Quantitative Cost and Schedule Risk Assessment and Management for Large Infrastructure Projects RT-05. Bill Roberds, Sc.D. Travis McGrath, Ph.D., P.E.

Size: px
Start display at page:

Download "Quantitative Cost and Schedule Risk Assessment and Management for Large Infrastructure Projects RT-05. Bill Roberds, Sc.D. Travis McGrath, Ph.D., P.E."

Transcription

1 Quantitative Cost and Schedule Risk Assessment and Management for Large Infrastructure Projects RT-05 Bill Roberds, Sc.D. Travis McGrath, Ph.D., P.E. PMI is a registered trade and service mark of the Project Management institute, Inc. Golder Associates, Inc. Redmond, WA

2 Introduction Cost and Schedule overruns are common on large infrastructure projects. Historically 1 : 90% of estimates for transportation infrastructure projects have been low On average, cost estimates for road projects have been 20% short of final costs Estimates for some projects have been off by 100% or more (e.g., the Big Dig ) 1. Flyvbjerg et.al., Journal of the American Planning Association, Summer,

3 Project Cost and Schedule Uncertainty Poor cost and schedule estimates lead to: Cost and schedule over-runs or under-runs Poor decisions (i.e., among alternatives) Resource competition among projects Media attention Public mistrust (and therefore funding problems) 3

4 Probabilistic Cost and Schedule Risk Assessment and Risk Management (RA/RM) Mitigate these problems by: Quantifying project cost and schedule uncertainty Identifying and prioritizing critical risks and key opportunities Quantifying potential benefits of riskmanagement strategies Improving project understanding and communication Increasing confidence in estimates and budgets 4

5 Outline Key Concepts Process and Examples Performance to Date Challenges for Better Implementation 5

6 Key Concepts Comprehensive look at the project at appropriate level of detail Quantify uncertainty in key project assumptions Utilize independent perspective (for validation) Employ a collaborative, team approach Achieve consensus (when possible) Focus attention on the key issues Update as the project changes significantly 6

7 Key Concepts, cont d Quantify uncertainty in project cost and schedule, which is a function of: Sequence of all significant project activities Base activity costs and durations Risks, Opportunities, and other uncertainties Prioritize critical activities, risks, and opportunities Identify and evaluate strategies to improve project performance 7

8 Describing Uncertainty Relative Likelihood Mean (Expected) Value Range in values Standard Deviation Cumulative Probability 100% 75% 50% 25% 0% Percentiles 10th 90th 80% confidence interval Value Probability Density Function (PDF) Cumulative Distribution Function (CDF) 8

9 Base + Risk Approach versus Traditional Single-Valued Approach Aggregate Risk and Opportunity Relative Likelihood Base (with uncertainties) Base + Risk 0 Traditional Contingency below the line + = Cost Traditional Traditional Conservative Single-valued above the line (Deterministic) Estimate 9

10 Outline Key Concepts Process and Examples Performance to Date Challenges for Better Implementation 10

11 Steps in Quantitative Cost and Schedule Risk Assessment and Risk Management Structuring: Review Project Plan, Develop Flow Chart, and Document Assumptions Review Cost and Schedule Estimates Develop Risk Register Workshop setting Develop Base Factors Develop Cost and Schedule Uncertainty Model Assess Risk Factors Collaborative effort Quantify Uncertainty and Sensitivity in Cost, Schedule, and Other Measures Identify and Evaluate Risk- Management Strategies Update Periodically or at Key Milestones Project team implements mitigation strategy and monitors performance 11

12 Steps: Structuring the RA/RM Structuring: Review Project Plan, Develop Flow Chart, and Document Assumptions Project team presents current plan Clarify project scope and delivery strategy List all significant project assumptions Develop project flow chart for each alternative: Sequence of major project activities (all precedence requirements) Based on team s strategy and schedule Reasonableness / accuracy check on schedule logic Appropriate level of detail Basis for integrated cost and schedule model 12

13 Example Project Flow Chart Pre-Construction Activities Programmed: 1/1/2005 Develop Alternatives Design 2 and ROW Funding Env Resource 1 Inventory 3 Design to 10% 4 S+50% Design to 30% + Design to 60% Design Approval 8 7 F-1 month Prepare Environmental Resource Doc + Approval Reports 6 5 Finalize Design and PS&E 9 S+50% Relocate Utilities 10 Acquire ROW 11 Permitting 12 Ad / Bid / Award / NTP Construction Activities Widen Existing Embankment 15 Construct New 14 Embankment 16 Paving 20 Open to Traffic 21 Demo Old Bridge 22 Programmed: Construction 1/1/2007 Funding 13 Remove Old Close-out Alignment Items Complete 25 Bridge Approaches 17 Remaining Bridge Construction 19 S + 1 month In-Water Bridge Construction 18 Critical path 13

14 Steps: Reviewing Project Estimates Structuring: Review Project Plan, Develop Flow Chart, and Document Assumptions Review Cost and Schedule Estimates Collaborative effort Confirm that cost matches scope Confirm that schedule matches scope Check reasonableness of design and strategy Identify and remove contingency and conservatism Note: Estimate is for the ultimate cost and schedule 14

15 Steps: Defining the Base Structuring: Review Project Plan, Develop Flow Chart, and Document Assumptions Review Cost and Schedule Estimates Develop Base Factors The Base The planned scope and strategy, with no problems Unbiased, excluding contingency and/or float Map the base estimates to flow chart activities For each flow chart activity, develop: Base cost (current $) Base duration (calendar time) Cost-escalation rate Include significant uncertainties and correlations 15

