Status Report Guidelines
|
|
- Loreen Cameron
- 8 years ago
- Views:
Transcription
1 Values - Goals.doc 1 of 8 10/27/2010
2 Values - Goals Table of Contents 1 Status Report Overview Status Report Type Instructions Monthly Instructions Weekly... 6.doc 2 of 8 10/27/2010
3 Values - Goals 1 Status Report Overview This document provides guidance on determining the most appropriate status report template for a project. There are three official templates: Dashboard, Monthly Status Report and Weekly Status Report. The specific report required is contingent upon: funding type, complexity level 1 and/or management discretion. The recommended status report types below are guidelines that can be adjusted by the management team and/or sponsor. 1.1 Status Report Type Dashboards are required for all Capital projects. At this time, the dashboards are created by the project advisors with data and assistance from the project managers who run the actual Capital projects. Non-Capital projects with a Complexity Level of 2 or 3 should complete the Monthly Status Report. Level 2 or 3 projects have the option to create a Dashboard in place of the monthly status. Projects with a Complexity Level of 1 should complete the Weekly Status Report. Some sponsors and management may request that Level 1 projects complete a monthly status report. The following sections will provide assistance on creating the Monthly & Weekly Status Reports. Dashboard creation is covered in a separate guide. It is important to note that, for the most part, the data needed to complete the status report templates requires rigorous adherence to the project management methodology. The initial sections in the weekly and monthly templates are similar. The two templates differ significantly in the latter sections. Note: the headers in the Instructions Sections (Monthly & Weekly) correspond to headers in templates; the numbering schemes are not related. 1 Complexity Level is determined by completing the Complexity Matrix in the Origination Stage of the Project Lifecycle.doc 3 of 8 10/27/2010
4 Values - Goals 1.2 Instructions Monthly This section describes how to complete the Monthly Status Report Template 1. General Information. Complete project descriptive data: a. Title b. Sponsor c. Project Manager d. Reporting Period i. Week-ending date (weekly) ii. Month and year (monthly) e. Current Stage: Origination, Initiation, Planning, Execution & Control or Closure 2. Project Health Indicator: In order to provide senior management with a snapshot of the overall health of a project, a tri-color coding scheme was developed. Review the guidelines below and set the Project Health Indicator to the color that most accurately reflects the project health and level of executive attention required. This indicator is set as follows: a. Enter a checkmark in the appropriate box to indicate project s health..doc 4 of 8 10/27/2010
5 Values - Goals 3. Schedule Information: This information is extracted from the project plan, preferably MS Project or a comparable scheduling tool. It is essential that the project schedule be kept current for the life of the project a. Project Start Date: specify the project start date from your scheduling tool b. Baseline Completion Date: specify the original baseline completion date c. Revised Completion Date: this date reflects changes to the baseline date and is extracted from your scheduling tool. This date changes when the original schedule must be modified to reflect changes to task estimates and/or new tasks. 4. Project Synopsis: This section provides an executive summary of the project. Include goals, objectives and business benefits in business terms. This information can be extracted from the Charter, Scope Statement or System Development Life Cycle document (SDLC) (e.g. business requirements). This description should not change during the life of the project unless there is a major change to scope. 5. Escalation Items: This section is devoted to flagging major issues and risks for senior management intervention. If the project health indicator is yellow or red, there should be escalation items in this section that describe the reasons for the growing troubles on the project. Escalation items should remain in the status report until they are satisfactorily resolved. Some managers may ask that escalation items be maintained in the status for the life of the project. This is a project specific decision. a. Escalation Item: carefully describe the issue or risk including impacts to the project b. Owner: name of person who needs to assist with issue c. Date Identified: record the date the item surfaced. The format is: mm/dd/yyyy. d. Recommended Assistance / Update: provide management with recommendations on how the issue or risk can be managed. Describe the type of assistance needed. Provide a detailed update on the progress made to date. e. Status: succinctly describe the status of each item (e.g. attention required, corrective action in-process or resolved). f. Date Resolved: identify the date the issue or risk was resolved. 6. Status & Plan Update: Highlight major deliverables/milestones in business terms. Specify: target end date, current status (planned-no activity, on-schedule, early, late, complete) and any comments 7. Scope Status: This section describes any changes to scope and the impact of each change on the schedule, budget or quality of the project. Information for this section of the report will come from the change request process and templates. Changes should be tracked until they are formally addressed in some fashion (e.g. approved, rejected or deferred). Some managers may.doc 5 of 8 10/27/2010
