Session Twelve: Protective Earthing, Impacts, Myths and Verification Tests

Size: px
Start display at page:

Download "Session Twelve: Protective Earthing, Impacts, Myths and Verification Tests"

Transcription

1 Session Twelve: Protective Earthing, Impacts, Myths and Verification Tests Paul Lo MIE Aust., Chartered Professional Engineer Abstract Protective earthing is essential for electrical safety and power system reliability and stability. The effectiveness of protective earthing design and installation affects not only the adequate clearance of the life critical electrical faults, but also the power system reliability and availability. The ineffective protective earthing will lead to the potential hazardous ground voltage (potential ) rise during the ground fault and the prolonged ground potential rise (GPR) will have significant impacts on: 1. Dangerous touch and step voltages 2. Unreliable voltage stability 3. The LV telecommunications insulation breakdown 4. The hazards in the interconnected installations, e.g. equipotential bonding equipment, plumbing, etc. The severity of potential rise and the safety protection with satisfactory fault clearance are dependent on the electrical earthing design and verification testing. The myths of protective earthing in Electrical design: Protective Earthing safety design beyond the limits of MEN Earthing system. Earth leakage disconnection Insulation breakdown of the telecommunications Protective earthing for ground fault damages control and system reliability Practical review of the most common verification tests of the protective earthing: Simple grounding Impedance measurement Traditional current injection tests Off-frequency current injection test. 1

2 Introduction Protective earthing is essential for electrical safety and power system reliability. The effectiveness of protective earthing design and installation affects not only the adequate clearance of the life critical electrical faults but also the power system reliability, stability and availability. 2.0 The ineffective protective earthing will lead to the potential hazardous ground voltage (potential ) rise during the ground fault and the prolonged ground potential rise (GPR) will have significant impacts on: 2.1 Dangerous touch and step voltages 2.2 Unreliable voltage stability 2.3 The LV telecommunications insulation breakdown 2.4 The hazards in the interconnected installations, e.g. plumbing 3.0 The severity of potential rise and the safety protection with satisfactory fault clearance are dependent on the electrical earthing design and verification testing. 3.1 In Australia, the best illustration of our MEN system can be found in Fig B5, AS When the normal (healthy) MEN installation with most of the fault current is conducted by the active and the neutral (return) conductor, the fault current through the earth electrode is minimal and the earth electrode service mainly as the zero reference point for earth potential. 3.3 However when the fault current through the earth electrode is significant due to unhealthy MEN installation (or excessive long feeder with high neutral impedance) the earth potential rise becomes critical to the safety. For illustration the earth fault dynamic with 100A circuit and Type D Circuit breaker, The fault current can be 1250 Amp with 240V and 0.19 ohm ELI, before the CB trips to protect the fault damages. Then, if the fault impedance of neutral conductor diverts 2% maximum fault current to the main earth conductor and the earth electrode with 25 Amp.. The earth grid and main earth conductor with traditional expectation of 2 ohm impedance will have 50 volt GPR,; whilst 5 ohm impedance due to installation degradation will have 125 volt GPR, well above the 50 volt safety limit voltage. 3.4 The HV motor installation and Harmonic dynamic of local Earth potential rise can further endanger the public and any live in contact. 4.0 The Protective Earthing Installation is dictated by various earthing connection systems, and forms the most critical integration of safety earthing protection. AS3000 clause 5.1.4, stipulates various earthing connection systems as alternative to achieve the electrical safety design for mining, direct earthing to IEC60364, direct earthing etc. 4.1 The most common earthing connection system includes IT, TT and TN systems TN System= One of the points in the generator or transformer is connected with earth, usually the star point in a three-phase system. The body of the electrical device is connected with earth via this earth connection at the transformer. TN-C-S system is the most common MEN system with additional configuration of: 2

3 C= Combined Neutral and protective conductor in consumer mains, submains and feeders. S= Separate neutral and earth protective conductors within the electrical services installation TT System - The protective earth connection of the consumer is provided by a local connection to earth, independent of any earth connection at the generator IT system - The electrical distribution system has no connection to earth at all, or it has only a high impedance connection. It use is limited for some special electrical installation when double insulation and /or the insulation monitoring device to monitor the impedance are used. 4.2 Comparison of Earthing Connection Systems Earth fault loop impedance High Highest Low RCD preferred? Yes Yes Yes PE conductor cost Low Low High Risk of broken neutral No No High Safety Safe Less Safe Safe Electromagnetic interference Least Least Low Safety risks Advantages TT High loop impedance (step voltages) Safe and reliable IT Double fault, overvoltage Continuity of operation, cost TN-C-S(= MEN) Broken neutral Safety and cost 2 Protective Earthing installation is made to: safely carry a fault-to-ground; provide a low impedance path-to-ground; eliminate step and touch potential; or Provide a stable reference voltage. Myths of protective Earthing in electrical design: As the Earthing protection installation is critical to the effective safety protection of the electrical services, more attention is therefore required on the risk control and validation of the effective Earthing installation. The following myths of protective Earthing installation must be taken into account: 2.1 MEN Earthing system limits and beyond Protective earthing system safety design is generally guided by AS3000 on MEN system. However there are limits of MEN application, and the effectiveness of protective earthing is subject to the earth loop impedance measurement is low 3

