1 Optimizing Boiler Inspections Joe Maciejczyk, P. E. IDEA Campus
2 Case Study Process and Heating steam user One PC Boiler, 3 Natural Gas Evaluate NG boilers for continued operation or replacement Boiler Inspection/SLIDE 2
3 Scope Steam Drum Tubing Refractory Burner Ductwork Flue Combustion Air Fan Mud Drums Boiler Inspection/SLIDE 3
4 Discussion Exclusions Stacks Deaerator/DA Storage (system) Boiler External Piping Feedwater Boiler Inspection/SLIDE 4
5 CE A-Style, Saturated Steam Packaged Boiler 1972 start-up Oil>Gas Hours and number of starts unknown 250psig, 121,000 pph No Economizer or Superheater Boiler Inspection/SLIDE 5
6 Typical Inspections Yearly AI inspection Water treatment vendor Operator daily/weekly inspections Exception inspections Boiler Inspection/SLIDE 6
7 Boiler Inspection/SLIDE 7
8 Scope Steam Drum Tubing Refractory Burner Ductwork Flue Combustion Air Fan Mud Drums Boiler Inspection/SLIDE 8
9 Steam Drum Pitting damage at the water line (layup and operating). Attachment welds and bolts on hangers & brackets supporting feedwater piping, baffle panels and primary & dryer screens. Inspection of the feedwater piping and internal distribution system. Drain piping connection to primary screen box. Gauge glass pipe penetrations to insure bore is open. Tube ligament penetrations surface NDE Man-way attachment for cracking or signs of leakage. Surface and volumetric NDE of head-to-shell and longitudinal welds. Evidence of leaking at the man-way seals. Video scope inspection of tube internals (%) for attack and/or wastage. Boiler Inspection/SLIDE 9
10 Phased Array Ultrasonic Boiler Inspection/SLIDE 10
11 Welds located with eddy current or etching Boiler Inspection/SLIDE 11
12 Scope Steam Drum Tubing Refractory Burner Ductwork Flue Combustion Air Fan Mud Drums Boiler Inspection/SLIDE 12
13 Inspect tube external surfaces for evidence of pitting, blistering, burning, bulging or swelling. Wall tube alignment. Tube UTT for general wastage Integrity of any hangers and supports. Refractory deficiencies. Perform Wet Florescent Magnetic Particle (WFMT) inspection of wide membrane at burner throats and other nested area (if applicable) for crack detection to insure no potential membrane cracking extends into the tube walls. Perform inspection of outer surface of accessible areas of the lower drums including tube stubs for corrosion damage. UT readings of Lower drum tube stubs (boiler bank tubes) if wastage is detected. Morphology of pitting if detected. Boiler Inspection/SLIDE 13
14 Tube thickness Use good nomenclature and have a plan that is easily repeatable. Boiler Inspection/SLIDE 14
15 Scope Steam Drum Tubing Refractory Burner Ductwork Flue Combustion Air Fan Mud Drums Boiler Inspection/SLIDE 15
16 Scope Steam Drum Tubing Refractory Burner Ductwork Flue Combustion Air Fan Mud Drums Boiler Inspection/SLIDE 16
17 Ductwork and Flue External casing and support inspection for any signs of distortion or damage. Inspection of expansion joints internally and externally. Visual (VT) internal inspection to verify integrity of the gas passages to the stack NDE of internals if areas of wastage or other defects are found visually Boiler Inspection/SLIDE 17
18 Scope Steam Drum Tubing Refractory Burner Ductwork Flue Combustion Air Fan Mud Drums Boiler Inspection/SLIDE 18
19 Scope Steam Drum Tubing Refractory Burner Ductwork Flue Combustion Air Fan Mud Drums Boiler Inspection/SLIDE 19
20 Joe Maciejczyk, PE Structural Integrity Associates Cell Austin Metallurgical lab Chicago Turbine inspection group State College, PA - NDE R&D, Guided Wave Boiler Inspection/SLIDE 20
Standard Recommendations for Pressure Part Inspection During a Boiler Life Extension Program
Standard Recommendations for Pressure Part Inspection During a Boiler Life Extension Program M.N. Hovinga G.J. Nakoneczny Babcock & Wilcox Barberton, Ohio, U.S.A. Presented to: ICOLM (International Conference
More informationInvestigating the Impact of Boiler Aging In Replacement Decisions
