Fast Track Recovery Mercy Health Center Joplin, MO. Kelly Turner, PE Olsson Associates
|
|
- Candace Lane
- 7 years ago
- Views:
Transcription
1 Fast Track Recovery Mercy Health Center Joplin, MO Kelly Turner, PE Olsson Associates
2 Mercy Orthopedic Hospital Springfield, Missouri Began Early beds 190 KSF $78.5 M August 2013 Associated Roadways US-65 & Evans Road Interchange Modifications Arterial & Collector Roadway Design Roundabout & Traffic Signal Design
3 Mercy Orthopedic Hospital
4 Mercy Orthopedic Hospital
5
6 May 22, 2011 EF-5 Tornado 25% of the City Destroyed $2.2 Billion in Insurance Payouts 161 Lives Lost St. John s Mercy Hospital Destroyed
7 Post-Tornado Assistance Olsson On-Site Saturday, May 29th Sites for Potential Safe Rooms Temporary MOB Planning (Trailers) Grading, Parking, Utilities Three Days Site for Permanent Temporary Facility Old Dump Site Geotech, Planning, Grading, Parking, Utilities Johnson Portables Modular Hospital Parking Lots, Utilities Friday through Monday Designs for Four or Five Weeks
8 Site Selection Process Existing Site Reuse Infeasible Contaminations Mine Features Proximity to Freeman Hospital 13 Potential New Sites for Review Site Selection Committee Community Representatives (Government, Civic, Industry) 13 Public Meetings/Hearings/Open Houses Numerous Stakeholder & Individual Meetings Narrowed to Two Sites: Interstate 44 Exit 6 Range Line Road and Interstate 44 Assisted with Due Diligence & Evaluation FEMA Environmental Assessment
9 New Mercy Health Center 116 Acres Purchase 100 Acre Initial Development Messenger College Pentecostal Church National Headquarters 15 Single-Family Homes Began Negotiations In May Closed by December
10 Project Location
11
12 New Mercy Health Center Nearly 1M SF Hospital $325M (Construction) $500M (Total) Open in Spring 2015 Other Facilities on Campus (Future) Rehabilitation Oncology Behavioral Health Hospice
13 Design & Construction Team Mercy Health Systems Northstar Management McCarthy Building Companies HKS Architects Archimages Architects SWT Landscape Architects Heideman Associates (MEP) Olsson Associates
14 Mass Grading McCarthy and Emery Sapp & Sons Began Mass Grading: January 2, 2012 Completed Mass Grading: March 1, Hour Operations 800,000 CY Mass Grading 900,000 CY Total Less than 100,000 CY Haul Away McCarthy Construction Record 25,000+ CY in 24 hours
15
16
17 Site Grading & Stormwater Management Earthwork Balance 6 = 50,000 CY Coordination of Roadway Design Sediment and Detention Basins Temporary and Permanent Early Installation of Roadway Storm Sewer
18
19
20
21
22 Transportation System September 2011 Site Meeting Established Project Team & Bi-Weekly Team Meetings Mercy -MoDOT SW District McCarthy -MoDOT Central Office Olsson Associates -FHWA Lathrop & Gage -City of Joplin
23 Transportation System Additional Stakeholder Coordination Village of Leawood Village of Shoal Creek Drive Calvary Baptist Church Joplin School District Regional Emergency Services Neighboring Residents & Businesses
24 Project Team & Cooperation Unique Project Circumstances Commitment to Speed & Schedule Begin Construction Jan 2012 Begin Roadway Construction March 2013 Hospital Open Spring 2015 Team Approach Development of Project Needs & Expectations
25 Project Team & Cooperation Access Justification Report Permit Process ROW & Utility Cooperation Cost Share vs. Assistance & Resources
26 Access Justification Report Access Justification Report (AJR) Trip Generation 22,323 vpd 1,536 AM 2,109PM Year ,207 AM Peak Hour Left-Turn Movements Trip Distribution Identification of Improvements
27 Access Justification Report Interchange Modifications Considered Existing Configuration Diverging Diamond Interchange (DDI) Single Point Urban Interchange (SPUI) Tight Diamond Interchange Modified Direct Access Interchange Combinations
