1 GITA 2011 Work Management and Mobile GIS Technology A Winning Combination Dave DiSera Vice President IT Practice Director & CTO Brian Schrantz Principal Consultant
2 Today s Presentation In Ten Parts 1. Introduction to New York Power Authority (NYPA) 2. Overview of WMS and Mobile Technology 3. Project Background 4. Project Expectations 5. Process 6. Project Results 7. Project Benefits 8. Current Status and Next Steps 9. Lessons Learned/Summary
3 Part 1 Introduction to New York Power Authority
4 Introduction to New York Power Authority (NYPA) The New York Power Authority is America's largest state-owned power organization. NYPA was established in 1931 to develop the hydroelectric resources of the St. Lawrence River. NYPA provides some of the lowest cost electricity in New York State. NYPA operates 18 generating facilities and more than 1,400 circuit-miles of transmission lines. NYPA s power supports more than 400,000 jobs statewide.
5 Part 2 Overview of WMS and Mobile GIS Technology
6 Key Work Management System (WMS) Capabilities Work Management Plan Schedule Cost Performance Asset Management Analysis and Procurement Reporting Vendors Purchase Requests Purchase Orders Contracts Specifications Condition Age History Inventory Control Parts/Tool Availability Warehouse Rolling Stock
7 WMS Manages Information Related to Work Activities and Physical Assets
8 GIS Capabilities Display data on a map easy visualization
9 GIS Capabilities Easily find assets by location OBJECTID GlobalID * TOWER TOWER_NU EQUIPMEN STATION HEIGHT POINT_OF_INTERS SPAN_LENGTH PROJECT DESCRIPTION HYPERLINK COMMENTS SOURCE LONGITUDE 2186 {FE2AC2DE- FS-01/04 01/ NO CETL, MISSING IN MAXIMO plans\11825fy10ar Digitized 76 24' 1.75" W 2187 {CF32C9C1- FS-01/07 01/ YES 200 CETL, MISSING IN MAXIMO plans\11825fy10br Digitized 76 24' 23.04" W 2188 {8CC FS-01/06 01/ NO CETL, MISSING IN MAXIMO plans\11825fy10br Digitized 76 24' 11.42" W 2189 {D58D UE / NO 300 CETL,MMTL UE1-7 STRUCTURE 0 plans\6488ue7t100 Digitized 75 13' 23.19" W 2190 {2A2933DC- UE1-01/02 01/ YES CETL,MMTL UE1-7 STRUCTURE plans\6488ue7t100 Digitized 75 13' 18.64" W 2191 {B6BF4A05- UE1-01/01 01/ NO CETL,MMTL UE1-7 STRUCTURE plans\6488ue7t100 Digitized 75 13' 21.71" W 2192 {B7044DD4-0 UE1-01/04 01/ YES NA CETL,MMTL UE1-7 STRUCTURE plans\6488ue7t100 Digitized 75 13' 17.75" W 2193 {297C3E8F-8 UE1-01/09 01/ NO CETL,MMTL UE1-7 STRUCTURE plans\174ue17t402 Digitized 75 13' 17.52" W 2194 {731887DF-E UE1-02/01 02/ YES CETL,MMTL UE1-7 STRUCTURE plans\174ue17t402 Digitized 75 13' 17.68" W 2195 {44E66614-F UE1-02/02 02/ NO 670 CETL,MMTL UE1-7 STRUCTURE plans\174ue17t402 Digitized 75 13' 21.38" W 2196 {68C61E96- UE1-02/03 02/ NO CETL,MMTL UE1-7 STRUCTURE plans\174ue17t402 Digitized 75 13' 25.35" W 2197 {B611E17C-E UE1-02/04 02/ YES CETL,MMTL UE1-7 STRUCTURE plans\174ue17t402 Digitized 75 13' 28.54" W 2198 {51DBF263-8 UE1-02/05 02/ YES CETL,MMTL UE1-7 STRUCTURE plans\174ue17t402 Digitized 75 13' 32.48" W 2199 {42AB633F-8 UE1-02/END 02/END NA NO NA CETL,MMTL MISSING IN MAXIMO plans\174ue17t402 Digitized 75 13' 34.64" W 2200 {0D38AA93- UE1-01/08 01/ NO 670 CETL,MMTL UE1-7 STRUCTURE plans\174ue17t402 Digitized 75 13' 17.57" W 2201 {3AD1B15A- MA2-60/08W 60/ YES MATL,SLTL MA2 STRUCTURE 60/0 plans\7t65.pdf GPS 75 16' 35.63" W 2202 {E96DA6FD- MA2-60/09W 60/ NO MATL,SLTL MA2 STRUCTURE 60/0 plans\7t65.pdf CALCULATED 75 16' 41.19" W
10 GIS Capabilities Edit and maintain spatial data Spatial Database GIS Editor
11 GIS and WMS Are Closely Related Technologies Both manage a database of facilities and assets Both use the same asset data Both support planning, operations, and maintenance activities
12 Getting The Most From The Technology Requires Integration Of Both Systems Work Mgmt PM GIS WMS Condition Monitoring Inventory Control
13 Part 3 Project Background
14 Transmission Maintenance The Transmission Business Unit s mission is to operate and maintain NYPA s high voltage transmission facilities. An integral part of the maintenance program is the performance of transmission structure and right of way inspections. The current process utilizes hardcopy reports and notes prepared by inspectors in the field, which are then reviewed by the planners.
