Calgary Regional Partnership. Regional Transit Service Business and Funding Models

Size: px
Start display at page:

Download "Calgary Regional Partnership. Regional Transit Service Business and Funding Models"

Transcription

1 Calgary Regional Partnership Regional Transit Service Business and Funding Models

2 Project Schedule January 2015 December 2015 January December 2016 Jan 2015 Phase 1A: Develop Business Model Phase 1B: Develop Funding Model APPROVAL May 2016 Workshop #1 Summary of What We Heard & Outline of Business/Funding Models & Evaluation Criteria Workshop #2 Summary of Evaluated & Shortlisted Business Models, Funding Options, Service Plan, New CPRP Partnership Model and Identified Member and Customer Benefits (More Cost - Benefit Analysis to be Done with Sep. Report) Model Foundation Report Submission of Recommended Business/Funding Model Report mid-sep. with Approval By Year End Late Nov 2015 Preliminary Implementation Strategy and Operating Bylaw Phase 2: Develop Implementation Strategy & Approval (will be shortened) Workshop #3 Consultation, Draft Implementation Report Submission Final Implementation Report Submission Oct 2016 Presentation to CRP Committees and Councils WE ARE HERE

3 Project Schedule Workshop #1 Workshop #2 Summary of Business/Funding Model Evaluation (More Details on Cost Benefit Analysis to Be Undertaken) WE ARE HERE

4 Project Schedule Workshop #2 Final Report Submission Recommended Obtain Approval WE ARE HERE Implementation Plan Strategy

5 June Workshop Objectives

6 Workshop Objectives Update from Last Workshop Summarize Evaluation of 4 Models We Examined Introduce New Model-CRP Partnership Company Model- Building on Foundation Established with South Pilot Service Work Outline Strategic 20 Year Service Plan and Costs Outline Some Funding Models Options-Decision Trees Have Breakout for Input/Discussion Discuss Benefits to Members, Existing Service Providers and Customers of New Business/Funding Model Outline Where We Are in Work Schedule and Future Directions

7 Workshop # 2 Agenda 1. April Workshop Summary Key Points 2. Four RFP Business Models and Evaluation 3. New CRP Partnership Company Model and Evaluation 4. Strategic Transit Service Plan 5. Plans s Operating and Capital Costs 6. Transit Funding Models Breakout - Discussion, Questions 7. Benefits - New CRP Business/Funding Model and Sharing Resources 8. Why Move Now? 9. Future Directions ENGAGE EVALUATE ENVISION NEW CRP BUSINESS & FUNDING MODEL IMPLEMENTATION

8 Breakout Questions 1. What key benefits and challenges do you see from the standpoint of CRP owning and operating regional transit service? 2. What important issues or questions need to be addressed to make this model work? 3. Please rank the 3 business models-commission, controlled corporation and partnering company. ENGAGE EVALUATE ENVISION NEW CRP BUSINESS & FUNDING MODEL IMPLEMENTATION

9 1. April Workshop Summary Key Points

10 Workshop Key Points Preference for Regional Transit Service Commission and Controlled Corporation. Strongest evaluation criteria: Clarity of oversight and responsibility Accountability Success obtaining funding Transit service coordination Increased efficiency and effectiveness Desired sustainable funding and fair formula for sharing: Consider: population, equalized assessment, capacity - hrs. or kms, equal municipal share and in future - ridership

11 Key Points All members need skin in the game annual contributions, and clear exit/entry rules. High quality service. Desired weighted voting. Local transit service- primary municipal responsibility. Realization that transit enhancements generate many benefits employment mobility, economic development, greenhouse gas reductions, and land use planning objectives. Cannot achieve future transit vision and success if all are working independently

12 Short-listed Evaluation Criteria Land Use and Transit Integration Responsiveness/Adaptability to Changing Conditions Regional Transit Service Coordination Accountability Recognizes Differences Among Members by Weighted Voting Enhances Efficiency and Effectiveness in Transit Services Able to Best Obtain Funding Strong Transit Advocacy to Senior Governments Regional Mobility Enhancements Clarity of Oversight and Responsibility Transparency

13 2. Four RFP Business Models and Evaluation

14 Business Model RFP Options Examined To Date Inter-Municipal Partnership Regional Transit Services Commission Controlled Corporation Cooperative Note: Models above do not work with/integrate current CRP Inc. as Part 9 Company compared to establishing internal separate regional service identify

15 Business Model - Inherent Strength and Issues Regional Transit Services Commission Widely used in North America for public transit systems, and there are implementation plans. Board members have fiduciary duty to the RTSC and not to the municipalities they come from. Board can have elected and non-elected members. Board can have weighted voting. Can borrow through the Alberta Capital Finance Authority (ACFA). Can expropriate land.

16 Business Model - Inherent Strength and Issues (cont.) Cooperative Model Generally not used as model in Canada or North America for public transit systems other than very small paratransit services (i.e. Nova Scotia, Coast Cooperative Alliance for Seacoast Transportation in NH). More used for taxis, car sharing and school transit systems. Can only have weighted voting imperfectly with more members. Harder to mandate financial responsibility and equitable rules on membership withdrawals. Cannot expropriate land or borrow from ACFA.

17 Business Model - Inherent Strength and Issues (cont.) Controlled Corporation More inclined to operate in business-like form than RTSC, therefore tends to not subsidize transit costs. Cannot expropriate land and use ACFA. Greater autonomy/separation from municipalities than the RTSC, but requires annual meetings with the municipalities in the Region. Board members have a fiduciary duty to the controlled corporation and not to the municipalities. Cannot borrow from the ACFA and expropriate land. Is not recognized as a common form of regional transit service business unit in North America but could be recognized as eligible transit for funding. Likely to require more time to get approval.

18 Detailed Business Model Evaluation Criteria Base Case Regional Transit Services Controlled Corporation Cooperative Purchase Capital Assets Weighted Votes Ability N/A Difficulty in Obtaining Provincial Approval Requires Strong Business/Funding Plan Transparency in Decision Not Suited Clarity of Oversight and Responsibility Clear Accountability to Requirements Greater Efficiency and Effectiveness Stronger & Coordinated Regional and Local Transit Services Less Suited Adequately Suited Advocate For Increased Funding/Friendly Policy Changes to Senior Governments Ability to mixed politicians and non-elected as directors Best Suited Funding Eligibility from Provincial & Federal Transit Capital Program High Clarity of Purpose Representativeness Can Obtain ACFA Funding Higher Desire to Restrain Costs Degree of Allegiance of Board Members to Regional Agency and Transfer of Power Powers of Expropriation Degree of Start-Up costs Profit Distribution Liability Transfer Responsiveness/Adaptability to Change Ability to Establish Membership Fees Ability to Integrate Transit Service and Land Use Best Meet the Criteria

19 Model Evaluation Note: Models above do not work with/integrate current CRP Inc. as Part 9 Company compared to establishing internal separate regional service identify

20 3. New CRP Partnership Company Model and Evaluation

21 Business Model Options CRP Incorporated was created in 1999 as Part 9 Company under Alberta Companies Act Can own and purchase transit capital assets It is non profit corporation (i.e. simply can t distribute any profits to members) Borrowing from AFCA and expropriating lands would have to be done through municipal members

22 Business Model Options With CRP as Part 9 Company can: Integrate regional transit agency as part of CRP Would have to adhere by land use CMP and servicing plans and policies Can have weighted voting For good business practices would want to keep financial, operational and administrative issues separate from other CRP areas Can have its new own Board and linkages to main Board Would establish via Implementation Plan and Operating Bylaw