4 enough to clear any earth fault with the circuit protection device, as per Section 8 of AS3000. A long final sub-circuit will most likely defeat the safety protection of the MEN earthing installation when the distance exceeds the Table B, AS3000. It is not uncommon to have more than 200m final sub-circuits to serve the boundary lighting and control devices, in a bigger industrial compounds or infrastructure installations. Protective MEN earthing system must have a low earth loop impedance, that can activate the automatic circuit protection device to clear the earth fault within the time threshold limits of electrical safety. To ensure the effective earthing protection, either MEN earthing system has to be modified or replaced with non-men earthing system. In most cases, the MEN system with additional MEN link(s) in accordance with the Out-building Earthing design will be able to compensate the earth loop impedance to satisfy the time limit of the safety clearance with the time curve of the Circuit Protection Device. If the earth loop impedance is so high, that MEN cannot provide effective protection for electrical faults, then, TT or IT protective earthing design my be required, as stipulated in AS Protective earthing design with Earth Leakage Protection Relay. When MEN earthing system cannot provide effective protection, other earthing system with earth leakage disconnection can be used for safety protection to clear any earth fault and protect human from electrical shocks. It can be either voltage or current based. Voltage based earth leakage protection relay disconnects the power system when dangerous voltage is sensed on the protection earth conductor, immediately. Current base earth leakage protection relay is the famous RCD that protects not only earth fault but also the inadvertent direct contact of human with the live conductors. 2.3 Risk of insulation breakdown of telecommunications The ground potential rise due to power system ground fault may cause telecommunications insulation breakdown and endanger the worker on the affected circuit. Telecommunication installations are design for safety LV and it insulation may be far below the integrity of power system earth fault; thus shall be gauged with the severity of the GPR during the real power system ground fault. 4

5 Physical segregation and/or earthed effective equipotential bonding barrier are necessary to keep the telecommunications safety and integrity, as per AS/S Protective earthing design for Ground fault damage control The Protective earthing design shall construct a sound grounding system with earthing electrode (and grid) to eliminate any potential hazardous ground voltage (potential) rise (GPR) during the ground fault and control the ground fault damages to human and equipment. The effective grounding system shall anchor the earthing reference to the power system for safety and power system stability; under all available electrical faults. Touch and step voltage shall be effectively controlled for site safety. The grounding system must be effective over time without aging degradation to endanger people and equipment, in case of the earth fault. The grounding system must allow the circuit protection device to clear the earth faults timely for electrical safety and selectively discrimination for the highest power system reliability and stability. 2.5 Effect of Leakage stray current and voltage on Earthing installations beyond the scope of safety earthing protection Stray voltage and current is another issues with the power system earthing installations. Stray voltage is the occurrence of electrical potential between two objects that ideally should not have any voltage difference between them, due to small leak current between two grounded objects in distant locations, commonly due to normal stray current flow in the power system. However the most significant stray current damage of electrolysis (galvanic) corrosion is mainly limited to Direct Current only. However, the electrical earthing has side effect with stray current and voltage, that is not directly applicable to electrical safety, hence not further pursued in this paper. 3 Practical review of the most common verification tests of protective earthing grounding system: The severity of potential rise and the safety protection with satisfactory fault clearance are dependent on the electrical earthing design and verification testing. Protective earthing system shall be able to conduct the maximum fault current and the touch and step voltage does not exceed the safety limit. However, soil is not a very good conductor. Only when the area of the earthing path for current is large enough and earth grids/ electrodes are effectively installed and connected, resistance can be quite low and the earth can be a good conductor. 5

6 The Grounding system testing provides a valuable feedback for design verification. The ground system testing does not only ensure that the ground faults can be adequately detected and cleared by the protective device but also control the risk of hazardous high ground grid voltage rise and consequently dangerous touch and step voltages. The impedance of a grounding system is the resistance of soil to the passage of current and tested to: ensure the earth electrode is adequate for the grounding design of electrical safety and power system reliability; monitor the condition of the grounding system over time Check the grounding is operating correctly and no voltage hazard exist both for the people and equipment. Various Earthing impedance measure methods for safety verification and validation are available at different price and the effectiveness of Earthing impedance measurement depends on various applications/influences from harmonic interferences and surges. 3.1 Simple Impedance measurement with 2 point and 3 point methods The simplest and most common method of the ground system test is the earth fault loop impedance measurement with 2 and 3 point methods. In MEN system, the earth fault loop impedance can then be measured by a simple portable tester. However, portable tester may not work for measuring touch and step voltages risks, because long testing leads are required between the ground grid, meter and the test point and also the followings may limit the success of the portable testers: Electrical noise on the ground grid from power system equipment Very low grid impedance (less than 5 ohm) Very large and or extensive ground grid. Ground systems have residual voltages not only at the power system foundation but also harmonic frequencies, due to unbalanced loads, electrostatic and electromagnetic inductions. This frequently leads to noise of stray voltage and current on the protective earthing system. 3.2 Traditional Current injection tests Current injection at the broad band can be used to test the grounding system where the portable ground testers are unsuitable to distinguish between the test signal and any unwanted noise. This traditional high current injection method swamps any noise on the system and can use the traditional RMS wide band multi-meters with a significant power source 6