15 Transmission Maintenance Reliance on hardcopy documents and forms presents the Line Crews with the arduous task of managing and maintaining hundreds of paper documents related to inspection results for a given line patrol. The inspection crews operate without the ability to access current WMS and GIS data while in the field.
16 Transmission Maintenance Identified Several Critical Issues 75% of Transmission Maintenance Work Orders are created from Inspections. Transmission Maintenance did not have an easy way to record line inspections. Several attempts at automating this process failed in the recent past due to: Lack of integration to WMS Software had been too extensive and cumbersome to support basic requirements.
17 Existing Inspection Process Was Cumbersome Transmission Asset Inspection Data Collection Current State Field Line Crew Conduct Inspection Capture Field Inspection data Review WMS work order Backlog Make note of potential GIS Update Complete Tower Inspection Sheet TBU MRM Planner Review Tower Inspection Sheet Office Work-Order Required? Yes Create New WMS Work-Order No Review / Comment on the Sheet File the Sheet for Archive GIS Admin Review potential GIS Update Office GIS Update Required? Yes Update GIS information File the note for Archive Enabler Hard Copy / Paper WMS & GIS Hard-Copy/Paper
18 Pre-project Deficiencies Trend analysis Work efficiencies Communication Duplicate work orders Knowledge Management
19 Part 4 Project Expectations
20 Business Opportunity: Reduce time associated with paper copy manipulation. Provide the Transmission Planners the tool required to assist in the planning effort. Free line crews from managing hardcopy forms for work order backlog. Provide line crews the ability to communicate potential GIS updates by providing the means to redline GIS maps in the field. Enable reporting of asset performance and maintenance. Provide an online historical record of the inspections performed and their status.
21 Project Objectives: Reduce the time it takes to create work orders and perform repairs based on deficiencies reported from the line inspection process. Provide a fast solution to process a simple transaction. Transition from manual (paper) to digital processing; providing the ability to retain and archive comments submitted by inspection and maintanance crews. Store data captured on transmission line inspection forms. Improve GIS data accuracy by using data collected in field mark-ups for map updates. Consistent synchronization of data between the existing enterprise system (GIS and WMS) and mobile solution. Develop a solution that is EASY to use for the crews.
22 NYPA Expected the Project to Deliver: An automated field inspection collection system. A consistent, effective method for both collecting and viewing WMS and GIS data in a timely manner. The ability to use GIS in the field during structure inspections. An automated line patrol history for potential audits, thus mitigating the potential for NERC fines in the event of a system failure.
23 Part 5 Project Process
24 Proposed Process and Solution Transmission Asset Inspection Data Collection Proposed Solution Office Field Office Line Crew Synch Laptop with WMS & GIS Conduct Inspection Review WMS Backlog Mark-up GIS map Complete Field Inspection Form Synch Laptop with WMS & GIS TBU Planner Office Review WMS Condition Table Work-Order Required? Yes Create New Work-Order No End GIS Admin Office Review Mark-up GIS Update Required? Yes Update GIS information End Enabler Mobile Asset NOtebook Modules Maximo & Esri
25 Integration Must Accommodate Sharing of Enterprise Asset Data Enterprise Asset ID Asset Must Be Commonly Known Across All Enterprise Systems WMS GIS CI=
26 Architecture Redlines Redline Manager Data Edits SDE WO Updates Copy.bat, Copy_centroid.bat Maximo Inspections to CM InspLoader.bat Redlines GDB Updates Staging Server ArcMap (Editors) Inspection Forms MXD Changes Code Updates, MXD Changes, New Data after testing Code Updates, MXD Changes, New Data for Testing Synchronization Engine Mobile_sync.bat Updated Code, MXD, Data Mobile Unit 1 Mobile Unit 2 Mobile Unit 3 Mobile Unit 4 Mobile Unit 5 Upload Insp. Forms, Redlines
27 Team Approach Helped Meet the Ambitious Project Schedule NYPA tasks: Normalize / synchronize the transmission structures ( towers ) data between Maximo and Esri Assign Maximo equipment numbers to the spans in Esri and adding spans to WMS Create a personal Geodatabase for the mobile units (tablets / laptops) Create virtual servers for the synchronizing function Provide remote access to the servers Update the Maximo Condition Monitoring table EMA tasks: Configure ArcObjects for mobile solution Develop the inspection forms designed in the initial meeting Create a Maximo work order (backlog) layer for Esri Create a Maximo condition monitoring interface Train NYPA IT and GIS staff ( train the trainer ) Advise and assist NYPA staff throughout the project
28 Part 6 Project Results
29 Pan Last View Launch Redlines Zoom Out Zoom In Global View Information Measure Map Notes Color Code Assets Work Location Table of Contents (Layers) NYPA Line Patrol Application Map View
30 Line-Workers Helped Define User-Friendly Forms 11. Once the Inspection Form button is hit. A sign in screen will appear where you HAVE TO Enter the crew information, and the Work Order # You are working on. 12. The Tower Inspection Form will appear once you click OK. You will notice that all the crew information is at the top. Under that you will find a series of boxes pertaining to a heading such as Hardware or Insulators. When you are inspecting the structure if you DO NOT find anything wrong with a particular part, leave the box blank. ONLY if something is wrong tap in the box and write in what you find in a manner so the planners can figure out what is wrong. If the structure has no issues scroll to the bottom of the form and click SUBMIT then close and move on to the next. NYPA Line Patrol Inspection Form
31 Drawing Toolbar allows you to write directly on the screen with the stylus anything you may want to convey to the GIS Administrators. Example: Access Road is located here. Or: Steep slope in this area.
