GSA Project. Andrew Peterman Josh Odelson. - Façade Re-model of Portland Federal Building

Size: px
Start display at page:

Download "GSA Project. Andrew Peterman Josh Odelson. - Façade Re-model of Portland Federal Building"

Transcription

1 NOTE: If opened with most recent version of Powerpoint, the image in back should be transparent. If you re not seeing the semi-transparant image it s because you re using an older version. GSA Project Andrew Peterman Josh Odelson - Façade Re-model of Portland Federal Building - Visual Representation and analysis of alternative methods for multi-year re-model process

2 2. PBS, OBS, and WBS PBS WBS OBS

3 3. Level 2 - Generic POP Model Business Objectives Process for achieving objectives Methods for monitoring objectives

4 4. 3-D Model

5 4. 3-D Model Walls, windows, roof, planting Level

6 5. 3-D Model- Coordination Trees interfere directly with façade construction at levels 2-72

7 5. 3-D Model- Coordination Trees interfere directly with façade construction at levels 2-72 *Note after presenting this to GSA and Portland Architects, we discovered they have already started working with the Portland Forester to remove or tie back these trees in advance.

8 5. 3-D Model- Coordination Trees interfere directly with façade construction at levels 1-61 *Note after presenting this to GSA and Portland Architects, we discovered they have already started working with the Portland Forester to remove or tie back these trees in advance.

9 5. 3-D Model- Coordination Lessons Learned: 1) Although the trees don t present a serious threat to construction processes, the building of the 3-D 3 D model highlighted a possible concern. G.C. was able to confirm mitigation plans have begun. 2) Simple interferences should be clear in architectural plan. They ve been discussing this as a problem, but it was no where explicit.

10 5. 3-D Model- Coordination Re-location will have to be coordinated internally between floors. Lobby construction must be coordinated with demolition, move-in in- move-out, out, and façade re- model on upper levels. Upper floors construction may cause interference on lobby construction with crane placement and other equipment placement.

11 6. Process Design Alternative Design Alternative will require additional team members as well as additional procedures Although architects had already included mitigation steps for trees, a planting and landscaping team should be explicitly stated in POP Model.

12 6. Process Design Alternative Process Req. change to 3 floors at a time and earlier completion time. Design Alternative will include changes to the floor shuffling mechanism. 3 floors of construction at a time changes process form.

13 6. Process Design Alternative Baseline requires that 1 floor of impacted work space at a time. Baseline achieves the goal of 1 impacted floor at at time by following this process form.

14 6. Process Design Alternative Process Req. change to 3 floors at a time and earlier completion time. Design Alternative will include changes to the floor shuffling mechanism. 3 floors of construction at a time changes process form.

15 6. Process Design Alternative Comparison Baseline 1 floor impacted during each phase Less coordination and thus less risk for cost/schedule over-runs 3 Flr. Construction Method Completion time << Baseline 3-4 floors impacted during each phase Higher risk for re-work and hidden work.

16 6. Process Design Alternative Comparison Baseline 1 floor impacted during each phase Less coordination and thus less risk for cost/schedule over-runs 3 Flr. Construction Method Completion time << Baseline 3-4 floors impacted during each phase Higher risk for re-work and hidden work. Based on Engineering Judgement Based on SimVision Analysis

17 7. Re-work Risk in 4-D Re-work and coordination due to space-time proximity Trees interfere with façade construction on floors 2-7 *Note after presenting this to GSA and Portland Architects, we discovered they have already started working with the Portland Forester to remove or tie back these trees in advance.

18 7. Re-work Risk in 4-D of Baseline Re-work and coordination due to space-time proximity Demolition on 8th floor may interfere with construction on lobby (falling debris, crane placement, etc.)

19 7. Re-work Risk in 4-D of Process Design Alternative Re-work and coordination due to space-time proximity Construction of 3 floors and lobby concurrently may create severe space- time coordination issues.

20 7. Scheduling Error Noticed w/ 4-D Schedule calls for duplication of work on floors 11 and 10.

21 7. Scheduling Error Noticed w/ 4-D Schedule calls for duplication of work on floors 11 and 10. QuickTime and a TIFF (LZW) decompressor are needed to see this picture.

