1 SPECIFICATIONS FOR OFFICE DUCT WORK CLEANING AT ENGINEERING DISTRICT (8-0) BUILDING CONTRACT ADMINISTRATOR 8-0 Mike Miller Tele: Fax: Dale Brenizer Tele: Fax:
2 SCOPE OF WORK 1. Contractor to provide all labor, lifts, and cleaning equipment and supplies needed to clean the duct work on the Ground floor. Service must be complete in one weekend after regular business hours between March 1 st and May 1 st Contractors must sign in and out at Visitors Entrance or payment will not be approved or authorized with no exceptions. This applies to all visits to the facility for work to be done. The contractor log will serve as documentation for hours worked. 3. Bid price must include all labor, lifts, cleaning equipment, and supplies. 4. Work hours are defined as, Friday 3pm 10pm Saturday 8am 6pm Sunday 8am 6pm 5. The contractor shall be responsible for all the permits and approvals needed before the start of any project. All permit applications are to be provided, reviewed, and approved by the Department prior to application being submitted to Pennsylvania Department of Labor & Industry. 6. Copies of all the permits approvals and warranties will be handed over to the Department Representative once work is completed and accepted. 7. Each bidder must attend the pre bid meeting and acquaint themselves with the exiting conditions before the bidding, so he/she is familiar with the conditions to be encountered and type of work that may be required. No claims of unfamiliarity or lack of knowledge or extra work will be allowed for failure to comply with this requirement. 8. Building access will be accommodated by the district office personnel, after hours phone numbers will be provided for the use to make contact, if any questions or issues would arise during these hours of work. 9. The Contract Administrator for the District building is Mike Miller 2
3 Office # Cell # Fax All labor and materials used at the facilities will be documented on a confirmation of service form. This form shall serve as documentation for payment and will be faxed to the District Purchasing Agent at (717) for acceptance by the District Contract Administrator, within 48 hours of completion of work. 11. Contractor will mail original invoices to the Comptroller s office as listed on the Purchase order. 12. The Department may terminate the contract at any time for convenience or otherwise, and, the Contractor shall be bound by the decision. I. Description of Work A. The work under the contract includes but not limited to, furnishing material, equipment to completely clean: The supply and return ductwork for the 5 RTU units 2 exhaust fans and 28 fan coil units and all associated ductwork including supply, return, fresh air intake, and exhaust. Provide HEPA filtered vacuums and dust collection machines to remove the debris per NADCA ACR 2013 Vacuum and wipe all ceiling diffusers and associated dirty ceiling tiles and clean all exterior duct work. Vacuum and clean all RTU units. Seal all leaks in the duct work B. All work shall meet or exceed the HVAC regulations of the Pennsylvania Department of labor and Industry and requirements contained in the latest addition of the NADCA ACR The work shall be performed in accordance with all State and Local laws, codes, and ordinances which relate to the work. C. Material and workmanship shall be guaranteed for a period of one year. The contractor shall be responsible for making any adjustments during this time period due to any defective workmanship. 3
4 II. Authorization to do work A. It is distinctly understood and agreed under this contract that the contractor shall perform such work and furnish such materials as authorized in writing by the District Contact Administrator or his/or her designated representative. III. Equipment maintenance & Use A. All HVAC system cleaning contractor cleaning equipment shall be maintained in good working order, consistent with the applicable jurisdictional requirements. Before any equipment is brought onto the work site it shall be cleaned and inspected to ensure that it will not introduce contaminants into the indoor environment or HVAC system. All equipment shall be serviced as needed to limit possible crosscontamination from poor hygiene, and/ or unsafe operating conditions for service personnel and building occupants. Any activity requiring the opening of contaminated vacuum collection equipment on-site, such as servicing or filter maintenance shall be performed in an appropriate containment area or outside of the building. All collection devices, vacuums and other tools and devices shall be cleaned or sealed before relocating to different areas of the building and before removing the equipment from building Fuel-powered equipment shall be positioned in a location to prevent combustion emissions and air exhaust emissions from entering the building envelope. The HVAC system cleaning contractor shall monitor and manage location of equipment to prevent introduction of combustion emissions into the occupied space. When using vacuum collection equipment exhausting within the building envelope, the HVAC system cleaning contractor shall utilize equipment fitted with HEPA filtration and the equipment shall have a collection efficiency of 99.97% at 0.3 micron particle size. IV. Disposal of debris & Contaminated Materials A. All debris removed from the HVAC System shall be disposed of in accordance with applicable federal, state, provincial and local requirements. To prevent cross-contamination, all contaminated materials removed from the HVAC system shall be properly contained prior to removal from the building. Materials 4
