1 Preparing to Operate a New Data Center Facility AFCOM October 3, 2012
2 Background Managed 100k sq.ft. critical data center facility for GTE Data Services (now Verizon) Site Uptime Network Program Director ComputerSite Engineering team leader David Boston Consulting since 2006 Critical Facilities Operations, including new facility start-up strategy and implementation assistance, procedures and training programs, assessments
3 Proper Planning An enormous amount of planning and coordination goes into the justification, design, and construction of a new data center facility Commissioning Factory acceptance Site acceptance Total systems integration
4 Proper Planning - continued
5 Proper Planning - continued It is equally important to thoroughly develop your strategy for staffing and operating the facility Much of the strategy must be implemented while the building is still under construction
6 Why is This Critical? Facilities related downtime for computer operations is caused by human error 60-80% of the time Processes are just as critical as equipment
7 Why is This Critical? - continued Companies that are serious about uptime dedicate significant effort to Facilities staff plans, procedures, and training, in addition to constructing systems designed for high reliability A data center facility will only operate successfully if the Facilities team is provided management support, appropriate resources, site-specific systems experience, and the resulting confidence level
8 Developing a Strategy Clarify your new facility s reliability objective Match Facilities Operations strategy to systems availability level expected This drives staff size, shift coverage, operating budget It will also dictate the level of training and procedures programs needed
9 Organizational Structure Determine optimal structure to maximize success Which department will Facilities Operations report to in order to receive the best communication, funding, and resources? (And achieve optimal shared processes for hardware master planning and power/network installation)
10 Sample Staff Plan
11 Annual Objectives Facilities staff objectives should include collective goals for consistent facilities systems uptime and successful/safe completion of all assigned PM tasks and customer requests Individual objectives should vary by position, allowing ownership of specific systems, tasks, and projects to be clear (accountability)
12 Hiring Timeline Hire the Facilities team early enough in the design/construction process Involvement in construction monitoring will pay off Several should participate in factory acceptance, site acceptance, and integrated systems commissioning
13 What is the Right Timing? What do you think the appropriate timing is to hire the Facilities Manager? Shift supervisor? Shift engineers? Support services coordinator? Project coordinator? Administrative assistant?
14 Almost Always Overlooked Unless 2-3 months are scheduled after the construction and commissioning process for Facilities training, the Facilities team cannot develop the needed confidence level to successfully respond to systems incidents Computer Operations and Network Operations groups can also use this time period to advantage
15 Procedures Recommendations A comprehensive program is needed ( Facilities procedures, depending on the facility design) A number of the desired procedures should be developed and tested prior to initial operation (tested during the 2-3 month window), if the schedule allows for this
16 Procedures - continued Unless all are completed in advance, a priority order for procedure development is important: 1. Emergency response procedures first 2. Planned system transfer procedures in the order that equipment PMs will be scheduled 3. MOPs for daily PM tasks (less risk)
17 Procedures - continued One of the Facilities team members should be assigned the responsibility of Procedures and Training Coordinator The Coordinator must be given resources to accomplish this In-house staff assigned to help part time Contracted system experts and writer
18 Procedures - continued Ensure that all procedures are tested What is clear to the author often leaves room for confusion for the reader If unclear, the procedure may actually introduce risk
19 Procedures - continued It is critical that two individuals participate in each planned activity that utilizes a procedure One to read aloud, the other to confirm and act This greatly diminishes the risk of skipping a step or performing a step out of order It also encourages discussion and a potential decision to back out if there is any confusion
20 Sample Procedures Format 1. Find breaker control switch GTA HVEA GEN. TIE BREAKER in the bottom row of controls in Master Control Cubicle MC 2. Turn this control switch counterclockwise to the TRIP position and then release
21 Training Program Each equipment vendor will typically deliver training after equipment has been installed Scheduling should be managed to prevent overload Review each vendor s materials in advance Professionally video record the training
22 Training Program More critical than vendor training is the implementation of monthly site-specific training (train on each system at least annually) January: Generators, controls, & fuel systems February: Life safety and evacuation March: Cooling towers, chillers, pumps, valves April: UPS, UPS switchgear, batteries May: CRAHs, VAVs, AHUs Etc.
