Cowlin Construction Limited South West & Southern Division
|
|
- Dortha Lewis
- 7 years ago
- Views:
Transcription
1 Cowlin Construction Limited South West & Southern Division James Square Academic Building BREEAM /Status List January 2008 Up Date rev D Management Complete Cannot be Needed Maxfordham Response Notes from Meeting 31/01/2008 UPP Need to appoint DCL as per the BREEAM report stating the services for monitoring commissioning. MF note that appointment Duty to the Employer is required. Check of specialist certificates and random spot service check, on behalf of Man 1 Commissioning Responsibilities Employer, is acceptable. UOP will need to DCL/UPP acknowledge the service. Letter confirming this appointment was drafted in meeting SV to issue. Man 2 Commissioning Awaiting response from on DCL letter sent 6/12/2007 which confirmed there appointment to monitor commissioning. to provide evidence of procedures being passed on to all relevant trades/contractors on site. Copy of QA procedures for commissioning to be forwarded as some commissioning done in house. letter of appointment to each complex service specialist sub contractor will be acceptable. Needed Man 3 Man 4 Seasonal Commissioning Building Information/Users Guide to confirm if we can we get points from getting end user to arrange his staff to monitor adjust the control panel and record the changes. CCL have sent Contents page from O & M manuals to confirm points issued to 16/10/2007 via . Had response 21/12/2007 from Stating that this is not acceptable it needs to be by the commissioning specialist and designer. Details of O & M manuals contents issued but rejected needs to have end user guide noted in index and contents page issued. stated that this my only involve 2 or 3 visits and 5 as originally viewed by both DCL and the specialist contractor. DCL could review their fee proposal and could also provide costs for carrying out their element if required. UOP may wish to take this option for additional points. UOP CCL need to update the O & M contents page to show the location of were the user guide will go. UPP need to provide the contents page headings and the end document in line with the PCG and appendix 2 confirmed that if CCL update the contents page for the O & M this will meet the requirements. Confirmed that UOP need to provide the contents page headings and the end document in line with the PCG and appendix 2 CCL UPP Man 5 Man 6 Considerate Constructors Construction Site Impacts CCL have sent confirmation of score to of 32 points. Volumes of timber being rechecked to go with certification See appendix 4 for format of how details need to be provided. CCL are requested to check records of monitoring temporary power supply to site, can monthly records be identified? Completed CCL to produce documents as per the Residential Building may be possible to issue paperwork for both buildings to check and report back to CCL.. confirm this action will satisfy the BRE need CCL/ CCL Page 1 of 8
2 Needed Maxfordham Response Notes from Meeting 31/01/2008 CCL are requested to identify the site waste strategy, practice record and points of disposal. Can waste groups and disposal rate graphs be illustrated. CCL are to issue copy of the site Environmental Policy and to indicate measures adopted and emergency procedure. confirm this action will satisfy the BRE need. confirm this action will satisfy the BRE need. Needed CCL CCL Man 7 Man 8 Man 9 Health and Wellbeing Hea 1 Hea 2 Hea 3 Stakeholder Consultation UPP/Lovejoy & WI to provide evidence of consultation. Draft Details have been provided by WI as a start copy issued to T & T & in meeting further details are needed from DMA, UOP & UPP UOP/UPP /DMA Post Construction Testing - UPP to provide mach Acoustics appoint ment Testing in Lecture Theatre needs to be carried DMA/Mac Acoustics documents ref post construction testing. out as per report and then issued to BRE. Acoustics Commissioning of Fume Cupboards Avoidance of Legionella - Air Avoidance of Legionella - Water Systems Potential for Natural Ventilation UOP to confirm that there is a recycling fume cupboard with the spec details for to assess. DCL have confirmed Specifications comply with the various regulations as requested. Statement needed From that they are compliant with CIBSE TM13 or HSE ACOP L8 Area details need to be sent to by DMA to demonstrate that the open able area in the façade is at lease 5% on a room by room bases. Windows evenly distributed to avoid dead spaces, DMA to send specification and elevations to justify Calculations for any stack vent need to be demonstrated by a copy of which needs to be sent to CCL for their records Letter needed confirming that installation complies with Specification, needs to be on headed paper RB to action. Ltt Letter needed ddconfirming i that thtinstallation tllti complies with Specification, needs to be on headed paper RB to action. to review details sent as the Fume cupboards have been confirmed by UOP as elf contained with filters. stated that these may now be able to be removed from the report all together but will con firm. CCL to send the attachment again which could not open which came from UOP> confirmed that this would satisfy BRE requirements. confirmed that this would satisfy BRE requirements. to check details issued should be OK to confirm. to check details issued should be OK Mall to confirm. to check details issued should be OK to confirm /CCL DCL Hea 4 Internal Air Pollution Can not be achieved NO ACTION DCL have confirmed compliance for MV areas. accepted details from DCL on notes but Hea 5 Ventilation Rates Lecture theatre on CO2 - OK. confirmation of the rates need to be issued. DCL DMA need to confirm window vents are to part F of building regulations and forward spec and marked up Elevation drawings. to check details issued should be OK to confirm. DMA Hea 6 Hea 7 Day lighting View Out and DMA have shown that only the art rooms pass Dam to issue up to date GA floor plans to confirm room locations i.e. Technicians office new location Furniture layouts issued to on 28/01/2008. NO ACTION to check details issued should be OK to confirm. to check details issued should be OK to confirm. DMA Page 2 of 8
