1 ASBESTOS MANAGEMENT PLAN PREPARED BY: Scott Gregory: Estates - Property Services DATE: 18/04/2014 STATUS: Draft ISSUE: 2014 (02) September 2014 NEXT REVISION DATE: April 2014

2 Contents 1.0 Introduction Page Process Page Programme for Enhanced Compliance Page Recording ACM s and Managing Risk Page Responsibilities Page Training Page Procedures for Project and Maintenance Works Page General and Emergency Control Procedures Page Monitor and Review Page Emergency Services Page Approved Contractors and Consultants Page 11 Appendix A Asbestos Management Flow Chart Page 12 Appendix B Statement on Asbestos - Text for Staff and Students Page 14 Appendix C Out of Hours Call Out Statement on Asbestos Page 16 Appendix D Asbestos Pro-Forma STATEMENT ON ASBESTOS Page 18

3 1.0 INTRODUCTION Under the Control of Asbestos Regulations 2012 the University has a legal duty to manage asbestos in non-domestic premises. For the purposes of managing asbestos around the University, these regulations shall be deemed to apply to all premises controlled by the University, and shall include student bedrooms and all other areas within Student Halls of Residence. This document sets out the University management plan and procedures for managing asbestos. It is to be read in conjunction with the following documents: Asbestos Management Strategy Managing Asbestos Removal Contractors MMU Health and Safety Policy MMU Health and Safety Manual The University Asbestos Management Procedures shall meet the requirements laid down in the Health and Safety at Work Act 1974, and the Control of Asbestos Regulations The overall aim is that all ACM s, through inspections, re-inspections, remedial or removal works are effectively managed and risks reduced (Asbestos Management Flow Chart Appendix A). 2.0 PROCESS The University has undertaken the following: Taken reasonable steps to identify materials in premises likely to contain asbestos and to check their condition Presumed that materials contain asbestos, unless strong evidence is available they do not Made a written record of the location and the condition of the asbestos and presumed asbestos-containing materials and continue to keep the records up-to-date Assessed the risk of the likelihood of anyone being exposed to these Prepared an action plan to manage that risk and put it into effect so that: - Any material known or presumed to contain asbestos is kept in a good state of repair - Any material that contains or is presumed to contain asbestos is, because of the risks associated with its location or condition, repaired or if necessary removed. - Information on the location and condition of asbestos material is available to anyone potentially at risk. - Incidents involving the release or suspected release of asbestos fibres shall initiate immediate and effective control measures and procedures to contain and manage the risk. The University shall undertake the following: Presume that materials contain asbestos; unless strong evidence is available they do not Maintain written records of the location and the condition of the asbestos and presumed asbestos-containing materials and keep the record up-to-date Page 3 of 19

4 Assess the risk of the likelihood of anyone being exposed to asbestos fibre from these Review and monitor the action plan and the arrangements made to put it in place To regularly review the University Asbestos Management Plan and Procedures as part of the quality management plan Carry out Refurbishment & Demolition surveys prior to all building/development works to identify the location and condition of any material that might contain asbestos. All findings to be made available to the Contractor and included in the pre tender Health and Safety Plan where appropriate Management (Type 2) Asbestos surveys have been undertaken for all reasonably accessible areas of the University. A comprehensive record of ACM s has been compiled. This information includes location, extent and condition of material and is be supported by photograph of sample points, CAD plans showing the presence of asbestos, risk assessments and an asbestos management plan. 3.0 PROGRAMME FOR ENHANCED COMPLIANCE All buildings deemed to potentially contain asbestos materials have now been surveyed. All materials identified during the survey process have been assessed and an annual action plan for remedial works put in place as from July The following programme for planned works for the period from August 2012 onwards has been prepared and is to be implemented. Year 2014/15 Continue with Management Plan works, including the 6 to 12 month inspections of known asbestos-containing materials and/or undertake new Management surveys across the Estate. Continue identified remedial works arising from the annual action plan Review the Management Plan periodically (bi-annually) or as required dependant on changes such as in legislation or working practices 4.0 RECORDING ACM s and MANAGING RISK 4.1 Management System ACM s are effectively recorded and managed using a management software package (PLANON database) which has been procured by the University. The database records the location and condition of ACM s by campus, building, floor, room or individual space. 4.2 Access to Information The custodian of the records shall be Estates-Property Services. The PLANON database will be accessible to all staff requiring such access. This is only be available over the University Intranet. Designated staff shall have read-only access. Authorised staff, including the appointed Asbestos Management Responsible Person and Assistant Asbestos Management Coordinators shall have full access and input capability. Page 4 of 19

5 4.3 Material Risk and Priority Assessments A Risk Assessment score for each ACM has been produced. This combines the Material Assessment (product type, damage/deterioration, surface treatment, asbestos type) and the Priority Assessment (location, material extent, use of location, occupancy level, activities carried out, likelihood/frequency of maintenance activities). This risk assessment forms the basis of asbestos management and will be used to determine the management and control actions necessary. 4.4 Monitoring and Re-inspection All ACM s will be re-inspected at between six to twelve monthly intervals as determined by risk assessment. Inspections shall be carried out by competent persons. The MICAD database will be updated to record inspection findings and action taken. 4.5 Updates The MICAD database will be constantly updated as further investigation; sampling and remedial works are carried out. 5.0 RESPONSIBILITIES The University has an explicit duty to assess and manage the risks from asbestos. The Board of Governors of Manchester Metropolitan University is ultimately responsible for the implementation of the University's Asbestos Management Strategy and the Asbestos Management Plan. The Directorate is the most senior management group within the University and is in a position to consider and implement policies and procedures concerning health, safety and welfare. 5.1 Asbestos Duty Holder The Head of Estates-Property Services Mike Price (the Duty Holder), has a professional and technical responsibility for the land, building fabric and the permanent services of the University's estate and compliance with the University's Asbestos Management Strategy and the Asbestos Management Plan. The Duty Holder will ensure that Facilities Property Services control the University s Asbestos Management Plan and that asbestos management across the University Estate is compliant with current legislation and the University's Asbestos Management Strategy. 5.2 Responsibilities for the delivery of the Asbestos Management Plan Estates-Property Services Maintenance Manager - Scott Gregory, in conjunction with the Duty Holder, will be responsible for preparing, reviewing and issue of the Asbestos Management Plan for the University including protocols and procedures for managing asbestos within the University. Scott Gregory is a BOHS Certified Competent Person and also holds the BOHS P407 qualification, and will, for the duration of this Asbestos Management Plan, provide advice and guidance to the Duty Holder on implementing the Asbestos Policy and Strategy in conjunction with the Health and Safety Unit and Directorate. They will jointly ensure that: The yearly Asbestos Action Plan for remedial works across the Estate, including identifying and prioritising ACM s by risk, is prepared and manages targeted funding to carry out works and management in line with the asbestos remediation budget. Page 5 of 19

