1 A collection of Safran Project report samples for project professionals Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger

2 Contents Introduction... 2 About the Reports in This Document... 3 Executive reporting... 4 Portfolio Performance, Bubble Chart... 4 Portfolio Milestone Overview... 5 Portfolio Performance Trends... 5 Portfolio Performance History... 6 Portfolio Status Overview... 6 Portfolio Budget Overview... 7 Status reporting... 8 Status Barchart with frontline... 8 Status Histogram and S-curve... 9 Status Histogram and S-curves, by category Tabular Status Report Six Period Summary Bull s Eye Chart Progress Status Report Change Management Approved Changes Since Last Cutoff New Change Request Change Impact Schedule Change Impact Manhour distribution Total Change History Awareness Issues Manpower Peaks against availability, by resource category Manpower Peaks against availability, total Schedule Front Creep Schedule Risk Analysis Schedule Risk Analysis Gantt Chart Schedule Risk Analysis Probability Distribution Schedule Risk Analysis Tornado Chart Performance-based forecasting Productivity-Based Forecast in Gantt Chart Forecast values in S-curves and Histograms Burn Down S-curves and Histograms Alternative Estimate at Completion (EAC) Calculations Variance At Completion (VAC) Trend Analysis Earned Value Method reports Formats Special reports OMB 300 and NASA 533 M Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 1

3 Introduction Within this collection of Project Controls Report Samples, you ll find typical reports used to demonstrate the ongoing status of a large multiphase project. As a Project Controls professional, you may find that these reports help you to determine a desired state for your project reporting function. We encourage you to browse the following samples and consider how they might impact the ability to report on projects, or streamline your reporting process. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 2

4 About the Reports in This Document All reports included are configurations of standard templates included with Safran software, and are widely regarded among both clients and competitors as the most comprehensive and industry-focused reports available in the project management software market. Safran reporting is generally favored due to the availability as a standard product deliverable, the embedded flexibility, and powerful synthesis of multiple project management data sources and types. Further, Safran reports are accessible without expert training by any end-user with project management and PC literacy skills. With better accessibility to reporting data and the ability to produce reports in mere minutes, Safran empowers users with a vastly simplified reporting process that saves valuable project time, and produces reports more easily understood by the wider project team. Reports can now be a commodity instead of an obstacle. The data used to produce the sample reports found here report is fictional, but representative of a general rig design and construction job undergoing engineering, fabrication, assembly and testing, in addition to general management. The reports contained within this document show: Executive-level comparison of this project to other projects in a portfolio Current status of a project Budget change history and implications Identified awareness issues Schedule Risk analysis Forecast and look-ahead For each report type, it is possible to narrow the data selection by employing filters. Filters can be created ad hoc or saved by name and reused for the same report, other reports or in input screens. Reports can be grouped by common information attributes. Time scales and units can be adjusted, colors, fonts, legend information and many other settings can be changed to meet reporting needs. Each project organization can quickly build a tool set of fixed configurations for consistent reporting, along with other setups that are used for modelling and monitoring the project as it is planned and executed. All project participants have the ability to generate reports, offering necessary information control for each project team member, at any level of operation. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 3

5 Executive Reporting Executive reporting A Safran Project database can hold an unlimited number of projects, and each project can be part of an unlimited number of portfolios. Using Enterprise Codes that your project organization can establish according to the project execution model, all projects and portfolios can be arranged in a structure that is easy to navigate, view in detail or at a summarized level, and all are specific to the way your organization runs projects. Key performance figures can be calculated and compared across otherwise independent projects, both with respect to the current situation and for historical values leading up to where the portfolios stand today. Any single projects or project organization areas that stand out from the expected development are thereby easily identified at an early stage, and can be made subject to further evaluations and modelled for corrective actions. Portfolio Performance, Bubble Chart Bubble charts are used in portfolio reporting to identify and compare the performance of a selection of projects each identified by a given color. The axis values show performance against budget and schedule execution. The size of each project mark is relative to the budgets within the selection. This plot illustrates the immediate condition of the portfolio, and demonstrate if any projects are falling out of the anticipated progress development. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 4

