Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Size: px
Start display at page:

Download "Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board"

Transcription

1 Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board PJM Staff Whitepaper February 2016

2 EXECUTIVE SUMMARY The PJM Board of Managers previously approved changes to the Regional Transmission Expansion Plan (RTEP) on December 16, 2015, totaling $ million, primarily to resolve identified reliability criteria violations. Since that time PJM has identified a number of changes to previously approved baseline projects resulting in an increase of $84.26 million. In addition to the changes to previously approved baseline reliability upgrades, PJM staff is also recommending several market efficiency projects to address energy market and capacity market congestion. These market efficiency projects, which were solicited through the 2014/15 long-term RTEP proposal window, have an estimated cost of $20.48 million and are expected to mitigate at least $300 million in energy market congestion over the next 15 years, and provide total annual savings of $118 million in capacity load payments in RPM. The net impact to the RTEP to include these new upgrades and changes to previously approved projects is an increase of $ million. With these changes, the RTEP will include over $28, million of transmission additions and upgrades since the first plan was approved by the Board in 2000., the elements of the 2016 RTEP for the additional baseline upgrades were presented for the Board Reliability Committee s (BRC) consideration and for recommendation to the PJM Board for approval and inclusion in the RTEP. The PJM Board approved the changes as described below. PJM 2015 Page 1 of 9 PJM DMS #

3 SUMMARY OF RESULTS In 2012 PJM filed proposed changes to the Operating Agreement in compliance with FERC Order Those changes were approved by the FERC and were implemented for the first time as part of the 2014 RTEP. As part of that implementation, PJM administered the first Long Term Market Efficiency Proposal Window from November 2014 through February of /2015 Long-Term Market Efficiency Proposal Window: Market Efficiency Analysis is a part of the overall Regional Transmission Planning Process (RTEP) to accomplish the following objectives: 1. Determine which reliability upgrades, if any, have an economic benefit if accelerated or modified. 2. Identify new transmission upgrades that may result in economic benefits. 3. Identify economic benefits associated with hybrid transmission upgrades. Hybrid transmission upgrades include proposed solutions which encompass modification to reliability-based enhancements already included in RTEP that when modified would relieve one or more economic constraints. Such hybrid upgrades resolve reliability issues but are intentionally designed in a more robust manner to provide economic benefits in addition to resolving those reliability issues. Market Efficiency analysis is conducted using a market simulation tool which models the hourly securityconstrained commitment and dispatch of generation over a future annual period. Economic benefits of transmission upgrades are determined by comparing results of simulations which include the study upgrade to results of simulations which do not include the study upgrade. Projects are measured using two Tariff/Operating Agreement criteria. First, the project must address congestion as simulated in the Market Efficiency analysis. Second, the project benefits must exceed the costs by at least 25 percent. Project benefits are measured by comparing the benefits in the form of net load payments and/or production costs with and without the proposed project for a 15-year study period. Prior to opening the 2014/15 long-term proposal window, PJM staff provided entities with a list of facilities, along with simulated congestion dollars. PJM received 93 project proposals to address either future simulated congestion or capacity costs from the 2014/15 long-term window. The Submitted proposals ranged in costs from $0.1 to $432 million and included Transmission Owner upgrades as well as Greenfield projects from incumbent transmission owners and non-incumbent entities. PJM 2015 Page 2 of 9 PJM DMS #

4 Market Efficiency 2015 Approved Projects In 2015, the PJM Board approved 11 Market Efficiency projects for inclusion in the 2015 RTEP. These projects, consisted of upgrades to existing equipment and were designated to the incumbent transmission owners. Figure 1 on the next page shows the location of the approved projects. Figure 1: Map of 2015 Approved Market Efficiency Projects 15-Year Savings: Production Costs: $224 million Load Payments: $692 million Congestion: $815 million Following the October 2015 Board meeting, PJM staff continued to assess two groups of projects. The first group included projects submitted to address congestion associated with PJM IROL (Interconnected Reliability Operating Limit) reactive interfaces. The second group included projects submitted to address increased capacity costs from restricted Capacity Emergency Transfer Limits (CETL) encountered in PJM s Reliability Pricing Model (RPM) auctions for the COMED Locational Deliverability Area (LDA). As result of this assessment PJM staff is recommending additional Market Efficiency projects to be included in the RTEP. The recommended projects are described below. IROL Market Efficiency Baseline Project B2729 Optimal Capacitor Configuration As mentioned above, PJM staff continued to assess separate projects directed at congestion associated with PJM IROL (Interconnected Reliability Operating Limit) reactive interfaces. Specifically these projects PJM 2015 Page 3 of 9 PJM DMS #

5 were recommended to reduce congestion on either the AP-South or AEP-DOM reactive interfaces 1. Of the 41 projects proposed to address the reactive interface congestion, six projects provided the most benefits. Many of these projects provided area reactive support through distributed capacitor installations. The addition of capacitors can help to maintain system voltages during heavy transfers however the addition of too many capacitors in a local area could create operational problems. PJM Markets, Planning, and Operations collaborated to select the optimal set of capacitors from those that were submitted in the proposal window. Based on the PJM analysis, a capacitor configuration that provides high market congestion benefits, high reliability, and allows for optimal operational impact was selected as solution. The recommended locations are depicted in the Figure 2, and consist of new capacitor installations of 175 MVAR, 175 MVAR, 300 MVAR, and 150 MVAR at the existing Brambleton, Ashburn, Shelhorn, and Liberty 230kV substations, respectively. These upgrades to existing equipment will be designated to the incumbent transmission owner. Figure 2: Location of Recommended Capacitors 1 PJM reactive interface limits are thermal limit (MW) values that correlate to power flows beyond which voltage violations may occur PJM 2015 Page 4 of 9 PJM DMS #

