IN-SITU U-VALUE MEASUREMENTS AND THERMOGRAPHIC SURVEY: SPACE COMMUNITY CENTRE EDINBURGH CRAIGMILLAR

Size: px
Start display at page:

Download "IN-SITU U-VALUE MEASUREMENTS AND THERMOGRAPHIC SURVEY: SPACE COMMUNITY CENTRE EDINBURGH CRAIGMILLAR"

Transcription

1 IN-SITU U-VALUE MEASUREMENTS AND THERMOGRAPHIC SURVEY: SPACE COMMUNITY CENTRE EDINBURGH CRAIGMILLAR Technical Report No. E4632_JS_ October Prepared for: CastleRock Edinvar Housing Association Edinburgh 1 Hay Avenue Edinburgh, EH16 4RW For the attention of: Chris Thompson Prepared by: Jon Stinson. Brief: To conduct side-by-side comparative study. Using in-situ U-value measurements and IR images to compare a thermal enhanced office space with a similar office with no thermal enhancement. [Forming part of a Technology Strategy Board funded project] Revised by: Julio Bors Williamson, SEC Consultant 42 Colinton Road, Edinburgh, EH10 5BT T: (0131) F: (0131) e: j.broswilliamson@napier.ac.uk

2 Contents Acknowledgement Introduction Methodology Results Review of results Conclusion U-value and IR thermography report 1

3 Acknowledgement The author would like to thank the funding body; Technology Strategy Board (TSB); the staff at SPACE community centre; and the staff within the two offices for facilitating this work. U-value and IR thermography report 2

4 1 Introduction This report forms part of the Technology Strategy Board (TSB) funded Invest in Innovative Refurbishment project awarded to Castlerock Edinvar Housing Association (CREHA). The (SEC) carried out a series of building performance tests upon the community centre called SPACE, an early 20 th century school converted into rentable offices, arts and community spaces. The work undertaken forms part of a wider report and submission to TSB for further funding to proceed with phase 2 of the innovative refurbishment plan. Work by the SEC was done to inform CREHA and the design teams appointed to instruct and project manage the fabric refurbishment work. In-situ U-value measurements were carried out on the building fabric. Equipment to measure thermal transmittance was installed within two rooms of the SPACE building One room to represented the existing fabric a second room underwent thermal upgrading. Infrared thermography survey was conducted localised to the same locations as the U-value probes. The monitoring and fabric evaluation study focused on four areas within each room: Window South wall - area below window South wall - top of wall North wall - top of wall U-value measurement equipment was installed in eight locations across two rooms on 24 th September Loggers were retrieved prematurely 2 weeks later in line with phase 1 TSB funding schedule, also to allow the results to populate the dynamic computer modeling and simulation scenarios undertaken by Green Energy Partners (GEP). The orientation and forecasted boundary temperature differential for September would result in an appropriate period of monitoring for this project to be 6 weeks. After the interim logger download to inform this report the data loggers have been redeployed into the building to allow for further measurements. The aim of the thermographic survey is to visually display areas of heat loss through the building fabric. Thermograms of the control room established a baseline representing the construction of the rest of the external envelope. Comparative thermograms of the refurbished room will assist in identifying areas where the thermal upgrading may require improvements and learn from areas that haven t been insulated properly or where thermal bridging may be occurring. U-value and IR thermography report 3

5 The following objectives have been identified; Establish thermal transmittance value (U-value) for existing and refurbished fabric elements Assess the continuity of insulation across the building facades Identify, where possible, air leakage paths resulting in excessive heat loss. The infrared survey was undertaken on the 2nd of October 2012, between 00:00 hrs 02:00 hrs, by Jon Stinson. 1.1 Survey description To take infrared images of the building, certain environmental conditions have to be met. To create a sufficient temperature gradient across the building structure, the survey is conducted in low ambient temperatures at night, and the building heating system is left on for a 24 hour period prior to the survey to maximise the temperature differential between internal and external environment. The survey is conducted with a minimum temperature internal to external temperature difference of 10 o C. This also ensures that the camera is detecting heat from within the building, and not latent heating remaining within the building structure from the day-time/solar gains. 1.2 Environmental conditions The environmental conditions were recorded before and after the survey. The measurement location of these parameters was selected to be representative of the mean. At the start of the survey, the internal temperature of the control room was 20.3 C. The refurbished room experienced an internal temperature of 22.9 C. External temperature of 3.3 C and a wind speed of between 1.3 m/s -1. At the end of the survey, the conditions had remained relatively stable, with an internal temperature similar to the above and an external temperature of 3.1 C and a wind speed of between 1.2 m/s -1. This provided a mean internal to external temperature differential of approximately 18.4 C. The survey was conducted in low wind conditions, which is within the permitted range which provides a more equal pressure and temperature differences over the facades of the building, increasing the comparability of images. The sky conditions were approximately 10% overcast throughout the survey. All building surfaces were dry and remained so for the duration of the survey. The relatively uniform night sky presented good survey conditions. U-value and IR thermography report 4

6 1.3 Building description The building originally constructed in 1930 s for use as a local primary school. The building underwent a change of use from a primary school to a mixed use office and community centre, during this time some refurbishment work was undertaken in early 2000 s with the addition of internal wall insulation at various point across the front facade. The exact make-up of the existing building elements is not known, architect assumptions have been used and comments have been made based on drawings used in this report. The report will focus upon two rooms, hereby referred to as a control room and a test room. Both rooms occupy the same general location within the building, frontal orientation and room dimensions, at time of this report both room were being occupied by the same tenant. The rooms are located beside one another on the first floor, East wing and facing approximately South-West. Each room measures 7.9m by 6.2m with one main entrance and four 1.2m by 1.9m timber sash and case windows. The test room is occupied by 10 workstations accommodating office staff for the average 35hr working week. The control room was occupied less often and used primarily for staff meetings and training space. To compensate for the difference in occupancy the control room was artificially heat to a similar level as that experienced during in the test room. Temperature loggers were deployed in both rooms to validate the heat profile in the rooms. For the purpose of this report the control room is representative for the construction type and elemental build-up for the rest of the existing structure. The test room has undergone thermal upgrading to select portions of 2 walls and each of the four windows. Detailed breakdown of existing and additional material is explained in Section 3. 2 Methodology The testing methodology for calculating the in situ U-value measurements was undertaken in the wellestablished format described in Baker (2008, 2011), Rye (2011) and Currie (2012). The U-value of a building element or component is defined in BS EN ISO 7345:1996 as the heat flow rate in the steady state divided by the area and the temperature difference between the surroundings on each side of a system. (BSI, 1996, p.5) U-value and IR thermography report 5

7 2.1 In-situ U-values The in-situ U-value measurements were taken with a Hukseflux HFP01 thermopile-based heat flux transducers (Figure 1) of 80 mm diameter and 5 mm thickness. These were attached to each building element being tested throughout the initial period of monitoring (for 2 weeks duration). The elemental U-values were determined by recording the heat flow through the element together with internal surface and external air or surface temperature. This was done by logging differential voltage from the heat flux transducers and temperature from calibrated K-type thermocouples (Figure 2). Grant Squirrel data loggers with 24bit A/D conversion resolution (Figure 3) were used to log data from the heat flux transducers and the thermocouples. Where required, Tinytag temperature and relative humidity loggers (Figure 3) were used for locations where cabling could not be run back to the main data logger. Figure 1 : Heat flux transducer (heat flow mat) mounted to wall face Figure 2: K-type thermocouple mounted to face of heat flux transducer Figure 3 : Grant Squirrel data logger to log data from heat flux transducers and thermocouples Figure 4: Stand-alone Tinytag View2 data logger measuring air temperature and relative humidity U-value and IR thermography report 6

