Cycle Review at The Regent s Park

Size: px
Start display at page:

Download "Cycle Review at The Regent s Park"

Transcription

1 The Royal Parks Cycle Review at The Regent s Park Project Ref: June 2008 Caversham Bridge House Waterman Place Reading Berkshire RG1 8DN reading@pba.co.uk

2 ii

3 DOCUMENT CONTROL SHEET Project Name: Cycle Review at The Regent s Park Project Ref: Report Title: Date: June 2008 Name Position Signature Date Prepared by Stacey Lloyd Engineer 9 th May 08 Checked by Phil Brady Senior Associate 9 th May 08 *Authorised for issue by For and on behalf of Peter Brett Associates *Issue Revision Description Date Signed Amended in line with input from TRP June 2008 *Delete as appropriate Peter Brett Associates disclaims any responsibility to the Client and others in respect of any matters outside the scope of this report. This report has been prepared with reasonable skill, care and diligence within the terms of the Contract with the Client and generally in accordance with ACE Short Form Conditions of Engagement and taking account of the manpower, resources, investigations and testing devoted to it by agreement with the Client. This report is confidential to the Client and Peter Brett Associates accepts no responsibility of whatsoever nature to third parties to whom this report or any part thereof is made known. Any such party relies upon the report at their own risk. Peter Brett Associates 2004

4 iv

5 TABLE OF CONTENTS 1. Introduction Introduction Background Report Framework Section One Broad Walk Summary of Route Options Broad Walk Route Design Envisaged level of service Stage 1 and 2 Safety Audit Speed Assessment Recommended Route Potential Route Extension Alternative Routes Summary of Section One Section Two - The Regent s Park on-carriageway Introduction mph speed limit The Outer Circle cycle infrastructure improvements Summary of Section Two Section Three - Implementation Mechanisms Programme of works Preliminary risk analysis Summary and Conclusion Introduction Conclusion and way forward...35 Recommendations...35 Way forward...36 Appendix A BTP Hyder Broad Walk segregated route drawings Appendix B BTP Hyder Broad Walk Un-segregated route drawings Appendix C Stage 1 and 2 Safety Audit Appendix D Engineers Response to Stage 1 Safety Audit

6 1. Introduction 1.1. Introduction The Royal Parks (TRP) is considering the opportunity to improve cycling provision to and within The Regent s Park. This entails investigating the feasibility of providing cycle routes within the Park either on carriageway and/or within the green space of the Park The Royal Parks commissioned consultants Bettridge Turner and Partners (BTP Hyder) to provide advice on providing cycling within the Park. Their analysis culminated in a temporary shared-use cycle route being initiated between early July and late September 2007 along the Broad Walk from Chester Road to the south to the Outer Circle to the north This report has been prepared by Peter Brett Associates in consultation with The Royal Parks. It provides advice on using the Broad Walk as an off carriageway cycle route, shared with pedestrians, and what measures could be implemented on carriageway within the Park to enhance use by cyclists This report is to be read in conjunction with the Peter Brett Associates (PBA) Public Consultation Report which analyses the movement survey, the questionnaire and the consultation responses undertaken to assess the viability of a permanent scheme along The Broad Walk Background Current Royal Parks Cycle Policy TRP is managed for the enjoyment of all who visit the parks and TRP aim to balance the needs of visitors and the protection of wildlife, heritage and conservation. Pedestrians are provided priority within the parkland and green spaces as they make up the majority of park users, however TRP is keen to support other appropriate activities in the parks The Regent s Park currently provides the largest outdoor sports area in London covering approximately 166 hectares and several tourist attractions including an Open Air Theatre and the London Zoo. The Regent s Park is earmarked as a venue for the finish to the Road Cycling event for the London 2012 Olympics TRP seek to promote cycling as a sustainable means of access, and hosted in Hyde Park and St. James s Park the Prologue route of the 2007 Tour de France It is understood that adult cycling is permitted only in line with the Statutory Instruments document Royal Parks and Other Open Spaces Regulations 1997 and subsequent amendments. Young children are permitted under the Regulations to cycle, it is perceived they pose little risk to other park users and allows them to learn to cycle in safety. 6

7 Previous studies A cycling strategy for The Regent s Park was undertaken by consultants Bettridge Turner and Partners (BTP Hyder) in July 2007 and provided advice on the feasibility of implementing cycle routes within The Regent s Park, in the form of off carriageway and on carriageway options Included in the report was a condition survey of the Broad Walk and cost estimates to carry out the schemes. A cyclist questionnaire survey was carried out in September 2007 and the results of which were included in the subsequent issue of the report late September Reference to the cyclist survey is included within the Peter Brett Associates Consultation Report dated January Construction issue drawings of the informal pedestrian crossing points and associated cycle infrastructure situated around The Outer Circle were made available for reference purposes. BTP Hyder and PBA have provided comment to The Royal Parks on these through separate technical papers and, as such deemed to be outside the remit of this report A number of surveys were conducted at the Broad Walk. Video surveys were designed to indicate the usage in the Park and questionnaire survey. The dates of the surveys were: Video movement survey Sunday 25 th March 2007 Pre survey commissioned by BTP Hyder Thursday 29 th March 2007 Pre survey commissioned by BTP Hyder Thursday 16 th August 2007 Post survey commissioned by PBA Sunday 26 th August 2007 Post survey commissioned by PBA Questionnaire survey 6 th September 2007 origin and destination survey by BTP Hyder Thursday 27 th September (7am to 7pm) Sunday 30 th September (10am to 6pm) PBA conducted a questionnaire survey to gauge the effect of implementing a cycle route along the Broad Walk. The results from some of the key questions are summarised in the charts and tables below. The majority of participants around 2/3rds were pedestrians, so as to get a general mix of comments and not to bias the survey, if only cyclists had been questioned. 7

8 The comments received relating to question 12 If you have any specific comments relating to the summer shared use-path trial on the Broad Walk in Regent s Park, please make them below were: Issues Number of Comments related to the issue Positive opinion of the cycle route 123 Negative opinion of the cycle route 35 Segregation of lanes 26 Other comment 22 Danger, speeding 21 More routes required, lack of routes 19 Tranquillity disrupted 9 Illegal cyclists 8 Behaviour of the cyclists 7 More space, wider paths 7 No comment 228 Comments on cycling on the Broad Walk The table sets out a summary of the main comments made to which PBA have sought to populate with the number of responses related to that comment. Of the people who responded to this question a little under half expressed a positive opinion of the cycle route whereas roughly a third was negative. The majority of those that were questioned provided no comment, which would suggest no real bias for either view When asked about safety concerns relating to cycling in the Park two thirds had no concerns and one third were concerned, citing factors such as cycle speeds and conflict potential For question 13 Would you cycle in the Park if more of the existing paths were open to cyclists the answers obtained are displayed below. Undisclosed 5% Definitely not 22% Yes, definitely 42% Probably not 11% Maybe 10% Yes, probably 10% Would you cycle in the Park if more paths were open to cyclists? Two thirds of respondents to this question expressed a positive opinion. Implementing cycling within The Regent s Park would support The Royal Parks aspirations to promote cycling as a sustainable means of access and provides an opportunity to cycle in a pleasant environment. 8

9 Questions posed relating to on-carriageway aspects included how well do the roads in The Regent s Park work for cyclists and what specific comments were recorded relating to cycling on roads in The Regent s Park. For example question 9 In your experience, how well do the roads in Regent s Park work for cyclists? the results were: Undisclosed 6% Very Badly 4% Badly 11% Haven t had experience of cycle routes 21% OK 21% Well 7% Very Well 30% How well do the roads work for cyclists? A little under two thirds of the opinions expressed indicated that the current facilities were good or adequate Question 10 If you have any specific comments relating to the cycling on the roads in Regent s Park, please make them below results are recorded below: Issues Number of Comments related to the issue No comment 199 Positive opinion of the cycle route 110 Other comment 95 Danger, speeding 53 More routes required, lack of routes Negative opinion of the cycle route Segregation of lanes 26 Illegal cyclists 24 More cycling provision 10 Tranquillity disrupted 9 More space, wider paths 9 Specific comments relating to cycling on roads in The Regent s Park The consensus of opinion from people who responded to this question is effectively split 50/50 between those who were favourable and those who were not. 9

10 In Question 14 How would you feel if cycling was allowed on more of the existing paths in The Regents Park? people were questioned as to whether they would cycle in the Park if more of the existing paths were opened up to cyclists. About ¾ of respondents felt that it was fine for cycling to be allowed on more paths, of which a ¼ felt that additional conditions, such as segregated paths, more policing and extensions to the route are needed to be implemented at the same time to make it safe. Only ¼ of respondents felt it was not fine for cycling to have allowance on more paths Report Framework This report consists of three sections. Section one will provide analysis of issues relating to the implementation of a permanent cycle route along the Broad Walk in the Park, section two will analyse additional factors around the Park not directly linked to the Broad Walk and Section three will discuss factors relating to delivery of the recommended elements to the project. In summary the sections will contain: Section One The Broad Walk Summary of route options Broad Walk route design Speed assessment Safety Audit Alternative routes within The Park Potential route extension Section Two The Regent s Park outer environs 20mph speed limit on roads within The Park The Outer Circle cycle infrastructure improvements Section Three - Implementation Mechanisms Draft Programme of Works Preliminary Risk Analysis 10

