1 THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL OCTOBER, 2013

2 TABLE OF CONTENTS 1. CHECKLIST PAGE NO. 2. CHECKLIST DETAILS A. Design Path 3 B. Property Acquisition 6 C. Outside Approvals 7 D. Pre-Construction Works 9 E. Contract Administration 10 F. Work By Delta 14 G. Contract Completion Services STANDARD LETTERS AND FORMS A. LETTERS Health Letters L.1 Advertisement L.2 Notice of Award L.3 Notice to Proceed L.4 Bid Bond Return L.5 Notice to Residents L.6 Notice of Substantial Completion L.7 Notice of Completion L.8 Notice of Acceptance L.9 B. FORMS DFO F.1 Addendum F.3 Progress Payment Certificate F.4 Change Order Forms F.5 Service Connection Forms F.6 Cost Data Sheet (Infrastructure Form) F.7 Pre-Construction Meeting Checklist F.8

3 GENERAL The Consultant is provided with this manual in order to facilitate an efficient systematic approach to projects. It is provided as a guideline and does not in any way alleviate the Consultant s responsibility for ensuring the works are designed in accordance with all applicable codes and standards and constructed in a cost effective, prudent manner. Any suggestions the Consultant may have to improve this process are appreciated. The Corporation of Delta (Delta) will assign a Delta Project Manager (Project Manager)to each project. All correspondence and communications relating to the project shall be directed through the Project Manager. All verbal communications to Delta from the Consultant shall be followed up with written confirmation of the discussion within a one week period or sooner as required by the Project Manager. CHECKLIST DETAILS A. DESIGN PATH 1. Initiate Work Order: (Delta) - Check Council Meeting Minutes for authorization of project by Council. - Check that a Certificate of Approval from the Ministry of Municipal Affairs, if required, has been received for the project.. - The Project Manager to initiate purchase order requisition through Capital Projects Manager. The Capital Projects Manager assigns a project ID number and forwards to Finance. 2. Pre-Design Meeting: (Consultant/Delta) - The Project Manager will arrange a pre-design meeting with the newly appointed Consultant to discuss the details of the project. - The Consultant will be provided with all as-constructed and legal information required for the project including all available digital information in the project vicinity as well as a copy of all pertinent engineering reports/studies. - A review of the project expectations and schedule will be undertaken. - The Project Manager will advise the Consultant of contract number and purchase order number(s).

4 Test Holes: (Consultant/Delta) - Should the Consultant indicate that test holes are required, the Project Manager will forward a work order to Delta s Engineering Operations with a sketch of approximate test hole locations as supplied by the Consultant. - The Consultant shall attend and record the test hole logs. - The Consultant shall review test hole results and accommodate soil conditions in the design. - Additional geotechnical investigation shall be arranged by the Consultant and approved by Delta as required. - It is the Consultant s responsibility to include all geotechnical information in the Contract Document. 4. Soil Corrosion Testing: (Consultant) - Should soil corrosion testing be required for a watermain and/or other utility installations, the Consultant shall take samples in conjunction with test holes. If test holes are not required, the Project Manager will initiate work order for separate excavations to be done by Delta Operations and coordinated by the Consultant. 5. Pre-Servicing: (Delta/Consultant) - The Project Manager will check with the Community Planning and Development (Development Services Section) to determine any requirements for pre-servicing of future lots and submit a key plan with description of proposed works if required. This information will be provided to the Consultant upon request. 6. Pre-Design Report: (Consultant) - The Consultant shall prepare a pre-design report of sufficient detail to fully address the design considerations and options applicable to the project. The report should detail the location, purpose, design alternatives/options and criteria for the project. - The Consultant shall make recommendations for the best design option.

5 The Project Manager shall provide a copy of the Pre-Design Report to the Deputy Director of Engineering (Operations) for circulation and comments (to be returned within one (1) week). - The Project Manager will assemble and forward comments within 2 weeks of receiving the Pre-Design Report. - The Consultant shall review all comments received from Delta and provide recommendations, comments and direction accordingly. 7. Interim Review Meetings: (Consultant/Delta) - The Project Manager/Consultant to arrange joint interim review meetings as required to ensure the project remains on track and on schedule. - Detailed design alternatives, property acquisition, outside approvals and preconstruction works are examples of pertinent issues. - The Consultant shall provide the Project Manager with all details required in order for Delta to proceed with property acquisition, outside approvals (where Consultant is unable to obtain) and pre-construction works. 8. Design: (Consultant/Delta) - Final design to be completed by the Consultant and submitted for the Project Manager s review, in accordance with specific terms outlines in the Request for Proposal - Design to normally include completed specifications and drawings (6 sets). 9. Drawings to Operations: (Delta) - The Project Manager to forward design drawings to the Deputy director of Engineering Operations for comments, when comments received, review with Engineer and then Consultant. 10. Fire Department Approval for Hydrants: - The Project Manager will forward 2 sets of watermain design drawings for the Fire Department s approval of fire hydrant locations. The drawings should be directed to the attention of Deputy Chief Fire Prevention.

6 11. Quantities: (Consultant) Use final design to determine project quantities. 12. Construction Estimate: (Consultant) - Use average unit rates with inflation as required to reflect the detail of work from recently tendered projects throughout the region and apply to above quantities to obtain the Engineer s estimate. 13. Specifications: (Consultant) - Use Delta s Engineering Master Specifications for each applicable section. Amend standard specifications by use of Special Provisions. - The contract documents shall be approved in their entirety by the Project Manager prior to tender. 14. Delta s Approval: - Consultant to forward final draft to the Project Manager for Delta s approval. B. PROPERTY ACQUISITION 1. Property Requested: - The consultant to determine from design the requirements for property acquisition. The Project Manager will initiate a request to the Land Solicitor, as required. 2. Right-of-Way Requests: - The consultant to provide recommendations to determine the restrictions on use of right-of-way. The Project Manager will initiate necessary changes to accommodate design requirements with the Land Solicitor. 3. Access Restrictions: - The Project Manager will consult with the Land Solicitor to determine access restrictions and special requirements for working on private property.

7 Right-of-Way Agreement Registration: - The Project Manager to confirm with the Land Solicitor that all Statutory right-of-way agreements have been finalized and registered prior to commencing construction. C. OUTSIDE APPROVALS The Consultant shall obtain all the outside approvals on behalf of Delta as listed below except for permits for test holes during the preliminary design stage. Test hole permits will be obtained by Delta s Operations personnel. All applications for approval shall be copied to the Project Manager. All approval permits shall be bound into the contract tender documents and referred to in the Special Provisions as requirements of the Contractor and payment included in the appropriate units. Where permits have not yet been received prior to tendering, a combination of notification of outstanding permits and typical conditions shall be included in the tender documents. 1. Fraser Health Authority: - The Consultant shall confirm with Delta that a Certificate of Health Approval has been received for the project where required. 2. Fisheries and Oceans Canada (DFO): - The Consultant shall complete a Project review and notification form, complete with any attachments and cover letter and submitit to the central address at DFO referralspacific@dfo-mpo.gc.ca. 3. Ministry of Environment: - The Consultant to submit design drawings and cover letter along with applicable applications to the Ministry of Environment. 4. Fortis BC: - The Consultant to submit design drawings and covering letter to BC Gas requesting permit to cross all high pressure gas mains. A permit is also required for any test holes during the design stage.