6 Values - Goals ask that changes remain in the status report for the life of the project. This is a project specific decision. a. Change Summary: carefully describe the requested change b. Synopsis of Impact: summarize how the proposed change will impact the projects scope, budget and/or quality. c. Status: Approved, Rejected, In-Process, Deferred 8. Financial Status: This section should reflect the budget summary and is extracted directly from the budget spreadsheet. It is a project specific decision regarding whether to include both the summary budget and/or the budget graphic. When pasting charts, tables or diagrams into the status report template, it is recommended that it be done using paste special in the enhanced meta file EMF format for ease and clarity of scaling. 9. Accomplishments: Create a bulleted list of major accomplishments for the month. Consider progress against project milestones and deliverables. This information should come from the project plan and will be updated monthly. 10. Plans for Next Month: Create a bulleted list of major plans for the following month. Consider reflecting the start or completion of major deliverables and/or the planned attainment of a milestone. This information should come from the project plan and will be updated monthly. 1.3 Instructions Weekly This section describes how to complete the Weekly Status Report Template 1. General Information: Complete project descriptive data: a. Title b. Sponsor c. Project Manager d. Week-ending date (format: mm/dd/yy) e. Current Stage: Origination, Initiation, Planning, Execution & Control or Closure 2. Project Health Indicator: In order to provide senior management with a snapshot of the overall health of a project, a tri-color coding scheme was developed. Review the guidelines below and set the Project Health Indicator to the color that most accurately reflects the project health and level of executive attention required. This indicator is set as follows: a. Enter a checkmark in the appropriate box to indicate project s health..doc 6 of 8 10/27/2010
7 Values - Goals 3. Schedule Information & Budget Information: This information is extracted from the project plan (preferably MS Project or a comparable scheduling tool) and the budget and actuals template It is essential that the schedule and budget be kept current for the life of the project a. Project Start Date: specify the project start date from your scheduling tool b. Baseline Completion Date: specify the original baseline completion date c. Revised Completion Date: this date reflects changes to the baseline date and is extracted from your scheduling tool. This date changes when the original schedule must be modified to reflect changes to task estimates and/or new tasks. d. Original baseline budget: this number represents the original approved project budget at the start of the project. e. Cumulative adjustments: this figure represents any authorized increases or decreases from the budget. This is extracted from the Adjustment sheet in the budget. Adjustments must be maintained throughout the life of the project. f. Revised budget = Original baseline budget plus or minus authorized adjustments 4. Project Synopsis: This section provides an executive summary of the project. Include goals, objectives and business benefits in business terms. This information can be extracted from the Charter, Scope Statement or System Development Life Cycle document (SDLC) (e.g. business.doc 7 of 8 10/27/2010
8 Values - Goals requirements). This description should not change during the life of the project unless there is a major change to scope. 5. Escalation Items: This section is devoted to flagging major issues and risks for senior management. If the project health indicator is yellow or red, there should be escalation items in this section that describe the reasons for the growing troubles on the project. Escalation items should remain in the status report until they are satisfactorily resolved. Some managers may ask that escalation items be maintained in the status for the life of the project. This is a project specific decision. g. Escalation Item: carefully describe the issue or risk including impacts to the project a. Owner: name of person who needs to assist with issue h. Date Identified: record the date the item surfaced. The format is: mm/dd/yyyy. i. Recommended Assistance / Update: provide management with recommendations on how the issue or risk can be managed. Describe the type of assistance needed. Provide a detailed update on the progress made to date. j. Status: succinctly describe the status of each item (e.g., attention required, corrective action in-process or resolved). k. Date Resolved: identify the date the issue or risk was resolved. 6. Accomplishments: Create a bulleted list of major accomplishments for the week. Consider progress against project milestones and deliverables. This information should come from the project plan and will be updated weekly. 7. Plans for Next Week: Create a bulleted list of major plans for the following week. Consider reflecting the start or completion of major deliverables and/or the planned attainment of a milestone. This information should come from the project plan and will be updated weekly..doc 8 of 8 10/27/2010
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
More informationPROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
More informationATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
More informationDashboard Reporting User Guide. Michigan Department of Information Technology Strategic Project Office
Dashboard Reporting User Guide Michigan Department of Information Technology Strategic Project Office November 2003 Table of Contents Introduction...3 Purpose of this Users Guide...3 Dashboard Roles...3
More informationPMO Metrics Recommendations
Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project
More informationWVU. PROJECT MANAGEMENT LITE Training Manual for Project Managers and Team Members. Robert C. Byrd Health Sciences Center Chancellor s Office
WVU Robert C. Byrd Health Sciences Center Chancellor s Office PROJECT MANAGEMENT LITE Training Manual for Project Managers and Team Members Fostering a culture of high purpose, accountability & accomplishment
More information- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
More informationOrganization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
More informationPROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in the Project Scope Statement is implicitly excluded from the project. Project Name: Prepared by: BI - IT Governance Amy Winkel Date: 12/20/2010
More informationCommonwealth of Massachusetts CommonWay Schedule Management Guidelines. Common Values - Common Goals Common Way. Schedule Management.
