1 QUESTIONS AND ANSWERS POSED AT PM AESIP & PM GFEBS INDUSTRY DAY 5 APRIL RESPONSES NOTED IN RED. AESIP 1. How do you plan to handle the various funding from all the Services at SOCOM? GFEBS already handles inter-service funding 2. CECOM has an established STAMIS SEC support structure. Are there any plans to leverage CECOM SEC for ERP Programs? Yes. The ASSC will take advantage of CECOM as needed. 3. Are there plans to have separate, parallel ERP support structures? What about the establishment of Army ERP support/help desk at the Shared Services Center? The same help desk for the whole enterprise is only good when solution is same (e.g., Windows). This does not work well with different functional solutions but we are consolidating level 2 & 3 helpdesk at ASSC. 4. Which of the AESIP SAP components are slated to migrate to SAP HANA, and what is the timeframe for the migration? LMP is implementing SAP HANA for a small Business Intelligence (BI) capability mostly to see if we can get it to work with DoD security 5. Has AESIP adopted canonical model communication and transformation protocols? Are you using SAP SOA PI, Oracle SOA, etc? We are using SAP MDM and PI at AESIP. The model is standard SAP. It is an all SAP stack. 6. Will GCSS-Army and LMP be required to implement the same auditability controls that GFEBS did? Yes 7. Can the GFEBS controls be reused? We (AESIP, GCSS-Army, LMP, and GFEBS) have a monthly forum where we discuss the status of auditability and preparedness to discuss the end state. We reuse information as much as possible.
2 8. Are all these controls expected to be completely automated? No. the majority are Standard Operating Procedure-like in nature (e.g., What is the acquisition value of the captured Iraqi tank? Do you have an x-ray machine?). 9. Will the Army consider moving current ERP systems to a secure cloud environment to reduce cost? Has the Army done a business case to determine if a cloud environment would be efficient? This is really an Army Data Center Consolidation Plan (ADCCP) question being managed outside of this acquisition. Work at DA continues on where we go next. 10. How can the Army have a viable approach to an Enterprise if HQ AES, TEWLS, IPPS-A and GFEBS are not part of an integrated sustainment approach? They may be eventually but we are starting with a baseline set of systems. They (the named systems in the question) are more different than alike. IPPS-A is where much of the current analysis is being performed and the legacy systems are more of a problem. 11. Will GFEBS and IPPS-A follow the standard processes of the Army SSC? GFEBS - Not at this time. Maybe someday. IPPS-A is not part of the ERP Services acquisition at this time. 12. Will the OBT work also be covered? ASSC does do work for OBT but is using other contracts. We will look at this for inclusion in this acquisition. 13. How will integration among systems be contracted? We will use this contract mechanism. 14. The Army stated ERP policy is to move legacy to ERP. How will Army address the many ERP solutions that will be covered in the future if the contract is AESIP & GFEBS? If they come into the scope of the ERP s they are covered. They will be included in different task orders. 15. What is the accreditation status of ERP and its Components? We are all accredited and have Authority to Operate (ATO s). 16. What significant security challenges remain?
3 Challenges are keeping up with the changes and strong desire for certain technologies (e.g., mobile phones with camera s, GPS locations services, mobile o/s s) 17. Of the systems currently integrated with AESIP, what percentage of overall transactions is routed through AESIP? Probably 70% because of the volume of materiel and requisitions. 18. Of the systems currently integrated with AESIP, does AESIP directly manage (own and maintain) interface control agreements (ICA s) with relative programs? Or, are the ICA s managed by the respective programs/systems? They are essentially contracts between the systems. 19. Does AESIP provide a centralized source for management and/or oversight/guidance for interface control agreements? They are essentially contracts between the systems. If they require data from AESIP, AESIP must be part of the design. 20. It was noted that Business Intelligence (BI) provides detailed visibility of tactical program/system (i.e. GCSS-Army) transactions. Is the BI configuration owned/managed by GFEBS? (or Jointly) Each system has a BI (system/tool). BI s are used for more than reporting. 21. Data Quality and Data Governance are integral to any ERP, including producing auditable reports. Can you speak to the Army s Data Quality struggles and issues and how you plan to address? It did not appear to be incorporated in the recent RFI. Data governance is run by DA CIO/G-6 and has a formal process. The Data Steward for the logistics domain is DA G-4 and AMC LOGSA is the execution arm for much of it. Sustainment services include data quality. 22. Is there any intent to merge all Army ERP systems into one platform or to maintain all systems separately in parallel at the Shared Services Center? No. But we are: Considering a streamlined contracting mechanism. Technically we also are integrating o Common SAN o COOP o Software o Virtualization
4 We are working on a plan for a common security enclave 23. What type of contracts are being planned to support the SSC in Sustaining LMP & GCSS Army? Small Business/Large Business? The market research is currently underway and will determine the strategy. 24. Is GCSS-Army sustainment part of or separate from Army Shared Services? The current plan is to transition sustainment of GCSS Army to the Army SSC. 25. Will there be 3 IDIQ s like AESIP? What are the anticipated IDIQ dollar value(s)? How many awards do you anticipate? The market research is currently underway and will determine the strategy. 26. What is the approximately timeframe the Army is looking for this new contract to be awarded? Quarter 2 Fiscal Year One the Army ERPs going to into sustainment (2017), is the Army going to do the operations and maintenance (O&M) of these systems or will that be contracted out. O&M (sustainment) of the ERPs will be accomplished through a combination of Government and contractor support. Each program is determining its own sustainment strategy, some of which may include leveraging the Army SSC. 28. Is the procurement functionality in LMP or an interface to PADDS? LMP maintains an interface to both PADDS and SPS to support procurement capability. 29. Who are the Small Businesses supporting Army SSC? The list of Small Business contractors are currently listed on the RFI Q&A link. 30. Small Businesses were recently interviewed as part of this process, does this mean that the Army intends to have Small Business set asides? All Small Businesses that responded to the Army ERP Services RFI were given the opportunity to participate in a one-on-one. The market research is currently underway and will determine the strategy.
