of regular monitoring and review of the Construction Stage Risk Register by risk owners for the Construction Stage Construction Stage Project Risk Register Contractor To confirm the owners of risks, actions and measures to mitigate the impact of the risks during the Construction Stage including risks identified by the Contractor as well as project related risks brought forward from the Client's Risk Register Site Organisation Chart Contractor To provide information on the reporting structure and lines of communication of key personnel and persons nominated for safety critical work and selfcertification (where required under the Contract) 16
17 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 17 Clause Deliverable Prepared by Scope and intent Training Plan Contractor To demonstrate how the Contractor intends to ensure all staff are and will remain adequately and suitably trained for the positions and responsibilities that they are to hold Method Statements Contractor To demonstrate and confirm working methods and plant, materials and level of labour to be used Inspection and Test Plans Contractor To demonstrates the Contractor's and Client's attitude to quality control and quality assurance Risk Assessments Contractor To demonstrate that hazards and associated risks involved in the construction works have been fully identified and assessed for inclusion in the Construction Stage Risk Register Independent Supervision Assurance Contractor To demonstrate how the Contractor will control and maintain independent supervision of the construction checking process in the case of Self-Certification Plant Selection Criteria Contractor To identify key plant and the maintenance regime e.g. level of spares, frequency of inspection, maintenance staff (to be included in Method Statements) Management Plan Contractor To identify and demonstrate the systems the Contractor intends to use to manage and control the construction process with regards to the requirement of the Contract and also with regard to identifying that the Contractor is working to current accepted best practice Audit Plan Contractor To demonstrates the Contractor's approach to internal and external auditing of the construction process Value Engineering Proposals Contractor To identify deviations from the original design, changes in methods to be used, changes to design parameters and implications including risks, perceived benefits accompanied by appropriate risk assessments 17
18 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 18 APPENDIX 3: Model Endorsement To Be Added to the Insurance Contract in respect of The 'Joint Code of Practice for in the UK' Introductory Notes: If an Insurance Policy provides cover for a site where the Code is in operation, such Policy should normally contain an endorsement noting this and outlining the respective rights and responsibilities of the Insured and the Insurer(s) (referred to below as 'the Company'). There is no mandatory version of such Policy endorsement, although the Association of British Insurers has issued a recommended form. This is shown below. The form may need to be adapted to ensure consistency with the terms and conditions and terminology used in the balance of the Policy wording. It is important that each party should consult their Insurance Advisers when considering any insurance implications of the Code. It is also important that Clients ensure that they have power under relevant contracts to require Contractors and Consultants to implement Remedial Measures stipulated by Insurers under the Endorsement. Attention is drawn here to clause of the Code. Model Endorsement The following Endorsement is added to the Policy The insured shall use all reasonable endeavours to comply with the 'Joint Code for Risk Management for Tunnel Works in the UK' (hereinafter referred to as the Code) or any subsequent amendment thereto or revised edition thereof current at inception or subsequent renewal of the Policy. Any representative appointed for the purpose by the Company shall have the right at all reasonable times and on reasonable notice to enter and inspect any construction site insured under the Policy and/or any relevant documents relating thereto for the purpose of checking whether these in all or any respects comply with the Code. In the event of the Company becoming aware of what it considers to be a breach of the Code, the Company may (but shall not be required to) inform the Client or his representative and the Main/Management Contractor's Construction Site management of the nature of the breach specifying the remedial measures required by the Company ('the Remedial Measures') and the period within which these shall be completed. The Client and the Main/Management Contractor will then ensure that all relevant Consultants and Trade/Subcontractors are made aware promptly of the relevant breach and that the Remedial Measures are carried out within the period being stipulated by the Company. Where the Company considers such a breach is of sufficient importance, the Company shall confirm the same by notice in writing to the Client and Main/Management Contractor at their respective addresses nominated by the Insured at the inception of cover or as