8 Ministry of Transportation and Infrastructure (M.O.T.I): - The Consultant to submit design drawings and covering letter to M.O.T.I, requesting a permit to carry out work on any M.O.T. road allowances, if the works are within M.O.T. jurisdiction. 6. Railway Crossings: - The Consultant to submit design drawings and covering letter to the project manager, addressed to the governing authority to receive construction requirements and permit. 7. BC Hydro Transmission Lines: - The Contractor to complete W.C.B. form 30M33, and the Consultant is to confirm this has been completed. - If working on a BC Hydro R-O-W, the consultant shall submit design drawings and covering letter to BC Hydro Property Services Division informing them of the project and to receive safety requirements and permit. - If working on the Municipal road allowance, the consultant is to contact BC Hydro site inspection 48 hours in advance of crossing at G.V.R.D./G.V.W.D.: - The Consultant must consult with Metro Vancouver during the design stage regarding tie-ins to G.V.W.D. mains. Submit design drawings and covering letter to G.V.W.D. to advise of any main crossings. 9. G.V.S. & D.D.: - The Consultant to submit design drawings and appropriate G.V.S. & D.D. application forms to Delta for execution and forwarding to G.V.S. & D.D. for the installation of sanitary sewer mains servicing new sewer areas only. Where connection to a G.V.S. & D.D. trunk sewer main is required, the design drawings and application form is also required. 10. Ministry of Forests, Lands and Natural Recourses Operations - Archaeology Branch: - Potential archaeological sites exist within Delta. The Consultant and the Project Manager shall review project locations to confirm designated

9 - 9 - archaeological areas prior to during the design phase. Appropriate action shall be undertaken if the project site is within a known archaeological area. Known archaeological areas within Delta can be found on DeltaMap under the Planning and Development Layer, through Delta s website, D. PRE-CONSTRUCTION WORKS 1. BC Hydro/Telus Pole Relocations: (Consultant) - The Consultant to submit design drawings and covering letter to Hydro/Tel advising them of the project complete with construction schedule and requesting an estimate of cost for the relocation of poles as shown on the drawings. 2. Delta Cable: (Consultant) - The Consultant to advise Delta Cable of project by sending a copy of the Telus letter and shall request Delta Cable to provide an estimate of cost to relocate their infrastructure. 3. BC Hydro/Telus and all other Underground Relocations: (Consultant) - It is unlikely that BC Hydro or Telus will relocate an underground installation to accommodate a proposed utility. If it is absolutely necessary, the Consultant shall submit design drawings and covering letter requesting an estimate of cost to relocate the given utility. - The Telus the Lightguide Transmission System is an extremely sensitive installation. Consultant to double check all underground installations by checking Telus as-built plans and notify Telus before proceeding with any test holes or crossings. 4. Fortis BC: (Consultant) - The Consultant to submit design drawings and covering letter to Fortis BC requesting estimate of cost to carry out relocations as shown on drawings. - The Consultant to request service location list for limits of project. 5. Watermain Fabrications and Tie-ins: (Consultant/Delta) - The Consultant to provide the Project Manager with details of fabrications

10 and tie-ins required to be undertaken by Engineering Operations and advise on the schedule required for each tie-in. - The Project Manager to forward G.L. number and design drawings for watermain fabrications and tie-ins to the Deputy Director of Engineering (Operations). 6. Materials Testing: (Consultant/Delta) - The Project Manager issues a Project Start-up memo with Delta s Material testing Consultant to coordinate materials testing during construction. Delta will pay invoices from the testing company directly. 7. Utility Companies: (Consultant) - Submit drawings to utility companies in the general vicinity of the proposed works. 8. Traffic Loops: (Consultant) - Make arrangements with Delta Roads Section or MoTi for temporary and permanent traffic loop replacements. Loops are not to be removed during construction without 2 weeks prior notification to the responsible authority. E. CONTRACT ADMINISTRATION 1. Advertisement: (Consultant/Delta) - When quantities are complete, the Consultant and the Project Manager shall set the date for tender issuance and complete letter L.2, Invitation to Tender. Delta will post this tender on BC Bid and be responsible for administering the tender process until closing. 2. Addendum: (Consultant) - Should an addendum be necessary, the Consultant shall provide all necessary technical data and drawings to the Project Manager so an addendum can be issued by Delta.

11 Tender Opening: (Delta/Consultant) - Arrangements for the Tender Opening are made by Delta s Finance Department. The Consultant is not required to attend the tender opening unless instructed otherwise. - Upon completion of the Tender Opening, the Consultant will be provided copies of all tender submissions, shall check and evaluate all tender submissions, and prepare a spreadsheet comparing at least the three (3) lowest bids. 4. Recommendation of Award: (Consultant) - The Consultant shall provide the Project Manager with a recommendation for award of Contract. The Project Manager shall then review and prepare a report to Council. 5. Report to Council: (Delta) - The Report to Council recommending acceptance of the Tender will be prepared by the Project Manager. Once all the comments have been received, the report must be submitted to the Director of Engineering by 12:00 noon Wednesday to be included on the agenda for an upcoming Council meeting. 6. Council Approval: (Delta) - The Project Manager to obtain and keep a copy of the Council Meeting Minutes for future reference on file. 7. Notice of Award: (Delta) - Notice of Award will be issued by Delta once Council approval is received, complete standard letter, L.3. This letter also provides the Contractor with a summary of Delta s requirements prior to the issuance of the Notice to Proceed. 8. Check Bonding: (Delta) - The Performance Bond and Labour and Materials Payment Bond are to be submitted to the Project Manager who will in turn provide these to Delta s Purchasing Manager for checking and binding into The Corporation of Delta Copy of contract.

12 Insurance: (Delta) - A complete copy (where required) of the Contractor s insurance policy must be submitted to the Project Manager who will in turn forward the documents to Delta s Risk Manager for checking and acceptance of insurance coverage. - The Project Manager will advise the Consultant when the insurance provided is acceptable to Delta. NOTE: The Contractor will not be permitted to start work before the insurance coverage is accepted by Delta. 10. Execute Contract: (Delta) - The Project Manager is to prepare three (3) copies of the contact documents for signing. They will include a copy of the addendum, a priced tender form, bid bond and completion of the Form of Contract (page C.1). The original Tender Form submitted by the Contractor is to be bound into The Corporation of Delta Copy contract document. A copy of the form of tender will be kept on file while the five copies of the contract documents are circulated for the appropriate signatures. 11. Construction Schedule: (Contractor/Consultant) - To be submitted by the Contractor at or before the pre-job meeting, but prior to the Notice to Proceed. The Consultant shall review schedule and provide recommendations relevant to acceptance to the Project Manager. 12. Notice to Proceed: (Delta) - Upon approval of the bonding, insurance, execution of the contract documents and conditions set forth in the Notice of Award, the Project Manager will issue the Notice to Proceed, standard letter L.4. The Contractors copy of the executed contract document will be forwarded with this letter. 13. Return Bid Bonds: (Delta) - After the Notice to Proceed has been issued, the Project Manager shall arrange for return the bid bonds to all the unsuccessful bidders accompanied by standard letter L.5.

