A PARTICULAR ASPECT OF DECIDE BID DECISION SUPPORT SYSTEM : MODELING OF LIFE-CYCLE PROCESSES AND COSTS

Size: px
Start display at page:

Download "A PARTICULAR ASPECT OF DECIDE BID DECISION SUPPORT SYSTEM : MODELING OF LIFE-CYCLE PROCESSES AND COSTS"

Transcription

1 A PARTICULAR ASPECT OF DECIDE BID DECISION SUPPORT SYSTEM : MODELING OF LIFE-CYCLE PROCESSES AND COSTS H Soliveres, TSI (Thomson-CSF Services Industrie), 105 Avenue du Général Eisenhower, BP 1009, Toulouse Cedex hubert.soliveres@tsi.thomson.fr A.M. Alquier, INPT-GSI, 6 allée Emile Monso, Toulouse Cedex alquier@univ-tlse.fr ABSTRACT ESPRIT project DECIDE n develop a methodology and a related decision support system to assist user companies in their bidding process. In this paper, the costing module will be discussed, in regard of industrial expectation for logistic business. This module is based on an Enterprise Products and Processes Repository (EPPMR). It manages product breakdown structure, supports the technical description of a bid, re-using previous bids elements (know-how capitalization). TSI developed a specific tool for logistic support cost evaluation (SICLO). This specific tool proposes a detailed cost structure, year by year, including all the elements involved in their product support : documentation, training, spare parts, test benches, maintenance,... As a result, it is possible to evaluate the overall global cost and its yearly decomposition. The focus will be on the use of DECIDE in the ILS (Integrated Logistic Support) business. In this way, common points and differences will be developed in order to promote DECIDE toolkit in this business context. KEY WORDS Logistics, life-cycle, corporate memory, knowledge capitalization, decision systems, human factors in design. 1. CONTEXT Each time a new invitation to tender triggers the manufacturer's relevant sales and projects departments into creating ideas and working to consider the following type of questions: -Should we reply to this invitation to tender? -What technical solution should we propose? -What sales price should we fix? -What is the minimum acceptable profit margin? -How do we develop a convincing strategy? The decisions to be taken are made more difficult due to the many parameters to be considered: -the company's own context (development strategy, sales policy, internal costs, level of technology, sector of activity, skills, previous project results, etc.) -external factors ( market prices, competitor know how and position), -client context and requirements (knowledge of sector, company history, product life time and method of use, etc.) -etc. The procedure for replying to tenders means integrating and dealing with all the above information. In order to be efficient in this area, companies organize themselves by applying a methodology

2 adapted to their own context, with the assistance of software tools (databases, costing, pricing, etc.). This document presents the current research at INPT-GSI to develop such tools adapted to this issue and the related concepts and methodology. The main reason of concentrating on the life-cycle first phase (bid process or product concept, called conceptual phase) is because, then, all actions are possible, the various issues have the greatest degree of liberty, and the decisions have the most important impacts. But reliable evaluation is also very difficult to make. This can be schematized saying that an inexpensive feasibility study will help quantify costs and provide a basis for deciding whether to go into development phase with minimum of risks. This is even more obvious with innovative products or processes, which is the case in DECIDE. We will focus on the costing module of the DECIDE project. It includes a product * process* resource description whose adaptation to the problem of Life-Cycle modelling and calculation will be evaluated in perspective with a more specialised software, SICLO, developed for the needs of life cycle cost evaluation by the TSI logistics specialists. The comparison between these tools will give issues on the approach of DECIDE on LCC (Life Cycle Cost) evaluation and simulation, and therefore identify its interest, limitations, and the future extensions. 2. LIFE CYCLE COSTING CONSIDERATIONS As far as costs are concerned, it is advisable to assess and simulate the consequences of the technical choices and commitments made by the company: cost of the proposed solution, long term support costs, etc. Maintenance and exploitation costs are used to argue the technical choices retained based on criteria other than just the acquisition cost: a solution may prove to be more advantageous if it includes minimized operating, maintenance and dismantling costs (life-cycle cost). 2.1 Total Cost Notion The classic ICEBERG diagram clearly shows the interest of considering the total costs over the overall life-cycle while trying to determine as accurately as possible the hidden costs : Documentation Training Tests Penalties Repairs Up grades Maintenance ACQUISITION Spares Installation Software Modifications Obsolescence Tools EXPLOITATION and MAINTENANCE Infrastructure servicing Removal from service Life-Cycle Cost corresponds to the sum of the following costs: -acquisition: research, development, production, -system installation: infrastructures, training, documentation, design and production of the support system, -operating, -main system and support system maintenance, -removal from service.

3 2.2 Durability of the Support System The system life duration, as required by the user, is related to his own operating constraints as regards to the expected service, staff (numbers, training), agreed investments, etc. Order of magnitude examples: Aircraft : more than 30 years; Nuclear power station: 30 years; Military products (radar equipment, transmission systems): years; Information System and related informatics: years. The support system comprises all the elements, options and services for maintenance and durability throughout all of the system's operational life cycle. We are quite sure today that the delivered products would not be able to meet, in their initial condition, long term needs due to the frequency of technological developments. The manufacturer is therefore advised to include in his proposal an operational lifetime warranty, and to offer solutions for prolonging products' life-cycle. 2.3 Design to Cost, Integrated Logistic Support in Project Management Manufacturer applies a project management method to: -confirm his ability to take in account the customer s requirements on project management -deal with the operations in progress (technical and financial aspects). The project's Management Plan is the document issued by the manufacturer to define the work to be carried out (products to be developed, documents, etc.), the organization implemented, the references that he is committed to follow, the schedule (milestones, reviews, etc.), the overall control procedure, etc. This document include: -the design to cost method, participants, cost targets, scheduling work meetings,... -the Integrated Logistic Support process, design of the support system, targets to be obtained, work to be placed under the responsibility of maintenance specialists, DECIDE The DSS costing and repository modules (DECIDE project) used for engineering and costing solutions deals with: -decomposition of alternative technical solutions answering the customer s requirements (EPPMR or «enterprise product process model repository»), with the required methodology adapted to bidding process -analytical costing, i.e. costs evaluation established using elemental costs evaluation. The decomposition precision is a main issue in this type of costing, in opposition with parametric costing for example, which rests on only a few parameters (for example plane wig weigh). This module is at the cross-roads of several main research issues related to business process reengineering and innovation : project management, business process innovation, and the related cooperative and strategic decision support systems. This is needed to answer the technicoeconomical trade-off in bidding process. Michaels & Wood 2 define the problematic of finding the right intermediate and cooperative structure in the «design to cost» method, which is a concurrent engineering approach, calling it «Cost Element Structure». The problem of finding the Cost Element Structure is left unanswered. Their presentation is summarized in the following diagram :