7 that can dominate the NOISE of the grounding system at the power system foundation frequency. However the required power source for broad band ground system current injection test can be prohibitively high and unrealistic in some electrical installations. The high injection current may also heat up the earthing electrodes/ grid and dry out the grounding surrounding; hence the voltage measurement will not be consistent for the duration of the test. 3.3 Off-frequency current injection test Off-frequency injection using a unique signal is a discrimination method against the interference signals. Off-frequency injection method can measure low injected signal levels with much higher background noise. Off-frequency injection testing requires a frequency locked current injection generator that can tolerate limited induced current and inject constant current (typically less than 100A) for ground system voltage measurement. The injection test frequency is locked away from the foundation and harmonic frequencies to test with an unique signal. A tuned voltmeter shall measure the ground voltage (GPR) due to the current injection but reject the power system noise on the ground system. The remote ground, free from earth fault impacts, is determined when the GPR measurement of the current injection test is relatively constant with the distance away from the injection electrode, as the rate of increase in GPR will decrease with the separation increases from the grounding system. 4 Conclusion AS3000 requires the protective earthing fault-loop impedance must be low enough to permit the passage of current necessary to operate the circuit protective device. The protective earthing system must be maintained properly and verified effectively for safety and risk control. This paper focuses on the verification and validation of effective earthing installation. References AS3000 BS7430 Code of electrical installation Code of Practice for Earthing, British Standards Institute 7

CHECKING AND TESTING ELECTRICAL INSTALLING WORK

CHECKING AND TESTING ELECTRICAL INSTALLING WORK CHECKING AND TESTING ELECTRICAL INSTALLING WORK Department of Consumer and Employment Protection Energy Safety Preface It is a requirement of the Electricity (Licensing) Regulations 1991 that all electrical

More information

PROTECTION AGAINST ELECTRIC SHOCK by John Ware

PROTECTION AGAINST ELECTRIC SHOCK by John Ware 16 become live under fault conditions. The potential of the metal enclosure is higher than that of the main earthing terminal of the installation (and that of Earth) because of a potential difference created

More information

Earthing Guidance Notes

Earthing Guidance Notes Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head

More information

GroundRod AC Substation Earthing Tutorial

GroundRod AC Substation Earthing Tutorial 1 GroundRod AC Substation Earthing Tutorial 1. Functions of an earthing system The two primary functions of a safe earthing system are: To ensure that a person who is in the vicinity of earthed facilities

More information

Interfacing electrification and system reliability. Earthing of AC and DC railways 4,10,13

Interfacing electrification and system reliability. Earthing of AC and DC railways 4,10,13 Interfacing electrification and system reliability Roger White Professional Head of Electrification and Plant Rail Abstract Integration is the term given to ensuring that the different elements of an electrified

More information

Electrical safety requirements in DC distribution systems

Electrical safety requirements in DC distribution systems Electrical safety requirements in DC distribution systems PAUL J.L.AN TICHELEN, DOMINIQUE WEYEN ITO Boeretang 200, 2400 Mol BELGIUM Abstract: This paper focuses on the safety requirements for the DC bus

More information

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO 250447392

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO 250447392 1 Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading By Ramandeep Kaur Aujla S.NO 250447392 ES 586b: Theory and applications of protective relays Department of

More information

CAPACITOR BANK TESTING SWP

CAPACITOR BANK TESTING SWP 1. PURPOSE AND SCOPE The purpose of this Standard Work Practice (SWP) is to standardise and prescribe the method for testing Capacitor Banks including capacitors, tuning reactors and inrush limiting reactors.

More information

Video Camera Installation Guide

Video Camera Installation Guide Video Camera Installation Guide The intent of this guide is to provide the information needed to complete or modify a video camera installation to avoid lightning and induced power surge damage. This guide

More information

100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd

100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd 100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center Introduction Roger Hedding Steven Schoenherr, P.E. ABB Inc. Minnesota Power 598 N. Buth Rd 3215 Arrowhead Rd Dousman,

More information

Guide to the Selection & Use of Residual Current Devices

Guide to the Selection & Use of Residual Current Devices Guide to the Selection & Use of Residual Current Devices ET214:2005 Edition 1 Electro-Technical Council of Ireland Limited Published by the Electro-Technical Council of Ireland Limited Date of Publication:

More information

Trouble-shoot and repair faults in low voltage electrical apparatus and circuits

Trouble-shoot and repair faults in low voltage electrical apparatus and circuits UEENEEG108A Trouble-shoot and repair faults in low voltage electrical apparatus and circuits AS3000:2007 & AS3017:2007 Summary MANUFACTURING AND ENGINEERING DIVISI M & E UEENEEG108A TESTING Before any

More information

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application g Digital Energy ITI Instrument Transformer Basic Technical Information and Application Table of Contents DEFINITIONS AND FUNCTIONS CONSTRUCTION FEATURES MAGNETIC CIRCUITS RATING AND RATIO CURRENT TRANSFORMER

More information

EARTHING AND BONDING AT SECONDARY SUBSTATIONS

EARTHING AND BONDING AT SECONDARY SUBSTATIONS DISTRIBUTION CONSTRUCTION MANUAL SECTION 4 - SUBSTATIONS ISSUE B SEPT 1996 4.4.4 EARTHING AND BONDING AT SECONDARY SUBSTATIONS 1 SCOPE This section of the Distribution Construction Manual lays down the

More information

Grounding of Electrical Systems NEW CODE: Grounding and Bonding

Grounding of Electrical Systems NEW CODE: Grounding and Bonding Grounding of Electrical Systems NEW CODE: Grounding and Bonding Presented By Scott Peele PE Grounding of Electrical Systems Outline Defining the Terms Why should I Ground? Types of Grounding Systems Separately

More information

Insulation resistance

Insulation resistance The insulation resistance is particularly important for the prevention of damage and injury, and for the reliability of electrical systems and equipment. On the one hand it is basis for the protection

More information

Residual Current Circuit Breaker

Residual Current Circuit Breaker Introduction Residual Current Circuit Breaker / ELCB The Fault current overloads and short circuits can be detected by circuit breakers like MCB s MCCB s & HRC Fuses etc. But, Circuit breakers don t detect