23 Training Program - continued The Procedures and Training Coordinator should involve many of the identified system experts to conduct initial monthly sessions In-house staff should become trainers over a planned timeline Classroom (group) and in-front-of-equipment (individual) sessions each month
24 Training Program - continued Engineers of Record or Commissioning Agents should be contracted to deliver Systems Design Concepts and Systems Overview training
25 Training Program - continued Identify system experts to help with initial inhouse monthly training sessions
26 Training Program - continued Once your site specific program is established: Internal certification Recognition Planned progression
27 Budget Planning Experience provides the best resource for planning your new facility s expense budget If your company has operated a data center previously, that expense history should be utilized when developing the new facility s initial budget History within same region most useful
28 Budget Planning - continued Your electrical engineer of record and your electric utility representative can help you estimate your initial year s utility costs Utility expenses are consistently the largest operating expense in a data center facility
29 Budget Planning - continued The second highest cost category will be labor and related expenses for Facilities Operations staff (in-house or contracted)
30 Budget Planning - continued Collectively, maintenance contracts for preventive maintenance (PM) on major systems will typically be the next highest expense Determine level of PM conducted by staff vs. vendors
31 Budget Planning - continued Remaining categories include: Spare parts, materials, tools, uniforms, supplies (First confirm what construction budget will cover) Janitorial (including sub-floor cleaning) Grounds Security (if Facilities is responsible)
32 Budget Planning - continued Expenses for individual data center facilities vary widely due to: Cost of electric utility service (kwh) Levels of redundancy & concurrent maintainability Load variances: types of computer hardware installed Salary & benefits for Facilities Operations team Union vs. non-union staff Single shift vs. continuous shift coverage Number of employees per shift Outsourced vs. in-house staff
33 Orientation Program Formal playbook to accelerate knowledge & confidence acquisition for new team members Include: Introduction (why site critical, cautionary philosophy) Systems overviews and descriptions One line diagrams, building layout Safety and Security policies Training session and major PM calendar, first year expectancies Prescribed individual shadow program
34 Workspace Strategies Benchmark with peers or hire service providers to help you maximize functionality for: Equipment rooms, parts storage areas Facilities shop, office, command center/library Loading dock, unpacking, staging and burn-in areas
35 Additional Strategies for Success Control processes Specific data center work rules Limited access minimize those permitted badges Shipping/receiving only on a planned basis Computer hardware installation planned in advance
36 Additional Strategies - continued Team Development Clearly defined IT and Facilities relationship, mutual expectations (or SLAs), shared incentives Defined Data Center Facilities and Office Facilities relationship (if other buildings on campus)
37 Measuring Success Effectively deploying these strategies will provide for a much higher reliability potential in the first year of operation Continued application will dramatically increase continuous facilities systems operation potential over the life of the facility
38 Measuring Success - continued You may realistically aim for multiple years of continuous facilities systems availability, a multi-million $ savings
39 Questions?
40 Web site: Contact Information References: upon request Phone: Fax: Address: 215 Wildwood Dr. Highlands, NC 28741
Disaster Recovery in the Contact Center
Disaster Recovery in the Contact Center Ensuring Business Continuity and Minimizing Impact from Disasters and Emergencies Table of Contents Introduction Impact on Contact Centers a. Operational b. Financial
More informationPursuing Operational Excellence. Better Data Center Management Through the Use of Metrics
Pursuing Operational Excellence Better Data Center Management Through the Use of Metrics Objective Use financial modeling of your data center costs to optimize their utilization. Data Centers are Expensive
More informationData Center Commissioning: What you need to know
Data Center Commissioning: What you need to know Course # CXENERGY1511 AIA Provider # 50111116 AABC Commissioning Group CxEnergy Conference Henderson, NV April 30, 2015 Presented by: Judson H. Adams, P.E.,
More informationIntroduction. More time to run their business, Less HR cost to reinvest back to their organization and
Introduction The Barbelo Group is a one stop Human Resources Outsourcing, Staffing and Consulting firm. It is the only outsource and consulting HR organization in the industry to apply Six Sigma methodologies
More informationGREEN HOUSE DATA. Managing IT in Uncertain Economic Times: Is a An External Private Cloud the Way to Go? Built right. Just for you.