13 14. Issue Drawings: (Consultant) The Consultant shall assemble the required number of contract drawings and documents and distribute to staff and the Contractor. - The Project Manager will forward one set of documents and drawings to Engineering Operations, one copy of drawings to the Engineering Inspector, one copy of drawings to the Survey Supervisor, and one copy to the project files. 15. Inspection Checklist for Consultant Projects: (Delta/Consultant) - The Project Manager will arrange a meeting with the Consultant including inspector(s) to go over the inspection checklist. 16. Arrange Survey/Inspection: (Consultant/Delta) - The Consultant shall arrange for all survey control points and inspection requirements for the project. - The Project Manager will undertake occasional supplemental site visits as required. 17. Pre-Construction Meeting: (Consultant/Delta) - The Project Manager shall arrange a pre-job meeting with the Contractor, Engineer, Consultant, and all other appropriate agencies. - The Project Manager will advise the Operations Superintendent(s) of the time and location of this meeting. - The Consultant shall take Minutes of the meeting and issue the construction drawings and documents to the Contractor. 18. Pre-Job Meeting Minutes: (Consultant/Delta) - The Consultant shall distribute Minutes to all those who attend the meeting. - The Project Manager to send a copy to the Deputy Director of Engineering (Operations) highlighting the schedule and emergency telephone numbers.

14 Notice to Council and Residents: (Delta) - The Project Manager shall arrange for delivery of a Notice to Residents on the project, see standard letter L.6. The Delta Inspector shall include this project in an updated list of current projects and Traffic Advisory notice which will then be distributed to Delta council and Delta s WebMaster. 20. Construction: (Consultant) - The Consultant shall submit on the Monday of each week a weekly construction report for the previous week s work to the Project Manager. - The Consultant shall hold regular bi-weekly construction site meetings. The Project Manager shall be advised as to when these meetings will be held in order to facilitate attendance as required. - Shop drawings shall be submitted by the Contractor to the Consultant for review.. Following their initial review, the Consultant shall forward the shop drawings to the Project Manager for additional comments which will be returned with 5 business days. The Consultant shall ensure all shop drawings meet: the design objectives, codes, and applicable standards and shall be responsible for final approval of all shop drawings. The Consultant shall forward a copy of the approved shop drawing to the Project Manager. 21. Progress Payment Certificate: (Consultant/Delta) - The Consultant shall prepare the progress payment certificate (see standards form F.4) by the 7 th day of each month complete with change order forms (see standard form F.5) attached. Consultant to ensure all signatures are obtained and forward complete with approved Statutory Declaration to the Project Manager for approval. The Project Manager shall prepare a job cost summary sheet itemizing each project and total cost to date. The completed package will be signed by the Capital Project Manager and submitted to the Administrative Assistant for checking and payment. 22. Service Cards and As-Built Drawings: (Consultant/Delta) - The Consultant shall record the location of all new and existing services on the appropriate Service Location Cards (see form F.6) and forward them to the Project Manager for processing. The Project Manager will forward this information to the Administration and Customer Service Manager for filing. - The Consultant shall compile all construction as-built information and create

15 record drawings in accordance with Delta s standard. Submission of asbuilts shall include 2 paper print sets and 1 copy of Civil 3D Auto cad 2012 drawing files. The Project Manager shall forward 1 drawing set and 1 electrical copy of the drawings to the GIS Supervisor for checking and microfilming. Where Operations is involved in the construction, a schematic diagram of the installation shall be prepared by the job foreman and submitted to the Project Manager. Elevations and dimensions required for the records shall be obtained by the Consultant. F. WORK BY DELTA 1. Plans and Work Orders: (Consultant) - The Consultant will provide the Project Manager with Issued for Construction design drawings for works to be undertaken by Delta. 2. Schedule: (Delta) - Engineering Operations will prepare an estimate of cost to do the work, advise the Project Manager, and schedule the job during the weekly scheduling meeting. 3. Pre-Construction Meeting: (Delta) - If required, the Project Manager will arrange a meeting with Superintendent, Foreman, Survey and Inspector. Schedule to be confirmed. 4. Arrange Survey and Inspection: (Delta) - The Survey Supervisor will arrange for survey. Inspection services by the Consultant are to be performed in a manner sufficient to allow for record drawings to be created and sealed by the consultant. 5. Construction: (Delta) - All work coordinated, supervised and carried out by Engineering Operations personnel. 6. Record Drawings: (Delta/Consultant) - Service cards and record field drawings to be completed by Engineering Operations. The Consultant shall prepare record drawings, signed and sealed.

16 G. CONTRACT COMPLETION SERVICES 1. Deficiency Inspection: (Consultant/Contract/Delta) - When the Contractor has completed all the work to the Consultant s satisfaction, a request in writing is required from the Contractor for a deficiency inspection of the works. The consultant shall have reviewed the works by the Contractor and be assured in his professional opinion that all works have been completed and no deficiencies except seasonal deficiencies are outstanding. A date/time for this inspection will be determined and the Consultant, Engineer, Project Manager, Contractor, appropriate Operations Superintendent(s) and other concerned bodies shall be invited to attend a site inspection coordinated by the Consultant. - The Consultant shall lead the inspection and record Minutes. Minutes shall be distributed to all attendees. 2. Notice of Substantial Completion: (Consultant/Delta) - Should the Contractor be unable to complete the project for reasons beyond his control, the Consultant shall make recommendation to Delta that Substantial Completion be given to the Contractor. The Project Manager shall prepare the Notice of Substantial Completion, standard letter L.7 for signing by the Capital Projects Manager or the Manager of Design and Construction. See Notice of Substantial Completion section of the General Conditions. 3. Rectify Deficiencies: (Consultant) - The Consultant shall ensure the Contractor rectifies all deficiencies prior to the release of the Deficiency Holdback as defined in Release of Deficiency Holdback section of the General Conditions. 4. Final Inspection: (Consultant/Delta/Contractor) - The Consultant, Project Manager, Contractor and the Operations personnel who attended the deficiency inspection shall be invited to the final inspection to ensure that all deficiencies have been rectified. The Consultant shall lead the inspection and record Minutes. Minutes shall be distributed to all attendees of both inspections. The Project Manager is to notify any other Delta personnel required to attend this inspection.

