1 Affiliated Teaching Hospital BOARD OF DIRECTORS 30 Th OCTOBER 2015 AGENDA ITEM: 8.3 SUBJECT: RESPONSIBLE DIRECTOR: AUTHOR: PREVIOUSLY CONSIDERED BY: BUSINESS CASE COSTING POLICY Kishamer Sidhu Director of Finance & IM&T Peter Bunnewell Trust Management Committee EXECUTIVE SUMMARY: This document proposes the methodologies that managers are to use for identifying the costs contained in capital business cases and how variances to original business case values are approved and reported. ACTION REQUIRED BY THE BOARD For information and approval RISK TO THE TRUST (include reference to BAF or Corporate Risk Register) WORKFORCE ISSUES: (including training and education implications) FINANCIAL IMPLICATIONS: Specify No/Yes (Detailed within the report). COMMUNICATION/CONSULTATION ISSUES (including patient and public involvement) STRATEGIC OBJECTIVE: (specify trust strategic objective) None at this time Yes detailed in the report Not applicable Not applicable CQC DOMAINS safe. effective. caring. responsive to people s needs. well-led Please indicate which domain the report is providing assurance on Well Led 1
2 Affiliated Teaching Hospital BUSINESS CASE COSTING POLICY 1. BACKGROUND 1.1 The Trust has a significant capital plan for both this financial year and future years. 1.2 It has been identified that a number of existing schemes have exceeded the budget approved with submitted cases. A cause of some of the additional costs is due to estimation being inaccurate in the original business case. 1.3 It is therefore necessary to provide a policy to managers which aims to help ensure costs provided are more accurate. 1.4 There are three types of capital expenditure the organisation typically expends; equipment, IT and Estates. The latter two are the principal causes of variance. 2. THE BUSINESS CASE PROCESS 2.1 The Business case process of the organisation is driven through the organisations SFI s. 2.2 The Trust capital plan at the beginning of the year determines the list of capital cases required before requisitions are raised. The capital plan is monitored through the Capital group through to TMC. 2.3 The capital case is submitted to the capital group and approval is provided where appropriate for cases up to, above this level all cases require Board approval. 3. COSTING POLICY 3.1 Business cases must include all costs relevant to the case and the author must ensure costs incurred by other departments are identified e.g. clinical support, estates and IT. 3.2 For all schemes where the actual cost obtained via the formal procurement exceeds the approved sum the project manager must seek approval for the additional cost from the approving committee (in line with SFI s). For urgent schemes the chairman of the relevant committee may give approval of the additional sum pending ratification at the next available committee meeting. Equipment 3.3 For capital equipment where the cost is expected to fall below 50,000 the provision of an estimate from at least one supplier. This to be used for creating a business case. A revised (final) business case would be submitted where the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions and approval is required before contracts are signed. 2
3 3.4 For schemes above 50,000, the business unit manager shall obtain at least one written quote (via the Procurement Dept) based on the services/equipment specification, from a framework supplier. This to be used for creating a business case. A revised (final) business case would be submitted where the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions and approval is required before contracts are signed. 3.5 For schemes above 500,000 the same process as 3.3 is applied but the outline business case has to be submitted to the Board of Directors for approval; a further case needs to be submitted if the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions. 3.6 Whilst one written quote is sufficient for business case approval the Standing Financial Instructions and Scheme of Delegation must be adhered to in relation to the actual procurement of the relevant goods and services i.e. competitive quotes/tenders and EU regulations (or a waiver is required). IT 3.7 For IT schemes where the cost is expected to fall below 50,000, the Head of IT shall provide the cost based on their professional expertise and knowledge of the IT market. This method to be used for creating the business case but where the actual cost exceeds the approved value a report must be provided to the Capital Investment prior to any contract being signed. 3.8 For IT schemes above 50,000, the Head of IT shall obtain at least one written quote based on the services/equipment specification, from a framework supplier. This to be used for creating a business case. A further case should be submitted where the tender cost exceeds the level in accordance with the Standing Financial Instructions. Approval is required before contracts are signed. 3.9 For IT schemes above 500,000 the same process as 3.7 is applied but the outline business case has to be submitted to the Board of Directors for approval and the final case needs to be submitted if the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions Whilst one written quote is sufficient for business case approval the Standing Financial Instructions and Scheme of Delegation must be adhered to in relation to the actual procurement of the relevant goods and services i.e. competitive quotes/tenders and EU regulations (or a waiver is required). Estates 3.11 For works, the Director of Estates is responsible for ensuring specifications are produced Where the cost is expected to be below 50,000, the Director of Estates shall provide the cost based on their professional expertise and knowledge of the market. This method to be used for creating the business case but where the actual cost exceeds the approved value a report must be provided to the Capital Investment prior to any contract being signed For works between 50,000 and under 500,000, the Director of Estates shall obtain a feasibility report from a cost consultant (QS), which includes the scope of 3
