Denver International Airport Data Center Commissioning Plan
|
|
|
- Albert Jefferson
- 10 years ago
- Views:
Transcription
1 Denver International Airport Data Center Jefferson County School District Columbine High School Renovation Date July 25th, 2014 Prepared by Patrick Corrigan, QCxP Commissioning Engineer McKinstry McKINSTRY FOR THE LIFE OF YOUR BUILDING Mechanical & Electrical Design/Build Mobile Service Energy Solutions Facility Management
2 INTRODUCTION THE PURPOSE OF THE COMMISSIONING (CX) PLAN This Commissioning (Cx) Plan describes the commissioning process for the Columbine High School renovation project located in Littleton, Colorado. This living document provides a high-level overview of the commissioning process, scope summary, and it identifies the various roles and respective responsibilities of those that will participate in the commissioning process. The end goal of the and the execution thereof is to ensure the systems are designed, installed, started, tested, and documented to meet both the owner s requirements and the specifications of the project. The contains the following sections: Introduction Purpose of the Project Description Systems to be Commissioned Commissioning Schedule Terminology Commissioning Overview Parties Involved Design Phase Construction Phase Acceptance Phase Close-Out/Transition Phase Operation & Maintenance (O&M) Phase Deliverables Responsibilities PROJECT DESCRIPTION The project includes a complete DDC replacement of the pneumatic controls system. The following valves will be replaced: all terminal unit re-heat valves (190), heating and cooling valves on the existing RTUs (10), new RTUs (7), and the cooling tower sump fill and drain valves (2). The existing valves are pneumatic controlled and will be replaced with direct digital controlled (DDC) valves. The project also includes the replacement and installation of (6) cooling only RTUs, (1) make-up air unit, (4) boilers, (2) heating hot water pumps. SYSTEMS TO BE COMMISSIONED The commissioning process for this project will include the following systems: Control Valve Replacement o Installation Verificaiton Rooftop Units o Submittal Review o Start-up Witnessing 2
3 Air Cooled Condensing Unit o Submittal Review o Start-up Witnessing Make-up Air Unit o Submittal Review o Start-up Witnessing Exhaust Fan o Submittal Review Boiler o Submittal Review o Witness Start-up and Combustion Analysis Chiller 3
4 TERMINOLOGY Below is a list of common terminology and abbreviations used throughout this document. A/E Architect/Engineer BOD Basis of Design Cx - Commissioning CxA Commissioning Agent FPT Functional Performance Test(s) OPR Owner s Project Requirements TAB Testing, Adjusting, and Balancing Contractor(s) Construction Manager/Prime Contractor(s) SOO Sequence of Operations CMMS Computerized Maintenance Management System KRC Knowledge Response Center M&V Measurement & Verification O&M Operations & Maintenance 4
5 Commissioning Overview DESCRIPTION Commissioning is the systematic process of ensuring that all building systems included in the scope perform interactively according to the design intent, BOD, and the Owner s operational needs. Generally, the CxA is involved in the process from design through post-construction. The CxA partners with the Owner, A/E firm(s), Contractors, and Owner s Facility Staff throughout the process to identify the operating requirements, verify system functionality & documentation, and assist with the transition of the facility to steady-state operations. Below is a high-level flowchart of the commissioning process, which is followed by a description of each phase. DESIGN PHASE Review Design Set Provide Cx Specs Review CD Set CONSTRUCTION PHASE Submit Cx Plan Review Construction Submittals and SOO Cx Kickoff Meeting Site Visits & Meetings Distribute Pre- /Start-Up Tests Submit Cx Tests for Review Maintain Observation Log ACCEPTANCE PHASE Review Pre-Start Tests Coordinate Start-Up Tests Review & Verify TAB PTP Verification Conduct FPTs CLOSE-OUT/TRANSITION PHASE Review O&M Manuals Verify Training Resolve Observation Log Deliver Cx Report 5
