Schedule Risk Analysis A large DoD Development Program

Size: px
Start display at page:

Download "Schedule Risk Analysis A large DoD Development Program"

Transcription

1 Schedule Risk Analysis A large DoD Development Program

2 So, who s the dude? Jim Aksel PMP, PMI SP Microsoft MVP 35 Years experience aerospace/defense Co Author PMI Practice Standard for Scheduling Program and Scheduling Excellence Guide (PASEG) DID MGT Full EVMS capabilities Scheduling Yoda jim@projectpmo.com ProjectPMO PO Box28113 Anaheim, CA (714)

3 What is a Schedule Risk Analysis Monte Carlo Simulation of a compliant Schedule Model Assists in establishing timeframe for event completion If Schedule Model is cost/resource loaded, can predict costs too

4 The Goal Land in the red box

5 Today s Example USN Missile Program Prime with 1 subcontractor Master/Subproject file 5277 discrete nonloe tasks Requires correlation Requires probabilistic branching

6 Preliminaries Schedule Model preparation Excel/Computer preparation

7 Schedule Model Preparation Proper Schedule Model status Consider an analysis tool such as DCMA14 Point Assessment Things that were supposed to happen actual did! No time warps Everyone has a proper successor xf

8 Schedule Model Preparation Custom Fields Clear all formulas, lookup values, etc. Consider deleting data Retain only Min, Most likely, Max Level of Effort Hammock Task Pure Level of Effort Constraints Remove MFO, MSO, SNET, SNLT, FNET, FNLT Retain only those from external Monte Carlo Engine does not need custom field calculations Level of Effort should never drive a path remove it. Think very carefully about constraint dates Schedule logic may change: FS, FF, SS, SF.

9 Excel and Computer Preparation Excel Latest Service Packs Enable Multi Threaded Calculations RAM! Consider Office x64 bit Windows manages Virtual Memory Disable power management including within the BIOS It will take some time, use a different machine

10 Triple Point Estimates Remaining Duration Minimum, Most Likely, Maximum Consider these Tasks with no upside (Min close to Most Likely compared to Max) Tasks with no downside (Max close to Most likely compared to Min) Inherent high risk (Max Min exceeds 25% of Most Likely) Or better... Is data available to support more realistic distributions? Requires only a mean and standard deviation or other factor

11 More on Triple Point Estimates Banding +x/ y need not be symmetrical Simple, not very rigorous More rigor required on Critical Path tasks (1 st,2 nd,3 rd ) Historical Performance Decomposition Analogy Ratio/Parametric Units Expert opinion Effort

12 Probability Distribution Use Triangular unless you have some valid reason to use something else. Why? Has the largest Standard Deviation of the common distributions Drives uncertainty Spreads the results Easily understood and adaptable Only requires three points

13 Match the Distribution to the Data Is this triple point truly Normally Distributed?

14 @Risk Tool Hints Check Simulation Engine settings for faster results (Standard, Accelerated) Consider using Project/Excel 2007 MS Project Table ready as you want it (Remaining Duration) Save frequently

15 @Risk Tool Hints Unprotect the Tasks Sheet to apply filtering

16 Correlations Tasks split between $ and hours (EVMS Requirement) Long preparation time Long test time

17 Probabilistic Branching A choice of task paths exists after completion of a task One to Many relationship (at least 2) Each successor path has a mutually exclusive probability Must sum to 1.0 Chains can be anywhere in the Schedule Model Need not end in same place Should trace forward to final task Use Inactive Tasks Could be Risk Register Items?

