Unit 06 Developing the Work Breakdown Structure
|
|
|
- Matthew Osborne
- 10 years ago
- Views:
Transcription
1 Unit 06 Developing the Work Breakdown Structure April 2007 Project Management Wilhelm F. Neuhäuser IBM Corporation 2007
2 Agenda Unit 6: Developing the Work Breakdown Structure Objectives Value of the WBS WBS definitions WBS development process Uses of the WBS Key Messages - Unit 6 2
3 Objectives At the end of this module, you will be able to - Develop a WBS for a project Define the WBS dictionary Decribe the importance and uses of the WBS for managing a project Distinguish between cost accounts and work packages 3
4 WBS - Work Breakdown Structure Dominant prerequisite for successfully integrating and controlling the total project Framework on which a project is built and the "map" for executing the project Graphically depicts the hierarchy of the project 4
5 Benefits of Using a WBS Provides the framework to identify development projects separately from geographies, accounting systems, funding sources, and so on Clarifies responsibilities Focuses attention on project objectives Encourages detailed planning and documentation Identifies specific work packages for estimating and assigning work 5
6 WBS Definitions WBS - A task- or product-oriented family-tree division of hardware, software, services, data, and other work tasks that completely define the project 1.0 XYZ Product Development 1.1 Develop Product Requirements and Concepts Receive concept for new products Form product development team Indentify members Schedule kickoff meeting Conduct meeting Develop initial product proposal and plan 1.1 Develop product reqrmt & concept XYZ Product Development Develop & verify product 1.3 Ramp-up and launch product -- Cost account level -- Work package level Size and number of WBS levels vary with project, but the WBS must be complete to relate all elements to one another and to the total product. 6
7 WBS Definitions (continued) Cost account One level above the work package where costs are accrued - lowest management and control level Work package Lowest level of the WBS consisting of required tasks to complete each product - used to budget and schedule with a defined delivery date Rule of Thumb: Work package should consist of approximately 80 hours of labor effort (PMI standard) 7
8 WBS Development Process 1. Develop and/or review project goals and objectives 2. Prepare a summary (high-level) WBS Total project: Level 1 Major subsystem and project services: Level 2 Major subsystems and project services elements: Level 3 3. Meet with responsible project team members, sponsors, and other project stakeholders (internal and external) 8
9 WBS Development Process (continued) 4. Responsible departments and geographies further define to lowest meaningful level, which produces work packages, including - Technical performance parameters Schedule (with a defined delivery date) Expenses 5. Prepare detailed WBS dictionairy 9
10 WBS Dictionary WBS dictionary must include Work item number Work item title Description of work Predecessors and successors Work to be accomplished Deliverable/objective How do you know you are done? Who needs the output? Ownership/participation Who is responsible? Who else will be involved? 10
11 Uses of the WBS Planning and budgeting Funding Estimating Scheduling Performance measurement Change management 11
12 Key Points on WBS Identify all tasks to accomplish the project Use good judgement as the key to an effective WBS - no hard and fast rules Structure WBS as work will be done Levels of detail should allow for realistic estimating Levels of detail should allow assignment to single organizational control unit 12
13 Key Points on WBS (continued) Limit level of detail to level of control Each lowest level task should result in a deliverable Each WBS description should include an action verb, for example - Establish manufactuarability criteria Prepare final product proposal package Update common software Each task should have single, identifiable owner 13
14 Key Messages The WBS is the cornerstone off quality project planning The WBS is a tool, not an end unto itself There are multiple uses of the WBS The WBS is not a schedule The WBS is a good project team-building tool 14
Project Management Planning
Develop Project Tasks One of the most important parts of a project planning process is the definition of activities that will be undertaken as part of the project. Activity sequencing involves dividing
PROJECT PLAN FOR. Project Name Here
PROJECT PLAN FOR Project Name Here Version # DatE Reviewed and Approved for submittal to Executive Sponsor , Project Manager Project Plan Approved for submittal to Executive Sponsor: , Project
What is Project Scope Management? Project Scope Management Summary. Project Scope Management Processes
What is Project Scope Management? Chapter 5 Project Scope Management October 27, 2008 Scope refers to all the work involved in creating the products of the project and the processes used to create them
Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes
Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1 Introduction to Project Management Learning Objectives Describe the importance of creating plans to guide project