6 DESIGN PHASE The Design Phase spans from pre-design through the generation of construction documents. In the Design Phase, the Cx steps are as follows: Review Design Set The A/E provides the CxA a design development set for review. The CxA reviews the design set for inconsistencies, misses, and opportunities for improvement. The CxA documents their comments and provides them to the A/E for incorporation into the design set. Provide Cx Specs The CxA provides Commissioning Specifications to the A/E to include in the Construction Document (CD) set. The CxA caters the specifications as necessary to the project. Review CD Set The A/E provides a Construction Document (CD) set that is near 100% complete to the CxA for review. The CxA reviews the set to verify previous comments have been addressed and to identify any further misses or opportunities. The CxA documents their comments and provides them to the A/E for incorporation into the construction set. CONSTRUCTION PHASE The Construction Phase spans from construction inception through system installation. In the Construction Phase, the CxA is involved through meetings and site visits. The CxA performs the following steps: Submit Cx Plan Based on the construction documents and Cx contract, the CxA develops the Cx Plan and submits it to the Owner and A/E for review. The CxA incorporates the feedback and submits the revised draft. The CxA maintains and updates the Cx Plan as necessary throughout the Cx process. Review Construction Submittals and Sequence of Operations (SOO) The CxA reviews the submittals and SOO which pertain to the Cx scope to confirm the systems/equipment meet the Owner s requirements and goals. The CxA documents their feedback and provides it to the A/E and/or Contractor as necessary. Cx Kickoff Meeting The CxA coordinates a Cx Kickoff Meeting with the Owner, A/E, and contractors to communicate the Cx process, their responsibilities, and overall expectations. Site Visits & Meetings The CxA will conduct site visits and attend project meetings as necessary to stay apprised of project status and to identify issues; such issues will be identified and communicated via the Observation Log. The CxA s presence will gradually increase as the project nears the Acceptance Phase. Distribute Pre-/Start-Up Tests The contractor distributes the Pre-Start and Start-up Tests to the CxA. Contractors should not start equipment without coordinating with the CxA; contractor shall give 7 days notice to CxA of equipment s readiness. Submit Cx Tests for Review The CxA develops the Functional Performance Tests and provides them to the A/E and Contractor for review. The CxA incorporates feedback as necessary. Maintain Observation Log The CxA will document identified issues from site visits and tests in the Observation Log. The CxA will communicate such issues as needed to the Owner, A/E, and/or Contractor. The CxA will maintain and update the log throughout the project and will submit a final log as part of the Cx Report. 6
7 ACCEPTANCE PHASE The Acceptance Phase spans from system start-up through building/system turn-over. In the Acceptance Phase, the CxA assumes the leadership role in coordinating system testing. The CxA performs the following steps: Review Pre-Start Tests The contractors submit completed Pre-Start Tests and manufacturer supplied tests to the CxA. The CxA reviews such documents to verify that the equipment/system is ready for start-up. In some cases the Pre-Start may be performed with the Start-Up Tests. Coordinate Start-Up Tests The CxA will work with the Contractor to coordinate system/equipment startup. The CxA will witness selective start-up activities as performed by the contractors per the CxA supplied Start-Up Tests. The CxA will document any issues on the Observation Log. Review & Verify TAB The CxA will spot verify the TAB as required by contract; the TAB Contractor will conduct the spot test as directed by the CxA. The CxA will document any issues in the Observation Log. PTP Verification The CxA will conduct a Point-to-Point sampling of the building controls system to verify that the field devices, system points, and graphic user interface (GUI) align. Conduct Functional Performance Tests (FPT) The CxA will coordinate with the Contractor and contractors to conduct the FPTs. The contractors will execute and assist with the tests as directed by the CxA. The CxA will document any issues in the Observation Log. CLOSE-OUT/TRANSITION PHASE The Project Close-Out or Transition focuses on the turnover of the facility/system to the Owner and facility operations staff. The CxA assists with this transition per the following steps: Review O&M Manuals The CxA will review the Operations & Maintenance (O&M) Manuals for completeness and adherence to project to requirements. The CxA will document the review and provide comments to the A/E and/or Contractor. Verify Training The CxA will verify the training of the facility operations staff on the various systems within the Cx scope. The contractors will provide the CxA with copies of the training material and completed training attendance logs. Resolve Observation Log The CxA will work with the Owner, A/E, Contractor, and contractors to resolve the open issues on the Observation Log. The end goal is to close all issues on the log or obtain mutual acceptance of outstanding issues. Deliver Cx Report The CxA will provide a draft Cx Report to the Owner and A/E to review. The CxA will incorporate feedback as necessary. The CxA will obtain all required documentation and update Cx Report. The CxA will deliver final Cx Report to the Owner. 7