11 2. Section One Broad Walk 2.1. Summary of Route Options The BTP Hyder report put forward three options to provide cycling along the Broad Walk and looked at alternative routes within The Park at Primrose Hill Gate and Charlbert Gate. This would constitute a network of cycle paths in the green space of The Park. The report did not recommend any particular route and concluded that each route is viable providing adequate signage be installed to inform people that cyclist now use The Park, tailored to the method of segregation The off carriageway route options, illustrated below, were: Route One - The Broad Walk between the Outer Circle at St Marks Bridge in the north and Chester Road in the south Route Two - The footpath between Primrose Bridge Gate in the north and Longbridge Gate at the Inner Circle Route Three - The footpath between Charlbert Gate in the north west and Longbridge Gate at the Inner Circle The routes were assessed in terms of surface condition and extent of pedestrian/cyclist segregation. Options were designed and discussed in the report. The outcome of this analysis was that a cycle route could be incorporated along the Broad Walk and the footpaths along Routes two and three listed above; - however it was recommended that the footways for Routes two and three be reconstructed to a width suitable for both pedestrians and cyclists. 11

12 2.1.4 A temporary experimental shared-use cycle route was implemented between early July and late September 2007 along the Broad Walk from Chester Road north to its junction with Outer Circle Peter Brett Associates were not involved in the initial choice of the Broad Walk as the possible route for cycle provision within the Park or the method of segregation. Through consultation with The Royal Parks, including the Park Manager, the provision of a network of routes has been initially reduced to one, with the Broad Walk appearing to be the premium route to permit cycles into the Park on a permanent basis without prejudicing existing pedestrian only paths that crisscross the Park Broad Walk Route Design The Broad Walk is a straight route through the Park running from St Mary s Bridge to the north to Park Square Gardens to the south and is approximately 10.5 metres to 12 metres wide along its length. The pavement surface is of bituminous material which is patchy in places and suffers elements of failure due to a damaged drain running linear along the centre of the Broad Walk. It is envisaged that the pavement will be repaired / reinstated if the proposal to provide a cycleway along the Broad Walk is successful There were three options available to implement a shared pedestrian / cycle route along the Board Walk. These were: Shared-use segregated Shared-use un-segregated Separate route parallel to Broad Walk Shared-use segregated In order to provide a segregated cycle path along the Broad Walk a number of factors need to be considered. These include the placement of street furniture, the form of segregation, the interaction at path crossings and the envisaged speed of cyclists The manner of segregation would influence the costs of implementing the scheme, from a relatively inexpensive line marking to a physical barrier method involving more extensive infrastructure works. This could entail either a line of granite setts with no level change to an engineered scheme separating the pedestrians and cyclists with a level difference of 50mm to 100mm. Physical measures to separate the modes will affect the opportunity to adapt the route efficiently in the future and may present an issue for partially sighted and mobility impaired users The design proposals put forward by BTP Hyder for a shared-use scheme illustrated a 3.0m wide cycle path bisecting the Broad Walk from Chester Road to the Outer Circle. This is illustrated in the Broad Walk cross section below. The route would be demarked with solid white lining at the edge and a centre line separating cycle streams. The drawings relating to this are located in Appendix A. It was proposed that the cycle route would have a tarmac surface with the remaining area for pedestrians to be of a gravel bound surface. Chester Road had advisory cycle markings along it, which appeared to replace the existing on street parking. The Broad Walk interface with Chester Road is shown on BTP Hyder drawing GD

13 Cross section of Broad Walk segregated route As the route progressed in the Park intersections with footpaths along the Broad Walk were demarked with white lining indicating NO CYCLING and Paragon signs to diag 951 of the Traffic Signs and General Directions 2002 (TSRGD) inset into the footpath. This is indicated on BTP Hyder plan GD04663/ The segregated cycle route split around the Readymoney fountain, again with NO CYCLING lining and Paragon signs at footpath intersections with the Broad Walk as illustrated on BTP Hyder drawing GD04663/ The segregated route ended at the Outer Circle with ladder paving and vertical signage at the mouth of the Broad Walk. BTP Hyder plan GD04663/115 also shows the provision of a 1.5m wide advisory cycle lane each way on the Outer Circle The advantage of providing a segregated shared-use scheme is separation of travel modes reducing the potential for conflict. This permits potential for travel at greater speeds for cyclists. People also feel safer if there is a degree of segregation between modes The disadvantages of providing a segregated scheme are: The requirement to relocate the refuse bins and benches along one side of the Broad Walk Reducing available space to pedestrians which would be an issue during times of high pedestrian patronage such as events and groups visits as illustrated in the photograph below Visual impact of the physical or line markings are undesirable in this historic park setting Segregation would permit higher cycle speeds in excess of the 5mph increasing collision severity and more signage will be required to alert users at path crossings that they are crossing a live cycle corridor. This additional signage may increase visual intrusion of the scheme Over spill by modes into the other lane may happen unless physical measures are installed to prevent this Contrasting surface marking to reinforce the different lanes will increase costs. Physical segregation is an issue for partially sighted and mobility impaired users. 13

14 Shared-use un-segregated Option Two for the Broad Walk was to create a shared-use un-segregated route for pedestrians and cyclists. The BTP Hyder drawings related to this option are located in Appendix B of this report. The principle of advisory cycle lanes along Chester Road are retained from the segregated scheme. The Broad Walk is to be tarmac throughout with connecting footpaths surfaced with bound gravel. Entry to the shared route would be indicated with white line cycle markings to 1057 and vertical signage at the gates to the Broad Walk. This is indicated on BTP Hyder drawing GD As with the segregated scheme, the intersections with footpaths along the Broad Walk were demarked with white lining indicating NO CYCLING and Paragon signs to diag 951 of the Traffic Signs and General Directions 2002 (TSRGD) inset into the footpath. However additional road markings proclaiming LOOK BOTH WAYS was added to warn pedestrians they were entering a path with different characteristics. This is indicated on BTP Hyder plan GD04663/ At the Readymoney fountain the existing gravel bound surface is replaced with blacktop but the NO CYCLING markings and Paragon signs inset into the footpath are carried over from the segregated option as illustrated on BTP Hyder drawing GD04663/121. Interestingly there is no LOOK BOTH WAYS markings proposed in this location On BTP Hyder drawing GD The un-segregated route starts/ends at the Outer Circle, however no markings or signage are proposed to inform people of the status of the Broad Walk. The provision of a 1.5m wide advisory cycle lane each way on the Outer Circle is retained from the segregated route option Elements from the un-segregated design drawings created by BTP Hyder were used for the temporary experimental shared-use cycle route between early July and late September 2007 along the Broad Walk from Chester Road north to its junction with Outer Circle A benefit of an un-segregated scheme, illustrated in the cross section below, is that shared space may promote lower cycle speeds particularly during congested periods. The visual impact of the 14

15 scheme is minimal for the majority of the route. The scheme, as temporarily implemented, will be familiar to users and be in essence more cost effective to develop permanently. Cross section of Broad Walk un-segregated route The disadvantages of providing an un-segregated scheme are: The possibility of collisions is increased with a shared surface scheme Some pedestrians register an increase feeling of vulnerability Pedestrians that are vulnerable or disabled may feel disadvantaged as the onus is on the cyclist to behave safely and appropriately. Separate route parallel to Broad Walk A separate cycle track running parallel to the existing Broad Walk would have the advantage of removing any potential conflict by mode over spill into the other lane. Cross section of separate route parallel to Broad Walk 15

16 The disadvantages of providing this form of scheme are: Dedicated use may promote higher speeds similar to segregated An additional route may result in a loss of green space and close proximity to foliage may cause damage Interaction with other footpaths crossing the route will entail additional signage To ensure conflict potential is mitigated detail of the commencement at Chester Road and the Outer Circle will need to be carefully considered to ensure limited conflict potential, or possibly the creation of new access points separate from the pedestrian access points Envisaged level of service A rudimentary level of service (los) assessment on the capacity of the path has been conducted. This assessment appraises width of the path and current level of use to determine whether sufficient space exists for the safe use of the Broad Walk as a shared route for pedestrians and cyclists. The criteria for this is based on information given in the Highway Capacity Manual (HCM) to provide a qualitative measure to describe the operational conditions of pedestrian and cycle traffic, mainly in an urban context. However the use of the HCM to analyse cycle level of service is limited to the analysis of two lane and three lane paths. These path widths are less than the effective width of the Broad Walk. Therefore the level of service has been produced from a pedestrian point of view As pedestrians often travel together as a group, voluntarily or involuntarily, due to geometrics, movement management such as signal control or other factors platooning can occur. Lower levels of service rates are therefore applied on facilities where platooning is expected. Definition Level of service A allows pedestrians to move in desired paths without altering there movements in response to other pedestrians. Walk speed is freely selected and conflict between pedestrians is unlikely Level of service B provides sufficient area for pedestrians to select walking speeds freely to bypass other pedestrians and avoid crossing conflicts. At this level pedestrians begin to be aware of other pedestrians and respond to their presence when choosing a walk path. 16

17 2.3.5 With level of service C space is sufficient for normal walk speed and for bypassing other pedestrians in predominantly unidirectional streams. Reverse direction or crossing movements can cause minor conflict Level of service D restricts the freedom to select individual walk speed and bypass other pedestrians. Crossing or reverse flow movements face a greater probability of conflict, requiring frequent changes in speed and location At level of service E virtually all pedestrians will restrict their normal walk speed. Space is not sufficient for passing slower pedestrians. Cross and reverse flow is possible with extreme difficulty and design volumes approach the limit of walkway capacity with interruptions and stoppages to flow With level of service F all walk speeds are severely restricted and forward progress is made by shuffling. There is frequent unavoidable contact with other pedestrians. Cross and reverse flow is virtually impossible. Flow is sporadic and unstable. Space is more characteristic of queuing pedestrians than moving pedestrian streams The flows used to calculate the capacity of the path have been obtained using the peak 15 minute segment two way flow from pedestrian / cycle movement survey information collected in August The peak period has been identified from the Broad Walk / Chester Road survey location on Sunday 26 th August The two way flows encountered at the Broad Walk / Chester Road are summarised in the chart below. The difference between the extent of pedestrian usage and cycle usage is apparent. The Broad Walk received a much greater patronage by pedestrians than cyclists. 17