Investigating the Impact of Boiler Aging In Replacement Decisions Siddika Pasi and Michael R. Muller, Rutgers University - Center for Advanced Energy Systems ABSTRACT Traditionally boilers were believed
More informationINSTRUCTION MANUAL. Boil-Out TABLE OF CONTENTS SAFETY WARNINGS 2-3 RESPONSIBILITY 3 INTRODUCTION 3 PRE-BOIL OUT PROCEDURES 3-5 BOIL OUT PROCESS 5-9
TABLE OF CONTENTS Description Page Number SAFETY WARNINGS 2-3 RESPONSIBILITY 3 INTRODUCTION 3 PRE-BOIL OUT PROCEDURES 3-5 BOIL OUT PROCESS 5-9 Indeck Keystone Energy, LLC. 5451 Merwin Lane, Suite 100 Erie,
More informationBoiler and Burner Cleaning and Servicing Specifications
Boiler and Burner Cleaning and Servicing Specifications The Town of Groton of Public Works Department is requesting bids to provide manufacturers recommended maintenance, repairs and emergency service
More informationCondition Assessment Services. Put our team of specialists to work for you
Condition Assessment Services Put our team of specialists to work for you HEADERS Don t let a steam leak be your first sign of header problems High Temperature Headers High temperature superheater and
More informationOil and Gas Pipeline Design, Maintenance and Repair
Oil and Gas Pipeline Design, Maintenance and Repair Dr. Abdel-Alim Hashem Professor of Petroleum Engineering Mining, Petroleum & Metallurgical Eng. Dept. Faculty of Engineering Cairo University aelsayed@mail.eng.cu.edu.eg
More informationA Primer on Protecting Idle Boilers By Howard Benisvy, Member ASHRAE
The following article was published in ASHRAE Journal, December 2002. Copyright 2002 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. It is presented for educational purposes
More informationWater-Tube Package Boilers Reliable and Economical Steam Production
Water-Tube Package Boilers Reliable and Economical Steam Production Water-Tube Package Boilers: Proven Design for Economical Steam Production Since 1867, The Babcock & Wilcox Company (B&W) has been designing,
More informationI. STEAM GENERATION, BOILER TYPES
I. STEAM GENERATION, BOILER TYPES and BOILER PLANT SYSTEMS 1 Steam Generation Water s Unique Properties: High Thermal Capacity (Specific Heat) High Critical Temperature Ideal Medium for Heat Delivery High
More informationCURRENT EXPERIENCE IN TYPICAL PROBLEMS AND FAILURES WITH BOILER PIPING COMPONENTS AND SUPPORTS
A DB RILEY TECHNICAL PUBLICATION CURRENT EXPERIENCE IN TYPICAL PROBLEMS AND FAILURES WITH BOILER PIPING COMPONENTS AND SUPPORTS by James P. King, Design Manager DB Riley, Inc. Presented at the 1998 ASME
More informationOPERATING EXPERIENCE OF LARGE REHEAT HRSGs in MERCHANT SERVICE
OPERATING EXPERIENCE OF LARGE REHEAT HRSGs in MERCHANT SERVICE Peter S. Jackson, PE David S. Moelling, PE Frederick C. Anderson, PE James W. Malloy TETRA ENGINEERING GROUP TETRA ENGINEERING GROUP TETRA
More informationEnergy Efficiency in Steam Systems
Energy Efficiency in Steam Systems Fundamentals of Energy Efficiency: An Introductory Workshop April 2008 John S. Raschko, Ph.D. Mass. Office of Technical Assistance www.mass.gov/envir/ota (617) 626-1093
More informationfor boilers From selecting the best NDT technique to monitoring inspection quality
Non-destructive testing for boilers From selecting the best NDT technique to monitoring inspection quality > Ensuring safe and efficient operation > Optimizing maintenance > Maximizing availability > Avoiding
More information1. A belt pulley is 3 ft. in diameter and rotates at 250 rpm. The belt which is 5 ins. wide makes an angle of contact of 190 over the pulley.
Sample Questions REVISED FIRST CLASS PARTS A1, A2, AND A3 (NOTE: these questions are intended as representations of the style of questions that may appear on examinations. They are not intended as study
More informationBoiler Preparation, Start-Up and Shutdown
Boiler Preparation, Start-Up and Shutdown Learning Outcome When you complete this module you will be able to: Describe the basic preparation of a boiler for start-up, and the start-up and shutdown procedures.