8 Error analysis of in-situ measured U-values The certainty of the measured in-situ U-values are influenced by sensor related errors. The sensitivity of the senor or probe will impact on each recorded value during the period of monitoring. Calculating the uncertainty related to temperature probes and HFM allows for an error range to be found which provides a ± value indicating the level of uncertainty derived from the individual temperature and heat flux measurements. An error analysis for the results from each case study has been calculated by using the established error analysis methodology (Baker 2011). The results are presented as part of the analysis of U-value results chapter Thermography Infrared thermography was used to locate areas of significant temperature differences and inhomogeneous construction elements. The IR camera also assisted with ensuring that the sensors were not placed on cold bridges, by identifying the placement of metal studs which assisted with the optimal placement of the heat flow mat. Table 1 provides equipment and calibration details for those items of equipment used during the survey. Table 1: Equipment and calibration information Equipment Serial No. Date of calibration expiration Calibration certification no. FLIR thermal imaging camera B335 with 320 x 240 pixel resolution and 25 o lens /03/12 n/a Anemo Rotating Cup Anemometer N/A N/A Testo 110 Thermometer with Probe /805 11/03/12 UK04606 U-value and IR thermography report 7

9 3 Results 3.1 Window The windows in the South facing facade tested in the study are single glazed timber sash and case window (Figure 5) these are representative of all the windows along the listed front facade. During the refurbishment the windows in the test room were thermal enhanced with the installation of toughened low-e double secondary glazing unit in an openable upvc frame with trickle vent added to the four windows. The secondary glazing unit called Thermal Shield developed by Adam Dudley Architects of Edinburgh, is installed internally with approx. 100mm gap between glazing units and the existing window. Additionally a novel radiant heat barrier window blind installed between glazing units (Figure 6). Figure 5:Internal view of window in control room, with HFM attached Figure 6: Internal view of window in test room, Thermal Shield secondary glazing installed and opened on vertical hinge Interim results from the U-value in-situ measurements have shown that the addition of Thermal Shield secondary glazing system improved the U-value of the glazing from 5.2 to 0.6 W/m²K results in Table 1. U-value of 5.2 W/m²K is typical for single glazing, whilst the measured U-value of 0.6 W/m²K is typical for the secondary glazing system that has been previously measured in past SEC historic building refurbishment performance evaluation projects. Therefore, the 2 week interim results would suggest that the addition of the radiant heat barrier blind has not influenced the U-value. However, four U-value and IR thermography report 8

10 temperature probes embedded either side of the blind has identified a noticeable temperature gradient, see Section Table 1: Comparative measured U-value results for glazing Building element Control room (Existing fabric) U-value (W/m²K) Enhanced room (Refurbished fabric) U- value (W/m²K) Glazing The significant improvement in U-value is visually represented in the thermogram displayed in Figure 9. Four windows highlighted in the left of Figure 9 have been treated with Thermal Shield in the test room, the four windows highlighted on the right are of the control room, and these windows are representative of the windows in the rest of the front facade. The darker hue across the four treated show less heat loss compared to their counterparts. The brighter spot above the darker windows is a security perimeter light clearly seen in Figure 10 and not a source of heat loss. Figure 7: Thermogram, front of SPACE building. Two rooms highlighted by black outline. Test room on left control room on right. U-value and IR thermography report 9

11 Figure 8: Front of SPACE building. Showing four windows of the test room (Highlighted by black outline) Heat barrier blind The results from the six temperature probes embedded at four points within the space between each the two glazing units are displayed in Figure 9, showing a temperature profile for two days at various points within and on either side of the window. Two temperature probes were installed on the outside of Thermal Shield facing toward the space between the double glazing and the heat barrier blind recording air temperature at two points, 100mm from the sill and 100mm from the header. The same was replicated on the inside of the single glazed pane, recording the air temperature at two points between the single glazing and heat barrier blind. The results suggest that the blind was acting in a manner that could be attributed to a heat barrier. However, the interim results suggest that Thermal Shield is doing most of the heat resisting show temperatures both sides of Thermal Shield. It was anticipated that a microclimate would form between both sets of glazing as a result of the introduction of the heat barrier blind. An advantage may have been the onset of convective heat currents operating within the microclimate. The results appear to suggest that the heat captured between Thermal Shield and the blind is rising as the heat increases inside the area between Thermal Shield and the heat barrier blind. However, it is difficult to ascertain if the trapped heat is being reintroduced into the room via the trickle vent at the top of Thermal Shield. U-value and IR thermography report 10

12 Figure 9: Temperature profile at six points across the window with Thermal Shield and Heat barrier Blind The results from the internal temperature probes shows a noticeable increase in temperature as the temperature difference either side of the blind increases at 16:00-17:00hrs on the two example days in Figure 9. A pattern has emerged from the peak temperature profile that would suggest that the marginal increase in room temperature may have been affected by the heat trapped on the inside of the heat barrier blind and reradiated back through the glazing and into the room. However, room user involvement with the heat system can be ruled out at this stage. It is worth commenting at this interim stage that the large amount of heat build-up between the blind and thermal Shield may be the result of heat struggling to pass back through the double glazing and into the room. Therefore the advantages of Thermal Shield as a barrier to internal heat escape may be negatively influencing the inherent properties of the blind as an alternative heat escape barrier. 3.2 Top of South wall Heat flow mats were applied to the area above the suspended ceiling and between each of the windows (see Figure 12 and 14). The elemental build-up of the existing structure consists 500mm precast concrete lintel, 75mm unventilated air gap, 50mm mineral wool insulation, 12.5mm plasterboard on 50mm metal framing (see Figure 10). During the refurbishment stage 75mm hemp insulation added to air gap between concrete lintel and mineral wool (see Figure 11). U-value and IR thermography report 11

13 100mm hemp insulation added atop joists 100mm hemp insulation added between joists 500mm precast concrete 75mm hemp insulation added into void between concrete and mineral wool Suspended ceiling tiles Existing 50mm mineral wool insulation Figure 10: Architect s detail of wall header section listing elemental construction. Materials added during refurbishment highlighted in black outline Table 2 lists the results from the in-situ U-value measurements. 50mm of mineral wool insulation added during a pervious upgrade programme resulted in the U-value now representative of the existing structure to be measured at 0.43 W/m²K. The addition of hemp to the void between the lintel and existing insulation has improved the U-value of the wall to 0.24 W/m²K. Extra insulation in this area coupled with lapped insulation to the joints above will reduce air leakage pathways and improve the junction s vulnerability to thermal bridging. Further work into the specificity of airtightness and thermal bridging is scheduled to be explored during further research in this area. Table 2: Comparative measured U-value results for wall above ceiling tiles Building element Control room (Existing fabric) U-value (W/m²K) Enhanced room (Refurbished fabric) U- value (W/m²K) Wall: above ceiling tiles between windows Thermogram in Figure 11 and Figure 13 show the temperature difference between the ceiling tiling and insulated walls for the control and test room respectively. Figure 11 indicates that the area above the suspended ceiling is colder and heat is escaping. In comparison, Figure 13 shows the temperature of the area above the ceiling tiles is similar to that on the insulated wall, showing that the added insulation in to wall header and joists have reduced heat loss. U-value and IR thermography report 12

14 Figure 11:Thermogram of wall in control room showing temperature difference between ceiling tile and wall Figure 12: Photograph of image in Figure 11 Figure 13: Thermogram of wall in test room showing temperature of ceiling tile Figure 14: Photograph of image in Figure 13 The brighter area at the top of the blinds (Figure 11) in the control room is representative of the highly reflective metal material and therefore does not represent actual heat loss through that area. Compared to the same area in Figure 13 which shows colder areas to the top of the window is common for timber surround and the opened trickle vent. U-value and IR thermography report 13

