District IT Infrastructure Upgrade Plan
|
|
- Tabitha Ross
- 8 years ago
- Views:
Transcription
1 District IT Infrastructure Upgrade Plan This document contains two different plans, one consisting of accomplishing all upgrades at one time the other is a plan to accomplish all upgrades over a 3 year period. Primary School cabling initiative costs not included in any of the totals due to undecided future of the building. Possible closing of this building can greatly effect total costs: fewer workstations, fewer data switches, fewer VoIP phones, fewer UPS units, lower Charter Business Networks cost. Single Year Upgrade (Summer 2014 or 2015) HP Data Switches (Redundant 10GB Core Fiber, POE, VoIP support) = $185,000 Primary School, Elementary School, Middle School, High Recurring Annual Service Agreement per Data Switch VoIP Phone System & Voic = $75,000 - $125,000 Recurring Annual Service Agreement APC Smart UPS with Environmental Monitoring = $28,000 Primary School, Elementary School, Middle School, High Recurring Battery Replacement required District installed Unitrends Backup Appliance - R712 4TB = $6,200 Windows Pro Upgrade & Software Assurance = $ $19.25 per 150 Symantec Endpoint Protection Enterprise Anti-Virus = $11,662 $13.72 per 850 workstations SonicWALL Firewall Appliance - Redundant Internet Protection = $6,000 Upgrade Novell OES, ZCM11, VMWare ESX, Update iscsi SAN Configuration, Anti- Virus, Win7/8 Images. Approximately 160 Technical Support Hours = $20,000 Approximately 160 Technical Support $125 per hour
2 Upgrade to 10GB Bandwidth between buildings Workstation Upgrades to Win7 - choose from following 400 Refurbished Optiplex 760 computers x 400 = $80,000 OR 400 New Dell Optiplex 7010 computers x 400 = $360, Refurbished Latitude E6500 laptops x 100 = $40,000 OR 100 New Dell Latitude series laptops x 100 = $85,000 Update data cabling at Middle School Office = Estimated $3,500 Move data drops and data switch to FACE closet Update data cabling at Primary School = Estimated $30,000 (not included in totals) Replace existing data cable with proper ducting Total Cost Estimates = $458, to $833, Recurring Annual Cost Increase = $14, plus Charter Business Networks increase *Note* VoIP Phone system requires Data Switch replacement and UPS installation be done
3 Immediate ( ) Replace failed drive in HP MSA 2000 SAN - $ (Completed 11/5/13) Upgrade VMware to current version - $ (Upgrade on order) Recurring annual license fee - $39.00 Replace failed UPS battery at High School Server Room (Replaced 10/31/13) Replace failed UPS battery at Elementary School MDF (Exchanged with PS UPS) Replace failed UPS at Primary School MDF (Retired server so no longer needed) Investigate alternative workstation anti-virus solution (Symantec Anti-Virus) Implement patch management solution for workstations Contract with Skyward to reprogram existing WSUS system Install Move Wireless access points as described in WiFi assessment Reposition AP in High School Commons Reposition AP in High School C wing Reposition AP from Primary School Room 205 to 200 hallway Reposition AP in Primary School Art/Music hallway Check on operation of AP in High School Auditorium Install New Wireless access points as described in WiFi assessment = $5000 Install additional AP in High School B wing Install additional AP in High School E wing Install additional AP in Elementary School Office Install additional AP in Primary School Speech/Language Room Install additional AP in Primary School Gymnasium
4 1st Year (Summer 2014) Upgrade Novell OES, ZCM11, VMWare ESX, Update iscsi SAN Configuration, Anti- Virus, Win7/8 Images. Approximately 160 Technical Support Hours = $20,000 Approximately 160 Technical Support $125 per hour Upgrade to 1GB Bandwidth between buildings Workstation Upgrades to Win7 - choose from following 400 Refurbished Optiplex 760 computers x 400 = $80,000 OR 400 New Dell Optiplex 7010 computers x 400 = $360, Refurbished Latitude E6500 laptops x 100 = $40,000 OR 100 New Dell Latitude series laptops x 100 = $85,000 Windows Pro Upgrade & Software Assurance = $ $19.25 per 150 Symantec Endpoint Protection Enterprise Anti-Virus = $11,662 $13.72 per 850 workstations Unitrends Backup Appliance - R712 4TB = $6,200 Update data cabling at Middle School Office = Estimated $3,500 Move data drops and data switch to FACE closet SonicWALL Firewall Appliance - Redundant Internet Protection = $6,000 Total Cost Estimates = $172, to $495, Recurring Annual Cost Increase = $14, plus Charter increase