23 Calgary Regional Partnership Future for Pilot Service and After-Transition in 3 rd Yr. Servicing (Water, etc.) Board Executive Committee Land Use Planning New CRP Staff Transit Functions - Regional Marketing /Branding, Communications/Education, Short/Strategic Planning, Financing and Capital Planning, Operations and Contracts o Potential contributed to by Membership Fees related to Population and Equalized Assessment Committees CRP Partnership Company Model Board Hybrid Members Could Be Politicians and Others Operating Bylaw & Clear Linkages to Board and Land Use and Servicing Plans Members Capital o Purchase of Vehicles & sharing on Cost of Park & Ride, Exchanges and Maintenance Facilities (Local & Regional) Funding o Cost sharing of Municipalities with formulaequal share, population, service hrs. etc. o Canada Building Infrastructure o GreenTRIP o Gas Tax o FCM Fund o Seed Funding Province Operating o Coordinate and Handle Functions for New Regional Services o Contractors - Operations Funding o Cost sharing Municipalities with formula o Fares, Advertising, Business Partnerships, others Benefits: Clear Oversight and Accountability Sharing of Vehicles & Other Capital Facilities for Regional and Local Transit Services (fewer facilities required) Assistance from Above Transit Functions New Regional Connections Negotiate with Railway Fare Integration and Consistent Standards Share Best Practices Research

24 CRP Partnership Company Model Evaluation ALTERNATIVE BUSINESS MODELS AND EVALUATION CRITERIA Regional Transit Service Entity within CRP Can Purchase Capital Assets Can purchase transit capital assets-buses, maintenance facilities etc. Ability for Weighted Votes Can have weighted votes for Board Directors to recognize population differences in municipalities Degree of Difficulty in Obtaining Provincial Approval Length of time for Provincial approval and degree of difficulty of implementation Requires Strong Business Plan and Sustainable Funding Model Transparency in Decision Making Greater transparency of making decisions Clarity of Oversight and Responsibility Clear Accountability to Requirements for a Regional Public Transit System and needs of Local Municipalities Can Achieve Greater Efficiency and Effectiveness-Transit Functions and Capital Requirements Can work towards greater efficiency and effectiveness of regional transit services delivery-in terms of delivering transit operational and administrative functions, and in terms of capital requirements Ability To More Strongly, Coordinate Regional and Local Transit Services Ability to Successfully Advocate For Increased Funding/Friendly Policy Changes to Senior Governments-Common to have relationships with senior governments to advocate for transit funding and transit friendly policy changes LEGEND: Best Suited Adequately Suited Less Suited Not Suited

25 CRP Partnership Company Model Evaluation (cont.) ALTERNATIVE BUSINESS MODELS AND EVALUATION CRITERIA Regional Transit Service Entity within CRP Ability to have mix of politicians and non-elected as directors Eligibility for Funding from Provincial and Federal Transit Capital Program such as GreenTRIP and Canada Building Infrastructure Fund High Clarity of Purpose - degree to which agency understands and acts on its direct and indirect purposes. Representativeness - extent of the ability of citizens in CRP to provide direct public input on decision-making and addressing issues needed Can Obtain ACFA Funding-Can borrow low cost capital from Alberta Capital Funding Authority Would have to go through one of the Municipal members Higher Desire to Restrain Costs due to Business Model Degree of Allegiance of Board Members to Regional Agency and Transfer of Power--Board Members Must have Firm Allegiance to Regional Transit Agency versus the Local Municipality they are from Powers of Expropriation-Can directly expropriate land Degree of Start-Up costs Would have to go through one of the Municipal Profit Distribution- Can distribute profits to members Liability Transfer -Transfers more liability to regional transit identity versus municipality LEGEND: Best Suited Adequately Suited Less Suited Not Suited

26 CRP Partnership Company Model Evaluation (cont.) ALTERNATIVE BUSINESS MODELS AND EVALUATION CRITERIA Regional Transit Service Entity within CRP Responsiveness/Adaptability to Change to Required Changes (i.e. to grow or to respond to future social, economic etc., changes and service needs) Is very adaptable and responsive to required changes and transition over time. Can Establish Membership Fees- Can set membership fees Establishing Required Transit Staff Expertise- Can establish transit staff expertise in a number of areas and will have additional resources to do so Ability To Establish Strong Exit and Entry Membership Rules-Ability to establish strong financial and time commitments for members to protect the investment interests of other members Exempt from Paying GST and Local Property Taxes Ease of Collaboration, Communication and Coordination with Local Municipalities from Previous History Ease of Changing Governing Corporate Documents Municipal Affairs approval Required to sell Assets Issuance of Shares Ability to Integrate Transit Service and Land Use -Able to best integrate transit plans and policies with regional land use and policies LEGEND: Best Suited Adequately Suited Less Suited Not Suited

27 4. Strategic Transit Service Plan

28 Input/Background for Strategic Plan (cont.) The City of Calgary s Investing in Mobility: The 10 Year Infrastructure Plan Study and RouteAhead. Estimates prepared by AECOM using industry standards and reasonable revenue cost ratios for local and regional services. Standard types of buses: regional service (coach buses and articulated buses) local service (cutaway shuttles and others) Standard costs for 50 buses or smaller bus maintenance/storage facilities, park and ride lots, and transit exchanges or cost estimates from the GreenTRIP application and other sources.

29 Input/Background for Strategic Plan CRP Pilot Feasibility Study on Nanton Black Diamond/Turner Valley-High River-Okotoks to Calgary. CRP GreenTRIP Application Previous transit feasibility studies completed for Okotoks, Cochrane, and Chestermere. Regional Transit Governance Phase 1 Report and Scenario 2. Airdrie Transit Capital Investment Plan and their recent Transportation Master Plan. Input from the City of Airdrie.

30 Proposed Regional Services in Strategic Plan (15-20yrs) A Strathmore - Chestermere service to Calgary downtown service, a Cochrane to Calgary LRT service and the Nanton - High River - Turner Valley/Black Diamond - Okotoks - Calgary LRT service. Weekend tourism train service between Calgary - Cochrane and Canmore, Banff and Lake Louise. An Iricanna to Calgary service through Airdrie. The following new regional connector services: Airdrie - Cochrane; Okotoks - Chestermere - Strathmore through Calgary; Strathmore - Chestermere to Airdrie through Calgary; Cochrane - Canmore; and Okotoks - Airdrie through Calgary.

31 New Proposed Services in Strategic Plan (15-20yrs) A new Airdrie ICE service - new routes and a future BRT ICE service. The enhancement of the existing Airdrie regional ICE service. The extension of the Canmore - Banff regional service to the Village of Lake Louise. The introduction of regional summer service in the BVRTSC to the camping areas. The provision of a new regional service in the Village of Lake Louise to Lake Louise and Lake Moraine.

32 Proposed Local Services in Strategic Plan (15-20yrs) Enhanced local service - Airdrie, Banff New Local Services in: Canmore Strathmore Chestermere Okotoks High River Cochrane

33 Regional and Local Transit Services Map Lake Louise Enhance Local Service & Extend Regional Service to Lake Louise Village Enhance Local Service & Regional ICE Service Lake Moraine Provide services to campground areas during Summer Canmore Banff Introduce Service to Lake Louise and Lake Moraine Bow Valley Initiate Local Service Cochrane Calgary Airdrie Chestermere Irricana Existing Bus Service with Planned Enhancements (service frequency increase, more buses, longer route) Initiate Local Service Turner Valley Somerset-Bridlewood Station Black Diamond Downtown Okotoks Strathmore Initiate Local Service Future Bus Service Future Rail Service Initiate Local Service High River Initiate Local Service Nanton

34 5. Plan s Capital and Operating Costs

35 Capital Cost - Regional Transit Service (15-20 Years) Regional Transit Service Elements From Number of Vehicles Direct Costs Average Annual Debt Strategic Transit Plan Facilities (Million) Cost (Compounding 2% Interest) Life Cycle of Asset VEHICLES Coaches-other Regional Connectors 45 $38 $ years Cutaways-BVRTSC Sub-total 4 49 $1.00 $39.00 $0.16 $ years PARK AND RIDE LOTS Park and Ride Facilities-Okotoks, Strathmore, Chestermere, Airdrie, Cochrane, Lake Louise/Lake Moraine 6 $6 $ years Intercept Facilities - Canmore and Banff 2 $6 $ years Sub-total 8 $12 $0.76 MAINTENANCE/STORAGE FACILITIES - 50 buses or less in case of Canmore and Banff-number may be able to be reduced ** Banff/Canmore- enlarged (Banff) or reused for buses- Canmore 2 $8 $ years Airdrie 1 $8 $ years Cochrane 1 $10 $ years Okotoks 1 $10 $ years Chestermere/Strathmore 1 $10 $ years Sub-Total 6 $46 $2.87 TRANSIT EXCHANGES Cochrane, Strathmore, Okotoks, Airdrie, Chestermere, Banff, Canmore 7 $20 $ years Sub-Total 7 $20 $1.22 OTHER Bus Zones-shelters, real time displays, shelters 13 $3.30 $ years Sub-Total 13 $3.30 $0.20 GRAND TOTAL $ $7.78