32 Flow of Redline Sketch Information Provides Effective Communication of Changes Performed in the Field Create redline sketch in the field Submit Edit in ArcGIS Automatic redline upload ArcSDE Redline Layer
33 Part 7 Project Benefits
34 Crews Participate in Increasing Asset Data Accuracy Crews create redlines of asset changes or discrepancies Updates are sent to the GIS Administrator and are available after next synchronization (weekly during the line inspection period). Work Order backlog is available to the line crew while they are physically at the asset location.
35 Increases Accuracy and Integrity of Enterprise Asset Data BEFORE Discovery of changes to field information stayed in crew s heads. Managing paper inspection forms is an arduous task where actionable data may not always be readily available. INTEGRATED Streamlined communication of asset changes from field to office. Work order backlog and GIS data available to the field in a timely manner. Reduced windshield time.
36 Part 8 Current Status and Next Steps
37 Current Status Inspected three of the major transmission facilities during the pilot: Moses-Adirondack Transmission Line (MA) Fitzpatrick-Edic Transmission Line (FE) Niagara Adirondack Tie Line (NATL). Total inspections included: 3,068 structures 2,501 spans 351 miles of right of way
38 Additional Functionality Mark the Project s Future Opportunities Danger Tree Application Aerial Line Patrol
39 Part 9 Summary/ Lessons Learned
40 GIS/WMS Integration Provides Complete Solution for Managing Distributed Work & Assets Integration Approach Provides: Improved asset data sharing across multiple enterprise systems. More efficient and effective work management. Effective tools for managing work and assets in the field. Increased accuracy and integrity of enterprise asset data.
41 Lessons Learned Get user acceptance and management buy in early in the process. Timely response to user comments during the pilot pays huge dividends. In-field support at beginning of pilot helps ensure end-user acceptance. Understand the hidden agendas of all participants. The degree of technical competence is inversely proportional to the level of management.
42 Testimonials It's heavy (compared with paper) but I think this will work. I am not especially computer literate but found this system to be straightforward and relatively easy to use. This is an important initiative to the Transmission Maintenance Business and our Transmission Infrastructure; this software and its ease of use has achieved the objective - Senior Manager of Transmission Maintenance. This works well, and we like having the GIS information available in the field. We have gotten good buy-in from the field, and the system has proven to be useful and reliable. I see no reason to continue paperbased inspections.
43 Questions? 2011 EMA, Inc. For more information, contact: or
Enhancing Asset Management with a GIS Program. Lori A. Burkert, P.G. lburkert@entecheng.com 610-373-6667
Enhancing Asset Management with a GIS Program Lori A. Burkert, P.G. lburkert@entecheng.com 610-373-6667 presentation overview Definitions Its all about your assets Components of a GIS Why use GIS for asset
More informationWFP Liberia Country Office
1 Oscar Gobbato oscar.gobbato@wfp.org oscar.gobbato@libero.it WFP Liberia Country Office GIS training - Summary Objectives 1 To introduce to participants the basic concepts and techniques in using Geographic
More informationBenefits of Mobile GIS for Public Works
Benefits of Mobile GIS for Public Works Freese and Nichols, Inc. NCAFPM 2013 Agenda General GIS Concepts Mobile GIS Overview Benefits of Mobile GIS Mobile GIS Project Examples Questions What is GIS? Geographic
More informationSpatial Database Support
Page 1 of 11 Spatial Database Support Global Mapper can import vector data from and export vector data to the following spatial databases: Esri ArcSDE Geodatabase Esri File Geodatabase Esri Personal Geodatabases
More informationINCOG Transportation Planning Division Spatial Data Management Workflow GIS-T 2008
INCOG Transportation Planning Division Spatial Data Management Workflow GIS-T 2008 Kevin Tartar, GISP Transportation Geodatabase Coordinator 201 West 5th Street, Suite 600 Tulsa, Oklahoma 74103 Phone:
More informationGeoManitoba Spatial Data Infrastructure Update. Presented by: Jim Aberdeen Shawn Cruise
GeoManitoba Spatial Data Infrastructure Update Presented by: Jim Aberdeen Shawn Cruise Organization Overview Manitoba Innovation Energy and Mines Business Transformation and Technology (BTT) Application
More informationThis is a training module for Maximo Asset Management V7.1. In this module, you learn to use the E-Signature user authentication feature.
