R101 Supplemental Review

Size: px
Start display at page:

Download "R101 Supplemental Review"

Transcription

1 R101 Supplemental Review For Midcontinent Independent System Operator Performed by: Dylan Stupca October 3, 2016

2 Table of Contents 1. Executive Summary Introduction Model Development Supplemental Review and Results Attachment X Minimum Load Screening Attachment X Minimum Load Screening Results Attachment X Voltage and Power Quality Screen Attachment X Voltage and Power Quality Screen Results Attachment X Safety and Reliability Screen Attachment X Safety and Reliability Screen Results Conclusion Appendix A System Voltage Tables Transient Voltage Tables Appendix B MISO Tariff Excerpts in Section of Attachment X List of Tables and Figures Figure 2-1: R101 Requested Interconnection Point and Local Area... 4 Table 3-1: R101 Supplemental Review Models... 5 Figure 4-1: Plummer 41.6 kv Circuit Breaker 435 Loading (MW)... 5 Table 4-2: Worst Contingencies and Switching Operations... 6 Table 4-3: Voltage Violations... 7 Table 4-4: Transient Voltage Violations... 8 Table 4-5: Reverse Flow Issues R101 Supplemental Review Page 2

3 1. Executive Summary Otter Tail has been requested to perform a Supplemental Review for the R101 interconnection request in accordance with Section of Attachment X to the MISO tariff - Generator Interconnection Procedures. The R101 project is comprised of small scale wind and solar generation with a total aggregated output of 4.6 MW that is in the MISO interconnection queue requesting interconnection to Otter Tail s 41.6 kv system southeast of Otter Tail s Red Lake Falls 41.6 kv substation in northwest Minnesota. Consistent with the MISO tariff, this Supplemental Review consists of analyzing this interconnection request by using three screening parameters (1) Minimum Loading Screen, (2) Voltage and Power Quality Screen, and (3) Safety and Reliability Screen. Through the course of performing this Supplemental Review, Otter Tail has determined: R101 failed the Minimum Loading Screen because the aggregated output of the Generating Facility is not less than 100% of the minimum load on the 41.6 kv circuit identified for the R101 interconnection. R101 passes two of the three requirements in the Voltage and Power Quality Screen identified in Attachment X. o Otter Tail was not able to perform an analysis verifying that harmonic levels with the R101 interconnection met IEEE Standard 519 limits. Otter Tail reserves the right to have this analysis performed in the future as part of the Voltage and Power Quality screen if the interconnection customer (R101) moves forward. R101 failed the Safety and Reliability Screen due to reverse power flow issues introduced at three adjacent 115/41.6 kv substations in the local area with the addition of R101. o R101 could pass this screening parameter if the reverse power flow issues are addressed at adjacent 115/41.6 kv substations so that Otter Tail equipment is not in jeopardy of being harmed with the addition of R101. R101 will need to verify that requirements included in sections and of the MISO tariff are met with the equipment being installed as part of this project. o Section : Otter Tail will require the interconnection customer to verify that the R101 project incorporates a time delay function to prevent reconnection of the generator to the system until system voltage and frequency are within normal limits for prescribed time. o Section : Otter Tail will require the interconnection customer to verify that the R101 project will employ equipment or systems certified by a recognized standards organization to address technical issues such as, but not limited to, islanding, reverse power flow, or voltage quality. Overall, R101 fails the Supplemental Review due to the Minimum Load Screen and the other screening parameters in the Safety and Reliability Screen. Otter Tail will need to review and approve voltage set points and transformer tap settings to ensure that the addition of the R101 project does not lead to reliability concerns on the transmission system. R101 Supplemental Review Page 3

4 2. Introduction Otter Tail has performed a Supplemental Review in accordance with Section of Attachment X to the MISO tariff Generator Interconnection Procedures. R101 is a 4.6 MW project comprised of small scale wind and solar generation requesting interconnection to Otter Tail s 41.6 kv system southeast of Otter Tail s Red Lake Falls 41.6 kv substation in northwest Minnesota. The figure below shows the location of the requested generator interconnection project, R101. [INFORMATION REDACTED] Figure 2-1: R101 Requested Interconnection Point and Local Area 3. Model Development A set of models were developed to assist in performing the Supplemental Review screens. The models utilized for this Supplemental Review originated from the 2015 series MISO Transmission Expansion Plan (MTEP). Otter Tail s 41.6 kv transmission system in the local area to R101 was then inserted into the models. For each set of seasonal models, a base case and a post-project case was developed in order to perform the screening analysis for the R101 project. The base case models contained the local 41.6 kv transmission system without the addition of the R101 project. The post case models contained the local 41.6 kv transmission system with the addition of R101 project. The modeling for the R101 project was based on the best information Otter Tail was provided from Appendix 1 of the Generator Interconnection Procedure supplied by the interconnection customer. Below is a table of models that were developed for this Supplemental Review. R101 Supplemental Review Page 4

5 MW Season Year Origin Summer Light Load 2017 MTEP 2015 Series with local 41.6 kv system added Summer Peak 2017 MTEP 2015 Series with local 41.6 kv system added Winter Peak 2020 MTEP 2015 Series with local 41.6 kv system added Table 3-1: R101 Supplemental Review Models 4. Supplemental Review and Results This Supplemental Review consisted of three screening parameters that are included within section of Attachment X to the MISO tariff. The screening requirements and corresponding results are provided below Attachment X Minimum Load Screening The first screening parameter investigated as part of this Supplemental Review is included in section of Attachment X of the MISO tariff, which is to investigate if the aggregate Generating Facility capacity on the line section is less than 100% of the minimum load for all line sections bounded by automatic sectionalizing devices upstream of the proposed Small Generating Facility. A full excerpt of section of Attachment X of the MISO tariff is included in Appendix B Attachment X Minimum Load Screening Results The R101 project is proposing to interconnect to a 41.6 kv line currently served from circuit breaker 435 at Otter Tail s Plummer 115/41.6 kv substation. Otter Tail was able to gather 12 months of historic loading data on all line sections bounded by an automatic sectionalizing device up stream of the proposed interconnection of R101. Below is a Load Duration Curve that shows the historical flow (MW) of circuit breaker 435 arranged from highest loading to the lowest loading throughout the 2015 calendar year Plummer 41.6 kv Circuit Breaker Loading Hour Plummer 41.6 kv CB 435 MW Requested Small Generating Facility MW Figure 4-1: Plummer 41.6 kv Circuit Breaker 435 Loading (MW) R101 Supplemental Review Page 5