28 Access Justification Report MO 86/Hearnes Boulevard & 50th Street Intersection Standard Signalized Intersection Partial Grade Separation Roundabout Continuous Flow Intersection (CFI)
29 Alternative Considerations Alternative Description Average Delay (sec) Average Stops (stops/veh) AM PM AM PM Standard Diamond Interchange with Signal at 50 th Street Tight Diamond Interchange with Roundabout at 50 th Street DDI Interchange with Signal at 50 th Street DDI interchange with Roundabout at 50 th Street DDI w/ Direct Access and Roundabout All intersections with LOS B or better All merge/diverge LOS D or better
30 Access Justification Report Additional Traffic Impact Analysis City of Joplin Village of Leawood AJR Submittal & Presentation to FHWA April 2012 Emphasize the 8 Policy Points Approval within Two Weeks
31 Transportation System Improvements Tight Diamond Interchange Reconfiguration Ramp Signalization MO 86 Widening & Resurfacing 50 th Street Reconstruction & Widening Indiana Avenue Reconstruction & Widening Two Multilane Roundabouts Glendale Boulevard Realignment
32
33
34 Construction Phasing Preliminary Stormwater Management Utility Relocations Property Owner Easement Negotiation Construction Phasing
35 Special Considerations Property Access Challenges Joplin Middle School Emergency Services Earthwork Management Construction Offices, Delivery, and Worker Staging
36 Utility Corridor
37
38
39
40
41
42
43
44 Transportation System Improvements Approximately 1.5 Miles $9 Million Begin Construction - March 2013 Original Completion Date December 2014 Revised Completion Date December 2013
45
46
FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST
FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST August 2003 Background: The Federal Highway Administration (FHWA) has retained all approval rights to the control
More informationRoadway Cost Per Centerline Mile Revised June 2014
Rural Arterial From LRE MOT * Mobilization * Subtotal Total PE Design (15%) CEI (15%) Total Project ** New (2-Lane Roadway) with 5' Paved Shoulders $3,351,896 $335,190 $368,709 $4,055,794 $1,013,949 $5,069,743
More informationJoplin, Missouri hit by EF-5 Tornado May 22, 2011
Kirstie Smith, Communications Director 320 East 4 th Street Joplin, MO 64801 417.624.4150 (O) 417.438.1738 (C) www.joplincc.com ksmith@joplincc.com Joplin, Missouri hit by EF-5 Tornado May 22, 2011 May
More informationFHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005
FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005 Background: It is in the national interest to maintain the Interstate System to provide the highest level of
More informationMaryland Invests $845 Million in New Highway and Bridge Projects
Maryland Invests $845 Million in New Highway and Bridge Projects Completing Widening of MD 404 Talbot And Caroline Counties Top Regional Priority Queen Anne s, Talbot, and Caroline Counties Widening MD
More informationLight Rail Transit in Phoenix
4. Presentation and Discussion: Phoenix Light Rail Implementation Wulf Grote Planning and Development Director, Phoenix Valley Metro Light Rail Transit in Phoenix Broadway Citizen s Task Force February
More informationIntroduction & Welcome
Proposed SM Wright Freeway Redevelopment Dallas District Halff Associates Baker Consulting Associates April 28, 2009 Introduction & Welcome Alva Baker Baker Consulting Associates Page 1 Project Overview
More informationSurface Transportation Program (STP) Projects
Toledo Metropolitan Area Council of Governments American Reinvestment and Recovery Act (Economic Stimulus Program) Application Packet for: Surface Transportation Program (STP) Projects APPLICATIONS DUE
More information8+ %!0"% 8+1!%"'$%,$"$
8+ 8+ %!0"% The next step in developing recommendations for improvements to Grand Avenue was to identify, develop and evaluate alternatives to address the issues and needs identified in the previous chapter.
