1 NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Risk Management Guide Version 0.3 Project Risk Management Support Guide version 0.3 Page 1

2 Version Date Author Change Description rd Mar, 2013 Gerald Kisongoch, PMP Draft development th June, 2013 Gerald Kisongoch, PMP, PMI-RMP Overall revision of document th June, 2013 Abdul Nsubuga, PMP General review and restructuring of the document Project Risk Management Support Guide version 0.3 Page 2

3 Table of Contents 1 INTRODUCTION Project Risk Management Overview Intended Audience Risk Management Approach Avenues for Risks Identification Documentation of Identified Risks Risk Strategies for Negative Risks (Threats) ROLES AND RESPONSIBILITIES Project Risk Management Support Guide version 0.3 Page 3

4 1 Introduction 1.1. Project Risk Management Overview Risk management is an undertaking to lessen the of potentially undesirable events on a project and amplify the of a positive event. Risk should be thought of as the possibility of suffering a negative to the project; it can result into decreased quality, increased cost, delayed completion, or project failure. Managing projects risks enhances project success so it should be the project manager s responsibility that he/ she puts an effort in managing risks To be successful, an organization should have a risk management policy in place; and all stakeholders must be committed to addressing risk management throughout the project life cycle. This guide provides highlights on how to document policies and procedures for identifying and handling uncommon causes of project variation (i.e. risk) Intended Audience Generally, the risk management plan should apply to everyone on the project, including any consulting/contractor teams or resources Risk Management Approach The overall risk management approach should follow a standard risk management model. Below is a recommended model to be followed in our case in order to enhance standardization of IT projects risk management. Project Risk Management Support Guide version 0.3 Page 4

5 Table 1: Risk Management Process Process Risk Identification Risk Analysis Risk Response Planning Risk Monitoring and Control Objective To identify risks that might affect the project and documenting their characteristics. Sources of risk, potential risk events, and symptoms of risk are identified. To perform risk analysis; the value of opportunities to pursue verses the threats to avoid; and the opportunities to ignore verses the threats to accept are assessed refer to Section 4 for further guidance To develop risk management and contingency plans refer to Section 5 for further guidance. To ensure that corrective action plans are developed, implemented, and monitored see section 6 for further guidance Risk Identification A project manager should lead a team to identify risks. Predefined risk categories can be developed in an organization to provide a structure that can help a project team to ensure that a systematic process is followed to identify risks. A Risk Breakdown Structure or categories in the following charts can be used as guides during risk identification exercise. Project Risk Management Support Guide version 0.3 Page 5

6 Chart 1: Sample Risk Categorization Chart 2: Sample Risk Breakdown Structure Project Risk Management Support Guide version 0.3 Page 6

7 Avenues for Risks Identification Risk identification is done throughout the project life cycle, although majority of the risks should be identified early on so that proper response planning and monitoring can occur. The following should be considered as potential sources for risk identification: 1. Project charter 2. Analysis of high-level deliverables 3. Analysis of the WBS and project implementation plan 4. Analysis of scope change requests 5. Analysis of project assumptions 6. Project team input (which can take the form of interviews, brainstorming sessions, and/or Delphi technique) 7. Stakeholder and sponsor input 8. Formal risk identification sessions 9. Previous lessons learned 10. Software Quality Assurance audits and reviews 11. Performance and status reports 12. Diagramming techniques such as cause and effect diagrams, process or system flows, and influence diagrams Documentation of Identified Risks All identified risks should be documented and entered into the risk register / matrix (a sample is provided below). Only Risk Identified and Risk Description columns are filled at this stage. A comprehensive job should be done during risks identification exercise. Project Risk Management Support Guide version 0.3 Page 7

8 Table2: Sample Risk Register / Matrix S. No. Risk Identified Risk Description Likelihood (Scale of 0.1-1) Impact (Scale of 0.1-1) Factor (likelihood x Impact) Category (L,M,H) Risk Owner Mitigation (Response Plan) Comments Status 1 Project Risk Management Support Guide version 0.3 Page 8

9 Furthermore, during risk identification, the following information should be documented: 1. Risk category 2. Risk trigger 3. Potential outcome 4. Raised By 5. Date Raised 6. Source Risk Riggers The risk trigger is the event that would need to happen in order for the potential outcome to occur. A project manager should always encourage the risk owners to pay attention to risk triggers of assigned risks throughout the project life. Risk triggers are usually expressed with some sort of dependency, or qualifier. For example, a risk trigger for a possible flood threat could be rain. Any form of rain therefore alerts the risk owner to ensure the contingency plan for a flood is ready to execute if the rain causes a flood Risk Analysis After identifying all possible risks, proceed to analyze the risks to ascertain their probability or likelihood of occurrence and their on the specific tasks and overall project should they occur. Impacts can be assessed against project cost, schedule, scope, and/or quality. If the risk event affects more than one dimension and the scores are different, the higher definition should be utilized Table 3 and table 4 provide probability and definitions respectively, which should be applied on all IT projects for purposes of standardization and comparability of IT projects in government. Project Risk Management Support Guide version 0.3 Page 9