36 Capital Cost - Local Transit Service (15-20 Years) Local Transit Service Elements From Strategic Transit Plan Number of Vehicles or Facilities Direct Costs (Million) Average Annual Debt Cost (Compounding 2% Interest) Life Cycle of Asset VEHICLES Cutaways-BVRTSC 19 $10 $ years Sub-total 19 $10 $1.55 OTHER Bus Zones-shelters, real time displays, shelters $3 $ years Sub-Total $3 $0.19 GRAND TOTAL $

37 Local & Regional Transit Service (15-20 Years) Strategic Regional Transit Service Plan Summary of Local and Regional Operating and Capital Cost Costs YEARS REGIONAL TRANSIT SERVICES TOTAL (without Debt Charges) in millions TOTAL CAPITAL COSTS - 20 YEARS $ ANNUAL CAPITAL COSTS $ 6.00 TOTAL OPERATING COSTS - 20 YEARS $ ANNUAL OPERATING COSTS (ABOVE 40%-50% Cost Recovery Fares) $ 3.80 ANNUAL OPERATING COSTS (AT 75%) $ 2.80 LOCAL TRANSIT SERVICES TOTAL CAPITAL COSTS - 20 YEARS $ ANNUAL CAPITAL COSTS $ 0.70 TOTAL OPERATING COSTS - 20 YEARS $ ANNUAL OPERATING COSTS (25% Cost-Recovery Fares) $ 4.70 REGIONAL SERVICES - TOTAL $ REGIONAL SERVICES - ANNUAL $ 9.80 LOCAL SERVICES - TOTAL $ LOCAL SERVICES - ANNUAL $ 5.40

38 6. Transit Funding Models

39 CRP Transit Operating Costs Funding Funding Transit Operating Costs New Business Transit Operating Funding Model Yes (Control Now) CRP Business Funding Model Options No (Future Potential) Enable New Regional Transit to be Provided Transit Fares - Various Recovery Targets Advertising Revenues Business Partnerships Municipal Gas Tax Funds contribute to CRP-Transit Local Municipality Operating Cost Share - MSI, Property Taxes, New Parking Fees CRP Regional Members Annual Transit Fees Administrative Contribution Potential New Sources %-50% Fare plus Municipal Contributions based on A Combination of Service Hrs., Kms. & Equalized Assessment, Population and Equal Share 75% Fare Recovery until 100% is reached in 3-5 Years plus Municipal Contributions based on A Combination of Service Hrs., Kms. & Equalized Assessment, Population and Equal Share 100% Fare Recovery Post 5 years New Regional Services Commission Grants, Enhanced Fuel Taxes, Parking Fees Fuel Tax Increase Funds Provincial Sales Tax Share Provincial Education Property Tax Share Private Sector Partnership Funds Funds From New Sources Regional License Fees or Vehicle Registration Fees, Funding Sources Newly Established in Calgary and Edmonton Regions for Economic Contribution of Transit Enable New Regional Transit to be Expanded More Quickly

40 CRP Transit Capital Costs Funding Funding Transit Capital Costs New Business Transit Capital Funding Model Yes (Control Now) CRP Business Funding Model Options No (Future Potential) GreenTRIP Program Building Canada Infrastructure Fund Small Community Portion FCM Green Municipal Fund Potential Other Sources Development Charges Business Partnerships, Parking Charges Regional License Fees or Vehicle Registration Fees, Funding Sources Newly Established in Calgary and Edmonton Regions for Transit Economic Benefit Fuel Tax Increase Funds Provincial Sales Tax Share Provincial Education Property Tax Share Private Sector Partnership Funds Funds From New Sources

41 Cost Allocation Who pays what? Each municipality is responsible for the local infrastructure related costs such as shelters and bus stop facilities. Regional infrastructure capital costs such as transit interchanges and terminals, park and ride lots, and storage/maintenance facilities to be shared by the new regional transit service organization and by all member municipalities. Regional operating/administrative costs paid for by transit fares, cost sharing formula and other funding programs, including annual membership fees.

42 Annual Membership Fees Could be based upon different population levels and equalized assessment. Would be used for administration/operating fees of new regional transit service entity. Recognize that all members benefit in terms of enhanced employment mobility, economic development, reduced congestion and road use, consulting assistance from regional transit service agency, reduced regional greenhouse gas emissions etc.

43 Breakout Discussion, Questions

44 Breakout Questions 1. What key benefits and challenges do you see from the standpoint of CRP owning and operating regional transit service? 2. What important issues or questions need to be addressed to make this model work? 3. Please rank the 3 business models-commission, controlled corporation and partnering company. ENGAGE EVALUATE ENVISION NEW CRP BUSINESS & FUNDING MODEL IMPLEMENTATION

45 7. Benefits-New CRP Business/Funding Model and Sharing Functions & Resources - Members/Customers

46 Benefits to Members Experience Examples Overall staff savings in required transit functions 4 to 5 positions or $0.4 million. Lower total costs (i.e. design and maintenance) in transit infrastructure for vehicles, park and ride lots, storage/maintenance facilities, technology and transit exchanges facilities shared for local and regional transit services. Optimized service, marketing, fares, standards/performance, scheduling designed for customer convenience. Stronger force in obtaining funds and negotiating to agencies such as the province and railways. Coordination and implementation of new regional services is easier with one agency than 13 municipalities.

47 With Regional Transit Services Business Model 5 positions 7.6 positions Total positions Savings from constant model positions Full Build Out-Regional Transit Services Board / Corporation (Mix of Elected Regional Board at Large & Directors Granted by Shareholders) Committees of Regional Board (Use of Consultants) Regional Service Transit Manager (Limited Use of Consultants) 1 Staff Linkages to CRP Board and Executive Committee, Land Use, Servicing Plans and Policies Communication & Education Lead 1 Staff Regional Marketing & Branding Finance & Capital Investments with Vehicle Procurement Lead 1 Staff Service and Strategic Planning Lead (Short & Long Term) 1 Staff Operations & Contracts 1 Staff Municipality Transit Staff (Developing/Implementing Local Services with regional assistance with some functions) Airdrie Staff 1 Staff 2 Staff 3 Nanton 0.1 Staff BVRTSC Canmore Banff Staff 1 Staff 2 Calgary Existing High River 0.1 Staff Okotoks 0.5 Staff BD/TV 0.1 Staff Irricana 0.1 Staff Chestermere Strathmore Cochrane 0.25 Staff 0.2 Staff 0.25 Staff Staff 4

48 Without Regional Transit Services Business Model CRP Board & Executive Committee 2 positions 14.9 positions Total 16.9 positions Regional Transportation & Mobility Committee Transit Services Manager & Assistant 2 Staff Very Limited Use of Consultants Municipality Transit Staff (slowing developing local services and limited new regional services) Airdrie BVRTSC Calgary High River Okotoks BD/TV Irricana Chestermere Strathmore Cochrane Nanton Staff 1 Staff 1 Existing Staff 1 Staff Staff 0.2 Staff Staff Staff Staff Staff Staff 2 Staff Staff Staff 3 Staff 3 Staff 4 Staff 4 Staff 5

49 Benefits to Members Experience Examples (cont.) Sharing costs of service via formulas combination factors such population, equal partner share, equalized assessment, km or service hrs. and future ridership. Ability to provide functions to local municipalities research of best practices etc., and low cost consulting for the development of local services. Developing standardized contracts with excellent performance components. Developing new funding forms and negotiating with the province.

