Explanatory report. WINDANKER Offshore Wind Farm

Size: px
Start display at page:

Download "Explanatory report. WINDANKER Offshore Wind Farm"

Transcription

1 concerning the application for planning permission in accordance with 2 of the SeeAnlV for the construction and operation of the WINDANKER Offshore Wind Farm Applicant and Project Owner IBERDROLA Renovables Deutschland GmbH Charlottenstraße Berlin Berlin, 13. April 2016

2 Table of contents 1 Subject of the document Brief description of the project Applicant Legal and planning framework Planning procedure Energy policy objectives Federal Offshore Plan Baltic Sea (BFO-O) Offshore Grid Development Plan Regional planning for the German EEZ in the Baltic Sea Description of the project Project area Wind turbine Foundation of the OWTGs Crater protection Corrosion protection Transformer platform Foundation structure for transformer platform Scour protection Corrosion protection Cabling within the wind farm Construction measures Installation of the OWTGs Installation of the transformer platform Cabling within the wind farm Decommissioning Impact on public concerns affected by the project Sea environment and bird migration Ship traffic Air traffic Pipelines and sea cables Raw material extraction Military interests Fishing Tourism Version: 13. April

3 6.9 Material and cultural assets Neighboring wind farms Other checked options Justification of plan Safety and precautionary measures Schedule and action plan Works cited Version: 13. April

4 List of abbreviations AIS AVV EEZ ROV EEZ North Sea BAW Research Agency) BBergG Automatic Identification System Allgemeine Verwaltungsvorschrift (General Administrative Regulation) Exclusive Economic Zone ROV for the German EEZ of the North Sea Bundesamt für Wasserbau (Federal Waterways Engineering and Bundesberggesetz (Federal Mining Act) BSH CONTIS DFS EnWG R & D FFH HVDC IALA LEP ODAS OWTG OWP ROG ROV SeeAnlV SeeAufgG SRÜ StUK UK Bundesamt für Seeschifffahrt und Hydrographie (Federal Maritime and Hydrographic Agency) Continental Shelf Information System Deutsche Flugsicherung (German Air Traffic Control) Energiewirtschaftsgesetz (German Energy Act) Research and Development Flora Fauna Habitat High-Voltage Direct Current International Association of Lighthouse Authorities Landesentwicklungsplan (Development Plan for a Federal State) Ocean Data Acquisition System Offshore Wind Turbine Generator Offshore-Windpark (Offshore Wind Farm) Raumordnungsgesetz (German Regional Planning Act) Raumordnungsverfahren (Regional Planning Procedure) Seeanlagenverordnung (Marine Facilities Ordinance) Seeaufgabengesetz (Federal Maritime Responsibilities Act) Seerechtsübereinkommen der Vereinten Nationen (United Nations Convention on the Law of the Sea) Standard Untersuchung der Auswirkungen von Offshore-Windenergieanlagen auf die Meeresumwelt (Investigation of the Impacts of Offshore Wind Turbines on the Marine Environment); as of February 2007 United Kingdom Version: 13. April

5 UVPG Umweltverträglichkeitsprüfungsgesetz (Environmental Impact Assessment Act) ÜNB TSS WT WSD WSV Übertragungsnetzbetreiber (Transmission System Operator) Traffic Separation Scheme Wind Turbine Wasser- und Schifffahrtsdirektion (Waterways and Shipping Directorate) Wasser- und Schifffahrtsverwaltung (Federal Waterways Administration) Index of Figures Figure 1: Location of the Windanker OWP project area... 7 Figure 2: BFO-O 2013, spatial positioning of the cluster in the German EEZ in the Baltic Sea Figure 3: BFO-O 2013, diagram summarising connection lines (2030) Figure 4: Cable for the wind farm and route corridor for the network connection Figure 5: O-NEP 2025 grid network connection cluster in the Baltic Sea, initial design Figure 6:confirmed O-NEP 2024; diagram of the OST-B-1 connection system Figure 7: O-NEP 2025, first draft, new OST-B-1 AC connection Figure 8: Integrating of the project into the spatial plan for the German EEZ in the Baltic Sea Figure 9: Location of the project area Figure 10: Detailed diagram of the wind farm with corner points Figure 11: Location of the wind farm and neighbouring projects Figure 12: Front-view of planned wind turbine generator (Conceptual design, Ramboll Feb 2016) 24 Figure 13: Schematic drawing of a monopile foundation Figure 14: Front-view of a potential substation (Ramboll 2016) Figure 15: Transformer platform of the OWF Wikinger (example) Index of Tables Table1: Key data for the Windanker OWP... 9 Table2: Corner coordinates of the Windanker OWP project area Table 3: Technical data about the OWTGs Table4: Ships expected during the construction phase Version: 13. April

6 Version: 13. April

7 1 Subject of the document This explanatory report is one of the planning documents forming the application for planning permission to construct and operate the Windanker Offshore Wind Farm. The applicant is Iberdrola Renovables Deutschland GmbH. According to 2 sub-section 1 of the SeeAnlV, the hearing authority and the authority responsible for the plan approval is the Federal Maritime and Hydrographic Agency. The planning documents consist of the following sections: I. List of the submitted planning documents II. including plan justification III. Drawn representations IV. Construction inventory V. Ecology VI. Shipping / aviation / other military matters VII. Issues regarding neighbouring uses VIII. Additional documents in accordance with 4 of the SeeAnlV The explanatory report shows the existing legal and planning framework for this application for planning permission, describes the project and any interests affected by the project and presents the aspects for consideration. Furthermore, other potential solutions are examined and justification for the project is given. Version: 13. April

8 2 Brief description of the project The Windanker offshore wind farm project covers the construction and operation of 42 offshore wind turbine generators, an offshore transformer platform and the cable required by the wind farm. The coordinates of the turbines are detailed in the construction inventory in section IV of the planning documents. The project area is about 38 km northeast of the Jasmund National Park on the German island of Rügen, immediately to the north of the especially suitable area outlined in 3a of the SeeAnlV and the Westlich Adlergrund wind energy priority area according to the ROV for the German EEZ of the Baltic Sea. The closest point on the mainland is the southern area of the Greifswalder Bodden in the municipality of Lubmin, which is 82 km away. The size of the project area is 17.9 km². The water depth is between 41 and 45 m. Figure 1: Location of the Windanker OWP project area Plans are based on using a 6 MW class wind turbine. It is considered that this power class will be well established on the market by the time the wind turbines are to be purchased. In order to take into account the emerging developments in the area of wind turbine technology, these documents assume a rotor blade diameter of up to 180 m. The hub elevation is 110 m. Version: 13. April

9 It is envisaged that construction for this project will begin in 2022 and operation is scheduled to begin in The project action plan and schedule can be found in section VIII of the planning documents. The project is located in grid network connection cluster 1, according to the Federal Offshore Plan for the German EEZ in the Baltic Sea. The schedule for construction and commissioning correlates with the schedule for commissioning of the grid connection. These details were confirmed by the German Federal Network Agency in its Offshore Network Development Plan 2024, as well as in the first draft of the transmission system operator s Offshore Grid Development Plan These plan documents work on the assumption that the network connection for this cluster will be in operation in The network connection between the offshore transformer platform at the wind farm itself and the feed point nearest the mainland, which allows the electricity generated at sea to be fed out, is the responsibility of the responsible transmission system operator, 50Hertz Transmission GmbH. The network connection is therefore not a matter that is addressed in this application. The responsible transmission system operator, 50Hertz Transmission GmbH, has been commissioned with providing the network connection. Close business contact has been established with transmission system operator 50Hertz. It is already involved in implementing the Iberdrola Wikinger offshore wind farm (construction beginning May 2016) and in the early planning stages of Iberdrola s planned Iberdrola projects, such as the Windanker offshore wind farm that this application concerns. Table1: Key data for the Windanker OWP Project area Size of the project area Water depth Distance from the island of Rügen Distance from mainland approximately 17.9 km² m 38 km 82 km Technical concept Number of OWTGs 42 Number of transformer platforms 1 Power class of the OWTGs Total power output of the wind farm Rotor blade diameter Hub elevation 6 MW 252 MW up to 180 m up to 110 m Version: 13. April

10 3 Applicant The applicant for the Windanker offshore wind farm project is Iberdrola Renovables Deutschland GmbH (formerly Iberdrola Renovables Offshore Deutschland Zwei GmbH). Business division for renewable energy Iberdrola Renovables The particular focus of the Renovables business division is on promoting, constructing and operating power generation plants using renewable energy sources, as well as selling the electricity that is generated. The company is currently concentrating on wind energy and energy from small hydroelectric plants. Iberdrola is also involved in the development of other technologies such as thermal solar plants, tidal power and generating energy from biomass. Its operating wind farms have over 13,500 MW of capacity, making Iberdrola the world market leader in the area of wind energy. At present, the Renovables division is operating in more than ten countries and it currently employs around 2,000 employees. In recent years, the Iberdrola Renovables business division has become the largest source of growth in the Iberdrola Group. The Iberdrola Group has a presence in around 40 countries. It is one of Spain s leading companies in the energy sector and it is one of the five largest electricity providers in the world. The Iberdrola Group currently employs around 27,000 people around the world. Iberdrola Renovables and offshore wind energy Iberdrola is making full use of the development of offshore wind energy. This is because, as a technology for generating electricity from renewable energy, it is at least equal to onshore wind energy in terms of efficiency, costs and volumes of energy generated. Offshore wind projects are currently being developed in Germany and the United Kingdom, and preparations are underway in other European countries. In the United Kingdom, Iberdrola is involved in the development of a variety of offshore projects with a total output power of 9.5 GW. Some of the projects are joint ventures, with Iberdrola s share amounting to around 5.7 GW. As an example, its subsidiary ScottishPower has a two thirds share in the West of Duddon Sands wind farm on Britain s West Coast, which has a capacity of 389 MW and is a joint venture with Dong Energy. The West of Duddon Sands wind farm was commissioned in Iberdrola, together with Vattenfall Europe, was also part of a consortium of bidders that successfully took part in the third stage of the UK Crown Estate s offshore tender process. This joint venture received exclusive rights to the Norfolk Zone (now called East Anglia), which has the potential to harness up to 7.2 GW of power. In France, Iberdrola is involved in a joint venture with Ailes Marine (eole RES and Caisse des Dépôts) at a 496 MW offshore wind farm called St Brieux. Iberdrola is also helping with the preparation for the development of offshore wind energy in Spain. Version: 13. April