5 2nd Year (Summer 2015) HP Data Switches (Redundant 10GB Core Fiber, POE, VoIP support) = $185,000 Primary School, Elementary School, Middle School, High Recurring Annual Service Agreement per Data Switch Upgrade to 10GB Bandwidth between buildings Total Cost Estimates = $185,000 plus Charter Business Networks increase 3rd Year (Summer 2016) VoIP Phone System & Voic = $75,000 - $125,000 Recurring Annual Service Agreement APC Smart UPS with Environmental Monitoring = $28,000 Primary School, Elementary School, Middle School, High Recurring Battery Replacement required District installed Update data cabling at Primary School = Estimated $30,000 (not included in totals) Replace existing data cable with proper ducting Total Cost Estimates = $130,000 to $153,000
Technology Department Infrastructure & Support
Technology Department Infrastructure & Support The Technology Department Team Executive Director of Technology Technology Coordinator Network Engineer Application Administrator Application Specialist Infrastructure
More informationUpper Perkiomen School District
Upper Perkiomen School District Network Infrastructure Review Executive Summary Prepared by 1001 James Drive, Suite A15 Leesport, PA 19533 610 916 9400 www.jlrconsulting.com Date: March 10, 2015 Report
More informationThe primary goals of the technology plan are to support the goals of the district strategic plan:
STOUGHTON PUBLIC SCHOOLS TECHNOLOGY PLAN 2012-2015 I. MISSION The mission of Stoughton Public School's Technology Program is to provide technology systems and support that meet the needs of students, teachers,
More informationSYSTEM REQUIREMENTS Single User & Red River Software ASP Users (See Specific Info for Tills and/or Meters) are not Supported in RRS
SYSTEM REQUIREMENTS Single User & Red River Software ASP Users (See Specific Info for Tills and/or Meters) Microsoft Windows Vista Business or Ultimate (Vista Home Basic and Home Premium not Supported)
More informationTECHNOLOGY PLAN SUMMARY
IV. TECHNOLOGY PLAN SUMMARY The Oklahoma City Metropolitan Area Public Schools (OCMAPS) Technology Plan serves as a guide for OCMAPS funding of technology into the Oklahoma City Public School District
More informationIVAN WINDON - CCENT NETWORK / SYSTEMS ADMINISTRATOR AREAS OF EXPERTISE:
IVAN WINDON - CCENT 5295 S Netherland Way, Centennial, CO 80015 720.258.6311 c https://www.l3pdu.com ivan.windon@l3pdu.com NETWORK / SYSTEMS ADMINISTRATOR Solutions-focused IT professional driven to advance
More informationBASEHOR-LINWOOD SCHOOL DISTRICT
BASEHOR-LINWOOD SCHOOL DISTRICT Network Overview- June 2013 Performed by Southeast Kansas Educational Service Center- Contents Introduction... 1 Overview... 1 Observations/Recommendations... 1 District-Wide...
More informationLHRIC Network Support - Additional Service Features
LHRIC Network Support - Additional Service Features It is important to note that costs associated with LHRIC Network Support service not only cover an on-site support engineer but also include a number
More informationNortheast Georgia Regional Library System. Request for Proposals 2015
Northeast Georgia Regional Library System Request for Proposals 2015 Contact: Lewis Lucas Asst Dir for Technology PO BOX 2020 Clarkesville, GA 30523 706-754-0416 x230 706-754-0420 (fax) llucas@negeorgialibraries.org
More informationREQUEST FOR PROPOSALS INFORMATION TECHNOLOGY SUPPORT SERVICES. Bid Packets are Due:
REQUEST FOR PROPOSALS INFORMATION TECHNOLOGY SUPPORT SERVICES Issue Date: Friday, March 15 th, 2013 Closing Date: Monday, April 15 th, 2013 University City District is requesting proposals from qualified,
More informationInformation Technology Division Technology Operations & Systems Management
Over the past decade, Texas Tech University has made great strides in protecting the critical information resources of its colleges, institutions and departments. (TOSM) has a 4000 sq/ft data center that
More informationIT Services Network Assessment Pittsville Public School District March 24, 2009
IT Services Network Assessment Pittsville Public School District March 24, 2009 Table of Contents TABLE OF CONTENTS... 2 GLOSSARY AND DEFINITIONS... 3 EXECUTIVE SUMMARY... 4 NETWORK INFRASTRUCTURE... 5
More informationCase Study: Oconomowoc Area School District
Prepared for CESA #1, Sponsored by Cisco Systems, Inc. Case Study: Oconomowoc Area School District Prepared by Rich Kaestner, CoSN TCO/VOI Project Director March 16, 2008 If a broadband fiber network were
More informationREQUEST FOR QUOTE. All out of date servers contain approximately 1 TB of data that needs to be migrated to the new Windows domain environment.