More information

The following table shows approximate percentage wise the

The following table shows approximate percentage wise the SHORT-CIRCUIT CALCULATION INTRODUCTION Designing an electrical system is easy and simple, if only the normal operation of the network is taken into consideration. However, abnormal conditions which are

More information

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS TESTS ON TRANSFORMERS 1. IR Values a) For 33/11 KV Power Transformer 2500 V megger is to be need. b) Power Transformer neutral Earthing is

More information

employed to ensure the continuing reliability of critical systems.

employed to ensure the continuing reliability of critical systems. 4 Regulations 1989, Regulation 4, places a duty on employers to provide safe systems for their workers: Regulation 4 of the Electricity at Work Regulations 1989 Systems, work activities and protective

More information

By Mark Coles. This article looks at the temporary use of portable generators in floating, earthed and reference-earthing scenarios.

By Mark Coles. This article looks at the temporary use of portable generators in floating, earthed and reference-earthing scenarios. 16 Operation of portable generators Operation of portable generators By Mark Coles This article looks at the temporary use of portable generators in floating, earthed and reference-earthing scenarios.

More information

ESP 120 M1, ESP 208 M1, ESP 240 M1, ESP 415 M1, ESP 277 M1, ESP 480 M1 and M1R variants. Installation instructions ESP M1/M1R mains protectors

ESP 120 M1, ESP 208 M1, ESP 240 M1, ESP 415 M1, ESP 277 M1, ESP 480 M1 and M1R variants. Installation instructions ESP M1/M1R mains protectors ESP 120 M1, ESP 208 M1, ESP 240 M1, ESP 415 M1, ESP 277 M1, ESP 480 M1 and M1R variants Installation instructions Contents Key points of installation Before installation Installation Installation check

More information

Electrical Safety Tester Verification

Electrical Safety Tester Verification Ensuring Validity of Regulatory Tests Verification of electrical safety testing equipment is a procedure that is often overlooked by manufacturers. Running test verification is crucial to ensuring that

More information

Grounding Demystified

Grounding Demystified Grounding Demystified 3-1 Importance Of Grounding Techniques 45 40 35 30 25 20 15 10 5 0 Grounding 42% Case 22% Cable 18% Percent Used Filter 12% PCB 6% Grounding 42% Case Shield 22% Cable Shielding 18%

More information

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) DETAILS OF THE CLEINT Client and address ADDRESS OF THE INSTALLATION Installation

More information

Dielectric Withstand Testing in a Production Environment

Dielectric Withstand Testing in a Production Environment Dielectric Withstand Testing in a Production Environment Performing a routine product safety test should not in itself represent a shock hazard to the operator who is conducting the test, yet anytime you

More information

How Much Voltage Drop Is Acceptable?

How Much Voltage Drop Is Acceptable? How Much Voltage Drop Is Acceptable? Article supplied by Ideal The National Electrical Code (NEC) recommends that the combined voltage drop of the electrical system (branch circuit and feeders) not exceed

More information

Fundamentals of Power

Fundamentals of Power Fundamentals of Power Fundamentals of Power 2008 American Power Conversion Corporation. All rights reserved. All trademarks provided are the property of their respective owners. Learning Objectives At

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

Lightning Protection Introduction

Lightning Protection Introduction Lightning Protection Introduction Structural lightning protection design considerations BS 6651 (Protection of structures against lightning) clearly advises strict adherence to the provision of a conventional

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

Fault location on power cables. Fault location on power cables

Fault location on power cables. Fault location on power cables Fault location on power cables Fault location on power cables Contents: 1. Introduction 2. Construction of power cables 3. Cable faults 01. Introduction Fault location on communication and power cables

More information

THE LIGHTNING PROTECTION INTERNATIONAL STANDARD

THE LIGHTNING PROTECTION INTERNATIONAL STANDARD THE LIGHTNING PROTECTION INTERNATIONAL STANDARD Prof.-Dr-Eng. Christian Bouquegneau, Chairman of IEC TC81 (Lightning Protection), Pro-rector of the Faculté Polytechnique de Mons (Belgium) Abstract The

More information

www.klmtechgroup.com TABLE OF CONTENT

www.klmtechgroup.com TABLE OF CONTENT Page : 1 of 13 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia ELECTIRAL GROUNDING TABLE OF CONTENT

More information

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting 12 SOLAR PHOTOVOLTAIC POWER by John Ware IT IS PLANNED for BS 7671:2008 to include a new Section 712 providing additional requirements for safety applicable to solar photovoltaic (pv) power supply systems.

More information

VOLTAGE REGULATOR AND PARALLEL OPERATION

VOLTAGE REGULATOR AND PARALLEL OPERATION VOLTAGE REGULATOR AND PARALLEL OPERATION Generator sets are operated in parallel to improve fuel economy and reliability of the power supply. Economy is improved with multiple paralleled generators by

More information

Power Quality for Information Technology System

Power Quality for Information Technology System Power Quality for Information Technology System ITS OBVIOUS THE TOLERANCE IS DIFFRENT But What isn t Tobvious? HOW MANY OF YOU HAVE : A COMPUTER AT HOME? = Computers are not screens and Keyboards COMPUTERS

More information

6 ELECTRICAL PARAMETERS

6 ELECTRICAL PARAMETERS 6 ELECTRICAL PARAMETERS For power, low voltage and medium voltage cables, cross section nominal areas are calculated in taking into account several parameters as: permissible current carrying capacities