3 Hea 8 Hea 9 Hea 10 Hea 11 Daylight Glare Control High Frequency Lighting Electric Lighting Design Lighting Zones Needed Maxfordham Response Notes from Meeting 31/01/2008 DMA spec confirms that blinds are to be fitted to all internally occupied rooms provide specification and drawing to show to demonstrate that high frequency ballasts are fitted in all occupied areas which have fluorescent fittings. Letter sent to 11/12/2007 with detailed Luxlevelstobeconfirmedtoby by issuing drawings and lighting level calculations. Details issued to on 9/1/2008 awaiting acceptance by. DCL have issued specifications but drawing showing zoning arrangements for each area is needed. confirmed that if DMA issue schedule which shows where all the blinds are going in occupied area this should meet the requirements. have checked details issued but need the light fitting detail as it was missing from the pack sent once this has been received should be sufficient fro BRE.. to check details issued and confirm back. Needed DMA /DCL DCL/ Letter sent to 11/12/2007 with detailed Cannot be achieved due the sensors in classrooms no points NO ACTION Hea 12 Thermal Zoning are happy with the specification but need the drawings to show the locations of the NO ACTION COMPLETED DCL/ TRV valves and any zoning. Letter sent to 11/12/2007 with detailed NO ACTION COMPLETED Hea 13 Thermal Comfort Modelling have had all the details from DCL but need dto confirm that tthis meets the requirements t NO ACTION COMPLETED drawings calc,s etc Hea 14 Internal Noise Levels Mach acoustic report within the ER not confirmed that the wrong units of acceptable by the BRE are to give DMA/Mach measurement had been used calculations need guidance on what is required then this can be Acoustics to be redone giving the DBLA EQT units reviewed Mach Acoustic report confirms compliance with Hea 15 Reverberation Times BB93, which will mean that the points should NO ACTION COMPLETED Hea 16 Hea 17 Hea 18 Hea 19 Hea 20 Lighting Controls Laboratory Fume Cupboard Extract Rates Laboratory Fume Cupboard & Safety Cabinet Design Laboratory Filters Laboratory Ventilation be achieved. DCL are to issue a statement of control for the 2 different methods used giving the areas to which they apply. Letter sent to 11/12/2007 with detailed details for to assess. details for to assess. details for to assess. Requires a review by DCL on what we have and then confirm to for assessment once Hea 17 to 19 is cleared MA to send to to confirm the lighting controls use is inline with the seating configuration. to look at removing from report ref to to look at removing from report ref to to look at removing from report ref to DCL have issued calculations to Filters not applicable. DCL DCL 0 0 Page 3 of 8
4 Hea 21 Energy Ene 1 Laboratory Safety & Security Sub-Metering Needed Maxfordham Response Notes from Meeting 31/01/2008 Details confirmed to in letter from DCL/SWL 11/12/2008 Safety services isolation confirmation needed by issuing drawings, specification (equipment data sheets) of these details for both Gas and Electrical installation needs to be forwarded to for assessment Letter sent to 11/12/2007 with detailed Needed Completed Completed Sub metering is not included in the design so not achievable. NO ACTION Ene 2 Ene 3 Ene 4 Ene 5 Ene 6 Ene 7 Ene 8 Ene 9 U Values Air Permeability Internal Lighting Controls Services Control / BEMS Internal Luminaries External Luminaries Specification of Heating System's) Specification of Water Heating Plant Small chance that the monitoring on the BMS system may give enough information to qualify for these points are checking what information can be picked up off the BMS system which then be sent to for assessment DMA have sent elemental values without areas. They need to issue details of all the areas and values for each material for this to progress. This can only be assessed when the final air test is carried out which may be too late. DCL have issued specifications but drawing showing zoning arrangements for each area is needed ddand dis likdt linked to Hea 11 Letter sent to 11/12/2007 with detailed to issue BMS control schematic and control statement to to issue to the BRE for assessment. Letter sent to 11/12/2007 with detailed to issue details of all lights stating efficiency as we require 80% of fittings to achieve 65 lumniaire-lumins/watt. Letter sent to 11/12/2007 with detailed 80% of external and outbuilding Luminaries need to have an efficacy of 100 luminairelumens/watt or greater. Efficiencies and number of Luminaries needs to be provided by UOP as this is being designed by a third party Details need to be supplied to confirm the efficiency of the plant selected calculations may be required. Details of plant and drawing showing location are to be sent to for second review to see if any points are actually available DMA to issue Build calculations on windows and Render to. DMA 0 0 once above item received will carryout cal to confirm the 5% betterment on Building regulations. Air test due end April CCL will forward results CCL Completed DCL/ Completed DCL/ NO ACTION CANNOT BE ACHIEVED Awaiting confirmation of specification from UOP for this item to progress. UOP Boiler details issued again in meeting which stated where acceptable. SV needs to issue Guide A statement to MFFLP to complete this section. DCL/ NO ACTION CANNOT BE ACHIEVED /DCL 0 0 Page 4 of 8
5 Ene 10 Ene 11 Specification of Mechanical Ventilation Plant Specification of Cooling / Air Conditioning Plant Needed Maxfordham Response Notes from Meeting 31/01/2008 Letter sent to 11/12/2007 with detailed to review plant selection and send full details spec data sheets drawings and any calculations needed to to review to review plant selection and send full details spec data sheets drawings and any calculations needed to to review to check details issued and confirm back. to check details issued and confirm back after confirmation of the following points from DCL in the meeting. Needed DCL change of 1st floor lecture theatre to General teaching my effect points due to ventilation 2nd credit for ventilation may be 0 0 achievable as a result of above to confirm. Ene 12 Renewable / Low Carbon Energy Feasibility Study Not achievable within the contract Ene 13 UOP to look at shipper to see if any of the Use of Renewable / Low Carbon energy they generate is from a renewable source Energy Source as this may get part of the point NO ACTION CANNOT BE ACHIEVED UOP Ene 15 Energy Efficient Design of Fume to look at removing from report ref to 0 0 Cupboards details for to assess. Ene 16 Fume Cupboard Face Velocity to look at removing from report ref to 0 0 details for to assess. Transport Credits Tra 1 Staff Transport Calculator UOP to up date the travel plan and