Denver International Airport Data Center Commissioning Plan

Size: px
Start display at page:

Download "Denver International Airport Data Center Commissioning Plan"

Transcription

1 Denver International Airport Data Center Jefferson County School District Columbine High School Renovation Date July 25th, 2014 Prepared by Patrick Corrigan, QCxP Commissioning Engineer McKinstry McKINSTRY FOR THE LIFE OF YOUR BUILDING Mechanical & Electrical Design/Build Mobile Service Energy Solutions Facility Management

2 INTRODUCTION THE PURPOSE OF THE COMMISSIONING (CX) PLAN This Commissioning (Cx) Plan describes the commissioning process for the Columbine High School renovation project located in Littleton, Colorado. This living document provides a high-level overview of the commissioning process, scope summary, and it identifies the various roles and respective responsibilities of those that will participate in the commissioning process. The end goal of the and the execution thereof is to ensure the systems are designed, installed, started, tested, and documented to meet both the owner s requirements and the specifications of the project. The contains the following sections: Introduction Purpose of the Project Description Systems to be Commissioned Commissioning Schedule Terminology Commissioning Overview Parties Involved Design Phase Construction Phase Acceptance Phase Close-Out/Transition Phase Operation & Maintenance (O&M) Phase Deliverables Responsibilities PROJECT DESCRIPTION The project includes a complete DDC replacement of the pneumatic controls system. The following valves will be replaced: all terminal unit re-heat valves (190), heating and cooling valves on the existing RTUs (10), new RTUs (7), and the cooling tower sump fill and drain valves (2). The existing valves are pneumatic controlled and will be replaced with direct digital controlled (DDC) valves. The project also includes the replacement and installation of (6) cooling only RTUs, (1) make-up air unit, (4) boilers, (2) heating hot water pumps. SYSTEMS TO BE COMMISSIONED The commissioning process for this project will include the following systems: Control Valve Replacement o Installation Verificaiton Rooftop Units o Submittal Review o Start-up Witnessing 2

3 Air Cooled Condensing Unit o Submittal Review o Start-up Witnessing Make-up Air Unit o Submittal Review o Start-up Witnessing Exhaust Fan o Submittal Review Boiler o Submittal Review o Witness Start-up and Combustion Analysis Chiller 3

4 TERMINOLOGY Below is a list of common terminology and abbreviations used throughout this document. A/E Architect/Engineer BOD Basis of Design Cx - Commissioning CxA Commissioning Agent FPT Functional Performance Test(s) OPR Owner s Project Requirements TAB Testing, Adjusting, and Balancing Contractor(s) Construction Manager/Prime Contractor(s) SOO Sequence of Operations CMMS Computerized Maintenance Management System KRC Knowledge Response Center M&V Measurement & Verification O&M Operations & Maintenance 4

5 Commissioning Overview DESCRIPTION Commissioning is the systematic process of ensuring that all building systems included in the scope perform interactively according to the design intent, BOD, and the Owner s operational needs. Generally, the CxA is involved in the process from design through post-construction. The CxA partners with the Owner, A/E firm(s), Contractors, and Owner s Facility Staff throughout the process to identify the operating requirements, verify system functionality & documentation, and assist with the transition of the facility to steady-state operations. Below is a high-level flowchart of the commissioning process, which is followed by a description of each phase. DESIGN PHASE Review Design Set Provide Cx Specs Review CD Set CONSTRUCTION PHASE Submit Cx Plan Review Construction Submittals and SOO Cx Kickoff Meeting Site Visits & Meetings Distribute Pre- /Start-Up Tests Submit Cx Tests for Review Maintain Observation Log ACCEPTANCE PHASE Review Pre-Start Tests Coordinate Start-Up Tests Review & Verify TAB PTP Verification Conduct FPTs CLOSE-OUT/TRANSITION PHASE Review O&M Manuals Verify Training Resolve Observation Log Deliver Cx Report 5

6 DESIGN PHASE The Design Phase spans from pre-design through the generation of construction documents. In the Design Phase, the Cx steps are as follows: Review Design Set The A/E provides the CxA a design development set for review. The CxA reviews the design set for inconsistencies, misses, and opportunities for improvement. The CxA documents their comments and provides them to the A/E for incorporation into the design set. Provide Cx Specs The CxA provides Commissioning Specifications to the A/E to include in the Construction Document (CD) set. The CxA caters the specifications as necessary to the project. Review CD Set The A/E provides a Construction Document (CD) set that is near 100% complete to the CxA for review. The CxA reviews the set to verify previous comments have been addressed and to identify any further misses or opportunities. The CxA documents their comments and provides them to the A/E for incorporation into the construction set. CONSTRUCTION PHASE The Construction Phase spans from construction inception through system installation. In the Construction Phase, the CxA is involved through meetings and site visits. The CxA performs the following steps: Submit Cx Plan Based on the construction documents and Cx contract, the CxA develops the Cx Plan and submits it to the Owner and A/E for review. The CxA incorporates the feedback and submits the revised draft. The CxA maintains and updates the Cx Plan as necessary throughout the Cx process. Review Construction Submittals and Sequence of Operations (SOO) The CxA reviews the submittals and SOO which pertain to the Cx scope to confirm the systems/equipment meet the Owner s requirements and goals. The CxA documents their feedback and provides it to the A/E and/or Contractor as necessary. Cx Kickoff Meeting The CxA coordinates a Cx Kickoff Meeting with the Owner, A/E, and contractors to communicate the Cx process, their responsibilities, and overall expectations. Site Visits & Meetings The CxA will conduct site visits and attend project meetings as necessary to stay apprised of project status and to identify issues; such issues will be identified and communicated via the Observation Log. The CxA s presence will gradually increase as the project nears the Acceptance Phase. Distribute Pre-/Start-Up Tests The contractor distributes the Pre-Start and Start-up Tests to the CxA. Contractors should not start equipment without coordinating with the CxA; contractor shall give 7 days notice to CxA of equipment s readiness. Submit Cx Tests for Review The CxA develops the Functional Performance Tests and provides them to the A/E and Contractor for review. The CxA incorporates feedback as necessary. Maintain Observation Log The CxA will document identified issues from site visits and tests in the Observation Log. The CxA will communicate such issues as needed to the Owner, A/E, and/or Contractor. The CxA will maintain and update the log throughout the project and will submit a final log as part of the Cx Report. 6