6 Ensure compliance with the Asbestos Management Plan. Ensure that the overall strategy for the safe operation and execution of all Estate Planning includes consideration of asbestos issues. 5.3 Asbestos Condition Monitoring Estates-Property Services Maintenance Manager Scott Gregory, in conjunction with the Duty Holder and Gary Tootle (Estates-Property Services Head of Building Maintenance), will be responsible for managing the annual programme of asbestos management re-inspection surveys in adherence to HSE best practice guidance HSG264 Asbestos: The Survey Guide. They will collectively ensure that: The management of any Refurbishment & Demolition, additional Management Surveys, follow up inspections, remedial works or maintenance activities with regard to updating of the Micad database and records are procedurally compliant. Surveying of the Estate takes all reasonable steps to determine the location of ACM s. That all known or identified asbestos is repaired, sealed, removed, or otherwise treated, if there is a risk of exposure. Periodically monitoring the condition of ACMs, updating the asbestos register and reassesses the risk due to its condition or location. Keep the Micad asbestos database of ACMs up to date and providing a record of the location, condition, maintenance and removal for all ACMs on the University's estate. 5.4 Operational Management of Asbestos Risk Estates-Property Services, Head of Building Maintenance Gary Tootle and the Property Services Building Maintenance Managers will collectively ensure that asbestos is safely managed during all operational maintenance activities within buildings under their control. They will: Carry out risk assessments and document all actions taken to manage the asbestos. Make all asbestos information available to all those who may come into contact or disturb ACMs. Information shall be provided in a written or electronic format and shall be correct on the date it is presented. Put operational managerial arrangements in place to make sure that all work, which may disturb suspected ACMs, is fully compliant with current legislation and the Asbestos Management Plan. Ensure that prior to the commencement of any works which may have the potential to bring staff into contact with ACMs, the PLANON asbestos database is consulted, or Refurbishment & Demolition surveys are carried out, and such information used within all work related risk assessments. Keep the Micad asbestos database of ACMs up to date by formally notifying Scott Gregory (Estates-Property Services Maintenance Manager) of all changes in condition, location or removal of ACMs within those maintained areas under their control across the University's Estate. Page 6 of 19

7 5.5 Asbestos Awareness and Training The Head of Estates-Property Services Mike Price (the Duty Holder), and Gary Tootle (Estates- Property Services Head of Building Maintenance), shall ensure that training is undertaken for maintenance staff and staff identified as requiring such training to safely carry out their role within the University. This will include dissemination of relevant information to staff, students, contractors or third parties as required ensuring safe working practices or occupancy of University buildings. 5.6 Responsibilities of Staff and Students They are personally responsible for ensuring that: They comply with their obligations as set out in the MMU Health and Safety Policy and the MMU Health and Safety Manual. That any activity that may disturb or damage ACM has been avoided. 5.7 Responsibilities of Human Resources Offering screening to members of staff who are known or suspected to have been exposed to asbestos materials. Counselling staff who may have been exposed to or who are concerned about possible exposure to asbestos materials, in liaison with Staff Counsellor and Counselling Service. Undertaking when requested an auditing role on representative projects carried out by the Responsible Person Asbestos, Asbestos Contractor or Analyst. Provide advice on Asbestos Awareness training for staff and students as necessary. 6.0 TRAINING The University will continue to provide its asbestos awareness training programme to staff that are likely to come into contact with the potential to disturb asbestos containing materials or those who have direct management and supervisory roles of staff or contractors in carrying out such work. All resident maintenance staff, including long term maintenance contract staff, shall attend asbestos awareness training or refreshers training every 2 years to make sure that all are competent in the recognition of asbestos and in the appropriate safe procedures to manage it. Additional training shall be provided to supervisory staff to maintain competency in the safe management of ACM s on the University premises as deemed suitable including refresher training every 2 years. The University will train the Responsible Person - Asbestos and Duty Holder to BOHS P407 level or similar recognized standard. Relevant Maintenance or Project Managers shall be trained to BOHS P405/P402 level or similar recognized standard and staff shall regularly attend further appropriate courses or refresher training to maintain competency in the recognition and management of asbestos. Continual assessment shall be undertaken to make sure that all staff are kept up to date with current and future legislation or working best practices. Estates-Property Services shall liaise with Human Resources to introduce Asbestos awareness as part of the induction process for all University staff. Estates-Property Services shall liaise with Student and Academic Services to incorporate Asbestos awareness into web based Faculty Student Page 7 of 19

8 Handbook and the Halls of Residence Handbook. The wording to be incorporated into the staff induction and the student handbooks will be as set out in Appendix B. 7.0 PROCEDURES FOR PROJECT AND MAINTENANCE WORKS All University Project Managers, Surveyors, and Engineers (including appointed external project managers or departmental staff nominated as project managers for specific projects) shall ensure that:- Project management consultants involved in their projects follow the University procedures and that all appropriate information is disseminated All areas are assessed prior to project/work start, and that they identify any known risk from asbestos via MICAD and make sure that, where applicable, further investigation including a Refurbishment & Demolition survey is undertaken All staff and contractors are informed of the location of any known asbestos affecting the project/work. The pro-forma contained in appendix D of this document must be used to record the transfer of information from the University to the Contractor That if required the project is effectively managed and monitored by an appointed Asbestos Consultant If suspect asbestos material is discovered during the course of work, all work is stopped, staff are informed, and advice is sought from the Responsible Person Asbestos / Asbestos Contractor/Consultant The Project Manager will seek advice from the Responsible Person Asbestos or approved Asbestos Contractor/Consultant on the most appropriate remedial action and shall arrange for any necessary analytical works Those recommendations made by the Responsible Person Asbestos or Contractor/Consultant for any remedial actions are incorporated into the project works The Responsible Person Asbestos is kept fully informed of all changes to any ACM s so that they can be recorded 8.0 GENERAL AND EMERGENCY CONTROL PROCEDURES 8.1 Entry into Asbestos contaminated area Access to contaminated areas will not be permitted until a risk assessment has been carried out. Access will be controlled by the Responsible Person Asbestos or his nominated competent person s and will be restricted to asbestos competent persons wearing the appropriate personal protective equipment. Access restrictions will remain in place until the Responsible Person Asbestos has all the test results necessary to verify all surfaces and airborne contamination has been dealt with. 8.2 Access to an Asbestos Enclosure Access to any asbestos enclosure will be restricted to authorised staff, consultants, and contractors only. Procedures for access will be strictly in accordance with a risk assessment prepared for the Page 8 of 19

9 work. Access restrictions will remain in place until a certificate of re-occupation has been issued by an authorised person. In the case of emergency, only authorised competent staff wearing the appropriate personal protective equipment will enter the live enclosure. 8.3 Labelling Asbestos Labelling of ACM s will not be used as a method of identification and management. 8.4 Working with Asbestos Containing Materials All work with ACM s is to be carried out by Specialist Contractors holding all the required statutory licences and insurance. This requirement shall also apply to ACM s defined in regulation 3(2) (c) (ii) as non-modifiable. Unlicensed contractors shall not be permitted to work on, disturb, or interfere with any ACM s. The work will be undertaken by competent staff, utilizing appropriated tools and personal protective equipment. The work will be carried out strictly adhering to Health and Safety Guidance documents including: Control of Asbestos Regulations Managing and Working with Asbestos, Control of Asbestos Regulations 2012 Approved Code of Practice and Guidance L143. Asbestos: The Survey Guide HSG264 (Second Edition). Asbestos: The Analyst s Guide for sampling, analysis and clearance procedures HSG 248. Asbestos: The Licensed Contractors Guide HSG Day to Day Maintenance Works A new integrated maintenance management system has been purchased to manage the day to day maintenance works around the University. This system includes control gate mechanisms to identify ACM s at the stage work notes are issued. Where a work note identifies the presence of asbestos, the Surveyor/Engineer/Supervisor, and the operative, must interrogate the asbestos register to determine if the location of any asbestos impacts on the work instructed. If operatives need to move outside the work area defined on the work note (e.g. to access a duct to isolate services) or are unsure about a material or task they must refer back to their Supervisor for further asbestos checks and instruction before proceeding. 8.6 Out of Hours Call Outs The University operate an out of hours call out service for attending to emergency faults, repairs and breakdowns. An approved asbestos remediation contractor shall be available on 24 hour call out to attend to any ACM s which may be encountered by operatives attending the premises out of normal working hours. Full contact details for the remediation contractor shall be placed in the call out handbook, and the contractor s telephone number shall be placed in the call out mobile phone. The call out Engineer/Surveyor is to engage the remediation contractor to deal with any material which they suspect may contain asbestos. See the OUT OF HOURS CALL OUTS - STATEMENT ON ASBESTOS in appendix C. 8.7 Emergency Procedure If anyone suspects that an ACM has been disturbed and that asbestos fibres have accidentally been released, the following action should be taken immediately: Page 9 of 19

