1 EDR s Cx Assistant: Helping Commissioning Teams Choose the Appropriate Level Treasa Sweek CTG Energetics, Inc. Ken Gillespie Pacific Gas & Electric Company Synopsis Cx Assistant is a free web-based assistance tool developed under Savings By Design, California's public goods funded state-wide new-construction energy efficiency program. The tool is part of the program s educational component, Energy Design Resources. The tool is intended to help new-construction commissioning teams initiate the commissioning process for projects in California. To date the tool contains the following modules: Scope Generator (RFP/RFQ) Commissioning Cost Estimator Design Intent Generator Basis of Design Generator Commissioning Specifications Generator Sequences of Operation Generator The paper explains Cx Assistant s approach to recommending a commissioning process. It also discusses how these recommendations affect the tool's output. About the Author(s) Treasa Sweek provides commissioning, energy audits, and energy simulation for commercial and municipal buildings. Treasa also has experience in the evaluation of building projects for cost effectiveness and performance verification. She has provided energy analysis for many commercial, institutional, and military facilities and has conducted electrical and mechanical energy audits for over 75 buildings totaling more than six million square feet. Treasa is a professionally registered Mechanical Engineer in California and Washington, a member of the California Commissioning Collaborative advisory board, the chair of the BCA s Administration Committee, and a corresponding member of ASHRAE s technical committee on commissioning. Ken Gillespie is a Technologist with the Performance Test and Analysis unit of PG&E's Technical & Ecological Services department in San Ramon, California. He has 25 years of performance test and monitoring experience in utility and building applications, with the past 15 years primarily focused on monitoring and commissioning of energy using systems in existing buildings. He is an Associate Member of ASHRAE. He is past vice chair of both Guideline Project Committee (GPC) 14P: The Measurement of Energy and Demand Savings, published in 2002 and GPC R: The HVAC Commissioning Process, published in He is

2 currently a member of ASHRAE's TC7.6: Systems Energy Utilization; GPC-20P: XML Definitions for HVAC&R; and GPC R. Ken is a founding member of the California Commissioning Collaborative and currently is a member of its advisory board. Introduction Savings By Design s Energy Design Resources (EDR) Program is a growing source of information on commissioning for design teams and building owners. In the past EDR has supported development of commissioning resources such as a Design Brief, a reference manual, and an interactive tool to guide users through various aspects of the commissioning process. As of February 2004, a new web-based reference tool enhances those EDR materials and provides updated information that reflects current trends in the commissioning world. The goal of this tool, dubbed "Cx Assistant," is to increase the adoption of high quality commissioning practices by helping owners and providers choose an appropriate range of commissioning services. The tool also is intended to provide example documents to get commissioning started in the right direction. It provides information to assist with a variety of commissioning related activities, from development of a request for proposal document (RFP) to creating better construction documents and tracking the building s overarching goals. Figure A. This excerpt of the cost-estimating tool in Cx Assistant shows a range of probable commissioning costs for a medium-sized office building. What is Cx Assistant? Energy Design Resources' Cx Assistant is a web-based reference designed to provide project specific commissioning information to the design team. The tool enables users to accomplish the following: 1. Evaluate probable commissioning cost. 2. Identify the appropriate commissioning scope for each project, and develop sample scope documents. 3. Develop a sample design intent document summarizing the owner s requirements with specific project inputs. 4. Develop a sample basis of design document with specific project inputs. 5. Access sample commissioning specifications related to specific project inputs. 6. View sample sequence of operations for their HVAC equipment.

3 In addition, Cx Assistant incorporates the most current trends in the commissioning industry by providing multiple paths graded into levels of commissioning services according to a project s size and the needs of the owner. LEVEL 1. The first level focuses on large or complex building projects that may include detailed sustainable design characteristics or cutting edge energy saving design elements. This level is called "comprehensive" commissioning and can also be used as a basis for wholebuilding commissioning or advanced LEED i Green Building commissioning. LEVEL 2. The second level focuses on standard commercial buildings that may include projects aiming to achieve a basic LEED Green Building Certification. This level is also appropriate for incorporating a commissioning quality assurance process into building projects as a matter of course and is called standard commissioning. LEVEL 3. The third level focuses on small, uncomplicated buildings and is referred to as "abbreviated" commissioning. Abbreviated commissioning is applicable to buildings without much complex energy-using equipment, but for which an owner desires to implement a commissioning quality assurance process. The levels of commissioning are used by Cx Assistant to tailor the tool s outputs to an appropriate level. Cx Assistant is focused on mass market building types as well as more complex building types in order to reach a broad audience throughout California s new construction sector. Occupancy types include: office, school, university, laboratory, library, auditorium/theatre, convention, grocery, retail/wholesale, restaurant, medical, high-bay industrial use, low-bay industrial use, and non-residential mixed use. How are Commissioning Levels determined? When a user enters Cx Assistant, the tool requests general information regarding a building project. This information includes the building s occupancy type, approximate square footage, location, and delivery method (i.e. plans & specs or design-build). The user can also choose a specific level of commissioning or let the tool recommend a level. The difference between commissioning levels is described below. Abbreviated Commissioning Abbreviated commissioning recognizes the need for an abbreviated, non-third party commissioning process. Since general contractors use the term commissioning as well as mechanical and electrical contractors, air balance specialists, turnkey contractors and a host of engineers and consultants, this term captures a multitude of activities and processes. ii Engineering research groups and professional societies around the country tend to discount the commissioning processes employed by contractors. However, denying the contractors commissioning activities creates a rift in the community, which only furthers an owner s confusion and a commissioning team s frustration when initiating a commissioning process.