18 Number of Users Way pedestrian 2 Way bicycle 0 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:30 16:00 16:30 17:00 17:30 Time Comparison of The Regent's Park Broad Walk usage The profile of cyclists using the Broad Walk is indicated in the chart below. Cycle usage along Broad Walk Number of users :00 10:45 11:30 12:15 13:00 13:45 Time 14:30 15:15 16:00 16:45 17:30 2 w ay cycle flow The peak 15 minute period (15: hrs) two way pedestrian flows are 526. The corresponding cycle two way flow is 14. Therefore there are 35 pedestrians and one cycle per minute entering the Broad Walk The width of Broad Walk varies from 10.2m -12m. The width of 10.2m has been used for the level of service calculation as it provides a worse case scenario. The effective width of the Broad Walk is the portion of pathway remaining after subtracting obstacle widths and shy distances that people use as a buffer to avoid obstacles Generally benches are staggered opposite each other, however for the purposes of simplicity and to continue the representation of a worse case scenario it is assumed that the width of the benches, at one metre, will run the length of each side of the Broad Walk. A shy distance of 0.3m has been added to the bench zones to provide for people to avoid obstacles. 18

19 The width used to represent two cycles passing each other has been taken as 2.5m. This is made up of a dynamic width of one metre for each cyclist and a separation width of 0.5m to allow cycles to pass in opposing directions The effective width of the Broad Walk for pedestrians to use is 5.1 metres. The resultant flow rate is seven people per minute per metre based on the division of pedestrians per minute by the effective width for pedestrians to use. Level of Service (LOS) Flow Rate (p/min/m) A <16 B >16-23 C >23-33 D >33-49 E >49-75 F varies Table 1 Pedestrian Level of Service Criteria based on flow rate The effect of platooning on the flow rate affects the level of service score attributed to it. Platooning is deemed to take place as a result of factors such as tourist and school groups using the Park. The adjusted flow rate criteria is summarised in Table 2 below. Level of Service (LOS) Flow Rate (p/min/m) A <1.6 B > C >10-20 D >20-36 E >36-59 F >59 Table 2 Platoon adjusted Pedestrian Level of Service Criteria based on flow rate Using the platoon adjusted level of service criteria the Broad Walk provides pedestrians with a level of service B. Therefore permitting cyclists to use the Broad Walk still provides sufficient area for pedestrians to select walking speeds freely to bypass other pedestrians and avoid crossing conflicts It is important to note that the calculated flow rate, based on the August 2007 survey, is less than that envisaged during an event. Unfortunately no events were taking place during the survey period which restricted the ability to obtain sufficient data to account for the expected uplift in pedestrian flow Another important factor to consider on measuring shared-use level of service is hindrance. Hindrance reflects the degree to which a user is restricted from the freedom to manoeuvre. This occurs when a cyclist passes a slower cyclist, a pedestrian or when he or she meets a pedestrian or cyclist travelling in the opposite direction Research has been conducted to try and understand the relationship hindrance has on the pedestrian level of service. John Fruin(1971) found that when neither opposing flow dominates then walk speed in either direction tends to be equal. However a stronger flow will impede a 19

20 weaker flow. The standard level of service calculation does not take into account that a highly lopsided bi-directional flow may result in a lower level of service for the flow in the weaker direction, so the single level of service is calculated for the whole facility based on the sum of pedestrians walking in both directions Additional factors that influence the suitability of a path for shared-use are gradient, crossfall, bounding, surface and sightlines. The Broad Walk does not suffer from any particularly adverse conditions relating to these additional factors. The gradient is very gentle, as is the crossfall. The Broad Walk is bound predominantly by grass verge, with shrubs and fencing at the entrances to the Park and various points along the path, notably at the London Zoo. Due to the straight alignment of the Broad Walk the route is considered very good with visibility at footpath intersections also very favourable. The surface is tarmac which is patchy in places. Level of service summary In summary, using the demand profile created from the Sunday 26 th August 2007 survey, the level of service attainable along the Broad Walk is seen to be comparable to level of service B. This permits cyclists to use the Broad Walk whilst providing sufficient area for pedestrians to select walking speeds freely to bypass other pedestrians and avoid crossing conflicts Although there is no data available to calculate an event flow, a sensitivity test whereby the pedestrian flow has a growth factor of two and three times have been undertaken. If the two way demand flow of pedestrians is increased to circa 1000 pedestrians per 15 minute period the resultant platoon adjusted level of service will be graded as C. A further increase in pedestrian flow to circa 1500 per 15 minute period would result in a level of service grade of borderline C /D As the pedestrian demand grows the space available to cycles will decrease to the point that cycling along the Broad Walk is too restrictive. Therefore the assessment shows that generally and for the majority of the time the Boardwalk is open, there would be limited conflict and the level of pedestrian and cycle movements could be accommodated as a shared provision. The assessment does however concluded that on major event days, when the pedestrian levels can reach very high concentrations, that cycling is unlikely to be viable, but these high levels are limited to specific events and times and as such for the majority of the time a shared cycle/pedestrian route along the Boardwalk is viable Stage 1 and 2 Safety Audit An independent safety audit was undertaken on the temporary shared-use cycle route designed by BTP Hyder. This was undertaken in December 2007, after the trial route had been terminated. This involved a review of the plans for the un-segregated route, site photographs and a site visit. The Safety Audit Report is located in Appendix A of this report The comments / issues raised in the report are: Inherent risk Speed limit Clarity of signage Intersections with other paths The inherent risk relates to the introduction of cycling onto the Broad Walk. It is stated that this will increase the risk of collision which is accepted, however the audit team consider there to be a reduced risk of accident compared with cycling on the carriageway. 20

21 2.4.4 The audit team state that the five miles per hour speed limit in operation during the trial shared cycle route was very low, and suggest that it would be quicker to make the journey on carriageway at normal speeds. Although the proposed shared cycle route is not designed principally as a commuter route it is felt that the five mph speed limit is too low. TA 90/05 refers to a shared-use pedestrian / cycle design speed of 30kph (18mph) with different authorities using a range of design speeds, from 10kph to 50kph It is understood that the optimum cycle design speed The Royal Parks would like to achieve is eight miles per hour therefore a five miles per hour speed limit was applied so that the greater majority of cyclists that exceeded this low speed limit would still be within the desired eight miles per hour It is noted by the audit team that clarity of signage is a problem and recommend that additional signage to diag. 951 of the Traffic Signs Regulations and General Directions 2002 and to diag. 956 may be used to reinforce the areas of prohibited cycling and shared-use route respectively. Diag 951 Diag The audit team note that there is insufficient notification of a potential hazard for blind and visually impaired pedestrians on the approach to intersections of the Broad Walk with footpaths. It is recommended that corduroy paving be used at the junctions with footpaths Speed Assessment A rudimentary evaluation of the time it could take to use the Broad Walk or the Outer Circle for cycling has been undertaken to gauge how attractive the route would be to bicycle commuters. The timing points are illustrated on the sketch below 21

22 2.5.2 The red route along the Outer Circle is 1080m in length and the green route along The Broad Walk / Chester Road is 1135m in length. The timing calculations do not take into account delay caused by entering / exiting the proposed cycle route along Broad Walk, delay on approach to intersections and delay to Outer Circle cyclists from the signalised pedestrian crossing at Gloucester Gate It is felt that a design speed of 30kph may be too high in the context of the Park usage so a cycle route design speed of 10mph, in line with London Cycling Design Standards, is recommended Using a design speed of 15mph (24kph) for the on carriageway cycling and 10mph (16kph) for the Broad Walk, the red route is completed in approximately 2mins 40sec and the green route will be completed in 4mins. It is envisaged the Outer Circle will be more attractive to commuter cyclists whose primary concern is to get from origin to destination in the shortest time will continue to cycle around the Outer Circle It is felt that a design speed of 30kph may be too high in the context of the Park usage so a cycle route design speed of 10mph, in line with London Cycling Design Standards, is recommended Using a design speed of 15mph (24kph) for the on carriageway cycling and 10mph (16kph) for the Broad Walk. The red route is completed in approximately 2mins 40sec and the green route will be completed in 4mins. It is envisaged the Outer Circle will be more attractive to commuter cyclists whose primary concern is to get from origin to destination in the shortest time will continue to cycle around the Outer Circle Although cycling through the Broad Walk will be slower it is anticipated that this route will appeal to those who regard the route and surroundings to be of greater importance than the speed to traverse it. Cycling off carriageway would feel safer than using the Outer Circle as there is significantly less conflict potential with vehicles Recommended Route Following favourable responses to cycling within the Park, and the options considered above it is proposed to provide the un-segregated scheme on a longer term basis, albeit with alterations to the entry points and inclusion of remedy measures in light of the Stage 1 & 2 Safety Audit It is envisaged that the Broad Walk scheme would be implemented in two sections, section one from Chester Road to the Readymoney fountain and section two from the Readymoney fountain to the Outer Circle The amended proposals for the Broad Walk scheme are illustrated on PBA drawing Figure / 3 Rev A and entail the provision of entry gateways at The Outer Circle and Chester Road, revised treatments of the intersections with footpaths and a speed limit of 10mph for cycles. All proposals are subject to detailed design There are two options of gateway for consideration. These are: A pinch point A central feature The pinch point could be developed using ornamental gates that are locked in place during days of reduced demand and opened up during event times when demand is at its greatest. In its closed state there would still be enough room for access by service and emergency vehicles. It 22