subsequently amended. Under the terms of this or any subsequent notice, the Company may suspend or cancel all cover under the Policy from the date stated in the notice (not being a date earlier than the date named for the completion of the Remedial Measures). Such notice shall be given by registered post, recorded delivery, confirmed facsimile transmission or by hand. If the notice provides for suspension of cover, only such cover shall be reinstated when the Company is satisfied that the Remedial Measures have been completed. If the notice provides for the cancellation of cover, the Company agrees to return to the Insured a pro rata proportion of the relevant part of the Policy premium. Cover under this Policy shall only be suspended or cancelled to the extent specified in the notice(s) and shall not apply to Works or cover or Insured not so specified. For the avoidance of doubt, the Company shall have no liability to indemnify any Insured whose cover has been suspended or cancelled under a notice under this Endorsement in respect of loss or damage that results from loss or damage, which occurs after cancellation or during the period of suspension as appropriate. Nothing in this Endorsement shall prejudice, waive or remove the rights of the Company under the terms of other Policy conditions and exclusions or otherwise under or in relation to the Policy. Subject otherwise to the terms, conditions and exclusions of this Policy 18
19 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 19
20 MASTER 07/09/03 JCoP 9/9/03 8:42 am Page 20 This Joint Code of Practice for in the UK contains a series of measures which, if implemented, will ensure the application of deemed best practice for the minimisation and management of risks associated with the design and construction of tunnels, caverns, shafts and associated underground structures including the renovation of existing underground structures. CONTENTS 1.OBJECTIVE OF THE CODE COMPLIANCE WITH THE CODE INTRODUCTION RISK ASSESSMENT AND MANAGEMENT CLIENT ROLE AND RESPONSIBILITIES PROJECT DEVELOPMENT STAGE CONSTRUCTION CONTRACT PROCUREMENT STAGE DESIGN STAGES CONSTRUCTION STAGE APPENDICES 1.Definitions and Terms used in this Code Schedule of Deliverables for use by Contract Insurers Model Endorsement
A CODE OF PRACTICE FOR RISK MANAGEMENT OF TUNNEL WORKS
ITI 30 January 2006 A CODE OF PRACTICE FOR RISK MANAGEMENT OF TUNNEL WORKS Prepared by The International Tunnelling Insurance Group Contributors to this Code ITIG (Insurance Members) P Bravery Swiss Re
Single Project Professional Indemnity Insurance Proposal Form. Note: This is a proposal form for a claims made policy
Single Project Professional Indemnity Insurance Proposal Form Note: This is a proposal form for a claims made policy Please provide any necessary explanations or additional details by attaching separate
CHAPTER 24: ENVIRONMENTAL MANAGEMENT
Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document
Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer
Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland
Document Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
SMS0045 Construction Health and Safety Policy and Procedures
SMS0045 Construction Health and Safety Policy and Procedures March 2015 Version 8 Please note that for projects utilising a CDM Co-ordinator under the transitional arrangements of CDM 2015 (between 6 April
R000. Revision Summary Revision Number Date Description of Revisions R000 Feb. 18, 2011 Initial issue of the document.
2 of 34 Revision Summary Revision Number Date Description of Revisions Initial issue of the document. Table of Contents Item Description Page 1. Introduction and Purpose... 5 2. Project Management Approach...
Clients in Construction Best Practice Guidance
Clients in Construction Best Practice Guidance Published in 2009 by the, Metropolitan Building, James Joyce Street, Dublin 1. Copyright The January 2009 Clients in Construction: Best Practice Guidance
WHS Contractor Management Procedure
Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety
BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011
BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under
WHS CONTRACTOR MANAGEMENT PROCEDURE
1. Overview The Port Augusta City Council as part of its commitment under its WHS Contractor Management policy, recognises its obligation to: Ensure, so far as is reasonably practicable, the health and
CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR
CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector
PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS
PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS 2014 Public Sector Standard Conditions of Contract for Construction Works 2014 Building and Construction Authority First published 1995
GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities
GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement
Construction (Design and Management) Regulations 2007
MEETING Finance, Procurement and Property Committee AGENDA ITEM 14 MEETING DATE 9 th July 2007 DOCUMENT NUMBER FEP 1052 SUBJECT REPORT Construction (Design and Management) Regulations 2007 (12/06/07) by
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company. Ref: Quality Manual.
