1 Affiliated Teaching Hospital BOARD OF DIRECTORS 30 Th OCTOBER 2015 AGENDA ITEM: 8.3 SUBJECT: RESPONSIBLE DIRECTOR: AUTHOR: PREVIOUSLY CONSIDERED BY: BUSINESS CASE COSTING POLICY Kishamer Sidhu Director of Finance & IM&T Peter Bunnewell Trust Management Committee EXECUTIVE SUMMARY: This document proposes the methodologies that managers are to use for identifying the costs contained in capital business cases and how variances to original business case values are approved and reported. ACTION REQUIRED BY THE BOARD For information and approval RISK TO THE TRUST (include reference to BAF or Corporate Risk Register) WORKFORCE ISSUES: (including training and education implications) FINANCIAL IMPLICATIONS: Specify No/Yes (Detailed within the report). COMMUNICATION/CONSULTATION ISSUES (including patient and public involvement) STRATEGIC OBJECTIVE: (specify trust strategic objective) None at this time Yes detailed in the report Not applicable Not applicable CQC DOMAINS safe. effective. caring. responsive to people s needs. well-led Please indicate which domain the report is providing assurance on Well Led 1

2 Affiliated Teaching Hospital BUSINESS CASE COSTING POLICY 1. BACKGROUND 1.1 The Trust has a significant capital plan for both this financial year and future years. 1.2 It has been identified that a number of existing schemes have exceeded the budget approved with submitted cases. A cause of some of the additional costs is due to estimation being inaccurate in the original business case. 1.3 It is therefore necessary to provide a policy to managers which aims to help ensure costs provided are more accurate. 1.4 There are three types of capital expenditure the organisation typically expends; equipment, IT and Estates. The latter two are the principal causes of variance. 2. THE BUSINESS CASE PROCESS 2.1 The Business case process of the organisation is driven through the organisations SFI s. 2.2 The Trust capital plan at the beginning of the year determines the list of capital cases required before requisitions are raised. The capital plan is monitored through the Capital group through to TMC. 2.3 The capital case is submitted to the capital group and approval is provided where appropriate for cases up to, above this level all cases require Board approval. 3. COSTING POLICY 3.1 Business cases must include all costs relevant to the case and the author must ensure costs incurred by other departments are identified e.g. clinical support, estates and IT. 3.2 For all schemes where the actual cost obtained via the formal procurement exceeds the approved sum the project manager must seek approval for the additional cost from the approving committee (in line with SFI s). For urgent schemes the chairman of the relevant committee may give approval of the additional sum pending ratification at the next available committee meeting. Equipment 3.3 For capital equipment where the cost is expected to fall below 50,000 the provision of an estimate from at least one supplier. This to be used for creating a business case. A revised (final) business case would be submitted where the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions and approval is required before contracts are signed. 2

3 3.4 For schemes above 50,000, the business unit manager shall obtain at least one written quote (via the Procurement Dept) based on the services/equipment specification, from a framework supplier. This to be used for creating a business case. A revised (final) business case would be submitted where the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions and approval is required before contracts are signed. 3.5 For schemes above 500,000 the same process as 3.3 is applied but the outline business case has to be submitted to the Board of Directors for approval; a further case needs to be submitted if the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions. 3.6 Whilst one written quote is sufficient for business case approval the Standing Financial Instructions and Scheme of Delegation must be adhered to in relation to the actual procurement of the relevant goods and services i.e. competitive quotes/tenders and EU regulations (or a waiver is required). IT 3.7 For IT schemes where the cost is expected to fall below 50,000, the Head of IT shall provide the cost based on their professional expertise and knowledge of the IT market. This method to be used for creating the business case but where the actual cost exceeds the approved value a report must be provided to the Capital Investment prior to any contract being signed. 3.8 For IT schemes above 50,000, the Head of IT shall obtain at least one written quote based on the services/equipment specification, from a framework supplier. This to be used for creating a business case. A further case should be submitted where the tender cost exceeds the level in accordance with the Standing Financial Instructions. Approval is required before contracts are signed. 3.9 For IT schemes above 500,000 the same process as 3.7 is applied but the outline business case has to be submitted to the Board of Directors for approval and the final case needs to be submitted if the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions Whilst one written quote is sufficient for business case approval the Standing Financial Instructions and Scheme of Delegation must be adhered to in relation to the actual procurement of the relevant goods and services i.e. competitive quotes/tenders and EU regulations (or a waiver is required). Estates 3.11 For works, the Director of Estates is responsible for ensuring specifications are produced Where the cost is expected to be below 50,000, the Director of Estates shall provide the cost based on their professional expertise and knowledge of the market. This method to be used for creating the business case but where the actual cost exceeds the approved value a report must be provided to the Capital Investment prior to any contract being signed For works between 50,000 and under 500,000, the Director of Estates shall obtain a feasibility report from a cost consultant (QS), which includes the scope of 3

