AGING BASED MAINTENANCE AND REINVESTMENT SCHEDULING OF ELECTRIC DISTRIBUTION NETWORK

Size: px
Start display at page:

Download "AGING BASED MAINTENANCE AND REINVESTMENT SCHEDULING OF ELECTRIC DISTRIBUTION NETWORK"

Transcription

1 Juha Korpijärvi AGING BASED MAINTENANCE AND REINVESTMENT SCHEDULING OF ELECTRIC DISTRIBUTION NETWORK Thesis for the degree of Doctor of Science (Technology) to be presented with due permission for public examination and criticism in the Auditorium of the Mikkeli University Consortium, Mikkeli, Finland on the 23rd of November, 2012, at noon. Acta Universitatis Lappeenrantaensis 481

2 Supervisor Professor, Dr. Jarmo Partanen Institute of Energy Technology Lappeenranta University of Technology Lappeenranta, Finland Reviewers and opponents Professor, Dr. Pertti Järventausta Departement of Electrical Energy Engineering Tampere University of Technology Tampere, Finland Director, Dr. Juha Lohjala Suur-Savon Sähkö Oy Mikkeli, Finland ISBN ISBN (PDF) ISSN Lappeenrannan teknillinen yliopisto Digipaino 2012

3 To Eeva-Leena

4 Abstract Juha Korpijärvi Aging based maintenance and reinvestment scheduling of electric distribution network Lappeenranta pages Acta Universitatis Lappeenrantaensis 481 Diss. Lappeenranta University of technology ISBN , ISBN (PDF), ISSN The maintenance of electric distribution network is a topical question for distribution system operators because of increasing significance of failure costs. In this dissertation the maintenance practices of the distribution system operators are analyzed and a theory for scheduling maintenance activities and reinvestment of distribution components is created. The scheduling is based on the deterioration of components and the increasing failure rates due to aging. The dynamic programming algorithm is used as a solving method to maintenance problem which is caused by the increasing failure rates of the network. The other impacts of network maintenance like environmental and regulation reasons are not included to the scope of this thesis. Further the tree trimming of the corridors and the major disturbance of the network are not included to the problem optimized in this thesis. For optimizing, four dynamic programming models are presented and the models are tested. Programming is made in VBA-language to the computer. For testing two different kinds of test networks are used. Because electric distribution system operators want to operate with bigger component groups, optimal timing for component groups is also analyzed. A maintenance software package is created to apply the presented theories in practice. An overview of the program is presented. Keywords: maintenance practices, dynamic programming, maintenance scheduling, reinvestment scheduling UDC : :658.58:657.47

5 Acknowledgements The results of this doctoral thesis are mainly based on the research work financed by TEKES, Etelä Savon Energia Oy, Joroisten energialaitos, Joutsenon Energia Oy, Imatran Seudun Sähkönsiirto Oy, Järvi-Suomen Energia Oy, KSS Verkko Oy, Kymenlaakson Sähköverkko Oy, Outokummun Energia Oy, Parikkalan Valo Oy and PKS Sähkönsiirto Oy. The final writing of dissertation was supported by Finnish Cultural Foundation, South Savo Regional fund. I thank all for financial support. I want to thank my employer Mikkeli University of Applied Sciences (MAMK) for working circumstances and organizing the research project. I thank my supervisor Professor Dr. Jarmo Partanen for his guidance and valuable contribution during this work. I express my gratitude to the reviewers of my thesis Professor Dr. Pertti Järventausta and Dr. Juha Lohjala for their critical review of my thesis manuscript and their comments. I want to thank Dr. Jari Kortelainen for the co-operation in developing the optimizing models, Mr Jyri Kivinen for developing the structure and interface of the maintenance software package, Mrs Aija Myyryläinen for collecting the survey material. The SPSS program was used by Mr Mauno Keto and Mr Tero Karjola implemented the test network. Mrs Kirsti Karttunen helped me in literature searching and Mr Jari Hartikainen in the English language. I want to thank them as well. Finally I thank my wife Eeva-Leena for her love during the process and my three beautiful daughters, Helka-Maaria, Helmi-Tuulia and Henni-Riikka for inspirational family atmosphere. Mikkeli, September 14 th, 2012 Juha Korpijärvi

6 Abstract Acknowledgments Nomenclature 1 Introduction Background Network asset management and reliability analysis Maintenance in Finnish system operators The distribution system operators analysed Maintenance policy in the analysed distribution system operators The average interruption time and maintenance Conclusion of the Finnish distribution system operator analysis The scope of the thesis Contributions Maintenance problem Problem description Failure modelling Maintenance activities Maintenance strategies Maintenance directions and cost optimization Objective of maintenance Modelling of cost components Determination of maintenance cost and failure cost Fault risk of the component in electric distribution system Outage cost The maintenance model Overhaul of the component Maintenance problem solving Decision of maintenance and investment actions Example of maintenance and reinvestment timing decision Optimization problem Possible optimization algorithms for maintenance problem solving Line clearance problem Line and generation outage scheduling problem Stochastic transition process Algorithm for sizing, locating and timing of feeder reinforcements Dynamic programming model Example of dynamic programming algorithm Dynamic programming models for maintenance and reinvestment optimization Three-state-model... 60

7 4.2.2 Three-state-plus-model Total-cost-model Annual-cost-model Conclusion of the presented models Fundamental improvement and dynamic programming Group optimization The analysis methods and the test networks Test network The analysis of components Separately optimized components Maintenance years The effect of maintenance on the reinvestment timing Results of the maintenance model three Component groups Test network The description of the network Failure rate levels and initial values in the network Results of the dynamic programming algorithm Sensitivity analysis Interrupted power The age of the component Interest rate Failure cost level Investment price Scale-factor λ Shape-factor β Conclusion of the sensitivity analysis Maintenance software package Discussion Conclusions References

8 Nomenclature Roman Letters a A 0 A 1 A 2 A02 A01 A11 A12 A22 A[] B[] c kw c kwh C C C clr (t) C comp (t) C dar C energy (t) C F (t) C F1 (t) C F (t,a) C F (a m (t),n) Chsar C ins (t) C I (t) C L (t) C ljtp C Mi C out (t) C ovh (t) C uitp C per C rep (t) C Ri C M (t) variable, which express the reference year after the maintenance action discounted failure costs to the end of the design period, if investment is not realized discounted failure costs to the end of the design period, if maintenance action is realized discounted failure costs to the end of the design period if investment is realized additional cost when transferring from no-state to investment state additional cost when transferring from no-state to maintenance state additional cost when transferring in maintenance state additional cost when transferring from maintenance state to investment state additional cost when transferring in the investment state additional cost in total-cost model the cost function to find the optimal route in annual cost model outage cost of power [ /kw] outage cost of no delivered energy [ /kwh] cost associated with the maintenance task total cost costs of clearing the corridors compensation costs including the costs not reaching the target level of the criteria cost of delayed automatic reclosing for the customer marginal profit of the undelivered energy failure costs in year t failure rate of the component in year t without maintenance action failure rate of the component a years after the maintenance action in year t outage cost per year when state alternative n is realized for component in age a m (t) cost of high speed automatic reclosing for the customer costs of inspection and costs of eliminating minor faults costs of investments in year t operational costs in year t maintenance cost of line j at time t at interval p maintenance cost for line i in interval j costs experienced by the customer costs of capital overhauls maintenance cost of unit i at time t at interval p. For instance t could be an hour and p could be a week long cost of permanent interruption for the customer repairing costs of the failure average repair cost for line i maintenance costs in year t

9 e Euler s number E cost-effectiveness of a maintenance task E i state of the process ( I = 1,2,,n) F objective function F ij (t) distribution function of the one-step transition time f failure rate f(t) density function F(t) probability of failure up to time t G(t,n) minimum costs up to state (t,n) I component I m the state the system enters at time t m j consumer l length of the conductor [km] M total number of lines in the system N the number of possible strategies N 1 total scheduling time intervals N 2 the number of components in one component group p rate of interest P power of interrupted load [kw] P[] probability function P={p ij } time homogeneous transition probabilities r(t) failure rate at time t r ij (σ i (k)) cost/reward of a transition (from E i to E j ) controlled by the strategy σ i (k) selected at t k R ij ( ) function which denotes the cost of transition of the system when it goes from state E i to E j t age of the component or reference year t ij length of interruption [h] t 1 step year t 2 year of the action (t,n) state T length of the design period T p utilization time of the investment V[1,2] transfer costs from state 1 to state 2 w i (σ i (k)) expected cost of the step k+1 if the system is in state E i at t k, and controlled by σ i (k) wn the weighting factor in group optimizing X ij maintenance decision variable for line i in j th time interval (0-no maintenance, 1-maintenance) X itp maintenance status of unit i at time t at interval p, 0 if unit is offline for maintenance, otherwise 1 Y jtp maintenance status of line I at time t at interval p, 0 if unit is offline for maintenance, otherwise 1 Z(t,n) the cumulative costs in year t in node n, when the minimum route is chosen