16 Example Base Factors (excerpt) Flowchart Number Project Activity Base Cost 1 (2005 $M) Base Duration 1 (months) Average Escalation Rate 1 (%/yr) 0 Costs to Date Design and ROW Funding milestone - 2 Develop Alternatives Env. Resource Inventory Design to 10% Prepare Resource Reports Environmental Doc + Approval Design to 30% + Approval Ad / Bid / Award / NTP Widen Existing Embankment Construct New Embankment Bridge Approaches In-Water Bridge Construction Remaining Bridge Construction Close-out Items Complete milestone - Note 1. May be uncertain and described with probability distributions; only the expected values are shown here. 16

17 Steps: Developing the Risk Register Structuring: Review Project Plan, Develop Flow Chart, and Document Assumptions Review Cost and Schedule Estimates Develop Risk Register Develop Base Factors Identify all potential events - risks and opportunities - outside the base assumptions Comprehensive and non-overlapping Appropriate level of detail Include significant relationships among risks Consider possible causes and effects 17

18 Steps: Quantifying the Risks Structuring: Review Project Plan, Develop Flow Chart, and Document Assumptions Review Cost and Schedule Estimates Develop Risk Register Develop Base Factors Assess Risk Factors For each risk and opportunity, quantify: Consequences if event occurs Changes in costs and durations to affected activities Other measures? Likelihood of occurrence, consistent with consequences Include significant uncertainties and correlations Ensure consistent with base 18

19 Steps: Quantifying the Risks, cont d Structuring: Review Project Plan, Develop Flow Chart, and Document Assumptions Review Cost and Schedule Estimates Develop Risk Register Develop Base Factors Assess Risk Factors Risk-factor assessments: Based on objective analysis when data are available Based on subjective assessments (from the experience and judgment of SMEs) if data are limited When properly elicited, subjective assessments have been shown to be accurate, defensible, and the best we can do 19

20 Example Event Tree for Structuring Risks and Opportunities Structure Type A. Cut-and-Cover Probability $ ($M) Months P A 1 P 0 ( base ) 1 0 Vertical Concept & Location 1. Tunnel P 1 2. At-grade P A 1 B. Bored / Mined P B 1 = 1- P A 1 P B 1 P P P 2 3. Bridge / Aerial C. Concrete Box P C 3 P C 3 P P 3 = 1-P 1 -P 2 D. Steel Plate Girder P D 3 = 1 - P C 3 P D 3 P Note: Probability of alternative concepts may consider factors other than cost or duration 20

21 Example Risk Register and Risk Factors (excerpt) Item D8 P4 Risk or Opportunity Project alignment different than assumed Includes related design, ROW, and construction impacts Potential mutually-exclusive outcomes include: A. EIS alignment ( base ), which passes through town on existing roadway alignment B. Alternative alignment #1, which bypasses town to north on new alignment C. Alternative alignment #2, which passes through town on new alignment to east of EIS alignment Delays in required transportation agency approvals Several agencies have review and approval authority over the design. Delays in approval are possible from delays in review cycle. Affected Project Activities 60% Design and ROW Acquisition 60% Design Probability of Occurrence Discrete distribution: A. 40% (Base) B. 40% C. 20% Cost change perfectly correlated to duration change Discrete distribution: A. 10% (Base) B. 60% C. 30% Cost Change (2005 $M) A. 0 (Base) B. 1.0 to Design; -5 to ROW C. 1.0 to Design; Uniform (2, 10) to ROW Additional escalation costs are simulated as a function of duration change Duration Change (months) A. 0 (Base) B. 6 to Design; -3 to ROW C. 6 to Design; Uniform (3, 9) to ROW Discrete distribution: A. 0 (base) B. 3 C. 6 21

22 Steps: Developing the Integrated Cost and Schedule Model Probabilistic computer model Can include Shut-down windows Decisions and other triggered actions Funding or other resource constraints Uncertainty in critical path Delay-related costs Structuring: Review Project Plan, Develop Flow Chart, and Document Assumptions Review Cost and Schedule Estimates Develop Base Factors Develop Cost and Schedule Uncertainty Model Develop Risk Register Assess Risk Factors 22

23 Steps: Quantifying Uncertainty in Project Cost and Schedule Combine base and risk factors in the model Simulate results of interest Structuring: Review Project Plan, Develop Flow Chart, and Document Assumptions Review Cost and Schedule Estimates Develop Base Factors Develop Cost and Schedule Uncertainty Model Develop Risk Register Assess Risk Factors Quantify Uncertainty and Sensitivity in Cost, Schedule, and Other Measures 23

24 Integrated Cost and Schedule Model _ Event X Uncertainty in Total Escalated Project Cost and Duration, plus Sensitivities Start Activity A Activity C Activity B End $ time T escalation cash flow Activity Base Costs (and Uncertainties) Activity Base Durations (and Uncertainties) Risk Events May (likelihood 9, 2006 of occurrence, and uncertainty Event _ Y in activity cost and duration changes if the event occurs) 24

25 Example Monte Carlo Sample Set Showing Cost and Schedule Correlation 4th Bore Opening Date Dec Dec Dec Dec Dec Dec Dec Dec Dec Dec Dec Dec Dec Total Project Cost ($M) unescalated escalated 25

26 Cumulative Probability (Percentile) 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Example CDF for Project Cost Showing Contributing Factors 2,400 Base (with no risk or opportunity; in 2005 $) With Risk and Opportunity, but Without Escalation (2005 $) With Risk and Opportunity and Escalation (Year-of-Expenditure $) With Risk and Opportunity and $400M/year Funding Constraint (YOE $) Mean risk and opportunity 2,500 2,600 2,700 2,800 2,900 3,000 Mean cost escalation 3,100 3,200 3,300 3,400 3,500 3,600 3,700 3,800 3,900 4,000 4,100 Mean funding constraint 4,200 4,300 4,400 4,500 Total Project PMI is a registered Cost trade and (2005 service mark of $Million the Project Management or institute, YOE Inc. $Million) 26