8 DELIVERABLES DESIGN PHASE The following deliverables should be expected during the Design Phase: Design Set Review Comments Commissioning Specifications Construction Document Set Review Comments CONSTRUCTION PHASE The following deliverables should be expected during the Construction Phase: Construction Submittal Review Comments Pre-Start & Start-Up Tests Review Comments Functional Performance Tests Observation Log ACCEPTANCE PHASE The following deliverables should be expected during the Acceptance Phase: Observation Log (update) TAB Review Comments CLOSE-OUT/TRANSITION PHASE The following deliverables should be expected during the Close-Out/Transition Phase: Operations & Maintenance (O&M) Manual Review Comments Commissioning Report (shall contain at least the following) Executive Summary Final Cx Plan Final Observation Log Document Review Comments Completed Test Forms TAB Report Training Documentation As-Builts with Sequence of Operations 8
9 Responsibilities PARTIES INVOLVED The commissioning process requires the involvement of various project stakeholders. Below is a list of parties, other than the CxA, who have responsibilities in the commissioning process. These responsibilities do not negate contract requirements or specifications. Owner Jefferson County School District R Quail Street Building #4, Lakewood, Colorado Tom Stapleton [email protected] Design Team (A/E) Sy-Bazz Architecture, LCC 1615 California Street, Suite 210, Denver, Colorado James Bazzanella [email protected] BCER Engineering, Inc Ward Road, Suite 200, Arvada, Colorado Paul Miskowicz, P.E [email protected] General Contractor (GC) Contractor GH Phipps 5995 Greenwood Plaza Blvd., Suite 100, Greenwood Village, Colorado Bea Mahoney [email protected] Marc Mumby [email protected] Mechanical Contractor Legacy Mechanical, Inc South palatte River Drive, Denver, Colorado Troy Kauffman [email protected] Barry Randall [email protected] Controls Contractor Johnson Controls, Inc West Centennial Road, Littleton, Colorado Jack Pine [email protected] 9
10 OWNER S RESPONSIBILITIES Below are the Owner s responsibilities by phase: Design Phase Select Commissioning Agent Review and provide feedback to CxA on the Construction Phase Include Commissioning Agent in pertinent communications and meetings, including meeting minutes, drawing updates, known issues, etc. Review and provide feedback to CxA of the test procedures Attend progress meetings to observe and provide direction on open issues Conduct periodic site visits; Report any issues to CxA for documentation and follow-up Witness Start-up Testing, if desired Periodically include Operations staff in site inspections Acceptance Phase Witness/participate in FPT at Owner s discretion Work with CxA, A/E, and Contractor to resolve issues Close-Out/Transition Phase Ensure Operations staff is available for training Review Final Commissioning Report Operations & Maintenance Phase Operate and maintain the systems & equipment facility per original equipment manufacturer (OEM) requirements or recommended maintenance practices Log system parameter changes and document any deficiencies Notify Cx Team of any significant facility/system changes required or of any unanticipated occupancy requirements that become evident Inform the design/construct team of any salient alterations or changes to the systems and their setup and indicate why it was necessitated Partner with CxA to resolve issues Provide building access to CxA to conduct site reviews, utility analysis, and resolve issues Provide remote access to controls system for the CxA to monitor; provide application and network login/username, as required 10
11 A/E S RESPONSIBILITIES Below are the A/E s responsibilities by phase: Design Phase Review and provide feedback to CxA The A/E is responsible for providing the CxA with a copy of the Design Documents (about 95% complete) for the commissioning review. The A/E should allow at least three weeks for a design review. The A/E is responsible for providing the CxA with a copy of the Construction Documents (about 100% complete) for the commissioning review. The A/E team will address/incorporate the CxA s review comments The A/E team will review and incorporate commissioning specifications into the construction documents Include Commissioning Agent in pertinent communications and meetings, including meeting minutes, drawing updates, known issues, etc Construction Phase Review submittals, shop drawings, and product data; forward copies to CxA Review