RFI Questions. Reference (Sect/Para/Pag e) QUESTION GOVERNMENT RESPONSE 1 RFP and Drawings

Size: px
Start display at page:

Download "RFI Questions. Reference (Sect/Para/Pag e) QUESTION GOVERNMENT RESPONSE 1 RFP and Drawings"

Transcription

1 PRE PROPOSAL INQUIRY FORM Government Reponse Project Title: NAVFAC - Paint and Repair Building 110 date: 8/23/12 SOLICITATION NO.: # RFI Questions Question No. Reference (Sect/Para/Pag e) QUESTION GOVERNMENT RESPONSE 1 RFP and Drawings The RFP references that this is a Design-Build project, however detailed plans including quantities have been provided. Please clarify the design intent on the project. eyes. There may be more. 2 Enclosure 3, Page 3 Factor 2, Item 2 requires a narrative describing the integration of construction within the existing building, keeping the building in full operation and coordinating the construction with overall building operations. General Note E on the plans, Sheet 1 of 5 indicates that the first floor and balcony will not be occupied during construction. Please clarify the occupancy of the building during construction and provide additional information of any building activities that will need to be coordinated during construction (if any). We expect to close operations during the project. However, since closing has a major negative impact on MWR profits the construction timeframe is 1 Dec to 3 Jan The shorter timeframe the better.

2 3 Asbestos Survey and Small Project Part 3 The contract documents include an asbestos survey with quantities. Then Part 3, F2020 of the contract documents indicates Contractor is to bid per square foot of asbestos containing ceiling or wall material for asbestos abatement. Then it further goes on to say Contractor will include in his bid $10, as reserve fund for asbestos abatement. Are we only to carry the $10, for asbestos abatement in our bid? If not please provide more information as to the expectations/requirements for the asbestos abatement work on our end? Asbestos survey is done in This survey is for reference only. Contractor will do his own HAZMAT survey to make sure asbestos and lead presence. 4 Drawings General Note H on the plans, Sheet 1 of 5 indicates we are to treat all painted surfaces as containing lead and we can dispose the lead as ordinary construction debris. Then the note right below that says lead shall be disposed of as lead waste. Please indicate which is correct? See Note H Last line- Abatement material shall be disposed of as lead waste in accordance with local, Federal, state and NSGL requirements. Part 3 page 16 line one: Contractor shall perform verification testing as required of additional HAZMAT material survey shall be performed 5 Drawings In addition to question 4 above please confirm that all painted surfaces are to be treated as containing lead. If not please provide more information as to the expectations/requirements for the lead abatement work on our end? See Note H Last line- Abatement material shall be disposed of as lead waste in accordance with local, Federal, state and NSGL requirements. Part 3 page 16 line one: Contractor shall perform verification testing as required of additional HAZMAT material survey shall be performed 6 Small Projects Part 3, C3010 of the contract documents indicates we are to repair 690 SF of CMU walls. Please provide more information as to the level of repair required? Are we replacing complete blocks of CMU or only patching? eyes. There may be more. (See specification Part 3 page 4 C3010.)

3 7 Small Projects 8 Small Projects Part 3, C3010 of the contract documents says Construct damaged 20 0 LF wall curb on South West wall 4 0 below ceiling. Please provide more information as to what is required by this note. Part 3, C3030 of the contract documents indicates Contractor is to repair Auditorium ceiling (3,160 SF). Then it indicates ceiling is light weight concrete on wire mesh. Please confirm we are to provide (3,160 SF) of concrete repair at the Auditorium ceiling? eyes. There may be more. eyes. There may be more. (See specification Part 3 page 4 C3010.) Ceiling base construction material is given for information only. General base repair for smooth surface to prepare for paint. Please inspect on the site visit. 9 Small Projects Part 3, C3030 of the contract documents indicates Contractor is to construct 200 SF broken ceiling surface. Please provide more information and detail as to what we are required to construct? Is this full depth concrete repair, eyes. There may be more. partial depth concrete repair? 10 Amendment 2, RFI 3 response Response to RFI #3 confirms we are to furnish a new hazardous material survey and report in our base bid. Please confirm all abatement and monitoring work required based on this new survey will be paid for out of the $10,000 HazMat Allowance. Confirmed

4 11 Amendment 2, RFI 6-9 responses Responses to RFI #6-9 indicates RFP provided quantities for Confirmed. Reminder that this quantitiy is for evaluation wall and ceiling repair are provided for information purposes and is a best guess. Final quantitiy may vary. purposes only, and alludes we are to "inspect with our bare eyes" the extent of the work required. This is an impossible task in a dimly lit auditorium with ceilings 50' above our heads. There is no way to quantify the extent of this work at bid time other than to throw money at it and make a guess. Please confirm quantities of repair work as indicated in the RFP should be used as a basis for our proposal. 12 Amendment 3, RFI 1 response Is this a design/build or bid/build solicitation? RFP Part 2A requires design deliverables, but per the site visit, the Navy is issuing color schemes in forthcoming Amendment. Per same RFP section, construction submittals are to be CQC approved except plaster patch, paint, and colors to be approved by DOR. If the Navy is DOR, there's nothing else to approve. Please clarify who is DOR, Navy or contractor? The Navy will submit a basic color scheme with some detail. The scheme will require design time working with the customer for detailed drawings. 13 RFP Part 3 C3010 Extent of wall paint scope near the stage was limited to vertical round columns and sides of stage. Per discussion at site visit, additional painting of existing plaster surround behind outer most layer of stage draperies at sides and overhead were to be painted as well. Please confirm. The rectangular support just behind the the round columns on the stage is to be painted. The painting is to extend as far as the existing painted surface and no farther.