18 Probabilistic Branching Prerequisite branches Choice 1a 90% Choice 2a 10%

19 Probabilistic Branching Certain material obsolescence issues (90/10) Setup logic drives both paths At least 1 day duration

20 The Main Event!

21

22 Effects of Conditional Branching

23 Tornado Chart

24 Tornado Correlations

25 Did we do enough? 1000 Iterations run Desired granularity ±1 day Error Term µ

26 Did we do enough? From Statistics Z=1.96 (95 th Percentile) s=σ=31.28 from prior slide Set error = 1 day Solve for n n=3759 At n=1000, Error is about 1.93 days

27 Output Convergence At some point, output changes small enough to be ignored You can effectively stop at this point See Simulation Settings

28 What We Learned Systems Engineering has more impact to Critical Path than we thought Balloon Squeezing is difficult Mitigations on the Tornado Tasks is only one way to do it. Forces creativity to increase probabilities of reaching set dates The Golden Rule

29 For Consideration Resource Leveling not considered Leveling delays? Overloaded resources? Money constraints Mitigate through corporate funding or other cost shares? Does it produce progress gaps (standing army)? Reduce conditional branching if possible Eliminate Correlation through improved logic?

30 Jim Aksel ProjectPMO PO Box Anaheim, CA (Office) or (Cell)

Basic Schedule Analysis

Basic Schedule Analysis Basic Schedule Analysis Topics Why are Schedules Important Scheduling Basics Attributes of a Valid Schedule Scheduling Best Practices Basic Schedule Analysis Tools and Techniques Sources: NASA Schedule

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Importance of Finish to Start Successors

Importance of Finish to Start Successors Importance of Finish to Start Successors Jim Aksel, PMP, PMI SP Director of Project Management Celeris Systems, Inc. In addition to creating schedule logic the way workers ordinarily perform their business

More information

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1 IT Training Microsoft Project Vicky Samways, IT Training Information System Services Version 2.1 Scope Learning outcomes Find out when and how to use Microsoft Project. Learn how to create a project, break

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added. Chapter 3 Effort Driven Task Type By now, you will be getting sick of my repetition of the effort driven formula: Resource Units X Duration = Work I make no apologies, as it needs to be engraved in the

More information

Quantitative Risk Analysis with Microsoft Project

Quantitative Risk Analysis with Microsoft Project Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials

More information

Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective

Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective 1. Abstract PM WORLD TODAY FEATURED PAPER MARCH 2009 Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective By Satya Narayan Dash, PMP, MCP and Uttam Kumar Singh, PMP, PAHM MS Project

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

The Basics of Best Practices. Elden F. Jones II, MSPM, PMP, CMII Elden.Jones@ThePMProfs.com

The Basics of Best Practices. Elden F. Jones II, MSPM, PMP, CMII Elden.Jones@ThePMProfs.com Scheduling 101 The Basics of Best Practices Elden F. Jones II, MSPM, PMP, CMII Elden.Jones@ThePMProfs.com The Build Develop thewbs Define work packages Define activities iii Define logic Define resources

More information

Contents. Preface 1. Best Practice 4 Establishing the Duration of All Activities 65 Durations 65 Estimating Durations 66 Calendars 68

Contents. Preface 1. Best Practice 4 Establishing the Duration of All Activities 65 Durations 65 Estimating Durations 66 Calendars 68 GAO Work package: Install first floor joists 1 Install first floor joists and decking 2 Install water proofing on exterior basemant walls 3 Finish excavate and pour basement floor 4 Frame first floor walls

More information

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides

More information

INT 3 Schedule Risk Analysis

INT 3 Schedule Risk Analysis INT 3 Schedule Risk Analysis David T. Hulett, Ph.D. Hulett & Associates, LLC ICEAA Professional Development and Training Workshop San Diego, CA June 9-12, 2015 1 Agenda Add uncertainty to the schedule,

More information

Chapter 6. (PMBOK Guide)

Chapter 6. (PMBOK Guide) Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

Problems, Methods and Tools of Advanced Constrained Scheduling

Problems, Methods and Tools of Advanced Constrained Scheduling Problems, Methods and Tools of Advanced Constrained Scheduling Victoria Shavyrina, Spider Project Team Shane Archibald, Archibald Associates Vladimir Liberzon, Spider Project Team 1. Introduction In this