4 works and optimisation bias (financial risk analysis). This cost is to be used for creating an Outline Business Case and to proceed to design/tender. A revised case would be submitted where the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions and approval is required before contracts are signed For works above 500,000 the same process as 3.12 is applied but the outline business case has to be submitted to the Board of Directors for approval and the final case needs to be submitted if the tender cost exceeds the tolerance level in accordance with the Standing Financial Instructions In line with the Trust section 42 requirements the Trust route will be P21+ unless VFM prevents this procurement route being used. 4. APPROVING AND REPORTING VARIATIONS 4.1 Cases above in variation will be transparent to the Board as they require Board approval. 4.2 Cases below in variation will be reported through to the Performance, Finance and Resources (PFR) Committee. Particular emphasis will be placed on reporting those cases where the variation is above 50k of the original proposal. Original Case Below 50k Between 50k and All Schemes Capital Investment Capital Investment Above Board of Directors Variation below 50k Variation between 50k and Variation above Variation below 50k Variation between 50k and Variation above Approval on variation Capital Investment Capital Investment Capital Investment Capital Investment Capital Investment PFR Committee Board of Directors Board of Directors Board of Directors Reporting on variation Capital Investment PFR Committee PFR Committee PFR Committee PFR Committee PFR Committee Board of Directors Board of Directors Board of Directors 5. RISK 5.1 The Trust has a significant capital programme and there are inherent risks associated with the procurement, if costs have not been accurately identified at the business case stage. 4

5 5.2 Whilst strengthening controls at the business case approval stage is advantageous, additional costs may arise in obtaining quotes and feasibility reports. This may also delay the process for producing business cases and some cases may have abortive costs if the case is subsequently rejected. The mitigation of risks will require better and prompt planning. 6. FINANCIAL IMPLICATIONS 6.1 Controls that improve the accuracy of costs at the business case stage should minimise the risk of overspends on capital schemes. 7. ACTION REQUIRED BY THE BOARD OF DIRECTORS 7.1 The Board of Directors is asked to note the contents of the report and is recommended to approve the additional controls contained in this document. PETER BUNNEWELL HEAD OF FINANCIAL SERVICES 5

EMRAD PACS & RIS Procurement. Kishamer Sidhu. Andrew Gill/Ketan Lad N/A

EMRAD PACS & RIS Procurement. Kishamer Sidhu. Andrew Gill/Ketan Lad N/A Affiliated Teaching Hospital BOARD OF DIRECTORS: 28 TH JULY 2014 AGENDA ITEM: 10.7 SUBJECT: RESPONSIBLE DIRECTOR: AUTHOR: PREVIOUSLY CONSIDERED BY: EMRAD PACS & RIS Procurement Kishamer Sidhu Andrew Gill/Ketan

More information

Report title: Extension to Temporary boiler provision for Myatts Field South

Report title: Extension to Temporary boiler provision for Myatts Field South Officer delegated decision Decision Due: 2 November 2015 Report title: Extension to Temporary boiler provision for Myatts Field South Ward: Vassall Report Authorised by: Sue Foster, Strategic Director

More information

create the most economically advantageous balance of quality and cost; reduce the burden on administrative and monitoring resources;

create the most economically advantageous balance of quality and cost; reduce the burden on administrative and monitoring resources; North Highland College Procurement Strategy 2012-2015 Strategic Context North Highland College s expenditure on bought-in goods and services is approximately 2.2M per annum. At all times the College has

More information

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to:

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to: HARPER ADAMS UNIVERSITY COLLEGE Code of Tendering Practice Introduction 1. The following guidelines are to be used in the conduct of tendering and contracting of major services and supplies commissioned

More information

STAFF SURVEY REPORT AND ACTION PLAN

STAFF SURVEY REPORT AND ACTION PLAN Affiliated Teaching Hospital BOARD OF DIRECTORS: 27 TH MAY 2016 AGENDA ITEM: 10.2 SUBJECT: STAFF SURVEY REPORT AND ACTION PLAN RESPONSIBLE DIRECTOR: Director of Human Resources & Organisational Development

More information

CABINET. 19 January 2016. Accountable Divisional Director: Martin Rayson, Divisional Director for Human Resources and Organisational Development

CABINET. 19 January 2016. Accountable Divisional Director: Martin Rayson, Divisional Director for Human Resources and Organisational Development CABINET 19 January 2016 Title: Oracle R12 - Proposal to Extend Contract for Hosting and Support Report of the Cabinet Member for Finance and Central Services Open Report Wards Affected: None Report Author:

More information

Courtney Davis Head of Information Management. Public with separate exempt report

Courtney Davis Head of Information Management. Public with separate exempt report ACTION TAKEN UNDER DELEGATED POWERS BY OFFICER [19 June 2015] Title Report of Wards Status Enclosures Decision to award Off Site Document Management Services Contract under ESPO framework Courtney Davis

More information

CABINET. 24 March 2015

CABINET. 24 March 2015 CABINET 24 March 2015 Title: Procurement of Electricity and Gas Supplies Report of the Cabinet Member for Finance Open Report with Exempt Appendix 4 Wards Affected: All Report Author: Andrew Sivess Group

More information

Procurement, Contracting and Contract Management Policy

Procurement, Contracting and Contract Management Policy Procurement, Contracting and Contract Management Policy Corporate policy 8.4 Responsible Officer: Group Manager Accounting and Taxation Policy Custodian: Chief Finance Officer Division: Finance and Resources

More information

POSITION INFORMATION DOCUMENT

POSITION INFORMATION DOCUMENT POSITION INFORMATION DOCUMENT Position Title: Senior Manager, ICT Contracts Classification Code: ASO8 Division: ICT Services Directorate: ICT Contracts & Performance Management Type of Appointment: Branch:

