1 Managing Asbestos Policy Liverpool Mutual Homes Page 1 of 16

2 Table of Contents 1. MANAGEMENT INFORMATION 2. POLICY STATEMENT 3. POLICY AIMS AND KEY OBJECTIVES 4. INTRODUCTION 5. DETAIL 6. LINKS TO LMH CORPORATE PLAN 7. IMPACT ON LMH FOCUSES 8. CUSTOMER SERVICE STANDARDS 9. PERFORMANCE MANAGEMENT 10. CUSTOMER SATISFACTION 11. CUSTOMER INVOLVEMENT 12. EQUALITY ANALYSIS 13. RISK MANAGEMENT 14. VALUE FOR MONEY 15. POLICY REVIEW AND IMPROVEMENT FRAMEWORK Liverpool Mutual Homes Page 2 of 16

3 1. MANAGEMENT INFORMATION Date Policy approved by LMH Board Replacing / Updating Updating Next Review Date August 2015 Drafted By: Responsible Executive Director and Board Champion Circulation list Michael Vickers Maggi Howard Available to all LMH staff electronically Available on LMH web site Liverpool Mutual Homes Page 3 of 16

4 2. POLICY STATEMENT LMH are committed to providing excellent customer services that represent value for money to our customers and partners. This policy is designed to provide a clear acknowledgement of the responsibilities that LMH has in relation to the management of asbestos and its approach to the management of asbestos within the properties it manages. 3. POLICY AIMS AND KEY OBJECTIVES The aims and objectives of this policy are summarised as follows: provides clear lines of responsibility within LMH for the management of asbestos specifies individual responsibilities in the management of asbestos provides a commitment to communication with customers regarding asbestos clarifies the LMH approach to surveying properties provides clear timetable and process for the review of the AMP, Policy and procedures establishes the Compliance Review Group which will review and monitor all areas of compliance within the directorate 4. INTRODUCTION LMH acknowledges and accepts its responsibilities under the Health and Safety at Work Etc. Act 1974, and the Control of Asbestos Regulations (CAR) 2012 to identify and to safely manage Asbestos Containing Materials (ACMs) on its premises. Approved Codes of Practice and guidance information published by the Health and Safety Commission and Executive shall be taken as the adopted standard. It is not a requirement of regulations for employers or persons responsible for health and welfare (of workers, employees, contractors, visitors, third parties likely to become affected by his undertakings), to remove all asbestos when identified. However, by the use of risk management they must manage ACMs via reasonable practicable means to prevent exposure to asbestos fibres and thus comply with the regulations. It is therefore NOT always essential to remove all asbestos-containing materials but to manage them safely, unless it becomes a risk for them to remain in-situ. In order to manage and control the risks from ACMs to employees, occupants, contractors and others, the measures within this policy will be adopted. Liverpool Mutual Homes Page 4 of 16

5 5. DETAIL 5.1. Introduction. Asbestos fibres have many properties which made them useful: good tensile strength, flexibility, chemical resistance, heat resistance, thermal and electrical insulation. Consequently asbestos has been widely used in many building materials especially between the period of 1930 s 1980 s. The main types of asbestos employed in building products in the U.K. were: Crocidolite, Amosite and Chrysotile. Crocidolite and Amosite were legally banned from use in the U.K. in 1985 with the last, Chrysotile, being banned in Therefore, all properties built before the year 2000 which have not undergone recent major refurbishment may hold Asbestos-Containing Materials (ACMs) of some description. (Further information on uses and applications of ACMs is contained in Appendix 1). The presence of ACMs in a building does not in itself present a risk as long as they remain in good condition and undisturbed. The UK Heath & Safety Executive (HSE) guidance is that ACMs in good condition are best left and managed in-situ rather than removed. The risk posed to health from asbestos occurs when the fibres are released into the air and breathed-in. Therefore, provided that ACMs are intact, and in a position where they will not be damaged they will not pose a risk to health. This policy document lays down the procedures to be employed by LMH, including its managers at all levels, maintenance staff, internal works operatives (HMS and resident caretakers/handy persons), staff and contractors, by which ACMs may remain in-situ within its properties by effectively managing the risks associated with them Management and Hierarchy of Control. To ensure that the asbestos Policy, Management Plan and Procedures are adhered to, suitably experienced and senior personnel within LMH will be nominated to act as a Responsible Person to oversee their effective implementation and review on behalf of the individual Duty Holder Management of Asbestos in Buildings Management Responsibilities. The duties as set out in Regulation 4 of The CAR 2012 Regulations will rest with the person in control of the premises and maintenance activities in the non-domestic premises and to those common areas (non-domestic areas) of properties providing rented or leased accommodation. Liverpool Mutual Homes Page 5 of 16

6 Effectively managing the risks from ACMs identified within properties in the LMH portfolio necessitates specific responsibilities being placed on a number of people. LMH has identified a specific manager, the Senior Maintenance Manager, who is most appropriate to act as the Duty Holder regarding the properties for which they hold responsibility. Effectively, the ultimate responsibility for the compliance regime will be held by the person retaining this post. Appropriate resources and systems will be required to execute this task robustly. In terms of the individual Duty Holders and their property portfolio, the responsibility for the implementation of this Policy, the associated Asbestos Management Plan and the supporting Procedures, will rest with selected members of the senior management team to act as appointed Responsible Persons in the management of ACMs. Those personnel within the LMH senior management structure, and their associated responsibilities in managing ACMs are given below: The Chief Executive of Liverpool Mutual Homes. Although the registered provider has an appointed Duty Holder, the LMH Chief Executive shall be ultimately responsible for ensuring compliance with current legislation and to ensure that LMH fulfils their duties and responsibilities as laid out in this document (and the Asbestos Management Plan). Associated tasks are as follows: (i) Reviewing and endorsing the Policies, Procedures and Guidance document produced for Liverpool Mutual Homes. (ii) Ensure that the Duty Holder understands and has the necessary training and resources to fulfil their duties in this role. (iii) At reasonable intervals, review with the individual Duty Holders and the appointed Responsible Persons, the implementation, observance and performance of this document and of the LMH Asbestos Management Plan. This task may in part be practically implemented via the Compliance Steering Group (CSG) The Appointed Duty Holder for LMH. Liverpool Mutual Homes Page 6 of 16

7 The named manager, acting as the nominated Duty Holder, shall hold responsibility for the implementation of this Poly, the Management Plan, and detailed Procedures for LMH. In addition they shall ensure suitable resources and arrangements are in place for: (i) Setting and endorsing the policy for ACM management and developing procedures for effective implementation. (ii) Ensuring that asbestos surveys are undertaken for all noncommercial properties, the common areas to properties providing rented or leased accommodation and other buildings in which LMH employees, managers and staff work (including HMS and resident caretakers/handy persons). This information must be accessible to the relevant persons, i.e. senior managers and staff of LMH and HMS. (iii) Ensuring that asbestos surveys are undertaken for properties providing domestic accommodation on a priority basis e.g. those timetabled for remedial work shall be scheduled first, together with priority 1 properties, until such time that all properties have been surveyed. (iv) Ensuring the maintenance of the LMH asbestos survey register database. (v) Ensuring that appropriate staff are available, and have been suitably trained, to provide advice and information on ACMs to persons who have an appropriate interest or connection. This shall also include ensuring that suitably trained staff are available to conduct specific inspections on site, whether these staff are employed directly by LMH or from the appointed asbestos consultant. (vi) Providing sufficient resources for staff and management in order for them to execute their duties and responsibilities in accordance with the CAR (vii) Appointing a Responsible Person(s) to undertake local management of ACMs on their behalf, if this duty is not to be personally undertaken. (viii) Ensuring that the Responsible Person(s) understand and have the necessary training and resources to fulfil their duties in this role; (viii) At reasonable intervals, review the implementation of the both this document and of the corporate Asbestos Management Plan Liverpool Mutual Homes Page 7 of 16