11 Additionally, Iberdrola is involved in R & D projects for offshore wind energy, such as the Offshore Wind Accelerator project, which is supported by the Carbon Trust in the UK and focuses on cost reduction. This area of work also involves analysing new concepts for foundations, such as floating foundations, and promoting new forms of research infrastructure for offshore wind energy. IBERDROLA Renovables Deutschland GmbH Since 1 July 2005, Iberdrola has been represented on the German market by its subsidiary, Iberdrola Renovables Deutschland GmbH. Iberdrola Renovables Deutschland GmbH is chiefly active in the area of offshore wind energy. Iberdrola is a member of the EWEA, the Bundesverband Windenergie (German Wind Energy Association), the Stiftung Offshore Windenergie (Offshore Wind Energy Foundation) and the Offshore Forum Windenergie (Forum for Offshore Wind Energy). One of the key goals for Iberdrola Renovables Deutschland GmbH is to develop its activities in the sustainable market in Germany in the medium and long term. It especially aims to become a wellestablished, long-term power plant operator in the offshore areas of the North Sea and Baltic Sea. Having taken over the entirety of the project rights in March 2010, Iberdrola became the owner of the Wikinger offshore wind farm (previously Ventotec Ost 2) in the Westlich Adlergrund cluster. Iberdrola will use the port of Sassnitz-Mukran for the construction of the Wikinger offshore wind farm. The port of Sassnitz-Mukran will also be used for operation and maintenance. A company building will be erected there for this purpose. In order to ensure that the Westlich Adlergrund cluster is used efficiently, Iberdrola has made applications for planning permission not only for the Windanker offshore wind farm, which is the subject of this application, but also for the Wikinger- Süd and Wikinger-Nord offshore wind farms. Version: 13. April

12 4 Legal and planning framework 4.1 Planning procedure The area relating to the application for the Windanker offshore wind farm is entirely within the German EEZ. In accordance with 2 sub-section 1 of the SeeAnlV, projects in the EEZ relating to the generation of wind energy require planning permission. According to 2 sub-section 2 of the SeeAnlV, the hearing authority and the authority responsible for the plan approval is the Federal Maritime and Hydrographic Agency. The SeeAnlV is based on the United Nations Convention on the Law of the Sea of 10 December 1982 and on the German Federal Maritime Responsibilities Act (SeeAufgG). In accordance with 17 of sub-section 3 and in connection with 5 sub-section 5 of the latest version of the SeeAnlV (updated 31 August 2015), the plan for a project in the EEZ can only be approved if: 1. there is no impairment to the safety and efficiency of traffic or to national and alliance defence; 2. there is no threat to the marine environment and in particular if there are no concerns about contamination of the marine environment within the meaning of Article 1 subsection 1 number 4 of the United Nations Convention on the Law of the Sea of 10 December 1982 (BGBl.[German Federal Law Gazette] 1994 II p. 1798, 1799) and if bird migration is not threatened; 3. other requirements relating to the Marine Facilities Ordinance or other provisions of public law are fulfilled. 4.2 Energy policy objectives In order to protect the environment, the German government has outlined its target of increasing the percentage of electricity that comes from renewable energy. In keeping with the German government s integrated energy and climate programme (2007), the current version of the Renewable Energy Act (2012) set a specific target of at least 35% renewable energy by 2020, with this percentage due to continually rise to 80% by In terms of meeting this target, there is enormous potential in offshore wind energy. In accordance with the German government s strategy of using wind energy at sea in connection with its sustainability strategy (January 2002), work should be done to create the framework conditions that will allow this potential to be utilised as quickly as possible. It is expected that wind energy will generate 20,000 to 25,000 MW of power by Version: 13. April

13 It is against this backdrop that especially suitable areas within the German EEZ were defined in 2005, in accordance with 3a of the SeeAnlV. The ROV for the German EEZ of the Baltic Sea came into force on 10 December This meant that the areas of Westlich Adlergrund and Kriegers Flak, which are defined in the SeeAnlV as especially suitable, were taken into account in the aims of the regional plan for the Baltic Sea and were identified as priority areas for wind energy. As noted in the explanatory memorandum to the SeeAnlV, (...)without generating wind energy at sea, it may not be possible to meet [the renewable energy targets formulated in the Renewable Energy Act] (...). The current Renewable Energy Act (2014) has further reinforced the German government s target for the energy transition and specifics have been determined for further developing renewable energies. By 2025, the proportion of renewable energy should be between 40 and 45 per cent and by 2035 it should be between 55 and 60 per cent. The proportion of wind energy at sea should rise to 6.6 gigawatts by 2020 and to 15 gigawatts by These figures clearly show the necessity of further developing offshore wind energy. Building on the foundation of the German Energy Act (EnWG), the political and planning framework conditions are being put into place in ways such as developing and updating the Federal Offshore Plan and the Offshore Grid Development Plan. This confirms the need for development in offshore wind energy. 4.3 Federal Offshore Plan Baltic Sea (BFO-O) The Federal Offshore Plan is based on 17a of the German Energy Act (EnWG). It states that the Federal Maritime and Hydrographic Agency must create an annual Offshore Grid Plan for Germany s EEZ (Federal Offshore Plan). This should be done in agreement with the German Federal Network Agency and in coordination with the Federal Agency for Nature Conservation and the coastal federal states. The Federal Offshore Plan should therefore include definitions, specifications for standardised technology and planning principles for the routes and route corridors for the grid connection as well as for the route guides and the location of platforms for converters and transformers. The Federal Offshore Plan for the North Sea was first presented in 2012 and was made public in March The first draft of the Federal Offshore Plan for the Baltic sea was presented in February 2013 and entered the relevant consultation process. On 7 March 2014, the Federal Offshore Plan Baltic Sea 2013 was established and made public. In a letter dated 25 November 2015, the Federal Maritime and Hydrographic Agency made it known that no update was required and that the BFO-O 2013 would not amended for The Windanker OWP project is located in cluster 1 of BFO-O 2013 (Figure 2). Version: 13. April

14 Figure 2: BFO-O 2013, spatial positioning of the cluster in the German EEZ in the Baltic Sea (Source: According to BFO-O 2013, the cluster is to be connected using three-phase current with a transmission voltage of 220 kv. In line with the planning principles regarding the locations of the transformer platforms, these are to be located as close to the edge of the wind farm as possible. This is intended to ensure that the route length does not exceed 100 km. Nevertheless, the location of the platform should also fit in well with the wind farm as a whole in terms of traffic. In line with this planning principle, the BFO-O 2013 would prefer that the transformer platform be located well inside the bounds of the wind farm (Figure 3). Version: 13. April

15 Figure 3: BFO-O 2013, diagram summarising connection lines (2030) (Source: In keeping with the planning principles and graphical representations of the BFO-O 2013, the network connection corridor is at the western edge of the wind farm. The size of this corridor is in keeping with the relevant distance regulations in the BFO-O The position of the transformer planform is also on the western edge and it is within the bounds of the wind farm, in line with the planning principles of the BFO-O ( Figure 4: Cable for the wind farm and route corridor for the network connection ) Version: 13. April

16 Figure 4: Cable for the wind farm and route corridor for the network connection The planned route corridor is 100 m wide and therefore allows parallel routing of up to two cable systems. There is also a distance of 500 m between the route corridor and constructions and of 300 m between the corridor and any shipping routes. Cable intersections are avoided. The remaining standardised technical requirements and planning principles of the BFO-O 2013 (such as the use of three-phase current technology, a transmission voltage of 220kV, cover for the long-term safety of the cable system, avoiding a temperature increase in the sediment, laying cable outside Natura2000 protection areas and protected habitats, careful laying processes, timely coordination of the laying work as a whole, taking into account cultural assets and any locations where weapons are found) are the responsibility of the transmission system operator. The Windanker OWP project thus conforms with the specifications of the most recent BFO-O Version: 13. April