This manual is proprietary and no part thereof shall be copied without written authorisation from the company Ref: Quality Manual.ind Issue: June 2009 INDEX 1 Amendment Status 2 Controlled Distribution
Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan
Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.
DIRECTORATE OF ESTATES & FACILITIES
DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:
Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 2014
for Inspecting and Certifying Buildings and Works Building Control Regulations 2014 February, 2014 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1 1.3 Application
Principal Designer Guidance
Principal Designer Five or more employees 1 CONTENTS INTRODUCTION 3 Further reading / additional resources 3 QUESTION 1: POLICY AND ORGANISATION 4 4 4 QUESTION 2: ARRANGEMENTS/PROCEDURES FOR HEALTH AND
Thames Water Utilities Limited. Settlement deed
Thames Water Utilities Limited Settlement deed DATED [ ] THAMES WATER UTILITIES LIMITED the Undertaker [ ] the Owner DEED relating to the mitigation of the effects of settlement arising from the construction
CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS
CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS 1. GENERAL PROVISIONS. 1.2 DEFINITIONS Where the words
CODE OF PRACTICE. Safety Management. Occupational Safety and Health Branch Labour Department CODE OF PRACTICE ON SAFETY MANAGEMENT 1
CODE OF PRACTICE On Safety Management Occupational Safety and Health Branch Labour Department CODE OF PRACTICE ON SAFETY MANAGEMENT 1 This Code of Practice is prepared by the Occupational Safety and Health
Ground-borne Vibrations and Ground Settlements Arising from Pile Driving and Similar Operations
Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-137 Ground-borne Vibrations and Ground Settlements Arising from Pile
Health and safety policy
1. General statement of intent The Company recognises and accepts its responsibilities as an employer to ensure, so far as is reasonably practicable, the health, safety and welfare of its employees and
Managing construction procurement risks
CONSTRUCTION PROCUREMENT BEST PRACTICE GUIDELINE #A5 Construction Industry Development Board Pretoria - Head Office Tel: 012 482 7200 Fraudline: 0800 11 24 32 Call Centre: 0860 103 353 E-mail: [email protected]
Management of Health and Safety for Work and Services Contractors Policy June 2010
June 2010 Contents 1. Introduction 3 2. Policy Statement 4 3. Policy Objectives 5 4. Application 6 5. Organisational Responsibilities 7 6. Glossary of Terms 11 7. Authorised Directors Appendix 1 2 www.surrey.ac.uk
Project manager services
Corporate Professional Local Project manager services For use with the RICS Standard form of consultant s appointment and RICS Short form of consultant s appointment The mark of property professionalism
Data Communications Company (DCC) price control guidance: process and procedures
Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: [email protected] Overview: The Data and Communications Company (DCC) is required
Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement
Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the
Preparation of a Rail Safety Management System Guideline
Preparation of a Rail Safety Management System Guideline Page 1 of 99 Version History Version No. Approved by Date approved Review date 1 By 20 January 2014 Guideline for Preparation of a Safety Management
Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce
Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO
GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No.
GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No. 2009-8M (Supersedes Report No. 21) F CHOWDHURY GEOMECHANICS AND STRUCTURAL MATERIALS ENGINEER S REHMAN GEOTECHNICAL
This AGREEMENT made the... day of... between the HUNTER WATER CORPORATION (hereinafter called the Corporation ) and ...
MINOR WORKS NO.... This AGREEMENT made the... day of... between the HUNTER WATER CORPORATION (hereinafter called the Corporation ) and of... Hereinafter called the Developer ) It is agreed that the Developer
Health, Safety and Environment Management System
Health, Safety and Environment Management System For Bridgeport Energy Ltd Level 7, 111 Pacific Highway North Sydney 2011 June, 2010 DOCUMENT CONTROL Title: Document Number: Health, Safety and Environmental
Role in the project (e.g. Prime Engineering Consultant or Contractor), and summary of professional Duties : Name Professional Duties Contract Awarded?