8 (minimum 12 monthly). This may be practically undertaken via the Compliance Steering Group (CSG) Senior managers acting as appointed Responsible Persons. The senior managers identified shall ensure suitable arrangements are in place for implementing the procedures contained within this document and the Management Plan. In particular this shall include: (i) Acting as a Responsible Person to undertake local management of ACMs on behalf of the Duty Holder as required. (ii) Ensuring any person undertaking work which may disturb ACMs has first examined and understood the LMH asbestos register system entry and is aware of their responsibility to avoid disturbing the material and, that they have undergone training in accordance with CAR 2012: Regulation 10 Information, Instruction and Training. (iii) Ensuring regular and routine re-inspections of ACMs identified in the LMH asbestos register system are undertaken at a frequency commensurate with the level of risk that these materials present (LMH re-inspection protocol). (iv) Informing and/or seeking advice from the appointed asbestos consultants regarding any amendments considered necessary to the LMH asbestos register system or survey information. (v) Seeking advice from appointed asbestos consultants in situations where the asbestos survey information is not sufficiently detailed or further advice/reassurance is required. (vi) Ensuring that the area adjacent to any ACMs or suspected ACMs is not contaminated, if they have been disturbed or damaged and seeking advice from the appointed asbestos consultants. (vii) Appointing Licensed Contractors (ARCA) for the removal of ACMs as found necessary to individual properties. (viii) To directly oversee, or appoint a competent body to audit asbestos removal works to ensure that they are completed to a satisfactory standard. (ix) To appoint a suitably accredited independent analyst (laboratory) to undertake visual inspections and air testing to ensure that an area is safe for re-occupation upon completion of the works. Air testing may be undertaken during removal works, but it will most likely to be required at Liverpool Mutual Homes Page 8 of 16

9 the end of any such works. Preferably, this role is to be conducted by the appointed/retained asbestos consultants. (x) To ensure that all relevant parties are informed as to the presence of any identified or presumed ACMs within the property for which they are responsible so that they may act accordingly. (xi) To act as contact in the case of any emergency in relation to asbestos for the property for which they are responsible Project Managers, Housing Officers, Housing and Property Staff. Project Managers, Housing Officers, Housing and Property Staff, or any others responsible for organising works in buildings which may affect the fabric of the structure, or equipment within it, and having regard to the possibility of disturbing ACMs. In particular they should: (i) Consider at the initial outset of the project the possibility of disturbing ACMs. (ii) Pass on information in regards to ACMs that are relevant to a property to a person in residence in conjunction with the associated level of risk that they pose (and associated dos and dont s ) Staff, internal works operatives, and Visiting Contractors. (i) Observe and implement the requirements of this Policy, the Asbestos Management Plan and related Procedures, and to assist in their implementation and maintenance. (ii) Co-operate with the Duty Holders and Responsible Persons in fulfilling their duties to manage asbestos. (iii) Visiting contractors, or internal works operatives (HMS), to fully observe their own obligations under current legislation and prevailing guidance Asbestos Surveys and Re-inspections. The first step in managing the risk from ACMs is to undertake a suitable and sufficient assessment as to the presence of ACMs, their location, asbestos fibre content, product type, and condition (i.e. a Material Assessment) together with an assessment of the risk of that material to cause harm based Liverpool Mutual Homes Page 9 of 16

10 on accessibility and the activities carried out in the area around the ACM (i.e. a Priority Assessment). All non-domestic properties (such as shops and offices etc.) and common areas to properties providing rented or leased accommodation inclusive of risers, storage areas etc. are the responsibility of the property Duty Holder and thus any ACMs present must be identified and appropriately managed under CAR The assessment for the presence of ACMs shall typically be in the form of an asbestos survey. The results from these surveys are currently held upon the LMH asbestos register remotely hosted by the retained surveying consultancy undertaking the surveys. The asbestos register/database system shall be accessed by ALL maintenance staff, and contractors prior to the commencement of any maintenance works on a property in order to check for, and to identify the presence of ACMs. The results of any such check shall be taken into consideration when planning and carrying out their works. This will be appropriately recorded for review. Re-inspections of identified ACMs will be carried out at regular intervals as directed by the relevant Responsible Person and in compliance with the LMH re-inspection protocol (as set out in the LMH Management Plan). The frequency of re-inspections shall be determined from the potential risk that a material may pose, represented by the Risk Code assigned to that material which shall be the combined scores from both the Material & Priority assessments. Irrespective, all materials within communal (non-domestic) areas will be reinspected annually. For domestic areas, materials which are assigned the Risk Code of A shall be inspected every 3 months (until removed/encapsulated). Materials which are assigned the Risk Code of B or C shall be inspected annually. Those materials assigned the Risk Codes of D & E shall be re-inspected at least every 5 years. Asbestos surveys and re-inspections shall address the following possible management recommendations: Leave In-Situ (in good condition) and Manage, Seal, Encapsulate (minor damage) Repair and Manage, and Remove (higher risk and in poor condition) and Dispose. Liverpool Mutual Homes Page 10 of 16

11 Prioritisation of Surveys. Initially a percentage of accommodation and communal areas, sufficient to be representative of the various property types, shall have their ACM content assessed. This shall be done to provide an sufficient level of information so that the Duty Holder has confidence to identify all typical ACMs that maybe present within any given property type within their portfolio. It is the ultimate goal of the LMH to have all appropriate properties (i.e. those constructed prior to 2000) to be surveyed by the end of To ensure a structured approach is employed in carrying out asbestos surveys LMH shall initially carry out a desk-top review of all currently nonsurveyed properties. Each property shall then be placed in one of three levels of priority for having a survey conducted: Priority 1, Priority 2 and Priority 3. Those properties within the Priority 1 rating being surveyed first. The criteria that shall be used for assigning the level of priority shall be: age of the property, past knowledge/experience in managing the property, planned maintenance works and the best information available at the time in regards to the presence of ACMs to that type of property Accessing and Maintaining Asbestos Survey Information. At the time of issuing this document the asbestos surveys are held for LMH on the Apec Environmental Ltd, Asbestos Survey Database system (access via secure password at: Maintenance work will only be awarded to/conducted by those contractors held on the LMH list of Approved Contractors or internal works operatives (HMS and resident caretakers/handy persons). Therefore, these companies shall have experience of the requirements of LMH when working on their properties and full knowledge of the system employed by LMH in managing ACMs and in making such information available for their properties. LMH will contact all contractors employed to confirm their understanding of asbestos related regulation/guidance and application of their associated obligations (and training) annually. In the rare event where works are required to be carried out by specialist contractors not included on the approved contractor list, this work will be subject to control via a issue of the asbestos register of ACMs identified or presumed to be present (extracted from the LMH asbestos register system) and by ensuring that the contractor (and their individual operatives employed) has undergone suitable asbestos awareness training within the last 12 months. Liverpool Mutual Homes Page 11 of 16

