TRANSNET PIPELINES. TPL 25 Tarlton Commissioning Plan

Size: px
Start display at page:

Download "TRANSNET PIPELINES. TPL 25 Tarlton Commissioning Plan"

Transcription

1 TPL 25 Tarlton Commissioning Plan Issue Date: 03/07/2015 Revision No.: A Project No.: 11992

2 Date: 03/07/2015 Document Title: TPL25 Tarlton Commissioning Plan Author: Edward Standen Revision Number: A Checked by: Trevor Albertyn Approved by: Didier Regnaud For: SiVEST Project Management Division Signature: Approved by: For: Charl Bothma (TPL Project Manager) Transnet Pipelines Signature:

3 Contents TPL 25 Commissioning Plan Page 1. Introduction: Extent of Work: Organisation: Stages to Construction and Commissioning C1 - Pre-Commissioning C2 - Cold Commissioning C3 - Hot Commissioning Roles and responsibilities Division of Works into sub-systems for Commissioning Commissioning activity sequencing Schedule: Individual Equipment Testing Procedures: Facility Testing Procedures: Safety: Check / Data Forms: Hand-over Procedures:... 9 Annexure A... 1 Annexure B... 2 Annexure C... 3 Annexure D... 4 Annexure E... 5 Annexure F July 2015 Page 1 of 9

4 1. Introduction: This document is a commissioning plan developed for the Tarlton Fire Protection upgrade and is to be used to inform the Contractor of the commissioning requirements for inclusion in the offer as well as to guide the construction and commissioning process during implementation. This document will require revision and updating by the Project Manager and Contractor during implementation. Areas requiring updated are indicated and updates may be in the form of revisions to the document or addition of Annexures and addendums. The intention of this document is to indicate the parties involved in commissioning and define the roles and responsibilities as well as reporting and approval requirements. 2. Extent of Work: The commissioning shall consider the full extent of the Works and shall encompass monitoring and approval of civil, structural and building works in addition to monitoring, approval, installation verification and performance testing of the piping, electrical, control and mechanical equipment installations. Commissioning shall be an ongoing process and shall commence during construction both in order to reduce the overall timeline as well as due to necessity as some commissioning activities need to be completed before other construction activities can commence; an example of this is the bottom layer of piping in trenches must be hydrostatically tested before the pipe can be backfilled and the piping layer above that layer can be installed. 3. Organisation: The organisation of the works will facilitate the efficient management and completion of the commissioning by defining responsibilities, defining the division of works into manageable and separate sub-systems and indicating a preliminary sequencing of the commissioning activities. These factors will inform the scheduling of commissioning activities as well as the interfaces between the Employer, Project Manager and Contractor Stages to Construction and Commissioning. The development from existing site to completed installation will develop through a number of stages broadly comprising construction and commissioning. There are a number of interfaces and at multiple points during construction and commissioning the Contractor shall be required to gain permission from the Project Manager to progress to the following stage. 03 July 2015 Page 2 of 9

5 The construction will primarily be controlled by the utilisation of Work Permits. Work Permits shall be completed for each area of work for each day and shall indicate any work to be completed which will require further permissions. Approval of a work permit will not constitute approval of that work requiring further permission and the relevant forms shall be completed for all such works. Works which require additional permission include: Excavation Work within bunds Work on Tanks Backfilling over pipelines Pouring Concrete The Contractor shall develop standard forms for management of all works requiring additional approval. These shall indicate the following as a minimum: Date Area of works (indicating extents) Node (i.e. pipe number) Permission Required Contractors Name, Position and Signature Once an area of works is complete the Construction team shall complete precommissioning. Once pre-commissioning has been completed and signed off, the commissioning team can complete cold-commissioning then hot-commissioning. These activities are defined as follows: C1 - Pre-Commissioning - Contractor and/or Suppliers & Construction Team Pre-commissioning consists of Punch Listing of discrete parts of equipment or systems by Contractors and/or Suppliers before handing over to the Commissioning Team. The Construction Engineer will sign off this stage of commissioning when the following have been achieved: Punch Listing by the Contractor and Project Construction Team Rectification of Cat 1 & 2 Punch List Items by the Contractor Cleaning of the area intended for hand-over Completion of test sheets such as for Megger, alignment and pressure tests The equipment or module shall have all hardwired interlocks and protective systems checked and tested by the Contractor or Supplier The Construction Engineers shall complete the Certificate once they have satisfied themselves that all the remaining items on the Punch List can be carried forward to run testing without endangering life or the safety of the works. They shall clear any uncertainties with the Construction Manager 03 July 2015 Page 3 of 9

6 The Construction Team, Commissioning Team and Client Commissioning Team shall sign the C1 Acceptance Certificate C1 Pre Commissioning shall be considered complete when all the above items have been addressed and all documentation submitted to the Document Controller. C1 - Document Package consists of: C1 - Acceptance Certificate QC Data Packs for all disciplines, which include: - All pre-commissioning checklists and test certificates. - Punch or Defect Lists The C1 Pre-Commissioning Acceptance Certificate must be signed off before proceeding to the next stage of commissioning C2 - Cold Commissioning - Contractors and/or Suppliers, Construction Team and Commissioning Team This involves running the equipment or module dry to test or perform relevant checks on the equipment or system. After all safety checks have been completed, all equipment such as conveyors, motors etc. are run for short periods under the supervision of the Contractors and/or Suppliers, Construction Engineer and Commissioning Engineers in accordance with the running tests and procedures provided by the Design Engineer, Contractor and/or Suppliers. The following shall be done during these tests: Equipment or module PLC sequence interlocks shall be checked Checking, calibration and rectification of all instrumentation such as level, flow, pressure, density, power meters etc.to ensure correct functionality Leaks, splashing and any other adverse operating feature shall be eliminated Unacceptable structural vibrations shall be identified and eliminated Warranty repairs shall be identified and the installation Contractor and/or Supplier will provide a programme for rectification All equipment that forms a zone or stream shall be run simultaneously where possible, to allow balancing and to check all interlocks and process control C2 - Document Package consists of: C2 - Acceptance Certificate Additions to QC Data Packs: - Dry run test certificates - Cold Commissioning Checklists - Master Punch or Defect Lists The C2 - Cold Commissioning Acceptance Certificate must be signed off before proceeding to the next stage of commissioning C3 - Hot Commissioning - Client Commissioning Team This involves operating systems to test or perform relevant checks in order to balance the operation and prove the performance of the system. After all cold commissioning has been completed, whole systems are operated under the supervision of the Contractors and/or Suppliers, Construction Engineer and 03 July 2015 Page 4 of 9