17 4.4 Offshore Grid Development Plan In accordance with 17b of the German Energy Act (EnWG) and on the basis of the scenario framework of the regulatory authority, the transmission system operators are obligated to present an annual national Offshore Grid Development Plan for the German EEZ and the German territorial waters up to the grid connection points on land, together with the national Grid Development Plan. Taking into account the specifications of the relevant and current BFO within the meaning of 17a, the joint national Offshore Grid Development Plan must contain a phased schedule that details any effective measures relating to the appropriate optimisation, enhancement and upgrading of the offshore connection cables and that will be required in the next ten years for the phased, appropriate and economical development of the offshore cable connections as well as for their safe and reliable operation. Figure 5: O-NEP 2025 grid network connection cluster in the Baltic Sea, initial design Version: 13. April

18 The Windanker OWP is located in grid network connection cluster 1 in the Baltic Sea (Figure 5), which is also the location of Westlich Adlergrund, an area defined as especially suitable, and of approved OWPs Wikinger and Arkona-Becken Südost. On 16 April 2014, the transmission system operator released the first draft of the Offshore Grid Development Plan 2024 (O-NEP 2024) for consultation. The revised second draft of the O-NEP 2024 was passed to the German Federal Network Agency for review on 4 November After this second consultation, the agency presented the initial findings of its review of the O-NEP 2024 document. In February 2015, the second draft of the Offshore Grid Development Plan 2024 was again passed to the German Federal Network Agency for consultation. On 4 September 2015 the German Federal Network Agency then confirmed the Grid Development Plan and the Offshore Grid Development Plan Figure 6:confirmed O-NEP 2024; diagram of the OST-B-1 connection system The O-NEP 2024 document was confirmed on 4 September 2015, thus confirming the go-ahead for the OST-B-1 connection system, which has a transmission capacity of 500 MW and is scheduled to be completed in Originally in the drafts for the O-NEP 2024 had envisaged that cluster 1, where the Windanker OWP is to be located, would use the connection systems OST-1-4 Version: 13. April

19 (completion in 2018) and OST-1-5 (completion in 2024), each with a capacity of 250 MW. During the consultation stages, the idea of a bundling point to allow an appropriate development of the offshore grid in the Baltic Sea became increasingly significant, eventually leading to confirmation that the OST-B-1 would be used to connect the OWPs in clusters 1, 2 and 4 in the German EEZ of the Baltic Sea (Figure 6Figure 7). On 30 October 2015, the transmission system operator then published the first draft of the Offshore Grid Development Plan The public consultation will continue until 13 December This draft for the 2025 document also contains reference to the OST-B-1 connection system that was confirmed in the O-NEP 2024, including the details of its 500 MW capacity and scheduled completion in Figure 7: O-NEP 2025, first draft, new OST-B-1 AC connection Version: 13. April

20 4.5 Regional planning for the German EEZ in the Baltic Sea The location of the project area was chosen so that there would be as few conflicts as possible with other regional planning matters. With regards to the organisational plan for the EEZ, there were no completely blank areas that had no regional planning specifications or memos from regional categories. In any case, it is necessary to evaluate the extent to which the various uses are compatible. In the case of Windanker, as is also true of the neighbouring Westlich Adlergrund area that is dedicated especially to wind energy, the project area overlaps with an area designated for military use (labelled military exercise areas ). In this case, however, the area is an exercise area for the German Air Force and thus requires airspace that is much higher than the sea level. Both uses are compatible (see ROV for German EEZ in the Baltic Sea), which means there is no conflict of use with the military exercise area. To the south, the project area is directly connected to the area of Westlich Adlergrund, which is designated as especially suitable and is a priority area. In 2005, special areas within the German EEZ were defined in accordance with 3a of the SeeAnlV. The designation of these especially suitable areas has a similar level of authority as an expert report, which determines the foundational suitability of the area for the construction of wind farms ( 3a sub-section 2of the SeeAnlV). In the Baltic Sea, two areas have been designated as particularly suitable: Kriegers Flak and Westlich Adlergrund. When the ROV for the EEZ in the Baltic Sea came into force on 10 December 2009, Westlich Adlergrund and Kriegers Flak, which are especially suitable areas according to the SeeAnlV, were additionally designated as priority areas for wind energy. This means that the purpose of these areas is first and foremost to generate wind energy. Other regionally significant uses that are not compatible with generating wind energy are not permitted in these areas, which serves to keep these areas free. The project that is the subject of this application is directly connected to the area of Westlich Adlergrund, which is designated as especially suitable and is a priority area. This proximity means that the assumptions that led to the designation of the wind energy priority area are also applicable to Windanker. Taking into consideration the volume of traffic, the organisational plan established priority areas for shipping. Additional safety areas were also defined, which are exclusively for shipping. In accordance with the organisational plan, the shipping priority areas and areas exclusively for shipping in the German EEZ in the Baltic Sea are located to the north and west of the project area. The turbines keep to the minimum distance from these areas of at least 900 m to the west and at least 2 km to the north Version: 13. April

21 Figure 8: Integrating of the project into the spatial plan for the German EEZ in the Baltic Sea In the organisational plan for the German EEZ of the Baltic Sea, a target corridor is planned for submarine cables to divert power produced in the EEZ. This is located 15 km south of the project area. Version: 13. April

22 5 Description of the project 5.1 Project area The project area is about 38 km northeast of the Jasmund National Park on the German island of Rügen, immediately to the north of the especially suitable area outlined in 3a of the SeeAnlV and the Westlich Adlergrund wind energy priority area according to the ROV for the German EEZ of the Baltic Sea. The closest point on the mainland is the southern area of the Greifswalder Bodden in the municipality of Lubmin, which is 82 km away. The size of the project area is 17.9 km². The initial applied area size of the project area was approx. 30 km².this was reduced to 17.9 km² in the course of the planning under the aspects of improvement related amongst others to Federal Offshore Plan, shipping and marine environment. The water depth is between 41 and 45 m. Figure 9: Location of the project area Figure 10 shows the positioning of the turbines and the corner points of the project area. The corner coordinates of the project area are listed in Table2. Version: 13. April

23 Table2: Corner coordinates of the Windanker OWP project area Corner coordinates of the Windanker OWP project area WGS 84 (geographical) Point East longitude North latitude A B C D E F Figure 10: Detailed diagram of the wind farm with corner points The border between the German EEZ and the Danish EEZ is immediately to the east of the wind farm. Each turbine on the wind farm is separated from the outermost point of the other turbines by a distance of at least 500 m. The beginning of the Swedish EEZ is over 6 km north of the project area. Version: 13. April

24 The planned project area is to the immediate north of the Westlich Adlergrund area outlined as being especially suitable in the Marine Facilities Ordinance (SeeAnlV) and designated as a wind energy priority area by the ROV for the German EEZ of the Baltic Sea (Figure 8). The approved projects Wikinger OWP (Iberdrola) and Arkona-Becken Südost OWP (AWE/E.ON) are located within the boundaries of this area, as are the planned Wikinger Nord (Iberdrola) and Wikinger Süd (Iberdrola) offshore wind farms (Figure 11). Findings from the relevant approval processes fed into the process of determining the especially suitable area. This application means that the neighbouring area to the north will now also be assessed in terms of its suitability to be used for wind energy purposes. Due to the proximity of the areas, it is expected that some of the approval prerequisites will be similar. The project is fundamentally in keeping with the targets that the German government is seeking to meet in terms of making the energy transition a reality and developing offshore wind energy. The planned Arcadis Ost 1 OWP, which is within the 12 nautical mile zone and is this the responsibility of the federal state of Mecklenburg-Vorpommern, is around 22 km east of the project area. The Federal Maritime and Hydrographic Agency nautical charts do not depict any underwater obstacles at this location. Figure 11: Location of the wind farm and neighbouring projects Version: 13. April

25 5.2 Wind turbine According to the latest plans, a 6 MW class wind turbine will be used. At the time of writing, the type of turbine has not yet been finalised. The choice of wind turbine will be the result of a project specific call for tenders at a later point in the project development. Figure 12: Front-view of planned wind turbine generator (Conceptual design, Ramboll Feb 2016) It is expected that the 6 MW class will become well established in the coming years and will gain the necessary offshore deployment experience. It is also expected, however, that the development of turbines will result in larger sizes, as has been the case in the onshore sector. This kind of development can have an impact on both the rotor blade size (optimised yield) and on the rated output (increased total output). This means that the 8 MW class could become established in the near future or even in the current young generation of turbines. Nevertheless, this development has not yet happened and it will be taken into account as required in the later stages of planning. When choosing the appropriate type of wind turbine, important influencing factors will include turbine cost and efficiency, reliability, robustness, the impacts of turbine failure and market availability. Version: 13. April

