Seminar on Challenges in Procurement and Contracting in Large Hydropower Projects
|
|
|
- Herbert Blake Jenkins
- 9 years ago
- Views:
Transcription
1 Seminar on Challenges in Procurement and Contracting in Large Hydropower Projects (Wednesday June 13, IFC Auditorium, Washington DC) Session 1 The Vision of a Consultant Jean BINQUET, Tractebel Engineering France Coyne et Bellier
2 Slide 2 Introduction General Contracting the construction of a large HPP is always challenging for all stakeholders (the Owner, Lenders, and the Contractors): - Projects are big with respect to the Assets of the Owner and balance sheets of the stakeholders - Projects are often vital for the national economy - Projects are risky by nature (environment, socio-economy, physical data, etc.) Challenges in Procurement/Contracting? - Procurement/Contracting proper, and/or - Steps prior to the Procurement leading to the Project s Implementation
3 Slide 3 Introduction General What is a successful Contracting? performance, time and cost as close as possible to the expected values The success of a Project is the success of all stakeholders and not of one against the others: - Same boat concept - Solution Finding using Value Engineering and Open Mind Approach under the contract provisions - Being lucid when serious difficulties arise and evaluate with fairness
4 Slide 4 Introduction General Two Points: - EPC or not EPC - Steps leading to the Procurement: as important or even more important than the Procurement itself to; the Ethiopian Way
5 Slide 5 EPC or Not EPC First large hydropower projects implementation using EPC Contract started in the Nineties Linked to the development of the Private Sector in hydropower generation Now current practice for hydropower projects implementation for both Public & Private Sectors Our firm involved in more than 20 large projects around the world: Turkey, Uganda, Gabon, Ghana, Ethiopia, Brazil, Argentine, India, Nigeria, Ecuador, Peru, etc. with a total installed capacity of around 17,000 MW
6 Slide 6 EPC or not EPC Extensively used by Private Developers in regions where IPPs are very active (imposed by senior debts lenders): Latin America, Turkey, India, Laos, etc. Starting to be used in some other countries by Public Utilities especially in Africa (e.g. Ethiopia, Gabon, Ghana, Senegal, Cameroun, Nigeria, etc.) but also in Latin America (Ecuador, Venezuela), etc.
7 Slide 7 EPC or not EPC Manufacturing a product with a given Performance, in a given Time for Completion and for a fixed Price This is, in principle: - Simplifying the job of the Owner (no design, no coordination) and - Reducing (eliminating) most of the classical Employer s risks linked to the Construction (design, local physical data like hydrology, geology, topography, gaps between various types of works, etc.) transferred to and to be borne by the Contractor Are all hydropower projects suitable for EPC type Contracts where Construction Risks are transferred to the Contractor?
8 Slide 8 EPC or not EPC The Answer is NO: - There are projects where it is not possible for several reasons to have an understanding of the site conditions (complex geology and high rock cover above headrace tunnel for example): The possible unforeseen cannot be assessed/estimated and priced even in an approximate manner the real/actual unforeseen can only possibly be borne by large Utilities who are able to mutualize the risks with other projects with lower risks - On the contrary there are projects where it is possible to understand the site conditions and to assess the possible unforeseen : This assessment can be discussed between the Owner and Employer and risks fairly shared. The EPC Contract Price will, as a result, be lower and the construction will be successful
9 Slide 9 EPC or not EPC As a consequence, don t use EPC type Contracts in exceptional risks situation (no understanding of the site conditions we have no idea of the possible unforeseen ) In other situations elaborate a sound sharing mechanism of the risks between the various stakeholders taking into account their capacity to absorb them