7 ACCEPTANCE PHASE The Acceptance Phase spans from system start-up through building/system turn-over. In the Acceptance Phase, the CxA assumes the leadership role in coordinating system testing. The CxA performs the following steps: Review Pre-Start Tests The contractors submit completed Pre-Start Tests and manufacturer supplied tests to the CxA. The CxA reviews such documents to verify that the equipment/system is ready for start-up. In some cases the Pre-Start may be performed with the Start-Up Tests. Coordinate Start-Up Tests The CxA will work with the Contractor to coordinate system/equipment startup. The CxA will witness selective start-up activities as performed by the contractors per the CxA supplied Start-Up Tests. The CxA will document any issues on the Observation Log. Review & Verify TAB The CxA will spot verify the TAB as required by contract; the TAB Contractor will conduct the spot test as directed by the CxA. The CxA will document any issues in the Observation Log. PTP Verification The CxA will conduct a Point-to-Point sampling of the building controls system to verify that the field devices, system points, and graphic user interface (GUI) align. Conduct Functional Performance Tests (FPT) The CxA will coordinate with the Contractor and contractors to conduct the FPTs. The contractors will execute and assist with the tests as directed by the CxA. The CxA will document any issues in the Observation Log. CLOSE-OUT/TRANSITION PHASE The Project Close-Out or Transition focuses on the turnover of the facility/system to the Owner and facility operations staff. The CxA assists with this transition per the following steps: Review O&M Manuals The CxA will review the Operations & Maintenance (O&M) Manuals for completeness and adherence to project to requirements. The CxA will document the review and provide comments to the A/E and/or Contractor. Verify Training The CxA will verify the training of the facility operations staff on the various systems within the Cx scope. The contractors will provide the CxA with copies of the training material and completed training attendance logs. Resolve Observation Log The CxA will work with the Owner, A/E, Contractor, and contractors to resolve the open issues on the Observation Log. The end goal is to close all issues on the log or obtain mutual acceptance of outstanding issues. Deliver Cx Report The CxA will provide a draft Cx Report to the Owner and A/E to review. The CxA will incorporate feedback as necessary. The CxA will obtain all required documentation and update Cx Report. The CxA will deliver final Cx Report to the Owner. 7

8 DELIVERABLES DESIGN PHASE The following deliverables should be expected during the Design Phase: Design Set Review Comments Commissioning Specifications Construction Document Set Review Comments CONSTRUCTION PHASE The following deliverables should be expected during the Construction Phase: Construction Submittal Review Comments Pre-Start & Start-Up Tests Review Comments Functional Performance Tests Observation Log ACCEPTANCE PHASE The following deliverables should be expected during the Acceptance Phase: Observation Log (update) TAB Review Comments CLOSE-OUT/TRANSITION PHASE The following deliverables should be expected during the Close-Out/Transition Phase: Operations & Maintenance (O&M) Manual Review Comments Commissioning Report (shall contain at least the following) Executive Summary Final Cx Plan Final Observation Log Document Review Comments Completed Test Forms TAB Report Training Documentation As-Builts with Sequence of Operations 8

9 Responsibilities PARTIES INVOLVED The commissioning process requires the involvement of various project stakeholders. Below is a list of parties, other than the CxA, who have responsibilities in the commissioning process. These responsibilities do not negate contract requirements or specifications. Owner Jefferson County School District R Quail Street Building #4, Lakewood, Colorado Tom Stapleton tstaplet@jeffco.k12.co.us Design Team (A/E) Sy-Bazz Architecture, LCC 1615 California Street, Suite 210, Denver, Colorado James Bazzanella bazz@sybazz.com BCER Engineering, Inc Ward Road, Suite 200, Arvada, Colorado Paul Miskowicz, P.E pmiskowicz@bcer.com General Contractor (GC) Contractor GH Phipps 5995 Greenwood Plaza Blvd., Suite 100, Greenwood Village, Colorado Bea Mahoney bea.mahoney@ghphipps.com Marc Mumby marc.mumby@ghphipps.com Mechanical Contractor Legacy Mechanical, Inc South palatte River Drive, Denver, Colorado Troy Kauffman tkauffman@legacy-mechanical.com Barry Randall brandall@legacy-mechanical.com Controls Contractor Johnson Controls, Inc West Centennial Road, Littleton, Colorado Jack Pine jack.pine@jci.com 9