REQUEST FOR QUOTE The Housing Authority of the City of Hartford is seeking quotations for the following project: Systems Department Enterprise Technology Enhancements The current infrastructure consists
More informationService Description. Remote Consulting Service. Introduction to your service agreement. The scope of your service agreement
Service Description Remote Consulting Service Introduction to your service agreement Remote ( RCS ) provide for remote assistance with certain IT infrastructure tasks ( Service or Services ). Each RCS
More informationDALLAS INDEPENDENT SCHOOL DISTRICT PURCHASING DEPARTMENT ADDENDUM No. 2 NETWORK ELECTRONICS
DALLAS INDEPENDENT SCHOOL DISTRICT PURCHASING DEPARTMENT ADDENDUM No. 2 REQUEST FOR PROPOSAL NO. BID #TF- 203970 NETWORK ELECTRONICS Amendment to RFP #TF-203970 NETWORK ELECTRONICS The purpose of Addendum
More informationTECHNICAL SUPPORT. and HARDWARE/SOFTWARE/NETWORK MAINTENANCE. for SCHOOL OF EDUCATION DOLNICK CENTER
IT Services Service Level Agreement TECHNICAL SUPPORT and HARDWARE/SOFTWARE/NETWORK MAINTENANCE for SCHOOL OF EDUCATION DOLNICK CENTER IT Services Service Level Agreement: School of Education Dolnick Center
More informationManaged Network Services RFP. Q&A Document. Q1: What types of hardware does Clark County Department of Job & Family Services (CCDJFS) currently have?
Managed Network Services RFP Q&A Document Q1: What types of hardware does Clark County Department of Job & Family Services (CCDJFS) currently have? A1: Currently we have a mixed server environment, however
More informationNetwork Infrastructure
Oyster River Cooperative School District REQUEST FOR PROPOSAL FOR Network Infrastructure Product Procurement Information Technology Department 33 Coe Drive Durham, NH 03824 Bids will be received by May
More informationTop 10 Most Common Malware - How to Avoid Them
Health check performed by: Jeremy Arndt My Company February 18 th, 2015 IT Health Check OVERALL SCORE 10 Users 3 Servers 1 Network 2 Backups 1 E mail 1 Antivirus 2 High Risk Risk Low Risk IT Health Check
More informationExecutive/Management bios
Project Team Staffing The Heritage team is a dynamic group of professionals, experienced and well trained in their areas of expertise. Our team uses an approach that provides an environment in which everyone
More informationService Description. Remote Consulting Service. Introduction to your service agreement. The scope of your service agreement
Service Description Remote Consulting Service Introduction to your service agreement Remote Consulting Services ( RCS ) provide for remote assistance with certain IT infrastructure tasks ( Service or Services
More informationThis Request for Proposal consists of providing the IT Infrastructure Setup and Ongoing Support RFP requirements outlined in this RFP.
October 7 th, 2015 Subject: Philadelphia Works To All Interested Vendors: Philadelphia Works ( Client ) has retained Watchdog Real Estate Project Managers ( Watchdog ) in connection with the construction/renovation
More informationACME Enterprises IT Infrastructure Assessment
Prepared for ACME Enterprises March 25, 2014 Table of Contents Executive Summary...2 Introduction...2 Background...2 Scope of IT Assessment...2 Findings...2 Detailed Findings for Key Areas Reviewed...3
More informationChabot Las Positas Community College District
Chabot Las Positas Community College District Information Technology Services Disaster Recovery Plan Supplement to August 1, 2014 Plan (General Version) Note: Selected charts and tables are blanked out
More information2015 Piqua City Schools RFP for Network Equipment under E-Rate Category 2
2015 Piqua City Schools RFP for Network Equipment under E-Rate Category 2 Section 1: Responses and contact information 1.0 RFP responses to: If by E:mail: Richard Kevern, E-Rate Connection: richardkevern@e-rateconnection.com
More informationServices that will be provided to the City include:
The City is requesting proposals from qualified professional network support firms for Information Technology Support Services. The qualified vendor will enable the City to improve and maintain Information
More informationSeward County Community College
Seward County Community College REQUEST FOR PROPOSALS Telephone System Replacement Response to Vendors Questions Issued: January 5, 2006 1. Please clarify counts, which includes detail on receptionist
More informationThis Request for Proposal (RFP) consists of providing the IT Infrastructure Setup and Ongoing Support requirements outlined in this RFP.