15 3.3 Wall: Below window The area below the windows on the South facing façade is built-up of 25mm roughcast external render, 230mm solid brickwork, 50mm mineral wool insulation, 170mm unventilated air gap, 12.5mm plasterboard internal lining. The refurbishment work included 170mm of bead insulation blown into the gap between mineral wool and plasterboard (see Figure 15). 230mm solid brickwork Existing 50mm mineral wool insulation between metal studwork 170mm blown insulation added to existing framed out void behind plasterboard Figure 15: Architect s detail of wall below window section listing elemental construction. Materials added during refurbishment highlighted in black outline Results from in-situ measured U-value have shown that the addition of blown bead insulation has improved the thermal transmittance of that area of wall from 0.36 W/m²K to 0.12 W/m²K (see Table 3). Table 3: Comparative measured U-value results for wall below window Building element Control room (Existing fabric) U-value (W/m²K) Enhanced room (Refurbished fabric) U- value (W/m²K) Wall: below window The results from the infrared thermography show that the area below the window in the control room is colder than that witnessed in the refurbished room (see Figure 16, 18, 20). The images confirm the finding in Table 3. The three thermograms have been scaled to within the same temperature range to allow for visual comparison. The darker coloured gradient spread across the surface of the wall below U-value and IR thermography report 14

16 the window in the control room (Figure 15) indicates areas of heat loss. This becomes more evident towards the bottom of the plastboard. Figure 16: Thermogram of wall in control room showing temperature of area below window Figure 17:Photograph representing Figure 16 Figure 18: Thermogram of wall in test room showing temperature of area below and left of window Figure 19: Photograph representing Figure 18 Retrofitting isolated areas of a wall presents issues with maintaining continuity of the thermal envelope. Figure 18 shows a dark area representing a cold area of heat loss left of the area beneath the window. Although this area has not been thermal enhanced it does show a clear contrast to area that has been treated. U-value and IR thermography report 15

17 Figure 20: Thermogram of wall in test room showing temperature of area below window Figure 21: Photograph representing Figure 21 Darker patches highlighting areas of heat loss in Figure 20 are limited to sections of the plasterboard where metal studwork has been detached. It is typical for IR images to highlight these areas therefore they are not of concern. This observation differs from Figure 16 as the wall area beneath the window in the test room is of a similar hue across the thermogram and is within the higher end of the temperature scale. U-value and IR thermography report 16

18 3.4 Top of North wall A small portion of the North facing wall in the main offices is a non-list cavity wall with the upper portion being an external wall. This upper external wall consists of 25mm roughcast external render, 90mm solid brickwork, 110mm cavity, 110mm brick, 50mm unventilated air gap, 50mm metal stud framing finished internally with 12.5mm plasterboard. During refurbishment 110mm blown bead insulation was pumped into the cavity between the brick leaf (see Figure 21). Further to this hemp insulation was installed to the cavity behind the plasterboard and to the overhead joists to form a continuous insulating layer in an attempt to mitigate cold bridging. 100mm hemp insulation added atop joists 100mm hemp insulation added between joists 75mm hemp insulation added wall above suspended ceiling 90mm brick outer leaf 110mm blown bead insulation added to cavity 110mm brick inner leaf Figure 22: Architect s detail of wall header and roof connection on North facing wall section listing elemental construction. Materials added during refurbishment highlighted in black outline With the addition of blown bead insulation the U-value of the wall in the test room is lower to that of the North wall U-value in the control ( see Table 4). However the measured U-value is not as low as that predicted for a thermal upgrade of this type and application. A number of variables can be identified to explain this result. Firstly, it is important to be cautious with results retrieved before the minimum period of monitoring has past as explained in Section 4. Therefore this reported value maybe misrepresented at this stage and by a very large uncertainty factor. Secondly, some or most of the blown bead insulation may have disproportionally settled and/or shifted after install resulting in less insulation within the cavity. Alternatively, the results may be an indication that the air gap between the internal lining and internal brick leaf is experiencing the infiltration of colder external air ventilating the cavity space. This U-value and IR thermography report 17

19 observation becomes more evident when considering the results witnessed in the thermograms of the North wall in both rooms. Table 4: Comparative measured U-value results for North wall Building element Control room (Existing fabric) U-value (W/m²K) Enhanced room (Refurbished fabric) U- value (W/m²K) Wall: North facing below ceiling tile The thermograph of the control room North wall shows heat loss through air leakage paths along the perimeter beneath the suspended ceiling on the North side. The darker areas in Figure 23 are inconsistent with the general surface temperature along the upper portion of the wall. Observations made in the test room show similar signs of ventilation heat loss along the area beneath the suspended ceiling. Although to a lesser degree, Figure 25 shows that heat is being lost in the same area which may be an indication of an issue with continuity when placing and lapping of insulation. Figure 23: Thermogram of wall in control room showing temperature of gradient across North wall Figure 24: Photograph representing Figure 23 Figure 25: Thermogram of wall in Test room showing temperature gradient across North wall Figure 26: Photograph representing Figure 25 U-value and IR thermography report 18

20 With the results gathered to date, the evidence would suggest that some infiltration ventilation effects are being witnessed behind the internal lining. Actions available to address that issue would include the insertion of additional hemp insulation into the framed out cavity behind the plasterboard, to a point below the suspended ceiling. However, this would prove challenging to identify the most cost effective depth and a mechanism by which to secure the hemp insulation without removing the internal lining. Alternatively, further post installation survey work can be undertake to identify if continuity of insulation has been compromised during the installation process along with the aid of airtightness testing and more exploratory infrared thermography. Further work into identifying the nature of this and similar issues is scheduled to be explored during further research in this area. 4 Review of results An error analysis has been carried out on the measured U-values results for both rooms. It is recognised that an uncertainty level of ±10% is common for this testing methodology; this is to account for diurnal cycles and measurement tolerance of the equipment. It has been identified that the results were calculated prematurely to satisfy various reasons. For work carried out on Southern façades, insufficient time was allowed to account for heat stored during prolonged period of solar heat again to the face of the building. In this respect the level of uncertainty for this round of results is between to ±50 and ±65%. These results correlate with previous SEC findings (Currie 2012), which demonstrated the relationship between the temperature differential and level of uncertainty attributed to the results collected on a South façade. Figures 27 and 28 have been generated to portray the level of uncertainty attributed to these sets of results. U-value and IR thermography report 19

21 In-situ measured U-value (W/m²K) In-situ measured U-value (W/m²K) Technical Report No. E4632_JS_ Existing Refurbished Glazing Building element Figure 27: Measured U-value results and error bars representing level of calculated uncertainty for glazing measured during first two weeks of monitorng Existing Refurbished Existing Refurbished Existing Refurbished Wall: above ceiling tiles between windows Wall: below window Building element Wall: North facing below ceiling tile Figure 28: Measured U-value results and error bars representing level of calculated uncertainty for walls measured during first two weeks of monitorng U-value and IR thermography report 20