10 OWNER S RESPONSIBILITIES Below are the Owner s responsibilities by phase: Design Phase Select Commissioning Agent Review and provide feedback to CxA on the Construction Phase Include Commissioning Agent in pertinent communications and meetings, including meeting minutes, drawing updates, known issues, etc. Review and provide feedback to CxA of the test procedures Attend progress meetings to observe and provide direction on open issues Conduct periodic site visits; Report any issues to CxA for documentation and follow-up Witness Start-up Testing, if desired Periodically include Operations staff in site inspections Acceptance Phase Witness/participate in FPT at Owner s discretion Work with CxA, A/E, and Contractor to resolve issues Close-Out/Transition Phase Ensure Operations staff is available for training Review Final Commissioning Report Operations & Maintenance Phase Operate and maintain the systems & equipment facility per original equipment manufacturer (OEM) requirements or recommended maintenance practices Log system parameter changes and document any deficiencies Notify Cx Team of any significant facility/system changes required or of any unanticipated occupancy requirements that become evident Inform the design/construct team of any salient alterations or changes to the systems and their setup and indicate why it was necessitated Partner with CxA to resolve issues Provide building access to CxA to conduct site reviews, utility analysis, and resolve issues Provide remote access to controls system for the CxA to monitor; provide application and network login/username, as required 10

11 A/E S RESPONSIBILITIES Below are the A/E s responsibilities by phase: Design Phase Review and provide feedback to CxA The A/E is responsible for providing the CxA with a copy of the Design Documents (about 95% complete) for the commissioning review. The A/E should allow at least three weeks for a design review. The A/E is responsible for providing the CxA with a copy of the Construction Documents (about 100% complete) for the commissioning review. The A/E team will address/incorporate the CxA s review comments The A/E team will review and incorporate commissioning specifications into the construction documents Include Commissioning Agent in pertinent communications and meetings, including meeting minutes, drawing updates, known issues, etc Construction Phase Review submittals, shop drawings, and product data; forward copies to CxA Review commissioning test procedures and provide feedback Participate in the resolution of system deficiencies identified during commissioning, in accordance with the contract documents Acceptance Phase Consult on and resolve any design-related issues that arise during acceptance testing Mechanical Design Engineer shall review and approve balancing reports Close-Out/Transition Phase Provide updated as-builts, one-line diagrams, and sequence of operations to CxA Operation & Maintenance Phase Consult with Owner as necessary to convey and maintain design intent and respond to any identified deficiencies Participate in the resolution of non-compliance, non-conformance and design deficiencies identified during warranty phase 11

12 GENERAL CONTRACTOR S AND CONTRACTORS RESPONSIBILITIES Below are the General Contractor s (GC) and Contractors responsibilities by phase. These are in addition to the Commissioning Specifications and contract documents. In general, the GC is responsible to ensure all their contractors support and meet the requirements of the commissioning process. Design Phase The GC is responsible for scheduling and cost estimating Include Commissioning Agent in pertinent communications and meetings, including meeting minutes, drawing updates, known issues, etc. Construction Phase Provide copy of submittals to CxA in a timely manner Install equipment per manufacturer and construction specifications Review commissioning test procedures and provide feedback to CxA Complete Pre-Start Tests and inform CxA equipment is ready for start-up Execute Start-Up Tests under direction of CxA Participate in the resolution of system deficiencies identified during commissioning, in accordance with the contract documents Include Commissioning Agent in pertinent communications and meetings, including meeting minutes, drawing updates, known issues, field changes, etc Assemble and provide copy of O&M Manual, updated drawings, final submittals, record product data, and other pertinent documents to the CxA for review Acceptance Phase Execute FPT under direction of CxA Resolve issues as identified Close-Out/Transition Phase Conduct training for Operations staff as coordinated by CxA Provide copy of training material to CxA Operation & Maintenance Phase Work with Owner and CxA to resolve issues as identified 12

Energy Design Resources Commissioning Plan Outline Template

Energy Design Resources Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project. DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly

More information

Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY

Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. HVAC Commissioning description. 2. HVAC Commissioning responsibilities. 1.2 REFERENCES A. American Society

More information

Design Guidelines for Facilities Construction:

Design Guidelines for Facilities Construction: Engineering Division Facilities Management Department Design Guidelines for Facilities Construction: DESIGN GUIDELINE DG01-9 General Commissioning Requirements Part 1 - GENERAL 1.1 SUMMARY A. Section includes

More information

Building Commissioning 17900-1

Building Commissioning 17900-1 SECTION 17900 BUILDING COMMISSIONING PART 1 - GENERAL 1.01 WORK DESCRIPTION: A. General: 1. The Commissioning process is a joint team effort to ensure that all mechanical equipment, controls, and systems

More information

COMMISSIONING OF FIRE ALARM SYSTEMS

COMMISSIONING OF FIRE ALARM SYSTEMS COMMISSIONING OF FIRE ALARM SYSTEMS OWNER FURNISHED The owner directly contracts an independent third party commissioning agent for this project. This Commissioning Plan has been included for reference