5 31. Will everyone have access to your slides from today? Yes. All presentations, Q&A s and attendance list will be posted at: AESIP & GFEBS ASSC 32. LMP & GFEBS are Fully Integrated and plans are in process to move operations to Government. Sites, however, are struggling with using the systems for many reasons (Discipline, Consistency of use, Data, Process, and Maturity of Users). What actions are being taken to help user sites to assimilate/conform/mature in system use? (Sites claim AMD & above levels must fund help) At LMP and GFEBS, we are over the major learning issues. There will be ongoing training programs and refreshers. 33. How big is your database? Which database is being used? Do we get a copy of this presentation? GFEBS: Currently 80 Terabytes (TB) with growth to 100 TB over the next 12 months. Oracle database. LMP: LMP Production storage is approximately 98 TB. LMP non production environments (including COOP, QAS, training, etc) is 240 TB (note that the 98 TB that backs up production in the COOP is included in this number). AESIP Hub: Production storage is 16,408 Gigabytes (GB) and non-production is 11,604 GB Yes, you will get a copy. 34. What is the relationship of SAP NS2 and Shared Services Center? The SSC has had a formal partnership with SAP and now NS2 for years to support federal solutions and support the Picatinny Enova system. 35. Why isn t the Army exploring the use of Small Business GWACs and DoD-wide contracts? Market research is currently underway and will help determine the contracting approach. 36. Is the Center of Expertise (COE) limited to only Army ERP? Or are organizations such as SOCOM areas for expansion for the SAP systems? The COE is now titled the Army SSC. Army SSC is not limited to only Army ERPs. The scope of the ERP Services acquisition is the AESIP, GCSS-Army, LMP, and GFEBS requirements. There are other Army requirements that the Army SSC will perform that are outside the coverage of the contract.
6 37. Why Picatinny and not ALTESS (in PEO-EIS)? Picatinny is not the only location of the Army SSC. The Army SSC is a virtual organization and includes CECOM SEC, ARDEC SEC, Redstone NEC and ALTESS today. ALTESS data center capabilities will be used by the Army SSC under a functional support agreement. Picatinny will not be a data center hosting activity. 38. Why are you using Oracle in the lab? Where in the Army is Oracle used? I thought it was all SAP. Oracle is used as a common database in PM AESIP Hub and other ERPs. 39. Does the Army SSC have the physical facilities and resources to support LMP sustainment requirements? The Army SSC is a lead system integrator that will leverage organic and contractor resources across AMC and the Army. Thus the facility requirement will not be totally at one installation. Picatinny is the location of the Army SSC and the ARDEC Software Engineering Center. Picatinny is a large installation that has existing facilities to support the anticipated Government and contract resources. 40. In the configuration management of each SAP system (LMP, AESIP, GCSS-Army) are there separate Solution Management systems being used to manage the development changes, support notifications, or testing? Each ERP program currently has its own approach to configuration management. The AESIP Hub, LMP, GCSS-Army, and LMP all use solution manager and CHARM. 41. If Solution Manager is used, do the different products use CHARM to manage the help desk issues? LMP is currently under transition from CSC. Use of CHARM will be determined as we move forward. 42. What are the major workstreams or areas of focus for the sustainment phase of ERP? For phase 2 of ERP? The initial workstreams for the transition of LMP will be the same as currently performed by CSC. As the Army SSC matures in terms of the LMP operations, these workstreams may be adjusted. The PMO LMP and Army SSC will perform in process reviews among CSC and functional stakeholders to determine workload and workstream priorities. 43. Could you describe the knowledge transfer processes you have been successful in using to migrate programs to sustainment within Army SSC? Prepare cost, schedule, and performance plan that includes: Scope Metrics In process reviews
7 Artifact IV&V (Physical and functional configuration audits) Skills transfer by presentation; document review, and shared-desk work for a set period and time appropriate to the function Joint sign-off by the departing and gaining personnel and project leads that transition is successfully complete 44. Are all current Small Businesses supporting the Army SSC providing their staffing onsite, at Picatinny Arsenal, NJ? The majority of work being executed under the AESIP Small Business contracts is being performed at Picatinny. The virtual nature of the Army SSC allows for mixed staffing depending on program and stakeholder requirements. 45. Is Army SSC s expectation that future contract staff will be on-site at Picatinny? Future work may be performed offsite or at other AMC/Army sites depending upon PM requirements and Army SSC lead system integrator work assignments to non-picatinny organizations. 