7 Commissioning Engineers in accordance with the running tests and procedures provided by the Design Engineer, Contractor and/or Suppliers. The following shall be done during these tests: Discharge flow rates are verified or balanced Pipelines, valves and systems are tested with full product flow. Pump flow tests are conducted to prove performance Foam dosing performance is tested to prove range of operation and correct foam premix generation Leaks, splashing and any other adverse operating feature shall be eliminated Unacceptable structural vibrations shall be identified and eliminated Warranty repairs shall be identified and the installation Contractor and/or Supplier will provide a programme for rectification C3 - Document Package consists of: C3 - Acceptance Certificate Additions to QC Data Packs: - Run test certificates - Hot Commissioning Checklists - Final / Master Punch or Defect Lists - Final Hand Over Certificates The C3 - Hot Commissioning Acceptance Certificate must be signed off in order to certify completion. Defect Classification: Cat 1 Cat 2 Cat 3 These deviations, defects or outstanding items may affect health and/or safety of personnel and operability and must therefore be rectified immediately. These deviations, defects or outstanding items may affect operability and must therefore be rectified before commencement of cold commissioning. These deviations, defects or outstanding items do not affect operability and therefore may rectified during operation but will be subject to access permits Roles and responsibilities There are three primary parties involved in the commissioning; these are the Employer, Project Manager and Contractor. The primary responsibility for the planning and completion of the commissioning including the development of all test procedures for equipment and facilities shall rest with the Contractor. The Contractor may develop these procedures or commission equipment or system suppliers to develop and complete these procedures however the responsibility shall at all times remain with the Contractor and the Employer or Project 03 July 2015 Page 5 of 9

8 Manager may at any time interact directly with the Contractor should problems arise in interaction with the Contractors appointed sub-consultants. The Contractor shall complete the following in addition to all commissioning tests: Develop Commissioning Schedule (may form part of master construction schedule) Develop Commissioning Control Document o This document shall indicate all commissioning activities and interfaces and shall be a live document, updated and signed off as activities are completed in order to indicate what following activities can occur. Develop a Safety Lock out Procedure Develop Individual Equipment Commissioning Procedures. Develop Facility Commissioning Procedures. Arrange for the attendance of the Employer and / or Project Manager at all activities they are required to witness (this includes planning of activities and liaison regarding the availability of necessary persons but does not included provision for travel, accommodation or other similar requirements for persons other than the Contractor or their suppliers or representatives) Maintain the records of all commissioning completed and all approved documents. The Employer and Project Manager shall be required to witness and approve all final facility testing. The Employer Project Manager shall also be required to approve the Commissioning Plan, the Contractors Commissioning Schedule and the Contractors Commissioning Control Document The Project Manager shall also be required to approve the Safety Lock-out Procedure and all Individual Equipment and Facility Commissioning Procedures and shall witness and approve all tests conducted during cold and hot commissioning. Particular activities which the Project Manager must approve are: All back filling must be approved prior to commencement. Connection to any power supply must be approved Filling or pressurising of any systems Starting of any drives (other than valve actuators) Particular tests which may not form part of cold or hot commissioning but that the Project Manager must witness and approve are: Alignment of the fire pump unit Piping connection to fixed / separately supported equipment 3.3. Division of Works into sub-systems for Commissioning The commissioning activities of each phase consider different scales of systems. Pre-commissioning activities consider individual pieces of equipment, lines or sections of lines and other small installations which form part of a larger system. The division of systems into separate elements for the pre-commissioning phase means that there are numerous interfaces which could be neglected and thus the pre-commissioning phase 03 July 2015 Page 6 of 9

9 must include consideration of interfaces; for instance the connection of pipework to a pump must be considered and this could form part of the pump or pipework precommissioning or a separate element. For the purpose of this project, all equipment will be pre-commissioned prior to the installation of pipework connections and the connection of pipework will form part of the pre-commissioning check for the pipework. This includes tanks, pumps and any separately supported valves. Further commissioning including cold and hot commissioning tests are performed on systems not elements and as such the scope for division is limited. Broadly there are storage, pumping, foam dosing, distribution, detection and control systems. Each of these can be cold-commissioned separately with further division possible. There are elements which will require sequencing such that one two aspects are commissioned together or for instance the piping can only be commissioned once the storage and pumping have been commissioned. Hot-commissioning requires that all systems related to the hot-commissioning activity have been cold-commissioned. Hot-commissioning will involve the operation of multiple systems concurrently to both ensure their operational functionality as well as to allow performance testing of the systems Commissioning activity sequencing The sequencing of the stages of commissioning is most critical at the interface with construction and particularly with regards to the installation of piping in trenches and to operational facilities. For the installation of piping in trenches, each level of piping needs to be backfilled before the level above it may be installed; in order to prevent significant rework, all pipework must be pre-commissioned before it may be backfilled as this verifies the pipework is free from leaks and suitable for service. For the installation of piping to tanks, gantries and other working areas, precommissioning shall be completed immediately after completion of the works in an area in order to prevent the need to grant further access for remedial work after the area has been returned to operation. Further to these sequencing considerations, as noted previously, piping may only be installed to equipment after the equipment has been installed and pre-commissioned. The Contractor therefore needs to consider this in the scheduling and management of the construction. 4. Schedule: The Contractor is to include the commissioning activities in the construction schedule. Commissioning activities are to take place from an early stage of construction and the necessary provision for time and resources shall be evident on the programme. The following is a draft breakdown of the activities during the various project stages: 03 July 2015 Page 7 of 9