6 Executive Reporting Portfolio Milestone Overview Using this report, key decision points can be rolled up and presented across the portfolio, given a minimum standardization of the project structure. This information can be very helpful to keep control of timing for critical decisions when assessing which projects should take priority, or be executed all. Portfolio Performance Trends Historical performance trends within the portfolio can be also be monitored using Safran standard reports. These give early warnings if any project is moving away from the normal range of performance values, and should be subject to more detailed follow-up procedures. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 5

7 Executive Reporting Portfolio Performance History Yet another way to view performance trends within the portfolio is by using a histogram and a trend line. Safran Project has a special report for this which also can be used at portfolio level. This gives an instant status of today s total performance and the history behind it. Portfolio Status Overview In this report, a portfolio of projects can be presented in comprehensive Gantt charts, grouped by higher level Enterprise Codes and exposed down to the desired detail level. Table columns and graphical elements can be designed to provide key information about critical control parameters throughout the portfolio. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 6

8 Executive Reporting Portfolio Budget Overview Budget Overview reports provide a view of portfolio project budgets presented in S-curves and histograms. As shown below, the information can be split across the contributing parts, making it easy to identify any total peak values and to understand where the contributing values originate. This report is updated in real time if a project schedule is altered, making it an interactive modelling tool for optimized resource leveling. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 7

9 Status Reporting Status reporting Project status reports are fundamental to Safran Project s standard reports. At all times, the present condition of the project or parts of it can be viewed in a number of different report views available in the core application. Possible control parameters include manhour and cost expenditure, manpower usage, physical and time progress, earned value method calculations, estimate to-complete figures, frontlines and more. Using free fields and user-defined formulas, a wide range of customized key performance indicators can be set up to fully deliver the monitoring tools the project and its stakeholders require. Present values can be compared with corresponding calculations for previous project periods, thus quickly displaying any positive or negative trends that should be consciously addressed in a timely manner before schedules and budgets are affected. Status Barchart with frontline All schedule barcharts can be configured freely with given columns, bars, summary levels, colors, filter and many other items to identify durations and progress. Using progress bars or a frontline, it is easy to compare the current results to the originally planned values. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 8

10 Status Reporting Status Histogram and S-curve Histograms and S-curves can be configured freely with given columns, lines, table entries, colors, filter and many other items. A Status histogram and S-curve quickly demonstrates the current state of the project, and trends over time are perceived at a glance. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 9

11 Status Reporting Status Histogram and S-curves, filtered and broken down by category Histograms and S-curves can also be filtered to contain only the relevant selection of activities that the user wants to study. A report can be broken down in groups, automatically broken into single pages by common activity attributes values. Reports like this quickly enable all parties to monitor and control sub-categories of activities that otherwise hide insight into crucial trends during execution of the project. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 10

12 Status Reporting Tabular Status Report In a Tabular Status Report, key figures for the whole project can be presented in a comprehensive tabular format that compares budgets to periodic and to-date achievements. Breakdown level, sections, columns and colors can be selected, and groups of activities can be selected or omitted as relevant. If a higher-level group item should stand out, further reports can be created within this group at a more detailed level to investigate the final source behind the overall figures. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 11

13 Status Reporting Six Period Summary Six Weeks Summary Reports give trend information across a multitude of commonly-accepted Earned Value Method parameters, as defined by the Project Management Institute (PMI) and other industry associations and professional bodies. Numbers are given both as quantities and cost values. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 12

14 Status Reporting Bull s Eye Chart The Bull s Eye Chart is another representation of performance for the whole project or a selected part of it. It effectively plots budget performance and schedule progress performance over time, showing whether there is a trend that moves away from an acceptable range of coordinates. Progress Status Report The Hanging Gardens Progress Status report is a simple, but effective count of activities that are planned to be executed at the given report periods. The color codes indicate whether the activities are already complete, are in progress or have not started yet. This report is used at operational level to understand if project activities are started on time, and to follow up any areas that could be lagging. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 13

15 Change Management Change Management Safran Project has an embedded Change Management module that allows teams to not only keep a register of all identified suggestions for scope changes, but also to track the status and history of each item. Since the Change Management model is a part of the core scheduling system, it is possible to illustrate and analyze the effect that one or more Change Order has on the total plan. The immediate addition or subtraction of budget can be viewed, and the resulting impact that the Change Order has on neighboring parts of the project can be modelled and evaluated prior to reviewing and approving changes. Approved Changes Since Last Cutoff As part of the Change Management functionality, it is possible to print overviews of entered Change Orders in their different stages. This can be structured and filtered in several ways. One typical use is to list all newly identified or altered Change Orders since the previous report cycle. Management can then evaluate each item and be made aware of all modifications that are presented to the project budget. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 14