Built right. Just for you. Managing IT in Uncertain Economic Times: Is a An External Private Cloud the Way to Go? Presented by: Shawn Mills, Founder and CEO of Green House Data Green House Data 340 Progress
More informationVendor Managed Services: Question and Answer
I. The Program a. In General how does the Vendor Managed Services (VMS) Program work and what are the benefits? The DSI VMS program is focused on solving a business challenge: Contingent labor procurement,
More informationReduce Your Forklift Fleet Costs
Five Ways to Reduce Your Forklift Fleet Costs Using T-Matics www.toyotaforklifts.com Overview The new economy is putting significant pressure on all businesses and management has to do more with less.
More informationCommissioning of Mission Critical Facilities
Commissioning of Mission Critical Facilities Terry L. Rodgers, CPE, CPMP VP of Sustainable Operations Primary Integration Solutions Paul Liesman SVP of FM & Commissioning Syska Hennessy Group AIA Quality
More informationManaging the Unmanaged Print Fleet
Managing the Unmanaged Print Fleet A Staples, Inc. White Paper April 2012 Executive Summary While office printers may seem easy enough to manage, many businesses are hard pressed to state exactly how many
More informationHow to Choose a Managed Network Services Provider
How to Choose a Managed Network Services Provider 6 Best Practices to Ensure a Thorough Evaluation Get Started Now: 877.611.6342 to learn more. www.megapath.com Could Managed Network Services Be Right
More informationAPPA Effective and Innovative Practices Award. Saint Louis University Facilities Services. In-House Construction Program
APPA Effective and Innovative Practices Award Saint Louis University Facilities Services In-House Construction Program STATEMENT OF PROGRAM AND RESULTS Saint Louis University s in-house construction unit,
More informationData Center Build vs. Buy
2014 Data Center Build vs. Buy More information available on our website: /page/whitepapers Data Center Build vs. Buy 2014 When considering colocating your data center, first you must understand your technical
More informationBICSI 002 / TIA 942 / Uptime
BICSI 002 / TIA 942 / Uptime Which Data Center Standard Should I Follow Phil Isaak, PE, P.Eng., RCDD, DCDC President, Master Instructor Isaak Technologies Inc. Standards Who are these People Standards
More informationCOMMODITIZING THE DATACENTER. Exploring the Impacts of the Shift to Virtualization and Cloud Computing
COMMODITIZING THE DATACENTER Exploring the Impacts of the Shift to Virtualization and Cloud Computing 3/5/2015 AGENDA Changing Environments What Is The Datacenter Why Do We Use Them Adapting To A Changing
More informationStaff Wage and Salary Guidelines
Staff Wage and Salary Guidelines Preface These procedures apply to staff employed by the University of Southern California. In the event of a discrepancy between these procedures and guidelines and a collective
More informationSolution Analysis White Paper CHOOSING THE RIGHT UPS FOR SMALL AND MIDSIZE DATA CENTERS: A COST AND RELIABILITY COMPARISON
Solution Analysis White Paper CHOOSING THE RIGHT UPS FOR SMALL AND MIDSIZE DATA CENTERS: A COST AND RELIABILITY COMPARISON Introduction A dependable uninterruptible power supply (UPS) system is essential
More informationFinding Your Cloud: A down-to-earth guide to planning your cloud investment. Getting the full benefit of a key strategic technology investment
Finding Your Cloud: A down-to-earth guide to planning your cloud investment Getting the full benefit of a key strategic technology investment Finding Your Cloud: A down-to-earth guide to planning your
More informationScheduling, Payroll and Benefit Management System
Scheduling, Payroll and Benefit Management System James R. Polkowski Executive Director of Business Services and Risk Management Schoolcraft College, Livonia, Michigan Abstract The College-wide systems
More informationStatement Of Work Professional Services
Statement Of Work Professional Services Data Center Electrical Efficiency Assessment Data Center Electrical Efficiency Assessment Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0
More informationSecurity Solutions in the Aerospace/Defense Industry A Pinkerton Government Services White Paper
Security Solutions in the Aerospace/Defense Industry A Pinkerton Government Services White Paper Robert Maydoney Vice President Sales Pinkerton Government Services, Inc. 740 North Main Street Mansfield,
More informationIT White Paper. N + 1 Become Too Many + 1?