4 Instead, it is important to bridge the division by contemplating cases where the non-third party model works. Abbreviated commissioning can be successful in retail, office, warehouse, and mixed-use building types. Speculatively developed buildings may be good candidates for abbreviated commissioning. This thinking is the foundation of Cx Assistant s abbreviated commissioning level, which is defined as follows: The abbreviated commissioning process generally applies to small and mediumsized buildings without centralized control schemes or highly integrated mechanical and electrical systems. Within these building projects, the more complex mechanical and electrical systems are commissioned. The abbreviated commissioning process combines key checks and test procedures into one on-site testing procedure performed by the Commissioning Provider. The process is managed by a Commissioning Provider who may be part of the contractor or ownership organization. Construction team members are present at and assist in some testing. Although the process should be started during design, abbreviated commissioning can begin after construction has started. Standard Commissioning While hundreds of projects suited for abbreviated commissioning are constructed each year, it is believed that buildings of a moderate size and complexity dominate the new construction market. Standard commissioning is based on the traditional HVAC commissioning process that mimics ASHRAE Guideline and the LEED Fundamental Building Systems Commissioning Process. Standard commissioning is applicable to owner-occupied buildings such as offices, schools, libraries, auditoriums, restaurants, industrial buildings and the like. As such, this level of commissioning also applies to many of the California High Performance Schools (CHPS) projects. This thinking is the foundation of Cx Assistant s standard commissioning level, which is defined as follows: The standard commissioning process generally applies to small and medium-sized buildings with centralized control schemes or complex zone-level HVAC or lighting systems. Within these building projects, the more complex mechanical and electrical systems are commissioned. The standard commissioning process begins during the design phase and continues through the end of the acceptance period. The standard commissioning process is managed by a Commissioning Provider who may be part of the contractor or ownership organization. During construction, the Commissioning Provider conducts site inspections and works with the construction team to complete on-site testing. Comprehensive Commissioning The foundation of comprehensive commissioning is a whole building commissioning process. Comprehensive commissioning is relevant to the most complicated building and campus projects constructed today such as medical facilities, laboratories, grocery stores, convention centers, and high-rise buildings. This level is based on the newest research conducted by ASHRAE and

5 NIBS as well as on the Additional Commissioning requirements included in LEED and CHPS. iii Cx Assistant s comprehensive commissioning level is defined as follows: The comprehensive commissioning process generally applies to medium and large-sized buildings with centralized control systems and complex zone-level HVAC and lighting systems. The comprehensive commissioning process begins during the schematic design phase and continues through the first year of the building's occupancy. In most cases, this process will be managed by an independent third party who specializes in building commissioning. During construction, the Commissioning Provider conducts regular site inspections. Members of the construction team complete the majority of the on-site testing while the Commissioning Provider directs and documents the tests. What activities are included in each Commissioning Level? Cx Assistant recommends different commissioning activities for each level of commissioning, as shown in Figure B. To some degree, the user can customize these activities. For example, if Cx Assistant recommends a Standard level of commissioning, the user has the option of removing the Systems Manual activity as well as the Design Review (CD) activity. The user may also add commissioning activities line Design Review (DD) or Submittal Review to further customize their commissioning documents. Cx Assistant recommends that if a user adds more than 2 activities to the recommended list, they consider changing the selected Commissioning Level. DID and BoD Cx Plan Design Review (DD) Design Review (CD) Commissioning Specs Abbreviated x x x x x x* Standard x x x* x x x x x x x* Comprehensive x x x x x x x x x x x x x x. * Optional Activity for this level of commissioning Submittal Review Prefunctional Testing Functional Testing Cx Report Meeting Attendance O&M Document Review Operator Training Systems Manual Post-Occupancy Review Figure B. Cx Assistant recommends some commissioning activities for all levels of commissioning. Other commissioning activities are only recommended for more complicated commissioning levels.

6 How does the level of commissioning affect Cx Assistant output? Each level of commissioning has unique output files. For example, if a designer had one large office building (comprehensive commissioning), one small office building (standard commissioning), and one medium-sized elementary school (standard commissioning), the request for proposal (RFP) for the small office and the school would be more similar to each other than the large office building s RFP. Some tools within Cx Assistant are based almost solely on the level of commissioning for example; the cost estimating tool is built this way. On the other hand, the sequences of operations recommended by Cx Assistant are based on the types of equipment designed for the project rather than the level of commissioning chosen for it. The following sections of this article provide more detail on Cx Assistant s output for three of its modules: the Design Intent Generator, the Basis of Design Generator, and the Sequences of Operations Generator. What s in the DID? Table 1. The section headings of the Design Intent Document include a broad range of information. DID Section Headings Location & Directions General Project Information General Building Standards Training, Operations, & Maintenance Building Space Summary Building Performance Criteria The Design Intent Document (DID) is written in order to communicate to the building s stakeholders about what the facility is. Because the level of commissioning chosen for the project may be an integral part of the project s design, construction, and operation, Cx Assistant provides different sample documents for different levels of commissioning. The samples are structured using a description of the Design Intent and Basis of Design developed by Karl Stum for the 2002 ASHRAE Annual Meeting. iv The content of the documents varies by level of commissioning and is based on a combination of products including ASHRAE Guideline , work completed by PG&E on Current Facilities Requirements, and a public review draft of ASHRAE s Guideline 0P. v The contents of the comprehensive document mimic ASHRAE s draft Owner s Project Requirements document but, because the term Owner s Project Requirements has not yet been officially recognized by ASHRAE, Cx Assistant uses Design Intent Document. vi

7 What s in the BoD? Table 2. The section headings of the Basis of Design follow those of the Design Intent Document. DID Section Headings General Project Information Training, Operations, & Maintenance Building Design Assumptions System Summary Building Performance Criteria Sequences of Operation The Basis of Design (BoD) is the technical architectural and engineering response to the owner s Design Intent. As such, Cx Assistant s BoD follows the formatting of the DID while providing space for an accounting of the technical assumptions used to design the building. As with the Design Intent, the BoD documents differ based on the project s level of commissioning. For example, the abbreviated level Basis of Design is focused on listing the basic engineering assumptions. Since buildings that use abbreviated commissioning contain few complicated systems, this approach captures the essential information without too much effort. On the other hand, the comprehensive BoD leaves space for very detailed engineering assumptions as well as a narrative description of the advantages and trade-offs of the chosen system design. Projects that employ a comprehensive commissioning process often contain complex, highly interactive systems that require careful design and need to be documented for the building owner. What are the Sequences based on? Sequences of operation are included in Cx Assistant in order to help raise the bar for standard practice contract documents. One great challenge in commissioning complicated control systems is the consistent lack of clearly defined, well-written sequences of operation. Cx Assistant provides sample sequences in plain English, as opposed to using programming terms or legalese. The samples show the level of detail and rigor required for commissioning common mechanical systems. vii The systems are intended to meet California s 2005 Title 24 energy efficiency standards. viii They are based on commercial building mechanical designs as follows: Split system air conditioner: single room, not continuously occupied, cooling only Packaged rooftop unit: single zone, 100% outdoor air, cooling and heating Evaporative cooler packaged unit: single zone, 100% outdoor air, cooling and heating Standard packaged: single zone, airside economizer, cooling and heating Packaged unit with variable volume, variable temperature (VVT) control: multiple zones, airside economizer, cooling and heating 4-pipe fan coil unit: constant volume fan coil units with chilled water cooling coils & hot water heating coils, constant volume outdoor air. Central plant for hot/chilled water. Condenser Water Loop Heat Pump System: constant volume heat pump units with condenser water loop, constant volume outdoor air. Central plant for maintenance of condenser water loop temperature. Constant air volume: air handling units with chilled water cooling coils & variable speed supply and return fans. Central plant for hot/chilled water, hot water constant volume reheat terminal units.

