3. Design Procedures. Design Procedures. Introduction

Size: px
Start display at page:

Download "3. Design Procedures. Design Procedures. Introduction"

Transcription

1 Design Procedures 3. Design Procedures Introduction This chapter presents a procedure for the design of natural channels. The chapter primarily focuses on those physical properties of the channel required for hydraulic stability. The design procedure is presented only as a guide and in most circumstances final channel dimensions should be appropriately varied along the channel to form a natural rather than constructed appearance. Note: This chapter should only need to be reviewed if the proposed stream rehabilitation works require the relocation, reconstruction or alteration of the main channel. In any case, wherever possible, all appropriate channel features (Appendix A) should be incorporated into the existing or reconstructed channel. Depending on the type of creek works proposed, there can be a number of design steps that should and should not be performed. In some cases the channel location may be preset, in other cases the purpose of the creek works may only be to improve the ecological values of the channel bed or banks. In any case, the design philosophy should be to review only those design steps relevant to the given circumstances. The design procedure presented below is based on the following design philosophy: (i) (ii) (iii) (iv) The channel s geometry, bed and floodplain are influenced by different design flow rates, those being: bankfull flow, low flows and flood flows. The channel width, depth, meander radius and allowable channel slope are determined by the adopted bankfull flow rate and the allowable bankfull flow velocity at various stages of revegetation. The bed design is determined by the adopted channel slope and low flow conditions. The overbank geometry and vegetation density is governed, in part, by high level flood flows. Remember: There is more than one way to solve a hydraulic problem, and there is more than one way to solve a ecological problem. It is important to be creative, thoughtful and flexible. Also, aesthetics is often not the primary controlling factor. Good aesthetics does not necessarily result in good ecological values. 24

2 Natural Channel Design Guidelines Data collection Where possible, obtain a long section survey of the channel bed. This will assist in the selection of channel gradient and in locating pools and riffles. Soil tests should be conducted to determine if the soil is dispersive (Emerson Aggregate Test) and what type of soil it is, e.g. sandy, sandy loam, or clay. Design steps The following steps are used in this design procedure. Step 1 Step 2 Step 3 Step 4 Step 5 Step 6 Step 7 Step 8 Step 9 Step 10 Step 10-1(a) Step 10-1(b) Step 10-2(b) Step 10-3(b) Step 10-4(b) Step 10-5(b) Step 10-6(b) Step 10-7(b) Step 10-8(b) Step 11 Select the reach of watercourse to be rehabilitated Determine channel fall Determine bankfull flow rate Select the type of channel Determine channel width and channel depth Channel bank slope Determine typical channel meander radius Select trial channel location Review riparian and floodplain vegetation Design of channel bed and low flow channel Bed design for channel with little or no bed vegetation - determine bed form Bed design for channels with bed vegetation determine bed form Determine the length of the low flow channel Determine the number of riffles Determine typical riffle dimensions Determine typical pool dimensions Determine pool length Determine riffle rock size Design low flow channels Incorporate channel features 25

3 Design Procedures Symbols D [m] Channel depth from bankfull water level to channel invert D N [m] Nominal rock diameter of which N% of the rock is smaller, i.e. 10% of the rock is smaller than the D 10 rock size. Rock size is measured as the diameter of a sphere with an equivalent volume to the individual rock D p [m] Maximum pool depth d/s [-] Downstream F r [m] Riffle fall measured from riffle crest to the low flow pool level within the downstream pool F t [m] Total channel fall across the proposed rehabilitation area equals upstream channel invert level minus downstream channel invert level L 1 [m] The valley length measured along a smooth straight or curved path (not including the channel meanders) from the upstream end of the channel reach to the downstream end of the channel reach L 2 [m] Length of a meandering watercourse channel measured along the channel centreline L 3 [m] Length of the low flow channel measured over a given reach of the watercourse L m [m] Straight line distance between successive channel meanders, or meander inflection points L p [m] Length of a low flow pool measured at the low flow water level L r [m] Riffle length measured from the riffle crest to the upstream end of the downstream low flow pool N [-] Number of riffles within a reach n [-] Manning s roughness value q [m 3 /s/m] Discharge per unit width for a nominated design event Q [m 3 /s] Discharge Q f [m 3 /s] Bankfull discharge Q fds [m 3 /s] Bankfull discharge immediately downstream of the works Q fus [m 3 /s] Bankfull discharge immediately upstream of the works Q [N] [m 3 /s] The peak design discharge at a given location that is expected to occur on average once every N years, i.e. the Q100 is the expected peak discharge during the 1 in 100 year design storm 26

4 Natural Channel Design Guidelines Symbols R c [m] Channel bend radius measured to the centre of the channel, or the low flow channel meander radius measured to the centre of the low flow channel R o [m] Bend radius measured to the outer bank of the channel at the elevation of bankfull flow S [m/m] Slope S o [m/m] Average channel slope over a selected reach S r [m/m] Slope of downstream face of riffle S i [-] Sinuosity = L 2 /L 1 or L 3 /L 2 u/s [-] Upstream V [m/s] Average flow velocity W [m] Channel top width measured at the height of the lower bank Wp [m] Maximum pool width measured at low flow water level W r [m] Riffle bed width [m] Average meander displacement, or half the amplitude of the meandering channel centreline or low flow channel centreline [deg] The angle measured between two consecutive inflection points Step 1. Select the reach of watercourse to be rehabilitated Waterways are normally rehabilitated in stages. Often the length, or reach, of a watercourse to be rehabilitated is determined by external factors beyond the control of the designer; however, where practicable, the length of rehabilitation should be restricted to a hydraulically and financially manageable reach length. A hydraulically manageable reach length is one where the occurrence of a 1 in 2 year flood during the revegetation phase does not result in unacceptable bank erosion or damage to newly established plants. A financially manageable reach length relates to the initial establishment cost as well as the short-term maintenance costs (i.e. weed control). The 1 in 2 year (or Q2) flow is important because it is considered that if most new plants are able to survive the first 2 years without suffering damage from a flood event, then they are likely to reach maturity. In a channel where the bankfull flow rate was around, say, the Q10 event, it would be unlikely for a Q10 event to occur within the first two years. Discussion on selecting the maximum reach length is provided in Technical Note