Schedule Management Values - Goals Schedule Management Schedule Management v1.0 1 of 6 10/27/2010 Schedule Management Values - Goals Table of Contents 1 Schedule Management Guideline... 3 1.1 Determine
More informationTenStep Project Management Process Summary
TenStep Project Management Process Summary Project management refers to the definition and planning, and then the subsequent management, control, and conclusion of a project. It is important to recognize
More informationOverview. The Concept Of Managing Phases By Quality and Schedule
The Project Management Dashboard: A Management Tool For Controlling Complex Projects Project Management White Paper Series--#1001 John Aaron, Milestone Planning And Research, Inc. 5/14/01 Overview The
More informationOE PROJECT CHARTER TEMPLATE
PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,
More information5.2. 5.2 Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]
231 5.2 Template for IT Project Plan Name of the Tool: Source: Usage: Description: Template for IT Project Plan GIZ This template has been designed as a tool to support the planning of IT projects for
More informationPROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
More informationHow To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
More informationBest Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
More informationProject Management Guidelines
Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of
More informationSTC - 2013 Test Report Dashboard Art of Showcasing data graphically, dynamically
STC - 2013 Test Report Dashboard Art of Showcasing data graphically, dynamically Prepared by: Indium Software India Ltd. Name : Poornima Gopalan & Vishnupriya B Email : poornima.g@indiumsoft.com vishnupriya.b@indiumsoft.com
More informationPHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
More information1200 Project Control System Procedures
Control System Manual Jefferson Science Associates, LLC 1200 Control System Procedures 1200 Control System Procedures Control System Manual Revision 7-102 - Control System Manual PCS-01 Schedule Planning
More informationProject Monitoring and Control
Project Monitoring and Control ProPath Office of Information and Technology Table of Contents Project Monitoring and Control Process Maps... 1 Process: Project Monitoring and Control... 10 Project Monitoring
More informationPHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
More informationPrepared for: Prepared by:
Executive Project Review Prepared for: Prepared by: Table of contents Introduction... 3 WHY an Executive Project Review?... 3 WHO is Involved?... 4 WHAT is an Executive Project Review?... 5 WHEN? - Schedule
More informationNational IT Project Management Methodology
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA National IT Project Management Methodology Project Reporting Support Guide Version 0.5 Project Reporting Support Guide version 0.5 Page 1 Document Version
More informationManaging Projects with ServiceNow at the University of San Francisco
Managing Projects with ServiceNow at the University of San Francisco PMI Methodology PMO website includes overview of methodology and links to the various SNC forms I ll be showing. o www.usfca.edu/its/projects/process
More informationEnterprise Test Management Standards
Enterprise Test Management Standards Version 4.0 09/28/2012 Document Number: FSA_TOADG_STDS_TEST.TMS_001 Document Version Control This section summarizes this document revision history. Each entry includes
More informationChange Management Plan
Change Management Plan Values - Goals Change Management Plan ITD MassMail IT Consolidation Allison Amundsen 8/22/09 ChangeManagementPlanSample 1 of 7 8/26/2009 Change Management Plan Values - Goals Version
More informationFramework. 3/3/2011 By Karla Campbell Project Manager PMP Certificated UCOP
PROJECT MANAGEMENT Framework 3/3/2011 By Karla Campbell Project Manager PMP Certificated UCOP Topics 1. Benefits Of Project Management 2. Definitions 3. Roles 4. Project Process Groups 5. Best Practices
More informationGuidelines: Project Schedule Project Management Office (PMO)
Guidelines: Project Schedule Project Management Office (PMO) Process The project Schedule outlines the tasks and activities of the project; the duration; start and end dates for each individual task and
More informationInput, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
More informationPatricia Mast (LCLS Project Controls Manager) Mark Reichanadter (LCLS Deputy Project Director) Signature Date
LCLS Project Management Document # 1.1-022 Project Management Revision 1.0 Earned Value Management System Monthly Status and Reporting Procedure Patricia Mast (LCLS Project Controls Manager) Signature
More informationSimple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
More informationIT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
More informationDepartment of Veterans Affairs VA DIRECTIVE 6071
Department of Veterans Affairs VA DIRECTIVE 6071 Washington, DC 20420 Transmittal Sheet PROJECT MANAGEMENT ACCOUNTABILITY SYSTEM (PMAS) 1. REASON FOR ISSUE. To set forth policies and responsibilities for
More informationEllucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases
Ellucian Implementation Methodology Summary of Project Management and Solution Delivery Phases Rev. 5/10/2013 Table of Contents Overview 3 Project Management Initiation 4 Planning 5 Execution 6 Monitor
More informationProject Management Center
Project Management Center Overview - 1 - OMNITRACKER Project Management Center Application to support an efficient management of projects, from initiation until closure Planning and administration of projects
More informationThe purpose of this course is to provide practical assistance for defining and managing project scope.