6 The loading in the figure above shows that the nameplate rating of the Generating Facility (only consisting of the R101 interconnection) is not less than 100% of the minimum load for all line sections bounded by automatic sectionalizing devices upstream of the proposed interconnection of R101. The loading on the 41.6 kv line normally served by Plummer circuit breaker 435 was less than the 4.6 MW generator interconnection request approximately 87% of the time in Based on this historical flow information, Otter Tail concludes that R101 fails the Minimum Load Screening requirements Attachment X Voltage and Power Quality Screen The second screening parameter investigated as part of this Supplemental Review is included in section of Attachment X of the MISO tariff, which states that, in aggregate with existing generation on the interconnecting line section: (1) the voltage regulation on the line section can be maintained in compliance with relevant requirements under all system conditions; (2) the voltage fluctuation is within acceptable limits as defined by Institute of Electrical and Electronics Engineers (IEEE) Standard 1453, or utility practice similar to IEEE Standard 1453; and (3) the harmonic levels meet IEEE Standard 519 limits. The language of section of Attachment X of the MISO tariff is included in Appendix B Attachment X Voltage and Power Quality Screen Results PSS/E revision 33.5 was utilized to screen system voltages and voltage fluctuations. System voltages and voltage fluctuations were analyzed for system intact conditions, as well as local contingency events. The worst contingencies in the area were determined through engineering judgment based on simulations performed during this review and experience from past studies. The worst contingencies, with their associated post-contingent switching procedure, analyzed in this Supplemental Review are listed below: Contingency Event Switching Procedure Connected Source System Intact N.A. Plummer Breaker 435 Loss of Red Lake Falls W. Gentilly Closed Gentilly Jct. Switch 449 Plummer Breaker 425 (R101) Loss of Red Lake Falls W. Gentilly Closed Gentilly Jct. Switch 448 Crookston Breaker 635 (R101) Loss of Red Lake Falls W. (R101) Closed Gentilly Jct. Switch 449 Plummer Breaker 425 Gentilly Loss of Crookston Crookston Plant Jct. Closed Gentilly Jct. Switch 448 Plummer Breaker 435 Table 4-2: Worst Contingencies and Switching Operations The criteria listed below were used to identify if voltages were outside of Otter Tail s reliability criteria during various system conditions and contingency events. System Voltage Criteria System Intact Conditions: 41.6 kv: 0.95 p.u. to 1.05 p.u. 115 kv: 0.97 p.u. to 1.07 p.u. 230 kv, 345 kv: 0.97 p.u. to 1.05 p.u. R101 Supplemental Review Page 6

7 Post Contingent Events: 41.6 kv: 0.95 p.u. to 1.05 p.u. (with post-contingent switching simulated) 41.6 kv, 115 kv, 230 kv, 345 kv: 0.92 p.u. to 1.10 p.u. (without post-contingent switching simulated) Transient Switching Criteria System Intact Conditions: Voltage change is limited to 3% of pre-switching voltage Post Contingent Events: Voltage change is limited to 5% of pre-switching voltage (1) Table 4.3 below summarizes the voltage criteria violations identified within the area and the models for which the violation appears. Model 2017 SLL 2017 SPK 2020 WPK Contingency Base Post Base Post Base Post System Intact V V V V - V Loss of Red Lake Falls W. Gentilly (R101) V V V V - - Closed Switch 449 Loss of Red Lake Falls W. Gentilly (R101) V V V V - - Closed Switch 448 Loss of Red Lake Falls W. (R101) Gentilly V V V V - V Closed Switch 449 Loss of Crookston Crookston Plant Jct. V V V V V V Closed Switch 448 * V denotes voltage violation Table 4-3: Voltage Violations All the violations appearing in the models for the 2017 Summer Light Load (SLL) and 2017 Summer Peak (SPK) models are in the Crookston area. The 41.6 kv transmission system in the Crookston area historically runs around 43.8 kv (1.052 p.u.). Since this voltage is above Otter Tail s high voltage criteria of 1.05 p.u., criteria violations were flagged in the base and postproject cases. Overall, there is minimal change in system voltages between the base and postproject cases in the 2017 SLL and 2017 SPK models and no new voltage violations occur in the post-project cases. In the 2020 Winter Peak (WPK) model, voltage criteria violations show up in the post-project cases and not in the base case for the system intact condition and the loss of the Red Lake Falls W. (R101) Gentilly 41.6 kv line when closing switch 449. During these conditions, the R101 project is isolated from the Crookston buses, which are where the voltage criteria violations are occurring. Therefore, these voltage violations in the 2020 WPK model are not attributed to the R101 project. A low voltage criteria violation occurs in the base case of the 2020 WPK model for the loss of the Crookston Crookston Plant Jct kv line when closing switch 448. In the corresponding post-project case, this low voltage violation is mitigated. The Crookston bus also has a voltage criteria violation due to high voltages in the 2020 WPK model, but this violation appears in both the base and post-project cases. Given the results from the voltage screening, there are no new voltage criteria violations caused by the interconnection of R101 Supplemental Review Page 7

8 R101, thus Otter Tail has concluded that this project passes this portion of the Voltage and Power Quality Screen. Detailed information on the voltages can be seen in Appendix A, System Voltage Tables. (2) To investigate transient voltage performance following the interconnection of the R101 project, Otter Tail performed an analysis to determine the instantaneous voltage change from the R101 project switching on-line or off-line as wind or solar conditions change. Table 4.4 below shows the results of the voltage fluctuation or transient voltage caused by the interconnection of R101 when the unit is tripped offline. Model 2017 SLL 2017 SPK 2020 WPK Contingency - - V System Intact Loss of Red Lake Falls W. Gentilly (R101), Sw Loss of Red Lake Falls W. Gentilly (R101), Sw Loss of Red Lake Falls W. (R101) Gentilly, Sw Loss of Crookston Crookston Plant Jct., Sw V * V denotes Transient Voltage Violation Table 4-4: Transient Voltage Violations Transient switching violations show up in the system intact case and the loss of Crookston Crookston Plant Jct. closing switch 448. The initial voltage control set point for the R101 project was set to control the voltage on the 41.6 kv system at the point of interconnection to 1.04 p.u. From Otter Tail s analysis results, it appears that this assumed voltage control point is too high because it causes a large voltage swing when the unit goes offline. If the voltage set point of the R101 project is set lower (~1.02 p.u.), transient voltage violations from switching events are mitigated in both base and post-project cases. Assuming that a change in the assumed voltage set point for the R101 project mitigates the transient voltage violations, no further mitigation will be necessary for voltage violations related to the R101 project. Therefore, R101 passes this portion of the Voltage and Power Quality Screen. Detailed information on the transient voltage results can be seen in Appendix A, Transient Voltage Tables. (3) Another requirement in the screening parameters identified in section of Attachment X to the MISO tariff is to confirm if harmonic levels on the transmission system meet IEEE Standard 519. Otter Tail has not completed analysis to verify the harmonic levels meet IEEE Standard 519 limits. Therefore, Otter Tail cannot determine whether R101 will pass or fail this portion of the screening parameters. If the interconnection customer (R101) moves forward, Otter Tail reserves the right to have this analysis performed in the future. R101 Supplemental Review Page 8