10 Slide 10 Example: 390 MW Dul Hasti Project in India Turnkey Contract: - 70 m high dam, 10 km long Headrace straight alignment Tunnel (8.0 m dia.) and underground powerhouse complex - 5 years construction time - Fixed price except in fossil valley (300 m long) Reality: - Graben much wider and deeper than Fossil Valley and filled with silty sand with 400 m of water head above the tunnel; crossing considered as almost not feasible - Geology generally much more complex than anticipated - Loop alignment invented for the tunnel to avoid graben - Serious conflicts between Owner and Contractor led to the change of the Civil Works member - Time for Construction of 15 years and final cost several times the original EPC Contract Price
11 Slide 11 Example: 390 MW Dul Hasti Project in India Conclusions: - Exceptional case in terms of geological conditions, long tunnel with high rock cover (more than 1,500 m), no intermediate window, very active seismo-tectonic area, etc. - Overall failure regarding the fixed Time for Completion and Cost - Actual Time for Completion and Cost more than 3 times the original - EPC type contract is one of the major reason of this Failure
12 Slide 12 Example: 672 MW Birecik Project in Turkey Turnkey Contract: - 70 m high dam 2.5 km long, 6 Units dam toe powerhouse, 18,000 m3/s gated spillway - Alluvial deposits over limestone rock foundation with heavy grouting works - Thorough joint preparation of the design between Owner s Engineer and Contractor before Contract conclusion - 5 years Construction Time Reality: - Some adverse geological conditions in some areas compensated by better conditions in other areas. No impact on cost and time - 5 years Construction Time
13 Slide 13 Example: 672 MW Birecik Project in Turkey Conclusions: - Simple overall geological features - Well prepared Contract - EPC type contract was a success (time, performance and cost respected) - EPC type of Contract well adapted to this type of Project and context
14 Slide 14 Example: 450 MW Cana Brava Project in Brazil Simple overall geological features Well prepared Contract EPC type contract was a success (commissioning ahead of schedule, performance and cost respected) EPC type of Contract well adapted to this type of Project and context
15 Slide 15 Examples: ongoing Projects in Ethiopia, Nigeria, Ecuador, etc. Turnkey Contracts - FIDIC Silver (1,870 MW Gibe III in Ethiopia, 700 MW Zungeru in Nigeria, etc.) or other specially developed contract (1,500 MW Coca Codo Sinclair in Ecuador) - Sufficiency of Tender - Sufficiency of the Contract Price - No adjustment of the Contract Price and Time for Completion in case of unforeseen difficulties (Fidic 4.12) - Some exceptions introduced which give the right to an Extension of the Time for Completion without any cost compensation - Exceptions may include special geological or geotechnical features like low mechanical properties materials, water ingress, heavily fractured rocks in faults with high water heads, high at-rest initial state of stress, etc.
16 Slide 16 Steps prior to the Procurement: the Ethiopian Way Ordinary Way: - Master Planning, Prefeasibility Studies, Feasibility, EIS, EIA, Financing Preparation, Final Design and Tendering for Construction, Selection of Consultants at each stage, etc to 20 years are necessary to achieve this process completely and reach the first m3 of excavation when it works; sometimes it doesn t works The Ethiopian Way: - Select a Strategic Partner who prepares the ground (investigations, designs, etc.) leading to an EPC Contract - Engage the EPC Contract with partial financing - Once the Project is engaged, complementary financing is found and project can be completed - Less than one year was required to start Gilgel Gibe II, Beles, Gibe III and Grand Renaissance (9,000 MW in total) - GGII and Beles (1,000 MW) in operation and Gibe III (1,870 MW) should be completed in the next 1.5 year.