commissioning test procedures and provide feedback Participate in the resolution of system deficiencies identified during commissioning, in accordance with the contract documents Acceptance Phase Consult on and resolve any design-related issues that arise during acceptance testing Mechanical Design Engineer shall review and approve balancing reports Close-Out/Transition Phase Provide updated as-builts, one-line diagrams, and sequence of operations to CxA Operation & Maintenance Phase Consult with Owner as necessary to convey and maintain design intent and respond to any identified deficiencies Participate in the resolution of non-compliance, non-conformance and design deficiencies identified during warranty phase 11
12 GENERAL CONTRACTOR S AND CONTRACTORS RESPONSIBILITIES Below are the General Contractor s (GC) and Contractors responsibilities by phase. These are in addition to the Commissioning Specifications and contract documents. In general, the GC is responsible to ensure all their contractors support and meet the requirements of the commissioning process. Design Phase The GC is responsible for scheduling and cost estimating Include Commissioning Agent in pertinent communications and meetings, including meeting minutes, drawing updates, known issues, etc. Construction Phase Provide copy of submittals to CxA in a timely manner Install equipment per manufacturer and construction specifications Review commissioning test procedures and provide feedback to CxA Complete Pre-Start Tests and inform CxA equipment is ready for start-up Execute Start-Up Tests under direction of CxA Participate in the resolution of system deficiencies identified during commissioning, in accordance with the contract documents Include Commissioning Agent in pertinent communications and meetings, including meeting minutes, drawing updates, known issues, field changes, etc Assemble and provide copy of O&M Manual, updated drawings, final submittals, record product data, and other pertinent documents to the CxA for review Acceptance Phase Execute FPT under direction of CxA Resolve issues as identified Close-Out/Transition Phase Conduct training for Operations staff as coordinated by CxA Provide copy of training material to CxA Operation & Maintenance Phase Work with Owner and CxA to resolve issues as identified 12
Energy Design Resources Commissioning Plan Outline Template
IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended
A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.
DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly
Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY
SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. HVAC Commissioning description. 2. HVAC Commissioning responsibilities. 1.2 REFERENCES A. American Society
Design Guidelines for Facilities Construction:
Engineering Division Facilities Management Department Design Guidelines for Facilities Construction: DESIGN GUIDELINE DG01-9 General Commissioning Requirements Part 1 - GENERAL 1.1 SUMMARY A. Section includes
Building Commissioning 17900-1
SECTION 17900 BUILDING COMMISSIONING PART 1 - GENERAL 1.01 WORK DESCRIPTION: A. General: 1. The Commissioning process is a joint team effort to ensure that all mechanical equipment, controls, and systems
COMMISSIONING OF FIRE ALARM SYSTEMS
COMMISSIONING OF FIRE ALARM SYSTEMS OWNER FURNISHED The owner directly contracts an independent third party commissioning agent for this project. This Commissioning Plan has been included for reference
Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES
SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work
The Life-Cycle of Commissioning for New Construction
The Life-Cycle of Commissioning for New Construction A Case Study at NGA Campus East Owner/Facility Manager: Dan Kailey and Matt Burkholder National Geospatial-Intelligence Agency (NGA) Commissioning Service
Volume II- Project Development Processes
Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required
Commissioning of Fire Protection and Life Safety Systems. Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA Fire Protection Engineering s role in sustainability through Commissioning
Planned and Emergency Utility Outage Guidelines
Revised: April 4, 2014 GUIDELINES: PURPOSE: The purpose of these guidelines is to define roles and responsibilities in requesting, coordinating scheduling, and executing utility outages and restoration
Exhibit C: Scope of Work and Schedule of Deliverables
Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza
Commissioning of Mission Critical Facilities
Commissioning of Mission Critical Facilities Terry L. Rodgers, CPE, CPMP VP of Sustainable Operations Primary Integration Solutions Paul Liesman SVP of FM & Commissioning Syska Hennessy Group AIA Quality