16 Change Management New Change Request Any Change Order can be listed in full detail with all contributing budget items and the overall descriptions and status values. This report can be used for communicating with the budget owner or any other relevant project sponsor. Change Impact Schedule By using the formatting and symbol properties of Safran reports, along with alternative schedule calculations, the immediate and derived effect of a Change Order can be easily visualized. Change Orders become more than just budget figures. The impact of the already-established plan can be assessed in a meaningful way, funding valid go/no-go decisions. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 15

17 Change Management Change Impact Manhour distribution Correspondingly, the manhour, manpower and cost load redistributions of a Change Order can be pictured in a Manhour Distribution Report. Again, this helps management understand the full impact of altered scope and how it also affects work that already is incorporated in the plan. Total Change History As the project progresses and more Change Orders are produced, the full overview of the current status can be listed. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 16

18 Awareness issues Awareness Issues Safran Project is an ideal tool for quickly bringing out unwanted conditions that should trigger corrective actions. This is done in real time as the project is updated with new information from the various participants. Single input values that can appear harmless in a limited context can yield severe conflicts when later enrolled into bigger pictures. Using predefined or ad-hoc techniques, any such effects can be caught and contained before they come anywhere near real life implementation. Manpower Peaks against availability, by resource category Safran Project can hold availability limits that can be used to controlthe plans for a group of activities that don t exceed a capability limit. Even if each group has different constraints, this can be modelled and presented correctly in a single, multipage report like those shown below. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 17

19 Awareness issues Manpower Peaks against availability, total The same values as shown above can also be summarized into one general view for the total project, to further analyze any troublesome peak values or periods where the resource pool still has capacity to offer. Schedule Front Creep More experienced Critical Path Method analysts might want to study the development of float values in the course of the project. Typically, available schedule float in any project will tend to be reduced as the project progresses. The Schedule Front Creep Report monitors this evolution and can identify areas that increasingly become critical for obtaining important project milestones. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 18

20 Schedule risk analysis Schedule Risk Analysis Safran Project is the only project management system today that offers full Monte Carlo based simulation of the project duration directly in the scheduling tool. As the calculations takes place in the memory of the software host, it is incredibly fast also for huge collections of data. The project team can identify conditions in the project that are notoriously included in critical paths and has time to test alternative execution models and decide the method that has the least risk of time and budget overruns. Schedule Risk Analysis Gantt Chart As direct output from the Monte Carlo based schedule risk analysis, calculated risk based minimum, maximum and P-dates can be brought up as table entries and graphical symbols in this Schedule Risk Analysis Gantt Chart. This helps the scheduler understand which activities are essential risk drivers and where mitigating actions will have most effect. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 19

21 Schedule risk analysis Schedule Risk Analysis Probability Distribution The risk model constantly produces distribution profiles and cumulated values of probabilities of completing the project or parts of it on time. This is both a reporting and a modelling tool, as the Schedule Risk Analysis is so quick to run that alternative models can be tested in real time. Again, the scheduler gets immediate feedback about where to accelerate project execution and rather take a short time cost for ensuring an optimized total profit. Schedule Risk Analysis Tornado Chart Another way to identify universally critical activities is to produce a Tornado Chart. This enlists activities that always or often appear on the critical path, independent of the many alternative durations that each activity is given during simulation. Activities that appear higher up on this list should always be scrutinized closely during execution. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 20

22 Performance-based testing Performance-based forecasting As project execution gets underway and harvesting relevant status values is possible, these figures can be used as input to forecasting analysis models that give well-funded projections of how the remaining part of the project will evolve, given the resource and time performance experienced to date. This helps project management understand whether the original budget estimates and time durations are trustworthy or if there is a need for adjusting the targets to more realistic levels. Productivity-Based Forecast in Gantt Chart Safran Project can take incurred productivity figures into account and calculate forecasts of remaining durations and estimates to complete. These figures can be used in Gantt charts and other reports as scientific predictions of how the project will be completed. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 21