22 8. SimVision Process-Organization Model Rework resulting from time-space interference of trees and façade work Secondary assignments indicate the tree mitigation team assisting the façade team The coordination activities between façade construction and the lobby renovation are necessary to insure a smooth construction process with minimal interference

23 8. SimVision Process-Organization Model Rework resulting from time-space interference of multiple levels being constructed simultaneously The coordination activities between façade construction and the lobby renovation are necessary to insure a smooth construction process with minimal interference

24 9. SV Baseline vs. Coordination & Rework Large schedule differences are a result of hidden work Schedule risks due to hidden work are large and can be found in all project activities Coordination & Rework Baseline This chart shows the amount of hidden work and schedule duration to expect versus an optimistic CPM schedule

25 9. SV Tree Mitigation Alternative Schedule risks to due hidden work are large and can be found in all project activities Notice almost 1 month reduction in schedule This chart compares a baseline case versus the use of a Tree Mitigation Team to minimize risk and schedule length due to tree interference Tree Mitigation Coordination & Rework Baseline

26 9. SV Baseline vs. Coordination & Rework Large schedule differences are a result of hidden work Schedule risks due to hidden work are large and can be found in all project activities Coordination & Rework Baseline This chart shows the amount of hidden work and schedule duration to expect versus an optimistic CPM schedule

27 9. SV 1 Floor vs. 3 Floors Notice almost 23 month reduction in schedule Schedule risks due to hidden work can be reduced by producing more than one floor at a time This chart compares the renovation of one floor versus three floors at a time in terms of amount of rework and schedule impact 3 Floors 1 Floor Baseline

28 Probability 10. Product and Program Risks Greatest risks 90% S Impacts Impacts During During Construction Operations 50% S Material Personnel 30% 5% 2% Least Risks 2 weeks C F $1M F C $5M *All risks marginally higher for 3 floors at a time because of increased activity Consequence S Schedule of reoccupation and work among floors C Cladding installation and performance F Falling objects or people

29 11. Business Recommendations VDC Implementation: -VDC from the start. Project team would have more efficiently been able to implement VDC solutions had the GSA (Portland) bought-in before we started. -Improves continuity between VDC Solutions and needs of GSA. -Efficient use of student/worker time.

30 11. Business Recommendations Next Steps: -Elaborate on 4-D Models to better reflect the anticipated effects of a 3-level move. Double check assumptions with GSA. -Update SimVision analysis to better represent coordination and re-work effects of the two different models. Affirm/Negate assumptions in our SimVision model -Implement current Revit 3-D Model into all of our models.

31 12. TEI iroom hardware PC 2, ,000 Projector 3, ,000 Smart Board 2, ,000 installation 2, ,000 Software 4D 10, ,000 ADT 15, ,000 Primavera 13, ,000 Organization model 10, ,000 Training (days) 2, ,500 Internal staff development ,500 Total 100,000 Budget 100,000 iroom hardware costs remain low because all participants agree to have project teams located in the same building All necessary software for modeling the façade and lobby renovations are included Total investment cost

32 12. TEI GSA Pays all GC pays 10% Sub pays 80% GSA pays 10% Time to payback (years) AEC IT investment by GC AEC IT investment by subcontractor AEC IT investment by Owner: GSA AEC IT investment by GC Rate Baseline ($K) Change Year-1 (K$) Revenue 100, % 102,000 Cost of contracted work 85% 85, % 84,660 Cost of self-performed wo 10% 10, % 12,240 Gross Margin 5,000 5,100 Sales, G&A 2% 2,000 2,040 IT investment 10 Amortized costs of IT/yr 33% 3 Net income 3,000 3,057 Time to payback (years) 0.2 Net Income change (%) 1.9 AEC IT investment by subcontractor Baseline Rate ($K) Change Year-1 (K$) Revenue 25,000 2% 25,500 Cost of self-performed wo 75% 18, % 18,615 Design fees 10% 2, % 3,060 Gross Margin 3,750 3,825 Sales, G&A 4% 1,000 1,020 IT investment 80 Amortized costs of IT/yea 33% 27 Net income 2,750 2,778 Time to payback (years) 2.8 Net Income change (%) 1.0 AEC IT investment by Owner: Rate Year 1: Design- Build w/o IT (K$) Change w/it Year-2 O&M w/o IT ($K) AEC IT investment by Owner: Year 1: Design- Build w/o IT (K$) Change w/it Year-2 O&M w/o IT ($K) Rate Net revenue from new facility 0 0.0% 15,000 Annual income/initial develop cost 15% Cost of work (or O&M) 10% 100,000 10,000 Design-build savings w/it 2% 2,000 0 O&M savings w/it 0% Amortized facility costs 2.6% 2,564 IT investment Amortized costs of IT/yea 33% 0 Net income 0 2,436 Time to payback (years) Net Income change (%) Best Solution Spreading the costs around to all the major participants allows the value of the investment to be realized within the lifetime of the technology

33 14. 4-D Animation Model QuickTime and a decompressor are needed to see this picture.