23 would be intended that cyclists would slow down on the approach to this feature as there would be less freedom to manoeuvre. The route would effectively end at this point, requiring the cyclist to dismount and join the foot traffic approaching the crossing at Chester Road. The location of the pinch point is governed by the location of the coffee shop and the requirements to ensure large vehicles entering the Park do not impact on the Chester Road footpaths The provision of a central feature could take the form of public art or information point, possibly removable, that people would have to negotiate around. This theme fits in with the Readymoney fountain in the Park. The feature would define the start / finish of the shared-use cycle route with road marking and granite setts laid across the path In response to the Stage 1 & 2 Safety Audit it is proposed to draw attention to the shared-use route at footpath intersections by putting up formal signs. It is envisaged that the signs would be sized and mounted on a bollard or wooden post as indicated on Figure / 3 Rev A With regard to the recommendation for the introduction of corduroy paving at the intersections the principle has been upheld. Corduroy paving material is not considered suitable in the listed landscape context of The Royal Parks so an alternative material of granite setts is proposed and has been incorporated into the design, indicated on Figure / 3 Rev A It is felt that a design speed of 30kph may be too high in the context of the Park usage so a cycle route design speed of 10mph, in line with London Cycling Design Standards, is recommended subject to The Royal Parks approval. Figure / 3 Rev A indicates the location of proposed 10mph roundels at the entrance to the shared cycle route Potential Route Extension Avenue Gardens Correspondence received during the consultation process has questioned the feasibility of extending the cycle route into Avenue Gardens. It is felt that the two areas are separate not just in terms of Chester Road severance but in character. Whereas the Broad Walk route through the Park is less formal and regimented, the ambience of the Avenue Gardens is not considered to reflect the same leisure provision in the Park The formal enclosed structure of the Avenue Gardens with numerous beds containing a wide variety of unusual plants, trees and shrubs. It is designed for people to congregate and reflect rather than provide for movement. This is in contrast to the Broad Walk with panoramic views rather than attractions at the forefront, therefore promoting movement. 23

24 2.7.3 Providing an additional route through the gardens will encourage the route as primarily a cut through direct route instead of the leisure route the Royal Parks team is aiming to achieve It is considered to not promote the cycle route through the Avenue Gardens. Marylebone Green or English Gardens An alternative route to extend the Broad Walk shared-use cycle path south without using the formal Avenue Gardens is to use Marylebone Green or a path through English Gardens. These are illustrated in the schematic diagram at the beginning of this section Both routes would retain the parkland feel to the route although connection between the routes and the Broad Walk would require a dog leg on carriageway along Chester Road. The possibility of an extension of the route was not considered within the original scope of the assessment into providing a permanent shared-use cycle scheme along the Broad Walk as it was understood that the provision of cycling within the green space of The Regent s Park would be centred on the Broad Walk as the primary route. However a desktop assessment of each route has been conducted and the findings are presented below. Marylebone Green There are two distinct routes that a shared-use path could take through the Marylebone Green. One path runs from Chester Road and emerges onto the Outer Circle at Park Square West. It runs parallel to the Avenue Gardens Broad Walk approximately 90 metres to the west. The other pathway deviates from the Chester Road access and curves around the tennis courts before emerging at York Bridge. The benefit of incorporating the curved route into the scheme is that it would provide an easily accessible link to the LCN+50 cycle route The width of the Marylebone Green paths satisfy the London Cycle Design Standard for a shared path, however it is unclear what level of service would be attributable to the paths without an evaluation of path usage. It is unknown what level of pedestrian traffic these paths carry so intensification of use by introducing cycles may require path widening in order to accommodate the uplift in traffic safely and comfortably The potential to connect with the LCN+50 would make the curved route the favourable path in Marylebone Green to incorporate into the Broad Walk shared-use cycle route scheme. This could be incorporated in a staged process if funds are not available to complete together. It is envisaged that the Broad Walk would be completed as phase one and Marylebone Green completed as phase two. English Gardens A north / south path running through English Gardens had been identified as a possible extension to a permanent shared cycle route along the Broad Walk. This would run from the access at Chester Road south to the junction of the Outer Circle with Park Square East The path is over four metres wide in places and is compliant with the width requirements for a shared-use path in the London Cycle Design Standard. Again the level of pedestrian traffic these paths carry is unknown so intensification of use by introducing cycles may require path widening in order to accommodate the uplift in traffic safely and comfortably A signage strategy to inform northbound cyclists that the route continues along the Broad Walk and not straight across into Cumberland Green would need to be in place. 24

25 A route through the English Gardens would be more difficult to define from the southern entrance and could encourage the use of Avenue Gardens. Access from the corner of the junction is poor Alternative Routes Although the proposal of a shared-use cycle route along the Broad Walk has been identified as the most favourable, alternative provision for allowing cycles into the park have been considered. However consultations with The Royal Parks have indicated that the scope to permit alternative routes within the park for future consideration is limited to providing a link to The Hub The Hub is a community sports pavilion serving field sports pitches within the Park. Currently access to The Hub is achieved using footpaths within the Park. There are no dedicated cycle paths to the pavilion. An additional route, using the existing footway to this building from Monkey Gate would be proposed for cycles to access The Hub and its cycle parking. This would entail the upgrade of the path width to comfortably accommodate pedestrians and cycles It is envisaged that, prior to implementation, this alternative route would need to follow a similar public consultation exercise and surveys as undertaken for the Broad Walk Summary of Section One Information provided by BTP Hyder in their report A cycling strategy for The Regent s Park in association with further analysis by PBA into the options to provide cycling within The Regent s Park indicate that the provision of cycling within the Park is feasible This is supported by a favourable response from people who took part in the questionnaire survey undertaken during the trial shared cycle route along the Broad Walk The preferred scheme is to provide the un-segregated shared cycle route along the Broad Walk A level of service assessment has been undertaken on the Broad Walk as an un-segregated shared-use cycle route. Using available survey information the Broad Walk would be able to accommodate a shared-use cycle route comfortably. Naturally the level of service to pedestrians will diminish as usage demand increases on the Broad Walk culminating in event traffic A rudimentary speed assessment of the proposed Broad Walk shared-use route illustrates that using the Outer Circle is quicker; however this serves to reinforce the Broad Walk as leisure route The Stage One and Two Safety Audit have not identified issues with the scheme that cannot be overcome during the detailed design element of the project. The design speed is recommended to increase from 5mph in the trial scheme to 10mph in the permanent scheme in line with London Cycle Design Standards There is merit in extending the cycle route into Marylebone Green providing the opportunity to link with the LCN+50 route at York Gate. This could be incorporated into a future phase of the project, however this would not provide the direct north/south route that has been requested by cyclists Although the Broad Walk is seen as the principal method of allowing cycling within the green space of The Regent s Park, within current budgetary constraints, a secondary option exists that 25

26 would serve the Hub. It is recommended that further analysis be undertaken on the feasibility of this route if the Broad Walk is not successful The Broad Walk scheme is to be implemented for a trial period of 18 months, following major refurbishment works of the current surface, following which additional surveys and observations will be undertaken to provide a more detailed understanding of the facility across the year. 26

27 3. Section Two - The Regent s Park on-carriageway 3.1. Introduction This section of the report discusses factors to do with cycling in The Regent s Park outside of the green space, predominantly on carriageway around the Outer Circle The factors are grouped thus: 20mph speed limit on roads within The Park The Outer Circle cycle infrastructure improvements mph speed limit Irrespective of the type of cycle route form along the Broad Walk, a raised zebra crossing is proposed at Chester Road. The existing crossing configuration is indicated in the photograph below. A raised crossing at this location would also be integrated into a possible future 20mph scheme on carriageways within The Regent s Park The management of speed is a key element to the UK s approach to road safety to reduce the risk of death or injury. One of the principle mechanisms available is the greater use of 20mph zones. New design guidelines such as Manual for Streets endorse designing to keep vehicle speeds at or below 20mph on residential streets unless there are overriding reasons for accepting higher speeds. 27

28 3.2.3 The THINK! Road Safety statistics indicate that: Pedestrians hit by a vehicle at 20mph have a 95% chance of survival Pedestrians hit by a vehicle at 30mph have a 80% chance of survival Pedestrians hit by a vehicle at 40mph have a 10% chance of survival (20% in the case of children) Information provided by the Parliamentary Advisory Council for Transport Safety (PACTS) in their recently published report Beyond 2010-a holistic approach to road safety in Great Britain indicate that a reduction in speed limit has a positive effect on casualty levels. In a TRL review of 250 schemes across the UK: Average speeds fell by 9mph Accidents fell by 60% a year Child accidents fell by 67% Cyclist accidents fell by 29% Traffic flow was reduced by 27% Flows on boundary roads increased by 12% The PACTS report recommends that a default speed limit of 20mph in all built up areas is implemented in ways that achieve high levels of compliance The report concedes that a significant impediment to lowering speed limits and expanding the 20mph network is that, currently, standard cameras are not an approved method to enforce limits below 30mph. Physical measures are therefore used such as traffic humps and chicanes. Traffic calming of this type, although effective, can be unpopular, expensive and cause inconvenience to service and emergency vehicles and may not be deemed suitable to use in a visually sensitive historic landscape such as the outer circle There are aspirations by some stakeholders to reduce the speed limit within the parks. The provision of this facility can be arranged in two categories: - The Outer Circle and The Inner Circle. TRP is keeping speed limits in the Royal Parks under review Many local authorities and TfL in particular are keen to explore the possibility of using time over distance cameras. TfL have been operating a trial site with zero casualties since introduction. In order for these cameras to be used in prosecutions the equipment will need to be type approved by the Home Office, an important but lengthy process. It is noted in the PACTS report that early type approval of time over distance cameras be a precursor to a wider roll out of 20mph zones It is understood that horizontal and vertical deflection measures along the proposed 20mph route are not considered feasible by the Royal Parks team, however it is proposed to replace the existing zebra crossing at Chester Road with a raised zebra crossing to reinforce this sensitive area and regulate speeds along this straight stretch of road. 28