10 Stop work or activity immediately. Evacuate the area without causing unnecessary alarm or potential spread of asbestos fibre, closing all windows and doors. Prohibit access to the area, cordon off / secure the area until and post warning notices. Report the incident immediately to the Responsible Person - Asbestos ( ), the University Health & Safety Unit ( ), or should these not be available the Estates-Property Management Help Desk ( ) or out of hours Security ( ) clearly stating that it is a suspected asbestos incident. Follow any instruction given to manage the situation until the Responsible Person - Asbestos or the University Health & Safety Unit attends the incident. Record if possible, the names of all persons potentially affected. In circumstances where a site is under the control of a Principal Contractor the procedures in the Health & Safety file should be followed. 8.8 Guidance on Containing an Accidental Fibre Release. The Responsible Person Asbestos and the University Health & Safety Advisor shall visit the site of the incident as soon as reasonably practical. The following action shall be taken:- Make sure all personnel have left the area and that their names have been recorded. Consult the MICAD asbestos database for that area to confirm the presence of known ACM s. Determine as far as is reasonably practical, the nature and extent of the release of any fibres. Secure the area by the use of hasp, staple and padlock. Retain all keys. Install approved signs to all doors leading to the affected area to restrict access. Notify reception staff. Notify the Site Service Manager and confirm in writing. Engage the services of an Asbestos Consultant to determine the scope of the release, to undertake bulk sampling and analysis if material is unknown and to provide advice on remedial action. Implement Asbestos Consultants recommendations. Assess the level of release and instigate reporting procedures under RIDDOR where the exposure to fibre is, in the opinion of the consultant, presumed to have been significant. 9.0 MONITOR AND REVIEW The Management Plan will be reviewed by the every 6 months to check that it is compliant with current legislation that all information is current and correct, and that objectives are being met. (Next Review date is April 2015). In the event of an incident, an interim review will be undertaken and noted to check that the management systems remain effective and any amendments required are documented EMERGENCY SERVICES Hard copy asbestos reports providing an overview of the asbestos present in the building shall be placed in each building adjacent to the fire logbook. These are not to be used to identify all known Page 10 of 19

11 or potential ACM s present within the building; rather the PLANON asbestos database must be consulted APPROVED CONTRACTORS AND CONSULTANTS Removal of asbestos based materials will be under the control of Estates Department and the Responsible Person Asbestos will either undertake the management of works or informed of such works that are to be managed others in line with University guidance and current legislation. The Estates Department shall maintain a list of vetted and approved Contractors, and shall have available the services of approved competent Consultants, full details of which shall be available from the Responsible Person Asbestos. Page 11 of 19

12 APPENDIX A ASBESTOS MANAGEMENT FLOW CHART Page 12 of 19

13 ASBESTOS MANAGEMENT FLOW CHART Feedback University Asbestos Management Plan Survey, Locate, Test, Record Remediate or Repair Risk Assess Manage and Re Inspect Entry Into Contaminated Areas Information Available to Contractor Consultants Students and Staff Control Procedures Access to Asbestos Enclosure Working with ACM s Training Day to Day Maintenance Work Updating to meet changes in Legislation Emergency Procedures Review Management Plan Development Work RaD Survey Page 13 of 19

14 Appendix B Statement on Asbestos Text for Staff and Students Page 14 of 19

15 STATEMENT ON ASBESTOS Under the Control of Asbestos Regulations 2012 the University has a legal duty to manage asbestos in non-domestic premises. The University has taken all reasonable steps to identify materials in premises likely to contain asbestos and have assessed the risk of anyone being exposed. The University are obliged to make sure that any material known or presumed to contain asbestos is kept in a good state of repair and that any material that contains or is presumed to contain asbestos is, because of the risks associated with its location or condition, repaired or if necessary removed. The Facilities Department are responsible for the day to day management of the asbestos existing in and around the University premises. Asbestos must be respected, but need not be feared. You can only be exposed to the risk of inhaling asbestos if it is damaged or disturbed and fibres are released into your breathing zone. Asbestos in good condition can be safely left in place and monitored. Staff and Students have a role to play in the Management of asbestos. They must avoid drilling, cutting, or in any other way interfering with the fabric of the buildings. They should maintain an awareness of the potential presence of asbestos within the workplace and report any material they suspect has been damaged or is in poor condition to the University Help Desk ( ), or the University Health and Safety Unit (tel ). Page 15 of 19

16 Appendix C Out of Hours Call Outs Statement on Asbestos Page 16 of 19

17 OUT OF HOURS CALL OUTS STATEMENT ON ASBESTOS Under the Control of Asbestos Regulations 2012 the University has a legal duty to manage asbestos in non-domestic premises. For the purposes of managing asbestos around the University, these regulations shall be deemed to apply to all premises controlled by the University. The on call Engineers/Surveyors and Building Operatives have a role to play in the Management of asbestos. Building operatives called to attend out of hours emergencies, faults, repairs or breakdowns must maintain an awareness of the potential presence of asbestos. They must avoid removing, drilling, cutting, or in any other way interfering with any material they suspect may contain asbestos. The operative must cease work immediately they encounter any suspect material and contact the on call Engineer/Surveyor for further instruction. The on call Engineer/Surveyor shall assess the need for the work to proceed (e.g. can it wait until the following day?). If it is essential that the work proceed, then the Engineer/Surveyor shall call out an approved asbestos remediation contractor to attend site and undertake the minimum amount of work necessary to facilitate the repair. Should it be deemed absolutely necessary the approved consultants should also be contacted to attend site. Contact details for the current approved consultants are:- Shield on Site-Services: Matthew Rogerson, Operations Manager: or (24hr response) Contact details for the current approved remediation contractor are:- Kaefer C&D Ltd: Alan Lee, Senior Contracts Manager: or (24hr response) Page 17 of 19

18 Appendix D Asbestos Pro-Forma Page 18 of 19

19 ASBESTOS PRO-FORMA INTRODUCTION This asbestos pro-forma has been developed to enable the appropriate transfer of information between the University and any Contractors in respect of asbestos based materials. The pro-forma shall be signed when the information is provided at tender stage, or at the pre-contract meeting as applicable or, in the case of smaller projects, at the time the information is handed to the Contractor. ASBESTOS BASED MATERIALS Tick Box 1 The University has advised that under the CDM Regulations the Pre-Tender Health & Safety Plan has identified, so far as is reasonably practicable, the presence and location of known or suspected asbestos based material. 2 Notification has been sent to you indicating the presence of known or suspected asbestos based materials in the building/room/location where you will be undertaking work. Copies of relevant sections of the University Asbestos Register and/or drawings have been passed to you by hand/letter. 3 The Asbestos Register is a non-exhaustive record, therefore all site operatives will have received suitable asbestos awareness training to ensure that any suspect materials are not disturbed. 4 Any suspect materials must be notified immediately to the Contract Administrator or an appropriate member of facilities Property Services Staff. Contract Title: Contractor: Signature: Position: Date:

The Management of Asbestos containing Materials

The Management of Asbestos containing Materials The Management of Asbestos containing Materials Status Owner Approval by University Court Draft Head of Estates and Building 1 Purpose... 1 2 Scope... 3 3 Principles... 4 4 Procedure... 5 5 Accountabilities...