9 4.3. Attachment X Safety and Reliability Screen The last screening parameter investigated as part of this Supplemental Review is included in section of Attachment X of the MISO tariff, which states that the location of the proposed small Generating Facility and the aggregate generation capacity on the line section do not create impacts to safety or reliability of the transmission system. The applicable language of section of Attachment X of the MISO tariff is included in Appendix B Attachment X Safety and Reliability Screen Results The results of Otter Tail s investigation of this project against that of the screening parameters included in section of Attachment X to the MISO tariff 1. Section : Otter Tail has confirmed that the line section R101 is requesting interconnection to is not dominated by large commercial customers. The majority of the load served off this line is due to residential customers. 2. Section : Otter Tail has determined that the loading on the line section R101 is requesting interconnection to is mainly dominated by three distribution substations located east of the R101 project. These three substations are electrically located between the R101 project and the Plummer 115/41.6 kv substation. There is one additional distribution substation located west of the R101 project that is fairly small in comparison to the other three distribution substations located on this circuit. 3. Section : Otter Tail understands that the requested interconnection point of the R101 project is located approximately 15 miles from the Plummer 115/41.6 kv substation. Otter Tail does allow emergency ratings on their 41.6 kv equipment; however, this line is currently limited by relay settings at the Plummer 115/41.6 kv Substation, thus there is not an emergency limit allowed on the 41.6 kv line that the R101 project is requesting interconnection to. 4. Section : Otter Tail will require the interconnection customer to verify that the functionality described in section is incorporated in the design of the R101 project. The interconnection customer will also be required to sign Otter Tail s Control Area Services and Operations Tariff (CASOT). 5. Section : In the screening analysis performed by Otter Tail, no overloads occurred on any Facilities nor were there any additional voltage criteria violations caused by the R101 project. However, Otter Tail did notice some reverse power flow concerns related to the R101 project when switching into adjacent transmission lines connecting the R101 project to other high voltage substations. Currently, Otter Tail s protection is not designed to accommodate reverse power flows on these 41.6 kv circuits. If these reverse power flow concerns are not mitigated, Otter Tail equipment is in jeopardy of being harmed with the addition of R101 project leading to reliability concerns on the 41.6 kv transmission system. The table below shows the substation locations that exhibited reverse power flow issues in the analysis. R101 Supplemental Review Page 9

10 Model Contingency Breaker Showing Reverse Flow Amount of Reverse Flow (MW) 2017 SLL System Intact Plummer SLL Loss of Red Lake Falls W. Gentilly (R101), Plummer Closing Gentilly Jct. Switch SLL Loss of Red Lake Falls W. Gentilly Crookston (R101),Closing Gentilly Jct. Switch SLL Loss of Red Lake Falls W. Gentilly Plummer (R101),Closing Gentilly Jct. Switch SUM System Intact Plummer SUM Loss of Red Lake Falls W. Gentilly (R101), Plummer Closing Gentilly Jct. Switch SUM Loss of Red Lake Falls W. Gentilly Crookston (R101),Closing Gentilly Jct. Switch SUM Loss of Red Lake Falls W. Gentilly Plummer (R101),Closing Gentilly Jct. Switch WPK Loss of Red Lake Falls W. Gentilly Crookston (R101),Closing Gentilly Jct. Switch 448 Table 4-5: Reverse Flow Issues Existing protective relaying schemes on the transmission lines off Plummer breakers 425 and 435, as well as Crookston breaker 635, will be required to be modified to handle reverse flows. If the R101 project continues forward, a Facility Study would be required to determine what would be required to upgrade the protection on these circuits noted above. 6. Section : Otter Tail will require the interconnection customer to verify that the R101 project will be designed to address the various technical issues stated in Conclusion Otter Tail performed a Supplemental Review for the R101 project proceeding through the MISO interconnection process. The Supplemental Review included three screening parameters (1) Minimum Loading Screen, (2) Voltage and Power Quality Screen, and (3) Safety and Reliability Screen. R101 failed the Minimum Loading Screen. The aggregated flow of the R101 generating facility was not less than 100% of the minimum load for the line sections bounded by automatic sectionalizing devices upstream of the proposed interconnection of the R101 project. R101 passed the first two requirements of the Voltage and Power Quality Screen. R101 did not create any new voltage criteria violations on the transmission system in the local area. R101 did flag some transient voltage violations; however, these violations could be resolved by adjusting the voltage set point of the R101 project. The last portion of the Voltage and Power Quality Screen, verifying harmonic levels meet IEEE Standard 519 limits was not performed by Otter Tail as part of this Supplemental Review. If the interconnection customer moves forward in the MISO interconnection process, Otter Tail reserves the right to have this analysis performed in the future. R101 Supplemental Review Page 10

11 R101 failed the Safety and Reliability Screen; however, concerns identified by Otter Tail could be addressed by certain design parameters used for the R101 project that would allow this project to pass the Safety and Reliability Screen, such as, but not limited to R101 will be required to verify that requirements outlined in sections and of Attachment X to the MISO tariff are met with the equipment being installed with the project. R101 will be required to address reverse power flow concerns identified by Otter Tail for three 41.6 kv transmission lines. o A Facility Study will be required to determine what necessary upgrades will be required for each substation that has reverse power flow issues identified on individual 41.6 kv transmission circuits. Overall, R101 fails the Supplemental Review due to the Minimum Load Screen and the items that would need to be addressed in the Safety and Reliability Screen. R101 Supplemental Review Page 11

12 Appendices R101 Supplemental Review Page 12

13 Appendix A System Voltage Tables System Intact Voltage (p.u.) 2017 SLL 2017 SPK 2020 WPK Bus Base Post Delta Base Post Delta Base Post Delta 7967 Plummer Plummer Tap Plummer Red Lake Falls Red Lake Falls W R101 POI N.A N.A. N.A N.A. N.A N.A Gentilly Gentilly Jct Brooks EP Brooks Erskine Jct Erskine Mentor Crookston Crookston Plant Jct Crookston Barrette Crookston Pipe Tap Crookston Pipe Loss of Red Lake Falls W. Gentilly (R101), Closing Gentilly Jct. Switch 449 (Plummer Breaker 425) Voltage (p.u.) 2017 SLL 2017 SPK 2020 WPK Bus Base Post Delta Base Post Delta Base Post Delta 7967 Plummer Plummer Tap Plummer Red Lake Falls Red Lake Falls W R101 POI N.A N.A. N.A N.A. N.A N.A Gentilly Gentilly Jct Brooks EP Brooks Erskine Jct Erskine Mentor Crookston Crookston Plant Jct Crookston Barrette Crookston Pipe Tap Crookston Pipe R101 Supplemental Review Page 13