More informationEXHIBIT A Accessible Truck Routes Map
EXHIBIT A Accessible Truck Routes Map ASHEVILLE, NORTH CAROLINA ROUTE: A ROUTE: B ROUTE: C ROUTE: D ROUTE: E EXHIBIT A EXHIBIT B Craven Street Improvements Map ASHEVILLE, NORTH CAROLINA EXHIBIT B EXHIBIT
More informationSR-18 Corridor Improvements in Wood County
Public Meeting Information Package SR- Corridor Improvements in Wood County Thursday, May 19, 2011 10:00 a.m. to 1:00 p.m. Meeting Location: Hancock-Wood Electric Cooperative Building 1399 Business Park
More informationThe financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan.
3 Financial Plan The purpose of the financial plan is to identify funding options that would be likely sources of money to advance recommendations made by this study. The Capitol Region Transportation
More informationNear Westside Neighborhood and University Avenue Corridor Transportation Study. Public Workshop #2. September 12 and 23, 2013
Near Westside Neighborhood and University Avenue Corridor Transportation Study Public Workshop #2 September 12 and 23, 2013 Presentation Outline: Brief Review of Study Scope, Background, and Current Conditions
More informationGENERAL EXPERIENCE OF FIRM
12200 NW Ambassador Drive, Suite 205 Kansas City, MO 64163 816-298-6465 www.garverusa.com November 15, 2013 Missouri 105 West Capitol Avenue Jefferson City, MO 65102 via email to MaryAnn.Jacobs@modot.mo.gov
More informationWelcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU
Purpose of Tonight s Meeting Informational Open House to discuss two City projects: Fairchild Street Subway Phase I Engineering: Immediate need to replace subway Bowman Avenue Feasibility Study Future
More informationAppendix G.3 Crain & Associates, Peer Review
Appendix G.3 Crain & Associates, Peer Review Transportation Planning / Traffic Engineering VIA HAND DELIVERED Wendy Lockwood Sirius Environmental 1478 N. Altadena Drive Pasadena, California 91107 Subject:
More informationInterchange Access Request. User s Guide. User Guide
Interchange Access Request User s Guide User Guide 2013 2013 TABLE OF CONTENTS Table of Contents Preface... 1 Purpose... 1 Scope... 1 Organization... 2 Distribution, Updates and Contact... 3 Chapter 1
More informationINTRODUCTION TO ZONING DISTRICT REGULATIONS
INTRODUCTION TO ZONING DISTRICT REGULATIONS Classification of Zoning Districts Zoning districts in Dorchester County are categorized as Suburban Urban, Suburban Transition, or Rural. These districts are
More informationSection 6 Traffic Analysis
Section 6 Traffic Analysis Traffic Operations of the Preferred Network Alternative After the Preferred Network was identified and confirmed by local policy makers and area residents, detailed traffic analysis
More informationCHAPTERTWO. Alternatives 2.1 ALTERNATIVES DEVELOPMENT PROCESS
2. Section 2 TWO CHAPTERTWO 2.1 ALTERNATIVES DEVELOPMENT PROCESS This EIS has been prepared in compliance with the Council on Environmental Quality (CEQ) regulations for implementing NEPA (40 CFR 1500-1508).