50 Benefits to Members Experience Examples (cont.) Procurement of vehicles. Acquiring transit technology. Establishing consistent fare integration and transfer policies. Conducting and disseminating best practices research. Generating greater leverage for funding governments, private sector partnerships. Negotiating with railways.

51 Benefits to Airdrie and BVRTSC New regional service connections to Airdrie and BVRTSC. Assistance for local transit services planning, etc. at a lower cost. Future staffing costs reduction for Airdrie Transit and BVRTSC. Total transit capital costs reduction for vehicles, Park and Ride facilities, bus maintenance/storage facilities, bus exchanges and new transit technology. Improvement of all regional and local transit services for the customers in terms of needs.

52 GreenTRIP - Airdrie & BVRTSC Transit Capital Investments TRANSIT CAPITAL INVESTMENTS TOTAL COST (MILLIONS) GREENTRIP REQUEST REMAINING AMOUNT GENERATES SAVINGS NEW REGIONAL BUSINESS MODEL ADDITIONAL CONTRIBUTION TO CAPITAL PROJECTS TO REDUCE AIRDRIE TRANSIT S AND BVRTSC S CONTRIBUTION AIRDRIE Transit Zone Improvements savings yes if some were for regional service Transit Technologies savings yes if some were for regional service Transit Facility - Maintenance Regional Fleet Expansion Transit Terminals Total BVRTSC Bus Storage/Maintenance Facility in Banff Canmore Transit Hub Banff Transit Hub Lake Louise and Lake Moraine Service - Buses Total Reduced by contributions from CRP, and other members Reduced by contributions from CRP, and other members savings yes intent is to share maintenance facilities for local and regional service, and costs could be reduced if heavy maintenance placed in another maintenance facility in the region or if can be shared with Chestermere/ Strathcona savings yes CRP would contribute and costs could be further reduced with CRP procurement savings yes as transit terminals/exchanges to be shared for local and regional service CRP new regional transit service business/funding model contributions would reduce Airdrie Transit s total of $7.69 million savings yes Intent is to share maintenance facilities for local and regional service, and cost could be reduced if heavy maintenance placed in another maintenance facility in the region savings yes as transit terminals/exchanges to be shared for local and regional service savings yes as transit terminals/exchanges to be shared for local and regional service savings yes CRP would contribute and costs could be further reduced with CRP procurement of vehicles CRP new regional transit service business/funding model contributions would reduce BVRTSC transit s total of $5.45 million

53 Car User s Perspective To Transit

54 Enhanced Customer Service Experience under New Model Clear and consistent information on complete trips. Consistent safety/security and performance standards. Integrated fare media and transfer policies so trips are seamless, affordable, accessible and coordinate before and after Calgary Connect Smart card Provide common and consistent marketing/branding information and quality service recognizable by customer. Easy and seamless connections between local and regional services. Consistent customer communications and messaging.

55 Customer s Perspective Initial Stage of New Model

56 Customer s Perspective New Model Implementation

57 8. Why MOVE NOW?

58 Benefits Why Move Now? Enhance employment mobility and regional economic competitiveness. Not as difficult as first envisioned as CRP Inc. is Part 9 Company Take advantage of ACFA, low interest environment and more positive government attitude towards transit investments with strong regional model. Take advantage now of relatively clean slate of transit systems, and achieve higher customer integration that is not in the Capital Region. Take advantage of cost reductions in terms of sharing facilities, vehicles and functions.

59 Benefits Why Move Now? (cont.) Implement new services shown in strategic plan and achieve in turn the following benefits: greenhouse gas reductions; enhanced mobility; and and increase transit ridership. Without the new business/funding model, individual municipalities will not be able to do and duplicate new pilot service.

60 9. Future Directions

61 Future Directions Address Questions, Issues and Opportunities that will arise out of the workshop including industry standard cost-benefit analysis Meet with Key MA and AT in summer on work done to date and directions Develop more details of CRP Partnership Company Model for approval and go through approval process - T and CM Committee, Executive Committee and Board-Bring Report to T@ CM Committee in September Have the Business/Funding model approved before the end of Develop Implementation Plan and Strategy, Operating Bylaw and any required other required details early in 2016

62 Questions?

63 TITLE Thank You Body Text 1 Body Text 2

Primer on Transportation Funding and Governance in Canada s Large Metropolitan Areas

Primer on Transportation Funding and Governance in Canada s Large Metropolitan Areas Transportation Association of Canada Primer on Transportation Funding and Governance in Canada s Large Metropolitan Areas The transportation funding and governance frameworks of Canada s metropolitan regions

More information

Transitways and the RouteAhead for Calgary Transit

Transitways and the RouteAhead for Calgary Transit Transitways and the RouteAhead for Calgary Transit Chris Jordan, P.Eng., M.Sc., Manager, Strategic Planning, Calgary Transit, Transportation, City of Calgary Jen Malzer, P.Eng., M.Sc., Senior Transit Planner,

More information

2012 Saskatoon Transit Services Annual Report

2012 Saskatoon Transit Services Annual Report 2012 Annual Report Saskatoon Transit provides a high quality of service for all citizens in our community, and is undertaking initiatives focused on building its ridership. Like most North American cities,

More information

MANAGEMENT PLAN. Fiscal Year 2015-2016

MANAGEMENT PLAN. Fiscal Year 2015-2016 MANAGEMENT PLAN Fiscal Year 2015-2016 May 6, 2015 Table of Contents I. Executive Summary... 2 Omnitrans Vision... 5 Omnitrans Mission Statement... 5 II. Strategic Initiatives... 5 Implementation... 6 Strategic

More information

Rapid Transit Backgrounder

Rapid Transit Backgrounder Rapid Transit Backgrounder Moving Forward On Rapid Transit The concept of a Rapid Transit System for Winnipeg has been debated for over 30 years. City Council and the Province of Manitoba have demonstrated

More information

BUSINESS PLAN 2015 TO 2016

BUSINESS PLAN 2015 TO 2016 BUSINESS PLAN 2015 TO 2016 TABLE OF CONTENTS Business Plan 2015-2016... 1 What s inside the Business Plan?... 1 Calgary Metropolitan Plan Implementation & Regional Servicing... 3 Overview... 4 Ongoing

More information

FTA OVERSIGHT PROGRAMS

FTA OVERSIGHT PROGRAMS U.S. Department of Transportation Federal Transit Administration FTA OVERSIGHT PROGRAMS FTA Region IV 2008 Conference 1 Session Outline Annual Grantee Assessment Oversight Activities Reviews (General,

More information

Submission from Living Streets Aotearoa Wellington City Public Transport Spine Study

Submission from Living Streets Aotearoa Wellington City Public Transport Spine Study Submission from Living Streets Aotearoa Wellington City Public Transport Spine Study Contact person: Ellen Blake Email: wellington@livingstreets.org.nz Phone: 021 1067139 Date: 30 September 2013 About

More information

The City of Calgary. Customer and Implementation Issues Arising from Business Tax Consolidation

The City of Calgary. Customer and Implementation Issues Arising from Business Tax Consolidation The City of Calgary Customer and Implementation Issues Arising from Business Tax Consolidation This page is intentionally left blank. Table of Contents Introduction... 1 A. Implementation time frame...