More information

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work

More information

The Life-Cycle of Commissioning for New Construction

The Life-Cycle of Commissioning for New Construction The Life-Cycle of Commissioning for New Construction A Case Study at NGA Campus East Owner/Facility Manager: Dan Kailey and Matt Burkholder National Geospatial-Intelligence Agency (NGA) Commissioning Service

More information

Volume II- Project Development Processes

Volume II- Project Development Processes Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required

More information

Commissioning of Fire Protection and Life Safety Systems. Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA

Commissioning of Fire Protection and Life Safety Systems. Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA Fire Protection Engineering s role in sustainability through Commissioning

More information

Planned and Emergency Utility Outage Guidelines

Planned and Emergency Utility Outage Guidelines Revised: April 4, 2014 GUIDELINES: PURPOSE: The purpose of these guidelines is to define roles and responsibilities in requesting, coordinating scheduling, and executing utility outages and restoration

More information

Exhibit C: Scope of Work and Schedule of Deliverables

Exhibit C: Scope of Work and Schedule of Deliverables Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza

More information

Commissioning of Mission Critical Facilities

Commissioning of Mission Critical Facilities Commissioning of Mission Critical Facilities Terry L. Rodgers, CPE, CPMP VP of Sustainable Operations Primary Integration Solutions Paul Liesman SVP of FM & Commissioning Syska Hennessy Group AIA Quality

More information

Commissioning Your Data Center for Greater Availability, Safety and Efficiency While Reducing Costs Throughout the Life Cycle

Commissioning Your Data Center for Greater Availability, Safety and Efficiency While Reducing Costs Throughout the Life Cycle A White Paper from the Experts in Business-Critical Continuity TM Commissioning Your Data Center for Greater Availability, Safety and Efficiency While Reducing Costs Throughout the Life Cycle Executive

More information

Summary of Modifications/Changes in this Update

Summary of Modifications/Changes in this Update Summary of Modifications/Changes in this Update This Summary of Changes is for information only. It is not a part of the referenced document, and should not be used for project documentation. U.S. Department

More information

Construction Management Standards of Practice

Construction Management Standards of Practice Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388

More information

COMMISSIONING SUMMARY TEMPLATE

COMMISSIONING SUMMARY TEMPLATE COMMISSIONING SUMMARY TEMPLATE The following template shall be completed and submitted for permit review. Provide additional attachments as appropriate. SECTION 1 PROJECT DESCRIPTION Name of Project Project

More information

The Building Commissioning Association

The Building Commissioning Association Best Practices in Commissioning Existing Buildings Building Commissioning Association EXECUTIVE SUMMARY The Building Commissioning Association (BCA) defines Existing Building Commissioning (EBCx) as: a

More information

Facilities Maintenance Standards rev 9-1-2015

Facilities Maintenance Standards rev 9-1-2015 Facilities Maintenance Standards rev 9-1-2015 Purpose The purpose of these standards is to outline the minimum requirements for maintaining state owned facilities and infrastructures in a manner that will

More information

Project Closeout Module 1 Construction Closeout Checklist

Project Closeout Module 1 Construction Closeout Checklist Project Closeout Module 1 Construction Closeout Checklist August 5, 2005 1 OAR Challenge How to Close the Project (Drain the Swamp) And Protect District Assets from Contractors (Alligators) 2 Project Closeout

More information

GSA Public Buildings Service. the building commissioning guide

GSA Public Buildings Service. the building commissioning guide GSA Public Buildings Service the building commissioning guide the building commissioning guide U.S. General Services Administration Public Buildings Service Office of the Chief Architect April 2005 table

More information

New Construction Building Commissioning Best Practice

New Construction Building Commissioning Best Practice New Construction Building Commissioning Best Practice Building Commissioning Association December 8, 2011 New Construction Building Commissioning Best Practice Table of Contents Section 1 Introduction

More information

Statement of Work. 3.0 Details of Service Pre Start-up. - 1 - Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary

Statement of Work. 3.0 Details of Service Pre Start-up. - 1 - Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary Installation Service Statement of Work - 1 - Cooling Start-up Service Cooling Start-up Service Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details

More information

The Future in Fire Protection and Life Safety Cx. David J. LeBlanc, PE, FSFPE

The Future in Fire Protection and Life Safety Cx. David J. LeBlanc, PE, FSFPE The Future in Fire Protection and Life Safety Cx David J. LeBlanc, PE, FSFPE AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute of Architects

More information

Collaborative Laboratory Commissioning and Sustaining the Optimal Building. By E. Lon Brightbill, P.E Facility Dynamics

Collaborative Laboratory Commissioning and Sustaining the Optimal Building. By E. Lon Brightbill, P.E Facility Dynamics Collaborative Laboratory Commissioning and Sustaining the Optimal Building By E. Lon Brightbill, P.E Facility Dynamics Overview DefineCommissioning (Cx) Put the Cx process in the Context of a State of

More information

GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES

GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Greenburgh Central School District No. 7 ( The District ) invites proposals to perform construction management

More information

CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning

CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning Presentation To: Canadian Fire Alarm Association (CFAA) Alberta Technical Seminar