34 14. Relative and Predicted costs and Benefits Costs Benefits Tree Risk without Tree Mitigation Team More time (925 days vs. 905 days) More rework (200 FTE days vs. 100 FTE days) Less product risk (60% vs. 75%) Tree Risk with Tree Mitigation Team More product risk (75% vs. 60%) Less time (905 days vs. 925 days) Less rework (100 FTE days vs. 200 FTE days) Costs and Benefits were determined by using the analysis from Sim Vision for the purpose of determining the alternative that will best allow the GSA to meet their business objectives

35 15. Measurable Process Objectives -Monitor Tenant satisfaction with construction process to ensure +/- 2% tenant occupancy after construction completion -VDC method: 3-D/4-D Model shown to stakeholders. 4-D will help mitigate conflicts with tenants on frontend. -0 RFI s on site construction as a result of clear construction schedule and 4-D model. All project team members are able to clearly measure on a weekly basis how many RFIs are recorded and compare with process objective.

36 16. Measurable Controllable Objectives -3-D Model represents 100% of objects specified in POP Model. -Monitor schedule conformance on weekly basis with respect to master schedule % of assumptions in model clearly stated by project team, GSA, and all stake holders.

37 17. Instance POP Model Product Form Organization Form Owner Organization General Contractor Design Team Demolition Team Construction Team Move Team Lobby Team Tree Mitigation Team (landscape) NOTE: Major changes between generic and instance occur in the form area. In order to display Product Forms, they are not listed by each individual wall object.

38 17. Instance POP Model Process Form 17th Flr. Move to 3rd Flr. (3 --> alt. facility) Vacate Floor 17 Flr. 17 Exterior Re-cladding 16th Flr. Move to 17th Floor Demolish 16th Floor Flr. 16 Exterior re-cladding 15th Flr. move to 16th Flr. Demolish 15th Floor Flr. 15 Exterior Re-cladding 14th Flr. Move to 15th Flr. Demolish 14th Flr. Flr. 14 Exterior Re-Cladding 13th Flr. Move to 14th Flr. Demolish 13th Flr. Flr. 13 Exterior Re-Cladding 12th Flr. Move to 13th Flr. Demolish 12th Flr. Flr. 12 Exterior Re-cladding 11th Flr. Move to 12th Flr. Demolish 11th Flr. Flr. 11 Exterior Re-Cladding 10th Flr. Move to 11th Flr. Demolish 10th Flr. Flr. 11 Exterior re-cladding (2) Re-occupy 11th Flr. (2) Demolish 10th Flr. (2) Flr. 10 Exterior re-cladding 9th Flr. Move to 10th Flr. Demolish 9th Flr. Flr. 9 Exterior Re-cladding Re-model Lobby 8th Flr. Move to 9th Flr. Demolish 8th Flr. Flr. 8 Exterior Re-cladding 7th Flr. Move to 8th Flr. Demolish 7th Flr. Flr. 7 Exterior Re-cladding 6th Flr. Move to 7th Flr. Demolish 6th Flr. Flr. 6 Exterior re-cladding 5th Flr. Move to 6th Flr. Demolish 5th Flr. Flr. 5 Exterior Re-cladding 4th Flr. Move to 5th Flr. Demolish 4th Flr. Flr. 4 Exterior Re-cladding 3rd Flr. Move to 4th Flr. Demolish 3rd Flr. Flr. 3 Exterior re-cladding 2nd Flr. Move to 3rd Flr. Demolish 2nd Flr. Flr. 2 Exterior re-cladding Re-occupy Flr. 2 Planting

39 18. Executive Summary The purpose of the GSA project was to examine the ramifications of not taking action to prevent trees from interfering with the process of renovating the façade of the Wendall Wyatt Federal Building and to prescribe a solution to this problem. To meet these objectives, Virtual Design and Construction practices were implemented including the use of 3D and 4D modeling, SimVision, Primavera, and POP models. These tools aided in determining the costs and benefits associated with having no response to the tree problem and having an active team working to mitigate the tree problem. Our analysis demonstrates clearly that creating a Tree Mitigation Team improves the schedule and rework performance of the project at negligible increases in product risk.

40 18. Executive Summary Part II After late discussions with the GSA, we found that the trees did not pose as much of a problem. The GSA Team was more interested in alternative floor shuffling methods from the proposed architectural program. We analyzed the challenges, benefits, and perceived negative impacts of a simultaneous 3-floor façade re-model. Using SimVision we analyzed hidden work, coordination, and risk. Using ADT, CommonPoint, and Primavera we were able to clearly represent visually the two different processes. Within the 3D/4D models we were able to identify possible coordination issues that may not have been apparent without a visual representation of the paper schedule.

School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191

School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191 School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191 Section 1: General 1.0 Alignment with Organizational Vision In the space provided below, read

More information

Project Management Plan for

Project Management Plan for Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...