Development Layout Design

Development Layout Design Development Layout Design General Design Considerations for Adoptable Highways Version 1 June 2012 Transportation, Waste and Environment Service Issue and Revisions Record Revision Date Originator Purpose

More information

Segregation of Shared Use Routes

Segregation of Shared Use Routes Segregation of Shared Use Routes Technical Information Note No. 19 April 2014 About Sustrans Sustrans makes smarter travel choices possible, desirable and inevitable. We re a leading UK charity enabling

More information

Construction Traffic Management Plan

Construction Traffic Management Plan Introduction This (CTMP) has been prepared in order to discharge Condition 20 of planning permission ref 07/02879/EFUL for the enabling site works associated with the wider Bath Western Riverside development.

More information

6 Streetscape character 6.1

6 Streetscape character 6.1 6 6.1 6 Streetscape character Introduction Transport interchanges The TLRN is the strategic road network for London and varies in character across the capital. The variation of the land use across London

More information

Cathkin Relief Road Planning Statement

Cathkin Relief Road Planning Statement Cathkin Relief Road Planning Statement The Proposal This statement sets out the background to the Cathkin Relief Road project currently being progressed by South Lanarkshire Council. The project will provide

More information

VEHICLE CROSSOVER INFORMATION PACK

VEHICLE CROSSOVER INFORMATION PACK VEHICLE CROSSOVER INFORMATION PACK CONTENTS Introduction Section A Section B Section C Section D Section E Criteria for approving a vehicle crossover application (Diagrams to demonstrate measurement criteria)

More information

In an age where life is increasingly fast-paced, and every day stresses can wear us down, it s important to find the time to slow down.

In an age where life is increasingly fast-paced, and every day stresses can wear us down, it s important to find the time to slow down. Sharing Towpaths A consultation on towpath use for the Canal & River Trust The Canal & River Trust is consulting with stakeholders, local authorities, communities and partners in order to put together

More information

PEDESTRIAN PLANNING AND DESIGN MARK BRUSSEL

PEDESTRIAN PLANNING AND DESIGN MARK BRUSSEL PEDESTRIAN PLANNING AND DESIGN MARK BRUSSEL CONTENT OF LECTURE a) Walking as a transport mode b) Walking in Sub Sahara Africa c) Policies for pedestrians d) Pedestrian characteristics e) Network planning

More information

A23 CHEQUERS ROUNDABOUT, HORLEY: PREDESTRIAN AND CYCLING CROSSING IMPROVEMENTS

A23 CHEQUERS ROUNDABOUT, HORLEY: PREDESTRIAN AND CYCLING CROSSING IMPROVEMENTS s A23 CHEQUERS ROUNDABOUT, HORLEY: PREDESTRIAN AND CYCLING CROSSING IMPROVEMENTS SURREY COUNTY COUNCIL S LOCAL COMMITTEE FOR REIGATE AND BANSTEAD 12 JANUARY 2004 KEY ISSUE To consider the conclusions of

More information

1. REPORT CONTEXT Description of the development (include all of the following that are known at the time of the application):

1. REPORT CONTEXT Description of the development (include all of the following that are known at the time of the application): Transportation Assessment and Management Study Guidelines for Consultants INTRODUCTION This document is intended to provide guidelines for transportation consultants who produce Transportation reports

More information

May 2015. The Right Direction. The Mayor s Strategy for improving transport safety, security and reliability in London 2015-2017 Executive Summary

May 2015. The Right Direction. The Mayor s Strategy for improving transport safety, security and reliability in London 2015-2017 Executive Summary May 2015 The Right Direction The Mayor s Strategy for improving transport safety, security and reliability in London 2015-2017 Executive Summary Greater London Authority May 2015 Published by Greater London

More information

Goals & Objectives. Chapter 9. Transportation

Goals & Objectives. Chapter 9. Transportation Goals & Objectives Chapter 9 Transportation Transportation MISSION STATEMENT: TO PROVIDE A TRANSPORTATION NETWORK CAPABLE OF MOVING PEOPLE AND GOODS EFFICIENTLY AND SAFELY. T he transportation system

More information

Delineation. Section 4 Longitudinal markings

Delineation. Section 4 Longitudinal markings Delineation Section 4 Longitudinal markings The delineation guidelines have been developed to assist in designing and maintaining a quality delineation system. The guidelines are to comprise 19 sections

More information

Vehicular Access Standards

Vehicular Access Standards Development Control Advice Note 15 (2nd Edition) Vehicular Access Standards August 1999 Development Control Advice Note 15 Vehicular Access Standards This is a joint Planning and Roads Service Development

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12

CONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12 If the project you are constructing was subject to planning permission and a condition requiring a Construction Traffic Management Plan (CTMP) was applied to the planning consent, this condition will need

More information

Engineering Standard

Engineering Standard Public Transport Services Engineering Standard Stations - Bicycle Facilities PART 129013 AR-PW-PM-SPE-00129013 (D073) Document Control Document Status Document Amendment Record Revision Change Description

More information

Technical note. 1. Background. 2. Document Purpose. Project: A350 Chippenham Dualling

Technical note. 1. Background. 2. Document Purpose. Project: A350 Chippenham Dualling Project: A350 Chippenham Dualling Subject: Benefits Realisation Plan & Monitoring and Evaluation Plan Date: 14 February 2013 1. Background Restrictions to the capacity of the A350 to the north of Chippenham

More information

DESIGN MANUAL FOR ROADS AND BRIDGES

DESIGN MANUAL FOR ROADS AND BRIDGES DESIGN MANUAL FOR ROADS AND BRIDGES VOLUME 11 SECTION 3 PART 8 PEDESTRIANS, CYCLISTS, EQUESTRIANS AND COMMUNITY EFFECTS CONTENTS 1. Introduction 2. Journey Length, Local Travel Patterns 3. Predicting Changes

More information

COPCUT RISE COPCUT RISE DROITWICH SPA CONSULTATION STATEMENT. November 2010. Prepared by Capita Lovejoy on behalf of William Davis Limited

COPCUT RISE COPCUT RISE DROITWICH SPA CONSULTATION STATEMENT. November 2010. Prepared by Capita Lovejoy on behalf of William Davis Limited COPCUT RISE DROITWICH SPA CONSULTATION STATEMENT COPCUT RISE November 2010 Prepared by Capita Lovejoy on behalf of William Davis Limited Copcut Rise Land north of Copcut Lane, Droitwich Spa: Consultation

More information

Site Layout & Traffic Plan

Site Layout & Traffic Plan Location Site address: Norbury Manor Business Enterprise College, Kensington Avenue, Thornton Heath, Croydon CR7 8BT. The new block will be constructed on the existing hard play area. The construction

More information

CONSULTATION REPORT REGARDING THE REPLACEMENT OF INVERURIE MARKET PLACE SCHOOL

CONSULTATION REPORT REGARDING THE REPLACEMENT OF INVERURIE MARKET PLACE SCHOOL Appendix 1 EDUCATION & CHILDREN S SERVICES CONSULTATION REPORT REGARDING THE REPLACEMENT OF INVERURIE MARKET PLACE SCHOOL NOVEMBER 2015 This Consultation Report has been issued by Education & Children

More information

Lawson Outline Plan External Traffic Analysis Working Paper

Lawson Outline Plan External Traffic Analysis Working Paper Total Lawson Development ACTPLA 16 January 2009 Document No.: Prepared for ACTPLA Prepared by Maunsell Australia Pty Ltd Level 2, 60 Marcus Clarke Street, Canberra ACT 2600, Australia T +61 2 6201 3000

More information

Major Improvement Schemes in Basingstoke

Major Improvement Schemes in Basingstoke Major Improvement Schemes in Basingstoke 1. Welcome Welcome to this exhibition, which provides information about the planned highway improvements being delivered in Basingstoke from 2015 2018. A30 Winchester

More information

Advantages and Disadvantages of One Way Streets October 30, 2007

Advantages and Disadvantages of One Way Streets October 30, 2007 Advantages and Disadvantages of One Way Streets October 30, 2007 0 P age Background As the revitalization of the Central Waterfront area moves forward, one issue that might need closer analysis is the

More information

AGENDA ITEM: 15 PROPOSED ZEBRA CROSSINGS AT VARIOUS LOCATIONS. Executive Director of Development & Environment

AGENDA ITEM: 15 PROPOSED ZEBRA CROSSINGS AT VARIOUS LOCATIONS. Executive Director of Development & Environment Croydon Council REPORT TO: TRAFFIC MANAGEMENT ADVISORY COMMITTEE 21 July 2014 AGENDA ITEM: 15 SUBJECT: LEAD OFFICER: CABINET MEMBER: PROPOSED ZEBRA CROSSINGS AT VARIOUS LOCATIONS Executive Director of