46. It is understood that transition/sustainment support contracts recently awarded were set-aside for Small Business. Is the Army SSC s expectation that future ERP transition/sustainment support contracts will be set-aside for Small Business and/or 8(a) firms (i.e. SDVOSB)? The market research is currently underway and will determine the strategy. ADDITIONAL ARMY SHARED SERVICE INFORMATION CAN BE FOUND AT: GFEBS 47. Has Army Contract Writing System always been under GFEBS? If not, when did it move over? Deferred until ACWS Brief 48. What lessons learned can you share regarding your Audit Readiness efforts? We implemented the Governance Risk & Compliance (GRC) tool to manage risks and provisioning. Included in this was a structured Segregation of Duties (SOD) policy and process. Had documented internal control processes (e.g., role design and approvals) Brought on independent auditors Added internal controls and documentation at the system administrator level 49. What impact does drawdown have on GFEBS positive? Negative? At this time, it is minimal impact. We are looking for our industry partner to assist us in being proactive in dealing with this
8 and any changes. 50. How does GFEBS and other ERP systems support DISA s JIE (Joint Info Enterprise)? We are looking at using DISA facilities to support the GFEBS-SA effort. 51. There was mention of Audit Readiness for both GFEBS and GCSS-A. Can you state the contractor(s) performing that work for both programs? Also, can you state the corresponding contract vehicle(s)? The contract is currently managed by ASA(FM&C) DASA-FO and the current contractor is IBM. Additional inquiries regarding this contract should be directed to ASA(FM&C) DASA-FO. 52. Why can t you standardize on the interfaces for GFEBS? We have standardized our process and leverage wherever feasible from one interface to another. However, we are dealing with many differing existing systems such as LMP and SPS which have varying infrastructure and design than GFEBS. We are looking for our industry partner to recommend wherever we can make improvements that are more efficient and can result in sustainment savings. 53. What are your lessons learned from GFEBS? Audit readiness as discussed above. Close interaction with our Sponsors, Process Owners and Commands Real-time memory management brought on as needed 54. What best practices will you leverage in the future? Continue to leverage SAP Industry Best Practices, strive for single army solutions within GFEBS, obtain buy-in from our Sponsors and Process Owners. 55. What is preferred contacting vehicle for BI capability? All contracted effort will be under the Single Sustainment Contract as briefed today. Army Contract Writing System (ACWS) 56. Is the Army acquisition strategy considering breaking up solution providers from the system integrator services? We are in the process of conducting market research that will determine acquisition strategy.
9 57. Is there a preference for a solution that is pre-categorized with ERP specifically GFEBS (i.e. SAP based system) or are you open to stand alone non-erp systems? There is no preference at this time. We are in the process of conducting market research that may have an impact on this decision. 58. Is ACWS conducting market research? And if so, how can a company offer a demo of their COTS solution. Yes, we plan to issue RFIs and a sources sought notice. 59. Will you be publishing the results of your AoA? TBD 60. Will you be able to replace SPS by the date set by DoD? The intent is to replace SPS NLT than the prescribed sunset date. 61. What portion of the contract is going to be set aside for small business? Unknown at this time. We are in the process of conducting market research which will determine small business strategy. 62. Is this related to the Army Procurement Execution Program (APEX)? Yes, APEX was the previous name for ACWS. 63. Does the Army has a contract vehicle preference or will this be a full and open competition? We intend to utilize full and open competition. 64. Do you anticipate a significant amount of legacy system data migration requirements to the target system? If yes, would consider separating that work from the system integrator working directly for the data owner? The Government does not currently have a response for this question. 65. Is ACWS fully funded? If so, how much? I could not find a budget line item for it. Where does the budget reside? No. The requirement definition will drive this. 66. Will ACWS be considered a new start? Yes.
10 67. Does the Army anticipate making a product selection prior to issuing an RFP for system integration No. 68. Does the Army have a software preference to meet the ACWS requirement? No. 69. Will you prescribe the technology (software) for this requirement? No. 70. Do you anticipate an extension for SPS? No. 71. Has the Government started meeting software vendors? Yes, for market research purposes. 72. With the current investment in SAP, why not leverage the business application of SAP for ACWS? Federal regulation requires competition for this requirement. 73. When do you think the ACWS RFP will be released and awarded? Anticipated RFP release is early Fiscal Year 14. Award is anticipated for late Fiscal Year The original vision for a tactical contract writing system was in GCSS-Army using DFPS and GCSS-Army SATCOM links. How will GFEBS support MTOE contracts during early phases of deployment (Iraq lessons learned)? All requirements for the contract writing system will be analyzed.
Questions and Answers. Army Enterprise Resource Planning (ERP) Services Industry Day 27 February 2014. Responses noted in blue italics.