IT White Paper Balancing Scalability and Reliability in the Critical Power system: When Does N + 1 Become Too Many + 1? Summary Uninterruptible Power Supply (UPS) protection can be delivered through a
More information'Strategic Data Center Management: Transforming Fear into Opportunity' A CoreNet Global and Johnson Controls Survey Research Project
'Strategic Data Center Management: Transforming Fear into Opportunity' A CoreNet Global and Johnson Controls Survey Research Project Presenters John Richard, Director Global Critical Environments Eric
More informationThe Build vs. Buy Decision IN THIS PAPER WHITE PAPER SERVICE TYPE. 03 The case for build. 05 The case for outsourcing (Buy) PAGE 3
Software-as-aservice Delivery: The Build vs. Buy Decision IN THIS PAPER 01 Introduction 02 The challenges of SaaS Delivery 03 The case for build (or DIY) 04 What s required to build it? PAGE 3 05 The case
More informationDATA CENTER ASSESSMENT SERVICES
DATA CENTER ASSESSMENT SERVICES ig2 Group Inc. is a Data Center Science Company which provides solutions that can help organizations automatically optimize their Data Center performance, from assets to
More informationDigital Realty Data Center Solutions Digital Chicago Datacampus Franklin Park, Illinois Owner: Digital Realty Trust Engineer of Record: ESD Architect
Digital Realty Data Center Solutions Digital Chicago Datacampus Franklin Park, Illinois Owner: Digital Realty Trust Engineer of Record: ESD Architect of Record: SPARCH Project Overview The project is
More informationEnergy Design Resources Commissioning Plan Outline Template
IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended
More informationCalculating Total Power Requirements for Data Centers
Calculating Total Power Requirements for Data Centers By Richard Sawyer White Paper #3 Executive Summary Part of data center planning and design is to align the power and cooling requirements of the IT
More informationTechnology Outsourcing. Tools to Manage Technology Providers Performance Risk: Service Level Agreements
Technology Outsourcing Tools to Manage Technology Providers Performance Risk: Service Level Agreements Technology Outsourcing Tools to Manage Technology Providers Performance Risk: Service Level Agreements
More informationCarbonDecisions. The green data centre. Why becoming a green data centre makes good business sense
CarbonDecisions The green data centre Why becoming a green data centre makes good business sense Contents What is a green data centre? Why being a green data centre makes good business sense 5 steps to
More informationEssential NCPI Service Requirements for Next Generation Data Centers
Essential NCPI Service Requirements for Next Generation Data Centers By Richard Sawyer White Paper #12 Executive Summary Data Centers are a significant investment to the corporations and IT departments
More informationBrivo OnAir TOTAL COST OF OWNERSHIP (TCO) How Software-as-a-Service (SaaS) lowers the Total Cost of Ownership (TCO) for physical security systems.
Brivo OnAir TOTAL COST OF OWNERSHIP (TCO) How Software-as-a-Service (SaaS) lowers the Total Cost of Ownership (TCO) for physical security systems. WHITE PAPER Page 2 Table of Contents Executive summary...
More informationApplying a Proven Learning Strategy in Bank Acquisition Environments
in Bank Acquisition Environments Nan Orth Lisa Schramm FIS Education and Training 800.822.6758 Executive Takeaways Effective training has a direct impact on individual performance. In turn, an organization
More informationData center management suite. Providing optimal control and efficiency to data center management. www.siemens.com/datacenters
Data center management suite Providing optimal control and efficiency to data center management www.siemens.com/datacenters Streamline operations with Siemens suite of integrated management tools You work
More informationGuilford Technical Community College Human Services Division, Anne Buchanan-Hockett, Div. Chair Early Childhood Associate, Joan Moran, Dept.
Guilford Technical Community College Human Services Division, Anne Buchanan-Hockett, Div. Chair Early Childhood Associate, Joan Moran, Dept. Chair Anne Buchanan-Hockett, Chair, Human Services Division
More informationEssential NCPI Management Requirements for Next Generation Data Centers
Essential NCPI Requirements for Next Generation Data Centers By Ted Ives White Paper #14 1 Executive Summary The management of physical infrastructure in data centers can no longer be considered independently
More information2015 EHR BUYER S GUIDE. For Behavioral Health and Human Services Providers
2015 EHR BUYER S GUIDE For Behavioral Health and Human Services Providers CHAPTER TITLE SUMMARY 1 Introduction Are you in the early stages of investing in an EHR? We have created this guide to simplify
More informationExecutive Summary... 2. Factors Affecting Benefits And Costs... 4. Disclosures... 5. TEI Framework And Methodology... 6. Analysis...