More information

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method

More information

LLamasoft K2 Enterprise 8.1 System Requirements

LLamasoft K2 Enterprise 8.1 System Requirements Overview... 3 RAM... 3 Cores and CPU Speed... 3 Local System for Operating Supply Chain Guru... 4 Applying Supply Chain Guru Hardware in K2 Enterprise... 5 Example... 6 Determining the Correct Number of

More information

www.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

www.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP PMBOK Guide 5 th Edition and MS Project 2010: A Practical Step-by-Step Approach 1. Abstract By Satya Narayan Dash, PMP, CSM, MCP Project Management Body of Knowledge (PMBOK) Guide, from PMI, comes with

More information

Project Day Numbering

Project Day Numbering Project Day Numbering How to format a Microsoft Project schedule to use Project Dates instead of Calendar Dates 2009 Celeris Systems, Inc. Jim Aksel, PMP, PMI SP, MVP Celeris Systems, Inc. Project Date

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Systems Analysis and Design

Systems Analysis and Design Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis

More information

Instruction Manual Service Program ULTRA-PROG-IR

Instruction Manual Service Program ULTRA-PROG-IR Instruction Manual Service Program ULTRA-PROG-IR Parameterizing Software for Ultrasonic Sensors with Infrared Interface Contents 1 Installation of the Software ULTRA-PROG-IR... 4 1.1 System Requirements...

More information

Representing Uncertainty by Probability and Possibility What s the Difference?

Representing Uncertainty by Probability and Possibility What s the Difference? Representing Uncertainty by Probability and Possibility What s the Difference? Presentation at Amsterdam, March 29 30, 2011 Hans Schjær Jacobsen Professor, Director RD&I Ballerup, Denmark +45 4480 5030

More information

A collection of Safran Project report samples for project professionals

A collection of Safran Project report samples for project professionals A collection of Safran Project report samples for project professionals Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger www.safran.com Contents Introduction... 2 About the Reports

More information

DCMA 14-Point Assessment Metrics

DCMA 14-Point Assessment Metrics DCMA 14-Point Assessment Metrics The integrity of a CPM schedule is one of the critical factors in improving a project s likelihood of success 1! There is a well-established correlation between the quality,

More information

Scheduling Process Maturity Level Self Assessment Questionnaire

Scheduling Process Maturity Level Self Assessment Questionnaire Scheduling Process Maturity Level Self Assessment Questionnaire Process improvement usually begins with an analysis of the current state. The purpose of this document is to provide a means to undertake

More information

USER S GUIDE for DSM@MIT

USER S GUIDE for DSM@MIT USER S GUIDE for DSM@MIT TABLE OF CONTENTS 1. OVERVIEW...3 2. INSTALLATION...5 3. FUNCTIONS...7 3.1 Inputs for the Structuring Module...7 3.2 Analyses in the Structuring Module...8 3.3 Editing the DSM...13

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management.

The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management. Knowledge Areas The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management. These are: Project Integration Management Project Scope

More information

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4 MACIASZEK, L.A. and LIONG, B.L. (2005): Practical Software Engineering. A Case Study Approach Addison Wesley, Harlow England, 864p. ISBN: 0 321 20465 4 Chapter 4 Software Project Planning and Tracking

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

Metadata-Based Project Management System. A Case Study at M-Files Corporation. Iulia Adomnita

Metadata-Based Project Management System. A Case Study at M-Files Corporation. Iulia Adomnita Metadata-Based Project Management System. A Case Study at M-Files Corporation Iulia Adomnita University of Tampere School of Information Sciences Computer Science M.Sc. Thesis Supervisors: Timo Poranen,

More information

Schedule Assessment Guide. Best Practices for Project Schedules

Schedule Assessment Guide. Best Practices for Project Schedules Schedule Assessment Guide Best Practices for Project Schedules December 2015 PREFACE The U.S. Government Accountability Office is responsible for, among other things, assisting the Congress in its oversight

More information

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain * TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited

More information

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle. Planning and Managing Software Projects 2011-12 Class 10 Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

More information

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software

More information

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety

More information

Fixed Work Breakdown Structures in Microsoft Project A Case for a Custom Outline Code Field