27 Example CDF for Project Schedule Showing Contributing Factors Cumulative Probability (Percentile) 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Jan 2015 Base (with no risk or opportunity) With Risk and Opportunity but Without Funding Constraint With Risk and Opportunity and $400M/year Funding Constraint Mean risk and opportunity Jan 2016 Jan 2017 Mean impact of funding constraint Jan 2018 Jan 2019 Jan 2020 Jan 2021 Jan 2022 Jan 2023 Jan 2024 Overall Project Completion Date 27

28 Example Probability of Meeting Specified Target Cumulative Probability (Percentile) 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 2,400 Base (with no risk or opportunity; in 2005 $) With Risk and Opportunity, but Without Escalation (2005 $) With Risk and Opportunity and Escalation (Year-of-Expenditure $) With Risk and Opportunity and $400M/year Funding Constraint (YOE $) 2,500 2,600 2,700 Probability of meeting $3.7B budget = 85% Probability of meeting $3.7B budget = 37% 2,800 2,900 3,000 3,100 3,200 3,300 3,400 3,500 3,600 3,700 3,800 3,900 Alternatively, could identify required budget for desired confidence level (e.g., 80 th percentile) 4,000 4,100 4,200 4,300 4,400 4,500 Total Project PMI is a registered Cost trade and (2005 service mark of $Million the Project Management or institute, YOE Inc. $Million) 28

29 4,000 Example Uncertainty in Cash Flow of Expenditures (Unconstrained Funding Scenario) Project Cash Flow Without $400M/year Funding Constraint (YOE $M) 3,500 3,000 2,500 2,000 1,500 1, Cumulative - 90th Percentile Cumulative - Mean Cumulative - 10th Percentile Annual - 90th Percentile Annual - Mean Annual - 10th Percentile Year 29

30 Example Impact of Scenario Assumptions on Uncertainty in Cash Flow Annual Cashflow (YOE $M) Constraint reduces peak expenditure by $270M at the mean Constraint delays peak expenditure by 5 years Year No Funding Constraint - 90th Percentile No Funding Constraint - Mean No Funding Constraint - 10th Percentile Funding Constraint - 90th Percentile Funding Constraint - Mean Funding Constraint - 10th Percentile However, constraint increases total cost significantly (increased schedule and thus escalation) 30

31 Steps: Quantifying Sensitivity in Project Cost and Schedule Evaluate sensitivity of cost and schedule to the uncertain base and risk factors: Mean Standard Deviation Percentile (combination) Structuring: Review Project Plan, Develop Flow Chart, and Document Assumptions Review Cost and Schedule Estimates Develop Base Factors Develop Cost and Schedule Uncertainty Model Develop Risk Register Assess Risk Factors Prioritize critical activities and risks in costs and time Quantify Uncertainty and Sensitivity in Cost, Schedule, and Other Measures 31

32 Example Sensitivity of 80 th Percentile of Project Cost to Uncertain Inputs Uncertain Factors (base uncertainty or risk/opportunity) Contribution ($M) to 80th Percentile of Escalated Project Cost B.3. Limited Number of Qualified Bidders D.26. Extended Pre-Construction Admin Costs C.35. Extended Construction Admin Costs 16.3 Identified Minor Risks (aggregate) 11.8 Unidentified Risks (aggregate) 11.7 E.1. Challenge to ROD/FONSI due to public opposition 7.8 C.25. Unanticipated Mitigation of Construction T raffic 6.7 B.11. Non-Responsive Low Bid 6.5 D.7. Unanticipated Mitigation for Impacts Outside of... 6 C.14. Valid Differing Site Conditions (DSC) (e.g., C.7. Inexperienced Contractor (Separate from C D.5. More Fire Protection / Ventilation Required 3.9 D.14. Conversion from Metric to English Units 3.8 C.5. Contractor Unfamiliarity with CalT rans Admin W Tunnel 2.9 C.15. T unnel Face Instability / Excessive Inflow 2.4 E Tunnel 2 C.29. Unanticipated Work Stoppage due to Adverse E.5. Unexpected / Late Number of Public Comments B.6. Poor Material Prices and Availability 1.7 C.20. Slope Instability / Retaining Wall Failure 1.6 B.5. Opposition from Local Contractors / Business D.16. Problems in Design Coordination (Including D.17. Design Changes / Breakage (Separate from E13. Additional Impact Analysis 1.1 August 2005$ / non-row escalation rate 1.1 C.16. T unnel Collapse During Construction D.4. Change in Design Standards (e.g., Seismic)

33 Steps: Managing Risk Identify potential riskmanagement actions (e.g., prevention; mitigation) Quantify likely implementation costs Quantify likely benefits Simulate net effect Ties in to Value Engineering Structuring: Review Project Plan, Develop Flow Chart, and Document Assumptions Review Cost and Schedule Estimates Develop Base Factors Develop Cost and Schedule Uncertainty Model Quantify Uncertainty and Sensitivity in Cost, Schedule, and Other Measures Identify and Evaluate Risk- Management Strategies Develop Risk Register Assess Risk Factors Project team implements mitigation strategy and monitors performance 33

34 Risk Management Relative Likelihood Risks and Opportunities with Risk Management Base (with uncertainties; now including RM costs) Total with Risk Management Performance (e.g., cost) Note: Base costs include mitigation implementation costs 34

35 Example Risk Management: Mitigated Cost Uncertainty (if Mitigation Succeeds) Probability Mitigated (Workshop Plan) Unmitigated (July ) The mitigation plan would save $10M at the owner s desired confidence level (80 th percentile) Total Project Cost (Future $M) 35