5 Design Procedures TECHNICAL NOTE 3.1 Often the governing factor in natural channel design is the allowable bankfull velocity during the early revegetation phase when the soil is disturbed and susceptible to erosion, and the effective channel roughness is low. Typically, during this post construction phase the Manning s n roughness of the channel is around n = 0.04 depending on the irregularity of the channel, the degree of meandering, and the size of the planted seedlings. If bankfull flow is less than say Q2, then it is likely that a bankfull flow will occur during the early growth stage of the plants. Therefore, if the bankfull flow velocities are high, say greater than 1 m/s (depending on soil type), then it is likely that significant damage will occur to the plants before they reach maturity. To avoid such problems, it may be desirable to rely on existing high channel roughness downstream of the rehabilitation works to reduce bankfull flow velocities throughout the work area. However, this will only be successful if the area of the proposed works is within the backwater region of the downstream channel. This can be confirmed with the use of a hydraulic backwater model, otherwise restrictions may need to be placed on the maximum allowable channel fall across a proposed section of creek works. In the absence of any other data or model results, if bankfull flow velocities are expected to be high, then the length of the proposed rehabilitation works should not extend over a total channel fall equal to half the channel depth (D). Under these conditions, it is likely that the channel works will occur within the backwater (ie low velocity) region of the downstream, vegetated channel. Step 2. Determine channel fall (F t ) It is important to walk the full length of any proposed channel works prior to commencing the design or even planning the works. Take note of any hydraulic controls, such as bed rock, pipe crossings, culverts or drop structures (natural or constructed). Any fixed bed features, such as bedrock, will affect the allowable fall of the channel bed and thus the profile of the channel bed as shown in Figure 3.1. Measure the elevation of any fixed bed structures and the total channel fall (F t ) across the proposed rehabilitation length (L 2 ). F t L 2 Figure 3.1 Channel long section 28

6 Natural Channel Design Guidelines Step 3. Determine bankfull flow rate (Q f ) Estimate bankfull flow rate upstream (Q fus ) and downstream (Q fds ) of the proposed works. In the unlikely situation where the bankfull flow rate is greater than the estimated Q100 discharge, then adopt the Q100 discharge. Calculate the Q1, Q1.5, Q2 and Q10 flow rates. As a first trial, nominate the bankfull flow rate (Q f ) based on the most appropriate of the following recommendations: (i) Average of Q fus and Q fds (if the length of the rehabilitated channel is small and there is a desire (aesthetically or otherwise) for the new channel to be of a similar size to the upstream and downstream channels. (ii) A calculated bankfull flow rate (Q f ) based on the monitoring of similar, stable streams and catchment land uses in the local region. (iii) Q1.5, if no specific regime equations have been developed for the local area, noting that in the Brisbane area, bankfull flow rates vary from less than Q1 to greater than Q10. (iv) A bankfull flow value based on local site constraints. In some circumstances the channel capacity may be determined by the requirements for flood control. In such cases a hydraulic model and study will be required for the complete floodplain. There is significant interaction between the channel and its floodplain and this should not be forgotten throughout the full design procedure. In long reaches it may be necessary to vary the bankfull discharge down the reach. Note: at Step 8 it may be necessary to reduce the nominated bankfull flow rate in order to obtain a stable channel (eg to reduce the bankfull velocity). Step 4. Select the type of channel The desirable style of drainage channel can vary from a grass-lined overland flow path for very small catchments to a fully established river channel for large catchments. Desirable bed conditions in a reconstructed watercourse usually depend on the following factors: catchment area catchment soil type (infiltration capacity) canopy cover Table 3.1 provides typical bed form conditions that are likely to occur in the Brisbane (Clayey Soil) region. The desirability of these bed form conditions of course depends on local hydraulic and ecological factors. 29

7 Design Procedures Table 3.1 Typical (desirable) bed conditions for the Brisbane region Catchment area Channel slope Desirable bed condition Less than 30 ha Open canopy Grassed bed urbanised catchment Closed canopy Rocky and/or vegetated bed Urbanised catchment between Steep channels Rock lined bed between 30 and 100 ha Grades > 1 in 20 Mild slopes Pool/riffle system, however, low flows Grades between may not be sufficient to maintain dry weather flows 1 in 20 and 1 in 100 and adequate pool water quality Flat slopes Grades < 1 in 500 Sandy channels Open earth or vegetated channel bed Sandy beds, some pools and riffles Greater than 100 ha mainly Steep channels Rock lined bed urbanised catchment Grades > 1 in 20 Mild slopes Grades between 1 in 20 and 1 in 100 Flat slopes Grades < 1 in 500 Sandy channels Pool/riffle system Open earth or vegetated channel bed Sandy, irregular bed with pools Less then 50 ha bushland catchment Open canopy Grassed bed Closed canopy Rocky and/or vegetated, bed Greater than 50 ha rural or Steep slopes > 1 in 150 Rock lined bushland catchments Mild slopes < 1 in 150 Pool/riffle system Flat slopes < 1 in 500 Sandy channels Open channel Sandy bed, some pools and riffles 30

8 Natural Channel Design Guidelines Step 5. Determine channel width (W) and channel depth (D) The channel width (W) is defined as the channel s top width measured at the elevation of its lowest bank (Figure 3.2). The channel depth (D) is defined as the elevation difference between bankfull water level and the channel invert. When short sections of a watercourse are to be reconstructed or rehabilitated, it is often desirable to maintain a channel depth similar to the existing channel depth to reduce earthworks and to allow the channel bed to have a constant fall to the existing downstream channel invert. For the reconstruction of gravel bed channels, the desired channel width and depth may be determined using one of two methods: the Hey and Thorne equations, or the Brisbane equations. For the reconstruction of sandy bed channels, the Simons and Albertson equation should be used. W D Figure 3.2 Channel and floodplain cross section TECHNICAL NOTE 3.2 The Hey and Thorne equations presented below for gravel bed waterways suggest that the channel width is significantly greater for an open canopy channel (e.g. grassed channel) than for a closed canopy channel with a dense stand of bank vegetation. This may be the case for streams with little or no bed vegetation, such as rivers and streams fed by snow melts, but for creeks in the Brisbane region, observations have shown that closed canopy creeks are often wider than open canopy creek systems. This is because open canopy creeks generally contain more groundcover vegetation (usually grasses and weeds) and the presence of this groundcover greatly reduces erosion. If bed vegetation is not significant within the given type of watercourse, then the Hey and Thorne equations should be used to estimate bank width and depth. If bed vegetation is a common feature of the type of watercourse you are designing, then the Brisbane-based equations are recommended. However, the final judgement on how channel width and depth are determined, is left to the designer s experience and judgement. It is always useful to compare the results of the two sets of equations with existing channels in the region. 31