More information

Officer Delegated Decision Report - Procurement

Officer Delegated Decision Report - Procurement G a t e w a y T h r e e For all procurement awards, waivers, contract extensions and variations Upgrade to NICE call recording system in the Lambeth Service Centre to deliver NICE Perform Analytics Release

More information

1.1 Approve the proposals for the roll-out of the new telephone system as set out in this report.

1.1 Approve the proposals for the roll-out of the new telephone system as set out in this report. APPENDIX L Agenda Item No. 13 REPLACEMENT OF TELEPHONE SYSTEM Councillor Cartwright Leader of the Council 1.0 Purpose The purpose of this paper is to recommend the progressive roll-out of new telephone

More information

Management and Leadership. Level 5 NVQ Diploma in Management and Leadership (QCF)

Management and Leadership. Level 5 NVQ Diploma in Management and Leadership (QCF) Management and Leadership Level 5 NVQ Diploma in Management and Leadership (QCF) 2014 Skills CFA Level 5 NVQ Diploma in Management and Leadership (QCF) Page 1 Level 5 NVQ Diploma in Management and Leadership

More information

Programme Delivery & Performance Management

Programme Delivery & Performance Management Chapter 13 Programme Delivery & Performance Management Chapter Overview This chapter explains how the County Council will ensure that its transport investment programme is delivered in a cost-effective

More information

Version Author Revisions Made Date 1.6 David Sharkey Executive Board 27 March 2012 2.0 Robin Hunt

Version Author Revisions Made Date 1.6 David Sharkey Executive Board 27 March 2012 2.0 Robin Hunt Purchasing Policy Originator name: Section / Dept: Implementation date: Date of next review: Related policies: Policy history: Robin Hunt Procurement 1 December 2013 Finance Regulations, Purchase Card

More information

Report Authorised by: Sue Foster, Strategic Director, Neighbourhoods and Growth

Report Authorised by: Sue Foster, Strategic Director, Neighbourhoods and Growth Officer delegated decision Decision Due: 25 November 2015 Extension to Existing Waiver for Hays Specialist Recruitment Wards: All Report Authorised by: Sue Foster, Strategic Director, Neighbourhoods and

More information

Wales Procurement Policy Statement

Wales Procurement Policy Statement Wales Procurement Policy Statement In December 2012 I launched the Wales Procurement Policy Statement (WPPS) setting out the principles by which I expect public sector procurement to be delivered in Wales.

More information

Progress of the implementation of SEN Transport Planning Software

Progress of the implementation of SEN Transport Planning Software S CHILDREN & FAMILIES SELECT COMMITTEE 30 October 2008 Progress of the implementation of SEN Transport Planning Software PURPOSE OF REPORT: Performance management This paper is to update the committee

More information

Guidance Developing Commissioning Support: Towards Service Excellence was published by the NHS Commissioning Board Authority in February 2012.

Guidance Developing Commissioning Support: Towards Service Excellence was published by the NHS Commissioning Board Authority in February 2012. Commissioning support: Key facts Introduction The setting up of the new clinical commissioning system has given the NHS the opportunity to think about what support clinical commissioners need to more efficiently

More information

A guide on how to do business with Stockport NHS Foundation Trust. Procurement Buying In to Buying Locally

A guide on how to do business with Stockport NHS Foundation Trust. Procurement Buying In to Buying Locally A guide on how to do business with Stockport NHS Foundation Trust Procurement Buying In to Buying Locally Contents Page Introduction 3 Aim of the guide 4 Corporate Citizenship more than a hospital 4 The

More information

PRINCE2 strengthens your projects governance

PRINCE2 strengthens your projects governance PRINCE2 strengthens your projects governance Guy Eastoe 1. Introduction... 1 2. The importance of project governance in today s organizations... 2 3. King III and PRINCE2... 3 4. The project duties of

More information

DELEGATED POWERS REPORT NO. All reports 1. Governance Service receive draft report Name of GSO Paul Frost

DELEGATED POWERS REPORT NO. All reports 1. Governance Service receive draft report Name of GSO Paul Frost DELEGATED POWERS REPORT NO. 1987 SUBJECT: Electoral Registration and Elections Management Software Contract Control sheet All of the following actions MUST be completed at each stage of the process and

More information

Financial performance

Financial performance Financial performance In our first NHS Financial Temperature Check briefing 2 we noted the number of organisations that were overspending or reporting a deficit has increased since the 2012/13 financial

More information

REQUEST FOR MAYORAL DECISION MD670. Title: Storage Area Network Maintenance Contract

REQUEST FOR MAYORAL DECISION MD670. Title: Storage Area Network Maintenance Contract REQUEST FOR MAYORAL DECISION MD670 Title: Storage Area Network Maintenance Contract Executive Summary: Approval is sought for the award of a two-year contract (with provision for the extension of the contract

More information

PROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY

PROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY PROJECT MANAGEMENT GUIDELINES FOR PROJECTS FUNDED BY THE NATIONAL TRANSPORT AUTHORITY (UP TO 20 MILLION IN VALUE) december 2011 Table of Contents Section A 1. Introduction 4 1.1 Purpose 4 1.2 Applicability

More information

RISK MANAGEMENT STRATEGY 2014-17

RISK MANAGEMENT STRATEGY 2014-17 RISK MANAGEMENT STRATEGY 2014-17 DOCUMENT NO: Lead author/initiator(s): Contact email address: Developed by: Approved by: DN128 Head of Quality Performance Julia.sirett@ccs.nhs.uk Quality Performance Team