10 Table 3: Risk Probability Definition Probability Category Probability Description Very High 0.9 Risk event expected to occur High 0.7 Risk event more likely than not to occur Probable 0.5 Risk event may or may not occur Low 0.3 Risk event less likely than not to occur Very Low 0.1 Risk event not expected to occur During risk analysis the potential of each risk should be analyzed, and an appropriate level (0.05, , 0.40, or 0.80) be selected based on the guidelines defined in table 4 below. Table 4: Risk Impact Definition Project Very Low Low Moderate High Very High Objective Cost Insignificant < 5 % cost 5-10% cost 10-25% cost > 25% cost cost Schedule Insignificant < 5% 5-10% 10-20% > 20% schedule schedule schedule schedule schedule Scope Barely Minor areas Major areas Changes Product noticeable ed ed unacceptable becomes to sponsor effectively useless Quality Barely Only very Sponsor Quality Product noticeable demanding must reduction becomes applications approve unacceptable effectively ed quality to sponsor useless reduction Project Risk Management Support Guide version 0.3 Page 10

11 Once the appropriate risk and probability are selected, the risk factor or priority (product of probability and ) can be determined. The matrix in table 5 below shows the combination of and probability that in turn yield a risk priority (shown by the red, yellow, and green colored shadings). Risk priority is utilized during response planning and risk monitoring/control. It is critical to understand the priority for each risk as it allows the project team to properly understand the relative importance of each risk. Table 5: Risk Factor or Priority Analysis Probability Risk Factor Impact Risks that fall into the red-shaded cells of the matrix are the highest priority, and should receive the majority of risk management resources during response planning and risk monitoring/control. Risks that fall into the yellow-shaded cells of the matrix are the next highest priority, followed by risks that fall into the green-shaded cells Develop a similar matrix for opportunities. It is a good risk management practice to start with identification and management of Project Risk Management Support Guide version 0.3 Page 11

12 positive risks as this gives the team the much needed motivation and optimism with regards to the project After the above analysis, you should be able record: Likelihood; Impact; Factor (likelihood x Impact); Category (Low, Medium, High) and Risk Owner in the risk register defined in table2 above Response Planning After completing risks identification and analysis, you should proceed to formulate a response plan of action to lessen the risks. During response planning, strategies and plans are developed to minimize the effects of the risk to a point where the risk can be controlled and managed Higher priority risks should receive more attention during response planning than lower priority risks. Every risk threat should be assigned an risk owner during response planning Risk Strategies for Positive Risks (Opportunities) The following response plan to opportunities could be considered: Enhance Risk enhancement increases the probability an opportunity will occur by focusing on the trigger conditions of the opportunity and optimizing the chances. Exploit Risk exploitation should be used on opportunities when the organization wishes to assure the opportunity is realized. For example hiring the best experts or assuring Project Risk Management Support Guide version 0.3 Page 12

13 the most technologically advanced resources are available to the project team. Share Risk sharing involves sharing responsibility and accountability with another to enable the team the best chance of seizing the opportunity. Accept Risk acceptance is any decision not to change to deal with a risk. Risk acceptance is either passively accepted by doing nothing or actively by establishing a contingency reserve Risk Strategies for Negative Risks (Threats) The following response plan to negative risks could be considered: Avoid Risk avoidance involves changing aspects of the overall project management plan to eliminate the threat, isolating project objectives from the risk s, or relaxing the objectives that are in threatened (e.g. extending the schedule or reducing the scope). Risks that are identified early in the project can be avoided by clarifying requirements, obtaining more information, improving communications, or obtaining expertise. Transfer Risk transference involves shifting the negative of a threat (and ownership of the response) to a third party. Project Risk Management Support Guide version 0.3 Page 13

14 Risk transference does not eliminate a threat; it simply makes another party responsible for managing it. Mitigate Risk mitigation involves reducing the probability and/or the of risk threat to an acceptable level. Taking early and pro-active action against a risk is often more effective than attempting to repair the damage a realized risk has caused. Developing contingency plans are examples of risk mitigation. Accept Acceptance is often taken as a risk strategy since it is very difficult to plan responses for every identified risk. Risk acceptance should normally only be taken for low-priority risks. Risk acceptance can be passive, where no action is taken at all, or active. The most common active approach to risk acceptance is to develop a cost and/or schedule reserve to accommodate known (or unknown) threats Documentation The results of response planning should be documented in the risk register (table 2 above). The following information should be entered in the register: 1) Response strategy (avoid, transfer, mitigate, or accept) 2) Response notes (description of plan) if a mitigation approach is taken, specific trigger points that require aspects of the contingency plan to be executed should be documented 3) Risk owner Project Risk Management Support Guide version 0.3 Page 14