4 Top-down cost estimating high level of cost aggregation Emphasis: what we're selling origin: sales manager General problem : develop acost element structure that couples from top to bottom preserves the integrity Bottom-up cost estimating of both approaches low levels of cost aggregation derived through piece-part procurement, accounting,... Emphasis: what we're making and buying origin: technical staff At one end people need only a high level of knowledge organization, typically, sales managers, to avoid too much detailed information about the product because this could lead to loss of time, difficulties to organize a correct requirement answer in the proposal for example. Sales managers need aggregated costs i.e. costs on high level piece parts of the product, for the negotiation with the customer. At the other end, other people need detailed knowledge leading to daily work organization, which is in correct correspondence with the global document reference of this work (customer contract). Typically, engineers in charge of quotations who need desegregated costs to make precise quotations. 2- corporate memory, with knowledge discovery, data mining and pattern modeling. Help bidding process requires «Design history» or semantic memorization from previous tasks which is a company s technological knowledge capitalization. This knowledge capitalization leads to the organization of standard parametric models of structural objects (see above the impact on the project management). In pattern modeling, standard models of sub-products and of corresponding cost analysis, prepared in advance, lead both to considerable reductions of time, cost and improvement of risk position. Feeding information into a standard design data base (source data of product model construction and of corresponding analysis) strengthens the company s capabilities for full knowledge capitalization and handling. The outcome is a quite fully conceived design with a considerable potential for improved reliability at the beginning (for example bid phase) of a project. Handle the two perspectives above leads to the organization of a cooperative high level information system (Alquier, 93). EPPMR deals with this problem. The concepts for Intelligent Information System modeling which help knowledge emergence, corporate memory are: - information profoundness is linked to knowledge representation technique, - information spatial organization relies on datawarehouse organization. Which is a cooperative information system in the form of a decomposition into products* processes* resources and the modeling of the request to proposal 1. product Technical solution process... Costing resource... elementary cost It corresponds to the CPPMR module which is the repository of the overall company know-how and contains technical and organizational information required for bidding. It is a data warehouse which includes mining links as well as the organization of extraction from the information system of the company.

5 4. SICLO Available to logistics specialists, this tool contributes towards the final selection of a support scenario and it is used to evaluate the costs hidden in the ICEBERG (see 1.1), with a Proposed Cost Structure : acquisition cost (research, industrialization, production, installation,...) and operation and removal from service cost (maintenance, services, management, consumption,...). Its technical functionalities, according to the general decision support system architecture, can be summarized as below : Scenarios : The logistics specialist develops the different possible maintenance concepts, taking into consideration the customer's operational requirements, the company's constraints and know how, technological development, and the support expected from suppliers. Each concept gives rise to a scenario specifying the work to be carried out on a yearly basis from the start of the project until the end. Data Entry : SICLO is mainly used to enter all the primary costs for each scenario. The software tool provides the operator with a complete cost structure which enables him to avoid omitting a subject ( service, maintenance option, etc.). Costs are entered in the form of cost units assigned to the various company control centers. Costs : The entered information is validated according to the company's own parameters (hourly rate, supply coefficients, etc.). The results are given in annual and total costs, expressed in monetary units. Presentations : It is possible to obtain reports in table or histogram format. Total costs will be presented through out the life cycle or on a yearly basis. -Cost of ownership, indicating the parts relative to acquisition, operation, maintenance and removal from service, -Acquisition cost, indicating the parts relative to the various elements, -Maintenance cost, indicating the parts relative to the various elements, -etc. Cost development installed operating support Scenario comparison Cost increase representation throughout life cycle Scenario no.1 Scenario no.2 Scenario no.3 Years SICLO appears as a Decision Support System for bidding and design to cost process. The project manager can select a technical solution and a maintenance concept from the evaluations of the annual and overall budgets. SICLO helps also to assess the commercial argumentation based on optimizing the total life cycle cost. 5. DECIDE FOR LIFE CYCLE COST Comparison between DECIDE and SICLO: SICLO supports all predefined logistic elements. Products and services: - spare parts, documentation, test benches,.. - hot line, repair, onsite assistance, up grades,... evaluates annual and global costs DECIDE models all elements of the proposal in the form of : product* process* resource evaluates global costs (costs are not dated)