More informationEnergy Efficient Operations and Maintenance Strategies for Boilers
Energy Efficient Operations and Maintenance Strategies for Boilers Large, complex and widely used, industrial boilers are major consumers of fuel. Proper operations and maintenance (O&M) procedures must
More informationNON-DESTRUCTIVE TESTING FULL SCOPE OF INTEGRATED NDT SERVICES
NON-DESTRUCTIVE TESTING FULL SCOPE OF INTEGRATED NDT SERVICES RIGHT SERVICE MAXIMUM RETURN Whether it is in fabrication, pipe manufacturing, pipeline, plant construction, chemical, petrochemical plants,
More informationPreventive Maintenance. State Energy Assessment Workshop By: DTE Energy Partnership & Services
Preventive Maintenance State Energy Assessment Workshop By: DTE Energy Partnership & Services Do you know? World wide research has shown that one of the reasons causing 80% of the accidents is deficient
More informationEvaluate, Clean, and Tune Guidance
Evaluate, Clean, and Tune Guidance The Evaluate, Clean and Tune (ECT) process serves three essential purposes in the Weatherization Assistance Program (WAP). The first is to evaluate the existing system
More informationRiccardo Pierini Customer Care - Yankee Dryer Service Engineer, Toscotec SpA Italy
TRACK A: YANKEE DRYER OPTIMISATION Steel Yankee Dryer TT SYD: Take Care of It! Riccardo Pierini Customer Care - Yankee Dryer Service Engineer, Toscotec SpA Italy Both during his years of university studies
More informationAction Plan Template HVAC Page 1
Action Plan Template HVAC Page 1 Once Establish expected HVAC system efficiency - Write down the expected efficiency of HVAC systems to use as a baseline - Add this information to maintenance plan documentation
More informationBoiler & Pressure Vessel Inspection discrepancies and failures
Boiler & Pressure Vessel Inspection discrepancies and failures Water Heaters / Pressure Vessels Pressure Vessels are inspected once every three years. This requires a test of A: safety relief devices B:
More informationPIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta
PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification Number: 3503-11.2.610 Rev. 2 Rubber Lined Steel Pipe and Fittings Mechanically Coupled Plain End Type System Issued Revised Approved
More informationOriginators of the Flexible Water Tube design
BRYAN FLEXIBLE WATER TUBE AB SERIES STEAM AND WATER BOILER 900,000 TO 3,000,000 BTUH FORCED DRAFT GAS, OIL OR DUAL FUEL FIRED Water Boiler AB120-W-FDGO Steam Boiler AB250-S-150-FDG Originators of the Flexible
More informationNFPA31FuelOilPiping 1 Revised 3-1-11
NFPA 31 Fuel Oil Piping, Installation and Testing Chapter 8 Fuel Piping Systems and Components 8.1 Scope. This chapter shall apply to piping systems and their components used to transfer fuel oil from
More informationPACKAGED FIRE TUBE BOILER
SAMPLE PREVENTIVE MAINTENANCE MANUAL PACKAGED FIRE TUBE BOILER 1 CONTENTS Introduction 1 Intention 2 Organisational setup 3 Boiler Fault reporting & Repair progression 4 Preventive Maintenance Schedules
More informationHeat Exchangers in Boilers
Helsinki University of Technology Department of Mechanical Engineering Energy Engineering and Environmental Protection Publications Steam Boiler Technology ebook Espoo 2002 Heat Exchangers in Boilers Sebastian
More informationDrying of Woody Biomass. Process Engineering / GEA Barr-Rosin
Drying of Woody Biomass BioPro Expo & Marketplace / Atlanta, GA / March 14-16, 2011 Drying of Woody Biomass Conventional Direct Fired Dryer Technology Proprietary work of the Copyright Owner Issues with
More informationChapter 9 O&M Ideas for Major Equipment Types
Chapter 9 O&M Ideas for Major Equipment Types 9.1 Introduction At the heart of all O&M lies the equipment. Across the Federal sector, this equipment varies greatly in age, size, type, model, fuel used,
More informationHOW TO SELECT A LOW VOLUME (L.V ) BOILER
HOW TO SELECT A LOW VOLUME (L.V ) BOILER FREQUENTLY ASKED QUESTIONS OR COMMENTS ON BOILERS Dear Potential Customer: Low Volume Operator Exempt boilers have been marketed in Ontario to eliminate the requirement
More informationDiagnostics for Mobile Homes: HVAC