More information

METHODS FOR ESTABLISHING SAFE SPEEDS ON CURVES

METHODS FOR ESTABLISHING SAFE SPEEDS ON CURVES Page 1 of 4 PRACTICES PART SECTION SUB-SECTION TRAFFIC OPERATIONS General Collision exposure is usually greater along horizontal curves than along tangent sections of a highway. The potential for collisions

More information

Speed Limit Policy Isle of Wight Council

Speed Limit Policy Isle of Wight Council APPENDIX C - 59 Speed Limit Policy Isle of Wight Council June 2009 Contents Section 1 Introduction 1.1 Links with the Local Transport Plan Section 2 Speed Limits on Urban Roads and Residential Areas 2.1

More information

Review of 20 mph zones in London Boroughs. by D C Webster and R E Layfield. Published Project Report PPR243

Review of 20 mph zones in London Boroughs. by D C Webster and R E Layfield. Published Project Report PPR243 Review of 20 mph zones in London Boroughs by D C Webster and R E Layfield Published Project Report PPR243 Review of 20 mph zones in London Boroughs by D C Webster and R E Layfield PUBLISHED PROJECT REPORT

More information

Design and Implementation of Slot Left-Turn Lanes on the Manitoba Highway Network

Design and Implementation of Slot Left-Turn Lanes on the Manitoba Highway Network Design and Implementation of Slot Left-Turn Lanes on the Manitoba Highway Network Brent Hartmann, P. Eng., Project Design Engineer, Manitoba Infrastructure and Transportation Derek Durant, P. Eng., Senior

More information

Why build the Silvertown Tunnel?

Why build the Silvertown Tunnel? Why build the Silvertown Tunnel? Over the last 30 years east London has changed with the redevelopment of former industrial areas into major commercial and residential districts. The development of Canary

More information

Economy, Transport and Environment Department. Traffic Management Policy & Guidance

Economy, Transport and Environment Department. Traffic Management Policy & Guidance Economy, Transport and Environment Department Traffic Management Policy & Guidance January 2014 Contents Part 1- Introduction to Traffic Management Traffic Management Strategy Legislation and the Legal

More information

Environment Committee 11 January 2016

Environment Committee 11 January 2016 Environment Committee 11 January 2016 Title Whole Life Costing of Footway Maintenance Treatments and Scheme Prioritisation Report of Wards Status Urgent Key Enclosures Commissioning Director, Environment

More information

VISION, DESIGN PRINCIPLES & OVERALL PLANNING STRATEGY

VISION, DESIGN PRINCIPLES & OVERALL PLANNING STRATEGY 3 VISION, DESIGN PRINCIPLES & OVERALL PLANNING STRATEGY The overall planning strategy for the Bank Street CDP is to ensure that future development is undertaken in a coordinated and planned approach, supported

More information

WELCOME PROPOSALS FOR PENTAVIA RETAIL PARK WELCOME TO OUR EXHIBITION WHICH SETS OUT OUR PLANS TO DEVELOP THE PENTAVIA RETAIL PARK SITE.

WELCOME PROPOSALS FOR PENTAVIA RETAIL PARK WELCOME TO OUR EXHIBITION WHICH SETS OUT OUR PLANS TO DEVELOP THE PENTAVIA RETAIL PARK SITE. WELCOME WELCOME TO OUR EXHIBITION WHICH SETS OUT OUR PLANS TO DEVELOP THE PENTAVIA RETAIL PARK SITE. The purpose of the exhibition is to provide the community with the opportunity to view our initial ideas

More information

Maximum speed. Stop and Give way to Manually operated temporary No entry for give way traffic on STOP and GO signs vehicular traffic major road

Maximum speed. Stop and Give way to Manually operated temporary No entry for give way traffic on STOP and GO signs vehicular traffic major road Signs giving orders Signs with red circles are mostly prohibitive. Plates below signs qualify their message. Entry to 20 mph zone End of 20 mph zone Maximum speed National speed limit applies School crossing

More information

TRAFFIC POLICY NOTE DTP 34/05 LOCAL SPEED LIMITS. Policy. Preamble. Devon Local Transport Plan Objectives. Revisions

TRAFFIC POLICY NOTE DTP 34/05 LOCAL SPEED LIMITS. Policy. Preamble. Devon Local Transport Plan Objectives. Revisions TRAFFIC POLICY NOTE LOCAL SPEED LIMITS DTP 34/05 Policy To work in partnership with local communities and in consultation with the police to: Provide 30 mph speed limits in communities Provide 20mph speed

More information

GENERAL GUIDE FOR WORKPLACE TRAFFIC MANAGEMENT

GENERAL GUIDE FOR WORKPLACE TRAFFIC MANAGEMENT 1 This General Guide provides information on how to manage traffic risks at a workplace. It is supported by specific guidance material on traffic management for shopping centres, construction workplaces,

More information

SCHEDULE 16 TO THE SPECIAL USE ZONE. Shown on the planning scheme map as SUZ16. BALLARAT RAILWAY STATION PRECINCT. Purpose

SCHEDULE 16 TO THE SPECIAL USE ZONE. Shown on the planning scheme map as SUZ16. BALLARAT RAILWAY STATION PRECINCT. Purpose SCHEDULE 16 TO THE SPECIAL USE ZONE Shown on the planning scheme map as SUZ16. BALLARAT RAILWAY STATION PRECINCT Purpose To facilitate the revitalisation of the Ballarat Station Precinct in accordance

More information

Evaluation of the Shared-Use Arrow

Evaluation of the Shared-Use Arrow Evaluation of the Shared-Use Arrow Table of Contents Page Evaluation of the Shared-Use ARROW Background... 1 ARROW Design... 1 ARROW Placement... 2 Wayne E. Pein William W. Hunter J. Richard Stewart Report

More information

3 Tappan Zee Bridge Rehabilitation Options

3 Tappan Zee Bridge Rehabilitation Options 3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:

More information

Stage 2 A660 Otley Rd Cycling Study

Stage 2 A660 Otley Rd Cycling Study Stage 2 A660 Otley Rd Cycling Study Cycle Audit Final Report October 2008 Page 1 of 19 Contents Page 1.0 Introduction 4 2.0 The Benefits of Increasing Cycling 4 3.0 Methodology 5 3.0 Background - Site

More information

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention

More information

OVERVIEW PROJECT SUMMARY

OVERVIEW PROJECT SUMMARY OVERVIEW Cesar Chavez showcases how to successfully redesign a primary arterial route into a neighborhood destination, improving modal share, water sensitive design, biodiversity and safety whilst maintaining

More information

Construction Traffic Management Plan

Construction Traffic Management Plan Construction Traffic Management Plan Proposed Additional Classroom Accommodation for Woolacombe Primary School Produced for and on behalf of Built Environments Team Devon County Council NPS South West

More information

MCH 1352 Issue D February 2002

MCH 1352 Issue D February 2002 Traffic Systems and Signing MCH 1352 Issue D February 2002 Crown Copyright 2002 Applications to reproduce this material should be made to The Controller of Her Majesty's Stationery Office First published

More information

INTERIM ADVICE NOTE 179/14

INTERIM ADVICE NOTE 179/14 INTERIM ADVICE NOTE 179/14 Guidance on the Use of Vehicle Mounted High Level to provide advance warning of lane closures for Relaxation Works on Dual Carriageways with a Hard Shoulder Summary Guidance

More information

ROAD SAFETY GUIDELINES FOR TAH ROAD INFRASTRUCTURE SAFETY MANAGEMENT

ROAD SAFETY GUIDELINES FOR TAH ROAD INFRASTRUCTURE SAFETY MANAGEMENT I. GENERAL ROAD SAFETY GUIDELINES FOR TAH ROAD INFRASTRUCTURE SAFETY MANAGEMENT ANNEX III B i. The setting up and implementing of appropriate management procedures is an essential tool for improving the

More information

Sustrans. The Merits of Segregated and Non-Segregated Traffic-Free Paths. A Literature-Based Review. Updated Report, August 2011

Sustrans. The Merits of Segregated and Non-Segregated Traffic-Free Paths. A Literature-Based Review. Updated Report, August 2011 Phil Jones Associates Transport Planning Consultants Sustrans The Merits of Segregated and Non-Segregated Traffic-Free Paths A Literature-Based Review Project Code 836 Phil Jones Associates Ltd The Innovation

More information

Joined-Up Cycling. Cycle Links for Horsham Town Centre

Joined-Up Cycling. Cycle Links for Horsham Town Centre Joined-Up Cycling Cycle Links for Horsham Town Centre 1 4 3 6 2 5 Proposals to improve cycle access to the town at the Albion Way/Bishopric junction and join up some of the fragmented cycle routes in the

More information

Site Assessment for Neighbourhood Plans: A toolkit for neighbourhood planners

Site Assessment for Neighbourhood Plans: A toolkit for neighbourhood planners Site Assessment for Neighbourhood Plans: A toolkit for neighbourhood planners Action the COI Table Of Contents Introduction... 3 Benefit of carrying out a site assessment... 4 How to carry out a site assessment

More information

BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project.

BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project. Smart Transportation Smart Transportation is a key concept for the Paoli Roadway Improvement Project. PennDOT s Smart Transportation Guidebook (2008) outlines a comprehensive approach to transportation

More information

TRANSPORT ASSESSMENT GUIDANCE

TRANSPORT ASSESSMENT GUIDANCE TRANSPORT ASSESSMENT GUIDANCE Contents 1 INTRODUCTION...1 Purpose of the Guidance...1 Policy Context...1 Who Should Read This Document?...2 Structure of Guidance...3 2 ASSESSMENT PRINCIPLES AND PROCESS...4

More information

DEPARTMENT OF TRANSPORT CYCLING STRATEGY 29 February 2008

DEPARTMENT OF TRANSPORT CYCLING STRATEGY 29 February 2008 DEPARTMENT OF TRANSPORT CYCLING STRATEGY 29 February 2008 INTRODUCTION The Department of Transport s Business Plan for the 2007/08 financial year stated the following: Government Aim: Quality Environment

More information

1. The consultation seeks views on the vision, targets and measures for improving road safety in Great Britain for the period beyond 2010.