1 Questions and Answers Army Enterprise Resource Planning (ERP) Services Industry Day 27 February 2014 Responses noted in blue italics. 1. If a Small Business has not responded to the Request for Information
More informationUNCLASSIFIED. FY 2016 Base FY 2016 OCO
Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Army : February 2015 2040: Research, Development, Test & Evaluation, Army / BA 7: Operational Systems Development COST ($ in Millions) Years FY 2014
More informationArmy Supply Chain: Delivering the Future to the Warfighter
Army Supply Chain: Delivering the Future to the Warfighter Logistics Supporting Activity Life Cycle Logistics Tools Workshop 8 March 2010 Army Transformation Demands SC Transformation Seven years of conflict
More informationIntroduction. Background. Army Enterprise Resource Planning (ERP) Services Request for Information
Introduction This is a (RFI), as defined in Federal Acquisition Regulation (FAR) 15.201(e). Small Businesses are strongly encouraged to submit responses to this RFI. This is not a request for proposal,
More informationUNCLASSIFIED. UNCLASSIFIED Army Page 1 of 19 R-1 Line #183
Exhibit R2, RDT&E Budget Item Justification: PB 2015 Army : March 2014 2040: Research, Development, Test & Evaluation, Army / BA 7: Operational s Development COST ($ in Millions) R1 Element (Number/Name)
More informationDISA Acquisition Opportunities
DISA Acquisition Opportunities 2014 Forecast to Industry 1 CAE Acquisition Opportunities GCCS-J Program support Base year and one 1 year option with total estimated value of $5M Current PoP ends 28 Nov
More informationCompany Overview EDC Consulting
Company Overview EDC Consulting Winter 2016 1 Esprit De Corps Esprit De Corps EDC Consulting embraces the spirit of esprit de corps. Esprit de corps (pronounced es-pree deh core ) is a translation from
More informationAssessing Your Information Technology Organization
Assessing Your Information Technology Organization Are you running it like a business? By: James Murray, Partner Trey Robinson, Director Copyright 2009 by ScottMadden, Inc. All rights reserved. Assessing
More informationMESSAGE from PM AESIP
January 2014 INSIDE THIS ISSUE 1 MESSAGE from PM AESIP 2 3 4-5 CUSTOMER CORNER: CASCOM Liaison Officers Have Boots on the Ground at AESIP Headquarters PROGRAM UPDATES: From around AESIP AESIP HUB: How
More informationSNOW SOFTWARE. Fredrik Spolén Country Manager Sales Director. Norway Denmark Finland
SNOW SOFTWARE Fredrik Spolén Country Manager Sales Director Norway Denmark Finland AGENDA FOR TODAY Introduction to SAM and Snow 4 th Generation SAM Snow SAM Platform Questions and Answers LACK OF SAM
More informationARMY PEO EIS. Soldiers attend class about the Global Combat Support System-Army, an ERP that supports tactical logistics.
The Army s ERP future The Army s enterprise resource planning programs carry out the Army s back-office functions, and they all are central to servicewide and DoD-wide operations. ARMY BY AMBER CORRIN
More informationArmy Enterprise Resource Planning (ERP) Services. Industry Day #2. 27 February 2014
Army Enterprise Resource Planning (ERP) Services Industry Day #2 27 February 2014 Administrative Comments Overflow parking is available in the corner of Abbot Rd and Gunston Rd. If you have NOT checked
More informationTEST MANAGEMENT SOLUTION Buyer s Guide WHITEPAPER. Real-Time Test Management
TEST MANAGEMENT SOLUTION Buyer s Guide WHITEPAPER Real-Time Test Management How to Select the Best Test Management Vendor? The implementation of a Test Management system to automate business processes
More informationProject Management Office Charter
Old Dominion University Office of Computing and Communication Services Project Management Office Charter Version: 1.0 Last Update: February 18, 2010 Created By: Anthony Fox, PMP OCCS Project Management
More informationGAO MAJOR AUTOMATED INFORMATION SYSTEMS. Selected Defense Programs Need to Implement Key Acquisition Practices
GAO United States Government Accountability Office Report to Congressional Addressees March 2013 MAJOR AUTOMATED INFORMATION SYSTEMS Selected Defense Programs Need to Implement Key Acquisition Practices
More informationInformation Briefing and Reception. Chris Van Metre President, SCRA Applied R&D December 4, 2014
Information Briefing and Reception Chris Van Metre President, SCRA Applied R&D December 4, 2014 Overview OT Consortium Business Model Section 845 Other Transactions Agreement DoD Spectrum Enterprise (DSE)
More informationStatus of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior Recommendations
Report No. DODIG-2013-111 I nspec tor Ge ne ral Department of Defense AUGUST 1, 2013 Status of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior s I N T
More informationBridging Development and Operations: The Secret of Streamlining Release Management
Bridging Development and Operations: The Secret of Streamlining Release Management Mark Levy, Product Manager Serena Software SERENA SOFTWARE INC. Release Management Goal Deploy application changes into
More informationAutomation Change Control Expert 2.0
Product Brief Automation Change Control Expert 2.0 Arbiter Software Automation Change Control Expert TM (ACCE TM ) provides object-level Lifecycle Management for CA Workload Automation AE (formerly CA
More informationSound Transit Internal Audit Report - No. 2014-3
Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management
More informationADVANTAGE YOU. Be more. Do more. With Infosys and Microsoft on your side!
ADVANTAGE YOU Be more. Do more. With Infosys and Microsoft on your side! Today s digital-led, rapidly evolving business scenarios pose unique challenges for enterprises across industries. While we hear
More informationOverview and Frequently Asked Questions
Overview and Frequently Asked Questions OVERVIEW Oracle is pleased to announce that we have completed our acquisition of Siebel Systems and we are now operating as one. As the leader in customer relationship
More informationSpace Ground Services in the Joint Information Environment (JIE)
Space Ground Services in the Joint Information Environment (JIE) Scott Niebuhr, Jeremy Burton, Judy Kerner, Sky Troyer The Aerospace Corporation 2015 The Aerospace Corporation Space Ground Services in
More informationA discussion of information integration solutions November 2005. Deploying a Center of Excellence for data integration.