More informationAlternatives Design Report. Draft
Draft 3/4/2014 TABLE OF CONTENTS I Introduction... 1 A. HISTORY... 1 B. PROJECT BACKGROUND... 1 II. ALTERNATIVES DEVELOPMENT... 8 A. ALTERNATE 1 NO BUILD... 8 B. ALTERNATE 2 IMPROVE ROADWAY ON EXISTING
More informationSOLD. Lot 1. 1 Mile: Population: 10,200 Median HH Income: $33,100. 3 Mile: Population: 80,200 Median HH Income: $34,900
Walmart Outparcels For Sale College Station, TX Store # 1150 1815 Brothers Blvd FM 2818 W SOLD Texas Ave S/ Hwy 6 Longmire Dr Brothers Blvd Lot 1 For more information about this site, contact: Lot 1: ±2.41
More informationAIR QUALITY TECHNICAL MEMORANDUM
AIR QUALITY TECHNICAL MEMORANDUM AIR QUALITY TECHNICAL MEMORANDUM GOLDEN GLADES INTERCHANGE PD&E STUDY Miami-Dade County, Florida Financial Management Number: 428358-1-22-01 Efficient Transportation Decision
More informationTHE COMMONWEALTH OF MASSACHUSETTS MASSACHUSETTS HIGHWAY DEPARTMENT PROJECT INITIATION FORM (PIF)
THE COMMONWEALTH OF MASSACHUSETTS MASSACHUSETTS HIGHWAY DEPARTMENT PROJECT INITIATION FORM (PIF) To: From: Contact Information: Roland Bartl, Planning, Town of Acton, 472 Main St. Acton MA 01440; 978-264-9639;
More informationMissouri Department of Transportation
Missouri Department of Transportation Transportation Alternatives 2014 Table of Contents A Guide to Transportation Alternatives Page I. Transportation Alternatives Activities 2 II. Project Eligibility
More informationThe Corporation of the TOWN OF MILTON
The Corporation of the TOWN OF MILTON Report to: From: Mayor G. A. Krantz & Members of Council M. Paul Cripps, P. Eng., Director, Engineering Services Date: November 11, 2013 Report No. ENG-039-13 Subject:
More informationAlternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011
Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011 CCRPC staff has developed a draft methodology described below and detailed in the attached pages for
More informationBruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road)
Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road) Industry Briefing - 13 February 2013 Bruce Highway Upgrade (Cooroy to Curra) The Bruce Highway Upgrade (Cooroy to
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS Engineering Design Services for the Preliminary (Design) Engineering 1. Imlay City Road Imlay City Road at Wilder Road (signal modernization), Lapeer Township 2. Imlay City Road Imlay
More informationPLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013
PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 NAME LOCATION Audubon Properties, LLC. 4700 & 4960 Dauphin Island Parkway West side of Dauphin Island Parkway, 580
More informationI-25 / Rio Bravo Interchange
I-25 / Rio Bravo Interchange TONIGHT S MEETING SCHEDULE OPEN HOUSE 6:00 PM TO 6:30 PM PRESENTATION BEGINS AT 6:30 PM Q & A FOLLOWING PRESENTATION CN A300280 / PNA300280 I-25 / Rio Bravo Interchange SECOND
More informationHIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES
Approved 6/26/01 HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES All new, modified and/or changed use access(es) onto county roads shall be subject to the access and corridor protection guidelines
More informationin Marina Del Rey Prepared by: County of Los Angeles Department of Public Works
Planned Public Works Projects in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Projects in Marina Del Rey Waterline Projects Phase II Phase III Roadway Projects Admiralty
More informationAPPENDIX F. Access Management Design Standards for Entrances and Intersections
APPENDIX F Access Management Design Standards for Entrances and Intersections PREFACE The access management regulations and standards do not apply in cities, towns of more than 3,500 and in counties (Henrico
More informationChapter 22. Lump Sum Project Guidelines
Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11
More informationENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS
ENGINEERING DESIGN GUIDELINES for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS City of Birmingham Department of Planning, Engineering and Permits Engineering Division Office of the City Engineer 2008 TABLE
More informationMulti-Modal Corridor Degree of Complexity: High Cost/Benefit: High
Multi-Modal Corridor Degree of Complexity: Cost/Benefit: Maintain the same level of service for Ensures continuous flow through the Might impact other transportation Consider road diet and/or different
More informationCE 401 Civil Engineering Design Project, Spring 2002 2:00 to 2:50 PM Monday and 2:00 to 4:50 PM Wednesday, Room 340
CE 401 Civil Engineering Design Project, Spring 2002 2:00 to 2:50 PM Monday and 2:00 to 4:50 PM Wednesday, Room 340 Catalog Data: Students use design software to design projects in teams, prepare construction
More informationIH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
More informationTRAFFIC IMPACT ANALYSIS
TRAFFIC IMPACT ANALYSIS Presenter Gerry Harter, PE, Area Traffic Engineer Acting Transportation and Land Use Director Why a TIA? Roads are a critical public resource and a major investment of public funds
More informationThe Top 50 Highway Projects to Support Economic Growth and Quality of Life in Alabama