5 14 Enclosure 3 - Factor 2 The Basis of Evaluation mentions complying with requirements for material specifications, recycling methods and goals, hazardous material disposal, etc. Is it intended for this Basis of Evaluation to be a part of Factor 1, Technical Solution rather than Factor 2 Project Schedule and Phasing? See revised evaluation factors dated 17 August Proposal Please advise if all (3) pages of the RFI issued in Amendment 2 shall be included along with the signed SF30 form in the price book or just page 3 of the RFI that includes the signature lines. Signed RFI response forms shall be submitted in full with the price proposal. Only the most current needs to be sent. 16 Per Walk - Thru What will be required by the GC in regards to the Stage Curtains? The curtains are not to be removed. Carefully pull back to allow access to the required surfaces. Secure until the paint is dry. If dusty prep work is required it may be wise to wrap them in plastic. 17 Per Walk - Thru It was mentioned at the walk - thru that the Lobby was not part of this contract. Please confirm. Confirmed 18 Part 3/Section C30 Base Scope of Work - RFP drawings denote specific locations and square footages for repairs and painting that do not appear to correlate to the specific square footages listed in Part 3/Section C30. Please confirm the base bid is to be based on the quantities specified in Section C30. Confirmed

6 19 Part 3/Section C3030 Ceiling Construction - During the site visit, it appeared the ceiling was cement plaster on wire mesh, but Part 3/Section C3030 indicates it is lightweight concrete on wire mesh. Please provide original building record drawing details and specification for the ceiling construction. Drawings provided on CD 20 Original Building Information - Please provide a complete set of the original building record drawings. Provided on CD 21 Fire Protection Engineer (FPE) As the project scope is limited to existing finish surface repairs and painting, please confirm the services of an FPE are not required for this project. It is the contractor's reponsibility to check the need of technical people. 22 Water Damage It appears some of the damaged surfaces may be the result of water from roof or pipe leaks. During the pre-proposal meeting it was indicated the roof had been recently replaced to resolve the source of the water damage, but water was seen dripping from the ceiling at the underside of the balcony. Please confirm all leaks will be repaired by others prior to the start of this project. The Roof was replaced FY11. If there are leaks they should be repaired prior to the start of construction. However, a check of the area can be done after award to confirm. The contractor is not responsible for leak repairs. 23 It appears that the existing paint is semi-gloss please confirm what the paint finish shall be desired? The recommended paint sheen will be noted in the submitted scheme which is expected to be complete by COB Friday 24 August. This could change before the final paint schedule is completed by the contractor.

7 24 Part 3/Section C30 Since the quantity given in Part 3/Section C30 in the base qty. is for evaluation purposes please revise the proposal sheet to add unit prices for plaster repair and painting. See revised pricing sheet dated 22 August 25 Part 3/Section C30 Part 3/Section C30 indicates repair auditorium ceiling 3,160 sf. Is the 200 sf in addition to the 3,160 sf? Ceiling SF is for reference only. I acknowledge receipt of these RFI responses Firm Name (printed) Name (signed)

MEMORANDUM. General: Foundation:

MEMORANDUM. General: Foundation: MEMORANDUM State of Alaska Department of Transportation and Public Facilities Central Region - Division of Construction and Operations Public Facilities Branch TO: Jennifer Murrel DATE: August 19, 2010

More information

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings CPE Candidate No. 0714108 December 2014 1 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings Table

More information

Saxe Middle School Auditorium Renovation February 4, 2015

Saxe Middle School Auditorium Renovation February 4, 2015 Saxe Middle School Auditorium Renovation February 4, 2015 OVERVIEW OF PRESENTATION Renovation of Saxe Auditorium State & Federal Testing requirements Town Hires Tighe & Bond to perform testing Summary

More information

THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2194 as follows:

THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2194 as follows: Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 14-MC-2194 ADDENDUM NUMBER ONE January 24, 2014 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM Paul Revere School Modernization and Interim Housing ADDENDUM NO.

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM Paul Revere School Modernization and Interim Housing ADDENDUM NO. SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM Paul Revere School Modernization and Interim Housing ADDENDUM NO. 1 PROJECT: Paul Revere School DATE: March 25, 2015 Modernization

More information

OGS LIMITED ASBESTOS & LEAD SURVEY REPORT

OGS LIMITED ASBESTOS & LEAD SURVEY REPORT our people and our passion in every project OGS LIMITED ASBESTOS & LEAD SURVEY REPORT Building 44 Willard Drug Treatment Center 7116 County Road 132 Willard, NY Prepared for: NYSOGS 33 rd Floor, Corning

More information

How To Repair A House

How To Repair A House Assessing Structural Damages Please note-this presentation is only intended to be used as a basic educational tool and is by no means all encompassing. Each property should be treated on a case by case

More information

Asbestos Abatement Work Plan for the Carter Carburetor Superfund Site

Asbestos Abatement Work Plan for the Carter Carburetor Superfund Site for the Prepared for: ACF Industries LLC 101 Clark Street St. Charles, Missouri 63301 Prepared by: AMEC Environment & Infrastructure, Inc. 15933 Clayton Road, Suite 215 Ballwin, Missouri 63011 Project