15 1.3.4 Risk Monitoring and Control After completing risks identification, analysis and developing strategies for response plan, you embark on controlling and managing risks. Planned risk responses should be executed as required over the project life cycle of the project, but the project should also be continuously monitored for new and changing risks. During risk monitoring and control the following tasks should be performed: 1) Identify, analyze, and plan for new risks 2) Risk owners should keep tracking identified risks and monitor trigger conditions 3) Review project performance information (such as progress/status reports, issues, and corrective actions) 4) Re-analyze existing risks to see if the probability,, or proper response plan has changed 5) Review the execution of risk responses and analyze their effectiveness 6) Ensure proper risk management policies and procedures are being utilized 7) Have specific risk review meetings Documentation The results of risk monitoring and control should be documented in the risk register (table 2 above). The following information should be captured: 1) Status valid statuses are: i. Identified Risk documented, but analysis not performed Project Risk Management Support Guide version 0.3 Page 15

16 ii. iii. iv. Analysis Complete Risk analysis done, but response planning not performed Planning Complete Response planning complete Triggered Risk trigger has occurred and threat has been realized v. Resolved Realized risk has been contained vi. vii. 2) Comments Retired Identified risk no longer requires active monitoring (e.g. risk trigger has passed) Trigger Date if the risk has been triggered 2 Roles and Responsibilities The following key stakeholders will be responsible for different aspects during project risk management effort. Below find guidelines for the same. Role Project Sponsor Responsibilities Should participate in risk identification and risk activities during project charter formulation. Should also receive escalated risks and assist with mitigation and contingency actions for escalated risks. Project Manager Responsible for approval of the risk management plan, Project Team Quality Leads and participates in the risk management process, and Takes ownership of risk mitigation/contingency planning and execution. The project manager is ultimately responsible for the final decision on risk actions, in coordination with the project sponsors. Project team members participate in the risk identification process and discuss risk monitoring and mitigation activities at team meetings. They can be risk owners if deemed capable by the project manager The software quality assurance (SQA) lead is responsible for Project Risk Management Support Guide version 0.3 Page 16

17 Assurance Lead Other Project Stakeholders ensuring identified risks are managed as per the risk management plan. The SQA lead also assist in identifying new risks and/or proposing mitigation strategies and contingency plans, along with proposing improvements to the risk management plan and processes. Stakeholders assist in identifying, analysis, response plans and monitoring risk action effectiveness and participate in risk escalation, as necessary. Project Risk Management Support Guide version 0.3 Page 17

Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge

Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge 1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project

More information

IT Project Management Methodology. Project Scope Management Support Guide

IT Project Management Methodology. Project Scope Management Support Guide NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized

More information

IT Project Management Methodology. Project Execution Support Guide. Version 0.3

IT Project Management Methodology. Project Execution Support Guide. Version 0.3 NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Execution Support Guide Version 0.3 Table of Contents 1 INTRODUCTION... 4 1.1 When should Project Execution

More information

Negative Risk. Risk Can Be Positive. The Importance of Project Risk Management

Negative Risk. Risk Can Be Positive. The Importance of Project Risk Management The Importance of Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding to risk throughout the life of a project and in the best interests t of

More information

Project Risk Management

Project Risk Management Project Risk Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Risk Management

More information

Strategic Risk Management for School Board Trustees

Strategic Risk Management for School Board Trustees Strategic Management for School Board Trustees A Management Process Framework May, 2012 Table of Contents Introduction Page I. Purpose....................................... 3 II. Applicability and Scope............................

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

Project Risk Analysis toolkit

Project Risk Analysis toolkit Risk Analysis toolkit MMU has a corporate Risk Management framework that describes the standard for risk management within the university. However projects are different from business as usual activities,

More information

Risk/Issue Management Plan

Risk/Issue Management Plan Risk/Issue Management Plan Centralized Revenue Opportunity System November 2014 Version 2.0 This page intentionally left blank Table of Contents 1. Overview... 3 1.1 Purpose... 3 1.2 Scope... 3 2. Roles

More information

Audit Committee, 28 November. HCPC Project Risk Management. Executive summary and recommendations. Introduction

Audit Committee, 28 November. HCPC Project Risk Management. Executive summary and recommendations. Introduction Audit Committee, 28 November HCPC Project Risk Management Executive summary and recommendations Introduction At its meeting on 29 September 2013 the Committee agreed that it would receive the Education

More information

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have

More information

FUNBIO PROJECT RISK MANAGEMENT GUIDELINES

FUNBIO PROJECT RISK MANAGEMENT GUIDELINES FUNBIO PROJECT RISK MANAGEMENT GUIDELINES OP-09/2013 Responsible Unit: PMO Focal Point OBJECTIVE: This Operational Procedures presents the guidelines for the risk assessment and allocation process in projects.