36 Example Risk Management: Mitigated Schedule Uncertainty July 2004 Mitigated July 2004 Unmitigated Cumulative Probability (Percentile) 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Jun 2008 Sep 2008 Dec 2008 Mar 2009 Jul 2009 Oct 2009 Jan 2010 May 2010 The mitigation plan would save 7-8 months at the owner s desired confidence level (80 th percentile) Revenue Service Date 36

37 Outline Key Concepts Process and Examples Performance to Date Challenges for Better Implementation 37

38 Performance Favorable reaction from public (i.e., public ok with ranges expressing uncertainty) Improved project team understanding Focused risk management Improved confidence in cost and schedule estimates, however Not many projects evaluated using this approach have been completed Can t fully evaluate performance (yet) As an interim measure, compared results from risk assessments to published costs for completed projects 38

39 Performance: Bias Comparisons Flyvbjerg et. al. (2002) calculated inaccuracy (bias) in cost estimates for completed projects as the percent difference between actual (ultimate) project cost and estimated cost at the time of decision to build As an interim measure, the authors calculated the apparent bias in project team estimates relative to the mean RA/RM results for projects still in design as follows: [mean unescalated cost from risk assessment team cost estimate (unescalated)] team cost estimate (unescalated) 39

40 Performance: Results from Risk Assessments vs. Published Results for Completed Projects Frequency From 62 Risk Assessments (2002 to 2005) on Northwestern US Road Projects After Flyvbjerg et. al. (2002) for 167 Completed Road Projects (Worldwide) Mean = 20% Standard deviation = 30% Mean = 14% Standard deviation = 24% Bias in Cost Estimate (%) 1 (numbers are upper bounds for bins) Similar partial validation of approach Note: Larger variability in completed projects likely reflects larger data set and variability among agencies 40

41 Performance: Apparent Bias in Cost Estimate versus Design Level Bias in Cost Estimate (%) From 62 Risk Assessments on Northwestern US Road Projects Mean plus one standard deviation Mean Mean minus one standard deviation Conceptual Preliminary Final Design Level at Time of Risk Assessment 41

42 Outline Key Concepts Process and Examples Performance to Date Challenges for Better Implementation 42

43 Challenges for Better Implementation If properly implemented and averaged over many projects, risk-based approaches appear to get closer to the ultimate project cost than does deterministic estimating, However, RA/RM is not perfect: Bids for some recent projects evaluated using probabilistic RA/RM (by the authors and by others) have fallen outside the RA/RM ranges Effort for RA/RM for some projects has been excessive This implies that probabilistic RA/RM still needs improvement 43

44 Challenges for Better Implementation 1. Convincing the owner that the RA should include all significant uncertainties Excluding major uncertainties makes the results: Conditional on key assumptions (often forgotten) Underestimate the true range of uncertainty, and perhaps inaccurate as well Examples of major uncertainties that are often excluded for political or other reasons: Uncertainty in the amount or timing of funding Potential delays due to process and management inefficiencies Uncertainty in key policies within stakeholder orgs Uncertainty in project scope (i.e., evaluating a particular scope instead of all possible project scopes) 44

45 Challenges for Better Implementation 2. Removing optimism and/or management bias (e.g., hidden agendas) from assessments Consensus is desirable, but should not be achieved at the expense of accuracy If necessary, risk assessors should infuse their experience from other projects to de-bias and/or expand ranges of critical assessments to ensure reasonable results 45

46 Challenges for Better Implementation 3. Making results of RA/RM understandable and useful to the owner Make sure the RA addresses the owner s specific needs Educate the owner on how to interpret and use the results Don t let the owner assign more certainty or precision to the results than is justifiable Qualify any limitations to avoid misunderstanding 46

47 Summary Probabilistic risk assessment and risk management for large infrastructure projects can costeffectively provide Better understanding and communication of project uncertainties More confidence in estimates Better project management and decision making However, careful (and better) implementation is required to ensure accurate and defensible results 47

48 Contact Information Dr. Travis McGrath, P.E. Golder Associates, Inc NE Union Hill Rd, Suite 200 Redmond, WA (425)

RISK-BASED COST AND SCHEDULE ESTIMATION FOR LARGE TRANSPORTATION PROJECTS

RISK-BASED COST AND SCHEDULE ESTIMATION FOR LARGE TRANSPORTATION PROJECTS RISK-BASED COST AND SCHEDULE ESTIMATION FOR LARGE TRANSPORTATION PROJECTS Maher, M L J Golder Associates Ireland Twon Centre House Dublin Road, Naas Co Kildare, Ireland and McGoey-Smith, A D Golder Associates

More information

Risk Review Process Basics

Risk Review Process Basics 2011 PMOC Annual Meeting FEDERAL TRANSIT ADMINISTRATION Risk Review Process Basics Michael P. Wetherell, PE - Urban Engineers David N. Sillars, PE Sillars Consulting FEDERAL TRANSIT ADMINISTRATION 2011

More information

Risk Workshop Overview. MOX Safety Fuels the Future

Risk Workshop Overview. MOX Safety Fuels the Future Risk Workshop Overview RISK MANAGEMENT PROGRAM SUMMARY CONTENTS: Control Account Element Definition ESUA Form Basis of Estimate Uncertainty Calculation Management Reserve 1. Overview 2. ESUA Qualification

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane samlane@aol.com Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,

More information

Using Risk Assessment to Improve Highway Construction Project Performance

Using Risk Assessment to Improve Highway Construction Project Performance Using Risk Assessment to Improve Highway Construction Project Performance Mohamed F. Diab, MBA, Ph.D. and Amiy Varma, Ph.D., PE North Dakota State University Fargo, ND Khaled Nassar, Ph.D. American University

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT 11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and

More information

Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge

Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge 1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project

More information

INT 3 Schedule Risk Analysis

INT 3 Schedule Risk Analysis INT 3 Schedule Risk Analysis David T. Hulett, Ph.D. Hulett & Associates, LLC ICEAA Professional Development and Training Workshop San Diego, CA June 9-12, 2015 1 Agenda Add uncertainty to the schedule,

More information

FUNBIO PROJECT RISK MANAGEMENT GUIDELINES

FUNBIO PROJECT RISK MANAGEMENT GUIDELINES FUNBIO PROJECT RISK MANAGEMENT GUIDELINES OP-09/2013 Responsible Unit: PMO Focal Point OBJECTIVE: This Operational Procedures presents the guidelines for the risk assessment and allocation process in projects.