17 Payment of Recoverable Work Orders: (Delta/Contractor/Consultant) - Confirm that all recoverable work orders have been presented to the Contractor and that payment has been made. 6. Release Deficiency Holdback: (Consultant/Delta) - Upon completion of all deficiencies and the final inspection, the Consultant shall recommend the release of the Deficiency Holdback. 7. Notice of Completion: (Consultant/Delta) - The Contractor shall make written request for total Completion. - The Consultant shall recommend to Delta issuance of Notice of Completion to the Contractor. - The Project Manager shall prepare the Notice of Completion, standard letter L.8, for signing by the Capital projects Manager or Manager of Design and Construction. See Notice of Completion section of the General Conditions. - Engineering Operations to be notified of warrantee period and start of maintenance by way of copy of this letter. 8. Final Payment: (Consultant/Delta) - The Consultant to obtain from the Contractor a written statement that all claims have been presented and then prepare the final Progress Payment for issuance by Delta. See Final Progress Payment section of the General Conditions. The Project Manager will review and acquire Capital Project Manager s approval. The Final Progress Certificate will then be forwarded to the Administrative Assistant for checking and processing. 9. Release of Builder s Lien Act Holdback: (Consultant/Delta) - Upon expiry of the lien period, the Consultant shall forward the Statutory Declaration, confirmation that there are no affidavits or claims filed against the lands and Work Safe BC certificate to the Project Manager with a recommendation that the Holdback be released. The Capital Projects Manager will then instruct the Administrative Assistant to release the Holdback.

18 Infrastructure Form: (Consultant/Delta) - Upon completion of the final progress payment and the record drawings, the Consultant shall complete the Construction Data Sheet (F.7), and forward it to the Project Manager. - The Project Manager shall at this time confirm that the record drawings and updating of these base maps has been completed and is correct. 11. One Year Guarantee: (Consultant/Delta) - The Consultant shall notify the Project Manager of the impending expiration of the one year guarantee period a minimum of one month prior to this date and arrange an inspection of the works. - Before the expiry of the one year guarantee period, the Project Manager will advise the Operations Superintendent and request comments on any deficiencies. All remedial work required must be undertaken in accordance with the One Year Guarantee section of the General Conditions. 12. Notice of Acceptance: (Consultant/Delta) - The Consultant shall recommend to the Project Manager the Notice of Acceptance. - The Project Manager will prepare the Notice of Acceptance, standard letter L.9, for signing by the Capital Projects Manager or Manger of Design and Construction. See Notice of Acceptance section of the General Conditions.

PROCEDURE MANUAL FOR ENGINEERING CONSULTANTS

PROCEDURE MANUAL FOR ENGINEERING CONSULTANTS PROCEDURE MANUAL FOR ENGINEERING CONSULTANTS CITY OF GREATER SUDBURY ENGINEERING SERVICES DIVISION JUNE 2005 TABLE OF CONTENTS Chapter 1 - Reference Procedure Manuals and Specifications - CAD Drawing Requirements

More information

Bidding / Contracts General Information

Bidding / Contracts General Information Bidding / Contracts General Information We have provided this information sheet on various requirements and terminology when bidding on or completing various service and/or construction contracts for the

More information

Guide to the Letters of Assurance in the B.C. Building Code 2006 December, 2010 Edition 5a

Guide to the Letters of Assurance in the B.C. Building Code 2006 December, 2010 Edition 5a Guide to the Letters of Assurance in the B.C. Building Code 2006 December, 2010 Edition 5a Building & Safety Standards Branch Ministry of Public Safety & Solicitor General Province of British Columbia

More information

California Ironworkers Collectively Bargained Workers Compensation Program. Pre-Approval Process Application Information Eligibility Checklist.

California Ironworkers Collectively Bargained Workers Compensation Program. Pre-Approval Process Application Information Eligibility Checklist. California Ironworkers Collectively Bargained Workers Compensation Program Pre-Approval Process Application Information Eligibility Checklist for Signatory Employers & Insurance Carriers Memorandum Date:

More information

Consultancy Services Proposal

Consultancy Services Proposal Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847

More information

SUBDIVISION APPLICATION GUIDE

SUBDIVISION APPLICATION GUIDE SUBDIVISION APPLICATION GUIDE August 2013 This brochure provides an overview of the steps involved in the Subdivision Application process. This is a general guide only. It is not meant to replace bylaws

More information

VERSION 07-0 GOLD SEAL SAMPLE QUESTIONS CANADIAN CONSTRUCTION ASSOCIATION LEVEL "PRACTICE EXAMINATION" NATIONAL GOLD SEAL COMMITTEE

VERSION 07-0 GOLD SEAL SAMPLE QUESTIONS CANADIAN CONSTRUCTION ASSOCIATION LEVEL PRACTICE EXAMINATION NATIONAL GOLD SEAL COMMITTEE VERSION 07-0 GOLD SEAL SAMPLE QUESTIONS CANADIAN CONSTRUCTION ASSOCIATION LEVEL "PRACTICE EXAMINATION" NATIONAL GOLD SEAL COMMITTEE SAMPLE EXAM QUESTIONS FOR GOLD SEAL APPLICANTS VERSION 07-0 Multiple

More information

Request for Proposals April 10, 2008 Freshwater Brook Sewer & Water Project Contract Administration & Inspection Page No. 1 TABLE OF CONTENTS

Request for Proposals April 10, 2008 Freshwater Brook Sewer & Water Project Contract Administration & Inspection Page No. 1 TABLE OF CONTENTS REQUEST FOR PROPOSAL Freshwater Brook Sewer and Water Project April 2008 Closing Date: Wednesday, April 23, 2008 Closing Time: 3:00 p.m. (Local Time) Halifax Water 200 Bluewater Road, Suite 201 P.O. Box

More information

Construction Notification and Start-Up

Construction Notification and Start-Up The University of British Columbia Land and Building Services Prepared by: Frank Geyer Work Procedure Approved by: David Barnes Construction Notification and Start-Up Issue Date: 08 October 2002 Replaces:

More information

Description of Selected Services under the UN CPC system in which the EC made Market Access Commitments in the EPA

Description of Selected Services under the UN CPC system in which the EC made Market Access Commitments in the EPA Description of Selected Services under the UN CPC system in which the EC made Market Access Commitments in the EPA 7471 Travel agency and tour operator services Services rendered for passenger travel by

More information

Right-of-Way Use Permit Application Instructions

Right-of-Way Use Permit Application Instructions Please type or print clearly. Incomplete applications will not be processed. Typical processing time is 5 business days. 1. Property Address (MANDATORY) Applicant must provide a physical property address

More information

Life of a Project. Phase General Activities Specific Activities Notes Expected Time Frame

Life of a Project. Phase General Activities Specific Activities Notes Expected Time Frame 1.0 Inception 1.1 Project Request from Client / User 1.2 Assignment 1.3 1.4 1.5 1.6 1.7 1.8 Preliminary Project Charter Submit Project Charter to Obtain internal project number Initial Project Authorization

More information

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of

More information

CITY OF HAMTRAMCK REQUEST FOR PROPOSALS PROFESSIONAL ARCHITECHURAL AND ENGINEERING SERVICES

CITY OF HAMTRAMCK REQUEST FOR PROPOSALS PROFESSIONAL ARCHITECHURAL AND ENGINEERING SERVICES CITY OF HAMTRAMCK REQUEST FOR PROPOSALS PROFESSIONAL ARCHITECHURAL AND ENGINEERING SERVICES ADVERTISE DATE September 12, 2014 QUESTION DEADLINE September 22, 2014 Submitted in writing via email to the