TABLE OF CONTENTS Executive Summary... 2 Factors Affecting Benefits And Costs... 4 Disclosures... 5 TEI Framework And Methodology... 6 Analysis... 7 Interview Highlights... 7 Costs... 9 Benefits... 10
More informationData Center Colocation Build vs. Buy
Data Center Colocation Build vs. Buy Comparing the total cost of ownership of building your own data center vs. buying third-party colocation services Executive Summary As businesses grow, the need for
More informationC24 - Inside the Data Center Andrew J. Luca
C24 - Inside the Data Center Andrew J. Luca Inside the Data Center What an auditor needs to know Course Objectives Understand the looks and feel of a data center Know what to look for and what questions
More informationStatement Of Work. Data Center Power and Cooling Assessment. Service. Professional Services. Table of Contents. 1.0 Executive Summary
Statement Of Work Professional Services Data Center Power and Cooling Assessment Data Center Power and Cooling Assessment Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features
More informationApplications for Infrared Thermography at Computer Centers
Applications for Infrared Thermography at Computer Centers By Eric Stockton CompuSCANIR, a division of Stockton Infrared Thermographic Services, Inc. 8472 Adams Farm Road Randleman, NC 27317 http://www.compuscanir.com/
More informationHelping Midsize Businesses Grow Through HR Technology
Helping Midsize Businesses Grow Through HR Technology As a business grows, the goal of streamlining operations is increasingly important. By maximizing efficiencies across the board, employee by employee,
More informationAn Integrated Modeling Approach for Analyzing Dependability, Cost and Sustainability of IT Data Center Systems
An Integrated Modeling Approach for Analyzing Dependability, Cost and Sustainability of IT Data Center Systems Gustavo Callou gustavo@deinfo.ufrpe.br Professor Paulo Maciel prmm@cin.ufpe.br Agenda Introduction
More informationKPIs in Service. Using Key Performance Indicators to Optimize Contract Services
KPIs in Service Using Key Performance Indicators to Optimize Contract Services by Chris Arlen President Service Performance (206) 780-2963 USA carlen@serviceperformance.com http://www.serviceperformance.com
More informationOur mission is to provide world class solutions, consulting and training on information and communication technologies.
Company Profile General Information Synapse ATS is an IT Service, Solution and Education Provider Company that helps customers to plan, design, implement, maintain and operate their IT infrastructure.
More informationRCM Success Starts with CMMS
RCM Success Starts with CMMS Ruth Olszewski, President CMMS data group, inc. 5701 N. Sheridan Road, Suite 17Q Chicago, Illinois 60660 Phone: (773) 275-8846 Fax: (801) 991-6567 ruth.olszewski@cmmsdatagroup.com
More informationFive steps to a successful material handling CMMS implementation
Five steps to a successful material handling CMMS implementation Upgrade maintenance operations with improved efficiency, quality and reduced overhead automation that delivers Five steps to a successful
More informationHow to Meet 24 by Forever Cooling Demands of your Data Center
W h i t e P a p e r How to Meet 24 by Forever Cooling Demands of your Data Center Three critical aspects that are important to the operation of computer facilities are matching IT expectations with the
More information2005 Rooney Award. Nomination: Innovative State Human Resource Management
2005 Rooney Award Nomination: Innovative State Human Resource Management Program Title: E-Learning Program State: North Carolina Contact Person: Thomas H. Wright Title: State Personnel Director Agency:
More informationCMMS/EAM. Maintenance Solutions
CMMS/EAM Maintenance Solutions Superior Functionality. Fully Integrated Solution. Maximum System Support. Maximize Critical Assets Maintenance Software Solutions For nearly 40 years, CHAMPS has remained
More informationSaaS or On-Premise Monitoring: 9 Reasons SaaS Makes More Sense
SaaS or On-Premise Monitoring: 9 Reasons SaaS Makes More Sense You know that cloud-based services provide advantages, including: Low upfront costs Fast deployment Simplified administration We know that
More informationBudget Documentation & Workpaper Guidelines for O&M and Capital Expenditures
Page 1 of 13 Budget Documentation & Workpaper Guidelines for O&M and Capital Expenditures (2013/2015 Budget) Revised March 2011 Table of Contents Page 2 of 13 Page - Introduction & Purpose 3 - Timeline
More informationOUTSOURCING YOUR GUARD SERVICE