More information

Fleet Services CORPORATE SERVICES. Branch Manager: Steve Rapanos 57 FLEET SERVICES 2016 2018 BUSINESS PLAN

Fleet Services CORPORATE SERVICES. Branch Manager: Steve Rapanos 57 FLEET SERVICES 2016 2018 BUSINESS PLAN Fleet Services CORPORATE SERVICES Branch Manager: Steve Rapanos 57 FLEET SERVICES 2016 2018 BUSINESS PLAN Table of Contents INTRODUCTION Our Branch 60 CONTRIBUTION TO THE CITY S VISION The Way Ahead 62

More information

Region of Waterloo Finance Department Financial Services and Development Financing

Region of Waterloo Finance Department Financial Services and Development Financing Region of Waterloo Finance Department Financial Services and Development Financing To: Chair Jim Wideman and Members of the Planning and Works Committee Date: May 27, 2014 File Code: T16-01 Subject: Stage

More information

Edmonton Transit Administration Review June 24, 2013

Edmonton Transit Administration Review June 24, 2013 Edmonton Transit Administration Review June 24, 2013 The Office of the City Auditor conducted this project in accordance with the International Standards for the Professional Practice of Internal Auditing

More information

Introduction to. Aalborg s Sustainability Strategy 2013-2016

Introduction to. Aalborg s Sustainability Strategy 2013-2016 Introduction to Aalborg s Sustainability Strategy 2013-2016 2 Foreword Aalborg should be a sustainable municipality, which will be to the benefit of local citizens, businesses and the environment. With

More information

Calgary Transit Funding and Fare Strategy Review. 2014 February

Calgary Transit Funding and Fare Strategy Review. 2014 February Calgary Transit Funding and Fare Strategy Review 2014 February Table of Contents 1. Introduction......1 2. Background.......1 A New Direction Route Ahead..1 Calgary Transit Ridership Trends.... 1 Changes

More information

Living After Stroke: Mobility and Transportation Options After Stroke. The Family of Community Transportation Options

Living After Stroke: Mobility and Transportation Options After Stroke. The Family of Community Transportation Options Living After Stroke: Mobility and Transportation Options After Stroke Karen Wolf-Branigin, MSW National Center on Senior Transportation Washington, DC The Family of Community Transportation Options This

More information

His Worship Jim Watson Mayor of the City of Ottawa 110 Laurier Avenue West Ottawa, Ontario K1P 1J1 Dear Mr. Mayor,

His Worship Jim Watson Mayor of the City of Ottawa 110 Laurier Avenue West Ottawa, Ontario K1P 1J1 Dear Mr. Mayor, His Worship Jim Watson Mayor of the City of Ottawa 110 Laurier Avenue West Ottawa, Ontario K1P 1J1 Dear Mr. Mayor, Thank you for writing regarding the Green Party s position on issues of interest to the

More information

Evaluation Criteria and Mode Progression for RouteAhead Rapid Transit Projects

Evaluation Criteria and Mode Progression for RouteAhead Rapid Transit Projects Evaluation Criteria and Mode Progression for RouteAhead Rapid Transit Projects C2012-0684 ATTACHMENT 2 The RouteAhead draft 30-year rapid transit plan was developed in coordination with the Investing in

More information

Transportation Breakout Session. Curvie Hawkins Mark Rauscher Mike Sims Paul Moore

Transportation Breakout Session. Curvie Hawkins Mark Rauscher Mike Sims Paul Moore Transportation Breakout Session Curvie Hawkins Mark Rauscher Mike Sims Paul Moore Curvie Hawkins Director of Planning Fort Worth Transportation Authority Fort Worth Transportation Authority The T Presented

More information

2016 Transit Service Review CCT Meeting #2. Calgary Transit April 19, 2016

2016 Transit Service Review CCT Meeting #2. Calgary Transit April 19, 2016 2016 Transit Service Review CCT Meeting #2 Calgary Transit April 19, 2016 Why a Transit Service Review? The 2016 Transit Service Review proposes a number of bus route changes. The goal of this review is

More information

Bus Priority Measures in Calgary: Past, Present and Future. Chris Jordan, M.Sc., P.Eng., Coordinator, Strategic Transit Planning, Calgary Transit

Bus Priority Measures in Calgary: Past, Present and Future. Chris Jordan, M.Sc., P.Eng., Coordinator, Strategic Transit Planning, Calgary Transit Bus Priority Measures in Calgary: Past, Present and Future Chris Jordan, M.Sc., P.Eng., Coordinator, Strategic Transit Planning, Calgary Transit Nora Kajdy, P.Eng., Transit Priority Engineer, Calgary Transit

More information

WORLD BANK WORLD BANK

WORLD BANK WORLD BANK XV. Financial Planning Public Transport Planning and Reform: An Introduction Public Transport Financial Planning Systematic approach that helps produce a financially sustainable program for implementing

More information

Service Alberta BUSINESS PLAN 2010 13

Service Alberta BUSINESS PLAN 2010 13 Service Alberta BUSINESS PLAN 2010 13 Service Alberta BUSINESS PLAN 2010-13 ACCOUNTABILITY STATEMENT The business plan for the three years commencing April 1, 2010 was prepared under my direction in accordance

More information

Sample: Request for Proposals District Official Community Plan. Request for Proposal. Elm Planning District

Sample: Request for Proposals District Official Community Plan. Request for Proposal. Elm Planning District Sample: Request for Proposals District Official Community Plan Request for Proposal For professional community planning services to the Elm Planning District, including, but not limited to, the preparation

More information

2008-11 BUSINESS PLAN

2008-11 BUSINESS PLAN 2008-11 BUSINESS PLAN FIRE AND EMERGENCY SERVICES - NEWFOUNDLAND AND LABRADOR MESSAGE FROM THE MINISTER As Minister responsible for Fire and Emergency Services Newfoundland and Labrador (FES-NL), I am

More information

T.I.F Frequently Asked Questions

T.I.F Frequently Asked Questions What does T.I.F. stand for? T.I.F T.I.F. stands for Tourism Improvement Fee. The 2% T.I.F. is being charged by lodging facilities and is part of a longer term strategy to maintain and improve the competitiveness

More information

How To Expand Commuter Rail Between Worcester And Boston

How To Expand Commuter Rail Between Worcester And Boston AN INDEPENDENT VOICE FOR RESPONSIBLE GOVERNMENT CONNECTING THE HEART OF THE COMMONWEALTH WITH THE HUB OF THE UNIVERSE: MAKING THE CASE FOR EXPANDING COMMUTER RAIL SERVICE BETWEEN WORCESTER AND BOSTON Report

More information

Pupil Transportation Cost and Outsourcing Feasibility Study Performed for the West Plains R-VII Schools May 2013

Pupil Transportation Cost and Outsourcing Feasibility Study Performed for the West Plains R-VII Schools May 2013 Pupil Transportation Cost and Outsourcing Feasibility Study Performed for the West Plains R-VII Schools May 2013 The TransPar Group, Inc. of Lee s Summit, Missouri was engaged by the West Plains Schools

More information

Government Relations & Public Affairs Committee

Government Relations & Public Affairs Committee Government Relations & Public Affairs Committee Item #16-6-6 Action May 27, 2016 Request for Proposals for Transit Marketing & Station Activation Services Issue: Should SACOG release a Request for Proposal

More information

Presto Fare Card ibus (Automated Stop Announcements, Cameras) Transit Operating System Replacement

Presto Fare Card ibus (Automated Stop Announcements, Cameras) Transit Operating System Replacement Transit Business Plan 2 011 2014 Transit Key Deliverables Sustain existing service levels Growth in fleet and service hours (modest) Build, commission and operate the BRT Conduct preliminary i design and

More information

Evergreen Line Rapid Transit Project Business Case Executive Summary. February 2008. Reviewed by

Evergreen Line Rapid Transit Project Business Case Executive Summary. February 2008. Reviewed by Evergreen Line Rapid Transit Project Business Case Executive Summary February 2008 Reviewed by Recommendation and Executive Summary The business case for the Evergreen Line Rapid Transit Project (the Project)

More information

Appendix E Transportation System and Demand Management Programs, and Emerging Technologies

Appendix E Transportation System and Demand Management Programs, and Emerging Technologies Appendix E Transportation System and Demand Management Programs, and Emerging Technologies Appendix Contents Transportation System Management Program Transportation Demand Management Program Regional Parking

More information

Tackling Fare Evasion on Calgary s CTrain System

Tackling Fare Evasion on Calgary s CTrain System Tackling Fare Evasion on Calgary s CTrain System 12 th National Light Rail Conference Sustaining the Metropolis: LRT and Street Cars for Super Cities Salt Lake City, Utah November 2012 Profile of Calgary

More information

Corporate Procurement and Supply Services

Corporate Procurement and Supply Services Corporate Procurement and Supply Services CORPORATE SERVICES Branch Manager: Dan Lajeunesse 16 CORPORATE PROCUREMENT AND SUPPLY SERVICES 2016 2018 BUSINESS PLAN Table of Contents INTRODUCTION Our Branch

