SUSTAINABLE DESIGN FOR THE SOLDIER CREEK LEVEE REPAIR. John Ruhl 1 Seth Laliberty 2 ABSTRACT

Size: px
Start display at page:

Download "SUSTAINABLE DESIGN FOR THE SOLDIER CREEK LEVEE REPAIR. John Ruhl 1 Seth Laliberty 2 ABSTRACT"

Transcription

1 SUSTAINABLE DESIGN FOR THE SOLDIER CREEK LEVEE REPAIR John Ruhl 1 Seth Laliberty 2 ABSTRACT The Soldier Creek Diversion Unit Repair Project represents the latest USACE Kansas City District investment in sustainable water infrastructure. Soldier Creek crosses the north side of the City of Topeka, Kansas through a partially developed floodplain of the Kansas River. The diversion unit, constructed in the 1950s, consists of eighteen miles of earthen levee, nine miles of improved channel, and thirty-five drainage structures. The 1950 s channelization project significantly changed the planform of the channel and induced substantial changes in profile. The instabilities identified today may be derived from the steep banks that resulted from these drops in channel elevation. The existing slope of the channel bed continues to amplify the rate of degradation, being steeper than the equilibrium slope, given the existing channel bed materials. In October 2005, the levee was overtopped and the diversion unit seriously damaged. Black & Veatch prepared a conceptual design for the repair using the Soar & Thorne approach and HEC-RAS to evaluate any changes in water surface profiles, stream velocities, and energy gradelines. The design features included rock checks to maintain bed elevation, vegetation to augment stability, and a meandering low flow channel within the levee system. Construction has been on-going since November A variety of construction challenges have arisen including unexpected utilities, differing geotechnical conditions from those expected, plant establishment, and high water events. Construction completion is expected late this year or early in INTRODUCTION Soldier Creek extends through a predominantly rural watershed downstream across the north side of the city of Topeka, Kansas in a partially developed floodplain area of the Kansas River. The watershed drains 334 square miles made up of approximately 60% grassland, 40% crops, and less than 1% urban area. The soils are generally silt loam and silty clay loam. The Topeka, Kansas Flood Protection Project which includes the Soldier Creek Diversion Unit was originally authorized for Federal funding in Construction of the Diversion Unit began in 1957 and was completed in The Diversion Unit is comprised of 17.9 miles of earthen levee, 9.2 miles of improved channel, and 35 drainage structures. These features extend upstream from the confluence at the Kansas River. The construction altered the confluence location of not only Soldier 1 Black & Veatch, 6601 College Blvd., Overland Park, KS, ruhljk@bv.com 2 Corps of Engineers, Kansas City District, 601 East 12 th Street, Kansas City, MO, seth.j.laliberty@usace.army.mil. Soldier Creek Levee Repair 839

2 Creek, but also Indian Creek, the previous confluence of which had been further east from the Soldier Creek confluence (See Figure 1). The project straightened the alignment of Soldier Creek in conjunction with the levee construction. Figure 1. Alignment of Soldier Creek Not only did the channelization project significantly change the planform of the channel, but very significant changes in the profile followed the completion of construction. In 2001, the USGS documented a 5-foot decline in the channel bed very soon after the completion of construction and a degradation rate of approximately 0.03 ft 1 year between 1962 and This resulted from the steepened channel gradient that was produced during original construction from the elimination of much of the sinuosity of the natural channel. This degradation has continued at a lesser rate throughout the subsequent years because the channel slope is steeper than the equilibrium slope given the existing channel bed materials. The history of bank failures in the Soldier Creek channel is the result of this combination of steepened channel slope and soil conditions. In October 2005, heavy rainfall resulted in levee overtopping and significant damage to the Soldier Creek channel. Approximately 10 miles of levee was damaged from the overtopping with the crushed aggregate surface on the levee crest washed away and minor erosion of the embankment resulting. Two reaches of the channel were damaged as shown in Figure 2. The longer damaged reach was from the confluence at the Kansas River to Kansas Avenue. A much shorter reach was damaged immediately downstream of Menoken Road. 840 Innovative Dam and Levee Design and Construction

3 Figure 2. Locations of Channel and Levee Repair The purpose of the Soldier Creek project is to restore the original project function. The project has included a study phase, a design phase, and a construction phase. The study phase, performed in 2008, compared the merits and the costs of two design alternatives. The first (the Conventional Alternative) consisted of repairing the banks to be consistent with the original design. The second alternative was a stable stream design which accounted for geomorphologic changes which the channel has experienced. The study resulted in the recommendation of the latter, the Stream Stability Alternative. The design phase, also performed during , produced plans and specifications for the selected alternative. The construction which began in 2009 is expected to be completed either in late 2011 or early STUDY PHASE Activities during the study phase included collection of topographic data, a field geomorphologic analysis, hydraulic modeling, development of the Stream Stability Alternative, and alternative assessment including preparation of cost estimates for each alternative. Collection of Topographic Data The primary topographic data source for this project was Light Detection and Ranging (LIDAR) data for Shawnee County, Kansas which was collected in This data was supplemented with field survey in areas of erosion. Soldier Creek Levee Repair 841

4 Field Geomorphologic Analysis Field reconnaissance consisted of a two-person team walking the channel to record observations. This reconnaissance was performed from the mouth of Soldier Creek upstream to Menoken Road. The types of observations made were as follows: the ordinary high water mark, top of bank, locations of riffles and pools, exposed bed rock or bed materials, scour and depositional areas, sandbar characterization, natural or invasive vegetation in the buffer zone, bank full depth and width, loss of riprap, flow orientation, and areas of debris collection. Figure 3 below is descriptive of the conditions which were observed. Figure 3. Looking Downstream at Meriden Road The reconnaissance was performed using a proprietary GIS-based, geomorphologic data acquisition system. The Kansas City Metropolitan Chapter of the American Public Works Association Channel Condition scoring matrix within APWA 5600 was the basis for identifying reaches of concern. Using the topographic and geomorphologic data, Black & Veatch determined the bank-full channel forming conditions, stream thalweg, total meander, valley length, and sinuosity. A condition score is determined for each stream reach. The results of the geomorphologic analysis are important in developing stream stability recommendations. 842 Innovative Dam and Levee Design and Construction