23 Performance-based testing Forecast values in S-curves and Histograms Productivity-based forecast calculations are just as interesting when showing the likely future of the resource and cost expenditure. This can be combined with predictions of how the remaining budget values will be earned, so management can evaluate if the productivity experienced to date is likely to continue. Burn Down S-curves and Histograms Some project managers like to see the outstanding work as Burn Down charts, with counts of remaining units to complete cumulatively or per period. This is really just the planned values turned upside down, but can be useful for focusing on the upcoming activities and when they need to be completed. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 22

24 Performance-based testing Alternative Estimate at Completion (EAC) Calculations Safran Project supports 9 different methods for forecasting the final sum of expenditures at the end of the project. Experienced project controllers can select the options that best suit the forecasting methodology used in their organization. This will yield trends of how the selected model develops over time. Below is a sample comprehensive graph with all options overlaid. All methods can be combined with any other historic planned, actual and earned values. Variance At Completion (VAC) Trend Analysis Another Earned Value Management (EVM) metric is Variance at Completion (VAC), calculated as the difference between Budget at Completion (BAC) and Estimate at Completion (EAC). Safran can present this figure by period, thus showing trends in this material for the project as a whole or for some group of activities, with automatic page breaks as requested. Below is a sample where the VAC value is overlaid on a horizontal scale of target areas, with supportive base figures in the table. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 23

25 Earned value method reports Earned Value Method reports US government agencies have specified a set of common reports that all of their contractors must adhere to for reporting purposes. This is to ensure that they follow sound EVM principles and practices and can demonstrate any deviations from agreed budgets at an early time. The report formats are extensive and can require a high level of effort if they are to be manually reproduced for every reporting period. Safran Project has all of the required reports readily available as a part of the core solution. Background data that are not a part of the normal Safran Project information structure can be recorded in special screens and kept for use by all reporting periods. Government EVM reports can thus be produced in a quick and organized manner, saving valuable time for hands-on project control work. Formats 1-5 The standard formats 1 5 calculate budget, earned and actual values by WBS, OBS or any other hierarchical structure defined in the project. Each format has a number of options that can be employed depending on the needs in the specific project. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 24

26 Earned value method reports Special reports OMB 300 and NASA 533 M Safran Project also supports the special forms OMB 300 for IT projects and NASA s 533M format. As for the Format 1 5 reports, the contents of which are built by static information that is kept in the database and live plan and status information directly from the project. Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger 25

Safran Project Program and Portfolio Management Planning Done Your Way

Safran Project Program and Portfolio Management Planning Done Your Way Safran Project The only enterprise project management solution exclusively focused on solutions for asset intensive industries. Safran products are used to manage and control some of the worlds most complex

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information

Project Management Institute. Practice Standard for EARNED VALUE MANAGEMENT. Global

Project Management Institute. Practice Standard for EARNED VALUE MANAGEMENT. Global Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management

More information

ARTEMIS VIEWS ADVANCED PLANNING. With ProjectView

ARTEMIS VIEWS ADVANCED PLANNING. With ProjectView ARTEMIS VIEWS ADVANCED PLANNING With ProjectView ADVANCED PLANNING Advanced Planning is a powerful role-based project and resource management application. Designed for project managers, project planners

More information

PROJECT TRACKING and CONTROL

PROJECT TRACKING and CONTROL PROJECT TRACKING and CONTROL 1 Outline of Project Tracking & Control 2 Project Planning & Control Context 3 Realistic and Measurable Plans Create Measurable Plans! 4 Data Sources for Project Tracking 5

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

P6 Analytics Reference Manual

P6 Analytics Reference Manual P6 Analytics Reference Manual Release 3.2 October 2013 Contents Getting Started... 7 About P6 Analytics... 7 Prerequisites to Use Analytics... 8 About Analyses... 9 About... 9 About Dashboards... 10 Logging

More information

PMP Exam Preparation Answer Key

PMP Exam Preparation Answer Key Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.