4 works and optimisation bias (financial risk analysis). This cost is to be used for creating an Outline Business Case and to proceed to design/tender. A revised case would be submitted where the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions and approval is required before contracts are signed For works above 500,000 the same process as 3.12 is applied but the outline business case has to be submitted to the Board of Directors for approval and the final case needs to be submitted if the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions In line with the Trust section 42 requirements the Trust route will be P21+ unless VFM prevents this procurement route being used. 4. APPROVING AND REPORTING VARIATIONS 4.1 Cases above in variation will be transparent to the Board as they require Board approval. 4.2 Cases below in variation will be reported through to the Performance, Finance and Resources (PFR) Committee. Particular emphasis will be placed on reporting those cases where the variation is above 50k of the original proposal. Original Case Below 50k Between 50k and All Schemes Capital Investment Capital Investment Above Board of Directors Variation below 50k Variation between 50k and Variation above Variation below 50k Variation between 50k and Variation above Approval on variation Capital Investment Capital Investment Capital Investment Capital Investment Capital Investment PFR Committee Board of Directors Board of Directors Board of Directors Reporting on variation Capital Investment PFR Committee PFR Committee PFR Committee PFR Committee PFR Committee Board of Directors Board of Directors Board of Directors 5. RISK 5.1 The Trust has a significant capital programme and there are inherent risks associated with the procurement, if costs have not been accurately identified at the business case stage. 4
5 5.2 Whilst strengthening controls at the business case approval stage is advantageous, additional costs may arise in obtaining quotes and feasibility reports. This may also delay the process for producing business cases and some cases may have abortive costs if the case is subsequently rejected. The mitigation of risks will require better and prompt planning. 6. FINANCIAL IMPLICATIONS 6.1 Controls that improve the accuracy of costs at the business case stage should minimise the risk of overspends on capital schemes. 7. ACTION REQUIRED BY THE BOARD OF DIRECTORS 7.1 The Board of Directors is asked to note the contents of the report and is recommended to approve the additional controls contained in this document. PETER BUNNEWELL HEAD OF FINANCIAL SERVICES 5
EMRAD PACS & RIS Procurement. Kishamer Sidhu. Andrew Gill/Ketan Lad N/A
Affiliated Teaching Hospital BOARD OF DIRECTORS: 28 TH JULY 2014 AGENDA ITEM: 10.7 SUBJECT: RESPONSIBLE DIRECTOR: AUTHOR: PREVIOUSLY CONSIDERED BY: EMRAD PACS & RIS Procurement Kishamer Sidhu Andrew Gill/Ketan
More informationReport title: Extension to Temporary boiler provision for Myatts Field South
Officer delegated decision Decision Due: 2 November 2015 Report title: Extension to Temporary boiler provision for Myatts Field South Ward: Vassall Report Authorised by: Sue Foster, Strategic Director
More informationcreate the most economically advantageous balance of quality and cost; reduce the burden on administrative and monitoring resources;
North Highland College Procurement Strategy 2012-2015 Strategic Context North Highland College s expenditure on bought-in goods and services is approximately 2.2M per annum. At all times the College has
More information2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to:
HARPER ADAMS UNIVERSITY COLLEGE Code of Tendering Practice Introduction 1. The following guidelines are to be used in the conduct of tendering and contracting of major services and supplies commissioned
More informationSTAFF SURVEY REPORT AND ACTION PLAN
Affiliated Teaching Hospital BOARD OF DIRECTORS: 27 TH MAY 2016 AGENDA ITEM: 10.2 SUBJECT: STAFF SURVEY REPORT AND ACTION PLAN RESPONSIBLE DIRECTOR: Director of Human Resources & Organisational Development
More informationCABINET. 19 January 2016. Accountable Divisional Director: Martin Rayson, Divisional Director for Human Resources and Organisational Development
CABINET 19 January 2016 Title: Oracle R12 - Proposal to Extend Contract for Hosting and Support Report of the Cabinet Member for Finance and Central Services Open Report Wards Affected: None Report Author:
More informationCourtney Davis Head of Information Management. Public with separate exempt report
ACTION TAKEN UNDER DELEGATED POWERS BY OFFICER [19 June 2015] Title Report of Wards Status Enclosures Decision to award Off Site Document Management Services Contract under ESPO framework Courtney Davis
More informationCABINET. 24 March 2015
CABINET 24 March 2015 Title: Procurement of Electricity and Gas Supplies Report of the Cabinet Member for Finance Open Report with Exempt Appendix 4 Wards Affected: All Report Author: Andrew Sivess Group
More informationProcurement, Contracting and Contract Management Policy
Procurement, Contracting and Contract Management Policy Corporate policy 8.4 Responsible Officer: Group Manager Accounting and Taxation Policy Custodian: Chief Finance Officer Division: Finance and Resources
More informationPOSITION INFORMATION DOCUMENT
POSITION INFORMATION DOCUMENT Position Title: Senior Manager, ICT Contracts Classification Code: ASO8 Division: ICT Services Directorate: ICT Contracts & Performance Management Type of Appointment: Branch:
More informationOfficer Delegated Decision Report - Procurement
G a t e w a y T h r e e For all procurement awards, waivers, contract extensions and variations Upgrade to NICE call recording system in the Lambeth Service Centre to deliver NICE Perform Analytics Release
More information1.1 Approve the proposals for the roll-out of the new telephone system as set out in this report.