A discussion of information integration solutions November 2005 Deploying a Center of Excellence for data integration. Page 1 Contents Summary This paper describes: 1 Summary 1 Introduction 2 Mastering
More informationApproaches to Legacy System Modernization. April 2016
Approaches to Legacy System Modernization April 2016 Approaches to Legacy System Modernization Today s Topics Why Legacy Modernization Projects are Complex Components of a Successful Project Best Practices
More informationA Comprehensive Cyber Compliance Model for Tactical Systems
A Comprehensive Cyber Compliance Model for Tactical Systems Author Mark S. Edwards, CISSP/MSEE/MCSE Table of Contents July 28, 2015 Meeting Army cyber security goals with an IA advocate that supports tactical
More informationTop 10 Trends In Business Intelligence for 2007
W H I T E P A P E R Top 10 Trends In Business Intelligence for 2007 HP s New Information Management Practice Table of contents Trend #1: BI Governance: Ensuring the Effectiveness of Programs and Investments
More informationSTATE OF NEW YORK IT Transformation. Request For Information (RFI) Enterprise Identity and Access Management Consolidated Questions and Responses
STATE OF NEW YORK IT Transformation Request For Information (RFI) Enterprise Identity and Access Management Consolidated Questions and Responses June 8, 2012 Appendix B Consolidated Vendor Questions with
More informationArmy Business Systems Information Technology Strategy Needs Improvement
Report No. DoDIG-2013-045 February 7, 2013 Army Business Systems Information Technology Strategy Needs Improvement Additional Copies To obtain additional copies of this report, visit the Web site of the
More informationEVOLVING THE PROJECT MANAGEMENT OFFICE: A COMPETENCY CONTINUUM
EVOLVING THE PROJECT MANAGEMENT OFFICE: A COMPETENCY CONTINUUM Gerard M. Hill Many organizations today have recognized the need for a project management office (PMO) to achieve project management oversight,
More informationTexas State Library and Archives Commission. Information Technology Detail. August 26, 2010
Texas State Library and Archives Commission Information Technology Detail 82 th Regular Session, Agency Submission, Version 1 August 26, 2010 PAGE: 1 of 6 5005 ACQUISITN INFO RES TECH 4 Computer Resources/Network
More informationGartner, Inc. DIR-SDD-2042
Texas Department of Information Resources STATEMENT OF WORK (SOW) FOR DELIVERABLES-BASED INFORMATION TECHNOLOGY SERVICES Identity & Access Management Analysis IT Assessment & Planning Gartner, Inc. DIR-SDD-2042
More informationHeadquarters U.S. Air Force. Building CERs & SERs for Enterprise Resource Planning (ERP)
Headquarters U.S. Air Force I n t e g r i t y - S e r v i c e - E x c e l l e n c e Building CERs & SERs for Enterprise Resource Planning (ERP) Programs Dr. Wilson Rosa, Travis Packard, Abishek Krupanand,
More informationTransportation Solutions Built on Oracle Transportation Management. Enterprise Solutions
Transportation Solutions Built on Oracle Transportation Management Enterprise Solutions Optimizing transportation operations and ensuring improved customer service Today s complex and challenging business
More informationCompany A Project Plan
Company A Project Plan Project Name: Close Optimization Project Example Prepared By: David Done - Project Manager Title: John Doe -Project Manager Date: March 17, 2011 Project Plan Approval Signatures
More informationA MATTER MANAGEMENT/e-BILLING BUYING GUIDE
A MATTER MANAGEMENT/e-BILLING BUYING GUIDE Finding the perfect, scalable solution for the corporate legal department TABLE OF CONTENTS Introduction...3 What Is Matter Management?...5 Managing the Legal
More informationSDLC- Key Areas to Audit in IT Projects ISACA Geek Week 2013 8/21/2013. PwC
SDLC- Key Areas to Audit in IT Projects ISACA Geek Week 2013 8/21/2013 1 Introductions and Projects Overview Presenters Charlie Miller and Andrew Gerndt The Coca-Cola Company Principal IT Auditors Atlanta,
More informationInnovation through Outsourcing
Innovation through Outsourcing Timothy Gehrig timothy.gehrig@cedarcrestone.com David Moore david.moore@cedarcrestone.com Agenda Expectations CedarCrestone Introduction Market Direction Outsourcing Solutions
More informationTALES FROM ESTABLISHING A PORTFOLIO AND PROJECT GOVERNANCE POLICIES. Chao-Yee Watson October 6, 2014
TALES FROM ESTABLISHING A PORTFOLIO AND PROJECT GOVERNANCE POLICIES Chao-Yee Watson October 6, 2014 Agenda Introduction Speaker Biography 2012: Disorganized Labor 2013: Laying the Foundations 2014: Execution
More informationUniversal Service Administrative Company (USAC) Request for Information (RFI) for Data Governance Software, Training and Support
RFI Number: USAC-IT-2016-03-009-RFI Universal Service Administrative Company (USAC) Request for Information (RFI) for Data Governance Software, Training and Support Title: Data Governance Software, Training
More informationHow To Write An Oor Ebusiness Ebusiness Solution
Q1. Is it a mandatory requirement to be an Oracle ebusiness Certified Partner or will you accept proof of successful implementations with Oracle, i.e., can use pre-existing setups and application security
More informationMark InfoTech. Expert IT Solutions that work for your business