9 Design Procedures (i) Hey and Thorne equations for gravel bed streams W = 4.33 x (Q f ) 0.5 W = 3.33 x (Q f ) 0.5 W = 2.73 x (Q f ) 0.5 W = 2.34 x (Q f ) 0.5 for vegetation type 1 grassed riparian zone, no trees and shrubs, Manning s n typically 0.03 to for vegetation type 2 scattered trees and shrubs, dense grass and weeds, Manning s n typically 0.04 to 0.06 for vegetation type 3 light to medium stand of trees and shrubs, Manning s n typically 0.07 to 0.09 for vegetation type 4 medium to dense stand of trees and shrubs, Manning s n typically 0.1 to 0.15 (ii) Brisbane s clay-based creek systems with significant sand and gravel bed deposits Q f 100 m 3 /s - typical bank width, W = 2.41 (Q f ) 0.5 and typical depth, D = 0.75 (Q f ) 0.5 Q f < 100 m 3 /s - typical bank width, W = 4.37 (Q f ) and typical depth, D = 1.07 (Q f ) The typical range of bank widths: 4.33 (Q f ) 0.5 > W > 1.78 (Q f ) 0.5 for all flow rates. The typical range of bank depths: W 0.6 > D > W 0.6 (iii) Simons and Albertson equations for sand bed waterways The equations may be applied to all sand bed streams in the Brisbane area. It should be noted that in some cases, this may be outside the range of data from which the equations were derived. (a) For sand bank (sandy loam) Bed width (m) = 5.72.Q f Mean depth (m) = Q f (b) For cohesive banks (some clay content or internal strength) Bed width (m) = 4.29.Q f Mean depth (m) = 0.59.Q f Surface width (m) = 1.1 x Bed width + 2. This should yield bank batters in the range 2H:1V for cohesive banks and 3H:1V for sandy banks. (c) For sand and cohesive banks Meander arc length (m) = 6.31.W 32

10 Natural Channel Design Guidelines Step 6. Channel bank slope The desirable channel bank slope on reconstructed channels may be determined from one of the following methods: (i) Obtained from Table 3.2. (ii) Obtained from geotechnical investigations. (iii) A bank slope similar to existing stable upstream and/or downstream bank slopes. In short reaches it is often necessary to blend in with the bank slope immediately upstream and downstream of the proposed channel works. However, in most cases trying to re-establish a steep bank slope similar to existing conditions will result in poor revegetation of the banks. Introducing a wide variation of bank slopes can be an effective tool in making a constructed or modified watercourse appear as natural as possible. It is usually highly desirable to avoid a regular trapezoidal channel shape down the reach of a watercourse. Steep banks of the outside of bends may be natural, but they are also highly unstable. Avoid placing steep, unprotected banks in areas where watercourse stability is desired. Berms (Figure 3.3) may need to be introduce to steep banks that are higher than 3 metres, or where erosion is expected along the toe of the bank. A typical berm width is one metre. It is noted that bank erosion is frequently caused by deepening of the channel (bed erosion). Therefore, there is often no point in treating the banks unless the bed is stabilised first. Where possible, when designing a modified watercourse, restrict the gradients on the 'over-bank' or 'high-bank' areas to 6(H):1(V) with a maximum grade of 5(H):1(V). Generally, for safety reasons, grassed bank grades of 4(H):1(V) and steeper are not recommended adjacent to a watercourse where: public access exists; the watercourse is considered a safety hazard during dry weather conditions or during regular flood events (up to the 5 year ARI); and satisfactory safety barriers such as fences, shrubs, bushland or flat landings do not exist between the embankment and floodway. 33

11 Design Procedures Berm or terrace Figure 3.3 Berm located on steep, high bank Table 3.2 Suggested bank slopes [1] (V):(H) Bank description 1:2 Good, erosion resistant clay or clay-loam soils with a healthy, deep-rooted bank vegetation formed by suitable riparian groundcover species, shrubs and trees 1:3 Sandy-loam soil with groundcover vegetation or a closed canopy channel with shaded banks and sparse bank vegetation 1:4 Sandy soils 1:6 Mowable, grassed banks (undesirable in Natural Channel Design) Note [1] The bank slopes presented in this table should be considered as a general guide only. Final bank slope should be based on bank stability and revegetation requirements. 34

12 Natural Channel Design Guidelines TECHNICAL NOTE 3.3 Establishing a berm on a watercourse bank can provide the following benefits: (i) If bank erosion occurs at the toe of the bank and this erosion results in soil slumping on the bank, then the berm can reduce the area of the bank over which this slumping occurs. (ii) Bank berms can be used to increase the stability of steep banks. (iii) Berms can be used to delay the effects of soil erosion around the root system of establishing trees. (iv) Wide berms can be used to provide pedestrian access to the watercourse banks for recreational and educational purposes. Step 7. Determine typical channel meander radius If a channel is to be reconstructed or relocated (ie when replacing an existing concrete drain with a natural channel) it is often desirable, if not necessary, to introduce some channel meanders. Meandering the channel can improve its aesthetics, increase habitat and channel diversity (through large-scale hydraulic turbulence) and can increase the effective channel length. Increasing the channel length is one of the most effective ways of reducing the bankfull flow velocity. The meander radius to the centre of the channel (Figure 3.4) is generally greater than three times the normal channel width. Select a desirable meander radius (to centre of channel) such that: R c 3W Alternatively, the meander radius to outer bank is given by: R o 3.5W. If a sharper meander radius needs to be constructed, then it may be necessary to rock-line the outer bank of the meander. W R c R o Waterway channel Channel meander Figure 3.4 Channel meander 35

13 Design Procedures Step 8. Select an initial channel location Often stream rehabilitation projects commence with a desired channel layout already known. However, as the design procedure progresses and hydraulic checks are done, it may become necessary to adjust the channel location until a stable channel geometry and flow condition is obtained. Some of the issues that should be considered when determining the desirable plan form of a watercourse are listed below: (i) historical or natural location of the channel; (ii) existence of steep, high channel banks or adjacent land forms; (iii) flood flow; (iv) bankfull velocity; (v) bend radius; (vi) location of essential or valued floodplain features (eg existing football fields, existing bushland or mature trees); (vii) current channel location. Discussion on each of these issues is provided in Chapter 2, Planning Aspects. The channel normally follows the invert of the valley floor so that the floodplain can drain freely into the channel. Ponding on the floodplain can cause maintenance problems (eg mowing) and mosquitoes; however, in some locations, ponding may be desirable to promote frog breeding. Expert advice should be sought. The channel location is important because it establishes the effective channel slope, and it is this slope that determines bankfull velocity. In many cases the ideal channel slope and dimensions cannot be achieved due to site constraints such as the proximity of existing structures, the desirable meander radius or the required minimum bed width. The location of the channel is often controlled by existing site constraints and urban structures such as bridges, culverts, stormwater outlets, rare or otherwise valued trees, including canopy trees, and other public assets. These items should be clearly identified on field or survey plans. A channel system should never be designed without performing a site visit and walking the length of the valley. In cases where the location of the channel is defined by site constraints, consideration should be given to the formation of minor channel meanders or variations in channel bank slope to provide some degree of irregularity to the channel. Two procedures are recommended for the establishment of a trial channel location: (a) (b) the allowable velocity method; and the allowable channel slope method. Each of these methods is detailed over. 36