More information

Fire Damage Repairs, 2510 Burton Street

Fire Damage Repairs, 2510 Burton Street Fire Damage Repairs, 2510 Burton Street Introduction: The Housing Authority of the County of San Joaquin (Authority) is seeking quotes from Class B General Building Contractors (Contractor) to provide

More information

NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS

NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS Rhode Island Department of Education School Building Authority 255 Westminster Street, Providence, RI 02909 Telephone (401)222-4600 Website: www.ride.ri.gov

More information

DIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions

DIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions DIVISION 248 ASBESTOS REQUIREMENTS Asbestos Emission Standards and Procedural Requirements 340-248-0250 Asbestos Abatement Project Exemptions (1) Any person who conducts or provides for the conduct of

More information

CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT. January 2014. Project Management Division

CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT. January 2014. Project Management Division CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT RIGHT: the proposed conceptual profile of the new Joe Redington Sr. JR/SR High School January 2014 Project Management Division New Knik Area Middle/High

More information

Lee, Here are the questions from bidders received between August 17, 2015 and August 24, 2015 followed by our responses.

Lee, Here are the questions from bidders received between August 17, 2015 and August 24, 2015 followed by our responses. Lee Householder Project Homes 88 Carnation Street Richmond, VA 2325 Re: William Byrd Renovation, Addendum 01 August 24, 2015 Lee, Here are the questions from bidders received between August 17, 2015 and

More information

Asbestos WHAT TO DO? Studies of people who were exposed to high levels of asbestos in factories and shipyards, are at increased risk of:

Asbestos WHAT TO DO? Studies of people who were exposed to high levels of asbestos in factories and shipyards, are at increased risk of: Asbestos WHAT TO DO? What Is Asbestos? Asbestos is mineral fiber. It can be positively identified only with a special type of microscope. There are several types of asbestos fibers. In the past, asbestos

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

ASBESTOS AWARENESS PLAN

ASBESTOS AWARENESS PLAN Asbestos Operations and Maintenance Program ASBESTOS AWARENESS PLAN Bryan V. Jandreau, Facilities Manager Dan Bouchard, Superintendent of Buildings Christina Theriault, Human Resource Coordinator Developed

More information

North Carolina State University. Asbestos Management Plan

North Carolina State University. Asbestos Management Plan North Carolina State University 1.0 Introduction Purpose The purpose of this plan is to establish the polices and procedures to be used at North Carolina State University (NCSU) in the management of building

More information

Asbestos Management Program

Asbestos Management Program Asbestos Management Program Facilities and Operations Revision #4: February 17, 2012 Page IMPORTANT Asbestos related incidents must be reported IMMEDIATELY to your supervisor Emergency Contacts During

More information

Estimated Cost of Repair

Estimated Cost of Repair 1 Applicant: Property: Home: Business: Assessor: Applicant Number: Type of Loss: Hurricane Date Contacted: 1/18/2014 Date of Loss: 10/29/2012 Date Received: 1/14/2014 Date Inspected: 2/4/2014 Date Entered:

More information

Rehab Inspection Report Page 1

Rehab Inspection Report Page 1 Rehab Inspection Report Page 1 Home Address: Construction Style: Number of bedrooms Square footage: Value of offer: Estimated rehab cost: Value of resale: Orientation of house: N S E W Note: orientation

More information

Bid Tabulation for IFB #9708 (Asbestos and Mold Abatement Services)

Bid Tabulation for IFB #9708 (Asbestos and Mold Abatement Services) Bid Tabulation for IFB #9708 (Asbestos and Services) Item IES of Marshall, Inc (SERVPRO) B&R Insulation Inc Major Abatement (Pipe Insulation up to 2-inch) Linear Foot (Pipe Insulation up to 2-inch) Linear

More information

Vendor Selection Overview UNIT PRICES FOR ASBESTOS ABATEMENT & DISPOSAL SERVICES VARIOUS SITES

Vendor Selection Overview UNIT PRICES FOR ASBESTOS ABATEMENT & DISPOSAL SERVICES VARIOUS SITES (ATTACHMENT 11) ACTION ON MONTHLY FACILITIES MATTERS: FMS AWARD OF CONTRACTS, RECOMMENDATION AND REQUEST FOR PROPOSAL OFFICE OF THE SUPERINTENDENT 5225 West Vliet Street P O Box 2181 Milwaukee, Wisconsin

More information

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER NOTICE TO PROPERTY OWNER Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. If your home or business is below

More information

LIVING WITH FIBRO JUNE 1998 WORKCOVER NSW HEALTH AND SAFETY NOTES. WorkCover. Watching out for you.

LIVING WITH FIBRO JUNE 1998 WORKCOVER NSW HEALTH AND SAFETY NOTES. WorkCover. Watching out for you. LIVING WITH FIBRO JUNE 1998 WORKCOVER NSW HEALTH AND SAFETY NOTES WorkCover. Watching out for you. Disclaimer This publication contains information regarding occupational health, safety, injury management

More information

Renovations for a New 18 Bed Gero-Psych Nursing Unit August 7, 2014 Lower Bucks Hospital Second Floor 501 Bath Road, Bristol, PA 19007 Addendum No.