Mark InfoTech Expert IT Solutions that work for your business CORE SERVICES REMOTE SAP BASIS ADMIN REMOTE DATABASE MANAGEMENT REMOTE SERVER ADMIN REMOTE INFRA SERVICES REMEDY IMPLEMENTATION BMC REMEDY
More informationSOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE CHAPTER IV
Application No.: A.0-0-0 Exhibit No.: SCG Date: March, 00 Witness: Christopher R. Olmsted SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE CHAPTER IV INFORMATION SYSTEMS, APPLICATION DEVELOPMENT
More informationUsing SAP Master Data Technologies to Enable Key Business Capabilities in Johnson & Johnson Consumer
Using SAP Master Data Technologies to Enable Key Business Capabilities in Johnson & Johnson Consumer Terry Bouziotis: Director, IT Enterprise Master Data Management JJHCS Bob Delp: Sr. MDM Program Manager
More informationDoD Cloud Computing Strategy Needs Implementation Plan and Detailed Waiver Process
Inspector General U.S. Department of Defense Report No. DODIG-2015-045 DECEMBER 4, 2014 DoD Cloud Computing Strategy Needs Implementation Plan and Detailed Waiver Process INTEGRITY EFFICIENCY ACCOUNTABILITY
More informationTECHNICAL WHITE PAPER. Accelerate UNIX-to-Linux Migration Programs with BMC Atrium Discovery and Dependency Mapping
TECHNICAL WHITE PAPER Accelerate UNIX-to-Linux Migration Programs with BMC Atrium Discovery and Dependency Mapping Table of Contents Who Should Read This Paper? 1 Current Economic Climate is Driving UNIX-to-Linux
More informationWindows Server 2003 migration: Your three-phase action plan to reach the finish line
WHITE PAPER Windows Server 2003 migration: Your three-phase action plan to reach the finish line Table of contents Executive summary...2 Windows Server 2003 and the big migration question...3 If only migration
More informationERP. Key Initiative Overview
Jeff Woods Research Managing Vice President This overview provides a high-level description of the ERP Key Initiative. IT leaders can use this overview to better understand what they need to do to prepare
More informationWhite Paper. Making the case for PPM
Introduction There are many reasons why organizations decide to implement project portfolio management solutions, but typically it is to help senior management confidently and consistently answer questions
More informationJourney of a Document CoE. History of a Document CoE At Unum Group September 2014
Journey of a Document CoE History of a Document CoE At Unum Group September 2014 1 Intro and Agenda Moderator: David Hines HP Exstream 2 Agenda Moderator: David Hines HP Exstream Introductions and overview
More informationEnterprise Resource Planning Systems Schedule Delays and Reengineering Weaknesses Increase Risks to DoD's Auditability Goals
Report No. DODIG-2012-111 July 13, 2012 Enterprise Resource Planning Systems Schedule Delays and Reengineering Weaknesses Increase Risks to DoD's Auditability Goals Additional Copies To obtain additional
More informationWorld-Renouned Services
World-Renouned Services Digital Intelligence Systems, LLC (DISYS) is a global managed staffing and services company with core capabilities in: Agile Solutions Infrastructure Support Services Application
More informationMaximizing Your Return on HR Information Technology (HRIT)
Maximizing Your Return on HR Information Technology (HRIT) Gerry Ledford Senior Research Scientist Center for Effective Organizations CEO Webinar March 17, 2014 Outline 1. What is HRIT and why does it
More informationBid/Proposal No. P15/9888 Business Intelligence Management
Answers to Vendor Questions Questions are in black, Answers are in red 1. Who is the Executive Sponsor(s) for this project Information not available at this time 2. Will PCC provide the selected consultant
More informationExposing Data as a Service in the Army Enterprise
Exposing as a Service in the Army Enterprise ABSTRACT DoD directives have been urging adoption of a Net-Centric approach toward information sharing, which makes it necessary to streamline the way data
More informationForecast to Industry 2015
Forecast to Industry 2015 Networking Technologies Ms. Lisa Belt Deputy, Infrastructure Directorate 2 November 2015 87 Infrastructure Directorate IE1 Transport Division IE Infrastructure Directorate Email:
More informationEnterprise Email in the Cloud. Consolidating 21 email systems into an enterprise system using Cloud Services. March 8, 2011
Enterprise Email in the Cloud Consolidating 21 email systems into an enterprise system using Cloud Services March 8, 2011 U.S. Department of Agriculture, Office of the Chief Information Officer 1 Executive
More informationAudit of the Management of Projects within Employment and Social Development Canada
Unclassified Internal Audit Services Branch Audit of the Management of Projects within Employment and Social Development Canada February 2014 SP-607-03-14E Internal Audit Services Branch (IASB) You can
More informationSAP Product Stewardship Network Supplier Enablement Service Description (English)
SAP PRODUCT STEWARDSHIP NETWORK - SUPPLIER ENABLEMENT - SERVICE DESCRIPTION SAP Product Stewardship Network Supplier Enablement Service Description (English) Table of Content 1 Definitions... 3 2 Introduction...