5 Hydraulic Modeling A HEC-RAS model was developed for each of the Conventional and Stream Stability Alternative conditions for the 2-year, 20-year, 100-year, and 200-year flood events. The models were based on a 2005 Kansas City District model with updates as required for bridge information, Manning s n values, and ineffective flow areas. Additional stream cross sections were also added. The shear stress was the most important variable analyzed from the HEC-RAS model. Shear stresses downstream of Kansas Avenue exceed 0.5 lbs/ft 2 for flows greater than the 10-year event. For the 200-year event, the shear stress values exceed 1 lbs/ft 2. Shear stresses are evaluated for the channel bottom, banks, and bends. The erosion due to insufficient shear strength of the bank materials is closely correlated to soil material type. The erosion is occurring in the alluvial clay loams, loams, and sandy loams of the Kansas River valley. Little erosion has occurred on the hillside slopes comprised of silty clay loams and relatively shallow bedrock. The model results indicated that Soldier Creek is a moveable bed system. The predominantly agricultural watershed provides a large sediment supply. The channel bed degradation documented by the USGS as mentioned above and the shear stress results from the HEC-RAS model are both consistent with this conclusion. As a result, the most important design criterion is the establishment of an equilibrium slope to stabilize the channel bed and prevent future degradation. The equilibrium slope balances the size and quantity of particles which the stream moves. Rock check dam spacing and sizing is based on the equilibrium slope. The Stream Stability Alternative maintains the 200-year water surface elevation within the project levees. Development of the Stream Stability Alternative The analysis of the topographic data, geomorphologic assessment, and hydraulic modeling led to the following conclusions: The channel has experienced mass wasting of erodible soils Formation of sand bars and flood benches has occurred The riprap was improperly sized. The drainage structures have become unstable The pool-riffle structure is undefined The channel lacks sinuosity Monoculture, invasive vegetation exists at the expense of a native grass/riparian corridor The research done by Philip J. Soar and Colin R. Thorne provides guidelines for stable stream design. The underlying assumptions from this research are that the dimensions of stable natural channels are proportional to the discharge and that they are inter-related. They indicate that the 2-year flood is an approximate upper boundary to bank full Soldier Creek Levee Repair 843

6 discharge. Studies in Kansas for urban streams have indicated that the 1-year event may be a better estimate. For Soldier Creek, a 1.5-year event was used. The channel width, pool-riffle (shallows) spacing, radius of curvature, and sinuosity were also determined. The appropriate spacing of pools and riffles can reduce shear stresses and decrease the need for resistive materials in between riffles. Figure 4 describes these stream characteristics. L Amp R c Alternative Assessment Figure 4. Soar and Thorn Stream Parameters As a final step in the study, the Conventional Alternative and the Stream Stability Alternative were compared. The alternatives can be summarized as follows: Conventional Alternative This alternative conformed to the Kansas City District Project Information Report developed following the 2005 flood. It consisted of reconstruction of the original 2 (H) to 1 (V) bank slope and a channel bottom width of 125 feet (25 feet wider than the original channel width). The channel near existing bridges would be restored to the original design to avoid impacting the bridge piers and foundation. Riprap would be placed on repaired channel slopes to restore the original condition. In areas where the levee has been overtopped, the crest would be graded to the original profile and resurfaced with 6 inches of crushed aggregate. The study level cost for this alternative was approximately $11,800,000. Stream Stability Alternative This alternative used the equilibrium slope and stable channel cross section as described above for the two project reaches shown in Figure 2. The low flow channel increases the channel length and results in a milder slope. Small rock check dams allow the channel to maintain an equilibrium slope and stable channel bed and preserve the channel toe. Enhanced vegetation was designed to provide stability and roughness to the flood bench which reduces the velocity and the associated erosive potential on the upper slopes. The treatment of the overtopped levee areas is identical to that for the Conventional Alternative. The study level cost for this alternative was approximately $8,500,000. Black & Veatch recommended the Stream Stability Alternative. This alternative provided the best choice for future stream stability and reduced maintenance costs, enhanced habitat, and could be constructed at the lowest capital cost. 844 Innovative Dam and Levee Design and Construction

7 DESIGN PHASE During the design phase, Black & Veatch prepared construction plans, specifications, a design analysis report, and updated cost estimate for the Stream Stability Alternative. The design included the stable stream features, bridge scour analysis, riprap, slope stability, hydraulic and structural analysis of the drainage structures, utilities, and ecosystem restoration features. Alignment and Stable Stream Design Features As determined in the study phase, two reaches as follows were identified for design: Project Site 1 This project reach extends from a location just upstream of the confluence at the Kansas River to Kansas Avenue. This reach is approximately 1.9 miles in length. Rock Checks #1 and #9 are located at the downstream and upstream ends of this project reach. The reach also includes bridges at the Union Pacific Railroad, US Highway 24, the ATT & SF Railroad, and Northeast Meriden Road; a total of eight rock check dams; eleven drainage structures, and the confluence of Indian Creek. Project Site 2 This project reach extends over approximately 1800 feet immediately downstream of NE Menoken Road. Rock Check #10 is near the downstream end of this reach. This reach does not include any bridges, other rock checks, drainage structures, or confluences. For Project Site 1, the existing survey documented centerline elevations of at the downstream end and at the upstream end for an average slope of approximately Eleven pools with alternating riffles were spaced according to the Soar and Thorne methodology. Bend scour calculations were used to determine a pool depth of 5 feet and the associated pool width. The Schoklitsh Method and Meyer-Peter, Muller Methods were used to determine the equilibrium channel slope based on a 1.5-year flood discharge and a mean sediment diameter of 2.4 mm for bed materials. The Newbury Rock riffle design method was applied to develop the rock check dimensions. A glide slope (upstream face) of 2(H) to 1 (V) and a run slope (downstream face) of 10 (H) to 1 (V) were developed. The rock checks are keyed into the bank slopes and are protected with riprap to resist the 200-year discharge. The rock check keys will be covered with topsoil to accelerate vegetation growth and blending into the adjacent banks. The construction plans included fourteen plan and profile sheets for Project Site 1 and three plan and profile sheets for Project Site 2. These sheets depict existing grade and finished grade contours in plan; existing grade, finished grade, and thalweg (deepest alignment through pools) in profile, finished grade lines in profile, locations of rock checks and drainage structures, and extent of riprap. Cross sections are also provided at intervals of 50 feet. The typical channel section reflects a lower channel side slope of 3 (H) to 1 (V), a bench of 10 (H) to 1 (V) side slope, and an upper slope of 3 (H) to 1 (V) to Soldier Creek Levee Repair 845