Renovations for a New 18 Bed Gero-Psych Nursing Unit August 7, 2014 Lower Bucks Hospital Second Floor 501 Bath Road, Bristol, PA 19007 Addendum No. Charles H. Cross III, AIA, NCARB, LEED AP Charles Cross Architecture, PC Renovations for a New 18 Bed Gero-Psych Nursing Unit Lower Bucks Hospital Second Floor 501 Bath Road, Bristol, PA 19007 Addendum

More information

WINDOW AND DOOR REPLACEMENT REQUIREMENTS

WINDOW AND DOOR REPLACEMENT REQUIREMENTS WINDOW AND DOOR REPLACEMENT REQUIREMENTS Should you have any questions after reading the following information, please call the Building Inspection Department at 651-439-4439 to discuss the topics of concern.

More information

Asbestos Survey Form (See Instructions)

Asbestos Survey Form (See Instructions) Asbestos Survey Form (See Instructions) 777 12th Street, 3rd Floor Sacramento, CA 95814 Office (916) 874-4800 Fax (916) 874-4899 Email: asbestos@airquality.org 1. Purpose of Survey Renovation Demolition

More information

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 BUILDING DIVISION (714) 961-7120 Single Family Residential New Construction, Additions & Alterations Submittal Requirements Required agency approvals

More information

NATIONAL INSTITUTE OF BIOLOGICALS

NATIONAL INSTITUTE OF BIOLOGICALS Short Term Notice Inviting Quotations Quotations No. S.1-36/07/NIB/Engg. (Civil) Invitation to short term quotations for Repairing of damaged gypsum board false ceiling and painting with epoxy paint in

More information

Approved by: UBC ACT Committee

Approved by: UBC ACT Committee The University of British Columbia Asbestos Safety Policy Prepared by: Russell R. English Policy Approved by: UBC ACT Committee Issue Date: April 1, 2004 Replaces: March, 1989 I-B-05 1.0 Policy: This policy

More information

Hartsfield-Jackson Atlanta International Airport s

Hartsfield-Jackson Atlanta International Airport s Hartsfield-Jackson Atlanta International Airport s 2008-09 Closed Projects (Posted 1/6/2009) FC-3007000038C: MISCELLANEOUS BUILT-UP ROOF AND SINGLE PLY ROOF REPAIRS AT H-JAIA Furnish all labor, equipment,

More information

Supplemental Investigation Summary Report

Supplemental Investigation Summary Report 130 Liberty Street New York, New York Supplemental Investigation Summary Report Visual Mold Inspection Summary Prepared for: Lower Manhattan Development Corporation One Liberty Plaza, 20 th Floor, New

More information

SECTION 02 8213 ASBESTOS ABATEMENT

SECTION 02 8213 ASBESTOS ABATEMENT PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification sections shall apply to work of this section.

More information

The Charter School Law establishes the following for charter schools with respect to school construction:

The Charter School Law establishes the following for charter schools with respect to school construction: Charter Schools - School Construction The Charter School Law establishes the following for charter schools with respect to school construction: 1. A charter school may be located in an existing public

More information

NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE GENERAL a. These specifications may be used in whole or in part by any party without

More information

HATFIELD TOWNSHIP DRY CLEANING PLANT PERMIT APPLICATION PROCEDURES

HATFIELD TOWNSHIP DRY CLEANING PLANT PERMIT APPLICATION PROCEDURES HATFIELD TOWNSHIP DRY CLEANING PLANT PERMIT APPLICATION PROCEDURES A Dry Cleaning Plant Operational Permit is required to engage in the business of dry cleaning or to change to a more hazardous cleaning

More information

Asbestos in your home

Asbestos in your home Asbestos in your home How to dispose of Asbestos safely Telephone Number: 01372 732000 contactus@epsom-ewell.gov.uk www.epsom-ewell.gov.uk If you would like a copy of this document in large print, on tape

More information

Asbestos Procedures. Asbestos Products

Asbestos Procedures. Asbestos Products Asbestos Procedures Asbestos Products Where is asbestos known to be located on The Evergreen State College? Please see Appendix A for a list of known asbestos containing materials located on the Olympia

More information

REQUEST FOR PROPOSAL # ----- PROFESSIONAL SERVICES Environmental Engineering Services September 25, 2015

REQUEST FOR PROPOSAL # ----- PROFESSIONAL SERVICES Environmental Engineering Services September 25, 2015 REQUEST FOR PROPOSAL # ----- PROFESSIONAL SERVICES Environmental Engineering Services September 25, 2015 Project: Atlantic Cape Community College Student Success and Career Planning Center Owner: Atlantic

More information

Basement & Foundation Damage

Basement & Foundation Damage Basement & Foundation Damage Please note-this presentation is only intended to be used as a basic educational tool and is by no means all encompassing. Each property should be treated on a case by case

More information

Washington University Asbestos Operations and Maintenance Plan

Washington University Asbestos Operations and Maintenance Plan 1. Purpose Washington University Asbestos Operations and Maintenance Plan 1.1. The purpose of this Asbestos Operations and Maintenance (O&M) Plan is to minimize the potential for exposure to airborne asbestos

More information

Vision Home Inspection

Vision Home Inspection Vision Home Inspection 324 Rams Run Shepherdsville KY 40165-7877 Inspector: James McFadden Property Inspection Report Client(s): Property address: Inspection date: View report summary This report is the

More information

Facts about Asbestos. Council policy

Facts about Asbestos. Council policy Facts about Asbestos Winchester City Council has produced this leaflet to give its tenants advice and information about the possible presence of asbestos in and around their homes. Its content gives general

More information

Triarch Products Over Various Interior Substrates

Triarch Products Over Various Interior Substrates Triarch products work well over a variety of substrates, both for interior and exterior settings. This document will only discuss interior substrates and is not intended to be a technical discussion of

More information

NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS

NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS The (NRDCA) has prepared this document to provide customers and installers information that the industry

More information

Asbestos in Your Home

Asbestos in Your Home Asbestos in Your Home You may have some asbestos in your home, but may not be sure what it is, what it looks like, or what to do about it. Just because asbestos is there doesn't mean there's a problem.