More information

Appendix V Risk Management Plan Template

Appendix V Risk Management Plan Template Appendix V Risk Management Plan Template Version 2 March 7, 2005 This page is intentionally left blank. Version 2 March 7, 2005 Title Page Document Control Panel Table of Contents List of Acronyms Definitions

More information

National IT Project Management Methodology

National IT Project Management Methodology NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA National IT Project Management Methodology Project Reporting Support Guide Version 0.5 Project Reporting Support Guide version 0.5 Page 1 Document Version

More information

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History

More information

Crosswalk Between Current and New PMP Task Classifications

Crosswalk Between Current and New PMP Task Classifications Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the

More information

Removal of Gender Restrictions on Australian Defence Force Combat Role Employment Categories

Removal of Gender Restrictions on Australian Defence Force Combat Role Employment Categories Removal of Gender Restrictions on Australian Defence Force Combat Role Employment Categories Risk Management Plan INTENTIONALLY BLANK 1. Introduction The purpose of this Risk Management Plan (RMP) is to

More information

Project Management Frequently Asked Questions:

Project Management Frequently Asked Questions: Project Management Frequently Asked Questions: Risk Management Version:1.4, November 2008 Inter Agency Policy and Projects Unit Department of Premier and Cabinet What are the benefits of risk management?

More information

IIS Project Management

IIS Project Management IIS Project Management Best Practices, Lessons Learned from the Field Katie Reed, MPA, PMP 2012 AIRA IIS Meeting 1 Copy right 2012 Hewlett-Packard Dev elopment Company, L.P. The inf ormation contained

More information

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,

More information

1.20 Appendix A Generic Risk Management Process and Tasks

1.20 Appendix A Generic Risk Management Process and Tasks 1.20 Appendix A Generic Risk Management Process and Tasks The Project Manager shall undertake the following generic tasks during each stage of Project Development: A. Define the project context B. Identify

More information

Risk Management Strategy and Policy. The policy provides the framework for the management and control of risk within the GOC

Risk Management Strategy and Policy. The policy provides the framework for the management and control of risk within the GOC Annex 1 TITLE VERSION Version 2 Risk Management Strategy and Policy SUMMARY The policy provides the framework for the management and control of risk within the GOC DATE CREATED January 2013 REVIEW DATE

More information

Policy 10.105: Enterprise Risk Management Policy

Policy 10.105: Enterprise Risk Management Policy Name: Responsibility: Complements: Enterprise Risk Management Framework Coordinator, Enterprise Risk Management Policy 10.105: Enterprise Risk Management Policy Date: November 2006 Revision Date(s): January

More information

Risk and Contingency Planning. Today s Topics. Key Terms. A Vital Component of Your ICD-10 Program

Risk and Contingency Planning. Today s Topics. Key Terms. A Vital Component of Your ICD-10 Program Risk and Planning A Vital Component of Your ICD-10 Program Today s Topics Key Terms Why is Risk Management Critical for ICD-10? Effective Risk Management and Best Concepts ICD-10 Risk Management Examples

More information

Project Management Guidebook

Project Management Guidebook METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple

More information

Project Risk Management Handbook: A Scalable Approach

Project Risk Management Handbook: A Scalable Approach Project Risk Management Handbook: A Scalable Approach Version 1 (June 2012) Risk Monitoring Qualitative Risk Analysis Risk Response A LETTER FROM THE CHIEF ENGINEER Welcome to the new Caltrans Project

More information

Hazard Identification, Risk Assessment and Management Procedure. Documentation Control

Hazard Identification, Risk Assessment and Management Procedure. Documentation Control Hazard Identification, Risk Assessment and Management Procedure Reference: Date approved: Approving Body: Implementation Date: Version: 3 Documentation Control GG/CM/007 Trust Board Supersedes: Version

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT 11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.