More information

Tutorial on Safety Standard Compliance For Hipot Testing

Tutorial on Safety Standard Compliance For Hipot Testing Chroma Systems Solutions, Inc. Tutorial on Safety Standard Compliance For Hipot Testing 19071, 19073 Hipot Testers Keywords: Safety Issues, Electrical Shock, Fire, Hipot (Dielectric Withstand), Leakage

More information

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation MTE SERIES RLW World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930 2009 MTE Corporation IMPORTANT USER INFORMATION NOTICE MTE Series RLW reactors are components designed to improve the reliability

More information

Substation Grounding Study Specification

Substation Grounding Study Specification Substation Grounding Study Specification Introduction A grounding study is required for name of station, a / / kv substation located in name of location and connected to the following circuits: number

More information

Douglas J. Reinemann, Ph.D. University of Wisconsin-Madison, Department of Agricultural Engineering Madison, Wisconsin. and

Douglas J. Reinemann, Ph.D. University of Wisconsin-Madison, Department of Agricultural Engineering Madison, Wisconsin. and Paper o. 953623 An ASAE Meeting Presentation ELECTRICAL SERVICE TO AGRICULTURAL BUILDIGS: FOUR- WIRE AD THREE-WIRE SYSTEMS by Mark A. Cook, Daniel M. Dasho P. E., and Richard Reines Public Service Commission

More information

12 Appendix 12 Earth Electrodes And Earth Electrode

12 Appendix 12 Earth Electrodes And Earth Electrode 12 Appendix 12 Earth Electrodes And Earth Electrode Testing 12.1 Introduction This appendix provides guidance and background information an earth electrode testing and some limited information on earth

More information

Ground Fault Protection

Ground Fault Protection Technical collection Ground Fault Protection Low voltage expert guides n 2 Contents The role of "Ground Fault Protection".. Safety and availability.2. Safety and installation standards.2.. The IEC 60

More information

A Guide to 17th Edition Testing

A Guide to 17th Edition Testing Seaward, Bracken Hill, South West Industrial Estate, Peterlee, County Durham, SR8 2SW United Kingdom Tel: +44 (0) 191 586 3511 Fax: +44 (0) 191 586 0227 Email: sales@seaward.co.uk Web: www.seaward.co.uk

More information

ELECTRICAL INSTALLATION CONDITION REPORT (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)

ELECTRICAL INSTALLATION CONDITION REPORT (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) Original Certificate DETAILS OF THE CLIENT Certificate reference: ELECTRICAL INSTALLATION CONDITION REPORT (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) Name: Address: PURPOSE

More information

Release: 2. UEENEEJ194A Solve problems in low voltage refrigeration circuits

Release: 2. UEENEEJ194A Solve problems in low voltage refrigeration circuits Release: 2 UEENEEJ194A Solve problems in low voltage refrigeration circuits UEENEEJ194A Solve problems in low voltage refrigeration circuits Modification History Not Applicable Unit Descriptor Unit Descriptor

More information

Bypass transfer switch mechanisms

Bypass transfer switch mechanisms Power topic #6013 Technical information from Cummins Power Generation transfer switch mechanisms > White paper By Gary Olson, Director, Power Systems Development This paper describes the configuration

More information

Cahier technique no. 178

Cahier technique no. 178 Collection Technique... Cahier technique no. 178 The IT earthing system (unearthed neutral) in LV F. Jullien I. Héritier Cahiers Techniques is a collection of documents intended for engineers and technicians,

More information

DC GROUND FAULT DETECTION PROVIDED FOR UNINTERRUPTIBLE POWER SUPPLIES

DC GROUND FAULT DETECTION PROVIDED FOR UNINTERRUPTIBLE POWER SUPPLIES DC GROUND FAULT DETECTION PROVIDED FOR UNINTERRUPTIBLE POWER SUPPLIES Edward P. Rafter, P. E. Principal Tier IV Consulting Group Lee s Summit, Missouri 64064 INTRODUCTION There are concerns among owners

More information

Are you aware. Outline

Are you aware. Outline Electrical Safety of Medical Equipment Hasan Al-Nashash School of Engineering American University of Sharjah (AUS) 1 Are you aware Electrocutions are the 5th leading cause of accidental death in the U.S.

More information

The Do s and Don ts of Pressure Transducers

The Do s and Don ts of Pressure Transducers The Do s and Don ts of Pressure Transducers ABSTRACT When specifying a pressure transducer for a process measurement, a number of items have to be considered. Some of the more important ones are discussed

More information

Section B: Electricity

Section B: Electricity Section B: Electricity We use mains electricity, supplied by power stations, for all kinds of appliances in our homes, so it is very important to know how to use it safely. In this chapter you will learn

More information

Guidance for upgrading to GB4943.1-2011 (IEC 60950-1: 2005, MOD)

Guidance for upgrading to GB4943.1-2011 (IEC 60950-1: 2005, MOD) Guidance for upgrading to GB4943.1-2011 (IEC 60950-1: 2005, MOD) Note: This guidance document is a translation of official Chinese document which is issued by CQC (China Quality Certification Center) on

More information

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance Annex I To Loughborough University (LU) Facilities Management (FM) Health and Safety Policy High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance 1. Introduction a. These Safety

More information

INSPECTION AND TESTING OF ELECTRICAL INSTALLATIONS RESIDUAL CURRENT DEVICES

INSPECTION AND TESTING OF ELECTRICAL INSTALLATIONS RESIDUAL CURRENT DEVICES 1 By kind permission of MK INSPECTION AND TESTING OF ELECTRICAL INSTALLATIONS RESIDUAL CURRENT DEVICES By Mark Coles The IEE receives many enquiries relating to the inspection and testing of electrical