17 Slide 17 Concluding Remarks We have known successes and failures with EPC Contracts for Hydropower Projects Success occurs when general physical conditions are simple and/or understood If it is not the case special risks allocation to be introduced to limit the risks to be borne by the Contractor in case of encountering specially adverse unforeseen conditions Projects with long tunnels, high rock cover, no intermediate windows and in very active seismo-tectonic areas are not recommended for EPC Contracts (without risks allocation)
18 Slide 18 Concluding Remarks Steps prior to the Procurement Process are tedious and extremely long (not adapted to the present needs of development) Often the process leads to a deadlock The Ethiopian Way which requires a strong political willingness may not be ideal but proved efficient and deserves attention and consideration There is the need of fast track approaches for hydropower projects in emerging economy countries
19 Slide 19 Thank you for your attention
National Electric Power Regulatory Authority
National Electric Power Regulatory Authority MECHANISM FOR DETERMINATION OF TARIFF FOR HYDROPOWER PROJECTS Preamble Conservative estimates show total hydroelectric potential in the country to be 45000
Hydropower in Rwanda: Ongoing Initiatives & New Investment Opportunities. Yves Muyange Director General Energy Water & Sanitation Authority
Hydropower in Rwanda: Ongoing Initiatives & New Investment Opportunities Yves Muyange Director General Energy Water & Sanitation Authority Rwanda: A Thousand hills between the two Major Drainage Basins
Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.
Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr. Civil Engineer Public Power Corporation, Greece Public Power Corporation
Infrastructure Planning and Management. Phases of an Infrastructure Project
Infrastructure Planning and Management Phases of an Infrastructure Project Agenda Talking about the various phases in an infrastructure project Introduction to the Infrastructure Process Infrastructure
Preliminary damage survey report on 2015 Nepal Gorkha Earthquake
Tokyo, 13 May 2015 Preliminary damage survey report on 2015 Nepal Gorkha Earthquake Pokhrel R.M., Chiaro G., Kiyota T., Katagiri T. Institute of Industrial Science, University of Tokyo, Japan Goda K. Bristol
A Conceptual Methodology and Practical Guidelines for Managing Data and Documents on Hydroelectric Projects
A Conceptual Methodology and Practical Guidelines for Managing Data and Documents on Hydroelectric Projects Alan Hodgkinson SoftXS GmbH Alpensrasse 14 CH-6300 Zug Switzerland Joseph J Kaelin Pöyry Infra
STUDENT GUIDE GEOLOGICAL ENGINEERING University of British Columbia 2013-2014
STUDENT GUIDE GEOLOGICAL ENGINEERING University of British Columbia 2013-2014 Introduction The purpose of this guide is to give you information about the structure and course requirements in the Geological
A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM
A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM Giang Pham Hong, Michel Hotakhanh, Nga Pham Hong, Hoai Nam Nguyen, Abstract:Dams have been taken an important role in time and surface redistribution of water for
Developing a Public-Private Partnership Framework: Policies and PPP Units
Note 4 May 2012 Developing a Public-Private Partnership Framework: Policies and PPP Units This note is the fourth in a series of notes on developing a comprehensive policy, legal, and institution framework
Railway Development in Ethiopia
Ethiopian Railways Corporation (ERC) Railway Development in Ethiopia Yehualaeshet Jemere (MSc. CEng) Addis Ababa-Djibouti Railway Project Manager Railway Development in Ethiopia Introduction National Railway
Consulting Boards for Large Civil Engineering Projects
Consulting Boards for Large Civil Engineering Projects Evert Hoek and Alan S. Imrie Published in Water Power and Dam Construction, Vol. 47, No. 8, pp 33-34, August 1995. Consulting Boards for Large Civil
The FIDIC Suite of Contracts
Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October
Project Layout & Design Features of the Project
Project Layout & Design Features of the Project 1 PROJECT LAYOUT DRI DAM DRI DAM TOE P/H U/G POWER HOUSE COMPLEX DRI DAM TOE POWER HOUSE TANGON DAM TOE POWER HOUSE TOTAL 3070 MW 19.60 MW 7.40 MW 3097 MW
Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee
FIDIC Conditions of Contract IBC Conference 2003 Presentation Notes on: OVERVIEW OF THE NEW MAJOR CONTRACTS Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman
Foreign Corrupt Practices Act (FCPA)/Bribery Act Integrity Due-Diligence & Investigations
Foreign Corrupt Practices Act (FCPA)/Bribery Act Integrity Due-Diligence & Investigations Clarity in a complex world www.mintzgroup.com How We Work: Because the reputations of companies and individuals
Gibe III won t affect Kenya: Ambassador
1870 MW January 2012 Volume IV Merry X-mass Gibe III won t affect Kenya: Ambassador Happy Ethiopian Epiphany The Ethiopian Herald on its issue on December 16, 2011 posted an interview with The Kenyan Ambassador
(1) risks should be allocated to the party that is in the position to control them and
Risk allocation in the FIDIC Conditions of Contract (1999) for Construction (Red Book) and the FIDIC Conditions of Contract (1999) for EPC/Turnkey Projects (Silver Book) from the perspective of a German
World Bank Guarantee Program
World Bank Guarantee Program for the Consultation of Modernizing the World Bank s Operational Policy on Guarantees January 2012 Why World Bank Guarantees? Guarantees are viewed as a key financial instrument
Resume. Thom L. Neff, PhD, President OckhamKonsult: Strategic Infrastructure Management Consulting. 21 Beacon Street tompino38@gmail.