More information

BOND FUND Memorandum Note

BOND FUND Memorandum Note 207 Memorandum Note The Bond Fund was established by the Resolution passed by the Legislative Council under section 29 of the Public Finance Ordinance (Cap. 2) on 8 July 2009 in connection with the implementation

More information

Table of Contents. 1 P a g e

Table of Contents. 1 P a g e Table of Contents Financial Regulations 2 General... 2 Accounting Procedures... 2 Internal Audit... 3 Budget Planning And Preparation... 3 Power To Incur Expenditure Within Approved Estimates... 4 Budget

More information

Annual Plan Part C. SOCIAL CARE BUSINESS SUPPORT SERVICE PLAN 2011-2014 March 2011

Annual Plan Part C. SOCIAL CARE BUSINESS SUPPORT SERVICE PLAN 2011-2014 March 2011 Annual Plan Part C SOCIAL CARE BUSINESS SUPPORT SERVICE PLAN 2011-2014 March 2011 SECTION 1 STRATEGIC OVERVIEW OF SERVICE The Business Support Service delivers a range of technical and support services

More information

Performance Measurement

Performance Measurement Brief 21 August 2011 Public Procurement Performance Measurement C O N T E N T S What is the rationale for measuring performance in public procurement? What are the benefits of effective performance management?

More information

Definition document for Health Bodies in Wales (including Local Health Boards, NHS trusts and Ambulance trusts)

Definition document for Health Bodies in Wales (including Local Health Boards, NHS trusts and Ambulance trusts) Freedom of Information Act 2000 Definition document for Health Bodies in Wales (including Local Health Boards, NHS trusts and Ambulance trusts) This guidance gives examples of the kinds of information

More information

Section 1 Summary and Recommendations

Section 1 Summary and Recommendations REPORT FOR: CABINET Date of Meeting: 13 January 2011 Subject: Key Decision: Responsible Officer: Portfolio Holder: Exempt: Decision subject to Call-in: Enclosures: Sports and Leisure Facilities Management

More information

Financial Regulations. Version 9-17 February 2014

Financial Regulations. Version 9-17 February 2014 Financial Regulations Version 9-17 February 2014 Contents Introduction... 6 Purpose of Financial Regulations... 6 Scope of Financial Regulations... 6 Corporate Governance... 7 Court... 7 University Council...

More information

INCOME MANAGEMENT POLICY

INCOME MANAGEMENT POLICY INCOME MANAGEMENT POLICY Version: 2.0 Ratified by: Trust Board Date ratified: November 2013 Title of originator/author: Title of responsible committee/group: Assistant Director of Finance, Technical. Trust

More information

APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES

APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES 1 PERFORMANCE PLANS 1.1 The key controls for performance plans are: (a) to ensure that all relevant plans are produced and that they are consistent

More information

Best Practice exensys Asset Purchases

Best Practice exensys Asset Purchases Best Practice exensys Asset Purchases Table of Contents Introduction:... 3 Overview:... 3 Benefits:... 4 Conclusion:... 4 Introduction: Accounting of fixed assets is a complex task. To effectively manage

More information

Urgent and Emergency Care Project Governance

Urgent and Emergency Care Project Governance Urgent and Emergency Care Project Governance Introduction Improving Urgent and Emergency Care for people in Northern Devon is a key priority for both Commissioner and Provider. The slide inserted below

More information

Cambridge City Council

Cambridge City Council Cambridge City Council Item To: Report by: Relevant scrutiny committee: Wards affected: Executive Councillor for Customer Services and Resources James Nightingale, Head of ICT Client Services Strategy

More information

CANI Financial Policy and Procedures

CANI Financial Policy and Procedures CANI Financial Policy and Procedures Policy CANI Council is conscious of the need to ensure that all funds received by the organisation are used in accordance with the aims and objectives of CANI; that

More information

Procurement and Contract Management Strategy 2013-2017

Procurement and Contract Management Strategy 2013-2017 Procurement and Contract Management Strategy 2013-2017 Title Owner Version 1 Distribution Procurement and Contract Management Strategy 2013 2017 Procurement and Performance Manager Corporate Issue date

More information

SUFFOLK COUNTY COUNCIL PROCUREMENT RULES. Version 2 Jan 2016. Page 1 of 19

SUFFOLK COUNTY COUNCIL PROCUREMENT RULES. Version 2 Jan 2016. Page 1 of 19 SUFFOLK COUNTY COUNCIL PROCUREMENT RULES 2015 Version 2 Jan 2016. Page 1 of 19 TABLE OF CONTENTS 1. Introduction and Definitions... 3 2. Scope... 4 3. General Principles... 5 4. Responsibilities... 7 5.