5 deemed to be hazardous by governmental agencies shall be handled in strict accordance with any applicable local, regional or national codes. V. HVAC System Cleaning Requirements A. All cleaning and restoration procedures shall achieve the minimum level of visibly clean or the specified level of cleanliness verification as defined in the contractual documents for components within the project scope of work as defined in NADCA Standard ACR. B. Negative Duct Pressurization Prior to and throughout duration of the cleaning process, the HVAC system and associated air duct shall be kept at an appropriate negative pressure differential relative to the indoor non-work area. This negative pressure differential shall be maintained between the portion of the HVAC duct system being cleaned and surrounding indoor occupant spaces. Under all circumstances, the HVAC system cleaning contractor shall verify pressurization differential during the project. When utilizing vacuum collection equipment exhausting indoors it shall utilize HEPA filtration and the equipment shall have a collection efficiency of 99.97% at 0.3 micron particle size and be capable of retaining dislodged debris. All equipment used to create negative duct pressurization that does not have HEPA filtration shall be exhausted outdoors to a location that would not allow reentrainment. The location is to be determined and agreed on by the department. VI. Service Openings A. The HVAC system cleaning contractor shall utilize service openings, as required for proper cleaning, at various points of the HVAC system for physical and mechanical entry, and inspection. The HVAC system cleaning contractor shall utilize existing service openings installed in the HVAC system where possible. Service openings installed into the system as needed shall not degrade the structural, thermal, or functional integrity of the system and shall comply with applicable UL, SMACNA and NFPA standards, as well as local, regional, and state codes. 5
6 Service openings shall be created in a manner that allows for proper closure and shall not hinder, restrict, or alter the airflow within the air duct. Service opening construction materials and methods shall be in compliance with industry standards and local codes, using materials acceptable under those standards and codes. The HVAC system cleaning contractor shall use duct access doors and permanent panels fabricated with materials classified for flammability and smoke spread if the material is exposed to the internal airstream. All tapes used in the installation and closure of service openings shall meet the requirements of UL 181A. Service panels used for closing service openings in the HVAC system shall be of an equivalent gauge or heavier so as to not compromise the structural integrity of the duct. Service panels used for closing service openings shall be mechanically fastened (screwed or riveted) at maximum every 4 on center and equally spaced. The panel shall overlap the duct surfaces by a minimum of 1 on all sides. Closures must be properly insulated to prevent heat loss/gain or condensation on surfaces within the system. Rigid fibrous glass duct systems shall be resealed in accordance with NAIMA recommended practices. Only closure techniques that comply with UL Standard 181 or UL Standard 181A are suitable for fibrous glass duct system closures. Access and closure of service openings installed in fibrous glass shall be created and closed in such a manner that there are no exposed fibrous glass edges within the system common to the airstream. Any fibrous glass removed during the installation of a service opening shall be repaired or replaced with like material of the same thickness so that there are no breaks or openings that would degrade the R value, service rating or vapor/air barrier characteristics. All service openings shall be closed with materials meeting UL 181 for smoke generation and flame spread. All service openings capable of being re-opened for future inspection or remediation shall be clearly marked and have their location reported to the owner in project report documents. 6
7 Cutting service openings into flexible duct is not permitted. Flexible duct shall be disconnected at the ends as needed for proper cleaning and inspection and shall be properly reconnected. All new and replacement panels shall be painted to match the color of the adjacent exiting ductwork Schedule Pre-bid Meeting: Date: PennDOT Engineering District Herr Street, Harrisburg PA Any questions for Department should be submitted by: Date: To: Melissa Malavenda Fax:
NADCA GENERAL SPECIFICATIONS FOR THE CLEANING OF COMMERCIAL HEATING, VENTILATING AND AIR CONDITIONING SYSTEMS
NADCA GENERAL SPECIFICATIONS FOR THE CLEANING OF COMMERCIAL HEATING, VENTILATING AND AIR CONDITIONING SYSTEMS National Air Duct Cleaners Association 1518 K Street, N.W. Suite 503 Washington, DC 20005 (202)
More informationSECTION 23 01 30.51 HVAC AIR-DISTRIBUTION SYSTEM CLEANING
SECTION 23 01 30.51 HVAC AIR-DISTRIBUTION PART 1 - GENERAL 1.1 SUMMARY A. Section includes cleaning of interior surfaces of HVAC equipment. The HVAC equipment cleaning work includes the following: 1. Air
More information1. Certification: Employ an ASCS certified by NADCA on a full-time basis. 2. Supervisor Qualifications: Certified as an ASCS by NADCA.
PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
More informationConstruction Indoor Air Quality Management Plans for LEED. Matt Gregg, PE, LEED AP
Construction Indoor Air Quality Management Plans for LEED Matt Gregg, PE, LEED AP Agenda What is a Construction IAQ Management Plan? What are the LEED Requirements? What is the Mechanical Contractor s
More informationCandidates Guide. for. Certified Ventilation Consultant (CVC)
Candidates Guide for Certified Ventilation Consultant (CVC) The Certified Ventilation Consultant (CVC) is an advanced, comprehensive certification targeted to highly qualified experts in the field of HVAC
More informationMOLD REMEDIATION PROCEDURES
Page: 1 of 5 1.0 PROGRAM OBJECTIVE The purpose of this procedure is to define the responsibilities, methods, procedures and training required to safely and effectively remove or clean mold-contaminated
More informationDUCT CLEANLINESS FOR NEW CONSTRUCTION GUIDELINES
DUCT CLEANLINESS FOR NEW CONSTRUCTION GUIDELINES Sheet Metal and Air Conditioning Contractors National Association, Inc. 4201 Lafayette Center Drive Chantilly, VA 20151-1209 DUCT CLEANLINESS FOR NEW CONSTRUCTION
More informationRadford University. Indoor Air Quality Management Plan
Radford University Indoor Air Quality Management Plan Spring 2015 Introduction Concerns with Indoor Air Quality (IAQ) have increased since energy conservation measures were instituted in office buildings
More informationUNIVERSITY OF TOLEDO
UNIVERSITY OF TOLEDO SUBJECT: INTERIM LIFE SAFETY MEASURES AND INFECTION Procedure No: LS-08-008 CONTROL PROCEDURE STATEMENT Interim life safety and infection control measures will be implemented to protect
More informationELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1
KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1
More informationACR The NADCA Standard for Assessment, Cleaning, and Restoration of HVAC Systems 2013
ACR The NADCA Standard for Assessment, Cleaning, and Restoration of HVAC Systems 2013 The International Standard Developed by the National Air Duct Cleaners Association (NADCA) ACR-13 Committee Roster
More informationBasics of HVAC Cleaning
Basics of HVAC Cleaning Seminar Outline Residential 1. Types of systems used and why 2. Types of air distribution systems 3. System components 4. Determining the need for cleaning (ACR2002) 5. Project
More informationGuidelines for Mold Remediation (Removal)
Guidelines for Mold Remediation (Removal) Indoor mold growth, water damage, or musty odors should be addressed quickly. Removing mold growth and correcting the underlying cause of water accumulation can
More informationPANDA SPRAY BOOTH FILTER INFORMATION
PANDA SPRAY BOOTH FILTER INFORMATION Our Spray Booth has been designed to reduce the risk of potential hazardous situations occurring. You must adhere to the specifications chart listed below when replacing
More informationBuilding and Grounds Maintenance Checklist
Building and Grounds Maintenance Checklist Name: School: Room or Area: Date Completed: Signature: Instructions 1. Read the IAQ Backgrounder and the Background Information for this checklist. 2. Keep the
More informationDESERT RESEARCH INSTITUTE MOLD ASSESSMENT AND REMEDIATEION PROCEDURE
1.0 Introduction DESERT RESEARCH INSTITUTE This Desert Research Institute (DRI) Mold Assessment and Remediation Procedure was established to assure that consistent and uniform information is provided to
More informationBUILDING DYNAMICS, LLC
BUILDING DYNAMICS, LLC www.building-dynamics.com INDUSTRIAL HYGIENE 1216 Ashton Road Ashton, MD 20861 240.899.6926 (mobile) elight@building-dynamics.com HVAC ENGINEERING 703.963.0824 (mobile) jbailey@building-dynamics.com
More informationMould Mould A Basic Guide
Mould A Basic Guide Summary Mould is a fact of life. Moulds will grow practically everywhere people live and work. Mould is recognized as an occupational hazard for indoor workers as well as outdoor workers
More informationIEQ Management Plan. Denver Museum of Nature and Science ECF Addition
IEQ Management Plan GH Phipps Construction Companies 5995 Greenwood Plaza Blvd., Suite 100 Greenwood Village, Colorado 80111-4710 303.571.5377 PHONE www.ghphipps.com Denver Museum of Nature and Science
More informationHEPA-filtered Negative Air Machines and their Role in Creating Airborne Infection Isolation Rooms with the ECU AnteRoom. Frequently Asked Questions
HEPA-filtered Negative Air Machines and their Role in Creating Airborne Infection Isolation Rooms with the ECU AnteRoom Frequently Asked Questions What is a negative air machine and why do I need one?
More informationKITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS
St. Louis County Department of Public Works Division of Code Enforcement KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS This guideline is intended to provide the homeowner/contractor with the
More informationRemediation of Mold Contaminated Ductwork
Remediation of Mold Contaminated Ductwork Roger G. Morse AIA, Paul Haas CSP, CIH, Dean Zehnter, Andrea Grdina Morse Zehnter Associates The Problem Visible mold growth on interior of liner inside air handling
More informationSpecifications for Removal and Replacement of Water Damaged/Mold Impacted Materials
Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials Park Potomac Place 12500 Park Potomac Avenue Potomac, Maryland 20854 KEM Project # 21703 Prepared for: Park Potomac Place
More informationASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate
More informationAsbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace
More informationThe Embassy of the United States of America invites you to submit an offer for supply and install the following A/Cs:
RFQ number PR4877728 The Embassy of the United States of America invites you to submit an offer for supply and install the following A/Cs: A- Supplying and installing 30 high wall A/C split unit 3HP- 24,000
More informationIEQ-15 Air Distribution System
AIM OF CREDIT To encourage and recognise the design and maintenance of air distribution systems that minimise the risk of particulate and microbial contamination to the internal air supply. CREDIT CRITERIA
More informationInfection Control Risk Assessment Matrix of Precautions for Construction & Renovation
Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Step One: Using the following table, identify the Type of Construction Project Activity (Type A-D) TYPE A TYPE B TYPE
More informationRequest for Proposals for Residential HVAC Services May 12 st, 2015
Request for Proposals for Residential HVAC Services May 12 st, 2015 Project Description: The Cabarrus County Planning and Development Services Department will be administering the Weatherization Program
More informationAir-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association
Air-Conditioning, Heating, and Refrigeration Institute Sheet Metal and Air-Conditioning Contractors National Association GUIDELINE B-1997 ACKNOWLEDGEMENT These guidelines for Roof Mounted Outdoor Air-
More informationALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.252 WELDING, CUTTING, AND BRAZING ( HOT WORK ) SECTION: 3600
OSHA REGULATION: 9 CFR 90.5 WELDING, CUTTING, AND BRAZING ( HOT WORK ) A. POLICY. This procedure follows requirements set forth in 9 CFR 90.5.. This policy applies to all Hot Work operations being done
More informationGramercy Place Condo Association, Inc.
Gramercy Place Condo Association, Inc. UNIT MODIFICATION REQUEST Date of Application: Name of Owner (s): Telephone: (Home) (Cell) E-Mail: Anticipated start date: Anticipated ending date: Permission is
More informationControlling Condensation On CWP Insulation BY ED LIGHT, MEMBER ASHRAE; JAMES BAILEY, P.E., MEMBER ASHRAE; AND ROGER GAY
This article was published in ASHRAE Journal, Decemeber 2014. Copyright 2014 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed electronically or in paper form without
More informationWater Incursion Standard Operating Procedure
Water Incursion Standard Operating Procedure Purpose: To provide a standardized procedure in the event of water incursion into any Penn State University facility. References: A Brief Guide to Mold, Moisture
More informationInfection Control Risk Assessment Matrix of Precautions for Construction & Renovation
Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Step One: Using the following table, identify the Type of Construction Project Activity (Type A-D) TYPE A TYPE B TYPE
More informationASBESTOS SCIENCE TECHNOLOGIES, INC.