This is a training module for Maximo Asset Management V7.1. In this module, you learn to use the E-Signature user authentication feature. Page 1 of 16 When you complete this module, you can perform these
More informationFinding Your Assets:
Finding Your Assets: City of Des Moines Sign Inventory Steve Schunzel GIS Administrator City of Des Moines, WA 2010 WAURISA GIS Conference April 21, 2010 The Problem (Where are our signs?) The Solution
More informationArcGIS Server Implementation HIGHS and lows
ArcGIS Server Implementation HIGHS and lows GIS-T March 2011 Eric Abrams Iowa DOT Eric.abrams@dot.iowa.gov Agenda The Problem Timeline Future Discussion/Questions The Problem - 2006 How does Iowa DOT integrate
More informationPublishing geospatial data to the web using the EEA infrastructure
Publishing geospatial data to the web using the EEA infrastructure *Note: Map Services should be published using the EEA Map Services Tick Sheet for guidance. Contact Sebastien Petit (Sebastien.Petit@eea.europa.eu)
More information8/4/2014. Mobile GIS for Public Works. Ames, Iowa. Background. 2014 APWA National Congress
Ben McConville, GIS Coordinator City of Ames Public Works Department Mobile GIS for Public Works Corey Mellies, P.E., Operations Manager City of Ames Public Works Department 2014 APWA National Congress
More informationArcGIS Mobile Application User s Guide
ArcGIS Mobile Application User s Guide 1 Contents Chapter 1 Chapter 2 Chapter 3 Chapter 4 2 5 5 6 7 7 8 8 11 12 14 15 19 21 22 23 37 38 ArcGIS Mobile User Interface Essentials Title Bar Menu Bar Hardware
More informationLeveraging Cartegraph Data for the Management of Public Works Assets for the City of Grapevine
Leveraging Cartegraph Data for the Management of Public Works Assets for the City of Grapevine Presented By: Suja Joseph & Julie Paine Public Works City of Grapevine Overview of Cartegraph System for the
More informationManitoba Dutch Elm Disease (DED) Field Data Capture using Collector for ArcGIS and ArcGIS Online
Manitoba Dutch Elm Disease (DED) Field Data Capture using Collector for ArcGIS and ArcGIS Online ESRI Regional User Conference Winnipeg, Manitoba April 21, 2015 1 Presentation Outline Business Problem
More informationsmespire - Exercises for the Hands-on Training on INSPIRE Network Services April 2014 Jacxsens Paul SADL KU Leuven
smespire - Exercises for the Hands-on Training on INSPIRE Network Services April 2014 Jacxsens Paul SADL KU Leuven These exercises aim at people who already have some basic knowledge of INSPIRE Network
More informationImplementing a Mobile GIS. Tom Brenneman Esri
Implementing a Mobile GIS Tom Brenneman Esri Agenda Mobile GIS Overview ESRI Mobile GIS Solutions - ArcPad - ArcGIS Mobile - ArcGIS for ios Select a Mobile GIS Solution Q&A Mobile GIS Overview ArcGIS 10
More informationAn Esri White Paper October 2010 Esri Production Mapping Product Library: Spatially Enabled Document Management System
An Esri White Paper October 2010 Esri Production Mapping Product Library: Spatially Enabled Document Management System Esri, 380 New York St., Redlands, CA 92373-8100 USA TEL 909-793-2853 FAX 909-793-5953
More informationCity of Dubuque, Iowa Request for Proposals for Software & Implementation of ADA Compliance & Transition Plan Management
City of Dubuque, Iowa Request for Proposals for Software & Implementation of ADA Compliance & Transition Plan Management Request Summary The City of Dubuque, IA is requesting detailed proposals from professional
More informationApplications of Mobile GIS in Forestry South Australia
Applications of Mobile GIS in Forestry South Australia D. T. Battad a, P. Mackenzie b a South Australian Forestry Corporation, Mt. Gambier, South Australia, Australia 5290 - battad.dionisio@forestrysa.com.au
More informationGIS Solutions for Highway and Roadway Management. Average Lane Speed (mph)
GIS Solutions for Highway and Roadway Management Average Lane Speed (mph) Collect Information from the Field with Mobile GIS Esri s mobile GIS technology allows transportation maintenance and inspection
More informationPrints and Photographs Online Catalog Web Address http://www.loc.gov/rr/print/catalog.html
Historic Photo Geographic Inventory A Guide for Geocoding Library of Congress Photo Images. NYS Adirondack Park Agency GIS J. W. Barge - January 19, 2006 Background The Library of Congress Prints and Photographs
More informationMobileMap and Spatial Content Management: Integrating Field Data Collection, Document Management and Enterprise GIS for Natural Resources
MobileMap and Spatial Content Management: Integrating Field Data Collection, Document Management and Enterprise GIS for Natural Resources BRIAN GRASS MASON, BRUCE & GIRARD The Mobile Revolution Proliferation
More informationAutomating Field Service Paperwork for Energy & Utilities
Automating Field Service Paperwork for Energy & Utilities Field service teams in the energy sector are facing increasing pressure to maintain uptime, respond quickly to issues, and document work for customers
More informationWhite Paper. Freeance Mobile for Cityworks
White Paper Freeance Mobile for Cityworks Version 1.1 May 2012 Freeance Mobile for Cityworks Freeance Mobile for Cityworks 2012.1 is a mobile application for the following smartphones and tablets: iphone
More informationEmpowering the Field Users in a Utility Enterprise. Lee Nelson PE 3-GIS
Empowering the Field Users in a Utility Enterprise Lee Nelson PE 3-GIS Introducing 3-GIS Founded in May 2006 2010 Esri s Strategic Gold Partner Award 2011 Esri s Partners Choice Award GTI Strategic Development
More informationESRI Mobile GIS Solutions Overview. Shane Clarke ESRI
ESRI Mobile GIS Solutions Overview Shane Clarke ESRI Agenda Overview of mobile GIS ESRI mobile GIS Solutions Selecting a mobile GIS solution Q & A 2 Mobile GIS Overview 3 What is mobile GIS? Extension
More informationDatabase Servers Tutorial
Copyright 1995-2010 Esri All rights reserved. Table of Contents A quick tour of the database servers tutorial........................ 3 Exercise 1: Add a database server to the Catalog tree and create
More informationMaximo Scheduler Update
Anthony Honaker, Maximo Product Strategy Maximo Scheduler Update 2012 IBM Corporation 2009 IBM Corporation Please note: IBM s statements regarding its plans, directions, and intent are subject to change
More informationE-fficient Network Reporting Solutions For Your Organization
PARTNER SOLUTIONS Automate your organization s processes to faciliate interdepartmental communication, reduce data entry error and increase efficiency. Maintenance Tracking Construction Design Map-Based
More informationA Workflow for Creating and Sharing Maps
A Workflow for Creating and Sharing Maps By Keith Mann, Esri What You Will Need Item Source ArcGIS Online for Organizations subscription ArcGIS 10.1 for Desktop (Any license level) ArcGIS Spatial Analyst
More informationESRI and Xplore Technologies 2008 Mobile Government Demonstration Project Grant Program Final Report
ESRI and Xplore Technologies 2008 Mobile Government Demonstration Project Grant Program Final Report Introduction and Project Purpose The ESRI and Xplore Technologies Mobile Government Demonstration Project
More informationVersion 3.0, April 16, 2012, updated for ArcGIS 10.0 Produced by the Geographic Information Network of Alaska http://www.gina.alaska.