10 Stage Activities Preconstruction Ensure the commissioning costs are considered in the estimate Make sure that the requirements of the commissioning process are clearly defined in the tender documentation that is issued to the specialist trade contractors Prepare the commissioning specification Produce a detailed commissioning programme Produce first draft O&M manuals, commissioning method statements and an offsite commissioning strategy before the start of installation work Construction Co-ordinate third party involvement in the commissioning process Conduct pre-commissioning works, involving verification of installation works and static tests. Verify and document that the required performance outcomes have been achieved Collate the pre-commissioning checklists and test sheets in the format agreed Monitor progress of commissioning activities and construction works Ensure that continual progress is made with the development of the O&M manuals Perform the setting to work of systems. Verify and document that the required performance outcomes have been achieved Carry out regulation of systems. Verify and document that the required performance outcomes have been achieved. Commissioning Undertake performance testing of the works. Verify and document that the required performance outcomes have been achieved. Involve facilities management personnel in the commissioning works Collate the commissioning checklists and test sheets in the format agreed by the commissioning team Finish the production of the O&M manuals and integrate the required commissioning information. Monitor progress of commissioning process activities and construction works Verify the quality of the documentary evidence from commissioning process works Pre-handover Ensure that all required statutory documentation has been produced Conduct training of users and operators Update the commissioning plan. Changes made and knowledge gained during sitebased works should be reflected in post-handover works 03 July 2015 Page 8 of 9

11 5. Individual Equipment Testing Procedures: The Contractor shall be responsible for the development of commissioning procedures and test forms for each piece of equipment and element of the works and each stage of commissioning. These shall correlate with the Commissioning Control Document. 6. Facility Testing Procedures: The Contractor shall be responsible for the development of the cold and hotcommissioning procedures and test forms for each system. These shall correlate with the Commissioning Control Document. 7. Safety: Safety is of the utmost importance during construction and no work shall be conducted in the vicinity of pressurised or running equipment. Commissioning work shall require the completion of work permits. 8. Check / Data Forms: In addition to the test forms and procedures for the various phases of commissioning, there shall be final approval forms. Draft forms have been included in the appendices. The forms required include: Pre-commissioning Acceptance Certificate Cold-commissioning Acceptance Certificate Hot-commissioning Acceptance Certificate Design Acceptance Change Control Notice Commissioning Dossier Checklist 9. Hand-over Procedures: The Contractor shall be responsible for the completion of all commissioning including hot-commissioning. Hand-over shall be achieved once all commissioning work has been completed with all tests, verifications and settings approved by the Engineer and the Employer. Hand-over shall also require that all documentation including all Manuals, Quality Control Files, asbuilt and red-lined drawings and operating spares have been supplied by the Contractor. 03 July 2015 Page 9 of 9

12 Annexure A C1 PRE-COMMISSIONING ACCEPTANCE CERTIFICATE AREA / SUB - AREA : MECHANICAL EQUIPMENT LIST ATTACHED ELECTRICAL EQUIPMENT LIST ATTACHED C & I EQUIPMENT LIST ATTACHED This is to certify that the Equipment / System (as per attached lists) has been tested and punch listed and cold commissioning may commence. It is the responsibility of the Contractor/Supplier to address the Punch Lists as per a program agreed with the Construction Manager. RESPONSIBLE PERSONS: MECHANICAL: DISCIPLINE NAME SIGNATURE DATE AREA ENGINEER COMMISSIONING ENGINEER ELECTRICAL: AREA ENGINEER COMMISSIONING ENGINEER C & I: AREA ENGINEER / COW DESIGN / COMM. ENGINEER OTHER: CONSTRUCTION MANAGER AREA TEAM LEADER CLIENT ELEC. ENGINEER CLIENT C & I ENGINEER CLIENT COMM. ENGINEER 03 July 2015 Page 1 of 6

13 Annexure B C2 COLD COMMISSIONING ACCEPTANCE CERTIFICATE AREA / SUB - AREA : MECHANICAL EQUIPMENT LIST ATTACHED ELECTRICAL EQUIPMENT LIST ATTACHED C & I EQUIPMENT LIST ATTACHED This is to certify that the Equipment / System (as per attached lists) has been tested and hot commissioning may commence. It is the responsibility of the Contractor/Supplier to address the Final / Master Punch Lists as per a program agreed with the Construction Manager. Final Hand Over / Release Certificates have been issued to the Contractor. Client has taken over the responsibility for the care, custody and control of the system/plant. RESPONSIBLE PERSONS: MECHANICAL: DISCIPLINE NAME SIGNATURE DATE COMMISSIONING ENGINEER DESIGN ENGINEER ELECTRICAL: COMMISSIONING ENGINEER C & I: DESIGN ENGINEER COMM / DESIGN ENGINEER AREA TEAM LEADER CLIENT ELEC. ENGINEER CLIENT C & I ENGINEER CLIENT COMM. ENGINEER CLIENT PROJECT MANAGER 03 July 2015 Page 2 of 6

14 Annexure C C3 HOT COMMISSIONING ACCEPTANCE CERTIFICATE AREA / SUB - AREA : MECHANICAL EQUIPMENT LIST ATTACHED ELECTRICAL EQUIPMENT LIST ATTACHED C & I EQUIPMENT LIST ATTACHED This is to certify that the Equipment / System (as per attached lists) has been tested and hot commissioned. It is the responsibility of the Contractor/Supplier to address the Final / Master Punch Lists as per a program agreed with the Construction Manager. Client has taken over the responsibility for the care, custody and control of the system/plant. RESPONSIBLE PERSONS: MECHANICAL: DISCIPLINE NAME SIGNATURE DATE COMMISSIONING ENGINEER DESIGN ENGINEER ELECTRICAL: COMMISSIONING ENGINEER C & I: DESIGN ENGINEER COMM / DESIGN ENGINEER AREA TEAM LEADER CLIENT ELEC. ENGINEER CLIENT C & I ENGINEER CLIENT COMM. ENGINEER CLIENT PROJECT MANAGER 03 July 2015 Page 3 of 6

15 AREA / SUB - AREA : Annexure D DESIGN ACCEPTANCE MECHANICAL EQUIPMENT LIST ATTACHED ELECTRICAL EQUIPMENT LIST / CABLE SCHEDULE ATTACHED C & I EQUIPMENT LIST / CABLE SCHEDULE ATTACHED DESIGNERS / SUPPLIERS; COMPANY DOCUMENT RECEIVED COMMENT The above mentioned installation / system has been constructed according to approved design and thus is fit for purpose. Alterations / Amendments / Additions / Exclusions / Restrictions Name Signature Date Design Engineer 03 July 2015 Page 4 of 6