More information

ASBESTOS IN THE HOME

ASBESTOS IN THE HOME ASBESTOS IN THE HOME This information will help you understand asbestos: what it is, its health effects, where it is in your home and what to do about it. Even if asbestos is present in your home, it is

More information

Inspection Item COMMENTS

Inspection Item COMMENTS APPENDIX 9 AFFORDABLE HOUSING PROGRAM INSPECTION CHECKLIST Participating Jurisdiction: Homeowner Name: Assisted Property Address: Date of Physical Inspection of Property: Total Square Footage of Property:

More information

ADDENDUM NO. 2. DATE: September 14, 2015 INVITATION FOR BID: IFB J160004535 Fire Station #22 Roof Replacement Project DATED: August 25, 2015

ADDENDUM NO. 2. DATE: September 14, 2015 INVITATION FOR BID: IFB J160004535 Fire Station #22 Roof Replacement Project DATED: August 25, 2015 ADDENDUM NO. 2 DATE: September 14, 2015 INVITATION FOR BID: IFB J160004535 Fire Station #22 Roof Replacement Project DATED: August 25, 2015 RECEIPT DATE: September 30, 2015 (CHANGED) OPENING DATE: October

More information

Architectural Engineering & Construction Management Proposal

Architectural Engineering & Construction Management Proposal Architectural Engineering & Construction Management Proposal for the Façade Renovation Project at Lauriedale Home Owners Association 58 Laurie Meadows Drive, San Mateo, CA 94403 prepared for Johanna MacDonald,

More information

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1

More information

ASBESTOS ABATEMENT GROUND FLOOR H101 056 227 SF 057 246 SF 054 173 SF 055A 111 SF 051C 336 SF 055 116 SF 051A 116 SF 058 73 SF 051B 47 SF 051D 91 SF

ASBESTOS ABATEMENT GROUND FLOOR H101 056 227 SF 057 246 SF 054 173 SF 055A 111 SF 051C 336 SF 055 116 SF 051A 116 SF 058 73 SF 051B 47 SF 051D 91 SF , ME, ME ACM BOILER COVER AND BREECH INSULATION ACM PIPE FITTING 056 227 SF 057 246 SF ACM PIPE FITTING ABOVE CEILING ACM CEMENTITIOUS CEILING ACM CEMENTITIOUS DOORS ACM INSULATED PIPE EXPOSED ACM DOOR

More information

STICKLEY AUDITORIUM RENOVATION Community and Stakeholder Presentation

STICKLEY AUDITORIUM RENOVATION Community and Stakeholder Presentation STICKLEY AUDITORIUM RENOVATION Community and Stakeholder Presentation APRIL 30, 2014 SCHEMATIC DESIGN PROGRESS Code Study Analysis: key issues and resolutions Seating Analysis of sightlines, seating and

More information

ADDENDUM #1. Can you add the material list per EA or LF, as listed on pages 52 and 53, to the pricing submittal form?

ADDENDUM #1. Can you add the material list per EA or LF, as listed on pages 52 and 53, to the pricing submittal form? ADDENDUM #1 To: All Companies Interested in Submitting a Bid From: Rebecca Johnson, CPPB, Purchasing Agent Bid: Fiber Installation & Maintenance Services for JCN (RFB #PUR0116-127); Dated: February 22,

More information

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

D Sample Notices to Property Owners, Sample Affidavits, and Other Material D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully

More information

PRE-PURCHASE INSPECTION REPORT

PRE-PURCHASE INSPECTION REPORT PRE-PURCHASE INSPECTION REPORT PREPARED FOR: PROPERTY ADDRESS: Waiheke Island DATE: 21 November 2012 Page 1 of 13 (a) This is a report of a visual only, non-invasive inspection of the areas of the building

More information

Request for Proposal

Request for Proposal Request for Proposal Central Library Building Assessment Review Issued by: Regina Public Library P.O. Box 2311 2311 12 th Avenue Regina, Saskatchewan S4P 3Z5 Issue Date: May 22, 2014 Closing Date: June

More information

PROJECT COST ESTIMATES & FEASIBILITIES

PROJECT COST ESTIMATES & FEASIBILITIES PROJECT COST ESTIMATES & FEASIBILITIES Project Cost and budget management Project success elements Scope meet the scope defined for the project Budget It is within established budget Programme It is designed

More information

Phased Building Information Management (BIM) and Modeling Implementation Plan. David J. Gutierrez, AIA September, 2014

Phased Building Information Management (BIM) and Modeling Implementation Plan. David J. Gutierrez, AIA September, 2014 Phased Building Information Management (BIM) and Modeling Implementation Plan David J. Gutierrez, AIA September, 2014 1 Current State: Design and construction data is not shared, maintained, or updated

More information

ADDENDUM 5 TO IFB 5212-BC UNLV UCC DORMITORY COMPLEX HUGHES AND FAIMAN HALLS HVAC AND ROOFING REPLACEMENT. University of Nevada, Las Vegas