More information

Manage Deliverables - Construction Step 6. July 12, 2012

Manage Deliverables - Construction Step 6. July 12, 2012 Manage Deliverables - Construction Step 6 July 12, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement

More information

APPLICATION & RULES FOR OWNERS, CONTRACTORS, MOVERS

APPLICATION & RULES FOR OWNERS, CONTRACTORS, MOVERS THE STRATFORD AT PELICAN BAY CONDOMINIUM ASSOCIATION, INC. Remodeling, Renovating, Altering, Repairing and Moving APPLICATION & RULES FOR OWNERS, CONTRACTORS, MOVERS 5601 TURTLE BAY DR. NAPLES, FL 34108

More information

Tool With Best Project Management Skills

Tool With Best Project Management Skills The Value of BIM We ADD TO PROJECTS : Tool With Best Project Management Skills - To save time, material management & cash flows - Project reviews and Management reporting - Issueless work at sites - Easy

More information

Saving Troubled Projects

Saving Troubled Projects Saving Troubled Projects 2012 Instructor and Developer Mark Waldof Mark Waldof Consulting Retired Lockheed Martin University of Minnesota Instructor CCE Business Improvements Consultant Project Management

More information

Seattle Public Schools The Office of Internal Audit

Seattle Public Schools The Office of Internal Audit seaonly Seattle Public Schools The Office of Internal Audit Capital Internal Audit Report Issue Date: June 16, 2015 Introduction and Background Executive Summary This report contains the results of our

More information

DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW DATA CENTER DESIGN OVERVIEW Presented by Horst Pfendt Critical Facilities Round Table 7 th QUARTERLY MEETING December 17, 2004 DATA CENTER DESIGN OVERVIEW INTRODUCTION In the next couple of hours I will

More information

ASBESTOS MANAGEMENT POLICY

ASBESTOS MANAGEMENT POLICY ASBESTOS MANAGEMENT POLICY Published : 4th Revision December 2014 1 Table of Contents INTRODUCTION... 3 DUTY TO MANAGE ASBESTOS... 3 DUTIES OF CAMPUS SERVICES... 3 1.0 POLICY OBJECTIVES... 5 2.0 RESPONSIBILITIES...

More information

Sample Examination Questions

Sample Examination Questions Sample Examination Questions The following questions are examples of the type of questions that appear on the PMP Certification Examination. Disclaimer: These questions are intended for study purposes

More information

PS.12. 4D Scheduling A Case Study

PS.12. 4D Scheduling A Case Study PS.12 4D Scheduling A Case Study Mr. Abhimanyu Basu PE PSP A 4D schedule is a 3 dimensional CAD model How long would it take. attached to the fourth dimension of time via a schedule. The concept of 4D

More information

NFSA Project Management Guidelines

NFSA Project Management Guidelines NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and

More information

MODEL SCHEDULING SPECIFICATION

MODEL SCHEDULING SPECIFICATION MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with

More information

NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE)

NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE) NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE) If your home or business is located within a 100-year floodplain and it was constructed through a County Building

More information

SWEBOK Certification Program. Software Engineering Management

SWEBOK Certification Program. Software Engineering Management SWEBOK Certification Program Software Engineering Management Copyright Statement Copyright 2011. All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Introduction to the ITS Project Management Methodology

Introduction to the ITS Project Management Methodology Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer

More information

PROJECT SCOPE MANAGEMENT

PROJECT SCOPE MANAGEMENT 5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully

More information

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by: Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective

More information

Corrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached

Corrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached ADDENDUM #1 RFP: 500 16 Design Build Maintenance & Operations Complex The following changes to the Request for Proposal and clarifications are provided based on questions received and must be added/considered

More information

Project Management Concepts

Project Management Concepts Project Management Concepts Day Workshop Course PM12 PM12 - Project Management Concepts Course ID: PM12 Credits: 21 PDUs Course Duration: 3 days Course Level: Basic 3 Days 21 PDUs Course Description: In

More information

Project Management Planning

Project Management Planning Overview of Resource Planning Every organization has a limited number of resources to perform tasks. A project manager's primary role is to find a way to successfully execute a project within these resource

More information

Applied Software Project Management

Applied Software Project Management Applied Software Project Management Project Schedules http://www.stellman-greene.com 1 What is a project schedule? The project schedule is a calendar that links the tasks to be done with the resources

More information

Industrial Case Study of Electronic Design, Cost and Schedule Integration

Industrial Case Study of Electronic Design, Cost and Schedule Integration Industrial Case Study of Electronic Design, Cost and Schedule Integration Sheryl Staub 1, Martin Fischer 2 and Melody Spradlin 3 1 Project Engineer, Hathaway/Dinwiddie Construction Group Santa Clara, CA