Resume Thom L. Neff, PhD, President OckhamKonsult: Strategic Infrastructure Management Consulting 21 Beacon Street [email protected] Suite 5 I 617 320 9936 (mob) Boston MA 02108 B.S Civil Engineering
OVERCOMING CHALLENGES ON A FAST TRACK ASH POND CONVERSION AND CLOSURE PROJECT TO MEET REGULATORY DEADLINES 2013 WORLD OF COAL ASH CONFERENCE
OVERCOMING CHALLENGES ON A FAST TRACK ASH POND CONVERSION AND CLOSURE PROJECT TO MEET REGULATORY DEADLINES 2013 WORLD OF COAL ASH CONFERENCE Presenters: Jimmy Mullins (TVA) David Mason (CDM Smith) April
THE REGULATORY FRAMEWORK FOR SOLID MINERALS DEVELOPMENT IN NIGERIA
1 THE REGULATORY FRAMEWORK FOR SOLID MINERALS DEVELOPMENT IN NIGERIA Gbite Adeniji [email protected] June 20, 2008 INTRODUCTION I FEATURES OF A MINING PROJECT 2 Activity Duration Cost (USD) Greenfield
Developing Securities Markets in East Africa: Challenging, but Well Worth the Effort
NOVEMBER 2010 ABOUT THE AUTHORS GRACE KIBUTHU ([email protected]) is an Associate Operations Officer for Global Capital Markets Development, based in Nairobi, Kenya. Prior to joining IFC, she worked for
Alstom Transport supplier of Tram Systems in PPP schemes
Alstom Transport supplier of Tram Systems in PPP schemes Arnaud de Monts 04/04/2014 Various procurement schemes A tramway system can be procured in various schemes, each of them have been experimented
AEG-ASCE SHORT COURSE
AEG-ASCE SHORT COURSE TUNNELS THROUGH FAULT ROCKS AND TECTONIC MELANGES May 31 and June 1, 2002 Gunter Riedmueller and Wulf Schubert Course Outline! Introduction! Characterization and Classification! Investigation!