8 Air cooled variable air volume: air handling units with chilled water cooling coils and variable speed supply and return fans. Central plant for hot/chilled water (air cooled), hot water variable volume re-heat terminal units. Water cooled variable air volume: air handling units with chilled water cooling coils and variable speed supply and return fans. Central plant for hot/chilled water (water cooled), hot water variable volume re-heat terminal units. Looking Towards the Future Cx Assistant may be accessed from (click on Cx Asst. under Online Tools). During the next phase of the project, the tool will gain three new modules: Commissioning Plan Generator Systems Manual Generator Training Plan Generator The current product was released for beta testing in February Prior to its public release, the Design Intent tool was demonstrated in a class at PG&E s Pacific Energy Center. Also, Cx Assistant s Scope Generator was used during a commissioning charrette for the California High Performance Schools (CHPS) program in April. The tool was also presented to a LEED subcommittee on commissioning as a potential resource for upcoming LEED reference materials. The authors hope to continue demonstrating the tool in the coming months and are open to feedback and comments. Cx Assistant has been designed to be applicable to a very wide range of new construction commercial building projects. The products generated by the tool are template documents and require further editing by the user before a commissioning team uses them. While this structure makes the tool useful to a wide audience, it detracts from the ability for the tool to home in on key parameters that are unique to different building types. Customizing Cx Assistant for more focused audiences such as educational facilities or grocery stores would allow the tool to delve into issues that are specific to different building types. The tool also may continue to grow by adding new components such as a design review wizard, a library of Title 24 acceptance tests, or a commissioning report template. Acknowledgements Ryan Stroupe, PG&E Pacific Energy Center, San Francisco CA Steve Taylor, Taylor Engineering, Alameda CA i The LEED Green Building Rating System is a trademark of the US Green Building Council. The authors of Cx Assistant referenced the rating system and reference guide for version 2.1 of the New Construction rating system (i.e. LEED-NC v2.1). ii Several contractors associations have published commissioning guidelines including the Air Conditioning Contractor s of America (ACCA Good Practices Manual), the National Environmental Balancing Bureau (NEBB

9 Procedural Standards for Building Systems Commissioning), and the Associated Air Balance Council (AABC Commissioning Guideline). These documents vary in scope and recommendations, just as commissioning guidelines published by engineering associations vary. iii ASHRAE Guideline 0, The Commissioning Process, provides a framework for a rigorous quality assurance whole building commissioning process. This Guideline is an integral part of the National Institute of Building Sciences total building commissioning guideline series. For more information, visit iv Stum, Karl. Design Intent and Basis of Design: Clarification of Terms, Structure, and Use ASHRAE Annual Meeting HI v Pacific Gas & Electric Company. Current Facility Requirements. San Francisco, vi ASHRAE s Guideline 0 describes an Owner s Project Requirements document that has previously been referred to as a Design Intent Document. The term Design Intent Document is used in ASHRAE s Guideline , The HVAC Commissioning Process and has gained wide acceptance in the commissioning community. vii To ensure their technical accuracy, Taylor Engineering LLC, an independent mechanical design firm, reviewed the sequences. viii Cx Assistant is based on the portion of Title 24, California s energy efficiency code, which is specific to nonresidential new construction. Title 24 is updated every 4 years and is one of the more rigorous energy efficiency codes in the county. For more information, go to

Measurement & Verification Plan

Measurement & Verification Plan Measurement & Verification Plan University of Florida UF-# Project Name City, Florida Insert Project Rendering/Photo Here Prepared By: University of Florida Department of Facilities, Planning & construction

More information

Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY

Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. HVAC Commissioning description. 2. HVAC Commissioning responsibilities. 1.2 REFERENCES A. American Society

More information

Mechanical Systems Proposal revised

Mechanical Systems Proposal revised Mechanical Systems Proposal revised Prepared for: Dr. William Bahnfleth, Professor The Pennsylvania State University, Department of Architectural Engineering Prepared by: Chris Nicolais Mechanical Option

More information

REAL OPERATING COST SAVINGS FROM RETRO- COMMISSIONING OPPORTUNITIES FOR SAVINGS IN ACADEMIC MEDICAL CENTERS

REAL OPERATING COST SAVINGS FROM RETRO- COMMISSIONING OPPORTUNITIES FOR SAVINGS IN ACADEMIC MEDICAL CENTERS REAL OPERATING COST SAVINGS FROM RETRO- COMMISSIONING OPPORTUNITIES FOR SAVINGS IN ACADEMIC MEDICAL CENTERS Ken L. Hansen P.E. University of Nebraska Medical Center hansenkl@unmc.edu 402-559- 5301 402-630-

More information

Example Retrocommissioning Measure: Opening Throttled Discharge Valves

Example Retrocommissioning Measure: Opening Throttled Discharge Valves Opening Throttled Discharge Valves This 21-story building, constructed in 1997, is located in Oregon and contains 589,000 gross square feet of mostly office occupancy. The HVAC system includes six large

More information

Energy Audit Skills: Tools, Data Collection Techniques and Calculations Spring 2012

Energy Audit Skills: Tools, Data Collection Techniques and Calculations Spring 2012 Energy Audit Skills: Tools, Data Collection Techniques and Calculations Spring 2012 These links are provided as information only and are not in any way to be considered a comprehensive listing or as an

More information

This notice sets forth interim guidance, pending the issuance of regulations,

This notice sets forth interim guidance, pending the issuance of regulations, Part III - Administrative, Procedural, and Miscellaneous Deduction for Energy Efficient Commercial Buildings Notice 2006-52 SECTION 1. PURPOSE This notice sets forth interim guidance, pending the issuance