More information

ALABAMA STATE DEPARTMENT OF EDUCATION

ALABAMA STATE DEPARTMENT OF EDUCATION ALABAMA STATE DEPARTMENT OF EDUCATION CONSTRUCTION REQUIREMENTS FOR COUNTY AND CITY PUBLIC SCHOOLS PROJECTS TOTALLY FUNDED WITH LOCAL FUNDS AND SUBMITTAL OF ALL PLANS AND SPECIFICATIONS Thomas R. Bice,

More information

SITE PLAN APPROVAL PROCESS INTRODUCTION

SITE PLAN APPROVAL PROCESS INTRODUCTION SITE PLAN APPROVAL PROCESS INTRODUCTION File Manager System for Site Plan Approval Process Site Plan Control in the City of London The City of London utilizes site plan control to ensure high quality site

More information

Demo Permit Guide For Homeowners

Demo Permit Guide For Homeowners Demo Permit Guide For Homeowners Building Services Tel: 705-436-3710 ext. 3504 or 3506 Fax: 705-436-7120 2101 Innisfil Beach Road, Innisfil, ON L9S 1A1 Website: www.innisfil.ca A Demo Permit Guide for

More information

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL August 2008 TABLE OF CONTENTS Section 1 - Introduction... 3 1.1 Defining Plan Quality...

More information

Contractor Safety Management

Contractor Safety Management 1.0 Introduction Memorial University will ensure that a diligent contractor management process is established. This procedure establishes requirements for contract administration and oversight of contractor

More information

CHAPTER 10 PERMIT PROCEDURES AND BONDING REQUIREMENTS FOR CONTRACTORS

CHAPTER 10 PERMIT PROCEDURES AND BONDING REQUIREMENTS FOR CONTRACTORS I "i,, I, 1 " CHAPTER 10 PERMIT PROCEDURES AND BONDING REQUIREMENTS FOR CONTRACTORS CHAPTER 10 PERMIT PROCEDURES A N D BONDING REQUIREMENTS FOR CONTRACTORS, Section I -, INDEX :, - % I I,,J Topic b 101

More information

5047P Architectural and Engineering Services for the Cambie Fire Hall and Ambulance Station Project- Addendum #2

5047P Architectural and Engineering Services for the Cambie Fire Hall and Ambulance Station Project- Addendum #2 January 23, 2013 Business and Financial Services Department Finance Division Telephone: 604-276-4218 Fax: 604-276-4162 Attention: To All Proponents Dear Bidders: Re: 5047P Architectural and Engineering

More information

THE CORPORATION OF THE CITY OF BURLINGTON D1 - AGREEMENT

THE CORPORATION OF THE CITY OF BURLINGTON D1 - AGREEMENT Agreement 2006 Page 1 THE CORPORATION OF THE CITY OF BURLINGTON D1 - AGREEMENT THIS AGREEMENT made in triplicate this day of 20 THE CORPORATION OF THE CITY OF BURLINGTON (hereinafter called "the City")

More information

Suggested Procedures for School Boards

Suggested Procedures for School Boards Suggested Procedures for School Boards The Chronology of a Project: Some of the steps described may not apply to certain types of projects, or might occur concurrently with others. As you confer with the

More information

LOUISIANA CAPITAL IMPROVEMENT PROJECTS PROCEDURE MANUAL FOR DESIGN AND CONSTRUCTION

LOUISIANA CAPITAL IMPROVEMENT PROJECTS PROCEDURE MANUAL FOR DESIGN AND CONSTRUCTION LOUISIANA CAPITAL IMPROVEMENT PROJECTS PROCEDURE MANUAL FOR DESIGN AND CONSTRUCTION 1985 Edition INCLUDING ADDENDA ONE AND TWO M.J. AMike@ Foster, Jr. Governor Mark C. Drennen, Commissioner of Administration

More information

Summary of Request for Applications to participate in a tender process for twenty year licenses together with the acquisition of the businesses of

Summary of Request for Applications to participate in a tender process for twenty year licenses together with the acquisition of the businesses of Summary of Request for Applications to participate in a tender process for twenty year licenses together with the acquisition of the businesses of two existing mobile network operators Issued by the Telecommunications

More information

Permit No. Permit Fee: $295.00. Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: E-mail Address:

Permit No. Permit Fee: $295.00. Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: E-mail Address: City of Woodland Park Internet Service Provider (IPS) Permit for Installation of Telecommunication Infrastructure within City Owned Rights-of-Way (up to five locations per single permit) Permit No. Permit

More information

The National Council of the Slovak Republic has adopted the following Act: Article I. 1 Scope of the act

The National Council of the Slovak Republic has adopted the following Act: Article I. 1 Scope of the act Slovak Investment and Trade Development Agency Address: Trnavská cesta 100, 821 01 Bratislava, Slovak Republic Tel.: +421 2 58 260 100, Fax: +421 2 58 260 109, E-mail: invest@sario.sk, www.sario.sk Act

More information

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT ADVERTISEMENT: REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT The WALTON COUNTY SCHOOL DISTRICT will receive

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

TABLE OF CONTENTS. Purchasing and Contracts Division... 1. Purchasing Policies and Procedures... 1. The Competitive Process... 2

TABLE OF CONTENTS. Purchasing and Contracts Division... 1. Purchasing Policies and Procedures... 1. The Competitive Process... 2 TABLE OF CONTENTS Title Page Purchasing and Contracts Division... 1 Purchasing Policies and Procedures... 1 The Competitive Process... 2 Vendor Participation... 2 Vendor Database... 2 Web Site Information...

More information

Project Management Procedures

Project Management Procedures 1201 Main Street, Suite 1600 Columbia, South Carolina 29201 Project Management Procedures Start Up The grant becomes effective upon return of one copy of the grant award executed by the Chief Executive

More information

GUIDELINE. Professional Engineers Providing Project Management Services. Published by Association of Professional Engineers of Ontario

GUIDELINE. Professional Engineers Providing Project Management Services. Published by Association of Professional Engineers of Ontario GUIDELINE Professional Engineers Providing Project Management Services 1991 Published by Association of Professional Engineers of Ontario CONTENTS FOREWORD...3 1.0 GENERAL INFORMATION AND DEFINITIONS...3

More information

RURAL UTILITIES SERVICE

RURAL UTILITIES SERVICE Rural Development United States Department of Agriculture RURAL UTILITIES SERVICE RUS Bulletin 1738-2 Rural Broadband Access Loan and Loan Guarantee Advance and Construction Procedures Guide Page 1 According

More information

(House and Land) Approved by the Nova Scotia Real Estate Commission for use by Industry Members under the Real Estate Trading Act.