14 Natural Channel Design Guidelines (a) Allowable velocity method (i) Estimate channel roughness for both short-term (post-construction, say n 0.04) and long-term conditions (fully vegetated). (ii) Determine the allowable bankfull velocity for both post-construction condition (low vegetation roughness Table 3.7) and long-term channel conditions (high vegetation roughness Table 3.3). (iii) Calculate the desired maximum channel slope (S) using the Manning s Equation or a hydraulic backwater model for the following conditions: (a) (b) initial channel roughness during Q2 or bankfull flow whichever is lower; and long-term channel roughness during Q100 or bankfull flow whichever is lower (in this case the 1 in 100 year flood event is used because it is the standard design event in Brisbane for major channels). Table 3.3 Recommended maximum velocity for various Manning s roughness to avoid significant vegetation damage [1] Average Manning s n roughness n = 0.03 n = 0.06 n = 0.09 n = 0.15 Recommended maximum velocity during bankfull flow and 1 in 50 year flood event [2] 2.0 m/s 1.7 m/s 1.5 m/s 1.0 m/s Notes: [1] As the vegetation density increases, and thus the channel roughness increases, it becomes harder for flood flows to pass around or through the vegetation without causing significant damage. A Manning s roughness of 0.03 represents a typical, deep water, grass channel where high flow velocities of around 2 m/s are expected to cause only minor damage. However, a Manning s roughness of 0.15 represents typical natural bushland for the Brisbane region. If a flow velocity of 2 m/s was allowed to flow through such bushland, significant damage to the vegetation would be expected. 37 [2] The 1 in 50 year flood event is chosen because it represents an extreme flood event during which some vegetation damage would be expected, but it is desirable to minimise this damage where possible. It is considered that a 1 in 20 year flood event would in most cases be too small to act as the design event for vegetation damage. The 1 in 100 year flood can be chosen, but it may be considered unrealistic to have minimal vegetation damage during such an extreme event.

15 Design Procedures (iv) Determine the channel length (L 2 ): where L 2 = (F t /S) Refer to Figure 3.5. (v) Measure the valley length (L 1 ) (vi) Determine the required channel sinuosity: S i = (L 2 /L 1 ) (vii) Determine the average meander displacement ( ) using Table 3.4 and Figure 3.6. (viii) (ix) Sketch the trial channel centreline on the valley plan. If the required channel length is excessive, then revise the channel location using Method (b) below. TECHNICAL NOTE 3.4 In the above design method it is assumed that bankfull velocity is controlled by the average channel slope (i.e. the pool/riffle system is totally drowned out). Such a flow condition can be assumed to exist if the channel depth (D) is at least twice the average riffle fall (F r ). In some cases it may be desirable to sketch an undistorted long section of the channel bed to visualise what possible impact that the pools and riffles may have on bankfull flow velocity. If the riffle height is significant, then the pools and riffles should be included in the hydraulic backwater model and the cross section spacing should be appropriately reduced. L 2 Figure 3.5 Channel reach length 38

16 Natural Channel Design Guidelines Table 3.4 Meander dimensions Meander Sinuosity /R c L m /R c Meander Sinuosity /R c L m /R c angle ( ) (L 2 /L 1 ) angle ( ) (L 2 /L 1 ) Lm R c Waterway channel W Figure 3.6 Channel meander (b) Allowable channel slope method (i) (ii) Select a trial channel location based on typical channel meander patterns upstream and downstream of the proposed works (assuming the u/s and d/s channel reaches are in the form of a natural channel design). Estimate the channel roughness for both short-term (post-construction) and long-term conditions. (iii) Given the measured channel fall (F t ) and channel length (L 2 ), determine the channel slope (S). It is noted that the channel length is measured along the centreline of the channel, not along the low flow channel. 39

17 Design Procedures (iv) Calculate the short-term (post-construction) bankfull or Q2 flow velocity (whichever is the lower discharge) and long-term bankfull or Q100 flow velocity (whichever is the lower discharge). Note: In the short term we are interested only in flood events less than the Q2 because it is desirable to minimise vegetation damage during the early growing phase. In the long term we need to consider the Q100 event because there may be factors other than vegetation damage that we need to consider, such as public safety. If there are no other stated velocity control issues other than vegetation damage, then the Q50 event should be checked rather than the Q100. (v) Compare the above channel velocities with the desirable flow velocities for the given channel conditions. If channel velocities are excessive, then modify the trial channel location or bed slope using one or more of the following options: (a) (b) (c) Increase the channel length. Increase the channel roughness - usually by increasing the post-construction channel roughness by planting more plants during the post-construction period or by planting more mature plants. Decrease the channel gradient by installing a rock chute or a series of rock chutes (vertical or near-vertical drop structures should be avoided in locations where fish migration is important). It is noted that installing a pool-riffle system will not decrease the effective channel gradient; however, it may slightly increase the channel roughness. (d) (e) Decrease the bankfull discharge, i.e decrease the channel width and depth. Maintain the selected bankfull discharge, but decrease the channel depth and consequently increase its width. When locating a trial channel location, consideration should be given to the following points: (i) (ii) The typical spacing of inflection points (i.e average spacing of meanders, L m ) is in the range 5W<L m <7W. When the valley length (L 1 ) and the desired channel length (L 2 ) are known, the average meander spacing (L m ) and amplitude can be determined from Table 3.4, where amplitude = 2. (iii) The valley topography and the encroachment of existing and/or future buildings, roads or other public or private assets can affect the location of the waterway channel. Where practicable, public assets such as roads and buildings should not be located within 15 m of the channel bank, or within the zone defined by a 1(V):3(H) gradient from the toe of the bank, unless the bank is formed from stable rock (Figure 3.7). 40

18 Natural Channel Design Guidelines Note that if a channel meander approaches a steep bank, then any future movement of the channel towards the bank may result in significant erosion, bank instabilities and sediment loss to the watercourse. 15m 1 3 Figure 3.7 Minimum placement of structures from channel bank (iv) Significant benefit can be achieved by starting rehabilitation in the upstream reaches of a watercourse thereby using the existing downstream fully vegetated or weed-infested creek to reduce bankfull velocities within the rehabilitated reach. Unfortunately, this usually does not apply to projects involving the reconstruction of concrete lined drainage channels where it may be more desirable to start at the downstream end of the watercourse. Step 9. Review riparian and floodplain vegetation When an acceptable trial channel alignment and cross section has been obtained, check that riparian vegetation can be introduced along the edges of the watercourse without causing unacceptable flood levels during the peak design flood event, usually the 1 in 100 year flood. Chapter 4 provides information on the design of riparian and floodplain vegetation. If the proposed channel meanders across the floodplain, then the establishment of riparian vegetation along the banks of the channel may significantly affect the hydraulic capacity of the floodplain. If this is the case, then the options are: (i) Decrease the density of riparian vegetation in selected areas to allow overbank flood flows to pass down the valley with few restrictions (refer to Chapter 4). (ii) Relocate the channel along one side of the valley (where channel velocities allow) to reduce the potential interference on overbank flood flows. 41