More information

ELECTRONIC DOCUMENT AND RECORDS MANAGEMENT SYSTEM REPORT OF THE HEAD OF INFORMATION MANAGEMENT AND TECHNOLOGY

ELECTRONIC DOCUMENT AND RECORDS MANAGEMENT SYSTEM REPORT OF THE HEAD OF INFORMATION MANAGEMENT AND TECHNOLOGY CAB2304 FOR DECISION WARD(S): GENERAL CABINET 13 June 2012 ELECTRONIC DOCUMENT AND RECORDS MANAGEMENT SYSTEM REPORT OF THE HEAD OF INFORMATION MANAGEMENT AND TECHNOLOGY Contact Officer: Tony Fawcett Tel

More information

PM Governance. Executive Team ADCA ADCA

PM Governance. Executive Team ADCA ADCA Item 6.5a Action Plan against the Recommendations Made in the Review of Risk Management Arrangements by PM Governance, November 2014 Key: PM Governance Paul Moore, Risk Consultant ADCA Associate Director

More information

Committees: Dates: Item no. Community and Children's Services Committee Projects Sub 10/07/2015 21/07/2015. Gateway 3/4 Options Appraisal.

Committees: Dates: Item no. Community and Children's Services Committee Projects Sub 10/07/2015 21/07/2015. Gateway 3/4 Options Appraisal. Committees: Dates: Item no. Community and Children's Services Committee Projects Sub 10/07/2015 21/07/2015 Subject: Heating and hot water equipment replacement - Golden Lane Estate. Report of: Director

More information

CENTRAL TABLELANDS ALLIANCE COUNCILS. Consolidated Report: PROCUREMENT, CONTRACTS AND PROJECT MANAGEMENT

CENTRAL TABLELANDS ALLIANCE COUNCILS. Consolidated Report: PROCUREMENT, CONTRACTS AND PROJECT MANAGEMENT CENTRA TABEANDS AIANCE COUNCIS Consolidated Report: PROCUREENT, CONTRACTS AND PROJECT ANAGEENT DRAFT APRI 2011 TABE OF CONTENTS EXECUTIVE SUARY... 1 INTRODUCTION... 1 OBJECTIVES... 1 ETHODOOGY AND SCOPE...

More information

Officer Delegated Decision Report - Procurement. For All Procurement Awards, Waivers, Contract Extensions & Variations

Officer Delegated Decision Report - Procurement. For All Procurement Awards, Waivers, Contract Extensions & Variations G atew a y T h r ee For All Procurement Awards, Waivers, Contract Extensions & Variations Fuel Cards Payment Solutions Contract Requisition Number R000760 Wards All Report authorised by: (Enter name and

More information

Author: Adrian Pengelly Role: Director of Assets. Recommendations: 1. That the review of the Assets Directorate budget pressures for 2014/15 is noted.

Author: Adrian Pengelly Role: Director of Assets. Recommendations: 1. That the review of the Assets Directorate budget pressures for 2014/15 is noted. Cornwall Housing Limited Report Template for DLT Agenda No: 7 Report to: The Board Part 1 Date: 27 July 2015 Title: Assets Directorate Budget Pressures 2014/15 Author: Adrian Pengelly Role: Director of

More information

PROCUREMENT STRATEGY. Charity number SC004401

PROCUREMENT STRATEGY. Charity number SC004401 Charity number SC004401 PROCUREMENT STRATEGY 1.PURPOSE... 2 2.OUR ROLE... 2 3. STRATEGIC VISION... 2 4.SPEND DATA... 3 5. ROAD MAP... 4 6. STRATEGIC INTENT... 4 7. OBJECTIVES... 5 7.1 Efficiency Objectives...

More information

I N T R O D U C T I O N THE PROCESS OF ACQUIRING GOODS WORKS AND SERVICES BY GOVERNMENT PROCURING ENTITIES.

I N T R O D U C T I O N THE PROCESS OF ACQUIRING GOODS WORKS AND SERVICES BY GOVERNMENT PROCURING ENTITIES. I N T R O D U C T I O N Public Procurement means: THE PROCESS OF ACQUIRING GOODS WORKS AND SERVICES BY GOVERNMENT PROCURING ENTITIES. This process includes purchasing, hiring, leasing or any other contractual

More information

Schools and Directorates Funded Projects for building, alteration and decorative works

Schools and Directorates Funded Projects for building, alteration and decorative works University of Sussex Schools and Directorates Funded Projects for building, alteration and decorative works Overview 1. All proposed building, alterations and decorative works to be funded from Schools

More information

POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT

POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT The intent of this policy is to establish a University-wide governance structure for managing contracts and other legally binding documents. The Policy

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

CONFIGURATION COMMITTEE. Terms of Reference

CONFIGURATION COMMITTEE. Terms of Reference SWBTB (8/13) 166 (g) CONFIGURATION COMMITTEE Terms of Reference 1. CONSTITUTION 1.1 The Board hereby resolves to establish a Committee of the Board to be known as the Configuration Committee (The Committee).

More information

NYCC SCHOOL LOANS SCHEME TERMS AND CONDITIONS

NYCC SCHOOL LOANS SCHEME TERMS AND CONDITIONS NYCC SCHOOL LOANS SCHEME TERMS AND CONDITIONS 1.0 PURPOSE 1.1 To detail the terms and conditions of the loans scheme for schools and Pupil Referral Services with delegated budgets through use of reserves

More information

MEMBERS CONSIDER THE RISK STRATEGY AND RECOMMEND APPROVAL TO COUNCIL.

MEMBERS CONSIDER THE RISK STRATEGY AND RECOMMEND APPROVAL TO COUNCIL. Agenda item: 8 Committee: Audit & Standards Committee Date of meeting: 19 th September 2011 Subject: Risk Management Strategy Lead Officer: Head of Finance Portfolio Holder: Resources - Councillor T Oliver

More information

1.1 To provide highlight reports for all the Council s corporately significant projects, covering the period up to the end of June 2006.