More information

A SUGGESTED HARMONIZATION OF DMAIC WITH PMBOK PROJECT LIFE CYCLES FOR PHARMACEUTICAL LEAN SIX SIGMA PROJECTS

A SUGGESTED HARMONIZATION OF DMAIC WITH PMBOK PROJECT LIFE CYCLES FOR PHARMACEUTICAL LEAN SIX SIGMA PROJECTS Abstract: With the increased emphasis within the pharmaceutical industry on business productivity through the dual application of Lean Six Sigma and disciplined project management methodologies, there

More information

Risk Management. Software SIG. Alfred (Al) Florence. The MITRE. February 26, 2013. MITRE Corporation

Risk Management. Software SIG. Alfred (Al) Florence. The MITRE. February 26, 2013. MITRE Corporation Risk Management Software SIG MITRE Corporation February 26, 2013 The MITRE Alfred (Al) Florence MITRE Corporation The MITRE Agenda Introduction Risk Management References Contact Information Al Florence

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11

More information

PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview

PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview Sante Torino PMI-RMP, IPMA Level B Head of Risk Management Major Programmes, Selex ES / Land&Naval Systems Division

More information

RiskManagement ESIEE 06/03/2012. Aloysius John March 2012

RiskManagement ESIEE 06/03/2012. Aloysius John March 2012 RiskManagement MOTIS ESIEE 06/03/2012 Aloysius John March 2012 Risk Management is a Introduction Process for Project manager to identify factors that may more or less affect the success or the achievement

More information

Risk Management Plan template <TEMPLATE> RISK MANAGEMENT PLAN FOR THE <PROJECT-NAME> PROJECT

Risk Management Plan template <TEMPLATE> RISK MANAGEMENT PLAN FOR THE <PROJECT-NAME> PROJECT RISK MANAGEMENT PLAN FOR THE PROJECT Prepared by: Approved by: Reference: Version: Date: INTRODUCTION This document is the Risk Management

More information

Project Risk Management. Presented by Stephen Smith

Project Risk Management. Presented by Stephen Smith Project Risk Management Presented by Stephen Smith Introduction Risk Management Insurance Business Financial Project Risk Management Project A temporary endeavour undertaken to create a unique product

More information

An Approach to Proactive Risk Classification

An Approach to Proactive Risk Classification An Approach to Proactive Risk Classification M.S. Rojabanu 1, Dr. K. Alagarsamy 2 1 Research Scholar, Madurai Kamaraj Universtiy, Madurai,India. 2 Associate Professor, Computer Centre, Madurai Kamaraj

More information

PMI Risk Management Professional (PMI-RMP) Exam Content Outline

PMI Risk Management Professional (PMI-RMP) Exam Content Outline PMI Risk Management Professional (PMI-RMP) Exam Content Outline Project Management Institute PMI Risk Management Professional (PMI-RMP) Exam Content Outline Published by: Project Management Institute,

More information

Module 7 Human Resources Management PMP Exam Questions

Module 7 Human Resources Management PMP Exam Questions Module 7 Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Question 1 You and your manager are discussing

More information

Project Scope Management in PMBOK made easy

Project Scope Management in PMBOK made easy By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating

More information

Bridgend County Borough Council. Corporate Risk Management Policy

Bridgend County Borough Council. Corporate Risk Management Policy Bridgend County Borough Council Corporate Risk Management Policy December 2014 Index Section Page No Introduction 3 Definition of risk 3 Aims and objectives 4 Strategy 4 Accountabilities and roles 5 Risk

More information

Risk Policy and Risk Management Procedures

Risk Policy and Risk Management Procedures Risk Policy and Risk Management Procedures Preface The University s Risk Policy sets out The University s approach to risk and its management together with the means for identifying, analysing and managing

More information

At the end of this chapter. Project Charter. What is a Project Charter? What is a Project Charter? Why is a Project Charter used?

At the end of this chapter. Project Charter. What is a Project Charter? What is a Project Charter? Why is a Project Charter used? At the end of this chapter Project Charter Describe what a project charter is and why it is critical to project success. Explain what a project scope statement is and why it is important. List the various

More information

Creating A Risk Management Plan

Creating A Risk Management Plan Creating A Risk Management Plan A presentation based on the concepts taught in the Risk Management 1A course. Carlos Consulting Group Roseville, CA. (916) 521-2520 www.carlosconsulting.com 1 Objectives

More information

Version Adoption by Council: 2013 Resolution Number: 2013/177 Current Version: V1.0 Administered by: Governance Coordinator

Version Adoption by Council: 2013 Resolution Number: 2013/177 Current Version: V1.0 Administered by: Governance Coordinator Risk Management Framework Version Adoption by Council: 2013 Resolution Number: 2013/177 Current Version: V1.0 TRIM CON: 12/1132 Administered by: Governance Coordinator Last Review Date: 2013 Next Review

More information

LEGAL PROJECT MANAGEMENT

LEGAL PROJECT MANAGEMENT LEGAL PROJECT MANAGEMENT Cost management of litigation is becoming a focus of legislators in both Australia and the UK, in an attempt to streamline litigation and ensure costs are proportionate. The Civil

More information

Framework. 3/3/2011 By Karla Campbell Project Manager PMP Certificated UCOP

Framework. 3/3/2011 By Karla Campbell Project Manager PMP Certificated UCOP PROJECT MANAGEMENT Framework 3/3/2011 By Karla Campbell Project Manager PMP Certificated UCOP Topics 1. Benefits Of Project Management 2. Definitions 3. Roles 4. Project Process Groups 5. Best Practices

More information

Project Management Professional (PMP) Examination Content Outline

Project Management Professional (PMP) Examination Content Outline Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP ) Examination Content Outline Revised August 2011 Published by: Project

More information

Project Management Plan for

Project Management Plan for Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...