22 5 Conclusion Through the use of side-by-side comparative data analysis, two rooms in the SPACE building at Craigmillar Edinburgh were monitored and surveyed for existing and enhanced levels of fabric thermal performance. The interim results from the first 2 weeks of in-situ U-value measurements have identified that the range of insulation and fabric upgrade work introduced into a test room has improved that room s ability to further resist the flow of heat lost through the fabric compared to the neighbouring room of similar dimensions and heating profile. Infrared thermography was undertaken to allow for the visual identification of heat loss. The external thermograms has shown that the Thermal Shield system has reduced the amount of heat loss through and around the existing windows as compared to the surrounding windows representing the primary window system type used in the front of the building. Internal images of the South wall have shown that the areas where additional insulation was added, the surface temperature of that element had become more uniformed show less heat loss through that portion of wall. The IR survey has highlighted a possible issue with the refurbishment strategy applied to the North wall. Therograms of the area beneath the suspended ceiling on the North side has shown signs of ventilation heat loss. Comparison between thermograms of each room would suggest that the ventilation heat loss has been mitigated to some extent by the addition of the insulation, however some still persists. The colder patches identified by the IR survey are an indication of heat escaping into a colder boundary, whether this be the cold attic space or the external environment is unclear. However, it would suggest that the insulation to the inside of the top of North wall and ceiling joists may have been compromised. This document is due for revision upon the completion of the full period of monitoring required for insitu U-value measurements. The longer required period of monitoring will allow of a measured U-value result that will be within the desired ±10 uncertainty level. Prepared by: Checked by: Jon Stinson Energy & Buildings Research Assistant Julio Bros Williamson - B Arch. (Hons), MSc Energy & Buildings Consultant U-value and IR thermography report 21

Module 3.7. Thermal bridging

Module 3.7. Thermal bridging Module 3.7 Thermal bridging Learning Outcomes On successful completion of this module learners will be able to - Describe construction details which influence thermal bridging. 2 Introduction to thermal

More information

EFA PSBP. Natural Ventilation Strategy. Introduction. 1.1 Relevant legislation. 1.1.1 The Building Regulations 2010

EFA PSBP. Natural Ventilation Strategy. Introduction. 1.1 Relevant legislation. 1.1.1 The Building Regulations 2010 EFA PSBP Natural Ventilation Strategy Introduction The Baseline Designs Project will provide scheme design details for a number of Primary and Secondary School Exemplars. For the purposes of setting a

More information

Adaptive strategies for office spaces in the UK climate

Adaptive strategies for office spaces in the UK climate International Conference Passive and Low Energy Cooling 631 Adaptive strategies for office spaces in the UK climate I. Gallou Environment & Energy Studies Programme, Architectural Association Graduate

More information

The Pleasance, Edinburgh

The Pleasance, Edinburgh Refurbishment Case Study 5 DRAFT The Pleasance, Edinburgh Insulation of coom ceiling, attic space & lightwell 2 nd edition The views expressed in commissioned case studies are those of the authors and

More information

ANSI/ASHRAE Standard 140-2004 Building Thermal Envelope and Fabric Load Tests

ANSI/ASHRAE Standard 140-2004 Building Thermal Envelope and Fabric Load Tests ANSI/ASHRAE Standard 140-2004 Building Thermal Envelope and Fabric Load Tests DesignBuilder Version 1.2.0 (incorporating EnergyPlus version 1.3.0) - June 2006 1.0 Purpose The ANSI/ASHRAE Standard 140-2004

More information

Preventing Ice Dams on Roofs

Preventing Ice Dams on Roofs Preventing Ice Dams on Roofs Facility Manager November/December 2005 When a roof leaks, facility managers inevitably receive complaints from building occupants. If it is winter, ice dams are often the

More information

BER Assessors Dwellings Technical Bulletin

BER Assessors Dwellings Technical Bulletin BER Assessors Dwellings Technical Bulletin Issue No. 2/12 April 2012 Contents: 1. SUPPLEMENTARY ELECTRIC WATER HEATING IN SUMMER... 2 2. PITCHED ROOF U-VALUE CALCULATIONS... 8 2.1. PITCHED ROOF, INSULATED

More information

Introduction. 1. Heat Transfer. In Townsville s climate it is essential to choose building materials that perform well in our local conditions.

Introduction. 1. Heat Transfer. In Townsville s climate it is essential to choose building materials that perform well in our local conditions. In Townsville s climate it is essential to choose building materials that perform well in our local conditions. Choosing the correct materials and insulation will improve the overall thermal performance

More information

Contents. APA Construction Details. Full fill cavity walls 2-13. Partial fill cavity walls 14-25. Solid externally insulated walls 26-37

Contents. APA Construction Details. Full fill cavity walls 2-13. Partial fill cavity walls 14-25. Solid externally insulated walls 26-37 Contents Pages Full fill cavity walls 2-13 Partial fill cavity walls 14-25 Solid externally insulated walls 26-37 Appendix (BRE confirmation of Ψ and y-values) 38-40 Page 1 of 40 APA Construction Details

More information

FACTORS AFFECTING ENERGY CONSUMPTION OF BUILDINGS

FACTORS AFFECTING ENERGY CONSUMPTION OF BUILDINGS FACTORS AFFECTING ENERGY CONSUMPTION OF BUILDINGS 1 Ralf Lindberg, Professor Minna Korpi, M.Sc. Juha Vinha, Dr.Tech. June 11, 2008 Department of Civil Engineering, Tampere University of Technology 2 BACKGROUND

More information

SOUND INSULATION FOR EXTERIOR WALLS AND FACADE SYSTEMS

SOUND INSULATION FOR EXTERIOR WALLS AND FACADE SYSTEMS NOISE TECHNICAL FACT SHEET FACT SHEET 5 SOUND INSULATION FOR EXTERIOR WALLS AND FACADE SYSTEMS The sound insulation of exterior walls and roof-ceiling systems refers to their ability to reduce external

More information

Mario D. Gonçalves, Patenaude-Trempe 1 Pierre Gendron, Patenaude-Trempe 2 Tony Colantonio, PWGSC 3. Abstract

Mario D. Gonçalves, Patenaude-Trempe 1 Pierre Gendron, Patenaude-Trempe 2 Tony Colantonio, PWGSC 3. Abstract Commissioning of Exterior Building Envelopes of Large Buildings for Air Leakage and Resultant Moisture Accumulation using Infrared Thermography and Other Diagnostic Tools Mario D. Gonçalves, Patenaude-Trempe

More information

Multi-layer Insulation Blanket for Roofs

Multi-layer Insulation Blanket for Roofs Multilayer Insulation Blanket for Roofs Thermal Insulation in a 40mm thin, flexible, multilayer membrane Meets requirements of L1A, L1B 2010 In accordance with BR443 NHBC Acceptance Pitched & Flat roof

More information

Fire 2This Technical Bulletin has been commissioned by the UK SIP Association in

Fire 2This Technical Bulletin has been commissioned by the UK SIP Association in REV 1-12.12.11/TB002 Technical Bulletin Fire 2This Technical Bulletin has been commissioned by the UK SIP Association in conjunction with TRADA Technology and is intended to provide the reader with introductory

More information

Energy Company Obligation (ECO): Technical Monitoring Questions

Energy Company Obligation (ECO): Technical Monitoring Questions Energy Company Obligation (ECO) Technical Monitoring Questions v1 30/05/2013 Energy Company Obligation (ECO): Technical Monitoring Questions Under ECO suppliers are required to instruct suitably qualified

More information

Section 3.1.2. Timber Frame Walls. Single layer between studs. Single layer between studs with service void. Between studs with insulated lining

Section 3.1.2. Timber Frame Walls. Single layer between studs. Single layer between studs with service void. Between studs with insulated lining Section Timber Frame Walls Single layer between studs Product: Earthwool FrameTherm Rolls and Slabs Tf01 Single layer between studs with service void Product: Earthwool FrameTherm Rolls and Slabs Tf02

More information

Section 5.0. Basements. Wall insulated externally. Wall insulated internally. Ba02. Product: Polyfoam ECO Floorboard Ba01.