(House and Land) Approved by the Nova Scotia Real Estate Commission for use by Industry Members under the Real Estate Trading Act. AGREEMENT OF PURCHASE & SALE FOR TURN KEY NEW CONSTRUCTION (House and Land) Approved by the Nova Scotia Real Estate Commission for use by Industry Members under the Real Estate Trading Act The Buyer of

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services

More information

APPENDIX "F' TREE REMOVAL F-1

APPENDIX F' TREE REMOVAL F-1 APPENDIX "F' TREE REMOVAL F-1 TABLE OF CONTENTS Page 1.0 Purpose...3 2.0 Objectives...3 3.0 Definitions...3 4.0 Statutory Authority...5 5.0 Responsibility...5 6.0 Tree Removal Criteria...6 7.0 The Tree

More information

Developer Constructed Headworks Process Information Guide

Developer Constructed Headworks Process Information Guide Information Guide CONTENTS PAGE 1.0 Introduction 3 1.1 Purpose and Objectives 3 1.2 The Developer Constructed Headwork Process 3 1.3 Fully Developer Funded Assets 3 2.0 The High Level process Steps 4 2.1

More information

Commercial Fax : 416-216-5705. COMMERCIAL TITLE INSURANCE ORDER FORM (Ontario Form) PAGE 1 of 5 LAW FIRM INFORMATION

Commercial Fax : 416-216-5705. COMMERCIAL TITLE INSURANCE ORDER FORM (Ontario Form) PAGE 1 of 5 LAW FIRM INFORMATION Royal Bank Plaza, North Tower 416-307-3300 200 Bay Street, Suite 2600 888-667-5151 Toronto, ON M5J 2J2 www.stewart.ca Commercial Fax : 416-216-5705 COMMERCIAL TITLE INSURANCE ORDER FORM (Ontario Form)

More information

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26 Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain

More information

LAKEHAVEN UTILITY DISTRICT. Developer Extension Agreement Application

LAKEHAVEN UTILITY DISTRICT. Developer Extension Agreement Application Applicant shall indicate that the required information has been provided or is not applicable to the project by placing the appropriate mark in the first column of this checklist. Missing or incomplete

More information

Let Us Give Utilities the Respect that they Deserve.

Let Us Give Utilities the Respect that they Deserve. Water & Sewer Utilities Miscellaneous Design and Plan Preparation Guidelines Issued by: Ray Mowla, P.E. Jefferson Parish Department of Engineering, Utilities Section The purpose of issuing these miscellaneous

More information

REAL ESTATE SELLING YOUR HOME

REAL ESTATE SELLING YOUR HOME Introduction Congratulations on the sale of your home. Selling a home is a major decision and we would like to assist you with the legal requirements. In the event that you choose RDM Lawyers, you can

More information

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland

More information

CHAPTER 10 - PERMIT PROCEDURES AND BONDING REQUIREMENTS

CHAPTER 10 - PERMIT PROCEDURES AND BONDING REQUIREMENTS CHAPTER 10 - PERMIT PROCEDURES AND BONDING REQUIREMENTS 10.1 APPLICATION REQUIREMENTS AND PROCEDURES 10.1.1 A permit shall be required for any construction or installation within the public right-of-way

More information

Development Variance Permit Application Package

Development Variance Permit Application Package When do I need a Development Variance Permit? Development Variance Permit Application Package If my proposed development does not meet the standards set out in the Zoning Regulation Bylaw on matters that

More information

Right-of-Way Permit Application Process (Plans that affect District owned or maintained right-of-way)

Right-of-Way Permit Application Process (Plans that affect District owned or maintained right-of-way) Flood Control District of Maricopa County (District) 2801 W. Durango Street Phoenix, AZ 85009 Telephone: 602-506-4583 or 602-506-5476 Fax: 602-506-1663 Right-of-Way Permit Application Process (Plans that

More information

Request for Quote Number: 2015-06-PRC Baseball Diamond Backstop Re-Fence

Request for Quote Number: 2015-06-PRC Baseball Diamond Backstop Re-Fence Request for Quote Number: 2015-06-PRC Baseball Diamond Backstop Re-Fence Sealed request for quotes will be received by Brian Tocheri, CAO/Clerk at 341 10 th St. Hanover, Ontario, N4N 1P5 until 2:00 pm,

More information

SPECIAL PROVISIONS - GENERAL

SPECIAL PROVISIONS - GENERAL SPECIAL PROVISIONS - GENERAL SPECIAL PROVISIONS - GENERAL INDEX No. Description Page G1 Execution of Contract 1 G2 Failure to Execute Contract 1 G3 Commencement and Completion 2 G4 Local Labour 2 G5 Non-Resident

More information

REQUEST FOR PROPOSALS For. Kelowna and Vernon Hospitals Project

REQUEST FOR PROPOSALS For. Kelowna and Vernon Hospitals Project REQUEST FOR PROPOSALS For The Kelowna and Vernon Hospitals Project VOLUME 2 of 4 Instructions to Proponents Closing Time: Delivery Address: 3:00 pm (local time) Thursday, March 6,2008 Kelowna and Vernon

More information

CONTRACT ADMINISTRATION. Procedures

CONTRACT ADMINISTRATION. Procedures CONTRACT ADMINISTRATION Procedures Check the Capital Project Delivery web site to ensure this is the current version. Index Section Page Introduction 1 Contract Administration Final Design PS&E / Advertising

More information

TENDER FOR ROOF REPAIR FOR THE NSLC S METEGHAN RETAIL STORE NOVA SCOTIA LIQUOR CORPORATION 93 CHAIN LAKE DRIVE HALIFAX, NOVA SCOTIA B3S 1A3

TENDER FOR ROOF REPAIR FOR THE NSLC S METEGHAN RETAIL STORE NOVA SCOTIA LIQUOR CORPORATION 93 CHAIN LAKE DRIVE HALIFAX, NOVA SCOTIA B3S 1A3 TENDER FOR ROOF REPAIR FOR THE NSLC S METEGHAN RETAIL STORE NOVA SCOTIA LIQUOR CORPORATION 93 CHAIN LAKE DRIVE HALIFAX, NOVA SCOTIA B3S 1A3 NSLC REFERENCE NO: CN-04-l-16 NSLC Contact: Email: Stephen Bayer

More information

How To Get A Job Done

How To Get A Job Done CUMBERLAND COUNTY COMMUNITY DEVELOPMENT (CCCD) HOUSING REHABILITATION PROGRAM PO DRAWER 1829 707 EXECUTIVE PLACE FAYETTEVILLE, NC 28302-1829 CONTRACTOR QUALIFICATIONS: REHABILITATION CONTRACTOR'S HANDBOOK

More information

WHS Contractor Management Procedure

WHS Contractor Management Procedure Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety

More information

AGREEMENT FOR THE PROVISION OF CONSULTANCY ENGINEERING SERVICES

AGREEMENT FOR THE PROVISION OF CONSULTANCY ENGINEERING SERVICES AGREEMENT FOR THE PROVISION OF CONSULTANCY ENGINEERING SERVICES This agreement is made and entered into, on day the. of, 1991 by and between: Mr/. of P.O. Box.. hereinafter refereed to as the "Owner" on

More information

REQUEST FOR EXPRESSIONS OF INTEREST AND STATEMENTS OF QUALIFICATIONS

REQUEST FOR EXPRESSIONS OF INTEREST AND STATEMENTS OF QUALIFICATIONS 1 REQUEST FOR EXPRESSIONS OF INTEREST AND STATEMENTS OF QUALIFICATIONS Title: TEMPORARY FLOW MONITORING SERVICES Project No.: 4712-2010 FOR MINOR WORKS PROJECTS RFEOI/SOQ for Project # 4712-2010 Page 1