Diagnostics for Mobile Homes: HVAC Adam Harris NYSWDA Wade Thompson - IWTC Objectives Identify different types of HVAC used in mobile homes Provide an overview of duct systems Demonstrate various tests
More informationSteam System Efficiency. Bill Lumsden Leidos Engineering
Steam System Efficiency Bill Lumsden Leidos Engineering Steam System Efficiency Steam System Efficiency Key Take-aways: Review of the properties of ice, water, and steam Learn the basics of steam trap
More informationELECTRODE BOILERS VAPOR POWER INTERNATIONAL
ELECTRODE BOILERS WITH JET-FLO Technology VAPOR POWER INTERNATIONAL ELECTRODE boilers The Electrode Steam Boiler with Jet-Flo technology consists of an insulated pressure vessel and is fully enclosed in
More informationAttachment J-C18.1. HVAC Work Instructions
. RFP: Attachment J-C18.1 HVAC Work Instructions NNC13ZFD017J SOW Item No. Title Page C18-02 Control Air Systems Annual PM 2 C18-03 Split System AC Indoor Section Annual PM 3 C18-04 Condensing Unit Semi-Annual
More informationPee Dee Empty Oil Storage Tank at
Mechanical Integrity Report for the Pee Dee Empty Oil Storage Tank at 208 North Palmetto Boulevard Clemson, South Carolina 29631 Inspection: 10 October 2012 Prepared by: George E. Matthews, E.I.T. Senior
More informationA REVIEW OF THE COMMON CAUSES OF BOILER FAILURE IN THE SUGAR INDUSTRY
A REVIEW OF THE COMMON CAUSES OF BOILER FAILURE IN THE SUGAR INDUSTRY K B MCINTYRE Alstom Power - John Thompson Boiler Division, Cape Town, South Africa E-mail: keithmac@johnthompsonafrica.co.za Abstract
More informationOROT RABIN POWER STATION UNITS 1-4. 4 x 350 MW
ISRAEL ELECTRIC OROT RABIN POWER STATION UNITS 1-4 4 x 350 MW COAL BOILER CONVERSION TO LOW NO X NATURAL GAS AND COAL FIRING BY PRIMARY AND SECONDARY MEASURES INSTALLATION Replacing the Burner Management
More information[[ ;/LON/P&M/896/8/09 Date: 22-05-2013. Notice inviting quotation for Repairing heating system
[[ ;/LON/P&M/896/8/09 Date: 22-05-2013 TENDER NOTICE Notice inviting quotation for Repairing heating system 1. High Commission of India invites bids from the prospective Heating/Boilers Companies with
More informationNAWTEC18-3541 CONCEPTS AND EXPERIENCES FOR HIGHER PLANT EFFICIENCY WITH MODERN ADVANCED BOILER AND INCINERATION TECHNOLOGY
Proceedings of the 18th Annual North American Waste-to-Energy Conference NAWTEC18 May 11-13, 2010, Orlando, Florida, USA NAWTEC18-3541 CONCEPTS AND EXPERIENCES FOR HIGHER PLANT EFFICIENCY WITH MODERN ADVANCED
More informationInspections Standard Operating Procedure 5 Aboveground Storage Tanks
Aboveground Storage Tanks Aboveground Storage Tank Inspection This Standard Operating Procedure describes the steps that campus units that manage aboveground oil storage tanks (ASTs) or containers must
More informationWorld Class Water Chemistry By Accident? BRO Chemistry Session 8/5/2014
World Class Water Chemistry By Accident? BRO Chemistry Session 8/5/2014 From Safe by Accident? by Judy Agnew & Aubrey Daniels Despite decades of reduction in safety related deaths and injuries on the job,
More informationCROWN BOILER COMPANY BWF SERIES BOILER CATEGORY I VENT KIT INSTALLATION AND OPERATING INSTRUCTIONS
CROWN BOILER COMPANY BWF SERIES BOILER CATEGORY I VENT KIT INSTALLATION AND OPERATING INSTRUCTIONS WARNING Improper installation, adjustment, alteration, service, or maintenance of this product can cause
More informationPressure Vessel Assessment Report
Project Information Client: Total Energy Location: Blackwell OK Date: 7/23/2013 Contact: Integrity Mgmt. Advisor: Chuck Easterbrooks - API 510 #2212 Cc: API / UT Inspector: Robert Van Pelt-API 510# 40899
More informationsteam centre of excellence Steam Boiler System Optimization
Steam Boiler System Optimization Introduction Gas Cost Metering Fluids Fuel, Water, Steam Steam Costs Boiler House Stack Losses Boiler Waterside Surfaces Blowdown Current Natural Gas Cost Projected Cost
More informationABOUT US PAUL SPENCE CHIEF EXECUTIVE OFFICER
WE WELCOME current and potential customers to review our safety and quality programs and certifications, visit our facilities, and talk to our employees and customers. See for yourself how our commitment
More informationWBIA Industry Days Recovery Boiler Presentation Appleton, WI.