Summary of Modifications/Changes in this Update
Summary of Modifications/Changes in this Update This Summary of Changes is for information only. It is not a part of the referenced document, and should not be used for project documentation. U.S. Department
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
COMMISSIONING SUMMARY TEMPLATE
COMMISSIONING SUMMARY TEMPLATE The following template shall be completed and submitted for permit review. Provide additional attachments as appropriate. SECTION 1 PROJECT DESCRIPTION Name of Project Project
The Building Commissioning Association
Best Practices in Commissioning Existing Buildings Building Commissioning Association EXECUTIVE SUMMARY The Building Commissioning Association (BCA) defines Existing Building Commissioning (EBCx) as: a
Facilities Maintenance Standards rev 9-1-2015
Facilities Maintenance Standards rev 9-1-2015 Purpose The purpose of these standards is to outline the minimum requirements for maintaining state owned facilities and infrastructures in a manner that will
Project Closeout Module 1 Construction Closeout Checklist
Project Closeout Module 1 Construction Closeout Checklist August 5, 2005 1 OAR Challenge How to Close the Project (Drain the Swamp) And Protect District Assets from Contractors (Alligators) 2 Project Closeout
GSA Public Buildings Service. the building commissioning guide
GSA Public Buildings Service the building commissioning guide the building commissioning guide U.S. General Services Administration Public Buildings Service Office of the Chief Architect April 2005 table
New Construction Building Commissioning Best Practice
New Construction Building Commissioning Best Practice Building Commissioning Association December 8, 2011 New Construction Building Commissioning Best Practice Table of Contents Section 1 Introduction
Statement of Work. 3.0 Details of Service Pre Start-up. - 1 - Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary
Installation Service Statement of Work - 1 - Cooling Start-up Service Cooling Start-up Service Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details
The Future in Fire Protection and Life Safety Cx. David J. LeBlanc, PE, FSFPE
The Future in Fire Protection and Life Safety Cx David J. LeBlanc, PE, FSFPE AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute of Architects
Collaborative Laboratory Commissioning and Sustaining the Optimal Building. By E. Lon Brightbill, P.E Facility Dynamics
Collaborative Laboratory Commissioning and Sustaining the Optimal Building By E. Lon Brightbill, P.E Facility Dynamics Overview DefineCommissioning (Cx) Put the Cx process in the Context of a State of
GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES
GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Greenburgh Central School District No. 7 ( The District ) invites proposals to perform construction management
CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning
CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning Presentation To: Canadian Fire Alarm Association (CFAA) Alberta Technical Seminar
2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT
Presentation Synopsis Heating, Ventilating and Air Conditioning Building Condition Assessment Vancouver, B.C. Prepared for: EPIC Prepared by: Douglas Spratt, P.Eng Douglas Spratt & Associates Ltd. www.dspratt-associates.com
Facility Operations Integration
Facility Operations Integration James Bartone, Schneider Electric Kevin Dalton, Digital Realty Trust Philip Beatty, Bradford Engineers Jason Schafer, Schneider Electric Michael Jordan, Vantage Data Centers
HVAC MAINTENANCE SUPERVISOR (Range 121)
(Range 121) DEFINITION Supervises, plans, coordinates and performs a variety of fundamental and skilled work in the building and mechanical trades to ensure the overall physical integrity of District Locations.
Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA
Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA Boggarm S. Setty, P.E., Fellow ASHRAE Setty & Associates, Ltd. 3040 Williams Drive, Suite 600, Fairfax,
Manage Deliverables - Construction Step 6. July 12, 2012
Manage Deliverables - Construction Step 6 July 12, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement
Life of a Project. Phase General Activities Specific Activities Notes Expected Time Frame
1.0 Inception 1.1 Project Request from Client / User 1.2 Assignment 1.3 1.4 1.5 1.6 1.7 1.8 Preliminary Project Charter Submit Project Charter to Obtain internal project number Initial Project Authorization
KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM
KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM AIR HANDLING UNITS... 1 CHILLERS... 2 COOLING TOWERS... 2 CLOSED LOOP COOLERS... 2 MISCELLANEOUS SUPPLY FANS...