More information

Risk Management Procedure

Risk Management Procedure Purpose of this document Develop and document procedures and work instructions for Risk Management to cover the project Stages set out in the Project Process Map. The purpose of this procedure is to identify

More information

Project Zeus. Risk Management Plan

Project Zeus. Risk Management Plan Project Zeus Risk Management Plan 1 Baselined: 5/7/1998 Last Modified: N/A Owner: David Jones/Zeus Project Manager Page Section 1. Introduction 3 1.1 Assumptions, Constraints, and Policies 3 1.2 Related

More information

Road Asset Management Plan Risk Management : Appendix H CONTENTS. 1.0 Risk Management 2. 2.0 Risk Identification... 2. 3.0 Risk Evaluation.

Road Asset Management Plan Risk Management : Appendix H CONTENTS. 1.0 Risk Management 2. 2.0 Risk Identification... 2. 3.0 Risk Evaluation. Road Management Plan Management : Appendix H CONTENTS 1.0 Management 2 2.0 Identification... 2 3.0 Evaluation. 3 4.0 Prioritisation. 3 5.0 Control... 4 6.0 Reviewing & Reporting... 4 7.0 Register. 4 28/09/2012

More information

Motivations. spm - 2014 adolfo villafiorita - introduction to software project management

Motivations. spm - 2014 adolfo villafiorita - introduction to software project management Risk Management Motivations When we looked at project selection we just took into account financial data In the scope management document we emphasized the importance of making our goals achievable, i.e.

More information

RISK AND OPPORTUNITY MANAGEMENT STRATEGY 2013-2014

RISK AND OPPORTUNITY MANAGEMENT STRATEGY 2013-2014 RISK AND OPPORTUNITY MANAGEMENT STRATEGY 2013-2014 Version 1.0 October 2013 Not protectively marked INDEX PAGE NO TITLE 3 Executive Summary 4 Our Shared Vision and Priorities 5 Outline of the Risk and

More information

RISK MANAGEMENT POLICY

RISK MANAGEMENT POLICY RISK MANAGEMENT POLICY Nuffield College s Risk Management Policy defines the College's approach to risk and how risk management should be embedded into management processes to ensure that the major risks

More information

Project Management Fact Sheet:

Project Management Fact Sheet: Project Management Fact Sheet: Developing a Risk Management Plan Version: 1.4, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

How To Write A Workforce Strategy

How To Write A Workforce Strategy Inspiring leaders to improve children s lives Building and implementing an effective local workforce strategy Module 4: project managing the workforce strategy development process August 2010 Resource

More information

The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman)

The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman) The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman) 11/17/07 Introduction Editor's Note: We liked so much of this book that we asked for the author's permission to quote

More information

ESKISP6056.01 Direct security testing

ESKISP6056.01 Direct security testing Direct security testing Overview This standard covers the competencies concerning with directing security testing activities. It includes setting the strategy and policies for security testing, and being

More information

Section Three Learning Module B: Focusing on the Outcome

Section Three Learning Module B: Focusing on the Outcome Section Three Learning Module B: Focusing On The Outcome 3.1 Module B: Objectives At the conclusion of this module you will be able to: Explain the importance of effectively defining the project outcome.

More information

Welcome to the Data Analytic Toolkit PowerPoint presentation an introduction to project management. In this presentation, we will take a brief look

Welcome to the Data Analytic Toolkit PowerPoint presentation an introduction to project management. In this presentation, we will take a brief look Welcome to the Data Analytic Toolkit PowerPoint presentation an introduction to project management. In this presentation, we will take a brief look at project management to understand the process and some

More information

Risk management in public procurement of innovation

Risk management in public procurement of innovation Risk management in public procurement of innovation 1 Don t focus so much on taking risks, per se, but on taking the risks OUT of big and bold ideas. Contents Introduction 5 Innovation and procurement

More information

Program Management Professional (PgMP) Examination Content Outline

Program Management Professional (PgMP) Examination Content Outline Program Management Professional (PgMP) Examination Content Outline Project Management Institute Program Management Professional (PgMP ) Examination Content Outline April 2011 Published by: Project Management

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane samlane@aol.com Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,

More information

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room. APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use

More information

A Risk Management Standard

A Risk Management Standard A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management

More information

Learning Outcome 1 The learner will: Be able to initiate the preliminary stages of a project.