26 Bearing in mind these assumptions of further development of technology, it is expected that the wind turbines can reach a rotor blade diameter of up to 180 m and a hub height of 110 m. The turbines will be in line with the state of the art. The wind turbines will be fully automated and will start working automatically when the wind speed reaches 3 to 4 m/s. The turbines reach their rated output at higher wind speeds of 12 to 14 m/s. The control of the rotor speed and the pitch angle of the rotor blades work to provide maximum aerodynamic efficiency. In order to ensure the highest level of protection from corrosion, particularly corrosion-resistant materials are used and the components that are most at risk have a multiple coating according to the highest protection class and in line with DIN EN ISO The cooling and ventilation of the components is provided either by an air-to-air or a water-to-air heat exchanger. The turbines are designed to not allow damp and salty outside air to get inside the turbine house or desalinate the surrounding air. To achieve lasting turbine operation, the wind turbines are equipped with service products. These are oils and fats to lubricate the turbine components, coolants to transfer away the heat created and hydraulic oils to run the hydraulic systems. Provisions have been made in the structural design of the wind turbines (catch basins) so that if any of the units discharge these service products, the discharge is collected and is not released into the environment. The turbines will be connected to the company s operations on the mainland via a communication network. This will be used to permanently monitor and control the turbines. This remote turbine monitoring makes it possible to be constantly receiving operation and error notifications as well as electrical, mechanical, static and meteorological information and data about the electricity grid. It is also possible to intervene with the running of the turbines. The wind turbines have a built-in condition monitoring system. Vibrations in the wind turbine s key components are constantly recorded and analysed. This makes it possible to regularly ascertain the status of the components and to plan further preemptive inspections or maintenance measures where needed. In order to achieve lasting turbine operation, the wind turbines are equipped with service products such as oils and fats to lubricate the turbine components, coolants to transfer away the heat created and hydraulic oils to run the hydraulic systems. Automatic lubrication takes place for parts such as the main bearing or the pitch bearing of the turbine. Any waste heat generated is transferred into the surroundings using a water-to-air heat exchanger. Provisions have been made in the structural design of the turbines (catch basins) so that if one of the units discharges these service products, the discharge is collected and is therefore not released into the environment. Version: 13. April

27 All of the turbines have built-in lightning protection systems to protect them from the consequences of being struck by lightning. They are designed in accordance with the requirements of the IEC standard for lightning protection. Table 3: Technical data about the OWTGs Turbine Rated output Rotor blade diameter Hub elevation Total height Output control Tower Construction Rotor blades Rotor blades approximately 6 MW max.180 m max.110 m above MSL max. 200 m above MSL Adjusting the rotor blade pitch angle Tubular steel tower, sealed 3 blades According to the applicable requirements, the turbines at the wind farm will be identifiable to shipping and air traffic, both optically and in terms of radio technology. This includes coloured markings and equipping the turbines with optical signals, AIS identification and sonar transponders. The specifications are defined in agreement with the responsible authorities. For the purpose of maintenance and repair, the turbines will predominantly be accessed by ship. In certain situations, the use of a helicopter will also be considered. The Wikinger OWP, which is immediately to the south of this project, will also be constructed and operated by Iberdrola. A synergy effect will be possible here, particularly in terms of maintaining and repairing the turbines. This optimisation will therefore minimise the transport required for maintenance. 5.3 Foundation of the OWTGs The choice of the foundation concept is largely determined by the wind turbine generator, the sea bed conditions, the water depths, as well as the requirements for the production and installation of the foundation. Environmental-friendliness, especially the requirements for noise mitigation, shall also be considered in the choice. The plan for the OWF Windanker project is to use a monopile foundation for the wind turbine generators (Figure 12). The monopile foundation consists mainly of a closed steel pipe that is usually pile-driven into the sea bed. The upper end of the monopile usually rises above the water after installation. A so-called transition piece is then installed on the upper end of the monopile. The monopile and the transition piece are usually connected with grout (mortar/concrete). Flange Version: 13. April

28 connections are also conceivable for this. The transition piece itself has a flange connection on the upper end in order to insert the tower of the wind turbine generator. The transition piece is usually equipped with a work platform, boat landing and so-called J-tubes for running the farm cables from the floor of the sea to the tower of the wind turbine generator (Figure 13). Figure 13: Schematic drawing of a monopile foundation The diameter of the monopile will ultimately depend on the selected wind turbine generator. It is assumed that the wind turbine generator will not have a diameter of more than 10 m. The expected progress in development in terms of state-of-the-art foundation techniques should take place in the realisation of the project. The detailed planning of the foundation structure is the subject matter of the design phase. The standards published by the BSH (Federal Maritime and Hydrographic Agency) (geotechnical site and route surveys, design of offshore wind turbine generators) and the pertinent and applicable guidelines, directives and norms shall apply. According BSH Standard Construction a conceptual design for the foundation structure has been elaborated by Ramboll. Following the demand of the BSH Standard Construction the foundation structure will be designed collision friendly. An according collision analysis is included in the planning documentation under part VI. The applicable requirements and provisions in the detailed plan shall be taken into account with respect to the impact on the sea environment. Noise will be emitted in the process of installing the foundation piles due to the pile driving. These expected emissions of noise are described in the noise forecast (Part V, Section 6 of the Plan Specification Documents). The use of a suitable noise mitigation system shall be required due to the forecast noise emissions. In the recently erected wind farm, also built with a monopile foundation, good results were achieved with the monopile systems installed there. It is assumed Version: 13. April

29 that this noise mitigation system will also continue to be developed and be available for the installation of the foundation monopiles for the OWF Windanker Crater protection The foundations are expected to be equipped with a crater protection. The scope and the development of the crater protection depends on the sea bed conditions, the local current and the details of the foundation elements. According to the current plan, a crater protection with a diameter of 50 m shall be built under the assumption of a monopile with a 10 m diameter. The crater protection shall be produced with rockfill Corrosion protection All the steel components of the OWTGs and the foundation must be protected against corrosion. To protect each individual structure, the selected coatings will be proven to be resistant to sea water and against UV radiation particularly in the area of the water-air layer of the foundation without or in the combination with sea water. The paint coating shall be state-of-the-art as applied for water construction. Particular attention will be paid to the compatibility of the paint with the sea environment. The painting of the foundation with anti-fouling agents to prevent possible vegetation is not planned. The underwater area is particularly at risk of corrosion and is essentially not accessible or only accessible with great difficulty for coating work during the life cycle of the foundations. In the design of offshore systems, it must be ensured in particular that the strengths assumed for the design will be maintained for the estimated life cycle due to the very corrosive conditions. For the areas of the foundation and its elements, a combination of coating and cathodic corrosion protection (impressed-current system or sacrificial anode) is planned. In order to achieve sufficient corrosion protection, the technical components shall receive special coatings. The following corrosivity classes shall apply: C5-M for exterior surfaces of the constructions that are exposed to a high concentration of salt spray and spraying water, C4-M for interior surfaces that are subject to outside air, and C3-M for interior surfaces that are not exposed to any outside air. The corrosion protection will be planned and carried out in accordance with the applicable norms (DIN EN ISO) and guidelines. The corrosion protection requirements for offshore generators as specified by the BSH (Federal Maritime and Hydrographic Agency) shall be taken into account in the design. Version: 13. April

30 5.4 Transformer platform The transformer platform is planned as an unmanned platform. Structurally, it will consist of a topside and a foundation structure. The topside shall enclose the entire technical equipment of the transformer substation and usually consists of multiple decks. It houses the rising cables and cable connections, the transformers, the switchgears, the control systems, etc. This equipment is installed for medium voltage (33 kv) for the wind turbine generators and for high voltage (220 kv) for the operation of the transmission network. To handle heavy loads, a crane will be available on the platform. There will also be safe rooms on the platform for maintenance staff. A boat landing and a helicopter landing pad will also be built for access. The designing and planning of the transformer substation/platform is largely defined by the electrotechnical requirements, on the one hand by the requirements made of the wind farm and on the other by the requirements and components for the operation of the transmission network. Current assumption is that the platform can reach a horizontal area of up to 30 m x 60 m. Additionally cantilevered constructive parts as for example the helicopter landing can be present. Figure 14: Front-view of a potential substation (Ramboll 2016) The adjacent OWF Wikinger will be connected directly to the network node point on land via a 220 kv three-phase asynchronous motor. The transmission distance largely determines the space required on the transmission platform for housing the required components for the operation of the Version: 13. April

31 transmission network. With the concept of a bundling point as pursued in the O-NEP, the necessary transmission distance may be less for the OWF Windanker. This would significantly reduce the need for technical equipment on the platform, as a result of which the platform could also be designed somewhat smaller. This depends on the future development, however. Concerning the visual impression of the transformer platform can be referred exemplarily to the transformer platform of the neighbouring OWF Wikinger (Figure 15). The basic area of this transformer station is roughly 25 m x 50 m. The final design of the transformer platform depends on the final details to be determined in further planning steps as well as the requirements of the responsible transmission system operator. Figure 15: Transformer platform of the OWF Wikinger (example) For the planning of the transformer platform the requirements of the BSH Standard Construction concerning the collision friendliness will be considered properly. 5.5 Foundation structure for transformer platform The transformer platform will have a foundation with a jacket structure according to the latest plans. The jacket consists of a grid structure that is anchored in the sea bed with foundation piles. The Version: 13. April