Scope Definition and Scope Management Purpose - To provide practical assistance for defining and managing project scope. This course will focus on tips for creating a scope statement rather than a step-by-step
More informationVoice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program
More informationNo man is wise enough by himself. -Plautus
Project Management Facilitation Skills No man is wise enough by himself. -Plautus This course is designed to help managers and facilitators better coordinate their project teams. Participants will learn
More informationCHANGE MANAGEMENT PLAN TEMPLATE
CHANGE MANAGEMENT PLAN TEMPLATE This template allows a project manager to control, manage and monitor change requests that occur throughout the life of a project. This plan defines who has the authority
More informationDevelop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
More informationPROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
More informationITS Project Management Methodology
ITS Project Management Methodology Information Technology Services Project Management Group 11/17/2014 Version 2.1 Author: ITS Project Management Group Document Control Change Record Date Author Version
More information<PROJECT NAME> PROJECT MANAGEMENT PLAN
PROJECT MANAGEMENT PLAN Version VERSION HISTORY [Provide information on how the development and distribution of the Project Management Plan was controlled and tracked.
More informationINTRODUCTION: Project Status Reports. The status report formats/examples start on page 3
What This Is INTRODUCTION: The status report formats/examples start on page 3 Five different formats and types of status information for summarizing and communicating project status to the team and Management.
More informationDepartment of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
More informationOPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)
OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.
More informationPO Audit The AXA PPP healthcare Project Data Health Check Tool
PO Audit The AXA PPP healthcare Project Data Health Check Tool > The discussion will cover how the AXA PPP data health check tool helps us manage and improve the quality of our project management data
More informationProject Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)
Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial
More informationINTRODUCTION. Page 1 of 16
INTRODUCTION CALIFORNIA STATE TEACHERS RETIREMENT SYSTEM REQUEST FOR QUOTE JAMA LICENSING AND SERVICES RFQ NUMBER 201204 Offer Due Date: July 23, 2013, 2:00 p.m. Pacific Time (PT) The California State
More informationTen Steps to Comprehensive Project Portfolio Management Part 3 Projects, Programs, Portfolios and Strategic Direction By R.
August 2007 Ten Steps to Comprehensive Project Portfolio Management Part 3 Projects, Programs, Portfolios and Strategic Direction By R. Max Wideman This series of papers has been developed from our work
More informationInformation Technology Projects: Project Management Process
Information Technology Projects: Project Management Process Introduction Ideas for Information Technology projects come from many sources: those who do the City s work, those who manage that work, City
More informationMicrosoft Office Small Business 2007
Microsoft Office Small Business 2007 Microsoft Office Small Business 2007 provides you with a complete set of productivity and contact management tools to accomplish routine tasks quickly, manage customer
More informationITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...