12 The LMH asbestos register database shall be updated following any asbestos removal works and following completion of re-inspections by those qualified/appointed to undertake them. Where building or engineering works are planned or due to be undertaken in properties, sufficient time must be given to the project to ensure any measures necessary as a result of the presence of asbestos in the property are properly allowed for. Thus, the presence of ACMs shall form part of any project meetings as shall the requirement to incorporate any notification period etc. required by the HSE for the removal of licensable materials from the property. Project managers, planners, designers and architects must therefore, have access to and understand the asbestos survey report and ensure that a report is in place prior to commencing their work. Contractors appointed to undertake remedial work or removal of asbestos containing materials shall be competent and listed on LMH s list of Approved Contractors. They shall hold a Licence issued by the Health and Safety Executive and be members of an appropriate trade association such as: ARCA the Asbestos Contractors Removal Association or TICA the Thermal Insulation Contractors Association. LMH currently employs Apec Environmental Limited as its strategic asbestos consultant who can be contacted to answer any questions and give advice to staff regarding asbestos matters as required Communication LMH is committed to communication with its staff, customers and partners about asbestos and how it is managed in the properties managed by LMH. The two key elements of this will be how we communicate with customers and provide support and training to staff. The implementation of this policy will include both communication and training strategies to deliver on this commitment Monitoring and Review. The relevant Responsible Person shall ensure that the LMH asbestos register is maintained in regards to all asbestos survey and removal Information held or commissioned for LMH properties. The relevant Responsible Person will monitor and review arrangements for asbestos management to premises during visits in the course of their work. Liverpool Mutual Homes Page 12 of 16

13 The relevant Responsible Person shall investigate and review the cause of any incidence (or near-miss ) involving the accidental damage of ACMs. The investigation shall identify the cause, review work procedures and those procedures set out in this document and the Management Plan to prevent a reoccurrence of that, or a similar incident. Such incidents will also be reported to the Asbestos Steering Group for strategic review across all activity within LMH Policy Monitoring and Review. The Policydocument will be reviewed and amended as and when Legislation is revised, or as a minimum every 12 months to ensure that this document and the associated Management Plan and Procedures remain up to date. This review should also appropriately reflect any additional changes required as a result of actual experience, or case studies. Any review of this document shall be undertaken by the Group Chief Executive, the individual Duty Holders, the appointed Responsible Persons and the Asbestos Steering Group in conjunction with the appointed asbestos consultant where appropriate Reference Legislation, Approved Codes of Practice (ACoPs) and Guidance Documentation. The following documents have been identified as being significantly relevant to managing risks from asbestos containing materials, and further information on any document below can be obtained from directly from the HSE Legislation. o The Health and Safety at Work Act o Control of Asbestos Regulations (CAR) o The Management of Health & Safety at Work Regulations o Workplace (Health, Safety and Welfare) Regulations o Hazardous Waste Regulations o Construction (Design and Management) Regulations Approved Codes of Practice (ACoP) (Health & Safety Commission). Liverpool Mutual Homes Page 13 of 16

14 o ACoP L127 Management of asbestos in non-domestic premises. o ACoP L143 - Work with materials containing asbestos. o MDHS100 Surveying, sampling and assessment of asbestos containing materials, holds ACoP status and was superseded in January 2010 by the following document, o HSG 264 Asbestos: The survey guide, holds ACoP status Guidance Documents (Health & Safety Executive). o HSG247 Asbestos: The licensed contractors guide. o HSG248 Asbestos: The analysts guide. o HSG189/2 Working with asbestos cement. o HSG213 Introduction to asbestos essentials (First Edition). o HSG210 Asbestos essentials task manual (Second Edition). o HSG33 Health and safety in roof work (First Edition). (Covers asbestos cement roof demolition). o HSG227 Comprehensive guide to managing asbestos in buildings. o EH51 Respiratory equipment for use in removing asbestos. 6. LINKS TO LMH CORPORATE PLAN This policy links to our Corporate Plan by aiming to: o Operate within an open and accountable environment; o Deliver excellent customer service; o Develop a full knowledge and awareness of customer needs. 7. IMPACT ON LMH FOCUSES Focus on Viability and Strength Maintain high standards of governance and compliance with legal and regulatory requirements; Control and manage all key risks through embedded and effective risk management approaches; Liverpool Mutual Homes Page 14 of 16

15 8. CUSTOMER SERVICE STANDARDS On approvals of the policy, a series of customer service standards will be developed and implemented in line with the detailed procedures and the policy will be updated with this during the initial 6 month review. 9. PERFORMANCE MANAGEMENT On approvals of the policy, the performance management standards and measures will be fully developed and implemented in line with the detailed procedures and the policy will be updated with this during the initial 6 month review. 10. CUSTOMER SATISFACTION Satisfaction with the delivery of any asbestos related works would be measured as part of the overall delivery of works and not directly with the policy. 11. CUSTOMER INVOLVEMENT The policy has been consulted on with customers through the Service Review Group, who were very supportive of the positive approach been taken in the management of asbestos. Following approval of the policy further consultation will be carried out on the related procedures, including our communication strategy. 12. EQUALITY ANALYSIS An equality analysis has been completed and no significant impacts have been identified that would be impacted by this policy. 13. RISK MANAGEMENT A risk assessment has been completed for the policy which highlights the risks associated with not effectively managing asbestos. The implementation of this policy will significantly reduce any asbestos associated risks to the organisation. 14. VALUE FOR MONEY A VFM assessment has been completed for the policy and the approach taken within the policy will ensure a positive external Liverpool Mutual Homes Page 15 of 16

16 assessment. 15. POLICY REVIEW AND IMPROVEMENT FRAMEWORK This policy has been reviewed in line with LMH Policy Review Framework. The next review will be completed in August In line with LMH continuous improvement strategy the policy review will incorporate an assessment of key internal and external influencers to ensure the policy reflects best practice together with all legal and statutory requirements. Liverpool Mutual Homes Page 16 of 16

Policy for the Management of Asbestos in Council Premises (Corporate and Housing)

Policy for the Management of Asbestos in Council Premises (Corporate and Housing) Policy for the Management of Asbestos in Council Premises (Corporate and Housing) Page 1 of 14 1. Policy Statement 1.1 This policy is designed to provide a clear acknowledgement of the responsibilities

More information

HAVEBURY HOUSING PARTNERSHIP

HAVEBURY HOUSING PARTNERSHIP HS028 HAVEBURY HOUSING PARTNERSHIP POLICY ASBESTOS MANAGEMENT Controlling Authority Director of Resources Policy No. HS028 Issue No. 3 Status Final Date November 2013 Review Date: November 2016 Equality

More information

Control of Asbestos Policy

Control of Asbestos Policy Control of Asbestos Policy Version Number: V1D Name of originator/author: Estates Manager 0161 277 1235 Name of responsible committee: Estates and Facilities Committee Name of executive lead: Director

More information

The Management of Asbestos containing Materials

The Management of Asbestos containing Materials The Management of Asbestos containing Materials Status Owner Approval by University Court Draft Head of Estates and Building 1 Purpose... 1 2 Scope... 3 3 Principles... 4 4 Procedure... 5 5 Accountabilities...