10 Greek Letters α α 1 β β 1 ε λ λ ij σ() σ j (k) ω discount factor parameter, which express the relation of the failure rate shape factor in Weibull distribution parameter, which express the annual increase of the failure rate after the maintenance action annuity factor scale factor in Weibull distribution failure rate of line i in j th time interval maintenance strategy maintenance action selected when arriving to state E j at time t k weighting factor Abbreviations DP INV INV RES MAIFI NG NL NP NT RNA/AM SAIDI SAIFI WASRI dynamic programming cost of reinvestment residual value of the previous investment of the component momentary event average interruption frequency number of units number of transmission lines number of intervals under study number of times at each interval reliability based network analysis tool system average interruption duration index system average interruption frequency index system average reliability index

11 11 1 Introduction 1.1 Background Ten Eastern-Finnish distribution system operators decided to develop their maintenance activities in the year All the companies had the same future challenges. The personnel have shorter careers so the maintenance and reinvestment decisions can no longer be based only on the opinion of the network designers. Secondly the capital tied to the network is increasing and money can be saved through the proper timing of maintenance actions and reinvestments. The third reason is the compensation which the distribution system operator has to pay for disturbances in electric distribution. For these reasons the operators decided to begin a project to study the maintenance practices. They decided to compare their practices to the those of the other fields and to improve their own maintenance system to have savings in failure and investment costs. The project took two and a half years. The content of this dissertation was produced in this project. The main idea of the project was to model the deterioration of distribution components depending on their age. The deterioration of components accounts for the failure costs of the components. When the failure costs of the components are modelled, it is possible to find the optimal maintenance and reinvestment moments for the distribution components. The analysis concentrates not only on single distribution components but on component groups as well. The objective of this dissertation is to develop methodology for the maintenance of electric distribution systems. The scope of this thesis is restricted to the deterioration due to aging. The trimming of the corridors, major disturbances, regulations and capacity of the network are ruled out of the scope of the thesis. The strategy of the distribution system operator is developed from the condition and time based strategy to the reliability centred maintenance strategy. Further it is proved that the reliability and likely failure costs of the electric distribution network can be a basis for modelling maintenance and investment scheduling of the network. 1.2 Network asset management and reliability analysis According to Lakervi and Partanen (Lakervi, Partanen, 2008) the network asset can be divided into three categories: the operating functions, maintenance functions and building functions. These three main functions are presented in Figure 1.1. The main objective of network asset management is to minimize the total costs of the network in design period and at the same time maximize the productivity of the invested capital.

12 12 Figure 1.1 The main functions of network asset management (Lakervi, Partanen, 2008) In further analysis the main interest is in network renovations and construction of new network. According to Jukka Lassila the most important reasons for large-scale renovation are environmental factors, the age of the network, poor reliability, changes in the objectives of network owners and the development of the needs of the society or changes in legislation (Jukka Lassila, 2009). Figure 1.2 sums up the most essential reasons for network renovation.

13 13 Figure 1.2 Drivers for network renovation according to Jukka Lassila (Jukka Lassila, 2009) In this thesis, the focus is in network age and condition. However this is seldom the only reason for renovation. The tightened reliability requirements, major disturbances and regulation, lead to the new operating, maintenance and construction functions of the electric distribution network. In the near future main focus is on the environmental reasons why network operators are transforming the open overhead lines beside the roads or to the underground cabling network. When talking about network age and condition the main interest is in the reliability of the network. The design process is started by analyzing the basic structure of the network by using traditional network criteria. After the construction of the basic network alternative plans are created. The reliability analyses are then made for the network alternatives. (Orvassaari et al., 2005). The reliability analysis can be made for the network with a suitable tool. In (Pylvänäinen et al., 2009) the reliability based network analysis and life cycle cost functionality (later RNA/AM) is used for analyzing the reliability of the network. The RNA/AM utilization in network planning is presented in Figure 1.3.

14 14 Figure 1.3 RNA/AM utilization in network planning according to Pylvänäinen et al. (Pylvänäinen et al., 2009) Figure 1.4 presents the process description of the maintenance problem presented in this thesis. In the figure the capacitive, environmental and regulation reasons are not included in the problem analyzing. These can be called external reasons. The internal reasons are aging and deterioration of the network which is the scope of this thesis. The aging and deterioration of the network is analyzed by age depending failure rates. According to these rates three possibilities are analyzed: no action, maintenance action and reinvestment. Also the fourth possibility, fundamental improvement, is presented. Two different analyses are made: the other for single components and the other for component groups. For optimizing the dynamic programming (DP) models are presented. The main focus in the modeling are the poles, overhead lines and transformers. Figure 1.4 Problem solving of the maintenance modelling in dissertation

15 Maintenance in Finnish system operators To understand the maintenance practices and policies in electric distribution system operators, the representatives of the distribution system operators were interviewed. First ten Eastern-Finnish companies financing the study were interviewed. After that the other Finnish distribution companies were asked if they were interested in answering the question sheet by mail. There were seventeen interested companies. The inquiry sheet is presented in Appendix 1 (In Finnish). The comparison of maintenance practices between different distribution system operators is quite difficult. The practices are not commensurable. However the maintenance level of the operators is compared by giving points to the operator depending on the maintenance practices. The correlation of points and the average interruption time of the distribution system operators are also studied The distribution system operators analysed Three of the 27 companies distribute electricity in big cities. They have more than customers and the electricity transmission is more than 1000 GWh per year. Three companies represent very big provincial companies, which operate in the very large area and they have over customers each. The distributed energy is over 1000 GWh in a year. Six companies represent medium size city companies. They have customers and the electricity transmission is GWh in year. Five companies are medium size provincial companies. They have customers and the energy transmission is GWh per year. The rest 10 companies are small companies. They have less than customers and the electricity transmission is less than 250 GWh per year. (Korpijärvi, 2009) The classified number of customers and the energy transmission is presented in Appendix 2. The 20 kv cable length, and the 20 kv cable length per customer is presented in Appendix 2 as well Maintenance policy in the analysed distribution system operators The maintenance policy of the distribution companies was evaluated based on eleven maintenance practises. These practises are checking interval of 0,4 kv network, checking interval of 20 kv network, checking interval of transformer substations, checking interval of disconnectors, checking interval of remote-controlled disconnectors, trimming interval of vegetation, helicopter checking, thermographic survey and checking the rate of decay of wooden poles. Further it was asked whether the company has used long term investment planning and if it would use a maintenance program. The frequencies of the practices are presented in Appendix 2 The distribution system operators are nearly at the same level with regard to some practices. Most of the companies have maintenance program in use and most of the companies make long term investment planning. In one company the maintenance

16 16 program was used only for the documentation of the poles, but the faults and problems were repaired immediately when they were detected but they were not documented. In one company the maintenance program was not very advanced and manual cards and Excel files were still in use. In the companies where a maintenance program is used, the program is based on predefined activities carried out at regular intervals (scheduled maintenance). In all companies including the companies where the program is not used, the 0,4 kv and 20 kv installations are checked every 5 10 years. The most common interval is 6 years. The remote controlled disconnectors are checked mostly every 3 and 5 years. The vegetation maintenance involving trimming and removing trees is made every 3 6 years excluding one company. In 11 companies the network is checked with the helicopter. This is done in addition to field checking. The checking interval in the companies where helicopter checking was used, was two to eight years. In most companies (21 of 27 companies) the 20 / 0,4 kv transformer stations were checked by an infrared camera. In some companies where infrared camera checking was used, this was done only for critical transformer stations. The critical component, where aging has a powerful effect, is the pole for an overhead line. Because wood is the used material, rot is a normal phenomenon. The rot inspection is made in 23 of 27 companies. The interval of the checking varies. In one company the checking is only made for poles over 40 years. In most companies the checking interval for poles varies from checking every pole every 5 years to checking poles every 6 years but only older poles are checked. In 20 companies of 27 the long-term investment plan is used. When there is the investment plan it is possible to decide whether to make an investment or to carry out a smaller or larger overhauling or maintenance action instead. The most typical criteria for investment are the age, reliability and availability. In some cases the city construction office gives boundary condition for the investment. To study the level of the maintenance policy of the company, all the maintenance practices are evaluated with points 1 3. If the maintenance is at the best level, the company receives 3 points and when it is at the lowest level company receives 1 point. The points of maintenance activities and the total points for the companies are presented in Appendix 2. The difference of the points between the highest and the lowest maintenance level is not very big. This is because the maintenance level is partly regulated by safety norms. However the difference exists and the highest frequency is in the middle of the highest and lowest value The average interruption time and maintenance The impact of the maintenance policy was analyzed by the interruption time of the company. The interruption time is energy weighted and is reported to the Energy Market Authority of Finland (year 2008). The interruption time is given for unexpected faults in 1 70 kv network for one customer. The classified average interruption time is given in Appendix 2.