More information

Electrical Infrastructure in Remote Areas. A Review of Potential Threats to Safety and Sustainability

Electrical Infrastructure in Remote Areas. A Review of Potential Threats to Safety and Sustainability Electrical Infrastructure in Remote Areas A Review of Potential Justin Buskmiller 1, Larry Bentley 2 and Jon Fripp 3, Subject Key Word: Energy Key Words: Electrical infrastructure, power supply, power

More information

Type SA-1 Generator Differential Relay

Type SA-1 Generator Differential Relay ABB Automation Inc. Substation Automation and Protection Division Coral Springs, FL 33065 Instruction Leaflet 41-348.11C Effective: November 1999 Supersedes I.L. 41-348.11B, Dated August 1986 ( ) Denotes

More information

Test Before Touch Easier Said Than Done. Ken Crawford, DuPont Kent Haggerty, Dupont

Test Before Touch Easier Said Than Done. Ken Crawford, DuPont Kent Haggerty, Dupont Test Before Touch Easier Said Than Done Ken Crawford, DuPont Kent Haggerty, Dupont Overview Test Before Touch (TBT) Principles Key Learnings by One Company One Method for Performing a TBT Induced Voltages

More information

Strength and Durability for Life CORROSION CONTROL. The Effect of Overhead AC Power Lines Paralleling Ductile Iron Pipelines

Strength and Durability for Life CORROSION CONTROL. The Effect of Overhead AC Power Lines Paralleling Ductile Iron Pipelines Strength and Durability for Life CORROSION CONTROL The Effect of Overhead AC Power Lines Paralleling Ductile Iron Pipelines Last Revised: May 2016 Sharing of rights-of-way by AC power lines and buried

More information

Best Methods for Safe Hipot Testing

Best Methods for Safe Hipot Testing Best Methods for Safe Hipot Testing When working with electrical safety test equipment, instruments that output potentially dangerous voltages and currents, it is always important to regular review and

More information

Exploring the Necessity of the Hot Hipot Test

Exploring the Necessity of the Hot Hipot Test Exploring the Necessity of the Hot Hipot Test Introduction In an industry comprised of workers with varying electronics knowledge, a Hipot test can seem a daunting task for some. Indeed, many test operators

More information

PART 1 - INTRODUCTION...

PART 1 - INTRODUCTION... Table of Contents PART 1 - INTRODUCTION... 3 1.1 General... 3 1.2 Sensor Features... 3 1.3 Sensor Specifications (CDE-45P)... 4 Figure 1-1 CDE-45P Sensor Dimensions (standard, convertible style)... 4 PART

More information

TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION GOVERNMENT BUILDINGS THE HONG KONG SPECIAL ADMINISTRATIVE REGION

TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION GOVERNMENT BUILDINGS THE HONG KONG SPECIAL ADMINISTRATIVE REGION TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION IN GOVERNMENT BUILDINGS OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION 2012 EDITION ARCHITECTURAL SERVICES DEPARTMENT THE GOVERNMENT OF THE

More information

TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION GOVERNMENT BUILDINGS THE HONG KONG SPECIAL ADMINISTRATIVE REGION

TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION GOVERNMENT BUILDINGS THE HONG KONG SPECIAL ADMINISTRATIVE REGION TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION IN GOVERNMENT BUILDINGS OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION 2007 EDITION ARCHITECTURAL SERVICES DEPARTMENT THE GOVERNMENT OF THE

More information

White Paper. Safety Considerations When Using Optocouplers and Alternative Isolators for Providing Protection Against Electrical Hazards.

White Paper. Safety Considerations When Using Optocouplers and Alternative Isolators for Providing Protection Against Electrical Hazards. Safety Considerations When Using Optocouplers and Alternative Isolators for Providing Protection Against Electrical Hazards White Paper Introduction Optocouplers and alternative isolation technologies

More information

Electrical Shore Connections / Cold Ironing

Electrical Shore Connections / Cold Ironing STANDARD FOR CERTIFICATION No. 2.25 Electrical Shore Connections / Cold Ironing JULY 2014 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version

More information

RCD Inspection Log Book

RCD Inspection Log Book RCD Inspection Log Book This book is the property of: Commenced: / /. Completed: / /. 2 Clipsal Australia Pty Ltd Clipsal Australia Pty Ltd 3 4 Clipsal Australia Pty Ltd Clipsal Australia Pty Ltd 5 6 Clipsal

More information

Grounding of AC generators and switching the neutral in emergency and standby power systems

Grounding of AC generators and switching the neutral in emergency and standby power systems Power topic #6006 Part 2 of 2 Technical information from Cummins Power eneration rounding of AC generators and switching the neutral in emergency and standby power systems > White paper By Lawrence A.