More information

Asbestos Policy ASBESTOS POLICY. Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy

Asbestos Policy ASBESTOS POLICY. Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy ASBESTOS POLICY Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy This is a controlled document. It should not be altered in any way without the express permission of the author or their representative.

More information

Asbestos Management Policy

Asbestos Management Policy Central Bedfordshire Council www.centralbedfordshire.gov.uk Asbestos Management Policy The Housing Service Version 1.0 Directorate Social Care Health and Housing Service Housing Service Approved by Director

More information

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN Revision Date Nature of Revision Prepared by Approved by 0.2 Jul 2013 Initial draft for comment Jon Fahie 0.3 Sep

More information

ROYAL HOLLOWAY, UNIVERSITY OF LONDON

ROYAL HOLLOWAY, UNIVERSITY OF LONDON ROYAL HOLLOWAY, UNIVERSITY OF LONDON ASBESTOS MANAGEMENT POLICY (Version 2) This Policy defines the College s arrangements for the management of asbestos and the measures to be taken for the protection

More information

Policy for the Management of Asbestos in the Workplace

Policy for the Management of Asbestos in the Workplace Southwark Council Management of Asbestos in the Workplace November 2011 Page 1 of 15 CONTENTS 1. INTRODUCTION... 3 2. POLICY STATEMENT... 3 3. ASBESTOS RISK CLASSIFICATION SCHEME... 5 4. SAMPLING OF ASBESTOS

More information

ASBESTOS MANAGEMENT POLICY

ASBESTOS MANAGEMENT POLICY ASBESTOS MANAGEMENT POLICY Published : 4th Revision December 2014 1 Table of Contents INTRODUCTION... 3 DUTY TO MANAGE ASBESTOS... 3 DUTIES OF CAMPUS SERVICES... 3 1.0 POLICY OBJECTIVES... 5 2.0 RESPONSIBILITIES...

More information

Asbestos Policy Lead officer: Date agreed: Review date: Working together to deliver quality homes and a better environment for all

Asbestos Policy   Lead officer: Date agreed: Review date: Working together to deliver quality homes and a better environment for all Asbestos Policy Lead officer: Jeff Scott Date agreed: May 2013 Review date: May 2016 Working together to deliver quality homes and a better environment for all Page 1 of 11 Contents Page 1 Introduction

More information

ASBESTOS MANAGEMENT PLAN. Borough of Poole Transportation Services, Property Management, Civic Centre, Poole, Dorset BH15 2RU

ASBESTOS MANAGEMENT PLAN. Borough of Poole Transportation Services, Property Management, Civic Centre, Poole, Dorset BH15 2RU ASBESTOS MANAGEMENT PLAN Borough of Poole Transportation Services, Property Management, Civic Centre, Poole, Dorset BH15 2RU CONTENTS 1. INTRODUCTION 2. HOW DOES THE BOROUGH OF POOLE MANAGE ITS ASBESTOS

More information

ASBESTOS MANAGEMENT PLAN

ASBESTOS MANAGEMENT PLAN ASBESTOS MANAGEMENT PLAN PREPARED BY: Scott Gregory: Estates - Property Services DATE: 18/04/2014 STATUS: Draft ISSUE: 2014 (02) September 2014 NEXT REVISION DATE: April 2014 Contents 1.0 Introduction

More information

Asbestos Policy. Planning, Performance Management and Support Services. Legacy Causeway Asbestos Policy (Ref: CHSST/04/211)

Asbestos Policy. Planning, Performance Management and Support Services. Legacy Causeway Asbestos Policy (Ref: CHSST/04/211) Asbestos Policy Reference Number: NHSCT/09/192 Responsible Directorate: Planning, Performance Management and Support Services Replaces (if appropriate): Legacy Causeway Asbestos Policy (Ref: CHSST/04/211)

More information

Asbestos Management Plan

Asbestos Management Plan Health and Safety Services Asbestos Management Plan Policy, Organisation and Arrangements Sean Callaghan Issue number 3 April 2014 Issue Date Nature of revision Prepared by Approved by 2 April 2013 First

More information

Asbestos-Containing Materials in Buildings: Asbestos Management Plan for LBC Housing

Asbestos-Containing Materials in Buildings: Asbestos Management Plan for LBC Housing LUTON BOROUGH COUNCIL, BUILDING AND TECHNICAL SERVICES CENTRAL DEPOT, KINGSWAY, LUTON LU4 8AU. Asbestos-Containing Materials in Buildings: Asbestos Management Plan for LBC Housing In accordance with the

More information

ASBESTOS POLICY AND PROCEDURES

ASBESTOS POLICY AND PROCEDURES ASBESTOS POLICY AND PROCEDURES a CORPORATE RESOURCES DEPARTMENT PROPERTY SERVICES POLICY FOR THE MANAGEMENT OF ASBESTOS IN BUILDINGS OWNED AND/OR OPERATED BY LEICESTERSHIRE COUNTY COUNCIL LCC ASB/001 ISSUE

More information

Author G Morton July 2015. Newcastle University Asbestos Management Plan 2015

Author G Morton July 2015. Newcastle University Asbestos Management Plan 2015 Newcastle University Asbestos Management Plan 2015 1 Contents 1.0 Introduction 2.0 Asbestos Management Duty Holder Responsibilities 2.1 Asbestos Manager (Head of Maintenance) 2.2 University Asbestos Survey

More information

ASBESTOS CONTAINING MATERIALS POLICY

ASBESTOS CONTAINING MATERIALS POLICY ASBESTOS CONTAINING MATERIALS POLICY Document Control Version 3 Ratified by Risk Management Sub Group Date Ratified 19 December 2012 Name of Originator/Author Head of Estates and Facilities Name of Responsible

More information

ASBESTOS MANAGEMENT POLICY AND GUIDANCE

ASBESTOS MANAGEMENT POLICY AND GUIDANCE ASBESTOS MANAGEMENT POLICY AND GUIDANCE Belvoir High School Policy and Procedures Date approved 08/10/2013 Signed by Chair of Governors (Mr B Lovegrove Date approved 08/10/2013 Signed by Executive Principal

More information

Asbestos Policy. Ymddiriedolaeth GIG Gwasanaethau Ambiwlans Cymru Welsh Ambulance Service (NHS) Trust. November 2007. All Staff.

