CHAPTER 4 PROJECT SCHEDULING

Size: px
Start display at page:

Download "CHAPTER 4 PROJECT SCHEDULING"

Transcription

1 HPTR PROJT SHULING In chapter, the O and ON networks were presented, also the time and cost of individual activities based were calculated. Yet, however, we do not know how long is the total project duration. lso, we need to evaluate the early and late times at which activities start and finish. In addition, since real-life projects involve hundreds of activities, it is important to identify the group of critical activities so that special care is taken to make sure they are not delayed. ll these statements are the basic objectives of the scheduling process, which adds a time dimension to the planning process. In other words, we can briefly state that: Scheduling = Planning + Time. Scheduling is the determination of the timing of the activities comprising the project to enable managers to execute the project in a timely manner. The project scheduling id sued for: - Knowing the activities timing and the project completion time. - Having resources available on site in the correct time. - Making correction actions if schedule shows that the plan will result in late completion. - ssessing the value of penalties on project late completion. - etermining the project cash flow. - valuating the effect of change orders on the project completion time. - etermining the value pf project delay and the responsible parties. onstruction Management 7 r. mad lbeltagi

2 . The ritical Path Method The most widely used scheduling technique is the critical path method (PM) for scheduling. This method calculates the minimum completion time for a project along with the possible start and finish times for the project activities. Many texts and managers regard critical path scheduling as the only usable and practical scheduling procedure. omputer programs and algorithms for critical path scheduling are widely available and can efficiently handle projects with thousands of activities. The critical path itself represents the set or sequence of activities which will take the longest time to complete. The duration of the critical path is the sum of the activities' durations along the path. Thus, the critical path can be defined as the longest possible path through the "network" of project activities. The duration of the critical path represents the minimum time required to complete a project. ny delays along the critical path would imply that additional time would be required to complete the project. There may be more than one critical path among all the project activities, so completion of the entire project could be delayed by delaying activities along any one of the critical paths. For example, a project consisting of two activities performed in parallel that each requires three days would have each activity critical for a completion in three days. Formally, critical path scheduling assumes that a project has been divided into activities of fixed duration and well defined predecessor relationships. predecessor relationship implies that one activity must come before another in the schedule. The PM is a systematic scheduling method for a project network and involves four main steps: - forward path to determine activities early-start times; - backward path to determine activities late-finish times; - Float calculations; and - Identifying critical activities. onstruction Management 7 r. mad lbeltagi

3 . alculations for the ritical Path Method The inputs to network scheduling of any project are simply the O or the ON networks with the individual activity duration defined. The network scheduling process for O and ON networks, however, is different. To demonstrate these two techniques, let s consider a simple -activity project, with activity at the start, followed by three parallel activities,, and ; which are then succeeded by activity. The O or the ON networks of this example are presented in Figure.. etailed analysis of theses O or the ON networks are presented in the following subsections. It is noted that the example at hand involves only simple finish-to-start relationships among activities. () d () () () () d i ctivity (duration) j 7 (a - O) () () () () ctivity (uration) (b - ON) () Figure.: Network example.. ctivity-on-rrow Networks alculations The objective of arrow network analysis is to compute for each event in the network its early and late timings. These times are defined as: - arly event time (T) is the earliest time at which an event can occur, considering the duration of preceding activities. onstruction Management 7 r. mad lbeltagi

4 - Late event time (LT) is the latest time at which an event can occur if the project is to be completed on schedule. Forward Path The forward path determines the early-start times of activities. The forward path proceeds from the most left node in the network (node Figure.) and moves to the right, putting the calculations inside the shaded boxes to the left. ach node in the network, in fact, is a point at which some activities end (head arrows coming into the node), as shown in Figure.. That node is also a point at which some activities start (tail arrows of successor activities). ertainly, all successor activities can start only after the latest predecessor is finished. Therefore, for the forward path to determine the early-start (S) time of an activity, we have to look at the head arrows coming into the start node of the activity. We then have to set the activity S time as the latest finish time of all predecessors. () d () () () () d 7 Figure.: Preparation for the forward path Predecessor Successor Predecessor no. Predecessor Successor Figure.: node in an O network onstruction Management 77 r. mad lbeltagi