More information

Developer s Guide To Turnkey Subdivisions. The Saskatchewan Turnkey Program

Developer s Guide To Turnkey Subdivisions. The Saskatchewan Turnkey Program Developer s Guide To Turnkey Subdivisions The Saskatchewan Turnkey Program Contents 1.0 Program Overview... 3 2.0 Eligibility Criteria... 3 3.0 Cable Companies... 3 4.0 Developer Responsibilities... 3

More information

Public Works Contract Completion

Public Works Contract Completion I. Policy A. The Port will formally identify when public works construction contracts are completed in order to administer payments in accordance with Washington statutes and in order to identify warranty

More information

BUILDING MAINTENANCE. Tender for Supply and Installation of Inverter Based AC Units (Split Units) for PWD Workshop Store Room and Office

BUILDING MAINTENANCE. Tender for Supply and Installation of Inverter Based AC Units (Split Units) for PWD Workshop Store Room and Office BUILDING MAINTENANCE Tender for Supply and Installation of Inverter Based AC Units (Split Units) for PWD Workshop Store Room and Office August 2015 Instructions to Tenderers 1. The contract conditions

More information

CHAPTER 7: SUBDIVISION CONSTRUCTION, INSPECTION AND BONDING. 7.05 Subdivision Improvement Performance Bond Requirements

CHAPTER 7: SUBDIVISION CONSTRUCTION, INSPECTION AND BONDING. 7.05 Subdivision Improvement Performance Bond Requirements CHAPTER 7: SUBDIVISION CONSTRUCTION, INSPECTION AND BONDING 7.00 Construction 7.01 Inspection and Testing of Improvements 7.02 Approval of Improvements 7.03 City Engineer s Acceptance of All Improvements

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

Design Deliverables Checklist

Design Deliverables Checklist S a n i tary Sewer Overflow (SSO) Control a n d Wastewater Facilities Program Deliverables Checklist City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared by:

More information

How To Audit A Financial Institution

How To Audit A Financial Institution Canadian Public Accountability Board (CPAB) Rules Section 100 Section 200 Section 300 Section 400 Section 500 Section 600 Section 700 Section 800 Section 900 General Participation and Withdrawal from Participation

More information

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals

More information

AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS

AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS Conducted By GASKIN CONSTRUCTION SERVICES PTY LTD TABLE OF CONTENTS SECTIONS Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7

More information

City of Coquitlam REQUEST FOR PROPOSALS RFP No. 14-01-14 CONSTRUCTION MANAGEMENT SERVICES

City of Coquitlam REQUEST FOR PROPOSALS RFP No. 14-01-14 CONSTRUCTION MANAGEMENT SERVICES City of Coquitlam REQUEST FOR PROPOSALS RFP No. 14-01-14 CONSTRUCTION MANAGEMENT SERVICES Proposals will be received on or before 2:00 pm local time Wednesday, March 12, 2014 (Closing date and time) Obtaining

More information

Request for Proposals. Site C Clean Energy Project. Worker Accommodation RFP #1807

Request for Proposals. Site C Clean Energy Project. Worker Accommodation RFP #1807 RFP #1807 Issued SUMMARY OF KEY INFORMATION Page i RFP TITLE CONTACT PERSON The title of this RFP is: RFP #1807 Worker Accommodation Proponents should use this title on all correspondence. The Contact

More information

PRIME CONSULTANT SERVICES

PRIME CONSULTANT SERVICES GUIDELINES FOR Professional Engineers providing PRIME CONSULTANT SERVICES 1.0 INTRODUCTION 1.1 PURPOSE OF GUIDELINES The "Guidelines for Professional Engineers providing Prime Consultant Services" have

More information

MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES

MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES This Master Agreement made this 11 day of December, 2012, by and between the St. Lucie County School Board (hereinafter referred to as the School Board

More information

CONSTRUCTION MANAGER-AT-RISK AGREEMENT. between. Houston Independent School District. and. [insert legal name of firm] for

CONSTRUCTION MANAGER-AT-RISK AGREEMENT. between. Houston Independent School District. and. [insert legal name of firm] for DRAFT CONSTRUCTION MANAGER-AT-RISK AGREEMENT between Houston Independent School District and [insert legal name of firm] for [insert name of school or project] CONSTRUCTION MANAGER-AT-RISK AGREEMENT TABLE

More information

Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015

Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015 Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015 For PROJECT : Renovation and Repair of Atlanta Jewish Academy

More information

Territory and Municipal Services Reference Document 10

Territory and Municipal Services Reference Document 10 Territory and Municipal Services Reference Document 10 REQUIREMENTS FOR SOFT LANDSCAPE CONSOLIDATION AND HANDOVER Issue 2 Revision 2 APPROVED FOR ISSUE Approved by: Fay Steward Executive Director Land

More information

Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way

Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way Public Works Department Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way October 2015 HillsboroughCounty.org HILLSBOROUGH COUNTY Office of the County

More information

DEVLOPMENT APPLICATION PROCEDURES

DEVLOPMENT APPLICATION PROCEDURES DEVLOPMENT APPLICATION PROCEDURES Bylaw No. 2444 and amendments thereto CONSOLIDATED FOR CONVENIENCE ONLY This is a consolidation of the bylaws listed below. The amending bylaws have been consolidated

More information

Small Business Permit Service

Small Business Permit Service Small Business Permit Service Building Permit Requirements For a Unit Finish or Interior Alteration Industrial, Commercial or Institutional Occupancies Building Permit Application The following documents

More information

TOWN OF RAYNHAM APPLICATION FOR COMMERCIAL BUILDING PERMIT

TOWN OF RAYNHAM APPLICATION FOR COMMERCIAL BUILDING PERMIT MAP PARCEL TOWN OF RAYNHAM APPLICATION FOR COMMERCIAL BUILDING PERMIT This form is an application for approval, not a building permit. Fill out application carefully. Applications lacking required data

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR)

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) For the Project: CITY OF KATY NEW KATY FIRE STATION #2 Issued: August 13, 2015 Katy Fire Station #2 August 13, 2015 Page 1 of 17 Request

More information

Form C: Application for Construction Insurance

Form C: Application for Construction Insurance Form C: Application for Construction Insurance Broker Information: Broker: BFL CANADA Insurance Services Inc. Contact: Address: 200, 1177 West Hastings Street, Vancouver, BC, V6E 2K3 Phone Number: 604-669-9600

More information

SCOPE OF APPLICATION AND DEFINITIONS

SCOPE OF APPLICATION AND DEFINITIONS Unofficial translation No. 398/1995 Act on Foreign Insurance Companies Issued in Helsinki on 17 March 1995 PART I SCOPE OF APPLICATION AND DEFINITIONS Chapter 1. General Provisions Section 1. Scope of

More information

Bylaw No. 8174. The City Administration Bylaw, 2003

Bylaw No. 8174. The City Administration Bylaw, 2003 Bylaw No. 8174 The City Administration Bylaw, 2003 Codified to Bylaw No. 9043 July 18, 2012 Bylaw No. 8174 The City Administration Bylaw, 2003 The Council of The City of Saskatoon enacts: Title 1. This

More information

Guide to Preparing a Quality Management Plan for Registered Code Agencies (under the Building Code Act, 1992 and Building Code )