More information

School Construction Projects

School Construction Projects The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect

More information

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses BIM.03 Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses Mr. Kevin Coyne, PE PSP T his paper explores the use of 4D models, which provide a virtual construction

More information

Construction of A hospital Building

Construction of A hospital Building Construction of A hospital Building Project Plan for Project Management Course-TNE065 (Version 1.0) Submitted by: Imran Kaleem Siddiqui-imrsi301 Mohammad Sajid--------muhsa777 Rajesh Kumar------------rajku619

More information

Applied Software Project Management

Applied Software Project Management Applied Software Project Management Software Project Planning http://www.stellman-greene.com 1 Who needs software? Most software is built in organizations for people with specific needs. A stakeholder

More information

Accounting System. Page 1 of 9

Accounting System. Page 1 of 9 Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

APPLICATION. Internal Use Only 1311 Chestnut Street TDLR# Bastrop, Texas 78602 Intake Date

APPLICATION. Internal Use Only 1311 Chestnut Street TDLR# Bastrop, Texas 78602 Intake Date For all Residential Construction, Commercial Construction, Fences, Accessory Buildings, and any other structural addition, remodel or new construction within the City Limits of Bastrop. No partial submittals

More information

Exhibit C: Scope of Work and Schedule of Deliverables

Exhibit C: Scope of Work and Schedule of Deliverables Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza

More information

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room. APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use

More information

Using the Autodesk Revit GSA Spatial Template

Using the Autodesk Revit GSA Spatial Template Autodesk Revit Template for the U.S. General Services Administration Using the Autodesk Revit GSA Spatial Template This document helps you to get started in using the GSA Spatial Template Revit file in

More information

Design Build Institute of America (DBIA)

Design Build Institute of America (DBIA) Design Build Institute of America (DBIA) 1 D E S I G N B U I L D L E S S O N S L E A R N E D J O S É D. N U Ñ E Z, L E E D A P V I C E C H A N C E L L O R F A C I L I T I E S P L A N N I N G, M A I N T

More information

Auditing construction contract change orders

Auditing construction contract change orders Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. Auditing construction contract change orders Presenter Tony Ollmann, CPA,

More information

Planning and Construction Management Services

Planning and Construction Management Services Planning and Construction Management Services Construction Project Management Services New construction, major renovations or improvements to building structures and systems are part of the Department's

More information

County Of Sonoma Agenda Item Summary Report

County Of Sonoma Agenda Item Summary Report County Of Sonoma Agenda Item Summary Report Department: General Services Contact: Rob Kambak Phone: (707) 565-3211 Board Date: 10/27/2009 4/5 Vote Required Deadline for Board Action: AGENDA SHORT TITLE:

More information

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS 14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya

More information

OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)

OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.

More information

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS MEETING DATE: March 16, 2011 SUBJECT: PRESENTER: ATTACHMENTS: Construction Management Update David Berry Yes 1. Construction Management

More information

Cost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP

Cost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP Cost & Schedule Risk Assessment Using @Risk 6.0 Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP 24 October 2012 What If? In Business and in Life: We always made the best possible decisions, and Implemented

More information

Software Project Management

Software Project Management Software Project Management Software Project Planning Vivek Bhatnagar Assoc Professor Who needs software? Most software is built in organizations for people with specific needs. A stakeholder is a anyone

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized

More information

Post Occupancy Evaluation (POE) Technical Instructions

Post Occupancy Evaluation (POE) Technical Instructions 1.0 Purpose These technical instructions define the typical steps required by HHS personnel in the use of the. The POE consists of a detailed and systematic assessment of a facility that is operational

More information

Multi-Site Project Management A Program for Reducing the Cost of Technology Deployment at Department of Energy Sites - 9480

Multi-Site Project Management A Program for Reducing the Cost of Technology Deployment at Department of Energy Sites - 9480 Multi-Site Project Management A Program for Reducing the Cost of Technology Deployment at Department of Energy Sites - 9480 N. R. Davis, E. R. Selden, D. B. Little, M. C. Coleman, J. T. Bennett Washington

More information

APPENDIX E GUIDELINES FOR PREPARING CAPITAL PROJECT COST ESTIMATES

APPENDIX E GUIDELINES FOR PREPARING CAPITAL PROJECT COST ESTIMATES APPENDIX E GUIDELINES FOR PREPARING CAPITAL PROJECT COST ESTIMATES The capital project cost estimate is a tool to assist agencies and institutions in creating a project construction budget. It can also