forward to have requested the 2003 version which to check details issued and confirm for assessment as the one issued does UOP is referred to in this report. back. not cover the James Square buildings As we have no showers with the building for the Tra 2 Cyclist Facilities amount of cycle racks required no credits achievable NO ACTION CANNOT BE ACHIEVED Provided Tra 5 Proximity and Provision of Public Details provided and cleared Transport Completed Provided Tra 6 Proximity to Key Amenities Details provided and cleared Completed Provided Tra 7 Proximity to Other Amenities Details provided and cleared Completed Provided Tra 8 Pedestrianised Routes Details of the external lighting which pick up the walk ways on the site boundary need to be provided or this score may be lost Further Clarification need from on this. Completed UOP Tra 11 Water Credits Watt 1 Travel Information Space Water Efficient Fittings A dedicated space for the provision of public transport information. This should be positioned where the public and members of staff can gain easy access and it should be easily identifiable within the building. Details of the above need to be provided by UOP to confirm the score Travel Plan issued to MFFLP awaiting response. Details of sanitary ware need to be resent to. Details of Ecoflo sensing and how it links to the PIR with explanation of operation needs to be sent to. Page 5 of 8 need copy of the sign that UOP will post in building to show provision of public transport information. RB to double check taps in Disabled toilets and confirm back to. Alternative to the above may be to have a flow restrictor fitted on supply to units, RB to see what is available and provide costs. As UOP may wish to take this option. UOP
6 Watt 2 Watt 3 Low Flush Toilets Sanitary Supply Shut Off Needed Maxfordham Response Notes from Meeting 31/01/2008 DMA to send Sanitary ware schedule and include flushing capacity for disabled WC to send confirmation that sanitary ware has been ordered as per the specification to and send the up to date data sheets for same. to send details of the solenoid isolation for the water supply for the toilet areas along with brief explanation of have it works. UOP may wish to take the above option to achieve points. RB to check if disabled toilets can be restricted to 5L size or dual flush 6/4 and confirm back to. Sensors have been added and isolation which will provide additional points to confirm. Needed UOP DMA Letter sent to 11/12/2007 with detailed Extract of BMS control to be provided by RB to demonstrate the operation of the above. Watt 4 Use of Grey water / Rainwater Not included within contract NO ACTION CANNOT BE ACHIEVED 0 0 Watt 5 Watt 6 Watt 7 Water Meter Major Leak Detection Irrigation Systems Materials & Waste Credits Confirmation needed from SWWA on the meter if it has the pulsed output capabilities. Drawing needed showing were isolation/meter are located ref to WATT 3 above. Letter sent to 11/12/2007 with detailed DCL letter 23/10/07 and love joys confirmation Completed Option on monitoring the meter output to be reviewed by UOP UOP may wish to look nat the option of adding additional detection through the BMS system. COMPLETED UOP UOP 0 0 DCL, provided M&W 1 Re-use of Façade Refurbish credit not available on this scheme NO ACTION CANNOT BE ACHIEVED M&W 2 Re-use of Structure Refurbish credit not available on this scheme NO ACTION CANNOT BE ACHIEVED M&W 3 M&W 4 M&W 5 Re-use of Aggregate Embodied Impact - Building Envelope Embodied Impact - Floor Finishes cowlins to investigate if the PFA used in the concrete will qualify for this credit DMA to submit details marked up drawings and specifications as substantiation, Info has been issued once DMA to reissue and copy PJA DMA to submit details marked up drawings and specifications and calculations as substantiation, Info has been issued once DMA to reissue and copy PJA to review the revised details which have been issued by DMA. Cowlins COMPLETED DMA M&W 6 Embodied Impact - Internal Walls Only 26.6% achieved not the 80% needed NO ACTION CANNOT BE ACHIEVED M&W 7 M&W 8 M&W 9 Embodied Impact - External Hard Surfaces & Fencing Asbestos Timber DMA to review details sent to as they state area is 72% A rated and we need 80%. Bond gravel is B rated although this being checked with BRE UPP to provide confirmation to Main Contract exclusion clause ref Asbestos Further details needed on volumes of timber and certificated sources needs to be 60% /75% by volume, including Sampson windows, Bridgeman doors etc DMA to double check the calculations as very close to requirements then resubmit to Copy of Prelims and schedule 7 issued to in meeting. to confirm points. CCL to produce documents as per the Residential Building may be possible to issue paperwork for both buildings to check and report back to CCL.. DMA & 0 0 UPP CCL/ 0 0 Page 6 of 8
7 Needed Maxfordham Response Notes from Meeting 31/01/2008 Needed CCL to confirm origins and provide certificates for timber. CCL 0 0 CCL to confirm origins and provide certificates also for skirting, architraves, doors, furnishings, etc. CCL 0 0 M&W 10 Durability / Impact Protection DMA to resubmit details and copy PJA sent to check details issued and confirm /9/06 and 24/11/06 back. M&W 11 Recyclable Storage DMA shows location - OK. UOP Size and labelling to be provided by UPP/UoP. DMA confirmed that G-09 is to be used and Reductions depend on UoP waste strategy and required area will be marked out on the floor classroom production. Waste strategy to be (10m2 Required) drawing to be issued to DMA presented to BRE. Does UoP know how much. waste is generated by academic buildings? M&W 13 LUE 1 Laboratory Furnishings & Fittings Land Use and Ecology Credits Re-use of Land DMA to resubmit details to and copy to PJA 75% of land has been previously built on or used for industrial purposes for 50 years UPP/UOP to formally confirm. COMPLETED DMA to provide overlay to show new and existing use and area covered by new building. DMA LUE 2 Use of Contaminated Land Not Contaminated NO ACTION CANNOT BE ACHIEVED Trees and hedges on site; not confirmed by Client to consider hiring Ecological consultant. LUE 3 Land of Low Ecological Value ecologist before removal; ecologist may be able to do something if details of these features can be supplied UOP 0 0 LUE 4 LUE 5 LUE 6 LUE 7 Pollution Credits Pol 1 Change in Ecological Value as a Result of Development Ecological Enhancement Advice Protection of Ecological Features