ADDENDUM 5 TO IFB 5212-BC UNLV UCC DORMITORY COMPLEX HUGHES AND FAIMAN HALLS HVAC AND ROOFING REPLACEMENT. University of Nevada, Las Vegas ADDENDUM 5 TO IFB 5212-BC UNLV UCC DORMITORY COMPLEX HUGHES AND FAIMAN HALLS HVAC AND ROOFING REPLACEMENT University of Nevada, Las Vegas Purchasing Department 4505 Maryland Parkway Las Vegas, Nevada 89154-1033

More information

Click to edit Master title style Maricopa County Asbestos NESHAP Overview. Valerie Brodeur Asbestos NESHAP Inspector

Click to edit Master title style Maricopa County Asbestos NESHAP Overview. Valerie Brodeur Asbestos NESHAP Inspector Click to edit Master title style Maricopa County Asbestos NESHAP Overview Valerie Brodeur Asbestos NESHAP Inspector Click to edit Master title style Some Asbestos Facts Asbestos is a proven human carcinogen

More information

Asbestos is found naturally in rock formations around the world. It is made up of lots of small fibres.

Asbestos is found naturally in rock formations around the world. It is made up of lots of small fibres. Your Guide to Asbestos March 2010 Many people worry about the health risks of asbestos, but as long as it is not damaged it is unlikely to cause problems. This booklet tells you what you need to know.

More information

ASBESTOS MANAGEMENT PROGRAM

ASBESTOS MANAGEMENT PROGRAM ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate

More information

Asbestos & Lead Program Update Project Managers Toolbox

Asbestos & Lead Program Update Project Managers Toolbox Asbestos & Lead Program Update Project Managers Toolbox November 2008 Ben Kuo Michael Lonon EHS Organization Operations Research Facilities Remote Facilities Training Management Systems Administration

More information

KEEP ASBESTOS YOUR QUICK GUIDE DON T BE AN EASY TARGET THIS GUIDE

KEEP ASBESTOS YOUR QUICK GUIDE DON T BE AN EASY TARGET THIS GUIDE KEEP THIS GUIDE ASBESTOS YOUR QUICK GUIDE DON T BE AN EASY TARGET Asbestos could be in the house or building you are working on right now. Left alone, it isn t dangerous. However, once disturbed, tiny

More information

CONTROL METHODS. There are five ways to control the release of asbestos fibers:

CONTROL METHODS. There are five ways to control the release of asbestos fibers: Control Methods CONTROL METHODS When asbestos containing materials are found in a building, the owner must decide which method or methods will be used to deal with the asbestos. The decision will be based

More information

Regulated Building Materials in Property Management. July 30, 2013

Regulated Building Materials in Property Management. July 30, 2013 Regulated Building Materials in Property Management July 30, 2013 Nicole Gladu Property Redevelopment Business Line Manager URS Corporation Century Square 1501 4 th Avenue, Suite 1400 Seattle, Washington

More information

Preventing Ice Dams on Roofs

Preventing Ice Dams on Roofs Preventing Ice Dams on Roofs Facility Manager November/December 2005 When a roof leaks, facility managers inevitably receive complaints from building occupants. If it is winter, ice dams are often the

More information

Asbestos Awareness Training; Protecting Both Adjusters and Insureds

Asbestos Awareness Training; Protecting Both Adjusters and Insureds Asbestos Awareness Training; Protecting Both Adjusters and Insureds By Everette Lee Herndon Jr. Is a lack of training in asbestos awareness resulting in the insured and others being unnecessarily exposed

More information

HATFIELD TOWNSHIP. FLAMMABLE and COMBUSTIBLE LIQUIDS PERMIT APPLICATION PROCEDURES

HATFIELD TOWNSHIP. FLAMMABLE and COMBUSTIBLE LIQUIDS PERMIT APPLICATION PROCEDURES HATFIELD TOWNSHIP FLAMMABLE and COMBUSTIBLE LIQUIDS PERMIT APPLICATION PROCEDURES A flammable and combustible liquids permit is required to store, transport on site, dispense, use or handle flammable and

More information

Management of Asbestos. Darren Arkins Senior Inspector Occupational Hygiene Unit Chemical Business Services Division

Management of Asbestos. Darren Arkins Senior Inspector Occupational Hygiene Unit Chemical Business Services Division Management of Asbestos Darren Arkins Senior Inspector Occupational Hygiene Unit Chemical Business Services Division Getting it Wrong! Asbestos What is it? With the Naked Eye! Naturally occurring silicates

More information

REGULATIONS for INSTALLATION, MAINTENANCE, and TESTING APPLICATION PACKET

REGULATIONS for INSTALLATION, MAINTENANCE, and TESTING APPLICATION PACKET REGULATIONS for INSTALLATION, MAINTENANCE, and TESTING FIRE SUPPRESSION SYSTEMS APPLICATION PACKET CITY OF NAPERVILLE 400 S. EAGLE STREET NAPERVILLE, Il 60540 PHONE: 630.420.6070 FAX: 630.420.6657 Fire

More information

CITY OF CHICAGO DEPARTMENT OF ENVIRONMENT. CONSTRUCTION or DEMOLITION SITE WASTE RECYCLING RULES AND REGULATIONS

CITY OF CHICAGO DEPARTMENT OF ENVIRONMENT. CONSTRUCTION or DEMOLITION SITE WASTE RECYCLING RULES AND REGULATIONS CITY OF CHICAGO DEPARTMENT OF ENVIRONMENT CONSTRUCTION or DEMOLITION SITE WASTE RECYCLING RULES AND REGULATIONS W hereas, pursuant to Chapters 11-4 and 2-30 of the Municipal Code of Chicago (the Code ),