December 3 rd, 2015 Subject: Philadelphia Works To All Interested Vendors: Philadelphia Works ( Client ) has retained Watchdog Real Estate Project Managers ( Watchdog ) in connection with the construction/renovation
More informationThree Areas of Focus. * Infrastructure * Systems * Processes
IT Three Areas of Focus * Infrastructure * Systems * Processes Adding Wireless * FCS core network to Millstream Tech Center * Admin building * Wireless in Millstream Tech Center Cellular * Infrastructure
More information1. Can you clearly state which piece of equipment we will be support and each site location?
1. Can you clearly state which piece of equipment we will be support and each site location? All desktops, servers, routers, and telephone equipment located at all locations. 2. I assume the camera systems
More informationCity of Coral Gables
City of Coral Gables Information Technology Department IT TECHNICAL SUPPORT DIVISION Infrastructure Upgrade Plan Systems, Applications, Network, and Telecommunications Infrastructure OVERVIEW Last revision:
More informationStatement of Work (SOW) For Technology Services Issued By Minnesota Office of the State Auditor
Business Need Statement of Work (SOW) For Technology Services Issued By Minnesota Office of the State Auditor Project Title: 2012-2013 Network Upgrade and Maintenance *Network (Data, Video, Voice) - LAN/
More informationWINNEBAGO COUNTY INFORMATION TECHNOLOGY STANDARDS 2014/2015
WINNEBAGO COUNTY INFORMATION TECHNOLOGY STANDARDS 2014/2015 Platform Architecture Standards: End User Software Platform Architecture Standards: End User Hardware Platform Architecture Standards: Hand Held
More information1.0 Purpose of Solicitation
Information Technology Consulting Services Notice of Request for Proposal Information Technology Managed Services and Support South Adams County Water and Sanitation District 1.0 Purpose of Solicitation
More informationParkview School District Request for Proposals
Parkview School District Request for Proposals Information Technology (IT) Management and Support Specifications 04/08/2013 Prepared by: Steve Lutzke District Administrator (608) 879-2717 Ext. 1 slutzke@email.parkview.k12.wi.us
More informationMSP Service Matrix. Servers
Servers MSP Service Matrix Microsoft Windows O/S Patching - Patches automatically updated on a regular basis to the customer's servers and desktops. MS Baseline Analyzer and MS WSUS Server used Server
More informationHuntsville City Schools
Huntsville City Schools 2012-13 Digital Initiative TekLinks and Partners Build New Infrastructure for Huntsville City Schools Huntsville, AL, School District unifies domain infrastructure and builds out
More informationPASADENA AREA COMMUNITY COLLEGE DISTRICT 1570 E. COLORADO BLVD. PASADENA, CALIFORNIA 91106-2003 RFP160001 MICROSOFT SYSTEMS CENTER INTERGRATION
PASADENA AREA COMMUNITY COLLEGE DISTRICT 1570 E. COLORADO BLVD. PASADENA, CALIFORNIA 91106-2003 MICROSOFT SYSTEMS CENTER INTERGRATION Addendum # 1 April 28, 2016 Page 1 of 9 The following information is
More informationIT Assessment Report. Prepared by: Date: BRI Works www.bri.works 321 East Main Street, Suite 200 Charlottesville VA 22902 434.951.
IT Assessment Report Prepared by: Date: BRI Works www.bri.works 321 East Main Street, Suite 200 Charlottesville VA 22902 434.951.7979 Table of Contents Executive Summary 3 IT Summary 3 Assessment Goal
More informationIT Solutions Savings through Sm@rt IT
IT Solutions Savings through Sm@rt IT Business Success Your most important asset and the key to business success is your people, never more so than in tough economic times. Smart Computers and Consulting
More informationCloud Computing Thunder and Lightning on Your Horizon?