More information

Chapter 11 Monte Carlo Simulation

Chapter 11 Monte Carlo Simulation Chapter 11 Monte Carlo Simulation 11.1 Introduction The basic idea of simulation is to build an experimental device, or simulator, that will act like (simulate) the system of interest in certain important

More information

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule 763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project

More information

Palisade Risk Conference, 2014

Palisade Risk Conference, 2014 Advanced Risk Management to Improve Cost and Schedule Performance on EPC Projects Risk-Management Best Practices from Nuclear Experience Palisade Risk Conference, 2014 Sola Talabi PhD MBA MSc BSc RMP Project

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

Integrated Cost and Schedule using Monte Carlo Simulation of a CPM Model - 12419

Integrated Cost and Schedule using Monte Carlo Simulation of a CPM Model - 12419 Integrated Cost and Schedule using Monte Carlo Simulation of a CPM Model - 12419 ABSTRACT David T. Hulett, Ph.D., Hulett & Associates, LLC Michael R. Nosbisch, CCC PSP, Project Time and Cost, Inc. This

More information

Monte Carlo analysis used for Contingency estimating.

Monte Carlo analysis used for Contingency estimating. Monte Carlo analysis used for Contingency estimating. Author s identification number: Date of authorship: July 24, 2007 Page: 1 of 15 TABLE OF CONTENTS: LIST OF TABLES:...3 LIST OF FIGURES:...3 ABSTRACT:...4

More information

A Model to Develop and Use Risk Contingency Reserve

A Model to Develop and Use Risk Contingency Reserve A Model to Develop and Use Risk Contingency Reserve NK Shrivastava, PMP, RMP, ACP, CSM, SPC CEO/Consultant/Agile Coach - RefineM Agenda 1. Your Expectations from this Presentation 2. Introduction Myself

More information

Project success depends on

Project success depends on Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we

More information

OWNERS RISK REDUCTION TECHNIQUES USING A CM. Ali Touran, Department of Civil & Environmental Engineering Northeastern University atouran@coe.neu.

OWNERS RISK REDUCTION TECHNIQUES USING A CM. Ali Touran, Department of Civil & Environmental Engineering Northeastern University atouran@coe.neu. OWNERS RISK REDUCTION TECHNIQUES USING A CM Ali Touran, Department of Civil & Environmental Engineering Northeastern University atouran@coe.neu.edu October 2006 1 TABLE OF CONTENTS TABLE OF CONTENTS...2

More information

RISK MANAGEMENT AND RISK-BASED COST ESTIMATION GUIDELINES

RISK MANAGEMENT AND RISK-BASED COST ESTIMATION GUIDELINES RISK MANAGEMENT AND RISK-BASED COST ESTIMATION GUIDELINES August 2012 This page is left intentionally blank NEVADA DEPARTMENT OF TRANSPORTATION RISK MANAGEMENT AND RISK-BASED COST ESTIMATION GUIDELINES

More information

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT PROJECT RISK MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_risk_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern

More information

The Business Case in the 21 st Century. Jeff Jackson

The Business Case in the 21 st Century. Jeff Jackson The Business Case in the 21 st Century Jeff Jackson Why do we need business cases? There has always been pressure for organisations both in the public and private sector to demonstrate delivery of value

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson

Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson Page 1 of 13 Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models Martin Hopkinson Abstract Monte Carlo schedule risk analysis has become a widely practiced

More information

The 10 Knowledge Areas & ITTOs

The 10 Knowledge Areas & ITTOs This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized

More information

Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)

Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Nutek, Inc. 3829 Quarton Road, Suite 102 Bloomfield Hills, Michigan 48302, USA. Phone: 248-540-4827, Email: Support@Nutek-us.com

More information

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling

More information

USING PROBABILISTIC FORECASTS TO IMPROVE PLANNING AND OPERATIONS FOR WATER RESOURCES SYSTEMS

USING PROBABILISTIC FORECASTS TO IMPROVE PLANNING AND OPERATIONS FOR WATER RESOURCES SYSTEMS USING PROBABILISTIC FORECASTS TO IMPROVE PLANNING AND OPERATIONS FOR WATER RESOURCES SYSTEMS W. JOSH WEISS, PH.D., P.E. jweiss@hazenandsawyer.com 2013 Susquehanna Water Science Forum October 7, 2013 OUTLINE

More information

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge

THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge Page 1 of 5 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK November 1990 Transport No. PS-2 THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE John R. Lethbridge The use of outside

More information

SSgA CAPITAL INSIGHTS

SSgA CAPITAL INSIGHTS SSgA CAPITAL INSIGHTS viewpoints Part of State Street s Vision thought leadership series A Stratified Sampling Approach to Generating Fixed Income Beta PHOTO by Mathias Marta Senior Investment Manager,

More information

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the

More information

Objectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources

Objectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources Project Management for Small Business Moderator: Maria Mancha Frontline Systems, Inc. Objectives Project Management Overview Successful Project Fundamentals Additional Training Resources Project Management