6 Table 1. Recommended Market Efficiency Project for PJM IROL Reactive interface PJM Baseline ID b2729 PJM Window Project ID Combination of several different proposals Project Description Optimal Capacitors Configuration: New 175 MVAR capacitor at Brambleton, new 175 MVAR capacitor at Ashburn, new 300 MVAR capacitor at Shelhorn, new 150 MVAR capacitor at Liberty Transmiss ion Zone Constraint Project Addresses Project Cost ($M) ISD Dominion AP-South $ The project is expected to cost $8.98 million and the required in service date is June 1, The cost allocation for this project is provided in Attachment A of this document. RPM Market Efficiency Baseline Project B2728 Mitigation of Loretto Wilton Center 345kV Sag Limitation During the 2014/2015 Long-Term Market Efficiency Proposal Window, PJM received nine proposals to address congestion on the Loretto to Wilton Center 345 kv line, in the COMED area. These nine proposals were received from three entities and their cost ranged from $11.5 million to $290 million. Two entities were not incumbent PJM transmission owners and the third entity was a PJM transmission owner, ComEd. Following the 2018/19 Reliability Pricing Model (RPM) Base Residual Auction (BRA) in August of 2015, imports into the COMED LDA were limited by the Loretto to Wilton Center 345 kv line. As a result, the nine proposals that were originally submitted to address energy market congestion on the Loretto to Wilton Center 345 kv line could also provide capacity market (i.e. RPM) benefits. PJM 2015 Page 5 of 9 PJM DMS #

7 Figure 3: Loretto - Wilton Center 345kV Market Efficiency Proposals The capacity benefits associated with the proposed projects were determined using the methodologies specified in Schedule 6 of the PJM Operating Agreement. PJM s annual capacity benefit calculation for regional facilities is weighted 50 percent to change in total system capacity cost and 50 percent to change in net load capacity payments for zones with a decrease in net load capacity payments as a result of the proposed project. PJM s annual capacity benefit calculation for lower voltage facilities is weighted 100 percent to zones with a decrease in net load capacity payments as a result of the proposed project. Change in net load capacity payment comprises the change in gross capacity payment offset by the change in capacity transfer rights. PJM determined the impact of each of the nine proposed projects on the COMED LDA Capacity Emergency Transfer Limit (CETL). By increasing the capability of the LDA s limiting element (i.e. Lorretto to Wilton Center), the COMED zone and other LDAs may be able to satisfy capacity requirements at a lower overall cost. PJM simulated the RPM process for multiple study years with the updated CETL values and measured each projects capacity benefits over a 15 year period. The total Market Efficiency benefit of a project is the summation of the energy market benefit and the capacity market benefit. The energy market benefits were derived from the 2015 sensitivity case analysis and the capacity benefits were derived from the RPM simulation analysis. PJM 2015 Page 6 of 9 PJM DMS #

8 The project shown in Figure 4 provides the highest total Market Efficiency benefit and was recommended for Board approval for inclusion into the RTEP. An annual estimated $118 million in capacity payment benefits is achieved when the COMED LDA is limiting. This project is an upgrade to existing equipment, is designated to the incumbent transmission owner, increases the summer normal rating on the Loretto Wilton 345 kv line by over 150 MVA, and increases the emergency rating by almost 250 MVA. The recommended solution is to eliminate sag limitations on the Loretto Wilton Center 345kV line, and upgrade station conductor at Wilton Center. The estimated cost is $11.5 million and the required in service date is June 1, The cost allocation for this project is provided in Attachment A of this document. Figure 4: RPM Recommended Project Loretto - Wilton Center 345kV Annual Potential Capacity Payment Savings: $118 million PJM Baseline ID b2728 PJM Window Project ID _1-10D Table 2. Recommended Market Efficiency Projects for RPM Project Description Mitigate sag limitations on Loretto - Wilton Center 345 kv Line and replace station conductor at Wilton Center Transmis sion Zone ComEd Constraint Project Addresses Lorreto to Wilton CTR 345 kv Project Cost ($M) ISD Total B/C Ratio (Energy+RPM) $ Changes to Previously Approved Projects Cost and scope of a number of previously approved RTEP baseline projects have been changed. In addition, a number or projects have been cancelled as they are no longer required. The net result of these PJM 2015 Page 7 of 9 PJM DMS #