More information

CITY OF ORILLIA ENERGY MANAGEMENT PLAN

CITY OF ORILLIA ENERGY MANAGEMENT PLAN CITY OF ORILLIA ENERGY MANAGEMENT PLAN Date: June, 2014 Introduction The City of Orillia Energy Management Plan is the path for the municipality to realize its goals and objectives as they relate to energy

More information

REQUEST FOR PROPOSAL BANFF TRAIL MASTER PLAN. Issued by the Town of Banff. P.O. Box 1260, 110 Bear St. Banff, AB T1L 1A1

REQUEST FOR PROPOSAL BANFF TRAIL MASTER PLAN. Issued by the Town of Banff. P.O. Box 1260, 110 Bear St. Banff, AB T1L 1A1 REQUEST FOR PROPOSAL TOWN OF BANFF TRAIL MASTER PLAN Issued by the Town of Banff Date of RFP Issue: June 2, 2014 Closing Date for Response: June 17, 2014 Contract Name: Agency Contact Person: Address:

More information

Building the Business Case for a Connected City. Economic Prosperity Steering Committee Calgary Regional Partnership March 23, 2016

Building the Business Case for a Connected City. Economic Prosperity Steering Committee Calgary Regional Partnership March 23, 2016 1 Building the Business Case for a Connected City Economic Prosperity Steering Committee Calgary Regional Partnership March 23, 2016 2 Building the Business Case 1. Challenges in developing the business

More information

Service Alberta BUSINESS PLAN 2009-12 ACCOUNTABILITY STATEMENT THE MINISTRY

Service Alberta BUSINESS PLAN 2009-12 ACCOUNTABILITY STATEMENT THE MINISTRY Service Alberta BUSINESS PLAN 2009-12 ACCOUNTABILITY STATEMENT The business plan for the three years commencing April 1, 2009 was prepared under my direction in accordance with the Government Accountability

More information

On the Public Transport Spine Study

On the Public Transport Spine Study On the Public Transport Spine Study Submission of the Wellington City Youth Council to Greater Wellington Regional Council The Wellington City Youth Council would also like to make an oral submission.

More information

Integrated Public Transport. Planning. National workshop on promoting sustainable transport solutions for East Africa

Integrated Public Transport. Planning. National workshop on promoting sustainable transport solutions for East Africa Integrated Public Transport National workshop on promoting sustainable transport solutions for East Africa Carly Koinange, GEF Sustran Consultant UN-HABITAT Urban Mobility Unit Urban Basic Services Branch

More information

Calgary Transit Environmental Stewardship

Calgary Transit Environmental Stewardship Calgary Transit Environmental Stewardship Calgary 1 Million Population Uni-City Governance Coordinated Land Use and Transportation Planning The City Fastest Growing Economy in Canada #2 Corporate Head

More information

time and thought that the buses had a higher on-time arrival rate than the actual on-time arrival rate. 2

time and thought that the buses had a higher on-time arrival rate than the actual on-time arrival rate. 2 TriMet Transit Tracker Implementation Summary Transit Tracker is a real-time bus arrival prediction system that provides information to riders at bus stops and light rail stations with a count down in

More information

1 REPORT OF YORK REGION HOMELESSNESS TASK FORCE

1 REPORT OF YORK REGION HOMELESSNESS TASK FORCE 1955 THE REGIONAL MUNICIPALITY OF YORK REPORT NO. 1 OF THE REGIONAL COMMISSIONER OF COMMUNITY SERVICES AND HOUSING For Consideration by The Council of The Regional Municipality of York on September 28,

More information

Program has been installed. Completed

Program has been installed. Completed Hume City Council Project Tracking for Greenhouse Action Plan Greenhouse Action Plan Recommendation Responsibility Timeframe Measure Required Current Progress 1. Adopt a GHG reduction target of 10% on

More information

METRO. Fiscal Year 2013 Monthly Board Report. June 2013 (Third Quarter Fiscal Year-to-Date)

METRO. Fiscal Year 2013 Monthly Board Report. June 2013 (Third Quarter Fiscal Year-to-Date) METRO Fiscal Year 2013 Monthly Board Report Revenue Expense Ridership Performance (Third Quarter Fiscal Year-to-Date) 7/16/2013 Table of Contents Section A Section B Section C Section D Section E Section

More information

Request for Proposal. City of Atlanta Taxicab Industry Analysis. May 30, 2012

Request for Proposal. City of Atlanta Taxicab Industry Analysis. May 30, 2012 City of Atlanta Taxicab Industry Analysis May 30, 2012 Contact: Kristi Rooks Central Atlanta Progress, Inc. 50 Hurt Plaza SE, Suite 110 Atlanta, GA 30303 (404) 658-5911 and krooks@atlantadowntown.com Page

More information

University of Guelph Transportation Demand Management (TDM) Plan Changing Our Travel Habits 2009/10 2019/20

University of Guelph Transportation Demand Management (TDM) Plan Changing Our Travel Habits 2009/10 2019/20 University of Guelph Transportation Demand Management (TDM) Plan Changing Our Travel Habits 2009/10 2019/20 Introduction: Over the years our society s dependence on the private automobile as the primary

More information

Municipal Transportation Quality Review

Municipal Transportation Quality Review Municipal Transportation Quality Review SFMTA Response June 2015 San Francisco, California Overview The Agency s response to recommended modifications in the Transportation Quality Review An update on

More information

27.ity of Johannesburg 27.2 Council 2016-03-18

27.ity of Johannesburg 27.2 Council 2016-03-18 27.ity of Johannesburg 27.1 Council 2016-03-18 27 AMENDMENT OF THE TARIFF FARE CHARGES FOR BRT REA VAYA FOR THE PERIOD 1 JULY 2016 TO 30 JUNE 2017 1 STRATEGIC THRUST A resilient, livable, sustainable urban

More information

The LYNX Transit Master Plan. METROPLAN Orlando Presentation

The LYNX Transit Master Plan. METROPLAN Orlando Presentation 2030 Paw Print: The LYNX Transit Master Plan D b 2010 December 2010 METROPLAN Orlando Presentation Project Partners Project Overview 18 Corridors Bridge between 5 Year Service Plan and Long Range Transportation

More information

Electric Vehicles in Canada

Electric Vehicles in Canada Electric Vehicles in Canada SFU Mechatronic Systems Engineering The time is right for electric vehicles. In fact, the time is crucial -Carlos Ghosn, CEO of Renault Motors Recent History of EV Sales in

More information

Four Pillars of Urban Sustainability Submission

Four Pillars of Urban Sustainability Submission Four Pillars of Urban Sustainability Submission Introduction The sustainability of a city can, in part, be measured by the quality of its infrastructure. Physical assets such as roads, sewer lines, transit,

More information

Traffic Signal Priority (TSP) and Automatic Vehicle Tracking System (AVTS) For Calgary Transit Buses

Traffic Signal Priority (TSP) and Automatic Vehicle Tracking System (AVTS) For Calgary Transit Buses Traffic Signal Priority (TSP) and Automatic Vehicle Tracking System (AVTS) For Calgary Transit Buses (Project #2001-06) Calgary Transit Transit Planning 2004 July Introduction The purpose of this report

More information

Comprehensive Analysis of Shortlisted Funding Mechanisms

Comprehensive Analysis of Shortlisted Funding Mechanisms Project Number: THE CITY OF CALGARY Comprehensive Analysis of Shortlisted Funding REPORT Statement of Qualifications and Limitations The attached Report (the Report ) has been prepared by AECOM Canada

More information

Leveraging Sustainability through Employee Engagement for a Competitive Future. Danielle Willis. Cleveland, OH

Leveraging Sustainability through Employee Engagement for a Competitive Future. Danielle Willis. Cleveland, OH Leveraging Sustainability through Employee Engagement for a Competitive Future Danielle Willis Greater Cleveland Regional Transit Authority Planning Team Ldr./Sustainability Coordinator Cleveland, OH Presentation