32 foundation piles will have a diameter of 3-4 m and also be pile-driven into the floor of the construction. The jacket structure and the foundation piles are usually connected by grouting Scour protection The foundation of the transformer platform does not include scour protection according to the current state of the plans. The need for scour protection depends on the sea floor conditions, the local current and the details of the foundation elements. The decision on the installation of scour protection shall be made in the course of the detailed planning. If crater protection is planned, it will be produced with rockfill Corrosion protection All the steel components of the OWTGs and the foundation must be protected against corrosion. To protect each individual structure, the selected coatings will be proven to be resistant to sea water and against UV radiation particularly in the area of the water-air layer of the foundation without or in the combination with sea water. The paint coating shall be state-of-the-art as applied for water construction. Particular attention will be paid to the compatibility of the paint with the sea environment. The painting of the foundation with anti-fouling agents to prevent possible vegetation is not planned. The underwater area is particularly at risk of corrosion and is essentially not accessible or only accessible with great difficulty for coating work during the life cycle of the foundations. In the design of offshore systems, it must be ensured in particular that the strengths assumed for the design will be maintained for the estimated life cycle due to the very corrosive conditions. For the areas of the foundation and its elements, a combination of coating and cathodic corrosion protection (impressed-current system or sacrificial anode) is planned. In order to achieve sufficient corrosion protection, the technical components shall receive special coatings. The following corrosivity classes shall apply: C5-M for exterior surfaces of the constructions that are exposed to a high concentration of salt spray and spraying water, C4-M for interior surfaces that are subject to outside air, and C3-M for interior surfaces that are not exposed to any outside air. The corrosion protection will be in accordance with DIN EN ISO and the guidelines for testing. The corrosion protection shall be planned and carried out in accordance with the applicable norms (DIN EN ISO) and the guidelines for testing. The corrosion protection requirements for offshore generators as specified by the BSH (Federal Maritime and Hydrographic Agency) shall be taken into account in the design. Version: 13. April

33 5.6 Cabling within the wind farm The wind farm cabling shall be installed as a three-phase, medium-voltage network with operating voltage of an anticipated 33 kv. The cables of the individual lines of the farm cabling shall meet in the offshore transformer station on the medium voltage side. Plastic-insulated medium-voltage cables will be used for the cabling within the wind farm. Due to the differences in transmission lengths and power, cable systems with three-core, XLPE-insulated copper cables and cross-sections between 120 mm 2 and 800 mm 2 shall be used. The cable design consists of multiple-wire copper or aluminium conductors with insulation made of crosslinked polyethylene (XLPE), which are watertight both lengthwise and crosswise and have a steel wire reinforcement to protect against damage. The sea cables are laid to protect the cables on the floor of the sea. If required, cable lengths can also be secured with rockfill, for example. Crosses with other cables or pipelines are not planned. 5.7 Construction measures The final installation concept depends on the final design of the wind farm and can only be specified at the end of the development phase. In the execution plan, all the details of the installation concept will be specified and it will be presented to the approval authority in due time prior to the beginning of construction. In accordance with the requirements and after coordination with the authorities, the construction site will be marked for ships (cardinal marks). When the wind farm is set up, the mark for ships and aviation will be activated. The appropriate authorities will be regularly informed about the status of the installation work. During the construction phase, the construction area will be secured with a traffic safety vessel. The task of the traffic safety vessel is to monitor the traffic zone by means of radar and AIS, and to notify traffic of safe passage options, if necessary. In emergencies, the navy coordination point will be notified; it will introduce appropriate measures and notify the appropriate authorities. During the construction phase, there will be a larger number of ships than normal in the construction area. The ships expected during the construction phase are described in Table4. Assembly will take place on land in advance wherever possible in order to keep the installation costs on sea as low as possible. Version: 13. April

Strategy of the German Government on the use of off-shore wind energy

Strategy of the German Government on the use of off-shore wind energy Strategy of the German Government on the use of off-shore wind energy in the context of its national sustainability strategy Ministries involved: Federal Ministry for the Environment, Nature Conservation

More information

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Submarine Power Cables State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Reliable submarine power cables ABB is one of the world s most

More information

Case Study 5 Use of Wind Turbine Technology

Case Study 5 Use of Wind Turbine Technology Case Study 5 Use of Wind Turbine Technology 1. Context Hong Kong relies on an adequate and reliable electricity supply for its economic development. Our electricity needs are met by the two electricity

More information

HV Submarine Cable Systems Design, Testing and Installation

HV Submarine Cable Systems Design, Testing and Installation HV Submarine Cable Systems Design, Testing and Installation CIGRE Ireland Technical Seminar 6 th October 2010 Robert Donaghy Senior Consultant Engineer, ESB International Presentation Overview Applications

More information

OCEAN LÍDER: Ocean Renewable Energy Leaders

OCEAN LÍDER: Ocean Renewable Energy Leaders OCEAN LÍDER: Ocean Renewable Energy Leaders Juan Amate López Offshore Projects Manager / Iberdrola I&C 7th October Removing barriers and building competences Ocean Líder : Harvesting the seas Road to Ocean

More information

WV Energie AG Offshore Wind Power. July 13

WV Energie AG Offshore Wind Power. July 13 WV Energie AG Offshore Wind Power July 13 WV Energie AG: Facts & Figures A joint venture of (primarily) municipal companies in Germany Founded in: 1904 Legal Form: Stockholders: Headquarters: Turnover*:

More information

Title: IEC WT 01 vs. IEC 61400-22 Development of a new standard and innovations in certification of Wind Turbines. mike.woebbeking@gl-group.

Title: IEC WT 01 vs. IEC 61400-22 Development of a new standard and innovations in certification of Wind Turbines. mike.woebbeking@gl-group. Title: IEC WT 01 vs. IEC 61400-22 Development of a new standard and innovations in certification of Wind Turbines Author: Address: Mike Woebbeking Germanischer Lloyd Industrial Services GmbH, Business

More information

Offshore Work Packages

Offshore Work Packages Rampion Offshore Wind Farm Offshore Work Packages Meet The Buyer Naren Mistry, Engineering Manager 26 th Feb 2014 Rampion Offshore Project Scope Design, manufacture, transportation and Installation: Up

More information

Annex to the Accreditation Certificate D-ZE-11326-01-00 according to DIN EN ISO/IEC 17065:2013

Annex to the Accreditation Certificate D-ZE-11326-01-00 according to DIN EN ISO/IEC 17065:2013 Deutsche Akkreditierungsstelle GmbH Annex to the Accreditation Certificate D-ZE-11326-01-00 according to DIN EN ISO/IEC 17065:2013 Period of validity: 27.01.2015 to 16.11.2019 Date of issue: 27.01.2015

More information

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy. Offshore Renewables Tidal Energy Transmission & Distribution Network Offshore Substation Wind Energy Onshore Substation Tidal Stream Energy Consumer Atkins in Offshore Renewables The offshore wind journey

More information

Offshore Wind and regional development the case of Rostock. Offshore Wind Energy 2013 Słupsk, Poland

Offshore Wind and regional development the case of Rostock. Offshore Wind Energy 2013 Słupsk, Poland Offshore Wind and regional development the case of Rostock Offshore Wind Energy 2013 Słupsk, Poland Hanseatic City of Rostock Geographic location Hanseatic City of Rostock Hanseatic City of Rostock Port

More information

Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site

Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site Developing Ocean Energy in Ireland Belmullet Wave Energy Test Site Where does our energy come from? Most of the energy we use in Ireland comes from fossil fuels such as oil, coal, peat and gas. We burn

More information

DONG Energy offshore wind experience

DONG Energy offshore wind experience DONG Energy offshore wind experience Future Tendering Process for Offshore Wind Energy February 10th 2011 Per Hjelmsted Pedersen Head of Project Development DONG Energy Renewables DONG Energy Renewables

More information

Offshore Wind: some of the Engineering Challenges Ahead

Offshore Wind: some of the Engineering Challenges Ahead Offshore Wind: some of the Engineering Challenges Ahead David Infield CDT in Wind Energy Systems Institute of Energy and Environment University of Strathclyde International context (from IPCC report) Greenhouse

More information

Offshore Wind. IEEE Boston PES - November 16, 2010

Offshore Wind. IEEE Boston PES - November 16, 2010 Offshore Wind IEEE Boston PES - November 16, 2010 Offshore Wind A high-level overview of offshore wind project development identifying current technologies, challenges, risks and costs. Presented by: Brook

More information

Future Offshore Wind Power Sites -2025

Future Offshore Wind Power Sites -2025 Danish Energy Authorithy Amaliegade 44 DK-1256 Copenhagen K Tel 33 92 67 00 Fax 33 11 47 43 CVR-nr: 59 77 87 14 ens@ens.dk www.ens.dk Rubrik Verdana Bold 18 punkt Underrubrik Verdana 18 punkt Brødtekst

More information

Brochure Introducing HVDC

Brochure Introducing HVDC Brochure Introducing HVDC ABB and HVDC The world s first commercial high-voltage direct current (HVDC) link, situated between the Swedish mainland and the island Gotland, was delivered by ABB already in

More information

London Array. Operations and Maintenance

London Array. Operations and Maintenance London Array londonarray.com London Array Operations & Maintenance Base Port of Ramsgate Military Road Ramsgate CT11 9LG Registered in England and Wales No 04344423 Operations and Maintenance 1 2 Operations

More information

London Array Off-Shore Wind Farm

London Array Off-Shore Wind Farm London Array Off-Shore Wind Farm 1 Jamie R Mathlin Construction Manager Off-Shore Sub-Stations Project Commissioning Manager 27 Years Experience in the Power Industry Grid Trained Electrical Engineer 10

More information

Undergrounding high voltage electricity transmission. The technical issues

Undergrounding high voltage electricity transmission. The technical issues Undergrounding high voltage electricity transmission The technical issues This is an interactive PDF document with clickable links from the contents to all sections and back and also to URL and email links.