ASBESTOS SCIENCE TECHNOLOGIES, INC. P.O. Box 505 Bangor, CA 95914 Phone (530) 518-0934 Email - astinc17@yahoo.com Report for Lincoln Elementary School 1582 Lincoln Road Yuba City, Ca. 95993 Mold Report
More informationAsbestos Work Permit Procedures
These procedures are to be followed by all persons required to perform the following work: Handling, installation or removal of non-friable manufactured products known to contain asbestos provided no sanding,
More informationEACO DOP / PAO TESTING GUIDELINE 2013
2013 Foreword The guideline promotes industry standards for training, equipment, and methodologies for HEPA filter integrity testing of negative air units, vacuums and any other HEPA filtered equipment
More informationREAD AND SAVE THESE INSTRUCTIONS
AUTOMATIC WITH To register this product visit: www.broan.com MODELS MD6T MD8T MD10T READ AND SAVE THESE INSTRUCTIONS FOR RESIDENTIAL USE ONLY Page 1 WARNING TO REDUCE THE RISK OF FIRE, ELECTRIC SHOCK,
More informationPrestige Home Inspection LLC
Cover Page Prestige Home Inspection LLC IAC2/ESA - Mold Assessment and Water Damage Report 555 W. Brook ave., Client's town MI, 48059 Inspection prepared for: Client's name Inspection Date: 10/15/2012
More informationPreventive Maintenance. Learning Objectives: Howdy! Learning Objectives Cont:
Preventive Maintenance Fountain of Youth for HVAC Successful Learning Environment Bonus Strategies James D. McClure, P.E. Action Planning Guide As you listen to this presentation, use the chart in your
More informationBUILDING ASSESSMENT QUESTIONNAIRE. B. TENANTS Is there more than one tenant in the building? YES
Department of Health and Human Services, Division of Public Health Occupational and Environmental Epidemiology Branch 1912 Mail Service Center, Raleigh, North Carolina 27699-1912 BUILDING ASSESSMENT QUESTIONNAIRE
More informationContract for Weatherization Management Address City & State
I. Parties Contract for Weatherization Management Address City & State This contract is made and entered into on and specifies the terms of the agreement between Client Name, homeowner, and Sherlock Homes
More informationInfection Control Risk Assessment : the Infection Preventionist s Role in Construction
Infection Control Risk Assessment : the Infection Preventionist s Role in Construction Key Concepts Use of ICRA is an important element in an infection prevention program Should be an integral part of
More informationAir Conditioning Equipment
1. PURPOSE OF THIS DOCUMENT This document has been written to assist DCC Premises Managers in obtaining quotations for the ongoing servicing and maintenance of where fitted to their premises. Specialist
More informationOwner s Manual Model 5000 Safety, Operating and Maintenance Instructions
Electronic Air Cleaner 90-1147 Owner s Manual Model 5000 Safety, Operating and Maintenance Instructions READ AND SAVE THIS MANUAL WARNING 120 Volts may cause serious injury from electrical shock. Disconnect
More informationHVAC Design Requirements
Maintenance of HVAC HVAC Design Requirements Air Flow Diagram แบบ Recirculation Air Flow Diagram แบบ Once Through Definition Of Conditions As built At rest In operation air air air Maintenance GMP Requirements
More informationTerms of Reference Air Handling Unit (HVAC System) Cleaning
Terms of Reference Air Handling Unit (HVAC System) Cleaning Introduction General cleaning of the air handling units is currently undertaken by the Mechanical Division staff composing of 3 personnel. Cleaning
More informationhave been provided with information on whether they do or do not contain asbestos before starting work;
Health Effects of Asbestos If your work involves possible exposure to asbestos, you should: be aware of the risks from asbestos exposure; understand the importance of keeping exposure as low as possible;
More informationOakland Unified San Jose Unified Stanford University Santa Ana Unified Newhall Unified Clovis Unified Merced Union High School Grossmont Union High
Oakland Unified San Jose Unified Stanford University Santa Ana Unified Newhall Unified Clovis Unified Merced Union High School Grossmont Union High School District Industry Standards Damage Assessments
More informationUV100A Ultraviolet Air Treatment System
UV100A Ultraviolet Air Treatment System INSTALLATION INSTRUCTIONS APPLICATION When installed in forced air heating and cooling systems, the UV100A Ultraviolet Air Treatment System kills airborne microorganism
More informationCONTROL METHODS. There are five ways to control the release of asbestos fibers:
Control Methods CONTROL METHODS When asbestos containing materials are found in a building, the owner must decide which method or methods will be used to deal with the asbestos. The decision will be based
More informationBefore You Start an Energy Efficiency Retrofit The Building Envelope
ABOUT YOUR HOUSE Before You Start an Energy Efficiency Retrofit The Building Envelope The building envelope is the outer layer of the building that separates the indoor living space from the outdoor environment,