More informationPMO Starter Kit. White Paper
PMO Starter Kit White Paper January 2011 TABLE OF CONTENTS 1. ABOUT THE PMO STARTER KIT...3 2. INTRODUCTION TO THE PMO STARTER KIT WHITE PAPER...3 3. PMO DEVELOPMENT ROADMAP...4 4. PLAN PHASE...5 4.1 CREATE
More informationProject Management Fundamentals. Office of the Senior Associate Vice President for Finance
Project Management Fundamentals Project Management Institute PMI is an aggregation of best practices from thousands of professional project managers Principles in this training are based on PMI methodologies,
More informationIndependent Verification and Validation of SAPHIRE 8 Software Project Plan
INL/EXT-09-17022 Rev. 2 Independent Verification and Validation of SAPHIRE 8 Software Project Plan March 2010 The INL is a U.S. Department of Energy National Laboratory operated by Battelle Energy Alliance
More informationProject Roles and Responsibilities Template
Purpose The purpose of this document is to provide a summary of the primary roles in the X project and the responsibilities associated with each role. A roles and responsibilities spreadsheet also maps
More informationContract Performance Framework
Contract Performance Framework Version 4 September, 2014 1 Provincial CCAC Client Service Contract Performance Framework Introduction: Home care plays a critical role in achieving successful and sustainable
More informationState of California. Contents. California Project Management Office Project Management Framework. Project Management. Framework.
Contents State of California Project Management Framework Page i Contents Overview 1 Introduction 3 8 15 Overview of the CA-PMF Document Structure and Convention Guide Discussion of Lifecycles Templates
More informationPROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
More informationProjectMinds Quick Guide to Project Management
ProjectMinds Quick Guide to Project Management By Manjeet Singh msingh@projectminds.com 1 A D I F F E R E N T K I N D O F C O P Y R I G H T No rights reserved. All the parts of this book can be reproduced,
More informationWho has Entered Objectives on their 2013 ACES Forms? & Exporting Data to Excel
I. Overview The Dashboard provides instant up-to-date onscreen reports. The following dashboard report will allow you to track the progress of which managers have started entering objectives onto their
More informationTechnical white paper. www.la-con.com
Business Intelligence applications developed with IBM s Cognos Technical white paper www.la-con.com Table of contents: BUSINESS INTELLIGENCE 3 SUCCEED BI 3 LIFELINE 4 REPORT AND CHART FEATURES 5 2 Business
More informationAn Oracle White Paper March 2013. Project Management Office Starter Kit
An Oracle White Paper March 2013 Project Management Office Starter Kit Executive Overview... 1 Introduction... 1 Plan Phase... 2 Create Statement of Purpose and Goals... 2 Define Scope and Target Maturity...
More information700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
More informationRequest for Resume (RFR) for Project Manager (Senior) CATS+ Master Contract All Master Contract Provisions Apply. Section 1 General Information
Request for Resume (RFR) for Project (Senior) Section General Information RFR Number: (Reference BPO Number) Functional Area (Enter One Only) Q00R00 BPO # 060B900 in ADPICS Functional Area 0 IT Management
More informationPROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
More informationPRINCE2:2009 Glossary of Terms (English)
accept (risk response) acceptance acceptance criteria activity agile methods approval approver assumption assurance A risk response to a threat where a conscious and deliberate decision is taken to retain
More informationITS Project Management
ITS Project Management Policy Contents I. POLICY STATEMENT II. REASON FOR POLICY III. SCOPE IV. AUDIENCE V. POLICY TEXT VI. PROCEDURES VII. RELATED INFORMATION VIII. DEFINITIONS IX. FREQUENTLY ASKED QUESTIONS
More informationAbar Solutions Petroleum Consultancy & Training Qualified From KPC Training & Consulting Services Provider. Code Period Language Start End Location
Training Course : Project Management Skills & Estimation Development Training Course For One Week In Canada, Montreal, Hyatt Regency Montreal Which Be Held As Under Details : Tel. : 00965 22610021 99600277,
More information2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster
2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster Traditional Classroom / Onsite Course No. 665 Duration: 2 days Credits: 14 PDUs / 1.4 CEUs Prerequisites Twelve hours of
More informationSCOPE MANAGEMENT PLAN <PROJECT NAME>
SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
More informationProject Management Methodology
Bridgewater State University Information Technology Project Management Office Project Management Methodology February 5, 2015 Version 15 1 2 Table of Contents REVISIONS HISTORY... 4 PROJECT MANAGEMENT
More informationProject Plan for <project name>
Note: Text displayed in blue italics is included to provide guidance to the author and should be deleted or hidden before publishing the document. This template can be used at it is, or to complete and
More informationEastern Illinois University EISE Configuration Management Plan
Eastern Illinois University EISE Configuration Management Prepared by: Bill Witsman Version: 10.0 Create Date: April 13, 2005 Approval Date: Last Revision Date: December 17, 2009 CM Analyst: Project Manager:
More informationCOMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME>
COMMUNICATIONS MANAGEMENT PLAN TEMPLATE This Project Communications Management Template is free for you to copy and use on your project and within your organization. We hope that you find this template
More informationSEBA Solutions Inc. 2802 Bellwind Circle Rockledge, Florida 32955 321.269.1222 voice, 321.577.0210 fax www.sebasolutions.com.