More information

How To Design A Power Plant

How To Design A Power Plant Taylor Engineering 1080 Marina Village Parkway, Suite 501 Alameda, CA 94501-6427 (510) 749-9135 Fax (510) 749-9136 LLC JEFF STEIN, P.E. Jeff Stein is a registered mechanical engineer with over 16 years

More information

Sample - Existing Building Commissioning Plan

Sample - Existing Building Commissioning Plan Sample - Existing Building Commissioning Plan Version: Draft for Review Final Approved: Owner Site Address: Primary Site Contact Name and Telephone Number: Date Building Description The site consists of

More information

Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks

Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks Presentation Outline Common Terms / Concepts HVAC Building Blocks Plant Level Building Blocks Description / Application Data Green opportunities Selection Criteria Air Distribution Building Blocks same

More information

VE 6.4.0.5: Thermal / Systems Pack. 1. Tabular Room Data editing for thermal properties

VE 6.4.0.5: Thermal / Systems Pack. 1. Tabular Room Data editing for thermal properties VE 6.4.0.5: Thermal / Systems Pack 1. Tabular Room Data editing for thermal properties There is a new button in Apache, UK Part L2, and PRM Tabular Room Data. This tool represents a real productivity enhancement

More information

American Society of Heating Refrigeration and Air Conditioning Engineers (ASHRAE) Procedures for Commercial Building Energy Audits (2004)

American Society of Heating Refrigeration and Air Conditioning Engineers (ASHRAE) Procedures for Commercial Building Energy Audits (2004) Excerpt from: American Society of Heating Refrigeration and Air Conditioning Engineers (ASHRAE) Procedures for Commercial Building Energy Audits (2004) 2004 American Society of Heating, Refrigerating and

More information

Energy Design Resources Commissioning Plan Outline Template

Energy Design Resources Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings

Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings Advanced Energy Design Guide LEED Strategies for Schools and High Performance Buildings Today s Presenters Stephen Koontz, LEED AP Energy Services Leader Tampa Bay Trane Allen Irvine General Sales Manager

More information

Part III. Administrative, Procedural, and Miscellaneous

Part III. Administrative, Procedural, and Miscellaneous Part III. Administrative, Procedural, and Miscellaneous Deduction for Energy Efficient Commercial Buildings Notice 2006 52 SECTION 1. PURPOSE This notice sets forth interim guidance, pending the issuance

More information

CHAPTER A-7 ENERGY ANALYSES, ECONOMIC ANALYSES, CONTROL SYSTEMS, UMCS INDEX

CHAPTER A-7 ENERGY ANALYSES, ECONOMIC ANALYSES, CONTROL SYSTEMS, UMCS INDEX CHAPTER A-7 ENERGY ANALYSES, ECONOMIC ANALYSES, CONTROL SYSTEMS, UMCS INDEX Revised March 2015 7.1 GENERAL 7.1.1 Analyses 7.1.2 Site Adaptations 7.1.3 Changes During Design 7.2 APPLICABLE PUBLICATIONS

More information

2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT

2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT Presentation Synopsis Heating, Ventilating and Air Conditioning Building Condition Assessment Vancouver, B.C. Prepared for: EPIC Prepared by: Douglas Spratt, P.Eng Douglas Spratt & Associates Ltd. www.dspratt-associates.com

More information

Modeling and Simulation of HVAC Faulty Operations and Performance Degradation due to Maintenance Issues

Modeling and Simulation of HVAC Faulty Operations and Performance Degradation due to Maintenance Issues LBNL-6129E ERNEST ORLANDO LAWRENCE BERKELEY NATIONAL LABORATORY Modeling and Simulation of HVAC Faulty Operations and Performance Degradation due to Maintenance Issues Liping Wang, Tianzhen Hong Environmental

More information

EnergyPro Building Energy Analysis. Assisted Living Building

EnergyPro Building Energy Analysis. Assisted Living Building EnergyPro Building Energy Analysis Assisted Living Building EnergyPro Building Energy Analysis for an assisted living building Project Scope The purpose of the EnergyPro energy model was to evaluate the

More information

How To Reduce Energy Use

How To Reduce Energy Use Opportunities for: Reducing Carbon Footprint Slashing Peak Demand Hybrid DX Air Conditioning utilizing ice storage Paul Kuhlman Director, Ice Energy Inc. pkuhlman@ice-energy.com We are experiencing a warming

More information

SIMULATION OF RADIANT COOLING PERFORMANCE WITH

SIMULATION OF RADIANT COOLING PERFORMANCE WITH SUMMARY REPORT MAY 2008 SIMULATION OF RADIANT COOLING PERFORMANCE WITH EVAPORATIVE COOLING SOURCES Timothy Moore Center for the Built Environment (CBE) University of California, Berkeley May 2008 EXECUTIVE

More information

PROTOCOL FOR BUILDING ENERGY ANALYSIS SOFTWARE For Class 3, 5, 6, 7, 8 and 9 buildings

PROTOCOL FOR BUILDING ENERGY ANALYSIS SOFTWARE For Class 3, 5, 6, 7, 8 and 9 buildings PROTOCOL FOR BUILDING ENERGY ANALYSIS SOFTWARE For Class 3, 5, 6, 7, 8 and 9 buildings Version 2006.1 AUSTRALIAN BUILDING CODES BOARD JANUARY 2006 TABLE OF CONTENTS Foreword 1. Scope 2. Purpose and context

More information

2009 Seattle Energy Code Impacts: See below for a recap of Changes in Envelope performance from 2006 to 2009

2009 Seattle Energy Code Impacts: See below for a recap of Changes in Envelope performance from 2006 to 2009 2009 Seattle Energy Code Impacts: Building Envelope Impacts: Below is a Summary of Changes that impact building envelope construction planned for 624 Yale. There are several modifications are required

More information

Denver International Airport Data Center Commissioning Plan

Denver International Airport Data Center Commissioning Plan Denver International Airport Data Center Jefferson County School District Columbine High School Renovation Date July 25th, 2014 Prepared by Patrick Corrigan, QCxP Commissioning Engineer McKinstry McKINSTRY

More information

UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01

UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01 GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per