Cloud Computing Thunder and Lightning on Your Horizon? Overview As organizations automate more and more of their manual processes, the Internet is increasingly becoming an important tool in the delivery
More informationDetermine dates with you telecom suppliers so that the new office is online before your move for both Phones and Data connections.
IT Office Move - Tips and Check List: Office IT Move Plan Introduction: If you are moving to a New Office and/or Data Center (Cloud), or if this is also a Colocation exercise please note this is a basic
More informationServer Infrastructure Upgrade Proposal
October 2011 Proposal approved and funded August 2012 Equipment fully implemented Information Systems Department Server Infrastructure Upgrade Proposal September 23, 2011 Prepared by: Kevin Stiles, Network
More informationRAS Associates, Inc. Systems Development Proposal. Scott Klarman. March 15, 2009
Systems Development Proposal Scott Klarman March 15, 2009 Systems Development Proposal Page 2 Planning Objective: RAS Associates will be working to acquire a second location in Detroit to add to their
More informationCompulink Advantage Cloud sm Software Installation, Configuration, and Performance Guide for Windows
Compulink Advantage Cloud sm Software Installation, Configuration, and Performance Guide for Windows Compulink Business Systems, Inc. 2645 Townsgate Road, Suite 200 Westlake Village, CA 91361 2013 Compulink
More informationNetwork Bandwidth and Infrastructure Study Report EXECUTIVE SUMMARY
Network Bandwidth and Infrastructure Study Report EXECUTIVE SUMMARY Purpose of Report: To provide to the School Board information regarding the Sioux Falls School District s network bandwidth usage and
More informationMilsoft IVR SIP Upgrade (Virtual Server) Presented by George Buckner (Central Florida Electric Cooperative, Inc.)
Milsoft IVR SIP Upgrade (Virtual Server) Presented by George Buckner (Central Florida Electric Cooperative, Inc.) Central Florida Electric Cooperative, Inc. Headquarters: Chiefland, FL Active Services:
More informationRequest for Proposals: Systems Replacement & Cloud Services. April 19, 2012
Request for Proposals: Systems Replacement & Cloud Services April 19, 2012 American Association of Family & Consumer Sciences 400 N. Columbus Street Suite 202 Alexandria, VA 22314 Phone: 703.706.4600 Table
More informationCurrent/Future /Long Term. Project Name. Intrusion Detection. LAN POE Switch Rollout. Interactive Board Rollout. Laptop Cart Trial
Project Name Intrusion Detection Wireless Rollout LAN POE Switch Rollout Interactive Board Rollout Document Cameras Laptop Carts Laptop Cart Trial 3D Printing Tech Rollout Bridgeport Univ - (Special Needs
More informationNetwork Status Review University of Moratuwa. Mr. Nadeesha Ranaweera (Systems Engineer, Center for IT Services)
Network Status Review University of Moratuwa Mr. Nadeesha Ranaweera (Systems Engineer, Center for IT Services) Introduction Center for Information Technology Enabled Services (CITeS) is the responsible
More informationADDENDUM NO. 03 August 22, 2014
ADDENDUM NO. 03 August 22, 2014 The following changes, additions, deletions or corrections shall become a part of the Contract Documents dated, July 22, 2014 for the RFP named below and all other conditions
More informationCitizen Machinery UK Ltd
JOB TITLE IT Support Engineer REPORTING TO European Business Systems Manager JOB PURPOSE Citizen Machinery UK Ltd is the Western Europe sales and support hub for the market leading ranges of Cincom sliding
More informationVoIP SYSTEM REQUEST FOR PROPOSAL QUESTIONS POSED BY VENDORS AS OF JUNE 23, 2014
1. With Respect to the paging at several locations, exactly how many paging speakers/horns are needed? a. There is one in each swimming pool. By location the breakdown is as follows: i. 1600 Brown 1 ii.