More information

2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT

2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT Presentation Synopsis Heating, Ventilating and Air Conditioning Building Condition Assessment Vancouver, B.C. Prepared for: EPIC Prepared by: Douglas Spratt, P.Eng Douglas Spratt & Associates Ltd. www.dspratt-associates.com

More information

Facility Operations Integration

Facility Operations Integration Facility Operations Integration James Bartone, Schneider Electric Kevin Dalton, Digital Realty Trust Philip Beatty, Bradford Engineers Jason Schafer, Schneider Electric Michael Jordan, Vantage Data Centers

More information

HVAC MAINTENANCE SUPERVISOR (Range 121)

HVAC MAINTENANCE SUPERVISOR (Range 121) (Range 121) DEFINITION Supervises, plans, coordinates and performs a variety of fundamental and skilled work in the building and mechanical trades to ensure the overall physical integrity of District Locations.

More information

Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA

Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA Boggarm S. Setty, P.E., Fellow ASHRAE Setty & Associates, Ltd. 3040 Williams Drive, Suite 600, Fairfax,

More information

Introducing Bihun Commercial Services, Inc.

Introducing Bihun Commercial Services, Inc. Introducing Bihun Commercial Services, Inc. HVAC Maintenance Building Automation Systems Control System: Repairs & Installation Experience and Innovation in HVAC Solutions Bihun Commercial Services brings

More information

Manage Deliverables - Construction Step 6. July 12, 2012

Manage Deliverables - Construction Step 6. July 12, 2012 Manage Deliverables - Construction Step 6 July 12, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement

More information

Life of a Project. Phase General Activities Specific Activities Notes Expected Time Frame

Life of a Project. Phase General Activities Specific Activities Notes Expected Time Frame 1.0 Inception 1.1 Project Request from Client / User 1.2 Assignment 1.3 1.4 1.5 1.6 1.7 1.8 Preliminary Project Charter Submit Project Charter to Obtain internal project number Initial Project Authorization

More information

KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM

KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM AIR HANDLING UNITS... 1 CHILLERS... 2 COOLING TOWERS... 2 CLOSED LOOP COOLERS... 2 MISCELLANEOUS SUPPLY FANS...

More information

Sample - Existing Building Commissioning Plan

Sample - Existing Building Commissioning Plan Sample - Existing Building Commissioning Plan Version: Draft for Review Final Approved: Owner Site Address: Primary Site Contact Name and Telephone Number: Date Building Description The site consists of

More information

Planned, Limited Notice and Emergency Outage Guidelines

Planned, Limited Notice and Emergency Outage Guidelines Applies to: All Facilities Management Employees GUIDELINES: Issued: April 22, 2014 Revised: February 24, 2015 Author: Communications Coordinator PURPOSE: The purpose of these guidelines is to define roles

More information

Developing a Proper Scope of Work, Request for Proposal & Commissioning Specification

Developing a Proper Scope of Work, Request for Proposal & Commissioning Specification Developing a Proper Scope of Work, Request for Proposal & Commissioning Specification Joseph Lorino, P.E., LEED Horizon Engineering Associates, LLP Synopsis In order for the commissioning process to have

More information

Cx for Enhanced Healthcare Project Delivery. Presentation Format. Project features and timeline

Cx for Enhanced Healthcare Project Delivery. Presentation Format. Project features and timeline Cx for Enhanced Healthcare Project Delivery Rick Staley Sr. Construction Manager PH&S Joe Webb Construction Manager PH&S Richard Beam Director, Energy Management Services PH&S Todd McGuire, PE - Sr. Project

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES A. General Information Part I: Qualifications Information The Tacoma School District is soliciting Qualifications for onsite

More information

City of Jersey City REQUEST FOR PROPOSALS. LEED Commissioning Services. for the New Rescue One Firehouse City of Jersey City Project # 2007-001

City of Jersey City REQUEST FOR PROPOSALS. LEED Commissioning Services. for the New Rescue One Firehouse City of Jersey City Project # 2007-001 City of Jersey City REQUEST FOR PROPOSALS LEED Commissioning Services for the New Rescue One Firehouse City of Jersey City Project # 2007-001 SUBMISSION DEADLINE 4:00 PM 29 October 2009 Glenn A. Wrigley,

More information

Data Center Commissioning: What you need to know

Data Center Commissioning: What you need to know Data Center Commissioning: What you need to know Course # CXENERGY1511 AIA Provider # 50111116 AABC Commissioning Group CxEnergy Conference Henderson, NV April 30, 2015 Presented by: Judson H. Adams, P.E.,

More information

Mandatory Addendum to the Owner/Architect Contract For Projects Funded in Whole or in Part with State Capital Outlay Funds

Mandatory Addendum to the Owner/Architect Contract For Projects Funded in Whole or in Part with State Capital Outlay Funds Page 1 of 5 Mandatory Addendum to the Owner/Architect Contract For Projects Funded in Whole or in Part with State Capital Outlay Funds The Owner may use any form of agreement mutually agreed upon by the

More information

Commissioning Design/Build Projects

Commissioning Design/Build Projects This article was published in ASHRAE Journal, October 2012. Copyright 2012 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/ or distributed electronically or in paper form without permission