8 tie into the levee or natural grade. Grading design was performed with Intergraph InRoads. The computation of earthwork quantities indicated an excess of excavated material. Identification of an off-site disposal area for this material was identified. Geotechnical Analyses/Riprap Two soil borings were taken in order to determine the grain size of the embankment materials and to collect strength data for slope stability analysis. Subsurface information from the original Soldier Creek Diversion Unit plans were also used. The original construction drawings show that the channel embankments were sloped at 2 (H) to 1 (V) The proposed channel embankments for Project Site 1 are to have slopes at 3 (H) to 1 (V) with a maximum height of the embankment including the levee of 46 feet. Most of this reach includes a bench near the middle of the slope. A conservative assumption to not include the bench in the slope stability analysis was made. Riprap was included at each of the Union Pacific Railroad, US Highway 24, ATT & SF Railroad (at and downstream for approximately 500 feet), and NE Meriden Road. Riprap was also included on the toe of slope between the Union Pacific Railroad and US Highway 24 bridges, on the outside of the bend upstream of US Highway 24 for approximately 1000 feet, and at the Indian Creek confluence. For the Project Site 2, the south embankment will be sloped at 2.5 (H) to 1 (V). The maximum height of the south embankment will be 30 feet. The slope will have riprap placed to a depth of 2 feet along the lower 12 feet of vertical height of the embankment. The slope stability analyses were performed using the SLOPE/W program for undrained, drained, and rapid drawdown conditions. The soil strengths were based on data from the subsurface exploration and engineering judgement. The results of the stability analyses confirmed that the proposed slopes meet the required factors of safety. An analysis of bridge scour was performed in order to design the riprap at each bridge. Contraction scour and local scour at piers were analyzed using the FHWA NHI , HEC18, Evaluating Scour at Bridges manual. This analysis resulted in riprap size and depth at each bridge. Drainage Structure Design The eleven drainage structures within the Project Site 1 are in various conditions of disrepair. In some cases, the pipe outlet structure and/or the channel that conveys flow to Soldier Creek are also in poor condition. In additional instances, the proposed channel slope is being flattened to a 3 (H)to 1 (V) to and requires modification to the structure. The proposed modifications included repairing, extending, or shortening the existing culverts without making any changes to their size. Modifications to the energy dissipators were also made on an as required basis. These modifications included either concrete structures with downstream riprap or riprap alone. 846 Innovative Dam and Levee Design and Construction

9 Other Design Considerations Project Sites 1 and 2 include a minimum of utilities impacted by the design. The only crossing is a force main approximately 800 feet downstream from the upstream end of Project Site 1. Because no vertical profile information for the force main was available, it required locating and possibly deepening a portion of the pipe in order to maintain the required cover depths. Vegetation was incorporated in the design in order to stabilize and reduce erosion on the stream banks. The following three planting zones were included: Zone A: Streamside Seeding Blend This blend will be provided for the portion of the cross section nearest to the water level. The blend will include plant communities that are adapted to periods of inundation, storm flows, and moist to saturated soil conditions. A salix species is also included in the Zone A area. Zone B Streambank and Lower Flood Bench Seeding Blend This zone is located immediately upslope from Zone A. Deep rooted prairie species will be included tolerant of either inundation of periods of drought. Zone C - Levee Seeding Blend This blend applies to levee areas which are required to be periodically inspected and maintained. Four native grasses will be used in these areas. The project specifications include information on ecological maintenance requirements. Levee reaches which were either overtopped during the 2005 flood or for which the crests are degraded shall be restored to a profile not lower than the higher of the original construction profile and the profile at the beginning of construction. Construction Summary CONSTRUCTION PHASE The construction contract for the Soldier Creek Diversion Unit repairs was awarded in November of 2009 to LaForge and Budd from Parsons, KS for $9.069M. The original contract duration was 360 days. To date (October, 2011), $1.2 million in modifications have been awarded and the period of performance has been extended over 400 days, primarily due to weather delays. The Corps of Engineers has a field office established in a construction trailer on site and co-located with the North Topeka Drainage District s maintenance shed and the construction contractor s field office. Project engineer services are provided through a contract with HNTB, while construction quality assurance is performed by the Kansas City District s resident office in Kansas City. Additionally, Black and Veatch is contracted to provide Engineering During Construction services. Soldier Creek Levee Repair 847

10 Major Construction Features Construction effort can be divided into three main areas: bank repairs, in-channel work (including rock check dam construction and thalweg construction), and levee top repairs. Each main effort is discussed further below. Bank Repairs. The bank repairs consisted of demolition, cut/fill, riprap placement, drainage structure outlet repair or replacement, and plantings. This was the first significant construction effort and repaired several vertical eroded banks that threatened levee integrity. Demolition included removal of flood debris, deteriorated and cracked drainage structures, and eroded riprap that had shifted out of place. The construction contractor used a digital model provided by the designer to create a surface that could be read by a GPS system mounted on their equipment. The GPS allowed accurate cut or fill operations at every location in the construction area. Riprap was placed on channel banks in select places to resist shear forces where the hydraulic model predicted high shear forces. The design didn t create a riprap surface, so plan and cross-section views were used to manually calculate riprap quantities. Several drainage structure outlets were either repaired or replaced due to erosion of their foundations. And finally, temporary seeding, native grasses seeding, and willow plantings were performed to stabilize the bank. The native grasses require three years to fully establish while the willows will establish in one year. In-Channel Construction. With few exceptions, in-channel construction was done at low flows (less than 15 cfs, or an elevation of one foot). The stable stream design relies on a series of pools and riffles created by rock check dams and thalweg pools. The rock check dams also act as grade control structures to control bed degradation. The thalwegs were excavated to create pools and sinuosity in the channel while the rock check dams hold the water back and fill the pools. The exception to construction during low flows was rock check construction, which was done in the dry. Construction of the first few check dams was done using a temporary inflatable dam upstream of the rock check and a temporary berm downstream of the rock check. The remaining water, and seepage, between the temporary dam and berm was pumped downstream to reveal the bottom of the channel. At low flows, this system provided 8-10 hours to construct the rock check. At the end of the day, the temporary dam was deflated enough to pass water overnight, then re-inflated the following day to resume work. Installation and removal of the temporary inflatable dam took between 2-5 hours, and it could not be left in place for extended periods. This process was labor-intensive and required constant monitoring. As water levels rose behind the dam, the risk of the dam rolling increased. Also, if flows increased, the work time decreased rapidly. An alternate method to construct the rock checks was developed by installing temporary sheet piles across the channel upstream of the rock check dam (or series of rock check dams). This created a more reliable and controllable temporary dam that could be quickly removed if higher flows arrived. Water was pumped around the dry reach. The pumps weren t sized to handle the entire flow, but they increased work time significantly. 848 Innovative Dam and Levee Design and Construction