6 SICLO presents obtained results with graphs (maturity of display effort) information reliability based on operator experience and expertise. autonomous works on a stable referential for costs organized through experience directly in the software code stand alone only costing functionalities DECIDE capability of exportation to MicroSoft products (EXCEL,...) re-use validated previous elements estimations cooperative use traceability of previous bids cost elements feature modeling, knowledge capitalization over the time : dynamic referential potential connection to information systems in relation with the other modules : pricing, value analysis of technical solutions This comparison shows the main advantages of the DECIDE EPPMR : -adaptability to any logistic configuration and scenario -connections with Information System -cooperative tool (GroupWare) -costing in relation with pricing and value analysis for a global decision support. The two main improvements which could be assumed from the comparison with SICLO are : -elements to be dated in order to obtain annual progression of cost -graphic man-machine interface and more generally decision facilities (simulation, graphs, forms, hypertext,...). Representation of accumulated costs Acquisition cost 6. CONCLUSION Cost of ownership Acquisition Exploitation and maintenance Removal from service For logistic business, DECIDE appears as a useful tool with a global approach. It appears also that the further expectations mentioned above could be fulfilled. For this topic the solutions that can be conceived are : -associating both tools (in the present DECIDE toolkit development solution : ACCESS and VB, it is easy to interconnect both tools to cover life-cycle cost), -or adding further development work. 7. REFERENCES 1. Alquier, 93 "Modélisation des systèmes d'information : modèle coopératif. Application à l'audit et aux schémas directeurs d'informatique" - Habilitation à diriger des recherches 1993, Université Toulouse 1 2. Michaels & Wood, 89 - Design to cost- Wiley, 91 An example of such a graphical decision facility is shown hereafter :

Early project organization and start-up techniques based on project management information system

Early project organization and start-up techniques based on project management information system Early project organization and start-up techniques based on project management information system A.M. ALQUIER, M. SALLES & M.H. TIGNOL Université des Sciences Sociales, Toulouse, France Département de

More information

Enterprise Resource Planning Analysis of Business Intelligence & Emergence of Mining Objects

Enterprise Resource Planning Analysis of Business Intelligence & Emergence of Mining Objects Enterprise Resource Planning Analysis of Business Intelligence & Emergence of Mining Objects Abstract: Build a model to investigate system and discovering relations that connect variables in a database

More information

Managing Variability in Software Architectures 1 Felix Bachmann*

Managing Variability in Software Architectures 1 Felix Bachmann* Managing Variability in Software Architectures Felix Bachmann* Carnegie Bosch Institute Carnegie Mellon University Pittsburgh, Pa 523, USA fb@sei.cmu.edu Len Bass Software Engineering Institute Carnegie

More information

Agile Manufacturing for ALUMINIUM SMELTERS

Agile Manufacturing for ALUMINIUM SMELTERS Agile Manufacturing for ALUMINIUM SMELTERS White Paper This White Paper describes how Advanced Information Management and Planning & Scheduling solutions for Aluminium Smelters can transform production

More information

Space Project Management

Space Project Management EUROPEAN COOPERATION FOR SPACE STANDARDIZATION Space Project Management Configuration Management Secretariat ESA ESTEC Requirements & Standards Division Noordwijk, The Netherlands Published by: Price:

More information

Data Mining Governance for Service Oriented Architecture

Data Mining Governance for Service Oriented Architecture Data Mining Governance for Service Oriented Architecture Ali Beklen Software Group IBM Turkey Istanbul, TURKEY alibek@tr.ibm.com Turgay Tugay Bilgin Dept. of Computer Engineering Maltepe University Istanbul,

More information

ICAO Procurement Process Briefing

ICAO Procurement Process Briefing ICAO Procurement Process Briefing The following is a briefing in an effort to provide the reader with an insight into the ICAO Technical Co-operation Bureau s Procurement Process and role in relation to

More information

CHAPTER 4 Data Warehouse Architecture

CHAPTER 4 Data Warehouse Architecture CHAPTER 4 Data Warehouse Architecture 4.1 Data Warehouse Architecture 4.2 Three-tier data warehouse architecture 4.3 Types of OLAP servers: ROLAP versus MOLAP versus HOLAP 4.4 Further development of Data

More information

STEPS IN THEATRE PROJECT PLANNING

STEPS IN THEATRE PROJECT PLANNING Janis A. Barlow & Associates Research, Planning and Management Consultants Specializing in Theatre since 1981 STEPS IN THEATRE PROJECT PLANNING Janis A. Barlow & Associates www.barlowandassociates.com

More information

The Software Process. The Unified Process (Cont.) The Unified Process (Cont.)

The Software Process. The Unified Process (Cont.) The Unified Process (Cont.) The Software Process Xiaojun Qi 1 The Unified Process Until recently, three of the most successful object-oriented methodologies were Booch smethod Jacobson s Objectory Rumbaugh s OMT (Object Modeling

More information

IFS-8000 V2.0 INFORMATION FUSION SYSTEM

IFS-8000 V2.0 INFORMATION FUSION SYSTEM IFS-8000 V2.0 INFORMATION FUSION SYSTEM IFS-8000 V2.0 Overview IFS-8000 v2.0 is a flexible, scalable and modular IT system to support the processes of aggregation of information from intercepts to intelligence

More information

An Introduction to. Metrics. used during. Software Development

An Introduction to. Metrics. used during. Software Development An Introduction to Metrics used during Software Development Life Cycle www.softwaretestinggenius.com Page 1 of 10 Define the Metric Objectives You can t control what you can t measure. This is a quote

More information

Power Generation Service Life Cycle Management for Power Plants

Power Generation Service Life Cycle Management for Power Plants Power Generation Service Life Cycle Management for Power Plants Power Generation Service is protecting your Investment by Step-wise Evolution and Updating of Instrumentation, Control and Electrical Systems.