Using the AlaskaMapped Web Services in ESRI ArcGIS Version 3.0, April 16, 2012, updated for ArcGIS 10.0 Produced by the Geographic Information Network of Alaska http://www.gina.alaska.edu AlaskaMapped
More informationAddendum #4 to Spotsylvania County RFP #15-10-36 for Enterprise Asset Management System Software June 10, 2015
Addendum #4 to Spotsylvania County RFP #15-10-36 for Enterprise Asset Management System Software June 10, 2015 Addendum #4 for Request for Proposal #15-10-36 is issued in accordance with the RFP Terms
More informationCDA Information Technology: Fiber To the Home
C O E U R D A L E N E T R I B E I N F O R M A T I O N T E C H N O L O GY GIS Program Spring 2014 Volume 1, Issue 1 GIS Program plans for new imagery of Reservation Inside this issue: Fiber to Home 2 WWP
More informationSpatial Adjustment Tools: The Tutorial
Spatial Adjustment Tools: The Tutorial By Peter Kasianchuk, ESRI Educational Services In this exercise, you will perform some spatial adjustment and data management operations data to be used in analysis
More informationSPRINGVILLE CITY, UTAH
SPRINGVILLE CITY, UTAH REQUEST FOR PROPOSALS ENTERPRISE ASSET MANAGEMENT AND WORK ORDER SOFTWARE AND SERVICES RFP #2013 02 1 Table of Contents PROJECT BACKGROUND:... 4 SCOPE OF WORK:... 4 ALTERNATE SCOPE
More informationBusiness Process Management & Workflow Solutions
Business Process Management & Workflow Solutions Connecting People to Process, Data & Activities TouchstoneBPM enables organisations of all proportions, in a multitude of disciplines, the capability to
More informationGIS Architecture and Data Management Practices Boone County GIS Created and Maintained by the Boone County Planning Commission GIS Services Division
GIS Architecture and Data Management Practices Boone County GIS Created and Maintained by the Boone County Planning Commission June 2008 Background Boone County s GIS program has been in existence for
More informationMaking Your Mobile Workforce More Efficient
ArcGIS for Mobile Making Your Mobile Workforce More Efficient What Is Mobile GIS? Mobile geographic information system (GIS) technology extends GIS beyond the office and allows organizations to make accurate,
More informationEditing Common Polygon Boundary in ArcGIS Desktop 9.x
Editing Common Polygon Boundary in ArcGIS Desktop 9.x Article ID : 100018 Software : ArcGIS ArcView 9.3, ArcGIS ArcEditor 9.3, ArcGIS ArcInfo 9.3 (or higher versions) Platform : Windows XP, Windows Vista
More informationVehicle Tracking Using ArcIMS and Geocortex IMF: A Winning Combination. Combination
Vehicle Tracking Using ArcIMS and Geocortex IMF: A Winning Combination Combination Jason Close Internet Geographer Latitude Geographics Group Ltd. jclose@latitudegeo.com The City of Garland, Texas, population
More informationAvantis Enterprise Asset Management Suite
Avantis Enterprise Asset Management Suite The Avantis Enterprise Asset Management Suite (EAM) of offerings represent the core of the Asset Performance Management (APM) solution set. APM will help you deliver
More informationKAREN E. RUSHING. Clerk of the Circuit Court and County Comptroller. Audit Services. Karen E. Rushing
KAREN E. RUSHING Clerk of the Circuit Court and County Comptroller AUDIT OF Sarasota County s Computerized Maintenance Management System (Maximo) Audit Services Karen E. Rushing Clerk of the Circuit Court
More informationArcGIS Reference Document
Migration of GIS Data to ArcSDE Page 1 of 10 Table of Contents A Brief Summary of DEP s GIS Data Storage o The Y Drive o ArcSDE (Spatial Database) Keeping Your GIS Project Data Current o Checking Your
More informationHow To Develop A Gis Based College Information System
Development of Web-GIS based College Information System Giridhar M.V.S.S. 1, Md.Nazia Firdouse 2, Durga Bhavani.S 3, Viswanadh.G.K 4, Chandra Bose A.S 5 1- Assistant Professor, CWR, IST, JNTUH, Hyderabad,
More informationActivity: Using ArcGIS Explorer
Activity: Using ArcGIS Explorer Requirements You must have ArcGIS Explorer for this activity. Preparation: Download ArcGIS Explorer. The link below will bring you to the ESRI ArcGIS Explorer download page.