1. The consultation seeks views on the vision, targets and measures for improving road safety in Great Britain for the period beyond 2010. Executive Summary 1. The consultation seeks views on the vision, targets and measures for improving road safety in Great Britain for the period beyond 2010. 2. We have made good progress in reducing road

More information

CAPACITY AND LEVEL-OF-SERVICE CONCEPTS

CAPACITY AND LEVEL-OF-SERVICE CONCEPTS CHAPTER 2 CAPACITY AND LEVEL-OF-SERVICE CONCEPTS CONTENTS I. INTRODUCTION...2-1 II. CAPACITY...2-2 III. DEMAND...2-2 IV. QUALITY AND LEVELS OF SERVICE...2-2 Service Flow Rates...2-3 Performance Measures...2-3

More information

ASSESSMENT OF LANDCAPE PROVISIONS FOR PROPOSED PLAN CHANGE 1. Inner Business Zone. Outer Business Zone PALMERSTON NORTH CITY COUNCIL

ASSESSMENT OF LANDCAPE PROVISIONS FOR PROPOSED PLAN CHANGE 1. Inner Business Zone. Outer Business Zone PALMERSTON NORTH CITY COUNCIL A division of Hudson Group Ltd ASSESSMENT OF LANDCAPE PROVISIONS FOR PROPOSED PLAN CHANGE 1 Inner Business Zone Outer Business Zone PALMERSTON NORTH CITY COUNCIL 1 2 A division of Hudson Group Ltd Prepared

More information

Siting Of Inductive Loops For Vehicle Detecting Equipments At Permanent Road Traffic Signal Installations

Siting Of Inductive Loops For Vehicle Detecting Equipments At Permanent Road Traffic Signal Installations Traffic Systems and Signing MCE 0108 Issue C March 2002 Siting Of Inductive Loops For Vehicle Detecting Equipments At Permanent Road Traffic Signal Installations Crown Copyright 2002 Applications to reproduce

More information

Note of Neighbourhood Meeting & Priorities

Note of Neighbourhood Meeting & Priorities Note of Neighbourhood Meeting & Priorities Neighbourhood Manadon with Widey Date 08/03/2012 Time (start & finish) 6pm-7.15 Venue Crownhill Library Councillors/Officials (name & title) in attendance; Chair

More information

How to implement cycling solutions in a post-communist street system (and mentality) Marcin Hyła, VeloForum, 16 Oct.

How to implement cycling solutions in a post-communist street system (and mentality) Marcin Hyła,  VeloForum, 16 Oct. How to implement cycling solutions in a post-communist street system (and mentality) Marcin Hyła, www.miastadlarowerow.pl VeloForum, 16 Oct. 2010 th What has communism to do with cycling? No free flow

More information

Temporary Traffic Management

Temporary Traffic Management Temporary Traffic Management Tom Kiddle 4 th July 2012 Temporary Traffic Management Auckland Transport TTM Operation Requirements AT TTM Audits Qualified Persons on site Pedestrian Management 1 AT Temporary

More information

Parking On-street parking Front garden parking Off-street parking

Parking On-street parking Front garden parking Off-street parking Nae place mair braw A guide to placemaking in Perth and Kinross Whan I haik't up to Craigie Hill And lookit east and west; "In a' the world," said I to mysel', "My ain shire is the best." Parking On-street

More information

Welcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site.

Welcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site. Welcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site. Background & Planning Context The Site The site is an area

More information

PART 3 TD 50/04 THE GEOMETRIC LAYOUT OF SIGNAL- CONTROLLED JUNCTIONS AND SIGNALISED ROUNDABOUTS SUMMARY

PART 3 TD 50/04 THE GEOMETRIC LAYOUT OF SIGNAL- CONTROLLED JUNCTIONS AND SIGNALISED ROUNDABOUTS SUMMARY DESIGN MANUAL FOR ROADS AND BRIDGES VOLUME 6 SECTION 2 ROAD GEOMETRY JUNCTIONS PART 3 TD 50/04 THE GEOMETRIC LAYOUT OF SIGNAL- CONTROLLED JUNCTIONS AND SIGNALISED ROUNDABOUTS SUMMARY This document sets

More information

ROTORUA ROTORUA DISTRICT COUNCIL SIGNS ON ROADS BYLAW

ROTORUA ROTORUA DISTRICT COUNCIL SIGNS ON ROADS BYLAW ROTORUA LAKES COUNCL Te kaunihera o nga roto o Rotorua ROTORUA DSTRCT COUNCL SGNS ON ROADS BYLAW 2015 Doc No: RDC-600343 ROTORUA DSTRCT COUNCL SGNS ON ROADS BYLAW 2015 Part 1 Preliminary 1. ntroduction

More information

City of Auburn Americans with Disabilities Act (ADA) Transition Plan for Curb Ramps, Sidewalks, and Pedestrian Signals ADA TRANSITION PLAN

City of Auburn Americans with Disabilities Act (ADA) Transition Plan for Curb Ramps, Sidewalks, and Pedestrian Signals ADA TRANSITION PLAN Americans with Disabilities Act (ADA) Transition Plan for Curb Ramps, Sidewalks, and Pedestrian Signals ADA TRANSITION PLAN December 21, 2009 Public Works Department 171 N. Ross Street, Suite 200 Auburn,

More information

Monitoring and evaluation of walking and cycling (draft)

Monitoring and evaluation of walking and cycling (draft) Sustrans Design Manual Chapter 16 Monitoring and evaluation of walking and cycling (draft) November 2014 September 2014 1 About Sustrans Sustrans makes smarter travel choices possible, desirable and inevitable.

More information

TEST ON Driving Safely Among Bicyclists and Pedestrians

TEST ON Driving Safely Among Bicyclists and Pedestrians TEST ON Driving Safely Among Bicyclists and Pedestrians Next you will take a 16 question test about driving safely among bicyclists and pedestrians. Please take out a sheet of paper to mark down and score

More information

The partnership has selected three intersections where enforcement, education, and engineering initiatives are being implemented to improve safety:

The partnership has selected three intersections where enforcement, education, and engineering initiatives are being implemented to improve safety: Hamilton-Finn Suite 310 Tel. (403) 207-6000 Road Safety 3016 5th Avenue N.E. Fax. (403) 273-3440 Consultants Ltd. Calgary, Alberta dawatt.dawatt.com www.hamiltonfinn.ca January 19, 2005 Mr. Don Szarko,

More information

Logo here. TRAFFIC MANAGEMENT PLAN Ref : xxxx Dated xxxxxx. Enter details. Delivery Address: Enter details

Logo here. TRAFFIC MANAGEMENT PLAN Ref : xxxx Dated xxxxxx. Enter details. Delivery Address: Enter details Logo here Ref : xxxx Dated xxxxxx Mandatory H&S 905 Rev 1: xxxxx Page 1 of 1 Project: Project No: Date: Prepared by: Enter details Enter details Enter details Enter details Delivery Address: Enter details

More information

Route Optimisation / Traffic Signals Efficiency

Route Optimisation / Traffic Signals Efficiency Route Optimisation / Traffic Signals Efficiency Glossary Auckland Council Advanced Real-time Traffic Information System Auckland Transport Closed Circuit Television (Traffic cameras) Full Time Equivalent

More information

HIGHWAY DESIGN GUIDE. 1.1 Foreword

HIGHWAY DESIGN GUIDE. 1.1 Foreword HIGHWAY DESIGN GUIDE Part 1 INTRODUCTION 1.1 Foreword Coventry City Council wants Coventry to be a growing, accessible city where people choose to live, work and be educated, and where businesses choose

More information

Report Purpose To seek Council s approval of Municipal Policy SER-009-040: Traffic Calming

Report Purpose To seek Council s approval of Municipal Policy SER-009-040: Traffic Calming Council Meeting Date: April 23, 2013 Agenda Item #: 13.1 MUNICIPAL POLICY (NEW) SER-009-040: TRAFFIC CALMING Report Purpose To seek Council s approval of Municipal Policy SER-009-040: Traffic Calming Recommendation

More information

The Roaches Asset Management Review. Draft Objectives for External Consultation. Fundamental Principles

The Roaches Asset Management Review. Draft Objectives for External Consultation. Fundamental Principles The Roaches Asset Management Review Draft Objectives for External Consultation Fundamental Principles the area of land under review is the Roaches Estate and Gradbach Car Park as shown on the attached

More information

THIS PAGE INTENTIONALLY LEFT BLANK

THIS PAGE INTENTIONALLY LEFT BLANK THIS PAGE INTENTIONALLY LEFT BLANK Construction Traffic Management Plan 2 Contents 1. Introduction... 4 1.1 Conditions of Consent... 4 2. Goals of the CTMP... 6 2.1 Objectives... 6 2.2 Predicted Construction

More information

11. Monitoring. 11.1 Performance monitoring in LTP2

11. Monitoring. 11.1 Performance monitoring in LTP2 178 11. Monitoring 11.1 Performance monitoring in LTP2 Performance against the suite of indicators adopted for LTP2 is shown in the following table. This shows progress between 2005/06 and 2009/10 (the

More information

ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES

ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES How to Get Started ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES Design Elements Selecting appropriate design treatments for school neighborhoods creates environments that address the needs of all

More information

DELIVERY & SERVICING PLAN. REDWOOD PARTNERSHIP Consulting Engineers Transportation Planners

DELIVERY & SERVICING PLAN. REDWOOD PARTNERSHIP Consulting Engineers Transportation Planners Redwood Partnership Transportation Limited Maritime House Basin Road North Portslade Brighton BN41 1WR T: 01273 414515 F: 01273 376824 E: consult@redwoodpartnership.co.uk www.redwoodpartnership.co.uk REDWOOD

More information

Taking In Charge Policy

Taking In Charge Policy COMHAIRLE CONTAE CHORCAÍ CORK COUNTY COUNCIL Taking In Charge Policy for Private Housing Developments 17 th October 2008 TABLE OF CONTENTS TABLE OF CONTENTS... 2 1 POLICY OBJECTIVE... 3 2 POLICY OVERVIEW...