11 Levee Top Repairs. Levee crest repairs restored nine miles on both sides of the channel to the originally constructed 1958 elevations. Over time, two factors primarily contributed to decreased levee height. The first is levee consolidation and settling of the soil. The second is minor erosion caused by overtopping during flood events. In addition to restoring the 1958 elevations, six inches of aggregate was placed on the levee crests to prevent wheel ruts when the soil is moist. Construction Challenges and Considerations Construction Sequence. A construction sequence was not specified in the design. The contractor chose to start work at the upstream end of the project and progress downstream, saving the majority of rock check dams and the entire lower reach until the majority of bank repairs are complete. This was not what the designer envisioned and resulted in increased risk exposure to high water or floods. The features critical to controlling degradation and erosion were not in place for the majority of the construction period. Also, the keystone rock check, the one closest to the mouth of the diversion unit, was not constructed until the end of the construction period. Significant weather delays and high water extended the construction period and further increased the risk of erosion. The construction sequence that most reduces risk may not be the most cost effective, so prior to bidding it is important to communicate the relative benefits of alternative construction sequences to potential construction contractors in order to allow them to factor them their bids. Plant Establishment Time. The willows require a one year establishment period while native grasses require a three year period. High water that inundates the willows or grasses for more than a week will kill the plants and require replanting. If the high water erodes the toe of the bank before the vegetation is established, reconstruction of the bank may be required if the erosion is severe or if it is in a critical location. Reconstruction of eroded areas is challenging due to the requirement to move equipment to the bottom of the channel while minimizing disturbance of repaired areas higher up the bank. High water isn t normally a frequent occurrence, but two or three sustained high water events in a three year period would not be unusual. These events could result in costly repairs of eroded areas. Customer Satisfaction. Customer satisfaction is very important. The customer was not involved in the technical design phases or the construction, but the customer is the end user and will ultimately judge the design performance and quality of construction. The completed work must allow the end user to operate and maintain the project at minimum expense and effort. Currently, the customer has expressed concerns with the design and construction related to sustainability and safety. Sustainability. The sustainability concern arose after two successive high water events (2- year and 5-year flows) during construction that eroded the toe of the channel in several locations. To a small degree, minor erosion is expected in the channel, especially below the willows. However, the erosion experienced during the two high water events was more severe than expected and the water stayed high for about 14 days. This severely Soldier Creek Levee Repair 849

12 impacted some of the willows by either washing them away completely or inundating them and killing them. However the area of most concern was just downstream of the confluence of Soldier Creek and Indian Creek. Erosion reached the toe of the levee in that location. Due to the relative watershed sizes of the two creeks, water from Indian Creek entered the Solider Creek channel at approximately a 45 degree angle and eroded the opposite bank until the water surface in Solider Creek increased sufficiently to dissipate the energy from the tributary. 3 Rock check #7, just downstream of the tributary confluence, also affects normal flow patterns that might otherwise center the flow. Riprap will be added in the areas where erosion was more severe. The potential for erosion should be significantly reduced once the willows are established. Occasional replacement of willows may be required if water levels stay high for extended periods. Safety. The safety concern is related to the removal of ramps and turnaround areas. Occasionally the customer hauls truckloads of rock or soil for minor repairs on the levees. These trucks need turnarounds and ramps to reach lower areas of the channel. These weren t reproduced in the new design. Levee Integrity & Sustainability. Soldier Creek is a flood damage reduction project and helps protect the City of Topeka from flooding. It is critical that the focus of design and construction be on proven methods for sustainability, reliability, operation, and maintenance. Levees that protect lives and property should keep sustainable construction methods in balance. While a uniform riprapped channel may be expensive to construct and less aesthetic, it is a proven and reliable flood damage reduction tool. A better balance between conventional and sustainable design should be sought. While the riprap provides immediate erosion protection, the willows contribute to a more visually appealing channel. Thalwegs. Construction of the thalweg pools was difficult due to the sandy soils prevalent in the channel. As soon as a bucket of soil was excavated, the side would cave in and nearly fill in the excavated area. Additionally, it only took a minor flow to transport enough sediment to fill in the thalwegs. In a channel with a sandy bed, it is nearly impossible to maintain anything but a flat channel bottom without constant and steady turbulence. Eventually the sand will self-level to remove any constructed slopes. Seven of the eleven thalweg pools were constructed and each filled in completely with the first high water event. Three of the four remaining pools were not constructed. The final pool, around the long bend near the mouth, was constructed. The long radius of this pool is more likely to develop a rolling current that will self-scour to maintain the pool structure as designed. Channel Bed Material. The channel bed material upstream of the approximate location of rock check #3 consists of coarse sand and pebbles. Downstream of rock check #3, the bed materials transition to a fine silt and sandy loam where the Kansas River frequently backs 3 Observations of Alan Schlindwein, P.E., river hydraulic engineer, with the Kansas City District of the US Army Corps of Engineers. 850 Innovative Dam and Levee Design and Construction

13 up into Soldier Creek. Neither of these bed materials lend themselves to thalweg pool construction or anchoring rock check dams. In particular, the first rock check dam called for 3-ton riprap to be placed in the bed. The bedding of these rocks is critical to maintain their grade in a fine sand channel 4, however due to the difficulty in preparing such bedding, a more economical solution was sought. The final solution was to shift the first rock check upstream to connect with riprap under the Union Pacific Railroad Bridge. The size of the rock check riprap was reduced to 1-ton. Hydraulic models demonstrated that shear forces permit the smaller riprap size. Figure 6. High Water Event at Downstream Bridges Channel-to-pier Alignment. It was discovered during construction that a large bend near the mouth of the diversion unit did not align flows with a pair of bridges at the exit of the bend (see Fig. 6 5 ). The design was modified to align the flows parallel to the bridge piers and minimize turbulence. Earthwork and Riprap Quantities. The construction contract is a lump sum contract. This simplifies the contract structure and bidding process, but leads to difficulties when negotiating modifications, as the designer and construction contractor rarely agree on quantities. In a large earthwork project, the quantities of cut/fill and riprap are significant costs and accurate quantities are necessary for pricing. A future recommendation would be to structure the contract to include certain unit prices to simplify future negotiations. Construction Successes Equipment-mounted GPS. The construction contractor used excavation equipment with GPS mounted on the blade or bucket. This gives the ability to construct very accurate channel banks and beds. This feature saves time and results in construction that more accurately reflects the intended design. 4 Ibid. 6 Photo credit US Army Corps of Engineers. Soldier Creek Levee Repair 851

14 Digital model. The design surface was provided to the construction contractor for their use. While it required conversion to a format they could use, it was a valuable tool for them to transfer the drawings to the channel construction. Temporary dams. Rock checks were constructed using temporary dams. After difficulties were encountered with inflatable dams, the sheet pile temporary dams offered a much improved solution. Aesthetics. The sinuous channel is more visually appealing than a uniform riprap-lined channel. In urban areas, although aesthetics are important, the right balance between sustainable and conventional design should be sought. Flexibility. Although, constructing the lower reach of the channel last was not anticipated, it did allow observation of the constructed upper reaches of the channel in two high water events. Through these observations, significant changes were made to the lower reach design, which will result in a more stable channel. CONCLUSIONS The following are the three foremost conclusions which have been drawn over the course of the study, design, and construction phases of this project: Construction performed based on the design principles common during the 1950 s (primarily involving stream straightening), may subsequently produce degraded profiles and eroded stream banks. Stream stability design principles should produce streams with reduced long term maintenance costs. These design principles include optimizing channel geometry, sinuosity, pool-riffle spacing, rock check dams, and vegetation. It is important to have a thorough knowledge of the site geology in order to achieve this. Construction challenges should be expected even for a contractor experienced with water control issues associated with working in a stream. Careful planning needs to go into the construction sequence in order to maximize the opportunity for plant establishment relative to the seasonal timing of high water events. REFERENCES Bentley, Intergraph Inroads, Version 8, Exton, PA. FHWA NHI , HEC-18, Evaluating Scour at Bridges, 4 th Edition, May GEO-SLOPE International, Ltd., SLOPE/W 2007, Calgary, Alberta, Canada. Juracek, Kyle. Historical Change Along Soldier Creek, Northeast Kansas. USGS Water Resources Investigations Report Innovative Dam and Levee Design and Construction