More information

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN Revision Date Nature of Revision Prepared by Approved by 0.2 Jul 2013 Initial draft for comment Jon Fahie 0.3 Sep

More information

Asbestos Policy ASBESTOS POLICY. Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy

Asbestos Policy ASBESTOS POLICY. Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy ASBESTOS POLICY Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy This is a controlled document. It should not be altered in any way without the express permission of the author or their representative.

More information

Author G Morton July 2015. Newcastle University Asbestos Management Plan 2015

Author G Morton July 2015. Newcastle University Asbestos Management Plan 2015 Newcastle University Asbestos Management Plan 2015 1 Contents 1.0 Introduction 2.0 Asbestos Management Duty Holder Responsibilities 2.1 Asbestos Manager (Head of Maintenance) 2.2 University Asbestos Survey

More information

Asbestos Management Plan

Asbestos Management Plan Health and Safety Services Asbestos Management Plan Policy, Organisation and Arrangements Sean Callaghan Issue number 3 April 2014 Issue Date Nature of revision Prepared by Approved by 2 April 2013 First

More information

ASBESTOS MANAGEMENT POLICY

ASBESTOS MANAGEMENT POLICY ASBESTOS MANAGEMENT POLICY Published : 4th Revision December 2014 1 Table of Contents INTRODUCTION... 3 DUTY TO MANAGE ASBESTOS... 3 DUTIES OF CAMPUS SERVICES... 3 1.0 POLICY OBJECTIVES... 5 2.0 RESPONSIBILITIES...

More information

ASBESTOS POLICY AND PROCEDURES

ASBESTOS POLICY AND PROCEDURES ASBESTOS POLICY AND PROCEDURES a CORPORATE RESOURCES DEPARTMENT PROPERTY SERVICES POLICY FOR THE MANAGEMENT OF ASBESTOS IN BUILDINGS OWNED AND/OR OPERATED BY LEICESTERSHIRE COUNTY COUNCIL LCC ASB/001 ISSUE

More information

Asbestos Management Policy (Version 3)

Asbestos Management Policy (Version 3) Asbestos Management Policy (Version 3) Contents Page Introduction 3 College Policy Statement for Asbestos Management 3 Objectives (of this Policy and Procedure) 3 Application of Policy 4 Licensed Asbestos

More information

ASBESTOS MANAGEMENT PLAN. Borough of Poole Transportation Services, Property Management, Civic Centre, Poole, Dorset BH15 2RU

ASBESTOS MANAGEMENT PLAN. Borough of Poole Transportation Services, Property Management, Civic Centre, Poole, Dorset BH15 2RU ASBESTOS MANAGEMENT PLAN Borough of Poole Transportation Services, Property Management, Civic Centre, Poole, Dorset BH15 2RU CONTENTS 1. INTRODUCTION 2. HOW DOES THE BOROUGH OF POOLE MANAGE ITS ASBESTOS

More information

ASBESTOS CONTAINING MATERIALS POLICY

ASBESTOS CONTAINING MATERIALS POLICY ASBESTOS CONTAINING MATERIALS POLICY Document Control Version 3 Ratified by Risk Management Sub Group Date Ratified 19 December 2012 Name of Originator/Author Head of Estates and Facilities Name of Responsible

More information

Control of Asbestos Policy

Control of Asbestos Policy Control of Asbestos Policy Version Number: V1D Name of originator/author: Estates Manager 0161 277 1235 Name of responsible committee: Estates and Facilities Committee Name of executive lead: Director

More information

Asbestos Management Policy

Asbestos Management Policy Central Bedfordshire Council www.centralbedfordshire.gov.uk Asbestos Management Policy The Housing Service Version 1.0 Directorate Social Care Health and Housing Service Housing Service Approved by Director

More information

Managing Asbestos Policy

Managing Asbestos Policy Managing Asbestos Policy Liverpool Mutual Homes Page 1 of 16 Table of Contents 1. MANAGEMENT INFORMATION 2. POLICY STATEMENT 3. POLICY AIMS AND KEY OBJECTIVES 4. INTRODUCTION 5. DETAIL 6. LINKS TO LMH

More information

ASBESTOS POLICY MANAGEMENT PLAN

ASBESTOS POLICY MANAGEMENT PLAN ASBESTOS POLICY & MANAGEMENT PLAN HS20 Version V2 Approved by: Health, Safety and Security Committee Date approved: March 2011 Ratified by: Hospital Executive Committee Date ratified 24 th April 2012 Document

More information

Asbestos Policy. Ymddiriedolaeth GIG Gwasanaethau Ambiwlans Cymru Welsh Ambulance Service (NHS) Trust. November 2007. All Staff.

Asbestos Policy. Ymddiriedolaeth GIG Gwasanaethau Ambiwlans Cymru Welsh Ambulance Service (NHS) Trust. November 2007. All Staff. Appendix 1 Ymddiriedolaeth GIG Gwasanaethau Ambiwlans Cymru Welsh Ambulance Service (NHS) Trust Asbestos Policy Approved by Date Review Date Target Audience Trust Board November 2007 November 2008 All

More information

ROYAL HOLLOWAY, UNIVERSITY OF LONDON

ROYAL HOLLOWAY, UNIVERSITY OF LONDON ROYAL HOLLOWAY, UNIVERSITY OF LONDON ASBESTOS MANAGEMENT POLICY (Version 2) This Policy defines the College s arrangements for the management of asbestos and the measures to be taken for the protection

More information

Asbestos Management Procedure

Asbestos Management Procedure Asbestos Management Procedure Reference: HS/021/2010 Version No: 2.0 Issue Date: July 2010 Document Control Document Ref: HS/021/2010 Date Created: Jan 2010 Version: 2 Date Modified: Revision due December

More information

HAVEBURY HOUSING PARTNERSHIP

HAVEBURY HOUSING PARTNERSHIP HS028 HAVEBURY HOUSING PARTNERSHIP POLICY ASBESTOS MANAGEMENT Controlling Authority Director of Resources Policy No. HS028 Issue No. 3 Status Final Date November 2013 Review Date: November 2016 Equality

More information

Policy for the Management of Asbestos in Council Premises (Corporate and Housing)

Policy for the Management of Asbestos in Council Premises (Corporate and Housing) Policy for the Management of Asbestos in Council Premises (Corporate and Housing) Page 1 of 14 1. Policy Statement 1.1 This policy is designed to provide a clear acknowledgement of the responsibilities