1.1 To provide highlight reports for all the Council s corporately significant projects, covering the period up to the end of June 2006. The Executive Agenda item: On 12 September Report Title: Programme Highlight Report June 2006 Forward Plan reference number (if applicable): Report of: The Chief Executive Wards(s) affected: All Report

More information

Welsh Ambulance Services NHS Trust

Welsh Ambulance Services NHS Trust Welsh Ambulance Services NHS Trust Financial Support to replace obsolete Ambulance Vehicles 2008/09 BUSINESS JUSTIFICATION CASE Version No: Page 1 of 10 VERSION HISTORY Version Date Brief Summary of Change

More information

ING Purchase Control. 1Take control of your purchase-to-pay cycle!

ING Purchase Control. 1Take control of your purchase-to-pay cycle! ING Purchase Control 1Take control of your purchase-to-pay cycle! ING Purchase Control Is your purchase process a time consuming activity? Do you want to have more control of your purchaseto-pay cycle

More information

PROCEDURE FS 1 PROCUREMENT POLICY

PROCEDURE FS 1 PROCUREMENT POLICY PROCEDURE FS 1 PROCUREMENT POLICY CONTENTS Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7 Section 8 Section 9 Section 10 Section 11 Section 12 Section 13 Appendix A Appendix B Appendix

More information

APUC Supply Chain Sustainability Policy

APUC Supply Chain Sustainability Policy APUC Supply Chain Sustainability Policy Vision APUC aims to be a leader, on behalf of client institutions, in driving forward the sustainable procurement agenda (please see Appendix 1 for the commonly

More information

JOB PROFILE. Collaborate and work effectively with team members within the section and the rest of the Transformation Service.

JOB PROFILE. Collaborate and work effectively with team members within the section and the rest of the Transformation Service. JOB PROFILE Job Title: Principal Commissioning Officer Consultant 3 Department: Corporate Resources Ref: DCC/14/0344 Section: Transformation Service Job Family: Transformation Job grade: 12 Purpose of

More information

University of Edinburgh Procurement Strategy 2012 16 updated May 2013

University of Edinburgh Procurement Strategy 2012 16 updated May 2013 University of Edinburgh Procurement Strategy 2012 16 updated May 2013 At the University of Edinburgh, we aim to meet our needs for goods, services and works in a way that achieves value for money on a

More information

CABINET 9TH JULY 2015. Report of the Head of Finance and Property Services. Lead Member: Councillor Tom Barkley. Part A

CABINET 9TH JULY 2015. Report of the Head of Finance and Property Services. Lead Member: Councillor Tom Barkley. Part A CABINET 9TH JULY 2015 Report of the Head of Finance and Property Lead Member: Councillor Tom Barkley Part A ITEM 8 ANNUAL PROCUREMENT PLAN 2015/16 UPDATE Purpose of Report This report sets out additions

More information

Cost improvement plans Quality Impact Assessment (QIA)

Cost improvement plans Quality Impact Assessment (QIA) Trust Board in public REPORT TITLE: EXECUTIVE SPONSOR/AUTHOR: AUTHOR Date: 28 November 2013 Agenda Item: 3.2 Cost improvement plans Quality Impact Assessment (QIA) Paul Simpson (Chief Finance Officer)

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Review of Capital Expenditure. Sedgefield Borough Council Audit 2007/08 September 2008

Review of Capital Expenditure. Sedgefield Borough Council Audit 2007/08 September 2008 Review of Capital Expenditure Sedgefield Borough Council Audit 2007/08 September 2008 Contents Summary report 3 Appendix 1 Action plan 10 Status of our reports The Statement of Responsibilities of Auditors

More information

Purchase to Pay Process

Purchase to Pay Process National Financial Regulations Purchase to Pay Process Contents MAIN CHAPTERS Chapter Description Page No. 1. Purchase to Pay (General) 1...3 2. Purchase To Pay Tendering Process...28 3. Purchase to Pay

More information

FINANCIAL MANAGEMENT MATURITY MODEL

FINANCIAL MANAGEMENT MATURITY MODEL Definition: Financial management is the system by which the resources of an organisation s business are planned, directed, monitored and controlled to enable the organisation s goals to be achieved. Guidance

More information

INFORMATION TECHNOLOGY THIRD PARTY SERVICE MANAGEMENT POLICY

INFORMATION TECHNOLOGY THIRD PARTY SERVICE MANAGEMENT POLICY INFORMATION TECHNOLOGY THIRD PARTY SERVICE MANAGEMENT POLICY Version 1.0 FEBRUARY 2007 Document Title: Summary: Information Technology Third Party Service Management Policy This policy defines the Institute

More information

FINANCE AND ASSET MANAGEMENT SUB-COMMITTEE. Meeting held at the Civic Centre, Uxbridge on Tuesday 20 June 2000 at 7.30pm

FINANCE AND ASSET MANAGEMENT SUB-COMMITTEE. Meeting held at the Civic Centre, Uxbridge on Tuesday 20 June 2000 at 7.30pm FINANCE AND ASSET MANAGEMENT SUB-COMMITTEE Meeting held at the Civic Centre, Uxbridge on Tuesday 20 June 2000 at 7.30pm Councillors: Robert Benson John Morse Jonathan Bianco Norman Nunn-Price Steve Carey