Long Term Impact on Biodiversity Refrigerants With GWP of Less Than 5 Likely to be change neutral. Client to consider Likely to be change neutral. Client to consider hiring Ecological consultant. hiring Ecological consultant. UOP Likely to be change neutral. Client to consider Likely to be change neutral. Client to consider hiring Ecological consultant. hiring Ecological consultant. UOP Trees/hedges removed; cannot be achieved NO ACTION CANNOT BE ACHIEVED Site clearance has completed & BRE have confirmed that there is no way this credit cannot now be achieved Refrigerant type to be checked now equipment selection complete RB to forward details. NO ACTION CANNOT BE ACHIEVED Refrigerant type to be checked now equipment selection complete RB to forward details and depending on gas may be less than 5 which will give credit Pol 2 Refrigerant Leak Detection Not achievable within the contract NO ACTION CANNOT BE ACHIEVED 0 Pol 3 Refrigerant Recovery Systems Not achievable within the contract NO ACTION CANNOT BE ACHIEVED 0 Pol 4 Insolent ODP and GWP RB to give final confirmation on material Monitoring all insulations specified and used Up Date Needed from on were we are specification should be all ok, will have within building and services ongoing g with this. to confirm 0 0 DMA to issue schedule of all materials with specification to confirm to that they all pass along with backup sheets, as already DMA 0 0 issued. Pol 5 NOx Emissions of Heating Source's) Spec states model; letter states efficiency. to supply manufacturer spec confirming emissions and test condition. to check details issued and confirm back. Could be up to 4 points? Details sent on boiler 9/1/2008 awaiting acceptance from. Pol 6 Watercourse Pollution Not achievable within design NO ACTION CANNOT BE ACHIEVED Airey Coles Page 7 of 8
8 Pol 7 Pol 8 Surface Water Run Off Attenuation Reduction of Light Pollution Needed Maxfordham Response Notes from Meeting 31/01/2008 Needed Not in currant scheme NO ACTION CANNOT BE ACHIEVED 0 Detailed design needed to send to BRE through UPP/UOP need to confirm the lighting design for the external works will meet the criteria set out on page 78 of the BREEAM report in all respects High risk. UOP Pol 9 Zero Emission Energy Source Not achievable within design NO ACTION CANNOT BE ACHIEVED An environmental noise assessment demonstrates that the rating level of the new RB needs to send plant details through DMA to allow calculations to be actioned and then Pol 10 Noise Assessment plant, associated with the new building works, issued to for approval. Mach/MFLL does not exceed the background noise level (as P defined in BS 4142:1997) by more than 5dB Mach Acoustic to provide report and calculations Page 8 of 8
HHHHH Outstanding 85%
Provinciehuis_Assessment_2040204_74,32%Final Score and Rating BREEAM Scheme: Europe 2009: Offices H Pass 30% Building Name: Provinciehuis Antwerpen HH Good 45% BREEAM Registration No.: BREEAM-0048-4626
More informationBREEAM Europe. This presentation aims to give the reader a general overview of the operational and technical aspects of BREEAM Europe.
BREEAM Europe BREEAM Europe This presentation aims to give the reader a general overview of the operational and technical aspects of BREEAM Europe. Key objectives Provide consistency and comparability
More informationBAM CONSTRUCT. Dunsbury Hill Farm. BREEAM Pre-assessment Summary. BAM Sustainability department 2015
BAM CONSTRUCT Dunsbury Hill Farm BREEAM Pre-assessment Summary BAM Sustainability department 2015 1.0 Introduction This report is intended as a summary of the pre-assessment for the following BREEAM assessment:
More informationSUSTAINABLE BUILDINGS
SUSTAINABLE BUILDINGS ACHIEVING A BREEAM EXCELLENT RATING GUIDANCE NOTE FOR BREEAM 2008 ASSESSMENTS Document Issued January 2009 CURRENT REQUIREMENTS: The Welsh Assembly Government has a duty to have a
More informationElaine Harvie & Jeremy Cruickshank Jan 10
Elaine Harvie & Jeremy Cruickshank Jan 10 3 Assembly Square, Cardiff - EXCELLENT BREEAM International Introduction Elaine Harvie Mechanical Engineer BREEAM Assessor Offices School/Education Industrial
More informationBREEAM Refurbishment and Fit-out 2014 Briefings. Part of the BRE Trust
BREEAM Refurbishment and Fit-out 2014 Briefings Part of the BRE Trust BREEAM for Refurbishment and Fit-out Follows 2 years of development Draft scheme published and consultation from 19 th July 2014 Launched
More informationCode for Sustainable Homes Guidelines
Canoldir Penrhos Anglesey LL65 2TS Phone: 01407 860666 Email: saps@easonline.co.uk www.easonline.co.uk Code for Sustainable Homes Guidelines A CSH rating is the responsibility of the Developer/ Architect
More informationProposal to achieve Code for Sustainable Homes Level 3 for a development of 7 detached dwellings
Duchy Homes Site: Cantley Lane Doncaster Proposal to achieve Code for Sustainable Homes Level 3 for a development of 7 detached dwellings 22 nd February 2013 Leanne Brooksbank Accredited Energy & Code
More informationRed Managed Services BREEAM Pre-Assessment. Lidl Head Office. Client. Lidl UK GmbH 19 Worple Road Wimbledon London SW19 4JS
Red Managed Services BREEAM Pre-Assessment Lidl Head Office Client Lidl UK GmbH 19 Worple Road Wimbledon London SW19 4JS Date 10 November 2015 Red Managed Services REVISION Issued for Document prepared
More informationLead architect: Ron Arad Architects - Executive architect: Jaspers & Eyers
SOLUTIONS FOR SUSTAINABLE BUILDINGS THE GUIDE TO BREEAM Lead architect: Ron Arad Architects - Executive architect: Jaspers & Eyers Reynaers develops innovative and sustainable aluminium solutions, for
More informationAPPENDIX 2: BREEAM ASSESSMENT
APPENDIX 2: ASSESSMENT CONTENTS Introduction... 1 Pre-assessment Estimate Results... 3 Management... 3 Health and Wellbeing... 7 Energy... 13 Transport... 18 Water... 22 Materials... 24 Waste... 29 Land-use
More informationEFA PSBP. Natural Ventilation Strategy. Introduction. 1.1 Relevant legislation. 1.1.1 The Building Regulations 2010
EFA PSBP Natural Ventilation Strategy Introduction The Baseline Designs Project will provide scheme design details for a number of Primary and Secondary School Exemplars. For the purposes of setting a
More informationRULES FOR THE SETTING UP OF SUSTAINABLE BRANCHES Summary
RULES FOR THE SETTING UP OF SUSTAINABLE BRANCHES Summary January 2013 TABLE OF CONTENTS INTRODUCTION... 3 GENERAL RECOMMENDATIONS... 3 Communication with customers in the field of environmental sustainability...