More informationBenchmark Testing Results: Telvent ArcFM Solution Running on Microsoft SQL Server
Benchmark Testing Results: Telvent ArcFM Solution Running on Microsoft SQL Server Benchmark testing confirms the superior performance and scalability of Telvent ArcFM Solution 10.0.1 SP1 running on SQL
More informationGeospatial-Enabled Field Inspection Management. Sean Graebner Alliances Manager Geospatial sean.graebner@schneider-electric.com
Geospatial-Enabled Field Inspection Management Sean Graebner Alliances Manager Geospatial sean.graebner@schneider-electric.com Agenda Mobile Utility - Business Drivers and Challenges Lincoln Electric System
More informationNetwork Analysis with ArcGIS Online
Federal GIS Conference February 9 10, 2015 Washington, DC Network Analysis with ArcGIS Online Matt Kennedy Topics Online versus on-premise network analysis services How to access online services How to
More informationCity of Grand Junction and inframap Software Mobile Field Application
1 City of Grand Junction and inframap Software Mobile Field Application City Of Grand Junction Grand Junction Colorado Scott List inframap Software Adam Hagee Colin Kennedy Grand Junction Background 2
More informationCloud Nine: Developing an Entirely Cloud Based GIS, Asset Management and Work Order System
Cloud Nine: Developing an Entirely Cloud Based GIS, Asset Management and Work Order System Corrie Bondar 1*, Mark Valentino 2 1 Freese and Nichols, Inc., Raleigh, North Carolina 2 Freese and Nichols, Inc.,
More informationTAMS 2.1 User s Manual. Utah LTAP Center. Contact: Utah LTAP 4111 Old Main Hill Logan, UT. 84322-4111 800-822-8878 www.utahltap.
TAMS 2.1 User s Manual Utah LTAP Center Contact: Utah LTAP 4111 Old Main Hill Logan, UT. 84322-4111 800-822-8878 www.utahltap.org Table of Contents Introduction 1 Initializing the program... 1 Data Needed
More informationHELCOM Data and Map Service. User Manual
HELCOM Data and Map Service User Manual Version 2.2 - February 2015 1 Table of contents 1. General Information... 3 1.1 Background... 3 1.2 Technical requirements... 3 1.3 Contact... 3 2. Accessing HELCOM
More informationPenn State University (PSU)
Penn State University (PSU) FAM Inventory Management Training Manual Prepared By Revision History Revision Date: March 18, 2014 Revision Number: 1 Revision # Date Collaborator Description 1.0 March 18,
More information15 th UPDEA CONGRESS THEME: GEOGRAPHIC INFORMATION SYSTEM: ECG S EXPERIENCE ABSTRACT. PATRICE AFENYO, Electricity Company of Ghana
15 th UPDEA CONGRESS THEME: GEOGRAPHIC INFORMATION SYSTEM: ECG S EXPERIENCE Author: PATRICE AFENYO, Electricity Company of Ghana ABSTRACT GIS (Geographic Information System) is an integrated system of
More informationHillsborough County Water
0407 FWRJ 3/20/07 4:23 PM Page 54 Selecting & Implementing a Comprehensive Asset Management System Celine A. Hyer Hillsborough County Water Resource Services (WRS) provides water, wastewater, and reclaimed
More informationMonitoring Your Spatial Enterprise: How IT/GIS Managers are Improving System Reliability with XMF Alerter.
: How IT/GIS Managers are Improving System Reliability with XMF Alerter. December, 2007 Page 1 Overview IT/GIS managers in both the public and private sector are facing everincreasing pressure to deliver
More informationArcGIS. Image Server tutorial
ArcGIS 9 ArcGIS Image Server tutorial Copyright 2006, 2007, and 2008 Zanja Technologies, Inc. All rights reserved. The information contained in this work is the property of Zanja Technologies, Inc., under
More informationCyberTracker. Step-by-Step Tutorial. How to Customise a Wildlife Monitoring Application
CyberTracker Step-by-Step Tutorial How to Customise a Wildlife Monitoring Application This tutorial will demonstrate how to customise a CyberTracker Wildlife Monitoring and Line Transect Survey Application.
More informationThe Redwood City Public Works Services (PWS) Department is comprised of four operating divisions:
City of Redwood City, Public Works Services (PWS) Work Process Needs Assessment By: Russell Narahara, Management Analyst II The purpose of this document is to provide an overview of how field work is currently
More informationThinManager and Active Directory
ThinManager and Active Directory Use the F1 button on any page of a ThinManager wizard to launch Help for that page. Visit http://www.thinmanager.com/kb/index.php/special:allpages for a list of Knowledge
More informationGIS and Document Management Integration
GIS and Document Management Integration Presented by: Steve Sherman, GISP City of Greensboro, NC ESRI Conference 2007 Presentation Goals Definition of Document Management What it is? Why it s s important
More informationURISA ESIG Application
RECOVER Rehabilitation Capability Convergence for Ecosystem Recovery An Automated Burned Area Emergency Response Decision Support System for Postfire Rehabilitation Management Application contents: A.