More information

SUSTAINABLE PROCUREMENT CENTRE OF EXCELLENCE FOR HIGHER EDUCATION. London Universities Environmental Group 8 th November 2011

SUSTAINABLE PROCUREMENT CENTRE OF EXCELLENCE FOR HIGHER EDUCATION. London Universities Environmental Group 8 th November 2011 SUSTAINABLE PROCUREMENT CENTRE OF EXCELLENCE FOR HIGHER EDUCATION London Universities Environmental Group 8 th November 2011 AGENDA Role of the SPCE Benefits Realisation SPCE Website Capacity Building

More information

A Ready Business has total visibility and control. Seamlessly manage your global telecommuncations in a secure environment

A Ready Business has total visibility and control. Seamlessly manage your global telecommuncations in a secure environment A Ready Business has total visibility and control Seamlessly manage your global telecommuncations in a secure environment 2 We live in a world of rapid and unpredictable change 22% Only 22% of businesses

More information

Procurement Guide. 3.1.12.2 Once you have found the required document, double click and it will upload onto the screen.

Procurement Guide. 3.1.12.2 Once you have found the required document, double click and it will upload onto the screen. 3.1.12 If you need to attach quotes, emails or other documents to the purchase order to adhere to the purchasing delegations and enable the release of the order, click on the Attachments option, which

More information

Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme

Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme Annex 2 is an integral part of the Framework Agreement between the Swiss Federal Council and the Government of the Republic of Poland

More information

Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement

Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement Action Note 14/15 27 August 2015 Issue 1. Raising skills levels within the UK workforce is key to delivering sustainable

More information

Supporting the local economy in Surrey. 14 th June 2012

Supporting the local economy in Surrey. 14 th June 2012 Supporting the local economy in Surrey 14 th June 2012 Surrey Based Suppliers Opening up business opportunities in Surrey. Andrew Forzani Head of Procurement and Commissioning Agenda 6.30pm Welcome by

More information

JE PANEL/BENCHMARKING REF NO: 867/4 EVALUATION DATE:

JE PANEL/BENCHMARKING REF NO: 867/4 EVALUATION DATE: 1. JOB TITLE Job Title: Project Manager (Transport Infrastructure) Reports to: Design Programme Manager Service: Highways and Transport Environment & Infrastructure Date: November 2014 2. JOB PURPOSE To

More information

the Audit Committee.

the Audit Committee. Audit Committee 22 Agenda Item No: 10 Report title Cabinet member with lead responsibility Accountable director Originating service The Introduction of Agresso Councillor Andrew Johnson Resources Keith

More information

Report title : Waiver for the hire and installation of two temporary boilers and one new permanent commercial boiler at Brixton Recreation Centre

Report title : Waiver for the hire and installation of two temporary boilers and one new permanent commercial boiler at Brixton Recreation Centre Officer delegated decision Report title : Waiver for the hire and installation of two temporary boilers and one new permanent commercial boiler at Brixton Recreation Centre Wards: Coldharbour Report Authorised

More information

Sustainable Supply Chain Policy

Sustainable Supply Chain Policy Sustainable Supply Chain Policy 1. Contents Page 2. Introduction & Purpose 1 3. Definitions 1 4. Benefits of a Sustainable approach to the Supply Chain 2 5. Operational Context 2 6. Elements & Principles

More information

NHS Procurement Dashboard: Overview

NHS Procurement Dashboard: Overview NHS Procurement Dashboard: Overview November 2013 You may re-use the text of this document (not including logos) free of charge in any format or medium, under the terms of the Open Government Licence.

More information

CAPITAL INVESTMENT POLICY

CAPITAL INVESTMENT POLICY CAPITAL INVESTMENT POLICY Document Profile Box Document Reference: Version: 0001 Ratified by: Trust Board Date ratified: March 2009 Name of originator/author: Duncan Sellers Name of responsible committee/individual:

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

Director of Nursing & Quality. Helen Coleman Associate Director for Nursing Workforce

Director of Nursing & Quality. Helen Coleman Associate Director for Nursing Workforce Reporting to: Trust Board - March 2015 Paper 8 Title Sponsoring Director Author(s) Nursing Revalidation Director of Nursing & Quality Helen Coleman Associate Director for Nursing Workforce Previously considered

More information

Government has set an aspiration of 25% of expenditure to flow through SMEs either directly or indirectly through the supply chain.

Government has set an aspiration of 25% of expenditure to flow through SMEs either directly or indirectly through the supply chain. DWP Revised SME Action Plan May 2014 Background and objectives The SME agenda is a crucial engine for the Government Growth Agenda and is also a key element of DWP s Commercial Strategy as we look to create

More information

Outcome of Brokerage Services(encompassing payroll) Tender

Outcome of Brokerage Services(encompassing payroll) Tender Report to Cabinet Outcome of Brokerage Services(encompassing payroll) Tender Portfolio Holder: Cllr Jenny Harrison, Social Care & Safeguarding Officer Contact: Maggie Kufeldt, Executive Director - Health

More information

Informatics: The future. An organisational summary

Informatics: The future. An organisational summary Informatics: The future An organisational summary DH INFORMATION READER BOX Policy HR/Workforce Management Planning/Performance Clinical Document Purpose Commissioner Development Provider Development Improvement