17 17 The hypothesis is that the maintenance policy of the distribution company has a strong effect on the interruption time of the company. The further hypothesis is that the high amount of cable network has an effect on the interruption time of the company so that a higher rate of cable network decreases the interruption time of the company. Also it was assumed that a modern network has lower interruption time than an old network. So the value ratio of the network to the replacement value of the network was studied. The cabling level of the 20 kv network and the current value of the network to the replacement value are presented in Appendix 2. The correlation matrix is presented in Table 1.1. The values are based on the statistics from (EMV, 2008) Table 1.1 The correlation matrix of the factors. We can notice a very high correlation (significant level under 0,01) in the relation of annual energy transmission and number of customers, which is obvious. Further there is a very high correlation between the current value of network and average time of interruption. The main reason is that the new conductor has a lower failure rate than the old conductor which has already deteriorated. We can also notice a correlation (significant level 0,01 0,05) between the total points of maintenance activities and average time of interruption. This correlation should be obvious but it is not so high as it could be assumed. Also a correlation between cabling level of 20 kv network and average time of interruption exists but it is lower than assumed. Furthermore there is a correlation between total points of maintenance activities and current value of the network. The reason for this is probably the fact that the distribution companies which invest more money in the network also maintain the network more intensively. Also the correlation between 1-70 kv conductor length (including overhead lines and underground cables) per customer and average time of interruption was studied. The correlation coefficient is 0,465 at the 0,05 significant level which is high enough to confirm the correlation between these two factors.

18 18 It is also interesting to see a correlation in two different groups - city operators (cabling level of 20 kv network over 15 %, 9 operators) and rural operators (cabling level under 15 %, 18 operators). The correlations are presented in Table 1.2 The energy and interruption data is according (EMV, 2008) Table 1.2 The correlation matrix for rural and city operators We can notice that the correlations between total points of maintenance activities and average time of interruption are in both groups lower if city and rural operators are analysed separately. Actually the correlation is very low for city operators. The correlation between current value of network and interruption time is high only for rural operators. The cabling level and interruption time has correlation only in city operators Conclusion of the Finnish distribution system operator analysis There are differences between maintenance actions in the distribution system operators analysed. The differences are between checking intervals and the use of checking methods. Of course the safety regulations set the minimum level to the maintenance policy.

19 19 There are meaningful correlations when all the electricity system operators are analysed together. The correlations are between the maintenance level and average time of interruption, between the maintenance level and the current value of the network, cabling level and the time of interruption and the cabling level and the maintenance level. When the operators are divided into two groups according to the cabling level, the meaningful correlations are between the network value and average interruption time for rural operators and current value of network and total points of maintenance activities for rural operators. There is also meaningful negative correlation between total points of maintenance activities and current value of network for city operators but this result is opposite to the result where city operators and rural operators are together. This result is not logical and could be coincidental. The biggest weakness of the study is the commensurability of the different maintenance parameters. It would have been possible to use weighting between different maintenance practises. However the value of the weighting parameters would have been questionable and so the weighting is not used. 1.4 The scope of the thesis The main objective of this thesis was to use deterioration curves of the distribution components as a base for maintaining and reinvesting the distribution components. This area is studied and further development is presented. The whole problem includes however not only deterioration but also other initial data. The initial data, calculation process and results are presented in Figure 1.5 The starting points, which are not included to the thesis are in the white boxes.

20 20 Figure 1.5 The maintenance problem Chapter 2 describes the maintenance problem, the objective function and the basis for calculating the objective function including the costs and failure rates of the electric distribution system. Chapter 3 describes the basic functions for solving maintenance and reinvestment time of the system. It describes the optimization problem and algorithms for problem solving in literature. The dynamic programming model for solving the optimization problem is described in chapter 4. The dynamic programming model includes four different kinds of algorithms presented in this chapter. Testing the presented optimization algorithms is carried out in chapter 5. Two different kinds of test networks are used. The first test network is imaginary and simple enough to test the models. The second test network is real to test the algorithms in real circumstances. The sensitivity analysis of the described models is presented in chapter 6. The maintenance software package is presented in chapter 7. The discussion and conclusion of the thesis are presented in chapters 8 and 9. The focus in this thesis is in aging and the deterioration of the network. So the environmental reasons are not included to the scope of this thesis.

21 Contributions In this thesis a methodology is created for scheduling the maintenance and reinvestment of the electric distribution components. The analyses include the network deterioration due to aging. For this scheduling four dynamic programming algorithms are created and tested. The four created models are so called three-state-model, three-state-plus-model, total-cost-model and annual-cost-model. The characteristic of these methods is described in this thesis. The experimental analysis is also made for comparing the results of the four presented dynamic programming models. Because it is economical for the distribution system operator to maintain or reinvest in components at the same time in one location, the component groups are studied in this thesis. A method to find the optimized time for maintenance action and reinvestment of component groups is created and tested. The environmental, capacitive and regulation reasons are not included to the analysis. However these point of view can be taken in account in weighting operations of component groups, which is presented in the thesis. To test the dynamic programming models in practice a maintenance software package is created. A short description of the maintenance software package is presented. The usability of the program would be however much better if the automatic data transmission between the network information system and the maintenance software package were developed. The maintenance strategies and policies of the distribution system operators are also analysed in this thesis. The study shows that the maintenance level of the operator has an effect on the interruption time of the operator but the effect is lower than was assumed. One reason can be the sample of the operators studied, the other reason can be the large scale interruptions caused by storms where the maintenance level and the modernity of the network have lower impact.

22 22 2 Maintenance problem 2.1 Problem description The main components in a distribution system include overhead lines (lines, poles and related items), cables (cables, junctions and related items), breakers, transformers, disconnectors, load disconnectors, fuses and bus bars (Bertling 2002). The further analysis concentrates on lines (including disconnectors) and transformers. The underground cables are not included to the test networks. The reason is that it was possible to collect failure rate data and the main interest of the distribution system operators is focused on these components. Furthermore there are established maintenance programs to transformer stations. There are four different kinds of maintenance impulses for distribution network. The environment, for example vegetation is the first impulse. The second impulse is deterioration or aging of the components which is the view of point in this dissertation. The third impulse is regulation. To achieve the desired return of investment according regulation the desired investments have to be done and interruption level has to be reached. The failures can also be random failures, which are not caused by environment or aging but may be impulse to maintenance action. (Endrenyi et al., 2001) According to Lina Bertling there are two major impacts on system reliability of overhead lines, trees and aging (wear) (Bertling 2002). Trees are included to the further analysis as location dependent initial values for failure rate data in the further model presented in this dissertation. The most interesting phenomenon is aging or deterioration because it gives impulse for maintenance activities of distribution equipment and also for the reinvestment of the equipment. The deterioration is modelled in the further analysis using age dependent failure rate curves. These failure rates can be found in literature. However the real failure rates depend on the producer of the component and on the environment where the component is used. Thus the used failure rate data gives only one possible basis for the analysis. Because the deterioration curves of the distribution components are used, the outage cost level of the component can be found. It is possible to decrease this cost level by maintenance or reinvestment action of the component. So it is possible to find the optimal moment for maintenance action or reinvestment for the distribution components. It is economical for the distribution system operator to maintain not only single components but whole component groups. This matter is analysed as well. There are different strategies for the design period. The first possibility is to do nothing, when the costs increase according to aging for the whole design period. The second possibility is to make a component reinvestment without maintenance and the third possibility is to have first maintenance and then reinvestment. There are still other strategies. The maintenance can be carried out several times during design period and also the reinvestment can be made twice. The objective of the chosen strategy is the high availability of the system or total cost (including investment, maintenance and failure costs) minimization during the design period.