More information

MAXIMISING YOUR. Offshore wind assets ASSET OPERATION & MAINTENANCE SERVICES

MAXIMISING YOUR. Offshore wind assets ASSET OPERATION & MAINTENANCE SERVICES MAXIMISING YOUR Offshore wind assets ASSET OPERATION & MAINTENANCE SERVICES RES is one of the world s leading renewable energy companies active in the wind, wave, tidal, solar and biomass sectors Asset

More information

Viking Link Interconnector

Viking Link Interconnector Viking Link Interconnector Public information event for Bicker Parish Why we re here today We re here today to introduce the Viking Link project, to explain what we want to build and to answer any questions

More information

Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation

Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation Position Statement regarding Offshore Wind Proposals on Lake Huron Lake Huron Centre for Coastal Conservation June 2010 Lake Huron Centre for Coastal Conservation (LHCCC) Corporate Position related to:

More information

Siemens D7 platform 6.0-MW and 7.0-MW direct drive wind turbines. The new standard for offshore. siemens.com/wind

Siemens D7 platform 6.0-MW and 7.0-MW direct drive wind turbines. The new standard for offshore. siemens.com/wind Siemens D7 platform 6.0-MW and 7.0-MW direct drive wind turbines The new standard for offshore siemens.com/wind The first SWT-6.0-154 prototype Siemens, the offshore leader Intelligent ways to drive down

More information

23.1 RENEWABLE ENERGY

23.1 RENEWABLE ENERGY Proposed Hastings District Plan as Amended 23.1 Renewable Energy 23.1 RENEWABLE ENERGY 23.1.1 INTRODUCTION The use of energy is of fundamental importance to the function and development of our society.

More information

Ampacity simulation of a high voltage cable to connecting off shore wind farms

Ampacity simulation of a high voltage cable to connecting off shore wind farms Ampacity simulation of a high voltage cable to connecting off shore wind farms Eva Pelster 1, Dr. David Wenger 1 1 Wenger Engineering GmbH, Einsteinstr. 55, 89077 Ulm, mail@wenger-engineering.com Abstract:

More information

Standards for design of offshore wind farm structures and their foundations

Standards for design of offshore wind farm structures and their foundations Standards for design of offshore wind farm structures and their foundations An overview Knut O. Ronold, DNV GL Overview of presentation Standards for design of offshore wind farm structures - What is available

More information

Optimization of the coupled grid connection of offshore wind farms

Optimization of the coupled grid connection of offshore wind farms Optimization of the coupled grid connection of offshore wind farms Dirk Schoenmakers Graduation project at Evelop Netherlands BV Technical University of Eindhoven September 2008 Supervisors: TU Eindhoven

More information

Nordex SE. Capital Markets Day Products & Sales - Lars Bondo Krogsgaard

Nordex SE. Capital Markets Day Products & Sales - Lars Bondo Krogsgaard Nordex SE Capital Markets Day Products & Sales - Lars Bondo Krogsgaard Rostock, 13 October 2011 SUMMARY The situation in the wind industry has changed: Attractive medium-term growth prospects Overcapacity

More information

OCEAN LIDER: Ocean Renewable Energy Leaders

OCEAN LIDER: Ocean Renewable Energy Leaders OCEAN LIDER: Ocean Renewable Energy Leaders J. Amate López 1 1 Product Development / Offshore, Iberdrola Ingeniería y Construcción, Avda. Manoteras 20, 28050, Madrid, Spain E-mail: jaez@iberdrola.es Abstract

More information

COWI offshore wind marine engineering services

COWI offshore wind marine engineering services COWI offshore wind marine engineering services 2 COWI expertise COWI is a highly versatile and multidisciplinary company. We provide services within engineering, environment and economics and operate worldwide

More information

Attachment. Spatial Plan for the German Exclusive Economic Zone in the North Sea - Text section. unofficial translation

Attachment. Spatial Plan for the German Exclusive Economic Zone in the North Sea - Text section. unofficial translation Attachment Spatial Plan for the German Exclusive Economic Zone in the North Sea - Text section unofficial translation Contents 1 Introduction... 3 2 Guidelines for spatial development in the EEZ... 3 2.1

More information

NSW Submarine Power. Cables for the future, delivered today.

NSW Submarine Power. Cables for the future, delivered today. Submarine Power. Cables for the future, delivered today. NorddeutSChe Seekabelwerke GmbH () for Renewable Energies The submarine competence center within the General Cable Group After was founded in by

More information

The Application of Rope Access Methods in the Construction, Inspection, Repair and Maintenance of Wind Turbines

The Application of Rope Access Methods in the Construction, Inspection, Repair and Maintenance of Wind Turbines The Application of Rope Access Methods in the Construction, Inspection, Repair and Maintenance of Wind Turbines Introduction IRATA International s rope access system is a safe method of working at height,

More information

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels E-Highway2050 WP3 workshop April 15 th, 2014 Brussels High voltage underground and subsea cable technology options for future transmission in Europe Ernesto Zaccone, Chairman Europacable High Voltage Systems

More information

Siemens D3 platform 3.0-MW, 3.2-MW, 3.3-MW, and 3.4-MW direct drive turbines. Reduced complexity, increased profitability. siemens.

Siemens D3 platform 3.0-MW, 3.2-MW, 3.3-MW, and 3.4-MW direct drive turbines. Reduced complexity, increased profitability. siemens. Siemens D3 platform 3.0-MW, 3.2-MW, 3.3-MW, and 3.4-MW direct drive turbines Reduced complexity, increased profitability siemens.com / wind As the major driver of innovation with more than 30 years of

More information

Maritime spatial planning in BSR and in Poland

Maritime spatial planning in BSR and in Poland Maritime spatial planning in BSR and in Poland Baltic Master II final conference Gdańsk 26 October 2011 Workshop on coastal management Jacek Zaucha, Magdalena Matczak Three parts: MSP - its origin and

More information

Preparatory Paper on Focal Areas to Support a Sustainable Energy System in the Electricity Sector

Preparatory Paper on Focal Areas to Support a Sustainable Energy System in the Electricity Sector Preparatory Paper on Focal Areas to Support a Sustainable Energy System in the Electricity Sector C. Agert, Th. Vogt EWE Research Centre NEXT ENERGY, Oldenburg, Germany corresponding author: Carsten.Agert@next-energy.de

More information

Turnkey cable solutions to better deploy your windfarm infrastructure

Turnkey cable solutions to better deploy your windfarm infrastructure Turnkey cable solutions to better deploy your windfarm infrastructure expertise supports your network s evolution Both on land and offshore, Nexans has the expertise to interconnect large wind turbines

More information

in-service inspections www.sgs.com

in-service inspections www.sgs.com in-service inspections www.sgs.com Minimising down -time for wind turbines One of the major concerns in investing in wind farm projects is related to turbine availability, which represents the risk of

More information

EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION

EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION 1 EFFICIENT ELECTRICAL ENERGY TRANSMISSION

More information

Transmission technologies for collective offshore wind farm connections

Transmission technologies for collective offshore wind farm connections Transmission technologies for collective offshore wind farm connections H. Brakelmann, K. Burges Abstract: Offshore wind farms under development have capacities of 4 MW and higher and are likely to be

More information

NSW Submarine Power. Cables for the future, delivered today

NSW Submarine Power. Cables for the future, delivered today NSW Submarine Power Cables for the future, delivered today NORDDEUTSCHE SEEKABELWERKE GMBH (NSW) The submarine competence center within the General Cable Group After NSW was founded in 1899 by Felten &

More information

OFFSHORE WIND PROCUREMENT

OFFSHORE WIND PROCUREMENT OFFSHORE WIND PROCUREMENT Raymond Cravitz Procurement Manager 17 09 2015 Irish Sea DONG Energy is a leading energy group in Northern Europe Overview #1 in Danish energy markets Global leader in offshore

More information

Contents. 1. PROFILE p2. 2. SERVICES 2.1 Offshore Support Services p 4 Offshore support p 6 ROV operations p 8

Contents. 1. PROFILE p2. 2. SERVICES 2.1 Offshore Support Services p 4 Offshore support p 6 ROV operations p 8 OCTOBER 2013 22 Contents 1. PROFILE p2 2. SERVICES 2.1 Offshore Support Services p 4 Offshore support p 6 ROV operations p 8 2.2 Hydrographic & Geophysical services p 10 Bathymetric surveys p 12 High resolution

More information

Dry-type transformers. Dry-type transformers from ABB The ideal solution for the oil and gas industry

Dry-type transformers. Dry-type transformers from ABB The ideal solution for the oil and gas industry Dry-type transformers Dry-type transformers from ABB The ideal solution for the oil and gas industry 2 Dry-type transformers for the oil and gas industry ABB s products and solutions for the oil and gas

More information

Offshore Windfarm Egmond aan Zee 4 years of Operation

Offshore Windfarm Egmond aan Zee 4 years of Operation Offshore Windfarm Egmond aan Zee 4 years of Operation CUEN Offshore Wind Energy Conference 28 June 2011, Cambridge Elke Delnooz Operations Support Manager www.noordzeewind.nl 1 Contents Project description

More information

Focus on Wind Energy Technology Onshore

Focus on Wind Energy Technology Onshore Focus on Wind Energy Technology Onshore SIAG Schaaf Industrie AG Burgweg 21-23 56428 Dernbach, Germany Phone: +49 (0) 26 02 / 93 40-0 Fax: +49 (0) 26 02 / 93 40-110 E-mail: info@siag-group.com Web: www.siag-group.com

More information

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC).