16 Annexure E CHANGE CONTROL NOTICE Contractor /Vendor:: Area: Attached : SI Nº CVCO Nº CN Nº: Originator : Date : Sign : Revision : Description : Requested by: Schedule checked Hazop completed Name Signature Date Disciplines Design Cost Equip. cost Estimated by Total Mechanical Elect/Instr/Contr Civil/Structural Other TICK IN APPROPRIATE BLOCK PROCEED WITH WORK Cost : PROCEED WITH CHANGE WHILE COST & SCHEDULE IMPACT IS BEING EVALUATED (EVALUATION TO BE COMPLETED WITHIN 2 WEEKS) HOLD UNTIL DETAILED EVALUATION OF COST & SCHEDULE IMPACT IS APPROVED SIGNING AUTHORITY FOR EMPLOYER Name :... Title Signed. Date July 2015 Page 5 of 6

17 AREA / SUB - AREA : Annexure F COMMISSIONING DOSSIER CHECKLIST MECHANICAL EQUIPMENT LIST ATTACHED ELECTRICAL EQUIPMENT LIST / CABLE SCHEDULE ATTACHED C & I EQUIPMENT LIST / CABLE SCHEDULE ATTACHED Checklist: 1. Mechanical QC Packs As - Built Drawings O & M Manuals (Spare Parts List) 2. C & I (Install) QC Packs Loop Drawings As - Built Cable Schedules 3. C & I (Supply) Certificates Of Compliance Calibration Certificates Delivery Acceptance Data Sheets 4. Electrical QC Packs As Built Drawings 5. Equipment: Data Sheets Certificates Of Compliance 6. Pre- Commission Acceptance Certificate 7. Cold commissioning Acceptance Certificate 8. Final Hand Over Certificates to Contractors 9. P & ID s (Redlined or As Built) 10. Other Drawings 11. Design Acceptance 12. READY FOR TRANSMITTAL TO CLIENT Yes No Comment 03 July 2015 Page 6 of 6

18 SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks PO Box 1899, Umhlanga Rocks South Africa Tel Fax info@sivest.co.za Contact Person: Didier Regnaud Cell No.: didier@sivest.co.za

PART 4: SITE INFORMATION

PART 4: SITE INFORMATION TRANSNET PIPELINES TENDER NUMBER: PYP/W1/6/21/1646 DESCRIPTION OF THE WORKS: CONSTRUCTION OF THE FIRE PROTECTION SYSTEM UPGRADE FOR THE FUEL HANDLING AREAS OF THE TARLTON DEPOT AND IRP REFRACTIONATOR ONLY

More information

HomeServices Terms and Conditions

HomeServices Terms and Conditions HomeServices Terms and Conditions Contents Definitions 03 The Contract 04 Start date 04 General Exclusions 11 Payment 12 Cancellation 13 Appointments 16 Product Renewal 16 Changes to contract 16 Safety

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company. Ref: Quality Manual.

Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company. Ref: Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company Ref: Quality Manual.ind Issue: June 2009 INDEX 1 Amendment Status 2 Controlled Distribution

More information

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+)

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+) Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+) 1. In addition to the information scheduled below, the pre-tender designer is responsible for: (i)

More information

Commissioning Plan Preparation Guide. Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012)

Commissioning Plan Preparation Guide. Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012) Commissioning Plan Preparation Guide Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012) September 2013 Commissioning Plan Preparation Guide Contents 1.0 Introduction...

More information

& Start-up Directory

& Start-up Directory & Start-up Directory INTEGRATED SERVICE SOLUTIONS Index C H A P T E R 1 INTRODUCTION 4 C H A P T E R 2 COMMISSIONING & START UP SERVICE 5 2.1 Standard Implementation Path 6 2.2 The Home Office Phase 7

More information

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project. DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly

More information

Project Management Handbook 2014. "To Understand the Causes of Things"

Project Management Handbook 2014. To Understand the Causes of Things Management Handbook 2014 "To Understand the Causes of Things" AMENDMENT RECORD This document has been issued and amended as follows: - Isu. Rev. Reason for Issue / revision Date Issued to Team Stakeholders

More information

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work

More information

COMMISSIONING OF FIRE ALARM SYSTEMS

COMMISSIONING OF FIRE ALARM SYSTEMS COMMISSIONING OF FIRE ALARM SYSTEMS OWNER FURNISHED The owner directly contracts an independent third party commissioning agent for this project. This Commissioning Plan has been included for reference

More information

ARTWORK COMMISSION AGREEMENT

ARTWORK COMMISSION AGREEMENT ARTWORK COMMISSION AGREEMENT THIS AGREEMENT is made the day of in the year BETWEEN the Minister for Works of Level 6, 16 Parkland Road, Osborne Park, WA 6017 being the body corporate created under Section

More information

TfNSW Standard Requirements TSR T Technical Management

TfNSW Standard Requirements TSR T Technical Management Template Applicable to: Transport Projects Quality Management System Status: Division: Approved Transport Projects Version: 5.0 Desksite No.: 3455797_1 Date of issue: 1 July 2014 Effective date: 1 July

More information

Company name Date submitted. Building address City State ZIP. E-mail* Building Sq. Ft.

Company name Date submitted. Building address City State ZIP. E-mail* Building Sq. Ft. Recommissioning Application Business Customer Information Company name Date submitted Building address City State ZIP Mailing address (if different) City State ZIP Contact person (print) Phone Fax E-mail*

More information

Water Damage on Construction Sites. A guide to loss prevention

Water Damage on Construction Sites. A guide to loss prevention Water Damage on Construction Sites A guide to loss prevention Water damage is the second most frequent cause of loss during building projects and represents a large percentage of Construction All Risk

More information

For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems

For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems BAFE Scheme: SP203-3 Version 1: July 2008 Amendment No: 1 Fire Protection Industry Scheme, Reference SP203 Part 3 For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression

More information

R E Q U E S T F O R P R O P O S A L S H U M A N R E S O U R C E S S T R A T E G I C A N D I M P L E M E N T A T I O N S U P P P O R T RFP/JHB/ 037

R E Q U E S T F O R P R O P O S A L S H U M A N R E S O U R C E S S T R A T E G I C A N D I M P L E M E N T A T I O N S U P P P O R T RFP/JHB/ 037 P.O. Box 3209, Houghton, 2041 Block A, Riviera Office Park, 6-10 Riviera Road, Riviera R E Q U E S T F O R P R O P O S A L S H U M A N R E S O U R C E S S T R A T E G I C A N D I M P L E M E N T A T I