The Top 50 Highway Projects to Support Economic Growth and Quality of Life in Alabama FEBRUARY 2016 Washington, DC 202-466-6706 Founded in 1971, TRIP of Washington, DC, is a nonprofit organization that
More informationAccess Management South Dakota Department of Transportation
Public Meeting/ Open House October 21, 2014 Minnehaha County Environmental Assessment and Section 4(f) De Minimis Analysis Northern Segment of Hwy 100 I-90 to South of Madison Street Minnehaha County The
More informationThe Need for Traffic Incident Management
The Need for Traffic Incident Management With traffic incidents responsible for approximately 50-60% of the congestion delays motorists encounter on the nation s roadways every day, increased roadway capacity
More informationAPPENDIX J TRAFFIC STUDY
APPENDIX J TRAFFIC STUDY May 7, 2014 Ms. Leianne Humble Denise Duffy and Associates, Inc. 947 Cass Street, Suite 5 Monterey, CA 93940 Re: Traffic Study for the Heritage Oaks Memorial Park in San Jose,
More informationPlanning Commission Staff Report
10 Planning Commission Staff Report TO: FROM: THROUGH: PLANNING COMMISSION AMY TEMES, SENIOR PLANNER (480) 503-6729, AMY.TEMES@GILBERTAZ.GOV CATHERINE LORBEER, AICP, PRINCIPAL PLANNER (480) 503-6016 CATHERINE.LORBEER@GILBERTAZ.GOV
More informationRestoration. a brief look at
Copyright 2009 Canin Associates, Inc. All rights reserved. No part of this publication may be reproduced or transmitted by any means without written permission from Canin Associates, Inc. a brief look
More information14-97. 14-97.002 Definitions. For the purposes of this rule chapter the following definitions shall apply unless the context clearly shows otherwise:
14-97 14-97.001 Purpose. This rule chapter sets forth an access control classification system and access management standards to implement the State Highway System Access Management Act of 1988. The implementation
More informationAppendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1
Appendix C Change Management Plan Communication Plan QA/QC Plan Transition and Closure Plan C-1 CHANGE MANAGEMENT PLAN Whether the effects of changes are positive or negative, managing change is an important
More informationNorth Avenue Corridor Study. Advisory Committee Meeting #5 June 11, 2014
North Avenue Corridor Study Advisory Committee Meeting #5 June 11, 2014 Agenda Welcome and introductions Concept refinement and evaluation: Public meeting and web survey General cross-section concepts
More informationI-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015
I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA PSPE Presentation, December 3, 2015 Location Map N PROJECT LOCATION 22 nd 18 th Streets PHILADELPHIA, PA General
More informationP. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL
P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL 1.0 Description. 1.1 This specification allows bidders the opportunity to include in their overall bid proposal, pricing for
More information5. Environmental Analysis
5.11 The potential for adverse impacts on utilities and service systems was evaluated based on information concerning current service levels and the ability of the service providers to accommodate the
More informationA Presentation to the Houston Hispanic Architects and Engineers
A Presentation to the Houston Hispanic Architects and Engineers Alan J. Potok, P.E. Director, Engineering and Construction Division Harris County Flood Control District February 6, 2014 Agenda Overview
More informationUrban Planning and Land Use
Urban Planning and Land Use 701 North 7 th Street, Room 423 Phone: (913) 573-5750 Kansas City, Kansas 66101 Fax: (913) 573-5796 Email: planninginfo@wycokck.org www.wycokck.org/planning To: From: Unified
More informationSurface Transportation Program (STP)
Project Name: Project Sponsor: FEDERAL FUNDS PROJECT APPLICATION TRANSPORTATION IMPROVEMENT PROGRAM 2008-2013 SALT LAKE and OGDEN/ LAYTON URBAN AREAS Surface Transportation Program (STP) Urban Surface
More informationDISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST
State of California Business, Transportation and Housing Agency DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST District / EA: District 3/ EA 03-3E380 Date Prepared: 1/10/2013 Prepared By: Robert Himes Stage
More informationDIVISION STREET CORRIDOR STRATEGY Arlington, Texas May 17, 2012
DIVISION STREET CORRIDOR STRATEGY Arlington, Texas May 17, 2012 Project Review: DCAC Meeting #2 March 8, 2012 Reviewed stakeholder meetings Online survey findings Market Assessment Macro Market Factors,
More informationCity of Houston Economic Development 2010 in Review
City of Houston Economic Development 2010 in Review TOTALS $654,000,000 in new capital investment 10,800 jobs TEXAS ENTERPRISE ZONE SPECIFIC PROJECTS The Texas Enterprise Zone Program is an economic development
More informationCHAPTER 27 New Public Road Connections. Table of Contents
Chapter 27 New Public Road Connections Table of Contents CHAPTER 27 New Public Road Connections Table of Contents CHAPTER 27 New Public Road Connections... 27-3 ARTICLE 1 - General... 27-3 Responsibility...