More informationRequest for Proposal
January 30, 2015 Form 470 Application#: 559990001327506 BREITUNG TOWNSHIP SCHOOL DISTRICT 2000 Pyle Drive Kingsford, MI 49802 906-779-2650 WIFI in Classrooms Project NOTICE OF BIDDERS The Breitung Township
More informationWarner CNR Computer Desktop Support Policy
Warner CNR Computer Desktop Support Policy Documentation Date: November, 2013 The Natural Resources Computing and Network Services (NRCNS) goal is to provide, support and encourage efficient and safe use
More information- Brazoria County on coast the north west edge gulf, population of 330,242
TAGITM Presentation April 30 th 2:00 3:00 slot 50 minutes lecture 10 minutes Q&A responses History/Network core upgrade Session Outline of how Brazoria County implemented a virtualized platform with a
More informationNetwork Attached Storage Common Configuration for Entry-Level
Common Configuration for Entry-Level ATTACHMENT VI Product Attribute Entry Level -- Description RFI Response Main Memory (Base): 4 Internal Storage Controller: Fiber Channel RAID Controller: Dual redundant
More informationPROTECTION AND SYSTEM MAINTENANCE COMPUTER AND COMUNICATION SYSTEM OF EXECUTIVE COUNCIL OF AUTONOMOUS PROVINCE OF VOJVODINA.
PROTECTION AND SYSTEM MAINTENANCE COMPUTER AND COMUNICATION SYSTEM OF EXECUTIVE COUNCIL OF AUTONOMOUS PROVINCE OF VOJVODINA Milan Paroški 1, Nenad Petrović, Rade Ćirić 2 1 Provincial Authorities Administrative
More informationINTRODUCTION TO NETGUARD
TECHNICAL HANDBOOK Table of Contents Introduction to NetGuard...2 Terminology...3 Network Options...4 Server Specifications...6 PC Specifications...6 Switch Specifications...6 Software Requirements...7
More informationOPM. Dell Laptop Docking Station Lenovo Thinkpad Mini-Dock 3 4337
OPM Room: Harbormaster Office Mfgr Model # Switchboard Phone Vodavi Starplus Triad TR9015-71 Computer Monitor Asus VE248 Computer Keyboard Dell Laptop Docking Station Lenovo Thinkpad Mini-Dock 3 4337 Room:
More informationWORKSHOP SYSTEM REQUIREMENTS & GUIDELINES CONTENTS
WORKSHOP SYSTEM REQUIREMENTS & GUIDELINES VIDA IN 2015, PEER-TO-PEER INFRASTRUCTURE CONTENTS 1 INTRODUCTION... 3 2 VIDA IN 2015... 4 2.1 Timeline... 4 3 REQUIREMENT DETAILS... 5 3.1 VIDA requirements...
More informationIndustrial Security for Process Automation
Industrial Security for Process Automation SPACe 2012 Siemens Process Automation Conference Why is Industrial Security so important? Industrial security is all about protecting automation systems and critical
More informationThe I.T. Experience Service and Pricing List 2015
The I.T. Experience Service and Pricing List 2015 Hourly Rates and Additional Services Residential Hourly Rate Hourly Rate All Services $59.00/hr. Business Hourly Rate Hourly Rate All Services $85.00/hr.
More informationDell Open Manage System Administrator (Free software to manage and maintain your server hardware) Hardware Dell PowerEdge T320 or R320
Greenway PrimeSUITE Overview This document is to be used only as a guideline when considering hardware for use with PrimeSUITE. All server and workstation specs are Dell hardware, MDS Medical's preferred
More informationService Catalog. Office of Information Technology Lenoir-Rhyne University
Service Catalog Office of Information Technology Lenoir-Rhyne University Updated July 28, 2014 Service Catalog Communication and Collaboration Campus Cable Television Service Campus Telephone Service (Nortel,
More informationStatement of Work RFP-DF-96217 Virtual Desktop Infrastructure
Statement of Work RFP-DF-96217 Virtual Desktop Infrastructure 1.0 Introduction Colorado Springs Utilities (UTILITIES) desires to contract with a reputable firm for the purchase and implementation of a
More informationConnect With Axiom www.connectwithaxiom.com 866-708-7998
Business Solutions Information Technology High-Speed Broadband Connect With Axiom OUR GOAL To provide the highest quality Broadband Internet Services to the unserved Homes and Businesses of Washington
More informationSagari Ltd. Service Catalogue and Service Level Agreement For Outsource IT Services
Sagari Ltd Service Catalogue and Service Level Agreement For Outsource IT Services Managed Services Service Level Agreement 1 Introduction This Service Catalogue and Service Level Agreement (SLA) constitutes