More information

Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues

Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues Design Guide Retrofitting Options For HVAC Systems In Live Performance Venues Heating, ventilation and air conditioning (HVAC) systems are major energy consumers in live performance venues. For this reason,

More information

PHCC Educational Foundation Contractor Library Engineering Continuing Education

PHCC Educational Foundation Contractor Library Engineering Continuing Education PHCC Educational Foundation Contractor Library Engineering Continuing Education Engineering-Specific Courses This list includes engineering-specific courses only. Descriptions for all approved courses

More information

Mechanical-Electrical Technology

Mechanical-Electrical Technology Mechanical-Electrical Technology MET Degrees: A.S. Mechanical-Electrical Technology A.S. Wastewater Treatment Plant Operation A.S. Water Treatment Plant Operation Division of Advanced Technology Donnetta

More information

Commissioning Design/Build Projects

Commissioning Design/Build Projects This article was published in ASHRAE Journal, October 2012. Copyright 2012 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/ or distributed electronically or in paper form without permission

More information

CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS

CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS By: Michael J. Bitondo, Mark J. Tozzi Carrier Corporation Syracuse, New York August 1999 INTRODUCTION In December of 1998, the American Refrigeration Institute

More information

Data Center Industry Leaders Reach Agreement on Guiding Principles for Energy Efficiency Metrics

Data Center Industry Leaders Reach Agreement on Guiding Principles for Energy Efficiency Metrics On January 13, 2010, 7x24 Exchange Chairman Robert Cassiliano and Vice President David Schirmacher met in Washington, DC with representatives from the EPA, the DOE and 7 leading industry organizations

More information

Seven Steps to Maximizing Central Plant Efficiency

Seven Steps to Maximizing Central Plant Efficiency White Paper Seven Steps to Maximizing Central Plant Efficiency David Klee Director, Channel Marketing & Strategy, HVAC Johnson Controls, Inc. Gary Gigot Vice President Business Development Optimum Energy,

More information

Amplification of Notice 2006-52; Deduction for Energy Efficient Commercial Buildings

Amplification of Notice 2006-52; Deduction for Energy Efficient Commercial Buildings Internal Revenue Bulletin: 2008-14 April 7, 2008 Notice 2008-40 Amplification of Notice 2006-52; Deduction for Energy Efficient Commercial Buildings Table of Contents SECTION 1. PURPOSE SECTION 2. BACKGROUND

More information

Building Performance Evaluation Guide Version 1.7

Building Performance Evaluation Guide Version 1.7 Building Performance Evaluation Guide Version 1.7 Prepared by Center for Energy and Environment January 2014 Minnesota Sustainable Building 2030: Building Performance Evaluation Guide p 1 1. Schematic

More information

Trade Professional Alliance. 2015 EE Programs Training. Napa, CA January 20, 2015 Mark Salavitch Trade Professional Manager, Bay Region

Trade Professional Alliance. 2015 EE Programs Training. Napa, CA January 20, 2015 Mark Salavitch Trade Professional Manager, Bay Region Trade Professional Alliance 2015 EE Programs Training Napa, CA January 20, 2015 Mark Salavitch Trade Professional Manager, Bay Region Welcome to North Bay Division Area: 1,345 square miles Cities: Marin

More information

MEETING AGENDA. Project Administrator:

MEETING AGENDA. Project Administrator: MEETING AGENDA Project Administrator: To: Ann Green M. Baker, SLCS C. Bullinger, SLCS R. Clark, SLCS Board C. Cox, SLCS S. Dotinga, Granger J. Graham, SLCS J. Gusick, SLCS, Board C. Hanshaw, SLCS Board

More information

VRF Life Cycle Cost Analysis. January 23, 2011

VRF Life Cycle Cost Analysis. January 23, 2011 VRF Life Cycle Cost Analysis January 23, 2011 Brian Thornton P.E., PNNL brian.thornton@pnnl.gov Introduction Purpose: Discuss life cycle cost trade-offs for VRF with other HVAC systems Outline Life cycle

More information

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project. DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly

More information

5.6 Technical Specification: Premium Efficiency Electric Air Conditioning Equipment

5.6 Technical Specification: Premium Efficiency Electric Air Conditioning Equipment 5.6 Technical Specification: Premium Efficiency Electric Conditioning Equipment Small Premium Project Type: For Premium Conditioning Retrofit Projects: Projects that voluntarily replace existing unitary

More information

Fundamentals of HVAC Control Systems

Fundamentals of HVAC Control Systems ASHRAE Hong Kong Chapter Technical Workshop Fundamentals of HVAC Control Systems 18, 19, 25, 26 April 2007 2007 ASHRAE Hong Kong Chapter Slide 1 Chapter 5 Control Diagrams and Sequences 2007 ASHRAE Hong

More information

Printing and Publishing Energy Savings Guide

Printing and Publishing Energy Savings Guide Printing and Publishing Energy Savings Guide Oregon printing and publishing plants face challenges of rising operating costs, environmental and other regulations, outdated equipment and customer demand

More information

Modeling Guide for Daikin VRV in EnergyPro 6

Modeling Guide for Daikin VRV in EnergyPro 6 Modeling Guide for Daikin VRV in EnergyPro 6 Table of Contents Introduction... 1 Program Installation... 2 Importing Designated VRV Product File... 3 System Modeling... 6 Modeling air-cooled outdoor units...

More information

Central Plant Air Systems: Keeping the Heart and. Title Style. Better Buildings Summit May 2016

Central Plant Air Systems: Keeping the Heart and. Title Style. Better Buildings Summit May 2016 Central Plant Air Systems: Keeping the Heart and Click Lungs To Healthy Edit Master Title Style Better Buildings Summit May 2016 Introductions Michael Deru National Renewable Energy Laboratory New Resources

More information

Knowledge for optimal efficiency

Knowledge for optimal efficiency Engineering Onboard Climate Control Knowledge for optimal efficiency MARINE HVAC-R MARINE HVAC-R ADVANTAGES 2 KNOWLEDGE FOR OPTIMAL EFFICIENCY The BRONSWERK Advantage It s like the ideal day at sea when

More information

HEATING, VENTILATION & AIR CONDITIONING

HEATING, VENTILATION & AIR CONDITIONING HEATING, VENTILATION & AIR CONDITIONING as part of the Energy Efficiency Information Grants Program Heating and cooling can account for approximately 23 % of energy use in pubs and hotels 1. Reducing heating

More information

Case Study. Crown Melbourne & BUENO Systems: Energy and Operational Savings Across a Multi-Use Entertainment Complex.