WBIA Industry Days Recovery Boiler Presentation Appleton, WI. Presented by Bob DeCaigny April 24, 2013 Objectives 1. Kraft recovery cycle overview 2. Recovery boiler explosion history (25 events in 28
More informationTUBE-TO-TUBESHEET JOINTS: THE MANY CHOICES ABSTRACT KEYWORDS. Seal welding, tube-to-tubesheet welds, heat exchanger, mock-up, tube expansion
B. J. Sanders Consultant 307 Meyer Street Alvin, Texas 77511 TUBE-TO-TUBESHEET JOINTS: THE MANY CHOICES ABSTRACT After a decision has been made to use zirconium as the material of construction for a shell
More informationBODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION
BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION 2015 (Replaces July 2013) API Authorized Piping Inspectors must have a broad knowledge base relating to maintenance, inspection,
More informationBOILER SELECTION CONSIDERATIONS
BOILER SELECTION CONSIDERATIONS CONTENTS Definitions - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
More informationGAS COOLING SYSTEMS FOR STEAM REFORMING PLANTS
GAS COOLING SYSTEMS FOR STEAM REFORMING PLANTS 1 1.1 INTRODUCTION is a leading and highly regarded supplier of components and systems for the petrochemical, chemical, refining & metallurgical industries.
More informationRules for construction of heating boilers, Boiler and Pressure Vessel Code, Section IV-2007
Boilers Introduction How Boilers Work Types of Boilers Key Components of Boilers Safety Issues Best Practices for Efficient Operation Best Practices for Maintenance References Introduction Boilers are
More informationTABLE OF CONTENTS INSTALLATION & OPERATING INSTRUCTIONS
TABLE OF CONTENTS RECTANGULAR ECONOMIZERS INSTALLATION & OPERATING INSTRUCTIONS SPECIFICATION SHEET MANUFACTURER S CODE DATA BILL(S) OF LADING WARRANTY PROCEDURE TERMS & CONDITIONS DRAWINGS Page 1 ECONOMIZER
More informationFactory owners must ensure the boiler is:
Factory owners must ensure the boiler is: * Registered with the Boilers and Pressure Vessels Division, Labour Department * Examined by an appointed examiner and has a valid certificate of fitness * Supervised
More informationSulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard
Sulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard Introduction SRU s (Sulfur Recovery Units) are critical pieces of equipment in refineries and gas plants. SRUs remove sulfur compounds from certain
More informationSpecific Volume of Liquid (Column 7). The volume per unit of mass in cubic feet per pound.
Steam Tables What They Are How to Use Them The heat quantities and temperature/ pressure relationships referred to in this Handbook are taken from the Properties of Saturated Steam table. Definitions of
More informationBoiler Calculations. Helsinki University of Technology Department of Mechanical Engineering. Sebastian Teir, Antto Kulla
Helsinki University of Technology Department of Mechanical Engineering Energy Engineering and Environmental Protection Publications Steam Boiler Technology ebook Espoo 2002 Boiler Calculations Sebastian
More informationOHIO MEDICAL CORPORATION. Medical Gas Panel. Installation and Maintenance Manual
OHIO MEDICAL CORPORATION Medical Gas Panel Installation and Maintenance Manual P/N 255105 (Rev.5) 08/2005 P/N 255105 (Rev.5) 08/2005 PAGE 2 OHIO MEDICAL CORPORATION PAGE 3 1.0 User Responsibilities The
More informationRoutine and Emergency Boiler Operation
Routine and Emergency Boiler Operation Learning Outcome When you complete this module you will be able to: Describe the routine safe and efficient operation of a packaged boiler. Learning Objectives Here
More informationBackup Fuel Oil System Decommissioning & Restoration Plan
Backup Fuel Oil System Page 1 of 19 Overview of Physical Fuel Oil System and Decommissioning Steps The fuel oil system at Milford Power consists of a number of subsystems. These include the following:
More informationAcumen Enterprises, Inc.