23 23 The analysed distribution network consists of 20 kv cables and overhead lines and 20/0,4 kv transformers. Because the failure costs of 0,4 kv network are not in the level to carry out reinvestment or capital overhaul, they are not included to the analysis. A typical analysed network is presented in Figure 2.1 Industry Household Services Public Farming 8 Disconnector FOREST ROAD 7 Disconnector 5 3 Remotecontrolled disconnector 110/20 kv 1 Disconnector 2 Disconnector Disconnector 6 FIELD 4 8 Disconnector 110/20 kv 1 3 Disconnector 2 Remotecontrolled disconnector 5 7 Disconnector Disconnector Disconnector 4 Disconnector 6 Figure 2.1 Example of analysed network

24 Failure modelling The reliability of the system is calculated as the sum of individual failure rates that affect the reliability of the system (Janjic, Popovic, 2007) The transmission and distribution system is composed of different components such as transmission lines, transformers, circuit breakers and transmission feeders. Each component has a failure rate. The failure rates of the component rise over time until maintenance is performed, which lowers the failure rate (Dai, Christie, 1994) The other way of decreasing the failure rate is reinvestment which decreases the failure rate to the initial value. According to (Sittithumwat et al., 2004) ( Chow, Taylor, 1995) the distribution outage causes can be divided into the following categories: equipment 14 %, trees 19 %, animals 18 %, lightning 9 % and others 40 %. In (Horton et al., 1991) the component failures accounted for 15 % of the total permanent outages. For the remaining 85 % of the outages, 75 % were due to external factors such as lightning strikes, trees, car-pole accidents and third party contacts and 10 % were attributed to substation or transmission outages. According to the outage statistics of Finnish Energy Industry the environmental reasons for interruptions account for 76 % of the outages, technical problems account for 10 % of the outages and others 14 % of the outages. This result is for open conductors without planned interruptions. For underground cables the share of natural reasons is 14% of the interruptions, the share of technical reasons 46 % and others 40 %. (Energy Industry, 2010) Sensitivity studies indicate that the cables have a significant impact on the system reliability and are therefore the critical component. The causes of failures which have significant impact on cables are a) damage 16 %; b) personnel 12 %; c) material and method 59 %. To material and method the main contributions to this failure are a) fabric and material 14 %; b) lack of maintenance 5 %; c) wrong method or instruction 15 % These can be divided into two categories deterioration and non-deterioration (random). (Bertling et al., 2001). The age dependent deterioration can be divided in to different kind of performance. In (Komonen, 2005) there are six types of patterns representing most kinds of aging and deterioration situations. These curves represent different failure models used in air traffic and ships. K.Harker (Harker, 1998) has the same figures presented in Figure 2.2

25 25 Figure 2.2 Failure models (failure rates) in air traffic and ships (Komonen, 2005) The first curve is the so called bathtub curve. It begins with a high failure rate followed by a constant failure rate. In the end of the bathtub curve the failure rate increases. The second curve shows constant or slowly increasing failure probability, ending with a slowly or exponentially growing failure rate. This model represents the classical failure rate model but it is valid only for certain types of simple equipment, and for some complex items with dominant failure modes. (Moubray, 1997). The third curve shows steadily increasing failure probability, but there is no identifiable wear-out age. The fourth curve represents the case when the beginning of the failure rate is low but increases rapidly to the constant level. The fifth curve represents the constant failure rate at all ages. The last pattern represents slowly increasing failure rate when the beginning of the curve is exponentially decreasing. It is debatable if it is possible to use the same failure models in electric distribution as is used in air traffic. The reason is that electric distribution is different from air traffic and the risks in air traffic are very high. The components in air industry are replaced well before aging. There are many stresses which occur during the service life of the component. They are associated with fatigue, corrosion, oxidation and evaporation (Moubray, 1997). The point at which the failure occurs is not very predictable. It can be said that there is useful life of the item, where the failure rate is very low and then a wear-out zone where the failure rate grows rapidly. The question is if it is possible to lengthen the useful life by maintenance or predict the moment when the failures occurs. Richard E. Brown (Brown, 2004) suggests that the failure rate of the power distribution component depends on the inspection outcome. The components are divided into three groups according to inspection: a) the best inspection outcome, b) the average inspection outcome and c) the worst inspection outcome. The failure rate per year varies between failure rate 0,001 for case (a) up to 1,0 for case (c) for the studied primary

26 26 trunk cable. For the other components studied the variation between the best and worst inspection level is not so high Maintenance activities Alexandar D. Janjic and Dragan S. Popovic present (Janjic, Popovic, 2007) that the failure rate of the component depends on the maintenance activities of the distribution company. They divide the preventive actions to a) inspection and minor repairs to solve minor damages, b) larger overhauls to solve major damages and c) trimming to solve the influence of vegetation. For overhead conductors the inspection means visiting the conductor along a corridor in order to check correct condition of insulation, lines, joints, sag control, determining necessary trimming, noticing all adjacent installations, thermo vision recording, grounding measurements, inspection and cleaning of insulators and climbing the poles for the purpose of control. The minor repairs mean straightening poles, replacing insulation, tightening conductors, replacing voltage arresters and replacing line disconnectors. Trimming means partial or total trimming of the feeder corridor. In addition to minor repairs also major repairs can be carried out for overhead lines. For example backing the pole is this kind of major repair. It also has to be determined if it is economical to make a reinvestment of the overhead conductor to the existing location or to a new location. Richard E Brown presents the maintenance for transformers to decrease the failure rate. For that purpose the inspections are used. The items to be inspected are the condition of internal solid insulation, oil type, condition of core, condition of tank, cooling system, tap changer, the inspection of the noise level, core and winding losses and oil analysis (Brown R., 2004). Endrenyi et al. divide the maintenance operations to minor maintenance, minor overhaul and major overhaul (Endrenyi et al., 2001). Minor maintenance means maintenance of limited effort and effect. Minor overhaul means an overhaul of substantial effort involving only a limited number of parts, whose effect is a considerable improvement of the equipment s condition. Major overhaul means an overhaul of extensive effort and duration which involves most or all parts of the equipment Maintenance strategies There are two main approaches in maintenance strategies: corrective approach and preventive maintenance.(nakagawa, 2005),(Hilber et al., 2007). Corrective maintenance (CM) can also be called run to failure and it is the most primitive maintenance strategy. This strategy is based on restoring operation by fixing or replacing the component in the case of failure and does not include any additional maintenance activities.(lehtonen, 2006),(Janjic, Popovic, 2007) Preventive maintenance (PM) can

27 27 further be divided to time-based maintenance (TBM) and condition-based maintenance (CBM) (Li, Brown, 2004) TBM is based on regular and scheduled intervals and on the service history of the component. CBM is based on the condition and state of equipment and maintenance activity is formulated when the condition falls below acceptable standard. Reliability-centered maintenance (RCM) is an improvement over TBM and CBM (Li, Brown, 2004) In RCM the maintenance is activated when the theoretical reliability of the component falls below standard. The overhaul or reinvestment can be activated when the failure costs rise over the maintenance or investment costs. The comparison between the maintenance action and reinvestment as well as the timing of the operations is possible using optimization algorithms. Lina Bertling et al. define reliability centered maintenance as a systematic method for achieving a cost-effective preventive maintenance strategy by balancing between corrective and preventive maintenance. (Bertling et al., 2003) In (Lehtonen, 2006) the role of RCM is to balance the spending in maintenance activities with their effect on the system performance. A general RCM process could include the following stages (Endrenyi et al, 2001) - listing of critical sub-components and their functions - failure mode and effect analysis for each chosen sub-component, determination of failure history and calculation of mean time between failures - categorization of failure effects and determination of possible maintenance tasks - maintenance task assignment - program evaluation, including cost analysis In Sweden, the RCM process has been presented as follows (Bertling et al., 2001) - choosing and defining the system to be analyzed - defining and collecting necessary input data - performing a reliability analysis on the chosen system - identifying the critical components - identifying the benefit of maintenance on the critical components from the knowledge of either their functions (for example transfer of energy), their failure modes (for example short circuit), their failure events ( for example insulation failure) or their failure causes ( for example matrial and method) (Yatomi et al., 2004) present Life-Cycle Maintenance (LCM) as a solution of preventive maintenance strategy, the. In this strategy the risk and maintenance costs of the plant are minimized during the life time of the plant. Risk Based Maintenance (RBM) is included in the LCM to assess the risk of the components in the plant. According to (Harker, 1998) there are still two more maintenance strategies apart from corrective and preventive maintenance. These two strategies are opportunity maintenance and statutory maintenance. Opportunity maintenance is carried out when a higher priority item of equipment is out of service. For example, generator-circuitbreaker maintenance is carried out only when the generator is out of service. Statutory maintenance is carried out to facilitate statutory timescales and requirements usually associated with health and safety.