More informationRESOLUTION NO. 1539 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BONNEY LAKE, PIERCE COUNTY, WASHINGTON, APPROVING THE 192 ND CORRIDOR STUDY AND DIRECTING THE MAYOR TO PROCEED WITH PARTIAL DESIGN AND
More informationThe Region s Most Expensive Commutes:
The Region s Most Expensive Commutes: Congested Corridors in the Pittsburgh Area and Steps Needed to Relieve Traffic Congestion June 2013 Washington, DC Phone: (202) 466-6706 www.tripnet.org Founded in
More informationChapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL
Chapter Forty-seven RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL Illinois RURAL TWO-LANE/MULTILANE STATE HIGHWAYS December 2009 2 Illinois
More informationScope of Work Construction Inspection and Materials Testing Services
Glenwood Resident Engineer 202 Centennial Drive Glenwood Springs, CO 81601 Scope of Work Construction Inspection and Materials Testing Services Estimated Start Date: November 1, 2015 Region 3 Project:
More informationSECTION XI OPINION OF PROBABLE COST
SECTION XI OPINION OF PROBABLE COST OPINION OF PROPABLE COSTS HARBOR ISLAND THE PAVILION 1) Provide a sprinkler system for the entire building. 8000 SF X $15/SF $120,000 2) Remove and replace existing
More informationMission Creek Flood Control & Restoration Project. City of Fremont, Alameda County
Mission Creek Flood Control & Restoration Project City of Fremont, Alameda County Agenda Background Why are proposed improvements necessary? Proposed project components Challenges Construction schedule/phasing
More informationGENERAL. This manual addresses five local programs that are funded under the current Highway Act:
OVERVIEW The Local Public Agency Manual published by the Missouri Department of Transportation (MoDOT) is intended to be used as a guide for cities and counties that sponsor projects utilizing federal
More informationChapter Thirty-five ACCESS CONTROL/ ACCESS MANAGEMENT BUREAU OF DESIGN AND ENVIRONMENT MANUAL
Chapter Thirty-five ACCESS CONTROL/ ACCESS MANAGEMENT BUREAU OF DESIGN AND ENVIRONMENT MANUAL Chapter Thirty-five ACCESS CONTROL/ACCESS MANAGEMENT Table of Contents Section Page 35-1 GENERAL CONCEPTS...