14 Loss of Red Lake Falls W. Gentilly (R101),Closing Gentilly Jct. Switch 448 (Crookston Breaker 635) Voltage (p.u.) 2017 SLL 2017 SPK 2020 WPK Bus Base Post Delta Base Post Delta Base Post Delta 7967 Plummer Plummer Tap Plummer Red Lake Falls Red Lake Falls W R101 POI N.A N.A. N.A N.A. N.A N.A Gentilly Gentilly Jct Brooks EP Brooks Erskine Jct Erskine Mentor Crookston Crookston Plant Jct Crookston Barrette Crookston Pipe Tap Crookston Pipe Loss of Red Lake Falls W. (R101) Gentilly, Closing Gentilly Jct. Switch 449 (Plummer Breaker 425) Voltage (p.u.) 2017 SLL 2017 SPK 2020 WPK Bus Base Post Delta Base Post Delta Base Post Delta 7967 Plummer Plummer Tap Plummer Red Lake Falls Red Lake Falls W R101 POI N.A N.A. N.A N.A. N.A N.A Gentilly Gentilly Jct Brooks EP Brooks Erskine Jct Erskine Mentor Crookston Crookston Plant Jct Crookston Barrette Crookston Pipe Tap Crookston Pipe R101 Supplemental Review Page 14

15 Loss of Crookston Crookston Plant Jct., Closing Switch 448 (Plummer Breaker 435) Voltage (p.u.) 2017 SLL 2017 SPK 2020 WPK Bus Base Post Delta Base Post Delta Base Post Delta 7967 Plummer Plummer Tap Plummer Red Lake Falls Red Lake Falls W R101 POI N.A N.A. N.A N.A. N.A N.A Gentilly Gentilly Jct Brooks EP Brooks Erskine Jct Erskine Mentor Crookston Crookston Plant Jct Crookston Barrette Crookston Pipe Tap Crookston Pipe R101 Supplemental Review Page 15

16 Transient Voltage Tables System Intact Transient Voltage (p.u.) 2017 SLL 2017 SPK 2020 WPK Bus Initial Post Delta Initial Post Delta Initial Post Delta 7967 Plummer Plummer Tap Plummer Red Lake Falls Red Lake Falls W R101 POI Gentilly Gentilly Jct Brooks EP Brooks Erskine Jct Erskine Mentor Crookston Crookston Plant Jct Crookston Barrette Crookston Pipe Tap Crookston Pipe Loss of Red Lake Falls W. Gentilly (R101), Closing Gentilly Jct. Switch 449 (Plummer Breaker 425) Voltage (p.u.) 2017 SLL 2017 SPK 2020 WPK Bus Initial Post Delta Initial Post Delta Initial Post Delta 7967 Plummer Plummer Tap Plummer Red Lake Falls Red Lake Falls W R101 POI Gentilly Gentilly Jct Brooks EP Brooks Erskine Jct Erskine Mentor Crookston Crookston Plant Jct Crookston Barrette Crookston Pipe Tap Crookston Pipe R101 Supplemental Review Page 16

17 Loss of Red Lake Falls W. Gentilly (R101),Closing Gentilly Jct. Switch 448 (Crookston Breaker 635) Voltage (p.u.) 2017 SLL 2017 SPK 2020 WPK Bus Initial Post Delta Initial Post Delta Initial Post Delta 7967 Plummer Plummer Tap Plummer Red Lake Falls Red Lake Falls W R101 POI Gentilly Gentilly Jct Brooks EP Brooks Erskine Jct Erskine Mentor Crookston Crookston Plant Jct Crookston Barrette Crookston Pipe Tap Crookston Pipe Loss of Red Lake Falls W. (R101) Gentilly, Closing Gentilly Jct. Switch 449 (Plummer Breaker 425) Voltage (p.u.) 2017 SLL 2017 SPK 2020 WPK Bus Initial Post Delta Initial Post Delta Initial Post Delta 7967 Plummer Plummer Tap Plummer Red Lake Falls Red Lake Falls W R101 POI Gentilly Gentilly Jct Brooks EP Brooks Erskine Jct Erskine Mentor Crookston Crookston Plant Jct Crookston Barrette Crookston Pipe Tap Crookston Pipe R101 Supplemental Review Page 17

18 Loss of Crookston Crookston Plant Jct., Closing Switch 448 (Plummer Breaker 435) Voltage (p.u.) 2017 SLL 2017 SPK 2020 WPK Bus Initial Post Delta Initial Post Delta Initial Post Delta 7967 Plummer Plummer Tap Plummer Red Lake Falls Red Lake Falls W R101 POI Gentilly Gentilly Jct Brooks EP Brooks Erskine Jct Erskine Mentor Crookston Crookston Plant Jct Crookston Barrette Crookston Pipe Tap Crookston Pipe R101 Supplemental Review Page 18

19 Appendix B MISO Tariff Excerpts in Section of Attachment X Minimum Load Screen: Where 12 months of line section minimum load data (including onsite load but not station service load served by the proposed Small Generating Facility) are available, can be calculated, can be estimated from existing data, or determined from a power flow model, the aggregate Generating Facility capacity on the line section is less than 100% of the minimum load for all line sections bounded by automatic sectionalizing devices upstream of the proposed Small Generating Facility. If minimum load data is not available, or cannot be calculated, estimated or determined, the Transmission Provider shall include the reason(s) that it is unable to calculate, estimate or determine minimum load in its supplemental review results notification under section The type of generation used by the proposed Small Generating Facility will be taken into account when calculating, estimating, or determining circuit of line section minimum load relevant for the application of screen Solar photovoltaic (PV) generation systems with no battery storage use daytime minimum load (i.e. 10 a.m. to 4 p.m. for fixed panel systems and 8 a.m. to 6 p.m. for PV systems utilizing tracking systems), while all other generation uses absolute minimum load When this screen is being applied to a Small Generating Facility that serves some station service load, only the net injection into the Transmission Provider s electric system will be considered as part of the aggregate generation Transmission Provider will not consider as part of the aggregate generation for purposes of this screen generating facility capacity known to be already reflected in the minimum load data Voltage and Power Quality Screen: In aggregate with existing generation on the line section: (1) the voltage regulation on the line section can be maintained in compliance with relevant requirements under all system conditions; (2) the voltage fluctuation is within acceptable limits as defined by Institute of Electrical and Electronics Engineers (IEEE) Standard 1453, or utility practice similar to IEEE Standard 1453; and (3) the harmonic levels meet IEEE Standard 519 limits Safety and Reliability Screen: The location of the proposed small Generating Facility and the aggregate generation capacity on the line section do not create impacts to safety or reliability that cannot be adequately addressed without application of the Study Process. The Transmission Provider shall give due consideration to the following and other factors in determining potential impacts to safety and reliability in applying this screen. R101 Supplemental Review Page 19