More informationFood Industry. www.ats global.com
Food Industry Significantly reduces scrap and rework cost Image driven inspection Web based analysis and reporting Eliminates paper checklists Real-time attribute data collection Easy-to-use operator interface
More informationLast Updated on 11/06/2008. www.jobprotech.com
Last Updated on 11/06/2008 www.jobprotech.com Copyright JobPro Technology, 2008 How to Use this Guide This manual is designed as a reference for JobPro customers. It is not intended to be a replacement
More informationGatekeeper Systems Mobile Work Orders System (MWO)
Mobile Work Orders System (MWO) Software Product Description Product Summary The Gatekeeper Mobile Work Orders System (MWO) allows mobile field personnel to take enterprise transactional data such as work
More informationTop 10 Do s and Don ts in Selecting Campus Recreation Software
Top 10 Do s and Don ts in Selecting Campus Recreation Software Discussion Paper Investing in technology can make your Campus Recreation department more efficient, increase revenues, reduce costs, and improve
More informationMANCHESTER WATER WORKS REQUEST FOR PROPOSALS FOR WATER ASSET MANAGEMENT SOFTWARE AND SERVICES RFP #FY15-804-64
FY15-804-64 MANCHESTER WATER WORKS REQUEST FOR PROPOSALS FOR WATER ASSET MANAGEMENT SOFTWARE AND SERVICES RFP #FY15-804-64 FY15-804-64 Invitation to Propose 2 Part 1 - Instructions to Proposers 1.1. Receipt
More informationArcGIS. Server. A Complete and Integrated Server GIS
ArcGIS Server A Complete and Integrated Server GIS ArcGIS Server A Complete and Integrated Server GIS ArcGIS Server enables you to distribute maps, models, and tools to others within your organization
More informationAsset Management Systems Information
Asset Management Systems Information Required to Maintain Service Delivery and Asset State Of Good Repair Willem Ebersöhn Ph.D. Vice president Encada. LLC. Valerie Marcolongo President Encada. LLC. 4/18/2012
More informationEAM and Field Service Roadmap für den schweizerischen Instandhaltertag
EAM and Field Service Roadmap für den schweizerischen Instandhaltertag Oktober 27, 2014 Georg Lessmöllmann Mobile Solution Management 2011 SAP AG. All rights reserved. This presentation and SAP s strategy
More informationEmploying GIS, Cloud, and Mobile Technologies to Support Asset Management and System Management
NAME OF MEETING: NC AWWA- WEA Annual Conference 2013 AUTHORS: Jayson Brennen, GISP SESSION/PAPER NO.: Policy & Management Session Tuesday 11/12/2013, 1:45PM PAPER FORMAT: MS Word ABSTRACT FORMAT: MS Word
More informationNatureServe s Environmental Review Tool
NatureServe s Environmental Review Tool A Repeatable Online Software Solution for Agencies For More Information, Contact: Lori Scott Rob Solomon lori_scott@natureserve.org rob_solomon@natureserve.org 703-908-1877
More informationBusiness Process Management (BPM) Software
FlowCentric Processware 2013 FlowCentric Business Process Management (BPM) Software and Services enable organisations of all proportions, in a multitude of industries, to satisfy and often exceed their
More informationArcGIS 9. Installation Guide: Workgroup for Microsoft SQL Server Express
ArcGIS 9 Installation Guide: Workgroup for Microsoft SQL Server Express Copyright 2006 ESRI All Rights Reserved. Printed in the United States of America. The information contained in this document is the
More informationGIS Databases With focused on ArcSDE
Linköpings universitet / IDA / Div. for human-centered systems GIS Databases With focused on ArcSDE Imad Abugessaisa g-imaab@ida.liu.se 20071004 1 GIS and SDBMS Geographical data is spatial data whose
More informationDatabase Production and Map Series Management. Using. The Production Line Tool Set
Database Production and Map Series Management Using The Production Line Tool Set Dewey Marino - ESRI Redlands Production Line Tool Set ArcGIS Solution for high volume database and map creation Creates
More informationThe Importance of Data Quality in your Enterprise
Federal GIS Conference February 9 10, 2015 Washington, DC The Importance of Data Quality in your Enterprise Heather Murnane & Sherry Fagin Workshop Agenda Importance of Data Quality What is ArcGIS Data
More informationHow to Setup and Manage Spatial Assets with ArcGIS Online for a Mobile Workforce
How to Setup and Manage Spatial Assets with ArcGIS Online for a Mobile Workforce W A U R I S A 2 0 1 4 Presented By Engineer Technician II Pierce County Public Works and Utilities Road Operations Division
More informationMethods and Practices: Cloud in Retail
Methods and Practices: Cloud in Retail IDC Retail Insights: Retail IT Infrastructure Strategies METHODS AND PRACTICES #RI243398 Kimberly Knickle Leslie Hand Global Headquarters: 5 Speen Street Framingham,
More informationGAEA Systems Pvt. Ltd. Providing Knowledge-based GIS and IT Solutions
GAEA Systems Pvt. Ltd. Providing Knowledge-based GIS and IT Solutions Registered Office: Business Address 6-3-249/4/6, G2, Dhanunjaya Towers Road No: 1, Banjara Hills Hyderabad 500 034 Andhra Pradesh,
More informationQuick Start Guide 0514US
Quick Start Guide Copyright Wasp Barcode Technologies 2014 No part of this publication may be reproduced or transmitted in any form or by any means without the written permission of Wasp Barcode Technologies.