More information

C P W R. Research & Training

C P W R. Research & Training C P W R Research & Training BCTD / AFL-CIO NIEHS CPWR CPWR Affiliated Unions CONSTRUCTION WORKFORCE Asbestos Workers & Insulators Boilermakers Bricklayers Carpenters & Joiners Plasterers & Cement Masons

More information

Building Code Clarifications - 7. Fire Resistance

Building Code Clarifications - 7. Fire Resistance Building Code Clarifications - 7. Fire Resistance 7.1 (15-12-030) Use of combustibles in Type III construction roof assemblies Code Section (15-12-030) Use of Combustibles was revised on May 17, 2000,

More information

Repair Project for April 7, 2009

Repair Project for April 7, 2009 Repair Project for April 7, 2009 Scope of the Project HVAC Upgrades Roof Replacement Window Replacement/Exterior Openings Science Lab Renovations New Fire Alarm/Electrical AAB (accessibility) Upgrades

More information

CITY OF BELL PROFESSIONAL CONSULTING SERVICES FOR ROOF REPAIRS TO CITY OWNED FACILITIES

CITY OF BELL PROFESSIONAL CONSULTING SERVICES FOR ROOF REPAIRS TO CITY OWNED FACILITIES CITY OF BELL 6330 PINE AVENUE BELL, CA 90201 PH: (323) 588-6211 FAX: (323) 771-9473 CITY OF BELL PROFESSIONAL CONSULTING SERVICES FOR ROOF REPAIRS TO CITY OWNED FACILITIES I. INTRODUCTION City of Bell

More information

The Richard Stockton University ASBESTOS MANAGEMENT PLAN

The Richard Stockton University ASBESTOS MANAGEMENT PLAN The Richard Stockton University ASBESTOS MANAGEMENT PLAN January 2015 Asbestos Management Plan Table of Contents I. Introduction II. III. IV. Definitions Identification of Asbestos Notification and Labeling

More information

G. Common Defects in Buildings - Leakage

G. Common Defects in Buildings - Leakage F. Common Defects in Buildings - Structural 32. Recently, some concrete chips have fallen from the ceiling in my kitchen. There are rusty steel bars and the area in question measures about 300 x 400mm.

More information

NDSU TABLE OF CONTENTS

NDSU TABLE OF CONTENTS NDSU TABLE OF CONTENTS 1.0 INTRODUCTION 2.0 DEFINITIONS AND DESCRIPTIONS 3.0 OPERATIONS AND MAINTENANCE PROCEDURES FOR ACM 4.0 FIBER RELEASE EPISODES 5.0 DEMOLITION INFORMATION 6.0 REMARKS 1.0 INTRODUCTION

More information

HOUSTON ELEMENTARY SCHOOL

HOUSTON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 59,900 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 291 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan HOUSTON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Asbestos NESHAP ISSUES AND QUESTIONS

Asbestos NESHAP ISSUES AND QUESTIONS Asbestos NESHAP ISSUES AND QUESTIONS FIRE-DAMAGED BUILDINGS HOW DOES THE NESHAP APPLY? After the Fire Is Out Building condition can vary widely from smoke damage to complete destruction with variations

More information

RFP VOICE OVER IP PHONE SYSTEM BID: #14-012- BOE

RFP VOICE OVER IP PHONE SYSTEM BID: #14-012- BOE SPECIFICATIONS AND BID FORMS FOR RFP VOICE OVER IP PHONE SYSTEM BID: #14-012- BOE Due on or before 11:00 A.M. ON FRIDAY, MARCH 7, 2014 at the: OFFICE OF THE PURCHASING COORDINATOR CENTRAL OFFICE WESTON

More information

Attachment 5 Electrical Engineering

Attachment 5 Electrical Engineering A. Phase 1, Preliminary Design: The CONSULTANT shall: Attachment 5 Electrical Engineering 1. Ascertain the requirements for each project through a meeting with the Capital Projects Division Manager or

More information

USES and CONCERNS. County of Santa Clara Safety Coordinator Forum

USES and CONCERNS. County of Santa Clara Safety Coordinator Forum ASBESTOS & LEAD USES and CONCERNS County of Santa Clara Safety Coordinator Forum What is Asbestos? A naturally occurring mineral found in certain rocks. This mineral separates into strong, thin fibers

More information

Georgia State University. Urban Life Building Roof Replacement

Georgia State University. Urban Life Building Roof Replacement ENGINEERING AND ENVIRONMENTAL 140 DECATUR STREET SE, ATLANTA, GA 30303 GEORGIA STATE UNIVERSITY - FACILITIES DESIGN & CONSTRUCTION 34 BROAD STREET, SUITE 100 ATLANTA, GA 30303 DRAWING INDEX A-0 PROJECT

More information

Defining who is responsible for items and areas in a Strata Scheme

Defining who is responsible for items and areas in a Strata Scheme www.lpi.nsw.gov.au No: 2011/07 Date: October 2011 Defining who is responsible for items and areas in a Strata Scheme Land and Property Information, a division of the Department of Finance and Services