More information

STRATEGIC PLANNING & PLACE BUILDING CONTRACT DIRECTIVE

STRATEGIC PLANNING & PLACE BUILDING CONTRACT DIRECTIVE BCD.26 STRATEGIC PLANNING & PLACE BUILDING CONTRACT DIRECTIVE DATE: March 2015 Copyright Reserved TESTING, ASSESSMENT AND WORK WITH ASBESTOS CONTAINING MATERIALS (ACM S) REFERENCE This Directive deals

More information

Asbestos Management Plan

Asbestos Management Plan Asbestos Management Plan This procedural document was previously incorporated within the Asbestos Management Policy and Procedures CORP/HSFS 10 v.3 Did you print this document yourself? The Trust discourages

More information

POLICY Contents. 1.0 Introduction Statement

POLICY Contents. 1.0 Introduction Statement POLICY Contents 1.0 Introduction Statement 2.0 Legal Responsibility 2.1 Asbestos Management Hierarchy 2.2 Duty Holders Responsibility 2.3 Employees Responsibility 3.0 Asbestos Management Procedure 4.0

More information

Policy on the Management of Asbestos

Policy on the Management of Asbestos WISHAW AND DISTRICT HOUSING ASSOCIATION Policy on the Management of Asbestos As with all the Association s policies and procedures, this document, where required, may be able to be translated into other

More information

ASBESTOS MANAGEMENT POLICY AND GUIDANCE

ASBESTOS MANAGEMENT POLICY AND GUIDANCE ASBESTOS MANAGEMENT POLICY AND GUIDANCE Belvoir High School Policy and Procedures Date approved 08/10/2013 Signed by Chair of Governors (Mr B Lovegrove Date approved 08/10/2013 Signed by Executive Principal

More information

Asbestos Policy & Procedure

Asbestos Policy & Procedure Asbestos Policy & Procedure 1. Purpose & Introduction This policy and procedure sets out Octavia s commitment and approach to ensuring, so far as reasonably practicable, that residents, contractors and

More information

Asbestos Management Plan

Asbestos Management Plan Harlow Council Asbestos Management Plan Version 4 Scope: This management plan applies to the management of all asbestos containing materials to properties under the ownership/management of Harlow Council

More information

Policy 7 Management of Asbestos

Policy 7 Management of Asbestos Policy 7 Management of Asbestos 1.0 Introduction Development & Infrastructure recognise both the need to protect their employees from the risks associated with encountering asbestos and the potential for

More information

Asbestos Management Plan

Asbestos Management Plan Safety Standard Asbestos Management Plan Version 8.0 May 2015 Page 1 of 60 Engineering Maintenance & Infrastructure Safety Standard Asbestos Management UNIVERSITY COLLEGE LONDON STANDARD ASBESTOS MANAGEMENT

More information

Asbestos Policy. Planning, Performance Management and Support Services. Legacy Causeway Asbestos Policy (Ref: CHSST/04/211)

Asbestos Policy. Planning, Performance Management and Support Services. Legacy Causeway Asbestos Policy (Ref: CHSST/04/211) Asbestos Policy Reference Number: NHSCT/09/192 Responsible Directorate: Planning, Performance Management and Support Services Replaces (if appropriate): Legacy Causeway Asbestos Policy (Ref: CHSST/04/211)

More information

REVISION 9 January 2015 ASBESTOS MANAGEMENT PLAN

REVISION 9 January 2015 ASBESTOS MANAGEMENT PLAN REVISION 9 January 2015 ASBESTOS MANAGEMENT PLAN ULSTER UNIVERSITY - ASBESTOS MANAGEMENT PLAN CONTENTS PAGE 1. Introduction 4 2. Background 4 2.1 Types of Asbestos 2.2 Hazards of Asbestos dust 2.3 Use

More information

Asbestos Management Plan. April 2011

Asbestos Management Plan. April 2011 Reviewed by: Approved by: Health & Safety Management Committee Management Board -. R3. Part 1: Introduction Part 2: Policy Part 3: Organisation and Responsibilities Part 4: Procedures Appendices: 1 Management

More information

Policy for the Management of Asbestos in Buildings

Policy for the Management of Asbestos in Buildings in Buildings Health and Safety Services 1 A1. Introduction If asbestos fibres enter the lungs they can cause cancer or incurable disease. Consequently the University is committed to ensure that all reasonably

More information

Policy for the Management of Asbestos in the Workplace

Policy for the Management of Asbestos in the Workplace Southwark Council Management of Asbestos in the Workplace November 2011 Page 1 of 15 CONTENTS 1. INTRODUCTION... 3 2. POLICY STATEMENT... 3 3. ASBESTOS RISK CLASSIFICATION SCHEME... 5 4. SAMPLING OF ASBESTOS

More information

Asbestos Policy and Management Plan 2013-16

Asbestos Policy and Management Plan 2013-16 Policy reviewed by Thomas Eggar Solicitors, January 2013 Equality Assessment completed January 2013 Policy reviewed by the Health and Safety Committee, February 2013 Policy reviewed and adopted by the

More information

ASBESTOS POLICY. Version: Asbestos Policy v 1.2. Date ratified: 22 nd March 2013 Approving Committee/Group (Date)

ASBESTOS POLICY. Version: Asbestos Policy v 1.2. Date ratified: 22 nd March 2013 Approving Committee/Group (Date) ASBESTOS POLICY Version: Asbestos Policy v 1.2 Ratified by: Policy Committee Date ratified: 22 nd March 2013 Approving Committee/Group (Date) Date Approved by Medicines Management Committee: (NB: All Procedural

More information

Bield Housing and Care POLICY, PROCEDURES. and MANAGEMENT PLAN ASBESTOS CONTAINING MATERIALS

Bield Housing and Care POLICY, PROCEDURES. and MANAGEMENT PLAN ASBESTOS CONTAINING MATERIALS Bield Housing and Care POLICY, PROCEDURES and MANAGEMENT PLAN for ASBESTOS CONTAINING MATERIALS Approved on: 24 April 2014 By Health & Safety Management Group Implementation date: 1 June 2014 Review Date

More information

Policy for the Management of Asbestos

Policy for the Management of Asbestos CARDIFF AND VALE NHS TRUST YMDDIRIEDOLAETH GIG CAERDYDD A R FRO Policy for the Management of Asbestos Author Keith Jones Estate Controls Assurance Officer / Environmental Management Co-ordinator Policy

More information

SMS0045 Construction Health and Safety Policy and Procedures

SMS0045 Construction Health and Safety Policy and Procedures SMS0045 Construction Health and Safety Policy and Procedures March 2015 Version 8 Please note that for projects utilising a CDM Co-ordinator under the transitional arrangements of CDM 2015 (between 6 April

More information

Accommodation Officers Information Booklet. Asbestos The Asbestos Abatement Programme and the Asbestos Management Policy

Accommodation Officers Information Booklet. Asbestos The Asbestos Abatement Programme and the Asbestos Management Policy Accommodation Officers Information Booklet Asbestos The Asbestos Abatement Programme and the Asbestos Management Policy This Guideline has been produced solely for use by State Authorities that come within

More information

Asbestos Policy. Policy. The whole of the Trust. Intranet

Asbestos Policy. Policy. The whole of the Trust. Intranet Document name: Document type: What does this policy replace? Staff group to whom it applies: Distribution: Asbestos Policy Policy Update of previous Procedure for the Safe Management of Asbestos guidance