More informationBREEAM versus LEED. White Paper first published February 2010. BREEAM versus LEED Page 1
BREEAM versus LEED White Paper first published February 2010 BREEAM versus LEED Page 1 About this White Paper Inbuilt leads the way in technical and consulting excellence for the design, delivery and development
More informationArchant London Environmental Awards
Archant London Environmental Awards Environmental Business of the Year Big Yellow Self Storage PLC Barking Central, Hertford Road, Barking, IG11 8BL Introduction Big Yellow is a local business that has
More informationBREEAM In-Use International
www.breeam.com BREEAM In-Use International Technical Manual SD221 2.0:2015 February 2016 83561 BRE Global Ltd 2016 Terms and conditions Disclaimer This Scheme Document is the property of BRE Global Limited
More informationIALN11006400 /05 01 19.06.13. FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF
IALN11006400 /05 01 19.06.13 FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF Dear Sir / Madam Re: 12/02994 BCA Sports Hall Condition
More informationBRE, BRE Global, BREEAM, Smartwaste and the Green Guide are all trademarks owned by either BRE or BRE Global Limited and
blank page Terms & conditions Terms and conditions Disclaimer This scheme document is the property of BRE Global Limited and is made publicly available for information purposes only. Any testing, assessment,
More informationSD 5066A: ISSUE 1.1 BREEAM
SD 5066A: ISSUE 1.1 BREEAM Europe Commercial 2009 Assessor Manual The BREEAM Assessor Manuals are technical guidance documents which have been created to aid licensed BREEAM Assessors in carrying out BREEAM
More informationGreen House, Hungary
Further information Skanska AB www.skanska.com Contact Noel Morrin, SVP Sustainability & Green Support noel.morrin@skanska.se Green House, Hungary Case Study 109 Aspects of Sustainability This project
More informationB-1 Buildings & Service Maintenance
B-1 Buildings & Service Maintenance B-1 Buildings & Service Maintenance SAFETY, HEALTH AND ENVIRONMENTAL POLICY: B-1 DATE OF ISSUE: AUGUST 1994. BUILDINGS AND SERVICES MAINTENANCE 1. Introduction It is
More informationMillennium Hall, Philadelphia, Pennsylvania is a Residence Hall/Dormitory building of approximately 102,680 ft². The client is Drexel University.
Page 1 of 6 INTRODUCTION Millennium Hall, Philadelphia, Pennsylvania is a Residence Hall/Dormitory building of approximately 102,680 ft². The client is Drexel University. Millennium Hall is described as
More informationhttp://www.bca.gov.sg/greenmark/others/gm_nreb_v2.1.pdf
Green Mark Criteria for Non-residential Existing Building (Version 2.1) GM for Non-residential Existing Buildings Criteria (Ver. 2.1) can be downloaded from : http://www.bca.gov.sg/greenmark/others/gm_nreb_v2.1.pdf
More informationIMPERIAL COLLEGE LONDON SUPPORT SERVICES BUILDING PROJECTS DIVISION
IMPERIAL COLLEGE LONDON SUPPORT SERVICES BUILDING PROJECTS DIVISION SUSTAINIBILITY SPECIFICATION JULY 2009 SS.01 Sustainability Specification Revision 1.01 Issue Date Comments 1 July 2009 General Issue
More informationHOUSING STANDARDS POLICY TRANSITION STATEMENT IMPLEMENTATION: OCTOBER 2015. May 2015
HOUSING STANDARDS POLICY TRANSITION STATEMENT IMPLEMENTATION: OCTOBER 2015 May 2015 MAYOR OF LONDON Housing Standards: Transition Policy Statement. On 25 March 2015 through a written ministerial statement,
More informationBCA-IDA Green Mark for Existing Data Centres Version EDC/1.0
BCA-IDA Green Mark for Existing Data Centres Version EDC/1.0 To achieve GREEN MARK Award Pre-requisite Requirement All relevant pre-requisite requirements for the specific Green Mark Rating are to be complied
More informationRESPONSIBILITY FOR REPAIRS AND MAINTENANCE FAIR FUNDING: April 2002
RESPONSIBILITY FOR REPAIRS AND MAINTENANCE FAIR FUNDING: April 2002 INDEX New Build Flat and Pitched Roofs Rainwater Goods Porches to Existing Buildings / Covered Links etc, Between Buildings Floors /
More informationHolistic Approach in Delivering Government Buildings The Low Carbon Concept
International Conference on Planning for Low Carbon Cities 22 May 2009 Holistic Approach in Delivering Government Buildings The Low Carbon Concept Ir. HO Sai-king, Assistant Director (Building Services),
More informationBREEAM UK New Construction 2014 Assessment Report
BREEAM UK New Construction 2014 Assessment Report General information BRE Assessment reference no. Client name Building end user/occupier Assessor name Assessors role Assessor organisation TBC (rev0.0
More informationENERGY MANAGEMENT SERVICE LEVEL AGREEMENT. 1.2 The Governing Body of School: the School. Main contact:, Headteacher
1234567 ENERGY MANAGEMENT SERVICE LEVEL AGREEMENT 1. PARTIES TO THIS AGREEMENT 1.1 The Energy Management Team: the Service Provider. Main contacts: Kevin Palmer, Energy Manager 024 7683 2713. Tanjee Virdi,
More informationQuantifying the energy and carbon effects of water saving summary report
Quantifying the energy and carbon effects of water saving summary report Domestic water use in the UK is around 150 litres per person per day. Taking water from the environment, treating it, distributing
More informationPassive & Active Design
Passive & Active Design CIBSE Building Simulations Group Peter A. Brown CEng, MBA October 2010 Introduction Passive & Active Design Introduction What are the interactions between passive and active design?