OUTSOURCING YOUR GUARD SERVICE A Strategy for Success! A Complimentary WHITE PAPER from www.minieriassociates.com Independent, Professional Security Consulting & Engineering Services Worldwide Contact:
More informationDepartment of Public Utilities Facilities Maintenance Operations
REPORT # 2010-02 LIMITED REVIEW of the Facilities Maintenance Operations September 2009 TABLE OF CONTENTS Executive Summary..... i Comprehensive List of Recommendations v Introduction, Scope, Objective
More informationMistakes Companies make when Outsourcing
P P W H I T E A E R Mistakes Companies make when Outsourcing Software Testing By: Sofía Palamarchuk @sopalamarchuk Abstracta 01.12.2016 abstracta www.abstracta.us ABSTRACT When it comes to completing software
More informationThe Why & How of Managed Services
SOLUTIONS Cut Costs While Improving Productivity The Why & How of Managed Services What are Managed Services? CIOs all face similar challenges: cost containment, reliability of systems and keeping pace
More informationROI CASE STUDY KRONOS AKER PHILADELPHIA SHIPYARD
ROI CASE STUDY KRONOS AKER PHILADELPHIA SHIPYARD THE BOTTOM LINE Aker Philadelphia Shipyard deployed Kronos Workforce Payroll and Workforce HR to reduce payroll staff, tax filing fees, and payroll error.
More informationTHE MULTI-TENANT DATA CENTER
THE MULTI-TENANT DATA CENTER IS IT RIGHT FOR YOUR ORGANIZATION? Josh Rabina Sentinel Data Center 1 AGENDA Introductions The Multi Tenant Data Center What is It? What is Driving Adoption (i.e. Value Proposition)?
More informationIN-HOUSE VS. FULL SERVICE MANAGED CHAT. Everything you need to know to choose the chat solution that s right for your dealership
IN-HOUSE VS. FULL SERVICE MANAGED CHAT Everything you need to know to choose the chat solution that s right for your dealership Chat Will Transform Your Internet Business Auto dealers eager to boost website
More informationWhat to Consider When Building An Internal Sourcing Function
What to Consider When Building An Internal Sourcing Function The vast majority of business leaders agree that having the right talent at the right time is the key to operating a successful business. Cisco
More informationTHE WHY & HOW OF MANAGED SERVICES
SOLUTIONS CUT COSTS WHILE IMPROVING PRODUCTIVITY THE WHY & HOW OF MANAGED SERVICES WHAT ARE MANAGED SERVICES? CIOs all face similar challenges: cost containment, reliability of systems and keeping pace
More informationMiddlesex Community College Library Strategic Plan 2013-18
Middlesex Community College Library Strategic Plan 2013-18 Table of Contents Introduction: Page 2 Goal 1: Instruction Page 3 Goal 2 Services Page 4 Goal 3 Staffing Page 5 Goal 4 Facilities Page 6 Goal
More information50 Questions before computerization
50 Questions before computerization Before computerization, as an organization, ask yourself: 1. Is there enough time, money and interest to involve all levels within the maintenance department and other
More informationFactors to Consider When Developing a Cloud ROI. Michelle Olson
Factors to Consider When Developing a Cloud ROI Michelle Olson Return On Investment (ROI) The calculation for return on investment can be modified to suit any situation. It all depends on what you decide
More informationShould You Outsource Your Email?
Should You Outsource Your Email? By: Brien M. Posey According to a recent study by Symantec and Gartner (http://www.itworld.com /Webcasts /bytopic/3/index.html), most companies consider email to be a mission
More informationFIVE KEY STEPS TO A SUCCESSFUL DATA-CENTER-RELOCATION
FIVE KEY STEPS TO A SUCCESSFUL DATA-CENTER-RELOCATION During the current economic downturn, more and more companies will relocate their data centers. There are many business reasons for data center relocation
More informationTDWI strives to provide course books that are content-rich and that serve as useful reference documents after a class has ended.
Previews of TDWI course books offer an opportunity to see the quality of our material and help you to select the courses that best fit your needs. The previews cannot be printed. TDWI strives to provide
More informationStatement Of Work. Data Center Thermography Assessment. Service. Professional Services. Table of Contents. 1.0 Executive Summary
Statement Of Work Professional Services Data Center Thermography Assessment Data Center Thermography Assessment Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits
More informationChallenges Facing Today s Data s Centers
Challenges Facing Today s Data s Centers Contents Challenges facing today s Data Centers... 3 Top Factors Affecting Data Center Efficiency... 3 Limited Capital... 3 Application of More Building Blocks
More informationExperience Matters...