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

Catchment Scale Processes and River Restoration. Dr Jenny Mant Jenny@therrc.co.uk. The River Restoration Centre therrc.co.uk

Catchment Scale Processes and River Restoration. Dr Jenny Mant Jenny@therrc.co.uk. The River Restoration Centre therrc.co.uk Catchment Scale Processes and River Restoration Dr Jenny Mant Jenny@therrc.co.uk The River Restoration Centre therrc.co.uk 3 Main Catchment Elements Hydrology Energy associated with the flow of water affects

More information

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES WATER RESOURCES MANAGEMENT DIVISION Water Investigations

More information

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration Stream Rehabilitation Concepts, Guidelines and Examples Pierre Y. Julien Wuhan 2005 Objectives Part I - Stream restoration and rehabilitation: 1. Present and discuss important concepts, laws, criteria

More information

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies. RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality

More information

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes Chapter 2 Flash Flood Science A flash flood is generally defined as a rapid onset flood of short duration with a relatively high peak discharge (World Meteorological Organization). The American Meteorological

More information

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness 3 Chapter 3 of Concentration and Travel Time Time of Concentration and Travel Time Travel time ( T t ) is the time it takes water to travel from one location to another in a watershed. T t is a component

More information

Prattsville Berm Removal Project. 1.0 Project Location

Prattsville Berm Removal Project. 1.0 Project Location Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed

More information

Crossing creeks Stream crossings on farms

Crossing creeks Stream crossings on farms Crossing creeks Stream crossings on farms Looking after all our water needs Crossing creeks Stream crossings on farms Looking after all our water needs Department of Water 168 St Georges Terrace Perth

More information

Floodplain Connectivity in Restoration Design

Floodplain Connectivity in Restoration Design Floodplain Connectivity in Restoration Design 2015 Symposium on Restoration in a Contaminated Environment: Lessons Learned and Challenges in Moving Forward Part II April 2015 Karin Boyd Applied Geomorphology,

More information

Stream Restoration Making It Happen: The Restoring The Waters Project

Stream Restoration Making It Happen: The Restoring The Waters Project Stream Restoration Making It Happen: The Restoring The Waters Project STEPHEN FROST, Fairfield City Council ROD WIESE, Department of Land & Water Conservation BARBARA SCHAFFER, Schaffer Barnsley Landscape

More information

1.7.0 Floodplain Modification Criteria

1.7.0 Floodplain Modification Criteria 1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:

More information

1. Carry water under the canal 2. Carry water over the canal 3. Carry water into the canal

1. Carry water under the canal 2. Carry water over the canal 3. Carry water into the canal Lecture 21 Culvert Design & Analysis Much of the following is based on the USBR publication: Design of Small Canal Structures (1978) I. Cross-Drainage Structures Cross-drainage is required when a canal

More information

CHAPTER 5 OPEN CHANNEL HYDROLOGY

CHAPTER 5 OPEN CHANNEL HYDROLOGY 5.4 Uniform Flow Calculations 5.4.1 Design Charts CHAPTER 5 OPEN CHANNEL HYDROLOGY Following is a discussion of the equations that can be used for the design and analysis of open channel flow. The Federal

More information

Waterway Technote Drains

Waterway Technote Drains Waterway Technote Drains Contents Benefits of good drain practice 1 Are your drains healthy? 2 The Sustainable Dairying Water Accord 3 Planning drain maintenance 3 Fencing and clearing 3 Bank shaping (battering)

More information

Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS

Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS Chapter 3 3.01 General Provisions 3.01.1 Introduction 3.01.2 Application and Interpretation of Chapter 3.01.3 Unbuildable Lots 3.01.4 Other Permits 3.01.5 Prohibited Activities 3.02 Service Provider Letter

More information

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES Run-off Analysis Methods This document sets forth the minimum design, technical criteria and specifications for the

More information

Riprap-lined Swale (RS)

Riprap-lined Swale (RS) Riprap-lined Swale (RS) Practice Description A riprap-lined swale is a natural or constructed channel with an erosion-resistant rock lining designed to carry concentrated runoff to a stable outlet. This

More information

Open Channel Flow 2F-2. A. Introduction. B. Definitions. Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow

Open Channel Flow 2F-2. A. Introduction. B. Definitions. Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow 2F-2 Open Channel Flow A. Introduction The beginning of any channel design or modification is to understand the hydraulics of the stream. The

More information

Rural Flooding: The Potential Role of Forestry

Rural Flooding: The Potential Role of Forestry Rural Flooding: The Potential Role of Forestry Nadeem Shah, Tom Nisbet, & Huw Thomas Centre for Forestry and Climate Change Structure Background Woodland and Flood Alleviation The Theory. Studies on Woodland

More information

Lecture 24 Flumes & Channel Transitions. I. General Characteristics of Flumes. Flumes are often used:

Lecture 24 Flumes & Channel Transitions. I. General Characteristics of Flumes. Flumes are often used: Lecture 24 Flumes & Channel Transitions I. General Characteristics of Flumes Flumes are often used: 1. Along contours of steep slopes where minimal excavation is desired 2. On flat terrain where it is

More information

Topic 8: Open Channel Flow

Topic 8: Open Channel Flow 3.1 Course Number: CE 365K Course Title: Hydraulic Engineering Design Course Instructor: R.J. Charbeneau Subject: Open Channel Hydraulics Topics Covered: 8. Open Channel Flow and Manning Equation 9. Energy,

More information

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the

More information

The Teton Creek Restoration Project Summary:

The Teton Creek Restoration Project Summary: The Teton Creek Restoration Project Summary: The Teton Creek Restoration Project area extends for approximately one mile upstream from the Cemetery Road Bridge and includes the Aspen Pointe, The Aspens

More information

General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title]

General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title] General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title] Purpose These rules set forth the conditions under which a person may, without an individual removal-fill permit

More information

SUSTAINABLE URBAN DRAINAGE SYSTEMS

SUSTAINABLE URBAN DRAINAGE SYSTEMS overflow can lead into a permeable conveyance system to increase further the benefit and reduce the need for pipe systems. Pollutant removal rates have been shown to be high, with some pollutants being

More information

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014 Guideline: Works that interfere with water in a watercourse watercourse diversions September 2014 This publication has been compiled by the Department of Natural Resources and Mines. State of Queensland,

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

Basic Hydrology. Time of Concentration Methodology

Basic Hydrology. Time of Concentration Methodology Basic Hydrology Time of Concentration Methodology By: Paul Schiariti, P.E., CPESC Mercer County Soil Conservation District What is the Time of Concentration? The time it takes for runoff to travel from

More information

Prepared By: Tom Parker Geum Environmental Consulting, Inc.