Hourly rates Discount w/o Rebate Electrician $78.00 10% $70.20 $70.73 HVAC Technician $78.00 10% $70.20 $70.73 Insulator $42.00 10% $37.80 $38.08 Sheet Metal Worker $74.00 10% $66.60 $67.10 Plumber/Pipefitter
More informationOBSERVING BOILER SAFETY RULES
OBSERVING BOILER SAFETY RULES The rules that follow are brief reminders of the possible consequences in a boiler plant of inappropriate operator response or questionable action in maintaining the boiler
More informationMOSS WOOD BOILER SYSTEMS
GEORGE K. MOSS CO., INC. INSIDE THIS ISSUE: WOOD WATER T U- TUBE BOILER WOOD FIREBOX BOILER WOOD HYBRID BOILER GASIFIER COM B- BUSTION SYS- TEM PNEUMATIC COMBUSTION SYSTEM WOOD BOILER PLC CONTROLS PLC
More informationCHALLENGES IN A DILUTION STEAM GENERATOR SYSTEM
CHALLENGES IN A DILUTION STEAM GENERATOR SYSTEM Lee Siang Hua Titan Petrochemicals (M) Sdn Bhd Cheah Phaik Sim Titan Petrochemicals (M) sdn Bhd piximmink@yahhoo.com Karl Kolmetz Westlake Group, Lake Charles,
More informationSelecting TEMA Type Heat Exchangers
Selecting TEMA Type Heat Exchangers TEMA is a set of standards developed by leading heat exchanger manufacturers that defines the heat exchanger style and the machining and assembly tolerances to be employed
More informationChapter 7 Hydraulic System Troubleshooting
Chapter 7 Hydraulic System Troubleshooting General The following troubleshooting information is provided as a general guide to identify, locate and correct problems that may be experienced with the hydraulic
More informationUniversity of Iowa Power Plant
University of Iowa Power Plant Contents Purpose... 2 History... 3 Cogeneration... 6 Boilers... 7 Environmental Impact... 10 Steam Turbine Generators... 12 Modernization... 14 Biomass Fuel Initiative...
More informationAlstom Thermal Services AmStar 888 Kraftvärme Conference, Sweden
Alstom Thermal Services AmStar 888 Kraftvärme Conference, Sweden Jiri Kubricht October 17 & 18, 2013 So, what is AmStar 888 material and how can it be used? AmStar 888 is a patented nickel-chrome alloy
More informationNON DESTRUCTIVE TESTING & ASNT WELD INSPECTION & AWS
NON DESTRUCTIVE TESTING & ASNT WELD INSPECTION & AWS What is ASNT? What is ASNT? The American Society for Nondestructive Testing, Inc. What is ASNT? ASNT is the world's largest technical society for nondestructive
More informationDepartment of Veterans Affairs VHA DIRECTIVE 2008-062 Veterans Health Administration Washington, DC 20420 October 15, 2008 BOILER PLANT OPERATIONS
CORRECTED COPY Department of Veterans Affairs VHA DIRECTIVE 2008-062 Veterans Health Administration Washington, DC 20420 BOILER PLANT OPERATIONS 1. PURPOSE: This Veterans Health Administration (VHA) Directive
More informationPLP - TERMS AND CONDITIONS
PLP - TERMS AND CONDITIONS 2014-2015 Philadelphia Gas Works Residential Parts & Labor Plan Contract This Residential Parts & Labor Plan Contract (this Plan ) is available to customers of the Philadelphia
More informationSAFETY HAZARDS CHAPTER 1: CHAPTER 2: CHAPTER 3: CHAPTER 4:
Section IV (previously Section III of Oregon OSHA s Technical Manual) SAFETY HAZARDS CHAPTER 1: OILWELL DERRICK STABILITY: GUYWIRE ANCHOR SYSTEMS CHAPTER 2: PETROLEUM REFINING PROCESSES CHAPTER 3: PRESSURE
More informationCondensing Boiler Efficiency
Condensing Boiler Efficiency Date: July 17, 2012 PRES E NT ED BY DO N L E O NA RDI LE O N A RD I I NC. HV AC T RAI N I N G & C ON SU LT IN G Concepts 1 The current state of evolution in boiler design 2
More informationPMCap Local Thin Area Repair and Restoration Component. for Pressure Retaining Items
by Paul S. Manzon President and John K. Wiedemann Vice President, Engineering PMC Engineering Solutions, Inc. 272 Grubb Rd. Pottstown, PA 19465 ABSTRACT A common method of pressure boundary repair for
More informationTEMA DESIGNATIONS OF HEAT EXCHANGERS REMOVABLE BUNDLE EXCHANGERS NON REMOVABLE BUNDLE EXCHANGERS SOURCE: WWW.WERMAC.ORG/