More information

For installation guide see reverse of book

For installation guide see reverse of book USERS GUIDE LOGIC Combi 24, 30, 35 For installation guide see reverse of book When replacing any part on this appliance, use only spare parts that you can be assured conform to the safety and performance

More information

Level 1 Certificate in Network Construction Operations - Gas (6028-10)

Level 1 Certificate in Network Construction Operations - Gas (6028-10) Level 1 Certificate in Network Construction Operations - Gas (6028-10) Learner logbook www.cityandguilds.com January 2013 Version 2.0 Qualification title Number QAN Level 1 Certificate in Network Construction

More information

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement

More information

WHS Contractor Management Procedure

WHS Contractor Management Procedure Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety

More information

Backup Fuel Oil System Decommissioning & Restoration Plan

Backup Fuel Oil System Decommissioning & Restoration Plan Backup Fuel Oil System Page 1 of 19 Overview of Physical Fuel Oil System and Decommissioning Steps The fuel oil system at Milford Power consists of a number of subsystems. These include the following:

More information

Management of Contractors and Suppliers Procedure

Management of Contractors and Suppliers Procedure Management of Contractors and HSE P1101 Table of Content 1 DOCUMENT CONTROL... 2 2 PURPOSE... 3 3 SCOPE... 3 4 DEFINITIONS... 3 5 ROLES AND RESPONSIBILITIES... 5 6 PROCESS DETAILS... 9 6.1 Confirm Need

More information

USERS GUIDE. LOGIC Heat 12, 15, 18, 24, 30. For installation guide see reverse of book

USERS GUIDE. LOGIC Heat 12, 15, 18, 24, 30. For installation guide see reverse of book USERS GUIDE LOGIC Heat 12, 15, 18, 24, 30 For installation guide see reverse of book When replacing any part on this appliance, use only spare parts that you can be assured conform to the safety and performance

More information

ITS specification Handover and commissioning process (ITS-10-01)

ITS specification Handover and commissioning process (ITS-10-01) ITS specification Handover and commissioning process (ITS-10-01) NZ Transport Agency Effective from September 2011 Copyright information This publication is copyright NZ Transport Agency (NZTA). Material

More information

CLIENT / PROJECT MANAGER AGREEMENT

CLIENT / PROJECT MANAGER AGREEMENT Authorship of this work is claimed by The Association of Construction Project Managers and any unauthorised reproduction constitutes an infringement in terms of the Copyright Act No 98 of 1978. CLIENT

More information

Energy Design Resources Commissioning Plan Outline Template

Energy Design Resources Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

Part 3: Quality Assurance

Part 3: Quality Assurance Part 3: Quality Assurance Contents 3.1 Referenced Documents...3-3 3.1.1 Source document...3-3 3.1.2 Guidelines...3-3 3.2 Introduction...3-3 3.3 Project Quality System... 3-4 3.3.1 Key achievement criteria...

More information

THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL

THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL OCTOBER, 2013 TABLE OF CONTENTS 1. CHECKLIST PAGE NO. 2. CHECKLIST DETAILS A. Design Path 3 B. Property Acquisition 6 C. Outside

More information

Building Commissioning 17900-1

Building Commissioning 17900-1 SECTION 17900 BUILDING COMMISSIONING PART 1 - GENERAL 1.01 WORK DESCRIPTION: A. General: 1. The Commissioning process is a joint team effort to ensure that all mechanical equipment, controls, and systems

More information

USERS GUIDE. LOGIC Combi 24, 30, 35. For installation guide see reverse of book

USERS GUIDE. LOGIC Combi 24, 30, 35. For installation guide see reverse of book USERS GUIDE LOGIC Combi 24, 30, 35 For installation guide see reverse of book When replacing any part on this appliance, use only spare parts that you can be assured conform to the safety and performance

More information

Water Damage During Construction

Water Damage During Construction Allianz Global Corporate & Specialty Americas Water Damage During Construction May 2012 A Contractor s Loss Prevention Guide Water damage losses are a major cause of loss during construction and represent

More information

DISTRIBUTION, OPERATION and MAINTENANCE STRATEGY ASSET MANAGEMENT WORK PROCEDURE SECONDARY DISINFECTION DESIGN AND INSTALLATION

DISTRIBUTION, OPERATION and MAINTENANCE STRATEGY ASSET MANAGEMENT WORK PROCEDURE SECONDARY DISINFECTION DESIGN AND INSTALLATION DISTRIBUTION, OPERATION and MAINTENANCE STRATEGY SECONDARY DISINFECTION DESIGN AND INSTALLATION Document Title: Document Reference: Work Procedure Secondary Disinfection Design and Installation Date: October

More information

ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)

ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal Forms Part 4:

More information

SMS0045 Construction Health and Safety Policy and Procedures

SMS0045 Construction Health and Safety Policy and Procedures SMS0045 Construction Health and Safety Policy and Procedures March 2015 Version 8 Please note that for projects utilising a CDM Co-ordinator under the transitional arrangements of CDM 2015 (between 6 April

More information

NCCER 13614 Progress Blvd., Alachua, FL 32615 Tel: (888) 622-3720 E-mail: info@nccer.org. Task Number Item Date(s) Recorded By

NCCER 13614 Progress Blvd., Alachua, FL 32615 Tel: (888) 622-3720 E-mail: info@nccer.org. Task Number Item Date(s) Recorded By NCCER 13614 Progress Blvd., Alachua, FL 32615 Tel: (888) 622-3720 E-mail: info@nccer.org PIPELINE MAINTENANCE On-the-Job Training Level One MODULE 66101-02 INTRODUCTION TO THE PIPELINE INDUSTRY This is

More information

JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management

JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management JOHN HART GENERATING STATION REPLACEMENT PROJECT Schedule 9 Quality Management SCHEDULE 9 QUALITY MANAGEMENT TABLE OF CONTENTS 1. QUALITY MANAGEMENT SYSTEM... 1 1.1 Quality Management System...1 1.2 Project

More information

Territory and Municipal Services Reference Document 10

Territory and Municipal Services Reference Document 10 Territory and Municipal Services Reference Document 10 REQUIREMENTS FOR SOFT LANDSCAPE CONSOLIDATION AND HANDOVER Issue 2 Revision 2 APPROVED FOR ISSUE Approved by: Fay Steward Executive Director Land