PROPOSAL FORM FOR SINGLE PROJECT PROFESSIONAL INDEMNITY NOTE: THIS IS A PROPOSAL FOR A CLAIMS MADE POLICY Note : Please provide any necessary explanations or additional details by attachment to this Proposal
HEALTH AND SAFETY POLICY AND PROCEDURES
HEALTH AND SAFETY POLICY AND PROCEDURES 1 Introduction 1. The Health and Safety at Work etc. Act 1974 places a legal duty on the University to prepare and revise as often as may be appropriate, a written
IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer
THE ROLE OF THE ENGINEER IN FIDIC 99 RED BOOK COULD IT BE PERFORMED BY A SUPERVISION CONSULTANT & A CONSTRUCTION MANAGER? Dr. Munther M. Saket December 2010 The Role of the Engineer 1 The ENGINEER S ROLE
GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES
GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES GENERAL CONDITIONS OF CONTRACT FOR MINOR WORKS PAGE 1 BASE D ON WA LOCAL GOVERNMENT ASSOCIATION MODEL 2010 TABLE OF CONTENTS 1 INTERPRETATION 2 RISE
The South African Council for the Project and Construction Management Professions (SACPCMP)
The South African Council for the Project and Construction Management Professions (SACPCMP) Registration Rules for Professional Construction Mentors in terms of Section 18(1) (c) of the Act, 2000 (Act
Managing Asbestos Policy
Managing Asbestos Policy Liverpool Mutual Homes Page 1 of 16 Table of Contents 1. MANAGEMENT INFORMATION 2. POLICY STATEMENT 3. POLICY AIMS AND KEY OBJECTIVES 4. INTRODUCTION 5. DETAIL 6. LINKS TO LMH
Procurement of Goods, Services and Works Policy
Procurement of Goods, Services and Works Policy Policy CP083 Prepared Reviewed Approved Date Council Minute No. Procurement Unit SMT Council April 2016 2016/0074 Trim File: 18/02/01 To be reviewed: March
This is Document Schedule 5 Part 1 referred to in this Contract SCOTTISH MINISTERS REQUIREMENTS SCHEDULE 5 PART 1 QUALITY MANAGEMENT SYSTEM
This is Document Schedule 5 Part 1 referred to in this Contract SCOTTISH MINISTERS REQUIREMENTS SCHEDULE 5 PART 1 QUALITY MANAGEMENT SYSTEM CONTENTS Page No 1 GENERAL REQUIREMENTS 1 1.1 Requirements 1
COMPANY NAME. Environmental Management System Manual
Revision No. : 1 Date : DD MM YYYY Prepared by : Approved by : (EMR) (Top Management) Revision History Revision Date Description Sections Affected Revised By Approved By Table of Content 0.0 Terms and
Managing Contractor Health and Safety Risks Guidelines for Local Government
Managing Contractor Health and Safety Risks Guidelines for Local Government Acknowledgements This manual has been prepared by Noel Arnold & Associates Pty Ltd, occupational health and safety consultants
How To Manage Risk In Ancient Health Trust
SharePoint Location Non-clinical Policies and Guidelines SharePoint Index Directory 3.0 Corporate Sub Area 3.1 Risk and Health & Safety Documents Key words (for search purposes) Risk, Risk Management,
Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000
Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE
Australian Transport Council. National Standard for the Administration of Marine Safety SECTION 4 SURVEYS OF VESSELS
Australian Transport Council National Standard for the Administration of Marine Safety SECTION 4 SURVEYS OF VESSELS Edition 1 Draft for comment issued 20 December 2005 Endorsed by the Australian Transport
Drinking Water Quality Management Plan Review and Audit Guideline
Drinking Water Quality Management Plan Review and Audit Guideline This publication has been compiled by Queensland Water Supply Regulator, Department of Energy and Water Supply. State of Queensland, 2013.