More informationMold Response and Remediation Plan
1.0 Policy Statement The University of New Haven has developed a mold response and remediation plan in accordance with best practices set forth by the Environmental Protection Agency (EPA), Occupational
More informationWalkthrough Inspection Checklist
Walkthrough Inspection Checklist This checklist is to aid during an IAQ Walkthrough of the school. The checklist includes considerations both inside and outside the school building: Instructions: 1. Read
More informationMOLD RESPONSE AND REMEDIATION PLAN
MOLD RESPONSE AND REMEDIATION PLAN Prepared By: Triumvirate Environmental Developed: April 2011 Last Revised: March 2015 Program Approval Associate Vice President of Public Safety & Administrative Services
More informationThe Basics of Commercial Kitchen Exhaust Cleaning
The Basics of Commercial Kitchen Exhaust Cleaning ANSI/IKECA C 10 ANSI/IKECA C 10: Standard for Cleaning of Commercial Exhaust Systems IKECA Introduces the Kitchen Exhaust Cleaning Industry s First American
More informationKey energy-efficient features of your new home
Key energy-efficient features of your new home Your thermal envelope The thermal envelope, or shell, of your home (walls, roof and floor) is designed to keep you dry and comfortable. It protects you from
More informationHVAC Checklist - Long Form
HVAC Checklist - Long Form Page 1 of 14 Appendix B discusses HVAC system components in relation to indoor air quality. utside Air Intake Location pen during occupied hours? Unobstructed? Standing water,
More informationComponents HVAC General Standards HVAC Guidelines HVAC System Selection Life Cycle Cost Analysis
Components HVAC General System Selection Life Cycle Cost Analysis Outdoor Air Design Values Indoor Air Design Values Outdoor Air Ventilation Welding Ventilation Temperature Control Systems Ductwork HVAC
More informationResidential Duct Systems for New and Retrofit Homes
Residential Duct Systems for New and Retrofit Homes Why it is important to properly design and install high quality, efficient ducted air systems? The efficiency of air distribution systems has been found
More informationProcedures for the Effective Use of Biological Safety Cabinets
Procedures for the Effective Use of Biological Safety Cabinets APPROVAL DATE BY BIOHAZARDS SUBCOMMITTEE: August 10, 2012 SUPERSEDES: March 1, 2012 This corporate guideline/procedure is intended as a minimum
More informationDEPARTMENT OF CODES AND BUILDING SAFETY FLOOD RECOVERY INFORMATION
May 2010 DEPARTMENT OF CODES AND BUILDING SAFETY FLOOD RECOVERY INFORMATION GUIDELINES FOR PERMITS ASSOCIATED WITH THE REPAIR OF FLOOD DAMAGED HOMES AND BUILDINGS The Department of Codes and Building Safety
More information07 21 19 Guide Specification STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM
07 21 19 STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM 7819 Broadview Road Cleveland, OH 44131 800-522-4522 February, 2011 SPEC NOTE: This guide specification is intended for use when specifying
More informationHouston ISD Deadly Middle School RR Renovations- Phase 3 VCS Architects, LLC
SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SECTION REQUIREMENTS A. Use Charges: Installation and removal of and use charges for temporary facilities shall be included in the
More informationMUNICIPALITY OF THAMES CENTRE COMMUNITY SERVICES AND DEVELOPMENT RECREATION
REPORT NO. PR-019-15 MUNICIPALITY OF THAMES CENTRE COMMUNITY SERVICES AND DEVELOPMENT RECREATION TO: Mayor and Members of Council FROM: Liz Murray Recreation and Facilities Manager DATE: July 13, 2015
More informationGUIDELINES FOR INSTALLATION OF AIR CONDITIONING UNITS 174-180 PHILLIP STREET, SYDNEY
GUIDELINES FOR INSTALLATION OF AIR CONDITIONING UNITS 174-180 PHILLIP STREET, SYDNEY July 2008 1.0 SCOPE These guidelines describe the way in which air conditioning units shall be installed or replaced
More informationSpray Booth Guideline
Department of Development Service 135 North D Street, Perris CA. 92570 Phone: (951) 443-1029 Fax: (951) 943-3293 PURPOSE The intent of this guideline is to provide the information necessary to ensure that
More informationRestoring your Property: How to be prepared for Rapid Response to Flood Damage
Restoring your Property: How to be prepared for Rapid Response to Flood Damage After a flood, the restoration process can be long and complex, particularly for large commercial properties. Failure to apply
More informationDESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS
DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS A. SCOPE 1. This information is intended to assist contractors, installers and code officials in the proper design and installation of flexible
More informationStaff shall ensure that airflow is not obstructed by the blocking of ventilators with posters, furniture, books, or other obstacles.