APPENDIX L Agenda Item No. 13 REPLACEMENT OF TELEPHONE SYSTEM Councillor Cartwright Leader of the Council 1.0 Purpose The purpose of this paper is to recommend the progressive roll-out of new telephone
More informationManagement and Leadership. Level 5 NVQ Diploma in Management and Leadership (QCF)
Management and Leadership Level 5 NVQ Diploma in Management and Leadership (QCF) 2014 Skills CFA Level 5 NVQ Diploma in Management and Leadership (QCF) Page 1 Level 5 NVQ Diploma in Management and Leadership
More informationProgramme Delivery & Performance Management
Chapter 13 Programme Delivery & Performance Management Chapter Overview This chapter explains how the County Council will ensure that its transport investment programme is delivered in a cost-effective
More informationVersion Author Revisions Made Date 1.6 David Sharkey Executive Board 27 March 2012 2.0 Robin Hunt
Purchasing Policy Originator name: Section / Dept: Implementation date: Date of next review: Related policies: Policy history: Robin Hunt Procurement 1 December 2013 Finance Regulations, Purchase Card
More informationReport Authorised by: Sue Foster, Strategic Director, Neighbourhoods and Growth
Officer delegated decision Decision Due: 25 November 2015 Extension to Existing Waiver for Hays Specialist Recruitment Wards: All Report Authorised by: Sue Foster, Strategic Director, Neighbourhoods and
More informationWales Procurement Policy Statement
Wales Procurement Policy Statement In December 2012 I launched the Wales Procurement Policy Statement (WPPS) setting out the principles by which I expect public sector procurement to be delivered in Wales.
More informationProgress of the implementation of SEN Transport Planning Software
S CHILDREN & FAMILIES SELECT COMMITTEE 30 October 2008 Progress of the implementation of SEN Transport Planning Software PURPOSE OF REPORT: Performance management This paper is to update the committee
More informationGuidance Developing Commissioning Support: Towards Service Excellence was published by the NHS Commissioning Board Authority in February 2012.