Asbestos Policy. Ymddiriedolaeth GIG Gwasanaethau Ambiwlans Cymru Welsh Ambulance Service (NHS) Trust. November 2007. All Staff. Appendix 1 Ymddiriedolaeth GIG Gwasanaethau Ambiwlans Cymru Welsh Ambulance Service (NHS) Trust Asbestos Policy Approved by Date Review Date Target Audience Trust Board November 2007 November 2008 All

More information

MANAGEMENT OF ASBESTOS POLICY

MANAGEMENT OF ASBESTOS POLICY MANAGEMENT OF ASBESTOS POLICY The application of this policy and procedure ensures that no employee receives less favourable treatment on grounds of sex, trans-gender status, sexual orientation, religion

More information

Asbestos Management Plan

Asbestos Management Plan Harlow Council Asbestos Management Plan Version 4 Scope: This management plan applies to the management of all asbestos containing materials to properties under the ownership/management of Harlow Council

More information

Policy for the Management of Asbestos

Policy for the Management of Asbestos CARDIFF AND VALE NHS TRUST YMDDIRIEDOLAETH GIG CAERDYDD A R FRO Policy for the Management of Asbestos Author Keith Jones Estate Controls Assurance Officer / Environmental Management Co-ordinator Policy

More information

POLICY Contents. 1.0 Introduction Statement

POLICY Contents. 1.0 Introduction Statement POLICY Contents 1.0 Introduction Statement 2.0 Legal Responsibility 2.1 Asbestos Management Hierarchy 2.2 Duty Holders Responsibility 2.3 Employees Responsibility 3.0 Asbestos Management Procedure 4.0

More information

Asbestos Management Procedure

Asbestos Management Procedure Asbestos Management Procedure Reference: HS/021/2010 Version No: 2.0 Issue Date: July 2010 Document Control Document Ref: HS/021/2010 Date Created: Jan 2010 Version: 2 Date Modified: Revision due December

More information

Policy on the Management of Asbestos

Policy on the Management of Asbestos WISHAW AND DISTRICT HOUSING ASSOCIATION Policy on the Management of Asbestos As with all the Association s policies and procedures, this document, where required, may be able to be translated into other

More information

Asbestos Management Policy (Version 3)

Asbestos Management Policy (Version 3) Asbestos Management Policy (Version 3) Contents Page Introduction 3 College Policy Statement for Asbestos Management 3 Objectives (of this Policy and Procedure) 3 Application of Policy 4 Licensed Asbestos

More information

Asbestos Management Policy

Asbestos Management Policy Asbestos Management Policy Originator: Approval date: Policy and Strategy Team Sovini Board PCHA Board OVH Board/EMT 3 rd December 2012 22 nd November 2012 25 th September 2012 Review date: December 2013

More information

Policy 7 Management of Asbestos

Policy 7 Management of Asbestos Policy 7 Management of Asbestos 1.0 Introduction Development & Infrastructure recognise both the need to protect their employees from the risks associated with encountering asbestos and the potential for

More information

Asbestos - Frequently Asked Questions

Asbestos - Frequently Asked Questions Asbestos - Frequently Asked Questions 1. What is asbestos? Asbestos is the name given to a group of fibrous minerals which occur naturally in the earth. These are grouped into two mineral types known as

More information

STRATEGIC PLANNING & PLACE BUILDING CONTRACT DIRECTIVE

STRATEGIC PLANNING & PLACE BUILDING CONTRACT DIRECTIVE BCD.26 STRATEGIC PLANNING & PLACE BUILDING CONTRACT DIRECTIVE DATE: March 2015 Copyright Reserved TESTING, ASSESSMENT AND WORK WITH ASBESTOS CONTAINING MATERIALS (ACM S) REFERENCE This Directive deals

More information

Asbestos at work guide

Asbestos at work guide Asbestos at work guide Contents Introduction.... 2 Frequently asked questions.... 4 The Control of Asbestos Regulations 2006... 5 Types of asbestos survey.... 7 1 Introduction This document provides a

More information

REVISION 9 January 2015 ASBESTOS MANAGEMENT PLAN

REVISION 9 January 2015 ASBESTOS MANAGEMENT PLAN REVISION 9 January 2015 ASBESTOS MANAGEMENT PLAN ULSTER UNIVERSITY - ASBESTOS MANAGEMENT PLAN CONTENTS PAGE 1. Introduction 4 2. Background 4 2.1 Types of Asbestos 2.2 Hazards of Asbestos dust 2.3 Use

More information

An Introduction to Asbestos, Legislation and Licensed

An Introduction to Asbestos, Legislation and Licensed An Introduction to Asbestos, Legislation and Licensed Contractor Selection MARK W ROBERTS Director Kitsons Environmental Europe Ltd Chair ARCA CHRIS BISHOP BA, C.Chem MRSC, MCQI CQP, CCP (Asbestos) Head

More information

Review Date 01/09/2015 Director of Estates and Facilities Expiry Date 11/09/2016 Withdrawn Date

Review Date 01/09/2015 Director of Estates and Facilities Expiry Date 11/09/2016 Withdrawn Date Policy No: RM78 Version: 1.0 Name of Policy: Corporate Asbestos Management Policy, Organisational Arrangements and Procedures Policy Effective From: 24/10/2013 Date Ratified 12/09/2013 Ratified Health

More information

Asbestos Safety Management Standard Issue 8 October 2008. www.walsall.org.uk/healthandsafety

Asbestos Safety Management Standard Issue 8 October 2008. www.walsall.org.uk/healthandsafety www.walsall.org.uk/healthandsafety Asbestos Safety Management Standard Issue 8 October 2008 Page 1 of 7 / WMBC/SMS Asb/008/01 UNCONTROLLED WHEN PRINTED Please contact us if you have any difficulty reading

More information

Asbestos Management Consultants COMPANY PROFILE Tersus Consultancy Limited

Asbestos Management Consultants COMPANY PROFILE Tersus Consultancy Limited Asbestos Management Consultants COMPANY PROFILE Tersus Consultancy Limited www.tersusgroup.co.uk Asbestos has been used in the UK construction industry since around 1890. Once hailed as the wonder building

More information

SAFETY RESPONSIBILITIES AND ARRANGEMENTS IN RESPECT OF ASBESTOS MANAGEMENT (ASBESTOS MANAGEMENT PLAN)

SAFETY RESPONSIBILITIES AND ARRANGEMENTS IN RESPECT OF ASBESTOS MANAGEMENT (ASBESTOS MANAGEMENT PLAN) KING S COLLEGE LONDON Health, Safety & Environmental Protection Office SAFETY RESPONSIBILITIES AND ARRANGEMENTS IN RESPECT OF ASBESTOS MANAGEMENT (ASBESTOS MANAGEMENT PLAN) Issue Date: May 2012 Issue Number:

More information

ASBESTOS POLICY MANAGEMENT PLAN

ASBESTOS POLICY MANAGEMENT PLAN ASBESTOS POLICY & MANAGEMENT PLAN HS20 Version V2 Approved by: Health, Safety and Security Committee Date approved: March 2011 Ratified by: Hospital Executive Committee Date ratified 24 th April 2012 Document