More informationHERS_IN. HIGHWAY ECONOMIC REQUIREMENTS SYSTEM (for) INDIANA. AASHTO Transportation Estimator Association Conference October 16, 2001
AASHTO Transportation Estimator Association Conference October 16, 2001 HERS_IN HIGHWAY ECONOMIC REQUIREMENTS SYSTEM (for) INDIANA OVERVIEW HERS Background System Planning Tool Development HERS_IN Structure
More informationMISSOURI TRANSPORTATION BY THE NUMBERS:
MISSOURI TRANSPORTATION BY THE NUMBERS: Meeting the State s Need for Safe and Efficient Mobility APRIL 2015 202-466-6706 tripnet.org Founded in 1971, TRIP of Washington, DC, is a nonprofit organization
More informationSave Our Heritage Organisation v. San Diego Unified Port District
Save Our Heritage Organisation v. San Diego Unified Port District 1 San Diego County Regional Airport Authority created by legislation in 2003 Operates San Diego International Airport Acts as the Airport
More informationWORK ZONE SAFETY & MOBILITY GUIDANCE DOCUMENT
WORK ZONE SAFETY & MOBILITY GUIDANCE DOCUMENT August 2007 Prepared by: Vermont Agency of Transportation The following document was drafted in response to updates made to the work zone regulations at 23
More informationOvercoming the. Challenges of ORT Conversion in an Urban Environment. July 12, 2015
Overcoming the July 12, 2015 Challenges of ORT Conversion in an Urban Environment PRESENTING: Daniel P. Menendez, P.E. Assistant Director of Engineering 1 The MDX System Highly Dense Urban Environment
More informationCity Council Agenda Item Report October 13, 2015
City Council Agenda Item Report October 13, 2015 Contact Chance Sparks, AICP, CNU-A, Director of Planning 512-312-0084 / csparks@ci.buda.tx.us SUBJECT: APPROVAL OF A PRELIMINARY PLAN FOR THE BUDA BUSINESS
More informationI-25/ARAPAHOE INTERCHANGE RECONSTRUCTION PROJECT
MANDATORY PRE-BID SIGN IN CDOT Carrie DeJiacomo, Program Engineer John Hall, Resident Engineer Telecia McCline, Project Manager Tammy Maurer, Assistant Project Manager David Evans/Hartwig Design Consultant
More informationComment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s.
Proposed Truck Climbing Lane Route 7 Westbound Between West Market Street and Route 9 UPC# 58599, Project # 6007-053-133, P101 Date of Meeting: August 24, 2010 Time: 6:00PM to 8:00PM Location: Rust Library
More informationDESIGN PUBLIC HEARING. August 10, 2015 WEST BOYLSTON TOWN HALL, BOARD MEETING ROOM. 140 Worcester Street WEST BOYLSTON, MASSACHUSETTS 6:30 PM
DESIGN PUBLIC HEARING August 10, 2015 AT WEST BOYLSTON TOWN HALL, BOARD MEETING ROOM 140 Worcester Street WEST BOYLSTON, MASSACHUSETTS 6:30 PM FOR THE PROPOSED Rehabilitation & Stormwater Improvements
More informationGeorge M. Camp, Ph.D., Criminal Justice Institute Lou Ragozzino, PE, Louis Berger Group Jeff Buck, DMJM H&N
Presentation to the North Dakota Legislative Council and its Correctional Facility Review Committee Criminal Justice Institute August 21, 2007 Criminal Justice Institute Team Presenters George M. Camp,
More information3 Tappan Zee Bridge Rehabilitation Options
3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:
More informationREQUEST FOR PROPOSAL/QUALIFICATIONS VILLAGE ENGINEER
VILLAGE OF NEWTOWN 3537 Church Street Newtown, Ohio 45244 (513)561-7097 ~ Fax (513)561-7555 Established 1792 REQUEST FOR PROPOSAL/QUALIFICATIONS VILLAGE ENGINEER REQUEST FOR PROPOSAL/QUALIFICATIONS Contract
More informationMajor Improvement Schemes in Basingstoke
Major Improvement Schemes in Basingstoke 1. Welcome Welcome to this exhibition, which provides information about the planned highway improvements being delivered in Basingstoke from 2015 2018. A30 Winchester
More informationDecision making in ODOT s Project Development Process. How to Use the Feasibility Study and Alternatives Evaluation Report in the PDP
Decision making in ODOT s Project Development Process How to Use the Feasibility Study and Alternatives Evaluation Report in the PDP Decision making in ODOT s PDP: FS and AER O Susan Daniels, PE, AICP
More informationPROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS
C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates
More informationCITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR
CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile
More informationAPPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP)
APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP) To be considered for STP funding, a proposed project must