9 changes to previously approved baseline projects is a net increase in the RTEP of $84.26 million. Some of the more significant cost changes are noted below. PPL has provided PJM with an updated cost estimate for the previously approved RTEP project B2006 which includes the installation of a new Lauschtown 500/230kV substation, the construction of a new 230/69kV Lauschtown substation, and the construction of a new 69/138kV transmission from Lauschtown 230/69kV sub to Brecknock and Honeybrook areas. The additional estimated cost for B2006 is $15.6 million. Also, the scope of the previously approved RTEP project B2187 to install four 230kV breakers at Shellhorn has been modified to install two additional 230kV breakers at Shellhorn and terminate the Enterprise Brambleton 230kV line into Shellhorn. The additional circuit breakers are required to address new N-1-1 criteria violations that were not identified initially. The additional estimated cost is $2 million. Finally, the scope of the previously approved RTEP project B1912 to install three +/- 125 MVAr STATCOM at three different 230kV substations (Landstown, Yadkin, and Fentress) has been modified to install a fourth +/- 125 MVAr STATCOM at Chesapeake and to install a +/-125 MVAr STATCOM at Lynnhaven 230kV in lieu of Yadkin. The new configuration will improve dynamic reactive capability in the area. The additional estimated cost is $35 million. Review by the Transmission Expansion Advisory Committee (TEAC) The results of the analyses summarized in this report were reviewed with the TEAC and Subregional RTEP Committees over several meetings throughout 2015 and The most recent analysis, along with recommended solutions, were reviewed at the January 7, 2016 TEAC meeting. Written comments were requested to be submitted to PJM communicating any concerns with the recommendation and any alternative transmission solutions for consideration. Cost Allocation Preliminary cost allocations to multiple transmission zones for the approved projects are shown in Attachment A. Cost allocations for the projects were calculated in accordance with the Schedule 12 of the OATT. Baseline reliability project allocations are calculated using a distribution factor methodology that allocates the cost to the load zones that contribute to the loading on the new facility. The market efficiency projects are allocated to the load zones that benefit from the project. The allocations will be filed at FERC 30 days following approval by the Board. Board Approval The PJM Board Reliability Committee endorsed the new baseline projects and associated cost allocations. The PJM Board Reliability Committee recommended to the Board the approval of the baseline upgrades to the 2016 RTEP, and the PJM Board of Managers have approved the changes to the RTEP. PJM 2015 Page 8 of 9 PJM DMS #

10 Attachment A Market Efficiency Multiple Zone Cost Allocations PJM Board Reliability Committee February 17, 2016 Market Efficiency and Project Multiple Zone Allocations Upgrade ID b2729 b2728 Description Optimal Capacitors Configuration: New 175 MVAR capacitor at Brambleton, new 175 MVAR capacitor at Ashburn, new 300 MVAR capacitor at Shelhorn, new 150 MVAR capacitor at Liberty Mitigate sag limitations on Loretto - Wilton Center 345 kv Line and replace station conductor at Wilton Center Cost Estimate ($M) Trans Owner $8.98 DOM $11.50 COMED Cost Responsibility AECO %, BGE %, DOM %, DPL %, JCPL %, LINDVFT %, METED %, NEPTHVDC %, O66HVDC %, PECO %, PEPCO %, PLGRP %, PSEG %. AEP %, COMED %, DUQ %, FE- ATSI %. Required IS Date 6/1/2019 6/1/2019 PJM 2015 Page 9 of 9 PJM DMS #

PJM Overview of Markets. Georgian Delegation PUCO Office April 11, 2013

PJM Overview of Markets. Georgian Delegation PUCO Office April 11, 2013 PJM Overview of Markets Georgian Delegation PUCO Office April 11, 2013 1 Agenda Introduction Energy Markets Locational Marginal Pricing - LMP Two Settlement - Day Ahead / Real time Ancillary Services Capacity

More information

2019/2020 RPM Base Residual Auction Results

2019/2020 RPM Base Residual Auction Results Executive Summary The 2019/2020 Reliability Pricing Model (RPM) Base Residual Auction (BRA) cleared 167,305.9 MW of unforced capacity in the RTO. Accounting for load and resource commitments under the

More information

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055 Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights

More information

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations PJM Overview and Wholesale Power Markets John Gdowik PJM Member Relations PJM s Role Ensures the reliability of the high-voltage electric power system Coordinates and directs the operation of the region

More information

Generation and Transmission Interconnection Process

Generation and Transmission Interconnection Process PJM Manual 14A Generation and Transmission Interconnection Process Revision: 18 Effective Date: January 28, 2016 Prepared by Planning Division Generation Interconnection Department PJM 2016 Table of Contents

More information

Options for Intermittent and Seasonal Resources for 2020/21 and beyond

Options for Intermittent and Seasonal Resources for 2020/21 and beyond Options for Intermittent and Seasonal Resources for 2020/21 and beyond April 26, 2016 www.pjm.com Base Capacity Resources Base Capacity Resources are resources that are not capable of sustained, predictable

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114. Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine

More information

PJM Electric Market. PJM Electric Market: Overview and Focal Points. Federal Energy Regulatory Commission Market Oversight www.ferc.

PJM Electric Market. PJM Electric Market: Overview and Focal Points. Federal Energy Regulatory Commission Market Oversight www.ferc. PJM Electric Market: Overview and Focal Points Page 1 of 14 PJM Electric Market Source: Velocity Suite Intelligent Map Updated August 23, 21 145 PJM Electric Market: Overview and Focal Points Page 2 of

More information

2016/2017 RPM Base Residual Auction Results

2016/2017 RPM Base Residual Auction Results Executive Summary The 2016/2017 Reliability Pricing Model (RPM) Base Residual Auction (BRA) cleared 169,159.7 MW of unforced capacity in the RTO. Accounting for load and resource commitments under the

More information

Section 4: Integrating Public Policy Drivers

Section 4: Integrating Public Policy Drivers Public Policy Drivers Section : Integrating Public Policy Drivers PJM DE DC IL IN KY MD MI NJ NC OH PA TN VA WV Section.0: The Role of Public Policy in the RTEP Process Figure.1: Public Policy Drivers

More information

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System Prepared By: Transmission Planning Unit Baltimore Gas & Electric Company Table of Contents 1. INTRODUCTION