20 Whether the line section has significant minimum loading levels dominated by a small number of customers (e.g., several large commercial customers) Whether the loading along the line section is uniform or even Whether the proposed Small Generating Facility is located in close proximity to the substation (i.e., less than 2.5 electrical circuit miles), and whether the line section from the substation to the Point of Interconnection is a Mainline rated for normal and emergency ampacity Whether the proposed Small Generating Facility incorporates a time delay function to prevent reconnection of the generator to the system until system voltage and frequency are within normal limits for a prescribed time Whether operational flexibility is reduced by proposed Small Generating Facility, such that transfer of the line section(s) of the Small Generating Facility to a neighboring distribution circuit/substation may trigger overloads or voltage issues Whether the proposed Small Generating Facility employs equipment or systems certified by a recognized standards organization to address technical issues such as, but not limited to, islanding, reverse power flow, or voltage quality. R101 Supplemental Review Page 20

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114. Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine

More information

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Presented by: Marianne Mannschreck Date: Welcome A Look at the Net Energy Metering

More information

NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario

NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario Table of Contents NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario Table of Contents... 2 1. Executive Summary...

More information

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055 Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights

More information

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives (Required per CPUC Decision No. C10-1328) Final Report (Submitted with Public Service s 2011 ERP) Executive Summary The objective

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator

More information

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 I. Background The Solar Alliance is a group of approximately 30 of the largest photovoltaic (PV) solar development and

More information

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.

More information

Rule 5.500 Fast Track Analysis for National Life Insurance Co.

Rule 5.500 Fast Track Analysis for National Life Insurance Co. Rule 5.500 Fast Track Analysis for National Life Insurance Co. For a 500 kw Solar array to be located at 155 Northfield Street in Montpelier, Vermont Green Mountain Power Pam Allen Date: 5/31/13 SECTION

More information

SPECIFICATION COG-2007

SPECIFICATION COG-2007 Cleco Power LLC SPECIFICATION COG-2007 FOR PARALLEL OPPERATION OF CUSTOMER-OWNED GENERATION ON CLECO S ELECTRICAL SYSTEM Revised: March 7, 2014 CONTENTS ITEM NO. TITLE PAGE NO. 1.0 Scope 3 2.0 Policy On

More information

Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables. Bob Yinger Southern California Edison April 15, 2014

Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables. Bob Yinger Southern California Edison April 15, 2014 1 Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables Bob Yinger Southern California Edison April 15, 2014 Southern California Edison SCE provides power to: Nearly

More information

FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria

FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria A. Purpose: The FRCC Reliability Coordinator (RC) Contingency Analysis (CA) application is essential to maintaining the reliability of the FRCC Bulk Electric System. The application has the capability

More information

SOUTH CAROLINA. Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)

SOUTH CAROLINA. Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) SOUTH CAROLINA Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: This Standard contains the requirements, in addition

More information

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems This Agreement is made and entered into this day of, 20, ( Effective Date ) by and between the Orlando Utilities Commission

More information

APPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution

APPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution APPLICATION NOTE Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution INCREASING PV HOSTING WITH EMPOWER TM SOLUTION Executive Summary Distributed solar photovoltaic

More information

Typical Data Requirements Data Required for Power System Evaluation

Typical Data Requirements Data Required for Power System Evaluation Summary 66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Harmonic Filter & Power Capacitor Bank Application Studies This document describes NEPSI

More information

INTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012

INTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012 INTRODUCTION TO SYSTEM PROTECTION Hands-On Relay School 2012 CONGRATULATIONS On choosing the field of system protection. It is an exciting, challenging profession. System protection has changed considerably

More information

Generation and Transmission Interconnection Process

Generation and Transmission Interconnection Process PJM Manual 14A Generation and Transmission Interconnection Process Revision: 18 Effective Date: January 28, 2016 Prepared by Planning Division Generation Interconnection Department PJM 2016 Table of Contents

More information

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES PURPOSE This section provides substation design information for Load Entities interconnected at transmission voltage

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

Updated November 20, 2015. Director, System Planning

Updated November 20, 2015. Director, System Planning Updated November 20, 2015 Job Descriptions Job Title Reports To Job Description SYSTEM PLANNING & SERVICES VP Compliance Manages the system planning and services staff. The director is responsible for

More information

RELIABILITY PLANNING CRITERIA

RELIABILITY PLANNING CRITERIA RELIABILITY PLANNING CRITERIA Version 4.0 01/20/2016 Date Rev. No. Individual Making Edits REVISION HISTORY Reason / Comments 07/01/2013 1 J. Johnson Initial document 06/06/2014 2 R. Chapman Document review;

More information

Engineering innovation

Engineering innovation Eaton's Electrical Engineering Services & Systems Solutions Focus Seamless Solutions for Reliable, Efficient and Safe Power Systems Engineering innovation Progressive solutions for today s power systems

More information

Experimental Verification of Advanced Voltage Control for Penetration of PV in Distribution System with IT Sectionalizing Switches

Experimental Verification of Advanced Voltage Control for Penetration of PV in Distribution System with IT Sectionalizing Switches 21, rue d Artois, F-75008 PARIS C6 _113 _2012 CIGRE 2012 http : //www.cigre.org Experimental Verification of Advanced Voltage Control for Penetration of PV in Distribution System with IT Sectionalizing

More information

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003 F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify

More information

How To Operate The Williston Uvls

How To Operate The Williston Uvls WND Winter Operating Guide 2012/2013 1 WND Operating Study Using EQ-890-2012WIN- FINAL.sav developed through the 890 process Got load updates from MDU, Central Power, UM G&T Made several topology updates

More information

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System Prepared By: Transmission Planning Unit Baltimore Gas & Electric Company Table of Contents 1. INTRODUCTION

More information

Comparison of Interconnection Standards 3/28/2003

Comparison of Interconnection Standards 3/28/2003 Comparison of Interconnection Standards 3/28/2003 Utility 12/3/01 Filing IEEE Rev 10 Wisconsin Draft 5.95 Proposed Minnesota Standard Electrical Code Compliance Installer must meet codes and permit requirements

More information

Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva

Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva Issued: August 2009 SIZED UP TO 100 KVA TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Applicability... 1 1.2 Definitions...