More informationDisclaimer. Copyright. Trade Marks
blank page Disclaimer This Scheme Document is the property of BRE Global Ltd and is made publicly available for information purposes only. Its use for testing, assessment, certification or approval must
More informationManagement of Asbestos. Darren Arkins Senior Inspector Occupational Hygiene Unit Chemical Business Services Division
Management of Asbestos Darren Arkins Senior Inspector Occupational Hygiene Unit Chemical Business Services Division Getting it Wrong! Asbestos What is it? With the Naked Eye! Naturally occurring silicates
More informationCode for Sustainable Homes. A step-change in sustainable home building practice
A step-change in sustainable home building practice www.communities.gov.uk community, opportunity, prosperity December 2006 On 5th May 2006 the responsibilities of the Office of the Deputy Prime Minister
More informationMechanical and Natural Ventilation
BBSE3006: Air Conditioning and Refrigeration II http://www.hku.hk/bse/bbse3006/ Mechanical and Natural Ventilation Dr. Sam C. M. Hui Department of Mechanical Engineering The University of Hong Kong E-mail:
More informationSIP (STRUCTURAL INSULATED PANEL)
SIP (STRUCTURAL INSULATED PANEL) KINGSPAN TEK ACORN SIP ABSTRACT BUILDING SERVICES Ltd Kingspan TEK is the manufacturer and supplier of the panels and components. Acorn SIP are the Architects who individually
More informationCONDUIT MAYFAIR READY FOR OCCUPATION SPRING 2014 GLINSMANWELLER.CO.UK A DEVELOPMENT BY LONDON PROPERTY PARTNERSHIP LTD
12 CONDUIT S T R E E T MAYFAIR READY FOR OCCUPATION SPRING 2014 020 7495 2728 GLINSMANWELLER.CO.UK A DEVELOPMENT BY LONDON PROPERTY PARTNERSHIP LTD 12 CONDUIT STREET The entire building is undergoing a
More informationBOMA BESt Assessment Overview
BOMA BESt Assessment Overview BOMA Building Environmental Standards OFFICE Module August 2013 The Voice of the Commercial Real Estate Industry in Canada The Building Owners and Managers Association of
More informationThe Integrated Design Process
The Integrated Design Process The Integrated Design Process (IDP) has been developed on the basis of experience gained from a small Canadian demonstration program for high-performance buildings, the C2000
More informationCode for Sustainable Homes
Code for Sustainable Homes Technical Guide November 2010 www.communities.gov.uk Code for Sustainable Homes Technical Guide November 2010 November 2010 Department for Communities and Local Government Copyright
More informationModular Accommodation Solutions. Flexibility, efficiency and quality in one complete package
Modular Accommodation Solutions Flexibility, efficiency and quality in one complete package Welcome Our Services Providing Your Solutions The clients who work with SEDAC Accommodation Solutions are extremely
More informationRestaurant & café guide
'Helping our customers stay in business by reducing risk' NZI Risk Solutions TM About NZI Risk Solutions NZI has extensive experience in providing expert risk management advice to help our commercial customers
More informationBloomsbury Colleges Environmental Policy Statement
15 December 2011 P a g e 1 Bloomsbury Colleges Environmental Policy Statement The Bloomsbury Colleges are committed to the responsible use of energy, water and other resources with the aim of minimising
More informationENGLISH MANUAL FOR NEW CONSTRUCTION AND REFURBISHMENT VERSION 1.0 EDITION 130501
ENGLISH MANUAL FOR NEW CONSTRUCTION AND REFURBISHMENT VERSION 1.0 EDITION 130501 BES 5066: ISSUE 1.1 BREEAM-SE ver. 1.0 The BREEAM Assessor Manuals are technical guidance documents which have been created
More informationLONDON BOROUGH OF HACKNEY BUILDING SERVICES ENGINEER REPORT GAS HOUSE, SPRINGFIELD PARK, HACKNEY
LONDON BOROUGH OF HACKNEY BUILDING SERVICES ENGINEER REPORT GAS HOUSE, SPRINGFIELD PARK, HACKNEY 10 TH JUNE 2011 London Borough of Hackney Page 1 of 6 Brief Description of the Proposed Works The existing
More informationSAM HOUSTON STATE UNIVERSITY
PART 1: GENERAL 1.01 General Requirements A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the
More informationFEDERAL LEADERSHIP IN HIGH PERFORMANCE and SUSTAINABLE BUILDINGS MEMORANDUM OF UNDERSTANDING
FEDERAL LEADERSHIP IN HIGH PERFORMANCE and SUSTAINABLE BUILDINGS MEMORANDUM OF UNDERSTANDING PURPOSE: With this Memorandum of Understanding (MOU), signatory agencies commit to federal leadership in the
More informationSchool in Schwanenstadt, Austria
School in Schwanenstadt, Austria 1. INTRODUCTION PROJECT SUMMARY - building period 1960s - numerous expansions SPECIAL FEATURES - Renovation to meet Passive House Standard - decentralized ventilation system
More informationHigh Performance School Buildings Resource and Strategy Guide
High Performance School Buildings Resource and Strategy Guide Published by: Sustainable Buildings Industry Council With support from: California Energy Commission National Concrete Masonry Association
More informationDesign Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+)
Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+) 1. In addition to the information scheduled below, the pre-tender designer is responsible for: (i)
More informationResidential Property Climate Bonds
Residential Property Climate Bonds Certification methodology Low Carbon Buildings Technical Working Group ABSTRACT This paper sets out guidance by the Low Carbon Buildings Technical Working Group on the
More informationMTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS
Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT
More informationPRE-LEASE SURVEY OF THE ENGINEERING SERVICES. XXXX London
PRE-LEASE SURVEY OF THE ENGINEERING SERVICES AT London Client: Clients Representative: For the Attention of: Telephone N o Site Address: London Report prepared by: Contact Name: FHP Engineering Services
More informationASTACEA4 Inspect complex/central air conditioning systems
Overview This Unit covers the competences required to inspect complex/central air conditioning systems as defined by the CIBSE TM 44 Figure 1.1: Summary of system types and their component parts. The air
More informationSustainable Real Estate Investments Policy
Sustainable Real Estate Investments Policy Usage statement This communication is intended for Global investments High Yield professionals Bond Fund 101 and should not be relied on by anyone else. Standard