More information

SAMPLE INVITATION TO TENDER ADVERTISEMENT (CONTRACT)

SAMPLE INVITATION TO TENDER ADVERTISEMENT (CONTRACT) SAMPLE INVITATION TO TENDER ADVERTISEMENT (CONTRACT) Invitation to Tender [Insert brief description of project/consultancy E.g. provision of legal services for X native title claim ]. [Name of Representative

More information

Contracting Practices in Mega Projects

Contracting Practices in Mega Projects CEM 520 Term Paper Contracting Practices in Mega Projects EPC and EPCM A L I A B D U L L A H A L - S A L E M 2 0 0 3 4 2 5 1 0 Outline Introduction Types of Contracts Contracting Strategies The Difference

More information

PREPARING THE AEC INDUSTRY FOR THE KNOWLEDGE ECONOMY

PREPARING THE AEC INDUSTRY FOR THE KNOWLEDGE ECONOMY PREPARING THE AEC INDUSTRY FOR THE KNOWLEDGE ECONOMY Dharmaraj Veeramani 1 and Jeffrey S. Russell 2? 1 Associate Professor, Dept. of Industrial Eng., University of Wisconsin-Madison, WI 53706. Telephone

More information

ORACLE PROJECT PLANNING AND CONTROL

ORACLE PROJECT PLANNING AND CONTROL ORACLE PROJECT PLANNING AND CONTROL (Formerly Oracle Project Management) KEY FEATURES COLLABORATIVE PROJECT PLANNING Define a project work breakdown structure to align plans to execution Coordinate financial

More information

Infor Equipment and Rental Fleet Operations - Understanding the Relationship

Infor Equipment and Rental Fleet Operations - Understanding the Relationship Technical paper Understand the return on investment before you jump in Dealers, service, and rental providers of heavy equipment face many of the same challenges, and must weigh the same factors as they

More information

Portland. Reducing Software Costs While Increasing Cost Predictability and Control. Abstract. Mikko Marttinen

Portland. Reducing Software Costs While Increasing Cost Predictability and Control. Abstract. Mikko Marttinen White paper Reducing Software Costs While Increasing Cost Predictability and Control Mikko Marttinen Abstract Effective software procurement addresses contractual and overall cost of ownership through

More information

THE CITY OF NORTH LAS VEGAS REQUEST FOR INFORMATION FOR ASSET TRACKING & INVENTORY MANAGEMENT RFI# 06-30-09-01 RELEASE DATE: JUNE 30, 2009

THE CITY OF NORTH LAS VEGAS REQUEST FOR INFORMATION FOR ASSET TRACKING & INVENTORY MANAGEMENT RFI# 06-30-09-01 RELEASE DATE: JUNE 30, 2009 THE CITY OF NORTH LAS VEGAS REQUEST FOR INFORMATION FOR ASSET TRACKING & INVENTORY MANAGEMENT RFI# 06-30-09-01 RELEASE DATE: JUNE 30, 2009 RESPONSES TO BE RECEIVED BY JULY 21, 2009 2:00 P.M. RETURN TO

More information

Module 1: Supply Chain Design

Module 1: Supply Chain Design Module 1: Supply Chain Design Module 1 Introduction Section A: Develop the Supply Chain Strategy Chapter 1: Inputs to Supply Chain Strategy o Topic 1: Business Model o Topic 2: External Inputs to Supply

More information

Software Testing Interview Questions

Software Testing Interview Questions Software Testing Interview Questions 1. What s the Software Testing? A set of activities conducted with the intent of finding errors in software. 2.What is Acceptance Testing? Testing conducted to enable

More information

Business Process Management In An Application Development Environment

Business Process Management In An Application Development Environment Business Process Management In An Application Development Environment Overview Today, many core business processes are embedded within applications, such that it s no longer possible to make changes to

More information

Reduce risk. Reduce cost. Raise performance.

Reduce risk. Reduce cost. Raise performance. Reduce risk. Reduce cost. Raise performance. Services for professional procurement. Be better informed, make better decisions. Achilles procurement toolkit Support for sourcing and supplier management

More information

Ontologies for Enterprise Integration

Ontologies for Enterprise Integration Ontologies for Enterprise Integration Mark S. Fox and Michael Gruninger Department of Industrial Engineering,University of Toronto, 4 Taddle Creek Road, Toronto, Ontario M5S 1A4 tel:1-416-978-6823 fax:1-416-971-1373

More information

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

Financial Deal Management as Key to Success in the IT Outsourcing Business

Financial Deal Management as Key to Success in the IT Outsourcing Business IT Outsourcing Financial Deal as Key to Success in the IT Outsourcing Business Active and transparent financial deal management is a major factor for the commercial success of an IT outsourcing deal. Cloud

More information

PIE. Internal Structure

PIE. Internal Structure PIE Internal Structure PIE Composition PIE (Processware Integration Environment) is a set of programs for integration of heterogeneous applications. The final set depends on the purposes of a solution

More information

Course 803401 DSS. Business Intelligence: Data Warehousing, Data Acquisition, Data Mining, Business Analytics, and Visualization

Course 803401 DSS. Business Intelligence: Data Warehousing, Data Acquisition, Data Mining, Business Analytics, and Visualization Oman College of Management and Technology Course 803401 DSS Business Intelligence: Data Warehousing, Data Acquisition, Data Mining, Business Analytics, and Visualization CS/MIS Department Information Sharing

More information

OIL & GAS SUPPORTING THE PROJECT & ASSET LIFECYCLE

OIL & GAS SUPPORTING THE PROJECT & ASSET LIFECYCLE OIL & GAS SUPPORTING THE PROJECT & ASSET LIFECYCLE KENNY INGRAM INDUSTRY DIRECTOR kenny.ingram@ifsworld.com AGENDA Who are IFS Typical Systems Landscape IFS Solution Benefits of IFS Solution SUPPLY CHAIN

More information

Project Management Guidelines

Project Management Guidelines Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.