Commissioning support: Key facts Introduction The setting up of the new clinical commissioning system has given the NHS the opportunity to think about what support clinical commissioners need to more efficiently
More informationA guide on how to do business with Stockport NHS Foundation Trust. Procurement Buying In to Buying Locally
A guide on how to do business with Stockport NHS Foundation Trust Procurement Buying In to Buying Locally Contents Page Introduction 3 Aim of the guide 4 Corporate Citizenship more than a hospital 4 The
More informationPRINCE2 strengthens your projects governance
PRINCE2 strengthens your projects governance Guy Eastoe 1. Introduction... 1 2. The importance of project governance in today s organizations... 2 3. King III and PRINCE2... 3 4. The project duties of
More informationDELEGATED POWERS REPORT NO. All reports 1. Governance Service receive draft report Name of GSO Paul Frost
DELEGATED POWERS REPORT NO. 1987 SUBJECT: Electoral Registration and Elections Management Software Contract Control sheet All of the following actions MUST be completed at each stage of the process and
More informationFinancial performance
Financial performance In our first NHS Financial Temperature Check briefing 2 we noted the number of organisations that were overspending or reporting a deficit has increased since the 2012/13 financial
More informationREQUEST FOR MAYORAL DECISION MD670. Title: Storage Area Network Maintenance Contract
REQUEST FOR MAYORAL DECISION MD670 Title: Storage Area Network Maintenance Contract Executive Summary: Approval is sought for the award of a two-year contract (with provision for the extension of the contract
More informationPROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY
PROJECT MANAGEMENT GUIDELINES FOR PROJECTS FUNDED BY THE NATIONAL TRANSPORT AUTHORITY (UP TO 20 MILLION IN VALUE) december 2011 Table of Contents Section A 1. Introduction 4 1.1 Purpose 4 1.2 Applicability
More informationRISK MANAGEMENT STRATEGY 2014-17
RISK MANAGEMENT STRATEGY 2014-17 DOCUMENT NO: Lead author/initiator(s): Contact email address: Developed by: Approved by: DN128 Head of Quality Performance Julia.sirett@ccs.nhs.uk Quality Performance Team
More informationBOND FUND Memorandum Note
207 Memorandum Note The Bond Fund was established by the Resolution passed by the Legislative Council under section 29 of the Public Finance Ordinance (Cap. 2) on 8 July 2009 in connection with the implementation
More informationTable of Contents. 1 P a g e
Table of Contents Financial Regulations 2 General... 2 Accounting Procedures... 2 Internal Audit... 3 Budget Planning And Preparation... 3 Power To Incur Expenditure Within Approved Estimates... 4 Budget
More informationAnnual Plan Part C. SOCIAL CARE BUSINESS SUPPORT SERVICE PLAN 2011-2014 March 2011
Annual Plan Part C SOCIAL CARE BUSINESS SUPPORT SERVICE PLAN 2011-2014 March 2011 SECTION 1 STRATEGIC OVERVIEW OF SERVICE The Business Support Service delivers a range of technical and support services
More informationPerformance Measurement
Brief 21 August 2011 Public Procurement Performance Measurement C O N T E N T S What is the rationale for measuring performance in public procurement? What are the benefits of effective performance management?
More informationDefinition document for Health Bodies in Wales (including Local Health Boards, NHS trusts and Ambulance trusts)
Freedom of Information Act 2000 Definition document for Health Bodies in Wales (including Local Health Boards, NHS trusts and Ambulance trusts) This guidance gives examples of the kinds of information
More informationSection 1 Summary and Recommendations
REPORT FOR: CABINET Date of Meeting: 13 January 2011 Subject: Key Decision: Responsible Officer: Portfolio Holder: Exempt: Decision subject to Call-in: Enclosures: Sports and Leisure Facilities Management
More informationFinancial Regulations. Version 9-17 February 2014
Financial Regulations Version 9-17 February 2014 Contents Introduction... 6 Purpose of Financial Regulations... 6 Scope of Financial Regulations... 6 Corporate Governance... 7 Court... 7 University Council...
More informationINCOME MANAGEMENT POLICY
INCOME MANAGEMENT POLICY Version: 2.0 Ratified by: Trust Board Date ratified: November 2013 Title of originator/author: Title of responsible committee/group: Assistant Director of Finance, Technical. Trust
More informationAPPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES
APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES 1 PERFORMANCE PLANS 1.1 The key controls for performance plans are: (a) to ensure that all relevant plans are produced and that they are consistent
More informationBest Practice exensys Asset Purchases
Best Practice exensys Asset Purchases Table of Contents Introduction:... 3 Overview:... 3 Benefits:... 4 Conclusion:... 4 Introduction: Accounting of fixed assets is a complex task. To effectively manage
More informationUrgent and Emergency Care Project Governance
Urgent and Emergency Care Project Governance Introduction Improving Urgent and Emergency Care for people in Northern Devon is a key priority for both Commissioner and Provider. The slide inserted below
More informationCambridge City Council
Cambridge City Council Item To: Report by: Relevant scrutiny committee: Wards affected: Executive Councillor for Customer Services and Resources James Nightingale, Head of ICT Client Services Strategy
More informationCANI Financial Policy and Procedures
CANI Financial Policy and Procedures Policy CANI Council is conscious of the need to ensure that all funds received by the organisation are used in accordance with the aims and objectives of CANI; that
More informationProcurement and Contract Management Strategy 2013-2017
Procurement and Contract Management Strategy 2013-2017 Title Owner Version 1 Distribution Procurement and Contract Management Strategy 2013 2017 Procurement and Performance Manager Corporate Issue date
More informationSUFFOLK COUNTY COUNCIL PROCUREMENT RULES. Version 2 Jan 2016. Page 1 of 19
SUFFOLK COUNTY COUNCIL PROCUREMENT RULES 2015 Version 2 Jan 2016. Page 1 of 19 TABLE OF CONTENTS 1. Introduction and Definitions... 3 2. Scope... 4 3. General Principles... 5 4. Responsibilities... 7 5.