1 Environmental Safety AR 3514 The Superintendent may designate and train one or more employees to oversee and coordinate the district's environmental safety program(s). The responsibilities of the coordinator(s)
More informationIndoor Environmental Quality Management Plan
RILLION PUBLIC SCHOOL BOARD OF EDUCATION SERIES 700: SUPPORT SERVICES FILE: 737 Indoor Air Quality Management Brillion Public Schools Indoor Environmental Quality Management Plan 1. Mission Statement School
More informationOld Dominion University Mold Management Plan
OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY 5255 Hampton Blvd. Spong Hall, suite 2501 Norfolk, Virginia 23529 Phone: (757) 683-4495 Fax: (757) 683-6025 Occupational Safety & Health Environmental Health Laboratory
More informationASBESTOS AWARENESS IN THE WORKPLACE. This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation.
ASBESTOS AWARENESS IN THE WORKPLACE This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation. Featured are: INTRODUCTION: A brief description of the program and the
More informationRisk Bulletin. Mold Prevention and Control for Mechanical and HVAC Contractors. XL Group Insurance
XL Group Insurance Risk Bulletin Mold Prevention and Control for Mechanical and HVAC Contractors Mechanical contractors have an inherent risk of mold claims arising out of the heating, ventilation, and
More informationSECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront
PART 1 GENERAL 1.01 Work Included SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS System 402 Flush-Glazed Screw Spline Storefront A. Furnish and install aluminum architectural storefront system
More informationASTACEA4 Inspect complex/central air conditioning systems
Overview This Unit covers the competences required to inspect complex/central air conditioning systems as defined by the CIBSE TM 44 Figure 1.1: Summary of system types and their component parts. The air
More information2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT
Presentation Synopsis Heating, Ventilating and Air Conditioning Building Condition Assessment Vancouver, B.C. Prepared for: EPIC Prepared by: Douglas Spratt, P.Eng Douglas Spratt & Associates Ltd. www.dspratt-associates.com
More informationUI Procedures for Asbestos Management
UI Procedures for Asbestos Management The University of Iowa Rev.12/12/2012 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing
More informationa. Proposals shall be submitted in a sealed envelope and addressed as follows:
1 CITY OF ATCHISON REQUEST FOR QUALIFICATIONS & PROPOSAL HVAC SERVICES JANUARY 1, 2014 THROUGH DECEMBER 31, 2014 DUE: DECEMBER 10, 2013 10:00 A.M. The City of Atchison (City) invites interested and qualified
More informationEXHIBIT A SCOPE OF WORK
EXHIBIT A SCOPE OF WORK 1. (Contractor) shall provide fire alarm system maintenance/repair/testing services as described herein to the California Department of Veterans Affairs (hereinafter CDVA, CalVet,
More informationSTATEMENT OF WORK (SOW) 2. Contract Title. HEPA Supply/Exhaust fans for Clean room USP 797 Compliance
1. Contracting Officer s Representative (COR). STATEMENT OF WORK (SOW) Name: Oscar Garcia Section: Engineering Address: 3350 La Jolla Village Dr. 92161 Phone Number: Fax Number: E-Mail Address: Oscar.garcia2@va.gov
More informationSafe Operating Procedure
Safe Operating Procedure (Revised 07/09) HOT WORK PERMIT OPERATIONS (For assistance, please contact EHS at (402) 472-4925, or visit our web site at http://ehs.unl.edu/) Authority In recognition of the
More informationMarch 2007. Get The Mold Out: Mold Clean-Up Guidance for Residences. Introduction
March 2007 Connecticut Department of Public Health Environmental Health Section Environmental & Occupational Health Assessment Program 410 Capitol Avenue MS # 11EOH, PO Box 340308 Hartford, CT 06134-0308
More informationMOISTURE MANAGEMENT DURING THE CONSTRUCTION PROCESS
MOISTURE MANAGEMENT DURING THE CONSTRUCTION PROCESS Ed Light 1,*, James Bailey 1, and Roger Gay 1 1 Building Dynamics, LLC, Ashton, MD (USA) *Corresponding email: ELight@building-dynamics.com Published