More information

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

PUBLIC SERVICE COMMISSION OF MARYLAND TEN-YEAR PLAN (2012 2021) OF ELECTRIC COMPANIES IN MARYLAND

PUBLIC SERVICE COMMISSION OF MARYLAND TEN-YEAR PLAN (2012 2021) OF ELECTRIC COMPANIES IN MARYLAND PUBLIC SERVICE COMMISSION OF MARYLAND TEN-YEAR PLAN (2012 2021) OF ELECTRIC COMPANIES IN MARYLAND Prepared for the Maryland Department of Natural Resources In compliance with Section 7-201 of the Maryland

More information

PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study

PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study PJM Merchant Transmission Request Queue #R75 Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study 413038v1a March 2007 PJM Interconnection 2007. All rights reserved. Preface The intent of the

More information

Energy Management System (EMS) Model Updates and Quality Assurance (QA)

Energy Management System (EMS) Model Updates and Quality Assurance (QA) PJM Manual 3A: Energy Management System (EMS) Model Updates and Quality Assurance (QA) Revision: 10 Effective Date: June 25, 2015 Prepared by: Operation Support Division PJM 2015 PJM 2007 Revision 0, Effective

More information

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach READ AND DELETE For best results with this template, use PowerPoint 2003 10 November 2015 Background and Importance of ICA Definition:

More information

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives (Required per CPUC Decision No. C10-1328) Final Report (Submitted with Public Service s 2011 ERP) Executive Summary The objective

More information

Enabling End Users to see Real Time Price Signals and Manage their Own Electricity Costs via the PJM Demand Side Response Program Delaware DNREC

Enabling End Users to see Real Time Price Signals and Manage their Own Electricity Costs via the PJM Demand Side Response Program Delaware DNREC Enabling End Users to see Real Time Price Signals and Manage their Own Electricity Costs via the PJM Demand Side Response Program Delaware DNREC Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693

More information

Cross-Tie Transmission Line. Ravikanth Varanasi Principal Transmission Planner

Cross-Tie Transmission Line. Ravikanth Varanasi Principal Transmission Planner Cross-Tie Transmission Line Ravikanth Varanasi Principal Transmission Planner Overview ~213 mile 500-kV transmission line between PacifiCorp s proposed Clover 500 kv substation with NV Energy s Robinson

More information

PJM LMP Market Overview

PJM LMP Market Overview PJM LMP Market Overview Andrew Ott Senior Vice President, Markets June 10, 2010 PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies 600+ millions of people

More information

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 I. Background The Solar Alliance is a group of approximately 30 of the largest photovoltaic (PV) solar development and

More information

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment March 20, 2009 Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Table of Contents:

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003 F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify

More information

Energy Efficiency Measurement & Verification

Energy Efficiency Measurement & Verification PJM Manual 18B: Energy Efficiency Measurement & Verification Revision: 02 Effective Date: 12/17/2015 Prepared by PJM Forward Market Operations PJM 2015 PJM 2008 Revision, Effective Date: i Table of Contents

More information

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Pakistan Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Final Report: Executive Summary - November 2015 for USAID Energy Policy

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

Q140 Cluster Addendum

Q140 Cluster Addendum Cluster Addendum 1. INTRODUCTION This Interconnection Customer (IC), submitted a Small Generator Interconnection Request (IR) to Arizona Public Service Company (APS) for their proposed project, located

More information

Workshop B. 11:15 a.m. to 12:30 p.m.

Workshop B. 11:15 a.m. to 12:30 p.m. Workshop B Advanced Energy Management Tools: Benefitting from the Competitive Electricity Marketplace Beyond the Fixed Rate & Key Issues to Understand when Comparing Electricity Quotes 11:15 a.m. to 12:30

More information

Transmission Planning in the ERCOT Interconnection

Transmission Planning in the ERCOT Interconnection Transmission Planning in the ERCOT Interconnection Warren Lasher Manager, Long-Term Planning and Policy Department of Energy Electricity Advisory Committee The ERCOT Interconnection The ERCOT Region is

More information

ELECTRIC POWER OUTLOOK FOR PENNSYLVANIA 2012 17

ELECTRIC POWER OUTLOOK FOR PENNSYLVANIA 2012 17 ELECTRIC POWER OUTLOOK FOR PENNSYLVANIA 2012 17 August 2013 Published by: Pennsylvania Public Utility Commission P.O. Box 3265 Harrisburg, PA 17105-3265 www.puc.pa.gov Technical Utility Services Paul T.

More information

TDI's NYC Merchant CHPE Transmission Project with POI at Astoria (NYISO Queue #305) Deliverability Analysis

TDI's NYC Merchant CHPE Transmission Project with POI at Astoria (NYISO Queue #305) Deliverability Analysis R103-11 TDI's NYC Merchant CHPE Transmission Project with POI at Astoria (NYISO Queue #305) Deliverability Analysis Prepared for Transmission Developers, Inc. Submitted by: Larry Eng, Staff Consultant

More information

Last revised: September 1, 2014 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS

Last revised: September 1, 2014 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS Last revised: September 1, 2014 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS EVP, Chief Operations Officer, has primary responsibility for the overall planning, operations and control of the transmission

More information

WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS. No of Staff Provided by BCE. Overall Project Value (SR)

WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS. No of Staff Provided by BCE. Overall Project Value (SR) WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS A. Completed December 2001 Shedgum Debottlenecking # 45943/00 47.34 Million Total 600.8 Million 154 n American Oil Co. (ARAMCO) ARAMCO Feb. 1998 to Dec.