15 Kansas City Metropolitan Chapter, American Public Works Association (KCAPWA), Construction and Material Specifications, Section 5600 Storm Drainage Systems and Facilities, Design Criteria. Pemberton E.L. & Lara, J.M. (1984). Computing Degradation and Local Scour. Technical guideline for Bureau of Reclamation, U.S. Department of Interior, Bureau of Reclamation, Denver, CO. Soar, Philip J. and Thorne, Colin R., Channel Restoration Design for Meandering Rivers. Engineer Research and Development Center, US Army Corps of Engineers. U.S. Army Corps of Engineers (USACE) Channel Stability Assessment for Flood Control Projects. Engineer Manual U. S. Army Corps of Engineers, Hydrologic Engineering Center, HEC-RAS, Hydrologic Modeling System, Version 3.1.3, Davis, California, January U.S. Army Corps of Engineers, Project Information Report, Rehabilitation of Damaged Flood Control Works. Part II. Basic Report, May Soldier Creek Levee Repair 853

16

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

Prattsville Berm Removal Project. 1.0 Project Location

Prattsville Berm Removal Project. 1.0 Project Location Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed

More information

3. Design Procedures. Design Procedures. Introduction

3. Design Procedures. Design Procedures. Introduction Design Procedures 3. Design Procedures Introduction This chapter presents a procedure for the design of natural channels. The chapter primarily focuses on those physical properties of the channel required

More information

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration Stream Rehabilitation Concepts, Guidelines and Examples Pierre Y. Julien Wuhan 2005 Objectives Part I - Stream restoration and rehabilitation: 1. Present and discuss important concepts, laws, criteria

More information

How To Check For Scour At A Bridge

How To Check For Scour At A Bridge Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway

More information

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES WATER RESOURCES MANAGEMENT DIVISION Water Investigations

More information

1.7.0 Floodplain Modification Criteria

1.7.0 Floodplain Modification Criteria 1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:

More information

Appendix 4-C. Open Channel Theory

Appendix 4-C. Open Channel Theory 4-C-1 Appendix 4-C Open Channel Theory 4-C-2 Appendix 4.C - Table of Contents 4.C.1 Open Channel Flow Theory 4-C-3 4.C.2 Concepts 4-C-3 4.C.2.1 Specific Energy 4-C-3 4.C.2.2 Velocity Distribution Coefficient

More information

ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND

ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND The Rose Creek Watershed (RCW) consists of three planning

More information

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies. RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover

More information

Final Report. Dixie Creek Restoration Project. Funded by Plumas Watershed Forum

Final Report. Dixie Creek Restoration Project. Funded by Plumas Watershed Forum Final Report Dixie Creek Restoration Project Funded by Plumas Watershed Forum Plumas Corporation January 2009 1 Background FR-CRM staff presented this project to the Dixie Valley Landowners Association

More information

ECONOMIC ANALYSIS FLOOD DAMAGE REDUCTION. Lower Carmel River Floodplain Restoration and Enhancement Project

ECONOMIC ANALYSIS FLOOD DAMAGE REDUCTION. Lower Carmel River Floodplain Restoration and Enhancement Project ECONOMIC ANALYSIS FLOOD DAMAGE REDUCTION Lower Carmel River Floodplain Restoration and Enhancement Project I. Description of the Project and its Relationship to Other Projects in the Proposal The Lower

More information

CHAPTER 9 CHANNELS APPENDIX A. Hydraulic Design Equations for Open Channel Flow

CHAPTER 9 CHANNELS APPENDIX A. Hydraulic Design Equations for Open Channel Flow CHAPTER 9 CHANNELS APPENDIX A Hydraulic Design Equations for Open Channel Flow SEPTEMBER 2009 CHAPTER 9 APPENDIX A Hydraulic Design Equations for Open Channel Flow Introduction The Equations presented

More information

EFFECTS OF ARUNDO DONAX ON RIVER HYDRAULICS, SEDIMENT TRANSPORT, AND GEOMORPHOLOGY, SANTA MARGARITA RIVER, CALIFORNIA

EFFECTS OF ARUNDO DONAX ON RIVER HYDRAULICS, SEDIMENT TRANSPORT, AND GEOMORPHOLOGY, SANTA MARGARITA RIVER, CALIFORNIA EFFECTS OF ARUNDO DONAX ON RIVER HYDRAULICS, SEDIMENT TRANSPORT, AND GEOMORPHOLOGY, SANTA MARGARITA RIVER, CALIFORNIA René Leclerc Geomorphologist Robert C. MacArthur, Ph.D., P.E. Principal Headwaters

More information

720 Contour Grading. General. References. Resources. Definitions

720 Contour Grading. General. References. Resources. Definitions 720 Contour Grading General Contour grading directs water to a desired point, prevents erosion, provides noise deflection, provides visual fit of the facility into the landscape, and protects desirable

More information

Neversink River East Branch

Neversink River East Branch Neversink River East Branch Management Unit 10 Summary of Post-Flood Recommendations Intervention Level Full restoration of the stream reach including the eroding bank site between Station 38380 and Station

More information

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes Chapter 2 Flash Flood Science A flash flood is generally defined as a rapid onset flood of short duration with a relatively high peak discharge (World Meteorological Organization). The American Meteorological

More information

Riprap-lined Swale (RS)

Riprap-lined Swale (RS) Riprap-lined Swale (RS) Practice Description A riprap-lined swale is a natural or constructed channel with an erosion-resistant rock lining designed to carry concentrated runoff to a stable outlet. This

More information

STORMWATER MANAGEMENT CHECKLIST

STORMWATER MANAGEMENT CHECKLIST STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative

More information

Evaluation of Open Channel Flow Equations. Introduction :

Evaluation of Open Channel Flow Equations. Introduction : Evaluation of Open Channel Flow Equations Introduction : Most common hydraulic equations for open channels relate the section averaged mean velocity (V) to hydraulic radius (R) and hydraulic gradient (S).