More informationInformation Technology Mission Statement. Information Technology Goals
Ionia County Information Technology Strategic Plan 2008-2013 Table of Contents Information Technology Mission 3 Information Technology Goals 3 Current Network Overview 4-5 Information Technology Focus
More informationGaLIX NETWORKING Pty Ltd YOUR TRUSTED PARTNER IN NETWORK SERVICES
CORPORATE PROFILE GaLIX NETWORKING Pty Ltd YOUR TRUSTED PARTNER IN NETWORK SERVICES Galix Networking (Pty) Ltd PO Box 3070, Cresta, Gauteng, 2118 Http://www.galix.com info@galix.com Telephone: +27 86 1
More informationLevittown Public Schools Information Technology 2015-2016 Proposed Budget
Levittown Public Schools Information Technology 205-206 Proposed Budget Presentation to the Board of Education Todd Connell, Director of IT February 4 th, 205 Servers/ Storage/ Backup Instructional Equipment
More informationData Network Security Policy
Authors: Mike Smith Rod Makosch Network Manager Data Security Officer IM&T IM&T Version No : 1 Approval Date: March 2005 Approved by : John Aird Director of IM&T Review Date : 1 April 2006 Trust Ref: C7/2005
More informationUpdated 7/02/2012 Infrastructure Opportunity Map
Updated 7/02/2012 Opportunity Map s Other Personnel Productivity DataCenter Plan UPS and GEN Laptop Encryption Client Domino E-Mail IMS Version 11 POP Server IT Asset Windows 7 OS Migration Good Technology
More information* * * AGENDA TRANSMITTAL FORM * * *
MONTEREY REGIONAL WATER POLLUTION CONTROL AGENCY * * * AGENDA TRANSMITTAL FORM * * * MEETING DATE: SEPTEMBER 28, 2015 AGENDA ITEM: AGENDA TITLE: 6 H APPROVE CONTRACT FOR RTP NETWORK CENTER CONSOLIDATION
More informationMAYA ANGELOU PUBLIC CHARTER SCHOOL
MAYA ANGELOU PUBLIC CHARTER SCHOOL REQUEST FOR PROPOSAL For RFP FY16 School Network Infrastructure 1. Overview Maya Angelou Public Charter School (the School ) is a Public Charter School operating in Northeast
More informationIT Setup Services IT SUPPORT SERVICES
IT Setup Services Investing in a server-run network represents a substantial investment in your business, with average costs running from $2,500 to $10,000. To help determine if this is an effective step
More informationMOUNTAIN EMPIRE UNIFIED SCHOOL DISTRICT REQUEST FOR PROPOSAL
MOUNTAIN EMPIRE UNIFIED SCHOOL DISTRICT REQUEST FOR PROPOSAL VOIP Communication System E-Rate Funding Year 2016 RFP No. 1004 Submittals due on or before: 3PM on January 15th, 2016 ATTN: Rob Foraker Information
More informationRFQ 12-21 IT Services. Questions and Answers
RFQ 12-21 IT Services Questions and Answers Question # 1: Just to clarify and I am more than certain that this is just a typo, but the due date for the submission of the IT Services RFP is January 7, 2013,
More informationPlanning Process and Methodology
Executive Summary Our mission is to provide students and staff with technology to meet their instructional and administrative needs. This incorporates all aspects of technology including networking, end
More informationCURRICULUM Based on guidelines from the State, developed by Subject Area Committees
CURRICULUM Based on guidelines from the State, developed by Subject Area Committees 78 INSTRUCTION How we deliver the curriculum to students TECHNOLOGY Tools to deliver and enhance instruction, and support
More informationThe Portable Datacenter R E F E R E N C E A R C H I T E C T U R E
R E F E R E N C E A R C H I T E C T U R E Contents Introduction...1 Portable Datacenter Requirements...1 Solution Implementation...2 Physical System Layout...2 Hardware...3 Management Case...3 Virtualization
More informationREQUEST FOR PROPOSALS INFORMATION TECHNOLOGY MANAGEMENT SERVICES AT THE SYRACUSE HANCOCK INTERNATIONAL AIRPORT
SYRACUSE REGIONAL AIRPORT AUTHORITY REQUEST FOR PROPOSALS INFORMATION TECHNOLOGY MANAGEMENT SERVICES AT THE SYRACUSE HANCOCK INTERNATIONAL AIRPORT RFP Reference 03-2014 SYRACUSE, NEW YORK ADDENDUM # 2
More informationAddendum No. 1 to Packet No. 28-13 Enterprise Data Storage Solution and Strategy for the Ingham County MIS Department
Addendum No. 1 to Packet No. 28-13 Enterprise Data Storage Solution and Strategy for the Ingham County MIS Department The following clarifications, modifications and/or revisions to the above project shall
More information2013-2016. Three Year District Technology Plan. Pasco School District #1 July 1, 2013 to June 30, 2016