More information

Estimator: Miami Estimates Business: (305) 395-4362. Date Entered: 04/30/2008

Estimator: Miami Estimates Business: (305) 395-4362. Date Entered: 04/30/2008 Insured: Property: Claim Rep.: Business: Estimator: Miami Estimates Business: (305) 395-4362 Claim Number Policy Number Type of Loss Deductible Dates: Date of Loss: 10/24/2005 Dwelling $0.00 Other structures

More information

ADDENDUM #2 November 4, 2015 IFB-15-881

ADDENDUM #2 November 4, 2015 IFB-15-881 ADDENDUM #2 November 4, 2015 IFB-15-881 Roof Replacement Housing Authority of Kansas City 920 Main Street, Suite 701 Kansas City, MO 64105 NOTICE TO ALL POTENTIAL RESPONDENTS The following addendum to

More information

Asbestos Survey Report

Asbestos Survey Report 0340 Asbestos Survey Report Sunnyside Court Avondale Road Southport PR9 0NU Client Contact: Gary Rostron The Regenda Group Regenda House Enterprise Business Park Northgate Close Horwich, Bolton BL6 6PQ

More information

BUILDING PERMIT APPLICATION APPLICABLE TO CITY LIMITS AND ETJ CHAPTER 18, General

BUILDING PERMIT APPLICATION APPLICABLE TO CITY LIMITS AND ETJ CHAPTER 18, General BUILDING PERMIT APPLICATION APPLICABLE TO CITY LIMITS AND ETJ CHAPTER 18, General Property Address: Property Owner: Lot: Block: Subdivision: Lot Size: Scope of Work: Note: Please attach copies of all general

More information

UNVERSITY HIGH SCHOOL U0018 65-108-9010-0001 500 W. Gregory St. Normal, IL 61761. School Asbestos Management Plan. Supplemental.

UNVERSITY HIGH SCHOOL U0018 65-108-9010-0001 500 W. Gregory St. Normal, IL 61761. School Asbestos Management Plan. Supplemental. UNVERSITY HIGH SCHOOL U0018 65-108-9010-0001 500 W. Gregory St. Normal, IL 61761 School Asbestos Management Plan Supplemental Prepared By: David Martin Management Planner Environmental Health and Safety

More information

Administrative Procedure. Asbestos

Administrative Procedure. Asbestos Administrative Procedure FT107 Asbestos Board Received: January 30, 2012 Review Date: February 2015 Accountability: 1. Frequency of Reports As needed 2. Severity Threshold As needed (eg. Ministry of Labour

More information

LEGAL REVIEW & UPDATE

LEGAL REVIEW & UPDATE LEGAL REVIEW & UPDATE There are lots of laws and regulations designed to protect workers, the general public, and the environment. However, not everyone follows the laws. Many people deliberately break

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-31 31 16.19 (February 2016) -------------------------------- Preparing Activity: NAVFAC Superseding UFGS 31 31 16.19 (August 2014) UFGS 31 31 16.20 (April 2006) UFGS

More information

CITY OF PLANO BUILDING INSPECTION FEE SCHEDULE. Initial Deposit/Fees are due at the time of the submittals. Effective 03/01/10

CITY OF PLANO BUILDING INSPECTION FEE SCHEDULE. Initial Deposit/Fees are due at the time of the submittals. Effective 03/01/10 CITY OF PLANO BUILDING INSPECTION FEE SCHEDULE Initial Deposit/Fees are due at the time of the submittals. Effective 03/01/10 A. Access Control $5.25/$1000.00 valuation of project Electric (if applicable)

More information

THE MINISTRY OF ENVIRONMENTAL PROTECTION, PHYSICAL PLANNING AND CONSTRUCTION

THE MINISTRY OF ENVIRONMENTAL PROTECTION, PHYSICAL PLANNING AND CONSTRUCTION THE MINISTRY OF ENVIRONMENTAL PROTECTION, PHYSICAL PLANNING AND CONSTRUCTION 1389 Pursuant to Article 104 paragraph 1 item 4 of the Waste Act (Official Gazette 178/04, 111/06), the Minister of Environmental

More information

Room ID------- Material ID ASBESTOS Components Positive? Yes, No, Trace, Assumed PISTM-1 White pipe insulation on hot water supply and return throughout building Yes 5-10% CH, 5-15%AM NA NA LF 1400 FLVCT-7

More information

BOROUGH OF NATIONAL PARK APPLICATION FOR A CERTIFICATE OF OCCUPANCY FOR CHANGE OF OCCUPANCY ADDRESS OF PROPERTY FOR INSPECTION CURRENT OWNER

BOROUGH OF NATIONAL PARK APPLICATION FOR A CERTIFICATE OF OCCUPANCY FOR CHANGE OF OCCUPANCY ADDRESS OF PROPERTY FOR INSPECTION CURRENT OWNER BOROUGH OF NATIONAL PARK APPLICATION FOR A CERTIFICATE OF OCCUPANCY FOR CHANGE OF OCCUPANCY ADDRESS OF PROPERTY FOR INSPECTION # BLOCK LOT VACANT YES NO CURRENT OWNER NAME ADDRESS TELEPHONE # PROSPECTIVE

More information

DRAPER ELEMENTARY SCHOOL

DRAPER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1953 BUILDING AREA 54,000 SF CURRENT PROGRAM CAPACITY 250 ENROLLMENT 2008 84 WARD 8 PROPOSED PROGRAM CAPACITY 325 Site Plan DRAPER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information