More information

ACG COMMISSIONING GUIDELINE. For Building Owners, Design Professionals and Commissioning Service Providers

ACG COMMISSIONING GUIDELINE. For Building Owners, Design Professionals and Commissioning Service Providers ACG COMMISSIONING GUIDELINE For Building Owners, Design Professionals and Commissioning Service Providers ACG COMMISSIONING GUIDELINE For Building Owners, Design Professionals and Commissioning Service

More information

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997 Why a Project Check List? A good way to ensure that all start-up tasks are completed prior to actually starting the project is to develop a start-up check list. The check list can be developed and then

More information

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services Project Management Methodology Framework 1 - Executive Summary The purpose of this document is to introduce the University community

More information

Commissioning and Maintenance: Two Sides of the Same Coin? Kristin Heinemeier, PE, PhD Principal Engineer UC Davis WCEC

Commissioning and Maintenance: Two Sides of the Same Coin? Kristin Heinemeier, PE, PhD Principal Engineer UC Davis WCEC Commissioning and Maintenance: Two Sides of the Same Coin? Kristin Heinemeier, PE, PhD Principal Engineer UC Davis WCEC AIA Quality Assurance The Building Commissioning Association is a Registered Provider

More information

Module 1: INTRODUCTION. Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION"

Module 1: INTRODUCTION. Submodule 1: What is Construction Quality Management (CQM)? PROACTIVE PREVENTION vs. REACTIVE INSPECTION Module 1: INTRODUCTION Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION" Objectives: After completing this submodule, you will be able to: State

More information

Enclosed Football Stadium Design History and Lessons Learned

Enclosed Football Stadium Design History and Lessons Learned Enclosed Football Stadium Design History and Lessons Learned Robert L. Towell, P.E., LEED AP, QCxP btowell@cxegroup.com CxE Group LLC St. Louis, Missouri 314-436-6543 With thanks to the St. Louis Convention

More information

Revised Work Scope Dated April 23 rd, 2015

Revised Work Scope Dated April 23 rd, 2015 Revised Work Scope Dated April 23 rd, 2015 2.4 SCOPE OF SERVICES The following combines the Scope of Services included in RFQ No. 671 dated March 12, 2015 and the Invitation to Interview letter dated March

More information

Service Solutions Maintenance Programs Construction Solutions Plumbing Building Automation & Controls

Service Solutions Maintenance Programs Construction Solutions Plumbing Building Automation & Controls Service Maintenance Programs Construction Plumbing Building Automation & Controls Service Our Service department can customize proposals to meet any mechanical or budgetary needs. Customers choose AMS

More information

Construction Management System (CMS) Deliverable Review Process

Construction Management System (CMS) Deliverable Review Process Construction Management System (CMS) Deliverable Review Process State of California Department of Transportation Division of Construction December 21, 2009 Version 1.0 Approvals Name: Title: Mark Leja

More information

GUIDELINES FOR AUGUST 1995

GUIDELINES FOR AUGUST 1995 GUIDELINES FOR ELECTRICAL ENGINEERING SERVICES AUGUST 1995 PUBLISHED BY: PROFESSIONAL ENGINEERS AND GEOSCIENTISTS OF NEWFOUNDLAND & LABRADOR (PEGNL) P.O. Box 21207, St. John's, NL A1A 5B2 Telephone: (709)

More information

4.4 Commissioning, Handover and Warranty

4.4 Commissioning, Handover and Warranty 4.4 Commissioning, Handover and Warranty 4.4.1 Building Commissioning and Manuals The Building Commissioning formalizes the review and integration of all project expectations during the planning and design,

More information

UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01

UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01 GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per

More information

Request of Qualification Proposal for Construction Management Services

Request of Qualification Proposal for Construction Management Services Request of Qualification Proposal for Construction Management Services Dated June 10, 2014 Table of Contents Overview 3 Introduction 4 Scope of Construction Managers Services 4 Submission of Qualifications

More information

Chris Clement 701 Bayou Lane Thibodaux, LA 70301 985.446.7320

Chris Clement 701 Bayou Lane Thibodaux, LA 70301 985.446.7320 Chris Clement 701 Bayou Lane Thibodaux, LA 70301 985.446.7320 Position: Facility Assistant Maintenance Manager B Date: May 17, 2010 - present 70% OF TIME- is spent on following duties. Assist the Facility

More information

Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings

Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings Advanced Energy Design Guide LEED Strategies for Schools and High Performance Buildings Today s Presenters Stephen Koontz, LEED AP Energy Services Leader Tampa Bay Trane Allen Irvine General Sales Manager

More information

Example Retrocommissioning Measure: Opening Throttled Discharge Valves

Example Retrocommissioning Measure: Opening Throttled Discharge Valves Opening Throttled Discharge Valves This 21-story building, constructed in 1997, is located in Oregon and contains 589,000 gross square feet of mostly office occupancy. The HVAC system includes six large

More information

REQUEST FOR PROPOSAL MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION

REQUEST FOR PROPOSAL MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION REQUEST FOR PROPOSAL For MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES For VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION CITY OF ROCHESTER November 2009 TABLE OF CONTENTS GENERAL INFORMATION