2013-2016 Three Year District Technology Plan Pasco School District #1 July 1, 2013 to June 30, 2016 Development History August 2012 November 2012 December 2012 December 2012 February 2013 March 2013 April
More informationProject Scope Statement
Project Scope Statement Project Name: Going Digital Department: Information Technology Department/Operations Department Project Manager: Colby Clark, Director of Information Technology Date: January 17,
More informationhttp://www.usac.org/sl/applicants/beforeyoubegin/eligible-services/priority-one.aspx
Coronado Unified School District RFP# 2012-02 Addendum - Wide Area Network Lease Contractor shall indicate on Carrier Proposal Form that Addendum #1 issued on November 10, 2012 and Addendum #2 issued on
More informationInformation Technology Standards Document
Information Technology Standards Document The Information Technology Standards Policy lists all technologies supported by the organization and serves as a guideline for all technology purchasing and use
More informationEnterprise Backup Solution Vendor Questions
Enterprise Backup Solution Vendor Questions What is the size of a single full back up? If Backups comprise 28% of the 19TB, can we assume that a single full (not compressed) is approximately 6TB? The approximate
More informationGigabit Passive Optical
Gigabit Passive Optical Networks Joseph E. Ford, RCDD Systems Specialist Bruce D. Osborn, RCDD Systems Specialist Bala Consulting Engineers, Inc. 1 Overview 2 2 Background 3 GPON Architecture 4 Infrast.
More informationHP E-PCM Plus Network Management Software Series
Data sheet Product overview HP E-PCM Plus Network Management is a Microsoft Windows -based network management platform that enables mapping, configuration, and monitoring. HP PCM Plus provides security
More informationInformation Technology Services in UB Owned, Controlled and Managed Space
Information Technology Services in UB Owned, Controlled and Managed Space Category: Information Technology Date Established: 5/2/2014 Responsible Office: VPCIO Date Last Revised: 8/14/2014 Responsible
More informationNEWSTAR ENTERPRISE and NEWSTAR Sales System Requirements
NEWSTAR ENTERPRISE and NEWSTAR Sales System Requirements July 21 st, 2014 Page 1 of 7 NEWSTAR Enterprise ( NSE ) and NEWSTAR Sales ( NSS ) on SQL Note: To determine the number of users, add the number
More informationPart-1: SERVER AND PC
Part-1: SERVER AND PC Item Item Details Manufacturer Quantity Unit Price Total Dell server or equivalent Intel Xeon E5-2420 1.90GHz, 15M Cache, 7.2GT/s QPI, Turbo, 6C, 95W or equivalent PCIE Riser for
More informationProven Technical and Management skills over a career spanning more than 10 years. Brunswick Vic 3056 Australia
Resume: Michael McNab Systems Administrator and Web Support Proven Technical and Management skills over a career spanning more than 10 years Name: Address: Phone: Email Address: Website: Michael McNab
More informationERP Infrastructure Guide APPENDIX B
ERP Infrastructure Guide APPENDIX B for State of Georgia State Road and Tollway Authority 47 Trinity Avenue, SW Atlanta, GA 30334 June 2013 Updated by: Updated on: Description of Update: Revision # DRY
More information5. Infrastructure, Hardware, Software, & Technical Support
5. Infrastructure, Hardware, Software, & Technical Support 5 A & B: Current District Hardware Existing hardware and electronic resources at each of our sites is included in Component 3a: Current Technology
More informationK1 Internet Service Fast, qualified and individual Management of your hosting.
K1 Internet Service Fast, qualified and individual Management of your hosting. The company: K1 Internet Service is the affiliated company of the Hanno Kirchhoff EDV Beratung GmbH, which provides IT consulting
More informationFaculty Curriculum Development Workstation Replacement
Technology Objectives 2005-2006 Objective 1 Student Workstation Replacement & Cascading Plan, evaluate, and recommend student workstation replacement to keep student computer equipment up-to-date in 06-07.
More informationCompulink Advantage Online TM
Compulink Advantage Online TM COMPULINK ADVANTAGE ONLINE TM INSTALLATION, CONFIGURATION AND PERFORMANCE GUIDE FOR WINDOWS (Revised 07/08/2011) 2011 Compulink Business Systems, Inc. All rights reserved
More information