More informationELECTRONIC DOCUMENT AND RECORDS MANAGEMENT SYSTEM REPORT OF THE HEAD OF INFORMATION MANAGEMENT AND TECHNOLOGY
CAB2304 FOR DECISION WARD(S): GENERAL CABINET 13 June 2012 ELECTRONIC DOCUMENT AND RECORDS MANAGEMENT SYSTEM REPORT OF THE HEAD OF INFORMATION MANAGEMENT AND TECHNOLOGY Contact Officer: Tony Fawcett Tel
More informationPM Governance. Executive Team ADCA ADCA
Item 6.5a Action Plan against the Recommendations Made in the Review of Risk Management Arrangements by PM Governance, November 2014 Key: PM Governance Paul Moore, Risk Consultant ADCA Associate Director
More informationCommittees: Dates: Item no. Community and Children's Services Committee Projects Sub 10/07/2015 21/07/2015. Gateway 3/4 Options Appraisal.
Committees: Dates: Item no. Community and Children's Services Committee Projects Sub 10/07/2015 21/07/2015 Subject: Heating and hot water equipment replacement - Golden Lane Estate. Report of: Director
More informationCENTRAL TABLELANDS ALLIANCE COUNCILS. Consolidated Report: PROCUREMENT, CONTRACTS AND PROJECT MANAGEMENT
CENTRA TABEANDS AIANCE COUNCIS Consolidated Report: PROCUREENT, CONTRACTS AND PROJECT ANAGEENT DRAFT APRI 2011 TABE OF CONTENTS EXECUTIVE SUARY... 1 INTRODUCTION... 1 OBJECTIVES... 1 ETHODOOGY AND SCOPE...
More informationOfficer Delegated Decision Report - Procurement. For All Procurement Awards, Waivers, Contract Extensions & Variations
G atew a y T h r ee For All Procurement Awards, Waivers, Contract Extensions & Variations Fuel Cards Payment Solutions Contract Requisition Number R000760 Wards All Report authorised by: (Enter name and
More informationAuthor: Adrian Pengelly Role: Director of Assets. Recommendations: 1. That the review of the Assets Directorate budget pressures for 2014/15 is noted.
Cornwall Housing Limited Report Template for DLT Agenda No: 7 Report to: The Board Part 1 Date: 27 July 2015 Title: Assets Directorate Budget Pressures 2014/15 Author: Adrian Pengelly Role: Director of
More informationPROCUREMENT STRATEGY. Charity number SC004401
Charity number SC004401 PROCUREMENT STRATEGY 1.PURPOSE... 2 2.OUR ROLE... 2 3. STRATEGIC VISION... 2 4.SPEND DATA... 3 5. ROAD MAP... 4 6. STRATEGIC INTENT... 4 7. OBJECTIVES... 5 7.1 Efficiency Objectives...
More informationI N T R O D U C T I O N THE PROCESS OF ACQUIRING GOODS WORKS AND SERVICES BY GOVERNMENT PROCURING ENTITIES.
I N T R O D U C T I O N Public Procurement means: THE PROCESS OF ACQUIRING GOODS WORKS AND SERVICES BY GOVERNMENT PROCURING ENTITIES. This process includes purchasing, hiring, leasing or any other contractual
More informationSchools and Directorates Funded Projects for building, alteration and decorative works
University of Sussex Schools and Directorates Funded Projects for building, alteration and decorative works Overview 1. All proposed building, alterations and decorative works to be funded from Schools
More informationPOLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT
POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT The intent of this policy is to establish a University-wide governance structure for managing contracts and other legally binding documents. The Policy
More informationPROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
More informationCONFIGURATION COMMITTEE. Terms of Reference
SWBTB (8/13) 166 (g) CONFIGURATION COMMITTEE Terms of Reference 1. CONSTITUTION 1.1 The Board hereby resolves to establish a Committee of the Board to be known as the Configuration Committee (The Committee).