Experience Matters... Travelport Data Center offers confidence and space to meet your demanding IT needs Transwestern presents the Travelport Data Center in Denver, Colorado totaling 267,000 SF with 121,600
More informationHow to choose the right email marketing partner for you
How to choose the right email marketing partner for you Over the past 3 years, there has been a 15% year on year increase in visitors who are interested in email marketing at the Technology for Marketing
More informationProject Management Best Practice Benchmarks
A PM SOLUTIONS RESEARCH COMPENDIUM Project Management COST SCOPE Quality SCHEDULE 2 Project Management Senior executives want to know one thing about project management: What s the value? Today more than
More informationEvaluating Workforce Management Solutions
Workforce Management Made Easy WHITE PAPER SERIES Evaluating Workforce Management Solutions A seven-step plan for selecting human resources and payroll management technology that meets your company s needs
More informationFive Nines and Infrared (IR) Testing at Data Centers
Five Nines and Infrared (IR) Testing at Data Centers By Gregory R. Stockton 99.999% uptime five nines. That is what IT (information technology) customers are looking for. Uptime or availability at data
More informationManage Assets With Intelligence Using Key Performance Indicators
E-ISG Asset Intelligence Manage Assets With Intelligence Using Key Performance Indicators A Process White Paper Eric L. Beser, eric.beser@e-isg.com 10/21/2008 Manage Assets with Intelligence Using Key
More informationImproving Data Centers Energy Reliability & Efficiency. December 2015
Improving Data Centers Energy Reliability & Efficiency December 2015 Background The challenges Alternative solutions SATEC approach Advantages Cases Summary Data Centers Energy Challenges Worldwide Data
More informationSaas vs. Traditional ERP: Which is Right for You?
Saas vs. Traditional ERP: Which is Right for You? Eric Kimberling President and Chairman Panorama Consulting Solutions www.panorama-consulting.com Phone: 720-515-1ERP Twitter: @erickimberling 1 Agenda
More informationUsing Overall Equipment Effectiveness: the Metric and the Measures
Using Overall Equipment Effectiveness: the Metric and the Measures The definition and use of Overall Equipment Effectiveness over the years has been widely debated. Many practitioners have found that OEE
More informationSELECTING BUSINESS APPLICATION SOFTWARE: BUILD VS. BUY
WHITE PAPER SELECTING BUSINESS APPLICATION SOFTWARE: BUILD VS. BUY Guidance for Associations Evaluating Software Technology Solutions Build or Buy? It s a recurring and timely question for associations
More informationService Squamish Initiative. Human Resources. Core Service Review
Service Squamish Initiative Human Resources Core Service Review Service Squamish Initiative Human Resources Core Service Review Final Report Executive Summary 5 Key Findings 7 Detailed Findings 9 Recommendations
More informationWhite Paper. Maximizing the Benefits of Computer Aided Medical Transcription by Outsourcing to Multiple MTSOs
White Paper Maximizing the Benefits of Computer Aided Medical Transcription by Outsourcing to Multiple MTSOs Introduction The potential for background speech recognition to decrease costs, reduce turnaround
More informationIntegrated Infrastructure Solutions. Building a Data Center for the Future
Integrated Infrastructure Solutions Building a Data Center for the Future Apps DATA CENTER STACK Information Technology Infrastructure Facilities DB OS VM Compute Storage Network Connectivity Rack Power
More informationFrequently Asked Questions: At-Home Agents
Frequently Asked Questions: At-Home Agents As more and more call center leaders consider, implement and scale the work athome agent model, they face many of the same issues. Knowlagent invited Michele
More informationAGENDA ITEM BACKGROUND TO: GOVERNING BOARD ITEM NUMBER
TO: GOVERNING BOARD AGENDA ITEM BACKGROUND DATE FROM: PRESIDENT SUBJECT: Information Technology Update April 11, 2011 ENCLOSURE(S) REASON FOR BOARD CONSIDERATION INFORMATION Storage Area Network (SAN)
More informationCAN T WE JUST OUTSOURCE IT? Outsourcing has its place. Know what it takes to get it right.