More information

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft

More information

PeopleSoft Program Management

PeopleSoft Program Management PeopleSoft Program Management Large enterprises and project-based organizations have long recognized the value of leveraging project knowledge across multiple projects. Yet today, 50 percent of IT projects

More information

Accounting System. Page 1 of 9

Accounting System. Page 1 of 9 Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010)

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010) Software Development & Education Center Microsoft Office 2010 (Microsoft Project 2010) Mastering Microsoft Project 2010 About This Course This three-day instructor-led course provides students with the

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days 3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: rwhitney@discoveritt.com Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:

More information

What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate

What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate The outcome of any venture is most often affected by the ready availability of useful information on which timely decisions can be taken. For project success, the need is therefore to know where you re

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

MSP How to guide session 2 (Resources & Cost)

MSP How to guide session 2 (Resources & Cost) MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or

More information

See What's Coming in Oracle Project Portfolio Management Cloud

See What's Coming in Oracle Project Portfolio Management Cloud See What's Coming in Oracle Project Portfolio Management Cloud Release 9 Release Content Document Table of Contents GRANTS MANAGEMENT... 4 Collaborate Socially on Awards Using Oracle Social Network...

More information

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing

More information

Earned Value and Agile Reporting

Earned Value and Agile Reporting Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,

More information

Amajor benefit of Monte-Carlo schedule analysis is to

Amajor benefit of Monte-Carlo schedule analysis is to 2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to

More information

White paper. Innate Resource Management Software. Introduction to Reports

White paper. Innate Resource Management Software. Introduction to Reports White paper Innate Resource Management Software Introduction to Reports Presenting project, cost, time and resource information, across the organization Innate reports can significantly improve the visibility

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Programme Description: Dedicated one full day training module in a structured and professional manner to

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu

More information

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 Duration: 03 days INTRODUCTION This course provides hands-on training for Primavera s web-based solution. Participants will create a project, add activities

More information

Cost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP

Cost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP Cost & Schedule Risk Assessment Using @Risk 6.0 Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP 24 October 2012 What If? In Business and in Life: We always made the best possible decisions, and Implemented

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

PROJECT AUDIT METHODOLOGY

PROJECT AUDIT METHODOLOGY PROJECT AUDIT METHODOLOGY 1 "Your career as a project manager begins here!" Content Introduction... 3 1. Definition of the project audit... 3 2. Objectives of the project audit... 3 3. Benefit of the audit

More information

INTEGRATED COST AND SCHEDULE CONTROL IN PROJECT MANAGEMENT

INTEGRATED COST AND SCHEDULE CONTROL IN PROJECT MANAGEMENT INTEGRATED COST AND SCHEDULE CONTROL IN PROJECT MANAGEMENT SECOND EDITION Ursula Kuehn, PMI> EVP m MANAGEMENTCONCEPTS CONTENTS Preface Acknowledgments xxi xxix Part 1 Project Management and the Integrated

More information

CA PA for CA Clarity PPM 14.2: Project and Investment Management 200

CA PA for CA Clarity PPM 14.2: Project and Investment Management 200 CA PRODUCTIVITY ACCELERATOR CONTENT DESCRIPTION CA PA for CA Clarity PPM 14.2: Project and Investment Management Content Overview PRODUCT RELEASE CA Clarity PPM 14.2 DURATION & COURSE CODE Three (3) Hours

More information

OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)

OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.

More information

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10. PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition

More information

Project Management Courses

Project Management Courses A well planned project will give results exactly as planned. Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the delivery

More information

ORACLE PROJECT MANAGEMENT

ORACLE PROJECT MANAGEMENT ORACLE PROJECT MANAGEMENT KEY FEATURES Oracle Project Management provides project managers the WORK MANAGEMENT Define the workplan and associated resources; publish and maintain versions View your schedule,

More information

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

THE PROJECT MANAGEMENT KNOWLEDGE AREAS THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

PLANNING AND MONITORING PROJECTS WITH MICROSOFT OFFICE PROJECT 2013 TRAINING

PLANNING AND MONITORING PROJECTS WITH MICROSOFT OFFICE PROJECT 2013 TRAINING PLANNING AND MONITORING PROJECTS WITH MICROSOFT OFFICE PROJECT 2013 TRAINING OBJECTIVE The purpose of this training is to qualify students to use the Microsoft Project 2013. The course presents the subject

More information

MICROSOFT OFFICE PROJECT - SYLLABUS

MICROSOFT OFFICE PROJECT - SYLLABUS MICROSOFT OFFICE PROJECT - SYLLABUS Sessions Session 1 Description 1. INTRODUCTION a. Introduction to CADFORUM and PPM b. Project c. Examples of project d. Project Triangle e. Project Management f. Life

More information

Project Management Courses

Project Management Courses "A well planned project will give results exactly as planned." Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the