5 In this example, the forward path calculations are as follows: - Start at node, the first node of the project, and assign it an early-start time of zero. Here, all activity times use an end-of-day notation. Therefore, the S of activity is zero means that activity starts at end of day zero, or the beginning of day in the project. - Then, move to node. This node receives one head arrow, and as such, it has one predecessor, activity. Since the predecessor started on time zero and has days duration, then, it ends early at time (arly-finish (F) = arly-start (S) + d). ccordingly, the S time of all successor activities to node (activities,, and ) is time. This value is therefore, put in the shaded box on top of node, as shown in Figure.. += Project S+d=F start= += d += d= d += +=7 or 7 += += Figure.: Forward path calculations in O networks - Now, move forward to successor nodes, 7, and. However, since node is linked to nodes and by dummy activities, we begin with nodes and 7. Node receives one head arrow from its predecessor activity, we evaluate the F time of as (S () + d ()). Successor activities to node, therefore, can have an S time of. Similarly, the S time at node 7 is calculated as time. - Moving to node, the F times of its predecessors (d,, and d) are time, 7, and, respectively. ccordingly, the S time of successor activities is the largest onstruction Management 78 r. mad lbeltagi

6 value. Notice that only the largest F value of predecessor activities is used to calculate the S of successor activities and all other values not used. s such, only S values can be directly read from the calculations in Figure.. F values, on the other hand can be calculated as F = S + d. - The last node () receives one head arrow, activity which has an S value of. The F time of activity, therefore = + = time. Since node is the last node, the F of this node becomes the end of the project, reaching total project duration of days. Generally, for any activity x connecting between nodes i and j as shown in Figure., the calculations as follows: Ti LTi ` i x dx Tj LTj j Figure.: ctivity times Tj = Ti + dx (.) In case of more than one arrow terminating at node j, then consider the largest value. ccordingly, Sx = Ti (.) Fx = Sx +dx (.) ackward Path The backward path determines the late-finish (LF) times of activities by proceeding backward from the end node to the starting node of the O network. We put the LF values in the right side boxes adjacent to the nodes, as shown in Figure.. For the example at hand, we do the following: onstruction Management 7 r. mad lbeltagi

7 -= -=, -=, or -= -= d d -= LF-d=LS 7 -= Figure.: ackward path calculations in O networks - Start from the last node of the network (node ) and we transfer the early-finish value from the left box to be the late-finish (LF) value at the right side box. - Then, move backward to node which has only one tail arrow of activity. With the LF time of being time, its LS time becomes LS = LF - d = = time. t node, therefore, time becomes the LF time of the predecessor activities of this node. - Moving backward to predecessor nodes, and 7. Node has one tail arrow of the dummy activity d, and as such, the LF time value to be used at node becomes. Similarly, the LF time value of node 7 becomes. - Moving to node, we evaluate the LS time of its successor activities,, and as,, and, respectively. The LF time at node, therefore, becomes the smallest value. With other LS values not used, the values in the calculation boxes, as such, directly show the LF times of activities. LS times can be calculated as LS = LF d. - Now, proceed to the first node in the network (node ). It connects to one tail arrow of activity. The LS time of, therefore, is LS = LF d = =, a necessary check to ensure the correctness of the calculation. onstruction Management 8 r. mad lbeltagi

8 Having Figure. again in mind and to generalize the calculations, for any activity x connecting between nodes i and j, the calculations as follows: LTi = LTj - dx (.) In case of more than one arrow leaving node i, then consider the smallest value. ccordingly, LFx = LTj (.) LSx = LFx -dx (.) Float alculations Once forward path and backward path calculations are complete, it is possible to analyze the activity times. First, let's tabulate the information we have as shown in Table.. One important aspect is Total-Float (TF) calculations, which determine the flexibility of an activity to be delayed. Notice in Table. that some activities such as activity has S time = LS time, and its F time = LF time, indicating no slack time for the activity. Other activities such as can start early at time and late at time, indicating a -day of total float. Float calculations can be illustrated as shown in Figure.7 for any activity. Table.: PM results ctivity uration arly Start (S) Late Finish (LF) Late Start (LS) arly Finish (F) Total Float (TF) ritical ctivity Yes No 7 No Yes Yes Figure.7 shows two ways of scheduling each activity using its activity times. One way is to schedule it as early as possible (using its S time). The other way is as late as onstruction Management 8 r. mad lbeltagi

9 possible (using its LS time). The activity float can, therefore, be represented by the following relationships: Total Float (TF) = LF F (.7) = LS S (.8) i Name duration = d j T LT T LT S = Ti Tj LF = LTj a) ctivity is early S F=S+d Total Float d LF b) ctivity is late S Total Float LS=LF-d d d Free Float (FF) Total time available for the activity = LF - S LF Figure.7: Float calculations lso, with the S and LF times directly read from the boxes used in forward and backward path calculations, the total float can also be calculated as; TF = LF S d. Using these relationships, activities total floats are calculated as shown in Table.. nother type of float often used in network analysis is the Free Float, which can be calculated as: Free Float (FF) = Tj Ti d (.) or FF = smallest S (of succeeding activities) F (of current activity) (.) The free float defines the amount of time that an activity can be delayed without affecting any succeeding activity. With free float available for an activity, a project manager onstruction Management 8 r. mad lbeltagi