More information

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES Run-off Analysis Methods This document sets forth the minimum design, technical criteria and specifications for the

More information

Floodplain Connectivity in Restoration Design

Floodplain Connectivity in Restoration Design Floodplain Connectivity in Restoration Design 2015 Symposium on Restoration in a Contaminated Environment: Lessons Learned and Challenges in Moving Forward Part II April 2015 Karin Boyd Applied Geomorphology,

More information

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

Open Channel Flow 2F-2. A. Introduction. B. Definitions. Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow

Open Channel Flow 2F-2. A. Introduction. B. Definitions. Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow 2F-2 Open Channel Flow A. Introduction The beginning of any channel design or modification is to understand the hydraulics of the stream. The

More information

The Teton Creek Restoration Project Summary:

The Teton Creek Restoration Project Summary: The Teton Creek Restoration Project Summary: The Teton Creek Restoration Project area extends for approximately one mile upstream from the Cemetery Road Bridge and includes the Aspen Pointe, The Aspens

More information

Mission Creek Flood Control & Restoration Project. City of Fremont, Alameda County

Mission Creek Flood Control & Restoration Project. City of Fremont, Alameda County Mission Creek Flood Control & Restoration Project City of Fremont, Alameda County Agenda Background Why are proposed improvements necessary? Proposed project components Challenges Construction schedule/phasing

More information

Jackson Gulch Outlet Canal Rehabilitation Project

Jackson Gulch Outlet Canal Rehabilitation Project Jackson Gulch Outlet Canal Rehabilitation Project Preliminary Budgetary Estimate for Rehabilitation February 2004 Prepared for the Mancos Water Conservancy District Jackson Gulch Reservoir 42888 County

More information

DANIELS RUN STREAM RESTORATION, FAIRFAX, VIRGINIA: FLOODPLAIN ANALYSIS REPORT

DANIELS RUN STREAM RESTORATION, FAIRFAX, VIRGINIA: FLOODPLAIN ANALYSIS REPORT DANIELS RUN STREAM RESTORATION, FAIRFAX, VIRGINIA: FLOODPLAIN ANALYSIS REPORT By: Conor C. Shea Stream Habitat Assessment and Restoration Program U.S. Fish and Wildlife Service CBFO-S07-01 Prepared in

More information

Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can

Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can do his or her share to protect Ohio's water resources

More information

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness 3 Chapter 3 of Concentration and Travel Time Time of Concentration and Travel Time Travel time ( T t ) is the time it takes water to travel from one location to another in a watershed. T t is a component

More information

URBAN DRAINAGE CRITERIA

URBAN DRAINAGE CRITERIA URBAN DRAINAGE CRITERIA I. Introduction This division contains guidelines for drainage system design and establishes a policy for recognized and established engineering design of storm drain facilities

More information

The Basics of Chapter 105 Waterways and Wetlands Permitting in PA

The Basics of Chapter 105 Waterways and Wetlands Permitting in PA The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers

More information

General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title]

General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title] General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title] Purpose These rules set forth the conditions under which a person may, without an individual removal-fill permit

More information

GLOSSARY OF TERMS CHAPTER 11 WORD DEFINITION SOURCE. Leopold

GLOSSARY OF TERMS CHAPTER 11 WORD DEFINITION SOURCE. Leopold CHAPTER 11 GLOSSARY OF TERMS Active Channel The channel that contains the discharge Leopold where channel maintenance is most effective, sediment are actively transported and deposited, and that are capable

More information

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN 3.4 DRAINAGE PLAN This section describes the existing onsite drainage characteristics and improvements proposed within this Specific Plan. Following this description, drainage plan development standards

More information

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED

More information

A Stream Restoration Case Study in the California Central Coast

A Stream Restoration Case Study in the California Central Coast International Erosion Control Association Annual Conference 2009, Reno, Nevada Case Study Technical Presentation A Stream Restoration Case Study in the California Central Coast Justin S. Rogers, P.E.,

More information

Topic 8: Open Channel Flow

Topic 8: Open Channel Flow 3.1 Course Number: CE 365K Course Title: Hydraulic Engineering Design Course Instructor: R.J. Charbeneau Subject: Open Channel Hydraulics Topics Covered: 8. Open Channel Flow and Manning Equation 9. Energy,

More information

Catchment Scale Processes and River Restoration. Dr Jenny Mant Jenny@therrc.co.uk. The River Restoration Centre therrc.co.uk

Catchment Scale Processes and River Restoration. Dr Jenny Mant Jenny@therrc.co.uk. The River Restoration Centre therrc.co.uk Catchment Scale Processes and River Restoration Dr Jenny Mant Jenny@therrc.co.uk The River Restoration Centre therrc.co.uk 3 Main Catchment Elements Hydrology Energy associated with the flow of water affects

More information

Swannanoa River Flood Risk Management Study

Swannanoa River Flood Risk Management Study Swannanoa River Flood Risk Management Study Measures Evaluated to Reduce Future Flood Damages City of Asheville U.S. Army Corps of Engineers Flooding History Part of the 132 square mile Swannanoa River

More information

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT 2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT Open channel flow is defined as flow in any channel where the liquid flows with a free surface. Open channel flow is not under pressure; gravity is the

More information

Prepared By: Tom Parker Geum Environmental Consulting, Inc.

Prepared By: Tom Parker Geum Environmental Consulting, Inc. Prepared By: Tom Parker Geum Environmental Consulting, Inc. Topics covered: Definition of riparian and floodplain restoration Floodplain attributes as a basis for developing criteria for restoration designs

More information

Small Dam Hazard Assessment Inventory

Small Dam Hazard Assessment Inventory Small Dam Hazard Assessment Inventory What would happen if your dam were to fail? This is a question that most dam owners hope they will never have to answer. However it is a question you, as a responsible

More information

Environmental Case Study Decatur, Georgia, DeKalb County A Suburban Creek Resists Channelization

Environmental Case Study Decatur, Georgia, DeKalb County A Suburban Creek Resists Channelization Introduction A visual examination of Doolittle Creek in a highly developed suburban county in Georgia yielded telltale signs of a creek whose original streambed had been altered. Examination of official

More information

Flood Hazard Area Technical Manual Section 8 Bank Stabilization and Stream Restoration

Flood Hazard Area Technical Manual Section 8 Bank Stabilization and Stream Restoration Flood Hazard Area Technical Manual Section 8 Bank Stabilization and Stream Restoration Prepared by: New Jersey Section American Water Resources Association Stream Restoration Committee FHA Subcommittee

More information

Guo, James C.Y. (2004). Design of Urban Channel Drop Structure, J. of Flood Hazards News, December,

Guo, James C.Y. (2004). Design of Urban Channel Drop Structure, J. of Flood Hazards News, December, Guo, James C.. (004). esign of Urban Channel rop Structure, J. of Flood azards News, ecember, Guo, James C.., (009) Grade Control for Urban Channel esign, submitted to Elsevier Science, J. of ydro-environmental

More information

Proposal to the Trinity Adaptive Management Working Group (TAMWG)