More information

Course Description Bachelor in Management Information Systems

Course Description Bachelor in Management Information Systems Course Description Bachelor in Management Information Systems 1605215 Principles of Management Information Systems (3 credit hours) Introducing the essentials of Management Information Systems (MIS), providing

More information

4. Project management triangle The Project Management Triangle (called also Triple Constraint or the Iron Triangle) is a model of the constraints of

4. Project management triangle The Project Management Triangle (called also Triple Constraint or the Iron Triangle) is a model of the constraints of 4. Project management triangle The Project Management Triangle (called also Triple Constraint or the Iron Triangle) is a model of the constraints of project management. It is a graphic aid where the three

More information

Project Management Case Study - A Strategic Perspective

Project Management Case Study - A Strategic Perspective Microsystems Case study Work Package 2 Author: Artur Ziółkowski, PhD., Eng. Table of contents:... 2 A- EXECUTIVE SUMMARY... 3 B BASIC INFORMATION ABOUT THE COMPANY... 4 C ENVIRONMENTAL ANALYSIS... 5 D

More information

Name Chapter 1: Introduction to Project Management Description Instructions

Name Chapter 1: Introduction to Project Management Description Instructions Name Chapter 1: Introduction to Project Management Description Instructions Modify Question 1 / 0 points Modify Remove Question Until the 1980s, project management primarily focused on providing schedule

More information

Cendec Systems Inc. http://www.cendec.com

Cendec Systems Inc. http://www.cendec.com The management of multi-million dollar assets and inventories can be a daunting task. For the past fifteen years, Oil and Gas companies have relied on Maintenance and Materials Management systems from

More information

Analysis of Fleet Replacement Lifecycle

Analysis of Fleet Replacement Lifecycle Analysis of Fleet Replacement Lifecycle Project #12-14 Prepared by Office of the Inspector General J. Timothy Beirnes, CPA, Inspector General TABLE OF CONTENTS BACKGROUND... 1 OBJECTIVE, SCOPE, AND METHODOLOGY...

More information

Ten steps to better requirements management.

Ten steps to better requirements management. White paper June 2009 Ten steps to better requirements management. Dominic Tavassoli, IBM Actionable enterprise architecture management Page 2 Contents 2 Introduction 2 Defining a good requirement 3 Ten

More information

Deductive Data Warehouses and Aggregate (Derived) Tables

Deductive Data Warehouses and Aggregate (Derived) Tables Deductive Data Warehouses and Aggregate (Derived) Tables Kornelije Rabuzin, Mirko Malekovic, Mirko Cubrilo Faculty of Organization and Informatics University of Zagreb Varazdin, Croatia {kornelije.rabuzin,

More information

Extend and optimize the life of your plant the modular Life Cycle Service portfolio

Extend and optimize the life of your plant the modular Life Cycle Service portfolio Extend and optimize the life of your plant the modular Life Cycle Service portfolio SIMATIC PCS 7 process control system www.siemens.com/simatic-pcs7 For planning security and availability: your plant

More information

Enhanced spare part engineering support

Enhanced spare part engineering support Enhanced spare part engineering support Smart spare parts' design for a part standardisation The Airbus ing team has developed the capability to create efficient engineering solutions for the design of

More information

Training for IT project managers and team leads

Training for IT project managers and team leads You will use on Monday what we will teach you on Friday! Training for IT project managers and team leads Innopolis University offers advanced training for top managers and senior executives, technical

More information

THIRD REGIONAL TRAINING WORKSHOP ON TAXATION. Brasilia, Brazil, December 3 5, 2002. Topic 4

THIRD REGIONAL TRAINING WORKSHOP ON TAXATION. Brasilia, Brazil, December 3 5, 2002. Topic 4 THIRD REGIONAL TRAINING WORKSHOP ON TAXATION Brasilia, Brazil, December 3 5, 2002 Topic 4 INFORMATION TECHNOLOGY IN SUPPORT OF THE TAX ADMINISTRATION FUNCTIONS AND TAXPAYER ASSISTANCE Nelson Gutierrez

More information

Reduce Capital Cost Overruns with Repeatable Engineering Designs

Reduce Capital Cost Overruns with Repeatable Engineering Designs WHITE PAPER Reduce Capital Cost Overruns with Repeatable Engineering Designs by Ron Beck, Industry Marketing Director, Aspen Technology, Inc. The use of standardized and modular designs to reduce engineering

More information

Service Oriented Architecture

Service Oriented Architecture Service Oriented Architecture Charlie Abela Department of Artificial Intelligence charlie.abela@um.edu.mt Last Lecture Web Ontology Language Problems? CSA 3210 Service Oriented Architecture 2 Lecture Outline

More information

Chapter 5 Business Intelligence: Data Warehousing, Data Acquisition, Data Mining, Business Analytics, and Visualization

Chapter 5 Business Intelligence: Data Warehousing, Data Acquisition, Data Mining, Business Analytics, and Visualization Turban, Aronson, and Liang Decision Support Systems and Intelligent Systems, Seventh Edition Chapter 5 Business Intelligence: Data Warehousing, Data Acquisition, Data Mining, Business Analytics, and Visualization

More information

CMMS/EAM AND FINANCIAL INTERFACES. Joe Grassi, Grassi & Associates

CMMS/EAM AND FINANCIAL INTERFACES. Joe Grassi, Grassi & Associates CMMS/EAM AND FINANCIAL INTERFACES Joe Grassi, Grassi & Associates Early this year I had the opportunity to address a number of Mainsaver customers at the 32 nd Annual User Conference and discuss the use

More information

Case Study: How Hollister Simultaneously Minimized Inventory Costs and Stabilized Service Levels Using Two Little Known, but Effective, Tools

Case Study: How Hollister Simultaneously Minimized Inventory Costs and Stabilized Service Levels Using Two Little Known, but Effective, Tools Case Study: How Hollister Simultaneously Minimized Inventory Costs and Stabilized Service Levels Using Two Little Known, but Effective, Tools Steve Grace Hollister Incorporated 2011 Wellesley Information