More information

Amajor benefit of Monte-Carlo schedule analysis is to

Amajor benefit of Monte-Carlo schedule analysis is to 2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to

More information

DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002

DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002 DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT

More information

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM

More information

Sample Examination Questions

Sample Examination Questions Sample Examination Questions The following questions are examples of the type of questions that appear on the PMP Certification Examination. Disclaimer: These questions are intended for study purposes

More information

Project Risk Management Basics: Cost and Schedule Impacts

Project Risk Management Basics: Cost and Schedule Impacts Project Risk Management Basics: Cost and Schedule Impacts CSVA 2011 Conference Toronto, Ontario Nov 14-16, 2011 Robert E. Rocco 1 Contents Background Fundamentals Process Tools/Supporting Documentation

More information

EST.491. Cost Estimation Challenges and Uncertainties Confronting Oil and Gas Companies

EST.491. Cost Estimation Challenges and Uncertainties Confronting Oil and Gas Companies EST.491 Cost Estimation Challenges and Uncertainties Confronting Oil and Gas Companies Nicolas Alexander Hall and Sarah Delille, PE ABSTRACT Usually, when a company has a history of successfully planning

More information

Module 3: The Project Planning Stage

Module 3: The Project Planning Stage Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF JULY 31, 2015 SEPTEMBER 2015 Phase 2 Cost Summary July Expenditures $ 19.2 Million Total Expenditures $ 508.7 Million

More information

PROJECT RISK ANALYSIS AND MANAGEMENT

PROJECT RISK ANALYSIS AND MANAGEMENT PROJECT RISK ANALYSIS AND MANAGEMENT A GUIDE BY THE ASSOCIATION FOR PROJECT MANAGEMENT (formerly The Association Of Project Managers) Compiled from information provided by members of the Special Interest

More information

AACE International Recommended Practices

AACE International Recommended Practices AACE International Recommended Practice No. 52R-06 TIME IMPACT ANALYSIS AS APPLIED IN CONSTRUCTION TCM Framework: 6.4 Forensic Performance Assessment, 7.2 Schedule Planning and Development, 10.2 Forecasting,

More information

Rehabilitation Scenarios for Sustainable Water Mains. University, Montreal, Quebec, Canada, PH (514) 848-2424 ext. 8779; FAX (514) 848-7965; email:

Rehabilitation Scenarios for Sustainable Water Mains. University, Montreal, Quebec, Canada, PH (514) 848-2424 ext. 8779; FAX (514) 848-7965; email: Rehabilitation Scenarios for Sustainable Water Mains Khaled Shahata 1 ; Tarek Zayed 2 ; and Saad Al-Jibouri 3 1 Graduate Student, Department of Building, Civil, and Environmental Engineering, Concordia

More information

Bridge Rehabilitation Financial Model and Case Study

Bridge Rehabilitation Financial Model and Case Study Session 1339 Bridge Rehabilitation Financial Model and Case Study Halvard E. Nystrom University of Missouri Rolla Abstract This article describes a financial model to identify the tangible and intangible

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices : A CDOT Guide to Better Project Management Practices Project Management practices have been a part of the CDOT culture for many years. However, with a transitioning workforce and increasing demands, it

More information

Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses

Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses David T. Hulett, Ph.D. Keith Hornbacher, MBA Waylon T. Whitehead Hulett & Associates, LLC Los

More information

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

THE PROJECT MANAGEMENT KNOWLEDGE AREAS THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human

More information

EXHIBIT 2-2-C PROGRESS SCHEDULES

EXHIBIT 2-2-C PROGRESS SCHEDULES EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,

More information

Directory of Expertise for Civil Works Cost Engineering COST AND SCHEDULE RISK ANALYSIS GUIDANCE

Directory of Expertise for Civil Works Cost Engineering COST AND SCHEDULE RISK ANALYSIS GUIDANCE Directory of Expertise for Civil Works Cost Engineering COST AND SCHEDULE RISK ANALYSIS GUIDANCE 17 May 2009 Table of Contents 1. PURPOSE...1 2. APPLICABILITY... 1 3. DISTRIBUTION STATEMENT... 1 4. REFERENCES...

More information

Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.

Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Critical Path Method Scheduling - Some Important Reservations The critical path method (CPM) of scheduling a project is a key tool for project

More information

The fact is that 90% of business strategies are not implemented through operations as intended. Overview

The fact is that 90% of business strategies are not implemented through operations as intended. Overview Overview It is important to recognize that a company s network determines its supply chain efficiency and customer satisfaction. Designing an optimal supply chain network means the network must be able

More information

Implementing Pavement Management Systems, Do's and Don ts at the Local Agency Level

Implementing Pavement Management Systems, Do's and Don ts at the Local Agency Level Implementing Pavement Management Systems, Do's and Don ts at the Local Agency Level Roger E. Smith, P.E., Ph.D. Zachry Department of Civil Engineering Texas A&M University 1 Do Understand Basic Pavement

More information

Risk Management Primer

Risk Management Primer Risk Management Primer Purpose: To obtain strong project outcomes by implementing an appropriate risk management process Audience: Project managers, project sponsors, team members and other key stakeholders

More information

2017 Budget and Grid Management Charge Initial Stakeholder Meeting

2017 Budget and Grid Management Charge Initial Stakeholder Meeting 2017 Budget and Grid Management Charge Initial Stakeholder Meeting June 16, 2016 Page 1 Agenda Topic 2017 Budget Process & GMC Rate Outlook Managing Employee Compensation Presenter(s) Ryan Seghesio & April

More information

21. Earned Value deals with: a. EV Scope b. PV Time c. AC Cost 22. Portfolios are organized around business goals. 23. Take stern action against