SAFETY and HEALTH MANAGEMENT STANDARDS
SAFETY and HEALTH STANDARDS The Verve Energy Occupational Safety and Health Management Standards have been designed to: Meet the Recognised Industry Practices & Standards and AS/NZS 4801 Table of Contents
Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION
EUROPEAN COMMISSION Brussels, XXX [ ] (2013) XXX draft Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION Providing minimum principles for the exploration and production of hydrocarbons (especially
A JCT 2011 Minor Works Building Contract
A JCT 2011 Minor Works Building Contract A20 JCT MINOR WORK BUILDING CONTRACT (MW) Minor works transparency document Rev A A20 / A20 JCT MINOR WORK BUILDING CONTRACT (MW) JCT MINOR WORKS BUILDING CONTRACT
Mandatory Provident Fund Schemes Authority COMPLIANCE STANDARDS FOR MPF APPROVED TRUSTEES. First Edition July 2005. Hong Kong
Mandatory Provident Fund Schemes Authority COMPLIANCE STANDARDS FOR MPF APPROVED TRUSTEES First Edition July 2005 Hong Kong Contents Glossary...2 Introduction to Standards...4 Interpretation Section...6
C162 Asbestos Convention, 1986
C162 Asbestos Convention, 1986 Convention concerning Safety in the Use of Asbestos (Note: Date of coming into force: 16:06:1989.) Convention:C162 Place:Geneva Session of the Conference:72 Date of adoption:24:06:1986
CCE-TRK-SPN-010 Specification for Movement Monitoring of Railway Track
Reference No. CCE-TRK-SPN-010 Version 1.0 Operative Date 02/08/2011 Status LIVE Prepared by Nick West, Colin Hedderly Checked by Cathal Mangan Approved by Éamonn Ballance CCE DEPARTMENT TECHNICAL SPECIFICATION
Corporate Standard. Contractor Management
Corporate Standard Contents Purpose... 2 Scope... 2 Definitions... 2 Background... 3 Specific Requirements... 4 Responsibilities... 11 Review Date... 11 References... 11 Date Issued July 2010 Management
NABL NATIONAL ACCREDITATION
NABL 160 NABL NATIONAL ACCREDITATION BOARD FOR TESTING AND CALIBRATION LABORATORIES GUIDE for PREPARING A QUALITY MANUAL ISSUE NO. : 05 AMENDMENT NO : 00 ISSUE DATE: 27.06.2012 AMENDMENT DATE: -- Amendment
Definitions used in these Grant Conditions can be found at paragraph 13.
GRANT CONDITIONS These Grant Conditions, together with the Award Letter and the Policies and Positions Statements, set out the terms and conditions on which the Grant is made by the Funders to the Host
Reserving Requirements for Non-Life Insurers and Non-Life and Life Reinsurers
2014 Reserving Requirements for Non-Life Insurers and Non-Life and Life Reinsurers 1 Reserving Requirements for Non-Life Insurers and Non-Life and Life Reinsurers Contents Introduction... 3 Definitions...
HEALTH CONTRACTOR INSURED CONSTRUCTION PROJECTS
HEALTH CONTRACTOR INSURED CONSTRUCTION PROJECTS Insurance and Indemnification Clauses (to be included in Supplementary Conditions to the CCDC 2 2008 Contracts for Health projects with an Estimated Project
Nominated Subcontractors on International Projects: Approaches to Risk Allocation
Nominated Subcontractors on International Projects: Approaches to Risk Allocation September 5, 2005 (he following outline was used in a presentation to the Overseas Construction Association of Japan, Inc.
SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and
SCHEDULE 16 Exit Plan 1. Scope 1.1 This schedule: (A) sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and requires the Service Provider
Contractor Safety Management
1.0 Introduction Memorial University will ensure that a diligent contractor management process is established. This procedure establishes requirements for contract administration and oversight of contractor
REPORT 4 FOR DECISION. This report will be considered in public
REPORT 4 Subject: Safety Readiness for the Summer 2013 Events Programme Agenda item: Public Item 7 Report No: 4 Meeting date: 28 May 2013 Report to: Board Report of: Mark Camley, Interim Executive Director
INSURANCE ACT 2008 CORPORATE GOVERNANCE CODE OF PRACTICE FOR REGULATED INSURANCE ENTITIES
SD 0880/10 INSURANCE ACT 2008 CORPORATE GOVERNANCE CODE OF PRACTICE FOR REGULATED INSURANCE ENTITIES Laid before Tynwald 16 November 2010 Coming into operation 1 October 2010 The Supervisor, after consulting
Vendor Management Program
The Corporation of the City of Kawartha Lakes is committed to the provision of a safe and healthy work environment for its employees, contractors and visitors. To promote this type of environment, the
Wharton Construction Ltd. Quality Manual. Kellaw Road Yarm Road Business Park Darlington DL1 4YA
Quality Manual Kellaw Road Yarm Road Business Park Darlington DL1 4YA MANUAL IDENTIFICATION This document is a controlled/uncontrolled copy. Copy Number:...of... Issued to... Title... Holders of controlled
Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)
Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament
Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors
Procurement guidance Engaging and managing consultants Includes definitions for consultants and contractors Procurement guidance: Engaging and managing consultants Page 2 of 17 Table of contents Table
Auditing Health and Safety Management Systems. 4th Edition
Auditing Health and Safety Management Systems 4th Edition SafetyMAP: AUDITING HEALTH AND SAFETY MANAGEMENT SYSTEMS 4th Edition Published by the Victorian WorkCover Authority Victorian WorkCover Authority
PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS
PROJECT MANAGEMENT MANUAL PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS FOR ESTATE MANAGEMENT November 2012 PMM REV1.4 CONTENTS INTRODUCTION PROJECT MANAGEMENT PROCESS FLOWCHARTS STAGE ZERO 0.0
4.05e WHS Guidelines for Incident Investigation Procedures Page 1 of 7
Page 1 of 7 1 Purpose It is a legal requirement under the NSW Work Health and Safety Act 2011 and NSW Work Health and Safety Regulation 2011 to identify hazards, assess the risk of those hazards, implement
GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005
GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 CONTENTS 1.0 INTRODUCTION 2.0 OVERVIEW OF SPT APPROACH TO DEVEOPMENTS/WORKS IN THE VICINITY OF
Standard conditions of purchase
Standard conditions of purchase 1 OFFER AND ACCEPTANCE 2 PROPERTY, RISK & DELIVERY 3 PRICES & RATES The Supplier shall provide all Goods and Services in accordance with the terms and conditions set out
JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management
JOHN HART GENERATING STATION REPLACEMENT PROJECT Schedule 9 Quality Management SCHEDULE 9 QUALITY MANAGEMENT TABLE OF CONTENTS 1. QUALITY MANAGEMENT SYSTEM... 1 1.1 Quality Management System...1 1.2 Project
Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26
Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain
For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems
BAFE Scheme: SP203-3 Version 1: July 2008 Amendment No: 1 Fire Protection Industry Scheme, Reference SP203 Part 3 For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression
Corporate Health and Safety Policy
Corporate Health and Safety Policy November 2013 Ref: HSP/V01/13 EALING COUNCIL Table of Contents PART 1: POLICY STATEMENT... 3 PART 2: ORGANISATION... 4 2.1 THE COUNCIL:... 4 2.2 ALLOCATION OF RESPONSIBILITY...
RISQS Audit Protocol: Network Rail On-Track Plant Operations Scheme (POS) module.