More information

INFORMATION FOR OBSERVERS

INFORMATION FOR OBSERVERS 30 Cannon Street, London EC4M 6XH, United Kingdom Tel: +44 (0)20 7246 6410 Fax: +44 (0)20 7246 6411 E-mail: iasb@iasb.org Website: www.iasb.org International Accounting Standards Board This document is

More information

Software Requirements Specification

Software Requirements Specification 1 of 7 17.04.98 13:32 Software Requirements Specification The sub-sections : 1. What is a Software Requirements Specification 2. Why is a Software Requirement Specification Required 3. What is Contained

More information

Supplementary Agenda Monday 23 April 2012 Council Chambers 126-138 Main Road Speers Point 7.00pm

Supplementary Agenda Monday 23 April 2012 Council Chambers 126-138 Main Road Speers Point 7.00pm Supplementary Agenda Monday Council Chambers 126-138 Main Road Speers Point 7.00pm Matters Referred: Extension of CMS software Brian Bell General Manager Note: Council Meeting Agendas will be available

More information

Continuous Sales & Operations Planning

Continuous Sales & Operations Planning Continuous Sales & Operations Planning Aamer Rehman VP, Manufacturing Solutions Las Vegas - Jan 27, 2012 Copyright 2012 Kinaxis Inc. All Rights Reserved. Prelude Volatility is a given in today s environment

More information

Offshore Wind Farm Layout Design A Systems Engineering Approach. B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy

Offshore Wind Farm Layout Design A Systems Engineering Approach. B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy Offshore Wind Farm Layout Design A Systems Engineering Approach B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy 0 Paper presented at Ocean Power Fluid Machinery, October 2010 Offshore Wind

More information

REQUEST FOR INFORMATION (RFI)

REQUEST FOR INFORMATION (RFI) REQUEST FOR INFORMATION (RFI) STATE OF ALASKA DIVISION OF LEGISLATIVE AUDIT Audit of Alaska s Integrated Resource Information Systems Enterprise Resource and Planning system Please respond no later than

More information

Digital Business Platform for SAP

Digital Business Platform for SAP BUSINESS WHITE PAPER Digital Business Platform for SAP SAP ERP is the foundation on which the enterprise runs. Software AG adds the missing agility component with a digital business platform. CONTENT 1

More information

Outline Business Intelligence Roadmap: The Complete Project Lifecycle for Decision-Support Applications

Outline Business Intelligence Roadmap: The Complete Project Lifecycle for Decision-Support Applications Outline Business Intelligence Roadmap: The Complete Project Lifecycle for Decision-Support Applications Introduction to the BI Roadmap Business Intelligence Framework DW role in BI From Chaos to Architecture

More information

CONDIS. IT Service Management and CMDB

CONDIS. IT Service Management and CMDB CONDIS IT Service and CMDB 2/17 Table of contents 1. Executive Summary... 3 2. ITIL Overview... 4 2.1 How CONDIS supports ITIL processes... 5 2.1.1 Incident... 5 2.1.2 Problem... 5 2.1.3 Configuration...

More information

Modernize your Monitor Pro software with less risk, less cost and less effort

Modernize your Monitor Pro software with less risk, less cost and less effort Modernize your Monitor Pro software with less risk, less cost and less effort Schneider Electric announces end of life for Monitor Pro With the release of Monitor Pro version 7.6, Schneider Electric has

More information

This software agent helps industry professionals review compliance case investigations, find resolutions, and improve decision making.

This software agent helps industry professionals review compliance case investigations, find resolutions, and improve decision making. Lost in a sea of data? Facing an external audit? Or just wondering how you re going meet the challenges of the next regulatory law? When you need fast, dependable support and company-specific solutions

More information

BuSineSS analytics for. SaleS and Marketing ManagerS. g ert H. n. Laursen. How to Compete in the information age

BuSineSS analytics for. SaleS and Marketing ManagerS. g ert H. n. Laursen. How to Compete in the information age BuSineSS analytics for How to Compete in the information age SaleS and Marketing ManagerS g ert H. n. Laursen Contents Preface vii Acknowledgments xiii Chapter 1: Introduction...1 Chapter 2: Identify What

More information

Reading Sample. Integration Scenarios with Other Project Management Tools. Contents. Index. The Author. Project Management with SAP Project System

Reading Sample. Integration Scenarios with Other Project Management Tools. Contents. Index. The Author. Project Management with SAP Project System First-hand knowledge. Reading Sample SAP Project System s innovative design allows for cross-platform usage. This is good news for companies who manage projects through different programs and software.

More information

Quick Reference Guide Interactive PDF Project Management Processes for a Project

Quick Reference Guide Interactive PDF Project Management Processes for a Project Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process

More information

Digital Asset Manager, Digital Curator. Cultural Informatics, Cultural/ Art ICT Manager

Digital Asset Manager, Digital Curator. Cultural Informatics, Cultural/ Art ICT Manager Role title Digital Cultural Asset Manager Also known as Relevant professions Summary statement Mission Digital Asset Manager, Digital Curator Cultural Informatics, Cultural/ Art ICT Manager Deals with

More information

BANKA SOCIETE GENERALE ALBANIA

BANKA SOCIETE GENERALE ALBANIA BANKA SOCIETE GENERALE ALBANIA Request for Proposals (RFP) for: Maintenance works for Bank's premises and Construction works for relocation of Bank s offices inside Twin Tower Premises Issued on November

More information

How do you design maximum data security?