More information

SETTING LOCAL SPEED LIMITS Draft: July 2012

SETTING LOCAL SPEED LIMITS Draft: July 2012 SETTING LOCAL SPEED LIMITS Draft: July 2012 CONTENTS 1. Introduction 2. Background and objectives of the Circular 3. The underlying principles of local speed limits 4. The legislative framework 5. The

More information

INTERIM ADVICE NOTE 65/05 DESIGN OF VEHICLE RECOVERY OPERATIONS AT ROAD WORKS

INTERIM ADVICE NOTE 65/05 DESIGN OF VEHICLE RECOVERY OPERATIONS AT ROAD WORKS INTERIM ADVICE NOTE 65/05 DESIGN OF VEHICLE RECOVERY OPERATIONS AT ROAD WORKS The Purpose of this document is to provide the Project Sponsor / Designer with comprehensive guidance on the range of issues

More information

How To Design A Crash Investigation Site

How To Design A Crash Investigation Site CHAPTER 7 CRASH INVESTIGATION SITES December, 2000 7. Crash Investigation Sites (CIS) 7.1. Introduction and Usage The idea of "crash investigation sites" or areas outside of the freeway mainline where

More information

Seagull Intersection Layout. Island Point Road - A Case Study. Authors: John Harper, Wal Smart, Michael de Roos

Seagull Intersection Layout. Island Point Road - A Case Study. Authors: John Harper, Wal Smart, Michael de Roos Seagull Intersection Layout. Island Point Road - A Case Study Authors: John Harper, Wal Smart, Michael de Roos Presented by Mr John Harper, Road Safety and Traffic Services Manager Phone: 4221 2456 Mobile:

More information

CONTRACT TRAFFIC MANAGEMENT PLAN

CONTRACT TRAFFIC MANAGEMENT PLAN CONTRACT TRAFFIC MANAGEMENT PLAN Project: Client: Gisborne District Council Contractor: PF Olsen Ltd TMP No.: Contract Plan Issue Date Document Control Document Authorisation 27.08.4 B McArthur Page Edition

More information

28.0 Development Permit Area #2 (Neighbourhood District)

28.0 Development Permit Area #2 (Neighbourhood District) 28.0 Development Permit Area #2 (Neighbourhood District) Goals and Objectives To provide a guide for infill and new development in the Neighbourhood District. To outline the nature, form and character

More information

chapter 3 basic driving skills

chapter 3 basic driving skills chapter 3 basic driving skills When curving to the left, keep the front wheels close to the right edge of the lane to keep your driver s side rear wheels out of the next lane of traffic. Curve ahead slow

More information

TRANSPORTATION MODELLING IN CALGARY

TRANSPORTATION MODELLING IN CALGARY TRANSPORTATION MODELLING IN CALGARY Why Do We Use Transportation Models? There are three approaches that can be used for proceeding to develop a transportation system for Calgary s future. One approach

More information

TRAFFIC DEMAND MANAGEMENT IN ACTION! Sue Peden, Travelwise Development Manager Southampton University Hospitals NHS Trust

TRAFFIC DEMAND MANAGEMENT IN ACTION! Sue Peden, Travelwise Development Manager Southampton University Hospitals NHS Trust TRAFFIC DEMAND MANAGEMENT IN ACTION! Sue Peden, Travelwise Development Manager Southampton University Hospitals NHS Trust 1. THE SETTING Southampton University Hospitals NHS Trust is a large 1,000 bed

More information

Managing Public Use of Freeway Emergency Access Gates and Median Crossovers

Managing Public Use of Freeway Emergency Access Gates and Median Crossovers Managing Public Use of Freeway Emergency Access Gates and Median Crossovers Operational Instruction Transport Services Division TRAFFIC MANAGEMENT Operational Instructions Managing Public Use of Freeway

More information

Alternatives and Design Evolution: Planning Application 1 - RBKC

Alternatives and Design Evolution: Planning Application 1 - RBKC 3 Alternatives and Design Evolution: Planning Application 1 - RBKC Design Freeze Draft One (January 2011) Figure 3-19 3.82 The design freeze draft one was a point in time in the evolution of the Masterplan

More information

Glossop Design & Place Making Strategy

Glossop Design & Place Making Strategy Supplementary Planning Document to the High Peak Local Plan June 2011 Design Brief for the Town Hall Complex GILLESPIES I GERALD EVE Reproduced from the Ordnance Survey map with the permission of Ordnance

More information

Workplace Transport Safety Reversing Vehicles Information Sheet What are the dangers associated with reversing vehicles? Why is reversing a problem?

Workplace Transport Safety Reversing Vehicles Information Sheet What are the dangers associated with reversing vehicles? Why is reversing a problem? Workplace Transport Safety Reversing Vehicles Information Sheet This information sheet aims to raise awareness of the dangers caused by reversing vehicles in the workplace. It provides basic information,

More information

Topic 2 11/28/2012 Blocks & Street Network

Topic 2 11/28/2012 Blocks & Street Network TOPIC 2 Blocks & Street Network Implementation Note: 1. Some recommendations are summarized in the tables herein. For complete recommendation language, please see the. 2. Recommendations referenced in

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13

CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13 Note: Please refer to the end of this document for guidance notes about completing this form Q1. What is the full postal address of the site? Your response Q2. Planning reference and revision number (if

More information

10.1 WILL HEY FARM WATFORD LANE NEW MILLS RETENSION OF NEW STABLE BLOCK, SAND PADDOCK AND ASSOCIATED EARTHWORKS AND LANDSCAPING (FULL - MINOR)

10.1 WILL HEY FARM WATFORD LANE NEW MILLS RETENSION OF NEW STABLE BLOCK, SAND PADDOCK AND ASSOCIATED EARTHWORKS AND LANDSCAPING (FULL - MINOR) HPK/2012/0207 03/04/2012 WILL HEY FARM WATFORD LANE NEW MILLS MR & MRS M WILSON KIRSTY WILSON EQUINE AND WILL HEY FARM BED & BREAKFAST RETENSION OF NEW STABLE BLOCK, SAND PADDOCK AND ASSOCIATED EARTHWORKS

More information

Waste management guidance notes for residential developments

Waste management guidance notes for residential developments Waste management guidance notes for residential developments February 2014 www.southwark.gov.uk This document provides guidance on the waste storage and collection requirements that should be considered

More information

Department of State Development, Infrastructure and Planning. State Planning Policy state interest guideline. State transport infrastructure

Department of State Development, Infrastructure and Planning. State Planning Policy state interest guideline. State transport infrastructure Department of State Development, Infrastructure and Planning State Planning Policy state interest guideline State transport infrastructure July 2014 Great state. Great opportunity. Preface Using this state

More information

Mount Browne (Surrey Police Head Quarters), Sandy Lane, Guildford Vision Statement. November 2013. with

Mount Browne (Surrey Police Head Quarters), Sandy Lane, Guildford Vision Statement. November 2013. with Mount Browne (Surrey Police Head Quarters), Sandy Lane, Guildford Vision Statement November 2013 with Tibbalds Planning & Urban Design 19 Maltings Place 169 Tower Bridge Road London SE1 3JB Telephone 020

More information

HIGHWAY DESIGN REPORT. Appendix 4. Proposed Design Principles for City Passings

HIGHWAY DESIGN REPORT. Appendix 4. Proposed Design Principles for City Passings HIGHWAY DESIGN REPORT Appendix 4 Proposed Design Principles for City Passings June 2000 Contents Page 1 Introduction 2 1.1 Purpose 2 1.2 Definition of city passing 2 1.3 Safety Problems 2 1.4 Planning

More information

PART 5 TA 87/04 TRAFFIC CALMING ON TRUNK ROADS A PRACTICAL GUIDE SUMMARY

PART 5 TA 87/04 TRAFFIC CALMING ON TRUNK ROADS A PRACTICAL GUIDE SUMMARY DESIGN MANUAL FOR ROADS AND BRIDGES VOLUME 6 SECTION 3 ROAD GEOMETRY HIGHWAY FEATURES PART 5 TA 87/04 TRAFFIC CALMING ON TRUNK ROADS A PRACTICAL GUIDE SUMMARY This document provides advice on the use of

More information

Criteria 3: Criteria 4: Traffic flow and traffic signals. Shakespeare Grove would be made one way running into Acland Street.

Criteria 3: Criteria 4: Traffic flow and traffic signals. Shakespeare Grove would be made one way running into Acland Street. Attachment D - Option Analysis Acland Street Acland Street Options Criteria 1: Criteria 7: Local access to the shopping strip - by walking, bike riding and by car (parking) Traffic flow and traffic signals

More information