Sample - Existing Building Commissioning Plan
Sample - Existing Building Commissioning Plan Version: Draft for Review Final Approved: Owner Site Address: Primary Site Contact Name and Telephone Number: Date Building Description The site consists of
Planned, Limited Notice and Emergency Outage Guidelines
Applies to: All Facilities Management Employees GUIDELINES: Issued: April 22, 2014 Revised: February 24, 2015 Author: Communications Coordinator PURPOSE: The purpose of these guidelines is to define roles
Developing a Proper Scope of Work, Request for Proposal & Commissioning Specification
Developing a Proper Scope of Work, Request for Proposal & Commissioning Specification Joseph Lorino, P.E., LEED Horizon Engineering Associates, LLP Synopsis In order for the commissioning process to have
Cx for Enhanced Healthcare Project Delivery. Presentation Format. Project features and timeline
Cx for Enhanced Healthcare Project Delivery Rick Staley Sr. Construction Manager PH&S Joe Webb Construction Manager PH&S Richard Beam Director, Energy Management Services PH&S Todd McGuire, PE - Sr. Project
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES A. General Information Part I: Qualifications Information The Tacoma School District is soliciting Qualifications for onsite
City of Jersey City REQUEST FOR PROPOSALS. LEED Commissioning Services. for the New Rescue One Firehouse City of Jersey City Project # 2007-001
City of Jersey City REQUEST FOR PROPOSALS LEED Commissioning Services for the New Rescue One Firehouse City of Jersey City Project # 2007-001 SUBMISSION DEADLINE 4:00 PM 29 October 2009 Glenn A. Wrigley,
Data Center Commissioning: What you need to know
Data Center Commissioning: What you need to know Course # CXENERGY1511 AIA Provider # 50111116 AABC Commissioning Group CxEnergy Conference Henderson, NV April 30, 2015 Presented by: Judson H. Adams, P.E.,
Mandatory Addendum to the Owner/Architect Contract For Projects Funded in Whole or in Part with State Capital Outlay Funds
Page 1 of 5 Mandatory Addendum to the Owner/Architect Contract For Projects Funded in Whole or in Part with State Capital Outlay Funds The Owner may use any form of agreement mutually agreed upon by the
Commissioning Design/Build Projects
This article was published in ASHRAE Journal, October 2012. Copyright 2012 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/ or distributed electronically or in paper form without permission
ACG COMMISSIONING GUIDELINE. For Building Owners, Design Professionals and Commissioning Service Providers
ACG COMMISSIONING GUIDELINE For Building Owners, Design Professionals and Commissioning Service Providers ACG COMMISSIONING GUIDELINE For Building Owners, Design Professionals and Commissioning Service
Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997
Why a Project Check List? A good way to ensure that all start-up tasks are completed prior to actually starting the project is to develop a start-up check list. The check list can be developed and then
Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK
Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services Project Management Methodology Framework 1 - Executive Summary The purpose of this document is to introduce the University community
Commissioning and Maintenance: Two Sides of the Same Coin? Kristin Heinemeier, PE, PhD Principal Engineer UC Davis WCEC
Commissioning and Maintenance: Two Sides of the Same Coin? Kristin Heinemeier, PE, PhD Principal Engineer UC Davis WCEC AIA Quality Assurance The Building Commissioning Association is a Registered Provider
Module 1: INTRODUCTION. Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION"
Module 1: INTRODUCTION Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION" Objectives: After completing this submodule, you will be able to: State
Enclosed Football Stadium Design History and Lessons Learned
Enclosed Football Stadium Design History and Lessons Learned Robert L. Towell, P.E., LEED AP, QCxP [email protected] CxE Group LLC St. Louis, Missouri 314-436-6543 With thanks to the St. Louis Convention
Revised Work Scope Dated April 23 rd, 2015
Revised Work Scope Dated April 23 rd, 2015 2.4 SCOPE OF SERVICES The following combines the Scope of Services included in RFQ No. 671 dated March 12, 2015 and the Invitation to Interview letter dated March
Construction Management System (CMS) Deliverable Review Process
Construction Management System (CMS) Deliverable Review Process State of California Department of Transportation Division of Construction December 21, 2009 Version 1.0 Approvals Name: Title: Mark Leja
GUIDELINES FOR AUGUST 1995