28 28 Key areas within the maintenance management problems are a) determining the time intervals or the equipment age for optimal maintenance, b) determining the frequency of inspections and condition based optimal maintenance, c) determining the optimal resources to meet maintenance requirements and d) finding the economic life cycle of an equipment studying the repair versus replace problem. (Marquez, Hequedas, 2002) The first step in drawing up an effective maintenance plan is to decide which parts of the system to maintain and how to perform the maintenance activities. To achieve this a sensitivity analysis is performed for the system with the aim of identifying the critical components, i.e. the components which have the largest influence on the system reliability. (Bertling et al., 2001) The life of power-system equipment is long, typically years for high-voltage equipment and years for protection and control equipment (Harker, 1998). In this life-cycle many maintenance actions can be activated: - periodic exercising of equipment - visual inspections - cleaning, dusting and painting - lubrication and periodic replacement of parts - monitoring and examination of interrupting and insulating mediums - equipment performance tests - removal of foliage to maintain clearances In addition to maintenance activities presented by Janjic and Popovic (Janjic, Popovic, 2007) and Harker, the reinvestment of the component is added to the activities modelled in this dissertation. Maintenance activities are carried out according to the following periodicity (Harker, 1998) - regular intervals according recommendations and experience - increased maintenance of older equipment - statutory maintenance activities - opportunity maintenance - targeted sampling of a population of equipment - no maintenance As to overhead lines and transformers, the preventive maintenance actions can be used. This means periodic checks and minor or larger overhauls of the components Maintenance directions and cost optimization In a maintenance model there are four possible directions: 1) maintenance costs minimization, 2) reliability maximization, 3) overall costs minimization and 4) overall risk minimization. (Janic, Popovic, 2007) The maintenance cost minimization doesn t take into account the straight failure costs and outage costs caused by the low maintenance level. So this strategy does not give the most economical life-time cost for

29 29 the system. This strategy is reasonable only if maintenance action doesn t decrease the failure level of the system. In this approach reliability is defined as a limit, or minimal requested level. Reliability maximization is not an economical solution. It is possible to increase the reliability level by investing more in maintenance, clearance of corridors and new components. However the marginal benefit of maintenance action decreases with a higher level of maintenance. Zhang et al. present that the security index of a traditional power system no more exists independently but together with the economic point of view. (Zhang et al., 2005) In the reliability maximization the effectiveness of maintenance can be modelled by using a weighted average system reliability index (WASRI) (Li, Brown, 2004). The WASRI index is modelled by using an index of system average interruption, an index of average interruption duration and an average temporary interruption index. If costs are not included to the examination of WASRI index the strategy is straight reliability maximization. (2.1) where WASRI SAIFI SAIDI MAIFI ω i system average reliability index system average interruption frequency index system average interruption duration index momentary event average interruption frequency weighting factor Using effectiveness index it is possible to achieve the most effective operations and maintenance tasks for system reliability. The goal is to minimize the WASRI index. The cost-effectiveness of minimizing the WASRI index can be taken account into by calculating relation (2.2). (2.2) where E ΔWASRI C cost-effectiveness of a maintenance task is the change of WASRI index is the cost associated with the maintenance task. In the model presented in this thesis SAIFI is the sum of the failure rates of all components in one feeder. The SAIDI index is found out by calculating the average failure length of the customers per one transformer area. The MAIFI index depends on the environment of the conductor and is the function of the number of re-closings. Because MAIFI doesn t depend on deterioration it is not included in the presented model (automatic reclosing is not included). In the fundamental improvement of the

Power products and systems. Intelligent solutions for power distribution Zone concept

Power products and systems. Intelligent solutions for power distribution Zone concept Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,

More information

IMPACT OF RELIABILITY OF SUPPLY ON LONG-TERM DEVELOPMENT APPROACHES TO ELECTRICITY DISTRIBUTION NETWORKS

IMPACT OF RELIABILITY OF SUPPLY ON LONG-TERM DEVELOPMENT APPROACHES TO ELECTRICITY DISTRIBUTION NETWORKS Juha Haakana IMPACT OF RELIABILITY OF SUPPLY ON LONG-TERM DEVELOPMENT APPROACHES TO ELECTRICITY DISTRIBUTION NETWORKS Thesis for the degree of Doctor of Science (Technology) to be presented with due permission

More information

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse How the National Grid System Operates Chris Gorman Lead Account Executive Syracuse 2 Parts of the Electric System Parts of the Electric System 1. Generating Station: Produces Electricity. 2. Transmission

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

Comparison between Gas- and Air Insulated Network Concepts with the Life Cycle Cost Method

Comparison between Gas- and Air Insulated Network Concepts with the Life Cycle Cost Method Comparison between Gas- and Air Insulated Network Concepts with the Life Cycle Cost Method Ingo Jeromin, Gerd Balzer, Technische Universität Darmstadt, Jürgen Backes, Richard Huber, EnBW Regional AG Stuttgart

More information

Reliability centered asset management tool

Reliability centered asset management tool Reliability centered asset management tool The development of RACalc Claes Böös and Richard Göransson Degree project in Electromagnetic Engineering Second Level, 30.0 HEC Stockholm, Sweden 2009 XR-EE-ETK

More information

BL20A0501 Electricity distribution technology. Introduction Jarmo Partanen

BL20A0501 Electricity distribution technology. Introduction Jarmo Partanen BL20A0501 Electricity distribution technology Introduction Jarmo Partanen Introduction to ED Prof. Jarmo Partanen, D.Sc Jukka Lassila Topics of lectures Introduction to Electricity Distribution, 27.10

More information

COMPARISON OF ELECTRICITY GENERATION COSTS

COMPARISON OF ELECTRICITY GENERATION COSTS Tarjanne Risto, Kivistö Aija COMPARISON OF ELECTRICITY GENERATION COSTS LAPPEENRANNAN TEKNILLINEN YLIOPISTO LAPPEENRANTA UNIVERSITY OF TECHNOLOGY TEKNILLINEN TIEDEKUNTA ENERGIA- JA YMPÄRISTÖTEKNIIKAN OSASTO

More information

Risk-Based Resource Allocation for Distribution System Maintenance

Risk-Based Resource Allocation for Distribution System Maintenance PSERC Risk-Based Resource Allocation for Distribution System Maintenance Final Project Report Power Systems Engineering Research Center A National Science Foundation Industry/University Cooperative Research

More information

6545(Print), ISSN 0976 6553(Online) Volume 4, Issue 2, March April (2013), IAEME & TECHNOLOGY (IJEET)

6545(Print), ISSN 0976 6553(Online) Volume 4, Issue 2, March April (2013), IAEME & TECHNOLOGY (IJEET) INTERNATIONAL International Journal of JOURNAL Electrical Engineering OF ELECTRICAL and Technology (IJEET), ENGINEERING ISSN 0976 & TECHNOLOGY (IJEET) ISSN 0976 6545(Print) ISSN 0976 6553(Online) Volume

More information

Electric System Performance Review Trustees Briefing. April 2013

Electric System Performance Review Trustees Briefing. April 2013 Electric System Performance Review Trustees Briefing April 2013 Electric Reliability Indices All Metrics Continue to Perform Within Historical Range Reliability Index 2012 Trend to 5-Year Avg. LIPA MSA

More information

When power interruptions happen.

When power interruptions happen. When power interruptions happen. We know it s never a good time to have your power go out, so we work all year pruning trees and investing in our system to cut down on problems before they start. Outage

More information

DISTRIBUTION OPERATIONS AND MAINTENANCE

DISTRIBUTION OPERATIONS AND MAINTENANCE EB-00-00 Filed: 00 Aug Page of DISTRIBUTION OPERATIONS AND MAINTENANCE PREVENTIVE MAINTENANCE Preventive Maintenance is intended to maintain or improve customer service reliability, extend equipment life

More information

How To Improve A Maintenance Improvement Project At The Utility Interelectra

How To Improve A Maintenance Improvement Project At The Utility Interelectra Designing and implementing a maintenance management system with an expert support system: Methodology, implementation, expert IT-system, achieved cost reductions Peter Hafkamp KEMA Transmission and Distribution

More information

SIEMENS Transmission and Distribution

SIEMENS Transmission and Distribution TITLE Long Term Maintenance and Care for S36A E. C. Wright 02/09/04 This document is to be used in conjunction with Installation, Operation and Maintenance Schedule IOMS 635. Its aim is to provide guidance

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

Optimization of Asset Management in High Voltage Substation Based on Equipment Monitoring and Power System Operation

Optimization of Asset Management in High Voltage Substation Based on Equipment Monitoring and Power System Operation Optimization of Asset Management in High Voltage Substation Based on Monitoring and Power System Operation Yotaro Suzui, Hiroi Kojima, Naoi Hayaawa, Fumihiro Endo, Hitoshi Oubo Nagoya University Furo-cho,