Solutions Inc. Project Status Dr. James T. Brown PMP A project status process is one of the greatest opportunities to establish a positive, disciplined project management culture. The status monitoring
More informationIT Project Management Methodology. Project Risk Management Guide. Version 0.3
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Risk Management Guide Version 0.3 Project Risk Management Support Guide version 0.3 Page 1 Version Date Author
More informationProject Management. An Overview for IT. Author: Kevin Martin & Denise Reeser
Project Management An Overview for IT Author: Kevin Martin & Denise Reeser Agenda Best Practices (5 min) Preliminary Assessment (10 min) The Need for Project Management (15 min) Involvement of EPMO (10
More informationUCPath Project Status Report
UCPath Project Status Report Report Date September 20, 2013 Program Directors Mark Cianca Sabu Varguese Executive Sponsors Nathan Brostrom Peter Taylor Project Summary The project s near-term priorities
More informationMINNESOTA STATE POLICY
Version: 2.00 Approved Date: 02/24/2012 Approval: Signature on file MINNESOTA STATE POLICY From the Office of Carolyn Parnell Chief Information Officer, State of Minnesota IT Project Portfolio Data Management
More informationProject Management Quick Reference Guide for MS Project 2010
Project Management Quick Reference Guide for MS Project 2010 Project 2010 offers flexibility and choice by providing tailored work management solutions for individuals, teams, and the enterprise. Besides
More information1 Project Management Methodology
1 Artech s is intended to promote the delivery of quality products that meet customers needs and results in projects that are completed on time and within budget The objective of the methodology is to
More informationEarned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
More informationMicrosoft Office Small Business 2007
Microsoft Office Small Business 2007 Microsoft Office Small Business 2007 provides you with a complete set of productivity and contact management tools to quickly accomplish routine tasks, manage customer
More informationCOMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME>
COMMUNICATIONS MANAGEMENT PLAN TEMPLATE This Project Communications Management Template is free for you to copy and use on your project and within your organization. We hope that you find this template
More informationSee What's Coming in Oracle Project Portfolio Management Cloud
See What's Coming in Oracle Project Portfolio Management Cloud Release 9 Release Content Document Table of Contents GRANTS MANAGEMENT... 4 Collaborate Socially on Awards Using Oracle Social Network...
More informationTHE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
More informationPHASE 1: INITIATION PHASE
PHASE 1: INITIATION PHASE The Initiation Phase begins when agency management determines that a business function requires enhancement through an agency information technology (IT) project and investment
More informationTemplate K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
More informationIT Project Management Practices Guide
IT Project Management Practices Guide Introduction The IT Project Management Practices Guide (Guide) contains a repeatable, institutionwide approach for the management of application development and/or
More informationCanvas Implementation STATUS REPORT FOR FEBRUARY, 2014 PROJECT MANAGEMENT TEAM
Canvas Implementation STATUS REPORT FOR FEBRUARY, 2014 PROJECT MANAGEMENT TEAM 1 Project Highlights o o o o o Technology Three instances of Canvas (e.g. Production, Testing, and Beta) since Summer 2013.
More informationMERGING THE SCIENTIFIC METHOD INTO THE PROJECT PLAN Paper Number 4340
MERGING THE SCIENTIFIC METHOD INTO THE PROJECT PLAN Paper Number 4340 Peter J. Boden, Kenneth J. Puckett Laser Product Safety, LLC, 3290A Green Level West Rd., Cary, NC, 27519, USA Abstract The success
More informationProject Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
More informationDo not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
More informationStakeholder management and. communication PROJECT ADVISORY. Leadership Series 3
/01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,
More informationBMC Software Consulting Services. Fermilab Computing Division Service Catalog & Communications: Process and Procedures
BMC Software Consulting Services Service Catalog & Communications: Process and Procedures Policies, Client: Date : Version : Fermilab 02/12/2009 1.0 GENERAL Description Purpose This document establishes
More informationLGS Project Management Methodology
Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant
More information