Case Study. Crown Melbourne & BUENO Systems: Energy and Operational Savings Across a Multi-Use Entertainment Complex. Case Study Crown Melbourne & BUENO Systems: Energy and Operational Savings Across a Multi-Use Entertainment Complex Version 1.0 June 2015 Find What Matters Crown Melbourne Analytics-Driven Energy and Operational

More information

Building Commissioning 17900-1

Building Commissioning 17900-1 SECTION 17900 BUILDING COMMISSIONING PART 1 - GENERAL 1.01 WORK DESCRIPTION: A. General: 1. The Commissioning process is a joint team effort to ensure that all mechanical equipment, controls, and systems

More information

ACG Commissioning Guideline

ACG Commissioning Guideline ACG Commissioning Guideline Appendix A Sample Commissioning Specification NOTES TO APPENDIX A This appendix contains a sample Request for Proposal (RFP) for Commissioning Services as would be issued by

More information

Silicon Valley Power 2015-2016 Data Center Program Rebate Application

Silicon Valley Power 2015-2016 Data Center Program Rebate Application Contact Information Silicon Valley Power Tax Status (check one) Sole Proprietor Contact Name Phone Corporation Partnership Company Email address Government Not-For-Profit Customer/Facility Information

More information

Codes and High Performance Hot Water Systems. Gary Klein Affiliated International Management, LLC 916 549 7080 gary@aim4sustainability.

Codes and High Performance Hot Water Systems. Gary Klein Affiliated International Management, LLC 916 549 7080 gary@aim4sustainability. Codes and High Performance Hot Water Systems Gary Klein Affiliated International Management, LLC 916 549 7080 gary@aim4sustainability.com Annual Energy Use for Heating Water Natural Gas Gallons Per Day

More information

ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations

ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations MECHANICAL SYSTEMS DESIGN STANDARDS Appendix A RECOMMENDED HVAC SYSTEMS BY TYPE OF SPACE Matt Higgins Valentin Lucero

More information

HVAC Systems: Overview

HVAC Systems: Overview HVAC Systems: Overview Michael J. Brandemuehl, Ph.D, P.E. University of Colorado Boulder, CO, USA Overview System Description Secondary HVAC Systems Air distribution Room diffusers and air terminals Duct

More information

DOE Data Center Energy Efficiency Program

DOE Data Center Energy Efficiency Program DOE Data Center Energy Efficiency Program Paul Scheihing U.S. Department of Energy Energy Efficiency and Renewable Energy April 2009 1 DOE Industrial Technologies Program Worki king to improve th e energy

More information

Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia

Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia Prepared for the U.S. Department of Energy s Federal Energy Management Program

More information

Residential Duct Systems for New and Retrofit Homes

Residential Duct Systems for New and Retrofit Homes Residential Duct Systems for New and Retrofit Homes Why it is important to properly design and install high quality, efficient ducted air systems? The efficiency of air distribution systems has been found

More information

Wet Bulb Temperature and Its Impact on Building Performance

Wet Bulb Temperature and Its Impact on Building Performance Wet Bulb Temperature and Its Impact on Building Performance By: Kurmit Rockwell, PE, CEM, LEED AP and Justin Lee, PE, LEED, AP BD+C Energy Solution Services, AtSite, Inc. 1 What is Wet Bulb Temperature?

More information

How Does Your Data Center Measure Up? Energy Efficiency Metrics and Benchmarks for Data Center Infrastructure Systems

How Does Your Data Center Measure Up? Energy Efficiency Metrics and Benchmarks for Data Center Infrastructure Systems How Does Your Data Center Measure Up? Energy Efficiency Metrics and Benchmarks for Data Center Infrastructure Systems Paul Mathew, Ph.D., Staff Scientist Steve Greenberg, P.E., Energy Management Engineer

More information

HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY

HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY Benson Kwong, CVS, PE, CEM, LEED AP, CCE envergie consulting, LLC Biography Benson Kwong is an independent consultant providing

More information

ULTRA-EFFICIENT HVAC DESIGN AND CONTROL

ULTRA-EFFICIENT HVAC DESIGN AND CONTROL CASE STUDY ULTRA-EFFICIENT HVAC DESIGN AND CONTROL MAJOR HEATING, VENTILATING AND AIR- CONDITIONING REPLACEMENT AT THE COUNTY OF SAN DIEGO CRIME LAB December 30, 2005 8520 Tech Way, Suite 110 San Diego,

More information

AIR COOLED CHILLER CHILLED WATER PUMP CONTROL: The chilled water pump with the lowest runtime will automatically start when the outside air temperature rises above the system enable setpoint. When the

More information

NFPA 3 and 4 Commissioning and Integrated Testing of Fire Protection and Life Safety Systems. Matt Klaus Senior Fire Protection Engineer NFPA

NFPA 3 and 4 Commissioning and Integrated Testing of Fire Protection and Life Safety Systems. Matt Klaus Senior Fire Protection Engineer NFPA NFPA 3 and 4 Commissioning and Integrated Testing of Fire Protection and Life Safety Systems Matt Klaus Senior Fire Protection Engineer NFPA 1 The Recommended Practice 2 Coming Soon 3 Overview What is

More information

The Integrated Design Process

The Integrated Design Process The Integrated Design Process The Integrated Design Process (IDP) has been developed on the basis of experience gained from a small Canadian demonstration program for high-performance buildings, the C2000

More information

Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001

Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001 Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001 Presented by: Liberty Engineering, LLP 1609 Connecticut Avenue

More information

Project 0811-021 Aug 2011 ADRIAN. Prepared by Victor Carroll

Project 0811-021 Aug 2011 ADRIAN. Prepared by Victor Carroll Project 0811-021 Aug 2011 ADRIAN Prepared by Victor Carroll Page 2 DISCLAIMER The attached sizing and layout design is for estimation purposes only. The actual size and performance of the system is the

More information

RFI Response RFP: HSCG88-16-R-PQQ015 Replace HVAC Bldg A & C San Diego, CA.