More information

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS 14:8-4.1 Scope This subchapter sets forth net metering requirements that apply to electric power suppliers, basic generation service providers

More information

Job Descriptions. Job Title Reports To Job Description TRANSMISSION SERVICES Manager, Transmission Services. VP Compliance & Standards

Job Descriptions. Job Title Reports To Job Description TRANSMISSION SERVICES Manager, Transmission Services. VP Compliance & Standards Updated July 11, 2013 Job Descriptions Job Title Reports To Job Description TRANSMISSION SERVICES VP Compliance & Standards Develops strategy and business plans for efficient, safe, reliable, regulatorycompliant

More information

Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns

Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Mehmet H. Cintuglu, mcint015@fiu.edu, Armando Altamirano, araltami@fiu.edu Osama A. Mohammed, mohammed@fiu.edu Energy Systems

More information

Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA

Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA CROSS SOUND CABLE PROJECT 330MW HVdc INTERCONNECTION BETWEEN NEW HAVEN, CONNECTICUT AND SHOREHAM, NY Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA Subordinate Status Removal and Amendment of Approved

More information

PacifiCorp Original Sheet No. 476 FERC Electric Tariff, Substitute 6 th Rev Volume No. 11 APPENDIX 2 TO SGIP

PacifiCorp Original Sheet No. 476 FERC Electric Tariff, Substitute 6 th Rev Volume No. 11 APPENDIX 2 TO SGIP PacifiCorp Original Sheet No. 476 APPENDIX 2 TO SGIP SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: Designated Contact Person: Address: Telephone Number: An Interconnection

More information

Integrating Renewable Electricity on the Grid. A Report by the APS Panel on Public Affairs

Integrating Renewable Electricity on the Grid. A Report by the APS Panel on Public Affairs Integrating Renewable Electricity on the Grid A Report by the APS Panel on Public Affairs 2 Integrating Renewable Electricity on the Grid Executive Summary The United States has ample renewable energy

More information

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

Design of electrical power system for a 1000MW nuclear power generating station

Design of electrical power system for a 1000MW nuclear power generating station Design of electrical power system for a 1000MW nuclear power generating station K Raja, K Yesunadam Dept. of Electrical & Electronics Engineering, Lingaya s Institute of Management & Technology, Vijayawada,

More information

Generator Interconnection and Deliverability Study Methodology Technical Paper

Generator Interconnection and Deliverability Study Methodology Technical Paper Generator Interconnection and Deliverability Study Methodology Technical Paper July 2, 2013 Generator Interconnection and Deliverability Study Methodology Table of Contents Introduction... 1 Section One:

More information

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer Size template Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer The average system size has doubled since 2010 Key Network Issues Reverse power on up to 12 off 11 kv feeders

More information

IEEE Smart Grid Series of Standards IEEE 2030 TM (Interoperability) and IEEE 1547 TM (Interconnection) Status. #GridInterop

IEEE Smart Grid Series of Standards IEEE 2030 TM (Interoperability) and IEEE 1547 TM (Interconnection) Status. #GridInterop IEEE Smart Grid Series of Standards IEEE 2030 TM (Interoperability) and IEEE 1547 TM (Interconnection) Status #GridInterop Smart Grid (IEEE 2030): the integration of power, communications, and information

More information

Guidelines for Large Photovoltaic System Integration

Guidelines for Large Photovoltaic System Integration 1 Guidelines for Large Photovoltaic System Integration Silviu Darie, PhD(EE), PE(EE) Abstract- The paper summarizes the result of a research project funded by the Department of Energy (DOE) in collaboration

More information

Grid of the Future. Integration of Renewables Energy Storage Smart Grid. Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations

Grid of the Future. Integration of Renewables Energy Storage Smart Grid. Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations Grid of the Future Integration of Renewables Energy Storage Smart Grid Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations Grid of the Future Current Power System Gen. Trans. Dist.Cust.

More information

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)

More information

TDI's NYC Merchant CHPE Transmission Project with POI at Astoria (NYISO Queue #305) Deliverability Analysis

TDI's NYC Merchant CHPE Transmission Project with POI at Astoria (NYISO Queue #305) Deliverability Analysis R103-11 TDI's NYC Merchant CHPE Transmission Project with POI at Astoria (NYISO Queue #305) Deliverability Analysis Prepared for Transmission Developers, Inc. Submitted by: Larry Eng, Staff Consultant

More information

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach READ AND DELETE For best results with this template, use PowerPoint 2003 10 November 2015 Background and Importance of ICA Definition:

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

Distributed Generation and the Impact on a Distribution System. Brian Lassiter Technical Sales Engineer

Distributed Generation and the Impact on a Distribution System. Brian Lassiter Technical Sales Engineer Distributed Generation and the Impact on a Distribution System Brian Lassiter Technical Sales Engineer Company Overview Founded in 1989 in Abilene, TX Industry leader in Engineering and Operations Utility

More information

Assessment of power swing blocking functions of line protective relays for a near scenario of the Uruguayan system

Assessment of power swing blocking functions of line protective relays for a near scenario of the Uruguayan system Assessment of power swing blocking functions of line protective relays for a near scenario of the Uruguayan system C. Sena, R. Franco, A. Giusto. Instituto de Ingeniería Eléctrica Facultad de Ingeniería

More information

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES 1. Acceptance of Electricity Service By establishing or requesting a POD or by continuing an

More information

Scope of Restoration Plan

Scope of Restoration Plan RWG Area Restoration Review Worksheet (10/28/09) EOP-006-02 Directory 8 EOP-005 NYSRG Rule G Text Restoration Plan Requirement R1.Each Reliability Coordinator shall have a Reliability Coordinator Area

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment March 20, 2009 Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Table of Contents:

More information

Distributed Power, Renewables, Stored Energy and the Grid Blinkless Synchronous Inverter System

Distributed Power, Renewables, Stored Energy and the Grid Blinkless Synchronous Inverter System Distributed Power, Renewables, Stored Energy and the Grid Blinkless Synchronous Inverter Go Electric Inc. www.goelectricinc.com 1 Distributed Power, Renewables, Stored Energy and the Grid Blinkless Synchronous

More information

Physical Address: City: State: Zip Code:

Physical Address: City: State: Zip Code: Application for Small Generator Facility Interconnection Tier 2, Tier 3 or Tier 4 Interconnection (For Small Generator Facilities with Electric Nameplate Capacities of 10 MW and less) Applicant Contact

More information

Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3

Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3 Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3 Basics of Power systems Network topology Transmission and Distribution Load and Resource Balance Economic Dispatch Steady State System

More information

100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd

100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd 100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center Introduction Roger Hedding Steven Schoenherr, P.E. ABB Inc. Minnesota Power 598 N. Buth Rd 3215 Arrowhead Rd Dousman,