Section 5.0. Basements. Wall insulated externally. Wall insulated internally. Ba02. Product: Polyfoam ECO Floorboard Ba01. Section 5.0 Basements Wall insulated externally Product: Polyfoam ECO Ba01 Wall insulated internally Product: Polyfoam ECO Ba02 Basements Basements Basement design Waterproofing BS 8102: 2009 Code of practice

More information

Response, Reliability and Results in the delivery of leak detection services

Response, Reliability and Results in the delivery of leak detection services Response, Reliability and Results in the delivery of leak detection services Response, Reliability and Results Polygon is a global provider of property damage restoration, property performance services

More information

Technical Paper 10. U values and traditional buildings

Technical Paper 10. U values and traditional buildings Conservation Group Technical Paper 10 U values and traditional buildings In situ measurements and their comparisons to calculated values Dr. Paul Baker (Glasgow Caledonian University) January 2011 Historic

More information

THE SPAB RESEARCH REPORT 1. U-VALUE REPORT

THE SPAB RESEARCH REPORT 1. U-VALUE REPORT THE SPAB RESEARCH REPORT 1. U-VALUE REPORT OCTOBER 2010. Dr Caroline Rye 1. Introduction The 2009-2010 SPAB U-value research project originally evolved from a 'Science and Heritage' research proposal developed

More information

BUILDING CONTROL GUIDANCE SHEET REPLACEMENT WINDOWS AND DOORS Last updated 16/11/2010

BUILDING CONTROL GUIDANCE SHEET REPLACEMENT WINDOWS AND DOORS Last updated 16/11/2010 Building Control Charnwood Borough Council Southfield Road Loughborough LE11 2TN BUILDING CONTROL GUIDANCE SHEET REPLACEMENT WINDOWS AND DOORS Last updated 16/11/2010 Page 1 of 6 PURPOSE: This Guidance

More information

Rockwool Flexi Insulation Application Guide

Rockwool Flexi Insulation Application Guide Pitched roof Rafters InterMediate floors INTERNAL partitions external Framed walls separating floors Separating Walls Rockwool Flexi Insulation Application Guide Ground floor The perfect fit for any framed

More information

Garden Bothy, Cumnock

Garden Bothy, Cumnock Refurbishment Case Study 8 DRAFT Garden Bothy, Cumnock Upgrades to walls, floors, windows & door The views expressed in commissioned case studies are those of the authors and do not necessarily represent

More information

Introduction & Principles Issued in support of Junction Details, Parts 1 to 5

Introduction & Principles Issued in support of Junction Details, Parts 1 to 5 Accredited Construction Details (Scotland) 2010 For the limitation of thermal bridging and air infiltration in low and medium rise domestic buildings Introduction & Principles Issued in support of Junction

More information

WALLS Three common wall types are described below, with their insulation solutions.

WALLS Three common wall types are described below, with their insulation solutions. APPENDIX 5: Building Envelope Insulation is vitally important for temperature controlled buildings. If fuel (and therefore money) is being used to heat a building, less fuel (and money) will be used if

More information

ROOFS, SNOW AND ICE DAMS

ROOFS, SNOW AND ICE DAMS ROOFS, SNOW AND ICE DAMS The Problem Ice dams are a common roof performance problem in cold climate buildings. Simply put, they are ridges of ice and icicles caused by melt water from further up the roof

More information

Improving thermal insulation of concrete sandwich panel buildings

Improving thermal insulation of concrete sandwich panel buildings Improving thermal insulation of concrete sandwich panel buildings Jørgen Munch-Andersen Danish Building Research Institute, Aalborg University LCUBE conference, Vienna 17-18 April 2007 Outline A general

More information

Energy Efficient Windows

Energy Efficient Windows Energy Efficient Windows All properties lose heat through their windows. But energy-efficient glazing keeps your home warmer and quieter as well as reducing your energy bills. That might mean double or

More information

Section 2.4. Built-up Metal Roofs. Rail and bracket system. Standing seam system. Bu02. Product: Earthwool FactoryClad range Bu01

Section 2.4. Built-up Metal Roofs. Rail and bracket system. Standing seam system. Bu02. Product: Earthwool FactoryClad range Bu01 Section Built-up Metal Roofs Rail and bracket system Product: Earthwool FactoryClad range Bu01 Standing seam system Product: Earthwool FactoryClad range and Earthwool Universal Slab Bu02 Built-up Metal

More information

High R-Value Does Not Always Mean High Performance

High R-Value Does Not Always Mean High Performance High R-Value Does Not Always Mean High Performance By Charlie Gohman, Building Science and Efficiency Manager, Energy Office, Arizona Department of Commerce Ever since the energy crisis of the 70s we have

More information

Moisture Content in Insulated Basement Walls

Moisture Content in Insulated Basement Walls Moisture Content in Insulated Basement Walls Peter Blom,PhD, SINTEF Building and Infrastructure; peter.blom@sintef.no, www.sintef.no/byggforsk Sverre B. Holøs M.Sc. SINTEF Building and Infrastructure;

More information

Building Control Guidance Note

Building Control Guidance Note Issued 01/01/13 Rev Page 1 of 5 If you intend to convert an existing loft space into additional rooms you will need to apply for Building Regulation Approval. You may also need Planning Permission if you

More information

GUIDANCE SHEET FOR CONSERVATORIES, SUNROOMS AND EXTENSIONS TO DWELLINGS.

GUIDANCE SHEET FOR CONSERVATORIES, SUNROOMS AND EXTENSIONS TO DWELLINGS. GUIDANCE SHEET FOR CONSERVATORIES, SUNROOMS AND EXTENSIONS TO DWELLINGS. This leaflet provides guidance on how to attain compliance with The Building (Amendment) Regulations (Northern Ireland) 2006, Part

More information

2014 British Columbia Building Code Changes

2014 British Columbia Building Code Changes District of Houston 250-845-2238 2014 British Columbia Building Code Changes A District of Houston interpretation of the 2014 Building Code Changes for 9.36 & 9.32 The following changes reflect the most

More information

NFRC 102-2010 THERMAL PERFORMANCE TEST REPORT. Rendered to: CR LAURENCE CO., INC. SERIES/MODEL: 7500 Concealed Vent TYPE: Projecting (Awning)

NFRC 102-2010 THERMAL PERFORMANCE TEST REPORT. Rendered to: CR LAURENCE CO., INC. SERIES/MODEL: 7500 Concealed Vent TYPE: Projecting (Awning) NFRC 102-2010 THERMAL PERFORMANCE TEST REPORT Rendered to: CR LAURENCE CO., INC. SERIES/MODEL: 7500 Concealed Vent TYPE: Projecting (Awning) Summary of Results Standardized Thermal Transmittance (U-Factor)

More information

BLUESTAR INFRARED. Description: Thermal Properties Comparison. Project Location: Client: 759 South Federal Hwy 225 Bayshore Drive 800-216-1820

BLUESTAR INFRARED. Description: Thermal Properties Comparison. Project Location: Client: 759 South Federal Hwy 225 Bayshore Drive 800-216-1820 BLUESTAR INFRARED We Bring Bad Things to Light SERVING ALL OF FLORIDA Infrared Inspection Services 24 Hour Emergency Service I n f r a r e d I n s p e c t i o n R e p o r t 772-215-8794 Description: Thermal

More information

State of Connecticut Department of Public Health RADON PROGRAM

State of Connecticut Department of Public Health RADON PROGRAM State of Connecticut Department of Public Health RADON PROGRAM Scope The Connecticut Department of Public Health (DPH) Radon Program is providing this information for contractors who decide to build radon