More information

University Project & Capital Planning Change Management Process

University Project & Capital Planning Change Management Process Overview Over the next six years, the university is facing an unprecedented amount of construction on campus. At a two day meeting held on May 8-9, 2008, over 55 members of key university areas presented

More information

Robust Adaptive Topology Control

Robust Adaptive Topology Control Robust Adaptive Topology Control Mladen Kezunovic, PI Texas A&M University Kory W. Hedman, Co-PI Arizona State University January 14-15, 2015 System Integration Robust Adaptive Topology Control (RATC)

More information

GIP. 3.2.3 Net Zero Interconnection Service.

GIP. 3.2.3 Net Zero Interconnection Service. GIP and GIA Energy Displacement Agreement shall mean an agreement between an Interconnection Customer with a commercially operating Generating Facility on the Transmission Provider s Transmission System

More information

Electric Field Operations Organization

Electric Field Operations Organization NSTAR Electric Transmission Function Job Summaries Electric Field Operations Organization Vice President, Electric Field Operations (Transmission) This position has primary responsibility for the planning,

More information

Presentation for The National Commission for Energy State Regulation of Ukraine

Presentation for The National Commission for Energy State Regulation of Ukraine Presentation for The National Commission for Energy State Regulation of Ukraine Todd Keech Laura Walter PJM Interconnection June 17, 2014 What is PJM? 1 What is PJM? ISO RTO Map Part of Eastern Interconnection

More information

IESO Supply Deliverability Guidelines

IESO Supply Deliverability Guidelines PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents

More information

NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario

NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario Table of Contents NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario Table of Contents... 2 1. Executive Summary...

More information

Summary of CIP Version 5 Standards

Summary of CIP Version 5 Standards Summary of CIP Version 5 Standards In Version 5 of the Critical Infrastructure Protection ( CIP ) Reliability Standards ( CIP Version 5 Standards ), the existing versions of CIP-002 through CIP-009 have

More information

In the Supreme Court of the United States

In the Supreme Court of the United States NOS. 14-614, 14-623 In the Supreme Court of the United States W. KEVIN HUGHES, et al., Petitioners, v. TALEN ENERGY MARKETING, LLC (F/K/A PPL ENERGYPLUS, LLC), et al., Respondents. CPV MARYLAND, LLC, v.

More information

FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria

FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria A. Purpose: The FRCC Reliability Coordinator (RC) Contingency Analysis (CA) application is essential to maintaining the reliability of the FRCC Bulk Electric System. The application has the capability

More information

PJM Interconnection LLC Regional Transmission Organization (RTO)

PJM Interconnection LLC Regional Transmission Organization (RTO) PJM Interconnection LLC Regional Transmission Organization (RTO) ComEd Generator Interconnection Meeting October 2015 William Patzin PJM Infrastructure Coordination October 2015 PJM 2013 Nine Major North

More information

Quantifying the Amount and Economic Impacts of Missing Energy Efficiency in PJM s Load Forecast

Quantifying the Amount and Economic Impacts of Missing Energy Efficiency in PJM s Load Forecast Quantifying the Amount and Economic Impacts of Missing Energy Efficiency in PJM s Load Forecast PREPARED FOR The Sustainable FERC Project PREPARED BY Ahmad Faruqui, Ph.D. Sanem Sergici, Ph.D. Kathleen

More information

Generator Interconnection and Deliverability Study Methodology Technical Paper

Generator Interconnection and Deliverability Study Methodology Technical Paper Generator Interconnection and Deliverability Study Methodology Technical Paper July 2, 2013 Generator Interconnection and Deliverability Study Methodology Table of Contents Introduction... 1 Section One:

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator

More information

Magnus Callavik, ABB Power Systems, HVDC, 721 64 Västerås, Sweden Phone: +46(0)21323226. e-mail: magnus.callavik@se.abb.com

Magnus Callavik, ABB Power Systems, HVDC, 721 64 Västerås, Sweden Phone: +46(0)21323226. e-mail: magnus.callavik@se.abb.com HVDC GRIDS FOR OFFSHORE AND ONSHORE TRANSMISSION Magnus Callavik, ABB Power Systems, HVDC, 721 64 Västerås, Sweden Phone: +46(0)21323226. e-mail: magnus.callavik@se.abb.com SUMMARY The objective with this

More information

Section 1: Executive Summary

Section 1: Executive Summary Section 1: Executive Summary SECTION 1: EXECUTIVE SUMMARY 1.1 SECTION PURPOSE This report has been prepared for the Nevada Energy Assistance Corporation (NEAC), a 501(c)(3) non-profit agency; in support

More information

The Value of Distributed Solar Electric Generation to New Jersey and Pennsylvania

The Value of Distributed Solar Electric Generation to New Jersey and Pennsylvania The Value of Distributed Solar Electric Generation to New Jersey and Pennsylvania Richard Perez Benjamin L. Norris Thomas E. Hoff November 2012 Prepared for: Mid Atlantic Solar Energy Industries Association

More information

Recommended Cost Allocation Treatment for the Supply to Essex County Transmission Reinforcement. Ontario Power Authority

Recommended Cost Allocation Treatment for the Supply to Essex County Transmission Reinforcement. Ontario Power Authority Recommended Cost Allocation Treatment for the Supply to Essex County Transmission Reinforcement Ontario Power Authority January, 01 Contents 1 Executive Summary... Introduction and Purpose... Assessment