More information

Governor s Two-Storm Panel: Distribution Infrastructure Hardening Options and Recommendations

Governor s Two-Storm Panel: Distribution Infrastructure Hardening Options and Recommendations Governor s Two-Storm Panel: Distribution Infrastructure Hardening Options and Recommendations Dana Louth, CL&P VP - Infrastructure Hardening December 14, 2011 0 Topics for today s presentation Review of

More information

Low Voltage Asset Management (LVAM) The key to reliable and safe electricity

Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Archie Jaykaran Distribution Division Eskom SA Contents Change drivers Scope, Approach, Project status LV Planning and Design

More information

ANN Based Fault Classifier and Fault Locator for Double Circuit Transmission Line

ANN Based Fault Classifier and Fault Locator for Double Circuit Transmission Line International Journal of Computer Sciences and Engineering Open Access Research Paper Volume-4, Special Issue-2, April 2016 E-ISSN: 2347-2693 ANN Based Fault Classifier and Fault Locator for Double Circuit

More information

Relion. Power system protection and automation reference Extending substation life cycle with IEC 61850

Relion. Power system protection and automation reference Extending substation life cycle with IEC 61850 Relion Power system protection and automation reference Extending substation life cycle with IEC 61850 Extending substation life cycle with IEC 61850 A step-by-step power system retrofit approach for optimizing

More information

Life Data Analysis using the Weibull distribution

Life Data Analysis using the Weibull distribution RELIABILITY ENGINEERING Life Data Analysis using the Weibull distribution PLOT Seminar October 2008 Ing. Ronald Schop Weibull: Reliability Engineering www.weibull.nl Content Why Reliability Weibull Statistics

More information

Asset management for power cable systems - Total cost optimization based on the Application of diagnostics -

Asset management for power cable systems - Total cost optimization based on the Application of diagnostics - 21, rue d Artois, F-75008 PARIS B1_212_2012 CIGRE 2012 http : //www.cigre.org Asset management for power cable systems - Total cost optimization based on the Application of diagnostics - T. NISHIKAWA Y.

More information

On-line PD Monitoring Makes Good Business Sense

On-line PD Monitoring Makes Good Business Sense On-line PD Monitoring Makes Good Business Sense An essential tool for asset managers to ensure reliable operation, improve maintenance efficiency and to extend the life of their electrical assets. Executive

More information

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI 1 Vision 2050 An Asset Management Strategy Jaclyn Cantler Manager, Transmission Planning, PHI 2 Agenda Case for Change About Vision 2050 Status Closing System Design Cybersecurity Interface with distributed/dispersed

More information

2. OUR NETWORK 4.42 74.74 16 POWERPOLES 2 POWERPOLES. Our distribution network comprises: For every 1 kilometre of powerlines: Essential Energy has

2. OUR NETWORK 4.42 74.74 16 POWERPOLES 2 POWERPOLES. Our distribution network comprises: For every 1 kilometre of powerlines: Essential Energy has 2. OUR NETWORK Essential Energy s network is unique in terms of the geographic area it covers, the terrain it traverses, the vegetation that grows within it and the diversity of weather that passes over

More information

Overhead lines Asset Management in the Belgian network. S. GERMAIN K. VAN DAM B. RISSE JF. GOFFINET Elia Belgium

Overhead lines Asset Management in the Belgian network. S. GERMAIN K. VAN DAM B. RISSE JF. GOFFINET Elia Belgium 21, rue d Artois, F-75008 PARIS B2-208 CIGRE 2012 http : //www.cigre.org Overhead lines Asset Management in the Belgian network. S. GERMAIN K. VAN DAM B. RISSE JF. GOFFINET Elia Belgium SUMMARY The Belgian

More information

Asset Management Strategy

Asset Management Strategy Asset Management Strategy ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office, Adelaide, South Australia 5000 Tel: (08) 8404 7966

More information

Improving Power Quality Through Distribution Design Improvements

Improving Power Quality Through Distribution Design Improvements Improving Power Quality Through Distribution Design Improvements Tom Short, EPRI PEAC, tshort@epri-peac.com Lee Taylor, Duke Power, lstaylor@duke-energy.com The three most-significant power quality concerns

More information

DISTRIBUTION RELIABILITY USING RECLOSERS AND SECTIONALISERS

DISTRIBUTION RELIABILITY USING RECLOSERS AND SECTIONALISERS ABB DISTIBUTION ELIABILITY USING ECLOSES AND SECTIONALISES obert E. Goodin Chief Engineer ABB Inc. Lake Mary, FL Timothy S. Fahey, PE Sr. Application Engineer ABB Inc. aleigh, NC Andrew Hanson, PE Executive

More information

Utilization of Automatic Meter Management in Smart Grid Development

Utilization of Automatic Meter Management in Smart Grid Development Utilization of Automatic Meter Management in Smart Grid Development Elenia Verkko Oy Ville Sihvola Head of Marketing and Sales ville.sihvola@elenia.fi Content of the presentation 1. What is Elenia Verkko

More information

ICM Project Station Infrastructure and Equipment

ICM Project Station Infrastructure and Equipment EB 0 00 Schedule B. ( pages) ICM Project Station Infrastructure and Equipment (THESL) EB 0 00 Schedule B. I EXECUTIVE SUMMARY 0. Project Description Many Municipal Substations (MS) located outside of downtown

More information

Enhance Power Equipment Reliability with Predictive Maintenance Technologies

Enhance Power Equipment Reliability with Predictive Maintenance Technologies Enhance Power Equipment Reliability with Predictive Maintenance Technologies November 2012/1910DB1208 by S. Frank Waterer, Electrical Engineerinig, Fellow Schneider Electric USA, Inc. Make the most of

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

control manual Optimal maintenance decisions for asset managers by andrew k.s. jardine and neil montgomery 44 Industrial Engineer

control manual Optimal maintenance decisions for asset managers by andrew k.s. jardine and neil montgomery 44 Industrial Engineer control manual Optimal maintenance decisions for asset managers by andrew k.s. jardine and neil montgomery 44 Industrial Engineer Most of us are familiar with the effort involved in purchasing a new car.

More information

SF 6 Gas Insulated Switchgear Type SDF for 170 kv

SF 6 Gas Insulated Switchgear Type SDF for 170 kv Three Phase Encapsulated Type SF 6 Gas Insulated Switchgear Type SDF for 170 kv 06B1-E-0001 With Trustworthy Technology, Structure Fuji Electric as a manufacturer of comprehensive substation equipment

More information

ECE 586b Course Project Report. Auto-Reclosing

ECE 586b Course Project Report. Auto-Reclosing ECE 586b Course Project Report Auto-Reclosing Srichand Injeti May 5, 2008 Department Of Electrical and computer Engineering University Of Western Ontario, London Ontario Table of contents 1. Introduction...1

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES C. Schwaegerl*, M.H.J. Bollen, K. Karoui #, A. Yagmur + *Siemens AG, # Tractebel STRI AB

More information

Vegetation Management Frequently Asked Questions

Vegetation Management Frequently Asked Questions Vegetation Management Frequently Asked Questions Q. Why does AEP Ohio clear vegetation away from power lines? A. AEP Ohio s goal is to provide safe, dependable electric service to its customers. Line clearance

More information

Treasure Valley Electric Plan - Community Advisory Committee

Treasure Valley Electric Plan - Community Advisory Committee Treasure Valley Electric Plan - Community Advisory Committee What is a transmission line and why are they necessary? A transmission line is used to conduct electricity between two points. Without high

More information

Washington DC Power Sector Overview

Washington DC Power Sector Overview Washington DC Power Sector Overview Kenneth (Ken) Glick Public Service Commission Of the District of Columbia December 8, 2014 DC Power Market Area - Summary Single electric utility that has divested itself

More information

IESO Supply Deliverability Guidelines

IESO Supply Deliverability Guidelines PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents

More information

Distribution Automation / Smart Grid. Kevin Whitten

Distribution Automation / Smart Grid. Kevin Whitten Distribution Automation / Smart Grid Kevin Whitten Main Overview Distribution Reliability Distribution Automation Smart Grid Distribution Reliability Distribution Reliability - Overview Introduction to

More information

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15-

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15- Th~NALZZ~ Exhibit STATE OF NEW HAMPSHIRE t~~eeee BEFORE THE FROM FILE PUBLIC UTILITIES COMMISSIO~t~ Liberty Utilities (Granite State Electric) Corp. dibla Liberty Utilities Calendar Year 2014 Reliability

More information

Considering UNDERGROUND. tampaelectric.com

Considering UNDERGROUND. tampaelectric.com Considering UNDERGROUND Electric Service? tampaelectric.com INTRODUCTION The majority of Tampa Electric s customers receive their electric service through overhead construction, which is the standard type