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC). Who are we? We re one of the world s leading power and gas companies. Here in the UK, we supply energy to more than 5 million customers, generate enough electricity for around 8 million homes and employ

More information

HVDC Light Cables. Submarine and land power cables

HVDC Light Cables. Submarine and land power cables HV Light Cables Submarine and land s The HV Light s to offshore platform The light and robust HV Light s can be laid with very cost effecient methods HV Light System HV Light is a transmission system in

More information

A clean energy solution from cradle to grave

A clean energy solution from cradle to grave Environmental Product Declaration A clean energy solution from cradle to grave Offshore wind power plant employing SWT-6.0-154 siemens.com / wind 2 Assessing the performance of a wind power plant The environmental

More information

1.1 The primary function of the ECDIS is to contribute to safe navigation.

1.1 The primary function of the ECDIS is to contribute to safe navigation. IMO RESOLUTION A.817 (19) PERFORMANCE STANDARDS FOR ELECTRONIC CHART DISPLAY AND INFORMATION SYSTEMS (ECDIS) Note: The IMO Performance Standards for ECDIS are reproduced in this publication for convenience,

More information

Offshore Platform Powered With New Electrical Motor Drive System

Offshore Platform Powered With New Electrical Motor Drive System Offshore Platform Powered With New Electrical Motor Drive System Authors: Jan O. Lamell, M.Sc E.E. ABB Automation Technologies Presenters: Thomas Johansson, M.Sc E.E. ABB Automation Technologies Timothy

More information

User manual data files meteorological mast NoordzeeWind

User manual data files meteorological mast NoordzeeWind User manual data files meteorological mast NoordzeeWind Document code: NZW-16-S-4-R03 Version: 2.0 Date: 1 October 2007 Author: ing. HJ Kouwenhoven User manual data files meteorological mast NoordzeeWind

More information

Power System for Offshore Wind Power

Power System for Offshore Wind Power Wind-Kraft Journal. German Offshore. 1. Auflage 2008. S. 2-3 und Wind-Kraft Journal. German Offshore. 5. Auflage 2008. S. 38-39. Outlook in the future of German North Sea 2020 ower System for Offshore

More information

IMO ROUTEING OF SHIPS, SHIP REPORTING AND RELATED MATTERS

IMO ROUTEING OF SHIPS, SHIP REPORTING AND RELATED MATTERS INTERNATIONAL MARITIME ORGANIZATION E IMO SUB-COMMITTEE ON SAFETY OF NAVIGATION 51st session Agenda item 3 NAV 51/3/6 3 March 2005 Original: ENGLISH ROUTEING OF SHIPS, SHIP REPORTING AND RELATED MATTERS

More information

Siemens Wind Turbine SWT-2.3-108. The new productivity benchmark. www.siemens.com/wind

Siemens Wind Turbine SWT-2.3-108. The new productivity benchmark. www.siemens.com/wind Siemens Wind Turbine SWT-2.3-108 The new productivity benchmark www.siemens.com/wind The industry standard, redefined The Siemens 2.3-MW family has firmly established itself as the tried and tested workhorse

More information

Annex to the Accreditation Certificate D-ZE-12007-01-02 according to DIN EN ISO/IEC 17065:2013

Annex to the Accreditation Certificate D-ZE-12007-01-02 according to DIN EN ISO/IEC 17065:2013 Deutsche Akkreditierungsstelle GmbH Annex to the Accreditation Certificate D-ZE-12007-01-02 according to DIN EN ISO/IEC 17065:2013 Period of validity: 06.05.2014 to 05.05.2019 Holder of certificate: TÜV

More information

Corrosion in offshore wind energy. a major issue. Harald van der Mijle Meijer

Corrosion in offshore wind energy. a major issue. Harald van der Mijle Meijer Corrosion in offshore wind energy a major issue Harald van der Mijle Meijer Corrosion in offshore wind energy A major issue Introduction TNO Den Helder What are the relevant types of corrosion? How to

More information

STATUS OF OFFSHORE WIND ENERGY DEVELOPMENT IN GERMANY

STATUS OF OFFSHORE WIND ENERGY DEVELOPMENT IN GERMANY On behalf of: Deutsche WindGuard GmbH - Oldenburger Straße 65-26316 Varel - Germany +49 (0)4451 9515-0 - info@windguard.de - www.windguard.com Additional [MW] Cumulative [MW] Cumulative (31.12.) Additions

More information

ROADMAP ON MARINE RENEWABLE ENERGY

ROADMAP ON MARINE RENEWABLE ENERGY FAME PROJECT - INTERNATIONAL WORKSHOP TERESA SIMAS 1 20 TH NOVEMBER, 2012 OBJECTIVES Overview of marine renewable energy development and prospects CONTENTS Green House Gas emissions targets Renewable energy

More information

Translating ecological research results into wind farm practice The Danish experience. Niels-Erik Clausen. 2 Risø DTU

Translating ecological research results into wind farm practice The Danish experience. Niels-Erik Clausen. 2 Risø DTU Translating ecological research results into wind farm practice The Danish experience Niels-Erik Clausen We@Sea Conference, Den Helder Holland 12-13 February 2009 Outline The Danish offshore monitoring

More information

Who is National Grid?

Who is National Grid? Who is National Grid? National Grid is a leading international energy infrastructure business In the UK, our business includes electricity and gas transmission networks and gas distribution networks. We

More information

Guidance on vessel traffic services (VTS) in Danish waters

Guidance on vessel traffic services (VTS) in Danish waters Translation. Only the Danish document has legal validity. Guidance no. 9680 of 16 December 2010 issued by the Danish Maritime Authority Guidance on vessel traffic services (VTS) in Danish waters Purpose

More information

Worldwide subsea pipeline cathodic protection surveys

Worldwide subsea pipeline cathodic protection surveys Worldwide subsea pipeline cathodic protection surveys World leaders in subsea pipeline cathodic protection surveys Corrintec are recognised as a world leader in the field of Subsea Pipeline Cathodic Protection

More information

GRAVITY BASE FOUNDATIONS

GRAVITY BASE FOUNDATIONS GRAVITY BASE FOUNDATIONS 2 Crown with reference to Marine All Activity Map Concrete gravity base foundations able to be floated and towed out to deeper water windfarms and installed without specialist

More information

Corporate Snapshot WV Energie AG. July 13

Corporate Snapshot WV Energie AG. July 13 Corporate Snapshot WV Energie AG July 13 About us 2 WV Energie AG: Facts & Figures A joint venture of (primarily) municipal companies in Germany Founded in: 1904 Legal Form: Stockholders: Headquarters:

More information

Estimation of electrical losses in Network Rail Electrification Systems

Estimation of electrical losses in Network Rail Electrification Systems Estimation of electrical losses in Network Rail Electrification Systems Page 1 of 16 Contents 1. BACKGROUND...3 2. PURPOSE...3 3. SCOPE...3 4. DEFINITIONS & ABBREVIATIONS...4 5. NETWORK RAIL INFRASTRUCTURE

More information

MODEL ORDINANCE FOR WIND ENERGY FACILITIES IN PENNSYLVANIA. This Ordinance shall be known as the Wind Energy Facility Ordinance for [municipality].

MODEL ORDINANCE FOR WIND ENERGY FACILITIES IN PENNSYLVANIA. This Ordinance shall be known as the Wind Energy Facility Ordinance for [municipality]. MODEL ORDINANCE FOR WIND ENERGY FACILITIES IN PENNSYLVANIA 3/21/06 1. TITLE This Ordinance shall be known as the Wind Energy Facility Ordinance for [municipality]. 2. PURPOSE The purpose of the Ordinance

More information

RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid

RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid During the 1.5 day workshop, more than 70 participants from industry,

More information

The Energy Triangle Wind Power

The Energy Triangle Wind Power Wind Power The Energy Triangle Wind Power In supplying society with its energy needs, a balance must be struck between three key dimensions: competitiveness, security of supply, and environment and climate.

More information

HVDC Technology for Large Scale Offshore Wind Connections

HVDC Technology for Large Scale Offshore Wind Connections HVDC Technology for Large Scale Offshore Wind Connections Nandan Mahimkar, Gunnar Persson,Claes Westerlind, ABB AB, SE-771 80, Ludvika, Sweden, nandan.mahimkar@in.abb.com, gunnar.persson@se.abb.com,claes.westerlind@se.abb.com,

More information

THE FUTURE OF THE OCEAN ECONOMY: AN OECD/IFP FORESIGHT PROJECT

THE FUTURE OF THE OCEAN ECONOMY: AN OECD/IFP FORESIGHT PROJECT THE FUTURE OF THE OCEAN ECONOMY: EXPLORING THE PROSPECTS FOR EMERGING OCEAN INDUSTRIES TO 2030 AN OECD/IFP FORESIGHT PROJECT BARRIE STEVENS OECD/DSTI Verftskonferansen 2013 Alesund, Norway, 5 th November

More information

GREEN POWER ISLAND DENMARK GOTTLIEB PALUDAN ARCHITECTS RISØ-DTU

GREEN POWER ISLAND DENMARK GOTTLIEB PALUDAN ARCHITECTS RISØ-DTU DENMARK GOTTLIEB PALUDAN ARCHITECTS RISØ-DTU - the instant and low tech answer to the growing problem of green energy overflow Pumped hydro Definition: Pumped storage hydroelectricity is a type of hydroelectric