More information

2013 Ventyx, an ABB company

2013 Ventyx, an ABB company Co-optimization of Congestion Revenue Rights in ERCOT Day-Ahead Market Chien-Ning Yu, Vladimir Brandwajn, Show Chang ABB/Ventyx Sainath M. Moorty ERCOT FERC Conference on increasing real-time and day-ahead

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) PROTEST OF THE INDEPENDENT MARKET MONITOR FOR PJM

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) PROTEST OF THE INDEPENDENT MARKET MONITOR FOR PJM UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION CPV Maryland, LLC ) ) ) Docket No. ER14-2106-000 PROTEST OF THE INDEPENDENT MARKET MONITOR FOR PJM Pursuant to Rule 211 of the Commission

More information

Merchant Generation Site Selection On the AEP Transmission System

Merchant Generation Site Selection On the AEP Transmission System Merchant Generation Site Selection On the AEP Transmission System Pursuant to the Federal Energy Regulatory Commission's Order of November 20, 2001, in AEP Power Marketing, Inc., et al, 97 FERC 61,219,

More information

Generation Interconnection Facilities Study Report. For. PJM Generation Interconnection Request Queue Position R11. South River

Generation Interconnection Facilities Study Report. For. PJM Generation Interconnection Request Queue Position R11. South River Generation Interconnection Facilities Study Report For PJM Generation Interconnection Request Queue Position R11 South River May 2012 Transmission Owner Facilities Study Summary Description of Project

More information

EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID

EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID Tension (kv) Impedance (Ohms) EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID frequency (Hz) Simon DESCHANVRES Yannick VERNAY RTE, CNER, Substations Department t (ms) EMTP-RV Users Group

More information

Reactive Power and Importance to Bulk Power System OAK RIDGE NATIONAL LABORATORY ENGINEERING SCIENCE & TECHNOLOGY DIVISION

Reactive Power and Importance to Bulk Power System OAK RIDGE NATIONAL LABORATORY ENGINEERING SCIENCE & TECHNOLOGY DIVISION Reactive Power and Importance to Bulk Power System OAK RIDGE NATIONAL LABORATORY ENGINEERING SCIENCE & TECHNOLOGY DIVISION Outline What is Reactive Power and where does it come from? Why is it important?

More information

Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA

Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA CROSS SOUND CABLE PROJECT 330MW HVdc INTERCONNECTION BETWEEN NEW HAVEN, CONNECTICUT AND SHOREHAM, NY Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA Subordinate Status Removal and Amendment of Approved

More information

Schedule 19 POWER PURCHASES FROM COGENERATION AND SMALL POWER PRODUCTION QUALIFYING FACILITIES

Schedule 19 POWER PURCHASES FROM COGENERATION AND SMALL POWER PRODUCTION QUALIFYING FACILITIES I. APPLICABILITY & AVAILABILITY This Schedule is applicable to any Cogenerator or Small Power Producer (Qualifying Facility), as defined in the Public Utility Regulatory Policies Act of 1978 (PURPA), which

More information

Market Solutions to Loop Flow

Market Solutions to Loop Flow Market Solutions to Loop Flow Robert Pike Director, Market Design New York Independent System Operator Business Issues Committee September 9, 2009 1 Agenda Background Recommendation Next Steps Solution

More information

The remainder of this memo provides a summary of market performance and trends in 2014 through November.

The remainder of this memo provides a summary of market performance and trends in 2014 through November. California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Eric Hildebrandt, Director, Market Monitoring Date: December 10, 2014 Re: Market monitoring report This memorandum

More information

FINAL. Alternative Evaluation. for the. Proposed Burlington-Wray 230-kilovolt Transmission Project

FINAL. Alternative Evaluation. for the. Proposed Burlington-Wray 230-kilovolt Transmission Project FINAL Alternative Evaluation for the Proposed Burlington-Wray 230-kilovolt Transmission Project Prepared by Tri-State Generation and Transmission Association, Inc. 1100 W. 116th Avenue Westminster, Colorado

More information

APPENDIX 7 TO LGIP INTERIM INTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT

APPENDIX 7 TO LGIP INTERIM INTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT APPENDIX 7 TO LGIP INTERIM INTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT THIS AGREEMENT is made and entered into this day of, 20 by and between, a organized and existing under the laws of the State of,

More information

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional power generation Power generation from renewables

More information

Northport - Norwalk Harbor Cable (NNC) Tie line

Northport - Norwalk Harbor Cable (NNC) Tie line September 9, 008 Northport - Norwalk Harbor Cable (NNC) Tie line Technical Assessment of Operating up to NNC Inter Tie STE Ratings Executive Summary Three (3) 38kV submarine cable circuits (Lines 60, 60,

More information

COLORADO SPRINGS UTILITIES ATTACHMENT K TO OPEN ACCESS TRANSMISSION TARIFF

COLORADO SPRINGS UTILITIES ATTACHMENT K TO OPEN ACCESS TRANSMISSION TARIFF COLORADO SPRINGS UTILITIES ATTACHMENT K TO OPEN ACCESS TRANSMISSION TARIFF I. INTRODUCTION The City of Colorado Springs, Colorado ( City ) is a Colorado home-rule municipal corporation with a population

More information

PATTERNS OF TRANSMISSION INVESTMENT. Paul L. Joskow 1 MIT ABSTRACT

PATTERNS OF TRANSMISSION INVESTMENT. Paul L. Joskow 1 MIT ABSTRACT March 15, 2005 PATTERNS OF TRANSMISSION INVESTMENT Paul L. Joskow 1 MIT ABSTRACT This paper examines a number of issues associated with alternative analytical approaches for evaluating investments in electricity