More informationMicrosoft Access 2010 handout
Microsoft Access 2010 handout Access 2010 is a relational database program you can use to create and manage large quantities of data. You can use Access to manage anything from a home inventory to a giant
More informationGeographic Information Systems (GIS) @ GIS at UCSD. Here to help you explore our world
Geographic Information Systems (GIS) @ GIS at UCSD Here to help you explore our world GIS at UCSD what it is and what it means to you Tracey Hughes UCSD GIS Coordinator 2006 Image from Google Earth An
More informationConverting GIS Datasets into CAD Format
Ball State University Libraries GIS Research and Map Collection Converting GIS Datasets into CAD Format Author: Angela Gibson, 6/13/2014 Overview: One of the most common requests from students is for GIS
More informationCity of Corpus Christi. Mobile GIS Viewer. For ipad
City of Corpus Christi Mobile GIS Viewer For ipad MIS - GIS 3/9/2012 P a g e 1 Contents Requirements... 2 Installation... 2 Using the ArcGIS Mobile App... 4 Connect to the Corpus Christi Mobile GIS Map
More informationTHE ADVANCES OF INTEGRATED GEOSPATIAL APPLICATION IN WORKFORCE MANAGEMENT AND FIELD SERVICE OPTIMIZATION
THE ADVANCES OF INTEGRATED GEOSPATIAL APPLICATION IN WORKFORCE MANAGEMENT AND FIELD SERVICE OPTIMIZATION Naomi KELLETT GE Energy United Kingdom Naomi.Kellett@ge.com Abstract: INTRODUCTION TO FIELD SERVICES
More informationUsing Mobile GIS Technology Tools to Support Asset Management and System Operations
Using Mobile GIS Technology Tools to Support Asset Management and System Operations Andrew Baranowski GISP, CDM Smith June 08, 2015 SFLUC 2015 Boca Raton, SFLUC FL Presentation 2015 Boca Raton, FL We are
More informationENVI and ArcGIS Integration Bringing Imagery to GIS
ITT ENVI and ArcGIS Integration Bringing Imagery to GIS The information contained in this document pertains to software products and services that are subject to the controls of the Export Administration
More informationAn Esri White Paper June 2011 ArcGIS for INSPIRE
An Esri White Paper June 2011 ArcGIS for INSPIRE Esri, 380 New York St., Redlands, CA 92373-8100 USA TEL 909-793-2853 FAX 909-793-5953 E-MAIL info@esri.com WEB esri.com Copyright 2011 Esri All rights reserved.
More informationWashtenaw County Geographic Information System Strategic Plan
Washtenaw County Geographic Information System Strategic Plan April 1999 1 Table of Contents Vision, Goals, and Strategies. 3 GIS Timeline 1999-2002. 8 GIS Timeline 1999-2010. 9 Washtenaw County GIS Program
More informationA PUBLICATION OF c-systems SOFTWARE, INC. A Dealer s Guide to COST ANALYSIS. How to Analyze Costs and Increase Revenue
A PUBLICATION OF c-systems SOFTWARE, INC. A Dealer s Guide to COST ANALYSIS How to Analyze Costs and Increase Revenue Table of Contents 1 Introduction 2 Pricing Controls 3 Inventory Control 4 Wholegoods
More informationCMMS/EAM. Maintenance Solutions
CMMS/EAM Maintenance Solutions Superior Functionality. Fully Integrated Solution. Maximum System Support. Maximize Critical Assets Maintenance Software Solutions For nearly 40 years, CHAMPS has remained
More informationVisualization of GIS Data in OCAD
OCAD-Tutorial Visualization of GIS Data in OCAD OCAD AG Mühlegasse 36 CH - 6340 Baar / Schweiz Tel (+41) 41 763 18 60 Fax (+41) 41 763 18 64 info@ocad.com http://www.ocad.com Contents 1 Open OCAD file
More informationMaximizing your SAP ERP
950 Tower Lane, Suite 750 Foster City, CA 94404 650.341.3310 phone 650.341.3610 fax www.guixt.com Maximizing your SAP ERP Desktop Suite GuiXT Portal Suite Web UI Suite Mobile Suite Offline Suite Developer
More informationGeographic Information Systems
Geographic Information Systems Visualize Listen first. Solve second. Geospatial Modeling of Strategic Farmland in the Inner Bluegrass Region KY Leading the Way Integration of the latest GIS technology
More informationneoconnex Server Manual Version 10.0
neoconnex Server Manual Version 10.0 Page 1 of 38 COPYRIGHT INFORMATION 3 SECTION 1 BEFORE YOU START 4 INTRODUCTION:... 5 neoterra Systems Contact information:... 5 Some value added inclusions within neoconnex
More informationDurango Migrates its Infrastructure GIS to an Asset Management System
Durango Migrates its Infrastructure GIS to an Asset Management System Rick Szmajter, GISP City of Durango Colorado ESRI International User Conference San Diego, CA July 22, 2015 rick.szmajter@durangogov.org
More information2 Working with a Desktop GeoDatabase
2 Working with a Desktop GeoDatabase Introduction... 3 1 Installation of an ESRI Desktop GeoDatabase... 3 1.1 Installation of Microsoft SL Server Express instance... 5 1.2 Installation of the ArcSDE libraries
More informationThe advantages of high accuracy GIS field data collection in the Transportation Industry. MGIS Overview Sergio Hernández
The advantages of high accuracy GIS field data collection in the Transportation Industry. MGIS Overview Sergio Hernández The big question: Where are our assets? Where do we need improvements? WHERE? Where
More information