Learning Outcome 1 The learner will: Be able to initiate the preliminary stages of a project. Unit Title: Project Management Guided Learning Hours: 210 Level: Level 6 Number of Credits: 25 Learning Outcome 1 The learner will: Be able to initiate the preliminary stages of a 1.1 Identify an appropriate

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Project Risk Management Basics: Cost and Schedule Impacts

Project Risk Management Basics: Cost and Schedule Impacts Project Risk Management Basics: Cost and Schedule Impacts CSVA 2011 Conference Toronto, Ontario Nov 14-16, 2011 Robert E. Rocco 1 Contents Background Fundamentals Process Tools/Supporting Documentation

More information

WFP ENTERPRISE RISK MANAGEMENT POLICY

WFP ENTERPRISE RISK MANAGEMENT POLICY WFP ENTERPRISE RISK MANAGEMENT POLICY Informal Consultation 3 March 2015 World Food Programme Rome, Italy EXECUTIVE SUMMARY For many organizations, risk management is about minimizing the risk to achievement

More information

Governance and Risk Management in the Public Sector. Fernando A. Fernandez Inter-American Development Bank (202) 623-1430 e-mail: fernandof@iadb.

Governance and Risk Management in the Public Sector. Fernando A. Fernandez Inter-American Development Bank (202) 623-1430 e-mail: fernandof@iadb. Governance and Risk Management in the Public Sector Fernando A. Fernandez Inter-American Development Bank (202) 623-1430 e-mail: fernandof@iadb.org 1 Agenda Governance, why is it important? Compliance

More information

Input, Output and Tools of all Processes

Input, Output and Tools of all Processes 1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and

More information

Risk Management Policy

Risk Management Policy Risk Management Policy Responsible Officer Author Ben Bennett, Business Planning & Resources Director Julian Lewis, Governance Manager Date effective from December 2008 Date last amended December 2012

More information

UNITED NATIONS OFFICE FOR PROJECT SERVICES. ORGANIZATIONAL DIRECTIVE No. 33. UNOPS Strategic Risk Management Planning Framework

UNITED NATIONS OFFICE FOR PROJECT SERVICES. ORGANIZATIONAL DIRECTIVE No. 33. UNOPS Strategic Risk Management Planning Framework UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES Headquarters, Copenhagen O.D. No. 33 16 April 2010 ORGANIZATIONAL DIRECTIVE No. 33 UNOPS Strategic Risk Management Planning Framework 1. Introduction 1.1.

More information

Confident in our Future, Risk Management Policy Statement and Strategy

Confident in our Future, Risk Management Policy Statement and Strategy Confident in our Future, Risk Management Policy Statement and Strategy Risk Management Policy Statement Introduction Risk management aims to maximise opportunities and minimise exposure to ensure the residents

More information

RISK MANAGEMENT REPORTING GUIDELINES AND MANUAL 2013/14. For North Simcoe Muskoka LHIN Health Service Providers

RISK MANAGEMENT REPORTING GUIDELINES AND MANUAL 2013/14. For North Simcoe Muskoka LHIN Health Service Providers RISK MANAGEMENT REPORTING GUIDELINES AND MANUAL 2013/14 For North Simcoe Muskoka LHIN Health Service Providers Table of Contents Purpose of this document... 2 Introduction... 3 What is Risk?... 4 What

More information

Corporate risk register

Corporate risk register EXECUTIVE BOARD EB133/10 133rd Session 17 May 2013 Provisional agenda item 7.3 Corporate risk register Organization-wide strategic risk management in WHO Report by the Secretariat 1. This report is submitted

More information

POL ENTERPRISE RISK MANAGEMENT SC51. Executive Services Department BUSINESS UNIT: Executive Support Services SERVICE UNIT:

POL ENTERPRISE RISK MANAGEMENT SC51. Executive Services Department BUSINESS UNIT: Executive Support Services SERVICE UNIT: POL ENTERPRISE RISK MANAGEMENT SC51 POLICY CODE: SC51 DIRECTORATE: Executive Services Department BUSINESS UNIT: Executive Support Services SERVICE UNIT: Executive Support Services RESPONSIBLE OFFICER:

More information

Risk Management Primer

Risk Management Primer Risk Management Primer Purpose: To obtain strong project outcomes by implementing an appropriate risk management process Audience: Project managers, project sponsors, team members and other key stakeholders

More information

Jeff Oltmann on Mastering Projects Backpacker s Guide to Lightweight Project Management Overwhelmed

Jeff Oltmann on Mastering Projects Backpacker s Guide to Lightweight Project Management Overwhelmed the right projects - done right Jeff Oltmann on Mastering Projects Backpacker s Guide to Lightweight Project Management Overwhelmed T 1 he field of project management has been around for decades, and the

More information

Supplier Training 8D Problem Solving Approach. 2013 Brooks Automation, Inc.