How do you design maximum data security? How do you design maximum data security? Integrated infrastructure solutions for data centers Answers for industry. 2 Siemens a system integrator with universal expertise. Data is the lifeblood of every

More information

IT Project: System Implementation Project Template Description

IT Project: System Implementation Project Template Description 2929 Campus Drive Suite 250 IT Project: System Implementation Project Template Description Table of Contents Introduction... 2 Project Phases... 3 Initiation & Requirements Gathering Milestone... 3 Initiation

More information

ORACLE FINANCIAL SERVICES BALANCE SHEET PLANNING

ORACLE FINANCIAL SERVICES BALANCE SHEET PLANNING ORACLE FINANCIAL SERVICES BALANCE SHEET PLANNING KEY FEATURES AND BENEFITS FEATURES Packaged application with prebuilt industry leading practices Net Interest Margin and balance sheet forecasts using cash

More information

Gartner, Inc. DIR-SDD-2042

Gartner, Inc. DIR-SDD-2042 Texas Department of Information Resources STATEMENT OF WORK (SOW) FOR DELIVERABLES-BASED INFORMATION TECHNOLOGY SERVICES Identity & Access Management Analysis IT Assessment & Planning Gartner, Inc. DIR-SDD-2042

More information

CHAPTER 9. DEVELOPING IT SY STEM S Bringing IT System s to Life

CHAPTER 9. DEVELOPING IT SY STEM S Bringing IT System s to Life CHAPTER 9 DEVELOPING IT SY STEM S Bringing IT System s to Life 9-2 Introduction Every Organization Is Using Information Technology But IT systems don t magically appear. Organizations spend billions of

More information

The design of a Logistic Support System

The design of a Logistic Support System A WHITE PAPER ON LOGISTIC SUPPORT SYSTEM EDITION 1.O MAY 2012 The design of a Logistic Support System How to reduce Life Cycle Costs with 54%? AUTHOR: RIK KUSTERS C O N S U L T I N G, E N G I N E E R I

More information

STRATEGIC AND FINANCIAL PERFORMANCE USING BUSINESS INTELLIGENCE SOLUTIONS

STRATEGIC AND FINANCIAL PERFORMANCE USING BUSINESS INTELLIGENCE SOLUTIONS STRATEGIC AND FINANCIAL PERFORMANCE USING BUSINESS INTELLIGENCE SOLUTIONS Boldeanu Dana Maria Academia de Studii Economice Bucure ti, Facultatea Contabilitate i Informatic de Gestiune, Pia a Roman nr.

More information

Delivering Smart Answers!

Delivering Smart Answers! Companion for SharePoint Topic Analyst Companion for SharePoint All Your Information Enterprise-ready Enrich SharePoint, your central place for document and workflow management, not only with an improved

More information

Rotorcraft Health Management System (RHMS)

Rotorcraft Health Management System (RHMS) AIAC-11 Eleventh Australian International Aerospace Congress Rotorcraft Health Management System (RHMS) Robab Safa-Bakhsh 1, Dmitry Cherkassky 2 1 The Boeing Company, Phantom Works Philadelphia Center

More information

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter 1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process

More information

BANKA SOCIETE GENERALE ALBANIA

BANKA SOCIETE GENERALE ALBANIA BANKA SOCIETE GENERALE ALBANIA Request for Proposals (RFP) for: Maintenance works for Bank's premises Issued on December 29 th, 2015 Deadline for Response: January 14 th, 2016 12:00 CET 1 Objective of

More information

Key Performance Indicators used in ERP performance measurement applications

Key Performance Indicators used in ERP performance measurement applications Key Performance Indicators used in ERP performance measurement applications A.Selmeci, I. Orosz, Gy. Györök and T. Orosz Óbuda University Alba Regia University Center Budai str. 45, H-8000 Székesfehérvár,

More information

A NAF-based proposition to leverage System Engineering change management in systems-ofsystems acquisition projects. CSD&M 2015 Thomas RIGAUT

A NAF-based proposition to leverage System Engineering change management in systems-ofsystems acquisition projects. CSD&M 2015 Thomas RIGAUT A NAF-based proposition to leverage System Engineering change management in systems-ofsystems acquisition projects CSD&M 2015 Thomas RIGAUT Description of the case Moving to Model-Based System Engineering

More information

Introduction to OpenPPM

Introduction to OpenPPM 0 Introduction to OpenPPM Content Table Introduction to OpenPPM... 1 0.1. OpenPPM: A tool thought by and for Project Managers... 2 0.2. Project, Program and Portfolio Management... 3 0.3. What is not OpenPPM?...

More information

Space project management

Space project management ECSS-M-ST-80C Space project management Risk management ECSS Secretariat ESA-ESTEC Requirements & Standards Division Noordwijk, The Netherlands Foreword This Standard is one of the series of ECSS Standards

More information

STRATEGY 1: DETERMINE DESIRED PERFORMANCE METRICS

STRATEGY 1: DETERMINE DESIRED PERFORMANCE METRICS operational, tactical, and strategic. 2 Operational and tactical decisions generally involve choices or decisions about current business processes. Although strategic decisions may relate to the current

More information

Information Systems Analysis and Design CSC340. XXIV. Other Phases

Information Systems Analysis and Design CSC340. XXIV. Other Phases XXIV. Other Phases Implementation Phase Testing and Installation Phase Post-Installation Tasks Course Summary 2004 John Mylopoulos Other Phases -- 1 The Software Lifecycle Revisited Survey project scope

More information

Computing Services Network Project Methodology

Computing Services Network Project Methodology Computing Services Network Project Prepared By: Todd Brindley, CSN Project Version # 1.0 Updated on 09/15/2008 Version 1.0 Page 1 MANAGEMENT PLANNING Project : Version Control Version Date Author Change

More information

Key Success Factors for Delivering Application Services

Key Success Factors for Delivering Application Services Key Success Factors for Delivering Application Services George Feuerlicht University of Technology, Sydney jiri@it.uts.edu.au Jiri Vorisek Prague University of Economics vorisek@vse.cz Keywords: ASP, Application

More information

Knowledge Discovery and Data. Data Mining vs. OLAP

Knowledge Discovery and Data. Data Mining vs. OLAP Knowledge Discovery and Data Mining Data Mining vs. OLAP Sajjad Haider Spring 2010 1 Acknowledgement All the material in this presentation is taken from the Internet. A simple search of Data Mining vs.