Services for professional procurement. Be better informed, make better decisions. RISQS Audit Protocol: Network Rail On-Track Plant Operations Scheme (POS) module. Contents Contents... 2 Preface... 3 Issue
Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue
Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority
7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers
Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4
HEALTH & SAFETY POLICY
HEALTH & SAFETY POLICY 1. STATEMENT OF INTENT & POLICY OBJECTIVES The Council, as the governing body of the School, recognises and accepts the responsibilities placed on it as 'Employer' by the Health
REQUIREMENTS FOR REGISTRATION AS A PROFESSIONAL ENGINEER WITH THE PROFESSIONAL ENGINEERS BOARD SINGAPORE
ATTACHMENT 9 REQUIREMENTS FOR REGISTRATION AS A PROFESSIONAL ENGINEER WITH THE PROFESSIONAL ENGINEERS BOARD SINGAPORE Requirements 1 The Professional Engineers Board will register a candidate as a professional
https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework
All interested parties Direct Dial: 020 7901 1849 Email: [email protected] Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance
Architects and Engineers Professional Liability Proposal Form
Notice:Statement pursuant to Section 25(5) of the Insurance Act (Cap 142) or any amendments thereof; You are to disclose in this application, fully and faithfully, all the facts which you know or ought
Jonathan Wilson. Sector Manager (Health & Safety)
Jonathan Wilson Sector Manager (Health & Safety) OHSAS 18001:2007 Making Life Easier For Health & Safety Managers Workshop Agenda 1. Introduction 2. Why Manage Health & Safety 3. OHSAS 18001 and OHSMS
CP14 ISSUE 5 DATED 1 st OCTOBER 2015 BINDT Audit Procedure Conformity Assessment and Certification/Verification of Management Systems
Certification Services Division Newton Building, St George s Avenue Northampton, NN2 6JB United Kingdom Tel: +44(0)1604-893-811. Fax: +44(0)1604-893-868. E-mail: [email protected] CP14 ISSUE 5 DATED 1 st OCTOBER
NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9
NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 A G U I D E T O A I M U K TA X B E N E F I T S 2 AIM Note for Mining, Oil and Gas Companies Contents Introduction 1 Companies to which this Note
Financial Services Act 2010
Financial Services Act 2010 CHAPTER 28 CONTENTS Objectives of FSA etc 1 Financial stability objective 2 Enhancing public understanding of financial matters etc 3 Meeting FSA s regulatory objectives Remuneration
INDEX 1.0 HEALTH, SAFETY & ENVIRONMENT 1.1 INTRODUCTION 1.2 OBJECTIVES 1.3 HEALTH, SAFETY & ENVIRONMENT STATEMENT 1.4 ENVIRONMENTAL STATEMENT
INDEX 1.0 HEALTH, SAFETY & ENVIRONMENT 1.1 INTRODUCTION 1.2 OBJECTIVES 1.3 HEALTH, SAFETY & ENVIRONMENT STATEMENT 1.4 ENVIRONMENTAL STATEMENT 2.0 HEALTH, SAFETY & ENVIRONMENT MANUAL 2.1 HAZARD MANAGEMENT
Economic and Social Council
UNITED NATIONS Economic and Social Council Distr. GENERAL E Informal document No. 14 20 September 2002 ENGLISH ONLY ECONOMIC COMMISSION FOR EUROPE INLAND TRANSPORT COMMITTEE Ad hoc Meeting of the Multidisciplinary
Royal Borough of Kensington and Chelsea. Data Quality Framework. ACE: A Framework for better quality data and performance information
Royal Borough of Kensington and Chelsea Data Quality Framework ACE: A Framework for better quality data and performance information March 2010 CONTENTS FOREWORD 2 A CORPORATE FRAMEWORK FOR DATA QUALITY
Guide Document for Development of WHS Management Plans
DISCLAIMER: THIS DOCUMENT IS PROVIDED AS GUIDANCE TO ASSIST CONTRACTORS IN MEETING THEIR OBLIGATIONS UNDER THE WHS LAW AND NTG CONTRACTS. NTG DOES NOT ACCEPT ANY RESPONSIBILITY FOR THE CONTENTS OF CONTRACTORS
SAMPLE SERVICES CONTRACT
SAMPLE SERVICES CONTRACT The parties to this contract are the SAN DIEGO COUNTY WATER AUTHORITY, a county water authority, (the Water Authority) and, [a / an], having its principal place of business at
Quality Management System
LH Sleightholme Ltd, Westfield Works, Helperthorpe, Malton, North Yorkshire YO17 8TQ Quality Management System MANUAL ISO 9001:2008 This Quality Management System Manual has been issued on the authority
Invitation to Tender
Invitation to Tender Provision of Training in Technology Transfer and Related Areas for The Southern Africa Innovation Support Programme 1. Drawing up the tender The tender must be submitted in writing