Prepared By: Tom Parker Geum Environmental Consulting, Inc. Prepared By: Tom Parker Geum Environmental Consulting, Inc. Topics covered: Definition of riparian and floodplain restoration Floodplain attributes as a basis for developing criteria for restoration designs

More information

Earth Science. River Systems and Landforms GEOGRAPHY 1710. The Hydrologic Cycle. Introduction. Running Water. Chapter 14.

Earth Science. River Systems and Landforms GEOGRAPHY 1710. The Hydrologic Cycle. Introduction. Running Water. Chapter 14. Earth Science GEOGRAPHY 1710 River Systems and Landforms DAVID R. SALLEE Robert W. Christopherson Charlie Thomsen Chapter 14 Introduction Rivers and streams are dynamic systems that continually adjust

More information

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT 2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT Open channel flow is defined as flow in any channel where the liquid flows with a free surface. Open channel flow is not under pressure; gravity is the

More information

GLOSSARY OF TERMS CHAPTER 11 WORD DEFINITION SOURCE. Leopold

GLOSSARY OF TERMS CHAPTER 11 WORD DEFINITION SOURCE. Leopold CHAPTER 11 GLOSSARY OF TERMS Active Channel The channel that contains the discharge Leopold where channel maintenance is most effective, sediment are actively transported and deposited, and that are capable

More information

A guide to preventing structural damage

A guide to preventing structural damage A guide to preventing structural damage Home owners guide to planning landscaping and maintenance of foundations Structural damage can result from movement in clay soils caused by varying moisture conditions

More information

CHAPTER 9 CHANNELS APPENDIX A. Hydraulic Design Equations for Open Channel Flow

CHAPTER 9 CHANNELS APPENDIX A. Hydraulic Design Equations for Open Channel Flow CHAPTER 9 CHANNELS APPENDIX A Hydraulic Design Equations for Open Channel Flow SEPTEMBER 2009 CHAPTER 9 APPENDIX A Hydraulic Design Equations for Open Channel Flow Introduction The Equations presented

More information

Small Dam Hazard Assessment Inventory

Small Dam Hazard Assessment Inventory Small Dam Hazard Assessment Inventory What would happen if your dam were to fail? This is a question that most dam owners hope they will never have to answer. However it is a question you, as a responsible

More information

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section:

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section: . Introduction Presented in this chapter are the criteria and methodology for design and evaluation of storm sewer inlets located in Town of Castle Rock. The review of all planning submittals will be based

More information

Neversink River East Branch

Neversink River East Branch Neversink River East Branch Management Unit 10 Summary of Post-Flood Recommendations Intervention Level Full restoration of the stream reach including the eroding bank site between Station 38380 and Station

More information

URBAN DRAINAGE CRITERIA

URBAN DRAINAGE CRITERIA URBAN DRAINAGE CRITERIA I. Introduction This division contains guidelines for drainage system design and establishes a policy for recognized and established engineering design of storm drain facilities

More information

STORMWATER MANAGEMENT CHECKLIST

STORMWATER MANAGEMENT CHECKLIST STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative

More information

Environmental Case Study Decatur, Georgia, DeKalb County A Suburban Creek Resists Channelization

Environmental Case Study Decatur, Georgia, DeKalb County A Suburban Creek Resists Channelization Introduction A visual examination of Doolittle Creek in a highly developed suburban county in Georgia yielded telltale signs of a creek whose original streambed had been altered. Examination of official

More information

Assessing Rivers for Restoration Purposes. Ann L. Riley Waterways Restoration Institute

Assessing Rivers for Restoration Purposes. Ann L. Riley Waterways Restoration Institute Assessing Rivers for Restoration Purposes Ann L. Riley Waterways Restoration Institute Assessing Rivers for Restoration Purposes Ann L. Riley Waterways Restoration Institute Assessing Rivers for Restoration

More information

How To Plan A Buffer Zone

How To Plan A Buffer Zone Backyard Buffers Protecting Habitat and Water Quality What is a buffer? A buffer (also called a riparian buffer area or zone) is the strip of natural vegetation along the bank of a stream, lake or other

More information

Evaluation of Open Channel Flow Equations. Introduction :

Evaluation of Open Channel Flow Equations. Introduction : Evaluation of Open Channel Flow Equations Introduction : Most common hydraulic equations for open channels relate the section averaged mean velocity (V) to hydraulic radius (R) and hydraulic gradient (S).

More information

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures.

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures. BMP: SUBSURFACE DRAIN Definition A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. PurRoses 1. To prevent sloping soils from becoming

More information

City of Austin Stream Restoration Program Mid-Atlantic Stream Restoration Conference, Rocky Gap, MD November 2011

City of Austin Stream Restoration Program Mid-Atlantic Stream Restoration Conference, Rocky Gap, MD November 2011 Welcome City of Austin Stream Restoration Program Mid-Atlantic Stream Restoration Conference, Rocky Gap, MD November 2011 Morgan Byars, P.E. City of Austin Watershed Protection Department Environmental

More information

Open Channel Flow in Aquaculture

Open Channel Flow in Aquaculture SRAC Publication No. 74 Southern Regional Aquaculture Center March 1995 PR VI Open Channel Flow in Aquaculture J. David Bankston, Jr. 1 and Fred Eugene Baker Open channel flow of water has been used in

More information

Engineering Specifications February, 2004 Schedule H to Bylaw 7452, Subdivision Bylaw Page 18

Engineering Specifications February, 2004 Schedule H to Bylaw 7452, Subdivision Bylaw Page 18 Schedule H to Bylaw 7452, Subdivision Bylaw Page 18 3.4 Sanitary Sewers 3.4.1 Materials 3.4.1.1 The class and type of pipe and fittings, together with required class of bedding and trench widths, shall

More information

Sediment Supply and the Upland-Stream Connection. Brian Bledsoe Department of Civil and Environmental Engineering Colorado State University

Sediment Supply and the Upland-Stream Connection. Brian Bledsoe Department of Civil and Environmental Engineering Colorado State University Sediment Supply and the Upland-Stream Connection Brian Bledsoe Department of Civil and Environmental Engineering Colorado State University Overview The sediment system (with an eye towards hillslope processes

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

GUIDELINES FOR SOIL FILTER MEDIA IN BIORETENTION SYSTEMS (Version 2.01) March 2008

GUIDELINES FOR SOIL FILTER MEDIA IN BIORETENTION SYSTEMS (Version 2.01) March 2008 GUIDELINES FOR SOIL FILTER MEDIA IN BIORETENTION SYSTEMS (Version 2.01) March 2008 The following guidelines for soil filter media in bioretention systems have been prepared on behalf of the Facility for

More information

CHAPTER 3 STORM DRAINAGE SYSTEMS

CHAPTER 3 STORM DRAINAGE SYSTEMS CHAPTER 3 STORM DRAINAGE SYSTEMS 3.7 Storm Drains 3.7.1 Introduction After the tentative locations of inlets, drain pipes, and outfalls with tail-waters have been determined and the inlets sized, the next