More informationA Woman- Owned, Small Business. Capability Briefing. March 2014
A Woman- Owned, Small Business Capability Briefing March 2014 Company Overview Thompson Gray is an emerging leader in providing superior solufons to customers across the Department of Defense. Founded:
More informationGSA White Paper The Network Services 2020 Strategy
GSA White Paper The Network Services 2020 Strategy NS2020: Defining the future of Federal telecommunications General Services Administration Integrated Technology Service April 2014 Background Today s
More informationHow Accenture is taking SAP NetWeaver Identity Management to the next level. Kristian Lehment, SAP AG Matthew Pecorelli, Accenture
How Accenture is taking SAP NetWeaver Identity Management to the next level Kristian Lehment, SAP AG Matthew Pecorelli, Accenture In This Session You will receive an overview of the functionality that
More informationIT Standards & Contract Management
Appendix F IT Standards & Table of Contents Vision of Action... 2 Background... 3 Goals and Objectives... 4 Projects... 5 Metrics and Measures... 6 F IT Standards & Carol Steffanni Director, MDIT Bureau
More informationOn-Demand SAP BPC Support
On-Demand SAP BPC Support Content Solution Overview Introduction to SAP RDS Solutions Solution Details SAP BPC 10 Techwave Consulting Inc. Data source: Gartner Techwave BPC Center of Excellence Implementation
More informationGuide to Successful Program Management
RG Perspective Guide to Successful Program Management 12 Ways to Make Your Program Deliver on Time, on Target, and on Budget 11 Canal Center Plaza Alexandria, VA 22314 HQ 703-548-7006 Fax 703-684-5189
More informationIntelligent Security Design, Development and Acquisition
PAGE 1 Intelligent Security Design, Development and Acquisition Presented by Kashif Dhatwani Security Practice Director BIAS Corporation Agenda PAGE 2 Introduction Security Challenges Securing the New
More informationProactive DATA QUALITY MANAGEMENT. Reactive DISCIPLINE. Quality is not an act, it is a habit. Aristotle PLAN CONTROL IMPROVE
DATA QUALITY MANAGEMENT DISCIPLINE Quality is not an act, it is a habit. Aristotle PLAN CONTROL IMPROVE 1 DATA QUALITY MANAGEMENT Plan Strategy & Approach Needs Assessment Goals and Objectives Program
More informationConducting a System Implementation Risk Review at Higher Education Institutions
Conducting a System Implementation Risk Review at Higher Education Institutions October 23, 2013 1 Webinar moderator Justin T. Noble ACUA Distance Learning Chairman 2 Your presenters Mike Cullen, Senior
More informationOffice of the Chief Information Officer
Office of the Chief Information Officer Business Plan: 2012 2015 Department / Ministère: Executive Council Date: November 15, 2012 1 P a g e This Page Left Intentionally Blank 2 P a g e Contents The Business
More informationServices for the CFO Financial Management Consulting
IBM Global Business Services Services for the CFO Financial Management Consulting Financial Management Chief financial officers (CFOs) are currently in a highly visible, highly influential position. They
More informatione-training Transition Project
e-training Transition Project Phase II e-training Communications Guide August 24, 2005 National Aeronautics and Space Administration Communications Guide for the Phase II e-training Transition August 24,
More informationSAM Benefits Overview SAM SOFTWARE ASSET MANAGEMENT
SAM Benefits Overview SAM SAM is critical to managing an IT environment because effectiveness is seriously compromised when an organization doesn t know what software assets it has, where they are located,
More informationArmy Regulation 702 11. Product Assurance. Army Quality Program. Headquarters Department of the Army Washington, DC 25 February 2014 UNCLASSIFIED
Army Regulation 702 11 Product Assurance Army Quality Program Headquarters Department of the Army Washington, DC 25 February 2014 UNCLASSIFIED SUMMARY of CHANGE AR 702 11 Army Quality Program This major
More informationProject organisation and establishing a programme management office
PROJECT ADVISORY Project organisation and establishing a programme office Leadership Series 1 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital
More informationACC-NJ Small Business Overview
ACC-NJ Small Business Overview Presented by: Christopher Heim Small Business Specialist US Army Contracting Command-NJ Christopher.a.heim4.civ@mail.mil 609-562-3193 19 June 2014 W15QKN- DoDAAC 1 Army Contracting
More informationEDI Modernization Case Studies and Best Practices
Simplify and Accelerate e-business Integration EDI Modernization Case Studies and Best Practices EDI Modernization Drivers External Locations, s, and Services Customers Suppliers / Service Providers Cloud/SaaS
More informationExhibit 16.1-4a Non Applications Services Labor Categories
Exhibit 16.1-4a Non Applications Services Labor Categories PAGE 1 1. Infrastructure System Administrator Description: The Infrastructure Systems Administrator s role is to: (1) deliver support to internal
More information2009 NASCIO Recognition Awards Page 2 of 7
State of Oklahoma 2009 NASCIO Recognition Awards Nomination Statewide ERP Implementation Office of State Finance Nominating Category: Enterprise IT Management Initiatives Lead, Support, Serve B. Executive
More information2007 Magnus.net All rights reserved. Next Generation Enterprise Network Architecture
2007 Magnus.net All rights reserved. Next Generation Enterprise Network Architecture Global Enterprise Business undergone major transformations Global enterprise is no longer Fortune 500 company Commoditization
More informationProject Management/Controls and their impact on Auditing and Accounting Issues. October 31, 2012
Project Management/Controls and their impact on Auditing and Accounting Issues October 31, 2012 Today s presenters Patrick Hagan National Managing Partner State and Local Government patrick.hagan@mcgladrey.com
More informationTechNet Land Forces South Small Business Opportunities. Carey Webster Director, Federal Information Solutions Deltek
TechNet Land Forces South Small Business Opportunities Carey Webster Director, Federal Information Solutions Deltek Agenda Review of Upcoming Opportunities for Small Businesses Army 8 Small Business Navy
More informationAppendix G: Organizational Change Management Plan. DRAFT (Pending approval) April 2007
Appendix G: Organizational Change Management Plan DRAFT (Pending approval) April 2007 Table of Contents TABLE OF CONTENTS... 1 INTRODUCTION:... 2 ABT ORGANIZATIONAL CHANGE MANAGEMENT SCOPE... 2 PEOPLESOFT
More informationHow To Develop A Data Center Cost Model
Considerations in Data Center Migration Life Cycle Cost Estimating A Joint Information Environment (JIE) Perspective Dennis J. McKeon June 2015 Approved for Public Release; Distribution Unlimited 15-1446.