More information

JOEGREEN ROADMAP TO ENERGY EFFICIENCY

JOEGREEN ROADMAP TO ENERGY EFFICIENCY 1 JOEGREEN Audit Team: Chris Henson Audit Date: May 26 th, 2010 Town of Topsfield Town Hall, Thank you, once again, for choosing us to be your partner in Energy Efficiency. The Joe Green Commercial Energy

More information

GHS Flood Final Report CTA Architects Engineers March 31, 2011

GHS Flood Final Report CTA Architects Engineers March 31, 2011 GHS Flood Final Report CTA Architects Engineers March 31, 2011 INTRODUCTION: Glacier High School underwent extensive flooding due to a broken frozen fire sprinkler joint of the ceiling in the Small Conference

More information

FIRE RATED GLAZING System Guide

FIRE RATED GLAZING System Guide SYSTEM GUIDE Issue date: 05-05-2015 Expiry date: 31-12-2016 System Guide Introduction Pyropanel Developments are specialists in fire rated glazing solutions, and our systems are designed for easy installation

More information

Timber Frame Walls Rethinking Construction

Timber Frame Walls Rethinking Construction Insulation Fifth Issue November 2007 Timber Frame Walls Rethinking Construction INSULATION BEST PRACTICE FOR THE 21ST CENTURY Summary 9 mm OSB sheathing 3 mm skim coated 15 mm plasterboard Rock or glass

More information

Constructions Database User Guide <Virtual Environment> 5.9

Constructions Database User Guide <Virtual Environment> 5.9 Constructions Database User Guide 5.9 Page 1 of 35 Contents 1. Introduction...3 2. Units...4 3. Main Dialogue Project Constructions...5 3.1. Outline...5 3.2. Construction Classes

More information

Non Invasive Roof Leak Detection Using Infrared Thermography

Non Invasive Roof Leak Detection Using Infrared Thermography Non Invasive Roof Leak Detection Using Infrared Thermography Scott Wood Four Star Cleaning and Restoration, Inc. ABSTRACT Residential roofs without attics are typically inspected for leaks by installing

More information

Rev 1-12.2013. Code of Practice. SIP Technology. www.uksips.org

Rev 1-12.2013. Code of Practice. SIP Technology. www.uksips.org Rev 1-12.2013 Code of Practice SIP Technology www.uksips.org What are Structural Insulated Panels (SIPS)? SIPS are prefabricated, high performance, lightweight, building panels that can be used in floors,

More information

Specification Guide. SmartSash. Fenestration Solutions for Public Sector & Commercial Applications ARCHITECTURAL. D11 +D13:X725 CI/SfB (31.4)+(31.

Specification Guide. SmartSash. Fenestration Solutions for Public Sector & Commercial Applications ARCHITECTURAL. D11 +D13:X725 CI/SfB (31.4)+(31. Uniclass L411 +L413:P7114 EPIC D11 +D13:X725 CI/SfB (31.4)+(31.5) Xn6 9/11 SmartSash A BRAND OF THE VEKA UK GROUP Specification Guide Fenestration Solutions for Public Sector & Commercial Applications

More information

Evaluating the Field Performance of Windows and Curtain Walls of Large Buildings

Evaluating the Field Performance of Windows and Curtain Walls of Large Buildings Best2 Airtightness of Buildings Session WB6-2 Evaluating the Field Performance of Windows and Curtain Walls of Large Buildings Mario D. Gonçalves, Patenaude-Trempe and Robert Jutras, Air-Ins Introduction

More information

Nondestructive Evaluation of USCG. 2401 Hawkins Pt. Road Curtis Bay, MD 21226. Provided by: HurleyIR

Nondestructive Evaluation of USCG. 2401 Hawkins Pt. Road Curtis Bay, MD 21226. Provided by: HurleyIR Nondestructive Evaluation of USCG 2401 Hawkins Pt. Road Curtis Bay, MD 21226 Provided by: HurleyIR On Tuesday May 20 th 2014, HurleyIR provided a nondestructive evaluation for Ruff Roofers of the USCG

More information

Opening the Bonnet. Prof Darren Woolf WYSINWYG 1

Opening the Bonnet. Prof Darren Woolf WYSINWYG 1 Opening the Bonnet Prof Darren Woolf WYSINWYG 1 WYSINWYG What You See Is NOT What You Get: Looking inside the Pandora s Box Prof Darren Woolf WYSINWYG 2 WYSIWYG implies a user interface that allows the

More information

Basement Waterproofing in Existing Buildings

Basement Waterproofing in Existing Buildings A S S O C I A T I O N Basement Waterproofing in Existing Buildings A guide to protecting your home Follow us on Twitter Find us on Facebook www.property-care.org A basic understanding of Basement Waterproofing

More information

Climate and Energy Responsive Housing in Continental Climates. The Suitability of Passive Houses for Iran's Dry and Cold Climate. Farshad Nasrollahi

Climate and Energy Responsive Housing in Continental Climates. The Suitability of Passive Houses for Iran's Dry and Cold Climate. Farshad Nasrollahi Climate and Energy Responsive Housing in Continental Climates The Suitability of Passive Houses for Iran's Dry and Cold Climate Farshad Nasrollahi Table of Contents Abstract German Abstract Introduction

More information

Signs of insulation problems In the winter. In the summer. conditioning system

Signs of insulation problems In the winter. In the summer. conditioning system about your house CE 19 While previous generations may have been content to live in drafty houses, most people now want comfortable warm houses. A healthy house today is well sealed, well insulated and

More information

Post-insulation of cellar ceiling and cellar walls

Post-insulation of cellar ceiling and cellar walls WP5 Education and Economic Promotion Post-insulation of cellar ceiling and cellar walls Educational product: New lecture material for training modules dealing with knowledge and skills how to apply suitable

More information

Diego Ibarra Christoph Reinhart Harvard Graduate School of Design

Diego Ibarra Christoph Reinhart Harvard Graduate School of Design Building Performance Simulation for Designers - Energy DesignBuilder // EnergyPlus Tutorial #3 Construction Assemblies, Load Reduction & Shading GEOMETRY LOADS RESULTS Diego Ibarra Christoph Reinhart Harvard

More information

Energy Efficiency in Buildings

Energy Efficiency in Buildings Energy Efficiency in Buildings Supplemental Guide to SANS 10400-XA & SANS 204 V. 3.0 Registered to: The Drawing Studio Image: digitalart / FreeDigitalPhotos.net Report Date: 26 August 2014 Practice Name:

More information

ENVIRONMENTAL INFORMATION APR 1200 products are made from glass mineral wool, one of the most environmentally friendly insulants available.