More information

Installation instructions for mains wire-in protectors ESP D1, D1R, D1/LCD and D1R/LCD variants

Installation instructions for mains wire-in protectors ESP D1, D1R, D1/LCD and D1R/LCD variants Installation instructions for mains wire-in protectors ESP D1, D1R, D1/LCD and D1R/LCD variants Introduction This document explains how to install Furse Electronic Systems s for mains power supplies: Single

More information

Electrical Essentials for HVAC&R Engineers. Wednesday, October 7

Electrical Essentials for HVAC&R Engineers. Wednesday, October 7 Electrical Essentials for HVAC&R Engineers Wednesday, October 7 Main Components of an Electrical System Accessibility of Switchboards AS/NZS 3000-2007 REQUIRES SWITCHBOARDS TO HAVE ADEQUATE SPACE TO ALLOW

More information

CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS

CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS Customer Handout Date Aug 2, 2010 Version 1.0 File Name Customer Requirements At Power Substations Document Id Outside Plant Engineering 1 Table Of Contents 1.0

More information

Electricity for the Entertainment Electrician Ef Technician

Electricity for the Entertainment Electrician Ef Technician Electricity for the Entertainment Electrician Ef Technician Richard Cadena ЩШ ' AMSTERDAM BOSTON HEIDELBERG LONDON NEW YORK JPPwlffl OXFORD PARIS SAN DIEGO SAN FRANCISCO л»еж SINGAPORE SYDNEY TOKYO ELSEVIER

More information

Neutral Wire Facts and Mythology. White Paper #21

Neutral Wire Facts and Mythology. White Paper #21 Neutral Wire Facts and Mythology White Paper #21 Executive Summary This Technical Note discusses many common misunderstandings about the function of the neutral wire and its relation to power problems.

More information

GUIDELINES TO INSTALL, OPERATE AND MAINTAIN HT CAPACITORS & IT S ASSOCIATED EQUIPMENT

GUIDELINES TO INSTALL, OPERATE AND MAINTAIN HT CAPACITORS & IT S ASSOCIATED EQUIPMENT GUIDELINES TO INSTALL, OPERATE AND MAINTAIN HT CAPACITORS & IT S ASSOCIATED EQUIPMENT GENERAL: 1. The selection of switchgear for switching the capacitors should be done carefully. The circuit breaker

More information

BSNL TTA Question Paper-Instruments and Measurement Specialization 2007

BSNL TTA Question Paper-Instruments and Measurement Specialization 2007 BSNL TTA Question Paper-Instruments and Measurement Specialization 2007 (1) Instrument is a device for determining (a) the magnitude of a quantity (b) the physics of a variable (c) either of the above

More information

EMI and t Layout Fundamentals for Switched-Mode Circuits

EMI and t Layout Fundamentals for Switched-Mode Circuits v sg (t) (t) DT s V pp = n - 1 2 V pp V g n V T s t EE core insulation primary return secondary return Supplementary notes on EMI and t Layout Fundamentals for Switched-Mode Circuits secondary primary

More information

HIGH VOLTAGE SHORE CONNECTION

HIGH VOLTAGE SHORE CONNECTION Guide for High Voltage Shore Connection GUIDE FOR HIGH VOLTAGE SHORE CONNECTION NOVEMBER 2011 American Bureau of Shipping Incorporated by Act of Legislature of the State of New York 1862 Copyright 2011

More information

Assessment of Soil Resistivity on Grounding of Electrical Systems: A Case Study of North-East Zone, Nigeria

Assessment of Soil Resistivity on Grounding of Electrical Systems: A Case Study of North-East Zone, Nigeria Assessment of Soil Resistivity on Grounding of Electrical Systems: A Case Study of North-East Zone, Nigeria Abstract Gabriel A. Adegboyega and Kehinde O. Odeyemi Department of Electrical and Electronic

More information

CSA Z32 TESTING GUIDELINE AND PROCEDURES

CSA Z32 TESTING GUIDELINE AND PROCEDURES PO Box 20020 Red Deer, AB T4N 6X5 Phone: 403.986.2939 Web: www.908eng.com July 9, 2012 CSA Z32 TESTING GUIDELINE AND PROCEDURES This document is intended to outline the various tests, procedures and preparations

More information

GUIDE TO THE MAINTENANCE, INSPECTION AND TESTING OF PORTABLE EQUIPMENT (ELECTRICAL APPLIANCES AND TOOLS) IN THE WORKPLACE

GUIDE TO THE MAINTENANCE, INSPECTION AND TESTING OF PORTABLE EQUIPMENT (ELECTRICAL APPLIANCES AND TOOLS) IN THE WORKPLACE GUIDE TO THE MAINTENANCE, INSPECTION AND TESTING OF PORTABLE EQUIPMENT (ELECTRICAL APPLIANCES AND TOOLS) IN THE WORKPLACE ET 215:2008 ELECTRO-TECHNICAL COUNCIL OF IRELAND 2008 Page 1 of 6 Published by

More information

Charged cable event. 1 Goal of the ongoing investigation. 2 Energy sources for the CDE. Content

Charged cable event. 1 Goal of the ongoing investigation. 2 Energy sources for the CDE. Content Charged cable event David Pommerenke, david_pommerenke@hp.com, 916 785 4550 Last update: Feb.23, 2001 Content Goal Energy sources, which may lead to CDE. Complexity of the different discharge modes. Possible

More information

TRACTION NETWORK MONITORING AND PROTECTION SYSTEM SMTN-3 CITY ELECTRIC TRANSPORT RAILWAYS METRO INDUSTRY

TRACTION NETWORK MONITORING AND PROTECTION SYSTEM SMTN-3 CITY ELECTRIC TRANSPORT RAILWAYS METRO INDUSTRY TRACTION NETWORK MONITORING AND PROTECTION SYSTEM SMTN-3 CITY ELECTRIC TRANSPORT RAILWAYS METRO INDUSTRY 2 TRACTION NETWORK MONITORING AND PROTECTION SYSTEM Traction network monitoring and protection system,

More information

SAMPLE OF THE STUDY MATERIAL PART OF CHAPTER 3. Symmetrical Components & Faults Calculations

SAMPLE OF THE STUDY MATERIAL PART OF CHAPTER 3. Symmetrical Components & Faults Calculations SAMPLE OF THE STUDY MATERIAL PART OF CHAPTER 3 3.0 Introduction Fortescue's work proves that an unbalanced system of 'n' related phasors can be resolved into 'n' systems of balanced phasors called the

More information

Grounding & Bonding Why it is done And How to Install Properly

Grounding & Bonding Why it is done And How to Install Properly Grounding & Bonding Why it is done And How to Install Properly The technical information provided herein is to assist qualifi ed persons in planning and installing electric service to farms and residences.