More information

ADDENDUM No. 2. RFP No. 14-15/27, Oakland Maintenance Center Facility Management Services

ADDENDUM No. 2. RFP No. 14-15/27, Oakland Maintenance Center Facility Management Services Purchasing Department 530 Water Street Oakland, CA 94607 March 6, 2015 ADDENDUM No. 2 RFP No. 14-15/27, Oakland Maintenance Center Facility Management Services This Addendum modifies the original RFP Documents

More information

Design Guidelines for Facilities Construction:

Design Guidelines for Facilities Construction: Engineering Division Facilities Management Department Design Guidelines for Facilities Construction: DESIGN GUIDELINE DG01-9 General Commissioning Requirements Part 1 - GENERAL 1.1 SUMMARY A. Section includes

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 2014

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 2014 for Inspecting and Certifying Buildings and Works Building Control Regulations 2014 February, 2014 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1 1.3 Application

More information

2. Performance Test Schedule and Certificates. 2.1 Definitions

2. Performance Test Schedule and Certificates. 2.1 Definitions 2. Performance Test Schedule and Certificates 2.1 Definitions 2.1.1 Unit shall mean the complete Power Station Assembly/Unit as defined in the Agreement (which consists of equipment provided by Contractor

More information

Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY

Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. HVAC Commissioning description. 2. HVAC Commissioning responsibilities. 1.2 REFERENCES A. American Society

More information

CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1

CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1 CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1 1 This Chapter of the FERC Engineering Guidelines has been prepared under contract with R & H Thomas, Inc. JANUARY 1993 Chapter VII Construction

More information

How To Get A Type B Gas Appliance Approved In Western Australia

How To Get A Type B Gas Appliance Approved In Western Australia Government of Western Australia Department of Commerce EnergySafety Guidelines for the approval of Type B (industrial) gas appliances in Western Australia Guidelines for the approval of Type B (industrial)

More information

Contractor Performance Report Scoring Guide

Contractor Performance Report Scoring Guide Report Main Roads Western Australia Table of Contents CONTRACTOR PERFORMANCE REPORT SCORING GUIDE... 3 1. APPLICATION... 3 2. REPORTING... 3 2.1 Objectives... 3 2.2 Frequency... 3 2.3 Responsibility...

More information

THE DELTON GROUP MANPOWER TRAINING CONSULTANCY SHORT COURSE PROGRAMME TOPICS LISTING

THE DELTON GROUP MANPOWER TRAINING CONSULTANCY SHORT COURSE PROGRAMME TOPICS LISTING THE DELTON GROUP MANPOWER TRAINING CONSULTANCY SHORT COURSE PROGRAMME TOPICS LISTING Delton Short Course Programmes English Language Technical English Language English Language for the Oil Industry Oil

More information

CONTRACTOR SAFETY MANAGEMENT PROCEDURE

CONTRACTOR SAFETY MANAGEMENT PROCEDURE CONTRACTOR SAFETY MANAGEMENT PROCEDURE Version 1.0 TRIM file number Short description Relevant to Authority Responsible officer Responsible office Date introduced July 20, 2015 Date(s) modified June 11,

More information

VDOT GOVERNANCE DOCUMENT

VDOT GOVERNANCE DOCUMENT VDOT GOVERNANCE DOCUMENT Minimum Requirements for Quality Assurance and Quality Control on Design Build and Public-Private Transportation Act Projects Location and Design Division Alternate Project Delivery

More information

COMMERCIAL REPORT / STOCK CONDITION SURVEY. Sydenham Hill Estate Sydenham Hill London SE 23

COMMERCIAL REPORT / STOCK CONDITION SURVEY. Sydenham Hill Estate Sydenham Hill London SE 23 COMMERCIAL REPORT / STOCK CONDITION SURVEY For Sydenham Hill Estate Sydenham Hill London SE 23 Submission Prepared by Gas Advisory Services Limited Date: 4 th June 2013 Gas Advisory Services Limited Phoenix

More information

Position Description

Position Description To apply for this position, please provide an up to date resume, covering letter, and statement addressing the Key Selection Criteria in section 6 of this Position Description. Your application will not

More information

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS 1. GENERAL PROVISIONS. 1.2 DEFINITIONS Where the words

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality Control/Quality Assurance (QC/QA) Program for

More information

focusfirst Construction factsheet Escape of water Things to consider

focusfirst Construction factsheet Escape of water Things to consider 07I08 focusfirst Construction factsheet Escape of water an awareness guide for construction companies The trend of losses in the construction industry has changed significantly in recent years with statistics

More information

Delivery Management Guidelines Delivery Process 2 - Project Management

Delivery Management Guidelines Delivery Process 2 - Project Management Delivery Management Guidelines Delivery Process 2 - Project Management Version control Version 9-1 Date 2010-10-18 Status Approved The IDMS Prov Infr Strat DP1: Portfolio Management DP1-1 Infrastructure

More information

DIRECTORATE OF ESTATES & FACILITIES

DIRECTORATE OF ESTATES & FACILITIES DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:

More information

Best Practice Guide BPGCS007

Best Practice Guide BPGCS007 Best Practice Guide BPGCS007 ENERGY MANAGEMENT Introduction: With rising fuel costs, opening of electricity and gas markets to alternate suppliers and climate change, the requirement to monitor and reduce

More information

ENVIRONMENTAL HEALTH AND SAFETY. Fire Protection System Impairment Procedure

ENVIRONMENTAL HEALTH AND SAFETY. Fire Protection System Impairment Procedure ENVIRONMENTAL HEALTH AND SAFETY Fire Protection System Impairment Procedure April 2013 Fire Protection System Impairment Procedures Table of Contents I. Purpose II. III. IV. Fire Protection Systems Compliance

More information

HANDOVER OF DISTRIBUTION NETWORK ASSETS (ELECTRICITY & WATER)

HANDOVER OF DISTRIBUTION NETWORK ASSETS (ELECTRICITY & WATER) Procedure # Page 1 of 19 HANDOVER OF DISTRIBUTION NETWORK ASSETS (ELECTRICITY & WATER) Prepared by: Asset Information Department Manager Reviewed by: Asset Management Director Endorsed by: Executive Operations