TEMA DESIGNATIONS OF HEAT EXCHANGERS Because of the number of variations in mechanical designs for front and rear heads and shells, and for commercial reasons, TEMA has designated a system of notations
More informationGLOBAL INSPECTION AND CERTIFICATION
GLOBAL INSPECTION AND CERTIFICATION CONTENTS About us 3 Services 3 Lifting Equipment Inspection & Certification 3 Conventional & Advanced Non Destructive Testing (NDT) 4 Rig Inspection & Commissioning
More informationOPERATIONS & MAINTENANCE SUBCOMMITTEE RECOVERY BOILER SAFETY AUDIT GUIDELINES
AMERICAN FOREST & PAPER ASSOCIATION AMERICAN FOREST & PAPER ASSOCIATION OPERATIONS & MAINTENANCE SUBCOMMITTEE RECOVERY BOILER SAFETY AUDIT GUIDELINES March 1990 Revised July 2004 Revised May 2012 893 McLean
More informationHeat Exchanger Thin Film Foul Release Applications Corrosion Resistant Protective Coatings Grit Blast Surface Prep of Tubular Equipment
Heat Exchanger Thin Film Foul Release Applications Corrosion Resistant Protective Coatings Grit Blast Surface Prep of Tubular Equipment Non-Destructive Examination Heat Exchanger Mechanical Repair Services
More informationSPECIFICATION TECHNICAL AIR-CONDITIONING UNITS SINGLE AND SPLIT (DUCTED) (AIR COOLED PACKAGED UNIT)
SPECIFICATION TECHNICAL AIR-CONDITIONING UNITS SINGLE AND SPLIT (DUCTED) (AIR COOLED PACKAGED UNIT) MAINTENANCE TYPE: STATUTORY 1.0 SCOPE OF SERVICES The Contractor shall provide maintenance Services for
More informationUnderstanding ejector systems necessary to troubleshoot vacuum distillation
TECHNOLOGY Understanding ejector systems necessary to troubleshoot vacuum distillation A complete understanding of ejector system performance characteristics can reduce the time and expense associated
More informationFORENSIC ENGINEERING ANALYSIS OF A COMBUSTION TURBINE COMPRESSOR BLADE FAILURE
FORENSIC ENGINEERING ANALYSIS OF A COMBUSTION TURBINE COMPRESSOR BLADE FAILURE Teodoro Leon-Salamanca, Ph.D. Reinhart & Associates, Inc. Austin, TX CT Compressor Blade Failure 36th Turbomachinery Symposium
More informationHIGH PRESSURE FEEDWATER HEATER REPAIR
HIGH PRESSURE FEEDWATER HEATER REPAIR B. W. Helton II Tennessee Valley Authority 1101 Market Street Chattanooga, Tennessee 37402 Peter Tallman CTI Industries Inc. 200 Benton Street Stratford, Connecticut
More informationSafe management of industrial steam and hot water boilers A guide for owners, managers and supervisors of boilers, boiler houses and boiler plant
Safe management of industrial steam and hot water boilers A guide for owners, managers and supervisors of boilers, boiler houses and boiler plant Health and Safety Safe management of industrial steam and
More informationQUADRANT SR- Thermal Oxidizer Process Design & Environmental Control Benefits for the Sand Coating Industries
> 99% VOC, HAP & CO Destruction Efficiency Time, temperature and turbulence are the basic design principles required for organic pollutant control. In the QUADRANT-SR SERIES Recuperative Thermal Oxidizers,
More informationAmendment: Combustion Appliance Testing Standards Removal. Proponent: Brett Dillon, Chair Standards Development Committee
Amendment: Combustion Appliance Testing Standards Removal Proponent: Brett Dillon, Chair Standards Development Committee Applies to: 2006 Mortgage Industry National Home Energy Rating Systems Standards,
More informationSelf-Home Inspection Checklist
To be used as a first home visit for note taking. Visit www.homeinspectiondirect.com for more tips and information about buying a home and hiring a home inspector. This form in no way replaces a professional
More informationBabcock & Wilcox's IR-CFB Boiler Technology. S. P. Ganeshan. Papertech -2010, Hyderabad. Divisional Manager, Thermax Limited, Boilers & Heaters Group
Babcock & Wilcox's IR-CFB Boiler Technology S. P. Ganeshan Divisional Manager, Thermax Limited, Boilers & Heaters Group Papertech -2010, Hyderabad Thursday 17, June 2010 1 Thermax - Vision To be a globally
More informationWhat is a successful Steam Trap Management Program?