More information

AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS

AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS Conducted By GASKIN CONSTRUCTION SERVICES PTY LTD TABLE OF CONTENTS SECTIONS Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7

More information

Asbestos Policy Lead officer: Date agreed: Review date: Working together to deliver quality homes and a better environment for all

Asbestos Policy   Lead officer: Date agreed: Review date: Working together to deliver quality homes and a better environment for all Asbestos Policy Lead officer: Jeff Scott Date agreed: May 2013 Review date: May 2016 Working together to deliver quality homes and a better environment for all Page 1 of 11 Contents Page 1 Introduction

More information

ASBESTOS MANAGEMENT POLICY

ASBESTOS MANAGEMENT POLICY Community Health Service ASBESTOS MANAGEMENT POLICY UNCONTROLLED COPY ONCE PRINTED. For CURRENT version check NHS Leicester City or LCCHS INTRANET. Reference Title: HS004 Asbestos Management Policy Version

More information

Plymouth City Council Asbestos Policy

Plymouth City Council Asbestos Policy Plymouth City Council Asbestos Policy Policy, Arrangements and Procedures for Asbestos Management in Buildings, Structures and Assets Owned or Occupied by Plymouth City Council. May 2008: Version 1.1-1

More information

Version: Date adopted: publication: Review date: September 2015. Expiry date: March 2016. Target audience: All staff

Version: Date adopted: publication: Review date: September 2015. Expiry date: March 2016. Target audience: All staff Asbestos Policy The Asbestos Policy provides guidance to ensure that all appropriate steps are taken to comply with the duty to manage asbestos and comply with asbestos related legislation, codes of practice

More information

An Introduction to Asbestos, Legislation and Licensed

An Introduction to Asbestos, Legislation and Licensed An Introduction to Asbestos, Legislation and Licensed Contractor Selection MARK W ROBERTS Director Kitsons Environmental Europe Ltd Chair ARCA CHRIS BISHOP BA, C.Chem MRSC, MCQI CQP, CCP (Asbestos) Head

More information

Asbestos Management Plan

Asbestos Management Plan Asbestos Management Plan Document title Asbestos Management Plan Document author and department Jonathan Latter Health and Safety Compliance Manager Approving body Responsible person and department Fiona

More information

Asbestos Management Policy

Asbestos Management Policy Asbestos Management Policy Originator: Approval date: Policy and Strategy Team Sovini Board PCHA Board OVH Board/EMT 3 rd December 2012 22 nd November 2012 25 th September 2012 Review date: December 2013

More information

UWE Facilities Asbestos Management Plan Issue 15

UWE Facilities Asbestos Management Plan Issue 15 UWE Facilities Asbestos Management Plan Issue 15 Review Date: March 2015 Contents Section 1: Introduction... 3 Asbestos Management Standard & Asbestos Management Plan (AMP)... 3 Section 2: Policy... 5

More information

DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM HS25 Asbestos Management Plan

DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM HS25 Asbestos Management Plan DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM HS25 Document Originated: November 2012 By: Lynn Fleming Issue Number: 4 Number of pages: 71 Approved by EMG: Status: Final Last

More information

21316 PROCEDURE CONTROL OF ASBESTOS. 2. Risk Assessments / Health and Safety Considerations

21316 PROCEDURE CONTROL OF ASBESTOS. 2. Risk Assessments / Health and Safety Considerations Version: 15 Last Updated: 12/08/14 Review Date: 04/08/17 ECHR Potential Equality Impact Assessment: Low 1. About This Procedure 1.1. This procedure sets out the processes for managing asbestos in Hampshire

More information

Asbestos at work guide

Asbestos at work guide Asbestos at work guide Contents Introduction.... 2 Frequently asked questions.... 4 The Control of Asbestos Regulations 2006... 5 Types of asbestos survey.... 7 1 Introduction This document provides a

More information

Asbestos-Containing Materials in Buildings: Asbestos Management Plan for LBC Housing

Asbestos-Containing Materials in Buildings: Asbestos Management Plan for LBC Housing LUTON BOROUGH COUNCIL, BUILDING AND TECHNICAL SERVICES CENTRAL DEPOT, KINGSWAY, LUTON LU4 8AU. Asbestos-Containing Materials in Buildings: Asbestos Management Plan for LBC Housing In accordance with the

More information

British Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT

British Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT BCIT Safety Manual Contents 1. Purpose... 3 2. Definitions... 3 2.1 Asbestos... 3 2.2 Asbestos Containing Material (ACM)... 3 2.3 Friable Material... 3 2.4 Low Risk Work Activity... 3 2.5 Moderate Risk

More information

ASBESTOS MATERIALS IN SCHOOLS

ASBESTOS MATERIALS IN SCHOOLS CODE OF PRACTICE FOR MANAGEMENT OF ASBESTOS MATERIALS IN SCHOOLS CONTENTS 1. Introduction 1.1 Scope 1.2 The OPW Health and Safety Unit 2 Background 2.1 General Information 2.2 Main Risks 2.3 Main Risk

More information

PROJECT BRIEF Version (insert number)

PROJECT BRIEF Version (insert number) PROJECT BRIEF Version (insert number) 1 Project Name ------------------------------------------------------------------- 1.1 The Project Project Address Nature of Work Location 1.2 DCC Client for Project

More information

Asbestos Management Consultants COMPANY PROFILE Tersus Consultancy Limited

Asbestos Management Consultants COMPANY PROFILE Tersus Consultancy Limited Asbestos Management Consultants COMPANY PROFILE Tersus Consultancy Limited www.tersusgroup.co.uk Asbestos has been used in the UK construction industry since around 1890. Once hailed as the wonder building

More information

Beech Housing Association Asbestos Management Policy

Beech Housing Association Asbestos Management Policy Beech Housing Association Asbestos Management Policy Policy Statement The aim of this document is to define a policy for the control and management of the risk of exposure to asbestos within the dwellings

More information

Asbestos Safety Management Standard Issue 8 October 2008. www.walsall.org.uk/healthandsafety

Asbestos Safety Management Standard Issue 8 October 2008. www.walsall.org.uk/healthandsafety www.walsall.org.uk/healthandsafety Asbestos Safety Management Standard Issue 8 October 2008 Page 1 of 7 / WMBC/SMS Asb/008/01 UNCONTROLLED WHEN PRINTED Please contact us if you have any difficulty reading

More information

MANAGEMENT OF ASBESTOS POLICY

MANAGEMENT OF ASBESTOS POLICY MANAGEMENT OF ASBESTOS POLICY The application of this policy and procedure ensures that no employee receives less favourable treatment on grounds of sex, trans-gender status, sexual orientation, religion

More information

Code of Practice EST 01 Decommissioning arrangements prior to site hand over Oct 2004

Code of Practice EST 01 Decommissioning arrangements prior to site hand over Oct 2004 Estates Division Imperial College London Room 503 Sherfield Building South Kensington Campus London SW7 2AZ, UK Tel: +44 (0)20 7594 9832 Fax: +44 (0)20 7594 9050 r.mayne@imperial.ac.uk www.imperial.ac.uk

More information

Aylesford School. and Sixth Form College. wonder aspiration respect discipline RISK MANAGEMENT POLICY. Finance and Premises Committee