More information

Harvard Computing Group Report

Harvard Computing Group Report Return On ing business goals Mining for savings Estimating costs Selecting applications Calculating Best Practices of Knowledge Management Recycle Republish Reduce Remove Relevance Harvard Computing Group

More information

SECTION 3: ANNEX J UNC CHARLOTTE ILM IMPLEMENTATION PLAN (New Section)

SECTION 3: ANNEX J UNC CHARLOTTE ILM IMPLEMENTATION PLAN (New Section) University of North Carolina at Charlotte Design and Construction Manual Section 3, Annex J UNC Charlotte ILM Implementation Plan SECTION 3: ANNEX J UNC CHARLOTTE ILM IMPLEMENTATION PLAN (New Section)

More information

Changing Project Management - A Quick Guide

Changing Project Management - A Quick Guide Project Management for Scientists Project Organization & Control Christoph U. Keller, c.u.keller@uu.nl Sterrekundig Instituut Utrecht Utrecht University www.astro.uu.nl/~keller Outline Recap Resource Allocation

More information

Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM)

Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM) Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM) Seon-Gyoo Kim Abstract The construction environment has been changing rapidly over

More information

Angelo State University Construction Report

Angelo State University Construction Report May 12, 2009 Angelo State University Construction Report Modular buildings will temporarily house ASU staff during the Hardeman renovation starting this fall. Prepared for: John Russell, Director of Planning

More information

STATE UNIVERSITY OF NEW YORK COLLEGE OF OPTOMETRY 2015 CAMPUS STATEMENT

STATE UNIVERSITY OF NEW YORK COLLEGE OF OPTOMETRY 2015 CAMPUS STATEMENT STATE UNIVERSITY OF NEW YORK COLLEGE OF OPTOMETRY 2015 CAMPUS STATEMENT The College of Optometry, located at 33 West 42nd Street in mid-manhattan, was founded as a State College within the SUNY system

More information

CONSTRUCTION RISK MANAGEMENT. TABLE of CONTENTS:

CONSTRUCTION RISK MANAGEMENT. TABLE of CONTENTS: CONSTRUCTION RISK MANAGEMENT TABLE of CONTENTS: 1. Introduction 2 2. Project Start Up Risk Exposure Analysis 3 3. Insurance 5 4. Additional Advice 8 5. Bonding 9 6. Subcontractor Default Insurance 11 1

More information

St. Jerome s University Responses to Pre-Submittal Questions

St. Jerome s University Responses to Pre-Submittal Questions St. Jerome s University Responses to Pre-Submittal Questions Questions have been assembled and placed in a consecutive numerical order for ease of referencing questions and responses. Identity of firm

More information

Program Life Cycle Cost Driver Model (LCCDM) Daniel W. Miles, General Physics, June 2008

Program Life Cycle Cost Driver Model (LCCDM) Daniel W. Miles, General Physics, June 2008 Program Life Cycle Cost Driver Model (LCCDM) Daniel W. Miles, General Physics, June 28 Introduction Several years ago during the creation of the Periscope Total Ownership Cost (TOC) Program, it became

More information

Asbestos Containing Materials Survey And Register Moil Shopping Centre

Asbestos Containing Materials Survey And Register Moil Shopping Centre Asbestos Survey and Register Asbestos Containing Materials Survey And Register Moil Shopping Centre Property Name: Moil Shopping Centre Property Address: 8 Moil Cres. Darwin, NT Prepared for: John Nicolakis

More information

TD AMERITRADE Park Omaha

TD AMERITRADE Park Omaha TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment

More information

Construction Webinar October 16, 2012. Stewart Roberts Claims Manager

Construction Webinar October 16, 2012. Stewart Roberts Claims Manager Construction Webinar October 16, 2012 Stewart Roberts Claims Manager CURIE Property Policy 4.3 PROPERTY EXCLUDED This policy does not apply to: a) motor vehicles licensed for regular highway use b) New

More information

BIM Extension into Later Stages of Project Life Cycle

BIM Extension into Later Stages of Project Life Cycle BIM Extension into Later Stages of Project Life Cycle Pavan Meadati, Ph.D. Southern Polytechnic State University Marietta, Georgia This paper discusses the process for extending the implementation of the

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and

More information

The Future of Project Management: Preparing The Next Generation Project Manager

The Future of Project Management: Preparing The Next Generation Project Manager 1 The Future of Project Management: Preparing The Next Generation Project Manager By Harold Kerzner, Ph.D. 10/9/2010 2010 International Institute for Learning, Inc. 1 Best Practices in Project Management

More information

Planning and Managing A Construction/Renovation Project

Planning and Managing A Construction/Renovation Project Planning and Managing A Construction/Renovation Project NAHC Annual Conference Presented by: Bill Henley, The Columbia Property Group This Old Co-op Planning a Rehab/Renovation Project All planning and