What is a successful Steam Trap Management Program? With today s energy costs, it is extremely important to have a proactive steam trap-testing program included with the overall Steam System Management
More informationHot Water Boilers and Controls Why Condensing Boilers are Different. Presented Oct. 14, 2008 Long Island Chapter, ASHRAE
Hot Water Boilers and Controls Why Condensing Boilers are Different Presented Oct. 14, 2008 Long Island Chapter, ASHRAE H.W. Boilers and Controls Major types of boilers Advantages and disadvantages Resistance
More informationSolving Persistent Moisture Problems and Moisture Damage
B etter buildings Solving Persistent Moisture Problems and Moisture Damage Summary This three-storey, 15-unit, 1,300 square metre (13,993 sq. ft) walk-up was built in 1958. In the 1980s, the building started
More informationBOILER ROOM GUIDE. Reference Guide
BOILER ROOM GUIDE Reference Guide Cleaver-Brooks FOREWORD This guide is provided to assist supervisory, operating and maintenance personnel in understanding the operation of boiler room equipment, and
More informationReplacement parts. WM97+ gas-fired water boiler Boiler Manual. OBTAIN PARTS ONLY THROUGH WEIL-McLAIN THE BOILER CONTAINS CERAMIC FIBER MATERIALS
Replacement parts DO NOT SERVICE THE BOILER WITHOUT A WM97+ MAINTENANCE KIT AVAILABLE Failure to adhere to these guidelines can result in severe personal injury, death or substantial property damage. The
More informationIndiana Boiler and Pressure Vessel Safety Section Frequently Asked Questions
Indiana Boiler and Pressure Vessel Safety Section Frequently Asked Questions What are the licensing requirements for boiler operators? Answer: Indiana statute (IC 22-15-6) and administrative rules (680
More informationThe soot and scale problems
Dr. Albrecht Kaupp Page 1 The soot and scale problems Issue Soot and scale do not only increase energy consumption but are as well a major cause of tube failure. Learning Objectives Understanding the implications
More informationpdi PLASTIC DRUM INSTITUTE Plastic Drum Paneling Issues
pdi PLASTIC DRUM INSTITUTE Plastic Drum Paneling Issues PANELING BACKGROUND This report will explain the causes of paneling and suggest some possible ways to eliminate or minimize the paneling of plastic
More informationSuccessful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units
Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units Thomas Kline Director- Concrete Repair Solutions STRUCTURAL TECHNOLOGIES, LLC Houston, Texas USA November
More informationSpill Prevention, Control and Countermeasure Plan (SPCC) Program
United States Environmental Protection Agency Office of Emergency Management August 2013 www.epa.gov/emergencies Spill Prevention, Control and Countermeasure Plan (SPCC) Program Bulk Storage Container
More informationNON-DESTRUCTIVE TESTING OF PIPELINES. L. Annila. Abstract
NON-DESTRUCTIVE TESTING OF PIPELINES L. Annila Abstract This paper shall present different, contemporarily available non-destructive testing (NDT) methods of pipelines and compare them to each other from
More informationGuelph WWTP Digester No. 1 Inspection Report
Guelph WWTP Digester No. 1 Inspection Report PREPARED FOR: The City of Guelph- Revised and finalized by City of Guelph. DATE: February 15, 2011 Background In 2010 the City tendered a digester cleaning
More informationCopyright 1999 Inter-Industry Conference On Auto Collision Repair v.4.0
Uniform Procedures For Collision Repair RO11 Removable Roof Copyright 1999 Inter-Industry Conference On Auto Collision Repair v.4.0 1. Description This procedure describes the repair and complete replacement
More informationNatural Gas Conversions of Existing Coal-Fired Boilers
White Paper MS-14 Natural Gas Conversions of Existing Coal-Fired s Authors: F.J. Binkiewicz Jr., P.E. R.J. Kleisley B.E. McMahon J.E. Monacelli D.A. Roth D.K. Wong Babcock & Wilcox Power Generation Group,
More information