21. Earned Value deals with: a. EV Scope b. PV Time c. AC Cost 22. Portfolios are organized around business goals. 23. Take stern action against PMP Short Notes Based on PMBOK Guide fifth edition By Dilip Chaturvedi,PMP Email id: info@justpmp.com To know about our training schedule, please visit www.justpmp.com 1. Communication is more complex

More information

The New Prior Approval Rate Application Process Frequently Asked Questions

The New Prior Approval Rate Application Process Frequently Asked Questions The New Prior Approval Rate Application Process Frequently Asked Questions 1. We understand that a complete underwriting manual must be filed electronically in SERFF with each private passenger automobile

More information

Probabilistic Risk Assessment Methodology for Criteria Calculation Versus the Standard (Deterministic) Methodology

Probabilistic Risk Assessment Methodology for Criteria Calculation Versus the Standard (Deterministic) Methodology Probabilistic Risk Assessment Methodology for Criteria Calculation Versus the Standard (Deterministic) Methodology State of Idaho Department of Environmental Quality March 2014 Background The equation

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing

More information

Capital Project Execution Risk and Mitigating Strategies

Capital Project Execution Risk and Mitigating Strategies Capital Project Execution Risk and Mitigating Strategies Wall Street Journal July 15 2005 Wall Street Journal July 15 2005 Yesterday, Shell said it had previously changed its management team at Sakhalin

More information

STANDARD. Risk Assessment. Supply Chain Risk Management: A Compilation of Best Practices

STANDARD. Risk Assessment. Supply Chain Risk Management: A Compilation of Best Practices A S I S I N T E R N A T I O N A L Supply Chain Risk Management: Risk Assessment A Compilation of Best Practices ANSI/ASIS/RIMS SCRM.1-2014 RA.1-2015 STANDARD The worldwide leader in security standards

More information

Financial Management of the Construction Projects: A Proposed Cash Flow Analysis Model at Project Portfolio Level

Financial Management of the Construction Projects: A Proposed Cash Flow Analysis Model at Project Portfolio Level Financial Management of the Construction Projects: A Proposed Cash Flow Analysis Model at Project Portfolio Level Augustin Purnus Technical University of Civil Engineering, Bucharest, Construction Management

More information

2010 FINANCIAL PLAN ANNUAL UPDATE

2010 FINANCIAL PLAN ANNUAL UPDATE THE INTERCOUNTY CONNECTOR PROJECT 2010 FINANCIAL PLAN ANNUAL UPDATE AS OF FISCAL YEAR ENDING JUNE 30, 2010 DATE SUBMITTED: JANUARY 6, 2011 SUBMITTED IN PARTNERSHIP BY: MARYLAND STATE HIGHWAY ADMINISTRATION

More information

Risk Assessment Worksheet and Management Plan

Risk Assessment Worksheet and Management Plan Customer/Project Name: The Basics There are four steps to assessing and managing risks, and effective risk management requires all four of them. 1. Identify the risks 2. Qualify the risks a. Assess each

More information

How to successfully manage your mega-project

How to successfully manage your mega-project How to successfully manage your mega-project Part I Early planning and organizing for success kpmg.com 2 Building, Construction & Real Estate How to successfully manage your mega-project A three-part series

More information

Understanding Software Project Management PMI fundamentals, Project Selection, Initial documents Emanuele Della Valle http://emanueledellavalle.

Understanding Software Project Management PMI fundamentals, Project Selection, Initial documents Emanuele Della Valle http://emanueledellavalle. Planning and Managing Software Projects 2011-12 Class 3 Understanding Software Project Management PMI fundamentals, Project Selection, Initial documents Emanuele Della Valle http://emanueledellavalle.org

More information

Course Outline. Foundation of Business Analysis Course BA30: 4 days Instructor Led

Course Outline. Foundation of Business Analysis Course BA30: 4 days Instructor Led Foundation of Business Analysis Course BA30: 4 days Instructor Led Prerequisites: No prerequisites - This course is suitable for both beginner and intermediate Business Analysts who would like to increase

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

Project Integration Management

Project Integration Management Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform

More information

Fairfield Public Schools

Fairfield Public Schools Mathematics Fairfield Public Schools AP Statistics AP Statistics BOE Approved 04/08/2014 1 AP STATISTICS Critical Areas of Focus AP Statistics is a rigorous course that offers advanced students an opportunity

More information

WM'99 CONFERENCE, FEBRUARY 28 - MARCH 4, 1999

WM'99 CONFERENCE, FEBRUARY 28 - MARCH 4, 1999 ROCKY FLATS CLOSURE PROJECT: PLANNING FOR UNCERTAINTY By Larry F. Burdge Vice President, Planning and Integration Kaiser-Hill company, LLC And Joe Nolter President Project Analysis & Evaluation, Inc. ABSTRACT

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Addressing Uncertainties in Design Inputs: A Case Study of Probabilistic Settlement Evaluations for Soft Zone Collapse at SWPF

Addressing Uncertainties in Design Inputs: A Case Study of Probabilistic Settlement Evaluations for Soft Zone Collapse at SWPF Addressing Uncertainties in Design Inputs: A Case Study of Probabilistic Settlement Evaluations for Soft Zone Collapse at SWPF Tom Houston, Greg Mertz, Carl Costantino, Michael Costantino, Andrew Maham

More information

Risk D&D Rapid Prototype: Scenario Documentation and Analysis Tool

Risk D&D Rapid Prototype: Scenario Documentation and Analysis Tool PNNL-18446 Risk D&D Rapid Prototype: Scenario Documentation and Analysis Tool Report to DOE EM-23 under the D&D Risk Management Evaluation and Work Sequencing Standardization Project SD Unwin TE Seiple

More information

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment // Taming an Unruly Schedule Using the 14-Point Schedule Assessment Dr. Dan Patterson, PMP CEO & President, Acumen February 2010 www.projectacumen.com Table of Contents Introduction... 3 The 14-Point Assessment...