leading thoughts / nov 2013 CAN T WE JUST OUTSOURCE IT? Outsourcing has its place. Know what it takes to get it right. By Lori Bocklund, Strategic Contact Inc. Pipeline Articles www.contactcenterpipeline.com
More informationUniversity of Maine System Talent Management Solution - RFP# 2016-013 ADDENDUM #01
QUESTIONS 1. What is the total employee count the talent management solution will cover? ANSWER: Estimated 10,000 employees with an additional 10,000 student employees overall. 2. What is the anticipated
More informationConverged Infrastructure Solutions. Building a Data Center for the Future
Converged Solutions Building a Data Center for the Future :: Traffic in data centers is growing at an unprecedented rate, with network traffic growing at 25+% and enterprise storage at 50+% annually, 1
More informationMoving the Contact Center to the Cloud? Consider the Options
Moving the Contact Center to the Cloud? Consider the Options DMG Consulting LLC, a leading provider of contact center, back-office and real-time analytics - market research and consulting services, predicts
More informationAnatomy of an IT Outsourcing Deal. Bruce Laco Deloitte John Pickett IT World Canada Barry Sookman McCarthy Tetrault
Anatomy of an IT Outsourcing Deal Bruce Laco Deloitte John Pickett IT World Canada Barry Sookman McCarthy Tetrault 3656867 Agenda Key Considerations for IT Outsourcing Decision Anatomy of an Outsourcing
More informationTRAINING SESSION SUMMARIES FOR MANUFACTURING
TRAINING SESSION SUMMARIES FOR MANUFACTURING Central to the lean philosophy is the mandate to educate everyone in an organization. Productivity s lean training has been called the best in the business,
More informationInformation Technology Integration Putting IT to work in driving deal success
February 2013 A publication from PwC's Deals M&A Integration practice Information Technology Integration Putting IT to work in driving deal success At a glance Research consistently shows that integrating
More informationCareer Development and Succession Planning. Changing Landscape of HR 2012 Conference
Career Development and Succession Planning Changing Landscape of HR 2012 Conference Overview Career Development Program Succession Planning Process Benefits Reduced organizational risk. Increased productivity.
More informationTen Errors to Avoid When Commissioning a Data Center
Ten Errors to Avoid When Commissioning a Data Center By Paul Marcoux White Paper # 149 Executive Summary Data center commissioning can deliver an unbiased evaluation of whether a newly constructed data
More informationEnvisioning the Facilities of The Future Collaborative & Integrated Program Planning February 2013 Update
Envisioning the Facilities of The Future Collaborative & Integrated Program Planning February 2013 Update Facilities Management Programs AALAC Accreditation Program Support Adopt-A-Spot Program Asset Management
More informationTECHNOLOGY SOURCING DECISIONS IN A COMPLEX MARKET
tech line / sep 2014 TECHNOLOGY SOURCING DECISIONS IN A COMPLEX MARKET Three clarifying questions to narrow the field. By Brian Hinton, Strategic Contact Inc. Pipeline Articles www.contactcenterpipeline.com
More informationThe Total Cost of Ownership of. Hosted UC
The Total Cost of Ownership of Hosted UC TCO in a Nutshell When you re shopping around for a new Unified Communications solution and the quotes are rolling in, it can be difficult to make a true apples-to-apples
More informationAPPENDIX 3 TO SCHEDULE 8.1
APPENDIX 3 TO SCHEDULE 8.1 TO THE COMPREHENSIVE INFRASTRUCTURE AGREEMENT 1.0 Transition Services and Affected Employees The highest priority in the design of Northrop Grumman s transition plan is to transfer
More informationMastering Disaster A DATA CENTER CHECKLIST
Mastering Disaster A DATA CENTER CHECKLIST Disaster Doesn t Sleep It s not always a hurricane or a power grid failure that causes businesses to lose their data. More often than not, an isolated event like
More informationA COST ANALYSIS OF OF OUTSOURCING SECURITY OPERATIONS CENTERS. Analysis of a global company with 500 employees in fifteen locations
A COST ANALYSIS OF OF OUTSOURCING SECURITY OPERATIONS CENTERS Analysis of a global company with 500 employees in fifteen locations SECURITY EXPENDITURES ON THE RISE AND SO ARE LOSSES GREATER THAN $10 MILLION
More information