More informationNYCC SCHOOL LOANS SCHEME TERMS AND CONDITIONS
NYCC SCHOOL LOANS SCHEME TERMS AND CONDITIONS 1.0 PURPOSE 1.1 To detail the terms and conditions of the loans scheme for schools and Pupil Referral Services with delegated budgets through use of reserves
More informationMEMBERS CONSIDER THE RISK STRATEGY AND RECOMMEND APPROVAL TO COUNCIL.
Agenda item: 8 Committee: Audit & Standards Committee Date of meeting: 19 th September 2011 Subject: Risk Management Strategy Lead Officer: Head of Finance Portfolio Holder: Resources - Councillor T Oliver
More information1.1 To provide highlight reports for all the Council s corporately significant projects, covering the period up to the end of June 2006.
The Executive Agenda item: On 12 September Report Title: Programme Highlight Report June 2006 Forward Plan reference number (if applicable): Report of: The Chief Executive Wards(s) affected: All Report
More informationWelsh Ambulance Services NHS Trust
Welsh Ambulance Services NHS Trust Financial Support to replace obsolete Ambulance Vehicles 2008/09 BUSINESS JUSTIFICATION CASE Version No: Page 1 of 10 VERSION HISTORY Version Date Brief Summary of Change
More informationING Purchase Control. 1Take control of your purchase-to-pay cycle!
ING Purchase Control 1Take control of your purchase-to-pay cycle! ING Purchase Control Is your purchase process a time consuming activity? Do you want to have more control of your purchaseto-pay cycle
More informationPROCEDURE FS 1 PROCUREMENT POLICY
PROCEDURE FS 1 PROCUREMENT POLICY CONTENTS Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7 Section 8 Section 9 Section 10 Section 11 Section 12 Section 13 Appendix A Appendix B Appendix
More informationAPUC Supply Chain Sustainability Policy
APUC Supply Chain Sustainability Policy Vision APUC aims to be a leader, on behalf of client institutions, in driving forward the sustainable procurement agenda (please see Appendix 1 for the commonly
More informationJOB PROFILE. Collaborate and work effectively with team members within the section and the rest of the Transformation Service.
JOB PROFILE Job Title: Principal Commissioning Officer Consultant 3 Department: Corporate Resources Ref: DCC/14/0344 Section: Transformation Service Job Family: Transformation Job grade: 12 Purpose of
More informationUniversity of Edinburgh Procurement Strategy 2012 16 updated May 2013
University of Edinburgh Procurement Strategy 2012 16 updated May 2013 At the University of Edinburgh, we aim to meet our needs for goods, services and works in a way that achieves value for money on a
More informationCABINET 9TH JULY 2015. Report of the Head of Finance and Property Services. Lead Member: Councillor Tom Barkley. Part A
CABINET 9TH JULY 2015 Report of the Head of Finance and Property Lead Member: Councillor Tom Barkley Part A ITEM 8 ANNUAL PROCUREMENT PLAN 2015/16 UPDATE Purpose of Report This report sets out additions
More informationCost improvement plans Quality Impact Assessment (QIA)
Trust Board in public REPORT TITLE: EXECUTIVE SPONSOR/AUTHOR: AUTHOR Date: 28 November 2013 Agenda Item: 3.2 Cost improvement plans Quality Impact Assessment (QIA) Paul Simpson (Chief Finance Officer)
More information6.0 Procurement procedure 1 Infrastructure
Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement
More informationReview of Capital Expenditure. Sedgefield Borough Council Audit 2007/08 September 2008
Review of Capital Expenditure Sedgefield Borough Council Audit 2007/08 September 2008 Contents Summary report 3 Appendix 1 Action plan 10 Status of our reports The Statement of Responsibilities of Auditors
More informationPurchase to Pay Process
National Financial Regulations Purchase to Pay Process Contents MAIN CHAPTERS Chapter Description Page No. 1. Purchase to Pay (General) 1...3 2. Purchase To Pay Tendering Process...28 3. Purchase to Pay
More informationFINANCIAL MANAGEMENT MATURITY MODEL
Definition: Financial management is the system by which the resources of an organisation s business are planned, directed, monitored and controlled to enable the organisation s goals to be achieved. Guidance
More informationINFORMATION TECHNOLOGY THIRD PARTY SERVICE MANAGEMENT POLICY
INFORMATION TECHNOLOGY THIRD PARTY SERVICE MANAGEMENT POLICY Version 1.0 FEBRUARY 2007 Document Title: Summary: Information Technology Third Party Service Management Policy This policy defines the Institute
More informationFINANCE AND ASSET MANAGEMENT SUB-COMMITTEE. Meeting held at the Civic Centre, Uxbridge on Tuesday 20 June 2000 at 7.30pm
FINANCE AND ASSET MANAGEMENT SUB-COMMITTEE Meeting held at the Civic Centre, Uxbridge on Tuesday 20 June 2000 at 7.30pm Councillors: Robert Benson John Morse Jonathan Bianco Norman Nunn-Price Steve Carey
More informationSUSTAINABLE PROCUREMENT CENTRE OF EXCELLENCE FOR HIGHER EDUCATION. London Universities Environmental Group 8 th November 2011
SUSTAINABLE PROCUREMENT CENTRE OF EXCELLENCE FOR HIGHER EDUCATION London Universities Environmental Group 8 th November 2011 AGENDA Role of the SPCE Benefits Realisation SPCE Website Capacity Building
More informationA Ready Business has total visibility and control. Seamlessly manage your global telecommuncations in a secure environment
A Ready Business has total visibility and control Seamlessly manage your global telecommuncations in a secure environment 2 We live in a world of rapid and unpredictable change 22% Only 22% of businesses
More informationProcurement Guide. 3.1.12.2 Once you have found the required document, double click and it will upload onto the screen.