More information

Evaluation of Data Submitted in APPA s 2013 Distribution System Reliability & Operations Survey

Evaluation of Data Submitted in APPA s 2013 Distribution System Reliability & Operations Survey Evaluation of Data Submitted in APPA s 2013 Distribution System Reliability & Operations Survey NOTE APPA staff has used a high degree of care in developing this report. However, APPA does not accept any

More information

PA PUC AERS & Metropolitan Edison Company Site Visit

PA PUC AERS & Metropolitan Edison Company Site Visit PA PUC AERS & Metropolitan Edison Company Site Visit October 26, 2010 Scott Lowry Director-Operation Services, Met-Ed Andrew Zulkosky Manager-Engineering, Met-Ed Curt Christenson Manager-York Customer

More information

Underground vs. Overhead Transmission and Distribution

Underground vs. Overhead Transmission and Distribution electric power engineering Underground vs. Overhead Transmission and Distribution Your Power System Specialists June 9, 2009 1 NATIONAL TRENDS Municipalities have passed laws requiring new distribution

More information

Attachment 20.64 SA Power Networks: Asset Management Plan 3.2.01 Substation Transformers 2014 to 2025

Attachment 20.64 SA Power Networks: Asset Management Plan 3.2.01 Substation Transformers 2014 to 2025 Attachment 20.64 SA Power Networks: Asset Management Plan 3.2.01 Substation Transformers 2014 to 2025 ASSET MANAGEMENT PLAN 3.2.01 SUBSTATION TRANSFORMERS 2014 TO 2025 Published: October 2014 SA Power

More information

Transmission Network Performance Report

Transmission Network Performance Report Transmission performance report cover.qxp 06/25/2008 11:50 AM Page 1 Transmission Network Performance Report 25 Research Drive Westborough, MA 01582 www.nationalgrid.com CD4369 (6/08) Fiscal Year 2008

More information

Q. Why does OG&E clear vegetation away from power lines? A. Trees that grow into power lines can cause problems in multiple ways:

Q. Why does OG&E clear vegetation away from power lines? A. Trees that grow into power lines can cause problems in multiple ways: Q. Why does OG&E clear vegetation away from power lines? A. Trees that grow into power lines can cause problems in multiple ways: Outages Tree limbs contacting power lines are one of the most common causes

More information

2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT

2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT 2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT Contents Overview... 3 1.0 Electric System Reliability... 4 1.1 Annual Reliability Data with Utility Comparisons... 4

More information

Advanced Distribution Grid Management for Smart Cities

Advanced Distribution Grid Management for Smart Cities Smart Grid Solutions Advanced Distribution Grid Management for Smart Cities Kevin Corcoran, Director Product Line Management IEEE SmartGridComm 2015 Miami, FL Bridging Smart Cities & Smart Grids Common

More information

Public Utility District #1 of Jefferson County Vegetation Clearance Policy And Specifications

Public Utility District #1 of Jefferson County Vegetation Clearance Policy And Specifications Jefferson County PUD Company Policy Policy No. Date: Public Utility District #1 of Jefferson County Vegetation Clearance Policy And Specifications Purpose The purpose of this policy statement and these

More information

Principles of Distribution charging:

Principles of Distribution charging: Principles of Distribution charging: Electricity networks Introduction A three-stage approach involves the following steps: 1. The analysis and quantification of costs. The cost concept that is relevant

More information

How To Develop A Smart Grid In Elenia

How To Develop A Smart Grid In Elenia GEODE Autumn Seminar in Brighton 12 th of November Utilization of Automatic Meter Management in Smart Grid Development Ville Sihvola Head of Marketing and Sales Elenia Oy Elenia Oy Turnover 220 M Employees

More information

Brochure Introducing HVDC

Brochure Introducing HVDC Brochure Introducing HVDC ABB and HVDC The world s first commercial high-voltage direct current (HVDC) link, situated between the Swedish mainland and the island Gotland, was delivered by ABB already in

More information

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com Agenda do Mini-Curso Sérgio Yoshio Fujii sergio.fujii@areva-td.com Ethan Boardman ethan.boardman@areva-td.com Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

PPL Electric Utilities Summer Readiness Overview June 2016

PPL Electric Utilities Summer Readiness Overview June 2016 SUMMARY PPL Electric Utilities Summer Readiness Overview June 2016 For PPL Electric Utilities (PPL Electric), summer readiness means the company must respond effectively to summer storms as well as provide

More information

New Residential Service Requiring Construction

New Residential Service Requiring Construction New Residential Service Requiring Construction What you should know about having service connected to your new home visit us at www.flintenergies.com FEMC 593 R2/12 All references from NEC 2011 New Residential

More information

The calm after the storm

The calm after the storm The calm after the storm Human decision support in storm outage recovery Rafael Ochoa, Amitava Sen It s a fact of life that interruptions in an electrical distribution utility happen. Although they can

More information

Integration of Distributed Generation in the Power System. IEEE Press Series on Power Engineering

Integration of Distributed Generation in the Power System. IEEE Press Series on Power Engineering Brochure More information from http://www.researchandmarkets.com/reports/2171489/ Integration of Distributed Generation in the Power System. IEEE Press Series on Power Engineering Description: A forward

More information

Cost-effective Distribution Reliability Improvement Using Predictive Models

Cost-effective Distribution Reliability Improvement Using Predictive Models Cost-effective Distribution Reliability Improvement Using Predictive Models Dr. Julio Romero Agüero Sr. Director, Distribution Quanta Technology Raleigh, NC julio@quanta-technology.com 919-334-3039 Table

More information

EFFECTS OF BENCHMARKING OF ELECTRICITY DISTRIBUTION COMPANIES IN NORDIC COUNTRIES COMPARISON BETWEEN DIFFERENT BENCHMARKING METHODS

EFFECTS OF BENCHMARKING OF ELECTRICITY DISTRIBUTION COMPANIES IN NORDIC COUNTRIES COMPARISON BETWEEN DIFFERENT BENCHMARKING METHODS EFFECTS OF BENCHMARKING OF ELECTRICITY DISTRIBUTION COMPANIES IN NORDIC COUNTRIES COMPARISON BETWEEN DIFFERENT BENCHMARKING METHODS Honkapuro Samuli 1, Lassila Jukka, Viljainen Satu, Tahvanainen Kaisa,

More information

The electrical energy produced at the gen

The electrical energy produced at the gen 300 300 Principles of Power System CHAPTER CHAPTER 12 Distribution Systems General 12.1 Distribution System 12.2 Classification of Distribution Systems 12.3 A.C. Distribution 12.4 D.C. Distribution 12.5

More information

Litigation Services & Information

Litigation Services & Information Litigation Services & Information Laurence "Lo" Lehman, P.E. Lehman Engineering Company Lehman Engineering has been providing engineering, design, and consulting services for electrical power systems to

More information

Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches

Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches Downtime Is Not An Option The industrial uninterruptible power supply (UPS) is the foundation of your

More information

MAINTENANCE STRATEGIES FOR DISTRIBUTION NETWORKS

MAINTENANCE STRATEGIES FOR DISTRIBUTION NETWORKS MAINTENANCE STRATEGIES FOR DISTRIBUTION NETWORKS M. Marketz 1*, J. Polster 1, M. Muhr 2 1 KELAG - Kärntner Elektrizitäts-Aktiengesellschaft, Klagenfurt, Austria 2 University of Technology, Institute of

More information

Asset Management Plan

Asset Management Plan 2014 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2014-2024 Network Asset Management Plan (AMP). The 2014 AMP follows on from the

More information

Airline Fleet Maintenance: Trade-off Analysis of Alternate Aircraft Maintenance Approaches

Airline Fleet Maintenance: Trade-off Analysis of Alternate Aircraft Maintenance Approaches 2003 2004 2005 2006 2007 2008 2009 2010 Cost per Flight Hour (USD) Airline Fleet Maintenance: Trade-off Analysis of Alternate Aircraft Maintenance Approaches Mike Dupuy, Dan Wesely, Cody Jenkins Abstract

More information

Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada

Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada DIRECT TESTIMONY OF GERRY SHEERIN, P. ENG ON BEHALF OF PIEDMONT ENVIRONMENTAL COUNCIL BEFORE THE STATE CORPORATION COMMISSION OF VIRGINIA CASE NOS. PUE-00-0001 AND PUE-00-000 1 1 1 1 1 1 1 1 1 Q: PLEASE

More information

Implementing Low-Cost Distribution Automation Programs

Implementing Low-Cost Distribution Automation Programs Implementing Low-Cost Distribution Automation Programs By: Jai Belagur, P.E. Contact: Jai Belagur Power System Engineering, Inc. 1532 West Broadway, Suite 100, Madison, WI 53713 Phone: 608-268-3544 E-mail:

More information

Reduction of Power Losses Using Phase Load Balancing Method in Power Networks

Reduction of Power Losses Using Phase Load Balancing Method in Power Networks Proceedings of the World Congress on Engineering and Computer Science 009 Vol I WCECS 009, October 0-, 009, San Francisco, USA eduction of Power Losses Using Phase Load Balancing Method in Power Networks

More information

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Title MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Duration 5 days Training Date MV, HV and EHV Switchgear Testing & Commissioning 5 20 24 Apr $3,750 Dubai, UAE In any of the 5 star

More information

2016 2020 Price Reset. Appendix H Service target performance incentive scheme

2016 2020 Price Reset. Appendix H Service target performance incentive scheme Appendix H Service target performance incentive scheme April 2015 Table of contents 1 SERVICE TARGET PERFORMANCE INCENTIVE SCHEME... 3 1.1 Reliability of supply targets... 3 1.2 SAIFI definition... 5 1.3

More information

How To Test For Safety On A Power Cable

How To Test For Safety On A Power Cable T H E M A G A Z I N E O F 7 x 2 4 E X C H A N G E I N T E R N AT I O N A L A Green Approach to Building a Superior Data Center S P R I N G 0 9 BUILD FOR TODAY. EXPAND ON DEMAND. Modularity in the data

More information

Guidelines for ATS selection: How to choose the right transfer solution for your power application.

Guidelines for ATS selection: How to choose the right transfer solution for your power application. Power topic #7012 Technical information from Cummins Power Generation Inc. Guidelines for ATS selection: How to choose the right transfer solution for your power application. > White Paper By Gary Olson,

More information

Attachments A through E provide the Distribution Reliability Initiative Reports filed with Newfoundland Power s CBA for the years 2009 through 2013.

Attachments A through E provide the Distribution Reliability Initiative Reports filed with Newfoundland Power s CBA for the years 2009 through 2013. Requests for Information CA-NP-161 NP 2013/2014 GRA 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Q. For each of the past five years, identify the fifteen worst performing circuits on Newfoundland Power

More information

Undergrounding high voltage electricity transmission. The technical issues

Undergrounding high voltage electricity transmission. The technical issues Undergrounding high voltage electricity transmission The technical issues This is an interactive PDF document with clickable links from the contents to all sections and back and also to URL and email links.

More information

Review of Florida s Investor-Owned Electric Utilities 2 0 1 4 Service Reliability Reports. November 2 0 1 5

Review of Florida s Investor-Owned Electric Utilities 2 0 1 4 Service Reliability Reports. November 2 0 1 5 Review of Florida s Investor-Owned Electric Utilities 2 0 1 4 Service Reliability Reports November 2 0 1 5 State of Florida Florida Public Service Commission Division of Engineering Review of Florida

More information

Failure Rate Modeling Using Equipment Inspection Data

Failure Rate Modeling Using Equipment Inspection Data Failure Rate Modeling Using Equipment Inspection Data Richard E. Brown (SM)* 1Abstract System reliability models typically use average equipment failure rates. Even if these models are calibrated based

More information

Electrical Safety Tips. Help us keep you safe

Electrical Safety Tips. Help us keep you safe Electrical Safety Tips Help us keep you safe To help you stay safe when using electricity, ActewAGL has compiled these electrical safety tips. For natural gas safety tips please see ActewAGL s natural

More information

Calculation of Voltage Sag Indices for Distribution Networks

Calculation of Voltage Sag Indices for Distribution Networks Calculation of Voltage Sag Indices for Distribution Networks Juan A. Martinez-Velasco, Member, IEEE, Jacinto Martin-Arnedo, Nonmember Abstract This paper is presenting the main results of a work aimed

More information

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents Federal Wage System Job Grading Standards for Electric Power Controlling, 5407 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 SPECIAL ADDITIONAL RESPONSIBILITIES...

More information

DISTRIBUTION SYSTEMS INDEX NOV 06 SECTION 2. Detroit...2-1-5 Ann Arbor...2-1-6 Mt. Clemens...2-1-7 Port Huron...2-1-8

DISTRIBUTION SYSTEMS INDEX NOV 06 SECTION 2. Detroit...2-1-5 Ann Arbor...2-1-6 Mt. Clemens...2-1-7 Port Huron...2-1-8 DISTRIBUTION SYSTEMS INDEX NOV 06 SECTION 2 Kinds and Uses of Service... 2-1-1 and 2-1-2 Wye Network Area Maps Detroit...2-1-5 Ann Arbor...2-1-6 Mt. Clemens...2-1-7 Port Huron...2-1-8 Transformer Connections

More information

690 V is a good alternative in the process industry

690 V is a good alternative in the process industry 690 V is a good alternative in the process industry The process industry in the Nordic countries generally uses voltage of 690 V for process motors, whereas Central Europe, Great Britain and the USA usually

More information

During the analysis of cash flows we assume that if time is discrete when:

During the analysis of cash flows we assume that if time is discrete when: Chapter 5. EVALUATION OF THE RETURN ON INVESTMENT Objectives: To evaluate the yield of cash flows using various methods. To simulate mathematical and real content situations related to the cash flow management

More information

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz) 24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690

More information

Hendrix Spacer Cable

Hendrix Spacer Cable Hendrix Spacer Cable What is Spacer Cable? Covered Conductor Withstands temporary branch contact Eliminates temporary faults Protects wildlife Less clearance issues Compact Configuration Multiple Circuits

More information

Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns

Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Mehmet H. Cintuglu, mcint015@fiu.edu, Armando Altamirano, araltami@fiu.edu Osama A. Mohammed, mohammed@fiu.edu Energy Systems

More information

ELECTRICAL SAFETY RISK ASSESSMENT

ELECTRICAL SAFETY RISK ASSESSMENT ELECTRICAL SAFETY RISK ASSESSMENT The intent of this procedure is to perform a risk assessment, which includes a review of the electrical hazards, the associated foreseeable tasks, and the protective measures

More information

Wireless power meter monitoring with power theft detection and intimation system using GSM and Zigbee networks

Wireless power meter monitoring with power theft detection and intimation system using GSM and Zigbee networks IOSR Journal of Electronics and Communication Engineering (IOSR-JECE) e-issn: 2278-2834,p- ISSN: 2278-8735.Volume 9, Issue 6, Ver. I (Nov - Dec. 2014), PP 04-08 Wireless power meter monitoring with power

More information

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2014-15 Electricity Network Tariffs and Charges and Future Price Trends August 2014 Power and Water Corporation Table of Contents 1 Business Characteristics... 3 2 2014 Network Price Determination...

More information

TRANSMISSION BUSINESS PERFORMANCE

TRANSMISSION BUSINESS PERFORMANCE Filed: 0-0- Tx 0-0 Rates Tab Schedule Page of TRANSMISSION BUSINESS PERFORMANCE.0 INTRODUCTION 0 Hydro One is focused on the strategic goals and performance targets in the area of safety, customer satisfaction,

More information

Pennsylvania Summer Reliability

Pennsylvania Summer Reliability A. Reliability Enhancement Programs In 2015, Pennsylvania Power Company s ( Penn Power or Company ) reliability plan incorporates projects and programs to enhance overall reliability. The plan is structured

More information

SP Energy Networks 2015 2023 Business Plan

SP Energy Networks 2015 2023 Business Plan Environmental Discretionary Reward Scheme 1 SP Energy Networks 2015 2023 Business Plan Executive summary SP Distribution Ltd SP Manweb plc July 2013 RIIO ED1 Business Plan 2015 to 2023 2 A Message from

More information

On-line monitoring of substation condition a Romanian experience. V. ZAHARESCU, Vl. ROSCA Nova Industrial SA. CN Transelectrica SA Romania

On-line monitoring of substation condition a Romanian experience. V. ZAHARESCU, Vl. ROSCA Nova Industrial SA. CN Transelectrica SA Romania 21, rue d Artois, F-75008 PARIS http : //www.cigre.org B3_201 CIGRE 2012 On-line monitoring of substation condition a Romanian experience C. MOLDOVEANU*, V. BREZOIANU, S. GAL, V. METIU, A. VASILE, V. URSIANU,

More information

Nexus Technology Review -- Exhibit A

Nexus Technology Review -- Exhibit A Nexus Technology Review -- Exhibit A Background A. Types of DSL Lines DSL comes in many flavors: ADSL, ADSL2, ADSL2+, VDSL and VDSL2. Each DSL variant respectively operates up a higher frequency level.

More information