More information

Bield Housing and Care POLICY, PROCEDURES. and MANAGEMENT PLAN ASBESTOS CONTAINING MATERIALS

Bield Housing and Care POLICY, PROCEDURES. and MANAGEMENT PLAN ASBESTOS CONTAINING MATERIALS Bield Housing and Care POLICY, PROCEDURES and MANAGEMENT PLAN for ASBESTOS CONTAINING MATERIALS Approved on: 24 April 2014 By Health & Safety Management Group Implementation date: 1 June 2014 Review Date

More information

Asbestos Policy and Management Plan 2013-16

Asbestos Policy and Management Plan 2013-16 Policy reviewed by Thomas Eggar Solicitors, January 2013 Equality Assessment completed January 2013 Policy reviewed by the Health and Safety Committee, February 2013 Policy reviewed and adopted by the

More information

Accommodation Officers Information Booklet. Asbestos The Asbestos Abatement Programme and the Asbestos Management Policy

Accommodation Officers Information Booklet. Asbestos The Asbestos Abatement Programme and the Asbestos Management Policy Accommodation Officers Information Booklet Asbestos The Asbestos Abatement Programme and the Asbestos Management Policy This Guideline has been produced solely for use by State Authorities that come within

More information

MAIDENHEAD AND DISTRICT HOUSING ASSOCIATION TITLE: PAGE:

MAIDENHEAD AND DISTRICT HOUSING ASSOCIATION TITLE: PAGE: TITLE: PAGE: 1 OF 23 Maidenhead and District Housing Association Asbestos Policy and Management Page 1 of 23 TITLE: PAGE: 2 OF 23 FOREWORD This document details the system for the management of health

More information

ASBESTOS MANAGEMENT POLICY

ASBESTOS MANAGEMENT POLICY Community Health Service ASBESTOS MANAGEMENT POLICY UNCONTROLLED COPY ONCE PRINTED. For CURRENT version check NHS Leicester City or LCCHS INTRANET. Reference Title: HS004 Asbestos Management Policy Version

More information

Asbestos Surveys and Removals Progress Report Financial Year 07/08

Asbestos Surveys and Removals Progress Report Financial Year 07/08 Report title Asbestos Surveys and Removals Progress Report Financial Year 07/08 Agenda item 8 Meeting Date Finance, Procurement & Property Committee 16 June 2008 Report by Document Number (12/05/2008)

More information

Asbestos Management Plan

Asbestos Management Plan Asbestos Management Plan This procedural document was previously incorporated within the Asbestos Management Policy and Procedures CORP/HSFS 10 v.3 Did you print this document yourself? The Trust discourages

More information

Beech Housing Association Asbestos Management Policy

Beech Housing Association Asbestos Management Policy Beech Housing Association Asbestos Management Policy Policy Statement The aim of this document is to define a policy for the control and management of the risk of exposure to asbestos within the dwellings

More information

Asbestos Management Plan

Asbestos Management Plan Safety Standard Asbestos Management Plan Version 8.0 May 2015 Page 1 of 60 Engineering Maintenance & Infrastructure Safety Standard Asbestos Management UNIVERSITY COLLEGE LONDON STANDARD ASBESTOS MANAGEMENT

More information

ASBESTOS POLICY AND MANAGEMENT PLAN

ASBESTOS POLICY AND MANAGEMENT PLAN ASBESTOS POLICY AND MANAGEMENT PLAN 1. INTRODUCTION 1.1. The Control of Asbestos at Work Regulations 2006 requires employers to prevent the exposure of their employees to asbestos, or where this is not

More information

Date of issue: January 2014. Date of next review: February 2016. Author: V Thornton. Service area applies to: Operations. Link to the 5 Pledges: Yes

Date of issue: January 2014. Date of next review: February 2016. Author: V Thornton. Service area applies to: Operations. Link to the 5 Pledges: Yes Title: Asbestos Policy 2013 Date of issue: January 2014 Date of next review: February 2016 Author: V Thornton Service area applies to: Operations Link to the 5 Pledges: Yes Approved by: Date approved:

More information

Asbestos Management Plan. Policy. The whole of the Trust. Intranet. The Trust Board/Executive Management Team

Asbestos Management Plan. Policy. The whole of the Trust. Intranet. The Trust Board/Executive Management Team Document name: Document type: What does this policy replace? Staff group to whom it applies: Distribution: Asbestos Management Plan Policy Update of previous Procedure for the Safe Management of Asbestos

More information

Asbestos Management Plan. April 2011

Asbestos Management Plan. April 2011 Reviewed by: Approved by: Health & Safety Management Committee Management Board -. R3. Part 1: Introduction Part 2: Policy Part 3: Organisation and Responsibilities Part 4: Procedures Appendices: 1 Management

More information

Asbestos Policy & Procedure

Asbestos Policy & Procedure Asbestos Policy & Procedure 1. Purpose & Introduction This policy and procedure sets out Octavia s commitment and approach to ensuring, so far as reasonably practicable, that residents, contractors and

More information

Report to Cabinet Item 25 June 2014

Report to Cabinet Item 25 June 2014 Report to Cabinet Item 25 June 2014 Report of Deputy Chief executive (operations) 12 Subject Asbestos Management Policy Purpose To consider the council s Asbestos Management Policy. Recommendation To approve

More information

Asbestos Policy. Policy. The whole of the Trust. Intranet

Asbestos Policy. Policy. The whole of the Trust. Intranet Document name: Document type: What does this policy replace? Staff group to whom it applies: Distribution: Asbestos Policy Policy Update of previous Procedure for the Safe Management of Asbestos guidance

More information

Derby City Council. Asbestos Management Plan

Derby City Council. Asbestos Management Plan Derby City Council Asbestos Management Plan April 2014 Page 1 of 44 Index of Contents 1.1 Introduction 3 1.2 Glossary of Terms 4 2.0 Action Plan 2.1 Scope and purpose 6 2.2 Competent persons who they are

More information

RSPH Level 3 Certificate in Asbestos Project Management. February 2013. 10 Guided Learning Hours 2 Prior Learning Hours

RSPH Level 3 Certificate in Asbestos Project Management. February 2013. 10 Guided Learning Hours 2 Prior Learning Hours RSPH Level 3 Certificate in Asbestos Project Management February 2013 10 Guided Learning Hours 2 Prior Learning Hours Description The Control of Asbestos Regulations impose duties on every person who has,

More information

Policy for the Management of Asbestos in Buildings

Policy for the Management of Asbestos in Buildings in Buildings Health and Safety Services 1 A1. Introduction If asbestos fibres enter the lungs they can cause cancer or incurable disease. Consequently the University is committed to ensure that all reasonably

More information

SMS0045 Construction Health and Safety Policy and Procedures

SMS0045 Construction Health and Safety Policy and Procedures SMS0045 Construction Health and Safety Policy and Procedures March 2015 Version 8 Please note that for projects utilising a CDM Co-ordinator under the transitional arrangements of CDM 2015 (between 6 April

More information

Asbestos Management & Abatement

Asbestos Management & Abatement Asbestos Management & Abatement Latest revised date: October 29, 2012 Page 1 of 18 1.0 LEGAL & LEGISLATIVE REQUIREMENTS This standard provides guidance to meeting the minimum requirements of the Act &