Fixed Work Breakdown Structures in Microsoft Project A Case for a Custom Outline Code Field Fixed Work Breakdown Structures in Microsoft Project A Case for a Custom Outline Code Field Jim Aksel, PMP, PMI SP ProjectPMO jim@projectpmo.com (714) 312 3120 Microsoft Project contains Work Breakdown

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized

More information

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 Agenda Revision of 108.03 Schedule How CDOT Uses Construction Schedules Critical Path Method Scheduling Microsoft Project Overview 1 Revision

More information

The Plan s Journey From Scope to WBS to Schedule

The Plan s Journey From Scope to WBS to Schedule The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)

More information

MSP How to guide session 2 (Resources & Cost)

MSP How to guide session 2 (Resources & Cost) MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or

More information

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Unit 4: Time Management (PMBOK Guide, Chapter 6) (PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may

More information

Project 2010 Introduction

Project 2010 Introduction Microsoft Application Series Project 2010 Introduction Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery

More information

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities

More information

DYNAMIC PROJECT MANAGEMENT WITH COST AND SCHEDULE RISK

DYNAMIC PROJECT MANAGEMENT WITH COST AND SCHEDULE RISK DYNAMIC PROJECT MANAGEMENT WITH COST AND SCHEDULE RISK In the world of project management, there are essentially two major sources of risks: schedule risk and cost risk. In other words, will the project

More information

Monte Carlo analysis used for Contingency estimating.

Monte Carlo analysis used for Contingency estimating. Monte Carlo analysis used for Contingency estimating. Author s identification number: Date of authorship: July 24, 2007 Page: 1 of 15 TABLE OF CONTENTS: LIST OF TABLES:...3 LIST OF FIGURES:...3 ABSTRACT:...4

More information

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.

More information

Amajor benefit of Monte-Carlo schedule analysis is to

Amajor benefit of Monte-Carlo schedule analysis is to 2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to

More information

Basic CPM Calculations

Basic CPM Calculations Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.

More information

Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.

Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Critical Path Method Scheduling - Some Important Reservations The critical path method (CPM) of scheduling a project is a key tool for project

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

Chapter 4: Project Time Management

Chapter 4: Project Time Management Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT 1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT 11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and

More information

CRASHING-RISK-MODELING SOFTWARE (CRMS)

CRASHING-RISK-MODELING SOFTWARE (CRMS) International Journal of Science, Environment and Technology, Vol. 4, No 2, 2015, 501 508 ISSN 2278-3687 (O) 2277-663X (P) CRASHING-RISK-MODELING SOFTWARE (CRMS) Nabil Semaan 1, Najib Georges 2 and Joe

More information

Project Management by Using MS PROJECT 2013

Project Management by Using MS PROJECT 2013 Project Management by Using MS PROJECT 2013 Program is offered by: 3D Educators Trainers & Consultants Table of Contents Detail Inauguration Structure Topics & Time Allocation Other Learning Activities

More information

Risk Workshop Overview. MOX Safety Fuels the Future

Risk Workshop Overview. MOX Safety Fuels the Future Risk Workshop Overview RISK MANAGEMENT PROGRAM SUMMARY CONTENTS: Control Account Element Definition ESUA Form Basis of Estimate Uncertainty Calculation Management Reserve 1. Overview 2. ESUA Qualification

More information

An Oracle White Paper June 2009. Successfully Managing Contract Risk by Forming Win-Win Relationships

An Oracle White Paper June 2009. Successfully Managing Contract Risk by Forming Win-Win Relationships An Oracle White Paper June 2009 Successfully Managing Contract Risk by Forming Win-Win Relationships Executive Overview This white paper identifies some of the risks involved with contract project work

More information

2. Filling Data Gaps, Data validation & Descriptive Statistics

2. Filling Data Gaps, Data validation & Descriptive Statistics 2. Filling Data Gaps, Data validation & Descriptive Statistics Dr. Prasad Modak Background Data collected from field may suffer from these problems Data may contain gaps ( = no readings during this period)