More information

Transportation and Public Works. Business Plan 2002-2003

Transportation and Public Works. Business Plan 2002-2003 Business Plan 2002-2003 March 27, 2002 Mission Transportation and Public Works Construct, maintain and manage provincial highways, buildings and related infrastructure, and provide accommodation, property

More information

Official Community Plan Guiding Principles:

Official Community Plan Guiding Principles: Live, Work, Play CORPORATE STRATEGIC PLAN 2014-2015 Official Community Plan Guiding Principles: Sooke s Thriveability; Sustainability; Environmental Stewardship; Economic Diversification; Smart Growth;

More information

NOTTINGHAM. Workplace Parking Levy

NOTTINGHAM. Workplace Parking Levy Workplace Parking Levy NOTTINGHAM About Nottingham Nottingham is an ambitious and vibrant city. It is designated as a core city and is ranked as a top ten UK retail centre. The Greater Nottingham economy

More information

2012 King County Metro Transit Peer Agency Comparison on Performance Measures

2012 King County Metro Transit Peer Agency Comparison on Performance Measures 2012 Peer Agency Comparison on Performance Measures Department of Transportation Metro Transit Division King Street Center, KSC-TR-0415 201 S. Jackson St Seattle, WA 98104 206-553-3000 TTY Relay: 711 www.kingcounty.gov/metro

More information

Request For Proposal. Design and Development of Municipal Website. Issue date: May 16, 2016. Submission deadline: on or before June 17, 2016 by 4 p.m.

Request For Proposal. Design and Development of Municipal Website. Issue date: May 16, 2016. Submission deadline: on or before June 17, 2016 by 4 p.m. Request For Proposal Design and Development of Municipal Website Issue date: May 16, 2016 Submission deadline: on or before June 17, 2016 by 4 p.m. Submission information in-person, by regular mail, or

More information

Mount Royal College Transit Service Plan

Mount Royal College Transit Service Plan Mount Royal College Transit Service Plan Background In 2007 November response to Council Report C2007-78 West LRT Alignment, Budget and Project Delivery, Council directed the Administration to report back

More information

DRIVE THE DREAM 2015 CEO ROUNDTABLE ON WORKPLACE CHARGING AND PLUG-IN ELECTRIC VEHICLES

DRIVE THE DREAM 2015 CEO ROUNDTABLE ON WORKPLACE CHARGING AND PLUG-IN ELECTRIC VEHICLES DRIVE THE DREAM 2015 CEO ROUNDTABLE ON WORKPLACE CHARGING AND PLUG-IN ELECTRIC VEHICLES Request for Proposal September 26, 2014 1. PEV COLLABORATIVE BACKGROUND The California Plug-In Electric Vehicle Collaborative

More information

Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit

Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Public Information Session May 31, 2016 Transportation

More information

Item No. 11.1.4 Halifax Regional Council January 14, 2014

Item No. 11.1.4 Halifax Regional Council January 14, 2014 Item No. 11.1.4 Halifax Regional Council January 14, 2014 TO: Mayor Savage and Members of Halifax Regional Council SUBMITTED BY: Richard Butts, Chief Administrative Officer DATE: December 18, 2013 Mike

More information

"Ride the Wind!" - A Success Story

Ride the Wind! - A Success Story "Ride the Wind!" - A Success Story Introduction Calgary Transit operates an extensive integrated transit network consisting of light rail transit (referred to as the C-Train), and regular bus and community

More information

SOUTHWEST OHIO TRANSPORTATION WORKGROUP

SOUTHWEST OHIO TRANSPORTATION WORKGROUP SOUTHWEST OHIO TRANSPORTATION WORKGROUP Started in June 2014 by UC UCEDD University Center for Excellence in Developmental Disabilities at Cincinnati Children s Hospital Medical Center Broad group of participants-

More information

About FEED NOVA SCOTIA

About FEED NOVA SCOTIA Membership About FEED NOVA SCOTIA FEED NOVA SCOTIA is the central collection and distribution point for donated food for member food banks, shelters and meal programs across the province. Founded in 1984,

More information

Strathcona County Final Report Recommendations Summary with Comments (Version Jan 10, 2013)

Strathcona County Final Report Recommendations Summary with Comments (Version Jan 10, 2013) Strathcona County Final Report Recommendations Summary with Comments (Version Jan 10, 2013) 1 TABLE OF CONTENTS Performance Management...3 Corporate Planning...4 Human Resources...4 Assessment and Tax...5

More information

Contact us to find the program that s right for you: Phone: 780-492-5832 // executiveeducation@ualberta.ca

Contact us to find the program that s right for you: Phone: 780-492-5832 // executiveeducation@ualberta.ca September 2014- August EXECUTIVE EDUCATION PROGRAM CALENDAR START HERE Executive Education Program Calendar Executive Education s 2014- professional development programs are listed within this guide. Select

More information

RULES AND REGULATIONS FOR FINANCING PROJECTS AND COMMERCIAL ACTIVITIES

RULES AND REGULATIONS FOR FINANCING PROJECTS AND COMMERCIAL ACTIVITIES Page 1 of 8 Section 1. Purpose These Rules and Regulations are adopted by the Board of Governors pursuant to Article 13.3. of the Agreement Establishing the Black Sea Trade and Development Bank (Establishing

More information

Tripp Umbach developed a detailed survey with input from the PDP and distributed the survey to six Downtown Pittsburgh market segments:

Tripp Umbach developed a detailed survey with input from the PDP and distributed the survey to six Downtown Pittsburgh market segments: I. INTRODUCTION In June 2005, the Pittsburgh Downtown Partnership (PDP) retained the consulting firm, Tripp Umbach & Associates (TUA), to complete a comprehensive study of Downtown Pittsburgh transit and

More information

Designation HRPA OFFICE OF THE REGISTRAR

Designation HRPA OFFICE OF THE REGISTRAR 2016 Guide to the CHRP Designation HRPA OFFICE OF THE REGISTRAR 1.0 TABLE OF CONTENTS Table of Contents... 1 AN OVERVIEW OF HRPA S CERTIFICATION PROCESS... 3 Certification and the public interest... 4

More information

Fares Policy In London: Impact on Bus Patronage

Fares Policy In London: Impact on Bus Patronage Fares Policy In London: Impact on Bus Patronage Agenda Introduction to Transport for London Overview of Bus Patronage in London Changes in Policy and patronage since 2000 Fares Strategy Ticketing Strategy

More information

Who are we? Jens Lohmueller, Credit Union Central of Ontario 3/9/2005

Who are we? Jens Lohmueller, Credit Union Central of Ontario 3/9/2005 Who are we? Credit Union (CUCO) is the trade organization of Ontario credit unions. We work within a collective network of service locations comparable in size to the major banks. There are over 700 branches

More information

Operating Budget. MARIN TRANSIT 2016 2025 SHORT RANGE TRANSIT PLAN Chapter 5: Financial Plan

Operating Budget. MARIN TRANSIT 2016 2025 SHORT RANGE TRANSIT PLAN Chapter 5: Financial Plan Operating Budget Marin Transit forecasts revenues and expenses for the 10-year period based on current contract rates, annual escalations, historical trends, and partner agencies revenue projections. Marin

More information

Mission, Vision and Values

Mission, Vision and Values Mission, Vision and Values The City of Greater Sudbury is a growing, world-class community bringing talent, technology and a great northern lifestyle together. We are committed to providing excellent access

More information

Integrating GO RER and SmartTrack. Leslie Woo, Chief Planning Officer February 10, 2016

Integrating GO RER and SmartTrack. Leslie Woo, Chief Planning Officer February 10, 2016 Integrating GO RER and SmartTrack Leslie Woo, Chief Planning Officer February 10, 2016 Purpose and Scope To present update on development of options for integrating SmartTrack and GO RER based on the following

More information

Riding Program - Feasibility and Insurance Options

Riding Program - Feasibility and Insurance Options Feasibility and Insurance Options for Ride Programs propriate McNair Illustration Here POTENTIAL USE OF RIDE PROGRAM WILL BE DETERMINED BY: Numbers of seniors in the catchment area Alternatives available

More information

London Transit Commission 2015-2018 Asset Management Plan

London Transit Commission 2015-2018 Asset Management Plan London Transit Commission 2015-2018 Asset Management Plan Appendix B Asset Management Plan Table of Contents Asset Management Plan and 2015-2018 Business Plan... 1 Asset Management Plan Introduction...