RFI Response RFP: HSCG88-16-R-PQQ015 Replace HVAC Bldg A & C San Diego, CA. 1. There is verbiage in the hazardous material report referring to a state licensed abatement contractor. Within the recommendations part of the report (page 64 of 111 of the specification pdf) is the

More information

Workforce Issues and Energy Efficiency Programs: A Plan for California s Utilities RECOMMENDATIONS TABLES

Workforce Issues and Energy Efficiency Programs: A Plan for California s Utilities RECOMMENDATIONS TABLES Workforce Issues Efficiency Programs: A Plan for California s Utilities RECOMMENDATIONS TABLES Submitted by the WE&T Consultants UC Berkeley Donald Vial Center Team UCB-DVC, May 2014 Chapter 2. DEMAND:

More information

SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT

SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT PART 1 - GENERAL 1.1 DESCRIPTION A. The Work specified in this Section consists of designing, furnishing and installing factory-assembled

More information

COMMERCIAL HVAC CHILLER EQUIPMENT. Air-Cooled Chillers

COMMERCIAL HVAC CHILLER EQUIPMENT. Air-Cooled Chillers COMMERCIAL HVAC CHILLER EQUIPMENT Air-Cooled Chillers Technical Development Programs (TDP) are modules of technical training on HVAC theory, system design, equipment selection and application topics. They

More information

Maximize energy savings Increase life of cooling equipment More reliable for extreme cold weather conditions There are disadvantages

Maximize energy savings Increase life of cooling equipment More reliable for extreme cold weather conditions There are disadvantages Objectives Increase awareness of the types of economizers currently used for data centers Provide designers/owners with an overview of the benefits and challenges associated with each type Outline some

More information

Energy Audits. Good energy management begins with an energy audit

Energy Audits. Good energy management begins with an energy audit Energy Audits Good energy management begins with an energy audit Effective management of energy-consuming systems can lead to significant cost and energy savings as well as increased comfort, lower maintenance

More information

Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 Design & Construction

Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 Design & Construction Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 Design & Construction Pertains to all Building Design & Construction and Interior Design & Construction LEED v2.0 through v2009 Rating

More information

SYSTEMS INTEGRATION SYSTEMS INTEGRATION. Air handler uses heat recovery on exhaust air to temper incoming ventilation air Oxbow skylight

SYSTEMS INTEGRATION SYSTEMS INTEGRATION. Air handler uses heat recovery on exhaust air to temper incoming ventilation air Oxbow skylight 100% outside air intake Air handler uses heat recovery on exhaust air to temper incoming ventilation air Oxbow skylight Smoke evacuation Natural convection exhaust Atrium skylight Phase change material

More information

FREQUENTLY ASKED QUESTIONS about HERS and CHEERS Provided by the California Energy Commission Consumer Energy Center

FREQUENTLY ASKED QUESTIONS about HERS and CHEERS Provided by the California Energy Commission Consumer Energy Center http://www.energy.ca.gov/ FREQUENTLY ASKED QUESTIONS about HERS and CHEERS Provided by the California Energy Commission Consumer Energy Center Relevant Standard The Residential Manual for Compliance with

More information

How To Buy A Lennox Power System

How To Buy A Lennox Power System HVAC for Schools A Comprehensive Look at Products for a Clean, Comfortable Learning Environment Why Schools Choose Lennox Even as resources for schools continue to be constrained, education leaders and

More information

Recommendations for Measuring and Reporting Overall Data Center Efficiency

Recommendations for Measuring and Reporting Overall Data Center Efficiency Recommendations for Measuring and Reporting Overall Data Center Efficiency Version 2 Measuring PUE for Data Centers 17 May 2011 Table of Contents 1 Introduction... 1 1.1 Purpose Recommendations for Measuring

More information

North Carolina Heating and Cooling Equipment Incentive Application

North Carolina Heating and Cooling Equipment Incentive Application North Carolina Heating and Cooling Incentive Application Questions? Call 1-866-380-9580 or visit www.duke-energy.com Email the complete, signed application with all required documents to PrescriptiveIncentives@duke-energy.com

More information

Power Plant Water Use By Alissa Cooperman; John Dieckmann, Member ASHRAE; and James Brodrick, Ph.D., Member ASHRAE S

Power Plant Water Use By Alissa Cooperman; John Dieckmann, Member ASHRAE; and James Brodrick, Ph.D., Member ASHRAE S EMERGING TECHNOLOGIES This article was published in ASHRAE Journal, January 2012. Copyright 2012 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. Posted at www.ashrae.org.

More information

Collaborative Laboratory Commissioning and Sustaining the Optimal Building. By E. Lon Brightbill, P.E Facility Dynamics

Collaborative Laboratory Commissioning and Sustaining the Optimal Building. By E. Lon Brightbill, P.E Facility Dynamics Collaborative Laboratory Commissioning and Sustaining the Optimal Building By E. Lon Brightbill, P.E Facility Dynamics Overview DefineCommissioning (Cx) Put the Cx process in the Context of a State of

More information

Section 2: Estimating Energy Savings and Incentives

Section 2: Estimating Energy Savings and Incentives Section 2: Estimating Energy Savings and Incentives 2.1 Estimating Energy Savings and Incentives... 2 2.2 Customized Measures - Estimation Software... 2 2.2.1 AC&R I - High Efficiency Chiller... 3 2.2.2

More information

Integrating Kitchen Exhaust Systems with Building HVAC

Integrating Kitchen Exhaust Systems with Building HVAC Design Guide 3 Improving Commercial Kitchen Ventilation System Performance Integrating Kitchen Exhaust Systems with Building HVAC This design guide provides information that may help achieve optimum performance

More information

Rittal White Paper 508: Economized Data Center Cooling Defining Methods & Implementation Practices By: Daniel Kennedy

Rittal White Paper 508: Economized Data Center Cooling Defining Methods & Implementation Practices By: Daniel Kennedy Rittal White Paper 508: Economized Data Center Cooling Defining Methods & Implementation Practices By: Daniel Kennedy Executive Summary Data center owners and operators are in constant pursuit of methods

More information

Vectren Commercial/Industrial New Construction Incentive Application

Vectren Commercial/Industrial New Construction Incentive Application Vectren Commercial/Industrial New Construction Application Completing and submitting this application is the first step to apply for incentives through Vectren s Commercial/Industrial New Construction

More information

Energy Implications of Economizer Use in California Data Centers

Energy Implications of Economizer Use in California Data Centers Energy Implications of Economizer Use in California Data Centers Arman Shehabi 1, Srirupa Ganguly 2,*, Kim Traber 3, Hillary Price 3 Arpad Horvath 1, William W Nazaroff 1, Ashok J Gadgil 2, 1 Department

More information

BUILDING PERFORMANCE METRICS

BUILDING PERFORMANCE METRICS BUILDING PERFORMANCE METRICS Hugh Crowther P. Eng. Executive Vice President, Product Management and Technology There is a steady and determined march towards designing better and better performing buildings.