More information

MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING

MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING MICROSOFT PROJECT SOFTWRE FOR THE PROJECT SCHEDULING ŠÁRK ČEMERKOVÁ Silesian University in Opava School of usiness dministration in Karviná Department of Mathematical Methods in Economics Czech Republic

More information

Introduction. http://www.alexsbrown.com/ Page 1

Introduction. http://www.alexsbrown.com/ Page 1 Modeling Tough Scheduling Problems with Project Management Software Alex S. Brown, PMP, Strategic Planning Manager, Mitsui Sumitomo Marine Management (U.S.A.), Inc. Introduction Despite year-over-year

More information

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start Project Management is the discipline of planning, organizing, and managing resources to complete a specific goal. Microsoft Project is software that helps you. Start your project Open Project 2010 and

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Activity Definition Input Work Breakdown Structure Scope Statement Historical Information

More information

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project

More information

Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP)

Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP) Earned Value Management System (EVMS) and Project Analysis Standard Operating Procedure (EPASOP) Issued by Office of Acquisition and Project Management MA-63 March 12, 2014 DEPARTMENT OF ENERGY Office

More information

Online Saturday & Sunday 4-Day Live PMP Training

Online Saturday & Sunday 4-Day Live PMP Training Online Saturday & Sunday 4-Day Live PMP Training Course Syllabus: DAY 1: Welcome a. Who is BOBCAT Academy? b. Introduce Yourself c. Follow Us Module 1: Course Introduction a. Course Dates b. Start/Stop

More information

Introduction to Project Management

Introduction to Project Management Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project

More information

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Precedence Diagram Method. CSTM 462 Planning & Scheduling Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.

More information

Agile and Earned Value. A white paper. October 2013. Author Stephen Jones, Sellafield Ltd

Agile and Earned Value. A white paper. October 2013. Author Stephen Jones, Sellafield Ltd Agile and Earned Value A white paper October 2013 Author Stephen Jones, Sellafield Ltd This document is a whitepaper produced by the APM Planning, Monitoring and Control SIG. It represents the thoughts

More information

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning

More information

OTC 12979. Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc.

OTC 12979. Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc. OTC 12979 Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc. Copyright 2001, Offshore Technology Conference This paper was prepared for

More information

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.

More information

PMI Lexicon of Project Management Terms

PMI Lexicon of Project Management Terms Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:

More information

Project Scheduling: PERT/CPM

Project Scheduling: PERT/CPM Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project

More information

Simulation and Lean Six Sigma

Simulation and Lean Six Sigma Hilary Emmett, 22 August 2007 Improve the quality of your critical business decisions Agenda Simulation and Lean Six Sigma What is Monte Carlo Simulation? Loan Process Example Inventory Optimization Example

More information

SPREADSHEET VALIDATION 101: CREATE AND VALIDATE FDA-COMPLIANT MS EXCEL SPREADSHEETS

SPREADSHEET VALIDATION 101: CREATE AND VALIDATE FDA-COMPLIANT MS EXCEL SPREADSHEETS SPREADSHEET VALIDATION 101: CREATE AND VALIDATE FDA-COMPLIANT MS EXCEL SPREADSHEETS 1 R A U L S O T O, M S C, C Q E I V T A P R I L 2 0 1 5 P H I L A D E L P H I A ABOUT THE AUTHOR 20+ years of experience

More information

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2010-11 Session 6 Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 These

More information

CHAPTER 1. Basic Concepts on Planning and Scheduling

CHAPTER 1. Basic Concepts on Planning and Scheduling CHAPTER 1 Basic Concepts on Planning and Scheduling Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the selection and ordering of activities as well as

More information

PMP Exam Preparation Answer Key

PMP Exam Preparation Answer Key Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.