Technical Consultant
Terms of Reference Technical Consultant Providing services in the framework of a Study for Rehabilitation of Zemo Samgori Irrigation System, Georgie (ref. ORIO13/GE/01) Introduction The Ministry of Agriculture
TBMs for Norwegian Hydropower projects. Sindre Log The Robbins Company
TBMs for Norwegian Hydropower projects Sindre Log The Robbins Company Who am I? Sindre Log M.Sc. Civil engineering, NTNU Specializations in tunneling, geology and Project management Working out of Oslo,
Lecture 4. Tunneling Through Fault Zones and Melanges
Lecture 4 Tunneling Through Fault Zones and Melanges BIMROCKS SHORT COURSE Dr. Edmund Medley Consulting Geological Engineer, Belmont, California, USA [email protected] Geological Engineering Department,
Feasibility Study Mzimvubu Water Project
Feasibility Study Mzimvubu Water Project Newsletter 2/September 2013 Activities and Achievements to Date A Detailed Feasibility Study is underway in the Eastern Cape to investigate a potential site for
Your Access to a World of Global Connectivity. www.nevigate.net
Your Access to a World of Global Connectivity Agenda Company Background / Profile Our Commitment Coverage Strengths Products Portfolio Deliverables Measurable Benefits Support Company Background Nevigate
Constructing globally. dams
Constructing globally dams WITH RCC (roller compacted concrete) placement ongoing at the 1.6 million m 3, 173 m high Ayvali Dam, and construction recently started at the 70 m high Kotanli Dam, both in
Assessment of hydropower resources
Assessment of hydropower resources Oliver Froend Assessment of hydropower resources Relevance of surveys, data assessment and analyses to the success of the project. Required data and field survey. Key
Establishing the feasibility of your proposed mining venture
RUPPRECHT, S. Establishing the feasibility of your proposed mining venture. International Platinum Conference Platinum Adding Value, The South African Institute of Mining and Metallurgy, 2004. Establishing
Access to Financial Services in Developing Countries: Identification of Obstacles. Liliana Rojas-Suárez July 2006
Access to Financial Services in Developing Countries: Identification of Obstacles Liliana Rojas-Suárez July 2006 Background Even though banks are the most important providers of financial services Evolution
THE RELATIONSHIP BETWEEN THE CLIENT, CLIENTS PROJECT TEAM AND THE EPCM PROJECT TEAM. Mr C. A. F. Sweet The South Institute of Mining and Metallurgy
THE RELATIONSHIP BETWEEN THE CLIENT, CLIENTS PROJECT TEAM AND THE EPCM PROJECT TEAM Mr C. A. F. Sweet The South Institute of Mining and Metallurgy The inter-relationship between these parties and the effect
Feasibility. A guide to feasibility planning for junior mining companies
Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Feasibility A guide to feasibility planning for junior mining companies
Analytical Approach for Cost Estimation of Low Head Small Hydro Power Schemes
Analytical Approach for Cost Estimation of Low Head Small Hydro Power Schemes S.K. Singal and R.P. Saini Alternate Hydro Energy Centre, Indian Institute of Technology, Roorkee, India Email : [email protected]
STUDENT GUIDE GEOLOGICAL ENGINEERING University of British Columbia 2014-2015
STUDENT GUIDE GEOLOGICAL ENGINEERING University of British Columbia 2014-2015 Introduction The purpose of this guide is to give you information about the structure and course requirements in the Geological
Corporate Risk Management Policy
Corporate Risk Management Policy Managing the Risk and Realising the Opportunity www.reading.gov.uk Risk Management is Good Management Page 1 of 19 Contents 1. Our Risk Management Vision 3 2. Introduction
Private Healthcare. How To Apply For IFC Financing About IFC CREATING OPPORTUNITY IN EMERGING MARKETS
How To Apply For IFC Financing About IFC A company or entrepreneur seeking to establish a new health project or expand an IFC, a member of the World Bank Group, is the largest global development existing
T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. PPP Modalities
PPP Modalities Types and characteristics of PPP are presented in several sections of the Toolkit: refer Types of PPP in Key Issues. This section provides some consideration of which modality, or which
The Follo Line Project
The Follo Line Project Longest. UrbAN. Complex. Faster. 2015/1 Norwegian National Rail Administration the follo line project 1 2 the follo line project The project The Follo Line Project is currently the
Railway Development in Ethiopia
Ethiopian Railways Corporation (ERC) Railway Development in Ethiopia November 2015, Rijswijk Yehualaeshet Jemere (MSc. CEng) Chief Officer, Construction and Project Execution Department Outline Introduction
ASSET. Unlock the power of your Digital Asset
Unlock the power of your Digital Asset What is the Digital Asset? The Digital Asset is the information core of every project and facility. It is the unification of the trusted information that flows through
Project Management for electrical Generation: Geothermal Energy in Combination with other Sources of Renewable Energy
Project Management for electrical Generation: Geothermal Energy in Combination with other Sources of Renewable Energy Rüdiger Pötter Business Line Manager Geothermal Pöyry Energy GmbH, Hamburg Global Experts
THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION
THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION GROUP 867 ARCHITECTURAL, ENGINEERING AND OTHER TECHNICAL SERVICES Excerpt from CPCprov-en-Publication.doc - United Nation Statistic Division Group Class Subclass
Member Nation Report 2010 from Denmark.