10 knows that the float can be used without changes the status of any non-critical activity to become critical. Identifying the ritical ctivities ctivities with zero total floats mean that they have to be constructed right at their schedule times, without delays. These activities are considered to be critical. They deserve the special attention of the project manager because any delay in critical activities causes a delay in the project duration. One interesting observation in the results of PM analysis is that critical activities form a continuous path of the critical activities that spans from the beginning to the end of the network. In our example, activities,, and (excluding dummy activities) are critical and the critical path is indicated by bold lines on Figure.. Notice that among the paths in this example (--; --; and --e), the critical path is the longest one, an important characteristic of the critical path. In real-life projects with many activities, it is possible that more than one critical path are formed. y definition, the length of these critical paths is the same... Precedence iagram Method (PM) Precedence iagram Method (PM) is the PM scheduling method used for ON networks and it follows the same four steps of the PM for O method. Forward Path Forward path can proceed from one activity to the other; the process is as follow (Figure.8): - t activity. It is the first activity in the network. We give it an early-start (S) of in the left top box. dding the activity duration, we determine the F time of the activity and we put it in the top right box. onstruction Management 8 r. mad lbeltagi

11 () () 7 (), 7, or () arly start alry Finish Name (duration) Late start Late finish () Figure.8: Forward Path in PM nalysis - Then, move forward to the succeeding activities,, and. These three activities have only as a predecessor with time as its F. s such, all the three activities can start as early as time (S = ). ach activity, accordingly, has its own F time based on its duration. - Moving forward to activity. This activity has predecessors ( head arrows) of activities,, and with their largest F time being. The S of activity, thus, with becomes time. dding its duration, the F becomes time. To generalize the calculations consider Figure., of two activities i and j with relationship finish to start and overlap between them. Overlaps will have a positive sign, while lags will have a negative sign. The forward path calculations are as follows: Si Fi i (di) LSi LFi overlap ij Sj Fj j (dj) LSj LFj Figure.: ctivities times in PM nalysis Sj = Fi - overlap ij (.) In case of more than one activity precedes activity j then consider the maximum. Then, apply quation. to calculate the early finish times. onstruction Management 8 r. mad lbeltagi

12 ackward Path Once the forward path is finished, the backward path can start, moving from the last activity to the first, putting the calculations in the bottom two boxes of each activity, as shown in Figure.. The process is as follows: () (),, or arly start arly Finish Name (duration) Late start Late finish 7 () () () Figure.: ackward path in PM analysis - Start at the last activity and we transfer the early-finish value to become the activity's late-finish (LF) time. Then, subtracting the activity's own duration, the latestart (LS) time is calculated as time and put in the bottom left box of the activity. - Moving backward to activities,, and all have one successor (activity ) with LS time of. The LF of all these activities becomes time. ach activity then has its own LS time, as shown in Figure.. - Moving to activity. The activity is linked to tail arrows (i.e., has successors) of activities,, and. The LF of activity, thus, is the smallest of its successors' LS times, or time. ctivity then has LS equals zero. onsidering Figure. again, the backward path calculations are as follows: LFi = LSj + overlap ij (.) onstruction Management 8 r. mad lbeltagi

13 In case of more than one activity succeeds activity j then consider the minimum. Then, apply quation. to calculate the late start times. Notice that by the end of the backward path, all activity times can be read directly from the boxes of information on the activity, without additional calculations. This also, makes it simple to calculate the total float of each activity using the same relationships used in the O analysis. Identifying ritical ctivities ritical activities can also be easily determined as the ones having zero float times, activities,, and. The critical path is then shown in bold as Figure.. The PM analysis, as explained, is a straight forward process in which each activity is considered as an entity that stores its own information.. Time-Scaled iagrams Time-scaled diagrams are used extensively in the construction industry. Such diagrams enable one to determine immediately which activities are scheduled to proceed at any point in time and to monitor field progress. lso, it can be used to determine resources need. The time scale used in time-scaled diagrams can be either the calendar dates or the working periods (ordinary dates), or using both at the same time. The activities are represented as arrows that drawn to scale to reflect the activity duration it represents. The horizontal dashed lines represent total float for groups of activities and free float for the immediate activity to the left of the dashed line. The precedence of an activity is the immediate activities before it or that linked to it through vertical dashed lines. The name and the duration of an activity are written above and below the arrow representing it respectively (Figure.). The S, F, and FF times of the activities can be easily read directly from the diagram. The TF for an activity is the smallest sum of succeeding FF on all paths. ccordingly, the LS and LF times can be easily calculated as follows: onstruction Management 8 r. mad lbeltagi