ENVIRONMENTAL INFORMATION APR 1200 products are made from glass mineral wool, one of the most environmentally friendly insulants available. APR 1200 Acoustic Partition Roll CI/Sfb Ref: APR002 Glass mineral wool roll designed to provide high levels of sound insulation in walls and floors to meet Part E (England & Wales) and Section 5 (Scotland)

More information

Eco Pelmet Modelling and Assessment. CFD Based Study. Report Number 610.14351-R1D1. 13 January 2015

Eco Pelmet Modelling and Assessment. CFD Based Study. Report Number 610.14351-R1D1. 13 January 2015 EcoPelmet Pty Ltd c/- Geoff Hesford Engineering 45 Market Street FREMANTLE WA 6160 Version: Page 2 PREPARED BY: ABN 29 001 584 612 2 Lincoln Street Lane Cove NSW 2066 Australia (PO Box 176 Lane Cove NSW

More information

Directorate for the Built Environment Building Standards Division

Directorate for the Built Environment Building Standards Division Directorate for the Built Environment Building Standards Division Energy Management Solutions Ltd Investigation of measures to improve the energy performance of a existing building: Retail JUNE 2009 Report

More information

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,

More information

Unbeatable energy efficient glass curtain wall system

Unbeatable energy efficient glass curtain wall system Unbeatable energy efficient glass curtain wall system CONTENT Introduction 1 System 2 World Class Engineering 4 Unit Selection 5 Energy Efficiency & Comfort 10 Maximised Installation Efficiency 12 Aesthetics

More information

Building Control Guidance Note

Building Control Guidance Note Elements Renovation / Replacement. Issued 25/01/13 Rev a Page 1 of 9 (Applies to both Domestic and Non-Domestic Premises) Works relating to thermal elements can arise in building an extension, a material

More information

Property Inspection. 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT

Property Inspection. 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT Property Inspection 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT March 2013 This document has been prepared for the benefit of Clint Marston. No liability is accepted by this company

More information

Investigation of thermal resistance and bridging in examples of contemporary and vernacular solid wall architecture

Investigation of thermal resistance and bridging in examples of contemporary and vernacular solid wall architecture Investigation of thermal resistance and bridging in examples of contemporary and vernacular solid wall architecture Oliver Kinnane, PhD March BE Jennifer McGinn, MAI Patrick O Shea MAI John Grimes, MPhil

More information

WHAT IS INFRARED (IR) THERMOGRAPHY

WHAT IS INFRARED (IR) THERMOGRAPHY WHAT IS INFRARED (IR) THERMOGRAPHY IR Thermography is the technique of producing pictures called from the invisible thermal radiation that objects emit. This is a non-contact means of identifying electrical

More information

Abstract. 2. Cold Pitched Roofs

Abstract. 2. Cold Pitched Roofs Heat and moisture transport between houses and cold lofts - a combination of convection and diffusion Emannuel Essah and Chris Sanders Glasgow Caledonian University Abstract About 80% of domestic pitched

More information

STEP-BY-STEP. construction guide. Delivering better priced Conservatories, Sun Lounges and Garden Rooms via the Internet.

STEP-BY-STEP. construction guide. Delivering better priced Conservatories, Sun Lounges and Garden Rooms via the Internet. STEP-BY-STEP construction guide Delivering better priced Conservatories, Sun Lounges and Garden Rooms via the Internet. Welcome to our CONSERVATORY AND SUNROOM CONSTRUCTION GUIDE What is the specification

More information

FIELD TESTING SERVICES

FIELD TESTING SERVICES FIELD TESTING SERVICES Chris Leach Director of Testing Baton Rouge, Louisiana Destin, Florida Scott Leach David Nichols Field Testing Representative Field Testing Representative 17485 Opportunity Avenue

More information

INTERIOR WALLS AND BASEMENTS CHOOSING THE RIGHT MEMBRANE FOR INTERIOR WALLS. Multi-Layer Technology provides increased strength.

INTERIOR WALLS AND BASEMENTS CHOOSING THE RIGHT MEMBRANE FOR INTERIOR WALLS. Multi-Layer Technology provides increased strength. INTERIOR WALLS AND BASEMENTS CHOOSING THE RIGHT MEMBRANE FOR INTERIOR WALLS Multi-Layer Technology provides increased strength. Specifically designed for interior applications. Compatible with most internal

More information

CERTIFICATE NAME OF PRODUCT MANUFACTURER PRODUCT DESCRIPTION CERTIFICATION PROCEDURE. No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011

CERTIFICATE NAME OF PRODUCT MANUFACTURER PRODUCT DESCRIPTION CERTIFICATION PROCEDURE. No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011 CERTIFICATE NAME OF PRODUCT No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011 H-CONTROL REFLEX+ reflective insulating vapour control layer for roof and wall applications MANUFACTURER ACTIS

More information

HEATING-COOLING WALL PANELS SYSTEM IN SLOVENE ETHNOGRAPHIC MUSEUM

HEATING-COOLING WALL PANELS SYSTEM IN SLOVENE ETHNOGRAPHIC MUSEUM 01-147 The 2005 World Sustainable Building Conference, HEATING-COOLING WALL PANELS SYSTEM IN SLOVENE ETHNOGRAPHIC MUSEUM Aleš KRAINER Prof. Dr. 1 Rudi Perdan 2 Gal Krainer 3 1 2 Faculty of Civil Engineering,

More information

1/9/2013. Terminology Calculating Heat Transfer Code Requirements Design Examples and Sustainability

1/9/2013. Terminology Calculating Heat Transfer Code Requirements Design Examples and Sustainability 1/9/13 By Brett T. Fagan, P.E. Presented by Marie Horan, P.E. Building Diagnostics, Inc. Building Diagnostics Terminology Calculating Heat Transfer Code Requirements Design Examples and Sustainability

More information

TGD L 2011. Limiting Thermal Bridging and Air Infiltration. Acceptable Construction Details. Introduction

TGD L 2011. Limiting Thermal Bridging and Air Infiltration. Acceptable Construction Details. Introduction TGD L 2011 Limiting Thermal Bridging and Air Infiltration Acceptable Construction Details Introduction Government of Ireland 2015 1 INTRODUCTION This guide to Acceptable Construction Details (ACDs) is

More information

Rockwool Cladding Roll

Rockwool Cladding Roll Rockwool Cladding Roll High performance industrial insulation has been specifically developed for use in lightweight cladding applications to commercial or industrial framed buildings. Cladding Roll U/F

More information

Sports Buildings: budget costs for the Flood Relief Fund

Sports Buildings: budget costs for the Flood Relief Fund Sports Buildings: budget costs for the Flood Relief Fund The list below provides typical costs for flood insurance works, typically required by sports clubs or facilities. The list is not exhaustive but

More information

BREEAM Refurbishment and Fit-out 2014 Briefings. Part of the BRE Trust

BREEAM Refurbishment and Fit-out 2014 Briefings. Part of the BRE Trust BREEAM Refurbishment and Fit-out 2014 Briefings Part of the BRE Trust BREEAM for Refurbishment and Fit-out Follows 2 years of development Draft scheme published and consultation from 19 th July 2014 Launched

More information

INFRARED DIAGNOSTIC REPORT ABLE INSPECTION COMPANY Post Office Box 820129 Houston, Texas 77282 (713) 465-0000

INFRARED DIAGNOSTIC REPORT ABLE INSPECTION COMPANY Post Office Box 820129 Houston, Texas 77282 (713) 465-0000 www.ableinfrared.co www.flirthermography.com INFRARED DIAGNOSTIC REPORT ABLE INSPECTION COMPANY Post Office Box 820129 Houston, Texas 77282 (713) 465-0000 CLIENT: PROPERTY SURVEYED: EMAIL: DATE: In accordance

More information

Replacement Windows and Doors

Replacement Windows and Doors Replacement Windows and Doors Short Policy Guide: Need for Planning Permission and Listed Building Consent For Replacement Windows and Doors Produced by City Development Department, Dundee City Council,

More information

CONDENSATION IN REFRIDGERATED BUILDINGS

CONDENSATION IN REFRIDGERATED BUILDINGS CONDENSATION IN REFRIDGERATED BUILDINGS By: Steve Salisbury Nov. 10, 2010 (revised Nov. 14, 2013) Introduction The following discussion reviews the basic causes of condensation in refrigerated buildings

More information

Sika Membran System For Sealing and Waterproofing Construction Gaps in Building Façades