Time Management. Part 2 Work Breakdown Structure (WBS) Review. Richard Boser
Time Management Part 2 Work Breakdown Structure (WBS) Review Richard Boser WBS Planning Process PMBOK WBS is deliverable-oriented grouping of components that organizes and defines the total scope of the
Introduction to Project Management
Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project
Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Project Control System Manual. Jefferson Science Associates, LLC. 200 Organization. Project Control System Manual Revision 7 - 7 -
Jefferson Science Associates, LLC 200 Organization Project Control System Manual Revision 7-7 - 200 Organization This section of the JSA Project Control System Manual describes the organizational elements
How to Craft a World-Class Work Breakdown Structure
How to Craft a World-Class Work Breakdown Structure Laura Miller, PMP [email protected] 1 Copyright Copyright 2012 2012 Hewlett-Packard Development Development Company, Company, L.P. The L.P. information
SCOPE MANAGEMENT PLAN <PROJECT NAME>
SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
How to Develop Work Breakdown Structures
How to Develop Work Breakdown Structures Michael D. Taylor Copyright 2003-2009 by Michael D. Taylor All Rights Reserved. No part of this work covered by the copyright hereon may be reproduced or used in
Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved
Description of Program Management Processes (Initiating, Planning) Topics Covered Program Management Process Groups salient features Description of all processes in Initiating Process Group: Initiate Program
PMLead. Project Management Professional. edition. Based on PMBOK Guide 4 th. www.pmlead.net
PMLead Project Management Professional Based on PMBOK Guide 4 th edition www.pmlead.net SECTION II Chapter 3 Project Management Processes Chapter 3 Project Process Groups A process is a set of interrelated
Applied Software Project Management
Applied Software Project Management Software Project Planning http://www.stellman-greene.com 1 Who needs software? Most software is built in organizations for people with specific needs. A stakeholder
Lecture Slides for Managing and Leading Software Projects. Chapter 5: Project Planning Techniques
Lecture Slides for Managing and Leading Software Projects Chapter 5: Project Planning Techniques developed by Richard E. (Dick) Fairley, Ph.D. to accompany the text Managing and Leading Software Projects
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE Head, Office of Project Support Services
Head, Office of Project Management Oversight
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Management Oversight REVISION: 43 APPROVED BY: TITLE Head, Office of Project Management
Lab 1 Introduction to Microsoft Project
Lab 1 Introduction to Microsoft Project Statement Purpose This lab provides students with the knowledge and skills to use Microsoft Project. This course takes students step-by-step through the features
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
Advanced Project Management Training Course
Advanced Project Management Training Course 1-34 Advanced Project Management Crea/ng the Scope Baseline 2-34 Crea/ng the Scope Baseline Module 1 Introduction Module 2 Creating the Project Charter Module
Deciding the work to be Performed (Work Breakdown Structure)
Deciding the work to be Performed (Work Breakdown Structure) Goals of the Unit Understanding the transition from project goals to the project schedule Introducing the Work Breakdown Structure notation
Project Management. Lecture 3. Software Engineering CUGS. Spring 2012 (slides made by David Broman) Kristian Sandahl
Project Lecture 3 Software Engineering CUGS Spring 2012 (slides made by David Broman) Kristian Sandahl Department of Computer and Information Science Linköping University, Sweden A Software Life-cycle
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Project Management Fact Sheet:
Project Management Fact Sheet: Developing a Work Breakdown Structure Version: 1.2, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities.
Creating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems
Creating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems The Work Breakdown Structure (WBS) is the foundation for project planning and control. It is the connecting
Introductory Project Management Module. Mansfield Adult Continuing Education 1 Inc
Managing Your Project: Planning & Time Introductory Project Management Module Mansfield Adult Continuing Education 1 Inc Project Management Learning Objectives Develop a working knowledge of basic project
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
Using Microsoft SharePoint for Project Management
ASPE IT Training Using Microsoft SharePoint for Project Management A WHITE PAPER PRESENTED BY ASPE www.aspe-it.com 877-800-5221 Using Microsoft SharePoint for Project Management A modern Project Management
Project Management Professional (PMP)
Project Management Professional (PMP) Duration: 5 days Course Objectives: PMI s Project Management Professional (PMP) credential is the most important industry-recognized certification for project managers.
Chapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
APM web briefing - Use of Product Breakdown Structures and Work Breakdown Structures
APM web briefing - Use of Product Breakdown Structures and Work Breakdown Structures Introduction Product Breakdown Structures and Work Breakdown Structures look very similar and both have important roles
PMBOK: Project Scope Management (SM) Knowledge Area. my perspective. Razvan Radulian. President Why-What-How Consulting, LLC
PMBOK: Project Scope Management (SM) Knowledge Area my perspective Razvan Radulian President Why-What-How Consulting, LLC Some definitions The rest of the world Out-of-scope Scope In general terms sets
10 Critical Steps to Create a Project Plan
10 Critical Steps to Create a Project Plan Elizabeth Larson, PMP, CBAP and Richard Larson, PMP, CBAP Principals, Watermark Learning, Inc. Industry Article Watermark Learning 7300 Metro Blvd, Suite 207
How To Organize A Business
Page 1 of 9 The Organization Breakdown Structure Figure 3-1: Organization Breakdown Structure (OBS) (see next page), shows a representative OBS. At the conclusion of this lesson you will be able to recognize
Unit 4: Time Management (PMBOK Guide, Chapter 6)
(PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may
A Comparison of PMI s PMBOK Guide Versions 4 & 3
PM WORLD TODAY FEATURED PAPER MAY 2009 A Comparison of PMI s PMBOK Guide Versions 4 & 3 By Germán Bernate The Project Management Institute PMI announced on December 31, 2008 the availability of PMBOK Version
Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them
Sponsored by Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them Joseph A. Lukas PMP, CSM, CCP, PE White Paper 1-888-762-3683 www.pmcentersusa.com Joe Lukas & PM Centers USA, LLC
Minnesota Health Insurance Exchange Project (MNHIX) Deliverable Definition Document (DDD) For Project Management Plan Date: 07-31-2012
Minnesota Health Insurance Exchange Project (MNHI) Deliverable Definition Document (DDD) For Project Plan Date: 07-31-2012 11/9/2012 1:18 PM Page 1 of 8 1. High Level Deliverable Description The Project
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Project Management Professional (Certified by PMI)
Project Management Professional (Certified by PMI) PMI certified Project Management Professional credential is the most important industryrecognized certification for project managers. This recognition
Project Management Professional Exam Prep Plus
In this course, you ll gain the essentials preparation needed to pass the PMP exam. Concentrating on exam content form the Guide to the Project Management Body of Knowledge-Fifth Edition (PMBOK Guide)
Program Management Professional. PgMP
Program Management Professional PgMP COURSE BACKGROUND COURSE LENGTH: 3 days (2.1 CEUs / 21 PDUs) COURSE DESCRIPTION: The Program Management course addresses the essential aspects or Program selection,
Software Project Management I
Software Project Management I Dr. Jong Yih Kuo Dr. Chien-Hung Liu Computer Science and Information Engineering National Taipei University of Technology Course Schedule Time Topic Document 18:10~18:55 (45
PRINCE2, the PMBOK Guide and ISO 21500:2012. Klas Skogmar. AXELOS.com
PRINCE2, the PMBOK Guide and ISO 21500:2012 Klas Skogmar AXELOS.com White Paper September 2015 Contents Introduction 3 Relationships between PRINCE2, the PMBOK Guide and ISO 21500 4 Major differences between
Earned Value Management for Enterprise Resource Planning Implementations
Earned Value Management for Enterprise Resource Planning Implementations Venu Kotamraju Abstract ERP implementations are a special breed of projects. They are often characterized by aggressive timelines,
Software Management. Dr. Marouane Kessentini Department of Computer Science
Software Management Dr. Marouane Kessentini Department of Computer Science 1 What is Project Management? Project management encompasses all the activities needed to plan and execute a project: Deciding
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Project Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
Applying the Work Breakdown Structure to the Project Management Lifecycle
Applying the Work Breakdown Structure to the Project Management Lifecycle Introduction Shelly A. Brotherton, PMP; Robert T. Fried, PMP; Eric S. Norman, PMP, PgMP Today, Project Managers are more frequently
Appeals Case Management System Project. Scope Management Plan. November 20, 2014
Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF
WORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
2.1 Initiation Phase Overview
2.1 Initiation Phase Overview The is the conceptualization of the project. This section describes the basic processes that must be performed to get a project started. Accordingly, the purpose of the is
PMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
Input, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) [email protected] 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
Effectively and Efficiently Managing Multiple Projects
Effectively and Efficiently Managing Multiple Projects Effectively and Efficiently Managing Multiple Projects Offered by: Askler, Fitch and Associates Course Length: One day Course Purpose The success
Project Delivery Process Overview
New Jersey Department of Transportation Project Delivery Process Overview Presented by the Program Management Office January, 2012 Project Delivery Process Overview The New Jersey Department of Transportation
2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster
2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster Traditional Classroom / Onsite Course No. 665 Duration: 2 days Credits: 14 PDUs / 1.4 CEUs Prerequisites Twelve hours of
Information Technology Project Management
Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction
Project Management Concepts and Strategies
Project Management Concepts and Strategies Contact Hours: 24 Course Description This series provides a detailed examination of project management concepts and strategies. It discusses the seven components
Appendix B: Work Breakdown Structure (WBS)
: Work Breakdown Structure (WBS) B.1. Introduction The WBS and WBS dictionary are effective management processes for planning, organizing, and administering NASA programs and projects. In accordance with
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Accounting System. Page 1 of 9
Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems
MODULE TWO PROJECT MANAGEMENT BACKGROUND & COMMUNICATION
Syed Quadri, PMP Region 5 RPM MODULE TWO PROJECT MANAGEMENT BACKGROUND & COMMUNICATION 0 Project Management Background Topics to be covered: Benefits of using PM tools PMI and PMBOK Strategic Project Management
Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 7 Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org Credits 2 This slides are largely based on Prof. John Musser class
IT/Software Project Management Core Functions
IT/Software Project Management Core Functions By: Prof. Dr. Eng. Ghazy Assassa, CMC-IMC Certified Management Consultant, Institute of Management Consultancy, UK Email: [email protected] Mobile: 0502862400
Impact of PMBOK 5 th Edition
PMP Exam Changes Impact of PMBOK 5 th Edition When the PMI exam will change Major Updates X1.1 Scope of Update Comments and feedbacks for prior version Overall review for accuracy Appropriate alignment
Guidelines: Project Schedule Project Management Office (PMO)
Guidelines: Project Schedule Project Management Office (PMO) Process The project Schedule outlines the tasks and activities of the project; the duration; start and end dates for each individual task and
Systems Analysis and Design in a Changing World, Fifth Edition
Systems Analysis and Design in a Changing World, Fifth Edition Learning Objectives Explain the elements of project management and the responsibilities of a project manager Explain project initiation and
How To Manage A Project
Project Management Tools & Techniques Susan W. Carey Workshop Objectives Recognize project management terminology Explain roles and responsibilities for key players Develop a project proposal Construct
Space Flight Project Work Breakdown Structure
APPENDIX G. (WBS) Space Flight Project Work Breakdown Structure G.1 Introduction G.1.1 The Project Work Breakdown Structure (WBS) is a key element of project management. The purpose of a WBS is to divide
Cost Management. How Much Will This Project Cost?
Cost Management How Much Will This Project Cost? Moderator Janelle Abaoag Project Insight Marketing, Public Relations [email protected] www.projectinsight.net All participants will be on
Making project management indispensable for business results. Project Management 101
Making project management indispensable for business results. Project Management 101 Donald E. Moore, MBA, PMP, President of PMI NB Kelly Barter, Chapter Manager of PMI NB AGM April 28, 2011 Topics of
Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition and ISO 21500
Project Training Company Comparing PMBOK Guide 4 th Edition, Edition and STS Sauter Training & Simulation S.A. Avenue de la Gare 10 1003 Lausanne Switzerland Web: www.sts.ch E-mail: [email protected] Phone:
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor
Chapter 3 Managing the Information Systems (IS) Project
Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project
Software Project Management
Software Project Management Week 5: Work Breakdown Structures and a Case Study COMP3711 Software Project Management 1 Project Planning: A 12 Step Program 1) Set goal and scope 2) Select lifecycle 3) Set
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition
Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition 1 Topics for Discussion
Chapter 5: Project Scope Management. Information Technology Project Management, Fifth Edition
Chapter 5: Project Scope Management Information Technology Project Management, Fifth Edition What is Project Scope Management? Scope refers to all the work involved in creating the products of the project
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
Project Planning. Project Scope. Work Breakdown Structure.
Chapter 5 Project Planning. Project Scope. Work Breakdown Structure. 1 Objectives Acquire a general understanding of the parts of the project management plan Understand the importance of discovering and
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
PMP Exam Prep Training - 5 Days
PMP Exam Prep Training - 5 Days (Based on the PMBOK Guide, 5 th Edition) Course Length: 5 Days Course Abstract: This workshop has a primary and a secondary goal. The primary goal is to prepare participants
Project Management Fundamentals. Office of the Senior Associate Vice President for Finance
Project Management Fundamentals Project Management Institute PMI is an aggregation of best practices from thousands of professional project managers Principles in this training are based on PMI methodologies,
Expert Reference Series of White Papers. Intersecting Project Management and Business Analysis
Expert Reference Series of White Papers Intersecting Project Management and Business Analysis 1-800-COURSES www.globalknowledge.com Intersecting Project Management and Business Analysis Daniel Stober,
Project Management Process. Prepared by Jay Knape
Project Management Process Prepared by Jay Knape PMI Project Project is... temporary endeavor undertaken to produce a unique products, service or result. UITS Project Definition For Columbus State University