14 LSi = Si + TFi (.) LFi = LSi + i (.) The critical path can be easily determined as the continuous lines from the beginning to the end of the network with any dashed lines. The main advantage of this diagram is its simple representation and it can be sued directly for determining resources need. However, its disadvantage is that it needs a great effort to be modified or updated. lso, it cannot be used to represent overlapping activities. Figure. shows the time-scaled diagram for the same -activities project solved previously using O and ON networks. 7 8 Figure.: Time-scaled diagram The TF for activity equals the smallest of the sum of the floats along all paths from the end of activity to the end of the project. The float on path =, path = and path =, then the TF of activity =. The calculations are shown in Table.. Table. Time-scaled diagram calculations ctivity S F FF TF LF=F+TF LS=LF-d 7 onstruction Management 87 r. mad lbeltagi

15 . Schedule Presentation fter the O and ON calculations are made, it is important to present their results in a format that is clear and understandable to all the parties involved in the project. The simplest form is the ar chart or Gantt chart, named after the person who first used it. bar chart is a time versus activity chart in which activities are plotted using their early or late times, as shown in Figures. a and b. arly bar chart is drawn using the S times of activities, while the late bar chart is drawn using the LS times. a) ctivity d= S = d= TF= S= d= TF= S= d= S= S= d= 7 8 Time ctivity b) d= LF= TF= d= TF= d= d= LF= LF= LF= d= LF= 7 8 Time Figure.: a) arly bar chat b) Late bar chart The bar chart representation, in fact, shows various details. Float times of activities, critical activities can be shown in a different color, or bold borders, as shown in Figure.. The bar chart can also be used for accumulating total daily resources and / or costs, as shown at the bottom part of Figure.. In this figure, the numbers on each activity represent the number of labors needed. onstruction Management 88 r. mad lbeltagi

16 ctivity 7 8 Time Profile of the labor resource demand Total labors Figure.: Using bar chart to accumulate resources One additional benefit of the bar chart is its use on site to plot and compare the actual progress in the various activities to their scheduled times. n example is shown on Figure., showing actual bars plotted at the bottom of the original bars of the schedule.. riticisms to Network Techniques The PM and PM analyses for network scheduling provide very important information that can be used to bring the project to success. oth methods, however, share some drawbacks that require special attention from the project manager. These drawbacks are: - ssume all required resources are available: The PM calculations do not incorporate resources into their formulation. lso, as they deal with activity durations only, it can result in large resource fluctuations. ealing with limited resources and resource leveling, therefore, has to be done separately after the analysis; onstruction Management 8 r. mad lbeltagi

17 - Ignore project deadline: The formulations of PM and PM methods do not incorporate a deadline duration to constrain project duration; - Ignore project costs: Since PM and PM methods deal mainly with activities durations, they do not deal with any aspects related to minimize project cost; - Use deterministic durations: The basic assumption in PM and PM formulations is that activity durations are deterministic. In reality, however, activity durations take certain probability distribution that reflect the effect of project conditions on resource productivity and the level of uncertainty involved in the project.. Solved xamples.. xample For the project data in Table., answer the following questions: a) raw an O network of the project? b) Perform forward path and backward path calculations? c) What is the effect of delaying activity by days? Table.: ata for xample ctivity F G uration Immediate predecessor -,, F onstruction Management r. mad lbeltagi

18 Solution a, b) or or or 8 G F ritical or c) Total float of activity = LF S d = 8 =. Then delaying activity by day more than its total float will cause a net delay in the whole project by day to become 7 days... xample Perform PM calculations for the small project below and determine activity times. urations are shown on the activities. I () () () G () () J (7) L () () () H () F () K () onstruction Management r. mad lbeltagi

19 Solution 7 I () () or () () 7 () () 7 7 G () 7 or 7 H () 7 or 8 or 7 J (7) 7 or or L () S F Name (duration) LS LF F () 8 K () ritical path.. xample For the activities listed in the table below, draw the time-scaled diagram and mark the critical path. etermine the completion time for the project. Tabulate activities times and floats. ctivity uration Predecessor F G H I J ,, F, G - G, I onstruction Management r. mad lbeltagi

20 Solution H 8 F G 8 I J 7 7 ctivity S F TF FF LS LF F G H I J xample Perform PM calculations for the small on network shown here. Pay special attention to the different relationships and the lag times shown on them. SS= () () () () () FF= onstruction Management r. mad lbeltagi

21 Solution () S Name (duration) LS SS= or or (-+) F LF += () 7 7 () 7 () -=, 7 or (+-) 7 () 7 FF=.7 xercises. The free float is defined as: a. The amount of time an activity can be delayed without affecting the following activity. b. The amount of time an activity can be delayed without affecting total project duration.. Total float equals: a. Late finish minus early finish c. Late start minus early start b. Late finish minus (early start + duration) d. ll of the above. State True (T) or False (F): a. The critical activities can be determined easily when using the bar chart. b. The network must have definite points of beginning and end. c. The network must be continuous from start to end. d. There s no dummy activities in the arrow networks, e. forward pass is used to determine late start and late finish times. onstruction Management r. mad lbeltagi