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services

More information

BUILDING ENVELOPE COMMISSIONING FOR THE EVERYDAY COMMISSIONING AGENT

BUILDING ENVELOPE COMMISSIONING FOR THE EVERYDAY COMMISSIONING AGENT BUILDING ENVELOPE COMMISSIONING FOR THE EVERYDAY COMMISSIONING AGENT Building Envelope for the Everyday CxA Presented by: Mark F. Warren, CCP, LEED AP Senior Vice President - WSP Flack + Kurtz Anand Seth,

More information

WESTERN MICHIGAN UNIVERSITY

WESTERN MICHIGAN UNIVERSITY WESTERN MICHIGAN UNIVERSITY Facilities Management Department DeVon Miller Building Commissioning Administrator 1 INTRODUCTION DeVon C. Miller, CPMP, LEED AP Building Commissioning Administrator Engineering

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT SECTION 6: QUALITY ASSURANCE PROCEDURE: PM 6.02 TITLE: QUALITY ASSURANCE AUDITS DATE:

More information

QUALITY MANAGEMENT SYSTEM (QMS) PROGRAM MANAGEMENT DIVISION

QUALITY MANAGEMENT SYSTEM (QMS) PROGRAM MANAGEMENT DIVISION The Port of Long Beach Quality Management System QUALITY MANAGEMENT SYSTEM (QMS) PROGRAM MANAGEMENT DIVISION File Name: Quality Management System Version Number: Rev 1.0 Version Date: 07/24/2013 Table

More information

Job Grading Appeal Decision Under Section 5346 of Title 5, United States Code

Job Grading Appeal Decision Under Section 5346 of Title 5, United States Code U.S. Office of Personnel Management Office of Merit Systems Oversight and Effectiveness Classification Appeals and FLSA Programs Dallas Oversight Division 1100 Commerce Street, Room 4C22 Dallas, TX 75242

More information

Denver International Airport Total Facility Optimization. Josh Foerschler Aurom Mahobian

Denver International Airport Total Facility Optimization. Josh Foerschler Aurom Mahobian Denver International Airport Total Facility Optimization Josh Foerschler Aurom Mahobian AGENDA DIA Intro BMcD-DIA History Optimization Projects Results Conclusion Denver International Airport Opened February

More information

NFPA 3 and 4 Commissioning and Integrated Testing of Fire Protection and Life Safety Systems. Matt Klaus Senior Fire Protection Engineer NFPA

NFPA 3 and 4 Commissioning and Integrated Testing of Fire Protection and Life Safety Systems. Matt Klaus Senior Fire Protection Engineer NFPA NFPA 3 and 4 Commissioning and Integrated Testing of Fire Protection and Life Safety Systems Matt Klaus Senior Fire Protection Engineer NFPA 1 The Recommended Practice 2 Coming Soon 3 Overview What is

More information

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86

More information

JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management

JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management JOHN HART GENERATING STATION REPLACEMENT PROJECT Schedule 9 Quality Management SCHEDULE 9 QUALITY MANAGEMENT TABLE OF CONTENTS 1. QUALITY MANAGEMENT SYSTEM... 1 1.1 Quality Management System...1 1.2 Project

More information

Project Management Plan for

Project Management Plan for Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...

More information

ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)

ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal Forms Part 4:

More information

OFFICE OF PERSONNEL MANAGEMENT ATLANTA OVERSIGHT DIVISION ATLANTA, GEORGIA

OFFICE OF PERSONNEL MANAGEMENT ATLANTA OVERSIGHT DIVISION ATLANTA, GEORGIA OFFICE OF PERSONNEL MANAGEMENT ATLANTA OVERSIGHT DIVISION ATLANTA, GEORGIA CLASSIFICATION APPEAL DECISION Under section 5112(b) of title 5, United States Code Appellant: [the appellant] Position: Engineering

More information

Company name Date submitted. Building address City State ZIP. E-mail* Building Sq. Ft.

Company name Date submitted. Building address City State ZIP. E-mail* Building Sq. Ft. Recommissioning Application Business Customer Information Company name Date submitted Building address City State ZIP Mailing address (if different) City State ZIP Contact person (print) Phone Fax E-mail*

More information

The main steam enters the building in the basement mechanical room; this is where the condensate line also leaves the building.

The main steam enters the building in the basement mechanical room; this is where the condensate line also leaves the building. MSV: Square Footage: 24,844 No. of Floors: 1 Year Built: 1963 Type of Use: Lounge and dining area open all night for snacks Steam Water-cooled condenser, 50-Ton York unit with a 6 cylinder-reciprocating

More information

Vendor Performance Evaluation Requirements

Vendor Performance Evaluation Requirements Vendor Performance Evaluation Requirements The awarded vendor should note that the Contract Administrator will document the contractor s performance by completing a Vendor Performance Evaluation based

More information

Florida Power & Light Company. Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards. Effective: November 9, 2015

Florida Power & Light Company. Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards. Effective: November 9, 2015 Florida Power & Light Company Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards Effective: November 9, 2015 Table of Contents Eligibility Requirements - Chiller... 2 Rebate Amount

More information

Post Occupancy Evaluation (POE) Technical Instructions

Post Occupancy Evaluation (POE) Technical Instructions 1.0 Purpose These technical instructions define the typical steps required by HHS personnel in the use of the. The POE consists of a detailed and systematic assessment of a facility that is operational