More information

A Tariff for Reactive Power Christopher Tufon, Alan Isemonger, Brendan Kirby, Senior Member, John Kueck, Senior Member, and Fangxing Li, Senior Member

A Tariff for Reactive Power Christopher Tufon, Alan Isemonger, Brendan Kirby, Senior Member, John Kueck, Senior Member, and Fangxing Li, Senior Member 1 A Tariff for Reactive Power Christopher Tufon, Alan Isemonger, Brendan Kirby, Senior Member, John Kueck, Senior Member, and Fangxing Li, Senior Member Abstract-- This paper describes a suggested tariff

More information

Understanding Power Factor and How it Affects Your Electric Bill. Presented by Scott Peele PE

Understanding Power Factor and How it Affects Your Electric Bill. Presented by Scott Peele PE Understanding Power Factor and How it Affects Your Electric Bill Presented by Scott Peele PE Understanding Power Factor Definitions kva, kvar, kw, Apparent Power vs. True Power Calculations Measurements

More information

Memorandum. This memorandum requires Board action. Executive Summary

Memorandum. This memorandum requires Board action. Executive Summary California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: July 8, 2014 Re: Decision on the Delaney-Colorado

More information

An Overview of the Midwest ISO Market Design. Michael Robinson 31 March 2009

An Overview of the Midwest ISO Market Design. Michael Robinson 31 March 2009 An Overview of the Midwest ISO Market Design Michael Robinson 31 March 2009 The Role of RTOs Monitor flow of power over the grid Schedule transmission service Perform transmission security analysis for

More information

September 13, 2010. Replace Tunis T1 Notification of Conditional Approval of Connection Proposal CAA ID Number: 2010-EX506

September 13, 2010. Replace Tunis T1 Notification of Conditional Approval of Connection Proposal CAA ID Number: 2010-EX506 September 13, 2010 Mr. Charles Wickham General Manager Eastern Operations Capital Power Corporation Suite 1301, 200 University Avenue Toronto, ON M5H 3C6 Dear Mr. Wickham: Replace Tunis T1 Notification

More information

ELECTRIC POWER OUTLOOK FOR PENNSYLVANIA 2013 2018

ELECTRIC POWER OUTLOOK FOR PENNSYLVANIA 2013 2018 ELECTRIC POWER OUTLOOK FOR PENNSYLVANIA 2013 2018 August 2014 Published by: Pennsylvania Public Utility Commission P.O. Box 3265 Harrisburg, PA 17105-3265 www.puc.pa.gov Technical Utility Services Paul

More information

Instructions for use:

Instructions for use: TRANSMISSION MONTHLY PROJECT PROGRESS REPORT INSTRUCTIONS FOR COMPLETION TEMPLATE Instructions for use: PURPOSE OF FORM: The Transmission monthly Project Progress Report form is to be used by the Transmission

More information

Deliverability Testing

Deliverability Testing Deliverability Testing Henry Chao Vice President System & Resource Planning New York Independent System Operator New York State Reliability Council Executive Committee Meeting September 12, 2008 Definition

More information

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market CALIFORNIA ISO Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market Prepared by the Department of Market Analysis California Independent System Operator September 1999 Table of Contents Executive

More information

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE Ana Diez Castro & Rickard Ellström Ying Jiang Häfner Christer Liljegren Vattenfall Utveckling AB ABB Power Systems Gotlands Energiverk AB

More information

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Presented by: Marianne Mannschreck Date: Welcome A Look at the Net Energy Metering

More information

AGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233

AGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233 SA 2507 INTERSTATE POWER AND LIGHT COMPANY E&P AGREEMENT VERSION 1.0.0 EFFECTIVE 3/1/2013 AGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233 Agreement for Preliminary Engineering Design - MISO

More information

Energy Storage Market Overview MADRI 3/3/2015 John Fernandes Policy & Market Development Manager

Energy Storage Market Overview MADRI 3/3/2015 John Fernandes Policy & Market Development Manager Energy Storage Market Overview MADRI 3/3/2015 John Fernandes Policy & Market Development Manager Storage Technologies 2 Over 100 Energy Storage Technologies Background to the Market Flywheels Thermal ES

More information

Before the New Hampshire Public Utilities Commission DE 15-464. Public Service Company of New Hampshire d/b/a Eversource Energy. Motion to Intervene

Before the New Hampshire Public Utilities Commission DE 15-464. Public Service Company of New Hampshire d/b/a Eversource Energy. Motion to Intervene Before the New Hampshire Public Utilities Commission DE 15-464 Public Service Company of New Hampshire d/b/a Eversource Energy Petition for Approval of Lease Agreement between PSNH dba Eversource Energy

More information

2012 San Francisco Colloquium

2012 San Francisco Colloquium 2012 San Francisco Colloquium http : //www.cigre.org Advances in voltage source converter (VSC) technologies B4-6 500 kv VSC Transmission System for lines and cables B. JACOBSON, B. WESTMAN, M. P. BAHRMAN*

More information

TRANSMISSION GRID DEVELOPMENT & PORTFOLIO SERVICES December 22, 2014. Senior Vice President Trans Grid Development & Portfolio Services

TRANSMISSION GRID DEVELOPMENT & PORTFOLIO SERVICES December 22, 2014. Senior Vice President Trans Grid Development & Portfolio Services TRANSMISSION GRID DEVELOPMENT & PORTFOLIO SERVICES December 22, 2014 Senior Vice President Trans Grid Development & Portfolio Services The Senior Vice President Transmission Grid Development & Portfolio