22 f. The time for completing a project is equal to the sum of the individual activity times.. For the Following project data, answer the following questions: ctivity uration (days) Predecessor F G --,, F a. raw an O network and perform forward and backward pass calculations? b. raw an ON network and perform forward and backward pass calculations? c. raw a time-scaled diagram of the project? d. Tabulate activities S, F, LS, LF, TF, and FF. e. What is the effect of delaying activity by days?. For the following O network, determine the following: a. alculate S, LF, & TF for all activities. Identify critical ones. b. raw an early ar hart for the project. c. What is the effect of delaying activity H by two days on the total project duration? () 7 7 onstruction Management r. mad lbeltagi

23 . Perform PM calculations for the project below and determine activity times. urations are shown on the activities I () () () G () () J (7) L () () () H () F () K () 7. gas station is proposed to be built on an already developed site. It will consist essentially of a sales outlet and an office block. The sales outlet comprises of cash office and gas pumps. The manager s office building, which also houses public washrooms and an air compressor, is called the office block. djacent to pumps will be a concrete pit that will house the gas tanks. The entire area, excluding the office and pumps site, is covered with a concrete slab, and there is a low perimeter wall in the rear. The utility company has undertaken to install an electric meter on the site and connect it to the mains. Gasoline pumps must be obtained from the manufacturers, and after being installed, they are to be connected to the gasoline tanks and the power supply. efore use the local authority to ensure safety and compliance with regulations must inspect them. Gasoline tanks are housed in concrete pits and covered by concrete slabs. efore they are covered, however, the tanks and the associated pipe work have to be inspected by the local authority. The sales outlet base is excavated first, the pipe work and tanks second, the office block third, and the onstruction Management r. mad lbeltagi

24 trench for underground services last. fter the excavation for the tanks and pipe work is completed, work can proceed on the construction of the perimeter wall and air points. No ctivity escription uration F G H I J K L M N O P Q R S T U V W X Y Z FF xcavate for sales outlet onstruct sales outlet base onstruct cash office Obtain pumps Install pumps onnect pumps Inspector approves pumps installation Paint & furnish office & washrooms onnect office & toilet lighting xcavate for office block onstruct office block uild office & washrooms + services Install electric meter onnect main cable to meter Install area lighting Mobilize site Set out and level site xcavate & lay underground services xcavate for pipes and tanks onstruct concrete pit Obtain pipes and tanks Install pipes and tanks Obtain compressor Install compressor onnect power to compressor Inspection of compressor ackfill and cover tanks Pour concrete slab onstruct perimeter wall + air points onnect air points emobilize and clean site Inspection of pipes and tanks onstruction Management 7 r. mad lbeltagi

25 ompressed air for inflated tires will be supplied by an electrically driven compressor, which must be inspected by a competent person before the compressor is put into use. The air lines to the free air points are installed with the general underground services, and the points themselves are mounted on the perimeter wall. The air pints can be hooked up after the concrete slab has been poured. Mobilization to start work comprises, among other preparations, the moving of a trailer to the site to store tools, furnishings, and any weather prone parts and to serve as the site office. Similarly, when work at the site is completed, the trailer will be removed, and all scaffolding and construction equipment taken away. This is known as demobilization and clean up of site. You are required to determine the project duration, critical path(s), and tabulate activity times (S, F, LS, LF, TF, and FF). 8. For the following list of activities, draw a time-scaled diagram and mark the critical path. etermine activities S, F, LS, LF, FF, and TF. ctivity uration (days) Predecessor F G H I J K L M --,, F,, G, H I J K, L onstruction Management 8 r. mad lbeltagi

26 . For the following PM, perform the forward pass and backward pass calculations. etermine the project duration and critical path. Tabulate the S, F, LS, LF, TF, and FF information for each activity. 7 FF7 SS, FF 8 SS FF F SS8 G SF 8 SS8 J FS H FF I 8 onstruction Management r. mad lbeltagi

Project Scheduling. Introduction

Project Scheduling. Introduction Project Scheduling Introduction In chapter, the O and ON networks were presented, also the time and cost of individual activities based were calculated. Yet, however, we do not know how long is the total

More information

CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING

CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING CRITICAL-PATH ANALYSIS FOR NTWORK SCHULING From studying this section, you will be able to: - Perform CPM and PM analyses for AOA and AON networks; - Calculate the early / late times that an activity can

More information

Resources Management

Resources Management Resources Management. Introduction s we have seen in network scheduling, the basic inputs to criticalpath analysis are the individual project activities, their durations, and their dependency relationships.

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Precedence Diagram Method. CSTM 462 Planning & Scheduling Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.