Proposal to the Trinity Adaptive Management Working Group (TAMWG) Proposal to the Trinity Adaptive Management Working Group (TAMWG) Request that the TAMWG recommend that the Trinity River Restoration Program fund BLM to purchase the Weigel parcel at Gold Bar (river mile

More information

SECTION 5: SANITARY SEWER SYSTEM DESIGN

SECTION 5: SANITARY SEWER SYSTEM DESIGN SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities

More information

FLOOD PROTECTION BENEFITS

FLOOD PROTECTION BENEFITS IV. (340 points) Flood Protection Benefits A. Existing and potential urban development in the floodplain (50) 1. Describe the existing and potential urban development at the site and the nature of the

More information

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES 5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES Flood damage reduction consists of two basic techniques structural and non-structural. Structural methods modify the flood and take the flood away from people

More information

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION 199 9.1(479,479B) General information. 9.1(1) Authority. The standards contained herein

More information

CHAPTER 3 STORM DRAINAGE SYSTEMS

CHAPTER 3 STORM DRAINAGE SYSTEMS CHAPTER 3 STORM DRAINAGE SYSTEMS 3.7 Storm Drains 3.7.1 Introduction After the tentative locations of inlets, drain pipes, and outfalls with tail-waters have been determined and the inlets sized, the next

More information

SECTION 5. Sediment Control Measures

SECTION 5. Sediment Control Measures SECTION 5 Sediment Control Measures 60. STORM DRAIN INLET PROTECTION When Runoff from earth change activities will discharge to a catch basin or storm drain inlet. A newly constructed catch basin or storm

More information

US Army Corps of Engineers BUILDING STRONG

US Army Corps of Engineers BUILDING STRONG Fort Worth District Public Meeting 20 August 2013 US Army Corps of Engineers Lewisville Dam - Authorization Authorized by the River and Harbor Act, approved 2 March 1945 (Public Law 14, 79th Congress,

More information

Appendix H Dredging and Stream Channel Restoration

Appendix H Dredging and Stream Channel Restoration Appendix H Dredging and Stream Channel Restoration Mankind s intrusion into the natural environment in West Virginia began in earnest following the Civil War when extractive industries and settlement all

More information

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local

More information

Basic Principles of Channel Design

Basic Principles of Channel Design United States Department of Agriculture Natural Resources Conservation Service Stream Restoration Design Chapter 7 Basic Principles of Channel Design Issued August 2007 Cover photo: Where modification

More information

TENNESSEE GAS PIPELINE COMPANY, L.L.C.

TENNESSEE GAS PIPELINE COMPANY, L.L.C. TENNESSEE GAS PIPELINE COMPANY, L.L.C. HYDROLOGIC & HYDRAULIC CALCULATIONS FOR WATERBODIES CROSSED BY CONNECTICUT PIPELINE EXPANSION PROJECT CONNECTICUT LOOP Submitted by: Tennessee Gas Pipeline Company,

More information

WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE

WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE May 24, 2005 Table of Contents Introduction...3 Definitions...3 Types of Wetland Restorations...4 Re-Contouring...4 Engineered...4 Water

More information

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION (1) Project Name: (2) Project Contractor: (3) Erosion Control Supervisor/SWMP Administrator: (4) CDOT Project

More information

City of Austin Stream Restoration Program Mid-Atlantic Stream Restoration Conference, Rocky Gap, MD November 2011

City of Austin Stream Restoration Program Mid-Atlantic Stream Restoration Conference, Rocky Gap, MD November 2011 Welcome City of Austin Stream Restoration Program Mid-Atlantic Stream Restoration Conference, Rocky Gap, MD November 2011 Morgan Byars, P.E. City of Austin Watershed Protection Department Environmental

More information

Table 4.9 Storm Drain Inlet Protetion Applicable for

Table 4.9 Storm Drain Inlet Protetion Applicable for BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection

More information

Scheduling Maintenance for Infiltration Basins and Trenches

Scheduling Maintenance for Infiltration Basins and Trenches Visual Inspection for Infiltration Practices Visual inspection is a rapid assessment procedure for qualitatively evaluating the functionality of a stormwater best management practice (BMP). Visual inspections

More information

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE 1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,

More information

LATEST ENHANCEMENTS TO THE RIVERMorph STREAM RESTORATION SOFTWARE

LATEST ENHANCEMENTS TO THE RIVERMorph STREAM RESTORATION SOFTWARE LATEST ENHANCEMENTS TO THE RIVERMorph STREAM RESTORATION SOFTWARE J. George Athanasakes, PE RIVERMorph, LLC 1901 Nelson Miller Parkway Louisville, KY 40223-2177 233 BIOGRAPHICAL SKETCH J. George Athanasakes,

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

Homeowner s Guide to Drainage

Homeowner s Guide to Drainage Homeowner s Guide to Drainage a scottsdale homeowner s guide to drainage produced by the city of scottsdale s stormwater management division Transportation Department TABLE OF CONTENTS Introduction 2 Drainage

More information

Managing Our Water Retention Systems

Managing Our Water Retention Systems Managing Our Water Retention Systems 29th Annual USSD Conference Nashville, Tennessee, April 20-24, 2009 Hosted by Corps of Engineers On the Cover Wolf Creek Dam is on the Cumberland River in South Central

More information

HCP Team Meeting. November 18, 2015. icfi.com

HCP Team Meeting. November 18, 2015. icfi.com HCP Team Meeting November 18, 2015 icfi.com 1 Welcome and Introductions Where are we in the HCP process Hydrology modeling update Native fish survey Fish translocation Finalize covered activities Next

More information

Various options are discussed below.these low cost, low impact interventions can also be applied as general erosion control methods.

Various options are discussed below.these low cost, low impact interventions can also be applied as general erosion control methods. Week 10 River Hydraulics Rehabilitating Urban Waterways (From http://hubpages.com/hub/river-bank-erosion-control-methods) See also the resources placed on Moodle. Water channels should be viewed as a resource

More information

ALTERNATIVES EVALUATION. SWEET POND DAM VT Dam #90.01 Town of Guilford, Vermont

ALTERNATIVES EVALUATION. SWEET POND DAM VT Dam #90.01 Town of Guilford, Vermont ALTERNATIVES EVALUATION SWEET POND DAM VT Dam #90.01 Town of Guilford, Vermont Prepared for: Vermont Department of Forests, Parks and Recreation Prepared by: January 27, 2012 D&K #221179 SWEET POND DAM

More information

Stormwater/Wetland Pond Construction Inspection Checklist

Stormwater/Wetland Pond Construction Inspection Checklist : Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials

More information

Shooks Run Drainage Study Basic Terminology

Shooks Run Drainage Study Basic Terminology Shooks Run Drainage Study Basic Terminology PREPARED FOR: PREPARED BY: City of Colorado Springs CH2M DATE: April 9, 2015 Introduction This document is intended to provide an introduction to Colorado Springs