More information

imagine SOLAR AIR CONDITIONING MADE EASY

imagine SOLAR AIR CONDITIONING MADE EASY imagine SOLAR AIR CONDITIONING MADE EASY WHY SOLAR COOLING? Imagine...being able to fit a solar air conditioning system to your building that would result in dramatic reductions in electricity consumption

More information

Energy Action Plan 2015

Energy Action Plan 2015 Energy Action Plan 2015 Purpose: In support of the Texas A&M University Vision 2020: Creating a Culture of Excellence and Action 2015: Education First Strategic Plan, the Energy Action Plan (EAP) 2015

More information

HVAC Technologies for Building Energy Efficiency Improvements 2013 National Symposium on Market Transformation. Richard Lord Carrier Fellow

HVAC Technologies for Building Energy Efficiency Improvements 2013 National Symposium on Market Transformation. Richard Lord Carrier Fellow HVAC Technologies for Building Energy Efficiency Improvements 2013 National Symposium on Market Transformation Richard Lord Carrier Fellow HVAC Industry Challenges and Issues Ozone Deletion Global Warming

More information

Evaporative Cooling for Residential and Light-Commercial

Evaporative Cooling for Residential and Light-Commercial EMERGING TECHNOLOGIES This article was published in ASHRAE Journal, October 2011. Copyright 2011 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. Posted at www.ashrae.org.

More information

SURVEY RESULTS: DATA CENTER ECONOMIZER USE

SURVEY RESULTS: DATA CENTER ECONOMIZER USE WHITE PAPER #41 SURVEY RESULTS: DATA CENTER ECONOMIZER USE EDITOR: Jessica Kaiser, Emerson Network Power CONTRIBUTORS: John Bean, Schneider Electric Tom Harvey, Emerson Network Power Michael Patterson,

More information

The HVAC manufacturer s new building showcases energy efficiency and sustainability. 1.13. EDCmag.com

The HVAC manufacturer s new building showcases energy efficiency and sustainability. 1.13. EDCmag.com 1.13. EDCmag.com ENVIRONMENTAL DESIGN + CONSTRUCTION edcthe OFFICIAL MAGAZINE FOR THE LEED PROFESSIONAL The HVAC manufacturer s new building showcases energy efficiency and sustainability Taco, Inc. 1160

More information

Mechanical-Electrical Technology MECHANICAL-ELECTRICAL TECHNOLOGY. 304 2015-16 Sacramento City College Catalog

Mechanical-Electrical Technology MECHANICAL-ELECTRICAL TECHNOLOGY. 304 2015-16 Sacramento City College Catalog MET Degree: A.S. Certificates of Achievement: Commercial Building Energy Auditing and Commissioning Specialist Mechanical Systems Technician Commercial Building Energy Auditing and Commissioning Specialist

More information

Guideline for Water and Energy Considerations During Federal Data Center Consolidations

Guideline for Water and Energy Considerations During Federal Data Center Consolidations Guideline for Water and Energy Considerations During Federal Data Center Consolidations Prepared for the U.S. Department of Energy Federal Energy Management Program By Lawrence Berkeley National Laboratory

More information

By Tom Brooke PE, CEM

By Tom Brooke PE, CEM Air conditioning applications can be broadly categorized as either standard or critical. The former, often called comfort cooling, traditionally just controlled to maintain a zone setpoint dry bulb temperature

More information

The Different Types of Air Conditioning Equipment for IT Environments

The Different Types of Air Conditioning Equipment for IT Environments The Different Types of Air Conditioning Equipment for IT Environments By Tony Evans White Paper #59 Executive Summary Cooling equipment for an IT environment can be implemented in 10 basic configurations.

More information

Florida Power & Light Company. Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards. Effective: November 9, 2015

Florida Power & Light Company. Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards. Effective: November 9, 2015 Florida Power & Light Company Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards Effective: November 9, 2015 Table of Contents Eligibility Requirements - Chiller... 2 Rebate Amount

More information

Ener.co & Viridian Energy & Env. Using Data Loggers to Improve Chilled Water Plant Efficiency. Randy Mead, C.E.M, CMVP

Ener.co & Viridian Energy & Env. Using Data Loggers to Improve Chilled Water Plant Efficiency. Randy Mead, C.E.M, CMVP Ener.co & Viridian Energy & Env. Using Data Loggers to Improve Chilled Water Plant Efficiency Randy Mead, C.E.M, CMVP Introduction Chilled water plant efficiency refers to the total electrical energy it

More information

San Francisco s Energy Performance Ordinance: Spotlighting. Commercial Building Energy Use

San Francisco s Energy Performance Ordinance: Spotlighting. Commercial Building Energy Use pg1 of 6 San Francisco s Energy Performance Ordinance: Spotlighting Commercial Building Energy Use by David C. Longinotti, LEED AP The City of San Francisco has joined New York, Seattle, Austin and other

More information

Industrial Green Building Retrofit 101 Opportunities and Challenges. Light Industrial Green Building Retrofits. Why Green Retrofit?

Industrial Green Building Retrofit 101 Opportunities and Challenges. Light Industrial Green Building Retrofits. Why Green Retrofit? Industrial Green Building 101 Opportunities and Challenges Joanne Sawatzky Senior Project Manager, Light House Sustainability at Work Re-visioning a Sustainable False Creek Flats Light Industrial Green

More information

Infrastructure & Cities Sector

Infrastructure & Cities Sector Technical Article Infrastructure & Cities Sector Building Technologies Division Zug (Switzerland), October 18, 2011 Saving Energy in a Data Center A Leap of Faith? New guidelines from ASHRAE (American

More information

Environmental Interface Limited

Environmental Interface Limited Environmental Interface Limited CAREER HIGHLIGHTS JOHN D. COWAN P.Eng, M.B.A, C.M.V.P. 1. Energy management consulting to direct industrial and commercial facility owners towards energy or environmental

More information