More information

PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study

PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study PJM Merchant Transmission Request Queue #R75 Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study 413038v1a March 2007 PJM Interconnection 2007. All rights reserved. Preface The intent of the

More information

About Southern California Edison

About Southern California Edison About Southern California Edison One of the nations largest investorowned utilities with 125 years of service. Service Area 50,000 square miles Over 430 cities and communities Population Served Nearly

More information

Effective: September 10, 2006 Vermont Attachment 1 to Rule 5.500 Public Service Board Page 1 of 6

Effective: September 10, 2006 Vermont Attachment 1 to Rule 5.500 Public Service Board Page 1 of 6 Public Service Board Page 1 of 6 STANDARD APPLICATION FOR INTERCONNECTION OF GENERATION RESOURCES IN PARALLEL TO THE ELECTRIC SYSTEM OF: (Interconnecting Utility) Preamble and Instructions: An owner of

More information

Northport - Norwalk Harbor Cable (NNC) Tie line

Northport - Norwalk Harbor Cable (NNC) Tie line September 9, 008 Northport - Norwalk Harbor Cable (NNC) Tie line Technical Assessment of Operating up to NNC Inter Tie STE Ratings Executive Summary Three (3) 38kV submarine cable circuits (Lines 60, 60,

More information

Security Policy Review: Credible Event Management. Scope and Methodology Draft for Industry 2014

Security Policy Review: Credible Event Management. Scope and Methodology Draft for Industry 2014 Security Policy Review: Credible Event Management Scope and Methodology Draft for Industry 2014 Version Date Change 1 26/03/2014 Draft for industry Position Date Prepared By: Reviewed By: Ina Ilieva, Senior

More information

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Pakistan Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Final Report: Executive Summary - November 2015 for USAID Energy Policy

More information

IESO Supply Deliverability Guidelines

IESO Supply Deliverability Guidelines PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents

More information

Application for Small Generator Facility Interconnection Tier 2, Tier 3 or Tier 4 Interconnection

Application for Small Generator Facility Interconnection Tier 2, Tier 3 or Tier 4 Interconnection Application for Small Generator Facility Interconnection Tier 2, Tier 3 or Tier 4 Interconnection (See ARSD chapter 20:10:36 for the requirements for a Tier 2, Tier 3, or Tier 4 Interconnection.) Applicant/Interconnection

More information

Power transformers. Phase shifting transformers Reliable and efficient power flow control

Power transformers. Phase shifting transformers Reliable and efficient power flow control Power transformers Phase shifting transformers Reliable and efficient power flow control 2 Phase shifting transformers Eliminating bottlenecks in AC networks Phase shifting transformers (PST) are crucial

More information

CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL

CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL FORM CM-36 CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL February 7,2012 AGENDA ITEM Request for Approval to Issue a Request for Qualification (RFQ) of Firms, and Request for Proposal (RFP) to Engineer,

More information

Session 10: General Overview of Interconnection Standards & Grid Codes for High Penetration PV October 21, 2015 Santiago, Chile

Session 10: General Overview of Interconnection Standards & Grid Codes for High Penetration PV October 21, 2015 Santiago, Chile Session 10: General Overview of Interconnection Standards & Grid Codes for High Penetration PV October 21, 2015 Santiago, Chile Michael Coddington National Renewable Energy Laboratory Golden, Colorado,

More information

Treasure Valley Electrical Plan

Treasure Valley Electrical Plan Treasure Valley Electrical Plan Community Advisory Committee January 25, 2006 Agenda 10 a.m. Welcome 10:10 a.m. Follow up DSM discussion 10:30 a.m. TVEP CAC process update 10:40 a.m. Transmission Presentation

More information

A Modelling Tool to Investigate the Effect of Electric Vehicle Charging on Low Voltage Networks

A Modelling Tool to Investigate the Effect of Electric Vehicle Charging on Low Voltage Networks EVS27 Barcelona, Spain, November 17-20, 2013 A Modelling Tool to Investigate the Effect of Electric Vehicle Charging on Low Voltage Networks Lacey G. 1, Putrus G., Bentley E., Johnston D., Walker S and

More information

Treasure Valley Electric Plan - Community Advisory Committee

Treasure Valley Electric Plan - Community Advisory Committee Treasure Valley Electric Plan - Community Advisory Committee What is a transmission line and why are they necessary? A transmission line is used to conduct electricity between two points. Without high

More information

2016 ERCOT System Planning Long-Term Hourly Peak Demand and Energy Forecast December 31, 2015

2016 ERCOT System Planning Long-Term Hourly Peak Demand and Energy Forecast December 31, 2015 2016 ERCOT System Planning Long-Term Hourly Peak Demand and Energy Forecast December 31, 2015 2015 Electric Reliability Council of Texas, Inc. All rights reserved. Long-Term Hourly Peak Demand and Energy

More information

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO 250447392

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO 250447392 1 Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading By Ramandeep Kaur Aujla S.NO 250447392 ES 586b: Theory and applications of protective relays Department of

More information

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE Ana Diez Castro & Rickard Ellström Ying Jiang Häfner Christer Liljegren Vattenfall Utveckling AB ABB Power Systems Gotlands Energiverk AB

More information

Advanced Inverter Overview

Advanced Inverter Overview Advanced Inverter Overview Renewables on the Distribution Grid Minnesota Public Utilities Commission April 11, 2014 Lise Trudeau Senior Engineering Specialist Minnesota Department of Commerce Division

More information

MINNESOTA POWER. Company Background: CapX2020 Transmission Plan

MINNESOTA POWER. Company Background: CapX2020 Transmission Plan TRANSMISSION PROJECTS: AT A GLANCE MINNESOTA POWER MINNESOTA POWER Company Background: Minnesota Power, a division of ALLETE, provides electricity in a 26,000 square mile electric service area located

More information

Distributed Generation and Power Quality Case Study

Distributed Generation and Power Quality Case Study 16 Distributed Generation and Power Quality Case Study Vu Van Thong and Johan Driesen C16.1 DISTRIBUTION NETWORK A segment of an existing Belgian medium-voltage distribution system is used to study the

More information

Kent Active System Management (KASM) Oct 2015 / Matthieu Michel

Kent Active System Management (KASM) Oct 2015 / Matthieu Michel Kent Active System Management (KASM) Oct 2015 / Matthieu Michel Project Background (update): D Heat Map: SPN D Connection Offers Accepted (Cumulative) 1W D Heat map (June 2015) SPN D Connection Offers

More information

Applicability and Eligibility

Applicability and Eligibility Application for Resource Adequacy Deliverability Status for a Distributed Generation Resource Interconnected or Seeking Interconnection to the Distribution Facilities of an Investor-Owned Utility Participating