More information

Cowley Resident Management Organisation Ltd Cowley House, 147 Brixton Road London SW9 6LZ

Cowley Resident Management Organisation Ltd Cowley House, 147 Brixton Road London SW9 6LZ Cowley Resident Management Organisation Ltd Cowley House, 147 Brixton Road London SW9 6LZ Tel: 020-7926 0690 Fax 020-7926 0692 www.cowleyrmo.org Gas Central Heating Contract for Homeowners Basic Service

More information

H.V.A.C. Design Plumbing Design

H.V.A.C. Design Plumbing Design H.V.A.C. Design H.V.A.C. Design Mira Costa College Arts Complex CP Upgrade 1. PART 1 GENERAL 1.1. DESCRIPTION SECTION 23 09 00 HVAC INSTRUMENTATION AND CONTROL 2. PART 2 - PRODUCTS 2.1. Materials

More information

How To Comply With The Loss Prevention Certification Board

How To Comply With The Loss Prevention Certification Board Loss Prevention Standard LPS 1014: Issue 5.3 This Loss Prevention Standard is the property of BRE Global Ltd. and is made publicly available for information purposes only. Its use for testing, assessment,

More information

COMMISSIONING OF HVAC SYSTEMS

COMMISSIONING OF HVAC SYSTEMS FORM CL-01 SYSTEMS / EQUIPMENT INCLUDED : SYSTEM STARTUP CHECKLIST I - PRE - STARTUP INSPECTION EQUIPMENT MOUNTING & SETTING CONTROL, INTERLOCK & POWER WIRING ALIGNMENT OF MOTORS & DRIVES PIPING, CONNECTIONS

More information

PROJECT DESIGN DELIVERABLES SEQUENCE (PDD)

PROJECT DESIGN DELIVERABLES SEQUENCE (PDD) PROJECT DESIGN DELIVERABLES SEQUENCE (PDD) INTRODUCTION There are several reasons which lead to delay in project completion, out of all, one main reason is delay in deliverable processing i.e., submission

More information

Consultancy Services Proposal

Consultancy Services Proposal Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847

More information

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near

More information

SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION

SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION The purpose of this guide specification is to assist the specifier in correctly specifying Mechanical System Testing

More information

Roles and Responsibilities of Plant Commissioning, Hydrocarbon Introduction and Acceptance Test Run

Roles and Responsibilities of Plant Commissioning, Hydrocarbon Introduction and Acceptance Test Run Page 1 of 8 Introduction Roles and Responsibilities of Plant Commissioning, Hydrocarbon Introduction and Acceptance Test Run There are many parts of a grass root chemical plant construction. They include

More information

DOCUMENTED PROCEDURE MANUAL

DOCUMENTED PROCEDURE MANUAL NAPIT REGISTERED INSTALLERS DOCUMENTED PROCEDURE MANUAL CONTENTS 1. INTRODUCTION 2. DEFINITIONS 3. RESPONSIBILITY FOR QUALITY 4. DOCUMENT AND DATA CONTROL 5. CUSTOMER ENQUIRIES AND QUOTATIONS 6. CONTRACTS

More information

Construction (Design and Management) Regulations 2007

Construction (Design and Management) Regulations 2007 MEETING Finance, Procurement and Property Committee AGENDA ITEM 14 MEETING DATE 9 th July 2007 DOCUMENT NUMBER FEP 1052 SUBJECT REPORT Construction (Design and Management) Regulations 2007 (12/06/07) by

More information

Mechanical Engineer. Process Engineer. Civil Engineer. PFD 001 - Inlet works and screening 40.0 27. PFD 002 - Membrane Bioreactor 34.

Mechanical Engineer. Process Engineer. Civil Engineer. PFD 001 - Inlet works and screening 40.0 27. PFD 002 - Membrane Bioreactor 34. 1.00 Site Visit / Data Gathering Scope definition & design verification,inspection of the site, Collation of information, Condition report and priorities, Cost estimates and Preliminary programme 35.5

More information

Examples of pressure systems and equipment are:

Examples of pressure systems and equipment are: Pressure systems A brief guide to safety Introduction Pressure systems A brief guide to safety If pressure equipment fails in use, it can seriously injure or kill people nearby and cause serious damage

More information

Maintaining Fire Protection Systems

Maintaining Fire Protection Systems Maintaining Fire Protection Systems Fire continues to be a major threat to your business and your personal safety. Each year several thousand people are injured or killed by fires and billions of dollars

More information

Final Construction Quality Control Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut

Final Construction Quality Control Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut Final Construction Quality Control Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut Revision 0 Prepared for: Olin Corporation Cleveland, Tennessee Prepared by: Sevenson Environmental

More information

INSTRUCTIONS FOR BUILDINGS WITH FIRE PROTECTION EQUIPMENT

INSTRUCTIONS FOR BUILDINGS WITH FIRE PROTECTION EQUIPMENT INSTRUCTIONS FOR BUILDINGS WITH FIRE PROTECTION EQUIPMENT FIRE EXTINGUISHERS,SPRINKLER SYSTEMS AND FIRE ALARMS Attachment #1 Inspection of Fire Extinguishers Fire Extinguishers must be tested according

More information

Form 20 Application for additional/change of qualified person for a contractor licence

Form 20 Application for additional/change of qualified person for a contractor licence Department of Justice and Attorney-General Electrical Safety Office Form 20 Application for additional/change of qualified person for a contractor licence V12.06-2014 Electrical Safety Act 2002 INSTRUCTIONS:

More information

Estates and Facilities Handover Procedure

Estates and Facilities Handover Procedure Estates and Facilities Handover Procedure Guide to the requirements for Project Completion and Handover at the and West Suffolk NHS Foundation Trust Properties Updates Issue 1 Jan 2010.. Issue 5 July 2012

More information

DUTIES and GUIDANCE. for. BOARDS of MANAGEMENT. DEALING with ASBESTOS CONTAINING MATERIALS. before, during & after

DUTIES and GUIDANCE. for. BOARDS of MANAGEMENT. DEALING with ASBESTOS CONTAINING MATERIALS. before, during & after DUTIES and GUIDANCE for BOARDS of MANAGEMENT on DEALING with ASBESTOS CONTAINING MATERIALS before, during & after SCHOOL REFURBISHMENT WORKS, DEMOLITIONS AND BUILDING WORKS PROJECTS CONTENTS CONTENTS...2