Sika Membran System For Sealing and Waterproofing Construction Gaps in Building Façades Construction Sika For Sealing and Waterproofing Construction Gaps in Building Façades Waterproof and Airtight Flexible Seal Controlled Vapour Diffusion Bonds to any Building Substrate Prevents Interstitial

More information

Diego Ibarra Christoph Reinhart Harvard Graduate School of Design

Diego Ibarra Christoph Reinhart Harvard Graduate School of Design Building Performance Simulation for Designers - Energy DesignBuilder // EnergyPlus Tutorial #2 Load Schedules GEOMETRY LOADS RESULTS Diego Ibarra Christoph Reinhart Harvard Graduate School of Design OVERVIEW

More information

Loss Prevention Standard

Loss Prevention Standard Loss Prevention Standard LPS 1581: Issue 2.1 Requirements and tests for LPCB approval of nonload This Loss Prevention Standard is the property of BRE Global Ltd. and is made publicly available for information

More information

Advice Series. the maintenance and repair of historic buildings

Advice Series. the maintenance and repair of historic buildings Advice Series the maintenance and repair of historic buildings Jacqui Donnelly - Architectural Conservation Advisor, Department of the Environment, Heritage & Local Government Current publications in the

More information

Glass partitions SFB 3074

Glass partitions SFB 3074 Glass partitions SFB 3074 Our facade system SFB 3074 is innovative in its design. We have made a great effort to obtain an energy effective system. The future requirements regarding the economical use

More information

IES <Virtual Environment> Tutorial. Apache Sim (Version 6.0)

IES <Virtual Environment> Tutorial. Apache Sim (Version 6.0) IES Tutorial Apache Sim (Version 6.0) Introduction This tutorial will begin by showing you how to use the Building Template Manager (BTM) to create thermal and construction data for

More information

ModuSec. Secure and efficient IT room solutions. Turnkey Modular Construction Fast clean build to any size or shape

ModuSec. Secure and efficient IT room solutions. Turnkey Modular Construction Fast clean build to any size or shape ModuSec Secure and efficient IT room solutions Turnkey Modular Construction Fast clean build to any size or shape Room in room Standalone external build Transportable Modusec SR Options Modusec SR Options

More information

HEAT LOAD AND SOLAR GAIN PREDICTION FOR SOLID WALL DWELLINGS RETROFITTED WITH TRIPLE VACUUM GLAZING FOR SELECTED WINDOW TO WALL AREA RATIOS

HEAT LOAD AND SOLAR GAIN PREDICTION FOR SOLID WALL DWELLINGS RETROFITTED WITH TRIPLE VACUUM GLAZING FOR SELECTED WINDOW TO WALL AREA RATIOS HEAT LOAD AND SOLAR GAIN PREDICTION FOR SOLID WALL DWELLINGS RETROFITTED WITH TRIPLE VACUUM GLAZING FOR SELECTED WINDOW TO WALL AREA RATIOS Saim Memon Philip C. Eames Centre for Renewable Energy Systems

More information

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003) NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:

More information

INTERNATIONAL ASSOCIATION OF CLASSIFICATION SOCIETIES. Interpretations of the FTP

INTERNATIONAL ASSOCIATION OF CLASSIFICATION SOCIETIES. Interpretations of the FTP INTERNATIONAL ASSOCIATION OF CLASSIFICATION SOCIETIES Interpretations of the FTP CONTENTS FTP1 Adhesives used in A or B class divisions (FTP Code 3.1, Res A.754 para. 3.2.3) June 2000 FTP2 Pipe and duct

More information

Windows are one of the most important components of a

Windows are one of the most important components of a design concepts Arjun Kamal MAKING BETTER INDOOR ENVIRONMENTS WITH ENERGY-EFFICIENT WINDOW DESIGN An insight into the various technologies used for constructing windows, and an attempt at understanding

More information

3-D Modeller Rendered Visualisations

3-D Modeller Rendered Visualisations Recognised energy Dynamic Simulation Modelling (DSM) software DesignBuilder is a user interface to the EnergyPlus DSM. EnergyPlus builds on the most popular features and capabilities of BLAST and DOE-2

More information

Structural Assessment Report

Structural Assessment Report Report Dallas Township Elementary School Dallas, Pennsylvania (JBCI Project No. 144911) 1655 Suburban Station Building 1617 John F. Kennedy Boulevard Philadelphia PA 19103 215 665 0497 5 Sandwood Drive

More information

Case Studies: Infrared Heating in Industrial Applications

Case Studies: Infrared Heating in Industrial Applications Case Studies: Infrared Heating in Industrial Applications Chao Chen, Puget Sound Energy ABSTRACT Puget Sound Energy (PSE) is a utility which serves more than one million electric customers and over 700,000

More information

Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit

Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed

More information

Exemplary Retrofitting of an Old School in Stuttgart - EROS -

Exemplary Retrofitting of an Old School in Stuttgart - EROS - Exemplary Retrofitting of an Old School in Stuttgart - EROS - City of Stuttgart, Summary The objective of the project was to demonstrate the potentials of a retrofitting process for a typical school in

More information

IGNITION-RESISTANT CONSTRUCTION: THE WHY BEHIND THE WHAT

IGNITION-RESISTANT CONSTRUCTION: THE WHY BEHIND THE WHAT IGNITION-RESISTANT CONSTRUCTION: THE WHY BEHIND THE WHAT WHAT IS THE RATIONALE BEHIND THE REQUIREMENTS FOR IGNITION RESISTANT CONSTRUCTION? The wildfires of 2003 and 2007 were the largest in California

More information

CAN DEMAND CONTROLLED VENTILATION REPLACE SPACE HEATING IN OFFICE BUILDINGS WITH LOW HEATING DEMAND?

CAN DEMAND CONTROLLED VENTILATION REPLACE SPACE HEATING IN OFFICE BUILDINGS WITH LOW HEATING DEMAND? Topic B3: Control of indoor environment CAN DEMAND CONTROLLED VENTILATION REPLACE SPACE HEATING IN OFFICE BUILDINGS WITH LOW HEATING DEMAND? Axel CABLE 1,*, Mads MYSEN 1,2, Kari THUNSHELLE 1 1 SINTEF,

More information

Case Studies of Successful Code for Sustainable Homes Projects

Case Studies of Successful Code for Sustainable Homes Projects Case Studies of Successful Code for Sustainable Homes Projects Sustainable Homes publish the Sustainable Homes Index For Tomorrow (SHIFT) and are a leading trainers of Code for Sustainable Homes assessors.

More information

Building Regulations for the Conservation of Fuel and Power

Building Regulations for the Conservation of Fuel and Power Insulation CI/SfB Rn7 M2 First Issue April 2014 Building Regulations for the Conservation of Fuel and Power ENGLAND EXISTING DWELLINGS 2013 EDITION Low Energy Low Carbon Buildings Contents Page Introduction

More information

Heating Load Calculation

Heating Load Calculation Heating Load Calculation ME 425 Air Conditioning System Design Keith E. Elder, P.E. Heating Load Calculation The heating load calculation begins with the determination of heat loss through a variety of

More information

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. CI/SfB Tn6 L6813 September 2013 RIW CAVITY DRAIN R20 R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. Other systems are available for specific uses,

More information

NAIOP OF SOUTHERN NEVADA SUSTAINABILE DEVELOPMENT COMMITTEE - EDUCATION SERIES

NAIOP OF SOUTHERN NEVADA SUSTAINABILE DEVELOPMENT COMMITTEE - EDUCATION SERIES THERMOGRAPHY 101 A short primer By Daniel S. Amster August 2011 Suppose you wanted to know where insulation, blocking or studs are located behind drywall, or maybe you suspect a water leak in a wall cavity

More information