Aylesford School. and Sixth Form College. wonder aspiration respect discipline RISK MANAGEMENT POLICY. Finance and Premises Committee Aylesford School and Sixth Form College wonder aspiration respect discipline RISK MANAGEMENT POLICY Written: January 2015 Review Date: January 2017 Lead: Site Manager Via: Finance and Premises Committee

More information

Asbestos Management Plan. Policy. The whole of the Trust. Intranet. The Trust Board/Executive Management Team

Asbestos Management Plan. Policy. The whole of the Trust. Intranet. The Trust Board/Executive Management Team Document name: Document type: What does this policy replace? Staff group to whom it applies: Distribution: Asbestos Management Plan Policy Update of previous Procedure for the Safe Management of Asbestos

More information

SAFETY RESPONSIBILITIES AND ARRANGEMENTS IN RESPECT OF ASBESTOS MANAGEMENT (ASBESTOS MANAGEMENT PLAN)

SAFETY RESPONSIBILITIES AND ARRANGEMENTS IN RESPECT OF ASBESTOS MANAGEMENT (ASBESTOS MANAGEMENT PLAN) KING S COLLEGE LONDON Health, Safety & Environmental Protection Office SAFETY RESPONSIBILITIES AND ARRANGEMENTS IN RESPECT OF ASBESTOS MANAGEMENT (ASBESTOS MANAGEMENT PLAN) Issue Date: May 2012 Issue Number:

More information

Review Date 01/09/2015 Director of Estates and Facilities Expiry Date 11/09/2016 Withdrawn Date

Review Date 01/09/2015 Director of Estates and Facilities Expiry Date 11/09/2016 Withdrawn Date Policy No: RM78 Version: 1.0 Name of Policy: Corporate Asbestos Management Policy, Organisational Arrangements and Procedures Policy Effective From: 24/10/2013 Date Ratified 12/09/2013 Ratified Health

More information

ASBESTOS POLICY AND MANAGEMENT PLAN

ASBESTOS POLICY AND MANAGEMENT PLAN ASBESTOS POLICY AND MANAGEMENT PLAN 1. INTRODUCTION 1.1. The Control of Asbestos at Work Regulations 2006 requires employers to prevent the exposure of their employees to asbestos, or where this is not

More information

Housing, Construction and Building Services. Supplementary Occupational Health and Safety Policy

Housing, Construction and Building Services. Supplementary Occupational Health and Safety Policy Supplementary Occupational Health and Safety Policy Statement Page 1 of 26 Housing, Construction and Building Services Supplementary Occupational Health and Safety Policy Date Author Version Status Reason

More information

Derby City Council. Asbestos Management Plan

Derby City Council. Asbestos Management Plan Derby City Council Asbestos Management Plan April 2014 Page 1 of 44 Index of Contents 1.1 Introduction 3 1.2 Glossary of Terms 4 2.0 Action Plan 2.1 Scope and purpose 6 2.2 Competent persons who they are

More information

Health and Safety Policy

Health and Safety Policy Health and Safety Policy October 2014 1 October 2014 Contents: Introduction 1. STATEMENT OF INTENT AND POLICY OBJECTIVES 2. RESPONSIBILITIES AND ACCOUNTABILITIES FOR HEALTH AND SAFETY 2.1 The Director

More information

Northwards Housing. Asbestos Management Plan. October 2014

Northwards Housing. Asbestos Management Plan. October 2014 rthwards Housing Asbestos Management Plan October 2014 Last Review October 2014 Reviewed by Simon Roffey Issued by Larry Patrick Next Review Due October 2015 1 Table of Content Section Content 1.0 Purpose

More information

Houses of Parliament. Health and Safety Policy Supplement (PS1) Accident and Incident Reporting

Houses of Parliament. Health and Safety Policy Supplement (PS1) Accident and Incident Reporting Health and Safety Policy Supplement (PS1) Accident and Incident Reporting This policy supplement has been prepared by the Parliamentary Safety Risk Management team and endorsed by the Director General

More information

Asbestos Survey Report

Asbestos Survey Report 0340 Asbestos Survey Report Sunnyside Court Avondale Road Southport PR9 0NU Client Contact: Gary Rostron The Regenda Group Regenda House Enterprise Business Park Northgate Close Horwich, Bolton BL6 6PQ

More information

UNIVERSITY HOSPITALS OF LEICESTER NHS TRUST POLICY FOR THE MANAGEMENT OF ASBESTOS

UNIVERSITY HOSPITALS OF LEICESTER NHS TRUST POLICY FOR THE MANAGEMENT OF ASBESTOS UNIVERSITY HOSPITALS OF LEICESTER NHS TRUST POLICY FOR THE MANAGEMENT OF ASBESTOS APPROVED BY: UHL H&S Committee and UHL H&S Committee TRUST REF: B27/2005 DATE APPROVED: March 2008 ORIGINATOR: Glyn Lambley

More information

CAPITAL WORKS GUIDANCE DOCUMENT

CAPITAL WORKS GUIDANCE DOCUMENT COMMUNITY BUILDINGS TRANSFER PROGRAMME CAPITAL WORKS GUIDANCE DOCUMENT This document has been prepared to assist and advise management groups of community buildings who are involved in Durham County Council

More information

The Management of Asbestos. County Council Occupied Premises

The Management of Asbestos. County Council Occupied Premises The Management of Asbestos in County Council Occupied Premises Policy, Strategy and Management Procedures Corporate Building Services November 2005 Policy, Strategy, and Implementation Plan for the Management

More information

Construction (Design and Management) Regulations 2007

Construction (Design and Management) Regulations 2007 MEETING Finance, Procurement and Property Committee AGENDA ITEM 14 MEETING DATE 9 th July 2007 DOCUMENT NUMBER FEP 1052 SUBJECT REPORT Construction (Design and Management) Regulations 2007 (12/06/07) by

More information

Principal Designer Guidance

Principal Designer Guidance Principal Designer Five or more employees 1 CONTENTS INTRODUCTION 3 Further reading / additional resources 3 QUESTION 1: POLICY AND ORGANISATION 4 4 4 QUESTION 2: ARRANGEMENTS/PROCEDURES FOR HEALTH AND

More information

MAIDENHEAD AND DISTRICT HOUSING ASSOCIATION TITLE: PAGE:

MAIDENHEAD AND DISTRICT HOUSING ASSOCIATION TITLE: PAGE: TITLE: PAGE: 1 OF 23 Maidenhead and District Housing Association Asbestos Policy and Management Page 1 of 23 TITLE: PAGE: 2 OF 23 FOREWORD This document details the system for the management of health

More information

Date of issue: January 2014. Date of next review: February 2016. Author: V Thornton. Service area applies to: Operations. Link to the 5 Pledges: Yes

Date of issue: January 2014. Date of next review: February 2016. Author: V Thornton. Service area applies to: Operations. Link to the 5 Pledges: Yes Title: Asbestos Policy 2013 Date of issue: January 2014 Date of next review: February 2016 Author: V Thornton Service area applies to: Operations Link to the 5 Pledges: Yes Approved by: Date approved:

More information

DUTIES and GUIDANCE. for. BOARDS of MANAGEMENT. DEALING with ASBESTOS CONTAINING MATERIALS. before, during & after

DUTIES and GUIDANCE. for. BOARDS of MANAGEMENT. DEALING with ASBESTOS CONTAINING MATERIALS. before, during & after DUTIES and GUIDANCE for BOARDS of MANAGEMENT on DEALING with ASBESTOS CONTAINING MATERIALS before, during & after SCHOOL REFURBISHMENT WORKS, DEMOLITIONS AND BUILDING WORKS PROJECTS CONTENTS CONTENTS...2

More information

CONTRACTOR CONTROL CONTRACTOR SELECTION STANDARDS FOR SAFE WORKING

CONTRACTOR CONTROL CONTRACTOR SELECTION STANDARDS FOR SAFE WORKING CONTRACTOR CONTROL INTRODUCTION When a contractor comes to carry out work at the University, both the contractor and the University have responsibilities for the health and safety aspects of the work.