More information

Follow-up of Recommendations For the Period December 2010 through July 2011. September 12, 2011

Follow-up of Recommendations For the Period December 2010 through July 2011. September 12, 2011 Follow-up of Recommendations For the Period December 2010 through July 2011 September 12, 2011 The Office of the City Auditor conducted this project in accordance with the International Standards for the

More information

WEST YORKSHIRE BUS STRATEGY

WEST YORKSHIRE BUS STRATEGY WEST YORKSHIRE BUS STRATEGY Phase 1 Consultation on Vision and Principles Introduction and Purpose There is a statutory requirement for the West Yorkshire Combined Authority (WYCA) to produce a Local Transport

More information

Universal Program Review

Universal Program Review 1. DEPARTMENTAL DESCRIPTION A. DEPARTMENTAL DESCRIPTION The Corporate Services Department provides centralized professional support services to all City departments (Centres of Expertise or COEs) and direct

More information

ELENA Application Form

ELENA Application Form ELENA Application Form The EIB accepts proposals in English and French. For the application of funding under the ELENA facility the following form 1 must be used. Content of ELENA application form: 1.

More information

REQUEST FOR PROPOSAL INFORMATION TECHNOLOGY SECURITY CONSULTING BID INSTRUCTIONS

REQUEST FOR PROPOSAL INFORMATION TECHNOLOGY SECURITY CONSULTING BID INSTRUCTIONS REQUEST FOR PROPOSAL INFORMATION TECHNOLOGY SECURITY CONSULTING BID INSTRUCTIONS NOVA SCOTIA LIQUOR CORPORATION 93 CHAIN LAKE DRIVE HALIFAX, NOVA SCOTIA B3S 1A3 NSLC REFERENCE NO: SR-39-H-15 NSLC Contact:

More information

First Dimension: Political, Social, Economic and Cultural Environment

First Dimension: Political, Social, Economic and Cultural Environment Different factors affect the performance of these collaboration projects. These factors are related either to the project's macro, meso or micro environments, to the partners involved, to the collaboration

More information

Cross Border Tax Issues

Cross Border Tax Issues Cross Border Tax Issues By Reinhold G. Krahn December 2000 This is a general overview of the subject matter and should not be relied upon as legal advice or opinion. For specific legal advice on the information

More information

ECO Stars Fleet Recognition Scheme Improving Local Air Quality Through Operator Engagement

ECO Stars Fleet Recognition Scheme Improving Local Air Quality Through Operator Engagement ECO Stars Fleet Recognition Scheme Improving Local Air Quality Through Operator Engagement Mark Cavers, Transport & Travel Research Ltd and Ann Beddoes, Barnsley Metropolitan Borough Council mark.cavers@ttr-ltd.com

More information

Estevan Student and Market Rental Housing Project. Assessment Report

Estevan Student and Market Rental Housing Project. Assessment Report Estevan Student and Market Rental Housing Project Assessment Report This Estevan Student and Market Rental Housing Project Assessment has been prepared by Preferred Choice (DJ Leier Enterprises Ltd.) with

More information

Running for Municipal Office in Alberta

Running for Municipal Office in Alberta Municipal Affairs Running for Municipal Office in Alberta A Candidate s Guide Alberta Municipal Affairs (2013) Running for Municipal Office in Alberta A Candidate s Guide Edmonton: Alberta Municipal Affairs

More information

Branch Corporate Communications

Branch Corporate Communications Branch Corporate Communications Introduction Corporate Communications Branch supports City departments and business units to inform and connect Edmontonians on municipal matters and civic services. Since

More information

Imperial Oil Limited 237 Fourth Avenue S.W. Calgary, Alberta T2P 3M9 imperialoil.ca

Imperial Oil Limited 237 Fourth Avenue S.W. Calgary, Alberta T2P 3M9 imperialoil.ca Imperial Oil Limited 237 Fourth Avenue S.W. Calgary, Alberta T2P 3M9 imperialoil.ca Table of contents Our approach 1 About us 2 Our approach 4 Business segments 7 Outlook for energy to 2030 9 Safety 11

More information

CALIFORNIA SECURE CHOICE RETIREMENT SAVINGS INVESTMENT BOARD

CALIFORNIA SECURE CHOICE RETIREMENT SAVINGS INVESTMENT BOARD SEPTEMBER 29, 2014 AGENDA ITEM 05 ACTION ITEM CALIFORNIA SECURE CHOICE RETIREMENT SAVINGS INVESTMENT BOARD Market Analysis and Feasibility Study Request for Proposals Discussion of Timeline and Process

More information

Montgomery County Coordinated Transportation Plan

Montgomery County Coordinated Transportation Plan Montgomery County Coordinated Transportation Plan Updated March 2009 Adopted by the Montgomery County Board of Supervisors Resolution 95 of 2009 April 28, 2009 Executive Summary A Locally Developed, Coordinated

More information

Atlantic Provinces Community College Consortium Business Plan 2005-2006

Atlantic Provinces Community College Consortium Business Plan 2005-2006 Atlantic Provinces Community College Consortium Business Plan 2005-2006 2 Table of Contents 1.0 Introduction.....3 2.0 The Planning Context..... 4 2.1 Vision and Mission..4 2.2 Strategic Planning Themes...4

More information

MetroAccess Business Model

MetroAccess Business Model WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY MetroAccess Business Model Finance and Administration Committee December 1, 2011 Purpose Review performance criteria for solicitation, outlining substantial

More information

Consolidated I&T Data Centre - P3 Canada Fund

Consolidated I&T Data Centre - P3 Canada Fund STAFF REPORT ACTION REQUIRED Consolidated I&T Data Centre - P3 Canada Fund Date: January 16, 2012 To: From: Wards: Reference Number: Government Management Committee Deputy City Manager & Chief Financial

More information

your Future. your Choice. your College.

your Future. your Choice. your College. your Future. your Choice. your College. Can you Find Some Money for My Department? August 17, 2009 Can You Find Some Money for My Department? YES August 17, 2009 2 Board of Regents Enhancement Grant for

More information

Opportunities for the Automotive Sector in Horizon 2020. Cliff Funnell UK FP7/H2020 Surface Transport NCP FP7UK

Opportunities for the Automotive Sector in Horizon 2020. Cliff Funnell UK FP7/H2020 Surface Transport NCP FP7UK Opportunities for the Automotive Sector in Horizon 2020 Cliff Funnell UK FP7/H2020 Surface Transport NCP Opportunity: The performance of the UK automotive sector and the success of the Low Carbon Vehicles

More information

National Energy Benchmarking Framework: Report on Preliminary Working Group Findings

National Energy Benchmarking Framework: Report on Preliminary Working Group Findings National Energy Benchmarking Framework: Report on Preliminary Working Group Findings January 2016 Prepared by: Contact: Sundeep Virdi, MES, SBA Manager, Advocacy & Policy Canada Green Building Council

More information

Ministerie van Toerisme, Economische Zaken, Verkeer en Telecommunicatie Ministry of Tourism, Economic Affairs, Transport and Telecommunication

Ministerie van Toerisme, Economische Zaken, Verkeer en Telecommunicatie Ministry of Tourism, Economic Affairs, Transport and Telecommunication SME Policy Framework for St. Maarten May, 2014 Department of Economic Affairs, Transportation & P. 1 of 16 TABLE OF CONTENTS 1. Introduction 2. SME Developments in St. Maarten 2.1 Definition 2.2 Government

More information

DART Mobile App Go Pass

DART Mobile App Go Pass 1 DART Mobile App Go Pass 2 Agenda Overview of DART Mobile ticketing procurement Technology/Business aspects Ticket purchase process Launch 3 DART Rail System Map 4 Mobile Application Procurement Objectives

More information