More information

Mission Creek Flood Control & Restoration Project. City of Fremont, Alameda County

Mission Creek Flood Control & Restoration Project. City of Fremont, Alameda County Mission Creek Flood Control & Restoration Project City of Fremont, Alameda County Agenda Background Why are proposed improvements necessary? Proposed project components Challenges Construction schedule/phasing

More information

Rivers Group. Effect of Canterbury Earthquakes on Waimakariri, Kaiapoi, & Halswell Rivers. Flooding & Drainage Perspectives

Rivers Group. Effect of Canterbury Earthquakes on Waimakariri, Kaiapoi, & Halswell Rivers. Flooding & Drainage Perspectives Rivers Group Effect of Canterbury Earthquakes on Waimakariri, Kaiapoi, & Halswell Rivers Flooding & Drainage Perspectives Waimakariri River Catchment Waimakariri River Hydrology Catchment area - 3,990

More information

STORM DRAINS CHAPTER 7

STORM DRAINS CHAPTER 7 CHAPTER 7 Chapter 7 - Storm Drains A storm drain is a drainage system that conveys water or stormwater, consisting of two or more pipes in a series connected by one or more structures. Storm drains collect

More information

Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. CIVL 1112 Detention Ponds - Part 1 1/12

Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. CIVL 1112 Detention Ponds - Part 1 1/12 CIVL 1112 - Part 1 1/12 The water cycle, also known as the hydrologic cycle, describes the continuous movement of water on, above and below the surface of the Earth. The water cycle, also known as the

More information

Appendix 4-C. Open Channel Theory

Appendix 4-C. Open Channel Theory 4-C-1 Appendix 4-C Open Channel Theory 4-C-2 Appendix 4.C - Table of Contents 4.C.1 Open Channel Flow Theory 4-C-3 4.C.2 Concepts 4-C-3 4.C.2.1 Specific Energy 4-C-3 4.C.2.2 Velocity Distribution Coefficient

More information

Architectural Processing and Inspections for Home Mortgage Insurance

Architectural Processing and Inspections for Home Mortgage Insurance Page 1 of 5 [Text Only] Architectural Processing and Inspections for Home Mortgage Insurance Directive Number: 4145.1 SITE GRADING AND DRAINAGE GUIDELINES Construction complaints and structural defect

More information

THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS

THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS Chapter 11 Slope Stabiliza bilization and Stability of Cuts and Fills THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS are 1) to create space for the road template and driving surface; 2) to balance material

More information

PART 6 HA 113/05 DRAINAGE

PART 6 HA 113/05 DRAINAGE DESIGN MANUAL FOR ROADS AND BRIDGES VOLUME 4 SECTION 2 GEOTECHNICS AND DRAINAGE DRAINAGE PART 6 HA 113/5 COMBINED CHANNEL AND PIPE SYSTEM FOR SURFACE WATER DRAINAGE SUMMARY This Advice Note gives guidance

More information

Lecture 22 Example Culvert Design Much of the following is based on the USBR technical publication Design of Small Canal Structures (1978)

Lecture 22 Example Culvert Design Much of the following is based on the USBR technical publication Design of Small Canal Structures (1978) Lecture 22 Example Culvert Design Much of the following is based on the USBR technical publication Design of Small Canal Structures (1978) I. An Example Culvert Design Design a concrete culvert using the

More information

Chapter 9. Steady Flow in Open channels

Chapter 9. Steady Flow in Open channels Chapter 9 Steady Flow in Open channels Objectives Be able to define uniform open channel flow Solve uniform open channel flow using the Manning Equation 9.1 Uniform Flow in Open Channel Open-channel flows

More information

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013.

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013. Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013 Rationale Underground infrastructure may be at risk from valley, streambank

More information

City of West Linn Public Works Design Standards 2010. Table of Contents

City of West Linn Public Works Design Standards 2010. Table of Contents City of West Linn Public Works Design Standards Table of Contents SECTION TWO STORM DRAIN REQUIREMENTS... 1 2.0000 STORM DRAINS... 1 2.0010 General Design Requirements...1 2.0011 Site Drainage Plans...2

More information

Design Charts for Open-Channel Flow HDS 3 August 1961

Design Charts for Open-Channel Flow HDS 3 August 1961 Design Charts for Open-Channel Flow HDS 3 August 1961 Welcome to HDS 3-Design Charts for Open-Channel Flow Table of Contents Preface DISCLAIMER: During the editing of this manual for conversion to an electronic

More information

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES 5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES Flood damage reduction consists of two basic techniques structural and non-structural. Structural methods modify the flood and take the flood away from people

More information

SUSTAINABLE DESIGN FOR THE SOLDIER CREEK LEVEE REPAIR. John Ruhl 1 Seth Laliberty 2 ABSTRACT

SUSTAINABLE DESIGN FOR THE SOLDIER CREEK LEVEE REPAIR. John Ruhl 1 Seth Laliberty 2 ABSTRACT SUSTAINABLE DESIGN FOR THE SOLDIER CREEK LEVEE REPAIR John Ruhl 1 Seth Laliberty 2 ABSTRACT The Soldier Creek Diversion Unit Repair Project represents the latest USACE Kansas City District investment in

More information

Appendix C. Project Opportunities. Middle Twisp River (RM 7.8 18.12)

Appendix C. Project Opportunities. Middle Twisp River (RM 7.8 18.12) Appendix C Project Opportunities Middle Twisp River (RM 7.8 18.12) This table describes project opportunities by project area. Locator maps of the project opportunities are included below the table. Reach

More information

Floodplain Development Land Use Review

Floodplain Development Land Use Review COMMUNITY DEVELOPMENT DEPARTMENT Planning Division P.O. Box 490 333 Broadalbin Street SW Albany, OR 97321 Phone 541-917-7550 Fax 541-791-0150 www.cityofalbany.net Floodplain Development Land Use Review

More information

Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans

Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans APPENDIX IV Version: February 2, 2015 Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans Please fill in all blanks and please reference the plan sheets/pages where the information may

More information

NJ650.1404 Interception Drainage

NJ650.1404 Interception Drainage NJ650.1404 Interception Drainage Interception drainage is used to intercept surface and subsurface water. The investigation, planning, and construction of surface interception drains follow the requirements

More information

Siting and settlement: The most important way to protect shelter from floods is to build in a place that is unlikely to be flooded.