More information

ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015

ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 Prepared For: (School Name) PREPARED BY: DIOCESE OF JOLIET ENVIRONMENTAL OFFICE FOR ANY ENVIRONMENTAL RELATED EMERGENCY CONTACT: RICHARD

More information

Facilities Management. Facilities Management Asbestos Policy & Management Plan

Facilities Management. Facilities Management Asbestos Policy & Management Plan Facilities Management Facilities Management Asbestos Policy & Management Plan PP&T code FM00174 Version 1.0 Last updated 01 Feb 12 Review Date 08 Aug 13 Owner Unit Approved by Mike Eastwood Facilities

More information

BEDFORD DESIGN GROUP REPORT NUMBER 61892 ASBESTOS SURVEY AT: ALL HALLOWS CAR PARK GREENHILL BEDFORD

BEDFORD DESIGN GROUP REPORT NUMBER 61892 ASBESTOS SURVEY AT: ALL HALLOWS CAR PARK GREENHILL BEDFORD BEDFORD DESIGN GROUP REPORT NUMBER ASBESTOS SURVEY AT: ALL HALLOWS CAR PARK GREENHILL BEDFORD CARRIED OUT BY: VINTEC LABORATORIES LTD SURVEY DATE: 08-01-2009 PREPARED BY: JAMES BROTHERTON CHECKED BY: ANDREW

More information

Property & Infrastructure Support Policy & Guidance

Property & Infrastructure Support Policy & Guidance Asbestos Policy & Procedures» March 2015 Policy & Guidance Asbestos Policy & Procedures Key Document Information Document Owner: Steve Hamilton Job Title Statutory Service Manager (Asebstos) Team ST PI

More information

Report to Cabinet Item 25 June 2014

Report to Cabinet Item 25 June 2014 Report to Cabinet Item 25 June 2014 Report of Deputy Chief executive (operations) 12 Subject Asbestos Management Policy Purpose To consider the council s Asbestos Management Policy. Recommendation To approve

More information

The Newcastle upon Tyne Hospitals NHS Foundation Trust. Asbestos Management Policy and Action Plan

The Newcastle upon Tyne Hospitals NHS Foundation Trust. Asbestos Management Policy and Action Plan The Newcastle upon Tyne Hospitals NHS Foundation Trust Asbestos Management Policy Action Plan Version No.:.3 Effective From: 24 August 205 Expiry Date: 24 August 208 Date Ratified: August 205 Ratified

More information

THE EXECUTIVE 13 APRIL 2004 JOINT REPORT OF THE DIRECTOR OF LEISURE AND ENVIRONMENTAL SERVICES AND THE DIRECTOR OF CORPORATE STRATEGY

THE EXECUTIVE 13 APRIL 2004 JOINT REPORT OF THE DIRECTOR OF LEISURE AND ENVIRONMENTAL SERVICES AND THE DIRECTOR OF CORPORATE STRATEGY THE EXECUTIVE 13 APRIL 2004 JOINT REPORT OF THE DIRECTOR OF LEISURE AND ENVIRONMENTAL SERVICES AND THE DIRECTOR OF CORPORATE STRATEGY ASBESTOS MANAGEMENT IN NON DOMESTIC PROPERTIES FOR DECISION This report

More information

Asbestos Management & Abatement

Asbestos Management & Abatement Asbestos Management & Abatement Latest revised date: October 29, 2012 Page 1 of 18 1.0 LEGAL & LEGISLATIVE REQUIREMENTS This standard provides guidance to meeting the minimum requirements of the Act &

More information

To inform the committee of the arrangements needed to implement an asbestos management action plan.

To inform the committee of the arrangements needed to implement an asbestos management action plan. SAF14-P5 19 February 2014 Subject: Origin: Asbestos Management HSM Purpose of This Paper To inform the committee of the arrangements needed to implement an asbestos management action plan. Action required

More information

University of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS

University of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS Page 1 of 5 The inhalation of asbestos fibers in excess amounts can lead to chronic lung disease. Our knowledge of these health effects comes from studies of workers exposed routinely to high concentrations

More information

Safety Management System

Safety Management System Safety Management System Title: Management of Contractors and Consultants Reference: SSC-PR-#001 Issue date: April 2010 Revision 1.0 Review date: Contents 1 Purpose 2 2 Scope 2 3 Definitions 2 4 Attachments

More information

Policy for the Control of Asbestos

Policy for the Control of Asbestos London School of Economics & Political Science Policy for the Control of Asbestos Final Draft 27.01.2014 Approved by Estates Strategy Committee 00.00.2014 Next Review Date 00.00.2015 London School of Economics

More information

OAKPARK SECURITY SYSTEMS LIMITED. Health & Safety Policy. Requests or suggestions for amendment to this procedure

OAKPARK SECURITY SYSTEMS LIMITED. Health & Safety Policy. Requests or suggestions for amendment to this procedure OAKPARK SECURITY SYSTEMS LIMITED Requests or suggestions for amendment to this procedure should be submitted to the owner of the process PROCESS OWNER: MANAGEMENT TEAM Current version: PREVIOUS VERSION

More information

Health and safety policy

Health and safety policy 1. General statement of intent The Company recognises and accepts its responsibilities as an employer to ensure, so far as is reasonably practicable, the health, safety and welfare of its employees and

More information

Summary of the main steps in managing asbestos (from HSG264) Find out if ACMs present: Check plans/ drawings. Carry out survey (2)

Summary of the main steps in managing asbestos (from HSG264) Find out if ACMs present: Check plans/ drawings. Carry out survey (2) Asbestos The University s asbestos management procedure follows the stages set out in guidance provided by the HSE (HSG64), as follows. (The numbers in the boxes below refer to the subsequent sections

More information

ANGUS COUNCIL SUPPLEMENTARY CONDITIONS OF CONTRACT. SC 01 - Contract Performance Guarantee Insurance

ANGUS COUNCIL SUPPLEMENTARY CONDITIONS OF CONTRACT. SC 01 - Contract Performance Guarantee Insurance SC 01 - Contract Performance Guarantee Insurance For contracts equal to or exceeding 750,000 in value the Contractor shall, within 28 days of the date of the award of the Contract, obtain and provide to

More information

ASBESTOS MANAGEMENT PROGRAM

ASBESTOS MANAGEMENT PROGRAM ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate

More information

Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW

Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW August 2006 NSW Department of Commerce Parsons Brinckerhoff Australia Pty Limited ACN 078 004 798 and Parsons

More information

HEALTH & SAFETY POLICY

HEALTH & SAFETY POLICY HEALTH & SAFETY POLICY 1. STATEMENT OF INTENT & POLICY OBJECTIVES The Council, as the governing body of the School, recognises and accepts the responsibilities placed on it as 'Employer' by the Health

More information