More information

Introduction to Data Centre Design

Introduction to Data Centre Design Introduction to Data Centre Design Barry Elliott BSc RCDD MBA CEng Earthing, grounding and bonding November 09 Earthing what s the point Safety from electrical hazards Reliable signal reference within

More information

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS Terence Hazel Senior Member IEEE Schneider Electric 38050 Grenoble France Abstract The power requirements for large industrial sites is increasing.

More information

Current Probes. User Manual

Current Probes. User Manual Current Probes User Manual ETS-Lindgren L.P. reserves the right to make changes to any product described herein in order to improve function, design, or for any other reason. Nothing contained herein shall

More information

Tips for connecting 24-volt power

Tips for connecting 24-volt power Digital Designer s Guide Application NoteAN0604D Revision B Tips for connecting 24-volt power This application note covers choosing a transformer and connecting 24 volt AC power to a KMC Controls DDC controller.

More information

)454 6 %LECTRICAL CHARACTERISTICS FOR BALANCED DOUBLECURRENT INTERCHANGE CIRCUITS OPERATING AT DATA SIGNALLING RATES UP TO -BITS

)454 6 %LECTRICAL CHARACTERISTICS FOR BALANCED DOUBLECURRENT INTERCHANGE CIRCUITS OPERATING AT DATA SIGNALLING RATES UP TO -BITS INTERNATIONAL TELECOMMUNICATION UNION )454 6 TELECOMMUNICATION STANDARDIZATION SECTOR OF ITU (10/96) SERIES V: DATA COMMUNICATION OVER THE TELEPHONE NETWORK Interfaces and voiceband modems %LECTRICAL CHARACTERISTICS

More information

EDS 06-0016 LV NETWORK EARTHING DESIGN

EDS 06-0016 LV NETWORK EARTHING DESIGN THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE Document Number: EDS 06-0016 ENGINEERING DESIGN STANDARD EDS 06-0016 LV NETWORK EARTHING DESIGN Network(s): EPN, LPN, SPN

More information

A Practical Guide to Dielectric Testing

A Practical Guide to Dielectric Testing Chroma Systems Solutions, Inc. A Practical Guide to Dielectric Testing 19032 Series Electrical Safety Analyzer & 19050 Series Hipot Tester AC/DC/IR/SCAN Keywords: Dielectric tests, insulation resistance

More information

Earth Ground Resistance

Earth Ground Resistance Principles, testing methods and applications Diagnose intermittent electrical problems Avoid unnecessary downtime Learn earth ground safety principles Earth Ground Resistance Why Ground, Why Test? Why

More information

Eliminating Parasitic Oscillation between Parallel MOSFETs

Eliminating Parasitic Oscillation between Parallel MOSFETs Eliminating Parasitic Oscillation between Parallel MOSFETs Based in part on a paper presented at Power Electronics Technology 2003 conference titled Issues with Paralleling MOSFETs and IGBTs by Jonathan

More information

IDEAL INDUSTRIES, INC. TECHNICAL MANUAL MODELS: 61-763 61-765

IDEAL INDUSTRIES, INC. TECHNICAL MANUAL MODELS: 61-763 61-765 IDEAL INDUSTRIES, INC. TECHNICAL MANUAL MODELS: 61-763 61-765 The Service Information provides the following information: Precautions and safety information Specifications Performance test procedure Calibration

More information

Balanced vs. Unbalanced Audio Interconnections

Balanced vs. Unbalanced Audio Interconnections Revised 7/2/08 Balanced vs. Unbalanced Audio Interconnections In discussing the characteristics and performance of various interconnect systems; two points should be kept in mind. Balance is defined in

More information

Table of Contents. The Basics of Electricity 2. Using a Digital Multimeter 4. Testing Voltage 8. Testing Current 10. Testing Resistance 12

Table of Contents. The Basics of Electricity 2. Using a Digital Multimeter 4. Testing Voltage 8. Testing Current 10. Testing Resistance 12 Table of Contents The Basics of Electricity 2 Using a Digital Multimeter 4 IDEAL Digital Multimeters An Introduction The Basics of Digital Multimeters is designed to give you a fundamental knowledge of

More information

Interference in the ECG and its elimination

Interference in the ECG and its elimination Interference in the ECG and its elimination General points The signal voltages in ECG recording are known to be very small and are in the millivolt range, i.e. they have amplitudes of only a few thousands

More information

GenTech Practice Questions

GenTech Practice Questions GenTech Practice Questions Basic Electronics Test: This test will assess your knowledge of and ability to apply the principles of Basic Electronics. This test is comprised of 90 questions in the following

More information

Criteria for Selecting a Residual-Current Device

Criteria for Selecting a Residual-Current Device Criteria for Selecting a Residual-Current Device Use of Residual-Current Devices for SUNNY BOY, SUNNY MINI CENTRAL and SUNNY TRIPOWER Content When installing inverters, there are often uncertainties when

More information