More information

Conditions of Contract

Conditions of Contract Amberley Main Street Upgrade Contract No. 10/21 10/21 - Amberley Main Street Upgrades CC Page 1 of 24 C Contents Conditions of Contract Table of Contents Page GENERAL CONDITIONS OF CONTRACT 3 FIRST SCHEDULE

More information

KEPPEL GAS GAS SUPPLY HANDBOOK

KEPPEL GAS GAS SUPPLY HANDBOOK KEPPEL GAS GAS SUPPLY HANDBOOK Page 1 of 21 INTRODUCTION This Gas Supply Handbook ( Handbook ) is prepared by Keppel Gas to serve as a guide to eligible Customers who are current or future offtakers of

More information

ABSTRACT. The Guidelines Section F is related to the Purchasing requirements of NSQ100 (Chapter 7.4). Summary

ABSTRACT. The Guidelines Section F is related to the Purchasing requirements of NSQ100 (Chapter 7.4). Summary Page 1 / 9 ABSTRACT This document is the Section F to NSQ-100 Guidelines. Its objective is to help to the understanding of NSQ-100 requirements through some examples or recommendations and descriptions

More information

SCHEDULE 25. Business Continuity

SCHEDULE 25. Business Continuity SCHEDULE 25 Business Continuity 1. Scope 1.1 This schedule covers TfL s requirements in respect of: any circumstance or event which renders, or which TfL considers likely to render, it necessary or desirable

More information

Embedded Parts Introduction - Anchors

Embedded Parts Introduction - Anchors In the plant construction or process plants such as chemical, petrochemical, gas or power plants various disciplines are brought into contact and built on each other. Civil, mechanical, electro technical

More information

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which must

More information

PROMG4 Install mining backup services

PROMG4 Install mining backup services Overview This standard is about: 1 interpreting information 2 adopting safe and healthy working practices 3 selecting materials, components and equipment 4 preparing, installing, using and removing below

More information

Developer Constructed Headworks Process Information Guide

Developer Constructed Headworks Process Information Guide Information Guide CONTENTS PAGE 1.0 Introduction 3 1.1 Purpose and Objectives 3 1.2 The Developer Constructed Headwork Process 3 1.3 Fully Developer Funded Assets 3 2.0 The High Level process Steps 4 2.1

More information

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.

More information

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services Project Management Methodology Framework 1 - Executive Summary The purpose of this document is to introduce the University community

More information

Static Electricity. A Health and Safety Guideline for Your Workplace. What Are Some Sources of Static Electricity? What is Static Electricity?

Static Electricity. A Health and Safety Guideline for Your Workplace. What Are Some Sources of Static Electricity? What is Static Electricity? A Health and Safety Guideline for Your Workplace What is static electricity? What causes it? How is it hazardous? And, most importantly, how can it be controlled? All of these questions will be answered

More information

How To Write A Contract

How To Write A Contract Government Gazette Staatskoerant REPUBLIC OF SOUTH AFRICA REPUBLIEK VAN SUID-AFRIKA Vol. 582 Pretoria, 4 December Desember 2013 No. 37102 N.B. The Government Printing Works will not be held responsible

More information

AWWA Small Systems Pipe Repair Checklist, as published in July 2008 Opflow Question of the Month

AWWA Small Systems Pipe Repair Checklist, as published in July 2008 Opflow Question of the Month , as published in July 2008 Opflow Question of the Month Thanks to: Mike Grahek, Los Angeles Department of Water, Los Angeles, California Ahmad Havivian, Black & Veatch, Gaithersburg, Maryland David Kroon,

More information

Australian Industry Participation (AIP) Plan for Midal Cables Aluminium Rod and Conductor Facility Tomago NSW

Australian Industry Participation (AIP) Plan for Midal Cables Aluminium Rod and Conductor Facility Tomago NSW Midal Cables International Pty Ltd Australian Industry Participation (AIP) Plan for Midal Cables Aluminium Rod and Conductor Facility Tomago NSW This Document Mailed From, VICTORIA COBURN Associate Director

More information

Utilities and existing services

Utilities and existing services Construction Services Building standards for mechanical and electrical installations Utilities and existing services October 2012 Directorate: Environment Construction Services - Building standards for

More information

Unit LT01 Carry Out Routine Lift Truck Maintenance

Unit LT01 Carry Out Routine Lift Truck Maintenance Unit LT01 Carry Out Routine Lift Truck Maintenance UNIT OVERVIEW This unit is about conducting routine maintenance, adjustment and replacement activities as part of the periodic servicing of Lift Trucks.

More information

TABLE OF CONTENTS. I. Introduction 3. II. Contractor Pre-Qualification Criteria 4. III. Procedure for Application of Contractor Pre-Qualification 6

TABLE OF CONTENTS. I. Introduction 3. II. Contractor Pre-Qualification Criteria 4. III. Procedure for Application of Contractor Pre-Qualification 6 Related To FEWA Electricity Network (Transmission & Distribution) Version 1.0 December 2014 TABLE OF CONTENTS Page I. Introduction 3 II. Contractor Pre-Qualification Criteria 4 III. Procedure for Application

More information

APPLICATION PACKAGE FOR LISTING AS A WATER AND/OR WASTEWATER INFRASTRUCTURE PROVIDER FOR DESIGNERS, CONSTRUCTORS

APPLICATION PACKAGE FOR LISTING AS A WATER AND/OR WASTEWATER INFRASTRUCTURE PROVIDER FOR DESIGNERS, CONSTRUCTORS APPLICATION PACKAGE FOR LISTING AS A WATER AND/OR WASTEWATER INFRASTRUCTURE PROVIDER FOR DESIGNERS, CONSTRUCTORS (Major & minor works) TO THE MANAGING NEW DEVELOPMENTS PROCESS For information regarding

More information

Imperial College of Science, Technology & Medicine

Imperial College of Science, Technology & Medicine Imperial College of Science, Technology & Medicine SERVICE LEVEL AGREEMENT Maintenance Support to Projects Agreement approved Director of Estates..date Revisions date.date 1.0 Introduction The following

More information

SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals.

SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals. SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS PART 1: GENERAL 1.01 SCOPE A. Abandonment in place, by cutting and capping, of existing water mains, hydrants, service lines, and valves. B. Abandonment in

More information