More informationSystems Selection Enclosure Systems Material Selection Assessment and Mitigation
Return to Curriculum Home CES Home Find an AIA/CES Registered Course Self Report a Learning Activity MATERIALS AND METHODS To develop professionally in Practice with a focus on sustainable design, you
More informationCIBSE Guide M: Maintenance engineering and management Statutory compliance legislation and guidance
CIBSE Guide M: Maintenance engineering and management compliance legislation and guidance Types of System/Plant Action required Frequency by Type of Fire and Smoke Fire extinguishers Discharge (not CO
More informationOEGNB - Open Source Building Assessment
OEGNB - Open Source Building Assessment Mag. Dr. Susanne Geissler SB13 26th September 2013 Graz ÖGNB sustainable building assessment/quality label The ÖGNB quality label is based on the TQB assessment
More informationRochdale Building Control Guide. Approved Document F Means of ventilation
Rochdale Building Control Guide Approved Document F Means of ventilation Coming into effect 1 st October 2010 As we build homes that are more airtight it is increasingly becoming important to ensure that
More informationBCA Green Mark for Existing Non-Residential Buildings Version 3.0
BCA Green Mark for Existing Non-Residential Buildings Version 3.0 Framework BCA Green Mark for Existing Non-Residential Buildings (version 3.0) To achieve Green Mark Award Pre-requisite Requirement All
More informationPolicy for the Management of Asbestos in Buildings
in Buildings Health and Safety Services 1 A1. Introduction If asbestos fibres enter the lungs they can cause cancer or incurable disease. Consequently the University is committed to ensure that all reasonably
More informationBCA-IDA Green Mark for New Data Centres Version NDC/1.0
BCA-IDA Green Mark for New Data Centres Version NDC/1.0 To achieve GREEN MARK Award Pre-requisite Requirement All relevant pre-requisite requirements for the specific Green Mark Rating are to be complied
More informationDraft UCL Heating, Cooling and Ventilation Policy
Draft UCL Heating, Cooling and Ventilation Policy Page 1 of 7 UCL Estates UCL Heating, Cooling & UCL Heating, Cooling and Document Owner UCL Estates Leadership Team is the Owner of this document. Distribution
More informationPROBIS SUPPORTING PUBLIC PROCUREMENT OF BUILDING INNOVATIVE SOLUTIONS
PROBIS SUPPORTING PUBLIC PROCUREMENT OF BUILDING INNOVATIVE SOLUTIONS Regione Lombardia ALER Bergamo Lecco Sondrio Treviglio via Dei Mulini n. 10/20 via Filzi n. 11/13 Prospectus Template provided by TEH-Ambrosetti.
More informationABERDEEN CITY COUNCIL. Communities, Housing and Infrastructure
ABERDEEN CITY COUNCIL COMMITTEE Communities, Housing and Infrastructure DATE 20 th January 2016 DIRECTOR TITLE OF REPORT REPORT NUMBER CHECKLIST COMPLETED Pete Leonard Buildings Performance Policy CHI/15/256
More informationOur Triple Bottom Line...
Our Triple Bottom Line... A Better Approach We embrace what we consider to be our responsibility as developers to balance profits with environmental and social dividends. We believe that our long-term
More informationGreen and Sustainable Buildings
Green and Sustainable Buildings Design Criteria and Application in Hong Kong Green building is the practice of increasing the efficiency with which buildings use resources energy, water and materials.
More informationPlanning Guidance for Food and Drink Establishments
Planning Guidance for Food and Drink Establishments ENVIRONMENT DIRECTORATE, CIVIC CENTRE, 44 YORK STREET, TWICKENHAM TW1 3BZ Planning Guidance for Food and Drink Establishments Introduction This guidance
More informationSchool Performance Specifications. SPACES Engineering Technical Meeting 22 September 2015
School Performance Specifications SPACES Engineering Technical Meeting 22 September 2015 EFA Facilities Output Specification: Introduced in 2013 to promote: well-integrated and simple buildings that benefit
More informationGreen Warehouses & Distribution Centers
Green Warehouses & Distribution Centers From Theory To Practice Serkan Emin LEED AP, CEM Emre ILICALI LEED AP, BREEAM Assessor Our Services Green Buildings - LEED Certification Management - BREEAM Certification
More informationNorwegian Tax Authority - Oslo Norway
1. INTRODUCTION Norwegian Tax Authority - Oslo Norway PROJECT SUMMARY Year of construction - 1980 No previous energy renovations SPECIAL FEATURES Main topics in the renovation are: High insulated pre fabricated
More informationSika Sarnafil World Class Roofing and Waterproofing
The following is a brief summary of the Leadership in Energy and Environmental Design program (LEED, Version 3) and the sections Sika Sarnafil s roofing systems can help contribute to obtaining LEED points.
More informationDISTRIBUTED GENERATION AND ENERGY EFFICIENCY FOR ACHIEVING ENERGY SELF-SUSTAINING INDUSTRIAL AREAS
DISTRIBUTED GENERATION AND ENERGY EFFICIENCY FOR ACHIEVING ENERGY SELF-SUSTAINING INDUSTRIAL AREAS Ing. Maria-Anna Segreto LAERTE Laboratory - 1 EUROPEAN DIRECTIVE 2010/31/UE It 's well known that higher
More informationDevelopment proposals will require to demonstrate, according to scale, type and location, that they:-
Appendix 2 : Relevant Development Plan Policies Angus Local Plan Review 2009 Policy S1 : Development Boundaries (a) Within development boundaries proposals for new development on sites not allocated on
More informationBOMA BESt AND LEED EBOM COMPARISON
BOMA BESt AND LEED EBOM COMPARISON INTERNATIONAL FACILITY MANAGEMENT ASSOCIATION James Furlong, CET, LEED AP - Senior Associate, Stantec Consulting Ltd. BOMA BESt BOMA - Building Owners and Managers Association
More information34% 81% 84% 19% GOLD PROJECT HIGHLIGHTS. LEED Facts. Stubbs Laboratory
HARVARD UNIVERSITY FACULTY OF ARTS AND SCIENCES LEED-CI V3.0 STUBBS LABORATORY GORDON MCKAY LABS BUILDING Gordon McKay Building, 9 Oxford Street, Cambridge, MA 02138 GOLD The Stubbs Laboratory is a 2,035
More informationENERGY STATEMENT for a proposed new residential care home at Great North Road, Doncaster, South Yorkshire, DN6 7EJ
ENERGY STATEMENT for a proposed new residential care home at Great North Road, Doncaster, South Yorkshire, DN6 7EJ Ref. No: 12/02870/FULM Contents 1. General... 2 2. Planning Condition... 2 3. Development...