Guide to Preparing a Quality Management Plan for Registered Code Agencies (under the Building Code Act, 1992 and Building Code ) Guide to Preparing a Quality Management Plan for Registered Code Agencies (under the Building Code Act, 1992 and Building Code ) March 2005 Building and Development Branch Ministry of Municipal Affairs

More information

Commercial Fax : 403-264-6861 / 1-866-765-0514. COMMERCIAL TITLE INSURANCE ORDER FORM (Western Canada Form) PAGE 1 of 5 LAW FIRM INFORMATION

Commercial Fax : 403-264-6861 / 1-866-765-0514. COMMERCIAL TITLE INSURANCE ORDER FORM (Western Canada Form) PAGE 1 of 5 LAW FIRM INFORMATION 520-5 Avenue SW, Suite 300 403-538-5125 Calgary, Alberta T2P 3R7 866-515-8401 www.stewart.ca Commercial Fax : 403-264-6861 / 1-866-765-0514 COMMERCIAL TITLE INSURANCE ORDER FORM (Western Canada Form) PAGE

More information

Owner-User Pressure Equipment Integrity Management Requirements

Owner-User Pressure Equipment Integrity Management Requirements the pressure equipment safety authority Owner-User Pressure Equipment Integrity Management Requirements AB-512 Edition 2, Revision 0 Issued 2015-06-25 Owner-user Pressure Equipment Integrity Management

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 2014

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 2014 for Inspecting and Certifying Buildings and Works Building Control Regulations 2014 February, 2014 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1 1.3 Application

More information

LEGAL ARTICLE FROM DE GRANDPRÉ CHAIT LLP INTERLAWYERS

LEGAL ARTICLE FROM DE GRANDPRÉ CHAIT LLP INTERLAWYERS LEGAL ARTICLE FROM DE GRANDPRÉ CHAIT LLP INTERLAWYERS CONSTRUCTION PROJECTS IN QUEBEC By David H. Kauffman dkauffman@dgclex.com Plus ça change, plus c est la même chose. Planning for a construction project

More information

Developer s/consultants Field Services Guidelines

Developer s/consultants Field Services Guidelines Developer s/consultants Field Services Guidelines 2007 Engineering and Works Department DEVELOPER S/CONSULTANT S FIELD SERVICES GUIDELINES Fourth Electronic Edition February 2007 STATEMENT OF COMPLETION

More information

INTRODUCTION... 3. 1.0 Purpose... 4. 2.0 Policy... 4. Exception for Short-Term Workplace Visits... 4. Relevant Legislation and Regulations...

INTRODUCTION... 3. 1.0 Purpose... 4. 2.0 Policy... 4. Exception for Short-Term Workplace Visits... 4. Relevant Legislation and Regulations... March 2006 INTRODUCTION... 3 1.0 Purpose... 4 2.0 Policy... 4 Exception for Short-Term Workplace Visits... 4 Relevant Legislation and Regulations... 5 Definitions... 5 Contractor Safety Coordination Overview...

More information

GUIDELINES FOR AUGUST 1995

GUIDELINES FOR AUGUST 1995 GUIDELINES FOR ELECTRICAL ENGINEERING SERVICES AUGUST 1995 PUBLISHED BY: PROFESSIONAL ENGINEERS AND GEOSCIENTISTS OF NEWFOUNDLAND & LABRADOR (PEGNL) P.O. Box 21207, St. John's, NL A1A 5B2 Telephone: (709)

More information

CHAPTER 48-01.2 PUBLIC IMPROVEMENT BIDS AND CONTRACTS

CHAPTER 48-01.2 PUBLIC IMPROVEMENT BIDS AND CONTRACTS CHAPTER 48-01.2 PUBLIC IMPROVEMENT BIDS AND CONTRACTS 48-01.2-01. Definitions. In this chapter, unless the context otherwise requires: 1. "Agency construction management" means a public improvement delivery

More information

Permit Number: Date Issued: Permit Fee: Invoice Number:

Permit Number: Date Issued: Permit Fee: Invoice Number: City of Burnaby Page 1 of 4 Encroachment Application and Permit Agreement (Testpit, Monitoring Well, Borehole or Vacuum-Hole Installation, Minor Excavation or other Non-Intrusive Work) Rev. 5-2013 Permit

More information

Construction Management Standards of Practice

Construction Management Standards of Practice Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388

More information

Statutes in translation Please note that this translations are not official translations. The translation is furnished for information purposes only

Statutes in translation Please note that this translations are not official translations. The translation is furnished for information purposes only Statutes in translation Please note that this translations are not official translations. The translation is furnished for information purposes only and the documents are not legal documents. The texts

More information

Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter.

Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. SCHEDULE OF CONSULTANT S SERVICES Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. Project (Insert name and description

More information

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices : A CDOT Guide to Better Project Management Practices Project Management practices have been a part of the CDOT culture for many years. However, with a transitioning workforce and increasing demands, it

More information

The Court of Protection Rules 2007

The Court of Protection Rules 2007 STATUTORY INSTRUMENTS 2007 No. 1744 (L. 12) MENTAL CAPACITY, ENGLAND AND WALES The Court of Protection Rules 2007 Made - - - - - 25th June 2007 Laid before Parliament 4th July 2007 Coming into force -

More information

O N T A R I O B U I L D I N G C O D E

O N T A R I O B U I L D I N G C O D E Professional Engineers Ontario GUIDELINE P R O F E S S I O N A L E N G I N E E R S P R O V I D I N G G E N E R A L R E V I E W O F C O N S T R U C T I O N A S R E Q U I R E D B Y T H E O N T A R I O B

More information

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1 REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Project Information PS-0748-A Page 1 5/4/2016 Table of Contents Project Budget Worksheet Program Plan Project Location (Site Plan) Scope of Services

More information

Building Mechanical Inspector Senior Building Mechanical Inspector Principal Building Mechanical Inspector Chief Building Mechanical Inspector - 2

Building Mechanical Inspector Senior Building Mechanical Inspector Principal Building Mechanical Inspector Chief Building Mechanical Inspector - 2 THE CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION 10-25-85 BUILDING MECHANICAL INSPECTOR, 4251 SENIOR BUILDING MECHANICAL INSPECTOR, 4253 PRINCIPAL BUILDING MECHANICAL INSPECTOR, 4255

More information

Exhibit C: Scope of Work and Schedule of Deliverables

Exhibit C: Scope of Work and Schedule of Deliverables Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza

More information

CSC-DIVISION 1-MASTER SECTIONS Description

CSC-DIVISION 1-MASTER SECTIONS Description CSC-DIVISION 1-MASTER SECTIONS Description 01 11 00 Summary of Work by Consultant 01 12 00 Multiple Contract Summary by Consultant 01 14 00 Work Restrictions see below 01 21 00 Allowances by Consultant

More information

A/E Consultant Handbook Engineering Department. Facilities Engineering Services Section April 2008

A/E Consultant Handbook Engineering Department. Facilities Engineering Services Section April 2008 A/E Consultant Handbook April 2008 The primary objective at Fermilab is that operations be conducted in a safe, deliberate and controlled manner. The role of the FESS/E procedures is to provide the best

More information