More information

Large Scale Systems Design G52LSS

Large Scale Systems Design G52LSS LSS antt harts Lecture 8 antt harts and PM onstructing antt harts Staff Profile and Utilisation Learning outcomes: interpret the information in antt charts; construct antt charts following Pert/PM method;

More information

Time Planning and Control

Time Planning and Control TOBIC 4 TIM SCLD NTWORK 1 June 3013 Time Planning and Control Time-Scaled Network G404 NGINRING MNGMNT 1 TOBIC 4 TIM SCLD NTWORK 1 June 3013 Processes of Time Planning and Control 1. Visualize and define

More information

Chapter-6. Developing a Project Plan

Chapter-6. Developing a Project Plan MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies

More information

Large Scale Systems Design G52LSS

Large Scale Systems Design G52LSS Large Scale Systems esign 52LSS Lecture 6 Project Scheduling With PRT Project Scheduling PRT iagrams onstructing Pert iagrams Learning outcomes: describe the purpose and steps of project scheduling within

More information

Project Control. 1. Schedule Updating

Project Control. 1. Schedule Updating Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools

More information

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

Network Planning and Analysis

Network Planning and Analysis 46 Network Planning and Analysis 1. Objective: What can you tell me about the project? When will the project finish? How long will the project take (project total duration)? 2. Why is this topic Important

More information

Project Scheduling by PERT/CPM

Project Scheduling by PERT/CPM Project Scheduling by PERT/PM Reference ooks: nderson, Sweeney, and Williams, N INTROUTION TO MNGEMENT SIENE, QUNTITTIVE PPROHES TO EISION MKING, th edition, West Publishing ompany,99 Hamdy. Taha, OPERTIONS

More information

2.3.5 Project planning

2.3.5 Project planning efinitions:..5 Project planning project consists of a set of m activities with their duration: activity i has duration d i, i = 1,..., m. estimate Some pairs of activities are subject to a precedence constraint:

More information

Project Scheduling: PERT/CPM

Project Scheduling: PERT/CPM Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times (as in exercises 1, 2, 3 and 5 in the handout) and considering Time-Cost Trade-Offs (as in exercises 4 and 6 in the handout). This

More information

Chapter 2: Project Time Management

Chapter 2: Project Time Management Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.

More information

Module 3: The Project Planning Stage

Module 3: The Project Planning Stage Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you

More information

Operational Research. Project Menagement Method by CPM/ PERT

Operational Research. Project Menagement Method by CPM/ PERT Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your

More information

Topic: The easiest way to calculate Critical Path, Total Float, Free Float, Early Start, Early Finish, Late Start, and Late Finish.

Topic: The easiest way to calculate Critical Path, Total Float, Free Float, Early Start, Early Finish, Late Start, and Late Finish. Hot Topics & hallenges Time Management Topic: The easiest way to calculate ritical Path, Total Float, Free Float, Early, Early, Late, and Late. Presenter: Sohel khter, PMP, N,ISMS PMP and Six Sigma instructor,

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Performing critical path analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the

More information

Project Planning and Scheduling

Project Planning and Scheduling Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination

More information

Scheduling. Anne Banks Pidduck Adapted from John Musser

Scheduling. Anne Banks Pidduck Adapted from John Musser Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart

More information

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking

More information

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761 Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity

More information

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

12 CRITICAL PATH ANALYSIS

12 CRITICAL PATH ANALYSIS 1 RTL PT NLYSS hapter 1 ritical Path nalysis Objectives fter studying this chapter you should be able to construct activity networks; be able to find earliest and latest starting times; be able to identify

More information

CHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS

CHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS 33 CHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS 4.1 BASICS OF LINEAR SCHEDULING The LSM is a graphical technique in which the locations or the length of the linear project is indicated

More information

2.3.4 Project planning

2.3.4 Project planning .. Project planning project consists of a set of m activities with their duration: activity i has duration d i, i =,..., m. estimate Some pairs of activities are subject to a precedence constraint: i j

More information

Time Management. Part 5 Schedule Development. Richard Boser

Time Management. Part 5 Schedule Development. Richard Boser Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms

More information

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method

More information

ME 407 Mechanical Engineering Design Spring 2016

ME 407 Mechanical Engineering Design Spring 2016 ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,

More information

Collaborative Scheduling using the CPM Method

Collaborative Scheduling using the CPM Method MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines

More information

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical

More information

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides

More information

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define

More information

Introduction to Project Management

Introduction to Project Management L E S S O N 1 Introduction to Project Management Suggested lesson time 50-60 minutes Lesson objectives To be able to identify the steps involved in project planning, you will: a b c Plan a project. You

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing

More information

CHAPTER 1. Basic Concepts on Planning and Scheduling

CHAPTER 1. Basic Concepts on Planning and Scheduling CHAPTER 1 Basic Concepts on Planning and Scheduling Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the selection and ordering of activities as well as