Siting and settlement: The most important way to protect shelter from floods is to build in a place that is unlikely to be flooded. Siting and settlement: The most important way to protect shelter from floods is to build in a place that is unlikely to be flooded. Key Messages Shelters and settlements should be sited above the highest

More information

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION Design Criteria Drainage Area The drainage area for storm drain inlets shall not exceed one acre. The crest elevations of these practices shall

More information

MIKE 21 FLOW MODEL HINTS AND RECOMMENDATIONS IN APPLICATIONS WITH SIGNIFICANT FLOODING AND DRYING

MIKE 21 FLOW MODEL HINTS AND RECOMMENDATIONS IN APPLICATIONS WITH SIGNIFICANT FLOODING AND DRYING 1 MIKE 21 FLOW MODEL HINTS AND RECOMMENDATIONS IN APPLICATIONS WITH SIGNIFICANT FLOODING AND DRYING This note is intended as a general guideline to setting up a standard MIKE 21 model for applications

More information

ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT

ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT 1. BACKGROUND There has been an increasing awareness of design features, which produce poor whole-of-life costs. These poor whole-of-life costs manifest

More information

DANIELS RUN STREAM RESTORATION, FAIRFAX, VIRGINIA: FLOODPLAIN ANALYSIS REPORT

DANIELS RUN STREAM RESTORATION, FAIRFAX, VIRGINIA: FLOODPLAIN ANALYSIS REPORT DANIELS RUN STREAM RESTORATION, FAIRFAX, VIRGINIA: FLOODPLAIN ANALYSIS REPORT By: Conor C. Shea Stream Habitat Assessment and Restoration Program U.S. Fish and Wildlife Service CBFO-S07-01 Prepared in

More information

Homeowner s Guide to Drainage

Homeowner s Guide to Drainage Homeowner s Guide to Drainage a scottsdale homeowner s guide to drainage produced by the city of scottsdale s stormwater management division Transportation Department TABLE OF CONTENTS Introduction 2 Drainage

More information

Basic Principles of Channel Design

Basic Principles of Channel Design United States Department of Agriculture Natural Resources Conservation Service Stream Restoration Design Chapter 7 Basic Principles of Channel Design Issued August 2007 Cover photo: Where modification

More information

SECTION 5 - STORM DRAINS

SECTION 5 - STORM DRAINS Drainage Criteria Manual SECTION 5 - STORM DRAINS 5.1.0 GENERAL This The purpose of this section discusses briefly is to consider the hydraulic aspects of storm drains and their appurtenances in a storm

More information

Guo, James C.Y. (2004). Design of Urban Channel Drop Structure, J. of Flood Hazards News, December,

Guo, James C.Y. (2004). Design of Urban Channel Drop Structure, J. of Flood Hazards News, December, Guo, James C.. (004). esign of Urban Channel rop Structure, J. of Flood azards News, ecember, Guo, James C.., (009) Grade Control for Urban Channel esign, submitted to Elsevier Science, J. of ydro-environmental

More information

SECTION 5.4 LOGJAM REMOVAL AND RIVER RESTORATION. Overview. Logjam Removal Using Heavy. Tools. Machinery. Large-Scale River Restoration

SECTION 5.4 LOGJAM REMOVAL AND RIVER RESTORATION. Overview. Logjam Removal Using Heavy. Tools. Machinery. Large-Scale River Restoration SECTION 5.4 LOGJAM REMOVAL AND RIVER RESTORATION Overview Practice 401 Practice 402 Practice 403 Logjam Removal Using Hand-held Tools Logjam Removal Using Heavy Machinery Large-Scale River Restoration

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

BRIDGE SCOUR INVESTIGATION: DEVELOPING A SCREENING AND HYDRAULIC VULNERABILITY RATING SYSTEM FOR BRIDGES B.HERON 1 & C.BOWE 2

BRIDGE SCOUR INVESTIGATION: DEVELOPING A SCREENING AND HYDRAULIC VULNERABILITY RATING SYSTEM FOR BRIDGES B.HERON 1 & C.BOWE 2 BRIDGE SCOUR INVESTIGATION: DEVELOPING A SCREENING AND HYDRAULIC VULNERABILITY RATING SYSTEM FOR BRIDGES B.HERON 1 & C.BOWE 2 1 O Connor Sutton Cronin Consulting Engineers, Dublin, Ireland 2 Iarnród Éireann,

More information

Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road,

Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road, Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road, Wolverhampton, WV6 0PJ Tel 01902 712200 Fax 01902 714096 e-mail sales@hy-tengabions.com

More information

Engineering in the water environment: good practice guide. River crossings

Engineering in the water environment: good practice guide. River crossings Engineering in the water environment: good practice guide River crossings Second edition, November 2010 Contents 1 Introduction 3 2 Impacts of crossings 5 2.1 Construction phase impacts 5 2.2 Barrier to

More information

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE 1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,

More information

How To Check For Scour At A Bridge

How To Check For Scour At A Bridge Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway

More information

What is the most obvious difference between pipe flow and open channel flow????????????? (in terms of flow conditions and energy situation)

What is the most obvious difference between pipe flow and open channel flow????????????? (in terms of flow conditions and energy situation) OPEN CHANNEL FLOW 1 3 Question What is the most obvious difference between pipe flow and open channel flow????????????? (in terms of flow conditions and energy situation) Typical open channel shapes Figure

More information

CHAPTER 860 OPEN CHANNELS

CHAPTER 860 OPEN CHANNELS HIGHWAY DESIGN MANUAL 860-1 CHAPTER 860 OPEN CHANNELS Topic 861 - General Index 861.1 - Introduction An open channel is a conveyance in which water flows with a free surface. Although closed conduits such

More information

Asset Management Guide For Project Design Format

Asset Management Guide For Project Design Format NZ Transport Agency Page 1 of 6 Asset Management Guide For Project Design Format 1 Background There has been an increasing awareness of design features, which produce poor wholeof-life costs. These poor

More information

Appendix H Dredging and Stream Channel Restoration

Appendix H Dredging and Stream Channel Restoration Appendix H Dredging and Stream Channel Restoration Mankind s intrusion into the natural environment in West Virginia began in earnest following the Civil War when extractive industries and settlement all

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices

Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices Purpose The purpose of this document is to provide guidance and recommendations for minimizing potential impacts to

More information

Flood Hazard Area Technical Manual Section 8 Bank Stabilization and Stream Restoration

Flood Hazard Area Technical Manual Section 8 Bank Stabilization and Stream Restoration Flood Hazard Area Technical Manual Section 8 Bank Stabilization and Stream Restoration Prepared by: New Jersey Section American Water Resources Association Stream Restoration Committee FHA Subcommittee

More information

CHAPTER 2 HYDRAULICS OF SEWERS

CHAPTER 2 HYDRAULICS OF SEWERS CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination

More information

Various options are discussed below.these low cost, low impact interventions can also be applied as general erosion control methods.

Various options are discussed below.these low cost, low impact interventions can also be applied as general erosion control methods. Week 10 River Hydraulics Rehabilitating Urban Waterways (From http://hubpages.com/hub/river-bank-erosion-control-methods) See also the resources placed on Moodle. Water channels should be viewed as a resource

More information