Supplier Training 8D Problem Solving Approach. 2013 Brooks Automation, Inc. Supplier Training 8D Problem Solving Approach What is the 8D method? 8D stands for the 8 disciplines or the 8 critical steps for solving problems. It is a highly disciplined and effective scientific approach

More information

The Key to a Successful KM Project

The Key to a Successful KM Project Introduction An integrated PKM methodology enables organizations to maximize their investments by ensuring initiatives are on time and within budget, while sharing project challenges and successes that

More information

The Lowitja Institute Risk Management Plan

The Lowitja Institute Risk Management Plan The Lowitja Institute Risk Management Plan 1. PURPOSE This Plan provides instructions to management and staff for the implementation of consistent risk management practices throughout the Lowitja Institute

More information

NORTH HAMPSHIRE CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY MANAGEMENT POLICY AND PLAN (COR/017/V1.00)

NORTH HAMPSHIRE CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY MANAGEMENT POLICY AND PLAN (COR/017/V1.00) NORTH HAMPSHIRE CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY MANAGEMENT POLICY AND PLAN (COR/017/V1.00) Subject and version number of document: Serial Number: Business Continuity Management Policy

More information

Risk Assessment Worksheet and Management Plan

Risk Assessment Worksheet and Management Plan Customer/Project Name: The Basics There are four steps to assessing and managing risks, and effective risk management requires all four of them. 1. Identify the risks 2. Qualify the risks a. Assess each

More information

Board of Directors Meeting 12/04/2010. Operational Risk Management Charter

Board of Directors Meeting 12/04/2010. Operational Risk Management Charter Board of Directors Meeting 12/04/2010 Document approved Operational Risk Management Charter Table of contents A. INTRODUCTION...3 I. Background...3 II. Purpose and Scope...3 III. Definitions...3 B. GOVERNANCE...4

More information

Risk Management Plan. Private Placement Content Management System. Kathy Cibotti 9/15/2009

Risk Management Plan. Private Placement Content Management System. Kathy Cibotti 9/15/2009 Values - Goals Risk Management Plan Private Placement Content Management System Kathy Cibotti 9/15/2009 Risk Management Plan SAMPLE 1 of 8 9/23/2009 Values - Goals Version History Date Version Author Change

More information

Introduction to the ITS Project Management Methodology

Introduction to the ITS Project Management Methodology Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer

More information

RISK MANAGEMENT GUIDANCE FOR GOVERNMENT DEPARTMENTS AND OFFICES

RISK MANAGEMENT GUIDANCE FOR GOVERNMENT DEPARTMENTS AND OFFICES RISK MANAGEMENT GUIDANCE FOR GOVERNMENT DEPARTMENTS AND OFFICES GOVERNMENT ACCOUNTING SECTION DEPARTMENT OF FINANCE MARCH 2004 Risk Management Guidance CONTENTS Pages List of guidelines on risk management

More information

MISTAKE #1: Too Much Detail

MISTAKE #1: Too Much Detail Twenty Common Mistakes Made by New or Inexperienced Project Managers By Harold Kerzner, Ph.D., PMP Published on Tuesday, August 17, 2010-12:49 PM You ve read the PMBOK Guide several times, taken the certification

More information

Making project management indispensable for business results. Project Management 101

Making project management indispensable for business results. Project Management 101 Making project management indispensable for business results. Project Management 101 Donald E. Moore, MBA, PMP, President of PMI NB Kelly Barter, Chapter Manager of PMI NB AGM April 28, 2011 Topics of

More information

The 10 Knowledge Areas & ITTOs

The 10 Knowledge Areas & ITTOs This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading

More information

Analyzing Risks in Healthcare. February 12, 2014

Analyzing Risks in Healthcare. February 12, 2014 Analyzing s in Healthcare February 12, 2014 1 Content What is Enterprise Management (ERM) ERM Benefits ERM Standards / ISO 31000:2009 ERM Process Register ERM Governance Model s Q&A 2 What is Enterprise

More information

Business Continuity Position Description

Business Continuity Position Description Position Description February 9, 2015 Position Description February 9, 2015 Page i Table of Contents General Characteristics... 2 Career Path... 3 Explanation of Proficiency Level Definitions... 8 Summary

More information

I. Organization Johns Hopkins Medicine Armstrong Institute for Patient Safety and Quality

I. Organization Johns Hopkins Medicine Armstrong Institute for Patient Safety and Quality I. Organization Johns Hopkins Medicine Armstrong Institute for Patient Safety and Quality II. III. Solution Title Pursuing High Reliability and National Leadership in Quality and Safety Program/Project

More information