Member Nation Report 2010 from Denmark. The has during the year 2010 arranged 6 member meetings including two technical site visits. The first technical site visit covered the 5.3 km long Leipzig City
ASSET MANAGEMENT. solutions. smec.com
ASSET MANAGEMENT solutions smec.com About SMEC SMEC is a professional services firm with a global footprint that provides high-quality consultancy services on major infrastructure projects. With over 5,300
Appendix 1: Full Country Rankings
Appendix 1: Full Country Rankings Below please find the complete rankings of all 75 markets considered in the analysis. Rankings are broken into overall rankings and subsector rankings. Overall Renewable
Republic of Zambia OPPORTUNITIES IN THE ENERGY SECTOR IN ZAMBIA
Republic of Zambia OPPORTUNITIES IN THE ENERGY SECTOR IN ZAMBIA Presentation Outline COUNTRY PROFILE KEY POWER SECTOR PLAYERS OVERVIEW OF THE ENERGY SECTOR IN ZAMBIA ZAMBIA ENERGY SITUATION PRESENTLY RESULT
XAYABURI HYDRO POWER PLANT, LAO PDR
XAYABURI HYDRO POWER PLANT, LAO PDR BACKGROUND MATERIAL ON PÖYRY S ASSIGNMENT CONTENT About Pöyry Pöyry s hydropower competences, p. 4-6 Xayaburi hydropower plant project, p. 7-14 Pöyry s role in the project,
2012 Global Agency Compensation Survey. R3:JLB May 9, 2012
2012 Global Agency Compensation Survey R3:JLB May 9, 2012 Survey Method Online Survey fielded Feb, March 2012 Survey completed April 2012 71 ANA member responses, representing 60 different global companies
Seismic Design and Performance Criteria for Large Storage Dams
Seismic Design and Performance Criteria for Large Storage Dams Dr. Martin Wieland Chairman, ICOLD Committee on Seismic Aspects of Dam Design Poyry Switzerland Ltd., Zurich, Switzerland Integral Dam Safety
Design Guidelines for Sequential Excavations Method (SEM) Practices for Road Tunnels in the United States
Design Guidelines for Sequential Excavations Method (SEM) Practices for Road Tunnels in the United States Vojtech Gall Gall Zeidler Consultants, Ashburn, Virginia Nasri Munfah Parsons Brinckerhoff, New
Clean Development Mechanism Project Opportunities in Indonesia
Clean Development Mechanism Project Opportunities in Indonesia Pre-feasibility Report on a Micro Hydro Power CDM Project Center for Research on Material and Energy Institut Teknologi Bandung October 2002
Evaluation of Inquiries about the UIS Environmental Studies Online Master s Degree Program
Evaluation of Inquiries about the UIS Environmental Studies Online Master s Degree Program Lenore Killam Hung-Lung Wei Dennis R. Ruez, Jr. University of Illinois at Springfield Introduction The Department
GEOTECNA PROGETTI S.r.l. Design and Works Supervision Consulting Engineers. Italian engineering since 1972... www.geotecna.it
Design and Works Supervision Consulting Engineers Italian engineering since 1972... June 2014 GEOTECNA PROGETTI S.r.l. RIVA DEL GARDA (TN) - Via Alberto Lutti, 10 38066 RIVA DEL GARDA (TN) ITALIA [email protected]
Botswana Power Development! March 2015!