More informationWORKSHOP: The roles of wood in green building and green building effects on the forest sector of in the UNECE region.
WORKSHOP: The roles of wood in green building and green building effects on the forest sector of in the UNECE region. Are ENGO s ready to promote the use of wood as the preferred building material? Alison
More informationOFFICES PROVIDING TEMPORARY, SEMI-PERMANENT AND PERMANENT OFFICE SOLUTIONS ELLIOTT, AN ESSENTIAL WORLDWIDE PLAYER TEMPORARY ACCOMMODATION
ELLIOTT, PROVIDING TEMPORARY, SEMI-PERMANENT AND PERMANENT OFFICE SOLUTIONS OFFICES TEMPORARY ACCOMMODATION OPEN PLAN OFFICES SEMI-PERMANENT BUILDINGS PERMANENT STRUCTURES PORTABLE BUILDINGS WORLD LEADER
More informationEnergy Efficiency HOSPITALITY. www.energia.ie
Energy Efficiency HOSPITALITY www.energia.ie Your chance to reduce your business energy usage by as much as 20%! 20% is a significant figure and reducing your energy bill by this amount could make a real
More informationScheme Document SD 5068
Scheme Document SD 5068 BREEAM Data Centres 2010 Uncontrolled copy if printed. Valid on day of printing only. SD 5068 Issue 1.0 25/05/2010 Page 1 of 325 BRE Global Limited (part of the BRE Group) is an
More informationGreen Buildings Guidelines for Harvard
Green Buildings Guidelines for Harvard Presentation to the Administrative Deans. October 26th 2007 Leith Sharp, Director, Harvard Green Campus Initiative What is a Green Building? Average Savings of Green
More informationStrategic approach to the selection and procurement of construction materials and products
www.breeam.com Briefing Paper Strategic approach to the selection and procurement of construction materials and products Alan Yates 02 The selection and procurement of construction materials makes a major
More informationService Level Agreement (SLA)
Hertford College, Oxford Service Level Agreement (SLA) For Maintenance, Risk Management, and Domestic Accommodation Services At Hertford College, its residential annexes and non- residential properties
More informationFire Safety Risk Assessment
1 Sources of ignition The main sources of ignition in Cass building are: PAF arrange for the fixed electrical installation to be tested in accordance with the British Standards. Test certificates are kept
More informationRepairs and looking after your home
A guide to Repairs and looking after your home Contents Page No. Introduction 1 Information for tenants 2 Information for homeowners 3-4 Information for onsite NHS workers 5 Information for students 5
More informationSistema de Etiquetagem Energética de Produtos (SEEP) Energy Labeling System for Products
Sistema de Etiquetagem Energética de Produtos (SEEP) Energy Labeling System for Products 10 reasons for an energy labeling system (1/2) The buildings sector is responsible for a considerable share of final
More informationSustainable Features. High-performance HVAC. High-performance Envelope Green Roof Day-Lighting Bicycle Infrastructure
Sustainable Features High-performance HVAC High-performance Envelope Green Roof Day-Lighting Bicycle Infrastructure Sustainable Landscaping Recycled and Regional Materials Storm-water Management District
More informationSustainability Fit Out Guide Retail and Leisure
Sustainability Fit Out Guide Retail and Leisure 1 Introduction This guide provides advice to occupiers who are carrying out fit-out works and is aligned to The Crown Estate s relevant sustainability principles
More informationCase Studies of Successful Code for Sustainable Homes Projects
Case Studies of Successful Code for Sustainable Homes Projects Sustainable Homes publish the Sustainable Homes Index For Tomorrow (SHIFT) and are a leading trainers of Code for Sustainable Homes assessors.
More informationEnergy Conservation Audits for Six Performing Arts Facilities A Toronto s Green Theatres Project
Energy Conservation Audits for Six Performing Arts Facilities A Toronto s Green Theatres Project Anthony Marshall, P.Eng., CEM January 2012 For Creative Trust for Arts & Culture Table of Contents Introduction
More informationNo. Name of Legislation Applicable Issues and Requirements Demonstration of Compliance 1. Health and Safety at Work Act 1974
The Police Treatment Centres Health and Safety Legal Compliance Register No. Name of Legislation Applicable Issues and Requirements Demonstration of Compliance 1. Health and Safety at Work Act 1974 2.
More informationAcoustic design of schools: performance standards. From 2003 to 2014: a brief guide to the changes in BB 93. by Jack Harvie-Clark, 9th January 2015
Acoustic design of schools: performance standards From 2003 to 2014: a brief guide to the changes in BB 93. by Jack Harvie-Clark, 9th January 2015 This document should be read in conjunction with the new
More informationCity Council Report for Information
City Council Report for Information Report to: Subject: Report of: Neighbourhood Scrutiny Committee Sustainable Development Assistant Chief Executive (Regeneration) Summary This report outlines measures
More informationSustainability: Green hotels
Sustainability: Green hotels 10 October 2013 How green is your hotel? Azita Dezfouli and Adam Mactavish of Sweett Group look at the practical steps for reducing the environmental impact of hotels during
More informationOnly two floors remaining
Only two floors remaining 2,697-20,615 sq ft St Peter s Square www.stpetersstockport.com Stockport town centre s first grade A, BREEAM Excellent office building. TO LET Stockport 51,402 sq ft Full grade
More informationDIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION
More informationControl of legionella bacteria in water systems
Control of legionella bacteria in water systems Audit checklists This is a free-to-download, web-friendly version of Control of legionella bacteria in water systems: Audit checklists (published 2003).
More information6 Schedule quarterly communications to keep employees involved in environmental improvements. WASTE REDUCTION REQUIRED MEASURES
GREEN BUSINESS CERTIFICATION (GBC) Business Name: Business Address: Plano, TX ZIP: Commercial Recycling 4200 W. Plano Parkway Plano, TX 75093 972-769-4393 OFFICE/RETAIL CHECKLIST General Education Waste