More information

STAG Technical Database Section 13

STAG Technical Database Section 13 Risk and Uncertainty May 2014 Transport Scotland Once printed or downloaded this document is considered to be uncontrolled. For the current version refer to the Scot-TAG section of the Transport Scotland

More information

Solvency II Preparation and IMAP James Latto

Solvency II Preparation and IMAP James Latto and James Latto Contents 2 1 Balancing priorities Insurers need to balance priorities over the next year: Main focus is often on Pillar 3 and external reporting needs sufficient focus Ensure smooth transition

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method

A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method Send Orders for Reprints to reprints@benthamscience.ae 254 The Open Cybernetics & Systemics Journal, 2014, 8, 254-258 Open Access A Robustness Simulation Method of Project Schedule based on the Monte Carlo

More information

Principles-based Valuation of Life Insurance Products

Principles-based Valuation of Life Insurance Products Principles-based Valuation of Life Insurance Products November 17, 2005 Shawn D. Parks, FSA, MAAA Vice President and Illustration Actuary 306PP9493 1105 This presentation expresses the views of the presenter

More information

ORACLE S PRIMAVERA RISK ANALYSIS

ORACLE S PRIMAVERA RISK ANALYSIS ORACLE S PRIMAVERA RISK ANALYSIS KEY FEATURES Risk Analysis Guide Schedule Check Templated Quick Risk Risk Register Wizard Risk Register Risk Analysis Every project has risks. The organizations that succeed

More information

Project Management Office (PMO)

Project Management Office (PMO) Contents I. Overview of Project Management...4 1. Project Management Guide (PMG)...4 1.1 Introduction...4 1.2 Scope...6 1.3 Project Types...6 2. Document Overview, Tailoring, and Guidance...7 3. The Project

More information

Quick Reference Guide Interactive PDF Project Management Processes for a Project

Quick Reference Guide Interactive PDF Project Management Processes for a Project Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process

More information

Risk Management Procedure

Risk Management Procedure Purpose of this document Develop and document procedures and work instructions for Risk Management to cover the project Stages set out in the Project Process Map. The purpose of this procedure is to identify

More information

Advancements in Construction Project Administration Session: 41 October 28, 2014

Advancements in Construction Project Administration Session: 41 October 28, 2014 Advancements in Construction Project Administration Session: 41 October 28, 2014 Room: C220-222 3:00PM 3:45PM Claims ance, Mitigation and Resolution Take Advantage of New Tools Presented by: Andrew Morse,

More information

MEASURES FOR EXCELLENCE Getting a "RUNAWAY" Software Development. Under Control. A Case Study

MEASURES FOR EXCELLENCE Getting a RUNAWAY Software Development. Under Control. A Case Study MEASURES FOR EXCELLENCE Getting a "RUNAWAY" Software Development Under Control A Case Study.J.W.E Greene QUANTITATIVE SOFTWARE MANAGEMENT LTD 7 rue Fenoux 93 Blythe Road, Paris 71 London W1 OHP Tel: 33-1-311

More information

www.pwc.com Business Resiliency Business Continuity Management - January 14, 2014

www.pwc.com Business Resiliency Business Continuity Management - January 14, 2014 www.pwc.com Business Resiliency Business Continuity Management - January 14, 2014 Agenda Key Definitions Risks Business Continuity Management Program BCM Capability Assessment Process BCM Value Proposition

More information

PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP

PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP TSE015 PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP Course Outline I. Introduction and Course Objectives A. About PMI B. PMP and CAPM

More information

Happily Ever After: Project Management Tips and Tricks for the SAMHSA Grantee

Happily Ever After: Project Management Tips and Tricks for the SAMHSA Grantee Happily Ever After: Project Management Tips and Tricks for the SAMHSA Grantee Lloyd Potter, PhD, MPH SPRC Tarsha M. Wilson, MSW SAMHSA/CMHS December 10-12, 2007 GLSMA Grantee Meeting Portland, OR Project

More information

Security Risk Assessment and Mitigation Prioritization

Security Risk Assessment and Mitigation Prioritization Security Risk Assessment and Mitigation Prioritization Stephanie King, PhD, PE Weidlinger Associates, Inc. FFC Committee on Physical Security and Hazard Mitigation July 15, 2008 www.wai.com New York Massachusetts

More information

Developing Critical Path Method Scheduling (CPM)

Developing Critical Path Method Scheduling (CPM) Developing Critical Path Method Scheduling (CPM) Pretest 1. An activity which is on critical path has a planned duration of 5 days. What is the total float for the activity? a. 0 b. 1 c. 2 d. 3 Pretest

More information

Money market portfolio

Money market portfolio 1 Money market portfolio April 11 Management of Norges Bank s money market portfolio Report for the fourth quarter 1 Contents 1 Key figures Market value and return 3 3 Market risk and management guidelines

More information

Life Cycle Cost Analysis (LCCA)

Life Cycle Cost Analysis (LCCA) v01-19-11 Life Cycle Cost Analysis (LCCA) Introduction The SHRP2 R-23 Guidelines provide a number of possible alternative designs using either rigid of flexible pavements. There is usually not a single

More information

BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18

BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18 Cambridge TECHNICALS OCR LEVEL 3 CAMBRIDGE TECHNICAL CERTIFICATE/DIPLOMA IN BUSINESS BUSINESS PROJECT MANAGEMENT K/502/5459 LEVEL 3 UNIT 18 GUIDED LEARNING HOURS: 60 UNIT CREDIT VALUE: 10 BUSINESS PROJECT

More information