More information

Contract / Construction Management. November 2006

Contract / Construction Management. November 2006 Contract / Construction Management November 2006 Presentation Outline I. Introduction Project Management II. Contract/Construction Management Stage 1: Construction Period Stage 2: Defects Liability Period

More information

Using Desktop Project Management Technology for Construction Close-Out

Using Desktop Project Management Technology for Construction Close-Out White Paper 2011 Using Desktop Project Management Technology for Construction Close-Out How utilizing desktop project management technology can improve efficiency, collaboration, and cost during close-out

More information

Engineering and Construction

Engineering and Construction Engineering and Construction I Manage risk. Protect profit. Today s engineering and construction market is highly competitive, driving profit margins down as risks increase. It only takes one failed project

More information

Work Breakdown Structure. http://www.mekonginstitute.org/

Work Breakdown Structure. http://www.mekonginstitute.org/ Work Breakdown Structure Project Scope Management Includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully

More information

Consultancy Services Proposal

Consultancy Services Proposal Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

Major Changes to Public Contracting and the CM/GC Delivery Method

Major Changes to Public Contracting and the CM/GC Delivery Method Major Changes to Public Contracting and the CM/GC Delivery Method Jeremy Vermilyea Schwabe Williamson & Wyatt Oregon Public Contracting Code & Model Public Contract Rules Section 137-049-0690 The CM/GC

More information

White paper. Innate Resource Management Software. Introduction to Reports

White paper. Innate Resource Management Software. Introduction to Reports White paper Innate Resource Management Software Introduction to Reports Presenting project, cost, time and resource information, across the organization Innate reports can significantly improve the visibility

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

FIVE-YEAR PLAN CAPITAL PROJECTS COST PROJECTIONS

FIVE-YEAR PLAN CAPITAL PROJECTS COST PROJECTIONS Xavier University of Louisiana Facility Planning and Management FIVE-YEAR PLAN CAPITAL PROJECTS COST PROJECTIONS Marion B. Bracy Vice President of Facility Planning and Management P.O. Box #54 Administration

More information

The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2

The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2 The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2 1 Curtin University of Technology, Perth, Western Australia 2 Broad Construction Services, Perth, Western

More information

The Integrated Design Process

The Integrated Design Process The Integrated Design Process The Integrated Design Process (IDP) has been developed on the basis of experience gained from a small Canadian demonstration program for high-performance buildings, the C2000

More information

Enhancing Pre-Design Services Using Business Intelligence and Building Information. Wednesday, May 2, 2007, 9:30a.m. to 11:00a.m.

Enhancing Pre-Design Services Using Business Intelligence and Building Information. Wednesday, May 2, 2007, 9:30a.m. to 11:00a.m. Enhancing Pre-Design Services Using Business Intelligence and Building Information Wednesday, May 2, 2007, 9:30a.m. to 11:00a.m. Enhancing Pre-Design Services Using Business Intelligence and Building Information

More information

SHARP. Focus. AESS serves as the focal point of a small eye-care office in Austin. BY BRIAN SAYRE, P.E., AND K. MARK MERRYMAN, P.E.

SHARP. Focus. AESS serves as the focal point of a small eye-care office in Austin. BY BRIAN SAYRE, P.E., AND K. MARK MERRYMAN, P.E. SHARP Focus BY BRIAN SAYRE, P.E., AND K. MARK MERRYMAN, P.E. AESS serves as the focal point of a small eye-care office in Austin. YOU COULD SAY THAT Eye Physicians of Austin had a clear vision for its

More information

Using the Coordination Monitoring Feature in Revit Structure to Manage Projects Across Disciplines

Using the Coordination Monitoring Feature in Revit Structure to Manage Projects Across Disciplines Using the Coordination Monitoring Feature in Revit Structure to Manage Projects Across Disciplines John Herridge, AIA Autodesk, Inc. SE204-1 Intended for existing Revit users, this session explores the

More information

CITY OF LOS ANGELES CALIFORNIA

CITY OF LOS ANGELES CALIFORNIA MERCEDES M. MÁRQUEZ GENERAL MANAGER PUBLIC COUNTERS 3550 WILSHIRE BOULEVARD, 15 TH FLOOR LOS ANGELES, CA 90010 3415 SOUTH SEPULVEDA BOULEVARD, SUITE 150 LOS ANGELES, CA 90034 8475 SOUTH VERMONT AVENUE

More information

General Liability Insurance Application (Contractors Supplemental Questionnaire)

General Liability Insurance Application (Contractors Supplemental Questionnaire) Insurance Services www.metroinsurance.com General Liability Insurance Application Note: Throughout this questionnaire the words you and your include all entities seeking coverage. Note: This and other

More information

Knock Down Rebuild. Building Process Building process - knock down rebuild 1

Knock Down Rebuild. Building Process Building process - knock down rebuild 1 Knock Down Rebuild Building Process Building process - knock down rebuild 1 Building Process Your action Our action REMINDER Pre site Step 1 New Home Selection Congratulations. This marks the start of

More information

Cover page. Introduction to the Earthquake Resistance Capacity Assessment and Reinforcement of Taipei Water Department Office Building.