More information

Asbestos Survey Report

Asbestos Survey Report 0340 Asbestos Survey Report Sunnyside Court Avondale Road Southport PR9 0NU Client Contact: Gary Rostron The Regenda Group Regenda House Enterprise Business Park Northgate Close Horwich, Bolton BL6 6PQ

More information

Asbestos Management Plan. Policy Owner: Head of Repairs Policy Author: Alan Assheton Date adopted: Review Date: Purpose

Asbestos Management Plan. Policy Owner: Head of Repairs Policy Author: Alan Assheton Date adopted: Review Date: Purpose Asbestos Management Plan Policy Owner: Head of Repairs Policy Author: Alan Assheton Date adopted: Review Date: Purpose The Health and Safety at Work etc Act 1974 places a duty on employers to take all

More information

ASBESTOS MATERIALS IN SCHOOLS

ASBESTOS MATERIALS IN SCHOOLS CODE OF PRACTICE FOR MANAGEMENT OF ASBESTOS MATERIALS IN SCHOOLS CONTENTS 1. Introduction 1.1 Scope 1.2 The OPW Health and Safety Unit 2 Background 2.1 General Information 2.2 Main Risks 2.3 Main Risk

More information

Approved Code of Practice. Management of Exposure to Asbestos in Workplace Buildings and Structures. Health and Safety at Work (Jersey) Law, 1989

Approved Code of Practice. Management of Exposure to Asbestos in Workplace Buildings and Structures. Health and Safety at Work (Jersey) Law, 1989 Approved Code of Practice Management of Exposure to Asbestos in Workplace Buildings and Structures Health and Safety at Work (Jersey) Law, 1989 ACoP 8 Revised 2015 Cover: Magnified image of asbestos fibres,

More information

The Management of Asbestos. County Council Occupied Premises

The Management of Asbestos. County Council Occupied Premises The Management of Asbestos in County Council Occupied Premises Policy, Strategy and Management Procedures Corporate Building Services November 2005 Policy, Strategy, and Implementation Plan for the Management

More information

UNIVERSITY HOSPITALS OF LEICESTER NHS TRUST POLICY FOR THE MANAGEMENT OF ASBESTOS

UNIVERSITY HOSPITALS OF LEICESTER NHS TRUST POLICY FOR THE MANAGEMENT OF ASBESTOS UNIVERSITY HOSPITALS OF LEICESTER NHS TRUST POLICY FOR THE MANAGEMENT OF ASBESTOS APPROVED BY: UHL H&S Committee and UHL H&S Committee TRUST REF: B27/2005 DATE APPROVED: March 2008 ORIGINATOR: Glyn Lambley

More information

Frequently Asked Questions. What is asbestos? 2. How is asbestos harmful? 2. What illnesses does asbestos cause? 3

Frequently Asked Questions. What is asbestos? 2. How is asbestos harmful? 2. What illnesses does asbestos cause? 3 Duty to Manage Asbestos in Non-Domestic Premises Frequently Asked Questions Page What is asbestos? 2 How is asbestos harmful? 2 What illnesses does asbestos cause? 3 How many people die as a result of

More information

Version: Date adopted: publication: Review date: September 2015. Expiry date: March 2016. Target audience: All staff

Version: Date adopted: publication: Review date: September 2015. Expiry date: March 2016. Target audience: All staff Asbestos Policy The Asbestos Policy provides guidance to ensure that all appropriate steps are taken to comply with the duty to manage asbestos and comply with asbestos related legislation, codes of practice

More information

H2 Opening Statement Asbestos

H2 Opening Statement Asbestos H2 Opening Statement Asbestos Every year there are thousands of asbestos related deaths. Asbestos fibres accumulate in the lungs, therefore several diseases can occur, among these are two main types of

More information

Management of Asbestos. Darren Arkins Senior Inspector Occupational Hygiene Unit Chemical Business Services Division

Management of Asbestos. Darren Arkins Senior Inspector Occupational Hygiene Unit Chemical Business Services Division Management of Asbestos Darren Arkins Senior Inspector Occupational Hygiene Unit Chemical Business Services Division Getting it Wrong! Asbestos What is it? With the Naked Eye! Naturally occurring silicates

More information

The asbestos crisis Why Britain needs an eradication law

The asbestos crisis Why Britain needs an eradication law Why Britain needs an eradication law All-Party Parliamentary Group on Occupational Safety and Health The All-Party Parliamentary Group on Occupational Safety and Health believes that the time has come

More information

The British Occupational Hygiene Society Faculty of Occupational Hygiene INTERNATIONAL MODULE SYLLABUS W504 ASBESTOS AND OTHER FIBRES

The British Occupational Hygiene Society Faculty of Occupational Hygiene INTERNATIONAL MODULE SYLLABUS W504 ASBESTOS AND OTHER FIBRES The British Occupational Hygiene Society Faculty of Occupational Hygiene INTERNATIONAL MODULE SYLLABUS W504 ASBESTOS AND OTHER FIBRES Aim: Learning Outcomes: This module enhances the student s knowledge

More information

P404 - Air Sampling of Asbestos and MMMF and Requirements for a Certificate of Reoccupation Following Clearance of Asbestos

P404 - Air Sampling of Asbestos and MMMF and Requirements for a Certificate of Reoccupation Following Clearance of Asbestos Proficiency Module Syllabus P404 - Air Sampling of Asbestos and MMMF and Requirements for a Certificate of Reoccupation Following Clearance of Asbestos Aim To provide candidates with theoretical and practical

More information

HEALTH & SAFETY POLICY

HEALTH & SAFETY POLICY HEALTH & SAFETY POLICY 1. STATEMENT OF INTENT & POLICY OBJECTIVES The Council, as the governing body of the School, recognises and accepts the responsibilities placed on it as 'Employer' by the Health

More information

BEDFORD DESIGN GROUP REPORT NUMBER 61892 ASBESTOS SURVEY AT: ALL HALLOWS CAR PARK GREENHILL BEDFORD

BEDFORD DESIGN GROUP REPORT NUMBER 61892 ASBESTOS SURVEY AT: ALL HALLOWS CAR PARK GREENHILL BEDFORD BEDFORD DESIGN GROUP REPORT NUMBER ASBESTOS SURVEY AT: ALL HALLOWS CAR PARK GREENHILL BEDFORD CARRIED OUT BY: VINTEC LABORATORIES LTD SURVEY DATE: 08-01-2009 PREPARED BY: JAMES BROTHERTON CHECKED BY: ANDREW

More information

Northwards Housing. Asbestos Management Plan. October 2014

Northwards Housing. Asbestos Management Plan. October 2014 rthwards Housing Asbestos Management Plan October 2014 Last Review October 2014 Reviewed by Simon Roffey Issued by Larry Patrick Next Review Due October 2015 1 Table of Content Section Content 1.0 Purpose

More information

ASBESTOS POLICY. Version: Asbestos Policy v 1.2. Date ratified: 22 nd March 2013 Approving Committee/Group (Date)