More information

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose 1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing

More information

PMP -Project Management Professional Course Agenda

PMP -Project Management Professional Course Agenda PMP -Project Management Professional Course Agenda Module-1: Introduction to PMP PMP: Introduction Agenda for the Workshop Pre-requisites for PMP Exam About the PMP Exam and Format Complete overview PMP

More information

Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson

Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson Page 1 of 13 Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models Martin Hopkinson Abstract Monte Carlo schedule risk analysis has become a widely practiced

More information

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost

More information

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP SCHEDULING AND TIME MANAGEMENT Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS

More information

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Preliminary 1. You must have Microsoft Project 2003 or higher installed to complete these procedures. 2. If necessary,

More information

Schedule Risk Analysis Simulator using Beta Distribution

Schedule Risk Analysis Simulator using Beta Distribution Schedule Risk Analysis Simulator using Beta Distribution Isha Sharma Department of Computer Science and Applications, Kurukshetra University, Kurukshetra, Haryana (INDIA) ishasharma211@yahoo.com Dr. P.K.

More information

State-Based Probabilistic Scheduling Using STROBOSCOPE s CPM Add-On

State-Based Probabilistic Scheduling Using STROBOSCOPE s CPM Add-On Proceedings, Construction Congress V, ASCE Stuart D. Anderson,ed State-Based Probabilistic Scheduling Using STROBOSCOPE s CPM Add-On by Julio C. Martinez 1 and Photios G. Ioannou 2 Abstract Critical path

More information

Web Load Stress Testing

Web Load Stress Testing Web Load Stress Testing Overview A Web load stress test is a diagnostic tool that helps predict how a website will respond to various traffic levels. This test can answer critical questions such as: How

More information

Optimization: Continuous Portfolio Allocation

Optimization: Continuous Portfolio Allocation Optimization: Continuous Portfolio Allocation Short Examples Series using Risk Simulator For more information please visit: www.realoptionsvaluation.com or contact us at: admin@realoptionsvaluation.com

More information

Microfinance Credit Risk Dashboard User Guide

Microfinance Credit Risk Dashboard User Guide Microfinance Credit Risk Dashboard User Guide PlaNet Finance Microfinance Robustness Program Risk Management Public Tools Series Microfinance is at a new stage where risk management will be decisive for

More information

ORACLE S PRIMAVERA RISK ANALYSIS

ORACLE S PRIMAVERA RISK ANALYSIS ORACLE S PRIMAVERA RISK ANALYSIS KEY FEATURES Risk Analysis Guide Schedule Check Templated Quick Risk Risk Register Wizard Risk Register Risk Analysis Every project has risks. The organizations that succeed

More information

SOLUTION BRIEF: SLCM R12.7 PERFORMANCE TEST RESULTS JANUARY, 2012. Load Test Results for Submit and Approval Phases of Request Life Cycle

SOLUTION BRIEF: SLCM R12.7 PERFORMANCE TEST RESULTS JANUARY, 2012. Load Test Results for Submit and Approval Phases of Request Life Cycle SOLUTION BRIEF: SLCM R12.7 PERFORMANCE TEST RESULTS JANUARY, 2012 Load Test Results for Submit and Approval Phases of Request Life Cycle Table of Contents Executive Summary 3 Test Environment 4 Server

More information

Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule

Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule 1 (Image) 2 The process required to manage timely completion of the project. Project time management start with planning by the project management team (not shown as a discrete process). In small project,

More information

Tech-Clarity Insight: Integrating PLM and MES. Realizing the Digital Factory

Tech-Clarity Insight: Integrating PLM and MES. Realizing the Digital Factory Tech-Clarity Insight: Integrating PLM and MES Realizing the Digital Factory Tech-Clarity, Inc. 2011 Table of Contents Executive Overview... 3 Why Now?... 4 Product Innovation and Execution Roles... 5 Integrating

More information

Scheduling. Anne Banks Pidduck Adapted from John Musser

Scheduling. Anne Banks Pidduck Adapted from John Musser Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart

More information

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT PREPARED BY James E Aksel, PMP jim@projectpmo.com http://www.msprojectdblog.com http://www.projectpmo.com Page 1 of 19 Table

More information