GUIDELINES FOR ELECTRICAL ENGINEERING SERVICES AUGUST 1995 PUBLISHED BY: PROFESSIONAL ENGINEERS AND GEOSCIENTISTS OF NEWFOUNDLAND & LABRADOR (PEGNL) P.O. Box 21207, St. John's, NL A1A 5B2 Telephone: (709)
4.4 Commissioning, Handover and Warranty
4.4 Commissioning, Handover and Warranty 4.4.1 Building Commissioning and Manuals The Building Commissioning formalizes the review and integration of all project expectations during the planning and design,
UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01
GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per
Request of Qualification Proposal for Construction Management Services
Request of Qualification Proposal for Construction Management Services Dated June 10, 2014 Table of Contents Overview 3 Introduction 4 Scope of Construction Managers Services 4 Submission of Qualifications
Chris Clement 701 Bayou Lane Thibodaux, LA 70301 985.446.7320
Chris Clement 701 Bayou Lane Thibodaux, LA 70301 985.446.7320 Position: Facility Assistant Maintenance Manager B Date: May 17, 2010 - present 70% OF TIME- is spent on following duties. Assist the Facility
Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings
Advanced Energy Design Guide LEED Strategies for Schools and High Performance Buildings Today s Presenters Stephen Koontz, LEED AP Energy Services Leader Tampa Bay Trane Allen Irvine General Sales Manager
Example Retrocommissioning Measure: Opening Throttled Discharge Valves
Opening Throttled Discharge Valves This 21-story building, constructed in 1997, is located in Oregon and contains 589,000 gross square feet of mostly office occupancy. The HVAC system includes six large
REQUEST FOR PROPOSAL MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION
REQUEST FOR PROPOSAL For MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES For VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION CITY OF ROCHESTER November 2009 TABLE OF CONTENTS GENERAL INFORMATION
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
BUILDING ENVELOPE COMMISSIONING FOR THE EVERYDAY COMMISSIONING AGENT
BUILDING ENVELOPE COMMISSIONING FOR THE EVERYDAY COMMISSIONING AGENT Building Envelope for the Everyday CxA Presented by: Mark F. Warren, CCP, LEED AP Senior Vice President - WSP Flack + Kurtz Anand Seth,
WESTERN MICHIGAN UNIVERSITY
WESTERN MICHIGAN UNIVERSITY Facilities Management Department DeVon Miller Building Commissioning Administrator 1 INTRODUCTION DeVon C. Miller, CPMP, LEED AP Building Commissioning Administrator Engineering
SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT
SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT SECTION 6: QUALITY ASSURANCE PROCEDURE: PM 6.02 TITLE: QUALITY ASSURANCE AUDITS DATE:
QUALITY MANAGEMENT SYSTEM (QMS) PROGRAM MANAGEMENT DIVISION
The Port of Long Beach Quality Management System QUALITY MANAGEMENT SYSTEM (QMS) PROGRAM MANAGEMENT DIVISION File Name: Quality Management System Version Number: Rev 1.0 Version Date: 07/24/2013 Table
Job Grading Appeal Decision Under Section 5346 of Title 5, United States Code
U.S. Office of Personnel Management Office of Merit Systems Oversight and Effectiveness Classification Appeals and FLSA Programs Dallas Oversight Division 1100 Commerce Street, Room 4C22 Dallas, TX 75242
Denver International Airport Total Facility Optimization. Josh Foerschler Aurom Mahobian
Denver International Airport Total Facility Optimization Josh Foerschler Aurom Mahobian AGENDA DIA Intro BMcD-DIA History Optimization Projects Results Conclusion Denver International Airport Opened February
NFPA 3 and 4 Commissioning and Integrated Testing of Fire Protection and Life Safety Systems. Matt Klaus Senior Fire Protection Engineer NFPA
NFPA 3 and 4 Commissioning and Integrated Testing of Fire Protection and Life Safety Systems Matt Klaus Senior Fire Protection Engineer NFPA 1 The Recommended Practice 2 Coming Soon 3 Overview What is
Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management
JOHN HART GENERATING STATION REPLACEMENT PROJECT Schedule 9 Quality Management SCHEDULE 9 QUALITY MANAGEMENT TABLE OF CONTENTS 1. QUALITY MANAGEMENT SYSTEM... 1 1.1 Quality Management System...1 1.2 Project
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)
ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal Forms Part 4:
OFFICE OF PERSONNEL MANAGEMENT ATLANTA OVERSIGHT DIVISION ATLANTA, GEORGIA
OFFICE OF PERSONNEL MANAGEMENT ATLANTA OVERSIGHT DIVISION ATLANTA, GEORGIA CLASSIFICATION APPEAL DECISION Under section 5112(b) of title 5, United States Code Appellant: [the appellant] Position: Engineering
The main steam enters the building in the basement mechanical room; this is where the condensate line also leaves the building.