More informationMaster Data Management: More than a single view of the enterprise? Tony Fisher President and CEO
Master Data Management: More than a single view of the enterprise? Tony Fisher President and CEO Agenda Why MDM? Why CDI? Business Drivers for MDM Are You Ready for MDM? What is Master Data Management?
More informationEstimating Cloud Computing Costs: Practical Questions for Programs
Estimating Cloud Computing Costs: Practical Questions for Programs Kathryn Connor RAND Corporation June 2014 In 2010, the OMB proposed Federal Agencies consolidate data centers to save money. In 2013,
More informationEstimating Cloud Computing Costs: Practical Questions for Programs. Kathryn Connor
Estimating Cloud Computing Costs: Practical Questions for Programs Kathryn Connor RAND Corporation June 2014 In 2010, the OMB proposed Federal Agencies consolidate data centers to save money. In 2013,
More informationWe want to clarify for all vendors our definition of SaaS and Managed Services.
RFP 6045 PeopleSoft Hosting Services BGSU RESPONSE Questions and Answers Special Note: We want to clarify for all vendors our definition of SaaS and Managed Services. SaaS would be using vendor s instances
More informationExhibit F. VA-130620-CAI - Staff Aug Job Titles and Descriptions Effective 2015
Applications... 3 1. Programmer Analyst... 3 2. Programmer... 5 3. Software Test Analyst... 6 4. Technical Writer... 9 5. Business Analyst... 10 6. System Analyst... 12 7. Software Solutions Architect...
More informationAgile Master Data Management A Better Approach than Trial and Error
Agile Master Data Management A Better Approach than Trial and Error A whitepaper by First San Francisco Partners First San Francisco Partners Whitepaper Executive Summary Market leading corporations are
More informationG-Cloud IV Services Service Definition Accenture Netsuite Cloud Services
G-Cloud IV Services Service Definition Accenture Netsuite Cloud Services 1 Table of contents 1. Scope of our services... 3 2. Methodology & Approach... 4 3. Assets and tools... 5 4. Pricing... 6 5. Contacts...
More informationAdvanced Systems & Development
Advanced Systems & Development Transitioning to an Enterprise Ground System Lt Col Matt Kimsal SMC/ADY Envisioning and Shaping the Future of Space BLUF SMC/AD is generating a plan for the transformation
More informationForecast to Industry 2015 External Contracting Opportunities
Forecast to Industry 2015 External Contracting Opportunities Mr. Douglas W. Packard Director, Procurement Services Directorate 2 November 2015 UNCLASSIFIED 109 103 ENCORE III Navy Maintenance Database
More informationBuilding Your EDI Modernization Roadmap
Simplify and Accelerate e-business Integration Building Your EDI Modernization Roadmap Background EDI Modernization Drivers Lost revenue due to missing capabilities or poor scorecard ratings High error
More informationMeeting the Needs of Private Equity in the Finance Organization
Meeting the Needs of Private Equity in the Finance Organization When there is a change in a company s ownership, significant changes are generally required in its finance organization. This is especially
More informationEXECUTIVE SUMMARY. Warehouse Management Systems. Technology for Global Supply Chain Performance. Authored By: Carla Reed. ChainLink Technology Series
EXECUTIVE SUMMARY ChainLink Technology Series Warehouse Management Systems Technology for Global Supply Chain Performance Copyright ChainLink Research 2007 Authored By: Carla Reed June, 2007 About ChainLink
More informationInformation Technology Solutions at Work
Information Technology Solutions at Work Company Overview Established in 2000, E Quality Corporation is a privately held company headquartered in Dallas, Texas with regional offices in Springfield, Virginia.
More informationC a p a b i l i t i e s
S o u t h p o r t s B u s i n e s s I n t e l l i g e n c e C a p a b i l i t i e s At Southport, we help our clients easily transform data into intuitive dashboards and reports for greater analytical
More informationraytek, Inc. Background Information and Capabilities
C raytek, Inc. Background Information and Capabilities About Us Craytek, Inc. was established in 2001 Incorporated in the state of Virginia 8a Certified through the SBA in June 2005 Certified Economically
More informationOverview. FedRAMP CONOPS
Concept of Operations (CONOPS) Version 1.0 February 7, 2012 Overview Cloud computing technology allows the Federal Government to address demand from citizens for better, faster services and to save resources,
More informationState of Vermont Joint Fiscal Office. Independent Review of State Information Technology Projects and Operations (H.492 Sec. 36)
State of Vermont Joint Fiscal Office Independent Review of State Information Technology Projects and Operations (H.492 Sec. 36) Project: Next Generation Case Management System (Judiciary) Interim Update
More information