More information

Preliminary Feasibility Assessment For. The Rio Tinto Alcan to BCH Transfer Limit of 460 MW. With 50% Series Compensation on Both KMO KIT lines

Preliminary Feasibility Assessment For. The Rio Tinto Alcan to BCH Transfer Limit of 460 MW. With 50% Series Compensation on Both KMO KIT lines Preliminary Feasibility Assessment For The Rio Tinto Alcan to BCH Transfer Limit of 460 MW With 50% Series Compensation on Both KMO KIT lines Report : ASP2010-T001 July 2010 Asset Strategy & Planning,

More information

ELECTRICITY SUPPLY CORPORATION OF MALAWI (ESCOM)

ELECTRICITY SUPPLY CORPORATION OF MALAWI (ESCOM) ELECTRICITY SUPPLY CORPORATION OF MALAWI (ESCOM) PRESENTATION EXECUTIVE EXCHANGE ON DEVELOPING AN ANCILLARY SERVICE MARKET FOR SAPP BACKGROUND INFORMATION Malawi-119 thousand square kilometers Malawi population-15

More information

Applicability and Eligibility

Applicability and Eligibility Application for Resource Adequacy Deliverability Status for a Distributed Generation Resource Interconnected or Seeking Interconnection to the Distribution Facilities of an Investor-Owned Utility Participating

More information

Ohio s Energy Efficiency Resource Standard: Impacts on the Ohio Wholesale Electricity Market and Benefits to the State

Ohio s Energy Efficiency Resource Standard: Impacts on the Ohio Wholesale Electricity Market and Benefits to the State Ohio s Energy Efficiency Resource Standard: Impacts on the Ohio Wholesale Electricity Market and Benefits to the State Max Neubauer, Ben Foster, R. Neal Elliott, David White, and Rick Hornby April 2013

More information

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES C. Schwaegerl*, M.H.J. Bollen, K. Karoui #, A. Yagmur + *Siemens AG, # Tractebel STRI AB

More information

Grid of the Future. Integration of Renewables Energy Storage Smart Grid. Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations

Grid of the Future. Integration of Renewables Energy Storage Smart Grid. Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations Grid of the Future Integration of Renewables Energy Storage Smart Grid Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations Grid of the Future Current Power System Gen. Trans. Dist.Cust.

More information

Transmission Function Employees Job Titles and Descriptions 18 C.F.R 358.7(f)(1)

Transmission Function Employees Job Titles and Descriptions 18 C.F.R 358.7(f)(1) Date of Last Change to the Provided Information August 27 th, 2015 Director, Transmission Operations The employee in this position is responsible for effectively managing the operation of FirstEnergy Utilities

More information

GPS Interfacing of Banediya Feeder (M.P) Using MI Power Software

GPS Interfacing of Banediya Feeder (M.P) Using MI Power Software GPS Interfacing of Banediya Feeder (M.P) Using MI Power Software Swati Paliwal 1, V.K Tayal 2, H.P Singh 3 Assistant professor, Department of Electrical & Electronics Engineering, Northern India Engineering

More information

2015 Project Schedule Milestone Update

2015 Project Schedule Milestone Update 2015 Schedule Milestone Update Robb Pike Director, & Product Management New York Independent System Operator Ryan Smith Senior Manager, Enterprise Product & Management New York Independent System Operator

More information

Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3

Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3 Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3 Basics of Power systems Network topology Transmission and Distribution Load and Resource Balance Economic Dispatch Steady State System

More information

Phase Attribute Identification using GPS Technology

Phase Attribute Identification using GPS Technology Phase Attribute Identification using GPS Technology Date 11 June 2009 John Sinclair Power Quality Manager Slide 1 Topics of Discussion Remote Phase Identification How it works Principals of operation Benefits

More information

SUBJECT: Marcy-South Series Compensation Project Capital Expenditure Authorization Request and Contract Award

SUBJECT: Marcy-South Series Compensation Project Capital Expenditure Authorization Request and Contract Award October 15, 2014 MEMORANDUM TO THE TRUSTEES FROM THE PRESIDENT and CHIEF EXECUTIVE OFFICER SUMMARY SUBJECT: Marcy-South Series Compensation Project Capital Expenditure Authorization Request and Contract

More information

COMMONWEALTH OF VIRGINIA LRK,'S UNCE AT RICHMOND, SEPTEMBER 7,2012 TRUL CE.. P 112 : 51 APPLICATION OF FINAL ORDER

COMMONWEALTH OF VIRGINIA LRK,'S UNCE AT RICHMOND, SEPTEMBER 7,2012 TRUL CE.. P 112 : 51 APPLICATION OF FINAL ORDER COMMONWEALTH OF VIRGINIA STATE CORPORATION COMMISSION LRK,'S UNCE AT RICHMOND, SEPTEMBER 7,2012 TRUL CE.. P 112 : 51 APPLICATION OF VIRGINIA ELECTRIC AND POWER COMPANY For approval and certification of

More information

Changes in FirstEnergy-Ohio Capacity Costs:

Changes in FirstEnergy-Ohio Capacity Costs: Changes in FirstEnergy-Ohio Capacity Costs: How Pricing, Contracting, and Consumption of Electricity Will Be Affected By Matt Brakey, President, Brakey Energy Now Updated with 2016/2017 Base Residual Auction

More information