More information

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

SESSION 4 PLANNING THE PROJECT PROJECT PLANNING DEFINITIONS

SESSION 4 PLANNING THE PROJECT PROJECT PLANNING DEFINITIONS SSSION 4 PLNNIN TH PROJT PROJT PLNNIN Scope planning Time planning ost planning Human resource planning Procurement planning Quality planning ommunication planning INITIONS The project plan is a list of

More information

Project Management. Week 4- Project Planning and Network Diagrams 2012-13

Project Management. Week 4- Project Planning and Network Diagrams 2012-13 Project Management Week 4- Project Planning and Network Diagrams 2012-13 Last Week Project Appraisal Techniques Scoping Tools-Breakdown Structures Estimation This Week What is Planning? Purpose of Planning

More information

The work breakdown structure can be illustrated in a block diagram:

The work breakdown structure can be illustrated in a block diagram: 1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as

More information

Basic CPM Calculations

Basic CPM Calculations Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.

More information

Cambridge International AS and A Level Computer Science

Cambridge International AS and A Level Computer Science Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

8. Project Time Management

8. Project Time Management 8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project

More information

EdExcel Decision Mathematics 1

EdExcel Decision Mathematics 1 EdExcel Decision Mathematics 1 Notes and Examples Critical Path Analysis Section 1: Activity networks These notes contain subsections on Drawing an activity network Using dummy activities Analysing the

More information

Critical Path Analysis

Critical Path Analysis Chapter 13 Critical Path Analysis Basic Concepts Activity An activity is any portion of a project which consumes time or resources and has a definable beginning and ending. For example, laying of pipe

More information

Lecture 26 CPM / PERT Network Diagram

Lecture 26 CPM / PERT Network Diagram Lecture 26 CPM / PERT Network Diagram 26.1 Introduction to CPM / PERT Techniques CPM (Critical Path Method) was developed by Walker to solve project scheduling problems. PERT (Project Evaluation and Review

More information

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead

More information

Project Management 1. PROJECT MANAGEMENT...1 2. PROJECT ANALYSIS...3

Project Management 1. PROJECT MANAGEMENT...1 2. PROJECT ANALYSIS...3 Project Management What is a project? How to plan a project? How to schedule a project? How to control a project? 1. PROJECT MNGEMENT...1 2. PROJECT NLYSIS...3 3 PROJECT PLNNING...8 3.1 RESOURCE LLOCTION...8

More information

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety

More information

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for

More information

Use project management tools

Use project management tools Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding

More information

Computer Training Centre University College Cork

Computer Training Centre University College Cork Computer Training Centre University College Cork Project 2013 Table of Contents What's new in Project 2013... 1 Manual scheduling... 1 Graphical Reports... 1 Trace task paths... 1 Easier view customization...

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Unit 1: Project Planning and Scheduling

Unit 1: Project Planning and Scheduling Unit : Project Planning and Scheduling Objective Ð To provide a brief introduction to project planning and scheduling. The critical area where project management meets system development. ackground Most

More information

CRITICAL PATH ANALYSIS AND GANTT CHARTS

CRITICAL PATH ANALYSIS AND GANTT CHARTS CRITICAL PATH ANALYSIS AND GANTT CHARTS 1. An engineering project is modelled by the activity network shown in the figure above. The activities are represented by the arcs. The number in brackets on each

More information

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget

More information

Project Planning Tools. GANTT Chart. Chapter 7 Project Planning. GANTT Chart (Figure 7.3) CPM Chart (Figure 7.12) PERT Chart (Figure 7.

Project Planning Tools. GANTT Chart. Chapter 7 Project Planning. GANTT Chart (Figure 7.3) CPM Chart (Figure 7.12) PERT Chart (Figure 7. Project Planning ools hapter 7 Project Planning Lecture 2 Project Planning nd Management ools GN hart (Figure 7.) PM hart (Figure 7.2) P hart (Figure 7.5) GN: eveloped by Henry Gantt PM: ritical Path Method

More information

CHAPTER 8 PROJECT TIME-COST TRADE-OFF

CHAPTER 8 PROJECT TIME-COST TRADE-OFF CHAPTER 8 PROJECT TIME-COST TRADE-OFF In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often vary

More information

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

Construction Project Scheduling

Construction Project Scheduling Construction Project Scheduling Produced and Distributed by Engineer Educators 857 East Park Avenue Tallahassee, FL 32301 1 Disclaimer The material in this course manual is not meant to infringe on any

More information

Scheduling Best Practices

Scheduling Best Practices In a continuing series of articles on specific aspects of critical path method (CPM) scheduling, Warner examines various facets of the process of preparing, analyzing and utilizing schedules in project