More information

The fact is that 90% of business strategies are not implemented through operations as intended. Overview

The fact is that 90% of business strategies are not implemented through operations as intended. Overview Overview It is important to recognize that a company s network determines its supply chain efficiency and customer satisfaction. Designing an optimal supply chain network means the network must be able

More information

IndustrialIT System 800xA Engineering

IndustrialIT System 800xA Engineering IndustrialIT System 800xA Engineering Overview Features and Benefits Integrated Engineering Environment: Supports the engineering of the entire extended automation system from field devices to plant management

More information

Web-Based Interactive-Video Retirement Plan Management System: Build it or Buy it?

Web-Based Interactive-Video Retirement Plan Management System: Build it or Buy it? Web-Based Interactive-Video Retirement Plan Management System: Build it or Buy it? As retirement plan providers continue to embrace web-based technologies for participant communication and plan management,

More information

The 10 Knowledge Areas & ITTOs

The 10 Knowledge Areas & ITTOs This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading

More information

Explaining EA: business architecture basics

Explaining EA: business architecture basics Explaining EA: business architecture basics All rights reserved, A. Samarin, 2011 The purpose of this document is to provide an explanation about Business Architecture (BA). Informally speaking, BA defines

More information

DESIGNED FOR YOUR INDUSTRY. SCALED TO YOUR BUSINESS. READY FOR YOUR FUTURE. SAP INDUSTRY BRIEFING FOR HEATING, VENTILATION, AIR CONDITIONING, AND

DESIGNED FOR YOUR INDUSTRY. SCALED TO YOUR BUSINESS. READY FOR YOUR FUTURE. SAP INDUSTRY BRIEFING FOR HEATING, VENTILATION, AIR CONDITIONING, AND DESIGNED FOR YOUR INDUSTRY. SCALED TO YOUR BUSINESS. READY FOR YOUR FUTURE. SAP INDUSTRY BRIEFING FOR HEATING, VENTILATION, AIR CONDITIONING, AND PLUMBING EQUIPMENT MANUFACTURERS BEST-RUN HVAC AND PLUMBING

More information

Topic 4: Different approaches to GDP

Topic 4: Different approaches to GDP Topic 4: Different approaches to GDP PRINCIPLES OF MACROECONOMICS Dr. Fidel Gonzalez Department of Economics and Intl. Business Sam Houston State University Three different approaches to measure the GDP

More information

Process Analysis. Work Process Documentation Guidelines. Purpose

Process Analysis. Work Process Documentation Guidelines. Purpose Purpose The purpose of this tool is threefold: Convey a common understanding of the basis for documenting work processes by defining the five levels of detail for capturing work process Provide instructions

More information

Chapter 11. MRP and JIT

Chapter 11. MRP and JIT Chapter 11 MRP and JIT (Material Resources Planning and Just In Time) 11.1. MRP Even if MRP can be applied among several production environments, it has been chosen here as a preferential tool for the

More information

Implementation of ANSI/AAMI/IEC 62304 Medical Device Software Lifecycle Processes.

Implementation of ANSI/AAMI/IEC 62304 Medical Device Software Lifecycle Processes. Implementation of ANSI/AAMI/IEC 62304 Medical Device Software Lifecycle Processes.. www.pharmout.net Page 1 of 15 Version-02 1. Scope 1.1. Purpose This paper reviews the implementation of the ANSI/AAMI/IEC

More information

Outsourcing Manufacturing: A 20/20 view

Outsourcing Manufacturing: A 20/20 view Outsourcing Manufacturing: A 20/20 view OUTSOURCING MANUFACTURING is becoming a well-established approach for companies that want to strategically manage materials in today s fast-paced business environment.

More information

Logistics: A Total System s Approach Benjamin S. Blanchard Professor-Emeritus, Virginia Tech

Logistics: A Total System s Approach Benjamin S. Blanchard Professor-Emeritus, Virginia Tech Logistics: A Total System s Approach Benjamin S. Blanchard Professor-Emeritus, Virginia Tech A Historical Perspective The subject of logistics can be approached from several different perspectives. The

More information

Business Process Redesign and Modelling

Business Process Redesign and Modelling Business Process Redesign and Modelling The Business Process Redesign the Process Handbook the key idea of the Process Handbook approach is that a richly structured online repository about business processes

More information

Business Intelligence System for Monitoring, Analysis and Forecasting of Socioeconomic Development of Russian Territories

Business Intelligence System for Monitoring, Analysis and Forecasting of Socioeconomic Development of Russian Territories Business Intelligence System for Monitoring, Analysis and Forecasting of Socioeconomic Development of Russian Territories The Ministry of Economic Development of the Russian Federation is responsible for

More information

EST.03. An Introduction to Parametric Estimating

EST.03. An Introduction to Parametric Estimating EST.03 An Introduction to Parametric Estimating Mr. Larry R. Dysert, CCC A ACE International describes cost estimating as the predictive process used to quantify, cost, and price the resources required

More information

TEACHING GUIDE PROJECT MANAGEMENT ACADEMIC YEAR 2013-2014

TEACHING GUIDE PROJECT MANAGEMENT ACADEMIC YEAR 2013-2014 TEACHING GUIDE PROJECT MANAGEMENT ACADEMIC YEAR 2013-2014 Introduction When the Steering Committee of a company decides to move from one situation to another in any area of management of the company (engineering,

More information