More informationArt Basel Miami Beach Dec 3 6 2015 Booth Design Regulations
1 6 1 BOOTH CONSTRUCTION The Art Basel in Miami Beach form an integral part of the contract between the exhibitor and Art Basel U.S. Corp. (see Art Basel in Miami Beach Exhibition Regulations). The following
More informationSECTION 23 81 03 - PACKAGED ROOFTOP AIR CONDITIONING UNITS NON-CUSTOM
SECTION 23 81 03 - PACKAGED ROOFTOP AIR CONDITIONING UNITS NON-CUSTOM PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Packaged rooftop air conditioning unit (5 tons and smaller). 2. Roof curb. 1.2
More informationHVAC Air Duct Leakage. Eli P. Howard, III Group Director Technical Resources SMACNA
HVAC Air Duct Leakage Eli P. Howard, III Group Director Technical Resources SMACNA Key Variables that Affect the Amount of Leakage Static Pressure Amount of Duct Openings in the Duct Surface Seams, Joints,
More informationQuestions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project
Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project The Watergate Community is currently in the process with the fire suppression and interior renovations
More informationReplacement of Heating, Ventilation, Air Conditioning (HVAC) Units In Apartments Located at 641 Fifth Avenue. Photo Essay
Original HVAC Units: Replacement of Heating, Ventilation, Air Conditioning (HVAC) Units In Apartments Located at 641 Fifth Avenue Photo Essay One fan motor draws air from the lower section of the unit,
More informationCeiling Mount Air Handler Manual
www.surna.com 303.993.5271 Ceiling Mount Air Handler Manual Models: CMAH12, CMAH18, CMAH24, CMAH30, CMAH36, CMAH48, CMAH60 Revised: September 2014 Table of Contents Warranty Information 4 Limited Warranty
More informationProject Close Out Summary
Project Close Out Summary 1. Final Cleaning and Inspection 2. Testing and Certification 3. Demonstration of Systems and Equipment 4. Inspections by Authorities Having Jurisdiction 5. O&M Manuals and As
More informationFire Safety Requirements for Child Care Centre
Fire Safety Requirements for Child Care Centre A. Restrictions on Location Child care centre shall not be located : - (a) (b) in any premises designed for residential use; in any industrial building, warehouses,
More informationNotice to Property Owners
Modification or Repair of your Flood Prone Property Notice to Property Owners Rebuilding or Remodeling Your Home If your home or business sustained damage, or if you are making improvements to the structure
More informationCONTRACTOR GUIDELINES
CONTRACTOR GUIDELINES WORKING IN NEIGHBORHOODS (WIN) HOUSING DIVISION 175 East Second Street, Suite 580 Tulsa, OK 74103 Telephone 918.576.5552 Fax 918.699.3239 Website www.cityoftulsa.org/housing Email
More informationOffice of the State Fire Marshal. Fire Rated Doors
Office of the State Fire Marshal Fire Rated Doors Fire Rated Doors These doors serve a purpose. They are manufactured in a way that is to help reduce the spread of fire and smoke. Fire rated doors allow
More information701210-393. 28 August 2014. Toronto Catholic District School Board Catholic Education Centre 80 Sheppard Avenue East North York, Ontario M2N 6E8
Toronto Catholic District School Board Catholic Education Centre 80 Sheppard Avenue East North York, Ontario M2N 6E8 Attention: Re: Ms. Kathleen Wilson Safety Officer, Accident Prevention, Occupational
More informationSTANDARD OPERATING PROCEDURES FOR MOLD REMEDIATION
West Virginia University Environmental Health and Safety STANDARD OPERATING PROCEDURES FOR MOLD REMEDIATION Origination Date August 2013. Contents Purpose:... 2 Job Scope... 2 Definitions... 2 Roles/Responsibilities:...
More informationSprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW
Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW August 2006 NSW Department of Commerce Parsons Brinckerhoff Australia Pty Limited ACN 078 004 798 and Parsons
More informationSECTION 23 05 12 GENERAL PROVISIONS FOR HVAC WORK
SECTION 23 05 12 GENERAL PROVISIONS FOR HVAC WORK 1 GENERAL 1.1 GENERAL REQUIREMENTS A. This Section is coordinated with and complementary to the General Conditions and Supplementary General Conditions