More information

A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com

A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com 2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com

More information

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule

More information

Chapter 4: Project Time Management

Chapter 4: Project Time Management Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed

More information

Figure out the early start and early finish. Early start. Early finish

Figure out the early start and early finish. Early start. Early finish Figure out the early start and early finish oming up with the float for each activity is useful, but you can actually do better! When you have a long critical path, but the other paths in your network

More information

Project Scheduling: PERT/CPM

Project Scheduling: PERT/CPM Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project

More information

CHAPTER 3 PROJECT PLANNING

CHAPTER 3 PROJECT PLANNING HPTER 3 PROJET PLNNING This chapter deals with preparing projects plans in terms of defining: work breakdown structure, activities, logical relations, durations and activities direct cost. Terminology

More information

SE351a: Software Project & Process Management

SE351a: Software Project & Process Management SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management

More information

Priori ty ... ... ...

Priori ty ... ... ... .Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared

More information

Leaving Certificate Technology. Project Management. Student Workbook

Leaving Certificate Technology. Project Management. Student Workbook Leaving Certificate Technology Project Management Student Workbook Project Management Student notes Introduction Project management is the name given to a number of techniques used in industry to manage

More information

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate

More information

Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.

Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment. Unit : P lanning construction work processes and efficient use of resources in construction and the. Links This topic links to: HNC in Construction and the Built Environment Unit : LO; HNC Unit 15: LO.

More information

Project Time Management

Project Time Management CHAPTER 8 Project Time Management The project scope identifies the objectives of the project, what activities will be performed, and some of the activities that are not included in the project. The scope

More information

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,

More information

Dashboards and Reporting for Program Management

Dashboards and Reporting for Program Management MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will

More information

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards... SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement

More information

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project

More information

Research on Task Planning Based on Activity Period in Manufacturing Grid

Research on Task Planning Based on Activity Period in Manufacturing Grid Research on Task Planning Based on Activity Period in Manufacturing Grid He Yu an, Yu Tao, Hu Da chao Abstract In manufacturing grid (MG), activities of the manufacturing task need to be planed after the

More information

Critical Path Method (CPM)

Critical Path Method (CPM) Project Management Templates (CPM) http://spreadsheetml.com/projectmanagement/criticalpathanalysis.shtml Copyright (c) 2009-2010, ConnectCode All Rights Reserved. ConnectCode accepts no responsibility

More information

An Introduction to the Management Principles of Scheduling

An Introduction to the Management Principles of Scheduling College of Engineering VDOT-VT Partnership for Project Scheduling Charles Edward Via, Jr. Department of Civil and Environmental Engineering 200 Patton Hall (0105) Blacksburg, Virginia 24061 540/231-0923

More information

Scheduling Resources and Costs

Scheduling Resources and Costs Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used

More information

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added. Chapter 3 Effort Driven Task Type By now, you will be getting sick of my repetition of the effort driven formula: Resource Units X Duration = Work I make no apologies, as it needs to be engraved in the

More information

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2010-11 Session 5 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides

More information

PROGRAMMING TECHNIQUES. Chapter 5(Part 2)

PROGRAMMING TECHNIQUES. Chapter 5(Part 2) PROGRAMMING TECHNIQUES Chapter 5(Part 2) LEARNING OUTCOME At the end of this lesson, students will be able to: Understand the different types of planning techniques. Understand the network analysis. Formulate

More information

EXHIBIT 2-2-C PROGRESS SCHEDULES

EXHIBIT 2-2-C PROGRESS SCHEDULES EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,

More information

Chapter 11 Monte Carlo Simulation

Chapter 11 Monte Carlo Simulation Chapter 11 Monte Carlo Simulation 11.1 Introduction The basic idea of simulation is to build an experimental device, or simulator, that will act like (simulate) the system of interest in certain important

More information

Leaving Certificate Technology. Project Management. Teacher Notes

Leaving Certificate Technology. Project Management. Teacher Notes Leaving Certificate Technology Project Management Teacher Notes 1 Project Management This is the first of three key topics that form Project and Quality Management in the Technology Syllabus core. These

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities

More information

Project Initiation and Revision Training Manual. Table of Contents

Project Initiation and Revision Training Manual. Table of Contents for Engineering and Construction v.4.1 Project Initiation and Revision Training Class Conducted by Evans Technology June 2005 Table of Contents Introduction to Primavera... 3 Project Management (P3eC)...

More information

B. 2-4-6 D. 3-4-5 E. 3-5-7 F. 5-7-9

B. 2-4-6 D. 3-4-5 E. 3-5-7 F. 5-7-9 Lesson 01 Project Management Solutions #1: The network diagram for a project is shown below, with three time estimates (optimistic, most likely, and pessimistic) for each activity. Activity times are in

More information