More information

FIT TIER 2 Application

FIT TIER 2 Application FIT TIER 2 Application Application Information The below information Auto-Fills from your registration information: Building Permit Application Date: Project Completion Date: Name: Address: City: State:

More information

Guidelines for Monthly Statistics Data Collection

Guidelines for Monthly Statistics Data Collection Guidelines for Monthly Statistics Data Collection Final version Data Expert Group 31 May 2015 1. Table of contents 1. Table of contents... 2 2. Remarks... 3 3. Introduction... 3 4. Geographical perimeter

More information

Nuclear Power Plant Electrical Power Supply System Requirements

Nuclear Power Plant Electrical Power Supply System Requirements 1 Nuclear Power Plant Electrical Power Supply System Requirements Željko Jurković, Krško NPP, zeljko.jurkovic@nek.si Abstract Various regulations and standards require from electrical power system of the

More information

Item 8: Houston Import RPG Project

Item 8: Houston Import RPG Project : Houston Import RPG Project Jeff Billo Manager, Transmission Planning Board of Directors Meeting April 8, 2014 Study Overview ERCOT has determined that there will be a need for additional import capacity

More information

Solar Power Plant Design and Interconnection

Solar Power Plant Design and Interconnection Solar Power Plant Design and Interconnection Wind & Solar Super Session July 27, 2011 E.H. Camm, S.E. Williams S&C Electric Company Outline Introduction Utility-scale PV power plant Grounding Reactive

More information

Advanced Protection of Distribution Networks with Distributed Generators

Advanced Protection of Distribution Networks with Distributed Generators Date:- 8 10 March 2011 Venue: University of Manchester EES-UETP Course title Advanced Protection of Distribution Networks with Distributed Generators Peter Crossley Director of the Joule Centre School

More information

SCE Experience with PV Integration

SCE Experience with PV Integration SCE Experience with PV Integration EPRI High Penetration PV Grid Integration Workshop April 19, 2012 Tucson, AZ Leading the Nation in Renewable Power Delivery Actual 2010 Renewable Resources 14.5 billion

More information

*.ppt 11/2/2009 12:48 PM 1

*.ppt 11/2/2009 12:48 PM 1 Digital Compressor Controller *.ppt 11/2/2009 12:48 PM 1 Copeland Scroll Digital Controller Simple Controller That Enables OEM s To Use Digital Scrolls Relieves OEM From Developing Special Controllers

More information

IBERDROLA USA ELECTRIC TRANSMISSION PLANNING MANUAL CRITERIA & PROCESSES

IBERDROLA USA ELECTRIC TRANSMISSION PLANNING MANUAL CRITERIA & PROCESSES IBERDROLA USA TECHNICAL MANUAL TM 1.10.00 Revision 01 Date : 11-2014 Technical Manual Iberdrola USA IBERDROLA USA ELECTRIC TRANSMISSION PLANNING MANUAL CRITERIA & PROCESSES New York State Electric & Gas

More information

Distributed Generation Interconnection Manual

Distributed Generation Interconnection Manual Distributed Generation Interconnection Manual Public Utility Commission of Texas Prepared by: Distributed Utility Associates Endecon Engineering 1062 Concannon Blvd. 347 Norris Court Livermore, CA 94550

More information

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional power generation Power generation from renewables

More information

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage Totally Integrated Power SIESTORAGE The modular energy storage system for a reliable power supply www.siemens.com/siestorage Totally Integrated Power (TIP) We bring power to the point. Our products, systems,

More information

CENTRAL ELECTRIC COOPERATIVE, INC. NET METERING AGREEMENT

CENTRAL ELECTRIC COOPERATIVE, INC. NET METERING AGREEMENT CENTRAL ELECTRIC COOPERATIVE, INC. NET METERING AGREEMENT This Agreement dated and effective this day of,, by and between Central Electric Cooperative, Inc. ( CEC ) and ( Customergenerator ) at (service

More information

DG Modeling Challenges & Results. Jens Schoene

DG Modeling Challenges & Results. Jens Schoene DG Modeling Challenges & Results Jens Schoene December 13, 2013 2 Outline PV Caused Issues on Distribution Systems Modeling Challenges Case Study 3 PV Caused Issues on Distribution Systems 4 Potential

More information

Energy storage in the UK and Korea: Innovation, Investment and Co-operation Appendix 4.1: Stakeholder interviews from Korea

Energy storage in the UK and Korea: Innovation, Investment and Co-operation Appendix 4.1: Stakeholder interviews from Korea Energy storage in the UK and Korea: Innovation, Investment and Co-operation Appendix.1: Stakeholder interviews from Korea Peter Taylor & Lloyd Davies, University of Leeds Appendix.1: Stakeholder interviews

More information

Context: significant penetration of DG = increased risks for system security

Context: significant penetration of DG = increased risks for system security Distributed Generation: towards an effective contribution to power system security IEEE Tampa GM 2007: Panel on Impact of Dispersed Generation on Power System structure & security Bruno Meyer Outline Context:

More information

General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System

General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System Direction Planification des actifs et expertise de transport February 2011 TABLE OF CONTENTS 1. CONDUCTING

More information

Network Consulting for Power Grid Optimization

Network Consulting for Power Grid Optimization Network Consulting for Power Grid Optimization Project experience in India Network Consulting Competences Page 1 Our worldwide representation Manchester The Hague Denver Schenectady San Diego Houston Mexico

More information

Guidelines for Generation, Tie-Line, and Substation Interconnections

Guidelines for Generation, Tie-Line, and Substation Interconnections Guidelines for Generation, Tie-Line, and Substation Interconnections Otter Tail Power Company compiled this document with input from others. Otter Tail Power Company gratefully acknowledges permission

More information

Electrical System Studies

Electrical System Studies Electrical System Studies INTRODUCTION s experienced professionals provide electrical systems planning and design services to improve the safety and the reliability of electric power systems. The planning,

More information

Interconnection Application For Residential and Commercial Power Systems 10 kw or Smaller

Interconnection Application For Residential and Commercial Power Systems 10 kw or Smaller Interconnection Application For Residential and Commercial Power Systems 10 kw or Smaller A fee of $0.00 must accompany this application Date: Section 1: Customer Information Section 2: Engineering firm

More information

ATTACHMENT F. Electric Utility Contact Information Utility Name. For Office Use Only

ATTACHMENT F. Electric Utility Contact Information Utility Name. For Office Use Only ATTACHMENT F CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 20 KW BUT LESS THAN OR EQUAL TO 150 KW Also Serves as Application for Category

More information

Chapter 7 - Appendix A

Chapter 7 - Appendix A Chapter 7 - Appendix A Transmission and Distribution Supplemental Information Table 7A.1 MTEP Transmission Projects in Missouri 1 Project Approved Project Title Project Description Category Estimated Cost

More information