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

Condensing Boiler Efficiency

Condensing Boiler Efficiency Condensing Boiler Efficiency Date: July 17, 2012 PRES E NT ED BY DO N L E O NA RDI LE O N A RD I I NC. HV AC T RAI N I N G & C ON SU LT IN G Concepts 1 The current state of evolution in boiler design 2

More information

Classification and Qualification STANDARDS

Classification and Qualification STANDARDS Classification and Qualification STANDARDS HVAC Series Classification Title Class Code Date Established Date Revised Operating Engineer Building Service Engineer Air Conditioning/Refrigeration Mechanic

More information

ACG Commissioning Guideline

ACG Commissioning Guideline ACG Commissioning Guideline Appendix A Sample Commissioning Specification NOTES TO APPENDIX A This appendix contains a sample Request for Proposal (RFP) for Commissioning Services as would be issued by

More information

Is the Grass Greener on the other side? Examples of Cx south of the border. Jorge Torres Coto, Empirical Engineering

Is the Grass Greener on the other side? Examples of Cx south of the border. Jorge Torres Coto, Empirical Engineering Is the Grass Greener on the other side? Examples of Cx south of the border Jorge Torres Coto, Empirical Engineering 21 st National Conference on Building Commissioning AIA Quality Assurance The Building

More information

DGS Prolog Manager & Prolog Converge User Manual

DGS Prolog Manager & Prolog Converge User Manual DGS Prolog Manager & Prolog Converge User Manual Table of Contents Prolog Overview Flowchart 1 Entering a New Project 2 Solicitations 7 Contracts Module 14 Change Orders 21 Change Order Workflow Diagram

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

QUALITY MANAGEMENT SYSTEM REQUIREMENTS

QUALITY MANAGEMENT SYSTEM REQUIREMENTS QUALITY MANAGEMENT SYSTEM REQUIREMENTS FOR BUILDERS 2014 400 Prince George s Blvd. Upper Marlboro, MD 20774 800.638.8556 HomeInnovation.com TABLE OF CONTENTS Introduction... iii Notes... iii 1 General...1

More information

Commissioning - Construction Documents (Page 1 of 6)

Commissioning - Construction Documents (Page 1 of 6) Commissioning - Construction Documents (Page 1 of 6) A. General Information Climate Zone: Building Type: Conditioned Area (sf): Reviewer's Name: Reviewer's Agency: Note: Design Review for each system/subsystem

More information

REQUEST FOR QUALIFICATIONS/PROPOSAL (RFQ/P) FOR A ROOF CONSULTANT

REQUEST FOR QUALIFICATIONS/PROPOSAL (RFQ/P) FOR A ROOF CONSULTANT REQUEST FOR QUALIFICATIONS/PROPOSAL (RFQ/P) FOR A ROOF CONSULTANT Durango School District 9 R (Owner) 201 East 12 th Street Durango, Colorado 81301 Phone (970) 247 5411, ext. 1458 PROPOSAL DUE DATE/DELIVERY

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.00 10 (February 2010) Change 1-05/15 ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 01 (January 2008) UNIFIED FACILITIES

More information

Consultancy Services Proposal

Consultancy Services Proposal Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847

More information

2012 BIM Guidelines and Standards (Rev. 00) University at Albany

2012 BIM Guidelines and Standards (Rev. 00) University at Albany A. Building Information Modeling (BIM) Guidelines: The Office of AECM will require the submission of BIM modeling files as part of an electronic file submission to the AECM project manager as requested

More information

National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, MD 20877-4121 ph: 301-977-3698 fax: 301-977-9589 www.nebb.

National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, MD 20877-4121 ph: 301-977-3698 fax: 301-977-9589 www.nebb. National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, MD 20877-4121 ph: 301-977-3698 fax: 301-977-9589 www.nebb.org PROCEDURAL STANDARDS FOR WHOLE BUILDING SYSTEMS COMMISSIONING

More information

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes

More information

SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION

SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION The purpose of this guide specification is to assist the specifier in correctly specifying Mechanical System Testing

More information

2611 Waterfront Parkway, Suite 340 Indianapolis, IN 46214 Tel. (317) 536-2618

2611 Waterfront Parkway, Suite 340 Indianapolis, IN 46214 Tel. (317) 536-2618 HOT WATER, LIGHTING CONTROLS, PHOTOVOLTAIC, BUILDING ENVELOPE, ELEVATORS, ACID WASTE PIPING, EMERGENCY POWER, FIRE ALARM and Note: The Unified Facilities Guide Specification Section 070523 was referenced

More information

City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E.

City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E. City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E. GENERAL PURPOSE Under direction, manages, oversees, evaluates,

More information

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES. Level III Content Outline

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES. Level III Content Outline Fire Alarm Systems Level III Content Outline The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 3.1

More information

Chapter 4: Contractor Quality Control

Chapter 4: Contractor Quality Control Chapter 4: Contractor Quality Control Seattle District, NWS Last updated: 05FEB14 Chapter 4 Contractor Quality Control 1. GENERAL. Contractor is responsible for quality control and shall establish and

More information