MSV: Square Footage: 24,844 No. of Floors: 1 Year Built: 1963 Type of Use: Lounge and dining area open all night for snacks Steam Water-cooled condenser, 50-Ton York unit with a 6 cylinder-reciprocating
Vendor Performance Evaluation Requirements
Vendor Performance Evaluation Requirements The awarded vendor should note that the Contract Administrator will document the contractor s performance by completing a Vendor Performance Evaluation based
Florida Power & Light Company. Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards. Effective: November 9, 2015
Florida Power & Light Company Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards Effective: November 9, 2015 Table of Contents Eligibility Requirements - Chiller... 2 Rebate Amount
Post Occupancy Evaluation (POE) Technical Instructions
1.0 Purpose These technical instructions define the typical steps required by HHS personnel in the use of the. The POE consists of a detailed and systematic assessment of a facility that is operational
Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue
Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority
Condensing Boiler Efficiency
Condensing Boiler Efficiency Date: July 17, 2012 PRES E NT ED BY DO N L E O NA RDI LE O N A RD I I NC. HV AC T RAI N I N G & C ON SU LT IN G Concepts 1 The current state of evolution in boiler design 2
Classification and Qualification STANDARDS
Classification and Qualification STANDARDS HVAC Series Classification Title Class Code Date Established Date Revised Operating Engineer Building Service Engineer Air Conditioning/Refrigeration Mechanic
ACG Commissioning Guideline
ACG Commissioning Guideline Appendix A Sample Commissioning Specification NOTES TO APPENDIX A This appendix contains a sample Request for Proposal (RFP) for Commissioning Services as would be issued by
DGS Prolog Manager & Prolog Converge User Manual
DGS Prolog Manager & Prolog Converge User Manual Table of Contents Prolog Overview Flowchart 1 Entering a New Project 2 Solicitations 7 Contracts Module 14 Change Orders 21 Change Order Workflow Diagram
<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
QUALITY MANAGEMENT SYSTEM REQUIREMENTS
QUALITY MANAGEMENT SYSTEM REQUIREMENTS FOR BUILDERS 2014 400 Prince George s Blvd. Upper Marlboro, MD 20774 800.638.8556 HomeInnovation.com TABLE OF CONTENTS Introduction... iii Notes... iii 1 General...1
Commissioning - Construction Documents (Page 1 of 6)
Commissioning - Construction Documents (Page 1 of 6) A. General Information Climate Zone: Building Type: Conditioned Area (sf): Reviewer's Name: Reviewer's Agency: Note: Design Review for each system/subsystem
REQUEST FOR QUALIFICATIONS/PROPOSAL (RFQ/P) FOR A ROOF CONSULTANT
REQUEST FOR QUALIFICATIONS/PROPOSAL (RFQ/P) FOR A ROOF CONSULTANT Durango School District 9 R (Owner) 201 East 12 th Street Durango, Colorado 81301 Phone (970) 247 5411, ext. 1458 PROPOSAL DUE DATE/DELIVERY
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.00 10 (February 2010) Change 1-05/15 ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 01 (January 2008) UNIFIED FACILITIES
Consultancy Services Proposal
Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847
2012 BIM Guidelines and Standards (Rev. 00) University at Albany
A. Building Information Modeling (BIM) Guidelines: The Office of AECM will require the submission of BIM modeling files as part of an electronic file submission to the AECM project manager as requested
National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, MD 20877-4121 ph: 301-977-3698 fax: 301-977-9589 www.nebb.
National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, MD 20877-4121 ph: 301-977-3698 fax: 301-977-9589 www.nebb.org PROCEDURAL STANDARDS FOR WHOLE BUILDING SYSTEMS COMMISSIONING
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes
SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION
SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION The purpose of this guide specification is to assist the specifier in correctly specifying Mechanical System Testing
2611 Waterfront Parkway, Suite 340 Indianapolis, IN 46214 Tel. (317) 536-2618
HOT WATER, LIGHTING CONTROLS, PHOTOVOLTAIC, BUILDING ENVELOPE, ELEVATORS, ACID WASTE PIPING, EMERGENCY POWER, FIRE ALARM and Note: The Unified Facilities Guide Specification Section 070523 was referenced
City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E.
City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E. GENERAL PURPOSE Under direction, manages, oversees, evaluates,
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES. Level III Content Outline
Fire Alarm Systems Level III Content Outline The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 3.1
Chapter 4: Contractor Quality Control
Chapter 4: Contractor Quality Control Seattle District, NWS Last updated: 05FEB14 Chapter 4 Contractor Quality Control 1. GENERAL. Contractor is responsible for quality control and shall establish and