More information

STORM DRAINS CHAPTER 7

STORM DRAINS CHAPTER 7 CHAPTER 7 Chapter 7 - Storm Drains A storm drain is a drainage system that conveys water or stormwater, consisting of two or more pipes in a series connected by one or more structures. Storm drains collect

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

Basic Hydrology. Time of Concentration Methodology

Basic Hydrology. Time of Concentration Methodology Basic Hydrology Time of Concentration Methodology By: Paul Schiariti, P.E., CPESC Mercer County Soil Conservation District What is the Time of Concentration? The time it takes for runoff to travel from

More information

Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road,

Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road, Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road, Wolverhampton, WV6 0PJ Tel 01902 712200 Fax 01902 714096 e-mail sales@hy-tengabions.com

More information

WHAT YOU NEED TO KNOW ABOUT LIVING NEAR INDIANA COAL MINES

WHAT YOU NEED TO KNOW ABOUT LIVING NEAR INDIANA COAL MINES WHAT YOU NEED TO KNOW ABOUT LIVING NEAR INDIANA COAL MINES Who Should Read This Guide? Home Buyers/Owners Lending Institutions Landowners Developers Local Officials Construction Design Realtors Companies

More information

March 2008. Prepared by: Irvine Ranch Water District. 15600 Sand Canyon Avenue. Irvine, CA 92618. Contact: Natalie Likens (949) 453-5633

March 2008. Prepared by: Irvine Ranch Water District. 15600 Sand Canyon Avenue. Irvine, CA 92618. Contact: Natalie Likens (949) 453-5633 ADDENDUM TO THE MICHELSON WATER RECLAMATION PLANT PHASE 2 & 3 CAPACITY EXPANSION PROJECT FEBRUARY 2006 FINAL ENVIRONMENTAL IMPACT REPORT AND THE SAN JOAQUIN FRESHWATER MARSH ENHANCEMENT PLAN REVISED SEPTEMBER

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

Part 7 GEOTEXTILE FILTER FABRICS

Part 7 GEOTEXTILE FILTER FABRICS Part 7 GEOTEXTILE FILTER FABRICS Well Screens Slotted casings are normally employed as well screens within the aquifers being taped by water wells. The width of the slots should allow 50 to 60% of the

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

Floodplain Development Land Use Review

Floodplain Development Land Use Review COMMUNITY DEVELOPMENT DEPARTMENT Planning Division P.O. Box 490 333 Broadalbin Street SW Albany, OR 97321 Phone 541-917-7550 Fax 541-791-0150 www.cityofalbany.net Floodplain Development Land Use Review

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)

More information

SIMULATION OF SEDIMENT TRANSPORT AND CHANNEL MORPHOLOGY CHANGE IN LARGE RIVER SYSTEMS. Stephen H. Scott 1 and Yafei Jia 2

SIMULATION OF SEDIMENT TRANSPORT AND CHANNEL MORPHOLOGY CHANGE IN LARGE RIVER SYSTEMS. Stephen H. Scott 1 and Yafei Jia 2 US-CHINA WORKSHOP ON ADVANCED COMPUTATIONAL MODELLING IN HYDROSCIENCE & ENGINEERING September 19-21, Oxford, Mississippi, USA SIMULATION OF SEDIMENT TRANSPORT AND CHANNEL MORPHOLOGY CHANGE IN LARGE RIVER

More information

Temporary Erosion-Control Measures

Temporary Erosion-Control Measures A Guide to Temporary Erosion-Control Measures for Contractors, Designers and Inspectors June 2001 North Dakota Department of Health Division of Water Quality A Guide to Temporary Erosion-Control Measures

More information

NJ650.1404 Interception Drainage

NJ650.1404 Interception Drainage NJ650.1404 Interception Drainage Interception drainage is used to intercept surface and subsurface water. The investigation, planning, and construction of surface interception drains follow the requirements

More information

NRCS Overview. National Dam Safety Program Technical Workshop #19 February 22-23, 2012

NRCS Overview. National Dam Safety Program Technical Workshop #19 February 22-23, 2012 NRCS Overview National Dam Safety Program Technical Workshop #19 February 22-23, 2012 Thomas Brown National Design, Construction, and Soil Mechanics Center (NDCSMC) Fort Worth, Texas NRCS Dam Inventory

More information

February 4, 2011. hoffman.stephen@epa.gov. Report Recommendations and NIPSCO Responses. 4.3 Maintaining and Controlling Vegetation Growth

February 4, 2011. hoffman.stephen@epa.gov. Report Recommendations and NIPSCO Responses. 4.3 Maintaining and Controlling Vegetation Growth February 4, 2011 VIA E-MAIL AND CERTIFIED MAIL #7010 0290 0002 0577 6226 Mr. Stephen Hoffman US Environmental Protection Agency (5304P) 1200 Pennsylvania Avenue, NW Washington, DC 20460 hoffman.stephen@epa.gov

More information

Frequently-Asked Questions about Floodplains and Flood Insurance FLOOD INSURANCE

Frequently-Asked Questions about Floodplains and Flood Insurance FLOOD INSURANCE Frequently-Asked Questions about Floodplains and Flood Insurance What is a floodplain? The floodplain is any area covered by water during normal water flows, and which could be inundated as a result of

More information

DEPARTMENT OF THE ARMY SECTION 404 REGIONAL GENERAL PERMIT CHANNEL AND BANK PROTECTION STRUCTURES ON THE SOUTH PLATTE RIVER

DEPARTMENT OF THE ARMY SECTION 404 REGIONAL GENERAL PERMIT CHANNEL AND BANK PROTECTION STRUCTURES ON THE SOUTH PLATTE RIVER DEPARTMENT OF THE ARMY SECTION 404 REGIONAL GENERAL PERMIT CHANNEL AND BANK PROTECTION STRUCTURES ON THE SOUTH PLATTE RIVER Permit Expires: December 31, 2017 Regional General Permit No. 87-01 Issuing Office:

More information

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map Parcel: Acreage: Plat: ADC Map & Grid Engineering

More information

CHAPTER 2 HYDRAULICS OF SEWERS

CHAPTER 2 HYDRAULICS OF SEWERS CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination

More information

HYDROLOGIC/HYDRAULIC MODELING OF WESTMINSTER WATERSHED ORANGE COUNTY, CALIFORNIA

HYDROLOGIC/HYDRAULIC MODELING OF WESTMINSTER WATERSHED ORANGE COUNTY, CALIFORNIA HYDROLOGIC/HYDRAULIC MODELING OF WESTMINSTER WATERSHED ORANGE COUNTY, CALIFORNIA James Chieh, Ph.D., P.E., Senior Hydraulic Engineer, USACE, Los Angeles, California, Shih.H.Chieh@usace.army.mil; Jay Pak,

More information