Botswana Power Development! March 2015! Power development business overview! Strong regional power demand underpinning business strategy " Independent power producers (IPPʼs) required to build new capacity"
Presentation of Grupo ACS. September 2009
Presentation of Grupo ACS September 2009 Strategic vision A global leader in infrastructure development In the fields of civil and industrial engineering activities With sustainable and profitable growing
Assessment of groundwater inflow into a metro tunnel (Ankara)
Géoline 25 Lyon, France 23 rd - 25 th, May/Mai 25 Assessment of groundwater inflow into a metro tunnel (Ankara) DOYURAN VEDAT Department of Geological Engineering, Middle East Technical University, 6531Ankara,
250348 - Bachelor's Thesis
Coordinating unit: 250 - ETSECCPB - Barcelona School of Civil Engineering Teaching unit: 250 - ETSECCPB - Barcelona School of Civil Engineering Academic year: Degree: 2012 BACHELOR'S DEGREE IN GEOLOGICAL
Emerson Job Description Matrix
S2 S3 S4 Job Family Support Support Support Job Level Grade Level Entry Grade 12 Intermediate Grade 13 Senior Grade 14 Aon Hewitt Job Characteristic Definitions and Descriptions Responsible for the delivery
SPEAKER EBOOK. Some of our key speakers share their thoughts, concerns and expectations for the market leading up to the conference
SPEAKER EBOOK Some of our key speakers share their thoughts, concerns and expectations for the market leading up to the conference Discover what these key names have said about the market inside: Jose
6 STEP 6 - PREPARING THE ACTION PLAN 2
CONTENTS 6 STEP 6 - PREPARING THE ACTION PLAN 2 6.1 USER GUIDE TO THIS STEP 2 6.2 KEY MESSAGES OF THIS STEP 4 6.3 PREPARING THE ACTION PLAN 5 6.4 PRE-FEASIBILITY STUDY 8 6.5 PREPARING AN INVESTMENT PLAN
Emerging Markets Value Stock Fund
SUMMARY PROSPECTUS PRIJX March 1, 2016 T. Rowe Price Emerging Markets Value Stock Fund A fund seeking long-term growth of capital through investments in undervalued stocks of companies in emerging market
Striving for Good Governance in Africa
Striving for Good Governance in Africa This presentation will: Introduce the ECA project Measuring and Monitoring Progress towards good governance in Africa Present a synopsis of the Africa Governance
All of these circumstances indicate that the world of tomorrow is as different as today s water utility business is from that of yesteryear.
EXECUTIVE SUMMARY PROJECT OVERVIEW Why Should We Invest in Strategic Planning? Strategic planning is a set of intentions expressed as a plan. The plan turns the intentions into reality by focusing on the
5O&M. new trends in onshore wind
5O&M new trends in onshore wind Five new trends in onshore wind O&M This report analyses trends in the way operations and maintenance (O&M) of European onshore wind farms is procured and undertaken. It
What is geotechnical risk?