More informationTraffic Forecasting. Resource Guidebook. Florida Department of Transportation District Five
Traffic Forecasting Resource Guidebook Florida Department of Transportation District Five Florida Department of Transportation District Five November November 2006 2006 Traffic Forecasting Resource Guidebook
More informationELEMENT 4 - FUTURE LAND USE ELEMENT
ELEMENT 4 - FUTURE LAND USE ELEMENT Goal 1 To create a long-range development pattern which directs growth into developable areas and away from environmentally sensitive areas, in a manner that is compatible
More informationTransportation Management Plan Template
DATE: TO: FROM: SUBJECT: Date Name Position Transportation Service Center Name Position Transportation Service Center Transportation Management Plan Job Number(s) Control Section(s) Route Details County
More informationTRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES
TRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES Background One of the most critical public services provided by a community is the community s transportation system. An effective
More information7.2 Warrants and Planning Considerations
Chapter 7 Interchanges 7.1 Introduction As discussed in Chapter 6, it is important that designers consider the needs and activities of the pedestrians, cyclists, and motorists to comprehensively plan for
More informationWilmington to Newark Commuter Rail Improvement Project
Wilmington to Newark Commuter Rail Improvement Project The Delaware Transit Corporation (DTC), a subsidiary of the Delaware Department of Transportation (DelDOT), is undertaking a rail capacity expansion
More informationDESIGN ASSISTANCE APPLICATION
DESIGN ASSISTANCE APPLICATION for FY 2016 NEW RIVER MULTI USE PATH: PINNACLE PEAK ROAD TO HAPPY VALLEY ROAD CITY OF PEORIA APPLICATIONS ARE DUE VIA ONLINE SUBMITTAL BY 10:00 AM ON MONDAY, JUNE 29, 2015
More informationINDOT 2000-2025 Long Range Plan
Chapter 9 INDOT 2000-2025 Long Range Plan Highway Needs Analysis Overview The statewide transportation planning process provides for the identification of highway needs through a comprehensive process
More informationPlanning and Zoning Commission Johnston, Iowa June 29, 2015
ITEM NO. 15-19 Planning and Zoning Commission Johnston, Iowa June 29, 2015 SUBJECT: Consider recommending approval of the Final Plat for Crosshaven Plat 6 subdividing 28.28 acres into 47 single family
More informationKansas City s Overflow Control Program
Kansas City s Overflow Control Program Kansas City Water Services Water Wastewater Stormwater 2 Water Services Department 1000 Positions 835 Employees 3 Utilities FY 13/14 Budget = $307 million Water Wastewater
More informationMoving a House in Pasadena
Moving a House in Pasadena To assist homeowners and contractors wishing to relocate a home in Pasadena, this handout summarizes the steps in the permitting process. Please keep in mind that the sequence
More informationSTANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN
STANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN JULY 2015 Standard Elements of a Construction Management Plan (CMP) This guidance tool was developed through partnership between the Department of Planning
More informationDE 8 Concept Plan and Operations Study. Dover Safety Advisory and Transportation Committee October 23, 2007
DE 8 Concept Plan and Operations Study Dover Safety Advisory and Transportation Committee October 23, 2007 Purpose Develop a concept plan describing the aesthetic qualities of the corridor as a gateway
More informationPlanning Level Cost Estimation Tool. User s Manual
Planning Level Cost Estimation Tool User s Manual Atlanta Regional Commission Submitted By: User s Manual Table of Contents 1. INTRODUCTION... 1 2. OBJECTIVE... 1 3. FRAMEWORK OF THE TOOL... 2 4. HOW TO
More informationS-11: Tacoma Link Extension to Tacoma Community College
Project Number S-11 Subarea Pierce Primary Mode Light Rail Facility Type Corridor Length 3.65 miles Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT
More informationCity of Valdosta Land Development Regulations. Table of Contents
TITLE 1 ADMINISTRATION Chapter 102 General Provisions 102-1 Title 102-2 Purpose 102-3 Authority 102-4 Jurisdiction 102-5 Application of Ordinance 102-6 Relationship to Existing Ordinances 102-7 Powers
More information