3.1.12 If you need to attach quotes, emails or other documents to the purchase order to adhere to the purchasing delegations and enable the release of the order, click on the Attachments option, which
More informationAnnex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme
Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme Annex 2 is an integral part of the Framework Agreement between the Swiss Federal Council and the Government of the Republic of Poland
More informationProcurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement
Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement Action Note 14/15 27 August 2015 Issue 1. Raising skills levels within the UK workforce is key to delivering sustainable
More informationSupporting the local economy in Surrey. 14 th June 2012
Supporting the local economy in Surrey 14 th June 2012 Surrey Based Suppliers Opening up business opportunities in Surrey. Andrew Forzani Head of Procurement and Commissioning Agenda 6.30pm Welcome by
More informationJE PANEL/BENCHMARKING REF NO: 867/4 EVALUATION DATE:
1. JOB TITLE Job Title: Project Manager (Transport Infrastructure) Reports to: Design Programme Manager Service: Highways and Transport Environment & Infrastructure Date: November 2014 2. JOB PURPOSE To
More informationthe Audit Committee.
Audit Committee 22 Agenda Item No: 10 Report title Cabinet member with lead responsibility Accountable director Originating service The Introduction of Agresso Councillor Andrew Johnson Resources Keith
More informationReport title : Waiver for the hire and installation of two temporary boilers and one new permanent commercial boiler at Brixton Recreation Centre
Officer delegated decision Report title : Waiver for the hire and installation of two temporary boilers and one new permanent commercial boiler at Brixton Recreation Centre Wards: Coldharbour Report Authorised
More informationSustainable Supply Chain Policy
Sustainable Supply Chain Policy 1. Contents Page 2. Introduction & Purpose 1 3. Definitions 1 4. Benefits of a Sustainable approach to the Supply Chain 2 5. Operational Context 2 6. Elements & Principles
More informationNHS Procurement Dashboard: Overview
NHS Procurement Dashboard: Overview November 2013 You may re-use the text of this document (not including logos) free of charge in any format or medium, under the terms of the Open Government Licence.
More informationCAPITAL INVESTMENT POLICY
CAPITAL INVESTMENT POLICY Document Profile Box Document Reference: Version: 0001 Ratified by: Trust Board Date ratified: March 2009 Name of originator/author: Duncan Sellers Name of responsible committee/individual:
More informationNetwork Rail Infrastructure Projects Joint Relationship Management Plan
Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf
More informationDirector of Nursing & Quality. Helen Coleman Associate Director for Nursing Workforce
Reporting to: Trust Board - March 2015 Paper 8 Title Sponsoring Director Author(s) Nursing Revalidation Director of Nursing & Quality Helen Coleman Associate Director for Nursing Workforce Previously considered
More informationGovernment has set an aspiration of 25% of expenditure to flow through SMEs either directly or indirectly through the supply chain.