Cover page. Introduction to the Earthquake Resistance Capacity Assessment and Reinforcement of Taipei Water Department Office Building. Cover page Title: Authors: Introduction to the Earthquake Resistance Capacity Assessment and Reinforcement of Taipei Water Department Office Building. Ming-Fuw Wang (Presenter and Contact person) Chief

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

CHAPTER 12 TRANSFER POLICY

CHAPTER 12 TRANSFER POLICY INTRODUCTION CHAPTER 12 TRANSFER POLICY This chapter explains the Housing Authority of Danville s transfer policy, based on HUD regulations, HUD guidance, and Housing Authority of Danville policy decisions.

More information

COMMISSIONING SUMMARY TEMPLATE

COMMISSIONING SUMMARY TEMPLATE COMMISSIONING SUMMARY TEMPLATE The following template shall be completed and submitted for permit review. Provide additional attachments as appropriate. SECTION 1 PROJECT DESCRIPTION Name of Project Project

More information

Multi-user Collaboration with Revit Worksets

Multi-user Collaboration with Revit Worksets Autodesk Revit White Paper Multi-user Collaboration with Revit Worksets Starting Your First Multi-user Project On many building projects, designers work in teams with each assigned a specific functional

More information

This AGREEMENT made the... day of... between the HUNTER WATER CORPORATION (hereinafter called the Corporation ) and ...

This AGREEMENT made the... day of... between the HUNTER WATER CORPORATION (hereinafter called the Corporation ) and ... MINOR WORKS NO.... This AGREEMENT made the... day of... between the HUNTER WATER CORPORATION (hereinafter called the Corporation ) and of... Hereinafter called the Developer ) It is agreed that the Developer

More information

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing

More information

Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling.

Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling. Planning & Scheduling CSTM 462 Managing a project through time and resources. The need for proper planning and scheduling. Project Management Objectives 1. Eliminate or reduce project RISK. 2. Obtain a

More information

BIM and Lean Construction Can BIM remove waste from construction processes?

BIM and Lean Construction Can BIM remove waste from construction processes? Tekla European BIM Forum 2014 BIM and Lean Construction Can BIM remove waste from construction processes? Assoc. Professor Rafael Sacks What is Lean Construction? Waste in construction? Lean and BIM Synergies

More information

Scheduling Best Practices

Scheduling Best Practices In this article, as part of a continuing series of articles regarding critical path method (CPM) scheduling, Warner reviews various facets of the process of preparing, analyzing and utilizing schedules

More information

Systems Selection Enclosure Systems Material Selection Assessment and Mitigation

Systems Selection Enclosure Systems Material Selection Assessment and Mitigation Return to Curriculum Home CES Home Find an AIA/CES Registered Course Self Report a Learning Activity MATERIALS AND METHODS To develop professionally in Practice with a focus on sustainable design, you

More information

Supporting Workflow Overview. CSC532 Fall06

Supporting Workflow Overview. CSC532 Fall06 Supporting Workflow Overview CSC532 Fall06 Objectives: Supporting Workflows Define the supporting workflows Understand how to apply the supporting workflows Understand the activities necessary to configure

More information

Scheduling Best Practices

Scheduling Best Practices RECOVERY SCHEDULES By Mark I. Anderson, Executive Vice President and Chief Operating Officer of Warner Construction Consultants, Inc. In this article, as part of a continuing series of articles regarding

More information

1.040 Project Management

1.040 Project Management MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Fred Moavenzadeh Spring 2009

More information

How To Use P6 For A Project Scheduling System

How To Use P6 For A Project Scheduling System Managing Assets Through Enterprise - Wide Scheduling Scott Lowe, P.E. Principal, Trauner Consulting Services, Inc. Scott Lowe, Principal, Trauner Consulting Services CPM Scheduler Claims Analyst Expert

More information

Planning and Scheduling Time it Right

Planning and Scheduling Time it Right Planning and Scheduling Time it Right Key drivers for Success Presentation by Mr Alan Bolger FIEAust to the Australian Cost Engineering Society, Victorian Branch 22 April 2013 Alan Bolger: Background Over

More information