More information

DARLINGTON BOROUGH COUNCIL LEARNING & SKILLS SERVICE SUPPLY CHAIN FEES AND CHARGES POLICY 2015/16

DARLINGTON BOROUGH COUNCIL LEARNING & SKILLS SERVICE SUPPLY CHAIN FEES AND CHARGES POLICY 2015/16 DARLINGTON BOROUGH COUNCIL LEARNING & SKILLS SERVICE SUPPLY CHAIN FEES AND CHARGES POLICY 2015/16 1. POLICY STATEMENT 1.1 Darlington Borough Council s Learning & Skills Service (the Service) is funded

More information

The Utilities Exchange Limited

The Utilities Exchange Limited The Utilities Exchange Limited Corporate and Government Energy Procurement Cut costs and carbon use and become more competitive Energy is essential for any business to function and it s cost has a critical

More information

Telecom Expense Management

Telecom Expense Management Telecom Expense Professional Cost Group Ltd. Control your costs Manage your assets Transform your business Visit us online: www.pcmg.co.uk/tem Your Challenges. For most companies, fixed and mobile communications

More information

Committees Date: Subject: Public Report of: For Information Summary

Committees Date: Subject: Public Report of: For Information Summary Committees Audit & Risk Management Committee Finance Committee Subject: Cyber Security Risks Report of: Chamberlain Date: 17 September 2015 22 September 2015 Public For Information Summary Cyber security

More information

Construction (Design and Management) Regulations 2007

Construction (Design and Management) Regulations 2007 MEETING Finance, Procurement and Property Committee AGENDA ITEM 14 MEETING DATE 9 th July 2007 DOCUMENT NUMBER FEP 1052 SUBJECT REPORT Construction (Design and Management) Regulations 2007 (12/06/07) by

More information

Guidelines for Capacity Building and Institutional Framework for e-governance under NeGP

Guidelines for Capacity Building and Institutional Framework for e-governance under NeGP Guidelines for Capacity Building and Institutional Framework for e-governance under NeGP Guidelines for Capacity Building and Institutional Framework for e-governance under NeGP Planning Commission & Department

More information

Business Case - Automotive Purchases and Alternative Solutions

Business Case - Automotive Purchases and Alternative Solutions THE SCOTTISH AMBULANCE SERVICE BOARD FULL BUSINESS CASE FOR THE REPLACEMENT OF EMERGENCY, PATIENT TRANSPORT AND SUPPORT VEHICLES 2009/10-2011/12 Scottish Ambulance Service National Headquarters Tipperlinn

More information

Achieving Excellence in Construction. A manager s checklist. Construction projects

Achieving Excellence in Construction. A manager s checklist. Construction projects Achieving Excellence in Construction A manager s checklist Construction projects Construction projects A manager s checklist This document outlines the key questions that a Senior Responsible Owner (SRO)

More information

Sunbeam House Services Title: Capital Expenditure Policy Policy Document Effective Date: 28 April 2015 Document Control Version Control

Sunbeam House Services Title: Capital Expenditure Policy Policy Document Effective Date: 28 April 2015 Document Control Version Control Document Control Policy Title Capital Expenditure Policy Policy Number 034 Owner Finance Manager Contributors Finance Manager Version 1.0 Date of Production 28 th April 2015 Review date 28 th April 2017

More information

GUIDE ON HOW TO DO BUSINESS WITH LIVERPOOL JOHN MOORES UNIVERSITY

GUIDE ON HOW TO DO BUSINESS WITH LIVERPOOL JOHN MOORES UNIVERSITY GUIDE ON HOW TO DO BUSINESS WITH LIVERPOOL JOHN MOORES UNIVERSITY PRODUCED BY LIVERPOOL JOHN MOORES UNIVERSITY PROCUREMENT SERVICE First Issued - ISSUED 11 th February 2011 VERSION 5.0 updated 13/04/15

More information

CABINET - 26 JULY 2011 REPORT OF THE DIRECTOR OF CORPORATE RESOURCES EAST MIDLANDS SHARED SERVICES: PROCUREMENT OF MANAGED HOSTING SERVICE

CABINET - 26 JULY 2011 REPORT OF THE DIRECTOR OF CORPORATE RESOURCES EAST MIDLANDS SHARED SERVICES: PROCUREMENT OF MANAGED HOSTING SERVICE N CABINET - 26 JULY 2011 REPORT OF THE DIRECTOR OF CORPORATE RESOURCES EAST MIDLANDS SHARED SERVICES: PROCUREMENT OF MANAGED HOSTING SERVICE Purpose 1. The purpose of the report is to: advise Cabinet of

More information

How To Be A Responsible Corporate Social Responsibility (Csr) Organisation

How To Be A Responsible Corporate Social Responsibility (Csr) Organisation CORPORATE SOCIAL RESPONSIBILITY STRATEGY 2013-2018 1 Contents Introduction...3 Our CSR Vision...5 Our CSR Objectives...7 Challenges and barriers...10 Implementation Framework...11 Communication Framework...13

More information

THE COMPLETE GUIDE TO PERFECT PROJECT MANAGEMENT

THE COMPLETE GUIDE TO PERFECT PROJECT MANAGEMENT THE COMPLETE GUIDE TO PERFECT PROJECT MANAGEMENT 1 CONTENTS Introduction 3 Prince2 5 Every as a project tool 6 Major development and building work 7 Further reading and information..9 2 THE COMPLETE GUIDE

More information