More information

EUROPASS DIPLOMA SUPPLEMENT

EUROPASS DIPLOMA SUPPLEMENT EUROPASS DIPLOMA SUPPLEMENT TITLE OF THE DIPLOMA Técnico Superior en Energías Renovables TRANSLATED TITLE OF THE DIPLOMA (EN) (1) Higher Technician in Renewable Energy Sources --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

More information

Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms

Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms As offshore wind farms move towards deploying higher capacity

More information

Establishing large-scale trans-boundaries MPA networks: the OSPAR example in North-East Atlantic

Establishing large-scale trans-boundaries MPA networks: the OSPAR example in North-East Atlantic Establishing large-scale trans-boundaries MPA networks: the OSPAR example in North-East Atlantic Introduction A pledge to establish a representative network of marine and coastal protected areas by 2012

More information

DANISH DISTRICT ENERGY PLANNING EXPERIENCE

DANISH DISTRICT ENERGY PLANNING EXPERIENCE MOWAT ENERGY, A RESEARCH HUB AT THE MOWAT CENTRE, AT THE REQUEST OF THE ONTARIO MINISTRY OF ENERGY FUTURE INNOVATION IN ENERGY PLANNING: A SPECIAL SESSION TO ADVISE ON ONTARIO S LONG-TERM ENERGY FUTURE

More information

Generating Current Electricity: Complete the following summary table for each way that electrical energy is generated. Pros:

Generating Current Electricity: Complete the following summary table for each way that electrical energy is generated. Pros: P a g e 1 Generating Current Electricity: Complete the following summary table for each way that electrical energy is generated. Generating Electrical Energy Using Moving Water: Hydro-Electric Generation

More information

Business Policy of CEZ Group and ČEZ, a. s.

Business Policy of CEZ Group and ČEZ, a. s. Business Policy of CEZ Group and ČEZ, a. s. Contents: Introduction 1. CEZ Group mission and vision 2. Scope of business of CEZ Group 3. Business concept Guiding principles Trade Generation Electricity

More information

Wind Turbine Power Calculations

Wind Turbine Power Calculations Wind Turbine Power Calculations RWE npower renewables Mechanical and Electrical Engineering Power Industry INTRODUCTION RWE npower is a leading integrated UK energy company and is part of the RWE Group,

More information

OFFSHORE WIND ENERGY IS GETTING CHEAPER

OFFSHORE WIND ENERGY IS GETTING CHEAPER OFFSHORE WIND ENERGY IS GETTING CHEAPER Market foresight and scale drive the cost down Dansk Energi, January 14, 2016 Sune Strøm, Manager, Regulatory Affairs Wind Power Offshore wind is closing in on the

More information

Design of Offshore Wind Farms Prepared by Flemming Jakobsen & Andrass Ziska Davidsen LICENGINEERING A/S

Design of Offshore Wind Farms Prepared by Flemming Jakobsen & Andrass Ziska Davidsen LICENGINEERING A/S Design of Offshore Wind Farms Prepared by Flemming Jakobsen & Andrass Ziska Davidsen Types of Foundations Overview of selected support structure and foundation types. From top left: 1. Monopile; 2. Tripod;

More information

environment briefing02

environment briefing02 PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The

More information

HYDROMATRIX Jebel Aulia - Sudan

HYDROMATRIX Jebel Aulia - Sudan HYDROMATRIX Jebel Aulia - Sudan www.andritz.com HYDROMATRIX - Concept Jebel Aulia - Sudan HYDROMATRIX is a new concept of hydraulic energy generation, which has been developed by an American engineer in

More information

OFFSHORE WIND TOWARD 2020 ON THE PATHWAY TO COST COMPETITIVENESS

OFFSHORE WIND TOWARD 2020 ON THE PATHWAY TO COST COMPETITIVENESS 1 OFFSHORE WIND TOWARD 2020 ON THE PATHWAY TO COST COMPETITIVENESS April 2013 Contents A B C Offshore market volume of EUR 130 bn by 2020 Agenda 2020 Markets Trends Competition Page 3 Value chain evaluation

More information

Offshore Renewable Energy Services and solutions

Offshore Renewable Energy Services and solutions Offshore Renewable Energy Services and solutions Where will our knowledge take you? Contents : Metocean Information Services : Marine Operations and Risk 3 3: Specialist Vessel Design 4: Engineering 4

More information

Summary of Electric Transmission Assessment Report

Summary of Electric Transmission Assessment Report Summary of Electric Transmission Assessment Report January 2010 Assessment and Analysis of the State-Of-the-Art High-Voltage Electric Transmission Systems with Specific Focus on High-Voltage Direct Current

More information

12.5: Generating Current Electricity pg. 518

12.5: Generating Current Electricity pg. 518 12.5: Generating Current Electricity pg. 518 Key Concepts: 1. Electrical energy is produced by energy transformations. 2. Electrical energy is produced from renewable and non-renewable resources. 4. Electrical

More information

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009 Preliminary Information Memorandum Thanet Offshore Transmission Assets July 2009 SUMMARY In April 2009 Ofgem distributed a teaser document, UK Offshore Transmission Investment Opportunity, to investors

More information

Offshore Wind Farm Layout Design A Systems Engineering Approach. B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy

Offshore Wind Farm Layout Design A Systems Engineering Approach. B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy Offshore Wind Farm Layout Design A Systems Engineering Approach B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy 0 Paper presented at Ocean Power Fluid Machinery, October 2010 Offshore Wind

More information

./01&2/M./T34 1MP36T ST3T.M./T. 1a$t3l$4 536e-al4 13$7363 83%3te9. Sol9ara 1 Pro;ect. !"l$%e ( Mai$ &e(ort. Te-t. )e*te%,e- 2//0 :; <//0=>=?

./01&2/M./T34 1MP36T ST3T.M./T. 1a$t3l$4 536e-al4 13$7363 83%3te9. Sol9ara 1 Pro;ect. !l$%e ( Mai$ &e(ort. Te-t. )e*te%,e- 2//0 :; <//0=>=? ./01&2/M./T34 1MP36T ST3T.M./T 1a$t3l$4 536e-al4 13$7363 83%3te9 Sol9ara 1 Pro;ect!"l$%e ( Mai$ &e(ort Te-t )e*te%,e- 2//0 :; =?@ ENVIRONMENTAL IMPACT STATEMENT VOLUME A: MAIN REPORT TEXT CR 7008_09_v4

More information

Applications. Civil engineering specialist civil engineering, road and path construction sewer and pipeline construction landfill technology

Applications. Civil engineering specialist civil engineering, road and path construction sewer and pipeline construction landfill technology Range of products and services Range of products and services Applications Lighting systems street and tunnel lighting, square and path lighting lighting for railway, motorway, airports lighting for stadiums

More information

QUALITY OF WIND POWER. How does quality affect the cost of electricity generation from wind power?

QUALITY OF WIND POWER. How does quality affect the cost of electricity generation from wind power? QUALITY OF WIND POWER How does quality affect the cost of electricity generation from wind power? QUALITY OF WIND POWER Wind power is a cornerstone in the green transition of the power sector, and onshore

More information

BMP Guidelines. Environmental Impact Assessment (EIA) report for activities related to hydrocarbon exploration and exploitation offshore Greenland

BMP Guidelines. Environmental Impact Assessment (EIA) report for activities related to hydrocarbon exploration and exploitation offshore Greenland BMP Guidelines for preparing an Environmental Impact Assessment (EIA) report for activities related to hydrocarbon exploration and exploitation offshore Greenland Danish National Environmental Research

More information

Facility Support Services

Facility Support Services Facility Support Services The Precision Group has a breadth of experience delivering innovative, first class facility support service solutions to clients across the public and private sectors. Our expert

More information

Esa Jokioinen Rolls Royce Marine 10.9.2014 MUNIN Workshop at SMM. Trusted to deliver excellence

Esa Jokioinen Rolls Royce Marine 10.9.2014 MUNIN Workshop at SMM. Trusted to deliver excellence Esa Jokioinen Rolls Royce Marine 10.9.2014 MUNIN Workshop at SMM 2014 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third

More information

I refer to the application made by Aquamarine Power Ltd. ( the Company ), dated 17 th June 2011 for:

I refer to the application made by Aquamarine Power Ltd. ( the Company ), dated 17 th June 2011 for: Ms Megan Richardson Aquamarine Power Ltd. Elder House 24 Elder Street Edinburgh EH1 3DX 14 February 2012 Dear Ms. Richardson, CONSENT FOR THE CONSTRUCTION AND OPERATION OF AN OFFSHORE DEMONSTRATOR WAVE

More information

NSW OFFSHORE AND SPECIAL CABLES. Cables for the future, delivered today.

NSW OFFSHORE AND SPECIAL CABLES. Cables for the future, delivered today. NSW OFFSHORE AND SPECIAL CABLES. Cables for the future, delivered today. NORDDEUTSCHE SEEKABELWERKE GMBH (NSW) The submarine competence center within the General Cable Group NSW was founded in 1899 by

More information

Offshore Wind China 2010 Bergen, 15th March 2010. Olivier Angoulevant Nexans Norway AS

Offshore Wind China 2010 Bergen, 15th March 2010. Olivier Angoulevant Nexans Norway AS Offshore Wind China 2010 Bergen, 15th March 2010 Olivier Angoulevant Nexans Norway AS At the core of performance At the core of performance : a worldwide leader Worldwide leader in cables, cabling systems

More information