1 MANAGING GEOTECHNICAL RISK Dr David Cathie, Cathie Associates What is geotechnical risk? The saying "ignorance is bliss" applies well to geotechnical problems. Out of sight, out of mind often applies
Sub-sea tunnels and lake taps in Norway - a short overview
Reference: www.rockmass.net Sub-sea tunnels and lake taps in Norway - a short overview Arild Palmström, Ph.D. (May 2002) Sub-sea tunnels are those tunnels, which pass beneath the sea or a lake bottom;
World Population to reach 10 billion by 2100 if Fertility in all Countries Converges to Replacement Level
UNITED NATIONS PRESS RELEASE EMBARGOED UNTIL 3 MAY 2011, 11:00 A.M., NEW YORK TIME World Population to reach 10 billion by if Fertility in all Countries Converges to Replacement Level UNITED NATIONS, 3
GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005
GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 CONTENTS 1.0 INTRODUCTION 2.0 OVERVIEW OF SPT APPROACH TO DEVEOPMENTS/WORKS IN THE VICINITY OF
Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)
Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament
Cash flow is the life line of a business. Many start-up
PM.02 ABC of Cash Flow Projections Mark T. Chen, PE CCE Cash flow is the life line of a business. Many start-up companies fail because of insufficient cash flow. From the perspectives of both owner and
Geotechnical risks on large civil engineering projects. Evert Hoek and Alessandro Palmeiri
Geotechnical risks on large civil engineering projects Evert Hoek and Alessandro Palmeiri Keynote address for Theme I International Association of Engineering Geologists Congress, Vancouver, Canada, September
NORWEGIAN PROJECT MANAGEMENT PRINCIPLES APPLIED IN THE JURONG ROCK CAVERN PROJECT
NORWEGIAN PROJECT MANAGEMENT PRINCIPLES APPLIED IN THE JURONG ROCK CAVERN PROJECT FINN FAGERVIK 1, PETTER PLASSBAK 1 and TEO TIONG YONG 2 1 Sintef-Tritech-Multiconsult (STM) Consortium, Singapore E-mail:[email protected]
PPP Basics and Principles of a PPP Framework
Note 1 May 2012 PPP Basics and Principles of a PPP Framework This note is the first in a series of notes on developing a comprehensive policy, legal, and institution framework for public-private partnership
Leader in investment management and engineering in the Renewable Energy Industry
Leader in investment management and engineering in the Renewable Energy Industry Index of contents 1. About us 2. Why Vector Cuatro? 3. Services lines 4. Business track record 2 1 About us Introduction
HEAD OF POLICY AND ADVOCACY
JOB DESCRIPTION JOB TITLE: DEPARTEMENT: LOCATION: REPORTING TO: COUNTRY REPRESENTATIVE - SENEGAL PAN- AFRICAN PROGRAMME DAKAR, SENEGAL HEAD OF POLICY AND ADVOCACY BACKGROUND & ORGANISATIONAL CONTEXT ACORD
Hon. Jemma Nunu Kumba Minister Ministry of Electricity and Water Resources Republic of South Sudan
Hon. Jemma Nunu Kumba Minister Ministry of Electricity and Water Resources Republic of South Sudan South Sudan Electricity Sector Investment Opportunities Introduction Status of electricity supply in South
COBALT CONFERENCE. Green ICT 4 Development in a Circular Economy
COBALT CONFERENCE Green ICT 4 Development in a Circular Economy SUSTAINABLE DEVELOPMENT GOALS Poverty & Hunger Education Gender Equality Health Environmental Sustainability access to INFORMATION & COMMUNICATION
Chapter 4A: World Opinion on Terrorism
1 Pew Global Attitudes Project, Spring 2007 Now I m going to read you a list of things that may be problems in our country. As I read each one, please tell me if you think it is a very big problem, a moderately
American Funds Insurance Series. New World Fund. Summary prospectus Class 2 shares May 1, 2015
American Funds Insurance Series New World Fund Summary prospectus Class 2 shares May 1, 2015 Before you invest, you may want to review the fund s prospectus and statement of additional information, which
PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS
ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS FEBRUARY 2008 PB POWER PB Power Page i EXECUTIVE SUMMARY General
Roseires Dam, Sudan, North Africa
Roseires Dam, Sudan, North Africa Original Roseires Dam Roseires Dam 2013 History of the Nile: The Nile is famous as the longest river in Africa, as well as in the world. The River Nile is about 6,670
Financing hydropower Introduction to the Specifics of Small Hydro Power Plants
EFSE Annual Meeting 2012, Tiblisi GGF Technical Workshop on Small Hydro Power Financing hydropower Introduction to the Specifics of Small Hydro Power Plants May 2012 01 June 2012 Arnsburger Str. 64, 60385
JOB DESCRIPTION. Job Purpose To provide overall leadership and strategic direction to the ACORD country programme.
JOB DESCRIPTION Position: Location: Responsible to: COUNTRY DIRECTOR (CD) ADDIS ABABA, ETHIOPIA with regular visits to all project locations in Ethiopia Head of Programmes Operations & Development Background