DWP Revised SME Action Plan May 2014 Background and objectives The SME agenda is a crucial engine for the Government Growth Agenda and is also a key element of DWP s Commercial Strategy as we look to create
More informationOutcome of Brokerage Services(encompassing payroll) Tender
Report to Cabinet Outcome of Brokerage Services(encompassing payroll) Tender Portfolio Holder: Cllr Jenny Harrison, Social Care & Safeguarding Officer Contact: Maggie Kufeldt, Executive Director - Health
More informationInformatics: The future. An organisational summary
Informatics: The future An organisational summary DH INFORMATION READER BOX Policy HR/Workforce Management Planning/Performance Clinical Document Purpose Commissioner Development Provider Development Improvement
More informationDARLINGTON BOROUGH COUNCIL LEARNING & SKILLS SERVICE SUPPLY CHAIN FEES AND CHARGES POLICY 2015/16
DARLINGTON BOROUGH COUNCIL LEARNING & SKILLS SERVICE SUPPLY CHAIN FEES AND CHARGES POLICY 2015/16 1. POLICY STATEMENT 1.1 Darlington Borough Council s Learning & Skills Service (the Service) is funded
More informationThe Utilities Exchange Limited
The Utilities Exchange Limited Corporate and Government Energy Procurement Cut costs and carbon use and become more competitive Energy is essential for any business to function and it s cost has a critical
More informationTelecom Expense Management
Telecom Expense Professional Cost Group Ltd. Control your costs Manage your assets Transform your business Visit us online: www.pcmg.co.uk/tem Your Challenges. For most companies, fixed and mobile communications
More informationCommittees Date: Subject: Public Report of: For Information Summary
Committees Audit & Risk Management Committee Finance Committee Subject: Cyber Security Risks Report of: Chamberlain Date: 17 September 2015 22 September 2015 Public For Information Summary Cyber security
More informationConstruction (Design and Management) Regulations 2007
MEETING Finance, Procurement and Property Committee AGENDA ITEM 14 MEETING DATE 9 th July 2007 DOCUMENT NUMBER FEP 1052 SUBJECT REPORT Construction (Design and Management) Regulations 2007 (12/06/07) by
More informationGuidelines for Capacity Building and Institutional Framework for e-governance under NeGP
Guidelines for Capacity Building and Institutional Framework for e-governance under NeGP Guidelines for Capacity Building and Institutional Framework for e-governance under NeGP Planning Commission & Department
More informationBusiness Case - Automotive Purchases and Alternative Solutions
THE SCOTTISH AMBULANCE SERVICE BOARD FULL BUSINESS CASE FOR THE REPLACEMENT OF EMERGENCY, PATIENT TRANSPORT AND SUPPORT VEHICLES 2009/10-2011/12 Scottish Ambulance Service National Headquarters Tipperlinn
More informationAchieving Excellence in Construction. A manager s checklist. Construction projects
Achieving Excellence in Construction A manager s checklist Construction projects Construction projects A manager s checklist This document outlines the key questions that a Senior Responsible Owner (SRO)
More informationSunbeam House Services Title: Capital Expenditure Policy Policy Document Effective Date: 28 April 2015 Document Control Version Control
Document Control Policy Title Capital Expenditure Policy Policy Number 034 Owner Finance Manager Contributors Finance Manager Version 1.0 Date of Production 28 th April 2015 Review date 28 th April 2017
More informationGUIDE ON HOW TO DO BUSINESS WITH LIVERPOOL JOHN MOORES UNIVERSITY
GUIDE ON HOW TO DO BUSINESS WITH LIVERPOOL JOHN MOORES UNIVERSITY PRODUCED BY LIVERPOOL JOHN MOORES UNIVERSITY PROCUREMENT SERVICE First Issued - ISSUED 11 th February 2011 VERSION 5.0 updated 13/04/15
More informationCABINET - 26 JULY 2011 REPORT OF THE DIRECTOR OF CORPORATE RESOURCES EAST MIDLANDS SHARED SERVICES: PROCUREMENT OF MANAGED HOSTING SERVICE
N CABINET - 26 JULY 2011 REPORT OF THE DIRECTOR OF CORPORATE RESOURCES EAST MIDLANDS SHARED SERVICES: PROCUREMENT OF MANAGED HOSTING SERVICE Purpose 1. The purpose of the report is to: advise Cabinet of
More informationHow To Be A Responsible Corporate Social Responsibility (Csr) Organisation
CORPORATE SOCIAL RESPONSIBILITY STRATEGY 2013-2018 1 Contents Introduction...3 Our CSR Vision...5 Our CSR Objectives...7 Challenges and barriers...10 Implementation Framework...11 Communication Framework...13
More informationTHE COMPLETE GUIDE TO PERFECT PROJECT MANAGEMENT
THE COMPLETE GUIDE TO PERFECT PROJECT MANAGEMENT 1 CONTENTS Introduction 3 Prince2 5 Every as a project tool 6 Major development and building work 7 Further reading and information..9 2 THE COMPLETE GUIDE
More information