ASBESTOS POLICY. Version: Asbestos Policy v 1.2. Date ratified: 22 nd March 2013 Approving Committee/Group (Date) ASBESTOS POLICY Version: Asbestos Policy v 1.2 Ratified by: Policy Committee Date ratified: 22 nd March 2013 Approving Committee/Group (Date) Date Approved by Medicines Management Committee: (NB: All Procedural

More information

Policy and Procedures For the Management of Asbestos

Policy and Procedures For the Management of Asbestos Policy and Procedures For the Management of Asbestos Version: 1.0 Ratified by: Health and Safety Committee Date ratified: 9 March 2009 Name of originator/author: NIFES Date issued: 20 April 2009 Review

More information

Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation

Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation Page 1 of 11 Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation This work is copyright. It may be reproduced in whole or in part for study or training purposes

More information

Health and Safety Executive ASBESTOS Approved Code of Practice Management of Exposure to Asbestos in Workplace Buildings and Structures

Health and Safety Executive ASBESTOS Approved Code of Practice Management of Exposure to Asbestos in Workplace Buildings and Structures Health and Safety Executive ASBESTOS Approved Code of Practice Management of Exposure to Asbestos in Workplace Buildings and Structures The Health and Safety at Work (General) (Guernsey) Ordinance, 1987

More information

UKATA. Certificate in Asbestos Awareness. Category A

UKATA. Certificate in Asbestos Awareness. Category A UKATA Certificate in Asbestos Awareness Category A Page 1 of 7 Introduction This syllabus sets out the guidance issued by the United Kingdom Asbestos Awareness Association (UKATA) for the provision of

More information

ADVICE to safety representatives

ADVICE to safety representatives UNITE LEGAL SERVICES - TRUST YOUR UNION ADVICE to safety representatives Unite has launched a new asbestos campaign aiming to: Raise members awareness of asbestos hazards at work Provide advice to Unite

More information

ASBESTOS MANAGEMENT PROGRAM

ASBESTOS MANAGEMENT PROGRAM ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate

More information

ASBESTOS MANAGEMENT INTRODUCTION

ASBESTOS MANAGEMENT INTRODUCTION SECTION: II. General Hygiene/ Safety Chapter: 7. Asbestos Management Revision Date: 12/05/2013 Review Date: ASBESTOS MANAGEMENT INTRODUCTION PURPOSE This policy has been developed to ensure that hazardous

More information

Asbestos in your home

Asbestos in your home Asbestos in your home Is it a problem? BVT RESIDENT A P P R O V E D This leaflet aims to address any concerns that you may have regarding asbestos and where it may be found in your home. It will cover

More information

Asbestos Awareness Syllabus (Category A)

Asbestos Awareness Syllabus (Category A) Asbestos Awareness Syllabus (Category A) Introduction This syllabus sets out the guidance issued by the UK Asbestos Training Association (UKATA) for the provision of asbestos awareness training as contained

More information

DUTIES and GUIDANCE. for. BOARDS of MANAGEMENT. DEALING with ASBESTOS CONTAINING MATERIALS. before, during & after

DUTIES and GUIDANCE. for. BOARDS of MANAGEMENT. DEALING with ASBESTOS CONTAINING MATERIALS. before, during & after DUTIES and GUIDANCE for BOARDS of MANAGEMENT on DEALING with ASBESTOS CONTAINING MATERIALS before, during & after SCHOOL REFURBISHMENT WORKS, DEMOLITIONS AND BUILDING WORKS PROJECTS CONTENTS CONTENTS...2

More information

Asbestos Awareness Training Requirements

Asbestos Awareness Training Requirements Asbestos Awareness Training Requirements Guidance Note 3 Jan 14 1 Introduction This Guidance Note gives practical information about asbestos awareness training. Sample wording for a tool box talk briefing

More information

The asbestos crisis. Why Britain needs an eradication Law. Background. Levels of mortality

The asbestos crisis. Why Britain needs an eradication Law. Background. Levels of mortality The asbestos crisis. Why Britain needs an eradication Law. The All-Party Parliamentary Group on Occupational Safety and Health believes that the time has come to put in place regulations requiring the

More information

Re Inspection of Asbestos Containing Materials

Re Inspection of Asbestos Containing Materials Environmental www.bodycote.com www.healthsciences.bodycote.com Re Inspection of Asbestos Containing s Frog Firle Alfriston Polegate East Sussex BN26 5TT Report Number: W07-1749 Page 1 of 11 Client YHA

More information

Administrative Procedure. Asbestos

Administrative Procedure. Asbestos Administrative Procedure FT107 Asbestos Board Received: January 30, 2012 Review Date: February 2015 Accountability: 1. Frequency of Reports As needed 2. Severity Threshold As needed (eg. Ministry of Labour

More information

Asbestos Management and Control Policy for Government Buildings

Asbestos Management and Control Policy for Government Buildings Asbestos Management and Control Policy for Government Buildings The Queensland Government s policy for the management and control of asbestos containing material in government buildings is one of proactive

More information

ASBESTOS MANAGEMENT PROGRAM

ASBESTOS MANAGEMENT PROGRAM ASBESTOS MANAGEMENT PROGRAM September 2015 Asbestos Management Program Table of Contents I. Purpose II. III. IV. Definitions Identification of Asbestos Asbestos Sampling V. Notification and Labeling VI.

More information

Policy on Asbestos Safety

Policy on Asbestos Safety Policy on Asbestos Safety November Index. Aims and Objectives. Policy Reference. Asbestos Safety Policy Statement 4. Responsibilities 5. Asbestos Register 6. Asbestos Survey 7. Staff Asbestos Training

More information

AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS

AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS Conducted By GASKIN CONSTRUCTION SERVICES PTY LTD TABLE OF CONTENTS SECTIONS Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7

More information

Plymouth City Council Asbestos Policy

Plymouth City Council Asbestos Policy Plymouth City Council Asbestos Policy Policy, Arrangements and Procedures for Asbestos Management in Buildings, Structures and Assets Owned or Occupied by Plymouth City Council. May 2008: Version 1.1-1

More information

Asbestos: Notifiable Non-Licensed Work. A Minor Change or a Significant Challenge

Asbestos: Notifiable Non-Licensed Work. A Minor Change or a Significant Challenge Asbestos: Notifiable Non-Licensed Work A Minor Change or a Significant Challenge John Evans B.Sc., CMIOSH, FRSPH, MIOA, PGCE Technical Director Santia Asbestos Management Limited The Control of Asbestos

More information

ASBESTOS MANAGEMENT SURVEY REPORT

ASBESTOS MANAGEMENT SURVEY REPORT ASBESTOS MANAGEMENT SURVEY REPORT for THE MORAY COUNCIL of B3239-1140002 Produced by ESG Asbestos Ltd, a wholly owned subsidiary of ESG Bretby Business Park, Ashby Road, Bretby, Burton upon Trent, Staffordshire

More information

Frequently asked questions

Frequently asked questions Frequently asked questions Asbestos investigation An investigation into asbestos-related health concerns has found that there is no evidence of elevated asbestos-related health risk to residents who have

More information