More information

Breaking Down the Work

Breaking Down the Work 021A Linden JUL 03 ONLINE Monitoring Progress in Software Development Joop van der Linden The Haagse Hogeschool To manage software development projects, a suitable model of the specific type of project

More information

Project Time Management an essential element to project success

Project Time Management an essential element to project success Project Time Management an essential element to project success Abstract This paper discusses the reasons behind the necessity to apply sound Project Time Management principles and processes to projects

More information

Involve-Project Manager

Involve-Project Manager Involve-Project Manager This article will describe: What is Project Management Why is Project Management so important to community and voluntary organisations The Key Phases of Project Management: o Initiation

More information

Deltek Maconomy Project Management

Deltek Maconomy Project Management Deltek Maconomy Project Management Managing the full project workflow To improve project profitability your ERP solution should support all stages of the project life cycle; from presales over project

More information

VIII. Project Management Glossary

VIII. Project Management Glossary https://www.wrike.com/project-management-guide/glossary/ VIII. Project Management Glossary Project management, like any other industry, has its share of unique terms. Don t be overwhelmed. Here is our

More information

5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter

5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter Develop Project Charter Develop Preliminary Project Scope Statement Develop Project Management Plan Scope Planning PROCESS GROUP: INITIATION 4.1 The project charter serves as the input document for the

More information

Glossary. Release 13.3.00

Glossary. Release 13.3.00 Glossary Release 13.3.00 This Documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation ) is for your informational purposes

More information

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

CA Clarity PPM. Glossary. Release 13.1.00

CA Clarity PPM. Glossary. Release 13.1.00 CA Clarity PPM Glossary Release 13.1.00 This Documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation ) is for your informational

More information

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

Project Management Tools

Project Management Tools Project Management Tools 1 Name: Subject: Professor: Date: Project Management Tools Project Management Tools 2 1. Introduction Project Management is a method of organizing and managing resources in strategic

More information

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2

More information

Microsoft Project Professional

Microsoft Project Professional Microsoft Project Professional A 100% practical workshop to master Microsoft Project, training the main features of the application for project management. Objective Insight into the functions required

More information

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management

More information

Project Management. In this Guide

Project Management. In this Guide A GUIDE TO MINDMANAGER Project Management Project success depends on both the effective management of information and the efficient coordination of resources and schedules. MindManager can help. In this

More information

A Framework for Project Metrics

A Framework for Project Metrics A Framework for Project Metrics Deciding what to measure and how to measure it August 13, 2007 Dr. Gary J. Evans, PMP CVR/IT Consulting LLC www.cvr-it.com Welcome! Focus of this workshop: Project Metrics

More information

SEVEN WAYS THAT BUSINESS PROCESS MANAGEMENT CAN IMPROVE YOUR ERP IMPLEMENTATION SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND

SEVEN WAYS THAT BUSINESS PROCESS MANAGEMENT CAN IMPROVE YOUR ERP IMPLEMENTATION SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND SEVEN WAYS THAT BUSINESS PROCESS MANAGEMENT CAN IMPROVE YOUR ERP IMPLEMENTATION SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND CONTENTS INTRODUCTION 3 EFFECTIVELY MANAGE THE SCOPE OF YOUR IMPLEMENTATION

More information

PMI Lexicon of Project Management Terms

PMI Lexicon of Project Management Terms Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:

More information

Project Execution - PM Elements

Project Execution - PM Elements Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead

More information

Welcome to the Data Analytic Toolkit PowerPoint presentation an introduction to project management. In this presentation, we will take a brief look

Welcome to the Data Analytic Toolkit PowerPoint presentation an introduction to project management. In this presentation, we will take a brief look Welcome to the Data Analytic Toolkit PowerPoint presentation an introduction to project management. In this presentation, we will take a brief look at project management to understand the process and some

More information

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by: Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you

More information

1 Start a new project

1 Start a new project Project Management Quick Reference Guide for Microsoft Project 2010 Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify

More information

How to successfully manage your mega-project

How to successfully manage your mega-project BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How

More information

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Project Management Fundamentals with Microsoft Project

Project Management Fundamentals with Microsoft Project Project Management Fundamentals with Microsoft Project Duration: 4 Days PDU Credits: 28 (Category A) This 4-day course is designed to provide practical, hands-on experience in the planning, development,

More information

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

PROJECTS. onepoint PROJECTS 13. Group Server and. Enterprise Cloud/Server. Tutorial

PROJECTS. onepoint PROJECTS 13. Group Server and. Enterprise Cloud/Server. Tutorial onepoint PROJECTS 13 Group Server and Enterprise Cloud/Server Tutorial 1 1 Introduction onepoint PROJECTS is the first open source project leadership software integrating project planning, controlling,

More information

ICT Project Management

ICT Project Management THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE PUBLIC SERVICE MANAGEMENT ICT Project Management A Step-by-step Guidebook for Managing ICT Projects and Risks Version 1.0 Date Release 04 Jan 2010 Contact

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 This three-day, instructor-led course is intended for individuals who are interested in expanding their knowledge base and technical skills about Microsoft Project. The course begins with the basic concepts

More information

The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman)

The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman) The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman) 11/17/07 Introduction Editor's Note: We liked so much of this book that we asked for the author's permission to quote

More information

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for

More information

DYNAMIC PROJECT MANAGEMENT WITH COST AND SCHEDULE RISK

DYNAMIC PROJECT MANAGEMENT WITH COST AND SCHEDULE RISK DYNAMIC PROJECT MANAGEMENT WITH COST AND SCHEDULE RISK In the world of project management, there are essentially two major sources of risks: schedule risk and cost risk. In other words, will the project

More information

WebSphere Business Monitor

WebSphere Business Monitor WebSphere Business Monitor Dashboards 2010 IBM Corporation This presentation should provide an overview of the dashboard widgets for use with WebSphere Business Monitor. WBPM_Monitor_Dashboards.ppt Page

More information

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing

More information

siemens.com/mobility Traffic data analysis in Sitraffic Scala/Concert The expert system for visualization, quality management and statistics

siemens.com/mobility Traffic data analysis in Sitraffic Scala/Concert The expert system for visualization, quality management and statistics siemens.com/mobility Traffic data analysis in Sitraffic Scala/Concert The expert system for visualization, quality management and statistics 2 Traffic data analysis produces transparent intersections The

More information

Collaborative Scheduling using the CPM Method

Collaborative Scheduling using the CPM Method MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines

More information

SOFTWARE PROJECT MANAGEMENT

SOFTWARE PROJECT MANAGEMENT SOFTWARE PROJECT MANAGEMENT http://www.tutorialspoint.com/software_engineering/software_project_management.htm Copyright tutorialspoint.com The job pattern of an IT company engaged in software development

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT 11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and

More information

Introduction to Project Management

Introduction to Project Management Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project

More information

Certification Preparation Course LATVIKON (R.E.P.)Centre

Certification Preparation Course LATVIKON (R.E.P.)Centre PMP Certification Preparation Course LATVIKON (R.E.P.)Centre ABOUT THIS COURSE Your ability as a project manager to demonstrate best practices in Project Management both on the job and through professional

More information

Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2

Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 P.G. Student, Department of Civil & Environmental Engineering, NITTTR, Bhopal,

More information

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3 /01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) GOAL In this lecture, we ll learn: Background of Primavera Project Planner (P6) Getting Started P6 Interface Basic Navigation and Operation Setting

More information

Making Every Project Business a Best-Run Business

Making Every Project Business a Best-Run Business SAP Functions in Detail SAP Business Suite SAP Commercial Project Management Making Every Project Business a Best-Run Business Table of Contents 3 Quick Facts 4 Facilitating Optimal Project Delivery for

More information

Core Scheduling Papers: #6 Schedule Levels Major Projects

Core Scheduling Papers: #6 Schedule Levels Major Projects Schedule Levels Major Projects Level 1 Schedule Executive Summary, also called a Project Master Schedule (PMS). This is a major milestone type of schedule; usually only one page, it highlights major project

More information

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4 MACIASZEK, L.A. and LIONG, B.L. (2005): Practical Software Engineering. A Case Study Approach Addison Wesley, Harlow England, 864p. ISBN: 0 321 20465 4 Chapter 4 Software Project Planning and Tracking

More information

Acompany that consistently selects the right projects and

Acompany that consistently selects the right projects and PM.01 How to Create a World Class Project Management Organization Dr. Nick J. Lavingia, PE Acompany that consistently selects the right projects and executes them with excellence can improve return on

More information

PMO Metrics Recommendations

PMO Metrics Recommendations Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project

More information